Southern Star Central Gas Pipeline, Inc.; Notice of Application, 28867-28868 [2012-11833]
Download as PDF
srobinson on DSK4SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 95 / Wednesday, May 16, 2012 / Notices
Louis District). The existing Lake
Shelbyville Dam was constructed in
1963 for the purposes of flood control,
recreation development, water supply,
navigation release, and fish and wildlife
conservation. In August of 1970, the
Corps closed the gates to start the initial
filling of the lake. The West Okaw and
Kaskaskia rivers were inundated for 17
miles upstream of the dam.
The Lake Shelbyville Dam is an
earthen embankment with an elevation
of 643 feet above mean sea level (MSL).
The dam is 3,025 feet long and rises 108
feet above the river bed. The concrete
spillway is located at 593 feet MSL and
is topped by three Tainter gates that are
approximately 45-feet-wide by 37-feethigh. The two regulating outlet
structures release water through the face
of the spillway. The impoundment
above the Lake Shelbyville Dam,
referred to as Lake Shelbyville, varies
according to flood control operations
controlled by the Corps. Lake
Shelbyville has a maximum storage
capacity of 684,000 acre-feet. Of the
684,000 acre-feet of storage, 474,000
acre-feet have been designated for flood
control. The average depth of the
reservoir is 16 feet and the maximum is
67 feet.
The proposed Lake Shelbyville
Project would consist of: (1) A trash rack
with 4-inch spacing integrated into the
Corps’ existing west intake structure; (2)
a steel liner installed in the Corps’
existing west outlet chamber
transitioning to a bifurcation; (3) a 13foot-diameter bifurcation and a river
release valve installed at the west outlet
structure; (4) a 13-foot-diameter
penstock at the bifurcation after which
it reduces to a 12-foot-diameter, 570foot-long steel penstock; (5) a 60-footlong, 40-foot-wide, 68.5-foot-high
reinforced concrete powerhouse
containing a 6.8-megawatt Kaplan
turbine-generator with a flow of 130 to
1,500 cubic feet per second (cfs) at a net
head of 33 to 77 feet; (6) an
approximately 25-foot-wide, 25-footlong draft tube; (7) a 25 to 105-footwide, 49-foot-long tailrace; (8) a 12.47kilovolt, 407-foot-long buried
transmission line connecting the project
to an existing Shelby Electric
Cooperative substation located 900 feet
downstream of the dam; and (9)
appurtenant facilities. The project
boundary would include 3.24 acres of
Federal lands owned by the Corps. The
annual average energy production is
estimated to be 20.3 gigawatt-hours.
The project would operate in a run-ofrelease mode utilizing releases from
Lake Shelbyville as they are dictated by
the Corps, with no proposed change to
the Corps’ facility operation. Power
VerDate Mar<15>2010
18:41 May 15, 2012
Jkt 226001
generation would be seasonally variable
as flow regimens and pool levels are set
forth by the Corps. The project would
generate power using flows between 130
and 1,500 cfs. When flows are below
130 cfs, all flows would be passed
through the Corps’ existing outlet
structure and the project would then be
offline. When flows are greater than
1,500 cfs, excess flow would be passed
through the existing outlet structure.
m. Scoping: Commission staff
completed the scoping process for the
proposed project, including a site visit
and public meeting, by letter issued on
March 12, 2010. Commission staff does
not intend to conduct additional
scoping.
n. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application,
or a notice of intent to file such an
application. Submission of a timely
notice of intent allows an interested
person to file the competing
development application no later than
120 days after the specified intervention
deadline date. Applications for
preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
unequivocal statement of intent to
submit a development application. A
notice of intent must be served on the
applicant(s) named in this public notice.
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
28867
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
When the application is ready for
environmental analysis, the
Commission will issue a public notice
requesting comments,
recommendations, terms and
conditions, or prescriptions.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE,’’ ‘‘NOTICE
OF INTENT TO FILE COMPETING
APPLICATION,’’ or ‘‘COMPETING
APPLICATION;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. Agencies
may obtain copies of the application
directly from the applicant. A copy of
any protest or motion to intervene must
be served upon each representative of
the applicant specified in the particular
application.
Dated: May 10, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–11837 Filed 5–15–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–285–000]
Southern Star Central Gas Pipeline,
Inc.; Notice of Application
Take notice that on April 27, 2012,
Southern Star Central Gas Pipeline, Inc.
(Southern Star), 4700 Highway 56,
Owensboro, Kentucky 42304, filed in
Docket No. CP12–285–000 an
application pursuant to section 7 of the
Natural Gas Act (NGA), as amended, for
authorization to expand the existing
certificated boundary and buffer zone by
160 acres at Southern Star’s existing
McLouth Gas Storage Field in Jefferson
and Leavenworth Counties, Kansas, all
as more fully set forth in the application
which is on file with the Commission
and open for public inspection.
Any questions regarding the
applications should be directed to David
N. Roberts, Staff Analyst, Regulatory
Affairs, Southern Star Central Gas
Pipeline, Inc. (Southern Star), 4700
Highway 56, Owensboro, Kentucky
42304, or call at 270–852–4654.
E:\FR\FM\16MYN1.SGM
16MYN1
srobinson on DSK4SPTVN1PROD with NOTICES
28868
Federal Register / Vol. 77, No. 95 / Wednesday, May 16, 2012 / Notices
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA
(18 CFR 157.10). A person obtaining
party status will be placed on the
service list maintained by the Secretary
of the Commission and will receive
copies of all documents filed by the
applicant and by all other parties. A
party must submit 7 copies of filings
made with the Commission and must
mail a copy to the applicant and to
every other party in the proceeding.
Only parties to the proceeding can ask
for court review of Commission orders
in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
VerDate Mar<15>2010
18:41 May 15, 2012
Jkt 226001
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 7 copies of the protest or
intervention to the Federal Energy
regulatory Commission, 888 First Street
NE., Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: May 31, 2012.
Dated: May 10, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–11833 Filed 5–15–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER12–1660–001.
Applicants: Tuscola Bay Wind, LLC.
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
Description: Amendment to Tuscola
Bay Wind, LLC MBR Tariff to be
effective 6/29/2012.
Filed Date: 5/8/12.
Accession Number: 20120508–5121.
Comments Due: 5 p.m. ET 5/29/12.
Docket Numbers: ER12–1713–001.
Applicants: Southwest Power Pool,
Inc.
Description: Amendment to 2415
Kansas Municipal Energy Agency
NITSA NOA to be effective 4/1/2012.
Filed Date: 5/9/12.
Accession Number: 20120509–5099.
Comments Due: 5 p.m. ET 5/30/12.
Docket Numbers: ER12–1744–000.
Applicants: Dennis Energy Company.
Description: Cancellation of Tariff to
be effective 5/8/2012.
Filed Date: 5/8/12.
Accession Number: 20120508–5125.
Comments Due: 5 p.m. ET 5/29/12.
Docket Numbers: ER12–1745–000.
Applicants: Copper Mountain Solar 2,
LLC.
Description: Copper Mountain Solar 2
LLC Concurrence to Joint Use
Agreement to be effective 5/8/2012.
Filed Date: 5/8/12.
Accession Number: 20120508–5136.
Comments Due: 5 p.m. ET 5/29/12.
Docket Numbers: ER12–1746–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Original Service
Agreement No. 3281; Queue No. W3–
101 to be effective 4/11/2012.
Filed Date: 5/9/12
Accession Number: 20120509–5034.
Comments Due: 5 p.m. ET 5/30/12.
Docket Numbers: ER12–1747–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Original Service
Agreement No. 3286; Queue No. X3–001
to be effective 4/13/2012.
Filed Date: 5/9/12.
Accession Number: 20120509–5035.
Comments Due: 5 p.m. ET 5/30/12.
Docket Numbers: ER12–1748–000.
Applicants: Midwest Independent
Transmission System Operator, Inc.
Description: G587 GIA to be effective
5/10/2012.
Filed Date: 5/9/12
Accession Number: 20120509–5057.
Comments Due: 5 p.m. ET 5/30/12.
Docket Numbers: ER12–1749–000.
Applicants: International
Transmission Company.
Description: Notice of Succession to
be effective 7/11/2012.
Filed Date: 5/9/12.
Accession Number: 20120509–5059.
Comments Due: 5 p.m. ET 5/30/12.
Docket Numbers: ER12–1750–000.
Applicants: Delmarva Power & Light
Company.
E:\FR\FM\16MYN1.SGM
16MYN1
Agencies
[Federal Register Volume 77, Number 95 (Wednesday, May 16, 2012)]
[Notices]
[Pages 28867-28868]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-11833]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP12-285-000]
Southern Star Central Gas Pipeline, Inc.; Notice of Application
Take notice that on April 27, 2012, Southern Star Central Gas
Pipeline, Inc. (Southern Star), 4700 Highway 56, Owensboro, Kentucky
42304, filed in Docket No. CP12-285-000 an application pursuant to
section 7 of the Natural Gas Act (NGA), as amended, for authorization
to expand the existing certificated boundary and buffer zone by 160
acres at Southern Star's existing McLouth Gas Storage Field in
Jefferson and Leavenworth Counties, Kansas, all as more fully set forth
in the application which is on file with the Commission and open for
public inspection.
Any questions regarding the applications should be directed to
David N. Roberts, Staff Analyst, Regulatory Affairs, Southern Star
Central Gas Pipeline, Inc. (Southern Star), 4700 Highway 56, Owensboro,
Kentucky 42304, or call at 270-852-4654.
[[Page 28868]]
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 7 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 7 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street NE., Washington,
DC 20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: May 31, 2012.
Dated: May 10, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-11833 Filed 5-15-12; 8:45 am]
BILLING CODE 6717-01-P