Cheniere Creole Trail Pipeline, L.P.; Notice of Application, 29624-29625 [2012-12066]
Download as PDF
29624
Federal Register / Vol. 77, No. 97 / Friday, May 18, 2012 / Notices
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–12065 Filed 5–17–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–351–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Cheniere Creole Trail Pipeline, L.P.;
Notice of Application
Take notice that on April 30, 2012,
Cheniere Creole Trail Pipeline, L.P.
(Cheniere), 700 Milam, Suite 800,
Houston, TX 77002, filed an application
in Docket No. CP12–351–000 pursuant
to Section 7(c) of the Natural Gas Act
(NGA) and Part 157 of the Commission’s
Regulations, for a certificate of public
convenience and necessity to construct
and operate its Creole Trail Expansion
Project (Project). Cheniere’s Project
would consist of construction of a new
VerDate Mar<15>2010
18:21 May 17, 2012
Jkt 226001
53,125 hp Gillis Compressor Station,
modifications to three existing meter
and regulation stations to allow bidirectional flow and increased capacity,
and 200 feet of 42-inch-diameter
pipeline connecting the Gillis
Compressor Station to the existing
Creole Trail Pipeline, all in Beauregard
Parish, Louisiana.
Cheniere states that the Project would
allow for a total of 1,530,000 dth per day
of firm reverse flow capacity on the
Creole Trail Pipeline to allow the
delivery of feed gas to the Sabine Pass
Liquefaction Project authorized in
CP11–72–000. Cheniere proposes to
construct the Project in two phases that
would coincide with anticipated firm
transportation service requirements of
Phase 1 of the Sabine Pass Liquefaction
Project. The estimated cost of the Project
is approximately $104,305,155.00. A
more detailed description of the project
is available in the application which is
on file with the Commission and open
for public inspection.
This filing is available for review at
the Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘e-Library’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676, or for TTY,
(202) 502–8659. Any questions
regarding this application should be
directed to Kieth Teague, Cheniere
Creole Trail Pipeline, L.P., 700 Milam,
Suite 800, Houston, TX 77002, (713)
375–5000 (phone),
keith.teague@cheniere.com or Lisa M.
Tonery, Fulbright & Jaworski, L.L.P.,
666 Fifth Avenue, New York, NY,
10103, (212) 318–3009 (phone),
ltonery@fulbright.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
E:\FR\FM\18MYN1.SGM
18MYN1
Federal Register / Vol. 77, No. 97 / Friday, May 18, 2012 / Notices
to seek court review of the
Commission’s final order.
Protests and interventions may be
filed electronically via the Internet in
lieu of paper; see, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Comment Date: June 1, 2012.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–12066 Filed 5–17–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2558–029]
mstockstill on DSK4VPTVN1PROD with NOTICES
Central Vermont Public Service
Corporation; Notice of Application
Ready for Environmental Analysis,
Soliciting Motions To Intervene and
Protests, and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2558–029.
c. Date filed: March 31, 2010, and
amended on August 1, 2011.
d. Applicant: Central Vermont Public
Service Corporation.
e. Name of Project: Otter Creek
Hydroelectric Project.
f. Location: The existing project is
located on Otter Creek in Addison and
Rutland counties, Vermont. The project
does not occupy federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mike Scarzello,
Generation Asset Manager, Central
Vermont Public Service Corporation, 77
Grove Street, Rutland, VT 05701;
Telephone: (802) 747–5207.
i. FERC Contact: Aaron Liberty, (202)
502–6862, aaron.liberty@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments, terms
and conditions, recommendations, and
prescriptions: 60 days from the issuance
date of this notice; reply comments are
due 105 days from the issuance date of
this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
VerDate Mar<15>2010
18:21 May 17, 2012
Jkt 226001
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. Project Description: The existing
Otter Creek Project consists of three
developments with a combined
installed capacity of 18.279 megawatts
(MW). The project produces an average
annual generation of 67,258 megawatthours. The energy from the project will
be used to serve Central Vermont’s retail
customers.
The Proctor development, located at
river mile 64.2, consists of the following
facilities: (1) An existing 13-foot-high,
128-foot-long dam with a 3-foot-high
inflatable flashboard system; (2) an
existing 95-acre reservoir with a storage
capacity of 275 acre-feet at a normal
maximum water surface elevation of
469.5 feet above mean sea level (msl);
(3) a gated-forebay intake structure
approximately 14 feet deep by 115 feet
long with a maximum width of 48 feet;
(4) two intakes with two penstocks: a 9foot-diameter, 460-foot-long, riveted
steel penstock that decreases to 8 feet in
diameter, and a 7-foot-diameter, 500foot-long, spiral welded steel penstock;
(5) an original concrete and brick
masonry powerhouse measuring 100 by
33 feet containing four vertical shaft
turbines: three 750-kilowatt (kW) units
and one 1,680-kW unit with a combined
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
29625
maximum hydraulic capacity of 565
cubic feet per second (cfs); (6) an
additional steel structure measuring 28
by 48 feet attached to the original
powerhouse containing one 3,000-kW
vertical shaft unit with a maximum
hydraulic capacity of 325 cfs; (7)
generator leads; (8) two banks of 0.48/
4.16-kilovolt (kV) single-phase
transformers; (9) a 0.48/43.8-kV three
winding transformer; and (10)
appurtenant facilities.
The Beldens development, located at
river mile 23, consists of the following
facilities: (1) Two existing concrete
dams on either side of a ledge/bedrock
island with 2.5-foot-high wooden
flashboards: a 15-foot-high, 56-foot-long
dam (west) and a 24-foot-high, 57-footlong dam (east); (2) an existing 22-acre
reservoir with a storage capacity of 253
acre-feet at a normal maximum water
surface elevation of 282.52 feet msl; (3)
two intakes equipped with trashracks: a
79-foot-long intake and a 35-foot-long
intake with a 95-foot-long sluiceway; (4)
a 12-foot-diameter, 30-foot-long steel
penstock that bifurcates into two 10foot-diameter sections, each leading to
an original powerhouse; (5) a 12-footdiameter, 45-foot-long concrete
penstock that leads to a newer
powerhouse; (6) an original concrete
and masonry powerhouse measuring 40
by 44 feet containing a 800-kW vertical
shaft unit and 949-kW vertical shaft unit
with combined maximum hydraulic
capacity of 650 cfs; (7) a second, newer
concrete powerhouse measuring 40 by
75 feet containing a 4,100-kW vertical
shaft unit with a maximum hydraulic
capacity of 1,350 cfs; (8) generator leads;
(9) a 2.4/46-kV step-up transformer
bank; and (10) appurtenant facilities.
The Huntington Falls development,
located at river mile 21, consists of: (1)
An existing 31-foot-high, 187-foot-long
concrete dam with a 2.5-foot-high
inflatable flashboard system; (2) an
existing 23-acre reservoir with a storage
capacity of 234 acre-feet at a normal
maximum water surface elevation of
217.8 feet msl; (3) two intakes equipped
with trashracks: a 40-foot-long intake
and a 26-foot-long intake; (4) three
penstocks: two 10-foot-diameter, 30foot-long steel penstocks leading to an
original powerhouse, and a 12-footdiameter, 75-foot-long concrete
penstock leading to a newer
powerhouse; (5) an original brick
masonry powerhouse measuring 42 by
60 feet containing a 600-kW vertical
shaft unit and a 800-kW vertical shaft
unit with a combined maximum
hydraulic capacity of 660 cfs; (6) a
second, newer powerhouse measuring
40 by 75 feet containing a 4,100-kW
vertical shaft unit with a maximum
E:\FR\FM\18MYN1.SGM
18MYN1
Agencies
[Federal Register Volume 77, Number 97 (Friday, May 18, 2012)]
[Notices]
[Pages 29624-29625]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-12066]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP12-351-000]
Cheniere Creole Trail Pipeline, L.P.; Notice of Application
Take notice that on April 30, 2012, Cheniere Creole Trail Pipeline,
L.P. (Cheniere), 700 Milam, Suite 800, Houston, TX 77002, filed an
application in Docket No. CP12-351-000 pursuant to Section 7(c) of the
Natural Gas Act (NGA) and Part 157 of the Commission's Regulations, for
a certificate of public convenience and necessity to construct and
operate its Creole Trail Expansion Project (Project). Cheniere's
Project would consist of construction of a new 53,125 hp Gillis
Compressor Station, modifications to three existing meter and
regulation stations to allow bi-directional flow and increased
capacity, and 200 feet of 42-inch-diameter pipeline connecting the
Gillis Compressor Station to the existing Creole Trail Pipeline, all in
Beauregard Parish, Louisiana.
Cheniere states that the Project would allow for a total of
1,530,000 dth per day of firm reverse flow capacity on the Creole Trail
Pipeline to allow the delivery of feed gas to the Sabine Pass
Liquefaction Project authorized in CP11-72-000. Cheniere proposes to
construct the Project in two phases that would coincide with
anticipated firm transportation service requirements of Phase 1 of the
Sabine Pass Liquefaction Project. The estimated cost of the Project is
approximately $104,305,155.00. A more detailed description of the
project is available in the application which is on file with the
Commission and open for public inspection.
This filing is available for review at the Commission in the Public
Reference Room or may be viewed on the Commission's Web site at https://www.ferc.gov using the ``e-Library'' link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676, or for
TTY, (202) 502-8659. Any questions regarding this application should be
directed to Kieth Teague, Cheniere Creole Trail Pipeline, L.P., 700
Milam, Suite 800, Houston, TX 77002, (713) 375-5000 (phone),
keith.teague@cheniere.com or Lisa M. Tonery, Fulbright & Jaworski,
L.L.P., 666 Fifth Avenue, New York, NY, 10103, (212) 318-3009 (phone),
ltonery@fulbright.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either complete
its environmental assessment (EA) and place it into the Commission's
public record (eLibrary) for this proceeding; or issue a Notice of
Schedule for Environmental Review. If a Notice of Schedule for
Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final EA for this proposal. The filing of the EA in the
Commission's public record for this proceeding or the issuance of a
Notice of Schedule for Environmental Review will serve to notify
federal and state agencies of the timing for the completion of all
necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made in the proceeding with the Commission
and must mail a copy to the applicant and to every other party. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right
[[Page 29625]]
to seek court review of the Commission's final order.
Protests and interventions may be filed electronically via the
Internet in lieu of paper; see, 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's web site under the ``e-Filing'' link.
The Commission strongly encourages electronic filings.
Comment Date: June 1, 2012.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-12066 Filed 5-17-12; 8:45 am]
BILLING CODE 6717-01-P