Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions; BOST4 Hydroelectric, LLC, 29623-29624 [2012-12065]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 97 / Friday, May 18, 2012 / Notices
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must: (1) Bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS’’; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–12063 Filed 5–17–12; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
18:21 May 17, 2012
Jkt 226001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12757–004]
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions; BOST4
Hydroelectric, LLC
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12757–004.
c. Date filed: February 24, 2011.
d. Applicant: BOST4 Hydroelectric,
LLC (BOST4).
e. Name of Project: Red River Lock &
Dam No. 4 Hydroelectric Project.
f. Location: The proposed project
would be located at the existing U. S.
Army Corps of Engineer’s (Corps) Red
River Lock & Dam No. 4 on the Red
River, in Red River Parish near the
Town of Coushatta, Louisiana. The
proposed project would occupy 135.1
acres of land administered by the Corps.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Douglas A.
Spalding, BOST4 Hydroelectric, LLC,
8441 Wayzata Blvd., Suite 101, Golden
Valley, MN 55426; (952) 544–8133.
i. FERC Contact: Jeanne Edwards
(202) 502–6181, or by email at
jeanne.edwards@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
29623
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. Project Description: The proposed
project would utilize the existing Corps
Red River Lock and Dam No. 4, and
operate consistent with the Corps
current operation policy. The proposed
project would consist of: (1) An
excavated 385-foot-long headrace
channel to convey water from the
upstream Pool No. 4 of the Red River to
a 301-foot-long by 90-foot-wide concrete
powerhouse located southwest of the
end of the existing overflow weir; (2) an
excavated 477-foot-long tailrace channel
to discharge water from the powerhouse
to the downstream Pool No. 3 of the Red
River; (3) a 28.1-megawatt horizontal
Kaplan bulb turbine/generator unit; (4)
a 2.8 mile-long 34.5-kilovolt (kV)
transmission line which would connect
to an existing 34-kV overhead
transmission line; and (5) appurtenant
facilities. The proposed project would
generate about 128,532 megawatt-hours
annually which would be sold to a local
utility.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must: (1) Bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS’’; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
E:\FR\FM\18MYN1.SGM
18MYN1
29624
Federal Register / Vol. 77, No. 97 / Friday, May 18, 2012 / Notices
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–12065 Filed 5–17–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–351–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Cheniere Creole Trail Pipeline, L.P.;
Notice of Application
Take notice that on April 30, 2012,
Cheniere Creole Trail Pipeline, L.P.
(Cheniere), 700 Milam, Suite 800,
Houston, TX 77002, filed an application
in Docket No. CP12–351–000 pursuant
to Section 7(c) of the Natural Gas Act
(NGA) and Part 157 of the Commission’s
Regulations, for a certificate of public
convenience and necessity to construct
and operate its Creole Trail Expansion
Project (Project). Cheniere’s Project
would consist of construction of a new
VerDate Mar<15>2010
18:21 May 17, 2012
Jkt 226001
53,125 hp Gillis Compressor Station,
modifications to three existing meter
and regulation stations to allow bidirectional flow and increased capacity,
and 200 feet of 42-inch-diameter
pipeline connecting the Gillis
Compressor Station to the existing
Creole Trail Pipeline, all in Beauregard
Parish, Louisiana.
Cheniere states that the Project would
allow for a total of 1,530,000 dth per day
of firm reverse flow capacity on the
Creole Trail Pipeline to allow the
delivery of feed gas to the Sabine Pass
Liquefaction Project authorized in
CP11–72–000. Cheniere proposes to
construct the Project in two phases that
would coincide with anticipated firm
transportation service requirements of
Phase 1 of the Sabine Pass Liquefaction
Project. The estimated cost of the Project
is approximately $104,305,155.00. A
more detailed description of the project
is available in the application which is
on file with the Commission and open
for public inspection.
This filing is available for review at
the Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘e-Library’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676, or for TTY,
(202) 502–8659. Any questions
regarding this application should be
directed to Kieth Teague, Cheniere
Creole Trail Pipeline, L.P., 700 Milam,
Suite 800, Houston, TX 77002, (713)
375–5000 (phone),
keith.teague@cheniere.com or Lisa M.
Tonery, Fulbright & Jaworski, L.L.P.,
666 Fifth Avenue, New York, NY,
10103, (212) 318–3009 (phone),
ltonery@fulbright.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
E:\FR\FM\18MYN1.SGM
18MYN1
Agencies
[Federal Register Volume 77, Number 97 (Friday, May 18, 2012)]
[Notices]
[Pages 29623-29624]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-12065]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12757-004]
Application Ready for Environmental Analysis and Soliciting
Comments, Recommendations, Terms and Conditions, and Prescriptions;
BOST4 Hydroelectric, LLC
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: P-12757-004.
c. Date filed: February 24, 2011.
d. Applicant: BOST4 Hydroelectric, LLC (BOST4).
e. Name of Project: Red River Lock & Dam No. 4 Hydroelectric
Project.
f. Location: The proposed project would be located at the existing
U. S. Army Corps of Engineer's (Corps) Red River Lock & Dam No. 4 on
the Red River, in Red River Parish near the Town of Coushatta,
Louisiana. The proposed project would occupy 135.1 acres of land
administered by the Corps.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Douglas A. Spalding, BOST4 Hydroelectric,
LLC, 8441 Wayzata Blvd., Suite 101, Golden Valley, MN 55426; (952) 544-
8133.
i. FERC Contact: Jeanne Edwards (202) 502-6181, or by email at
jeanne.edwards@ferc.gov.
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. Project Description: The proposed project would utilize the
existing Corps Red River Lock and Dam No. 4, and operate consistent
with the Corps current operation policy. The proposed project would
consist of: (1) An excavated 385-foot-long headrace channel to convey
water from the upstream Pool No. 4 of the Red River to a 301-foot-long
by 90-foot-wide concrete powerhouse located southwest of the end of the
existing overflow weir; (2) an excavated 477-foot-long tailrace channel
to discharge water from the powerhouse to the downstream Pool No. 3 of
the Red River; (3) a 28.1-megawatt horizontal Kaplan bulb turbine/
generator unit; (4) a 2.8 mile-long 34.5-kilovolt (kV) transmission
line which would connect to an existing 34-kV overhead transmission
line; and (5) appurtenant facilities. The proposed project would
generate about 128,532 megawatt-hours annually which would be sold to a
local utility.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
All filings must: (1) Bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS''; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions
[[Page 29624]]
or prescriptions must set forth their evidentiary basis and otherwise
comply with the requirements of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from the applicant. Each filing must
be accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-12065 Filed 5-17-12; 8:45 am]