Drawbridge Operation Regulations; Saugus River, Lynn and Revere, MA, 42433 [2012-17577]
Download as PDF
Federal Register / Vol. 77, No. 139 / Thursday, July 19, 2012 / Rules and Regulations
Basis and Purpose
On May 2, 2012, we published a
temporary deviation entitled
‘‘Drawbridge Operations: Niantic River,
Niantic, CT’’ in the Federal Register (77
FR 25889) for the Amtrak Railroad
Bridge, across the Niantic River, mile
0.0, at Niantic, Connecticut. This
deviation from the operating regulations
was authorized under 33 CFR 117.35.
Cancellation
The Coast Guard previously issued a
temporary deviation to Amtrak
published on May 2, 2012 (77 FR 25889)
to allow their bridge to remain in the
closed position from 11 p.m. through 6
a.m., Monday through Thursday,
beginning May 15, 2012 until August
15, 2012. The temporary deviation was
necessary to facilitate completion of
machinery installation and lift span
work at the new railroad bridge.
In May 2012, the contractor building
the bridge discovered a minor shift in
the bascule pier, causing a misalignment
of the new bridge. Until the pier
alignment problem is resolved, the work
anticipated to be completed during the
closures authorized under the May 2,
2012 (77 FR 25889) temporary deviation
could not be completed.
In order to complete all the remaining
work and correct the pier alignment
problem a new temporary deviation is
required authorizing a 48 hour bridge
closure from 9 p.m. July 15 to 9 p.m.
July 17, 2012 and a series of overnight
closures between July 22 and August 22,
2012.
As a result of all the above
information it was determined that the
temporary deviation published on May
2, 2012 (77 FR 25889) must be cancelled
on July 14, 2012.
Dated: July 9, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard
District.
[FR Doc. 2012–17580 Filed 7–18–12; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
tkelley on DSK3SPTVN1PROD with RULES
[Docket No. USCG–2012–0547]
Drawbridge Operation Regulations;
Saugus River, Lynn and Revere, MA
Coast Guard, DHS.
Notice of temporary deviation
from regulations.
AGENCY:
ACTION:
VerDate Mar<15>2010
16:56 Jul 18, 2012
The Commander, First Coast
Guard District, has issued a temporary
deviation from the regulation governing
the operation of the General Edwards
Bridge, mile 1.7, across the Saugus River
between Lynn and Revere,
Massachusetts. The deviation is
necessary to facilitate major bridge
rehabilitation construction. This
deviation allows the bridge to remain in
the closed position during the
rehabilitation of the electrical and
mechanical components that lift the
bridge spans.
DATES: This deviation is effective from
September 4, 2012 through February 27,
2013.
ADDRESSES: Documents mentioned in
this preamble as being available in the
docket are part of docket USCG–2012–
0547 and are available online at
www.regulations.gov, inserting USCG–
2012–0547 in the ‘‘Keyword’’ and then
clicking ‘‘Search’’. They are also
available for inspection or copying at
the Docket Management Facility (M–30),
U.S. Department of Transportation,
West Building Ground Floor, Room
W12–140, 1200 New Jersey Avenue SE.,
Washington, DC 20590, between 9 a.m.
and 5 p.m., Monday through Friday,
except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this rule, call or
email Mr. John W. McDonald, Project
Officer, First Coast Guard District,
john.w.mcdonald@uscg.mil, or
telephone 617–223–8364. If you have
questions on viewing the docket, call
Renee V. Wright, Program Manager,
Docket Operations, telephone 202–366–
9826.
SUPPLEMENTARY INFORMATION: The
General Edwards Bridge, across the
Saugus River, mile 1.7, between Lynn
and Revere, Massachusetts, has a
vertical clearance in the closed position
of 27 feet at mean high water and 36 feet
at mean low water. The drawbridge
operation regulations are listed at 33
CFR 117.618(b).
The waterway users are recreational
vessels of various sizes. During the nonboating season the bridge rarely opens
since the recreational vessels that transit
this waterway are normally in winter
storage. The bridge has opened five
times since 2010 during the winter
months.
The owner of the bridge,
Massachusetts Department of
Transportation, requested a temporary
deviation from the regulations to help
facilitate rehabilitation of the electrical
and mechanical components that lift the
opening spans.
Under this temporary deviation the
General Edwards Bridge may remain in
SUMMARY:
Jkt 226001
PO 00000
Frm 00017
Fmt 4700
Sfmt 4700
42433
the closed position from September 4,
2012 through February 27, 2013.
Vessels that can pass under the bridge
in the closed position may do so at any
time.
The Coast Guard believes that this
temporary deviation meets the
reasonable needs of navigation because
the recreational users that normally use
this bridge are recreational vessels that
do not operate during the winter months
when this deviation will be in effect.
In accordance with 33 CFR 117.35(e),
the bridge must return to its regular
operating schedule immediately at the
end of the designated time period. This
deviation from the operating regulations
is authorized under 33 CFR 117.35.
Dated: June 29, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard
District.
[FR Doc. 2012–17577 Filed 7–18–12; 8:45 am]
BILLING CODE 9110–04–P
ENVIRONMENTAL PROTECTION
AGENCY
40 CFR Part 180
[EPA–HQ–OPP–2011–0300; FRL–9354–9]
Difenoconazole; Pesticide Tolerances
Environmental Protection
Agency (EPA).
ACTION: Final rule.
AGENCY:
This regulation establishes
tolerances for residues of
difenoconazole in or on multiple
commodities identified and discussed
in this document and amends the
established tolerances in or on
vegetable, tuberous and corm, subgroup
1C and potato, processed waste. In
addition, this regulation removes
established tolerances for certain
commodities/groups superseded by this
action. The Interregional Research
Project Number 4 (IR–4) requested these
tolerances under the Federal Food,
Drug, and Cosmetic Act (FFDCA).
DATES: This regulation is effective July
19, 2012. Objections and requests for
hearings must be received on or before
September 17, 2012, and must be filed
in accordance with the instructions
provided in 40 CFR part 178 (see also
Unit I.C. of the SUPPLEMENTARY
INFORMATION).
ADDRESSES: The docket for this action,
identified by docket identification (ID)
number EPA–HQ–OPP–2011–0300, is
available at https://www.regulations.gov
or at the OPP Docket in the
Environmental Protection Agency
Docket Center (EPA/DC), located in EPA
SUMMARY:
E:\FR\FM\19JYR1.SGM
19JYR1
Agencies
[Federal Register Volume 77, Number 139 (Thursday, July 19, 2012)]
[Rules and Regulations]
[Page 42433]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-17577]
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2012-0547]
Drawbridge Operation Regulations; Saugus River, Lynn and Revere,
MA
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulations.
-----------------------------------------------------------------------
SUMMARY: The Commander, First Coast Guard District, has issued a
temporary deviation from the regulation governing the operation of the
General Edwards Bridge, mile 1.7, across the Saugus River between Lynn
and Revere, Massachusetts. The deviation is necessary to facilitate
major bridge rehabilitation construction. This deviation allows the
bridge to remain in the closed position during the rehabilitation of
the electrical and mechanical components that lift the bridge spans.
DATES: This deviation is effective from September 4, 2012 through
February 27, 2013.
ADDRESSES: Documents mentioned in this preamble as being available in
the docket are part of docket USCG-2012-0547 and are available online
at www.regulations.gov, inserting USCG-2012-0547 in the ``Keyword'' and
then clicking ``Search''. They are also available for inspection or
copying at the Docket Management Facility (M-30), U.S. Department of
Transportation, West Building Ground Floor, Room W12-140, 1200 New
Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m.,
Monday through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If you have questions on this rule,
call or email Mr. John W. McDonald, Project Officer, First Coast Guard
District, john.w.mcdonald@uscg.mil, or telephone 617-223-8364. If you
have questions on viewing the docket, call Renee V. Wright, Program
Manager, Docket Operations, telephone 202-366-9826.
SUPPLEMENTARY INFORMATION: The General Edwards Bridge, across the
Saugus River, mile 1.7, between Lynn and Revere, Massachusetts, has a
vertical clearance in the closed position of 27 feet at mean high water
and 36 feet at mean low water. The drawbridge operation regulations are
listed at 33 CFR 117.618(b).
The waterway users are recreational vessels of various sizes.
During the non-boating season the bridge rarely opens since the
recreational vessels that transit this waterway are normally in winter
storage. The bridge has opened five times since 2010 during the winter
months.
The owner of the bridge, Massachusetts Department of
Transportation, requested a temporary deviation from the regulations to
help facilitate rehabilitation of the electrical and mechanical
components that lift the opening spans.
Under this temporary deviation the General Edwards Bridge may
remain in the closed position from September 4, 2012 through February
27, 2013.
Vessels that can pass under the bridge in the closed position may
do so at any time.
The Coast Guard believes that this temporary deviation meets the
reasonable needs of navigation because the recreational users that
normally use this bridge are recreational vessels that do not operate
during the winter months when this deviation will be in effect.
In accordance with 33 CFR 117.35(e), the bridge must return to its
regular operating schedule immediately at the end of the designated
time period. This deviation from the operating regulations is
authorized under 33 CFR 117.35.
Dated: June 29, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. 2012-17577 Filed 7-18-12; 8:45 am]
BILLING CODE 9110-04-P