Loup River Public Power District; Notice of Application Tendered For Filing With the Commission and Establishing Procedural Schedule For Licensing and Deadline for Submission of Final Amendments, 25997-25998 [2012-10534]
Download as PDF
Federal Register / Vol. 77, No. 85 / Wednesday, May 2, 2012 / Notices
p. Procedural schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule will
be made as appropriate (e.g., if scoping
is not waived, the schedule would be
lengthened).
Milestone
Notice of the availability of the
EA .........................................
Target date
July 2012.
Dated: April 24, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–10531 Filed 5–1–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1256–031]
Loup River Public Power District;
Notice of Application Tendered For
Filing With the Commission and
Establishing Procedural Schedule For
Licensing and Deadline for
Submission of Final Amendments
mstockstill on DSK4VPTVN1PROD with NOTICES
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 1256–031.
c. Date Filed: April 16, 2012.
d. Applicant: Loup River Public
Power District (Loup Power District).
e. Name of Project: Loup River
Hydroelectric Project (Loup River
Project).
f. Location: On the Loup River, Loup
Canal (a diversion canal off the Loup
River), and Platte River in Nance and
Platte counties, Nebraska. The project
does not occupy federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Neal Suess,
President/CEO, Loup Power District,
P.O. Box 988, 2404 15th Street
Columbus, Nebraska 68602, Telephone
(866) 869–2087.
i. FERC Contact: Lee Emery, (202)
502–8379 or lee.emery@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The project
consists of (upstream to downstream):
(1) A 1,320-foot-long, 6-foot-high
diversion dam on the Loup River; (2) an
intake structure composed of eleven 24foot-long by 5-foot-high steel intake
gates located on the north bank of the
Loup River immediately upstream of the
diversion dam; (3) three 20-foot-long by
6-foot-high steel sluice gates located
between the diversion dam and the
intake structure; (4) the 35-mile-long
Loup Canal; (5) a 2-mile-long settling
basin located in the upper portion of the
Loup Canal and containing a floating
hydraulic dredge and skimming weir;
(6) the Monroe Powerhouse containing
three Francis-type, turbine-generating
units each with a rated capacity of 2.612
megawatts (MW); (7) a 760-acre
regulating reservoir, Lake Babcock, with
a storage capacity of 2,270 acre-feet at
its full pool elevation of 1,531 feet; (8)
a 200-acre regulating reservoir, Lake
North, with a storage capacity of 2,080
acre-feet at an elevation of 1,531 feet; (9)
a concrete control structure in the south
dike linking the two reservoirs; (10) a
60-foot-long by 104-foot-wide by 40foot-high inlet structure with trashracks;
(11) three 20-foot-diameter by 385-footlong steel penstocks connecting the inlet
structure with a powerhouse (Columbus
Powerhouse); (12) the Columbus
Powerhouse containing three Francistype, turbine-generating units each with
a rated capacity of 15.2 MW; and (13)
appurtenant facilities. The project has a
combined installed capacity of 53.4
MW.
The Monroe Powerhouse operates in
a run-of-river mode (i.e., canal inflow to
the powerhouse closely approximates
outflow from the powerhouse with no
storage of canal flow). The maximum
hydraulic capacity of the canal at the
Monroe Powerhouse is 3,500 cubic feet
per second (cfs). The Monroe
Powerhouse spans the canal and
functions as an energy-producing canal
drop structure.
The Columbus Powerhouse operates
as a daily peaking facility. The water
levels in Lake Babcock and Lake North
are generally drawn down about 2 to 3
feet to produce power during times of
peak electrical demand. In off-peak
hours, when there is less demand for
25997
electricity, the turbines are turned down
or shut off, which allows Lake Babcock
and Lake North to refill, thereby
allowing peaking operations to occur
the following day. The hydraulic
capacity of the canal at the Columbus
Powerhouse is 4,800 cfs.
The minimum leakage rate at the
Loup River diversion dam and sluice
gate structure is about 50 cfs. During hot
weather conditions, Loup Power District
operates the diversion in a manner that
allows flows of between 50 to 75 cfs
(including the leakage flow) to pass into
the Loup River downstream of the
diversion to prevent high water
temperatures that could cause fish
mortality.
Loup Power District proposes new
and improved recreational amenities at
the project; however, there are no
proposed changes to the existing project
facilities or operations.
Loup Power District proposes to
remove three areas of land from the
project boundary that it finds are not
necessary for project operations or
purposes. In addition, Loup Power
District proposes to add three parcels of
land to the project boundary that it finds
are needed for project purposes.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................
Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ..............................................................
Commission issues Draft EA ............................................................................................................................................................
Comments on Draft EA ....................................................................................................................................................................
Modified terms and conditions ..........................................................................................................................................................
Commission issues Final EA ............................................................................................................................................................
June 2012.
August 2012.
February 2013.
March 2013.
May 2013.
August 2013.
VerDate Mar<15>2010
16:55 May 01, 2012
Jkt 226001
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
E:\FR\FM\02MYN1.SGM
02MYN1
25998
Federal Register / Vol. 77, No. 85 / Wednesday, May 2, 2012 / Notices
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: April 24, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–10534 Filed 5–1–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14308–001]
mstockstill on DSK4VPTVN1PROD with NOTICES
Carbon Zero, LLC; Notice of
Application Accepted for Filing With
the Commission, Intent To Waive
Scoping, Soliciting Motions To
Intervene and Protests, Ready for
Environmental Analysis, and Soliciting
Comments, Terms and Conditions,
Recommendations, and Prescriptions,
and Establishing an Expedited
Schedule for Processing
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original
Minor License.
b. Project No.: 14308–001.
c. Date filed: February 17, 2011.
d. Applicant: Carbon Zero, LLC.
e. Name of Project: Vermont Tissue
Mill Hydroelectric Project.
f. Location: On the Walloomsac River,
in the Town of Bennington, Bennington
County, Vermont. The project would not
occupy lands of the United States.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: William F.
Scully, Carbon Zero, LLC, P.O. Box 338,
North Bennington, VT 05257; (802) 442–
0311; wfscully@gmail.com.
i. FERC Contact: Amy K. Chang, (202)
502–8250, or email at
amy.chang@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments, terms
and conditions, recommendations, and
prescriptions: 60 days from the issuance
date of this notice; reply comments are
due 105 days from the issuance date of
this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
VerDate Mar<15>2010
16:55 May 01, 2012
Jkt 226001
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. Project Description: Vermont Tissue
Mill Project would consist of two
existing dams separated by a 500-footwide island and include: (1) An existing
15-foot-high, 85-foot-long primary dam
with a spillway crest elevation of 555.0
feet above mean sea level (msl) topped
with reinstalled 4-inch-high
flashboards; (2) a refurbished 6-foothigh, 8-foot-wide flood gate located on
the primary dam south abutment; (3) an
existing 6-foot-high, 80-foot-long
secondary dam with a spillway crest
elevation of 555.33 feet above msl with
a new 2.5-foot-high, 2.5-foot-wide
minimum flow weir equipped with stop
logs; (4) an existing 2,400-foot-long, 6.4acre impoundment with a normal water
surface elevation of 555.41 feet above
msl; (5) an existing intake structure
equipped with two 12-foot-high, 16foot-wide flume openings equipped
with stop log slots and new trashracks
connected to two water conveyance
channels, one 12-foot-high, 35-foot-long
and one 12-foot-high, 85-foot-long; (6)
an existing powerhouse with two new
Kaplan turbine generating units, a 215
kilowatt (kW) unit and a 145 kW unit,
with a total installed capacity of 360
kW; (7) a refurbished tailrace
discharging water from the powerhouse
into the main channel downstream of
the primary dam; (8) a new 1.5-footdiameter minimum flow valve in the
powerhouse discharging water into an
existing 35-foot-wide, 50-foot-long
tailrace; (9) a reconstructed, breached 8-
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
foot-high, 2-foot-wide, 45-foot-long
retaining wall; and (10) a new buried
480-volt, 125-foot-long transmission line
connecting the powerhouse to the
regional grid. The project would be
operated in a run-of-river mode and
would have an annual generation of
1,447.5 megawatt-hours.
m. Due to the project works already
existing and the limited scope of
proposed rehabilitation of the project
site described above, the applicant’s
close coordination with federal and
state agencies during the preparation of
the application, and agency
recommended preliminary terms and
conditions, we intend to waive scoping
and expedite the licensing process.
Based on a review of the application,
resource agency consultation letters
including the preliminary terms and
conditions, and comments filed to date,
Commission staff intends to prepare a
single environmental assessment (EA).
Commission staff determined that the
issues that need to be addressed in its
EA have been adequately identified
during the pre-filing period, and no new
issues are likely to be identified through
additional scoping. The EA will
consider assessing the potential effects
of project construction and operation on
geology and soils, aquatic, terrestrial,
threatened and endangered species, and
cultural and historic resources.
n. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application,
or a notice of intent to file such an
application. Submission of a timely
notice of intent allows an interested
person to file the competing
development application no later than
120 days after the specified intervention
deadline date. Applications for
preliminary permits will not be
accepted in response to this notice.
E:\FR\FM\02MYN1.SGM
02MYN1
Agencies
[Federal Register Volume 77, Number 85 (Wednesday, May 2, 2012)]
[Notices]
[Pages 25997-25998]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-10534]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1256-031]
Loup River Public Power District; Notice of Application Tendered
For Filing With the Commission and Establishing Procedural Schedule For
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 1256-031.
c. Date Filed: April 16, 2012.
d. Applicant: Loup River Public Power District (Loup Power
District).
e. Name of Project: Loup River Hydroelectric Project (Loup River
Project).
f. Location: On the Loup River, Loup Canal (a diversion canal off
the Loup River), and Platte River in Nance and Platte counties,
Nebraska. The project does not occupy federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Neal Suess, President/CEO, Loup Power
District, P.O. Box 988, 2404 15th Street Columbus, Nebraska 68602,
Telephone (866) 869-2087.
i. FERC Contact: Lee Emery, (202) 502-8379 or lee.emery@ferc.gov.
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The project consists of (upstream to
downstream): (1) A 1,320-foot-long, 6-foot-high diversion dam on the
Loup River; (2) an intake structure composed of eleven 24-foot-long by
5-foot-high steel intake gates located on the north bank of the Loup
River immediately upstream of the diversion dam; (3) three 20-foot-long
by 6-foot-high steel sluice gates located between the diversion dam and
the intake structure; (4) the 35-mile-long Loup Canal; (5) a 2-mile-
long settling basin located in the upper portion of the Loup Canal and
containing a floating hydraulic dredge and skimming weir; (6) the
Monroe Powerhouse containing three Francis-type, turbine-generating
units each with a rated capacity of 2.612 megawatts (MW); (7) a 760-
acre regulating reservoir, Lake Babcock, with a storage capacity of
2,270 acre-feet at its full pool elevation of 1,531 feet; (8) a 200-
acre regulating reservoir, Lake North, with a storage capacity of 2,080
acre-feet at an elevation of 1,531 feet; (9) a concrete control
structure in the south dike linking the two reservoirs; (10) a 60-foot-
long by 104-foot-wide by 40-foot-high inlet structure with trashracks;
(11) three 20-foot-diameter by 385-foot-long steel penstocks connecting
the inlet structure with a powerhouse (Columbus Powerhouse); (12) the
Columbus Powerhouse containing three Francis-type, turbine-generating
units each with a rated capacity of 15.2 MW; and (13) appurtenant
facilities. The project has a combined installed capacity of 53.4 MW.
The Monroe Powerhouse operates in a run-of-river mode (i.e., canal
inflow to the powerhouse closely approximates outflow from the
powerhouse with no storage of canal flow). The maximum hydraulic
capacity of the canal at the Monroe Powerhouse is 3,500 cubic feet per
second (cfs). The Monroe Powerhouse spans the canal and functions as an
energy-producing canal drop structure.
The Columbus Powerhouse operates as a daily peaking facility. The
water levels in Lake Babcock and Lake North are generally drawn down
about 2 to 3 feet to produce power during times of peak electrical
demand. In off-peak hours, when there is less demand for electricity,
the turbines are turned down or shut off, which allows Lake Babcock and
Lake North to refill, thereby allowing peaking operations to occur the
following day. The hydraulic capacity of the canal at the Columbus
Powerhouse is 4,800 cfs.
The minimum leakage rate at the Loup River diversion dam and sluice
gate structure is about 50 cfs. During hot weather conditions, Loup
Power District operates the diversion in a manner that allows flows of
between 50 to 75 cfs (including the leakage flow) to pass into the Loup
River downstream of the diversion to prevent high water temperatures
that could cause fish mortality.
Loup Power District proposes new and improved recreational
amenities at the project; however, there are no proposed changes to the
existing project facilities or operations.
Loup Power District proposes to remove three areas of land from the
project boundary that it finds are not necessary for project operations
or purposes. In addition, Loup Power District proposes to add three
parcels of land to the project boundary that it finds are needed for
project purposes.
l. Locations of the Application: A copy of the application is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's Web site at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov
or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural Schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready June 2012.
for Environmental Analysis.
Filing of recommendations, preliminary August 2012.
terms and conditions, and fishway
prescriptions.
Commission issues Draft EA............. February 2013.
Comments on Draft EA................... March 2013.
Modified terms and conditions.......... May 2013.
Commission issues Final EA............. August 2013.
------------------------------------------------------------------------
[[Page 25998]]
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: April 24, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-10534 Filed 5-1-12; 8:45 am]
BILLING CODE 6717-01-P