Freedom Falls, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 36524-36525 [2012-14877]
Download as PDF
srobinson on DSK4SPTVN1PROD with NOTICES
36524
Federal Register / Vol. 77, No. 118 / Tuesday, June 19, 2012 / Notices
applications submitted by project
sponsors that meet CCPI’s goals.
Recognizing that the range of
reasonable alternatives in the context of
financial assistance and contracting is in
large part determined by the number
and nature of the proposals submitted,
section 216 of DOE’s NEPA regulations
requires the Department to prepare an
‘‘environmental critique’’ that assesses
the environmental impacts and issues
relating to each of the proposals that the
DOE selecting official considers for an
award. See 10 CFR 1021.216. This
official considers these impacts and
issues, along with other aspects of the
proposals (such as technical merit and
financial ability) and the program’s
objectives, in making awards. DOE
prepared a critique of the proposals that
were deemed suitable for selection in
this round of awards for the CCPI
program.
Once DOE selects a project for an
award, the range of reasonable
alternatives becomes the project as
proposed by the applicant, any
alternatives still under consideration by
the applicant or that are reasonable
within the confines of the project as
proposed (e.g., the particular location of
the generating plant on the 1,106-acre
site or the rights-of-way (ROWs) for
linear facilities), and a no action
alternative. Regarding the no action
alternative, DOE assumes for purposes
of the EIS that, if it were to decide to
withhold financial assistance from the
project, the project would not proceed.
DOE currently plans to analyze the
project as proposed by HECA (with and
without any mitigating conditions that
DOE or the CEC may identify as
reasonable and appropriate);
alternatives to HECA’s proposal that it
is still considering (e.g., the ROWs for
linear facilities); and the no action
alternative.
As noted above, DOE will analyze any
‘‘project-specific’’ alternatives that
HECA is still considering such as the
coal delivery alternatives, and other
reasonable alternatives that may be
suggested during the scoping period.
HECA is no longer considering other
project-specific alternatives identified in
the original NOI (i.e., the location of the
facility within the site boundaries,
alternative routes for the process water
supply pipeline, CO2 pipeline and
transmission line).
Under the no action alternative, DOE
would not provide funding to HECA. In
the absence of financial assistance from
DOE, HECA could reasonably pursue
two options. It could build the project
without DOE funding; the impacts of
this option would be essentially the
same as those of DOE’s proposed action.
VerDate Mar<15>2010
16:39 Jun 18, 2012
Jkt 226001
Or, HECA could choose not to pursue its
project, and there would be no impacts
from the project. This option would not
contribute to the goal of the CCPI
program, which is to accelerate
commercial deployment of advanced
coal technologies that provide the
United States with clean, reliable, and
affordable energy. However, as required
by NEPA, DOE analyzes this option as
the no action alternative in order to
have a meaningful comparison between
the impacts of DOE providing financial
assistance and withholding that
assistance.
Alternatives considered by HECA in
developing its proposed project will be
discussed in the EIS. Differences
between DOE’s range of reasonable
alternatives and those considered by the
CEC will also be delineated. HECA
analyzed several alternative sites and
determined that the only reasonable site
alternative was its proposed site based
on, among other things, the presence or
absence of sensitive resources; the
availability of land; and the site’s
proximity to the brackish groundwater
supply, to electric transmission and
natural gas facilities, and to a CO2
storage reservoir.3 The EIS will describe
HECA’s site selection process. However,
DOE does not plan to analyze in detail
the alternatives sites considered by
HECA because HECA is no longer
considering these sites, they were not
part of HECA’s proposal, and therefore
they are no longer reasonable
alternatives.
Floodplains and Wetlands
The footprint of the proposed IGCC
and manufacturing facility and carbon
capture facility would not affect any
wetlands or floodplains. Wetland and
floodplain impacts, if any, from the
construction of pipelines would be
avoided by the use of horizontal
directional drilling. In the event that the
EIS identifies that wetlands or
floodplains on the surface would be
affected by the project (including its
linear facilities) or connected actions,
DOE will prepare a floodplain and
wetland assessment in accordance with
its regulations at 10 CFR Part 1022 and
include the assessment in the EIS.
Preliminary Identification of
Environmental Issues
The original NOI contained a
preliminary list and description of
potential environmental issues (75 FR
17397–401); the list of issues would
remain the same for the project as
3 HECA initially selected another site; it
subsequently decided to move the project when it
discovered the existence of sensitive biological
resources at the initial site.
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
modified after SCS Energy’s acquisition
of HECA. The list includes those
impacts and resource areas typically
addressed in an EIS for a project of this
type: Atmospheric resources; water
resources; infrastructure and land use;
solid waste; visual resources;
floodplains and wetlands; ecological
resources; safety and health;
construction-related impacts;
community impacts; cultural and
archaeological resources; threatened and
endangered species; 4 and cumulative
effects. Currently, no threatened or
endangered species have been identified
at the proposed plant site; three listed
plant species and nine listed wildlife
species (rather than the eight as stated
in the original NOI) have the potential
to occur in the ROWs of the linear
facilities.
Additions to or deletions from the list
may occur as a result of this scoping
process. The level of analysis of issues
in the EIS will be in accordance with
their level of importance. The most
detailed analyses are likely to focus on
potential impacts to air, water, and
ecological resources.
Issued in Pittsburgh, PA, this 12th day of
June 2012.
Anthony V. Cugini,
Director, National Energy Technology
Laboratory.
[FR Doc. 2012–14867 Filed 6–18–12; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14421–000]
Freedom Falls, LLC; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Exemption
from Licensing.
b. Project No.: 14421–000.
c. Date filed: June 1, 2012.
d. Applicant: Freedom Falls, LLC.
e. Name of Project: Freedom Falls
Hydroelectric Project.
f. Location: On Sandy Stream, in the
Town of Freedom, Waldo County,
4 No threatened or endangered species have been
identified at the proposed plant site; three listed
plant species and nine listed wildlife species (rather
than the eight as stated in the original NOI) have
the potential to occur in the ROWs of the linear
facilities.
E:\FR\FM\19JNN1.SGM
19JNN1
srobinson on DSK4SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 118 / Tuesday, June 19, 2012 / Notices
Maine. The project would not occupy
lands of the United States.
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Anthony P.
Grassi, Freedom Falls LLC, 363 Belfast
Road, Camden, ME 04843, (207) 236–
4663.
i. FERC Contact: Samantha Davidson,
(202) 502–6839 or samantha.davidson@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: July 31, 2012.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
ferconline.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
information at the end of your
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
m. The application is not ready for
environmental analysis at this time.
VerDate Mar<15>2010
16:39 Jun 18, 2012
Jkt 226001
n. The proposed Freedom Falls
Hydroelectric Project would consist of:
(1) An existing 90-foot-long, 12-foothigh concrete-capped stone masonry
dam with a 25-foot-long, 10-foot-high
spillway with two vertical lift sluice
gates and a crest elevation of 452.5 feet
mean sea level (msl); (2) an existing 1.6acre impoundment with a normal
maximum water surface elevation of
453.0 feet msl; (3) a new intake structure
equipped with an 8-foot-high, 5-footwide trashrack that would be modified
to have 1-inch clear bar spacing, and a
3-foot-high, 4.75-foot-wide slide gate; (4)
a new downstream American eel
passage facility and working platform;
(5) a new 60-foot-long, 30-inch-diameter
steel penstock leading to; (6) an existing
20-foot-wide, by 30-foot-long generating
room containing a new 38.3 kilowatt
turbine-generator unit; (7) a new 20foot-long, 5-foot-wide tailrace; (8) a new
30-foot-long, 110-volt transmission line;
and (9) appurtenant facilities. The
proposed project is estimated to
generate an average of 66,000 kilowatthours annually.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Maine Historic
Preservation Commission, as required
by 106, National Historic Preservation
Act, and the regulations of the Advisory
Council on Historic Preservation, 36,
CFR, at 800.4.
q. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate
(e.g., if scoping is waived, the schedule
would be shortened).
Issue Deficiency Letter ......
Issue Notice of Acceptance
Issue Scoping Document ..
Issue Notice of ready for
environmental analysis.
Issue Notice of the availability of the EA.
PO 00000
Frm 00049
Fmt 4703
August 2012.
October 2012.
November 2012.
January 2013.
May 2013.
Sfmt 4703
36525
Dated: June 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–14877 Filed 6–18–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–351–000]
Cheniere Creole Trail Pipeline
Company, L.P.; Notice of Intent To
Prepare an Environmental Assessment
for the Proposed Creole Trail
Expansion Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Creole Trail Expansion Project
involving construction and operation of
facilities by Cheniere Creole Trail
Pipeline Company, L.P. (Cheniere) in
Beauregard and Cameron Parishes,
Louisiana. The Commission will use
this EA in its decision-making process
to determine whether the project is in
the public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on July 13,
2012.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
Summary of the Proposed Project
Cheniere proposes to construct and
operate a new compressor station and
associated facilities in Beauregard
Parish, Louisiana, and miscellaneous
facilities at the existing Sabine Pass
Liquefied Natural Gas (LNG) Terminal
in Cameron Parish, Louisiana.
According to Cheniere, its project would
enable bi-directional gas flow on the
Creole Trail Pipeline system and allow
for the delivery of feed gas to the Sabine
Pass Liquefaction Project. The Creole
Trail Expansion Project would create
1,530,000 dekatherms per day of new
firm reverse flow capacity.
The Creole Trail Expansion Project
would consist of the following facilities:
E:\FR\FM\19JNN1.SGM
19JNN1
Agencies
[Federal Register Volume 77, Number 118 (Tuesday, June 19, 2012)]
[Notices]
[Pages 36524-36525]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-14877]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14421-000]
Freedom Falls, LLC; Notice of Application Tendered for Filing
With the Commission and Soliciting Additional Study Requests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Exemption from Licensing.
b. Project No.: 14421-000.
c. Date filed: June 1, 2012.
d. Applicant: Freedom Falls, LLC.
e. Name of Project: Freedom Falls Hydroelectric Project.
f. Location: On Sandy Stream, in the Town of Freedom, Waldo County,
[[Page 36525]]
Maine. The project would not occupy lands of the United States.
g. Filed Pursuant to: Public Utility Regulatory Policies Act of
1978, 16 U.S.C. 2705, 2708.
h. Applicant Contact: Anthony P. Grassi, Freedom Falls LLC, 363
Belfast Road, Camden, ME 04843, (207) 236-4663.
i. FERC Contact: Samantha Davidson, (202) 502-6839 or
samantha.davidson@ferc.gov.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: July 31, 2012.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/ferconline.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-
3676; or, for TTY, contact (202) 502-8659. Although the Commission
strongly encourages electronic filing, documents may also be paper-
filed. To paper-file, mail an original and seven copies to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
m. The application is not ready for environmental analysis at this
time.
n. The proposed Freedom Falls Hydroelectric Project would consist
of: (1) An existing 90-foot-long, 12-foot-high concrete-capped stone
masonry dam with a 25-foot-long, 10-foot-high spillway with two
vertical lift sluice gates and a crest elevation of 452.5 feet mean sea
level (msl); (2) an existing 1.6-acre impoundment with a normal maximum
water surface elevation of 453.0 feet msl; (3) a new intake structure
equipped with an 8-foot-high, 5-foot-wide trashrack that would be
modified to have 1-inch clear bar spacing, and a 3-foot-high, 4.75-
foot-wide slide gate; (4) a new downstream American eel passage
facility and working platform; (5) a new 60-foot-long, 30-inch-diameter
steel penstock leading to; (6) an existing 20-foot-wide, by 30-foot-
long generating room containing a new 38.3 kilowatt turbine-generator
unit; (7) a new 20-foot-long, 5-foot-wide tailrace; (8) a new 30-foot-
long, 110-volt transmission line; and (9) appurtenant facilities. The
proposed project is estimated to generate an average of 66,000
kilowatt-hours annually.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. With this notice, we are initiating consultation with the Maine
Historic Preservation Commission, as required by 106, National Historic
Preservation Act, and the regulations of the Advisory Council on
Historic Preservation, 36, CFR, at 800.4.
q. Procedural schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule will be made as appropriate (e.g., if scoping is waived, the
schedule would be shortened).
------------------------------------------------------------------------
------------------------------------------------------------------------
Issue Deficiency Letter................ August 2012.
Issue Notice of Acceptance............. October 2012.
Issue Scoping Document................. November 2012.
Issue Notice of ready for environmental January 2013.
analysis.
Issue Notice of the availability of the May 2013.
EA.
------------------------------------------------------------------------
Dated: June 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-14877 Filed 6-18-12; 8:45 am]
BILLING CODE 6717-01-P