Federal Register / Vol. 77, No. 133 / Wednesday, July 11, 2012 / Rules and Regulations
Dated: June 27, 2012.
Jay W. Jewess,
Captain, U.S. Coast Guard, Captain of the
Port San Francisco, Acting.
Risks and Safety Risks. This rule is not
an economically significant rule and
does not create an environmental risk to
health or risk to safety that may
disproportionately affect children.
PART 165—REGULATED NAVIGATION
AREAS AND LIMITED ACCESS AREAS
11. Indian Tribal Governments
Authority: 33 U.S.C. 1226, 1231; 46 U.S.C.
Chapter 701, 3306, 3703; 50 U.S.C. 191, 195;
33 CFR 1.05–1(g), 6.04–1, 6.04–6, and 160.5;
Pub. L. 107–295, 116 Stat. 2064; Department
of Homeland Security Delegation No. 0170.1.
BILLING CODE 9110–04–P
■
2. Add temporary § 165.T11–502 to
read as follows:
Saint Lawrence Seaway Development
Corporation
§ 165.T11–502 Safety zone; Sacramento
River Closure for Aerial Cable Installation,
Sacramento, CA.
33 CFR Part 401
(a) Location. This temporary safety
zone is established for the navigable
waters of the Sacramento River near
Sherman Island, California as depicted
in National Oceanic and Atmospheric
Administration (NOAA) Chart 18661.
The safety zone will extend 200 yards
from a line connecting the following
points: 38°04′15″ N, 121°47′20″ W;
38°03′38″ N, 121°46′58″ W (NAD 83).
(b) Enforcement Period. The zone
described in paragraph (a) of this
section will be enforced from 6 a.m.
through 1 p.m. on July 11, 2012 through
July 13, 2012. The Captain of the Port
San Francisco (COTP) will notify the
maritime community of periods during
which this zone will be enforced via
Broadcast Notice to Mariners in
accordance with 33 CFR 165.7.
(c) Definitions. As used in this
section, ‘‘designated representative’’
means a Coast Guard Patrol
Commander, including a Coast Guard
coxswain, petty officer, or other officer
on a Coast Guard vessel or a Federal,
State, or local officer designated by or
assisting the COTP in the enforcement
of the safety zone.
(d) Regulations. (1) Under the general
regulations in 33 CFR Part 165, Subpart
C, entry into, transiting or anchoring
within this safety zone is prohibited
unless authorized by the COTP or a
designated representative.
(2) The safety zone is closed to all
vessel traffic, except as may be
permitted by the COTP or a designated
representative.
(3) Vessel operators desiring to enter
or operate within the safety zone must
contact the COTP or a designated
representative to obtain permission to
do so. Vessel operators given permission
to enter or operate in the safety zone
must comply with all directions given to
them by the COTP or a designated
representative. Persons and vessels may
request permission to enter the safety
zone on VHF–23A or through the 24hour Command Center at telephone
(415) 399–3547.
RIN 2135–AA30
This rule does not have tribal
implications under Executive Order
13175, Consultation and Coordination
with Indian Tribal Governments,
because it does not have a substantial
direct effect on one or more Indian
tribes, on the relationship between the
Federal Government and Indian tribes,
or on the distribution of power and
responsibilities between the Federal
Government and Indian tribes.
12. Energy Effects
This action is not a ‘‘significant
energy action’’ under Executive Order
13211, Actions Concerning Regulations
That Significantly Affect Energy Supply,
Distribution, or Use.
13. Technical Standards
This rule does not use technical
standards. Therefore, we did not
consider the use of voluntary consensus
standards.
14. Environment
We have analyzed this rule under
Department of Homeland Security
Management Directive 023–01 and
Commandant Instruction M16475.lD,
which guide the Coast Guard in
complying with the National
Environmental Policy Act of 1969
(NEPA) (42 U.S.C. 4321–4370f), and
have determined that this action is one
of a category of actions that do not
individually or cumulatively have a
significant effect on the human
environment. This rule involves a safety
zone of limited size and duration. This
rule is categorically excluded from
further review under paragraph 34(g) of
Figure 2–1 of the Commandant
Instruction. An environmental analysis
checklist supporting this determination
and a Categorical Exclusion
Determination are available in the
docket where indicated under
ADDRESSES. We seek any comments or
information that may lead to the
discovery of a significant environmental
impact from this rule.
erowe on DSK2VPTVN1PROD with RULES
List of Subjects in 33 CFR Part 165
Harbors, Marine safety, Navigation
(water), Reporting and recordkeeping
requirements, Security measures, and
Waterways.
For the reasons discussed in the
preamble, the Coast Guard amends 33
CFR part 165 as follows:
VerDate Mar<15>2010
14:30 Jul 10, 2012
Jkt 226001
1. The authority citation for part 165
continues to read as follows:
■
PO 00000
Frm 00018
Fmt 4700
Sfmt 4700
[FR Doc. 2012–16953 Filed 7–10–12; 8:45 am]
DEPARTMENT OF TRANSPORTATION
[Docket No. SLSDC–2012–0001]
Seaway Regulations and Rules:
Periodic Update, Various Categories
Saint Lawrence Seaway
Development Corporation, DOT.
ACTION: Final rule.
AGENCY:
The Saint Lawrence Seaway
Development Corporation (SLSDC) and
the St. Lawrence Seaway Management
Corporation (SLSMC) of Canada, under
international agreement, jointly publish
and presently administer the St.
Lawrence Seaway Regulations and
Rules (Practices and Procedures in
Canada) in their respective jurisdictions.
Under agreement with the SLSMC, the
SLSDC is amending the joint regulations
by updating the Seaway Regulations and
Rules in various categories. The changes
will update the following sections of the
Regulations and Rules: Condition of
Vessels; Seaway Navigation; Dangerous
Cargo; Information and Reports;
General; and, Navigation Closing
Procedures. These amendments are
necessary to take account of updated
procedures and will enhance the safety
of transits through the Seaway. Several
of the amendments are merely editorial
or for clarification of existing
requirements.
SUMMARY:
DATES:
The final rule is effective July 11,
2012.
FOR FURTHER INFORMATION CONTACT:
Carrie Mann Lavigne, Chief Counsel,
Saint Lawrence Seaway Development
Corporation, 180 Andrews Street,
Massena, New York 13662; 315/764–
3200.
The Saint
Lawrence Seaway Development
Corporation (SLSDC) and the St.
Lawrence Seaway Management
Corporation (SLSMC) of Canada, under
international agreement, jointly publish
and presently administer the St.
Lawrence Seaway Regulations and
Rules (Practices and Procedures in
Canada) in their respective jurisdictions.
SUPPLEMENTARY INFORMATION:
E:\FR\FM\11JYR1.SGM
11JYR1
Federal Register / Vol. 77, No. 133 / Wednesday, July 11, 2012 / Rules and Regulations
erowe on DSK2VPTVN1PROD with RULES
Under agreement with the SLSMC, the
SLSDC is amending the joint regulations
by updating the Regulations and Rules
in various categories. The changes
would update the following sections of
the Regulations and Rules: Condition of
Vessels; Seaway Navigation; Dangerous
Cargo; Information and Reports;
General; and, Navigation Closing
Procedures. These amendments are
necessary to take account of updated
procedures which will enhance the
safety of transits through the Seaway.
Many of these changes are to clarify
existing requirements in the regulations.
Where new requirements or regulations
are being made, an explanation for such
a change is provided below.
The joint regulations became effective
in Canada on July 9, 2012. For
consistency, because these are joint
regulations under international
agreement, and to avoid confusion
among users of the Seaway, the SLSDC
finds that there is good cause to make
the U.S. version of the amendments
effective upon the date of publication in
the Federal Register.
Regulatory Notices
Privacy Act: Anyone is able to search
the electronic form of all comments
received into any of our dockets by the
name of the individual submitting the
comment (or signing the comment, if
submitted on behalf of an association,
business, labor union, etc.). You may
review DOT’s complete Privacy Act
Statement in the Federal Register
published on April 11, 2000 (65 FR
19477–19478) or you may visit https://
www.Regulations.gov. The Notice of
Proposed Rulemaking was published in
the Federal Register on May 31, 2012
(76 FR 13088). No comments were
received.
The SLSDC is amending three
sections of the Condition of Vessels
portion of the joint Seaway regulations.
Under section 401.11, ‘‘Fairleads’’, due
to damage from fairleads on new
vessels, the SLSDC is requiring that all
sharp edges be rounded. In section
401.12, ‘‘Minimum requirements—
mooring lines and fairleads’’, the SLSDC
is addressing the use of wire lines on
vessels 100 m or less. In section 401.15,
‘‘Stern anchors’’, the Seaway entities are
requiring vessels of more than 125 m in
overall length as well as every
integrated tug and barge or articulated
tug and barge unit greater than 125 m in
overall length be equipped with a stern
anchor.
Several changes to the Seaway
Navigation section are being made. The
Seaway Corporations are amending their
joint rules in section 401.29, ‘‘Maximum
draft’’, to permit vessels using a ‘‘Draft
VerDate Mar<15>2010
14:30 Jul 10, 2012
Jkt 226001
Information System’’ (DIS) to transit the
Seaway up to 7 cm (3 inches) above the
maximum permissible draft allowed at
the time. The use of a DIS is an optional,
not a mandatory requirement, to transit
the Seaway. The DIS will allow the
vessel to transit the Seaway at a draft up
to 3 inches (7 cm) more than the
published maximum draft with prior
approval from the two Seaway entities.
Benefits of Using the DIS
The primary purpose of this
amendment is safety. The use of the DIS
will ensure that vessels maintain a safe
under keel clearance as they make
maximum use of the available water
column. DIS uses water level
measurements, bathymetry of the
channel bottom, and squat of the vessel
as it moves at different speeds and in
different channel types. The squat of a
vessel varies depending on the vessel
type, hull shape, and the type of
channel in which it is operating, and the
vessel’s speed. By including all the
factors, the under keel clearance value
is determined in real time. The
information on the projected under keel
clearance is integrated electronically
with chart data, high-resolution
bathymetry and other readings on a
single bridge display.
The technology features an algorithm,
which allows the Master to estimate
under keel clearance ahead, offering
time for a course change or other
required reaction in transit. With
Masters having more precise
information regarding the available
water column, the risk of a vessel
touching bottom or grounding is
reduced.
In addition to the safety benefits,
increasing the maximum allowable draft
will improve the Seaway’s productivity
and competitiveness. Depending on the
commodity carried, an additional three
inches of draft might account for as
much as 360 additional metric tons per
voyage.
Development of DIS Specification
The use of a DIS tool began in 2003
in the St. Mary’s River. In 2006, the
Seaway entities conducted 4 trials of the
tool used in the St. Mary’s River as a
proof of concept. Three tests were
conducted in the Montreal to Lake
Ontario (MLO) section of the Seaway
during 2007 under low water
conditions. During 2008, tests were
conducted in the MLO and Welland
Canal sections of the Seaway. In 2009,
eight (8) trials were conducted in the
Welland Canal section and ten (10)
trials were conducted in the MLO
section of the Seaway. In 2010 a DIS
pilot program was instituted in the MLO
PO 00000
Frm 00019
Fmt 4700
Sfmt 4700
40803
and Welland Canal. After successful
completion of the test trials and pilot
program and to ensure future
consistency and reliability of the DIS,
the two Seaway entities began the
development of a standard DIS
specification.
On January 19, 2011, the two Seaway
Corporations jointly published an
industrial implementation specification
entitled, ‘‘Implementation
Specification—a Draft Information
System for the St. Lawrence Seaway’’
(Specification). Following a public
comment period during which
comments received were considered in
the development of the Specification, a
final Implementation Specification was
published on the bi-national Web site at
https://www.greatlakes-seaway.com on
March 16, 2011. The Specification was
developed under the guidance of the St.
Lawrence Seaway Management
Corporation, the SLSDC, together with
representatives from system
manufacturers and the shipping
industry. The development of the
Specification followed accelerated
procedures derived from the
International Organization for Standards
(ISO) standardization process that
endeavored to develop a broad based
consensus standard. The DIS
Implementation Specification describes
the functionality and interfaces for a
system which utilizes water levels,
channel type, bathymetry, and vessel
speed and characteristics to determine
current and predicted under keel
clearance. On March 18, 2012, the first
DIS Tool was verified by a member of
the International Association of
Classification Societies (IACS) to be
compliant with the Specification.
In addition to these changes, the two
Seaway Corporations, in section 401.32,
‘‘Cargo booms—deck cargo’’ are
requiring notification of the height of
deck cargo in order to determine
appropriate wind restrictions.
In the Information and Reports
section, a change to section 401.79,
‘‘Advance notice of arrival, vessels
requiring inspection’’ is being made.
The amendments provide requirements
for reporting notice of arrival depending
on the vessel’s voyage time. Further,
vessels requiring inspection or reinspection will be required to provide a
24-hour notice of inspection based on
certain specified factors. The Advance
Notice of Arrival procedures are
currently in effect pursuant to Seaway
Notices.
The other changes to the joint
regulations are merely editorial or to
clarify existing requirements.
E:\FR\FM\11JYR1.SGM
11JYR1
40804
Federal Register / Vol. 77, No. 133 / Wednesday, July 11, 2012 / Rules and Regulations
Regulatory Evaluation
PART 401—SEAWAY REGULATIONS
AND RULES
This regulation involves a foreign
affairs function of the United States and
therefore Executive Order 12866 does
not apply and evaluation under the
Department of Transportation’s
Regulatory Policies and Procedures is
not required.
■
Regulatory Flexibility Act
Determination
■
Subpart A—Regulations
1. The authority citation for subpart A
of part 401 continues to read as follows:
Authority: 33 U.S.C. 983(a) and 984(a) (4),
as amended; 49 CFR 1.52, unless otherwise
noted.
2. In § 401.11, add paragraph (a)(4) to
read as follows:
I certify that this regulation will not
have a significant economic impact on
a substantial number of small entities.
The St. Lawrence Seaway Regulations
and Rules primarily relate to
commercial users of the Seaway, the
vast majority of whom are foreign vessel
operators. Therefore, any resulting costs
will be borne mostly by foreign vessels.
Environmental Impact
This regulation does not require an
environmental impact statement under
the National Environmental Policy Act
(49 U.S.C. 4321, et seq.) because it is not
a major federal action significantly
affecting the quality of the human
environment.
§ 401.11
Fairleads.
(a) * * *
(4) When passing synthetic lines
through a type of fairlead or closed
chock acceptable to the Manager and the
Corporation all sharp edges of the
fairlead, closed chock and/or bulwark
shall be rounded to protect the line from
chafing or breakage.
*
*
*
*
*
■ 3. In § 401.12 revise paragraph
(a)(1)(ii) to read as follows:
§ 401.12 Minimum requirements—mooring
lines and fairleads.
The Corporation has analyzed this
rule under the principles and criteria in
Executive Order 13132, dated August 4,
1999, and has determined that this
proposal does not have sufficient
federalism implications to warrant a
Federalism Assessment.
(a) * * *
(1) * * *
(ii) One synthetic hawser may be
hand held or if wire line is used shall
be powered. The line shall lead astern
from the break of the bow through a
closed chock to suitable bitts on deck
for synthetic line or led from a capstan,
winch drum or windlass to an approved
fairlead for a wire line.
*
*
*
*
*
■ 4. Revise § 401.15 to read as follows:
Unfunded Mandates
§ 401.15
Federalism
The Corporation has analyzed this
rule under Title II of the Unfunded
Mandates Reform Act of 1995 (Pub. L.
104–4, 109 Stat. 48) and determined that
it does not impose unfunded mandates
on State, local, and tribal governments
and the private sector requiring a
written statement of economic and
regulatory alternatives.
Paperwork Reduction Act
This regulation has been analyzed
under the Paperwork Reduction Act of
1995 and does not contain new or
modified information collection
requirements subject to the Office of
Management and Budget review.
erowe on DSK2VPTVN1PROD with RULES
List of Subjects in 33 CFR Part 401
Hazardous materials transportation,
Navigation (water), Penalties, Radio,
Reporting and recordkeeping
requirements, Vessels, Waterways.
Accordingly, the Saint Lawrence
Seaway Development Corporation
amends 33 CFR part 401 as follows:
VerDate Mar<15>2010
14:30 Jul 10, 2012
Jkt 226001
Stern anchors.
(a) Every vessel of more than 125 m
in overall length, the keel of which is
laid after January 1, 1975, shall be
equipped with a stern anchor.
(b) Every integrated tug and barge or
articulated tug and barge unit greater
than 125 m in overall length which is
constructed after January 1, 2003 shall
be equipped with a stern anchor.
■ 5. In § 401.28 revise paragraph (d) to
read as follows:
§ 401.28
*
*
*
*
(d) Notwithstanding the above speed
limits, every vessel approaching a free
standing lift bridge shall proceed at a
speed that it will be able to stop prior
to it reaching the Limit of Approach
sign should the raising of the bridge be
delayed.
*
*
*
*
*
■ 6. Revise § 401.29 to read as follows:
Maximum draft.
(a) Notwithstanding any provision
herein, the loading of cargo, draft and
PO 00000
Frm 00020
Fmt 4700
Sfmt 4700
(68 Stat. 93–96, 33 U.S.C. 981–990, as
amended and secs. 4, 5, 6, 7, 8, 12 and 13
of Sec. 2 of Pub. L. 95–474, 92 Stat. 1471)
7. In § 401.32 add paragraph (c) to
read as follows:
■
§ 401.32
Cargo booms-deck cargo.
*
Speed limits.
*
§ 401.29.
speed of a vessel in transit shall be
controlled by the master, who shall take
into account the vessel’s individual
characteristics and its tendency to list or
squat, so as to avoid striking bottom.1
(b) The draft of a vessel shall not, in
any case, exceed 79.2 dm or the
maximum permissible draft designated
in a Seaway Notice by the Manager and
the Corporation for the part of the
Seaway in which a vessel is passing.
(c) Any vessel equipped with An
operational Draft Information System
(DIS) Tool verified by a member of the
International Association of
Classification Societies (IACS) as
compliant with the Implementation
Specifications found at https://
www.greatlakes-seaway.com and
contained in the Seaway Handbook
under ‘‘Ship Transit and Equipment
Requirements’’ shall have onboard:
(1) Up-to-date electronic navigational
charts; and
(2) Up-to-date charts containing highresolution bathymetric data; and
(3) A pilot plug, if using a portable
DIS Tool, will be permitted, when using
the DIS Tool, subject to paragraph (a) of
this section, to increase their draft by no
more than 7 cm above the maximum
permissible draft prescribed under
paragraph (b) of this section in effect at
the time.
(d) Any vessel intending to use DIS
must notify the Manager or the
Corporation in writing at least 24-hours
prior to commencement of its initial
transit in the System with the DIS Tool.
(e) Verification document of the DIS
Tool must be kept on board the vessel
at all times and made available for
inspection.
(f) If for any reason the DIS becomes
inoperable, malfunctions, or is not used,
the vessel must notify the Manager or
the Corporation immediately.
*
*
*
*
(c) Seaway Traffic Control Center
shall be notified of the height of deck
cargo prior to transiting the Seaway or
when departing from a Port or Wharf
within the Seaway.
■ 8. In § 401.44, revise paragraph (b) to
read as follows:
§ 401.44
Mooring in locks.
*
*
*
*
*
(b) Once the mooring lines are on the
mooring posts, lines shall be kept slack
1 The main channels between the Port of Montreal
and Lake Erie have a controlling depth of 8.23m.
E:\FR\FM\11JYR1.SGM
11JYR1
40805
Federal Register / Vol. 77, No. 133 / Wednesday, July 11, 2012 / Rules and Regulations
until the ‘‘all clear’’ signal is given by
the lock personnel. When casting off
signal is received, mooring lines should
be kept slack until the ‘‘all clear’’ signal
is given by the lock personnel.
■ 9. In § 401.59, add paragraph (e) to
read as follows:
§ 401.59
Pollution.
*
*
*
*
*
(e) Except as authorized by the
Manager or the Corporation, no over the
side painting shall be allowed in the
Seaway.
*
*
*
*
*
■ 10. In § 401.72, revise paragraph (d) to
read as follows:
§ 401.72 Reporting—explosive and
hazardous cargo vessels.
*
*
*
*
*
(d) Every vessel carrying radioactive
substances shall, when reporting in,
give the number and date of issue of any
required certificate issued by the
Canadian Nuclear Safety Commission
(CNSC) and/or the U.S. Nuclear
Regulatory Commission (USNRC)
authorizing such shipment.
*
*
*
*
*
■ 11. Revise § 401.79 to read as follows:
§ 401.79 Advance notice of arrival, vessels
requiring inspection.
(a) Advance notice of arrival. All
foreign flagged vessels intending to
transit the Seaway shall submit one
complete electronic Notice of Arrival
(NOA) prior to entering at call in point
2 (CIP 2) as follows:
(1) If your voyage time to CIP 2 is 96
hours or more, you must submit an
electronic NOA 96 hours before entering
the Seaway at CIP 2.
(2) If your voyage time to CIP 2 is less
than 96 hours, you must submit an
electronic NOA before departure, but at
least 24 hours before entering the
Seaway at CIP 2.
(3) If there are changes to the
electronic NOA, submit them as soon as
practicable but at least 12 hours before
entering the Seaway at CIP 2.
(4) The NOA must be provided
electronically following the USCG
National Vessel Movement Center’s
(NVMC) procedures (https://
www.nvmc.uscg.gov).
(5) To complete the NOA correctly for
Seaway entry, select the following:
(i) ‘‘CIP 2’’ as the Arrival Port,
(ii) ‘‘Foreign to Saint Lawrence
Seaway’’ as the Voyage Type, and
(iii) ‘‘Saint Lawrence Seaway Transit’’
as the Arrival State, City and Receiving
Facility.
(b) Vessels requiring inspection or
reinspection. All pre-cleared vessels
must provide a 24 hour notice of
inspection as follows:
(1) Enhanced Seaway inspection. All
foreign flagged vessels and vessels of
unusual design are subject to a Seaway
inspection prior to initial transit of the
Seaway each navigation season.
(2) Inland self-inspection. Inland
domestic vessels which are approved by
the Seaway and are ISM certified and
have a company quality management
system, must submit the ‘‘SelfInspection Report’’, every 2 navigation
seasons and not later than 30 days after
‘‘fit out’’.
(3) Inland domestic vessels not
participating in the ‘‘Self-Inspection
Program’’ are subject to Seaway
inspection prior to every transit of the
Seaway.
(4) Tub/barge combinations not on the
‘‘Seaway Approved Tow’’ list are
subject to Seaway inspection prior to
every transit of the Seaway.
12. In § 401. 84, revise paragraph (c)
to read as follows:
■
§ 401.84 Reporting of impairment or other
hazard by vessels transiting within the
Seaway.
*
*
*
*
*
(c) Any malfunction of equipment on
the vessel
*
*
*
*
*
13. In § 401.89, add paragraph (a)(4) to
read as follows:
■
§ 401.89
Transit refused.
(a) * * *
(4) The vessel is not in compliance
with flag state and/or classification
society regulations.
■
14. Revise § 401.92 to read as follows:
§ 401.92
Wintering and laying-up.
No vessel shall winter within the
Seaway or lay-up within the Seaway
during the navigation season except
with the written permission of the
Manager or the Corporation and subject
to the conditions and charges that may
be imposed.
15. In Schedule II to Subpart A of Part
401—Table of Speeds, revise section
number 2 and footnote 1 to read as
follows:
*
*
*
*
*
■
SCHEDULE II TO SUBPART A OF PART 401—TABLE OF SPEEDS 1
Maximum speed over the bottom (knots)
From—
To—
Column III
*
*
*
*
*
2. Lake St. Louis Buoy A13 ................................. Lower Entrance Lower Beauharnois Lock ...........
*
*
*
*
*
12 (dnb); 14 (upb)
*
*
Column IV
*
11 (upb); 13 (dnb).
*
1 Maximum
erowe on DSK2VPTVN1PROD with RULES
speeds at which a vessel may travel in the identified area in both normal and high water conditions are set out in this schedule.
The Manager and the Corporation will, from time to time, designate the set of speed limits that is in effect.
Issued at Washington, DC on July 5, 2012.
Saint Lawrence Seaway Development
Corporation.
Craig H. Middlebrook,
Acting Administrator.
[FR Doc. 2012–16859 Filed 7–10–12; 8:45 am]
BILLING CODE 4910–61–P
ACTION:
34 CFR Part 690
SUMMARY:
[Docket ID ED–2012–OPE–0006]
RIN 1840–AD11
Federal Pell Grant Program; Correction
Office of Postsecondary
Education, Department of Education.
AGENCY:
VerDate Mar<15>2010
14:30 Jul 10, 2012
Jkt 226001
Interim final rule; correction.
DEPARTMENT OF EDUCATION
PO 00000
Frm 00021
Fmt 4700
Sfmt 4700
The Secretary of Education is
correcting the Federal Pell Grant
Program interim final rule published in
the Federal Register on May 2, 2012 (77
FR 25893). We waived rulemaking and
the delayed effective date under the
Administrative Procedure Act in this
interim final rule, but we did not
expressly waive the 60-day time period
for a major rule to become effective
E:\FR\FM\11JYR1.SGM
11JYR1
Agencies
[Federal Register Volume 77, Number 133 (Wednesday, July 11, 2012)]
[Rules and Regulations]
[Pages 40802-40805]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-16859]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Saint Lawrence Seaway Development Corporation
33 CFR Part 401
[Docket No. SLSDC-2012-0001]
RIN 2135-AA30
Seaway Regulations and Rules: Periodic Update, Various Categories
AGENCY: Saint Lawrence Seaway Development Corporation, DOT.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Saint Lawrence Seaway Development Corporation (SLSDC) and
the St. Lawrence Seaway Management Corporation (SLSMC) of Canada, under
international agreement, jointly publish and presently administer the
St. Lawrence Seaway Regulations and Rules (Practices and Procedures in
Canada) in their respective jurisdictions. Under agreement with the
SLSMC, the SLSDC is amending the joint regulations by updating the
Seaway Regulations and Rules in various categories. The changes will
update the following sections of the Regulations and Rules: Condition
of Vessels; Seaway Navigation; Dangerous Cargo; Information and
Reports; General; and, Navigation Closing Procedures. These amendments
are necessary to take account of updated procedures and will enhance
the safety of transits through the Seaway. Several of the amendments
are merely editorial or for clarification of existing requirements.
DATES: The final rule is effective July 11, 2012.
FOR FURTHER INFORMATION CONTACT: Carrie Mann Lavigne, Chief Counsel,
Saint Lawrence Seaway Development Corporation, 180 Andrews Street,
Massena, New York 13662; 315/764-3200.
SUPPLEMENTARY INFORMATION: The Saint Lawrence Seaway Development
Corporation (SLSDC) and the St. Lawrence Seaway Management Corporation
(SLSMC) of Canada, under international agreement, jointly publish and
presently administer the St. Lawrence Seaway Regulations and Rules
(Practices and Procedures in Canada) in their respective jurisdictions.
[[Page 40803]]
Under agreement with the SLSMC, the SLSDC is amending the joint
regulations by updating the Regulations and Rules in various
categories. The changes would update the following sections of the
Regulations and Rules: Condition of Vessels; Seaway Navigation;
Dangerous Cargo; Information and Reports; General; and, Navigation
Closing Procedures. These amendments are necessary to take account of
updated procedures which will enhance the safety of transits through
the Seaway. Many of these changes are to clarify existing requirements
in the regulations. Where new requirements or regulations are being
made, an explanation for such a change is provided below.
The joint regulations became effective in Canada on July 9, 2012.
For consistency, because these are joint regulations under
international agreement, and to avoid confusion among users of the
Seaway, the SLSDC finds that there is good cause to make the U.S.
version of the amendments effective upon the date of publication in the
Federal Register.
Regulatory Notices
Privacy Act: Anyone is able to search the electronic form of all
comments received into any of our dockets by the name of the individual
submitting the comment (or signing the comment, if submitted on behalf
of an association, business, labor union, etc.). You may review DOT's
complete Privacy Act Statement in the Federal Register published on
April 11, 2000 (65 FR 19477-19478) or you may visit https://www.Regulations.gov. The Notice of Proposed Rulemaking was published in
the Federal Register on May 31, 2012 (76 FR 13088). No comments were
received.
The SLSDC is amending three sections of the Condition of Vessels
portion of the joint Seaway regulations. Under section 401.11,
``Fairleads'', due to damage from fairleads on new vessels, the SLSDC
is requiring that all sharp edges be rounded. In section 401.12,
``Minimum requirements--mooring lines and fairleads'', the SLSDC is
addressing the use of wire lines on vessels 100 m or less. In section
401.15, ``Stern anchors'', the Seaway entities are requiring vessels of
more than 125 m in overall length as well as every integrated tug and
barge or articulated tug and barge unit greater than 125 m in overall
length be equipped with a stern anchor.
Several changes to the Seaway Navigation section are being made.
The Seaway Corporations are amending their joint rules in section
401.29, ``Maximum draft'', to permit vessels using a ``Draft
Information System'' (DIS) to transit the Seaway up to 7 cm (3 inches)
above the maximum permissible draft allowed at the time. The use of a
DIS is an optional, not a mandatory requirement, to transit the Seaway.
The DIS will allow the vessel to transit the Seaway at a draft up to 3
inches (7 cm) more than the published maximum draft with prior approval
from the two Seaway entities.
Benefits of Using the DIS
The primary purpose of this amendment is safety. The use of the DIS
will ensure that vessels maintain a safe under keel clearance as they
make maximum use of the available water column. DIS uses water level
measurements, bathymetry of the channel bottom, and squat of the vessel
as it moves at different speeds and in different channel types. The
squat of a vessel varies depending on the vessel type, hull shape, and
the type of channel in which it is operating, and the vessel's speed.
By including all the factors, the under keel clearance value is
determined in real time. The information on the projected under keel
clearance is integrated electronically with chart data, high-resolution
bathymetry and other readings on a single bridge display.
The technology features an algorithm, which allows the Master to
estimate under keel clearance ahead, offering time for a course change
or other required reaction in transit. With Masters having more precise
information regarding the available water column, the risk of a vessel
touching bottom or grounding is reduced.
In addition to the safety benefits, increasing the maximum
allowable draft will improve the Seaway's productivity and
competitiveness. Depending on the commodity carried, an additional
three inches of draft might account for as much as 360 additional
metric tons per voyage.
Development of DIS Specification
The use of a DIS tool began in 2003 in the St. Mary's River. In
2006, the Seaway entities conducted 4 trials of the tool used in the
St. Mary's River as a proof of concept. Three tests were conducted in
the Montreal to Lake Ontario (MLO) section of the Seaway during 2007
under low water conditions. During 2008, tests were conducted in the
MLO and Welland Canal sections of the Seaway. In 2009, eight (8) trials
were conducted in the Welland Canal section and ten (10) trials were
conducted in the MLO section of the Seaway. In 2010 a DIS pilot program
was instituted in the MLO and Welland Canal. After successful
completion of the test trials and pilot program and to ensure future
consistency and reliability of the DIS, the two Seaway entities began
the development of a standard DIS specification.
On January 19, 2011, the two Seaway Corporations jointly published
an industrial implementation specification entitled, ``Implementation
Specification--a Draft Information System for the St. Lawrence Seaway''
(Specification). Following a public comment period during which
comments received were considered in the development of the
Specification, a final Implementation Specification was published on
the bi-national Web site at https://www.greatlakes-seaway.com on March
16, 2011. The Specification was developed under the guidance of the St.
Lawrence Seaway Management Corporation, the SLSDC, together with
representatives from system manufacturers and the shipping industry.
The development of the Specification followed accelerated procedures
derived from the International Organization for Standards (ISO)
standardization process that endeavored to develop a broad based
consensus standard. The DIS Implementation Specification describes the
functionality and interfaces for a system which utilizes water levels,
channel type, bathymetry, and vessel speed and characteristics to
determine current and predicted under keel clearance. On March 18,
2012, the first DIS Tool was verified by a member of the International
Association of Classification Societies (IACS) to be compliant with the
Specification.
In addition to these changes, the two Seaway Corporations, in
section 401.32, ``Cargo booms--deck cargo'' are requiring notification
of the height of deck cargo in order to determine appropriate wind
restrictions.
In the Information and Reports section, a change to section 401.79,
``Advance notice of arrival, vessels requiring inspection'' is being
made. The amendments provide requirements for reporting notice of
arrival depending on the vessel's voyage time. Further, vessels
requiring inspection or re-inspection will be required to provide a 24-
hour notice of inspection based on certain specified factors. The
Advance Notice of Arrival procedures are currently in effect pursuant
to Seaway Notices.
The other changes to the joint regulations are merely editorial or
to clarify existing requirements.
[[Page 40804]]
Regulatory Evaluation
This regulation involves a foreign affairs function of the United
States and therefore Executive Order 12866 does not apply and
evaluation under the Department of Transportation's Regulatory Policies
and Procedures is not required.
Regulatory Flexibility Act Determination
I certify that this regulation will not have a significant economic
impact on a substantial number of small entities. The St. Lawrence
Seaway Regulations and Rules primarily relate to commercial users of
the Seaway, the vast majority of whom are foreign vessel operators.
Therefore, any resulting costs will be borne mostly by foreign vessels.
Environmental Impact
This regulation does not require an environmental impact statement
under the National Environmental Policy Act (49 U.S.C. 4321, et seq.)
because it is not a major federal action significantly affecting the
quality of the human environment.
Federalism
The Corporation has analyzed this rule under the principles and
criteria in Executive Order 13132, dated August 4, 1999, and has
determined that this proposal does not have sufficient federalism
implications to warrant a Federalism Assessment.
Unfunded Mandates
The Corporation has analyzed this rule under Title II of the
Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4, 109 Stat. 48) and
determined that it does not impose unfunded mandates on State, local,
and tribal governments and the private sector requiring a written
statement of economic and regulatory alternatives.
Paperwork Reduction Act
This regulation has been analyzed under the Paperwork Reduction Act
of 1995 and does not contain new or modified information collection
requirements subject to the Office of Management and Budget review.
List of Subjects in 33 CFR Part 401
Hazardous materials transportation, Navigation (water), Penalties,
Radio, Reporting and recordkeeping requirements, Vessels, Waterways.
Accordingly, the Saint Lawrence Seaway Development Corporation
amends 33 CFR part 401 as follows:
PART 401--SEAWAY REGULATIONS AND RULES
Subpart A--Regulations
0
1. The authority citation for subpart A of part 401 continues to read
as follows:
Authority: 33 U.S.C. 983(a) and 984(a) (4), as amended; 49 CFR
1.52, unless otherwise noted.
0
2. In Sec. 401.11, add paragraph (a)(4) to read as follows:
Sec. 401.11 Fairleads.
(a) * * *
(4) When passing synthetic lines through a type of fairlead or
closed chock acceptable to the Manager and the Corporation all sharp
edges of the fairlead, closed chock and/or bulwark shall be rounded to
protect the line from chafing or breakage.
* * * * *
0
3. In Sec. 401.12 revise paragraph (a)(1)(ii) to read as follows:
Sec. 401.12 Minimum requirements--mooring lines and fairleads.
(a) * * *
(1) * * *
(ii) One synthetic hawser may be hand held or if wire line is used
shall be powered. The line shall lead astern from the break of the bow
through a closed chock to suitable bitts on deck for synthetic line or
led from a capstan, winch drum or windlass to an approved fairlead for
a wire line.
* * * * *
0
4. Revise Sec. 401.15 to read as follows:
Sec. 401.15 Stern anchors.
(a) Every vessel of more than 125 m in overall length, the keel of
which is laid after January 1, 1975, shall be equipped with a stern
anchor.
(b) Every integrated tug and barge or articulated tug and barge
unit greater than 125 m in overall length which is constructed after
January 1, 2003 shall be equipped with a stern anchor.
0
5. In Sec. 401.28 revise paragraph (d) to read as follows:
Sec. 401.28 Speed limits.
* * * * *
(d) Notwithstanding the above speed limits, every vessel
approaching a free standing lift bridge shall proceed at a speed that
it will be able to stop prior to it reaching the Limit of Approach sign
should the raising of the bridge be delayed.
* * * * *
0
6. Revise Sec. 401.29 to read as follows:
Sec. 401.29. Maximum draft.
(a) Notwithstanding any provision herein, the loading of cargo,
draft and speed of a vessel in transit shall be controlled by the
master, who shall take into account the vessel's individual
characteristics and its tendency to list or squat, so as to avoid
striking bottom.\1\
---------------------------------------------------------------------------
\1\ The main channels between the Port of Montreal and Lake Erie
have a controlling depth of 8.23m.
---------------------------------------------------------------------------
(b) The draft of a vessel shall not, in any case, exceed 79.2 dm or
the maximum permissible draft designated in a Seaway Notice by the
Manager and the Corporation for the part of the Seaway in which a
vessel is passing.
(c) Any vessel equipped with An operational Draft Information
System (DIS) Tool verified by a member of the International Association
of Classification Societies (IACS) as compliant with the Implementation
Specifications found at https://www.greatlakes-seaway.com and contained
in the Seaway Handbook under ``Ship Transit and Equipment
Requirements'' shall have onboard:
(1) Up-to-date electronic navigational charts; and
(2) Up-to-date charts containing high-resolution bathymetric data;
and
(3) A pilot plug, if using a portable DIS Tool, will be permitted,
when using the DIS Tool, subject to paragraph (a) of this section, to
increase their draft by no more than 7 cm above the maximum permissible
draft prescribed under paragraph (b) of this section in effect at the
time.
(d) Any vessel intending to use DIS must notify the Manager or the
Corporation in writing at least 24-hours prior to commencement of its
initial transit in the System with the DIS Tool.
(e) Verification document of the DIS Tool must be kept on board the
vessel at all times and made available for inspection.
(f) If for any reason the DIS becomes inoperable, malfunctions, or
is not used, the vessel must notify the Manager or the Corporation
immediately.
(68 Stat. 93-96, 33 U.S.C. 981-990, as amended and secs. 4, 5, 6, 7,
8, 12 and 13 of Sec. 2 of Pub. L. 95-474, 92 Stat. 1471)
0
7. In Sec. 401.32 add paragraph (c) to read as follows:
Sec. 401.32 Cargo booms-deck cargo.
* * * * *
(c) Seaway Traffic Control Center shall be notified of the height
of deck cargo prior to transiting the Seaway or when departing from a
Port or Wharf within the Seaway.
0
8. In Sec. 401.44, revise paragraph (b) to read as follows:
Sec. 401.44 Mooring in locks.
* * * * *
(b) Once the mooring lines are on the mooring posts, lines shall be
kept slack
[[Page 40805]]
until the ``all clear'' signal is given by the lock personnel. When
casting off signal is received, mooring lines should be kept slack
until the ``all clear'' signal is given by the lock personnel.
0
9. In Sec. 401.59, add paragraph (e) to read as follows:
Sec. 401.59 Pollution.
* * * * *
(e) Except as authorized by the Manager or the Corporation, no over
the side painting shall be allowed in the Seaway.
* * * * *
0
10. In Sec. 401.72, revise paragraph (d) to read as follows:
Sec. 401.72 Reporting--explosive and hazardous cargo vessels.
* * * * *
(d) Every vessel carrying radioactive substances shall, when
reporting in, give the number and date of issue of any required
certificate issued by the Canadian Nuclear Safety Commission (CNSC)
and/or the U.S. Nuclear Regulatory Commission (USNRC) authorizing such
shipment.
* * * * *
0
11. Revise Sec. 401.79 to read as follows:
Sec. 401.79 Advance notice of arrival, vessels requiring inspection.
(a) Advance notice of arrival. All foreign flagged vessels
intending to transit the Seaway shall submit one complete electronic
Notice of Arrival (NOA) prior to entering at call in point 2 (CIP 2) as
follows:
(1) If your voyage time to CIP 2 is 96 hours or more, you must
submit an electronic NOA 96 hours before entering the Seaway at CIP 2.
(2) If your voyage time to CIP 2 is less than 96 hours, you must
submit an electronic NOA before departure, but at least 24 hours before
entering the Seaway at CIP 2.
(3) If there are changes to the electronic NOA, submit them as soon
as practicable but at least 12 hours before entering the Seaway at CIP
2.
(4) The NOA must be provided electronically following the USCG
National Vessel Movement Center's (NVMC) procedures (https://www.nvmc.uscg.gov).
(5) To complete the NOA correctly for Seaway entry, select the
following:
(i) ``CIP 2'' as the Arrival Port,
(ii) ``Foreign to Saint Lawrence Seaway'' as the Voyage Type, and
(iii) ``Saint Lawrence Seaway Transit'' as the Arrival State, City
and Receiving Facility.
(b) Vessels requiring inspection or reinspection. All pre-cleared
vessels must provide a 24 hour notice of inspection as follows:
(1) Enhanced Seaway inspection. All foreign flagged vessels and
vessels of unusual design are subject to a Seaway inspection prior to
initial transit of the Seaway each navigation season.
(2) Inland self-inspection. Inland domestic vessels which are
approved by the Seaway and are ISM certified and have a company quality
management system, must submit the ``Self-Inspection Report'', every 2
navigation seasons and not later than 30 days after ``fit out''.
(3) Inland domestic vessels not participating in the ``Self-
Inspection Program'' are subject to Seaway inspection prior to every
transit of the Seaway.
(4) Tub/barge combinations not on the ``Seaway Approved Tow'' list
are subject to Seaway inspection prior to every transit of the Seaway.
0
12. In Sec. 401. 84, revise paragraph (c) to read as follows:
Sec. 401.84 Reporting of impairment or other hazard by vessels
transiting within the Seaway.
* * * * *
(c) Any malfunction of equipment on the vessel
* * * * *
0
13. In Sec. 401.89, add paragraph (a)(4) to read as follows:
Sec. 401.89 Transit refused.
(a) * * *
(4) The vessel is not in compliance with flag state and/or
classification society regulations.
0
14. Revise Sec. 401.92 to read as follows:
Sec. 401.92 Wintering and laying-up.
No vessel shall winter within the Seaway or lay-up within the
Seaway during the navigation season except with the written permission
of the Manager or the Corporation and subject to the conditions and
charges that may be imposed.
0
15. In Schedule II to Subpart A of Part 401--Table of Speeds, revise
section number 2 and footnote 1 to read as follows:
* * * * *
Schedule II to Subpart A of Part 401--Table of Speeds \1\
----------------------------------------------------------------------------------------------------------------
Maximum speed over the bottom (knots)
From-- To-- ----------------------------------------------------------
Column III Column IV
----------------------------------------------------------------------------------------------------------------
* * * * * * *
2. Lake St. Louis Buoy A13...... Lower Entrance 12 (dnb); 14 (upb) 11 (upb); 13 (dnb).
Lower Beauharnois
Lock.
* * * * * * *
----------------------------------------------------------------------------------------------------------------
\1\ Maximum speeds at which a vessel may travel in the identified area in both normal and high water conditions
are set out in this schedule. The Manager and the Corporation will, from time to time, designate the set of
speed limits that is in effect.
Issued at Washington, DC on July 5, 2012.
Saint Lawrence Seaway Development Corporation.
Craig H. Middlebrook,
Acting Administrator.