Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions; BOST3 Hydroelectric, LLC, 29626-29627 [2012-12064]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
29626
Federal Register / Vol. 77, No. 97 / Friday, May 18, 2012 / Notices
hydraulic capacity of 1,350 cfs; (7)
generator leads; (8) a 2.4/46-kV step-up
transformer bank; and (9) appurtenant
facilities.
Currently, the Proctor development
operates in a modified run-of-river
mode, with infrequent diversions at the
direction of the Independent System
Operator—New England, while the
Beldens and Huntington Falls
developments operate in a run-of-river
mode. The Proctor development
currently provides a continuous
downstream minimum flow of 100 cfs
or inflow to the development,
whichever is less, with minimum flows
from April through mid-June equal to at
least 50 percent of project inflows. A
bypassed reach minimum flow of 5 cfs
is currently released at the Beldens
development through an opening in the
flashboards along the west dam. A
bypassed reach minimum flow of 15 cfs
is currently released at the Huntington
Falls development via a minimum flow
gate at the right abutment of the dam.
Central Vermont proposes several
physical changes to existing project
facilities at the Proctor and Huntington
Falls developments. At the Proctor
development, Central Vermont proposes
to: (1) Realign the intake headworks,
such that the existing structure and
components (sluice gate, trashracks,
and/or headgates) will be modified with
the entrance widened and deepened to
reduce significant head losses through
the intake structure; (2) install a new
runner at Unit 1; replace Units 2–4 with
new turbines/generators; and install
new electrical switchgear, breakers,
controls, and relays, resulting in an
increase in nameplate capacity from
6,930 kW to a preliminary estimated
design of 9,402 kW, and an increase in
the existing hydraulic capacity from 890
cfs to approximately 1,158 cfs; and (3)
install a new trashrack with 2-inch clear
bar spacing, oriented at 42.5 degrees to
river flow.
At the Huntington Falls development,
Central Vermont proposes to: (1)
Upgrade Units 1 and 2, resulting in an
increase in nameplate capacity from
5,500 kW to a preliminary estimated
design of 6,344 kW, and an increase in
the existing hydraulic capacity from
2,010 cfs to approximately 2,144 cfs; (2)
install new switchgear, breakers,
control, and relays; and (3) install a new
trashrack for the Unit 3 intake that
would have 3-inch clear bar spacing and
be oriented at a 90 degree angle to river
flow.
Central Vermont proposes operational
changes to existing project operations at
the Proctor development. Central
Vermont proposes to eliminate the
existing 4-foot drawdown of the
VerDate Mar<15>2010
18:21 May 17, 2012
Jkt 226001
reservoir surface, with the exception of
infrequent emergency operations and
maintenance, and to implement a
cycling operation that would utilize a
1.5-foot drawdown/refill cycle between
June 16 and March 31, provided that the
existing downstream minimum flow
requirement of 100 cfs is maintained
during refill. Central Vermont also
proposes to refrain from conducting
reservoir drawdowns during the period
of April 1 to June 15, when Proctor
would be operated in a run-of-river
mode. In addition, peaking constraints
would be utilized under normal
operations of no greater than a 4.5:1
ratio between maximum and minimum
flow in a 24-hour period.
Central Vermont is also proposing to
alter the existing bypassed reach
minimum flows at the Proctor and
Beldens developments. At the Proctor
development, Central Vermont is
proposing to provide a continuous
bypassed reach minimum flow of 54 cfs,
and to provide the remainder of the
existing 100-cfs minimum tailrace flow
through the powerhouse. At the Beldens
development, Central Vermont is
proposing to provide a 10-cfs minimum
flow in both the east and west channels.
Central Vermont is also proposing the
following environmental measures: (1)
Improve and enhance the existing takeout for the canoe portage around the
Beldens dam; and (2) formalize and
enhance the tailwater access site at the
Proctor development.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in Item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, .214. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must: (1) Bear in all capital
letters the title ‘‘PROTEST,’’ or
‘‘MOTION TO INTERVENE,’’ or
‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’
RECOMMENDATIONS,’’ ‘‘TERMS AND
CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’
(2) set forth in the heading the name of
the applicant and the project number of
the application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon the representative of the applicant.
A copy of all other filings must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. A license applicant must file, no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: May 14, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–12069 Filed 5–17–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12756–003]
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions; BOST3
Hydroelectric, LLC
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12756–003.
c. Date filed: July 26, 2010.
E:\FR\FM\18MYN1.SGM
18MYN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 97 / Friday, May 18, 2012 / Notices
d. Applicant: BOST3 Hydroelectric,
LLC (BOST3).
e. Name of Project: Red River Lock &
Dam No. 3 Hydroelectric Project.
f. Location: The proposed project
would be located at the existing U.S.
Army Corps of Engineer’s (Corps) Red
River Lock & Dam No. 3 on the Red
River, in Natchitoches Parish near the
City of Colfax, Louisiana. The proposed
project would occupy 60.2 acres of land
administered by the Corps.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Douglas A.
Spalding, BOST3 Hydroelectric, LLC,
8441 Wayzata Blvd., Suite 101, Golden
Valley, MN 55426; (952) 544–8133.
i. FERC Contact: Jeanne Edwards
(202) 502–6181, or by email at
Jeanne.edwards@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. Project Description: The proposed
project would utilize the existing Corps
Red River Lock and Dam No. 3, and
VerDate Mar<15>2010
18:21 May 17, 2012
Jkt 226001
operate consistent with the Corps’
current operating policy. The proposed
project consists of: (1) An excavated
635-foot-long headrace channel to
convey water from the upstream Pool
No. 3 of the Red River to a 301-foot-long
by 90-foot-wide concrete powerhouse
located southwest of the end of the
existing spillway, on the right (west)
abutment of the Corps’ Lock and Dam
No. 3; (2) an excavated 820-foot-long
tailrace channel to discharge water from
the powerhouse to the downstream Pool
No. 2 of the Red River; (3) a 36.2megawatt horizontal Kaplan bulb
turbine/generator unit; (4) a 8,400-footlong, 13.2-kilovolt transmission line
which would connect to an existing
Central Louisiana Electric Company
substation; and (5) appurtenant
facilities. The proposed project would
generate about 172,779 megawatt-hours
annually which would be sold to a local
utility.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must: (1) Bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS’’; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
29627
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–12064 Filed 5–17–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC12–100–000.
Applicants: Alpha Gas and Electric,
LLC.
Description: Application for
Authorization for Disposition of
Jurisdictional Facilities and Request for
Expedited Action of Alpha Gas and
Electric, LLC.
Filed Date: 5/10/12.
Accession Number: 20120510–5142.
Comments Due: 5 p.m. ET 5/31/12.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2179–010;
ER10–2181–010; ER10–2182–010.
Applicants: R.E. Ginna Nuclear Power
Plant, LLC, Calvert Cliffs Nuclear Power
Plant, LLC, Nine Mile Point Nuclear
Station, LLC.
Description: On 5/10/12 CENG
Nuclear Entities submits Notice of
Change in Status and on 5/11/12
submits Supplemental Information.
Filed Date: 5/10/12; 5/11/12.
Accession Number: 20120510–5146;
20120511–5139.
Comments Due: 5 p.m. ET 5/31/12.
Docket Numbers: ER12–397–001.
E:\FR\FM\18MYN1.SGM
18MYN1
Agencies
[Federal Register Volume 77, Number 97 (Friday, May 18, 2012)]
[Notices]
[Pages 29626-29627]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-12064]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12756-003]
Application Ready for Environmental Analysis and Soliciting
Comments, Recommendations, Terms and Conditions, and Prescriptions;
BOST3 Hydroelectric, LLC
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: P-12756-003.
c. Date filed: July 26, 2010.
[[Page 29627]]
d. Applicant: BOST3 Hydroelectric, LLC (BOST3).
e. Name of Project: Red River Lock & Dam No. 3 Hydroelectric
Project.
f. Location: The proposed project would be located at the existing
U.S. Army Corps of Engineer's (Corps) Red River Lock & Dam No. 3 on the
Red River, in Natchitoches Parish near the City of Colfax, Louisiana.
The proposed project would occupy 60.2 acres of land administered by
the Corps.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Douglas A. Spalding, BOST3 Hydroelectric,
LLC, 8441 Wayzata Blvd., Suite 101, Golden Valley, MN 55426; (952) 544-
8133.
i. FERC Contact: Jeanne Edwards (202) 502-6181, or by email at
Jeanne.edwards@ferc.gov.
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, or toll free at 1-866-208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. Project Description: The proposed project would utilize the
existing Corps Red River Lock and Dam No. 3, and operate consistent
with the Corps' current operating policy. The proposed project consists
of: (1) An excavated 635-foot-long headrace channel to convey water
from the upstream Pool No. 3 of the Red River to a 301-foot-long by 90-
foot-wide concrete powerhouse located southwest of the end of the
existing spillway, on the right (west) abutment of the Corps' Lock and
Dam No. 3; (2) an excavated 820-foot-long tailrace channel to discharge
water from the powerhouse to the downstream Pool No. 2 of the Red
River; (3) a 36.2-megawatt horizontal Kaplan bulb turbine/generator
unit; (4) a 8,400-foot-long, 13.2-kilovolt transmission line which
would connect to an existing Central Louisiana Electric Company
substation; and (5) appurtenant facilities. The proposed project would
generate about 172,779 megawatt-hours annually which would be sold to a
local utility.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
All filings must: (1) Bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS''; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Dated: May 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-12064 Filed 5-17-12; 8:45 am]
BILLING CODE 6717-01-P