Virgina Electric and Power Company; Receipt of Request for Action, 12887-12888 [2012-5150]
Download as PDF
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 42 / Friday, March 2, 2012 / Notices
February 6, 2012, and included the
opportunity for restorative rest for the
HRO staff.
The exemption request specifies that
the exemption is not for discretionary
maintenance activities. The exemption
request states that the exemption would
provide for use of whatever plant staff
and resources may be necessary to
respond to a plant emergency and
ensure that the units achieve and
maintain a safe and secure status and
can be safely restarted. The exemption
request also states that maintenance
activities for structures, systems and
components that are significant to
public health and safety will be
performed, if required. The NRC staff
finds the exclusion of discretionary
maintenance from the exemption
request to be consistent with the intent
of the exemption.
In its exemption request, the licensee
committed to maintain the following
guidance in a Millstone site procedure:
• The conditions necessary to
sequester site personnel that are
consistent with the conditions specified
in this exemption request.
• The provisions for ensuring that
personnel who are not performing
duties are provided an opportunity, as
well as accommodations, for restorative
rest.
• The condition for departure from
this exemption, consistent with the Site
Vice President’s (or his designee’s)
determination that adequate staffing is
available to meet the requirements of 10
CFR 26.205(c) and (d).
When the exemption period(s) ends,
the licensee is immediately subject to
the scheduling requirements of 10 CFR
26.205(c) and the work hour/rest break/
days off requirements of 10 CFR
26.205(d), and must ensure that any
individual performing covered work
complies with these requirements. 10
CFR 26.205(d)(3) requires the licensee to
‘‘look back’’ over the calculation period
and count the hours the individual has
worked and the rest breaks and days off
he/she has had, including those that
occurred during the licensee-declared
emergency. Hours worked must be
below the maximum limits and rest
breaks must be above the minimum
requirements in order for the licensee to
allow the individual to perform covered
work. Days off and hours and shifts
worked during the licensee-declared
emergency and the exempted period
before and after the declared emergency
would be counted as usual in the
establishment of the applicable shift
schedule and compliance with the
minimum-days-off requirements.
Granting these exemptions is
consistent with 10 CFR 26.207(d) Plant
VerDate Mar<15>2010
17:01 Mar 01, 2012
Jkt 226001
Emergencies which allows the licensee
to not meet the requirements of 10 CFR
26.205(c) and (d) during declared
emergencies as defined in the licensee’s
emergency plan. The Part 26 Statement
of Considerations, page 17148 states
that, ‘‘[p]lant emergencies are
extraordinary circumstances that may be
most effectively addressed through staff
augmentation that can only be
practically achieved through the use of
work hours in excess of the limits of
§ 26.205(c) and (d).’’ The objective of the
exemption is to ensure that the control
of work hours do not impede a
licensee’s ability to use whatever staff
resources may be necessary to respond
to a plant emergency and ensure that the
plant reaches and maintains a safe and
secure status. The actions described in
the exemption request and submitted
procedures are consistent with the
recommendations in NUREG–1474.
Also consistent with NUREG–1474,
NRC staff expects the licensee would
have completed a reasonable amount of
hurricane preparation prior to the need
to sequester personnel, in order to
minimize personnel exposure to high
winds.
The NRC staff has reviewed the
exemption request from certain work
hour controls during conditions of high
winds and recovery from high wind
conditions. Based on the considerations
discussed above, the NRC staff has
concluded that (1) there is a reasonable
assurance that the health and safety of
the public will not be endangered by the
proposed exemption, (2) such activities
will be consistent with the
Commission’s regulations and guidance,
and (3) the issuance of the exemption
will not be contrary to the common
defense and security or to the health
and safety of the public.
Consistent With Common Defense and
Security
This change has no relation to
security issues. Therefore, the common
defense and security is not impacted by
this exemption.
4.0 Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
26.9, granting an exemption to the
licensee from the requirements in 10
CFR 26.205(c) and (d) during severe
wind events such as tropical storms and
hurricanes and bounded by the entry
and exit conditions of the exemption
request, by allowing Millstone to
sequester individuals to ensure the
plant reaches and maintains a safe and
secure status, is authorized by law and
will not endanger life or property and is
otherwise in the public interest.
PO 00000
Frm 00096
Fmt 4703
Sfmt 4703
12887
Therefore, the Commission hereby
grants DNC an exemption from the
requirements of 10 CFR 26.205(c) and
(d) during periods of severe winds at the
Millstone site.
Pursuant to 10 CFR 51.32, the
Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment as published in the
Federal Register on August 31, 2011 (76
FR 54260).
This exemption is effective upon
issuance.
For the Nuclear Regulatory Commission.
Dated at Rockville, Maryland, this 24th day
of February 2012.
Michele G. Evans,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2012–5148 Filed 3–1–12; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–338 and 50–339; NRC–
2012–0051; License Nos. NPF–4 and
NPF–7]
Virgina Electric and Power Company;
Receipt of Request for Action
Notice is hereby given that by petition
dated September 8, 2011 (Agencywide
Documents Access and Management
System (ADAMS) Accession No.
ML11256A019), as supplemented by
letters dated September 8, 2011
(ADAMS Accession No. ML11334A152),
and October 21, 2011 (ADAMS
Accession No. ML11308A016), Thomas
Saporito (the petitioner) requests that
the U.S. Nuclear Regulatory
Commission (NRC or the Commission)
take action with regard to Virginia
Electric and Power Company’s (the
licensee’s) North Anna Power Station,
Units 1 and 2 (North Anna 1 and 2). The
petitioner requests that the NRC:
(1) Take escalated enforcement action
against the licensee and suspend, or
revoke, the operating licenses for North
Anna 1 and 2;
(2) Issue a notice of violation against
the licensee with a proposed civil
penalty in the amount of 1 million
dollars; and
(3) Issue an order to the licensee
requiring the licensee to keep North
Anna 1 and 2, in a ‘‘cold shutdown’’
mode of operation until such time as a
series of actions described in the
petition are completed.
As the basis for this request, the
petitioner states that:
(1) On August 23, 2011, North Anna
1 and 2, automatically tripped offline as
E:\FR\FM\02MRN1.SGM
02MRN1
tkelley on DSK3SPTVN1PROD with NOTICES
12888
Federal Register / Vol. 77, No. 42 / Friday, March 2, 2012 / Notices
a direct result of ground motion caused
by an earthquake centered in Mineral,
Virginia, approximately 10 miles from
North Anna 1 and 2. The licensee has
not determined the root cause of this
event, nor has it explained why the
reactor tripped on ‘‘negative flux rate’’
rather than on loss of offsite power.
(2) Subsequent to the earthquake, the
licensee initiated various inspection
activities and tests to discover the extent
of damage to the nuclear facility, but
these inspection and testing activities
continue and remain incomplete and
non-validated.
(3) The licensee had set an overly
aggressive schedule for restarting North
Anna 1 and 2 that was based on
economic considerations rather than
safety.
(4) The licensee needs to amend its
licensing documents, including its
licenses and the updated facility
analysis report. As a result of ground
motion experienced at, and damage
sustained to, North Anna 1 and 2, due
to the earthquake of August 23, 2011,
which is greater than the licensee’s
design and safety bases, North Anna 1
and 2, are in an unanalyzed condition
and current licensing documents are
erroneous and incomplete. As a result,
the licensee cannot rely on them to
provide reasonable assurance to the
NRC that these nuclear reactors can be
operated in a safe and reliable manner
to protect public health and safety.
(5) The licensee needs to conduct new
seismic and geological evaluations of
the North Anna 1 and 2, site that are
independent. These evaluations should
ascertain the degree and magnitude of
future earthquake events and address a
‘‘worst case’’ earthquake.
(6) There are numerous issues with
the seismic instrumentation at North
Anna 1 and 2, including lack of free
field instrumentation, issues associated
with conversion of analog data to digital
data, issues with lack of on-site
personnel with sufficient training in
seismic measurements, and potential
skewing of ground motion data due to
the location of the ‘‘scratch plates.’’
(7) Retrofitting of North Anna 1 and
2, is required due to damage to North
Anna 1 and 2, from the earthquake of
August 23, 2011.
(8) There are concerns with the
impact of the August 23, 2011,
earthquake on the North Anna 1 and 2,
Independent Spent Fuel Storage
Installation (ISFSI) including the fact
that 25 casks weighing over 115 tons
were not supposed to shift as much as
4.5 inches during a predicted
earthquake, validation of the integrity of
the seals inside the spent fuel casks,
assessing whether spent nuclear fuel
VerDate Mar<15>2010
17:01 Mar 01, 2012
Jkt 226001
storage facilities could topple or
otherwise sustain significant damage
resulting in a release, and assessing
whether the licensee’s emergency plans
adequately addressed damage to the
ISFSI as a result of a severe earthquake.
(9) The petitioner is concerned that
the licensee cannot be trusted to
communicate reliable information to the
public or the regulator based on the fact
that the licensee in the 1970s failed to
promptly disclose the discovery of
geological information and was
subjected to a monetary fine for the
violation.
The request is being treated pursuant
to Title 10 of the Code of Federal
Regulations (10 CFR) 2.206, ‘‘Requests
for action under this subpart,’’ of the
Commission’s regulations. The request
has been referred to the Director of the
Office of Nuclear Reactor Regulation. As
provided by § 2.206, appropriate action
will be taken on this petition within a
reasonable time. The petitioner met
with the NRR petition review board on
September 29, 2011 (transcript at
ADAMS Accession No. ML11332A046),
and November 7, 2011 (transcript at
ADAMS Accession No. ML113530035),
to discuss the petition. The results of
these discussions were considered in
the PRB’s final recommendation to
accept the petition for review and in
establishing the schedule for the review
of the petition.
A copy of the petition is available for
inspection at the Commission’s Public
Document Room, located at One White
Flint North, Public File Area O1–F21,
11555 Rockville Pike (first floor),
Rockville, Maryland 20852. Publicly
available documents created or received
at the NRC are accessible electronically
through the NRC’s Agencywide
Documents Access and Management
System (ADAMS) in the NRC Library at
https://www.nrc.gov/reading-rm/
adams.html. Persons who do not have
access to ADAMS or who encounter
problems in accessing the documents
located in ADAMS should contact the
NRC PDR Reference staff by telephone
at 1–800–397–4209 or 301–415–4737, or
by email to PDR Resource@nrc.gov
Dated at Rockville, Maryland, this 22nd
day of February, 2012.
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor
Regulation.
[FR Doc. 2012–5150 Filed 3–1–12; 8:45 am]
BILLING CODE 7590–01–P
PO 00000
Frm 00097
Fmt 4703
Sfmt 4703
POSTAL REGULATORY COMMISSION
[Docket No. CP2012–17; Order No. 1261]
International Mail Contract
Postal Regulatory Commission.
Notice.
AGENCY:
ACTION:
The Commission is noticing a
recently-filed Postal Service request to
enter into an additional International
Business Reply Service contract. This
document invites public comments on
the request and addresses several
related procedural steps.
ADDRESSES: Submit comments
electronically by accessing the ‘‘Filing
Online’’ link in the banner at the top of
the Commission’s Web site (https://www.
prc.gov) or by directly accessing the
Commission’s Filing Online system at
https://www.prc.gov/prc-pages/filingonline/login.aspx. Commenters who
cannot submit their views electronically
should contact the person identified in
the FOR FURTHER INFORMATION CONTACT
section as the source for case-related
information for advice on alternatives to
electronic filing.
DATES: Comments are due: March 6,
2012.
SUMMARY:
FOR FURTHER INFORMATION CONTACT:
Stephen L. Sharfman, General Counsel,
at 202–789–6820 (case-related
information) or DocketAdmins@prc.gov
(electronic filing assistance).
SUPPLEMENTARY INFORMATION:
Table of Contents
I. Introduction
II. Notice of Filing
III. Ordering Paragraphs
I. Introduction
On February 24, 2012, the Postal
Service filed a notice announcing that it
has entered into an additional
International Business Reply Service
(IBRS) contract.1 The Postal Service
asserts that the instant contract is
functionally equivalent to the IBRS 3
baseline contract originally filed in
Docket Nos. MC2011–21 and CP2011–
59 and supported by Governors’
Decision No. 08–24 (IBRS 3 baseline
contract). Id., Attachment 3. The notice
explains that Order No. 684, which
established IBRS Competitive Contracts
3 as a product, also authorized
functionally equivalent agreements to be
included within the product, provided
that they meet the requirements of 39
U.S.C. 3633. Id. at 1–2.
1 Notice of the United States Postal Service Filing
of a Functionally Equivalent International Business
Reply Service Competitive Contract 3 Negotiated
Service Agreement, February 24, 2012 (notice).
E:\FR\FM\02MRN1.SGM
02MRN1
Agencies
[Federal Register Volume 77, Number 42 (Friday, March 2, 2012)]
[Notices]
[Pages 12887-12888]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-5150]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-338 and 50-339; NRC-2012-0051; License Nos. NPF-4 and
NPF-7]
Virgina Electric and Power Company; Receipt of Request for Action
Notice is hereby given that by petition dated September 8, 2011
(Agencywide Documents Access and Management System (ADAMS) Accession
No. ML11256A019), as supplemented by letters dated September 8, 2011
(ADAMS Accession No. ML11334A152), and October 21, 2011 (ADAMS
Accession No. ML11308A016), Thomas Saporito (the petitioner) requests
that the U.S. Nuclear Regulatory Commission (NRC or the Commission)
take action with regard to Virginia Electric and Power Company's (the
licensee's) North Anna Power Station, Units 1 and 2 (North Anna 1 and
2). The petitioner requests that the NRC:
(1) Take escalated enforcement action against the licensee and
suspend, or revoke, the operating licenses for North Anna 1 and 2;
(2) Issue a notice of violation against the licensee with a
proposed civil penalty in the amount of 1 million dollars; and
(3) Issue an order to the licensee requiring the licensee to keep
North Anna 1 and 2, in a ``cold shutdown'' mode of operation until such
time as a series of actions described in the petition are completed.
As the basis for this request, the petitioner states that:
(1) On August 23, 2011, North Anna 1 and 2, automatically tripped
offline as
[[Page 12888]]
a direct result of ground motion caused by an earthquake centered in
Mineral, Virginia, approximately 10 miles from North Anna 1 and 2. The
licensee has not determined the root cause of this event, nor has it
explained why the reactor tripped on ``negative flux rate'' rather than
on loss of offsite power.
(2) Subsequent to the earthquake, the licensee initiated various
inspection activities and tests to discover the extent of damage to the
nuclear facility, but these inspection and testing activities continue
and remain incomplete and non-validated.
(3) The licensee had set an overly aggressive schedule for
restarting North Anna 1 and 2 that was based on economic considerations
rather than safety.
(4) The licensee needs to amend its licensing documents, including
its licenses and the updated facility analysis report. As a result of
ground motion experienced at, and damage sustained to, North Anna 1 and
2, due to the earthquake of August 23, 2011, which is greater than the
licensee's design and safety bases, North Anna 1 and 2, are in an
unanalyzed condition and current licensing documents are erroneous and
incomplete. As a result, the licensee cannot rely on them to provide
reasonable assurance to the NRC that these nuclear reactors can be
operated in a safe and reliable manner to protect public health and
safety.
(5) The licensee needs to conduct new seismic and geological
evaluations of the North Anna 1 and 2, site that are independent. These
evaluations should ascertain the degree and magnitude of future
earthquake events and address a ``worst case'' earthquake.
(6) There are numerous issues with the seismic instrumentation at
North Anna 1 and 2, including lack of free field instrumentation,
issues associated with conversion of analog data to digital data,
issues with lack of on-site personnel with sufficient training in
seismic measurements, and potential skewing of ground motion data due
to the location of the ``scratch plates.''
(7) Retrofitting of North Anna 1 and 2, is required due to damage
to North Anna 1 and 2, from the earthquake of August 23, 2011.
(8) There are concerns with the impact of the August 23, 2011,
earthquake on the North Anna 1 and 2, Independent Spent Fuel Storage
Installation (ISFSI) including the fact that 25 casks weighing over 115
tons were not supposed to shift as much as 4.5 inches during a
predicted earthquake, validation of the integrity of the seals inside
the spent fuel casks, assessing whether spent nuclear fuel storage
facilities could topple or otherwise sustain significant damage
resulting in a release, and assessing whether the licensee's emergency
plans adequately addressed damage to the ISFSI as a result of a severe
earthquake.
(9) The petitioner is concerned that the licensee cannot be trusted
to communicate reliable information to the public or the regulator
based on the fact that the licensee in the 1970s failed to promptly
disclose the discovery of geological information and was subjected to a
monetary fine for the violation.
The request is being treated pursuant to Title 10 of the Code of
Federal Regulations (10 CFR) 2.206, ``Requests for action under this
subpart,'' of the Commission's regulations. The request has been
referred to the Director of the Office of Nuclear Reactor Regulation.
As provided by Sec. 2.206, appropriate action will be taken on this
petition within a reasonable time. The petitioner met with the NRR
petition review board on September 29, 2011 (transcript at ADAMS
Accession No. ML11332A046), and November 7, 2011 (transcript at ADAMS
Accession No. ML113530035), to discuss the petition. The results of
these discussions were considered in the PRB's final recommendation to
accept the petition for review and in establishing the schedule for the
review of the petition.
A copy of the petition is available for inspection at the
Commission's Public Document Room, located at One White Flint North,
Public File Area O1-F21, 11555 Rockville Pike (first floor), Rockville,
Maryland 20852. Publicly available documents created or received at the
NRC are accessible electronically through the NRC's Agencywide
Documents Access and Management System (ADAMS) in the NRC Library at
https://www.nrc.gov/reading-rm/adams.html. Persons who do not have
access to ADAMS or who encounter problems in accessing the documents
located in ADAMS should contact the NRC PDR Reference staff by
telephone at 1-800-397-4209 or 301-415-4737, or by email to PDR
Resource@nrc.gov
Dated at Rockville, Maryland, this 22nd day of February, 2012.
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor Regulation.
[FR Doc. 2012-5150 Filed 3-1-12; 8:45 am]
BILLING CODE 7590-01-P