Cheniere Creole Trail Pipeline Company, L.P.; Notice of Intent To Prepare an Environmental Assessment for the Proposed Creole Trail Expansion Project and Request for Comments on Environmental Issues, 36525-36527 [2012-14879]

Download as PDF srobinson on DSK4SPTVN1PROD with NOTICES Federal Register / Vol. 77, No. 118 / Tuesday, June 19, 2012 / Notices Maine. The project would not occupy lands of the United States. g. Filed Pursuant to: Public Utility Regulatory Policies Act of 1978, 16 U.S.C. 2705, 2708. h. Applicant Contact: Anthony P. Grassi, Freedom Falls LLC, 363 Belfast Road, Camden, ME 04843, (207) 236– 4663. i. FERC Contact: Samantha Davidson, (202) 502–6839 or samantha.davidson@ ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: July 31, 2012. All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ ferconline.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc. gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. m. The application is not ready for environmental analysis at this time. VerDate Mar<15>2010 16:39 Jun 18, 2012 Jkt 226001 n. The proposed Freedom Falls Hydroelectric Project would consist of: (1) An existing 90-foot-long, 12-foothigh concrete-capped stone masonry dam with a 25-foot-long, 10-foot-high spillway with two vertical lift sluice gates and a crest elevation of 452.5 feet mean sea level (msl); (2) an existing 1.6acre impoundment with a normal maximum water surface elevation of 453.0 feet msl; (3) a new intake structure equipped with an 8-foot-high, 5-footwide trashrack that would be modified to have 1-inch clear bar spacing, and a 3-foot-high, 4.75-foot-wide slide gate; (4) a new downstream American eel passage facility and working platform; (5) a new 60-foot-long, 30-inch-diameter steel penstock leading to; (6) an existing 20-foot-wide, by 30-foot-long generating room containing a new 38.3 kilowatt turbine-generator unit; (7) a new 20foot-long, 5-foot-wide tailrace; (8) a new 30-foot-long, 110-volt transmission line; and (9) appurtenant facilities. The proposed project is estimated to generate an average of 66,000 kilowatthours annually. o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. With this notice, we are initiating consultation with the Maine Historic Preservation Commission, as required by 106, National Historic Preservation Act, and the regulations of the Advisory Council on Historic Preservation, 36, CFR, at 800.4. q. Procedural schedule: The application will be processed according to the following preliminary Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate (e.g., if scoping is waived, the schedule would be shortened). Issue Deficiency Letter ...... Issue Notice of Acceptance Issue Scoping Document .. Issue Notice of ready for environmental analysis. Issue Notice of the availability of the EA. PO 00000 Frm 00049 Fmt 4703 August 2012. October 2012. November 2012. January 2013. May 2013. Sfmt 4703 36525 Dated: June 13, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–14877 Filed 6–18–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP12–351–000] Cheniere Creole Trail Pipeline Company, L.P.; Notice of Intent To Prepare an Environmental Assessment for the Proposed Creole Trail Expansion Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Creole Trail Expansion Project involving construction and operation of facilities by Cheniere Creole Trail Pipeline Company, L.P. (Cheniere) in Beauregard and Cameron Parishes, Louisiana. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on July 13, 2012. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. Summary of the Proposed Project Cheniere proposes to construct and operate a new compressor station and associated facilities in Beauregard Parish, Louisiana, and miscellaneous facilities at the existing Sabine Pass Liquefied Natural Gas (LNG) Terminal in Cameron Parish, Louisiana. According to Cheniere, its project would enable bi-directional gas flow on the Creole Trail Pipeline system and allow for the delivery of feed gas to the Sabine Pass Liquefaction Project. The Creole Trail Expansion Project would create 1,530,000 dekatherms per day of new firm reverse flow capacity. The Creole Trail Expansion Project would consist of the following facilities: E:\FR\FM\19JNN1.SGM 19JNN1 36526 Federal Register / Vol. 77, No. 118 / Tuesday, June 19, 2012 / Notices • A new 53,125-horsepower compressor station (Gillis Compressor Station); • Reconfiguration of three existing meter and regulation (M&R) stations to allow bi-directional flow and increased capacity; • Approximately 200 feet of 42-inchdiameter pipeline from the existing mainline pipeline into the existing Sabine Pass LNG Terminal; and • A pig 1 trap and associated valves at the Sabine Pass LNG Terminal. The general location of the project facilities is shown in appendix 1.2 Land Requirements for Construction Construction of the proposed facilities would disturb about 31.5 acres of land for the aboveground facilities and the pipeline. Following construction, Cheniere would maintain about 15.7 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. Two of the M&R stations are co-located with the proposed Gillis Compressor Station and the other is located approximately 1.0 mile north of the proposed compressor station. The pipeline, pig trap, and associated valves would be located at the Sabine Pass LNG Terminal. srobinson on DSK4SPTVN1PROD with NOTICES The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the 1 A ‘‘pig’’ is a tool that is inserted into and moves through the pipeline, and is used for cleaning the pipeline, internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. VerDate Mar<15>2010 16:39 Jun 18, 2012 Jkt 226001 proposed project under these general headings: • Geology and soils; • Land use; • Water resources, fisheries, and wetlands; • Cultural resources; • Socioeconomics; • Vegetation and wildlife; • Air quality and noise; • Endangered and threatened species; and • Public safety. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section beginning on page 4. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA 4. Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the Louisiana State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.5 We will define the 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before July 13, 2012. For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP12–351–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. in or eligible for inclusion in the National Register of Historic Places. E:\FR\FM\19JNN1.SGM 19JNN1 Federal Register / Vol. 77, No. 118 / Tuesday, June 19, 2012 / Notices Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. srobinson on DSK4SPTVN1PROD with NOTICES Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP12–351). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the VerDate Mar<15>2010 16:39 Jun 18, 2012 Jkt 226001 Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: June 13, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–14879 Filed 6–18–12; 8:45 am] 36527 Persons unable to file electronically should submit an original and 7 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on Monday, June 25, 2012. BILLING CODE 6717–01–P Dated: June 13, 2012. Kimberly D. Bose, Secretary. DEPARTMENT OF ENERGY [FR Doc. 2012–14878 Filed 6–18–12; 8:45 am] BILLING CODE 6717–01–P Federal Energy Regulatory Commission DEPARTMENT OF ENERGY [Docket No. PR12–28–000] Enstor Grama Ridge Storage and Transportation, L.L.C.; Notice of Filing Take notice that on June 11, 2012, Enstor Grama Ridge Storage and Transportation, L.L.C. filed to revise its Statement of Operating Conditions to correct, update, and or remove certain provisions and other housekeeping changes as more fully described in the filing. Any person desiring to participate in this rate filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the date as indicated below. Anyone filing an intervention or protest must serve a copy of that document on the Applicant. Anyone filing an intervention or protest on or before the intervention or protest date need not serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 Federal Energy Regulatory Commission [Docket No. PR12–29–000] Enstor Katy Storage and Transportation, L.P.; Notice of Filing Take notice that on June 12, 2012, Enstor Katy Storage and Transportation, L.P. filed to revise its Statement of Operating Conditions to correct, update, and or remove certain provisions and other housekeeping changes as more fully described in the filing. Any person desiring to participate in this rate filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the date as indicated below. Anyone filing an intervention or protest must serve a copy of that document on the Applicant. Anyone filing an intervention or protest on or before the intervention or protest date need not serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and E:\FR\FM\19JNN1.SGM 19JNN1

Agencies

[Federal Register Volume 77, Number 118 (Tuesday, June 19, 2012)]
[Notices]
[Pages 36525-36527]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-14879]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP12-351-000]


Cheniere Creole Trail Pipeline Company, L.P.; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Creole Trail 
Expansion Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Creole Trail Expansion Project 
involving construction and operation of facilities by Cheniere Creole 
Trail Pipeline Company, L.P. (Cheniere) in Beauregard and Cameron 
Parishes, Louisiana. The Commission will use this EA in its decision-
making process to determine whether the project is in the public 
convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on July 13, 2012.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.

Summary of the Proposed Project

    Cheniere proposes to construct and operate a new compressor station 
and associated facilities in Beauregard Parish, Louisiana, and 
miscellaneous facilities at the existing Sabine Pass Liquefied Natural 
Gas (LNG) Terminal in Cameron Parish, Louisiana. According to Cheniere, 
its project would enable bi-directional gas flow on the Creole Trail 
Pipeline system and allow for the delivery of feed gas to the Sabine 
Pass Liquefaction Project. The Creole Trail Expansion Project would 
create 1,530,000 dekatherms per day of new firm reverse flow capacity.
    The Creole Trail Expansion Project would consist of the following 
facilities:

[[Page 36526]]

     A new 53,125-horsepower compressor station (Gillis 
Compressor Station);
     Reconfiguration of three existing meter and regulation 
(M&R) stations to allow bi-directional flow and increased capacity;
     Approximately 200 feet of 42-inch-diameter pipeline from 
the existing mainline pipeline into the existing Sabine Pass LNG 
Terminal; and
     A pig \1\ trap and associated valves at the Sabine Pass 
LNG Terminal.
---------------------------------------------------------------------------

    \1\ A ``pig'' is a tool that is inserted into and moves through 
the pipeline, and is used for cleaning the pipeline, internal 
inspections, or other purposes.
---------------------------------------------------------------------------

    The general location of the project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 31.5 
acres of land for the aboveground facilities and the pipeline. 
Following construction, Cheniere would maintain about 15.7 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses. Two of the M&R stations 
are co-located with the proposed Gillis Compressor Station and the 
other is located approximately 1.0 mile north of the proposed 
compressor station. The pipeline, pig trap, and associated valves would 
be located at the Sabine Pass LNG Terminal.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     Land use;
     Water resources, fisheries, and wetlands;
     Cultural resources;
     Socioeconomics;
     Vegetation and wildlife;
     Air quality and noise;
     Endangered and threatened species; and
     Public safety.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section beginning on page 4.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the EA 
\4\. Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the Louisiana State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before July 
13, 2012.
    For your convenience, there are three methods which you can use to 
submit your comments to the Commission. In all instances please 
reference the project docket number (CP12-351-000) with your 
submission. The Commission encourages electronic filing of comments and 
has expert staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for interested persons to 
submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

[[Page 36527]]

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
like to remove your name from the mailing list, please return the 
attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP12-
351). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: June 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-14879 Filed 6-18-12; 8:45 am]
BILLING CODE 6717-01-P