Actions Taken at March 15, 2012, Meeting, 19052-19054 [2012-7528]

Download as PDF 19052 Federal Register / Vol. 77, No. 61 / Thursday, March 29, 2012 / Notices 21. Project Sponsor and Facility: Williams Production Appalachia, LLC (Middle Branch Wyalusing Creek), Forest Lake Township, Susquehanna County, Pa. Surface water withdrawal of up to 0.750 mgd. 22. Project Sponsor and Facility: Williams Production Appalachia, LLC (Snake Creek–2), Franklin Township, Susquehanna County, Pa. Surface water withdrawal of up to 0.999 mgd. 23. Project Sponsor and Facility: Williams Production Appalachia, LLC (Susquehanna River), Great Bend Township, Susquehanna County, Pa. Commission-initiated modification to project features and conditions of the surface water withdrawal approval (Docket No. 20090303), making a correction and reducing the approved surface water withdrawal amount from 3.00 mgd to 1.00 mgd. 24. Project Sponsor and Facility: Williams Production Appalachia, LLC (Susquehanna River–2), Great Bend Township, Susquehanna County, Pa. Surface water withdrawal of up to 2.000 mgd. Authority: Pub. L. 91–575, 84 Stat. 1509 et seq., 18 CFR parts 806, 807, and 808. Dated: March 23, 2012. Thomas W. Beauduy, Deputy Executive Director. [FR Doc. 2012–7552 Filed 3–28–12; 8:45 am] BILLING CODE 7040–01–P SUSQUEHANNA RIVER BASIN COMMISSION Actions Taken at March 15, 2012, Meeting Susquehanna River Basin Commission. ACTION: Notice. AGENCY: As part of its regular business meeting held on March 15, 2012, in Harrisburg, Pennsylvania, the Commission took the following actions: (1) Reconsidered certain actions taken at its December 15, 2011, public hearing; (2) upon reconsideration, approved or denied the applications of certain water resources projects, originally considered at the December 15, 2011, public hearing; (3) rescinded approval for one additional water resources project; (4) approved, tabled or denied the applications of certain additional water resources projects; and (5) took additional actions as set forth in the Supplementary Information below. DATES: March 15, 2012. ADDRESSES: Susquehanna River Basin Commission, 1721 N. Front Street, Harrisburg, PA 17102–2391. mstockstill on DSK4VPTVN1PROD with NOTICES SUMMARY: VerDate Mar<15>2010 17:14 Mar 28, 2012 Jkt 226001 FOR FURTHER INFORMATION CONTACT: Richard A. Cairo, General Counsel, telephone: (717) 238–0423, ext. 306; fax: (717) 238–2436; email: rcairo@srbc.net. Regular mail inquiries may be sent to the above address. See also Commission Web site at www.srbc.net. SUPPLEMENTARY INFORMATION: In addition to its related actions on projects identified in the summary above and the listings below, the following items were also presented or acted on at the business meeting: (1) Adoption of a resolution encouraging the use of lesser quality waters; (2) approval for expenditures for the Susquehanna River Flow Management Project; (3) adoption of an investment policy statement and amendments of the By-Laws; (4) approval of a partial waiver of the fee for transfer of approvals to SWEPI, LP; (5) adoption of the revised operating budget and a capital budget for FY–2013; (6) approval for staff to release a draft Low Flow Protection Policy for public review and comment; (7) ratification of a settlement agreement with C&N Dining; and (8) ratification of grants/contracts. The Commission also took the following specific actions: Project Applications Originally Considered at the December 15, 2011, Public Hearing, Approved Upon reconsideration, the Commission approved the following project applications originally acted upon at the December 15, 2011, public hearing: 1. Project Sponsor: Bioenergy International, LLC. Project Facility: Bionol Clearfield, LLC, Clearfield Borough, Clearfield County, Pa. Modification to conditions of the surface water withdrawal approval (Docket No. 20070904). 2. Project Sponsor: Borough of Ephrata. Project Facility: Ephrata Area Joint Authority, Ephrata Borough, Lancaster County, Pa. Modification to conditions of the groundwater withdrawal approval (Docket No. 20110902). 3. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Mosquito Creek–2), Karthaus Township, Clearfield County, Pa. Surface water withdrawal of up to 2.160 mgd. 4. Project Sponsor and Facility: Central New York Oil and Gas Company, LLC (Susquehanna River), Wilmot Township, Bradford County, Pa. Surface water withdrawal of up to 0.540 mgd. 5. Project Sponsor and Facility: Central New York Oil and Gas Company, LLC, Wilmot Township, Bradford County, Pa. Consumptive water use of up to 0.105 mgd. PO 00000 Frm 00056 Fmt 4703 Sfmt 4703 6. Project Sponsor and Facility: Chesapeake Appalachia, LLC (Susquehanna River—Babcock), Ulster Township, Bradford County, Pa. Surface water withdrawal of up to 3.000 mgd. 7. Project Sponsor and Facility: Chesapeake Appalachia, LLC (Susquehanna River—Elmglade), Wilmot Township, Bradford County, Pa. Surface water withdrawal of up to 2.016 mgd. 8. Project Sponsor and Facility: Chesapeake Appalachia, LLC (Towanda Creek—Sechrist), Canton Township, Bradford County, Pa. Surface water withdrawal of up to 0.504 mgd. 9. Project Sponsor: Clark Trucking, LLC. Project Facility: Northeast Division (Lycoming Creek), Lewis Township, Lycoming County, Pa. Surface water withdrawal of up to 0.500 mgd. 10. Project Sponsor: Clark Trucking, LLC. Project Facility: Northeast Division (Muncy Creek), Muncy Creek Township, Lycoming County, Pa. Surface water withdrawal of up to 0.700 mgd. 11. Project Sponsor and Facility: Dunn Lake LLC (Dunn Pond), Ararat Township, Susquehanna County, Pa. Surface water withdrawal of up to 0.999 mgd. 12. Project Sponsor and Facility: EXCO Resources (PA), LLC (Muncy Creek—McClintock), Penn Township, Lycoming County, Pa. Surface water withdrawal of up to 1.500 mgd. 13. Project Sponsor: Glenn O. Hawbaker, Inc. Project Facility: Greens Landing Aggregate Plant, Athens Township, Bradford County, Pa. Surface water withdrawal of up to 0.249 mgd. 14. Project Sponsor: Glenn O. Hawbaker, Inc. Project Facility: Greens Landing Aggregate Plant, Athens Township, Bradford County, Pa. Consumptive water use of up to 0.249 mgd. 15. Project Sponsor: Hazleton Creek Properties, LLC. Project Facility: Hazleton Mine Reclamation, Hazleton City, Luzerne County, Pa. Modification to increase groundwater withdrawal by an additional 0.145 mgd, for a total of 0.200 mgd (30-day average) (Docket No. 20110307). 16. Project Sponsor and Facility: Keystone Clearwater Solutions, LLC (Babb Creek), Morris Township, Tioga County, Pa. Surface water withdrawal of up to 0.950 mgd. 17. Project Sponsor and Facility: Sugar Hollow Trout Park and Hatchery, Eaton Township, Wyoming County, Pa. Modification to project features and conditions of the groundwater withdrawal approval (Docket No. 20100913). 18. Project Sponsor and Facility: Sugar Hollow Water Services, LLC E:\FR\FM\29MRN1.SGM 29MRN1 Federal Register / Vol. 77, No. 61 / Thursday, March 29, 2012 / Notices mstockstill on DSK4VPTVN1PROD with NOTICES (Susquehanna River—Chellis), Eaton Township, Wyoming County, Pa. Surface water withdrawal of up to 1.500 mgd. 19. Project Sponsor: The Municipal Authority of the Borough of Berlin. Project Facility: Berlin Borough Municipal Authority, Allegheny Township, Somerset County, Pa. Modification to conditions of the groundwater withdrawal approval (Docket No. 19980702). 20. Project Sponsor and Facility: Walker Township Water Association, Walker Township, Centre County, Pa. Modification to increase the total groundwater system withdrawal limit from 0.523 mgd to 0.753 mgd (30-day average) (Docket No. 20070905). 21. Project Sponsor and Facility: Williams Production Appalachia, LLC (Middle Branch Wyalusing Creek), Forest Lake Township, Susquehanna County, Pa. Surface water withdrawal of up to 0.750 mgd. 22. Project Sponsor and Facility: Williams Production Appalachia, LLC (Snake Creek–2), Franklin Township, Susquehanna County, Pa. Surface water withdrawal of up to 0.999 mgd. 23. Project Sponsor and Facility: Williams Production Appalachia, LLC (Susquehanna River), Great Bend Township, Susquehanna County, Pa. Commission-initiated modification to project features and conditions of the surface water withdrawal approval (Docket No. 20090303), making a correction and reducing the approved surface water withdrawal amount from 3.00 mgd to 1.00 mgd. 24. Project Sponsor and Facility: Williams Production Appalachia, LLC (Susquehanna River–2), Great Bend Township, Susquehanna County, Pa. Surface water withdrawal of up to 2.000 mgd. Project Application Originally Considered at the December 15, 2011, Public Hearing, Denied Upon reconsideration, the Commission denied the following project application originally acted upon at the December 15, 2011, public hearing: 1. Project Sponsor: Anadarko E&P Company LP. Project Facility: Sproul State Forest—Council Run, Snow Shoe Township, Centre County, Pa. Application for groundwater withdrawal of up to 0.715 mgd (30-day average) from Well PW–11. Rescission of Project Approval The Commission rescinded approval for the following project: 1. Project Sponsor and Facility: Texas Eastern Transmission LP (Susquehanna VerDate Mar<15>2010 17:14 Mar 28, 2012 Jkt 226001 River) (Docket No. 20110314), East Donegal Township, Lancaster County, Pa. Project Applications Approved The Commission approved the following project applications: 1. Project Sponsor and Facility: Anadarko E&P Company LP (Lycoming Creek), Lewis Township, Lycoming County, Pa. Surface water withdrawal of up to 1.340 mgd (peak day). 2. Project Sponsor and Facility: Aqua Infrastructure, LLC (West Branch Susquehanna River), Piatt Township, Lycoming County, Pa. Surface water withdrawal of up to 3.000 mgd (peak day). 3. Project Sponsor and Facility: Black Bear Waters, LLC (Lycoming Creek), Lewis Township, Lycoming County, Pa. Surface water withdrawal of up to 0.400 mgd (peak day). 4. Project Sponsor and Facility: Blossburg Municipal Authority, Bloss Township, Tioga County, Pa. Groundwater withdrawal of up to 0.396 mgd (30-day average) from Route 15 Well. 5. Project Sponsor and Facility: Buck Ridge Stone, LLC (Salt Lick Creek), New Milford Township, Susquehanna County, Pa. Modification to increase surface water withdrawal by an additional 0.637 mgd, for a total of 0.720 mgd (peak day) (Docket No. 20100905). 6. Project Sponsor and Facility: Cabot Oil & Gas Corporation (Susquehanna River), Susquehanna Depot Borough, Susquehanna County, Pa. Modification to increase surface water withdrawal by an additional 0.780 mgd, for a total of 1.500 mgd (peak day) (Docket No. 20080908). 7. Project Sponsor and Facility: Cabot Oil & Gas Corporation (Susquehanna River), Great Bend Township, Susquehanna County, Pa. Modification to increase surface water withdrawal by an additional 1.280 mgd, for a total of 2.000 mgd (peak day) (Docket No. 20080905). 8. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Middle Branch Wyalusing Creek), Forest Lake Township, Susquehanna County, Pa. Modification to conditions of the surface water withdrawal approval (Docket No. 20110604). 9. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Moshannon Creek), Decatur Township, Clearfield County, Pa. Surface water withdrawal of up to 2.590 mgd (peak day). 10. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Unnamed Tributary of Middle Branch Wyalusing Creek), Forest Lake Township, Susquehanna County, Pa. Modification PO 00000 Frm 00057 Fmt 4703 Sfmt 4703 19053 to conditions of the surface water withdrawal approval (Docket No. 20110605). 11. Project Sponsor and Facility: EQT Production Company (Bennett Branch Power), Jay Township, Elk County, Pa. Surface water withdrawal of up to 2.500 mgd (peak day). 12. Project Sponsor and Facility: EQT Production Company (Wilson Creek), Duncan Township, Tioga County, Pa. Surface water withdrawal of up to 0.740 mgd (peak day). 13. Project Sponsor: IBM Corporation. Project Facility: Endicott Facility, Village of Endicott, Broome County, N.Y. Modification to increase total groundwater system withdrawal by an additional 0.499 mgd, for a total of 1.509 mgd (30-day average) (Docket No. 20090329). 14. Project Sponsor and Facility: Keystone Landfill, Inc., Dunmore Borough, Lackawanna County, Pa. Modification to increase groundwater withdrawal by an additional 0.150 mgd, for a total of 0.160 mgd (30-day average) (Docket No. 20080611). 15. Project Sponsor and Facility: Keystone Landfill, Inc., Dunmore Borough, Lackawanna County, Pa. Modification to increase consumptive water use by an additional 0.260 mgd, for a total of up to 0.360 mgd (30-day average) (Docket No. 20080611). 16. Project Sponsor: Pine Creek Municipal Authority. Project Facility: Wastewater Treatment Plant, Pine Creek Township, Clinton County, Pa. Withdrawal of treated wastewater effluent of up to 0.999 mgd. 17. Project Sponsor and Facility: Roaring Spring Water–Division of Roaring Spring Blank Book (Roaring Spring), Roaring Spring Borough, Blair County, Pa. Surface water withdrawal of up to 0.302 mgd (peak day). 18. Project Sponsor and Facility: Roaring Spring Water–Division of Roaring Spring Blank Book, Roaring Spring Borough, Blair County, Pa. Consumptive water use of up to 0.255 mgd (30-day average). 19. Project Sponsor and Facility: Southwestern Energy Production Company (Blockhouse Creek), Jackson Township, Lycoming County, Pa. Surface water withdrawal of up to 0.999 mgd (peak day). 20. Project Sponsor and Facility: Southwestern Energy Production Company (Susquehanna River), Oakland Township, Susquehanna County, Pa. Surface water withdrawal of up to 3.000 mgd (peak day). 21. Project Sponsor and Facility: Southwestern Energy Production Company (Tunkhannock Creek), Lenox Township, Susquehanna County, Pa. E:\FR\FM\29MRN1.SGM 29MRN1 19054 Federal Register / Vol. 77, No. 61 / Thursday, March 29, 2012 / Notices mstockstill on DSK4VPTVN1PROD with NOTICES Surface water withdrawal of up to 1.500 mgd (peak day). 22. Project Sponsor and Facility: SWEPI LP (Cowanesque River— Egleston), Nelson Township, Tioga County, Pa. Modification to increase surface water withdrawal by an additional 0.267 mgd, for a total of 0.534 mgd (peak day) (Docket No. 20100604). Project Applications Tabled The following project applications were tabled by the Commission: 1. Project Sponsor and Facility: Aqua Resources, Inc. (Susquehanna River), Athens Township, Bradford County, Pa. Application for surface water withdrawal of up to 0.900 mgd (peak day). 2. Project Sponsor and Facility: Empire Kosher Poultry, Inc., Walker Township, Juniata County, Pa. Modification to increase total groundwater system withdrawal by an additional 0.499 mgd, for a total of 1.269 mgd (30-day average) (Docket No. 20030809). 3. Project Sponsor and Facility: Jo Jo Oil Company, Inc. (Tunkhannock Creek), Tunkhannock Township, Wyoming County, Pa. Application for surface water withdrawal of up to 0.999 mgd (peak day). 4. Project Sponsor and Facility: Northwestern Lancaster County Authority, Penn Township, Lancaster County, Pa. Application for groundwater withdrawal of up to 0.324 mgd (30-day average) from Well 2. 5. Project Sponsor and Facility: Northwestern Lancaster County Authority, Penn Township, Lancaster County, Pa. Application for groundwater withdrawal of up to 1.000 mgd (30-day average) from Well 3. 6. Project Sponsor and Facility: Southwestern Energy Production Company (East Branch Tunkhannock Creek), Lenox Township, Susquehanna County, Pa. Application for surface water withdrawal of up to 1.500 mgd (peak day). 7. Project Sponsor: Viking Energy of Northumberland, LLC. Project Facility: Power Plant, Point Township, Northumberland County, Pa. Application for consumptive water use of up to 0.387 mgd (30-day average). 8. Project Sponsor: Viking Energy of Northumberland, LLC. Project Facility: Power Plant, Point Township, Northumberland County, Pa. Application for groundwater withdrawal of up to 0.172 mgd from Well 1, and a total system withdrawal limit of up to 0.391 mgd (30-day average). 9. Project Sponsor: Viking Energy of Northumberland, LLC. Project Facility: VerDate Mar<15>2010 17:14 Mar 28, 2012 Jkt 226001 Power Plant, Point Township, Northumberland County, Pa. Application for groundwater withdrawal of up to 0.172 mgd from Well 2, and a total system withdrawal limit of up to 0.391 mgd (30-day average). 10. Project Sponsor: Viking Energy of Northumberland, LLC. Project Facility: Power Plant, Point Township, Northumberland County, Pa. Application for groundwater withdrawal of up to 0.172 mgd from Well 4, and a total system withdrawal limit of up to 0.391 mgd (30-day average). Project Applications Denied The following project applications were denied by the Commission: 1. Project Sponsor and Facility: Stanley S. Karp Sr. (Tunkhannock Creek), Nicholson Township, Wyoming County, Pa. Application for surface water withdrawal of up to 0.510 mgd (peak day). 2. Project Sponsor and Facility: Water Treatment Solutions, LLC (South Mountain Lake), Woodward Township, Lycoming County, Pa. Application for surface water withdrawal of up to 0.499 mgd (peak day). Authority: Pub. L. 91–575, 84 Stat. 1509 et seq., 18 CFR parts 806, 807, and 808. Dated: March 23, 2012. Thomas W. Beauduy, Deputy Executive Director. [FR Doc. 2012–7528 Filed 3–28–12; 8:45 am] BILLING CODE 7040–01–P DEPARTMENT OF TRANSPORTATION Federal Railroad Administration [Docket No. FRA–2000–7257; Notice No. 68] Railroad Safety Advisory Committee; Notice of Meeting Federal Railroad Administration (FRA), Department of Transportation (DOT). ACTION: Announcement of Railroad Safety Advisory Committee (RSAC) meeting. AGENCY: FRA announces the fortysixth meeting of the RSAC, a Federal Advisory Committee that develops railroad safety regulations through a consensus process. The RSAC meeting topics will include opening remarks from the FRA Administrator, and status reports will be provided by the Track Safety Standards, Critical Incident, Dark Territory, Fatigue Management, Risk Reduction, Electronic Device Distraction, and Passenger Safety SUMMARY: PO 00000 Frm 00058 Fmt 4703 Sfmt 9990 Working Groups. This agenda is subject to change, including the possible addition of further proposed tasks under the Rail Safety Improvement Act of 2008. The meeting of the RSAC is scheduled to commence at 9:30 a.m. on Thursday, April 26, 2012, and will adjourn by 4:30 p.m. DATES: The RSAC meeting will be held at the National Housing Center, 1201 15th Street NW., Washington, DC 20005. The meeting is open to the public on a first-come, first-served basis, and is accessible to individuals with disabilities. Sign and oral interpretation can be made available if requested 10 calendar days before the meeting. ADDRESSES: Mr. Larry Woolverton, RSAC Administrative Officer/Coordinator, FRA, 1200 New Jersey Avenue SE., Mailstop 25, Washington, DC 20590, (202) 493–6212; or Mr. Robert C. Lauby, Deputy Associate Administrator for Regulatory and Legislative Operations, FRA, 1200 New Jersey Avenue SE., Mailstop 25, Washington, DC 20590, (202) 493–6404. FOR FURTHER INFORMATION CONTACT: Pursuant to Section 10(a)(2) of the Federal Advisory Committee Act (Pub. L. 92– 463), FRA is giving notice of a meeting of the RSAC. The RSAC was established to provide advice and recommendations to FRA on railroad safety matters. The RSAC is composed of 54 voting representatives from 31 member organizations, representing various rail industry perspectives. In addition, there are non-voting advisory representatives from the agencies with railroad safety regulatory responsibility in Canada and Mexico, the National Transportation Safety Board, and the Federal Transit Administration. The diversity of the Committee ensures the requisite range of views and expertise necessary to discharge its responsibilities. See the RSAC Web site for details on prior RSAC activities and pending tasks at: https://rsac.fra.dot.gov/. Please refer to the notice published in the Federal Register on March 11, 1996 (61 FR 9740), for additional information about the RSAC. SUPPLEMENTARY INFORMATION: Issued in Washington, DC, on March 22, 2012. Robert C. Lauby, Deputy Associate Administrator for Regulatory and Legislative Operations. [FR Doc. 2012–7492 Filed 3–28–12; 8:45 am] BILLING CODE 4910–06–P E:\FR\FM\29MRN1.SGM 29MRN1

Agencies

[Federal Register Volume 77, Number 61 (Thursday, March 29, 2012)]
[Notices]
[Pages 19052-19054]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-7528]


-----------------------------------------------------------------------

SUSQUEHANNA RIVER BASIN COMMISSION


Actions Taken at March 15, 2012, Meeting

AGENCY: Susquehanna River Basin Commission.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: As part of its regular business meeting held on March 15, 
2012, in Harrisburg, Pennsylvania, the Commission took the following 
actions: (1) Reconsidered certain actions taken at its December 15, 
2011, public hearing; (2) upon reconsideration, approved or denied the 
applications of certain water resources projects, originally considered 
at the December 15, 2011, public hearing; (3) rescinded approval for 
one additional water resources project; (4) approved, tabled or denied 
the applications of certain additional water resources projects; and 
(5) took additional actions as set forth in the Supplementary 
Information below.

DATES: March 15, 2012.

ADDRESSES: Susquehanna River Basin Commission, 1721 N. Front Street, 
Harrisburg, PA 17102-2391.

FOR FURTHER INFORMATION CONTACT: Richard A. Cairo, General Counsel, 
telephone: (717) 238-0423, ext. 306; fax: (717) 238-2436; email: 
rcairo@srbc.net. Regular mail inquiries may be sent to the above 
address. See also Commission Web site at www.srbc.net.

SUPPLEMENTARY INFORMATION: In addition to its related actions on 
projects identified in the summary above and the listings below, the 
following items were also presented or acted on at the business 
meeting: (1) Adoption of a resolution encouraging the use of lesser 
quality waters; (2) approval for expenditures for the Susquehanna River 
Flow Management Project; (3) adoption of an investment policy statement 
and amendments of the By-Laws; (4) approval of a partial waiver of the 
fee for transfer of approvals to SWEPI, LP; (5) adoption of the revised 
operating budget and a capital budget for FY-2013; (6) approval for 
staff to release a draft Low Flow Protection Policy for public review 
and comment; (7) ratification of a settlement agreement with C&N 
Dining; and (8) ratification of grants/contracts. The Commission also 
took the following specific actions:

Project Applications Originally Considered at the December 15, 2011, 
Public Hearing, Approved

    Upon reconsideration, the Commission approved the following project 
applications originally acted upon at the December 15, 2011, public 
hearing:
    1. Project Sponsor: Bioenergy International, LLC. Project Facility: 
Bionol Clearfield, LLC, Clearfield Borough, Clearfield County, Pa. 
Modification to conditions of the surface water withdrawal approval 
(Docket No. 20070904).
    2. Project Sponsor: Borough of Ephrata. Project Facility: Ephrata 
Area Joint Authority, Ephrata Borough, Lancaster County, Pa. 
Modification to conditions of the groundwater withdrawal approval 
(Docket No. 20110902).
    3. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Mosquito 
Creek-2), Karthaus Township, Clearfield County, Pa. Surface water 
withdrawal of up to 2.160 mgd.
    4. Project Sponsor and Facility: Central New York Oil and Gas 
Company, LLC (Susquehanna River), Wilmot Township, Bradford County, Pa. 
Surface water withdrawal of up to 0.540 mgd.
    5. Project Sponsor and Facility: Central New York Oil and Gas 
Company, LLC, Wilmot Township, Bradford County, Pa. Consumptive water 
use of up to 0.105 mgd.
    6. Project Sponsor and Facility: Chesapeake Appalachia, LLC 
(Susquehanna River--Babcock), Ulster Township, Bradford County, Pa. 
Surface water withdrawal of up to 3.000 mgd.
    7. Project Sponsor and Facility: Chesapeake Appalachia, LLC 
(Susquehanna River--Elmglade), Wilmot Township, Bradford County, Pa. 
Surface water withdrawal of up to 2.016 mgd.
    8. Project Sponsor and Facility: Chesapeake Appalachia, LLC 
(Towanda Creek--Sechrist), Canton Township, Bradford County, Pa. 
Surface water withdrawal of up to 0.504 mgd.
    9. Project Sponsor: Clark Trucking, LLC. Project Facility: 
Northeast Division (Lycoming Creek), Lewis Township, Lycoming County, 
Pa. Surface water withdrawal of up to 0.500 mgd.
    10. Project Sponsor: Clark Trucking, LLC. Project Facility: 
Northeast Division (Muncy Creek), Muncy Creek Township, Lycoming 
County, Pa. Surface water withdrawal of up to 0.700 mgd.
    11. Project Sponsor and Facility: Dunn Lake LLC (Dunn Pond), Ararat 
Township, Susquehanna County, Pa. Surface water withdrawal of up to 
0.999 mgd.
    12. Project Sponsor and Facility: EXCO Resources (PA), LLC (Muncy 
Creek--McClintock), Penn Township, Lycoming County, Pa. Surface water 
withdrawal of up to 1.500 mgd.
    13. Project Sponsor: Glenn O. Hawbaker, Inc. Project Facility: 
Greens Landing Aggregate Plant, Athens Township, Bradford County, Pa. 
Surface water withdrawal of up to 0.249 mgd.
    14. Project Sponsor: Glenn O. Hawbaker, Inc. Project Facility: 
Greens Landing Aggregate Plant, Athens Township, Bradford County, Pa. 
Consumptive water use of up to 0.249 mgd.
    15. Project Sponsor: Hazleton Creek Properties, LLC. Project 
Facility: Hazleton Mine Reclamation, Hazleton City, Luzerne County, Pa. 
Modification to increase groundwater withdrawal by an additional 0.145 
mgd, for a total of 0.200 mgd (30-day average) (Docket No. 20110307).
    16. Project Sponsor and Facility: Keystone Clearwater Solutions, 
LLC (Babb Creek), Morris Township, Tioga County, Pa. Surface water 
withdrawal of up to 0.950 mgd.
    17. Project Sponsor and Facility: Sugar Hollow Trout Park and 
Hatchery, Eaton Township, Wyoming County, Pa. Modification to project 
features and conditions of the groundwater withdrawal approval (Docket 
No. 20100913).
    18. Project Sponsor and Facility: Sugar Hollow Water Services, LLC

[[Page 19053]]

(Susquehanna River--Chellis), Eaton Township, Wyoming County, Pa. 
Surface water withdrawal of up to 1.500 mgd.
    19. Project Sponsor: The Municipal Authority of the Borough of 
Berlin. Project Facility: Berlin Borough Municipal Authority, Allegheny 
Township, Somerset County, Pa. Modification to conditions of the 
groundwater withdrawal approval (Docket No. 19980702).
    20. Project Sponsor and Facility: Walker Township Water 
Association, Walker Township, Centre County, Pa. Modification to 
increase the total groundwater system withdrawal limit from 0.523 mgd 
to 0.753 mgd (30-day average) (Docket No. 20070905).
    21. Project Sponsor and Facility: Williams Production Appalachia, 
LLC (Middle Branch Wyalusing Creek), Forest Lake Township, Susquehanna 
County, Pa. Surface water withdrawal of up to 0.750 mgd.
    22. Project Sponsor and Facility: Williams Production Appalachia, 
LLC (Snake Creek-2), Franklin Township, Susquehanna County, Pa. Surface 
water withdrawal of up to 0.999 mgd.
    23. Project Sponsor and Facility: Williams Production Appalachia, 
LLC (Susquehanna River), Great Bend Township, Susquehanna County, Pa. 
Commission-initiated modification to project features and conditions of 
the surface water withdrawal approval (Docket No. 20090303), making a 
correction and reducing the approved surface water withdrawal amount 
from 3.00 mgd to 1.00 mgd.
    24. Project Sponsor and Facility: Williams Production Appalachia, 
LLC (Susquehanna River-2), Great Bend Township, Susquehanna County, Pa. 
Surface water withdrawal of up to 2.000 mgd.

Project Application Originally Considered at the December 15, 2011, 
Public Hearing, Denied

    Upon reconsideration, the Commission denied the following project 
application originally acted upon at the December 15, 2011, public 
hearing:
    1. Project Sponsor: Anadarko E&P Company LP. Project Facility: 
Sproul State Forest--Council Run, Snow Shoe Township, Centre County, 
Pa. Application for groundwater withdrawal of up to 0.715 mgd (30-day 
average) from Well PW-11.

Rescission of Project Approval

    The Commission rescinded approval for the following project:
    1. Project Sponsor and Facility: Texas Eastern Transmission LP 
(Susquehanna River) (Docket No. 20110314), East Donegal Township, 
Lancaster County, Pa.

Project Applications Approved

    The Commission approved the following project applications:
    1. Project Sponsor and Facility: Anadarko E&P Company LP (Lycoming 
Creek), Lewis Township, Lycoming County, Pa. Surface water withdrawal 
of up to 1.340 mgd (peak day).
    2. Project Sponsor and Facility: Aqua Infrastructure, LLC (West 
Branch Susquehanna River), Piatt Township, Lycoming County, Pa. Surface 
water withdrawal of up to 3.000 mgd (peak day).
    3. Project Sponsor and Facility: Black Bear Waters, LLC (Lycoming 
Creek), Lewis Township, Lycoming County, Pa. Surface water withdrawal 
of up to 0.400 mgd (peak day).
    4. Project Sponsor and Facility: Blossburg Municipal Authority, 
Bloss Township, Tioga County, Pa. Groundwater withdrawal of up to 0.396 
mgd (30-day average) from Route 15 Well.
    5. Project Sponsor and Facility: Buck Ridge Stone, LLC (Salt Lick 
Creek), New Milford Township, Susquehanna County, Pa. Modification to 
increase surface water withdrawal by an additional 0.637 mgd, for a 
total of 0.720 mgd (peak day) (Docket No. 20100905).
    6. Project Sponsor and Facility: Cabot Oil & Gas Corporation 
(Susquehanna River), Susquehanna Depot Borough, Susquehanna County, Pa. 
Modification to increase surface water withdrawal by an additional 
0.780 mgd, for a total of 1.500 mgd (peak day) (Docket No. 20080908).
    7. Project Sponsor and Facility: Cabot Oil & Gas Corporation 
(Susquehanna River), Great Bend Township, Susquehanna County, Pa. 
Modification to increase surface water withdrawal by an additional 
1.280 mgd, for a total of 2.000 mgd (peak day) (Docket No. 20080905).
    8. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Middle 
Branch Wyalusing Creek), Forest Lake Township, Susquehanna County, Pa. 
Modification to conditions of the surface water withdrawal approval 
(Docket No. 20110604).
    9. Project Sponsor and Facility: Carrizo (Marcellus), LLC 
(Moshannon Creek), Decatur Township, Clearfield County, Pa. Surface 
water withdrawal of up to 2.590 mgd (peak day).
    10. Project Sponsor and Facility: Carrizo (Marcellus), LLC (Unnamed 
Tributary of Middle Branch Wyalusing Creek), Forest Lake Township, 
Susquehanna County, Pa. Modification to conditions of the surface water 
withdrawal approval (Docket No. 20110605).
    11. Project Sponsor and Facility: EQT Production Company (Bennett 
Branch Power), Jay Township, Elk County, Pa. Surface water withdrawal 
of up to 2.500 mgd (peak day).
    12. Project Sponsor and Facility: EQT Production Company (Wilson 
Creek), Duncan Township, Tioga County, Pa. Surface water withdrawal of 
up to 0.740 mgd (peak day).
    13. Project Sponsor: IBM Corporation. Project Facility: Endicott 
Facility, Village of Endicott, Broome County, N.Y. Modification to 
increase total groundwater system withdrawal by an additional 0.499 
mgd, for a total of 1.509 mgd (30-day average) (Docket No. 20090329).
    14. Project Sponsor and Facility: Keystone Landfill, Inc., Dunmore 
Borough, Lackawanna County, Pa. Modification to increase groundwater 
withdrawal by an additional 0.150 mgd, for a total of 0.160 mgd (30-day 
average) (Docket No. 20080611).
    15. Project Sponsor and Facility: Keystone Landfill, Inc., Dunmore 
Borough, Lackawanna County, Pa. Modification to increase consumptive 
water use by an additional 0.260 mgd, for a total of up to 0.360 mgd 
(30-day average) (Docket No. 20080611).
    16. Project Sponsor: Pine Creek Municipal Authority. Project 
Facility: Wastewater Treatment Plant, Pine Creek Township, Clinton 
County, Pa. Withdrawal of treated wastewater effluent of up to 0.999 
mgd.
    17. Project Sponsor and Facility: Roaring Spring Water-Division of 
Roaring Spring Blank Book (Roaring Spring), Roaring Spring Borough, 
Blair County, Pa. Surface water withdrawal of up to 0.302 mgd (peak 
day).
    18. Project Sponsor and Facility: Roaring Spring Water-Division of 
Roaring Spring Blank Book, Roaring Spring Borough, Blair County, Pa. 
Consumptive water use of up to 0.255 mgd (30-day average).
    19. Project Sponsor and Facility: Southwestern Energy Production 
Company (Blockhouse Creek), Jackson Township, Lycoming County, Pa. 
Surface water withdrawal of up to 0.999 mgd (peak day).
    20. Project Sponsor and Facility: Southwestern Energy Production 
Company (Susquehanna River), Oakland Township, Susquehanna County, Pa. 
Surface water withdrawal of up to 3.000 mgd (peak day).
    21. Project Sponsor and Facility: Southwestern Energy Production 
Company (Tunkhannock Creek), Lenox Township, Susquehanna County, Pa.

[[Page 19054]]

Surface water withdrawal of up to 1.500 mgd (peak day).
    22. Project Sponsor and Facility: SWEPI LP (Cowanesque River--
Egleston), Nelson Township, Tioga County, Pa. Modification to increase 
surface water withdrawal by an additional 0.267 mgd, for a total of 
0.534 mgd (peak day) (Docket No. 20100604).

Project Applications Tabled

    The following project applications were tabled by the Commission:
    1. Project Sponsor and Facility: Aqua Resources, Inc. (Susquehanna 
River), Athens Township, Bradford County, Pa. Application for surface 
water withdrawal of up to 0.900 mgd (peak day).
    2. Project Sponsor and Facility: Empire Kosher Poultry, Inc., 
Walker Township, Juniata County, Pa. Modification to increase total 
groundwater system withdrawal by an additional 0.499 mgd, for a total 
of 1.269 mgd (30-day average) (Docket No. 20030809).
    3. Project Sponsor and Facility: Jo Jo Oil Company, Inc. 
(Tunkhannock Creek), Tunkhannock Township, Wyoming County, Pa. 
Application for surface water withdrawal of up to 0.999 mgd (peak day).
    4. Project Sponsor and Facility: Northwestern Lancaster County 
Authority, Penn Township, Lancaster County, Pa. Application for 
groundwater withdrawal of up to 0.324 mgd (30-day average) from Well 2.
    5. Project Sponsor and Facility: Northwestern Lancaster County 
Authority, Penn Township, Lancaster County, Pa. Application for 
groundwater withdrawal of up to 1.000 mgd (30-day average) from Well 3.
    6. Project Sponsor and Facility: Southwestern Energy Production 
Company (East Branch Tunkhannock Creek), Lenox Township, Susquehanna 
County, Pa. Application for surface water withdrawal of up to 1.500 mgd 
(peak day).
    7. Project Sponsor: Viking Energy of Northumberland, LLC. Project 
Facility: Power Plant, Point Township, Northumberland County, Pa. 
Application for consumptive water use of up to 0.387 mgd (30-day 
average).
    8. Project Sponsor: Viking Energy of Northumberland, LLC. Project 
Facility: Power Plant, Point Township, Northumberland County, Pa. 
Application for groundwater withdrawal of up to 0.172 mgd from Well 1, 
and a total system withdrawal limit of up to 0.391 mgd (30-day 
average).
    9. Project Sponsor: Viking Energy of Northumberland, LLC. Project 
Facility: Power Plant, Point Township, Northumberland County, Pa. 
Application for groundwater withdrawal of up to 0.172 mgd from Well 2, 
and a total system withdrawal limit of up to 0.391 mgd (30-day 
average).
    10. Project Sponsor: Viking Energy of Northumberland, LLC. Project 
Facility: Power Plant, Point Township, Northumberland County, Pa. 
Application for groundwater withdrawal of up to 0.172 mgd from Well 4, 
and a total system withdrawal limit of up to 0.391 mgd (30-day 
average).

Project Applications Denied

    The following project applications were denied by the Commission:
    1. Project Sponsor and Facility: Stanley S. Karp Sr. (Tunkhannock 
Creek), Nicholson Township, Wyoming County, Pa. Application for surface 
water withdrawal of up to 0.510 mgd (peak day).
    2. Project Sponsor and Facility: Water Treatment Solutions, LLC 
(South Mountain Lake), Woodward Township, Lycoming County, Pa. 
Application for surface water withdrawal of up to 0.499 mgd (peak day).

    Authority: Pub. L. 91-575, 84 Stat. 1509 et seq., 18 CFR parts 
806, 807, and 808.

    Dated: March 23, 2012.
Thomas W. Beauduy,
Deputy Executive Director.
[FR Doc. 2012-7528 Filed 3-28-12; 8:45 am]
BILLING CODE 7040-01-P