Central Vermont Public Service Corporation; Green Mountain Power Corporation; Notice of Application for Transfer of Licenses, and Soliciting Comments and Motions To Intervene, 41975 [2012-17321]
Download as PDF
Federal Register / Vol. 77, No. 137 / Tuesday, July 17, 2012 / Notices
specified for filing comments, it will be
presumed to have no comments. One
copy of an agency’s comments must also
be sent to the Applicant’s
representatives.
Dated: July 9, 2012.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project Nos. 2205–057, 2396–034, 2397–
031, 2399–037, 2400–033, 2445–024, 2489–
046, 2490–028, 2558–032, 2731–042, 2737–
022, 11475–015, 11478–014, and 12766–004]
41975
CVPSC) and Green Mountain Power
Corporation (transferee or GMPC) filed
an application to transfer the licenses
and substitute applicant for the
following projects:
Central Vermont Public Service
Corporation; Green Mountain Power
Corporation; Notice of Application for
Transfer of Licenses, and Soliciting
Comments and Motions To Intervene
[FR Doc. 2012–17325 Filed 7–16–12; 8:45 am]
BILLING CODE 6717–01–P
On June 28, 2012, Central Vermont
Public Service Corporation (transferor or
Project name
Location
2205 ...............
2396 ...............
2397 ...............
2399 ...............
2400 ...............
2445 ...............
2489 ...............
2490 ...............
2558 ...............
2731 ...............
2737 ...............
11475 .............
Lamoille River Hydroelectric ..................................
Pierce Mills Hydroelectric .......................................
Gage Hydroelectric ................................................
Arnold Falls Hydroelectric ......................................
Passumpsic Hydroelectric ......................................
Center Rutland Hydroelectric .................................
Cavendish Hydroelectric ........................................
Taftsville Hydroelectric ...........................................
Otter Creek .............................................................
Weybridge Hydroelectric ........................................
Middlebury Lower Hydroelectric .............................
Carver Falls Hydroelectric ......................................
11478 .............
12766 .............
tkelley on DSK3SPTVN1PROD with NOTICES
Project No.
Silver Lake Hydroelectric .......................................
Clay Hill Road Transmission Line ..........................
Lamoille River in Chittenden, Franklin, and Lamoille counties, Vermont.
Passumpsic River in Caledonia County, Vermont.
Passumpsic River in Caledonia County, Vermont.
Passumpsic River in Caledonia County, Vermont.
Passumpsic River in Caledonia County, Vermont.
Otter Creek in Rutland County, Vermont.
Black River in Windsor County, Vermont.
Ottaquechee River in Windsor County, Vermont.
Otter Creek in Rutland County, Vermont.
Otter Creek in Addison County, Vermont.
Otter Creek in Addison County, Vermont.
Poultney River in Washington County, New York and Rutland County,
Vermont.
Sucker Brook in Addison County, Vermont.
Six miles of 12.5 kV, three-phase transmission line mounted on top of
CVPSC’s Line along Clay Hill Road from Pole #115 to CVPSC’s
Quechee substation.
Applicants seek Commission approval
to transfer the licenses for the above
projects from the transferor to the
transferee.
Applicants’ Contact: Transferor: Mr.
Michael Scarzello, P.E., Central
Vermont Public Service Corporation, 77
Grove Street, Rutland, VT 05701, (802)
747–5207. Transferee: Ms. Mari M.
McClure, Esq., Corporate Attorney,
Green Mountain Power Corporation, 163
Acorn Lane, Colchester, VT 05446, (802)
655–8749. Also for the transferor and
transferee: Ms. Nicole S. Allen and Ms.
Carmen L. Gentile, Bruder, Gentile &
Marcoux, LLP, 1701 Pennsylvania Ave.
NW., Washington, DC 20006, (202) 296–
1500.
FERC Contact: Patricia W. Gillis (202)
502–8735, patricia.gillis@ferc.gov.
Deadline for filing comments and
motions to intervene: 30 days from the
issuance date of this notice. Comments
and motions to intervene may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1) and the instructions
on the Commission’s Web site under
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
VerDate Mar<15>2010
16:53 Jul 16, 2012
Jkt 226001
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original plus
seven copies should be mailed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
More information about this project can
be viewed or printed on the eLibrary
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket numbers
(P–2205–057, P–2737–022, P–11475–
015, P–11478–014, P–12766–004, P–
2490–028, P–2731–042, P–2396–034, P–
2397–031, P–2399–037, P–2400–033, P–
2445–024, P–2489–046, and P–2558–32)
in the docket number field to access the
document. For assistance, call toll-free
1–866–208–3372.
Dated: July 9, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–17321 Filed 7–16–12; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00009
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–479–000]
Southern Star Central Gas Pipeline,
Inc.; Notice of Application
Take notice that on June 27, 2012,
Southern Star Central Gas Pipeline, Inc.
(Southern Star), 4700 Highway 56,
Owensboro, Kentucky 42301, filed an
application in the above referenced
docket pursuant to section 7(b) of the
Natural Gas Act (NGA) requesting
authorization to abandon in place, and
certain sections by removal by request
of landowners, approximately 16.14
miles of 20-inch diameter pipeline
located in Oklahoma and Logan
Counties, Oklahoma (Line V). Southern
Star states that due to the age of Line V
and the use of coupled pipe, Line V
cannot be inspected to meet Pipeline
Hazardous Materials Safety
Administration (PHMSA) requirements.
Southern Star asserts that there are no
customers being served off Line V and
the existing parallel loop Line VJ is
adequate to serve Southern Star’s firm
E:\FR\FM\17JYN1.SGM
17JYN1
Agencies
[Federal Register Volume 77, Number 137 (Tuesday, July 17, 2012)]
[Notices]
[Page 41975]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-17321]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. 2205-057, 2396-034, 2397-031, 2399-037, 2400-033, 2445-
024, 2489-046, 2490-028, 2558-032, 2731-042, 2737-022, 11475-015,
11478-014, and 12766-004]
Central Vermont Public Service Corporation; Green Mountain Power
Corporation; Notice of Application for Transfer of Licenses, and
Soliciting Comments and Motions To Intervene
On June 28, 2012, Central Vermont Public Service Corporation
(transferor or CVPSC) and Green Mountain Power Corporation (transferee
or GMPC) filed an application to transfer the licenses and substitute
applicant for the following projects:
------------------------------------------------------------------------
Project No. Project name Location
------------------------------------------------------------------------
2205............. Lamoille River Lamoille River in Chittenden,
Hydroelectric. Franklin, and Lamoille
counties, Vermont.
2396............. Pierce Mills Passumpsic River in Caledonia
Hydroelectric. County, Vermont.
2397............. Gage Hydroelectric... Passumpsic River in Caledonia
County, Vermont.
2399............. Arnold Falls Passumpsic River in Caledonia
Hydroelectric. County, Vermont.
2400............. Passumpsic Passumpsic River in Caledonia
Hydroelectric. County, Vermont.
2445............. Center Rutland Otter Creek in Rutland County,
Hydroelectric. Vermont.
2489............. Cavendish Black River in Windsor County,
Hydroelectric. Vermont.
2490............. Taftsville Ottaquechee River in Windsor
Hydroelectric. County, Vermont.
2558............. Otter Creek.......... Otter Creek in Rutland County,
Vermont.
2731............. Weybridge Otter Creek in Addison County,
Hydroelectric. Vermont.
2737............. Middlebury Lower Otter Creek in Addison County,
Hydroelectric. Vermont.
11475............ Carver Falls Poultney River in Washington
Hydroelectric. County, New York and Rutland
County, Vermont.
11478............ Silver Lake Sucker Brook in Addison
Hydroelectric. County, Vermont.
12766............ Clay Hill Road Six miles of 12.5 kV, three-
Transmission Line. phase transmission line
mounted on top of CVPSC's
Line along Clay Hill Road
from Pole 115 to
CVPSC's Quechee substation.
------------------------------------------------------------------------
Applicants seek Commission approval to transfer the licenses for
the above projects from the transferor to the transferee.
Applicants' Contact: Transferor: Mr. Michael Scarzello, P.E.,
Central Vermont Public Service Corporation, 77 Grove Street, Rutland,
VT 05701, (802) 747-5207. Transferee: Ms. Mari M. McClure, Esq.,
Corporate Attorney, Green Mountain Power Corporation, 163 Acorn Lane,
Colchester, VT 05446, (802) 655-8749. Also for the transferor and
transferee: Ms. Nicole S. Allen and Ms. Carmen L. Gentile, Bruder,
Gentile & Marcoux, LLP, 1701 Pennsylvania Ave. NW., Washington, DC
20006, (202) 296-1500.
FERC Contact: Patricia W. Gillis (202) 502-8735,
patricia.gillis@ferc.gov.
Deadline for filing comments and motions to intervene: 30 days from
the issuance date of this notice. Comments and motions to intervene may
be filed electronically via the Internet. See 18 CFR 385.2001(a)(1) and
the instructions on the Commission's Web site under https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. If unable to be filed electronically, documents may be paper-
filed. To paper-file, an original plus seven copies should be mailed
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC 20426. More information about this
project can be viewed or printed on the eLibrary link of Commission's
Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the
docket numbers (P-2205-057, P-2737-022, P-11475-015, P-11478-014, P-
12766-004, P-2490-028, P-2731-042, P-2396-034, P-2397-031, P-2399-037,
P-2400-033, P-2445-024, P-2489-046, and P-2558-32) in the docket number
field to access the document. For assistance, call toll-free 1-866-208-
3372.
Dated: July 9, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-17321 Filed 7-16-12; 8:45 am]
BILLING CODE 6717-01-P