Drawbridge Operation Regulation; Curtis Creek, Baltimore, MD, 12476 [2012-4929]

Download as PDF 12476 Federal Register / Vol. 77, No. 41 / Thursday, March 1, 2012 / Rules and Regulations closure periods for the bridge so that vessels can arrange their transits to minimize any impacts caused by the temporary deviation. In accordance with 33 CFR 117.35(e), the drawbridge must return to its original operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. Dated: February 10, 2012. Waverly W. Gregory, Jr., Bridge Program Manager, Fifth Coast Guard District. [FR Doc. 2012–4918 Filed 2–29–12; 8:45 am] BILLING CODE 9110–04–P DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [Docket No. USCG–2012–0012] RIN 1625–AA09 Drawbridge Operation Regulation; Curtis Creek, Baltimore, MD Coast Guard, DHS. Notice of temporary deviation from regulations. AGENCY: ACTION: The Coast Guard has issued a temporary deviation from the operating schedule that governs the I–695 Bridge, across Curtis Creek, mile 1.0, at Baltimore, MD. This deviation allows the bridge to operate on a restricted schedule including six (6) multi-day closures to complete structural repairs. DATES: This deviation is effective from 6 a.m. on March 1, 2012, to 11:59 p.m. on July 17, 2012. The deviation has been enforced with actual notice since February 10, 2012. ADDRESSES: Documents mentioned in this preamble as being available in the docket are part of docket USCG–2012– 0012 and are available online by going to www.regulations.gov, inserting USCG–2012–0012 in the ‘‘Keyword’’ box, and clicking ‘‘Search.’’ This material is also available for inspection or copying at the Docket Management Facility (M–30), U.S. Department of Transportation, West Building Ground Floor, Room W12–140, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: If you have questions on this rule, call Bill H. Brazier, Bridge Management Specialist, Fifth Coast Guard District; tkelley on DSK3SPTVN1PROD with RULES SUMMARY: VerDate Mar<15>2010 16:41 Feb 29, 2012 Jkt 226001 telephone 757–398–6422, email Bill.H.Brazier@uscg.mil. If you have questions on viewing the docket, call Renee V. Wright, Program Manager, Docket Operations, telephone 202–366– 9826. SUPPLEMENTARY INFORMATION: The Maryland Transportation Authority, who owns and operates this double-leaf bascule drawbridge, has requested a temporary deviation from the current operating schedule set out in 33 CFR 117.557 which requires the bridge to open on signal if at least a one-hour advance notice is given to the Maryland Transit Authority in Baltimore. The I–695 Bridge has a vertical clearance in the closed position of 58 feet, above mean high water. Under this temporary deviation to facilitate the replacement of the grid deck, floor beams and stringers, the drawbridge will be closed for six (6) multi-day periods from 7 a.m. on February 10, 2012, through 7 a.m. May 17, 2012, as is more specifically set out below. During these closure periods no vessel openings will be provided. At all others times, vessel openings will be provided on signal if at least 24 hours advance notice is given. This temporary deviation will not significantly disrupt vessel traffic because mariners can plan their trips to pass through the bridge between the closure periods when the bridge will be fully operational and vessels that can pass under the bridge without a bridge opening may do so at all times. There is no alternate route for vessels and the bridge will not be able to open in the event of an emergency during the stated closure periods. In accordance with 33 CFR 117.35(e), the drawbridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. During this deviation, the bridge will operate as follows: (1) From 6 a.m. on February 10 through 11:59 p.m. on July 17, 2012, will open on signal if at least 24 hours advance notice is given, except (2) The bridge need not open during the following specified closure periods: (i) From 7 a.m. on February 10, 2012 until 7 a.m. on February 15, 2012; (ii) From 7 a.m. on February 18, 2012 until 7 a.m. on February 24, 2012; (iii) From 7 a.m. on February 28, 2012 until 7 a.m. on March 10, 2012; (iv) From 7 a.m. on April 12 until 7 a.m. on April 19, 2012; (v) From 7 a.m. on April 28, 2012 until 7 a.m. on May 4, 2012; and (vi) From 7 a.m. on May 7, 2012 until 7 a.m. on May 17, 2012. PO 00000 Frm 00040 Fmt 4700 Sfmt 4700 Dated: January 30, 2012. William D. Lee, Rear Admiral, U.S. Coast Guard, Commander, Fifth Coast Guard District. [FR Doc. 2012–4929 Filed 2–29–12; 8:45 am] BILLING CODE 9110–04–P DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [Docket No. USCG–2012–0108] Drawbridge Operation Regulation; Lake Pontchartrain, Between Jefferson and St. Tammany Parishes, LA Coast Guard, DHS. Notice of temporary deviation from regulations. AGENCY: ACTION: The Commander, Eighth Coast Guard District has issued a temporary deviation from the regulations governing the operation of the north bascule span of the Greater New Orleans Expressway Commission Causeway across Lake Pontchartrain between Metairie, Jefferson Parish and Mandeville, St. Tammany Parish, Louisiana. This deviation allows the draws of the bridge to remain closed to navigation for four days to allow for the repair and maintenance of mechanical parts of the bascule. DATES: This deviation is effective from 6 a.m. on Tuesday, March 13, 2012 until 6 p.m. on Friday, March 16, 2012. ADDRESSES: Documents mentioned in this preamble as being available in the docket are part of docket USCG–2012– 0108 and are available online by going to https://www.regulations.gov, inserting USCG–2012–0108 in the ‘‘Keyword’’ box and then clicking ‘‘Search.’’ They are also available for inspection or copying at the Docket Management Facility (M–30), U.S. Department of Transportation, West Building Ground Floor, Room W12–140, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: If you have questions on this rule, call or email Mr. Jim Wetherington, Bridge Specialist, Eighth Coast Guard District Bridge Branch, U.S. Coast Guard; telephone 504–671–2128 or email james.r.wetherington@uscg.mil. If you have questions on viewing the docket, call Renee V. Wright, Program Manager, Docket Operations, telephone 202–366– 9826. SUMMARY: E:\FR\FM\01MRR1.SGM 01MRR1

Agencies

[Federal Register Volume 77, Number 41 (Thursday, March 1, 2012)]
[Rules and Regulations]
[Page 12476]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-4929]


-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2012-0012]
RIN 1625-AA09


Drawbridge Operation Regulation; Curtis Creek, Baltimore, MD

AGENCY: Coast Guard, DHS.

ACTION: Notice of temporary deviation from regulations.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the I-695 Bridge, across Curtis Creek, 
mile 1.0, at Baltimore, MD. This deviation allows the bridge to operate 
on a restricted schedule including six (6) multi-day closures to 
complete structural repairs.

DATES: This deviation is effective from 6 a.m. on March 1, 2012, to 
11:59 p.m. on July 17, 2012. The deviation has been enforced with 
actual notice since February 10, 2012.

ADDRESSES: Documents mentioned in this preamble as being available in 
the docket are part of docket USCG-2012-0012 and are available online 
by going to www.regulations.gov, inserting USCG-2012-0012 in the 
``Keyword'' box, and clicking ``Search.'' This material is also 
available for inspection or copying at the Docket Management Facility 
(M-30), U.S. Department of Transportation, West Building Ground Floor, 
Room W12-140, 1200 New Jersey Avenue SE., Washington, DC 20590, between 
9 a.m. and 5 p.m., Monday through Friday, except Federal holidays.

FOR FURTHER INFORMATION CONTACT: If you have questions on this rule, 
call Bill H. Brazier, Bridge Management Specialist, Fifth Coast Guard 
District; telephone 757-398-6422, email Bill.H.Brazier@uscg.mil. If you 
have questions on viewing the docket, call Renee V. Wright, Program 
Manager, Docket Operations, telephone 202-366-9826.

SUPPLEMENTARY INFORMATION: The Maryland Transportation Authority, who 
owns and operates this double-leaf bascule drawbridge, has requested a 
temporary deviation from the current operating schedule set out in 33 
CFR 117.557 which requires the bridge to open on signal if at least a 
one-hour advance notice is given to the Maryland Transit Authority in 
Baltimore.
    The I-695 Bridge has a vertical clearance in the closed position of 
58 feet, above mean high water.
    Under this temporary deviation to facilitate the replacement of the 
grid deck, floor beams and stringers, the drawbridge will be closed for 
six (6) multi-day periods from 7 a.m. on February 10, 2012, through 7 
a.m. May 17, 2012, as is more specifically set out below. During these 
closure periods no vessel openings will be provided. At all others 
times, vessel openings will be provided on signal if at least 24 hours 
advance notice is given.
    This temporary deviation will not significantly disrupt vessel 
traffic because mariners can plan their trips to pass through the 
bridge between the closure periods when the bridge will be fully 
operational and vessels that can pass under the bridge without a bridge 
opening may do so at all times. There is no alternate route for vessels 
and the bridge will not be able to open in the event of an emergency 
during the stated closure periods.
    In accordance with 33 CFR 117.35(e), the drawbridge must return to 
its regular operating schedule immediately at the end of the designated 
time period. This deviation from the operating regulations is 
authorized under 33 CFR 117.35.
    During this deviation, the bridge will operate as follows:
    (1) From 6 a.m. on February 10 through 11:59 p.m. on July 17, 2012, 
will open on signal if at least 24 hours advance notice is given, 
except
    (2) The bridge need not open during the following specified closure 
periods:
    (i) From 7 a.m. on February 10, 2012 until 7 a.m. on February 15, 
2012;
    (ii) From 7 a.m. on February 18, 2012 until 7 a.m. on February 24, 
2012;
    (iii) From 7 a.m. on February 28, 2012 until 7 a.m. on March 10, 
2012;
    (iv) From 7 a.m. on April 12 until 7 a.m. on April 19, 2012;
    (v) From 7 a.m. on April 28, 2012 until 7 a.m. on May 4, 2012; and
    (vi) From 7 a.m. on May 7, 2012 until 7 a.m. on May 17, 2012.

    Dated: January 30, 2012.
William D. Lee,
Rear Admiral, U.S. Coast Guard, Commander, Fifth Coast Guard District.
[FR Doc. 2012-4929 Filed 2-29-12; 8:45 am]