Loup River Public Power District; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 25158-25159 [2012-10222]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
25158
Federal Register / Vol. 77, No. 82 / Friday, April 27, 2012 / Notices
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis (EA).
l. The Project Description: The
proposed Admiralty Inlet Pilot Tidal
Project would consist of: (1) Two 19.7foot-diameter Open-Centre turbines,
supplied by OpenHydro Group Ltd.,
mounted on completely submerged
gravity foundations; (2) two
transmission cables which run from the
turbines to the cable termination vault;
(3) two transmission cables from the
cable termination vault to the proposed
cable control building; (4) a cable
control building housing the power
conditioning and monitoring
equipment; (5) a transmission cable
bringing power from the cable control
building to an existing 12.47-kilovolt
transmission line; and (6) appurtenant
facilities for operation and maintenance.
The estimated average annual
generation of the project is 216,000
kilowatt-hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
VerDate Mar<15>2010
17:44 Apr 26, 2012
Jkt 226001
385.210, .211, .214. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST,’’ ‘‘MOTION
TO INTERVENE,’’ ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or ‘‘FISHWAY
PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b) except to the extent
that this notice establishes deadlines
different from those in the regulation.
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application. A copy of
all other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
o. Procedural Schedule:
The application will be processed
according to the following Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Due date
Filing of recommendations, terms and conditions, and fishway
prescriptions.
Commission issues Single EA.
Comments on EA ..........
May 23, 2012.
July 23, 2012.
August 22, 2012.
p. Waiver of deadline to file
competing applications filed pursuant
to a notice of intent (NOI):
Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application or
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
an NOI to file such an application.
Section 4.36(b)(2) of the Commission’s
regulations, which allows 120 days from
the specified intervention deadline date
for interested parties to file competing
development applications in which
timely NOIs have been submitted, is
hereby waived. Due to the expedited
nature of the pilot project licensing
procedures, the submission of a timely
NOI will instead allow an interested
person to file the competing
development application no later than
30 days after the specified intervention
deadline date. Applications for
preliminary permits will not be
accepted in response to this notice.
An NOI must specify the exact name,
business address, and telephone number
of the prospective applicant, and must
include an unequivocal statement of
intent to submit a development
application. An NOI must be served on
the applicant named in this public
notice.
Dated: April 23, 2012.
Kimberly D. Bose,
Secretary .
[FR Doc. 2012–10221 Filed 4–26–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1256–031]
Loup River Public Power District;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 1256–031.
c. Date Filed: April 16, 2012.
d. Applicant: Loup River Public
Power District (Loup Power District).
e. Name of Project: Loup River
Hydroelectric Project (Loup River
Project).
f. Location: On the Loup River, Loup
Canal (a diversion canal off the Loup
River), and Platte River in Nance and
Platte counties, Nebraska. The project
does not occupy federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Neal Suess,
President/CEO, Loup Power District,
P.O. Box 988, 2404 15th Street,
E:\FR\FM\27APN1.SGM
27APN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 82 / Friday, April 27, 2012 / Notices
Columbus, Nebraska 68602, Telephone
(866) 869–2087.
i. FERC Contact: Lee Emery, (202)
502–8379 or lee.emery@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The project
consists of (upstream to downstream):
(1) A 1,320-foot-long, 6-foot-high
diversion dam on the Loup River; (2) an
intake structure composed of eleven 24foot-long by 5-foot-high steel intake
gates located on the north bank of the
Loup River immediately upstream of the
diversion dam; (3) three 20-foot-long by
6-foot-high steel sluice gates located
between the diversion dam and the
intake structure; (4) the 35-mile-long
Loup Canal; (5) a 2-mile-long settling
basin located in the upper portion of the
Loup Canal and containing a floating
hydraulic dredge and skimming weir;
(6) the Monroe Powerhouse containing
three Francis-type, turbine-generating
units each with a rated capacity of 2.612
megawatts (MW); (7) a 760-acre
regulating reservoir, Lake Babcock, with
a storage capacity of 2,270 acre-feet at
its full pool elevation of 1,531 feet; (8)
a 200-acre regulating reservoir, Lake
North, with a storage capacity of 2,080
acre-feet at an elevation of 1,531 feet; (9)
a concrete control structure in the south
dike linking the two reservoirs; (10) a
60-foot-long by 104-foot-wide by 40foot-high inlet structure with trashracks;
(11) three 20-foot-diameter by 385-footlong steel penstocks connecting the inlet
structure with a powerhouse (Columbus
Powerhouse); (12) the Columbus
Powerhouse containing three Francistype, turbine-generating units each with
a rated capacity of 15.2 MW; and (13)
appurtenant facilities. The project has a
combined installed capacity of 53.4
MW.
The Monroe Powerhouse operates in
a run-of-river mode (i.e., canal inflow to
the powerhouse closely approximates
outflow from the powerhouse with no
storage of canal flow). The maximum
hydraulic capacity of the canal at the
Monroe Powerhouse is 3,500 cubic feet
per second (cfs). The Monroe
Powerhouse spans the canal and
functions as an energy-producing canal
drop structure.
The Columbus Powerhouse operates
as a daily peaking facility. The water
levels in Lake Babcock and Lake North
are generally drawn down about 2 to 3
feet to produce power during times of
peak electrical demand. In off-peak
hours, when there is less demand for
electricity, the turbines are turned down
or shut off, which allows Lake Babcock
and Lake North to refill, thereby
allowing peaking operations to occur
the following day. The hydraulic
VerDate Mar<15>2010
17:44 Apr 26, 2012
Jkt 226001
capacity of the canal at the Columbus
Powerhouse is 4,800 cfs.
The minimum leakage rate at the
Loup River diversion dam and sluice
gate structure is about 50 cfs. During hot
weather conditions, Loup Power District
operates the diversion in a manner that
allows flows of between 50 to 75 cfs
(including the leakage flow) to pass into
the Loup River downstream of the
diversion to prevent high water
temperatures that could cause fish
mortality.
Loup Power District proposes new
and improved recreational amenities at
the project; however, there are no
proposed changes to the existing project
facilities or operations.
Loup Power District proposes to
remove three areas of land from the
project boundary that it finds are not
necessary for project operations or
purposes. In addition, Loup Power
District proposes to add three parcels of
land to the project boundary that it finds
are needed for project purposes.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule:
The application will be processed
according to the following preliminary
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Target date
Notice of Acceptance/Notice
of Ready for Environmental Analysis.
Filing of recommendations,
preliminary terms and
conditions, and fishway
prescriptions.
Commission issues Draft EA
Comments on Draft EA .......
Modified terms and conditions.
Commission issues Final EA
PO 00000
Frm 00039
Fmt 4703
June 2012.
August 2012.
February 2013.
March 2013.
May 2013.
August 2013.
Sfmt 4703
25159
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: April 23, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–10222 Filed 4–26–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG12–59–000.
Applicants: Copper Mountain Solar 2,
LLC.
Description: Self-Certification of EG or
FC of Copper Mountain Solar 2, LLC in
EG12–59.
Filed Date: 4/18/12.
Accession Number: 20120418–5245.
Comments Due: 5 p.m. ET 5/9/12.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1806–004;
ER11–1939–002; ER11–2754–002.
Applicants: AP Gas & Electric (PA),
LLC, AP Gas & Electric (TX), LLC, AP
Holdings, LLC.
Description: Change-in-Status Report
of AP Holdings, LLC, et al.
Filed Date: 4/18/12.
Accession Number: 20120418–5242.
Comments Due: 5 p.m. ET 5/9/12.
Docket Numbers: ER10–3082–002.
Applicants: Motiva Enterprises LLC.
Description: Supplement to Notice of
Change in Status of Motiva Enterprises
LLC.
Filed Date: 4/18/2012.
Accession Number: 20120418–5260.
Comment Date: 5 p.m. ET 5/9/12.
Docket Numbers: ER12–165–001.
Applicants: Midwest Independent
Transmission System Operator, Inc.
Description: G746 Compliance filing
to be effective 12/21/2011.
Filed Date: 4/18/12.
Accession Number: 20120418–5163.
Comments Due: 5 p.m. ET 5/9/12.
Docket Numbers: ER12–1552–000.
Applicants: Southwest Power Pool,
Inc.
Description: Errata Filing in Docket
No. ER12–1552—Implement Balanced
Portfolio Transfers to be effective N/A.
Filed Date: 4/18/12.
Accession Number: 20120418–5127.
E:\FR\FM\27APN1.SGM
27APN1
Agencies
[Federal Register Volume 77, Number 82 (Friday, April 27, 2012)]
[Notices]
[Pages 25158-25159]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-10222]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1256-031]
Loup River Public Power District; Notice of Application Tendered
for Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 1256-031.
c. Date Filed: April 16, 2012.
d. Applicant: Loup River Public Power District (Loup Power
District).
e. Name of Project: Loup River Hydroelectric Project (Loup River
Project).
f. Location: On the Loup River, Loup Canal (a diversion canal off
the Loup River), and Platte River in Nance and Platte counties,
Nebraska. The project does not occupy federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Neal Suess, President/CEO, Loup Power
District, P.O. Box 988, 2404 15th Street,
[[Page 25159]]
Columbus, Nebraska 68602, Telephone (866) 869-2087.
i. FERC Contact: Lee Emery, (202) 502-8379 or lee.emery@ferc.gov.
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The project consists of (upstream to
downstream): (1) A 1,320-foot-long, 6-foot-high diversion dam on the
Loup River; (2) an intake structure composed of eleven 24-foot-long by
5-foot-high steel intake gates located on the north bank of the Loup
River immediately upstream of the diversion dam; (3) three 20-foot-long
by 6-foot-high steel sluice gates located between the diversion dam and
the intake structure; (4) the 35-mile-long Loup Canal; (5) a 2-mile-
long settling basin located in the upper portion of the Loup Canal and
containing a floating hydraulic dredge and skimming weir; (6) the
Monroe Powerhouse containing three Francis-type, turbine-generating
units each with a rated capacity of 2.612 megawatts (MW); (7) a 760-
acre regulating reservoir, Lake Babcock, with a storage capacity of
2,270 acre-feet at its full pool elevation of 1,531 feet; (8) a 200-
acre regulating reservoir, Lake North, with a storage capacity of 2,080
acre-feet at an elevation of 1,531 feet; (9) a concrete control
structure in the south dike linking the two reservoirs; (10) a 60-foot-
long by 104-foot-wide by 40-foot-high inlet structure with trashracks;
(11) three 20-foot-diameter by 385-foot-long steel penstocks connecting
the inlet structure with a powerhouse (Columbus Powerhouse); (12) the
Columbus Powerhouse containing three Francis-type, turbine-generating
units each with a rated capacity of 15.2 MW; and (13) appurtenant
facilities. The project has a combined installed capacity of 53.4 MW.
The Monroe Powerhouse operates in a run-of-river mode (i.e., canal
inflow to the powerhouse closely approximates outflow from the
powerhouse with no storage of canal flow). The maximum hydraulic
capacity of the canal at the Monroe Powerhouse is 3,500 cubic feet per
second (cfs). The Monroe Powerhouse spans the canal and functions as an
energy-producing canal drop structure.
The Columbus Powerhouse operates as a daily peaking facility. The
water levels in Lake Babcock and Lake North are generally drawn down
about 2 to 3 feet to produce power during times of peak electrical
demand. In off-peak hours, when there is less demand for electricity,
the turbines are turned down or shut off, which allows Lake Babcock and
Lake North to refill, thereby allowing peaking operations to occur the
following day. The hydraulic capacity of the canal at the Columbus
Powerhouse is 4,800 cfs.
The minimum leakage rate at the Loup River diversion dam and sluice
gate structure is about 50 cfs. During hot weather conditions, Loup
Power District operates the diversion in a manner that allows flows of
between 50 to 75 cfs (including the leakage flow) to pass into the Loup
River downstream of the diversion to prevent high water temperatures
that could cause fish mortality.
Loup Power District proposes new and improved recreational
amenities at the project; however, there are no proposed changes to the
existing project facilities or operations.
Loup Power District proposes to remove three areas of land from the
project boundary that it finds are not necessary for project operations
or purposes. In addition, Loup Power District proposes to add three
parcels of land to the project boundary that it finds are needed for
project purposes.
l. Locations of the Application: A copy of the application is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's Web site at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov
or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural Schedule:
The application will be processed according to the following
preliminary Hydro Licensing Schedule. Revisions to the schedule may be
made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready for June 2012.
Environmental Analysis.
Filing of recommendations, preliminary August 2012.
terms and conditions, and fishway
prescriptions.
Commission issues Draft EA.............. February 2013.
Comments on Draft EA.................... March 2013.
Modified terms and conditions........... May 2013.
Commission issues Final EA.............. August 2013.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: April 23, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-10222 Filed 4-26-12; 8:45 am]
BILLING CODE 6717-01-P