Alliance Pipeline, L.P.; Notice of Availability of the Environmental Assessment for the Proposed Tioga Lateral Project, 42719-42720 [2012-17653]

Download as PDF 42719 Federal Register / Vol. 77, No. 140 / Friday, July 20, 2012 / Notices Order 1000 Tariff Draft Task Force July 24, 2012 2:00 p.m.–6:00 p.m. CDT July 25, 2012 9:30 a.m.–1 p.m. CDT The above-referenced meetings will be held at: AEP Offices, 1201 Elm Street, 8th Floor, Dallas, TX 75270. The above-referenced meetings are open to stakeholders. Further information may be found at www.spp.org. The discussions at the meetings described above may address matters at issue in the following proceedings: Docket No. ER09–35–001, Tallgrass Transmission, LLC Docket No. ER09–36–001, Prairie Wind Transmission, LLC Docket No. ER09–548–001, ITC Great Plains, LLC Docket No. ER11–4105–000, Southwest Power Pool, Inc. Docket No. EL11–34–001, Midwest Independent Transmission System Operator, Inc. Docket No. ER12–1179–000, Southwest Power Pool, Inc. Docket No. ER12–1415–000, Southwest Power Pool, Inc. Docket No. ER12–1460–000, Southwest Power Pool, Inc. Docket No. ER12–1610–000, Southwest Power Pool, Inc. Docket No. ER12–1772–000, Southwest Power Pool, Inc. Docket No. ER12–2176–000, Southwest Power Pool, Inc. For more information, contact Luciano Lima, Office of Energy Markets Regulation, Federal Energy Regulatory Commission at (202) 502–6210 or luciano.lima@ferc.gov. Dated: July 12, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–17655 Filed 7–19–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [EG12–43–000, EG12–53–000, EG12–54– 000, et al.] Notice of Effectiveness of Exempt Wholesale Generator or Foreign Utility Company Status Docket Nos. Sherbino I Wind Farm LLC ............................................................................................................................................................... Eagle Point Power Generation LLC ................................................................................................................................................. Cimarron Windpower II, LLC ............................................................................................................................................................ Ironwood Windpower, LLC ............................................................................................................................................................... NRG Solar Alpine LLC ..................................................................................................................................................................... Cayuga Operating Company, LLC ................................................................................................................................................... Somerset Operating Company, LLC ................................................................................................................................................ Copper Mountain Solar 2, LLC ......................................................................................................................................................... Minok Wind, LLC .............................................................................................................................................................................. Senate Wind, LLC ............................................................................................................................................................................ Canadian Hills Wind, LLC ................................................................................................................................................................ Moore Solar, Inc. .............................................................................................................................................................................. Sombra Solar, Inc. ............................................................................................................................................................................ Take notice that during the month of June 2012, the status of the abovecaptioned entities as Exempt Wholesale Generators or Foreign Utility Companies became effective by operation of the Commission’s regulations. 18 CFR 366.7(a). Dated: July 12, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–17658 Filed 7–19–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission mstockstill on DSK4VPTVN1PROD with NOTICES [Docket No. CP12–50–000] Alliance Pipeline, L.P.; Notice of Availability of the Environmental Assessment for the Proposed Tioga Lateral Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Tioga Lateral Project, proposed by VerDate Mar<15>2010 18:18 Jul 19, 2012 Jkt 226001 Alliance Pipeline L.P. (Alliance) in the above-referenced docket. Alliance requests authorization to construct and operate approximately 79.3 miles of new 12-inch-diameter natural gas pipeline lateral and appurtenant facilities in Williams, Mountrail, Burke, and Renville Counties, North Dakota. The Tioga Lateral Project would be designed and constructed to provide about 106.5 million cubic feet per day of new transportation capacity to the Chicago market area. The EA assesses the potential environmental effects of the construction and operation of the Tioga Lateral Project in accordance with the requirements of the National Environmental Policy Act (NEPA). The FERC staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment. The U.S. Fish and Wildlife Service (FWS) and the U.S. Army Corps of Engineers (COE) participated as cooperating agencies in the preparation of the EA. Cooperating agencies have PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 EG12–43–000 EG12–53–000 EG12–54–000 EG12–55–000 EG12–56–000 EG12–57–000 EG12–58–000 EG12–59–000 EG12–60–000 EG12–61–000 EG12–62–000 FC12–6–000 FC12–7–000 jurisdiction by law or special expertise with respect to resources potentially affected by the proposal and participate in the NEPA analysis. The proposed Tioga Lateral Project includes the following facilities: • Approximately 79.3 miles of 12inch-diameter natural gas pipeline crossing portions of Williams, Mountrail, Burke, Ward, and Renville Counties, North Dakota; • A 6,000 horsepower compressor station (Tioga Compressor Station) containing three natural gas-driven engines/compressors in Williams County; • One meter station within the proposed compressor station site in Williams County; • One pressure regulating station adjacent to the existing Alliance mainline in Renville County; • One pig 1 launcher at the proposed compressor station site and one pig receiver at the pressure regulating station site; and • Five mainline block valves. 1 A ‘‘pig’’ is a tool that is inserted into and moves through the pipeline, and is used for cleaning the pipeline, internal inspections, or other purposes. E:\FR\FM\20JYN1.SGM 20JYN1 mstockstill on DSK4VPTVN1PROD with NOTICES 42720 Federal Register / Vol. 77, No. 140 / Friday, July 20, 2012 / Notices The FERC staff mailed copies of the EA to Federal, State, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; newspapers and libraries in the project area; and parties to this proceeding. In addition, the EA is available for public viewing on the FERC’s Web site (www.ferc.gov) using the eLibrary link. A limited number of copies of the EA are available for distribution and public inspection at: Federal Energy Regulatory Commission, Public Reference Room, 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502–8371. Any person wishing to comment on the EA may do so. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before August 13, 2012. For your convenience, there are three methods you can use to file your comments to the Commission. In all instances, please reference the project docket number (CP12–50–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can also file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory VerDate Mar<15>2010 18:18 Jul 19, 2012 Jkt 226001 Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214).2 Only intervenors have the right to seek rehearing of the Commission’s decision. The Commission grants affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search,’’ and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP12–50). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Dated: July 13, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–17653 Filed 7–19–12; 8:45 am] BILLING CODE 6717–01–P 2 See the previous discussion on the methods for filing comments. PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER12–2231–000] Shiloh IV Wind Project, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding, of Shiloh IV Wind Project, LLC’s application for market-based rate authority, with an accompanying rate schedule, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability is August 6, 2012. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First St. NE., Washington, DC 20426. The filings in the above-referenced proceeding(s) are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC E:\FR\FM\20JYN1.SGM 20JYN1

Agencies

[Federal Register Volume 77, Number 140 (Friday, July 20, 2012)]
[Notices]
[Pages 42719-42720]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-17653]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP12-50-000]


Alliance Pipeline, L.P.; Notice of Availability of the 
Environmental Assessment for the Proposed Tioga Lateral Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the Tioga 
Lateral Project, proposed by Alliance Pipeline L.P. (Alliance) in the 
above-referenced docket. Alliance requests authorization to construct 
and operate approximately 79.3 miles of new 12-inch-diameter natural 
gas pipeline lateral and appurtenant facilities in Williams, Mountrail, 
Burke, and Renville Counties, North Dakota. The Tioga Lateral Project 
would be designed and constructed to provide about 106.5 million cubic 
feet per day of new transportation capacity to the Chicago market area.
    The EA assesses the potential environmental effects of the 
construction and operation of the Tioga Lateral Project in accordance 
with the requirements of the National Environmental Policy Act (NEPA). 
The FERC staff concludes that approval of the proposed project, with 
appropriate mitigating measures, would not constitute a major federal 
action significantly affecting the quality of the human environment.
    The U.S. Fish and Wildlife Service (FWS) and the U.S. Army Corps of 
Engineers (COE) participated as cooperating agencies in the preparation 
of the EA. Cooperating agencies have jurisdiction by law or special 
expertise with respect to resources potentially affected by the 
proposal and participate in the NEPA analysis.
    The proposed Tioga Lateral Project includes the following 
facilities:
     Approximately 79.3 miles of 12-inch-diameter natural gas 
pipeline crossing portions of Williams, Mountrail, Burke, Ward, and 
Renville Counties, North Dakota;
     A 6,000 horsepower compressor station (Tioga Compressor 
Station) containing three natural gas-driven engines/compressors in 
Williams County;
     One meter station within the proposed compressor station 
site in Williams County;
     One pressure regulating station adjacent to the existing 
Alliance mainline in Renville County;
     One pig \1\ launcher at the proposed compressor station 
site and one pig receiver at the pressure regulating station site; and
---------------------------------------------------------------------------

    \1\ A ``pig'' is a tool that is inserted into and moves through 
the pipeline, and is used for cleaning the pipeline, internal 
inspections, or other purposes.
---------------------------------------------------------------------------

     Five mainline block valves.

[[Page 42720]]

    The FERC staff mailed copies of the EA to Federal, State, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; newspapers and libraries in the project area; and parties to 
this proceeding. In addition, the EA is available for public viewing on 
the FERC's Web site (www.ferc.gov) using the eLibrary link. A limited 
number of copies of the EA are available for distribution and public 
inspection at: Federal Energy Regulatory Commission, Public Reference 
Room, 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502-
8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on this project, it is important 
that we receive your comments in Washington, DC on or before August 13, 
2012.
    For your convenience, there are three methods you can use to file 
your comments to the Commission. In all instances, please reference the 
project docket number (CP12-50-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR 385.214).\2\ Only intervenors have the 
right to seek rehearing of the Commission's decision. The Commission 
grants affected landowners and others with environmental concerns 
intervenor status upon showing good cause by stating that they have a 
clear and direct interest in this proceeding which no other party can 
adequately represent. Simply filing environmental comments will not 
give you intervenor status, but you do not need intervenor status to 
have your comments considered.
---------------------------------------------------------------------------

    \2\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP12-
50). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.

    Dated: July 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-17653 Filed 7-19-12; 8:45 am]
BILLING CODE 6717-01-P