Bluewater Gas Storage, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed St. Clair River Crossing Replacement Project, Request for Comments on Environmental Issues, and Notice of Onsite Environmental Review, 11527-11529 [2012-4405]
Download as PDF
Federal Register / Vol. 77, No. 38 / Monday, February 27, 2012 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–51–000]
srobinson on DSK4SPTVN1PROD with NOTICES
Bluewater Gas Storage, LLC; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed St. Clair
River Crossing Replacement Project,
Request for Comments on
Environmental Issues, and Notice of
Onsite Environmental Review
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Bluewater Gas Storage, LLC
(Bluewater) St. Clair River Crossing
Replacement Project (Project) involving
the construction of the United States
portion of the U.S.-Canada cross-border
pipeline facilities from St. Clair County,
Michigan to the international boundary
within the St. Clair River for the importexport of up to 300 million cubic feet
per day (MMCf/d) of natural gas. This
EA will be used by the Commission in
its decision-making process to
determine whether the project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
project scoping period will close on
March 17, 2012. Further details on how
to submit written comments are
provided in the Public Participation
section of this notice.
The office of Energy Projects staff will
conduct an onsite environmental review
of the project area to gather data for its
environmental analysis of the proposed
project. Viewing of the project area is
anticipated to be from Bluewater’s
property along River Road. Those
attending should meet at the following
location and time: FERC Onsite
Environmental Review, St. Clair River
Crossing Replacement Project, February
28, 2012 at 9 a.m. Eastern Time, 1060
River Road, Marysville, Michigan
48040–1510.
This notice is being sent to the
Commission’s current environmental
mailing list for this project as described
under the Environmental Mailing List
Section of this notice. The notice is also
being sent to those landowners outside
of the immediate construction work
areas who could potentially be affected
during construction from secondary,
short-term construction-related noise
VerDate Mar<15>2010
18:10 Feb 24, 2012
Jkt 226001
and/or visual impacts. State and local
government representatives are asked to
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, and you are contacted by a
representative of Bluewater about the
acquisition of an easement to construct,
operate, and maintain the proposed
facilities, please note that the company
would seek to negotiate a mutually
acceptable agreement. However, if the
project is approved by the Commission,
that approval conveys with it the right
of eminent domain. Therefore, if
easement negotiations fail to produce an
agreement, the company could initiate
condemnation proceedings where
compensation would be determined in
accordance with state law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ was attached to the project
notice Bluewater provided to
landowners. This fact sheet addresses a
number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Summary of the Proposed Project
Bluewater proposes to construct and
operate a new natural gas pipeline
directionally drilled underneath the St.
Clair River from Bluewater’s header
system in St. Clair County, Michigan to
the International Border. The proposed
Project would consist of:
• The construction and operation of
approximately 1,500 feet of 20-inchdiameter pipeline directionally drilled
underneath the St. Clair River to the
international border (Cross Border
Facilities) within the St. Clair River and
construction of approximately 345 feet
of 20-inch-diameter replacement
pipeline facilities 1 to connect the CrossBorder Facilities to Bluewater’s existing
30-mile, 20-inch-diameter pipeline
header system in Marysville, St. Clair
County, Michigan;
• A Presidential Permit authorizing
Bluewater to install, construct, own,
operate and maintain the U.S. portion of
the cross-border facilities, pursuant to
Part 153, Subpart C of the Commission’s
regulations, and Executive Order No.
10,485, as amended by Executive Order
No. 12,038;
• Vacating an existing Section 3
Authorization and Presidential Permit
1 Requested
under Bluewater’s existing National
Gas Act Section 7 Blanket Certificate.
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
11527
with respect to leased facilities with
Nova Chemicals;
• Remove approximately 245 feet of
20-inch-diameter pipeline and 30 feet of
12-inch-diameter pipeline; 2 and
• Modify an existing meter station to
increase its measurement capacity.2
The general location of the Project
facilities is shown in appendix 1.
Land Requirements for Construction
Construction of the Project pipeline
facilities would be conducted by the
horizontal directional drilling method
(HDD) from a location approximately
425 feet on the U.S. inland side of the
St. Clair River (entry point) to the U.S.Canada international border within the
river (Appendix 1). The Project would
permanently disturb about 0.95 acres of
land.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 3 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. All comments
received will be considered during the
preparation of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• Land use;
• Water resources, fisheries, and
wetlands;
• Cultural resources;
• Vegetation and wildlife;
• Air quality and noise;
• Endangered and threatened species;
and
• Public safety.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be presented in the EA. The
2 Ibid.
3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
E:\FR\FM\27FEN1.SGM
27FEN1
11528
Federal Register / Vol. 77, No. 38 / Monday, February 27, 2012 / Notices
EA will be placed in the public record
and, depending on the comments
received during the scoping process,
may be published and distributed to the
public. A comment period will be
allotted if the EA is published for
review. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section of this notice.
With this notice, we are asking
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to formally
cooperate with us in the preparation of
the EA. These agencies may choose to
participate once they have evaluated the
proposal relative to their
responsibilities. Agencies that would
like to request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
srobinson on DSK4SPTVN1PROD with NOTICES
Consultations Under Section 106 of the
Natural Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the Natural Historic Preservation
Act, we are using this notice to initiate
consultation with applicable State
Historic Preservation Office(s) (SHPO),
and to solicit their views and those of
other government agencies, interested
Indian tribes, and the public on the
project’s potential effects on historic
properties.4 We will define the projectspecific Area of Potential Effects (APE)
in consultation with the SHPO(s) as the
project is further developed. On natural
gas facility projects, the APE at a
minimum encompasses all areas subject
to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA would document our findings
on the potential project impacts on
historic properties and summarize the
status of consultations under section
106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the Natural
Register of Historic Places.
VerDate Mar<15>2010
18:10 Feb 24, 2012
Jkt 226001
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that they will be received in
Washington, DC on or before March 17,
2012.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number (CP12–51–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s Web site at www.ferc.gov
under the link to Documents and
Filings. An eComment is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at www.ferc.gov
under the link to Documents and
Filings. With eFiling, you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing’’; or
(3) You may file a paper copy of your
comments at the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Room 1A, Washington,
DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials; Native
American Tribes; environmental and
public interest groups; other interested
parties; and local libraries and
newspapers. This list also includes all
affected landowners (as defined in the
Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. In this notice
we have also included landowners that
could be inadvertently affected by
construction noise or visual impacts.
We will update the environmental
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
mailing list as the analysis proceeds to
ensure that we send the information
related to this environmental review to
all individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket number
field (i.e., CP12–51). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
E:\FR\FM\27FEN1.SGM
27FEN1
Federal Register / Vol. 77, No. 38 / Monday, February 27, 2012 / Notices
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on March 15, 2012.
EventCalendar/EventsList.aspx along
with other related information.
Dated: February 16, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–4405 Filed 2–24–12; 8:45 am]
BILLING CODE 6717–01–P
Dated: February 16, 2012.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[FR Doc. 2012–4407 Filed 2–24–12; 8:45 am]
BILLING CODE 6717–01–P
Louisville Gas and Electric Company;
Kentucky Utilities Company; Notice of
Petition for Declaratory Order
srobinson on DSK4SPTVN1PROD with NOTICES
[Docket No. EL12–27–000]
DEPARTMENT OF ENERGY
Take notice that on February 14, 2012,
pursuant to Rule 207 of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.207, Louisville
Gas and Electric Company and
Kentucky Utilities Company, filed a
Petition for Declaratory Order,
requesting that the Commission find
that the payment of dividends from
equity accounts that represent adjusted
retained earnings will not violate
section 305(a) of the Federal Power Act,
16 U.S.C. 825d.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
VerDate Mar<15>2010
18:10 Feb 24, 2012
Jkt 226001
Federal Energy Regulatory
Commission
[Project No. 14356–000]
Nushagak Electric and Telephone
Cooperative, Inc.; Notice of Preliminary
Permit Application Accepted for Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
On January 25, 2012, the Nushagak
Electric and Telephone Cooperative,
Inc. filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Dillingham Area Hydroelectric Project
(Dillingham Project or project) to be
located on Elva Creek and Grant River,
near the town of Dillingham, Bristol Bay
Borough, Alaska. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project has two
developments. The total installed
capacity of both developments would be
3.2 megawatts (MW) and the total
estimated annual generation of the
Dillingham Project would be 20.057
gigawatt-hours (GWh).
Lake Elva Development
The proposed project would consist of
the following: (1) A 50-foot-long, 10foot-high rock-fill diversion dam
constructed on the outlet of Lake Elva;
(2) a 4,100-foot-long, 4-foot-diameter
lake tap pipeline; (3) a 3,200-foot-long,
3- to 3.5-foot-diameter penstock leading
from the lake tap pipeline to the
powerhouse; (4) a powerhouse
containing two 0.75–MW Francis
turbine/generator units; (5) a 40-foot-
PO 00000
Frm 00050
Fmt 4703
Sfmt 4703
11529
long, 20-foot-wide tailrace discharging
flows from the powerhouse into Elva
Creek; (6) a 49-mile-long, 34.5-kilovolt
(kV) transmission line extending from
the project powerhouse to a new
substation approximately 5 miles north
of Dillingham; (7) an approximately 3mile-long access road; and (8)
appurtenant facilities. The estimated
annual generation of the Lake Elva
development would be 7.927 GWh.
Grant Lake Development
The proposed project would consist of
the following: (1) A 900-foot-long, 20foot-high rock-fill diversion dam
constructed on the outlet of Grant Lake
(main dam); (2) a 1-mile-long, 20-foothigh diversion canal excavated
approximately 1 mile north of the main
dam; (3) a 300-foot-long, 20-foot-high
rock-fill diversion dam constructed at
the terminus of the diversion canal; (4)
an intake structure on the diversion dam
leading to a 5,000-foot-long, 5-footdiameter pipeline; (5) a 3,100-foot-long,
4-foot-diameter penstock leading from
the pipeline to the powerhouse; (6) a
powerhouse containing a 1.7–MW
Turgo turbine/generator unit; (7) a 40foot-long, 20-foot-wide tailrace
discharging flows from the powerhouse
into Grant River; (8) a 46-mile-long,
34.5-kV transmission line extending
from the project powerhouse to a new
substation approximately 5 miles north
of Dillingham; (9) an approximately 2.5mile-long access road; and (10)
appurtenant facilities. The estimated
annual generation of the Grant Lake
development would be 12.13 GWh.
Applicant Contact: Mr. Mike Megli,
CEO/General Manager, Nushagak
Electric & Telephone Cooperative, Inc.,
557 Kenny Wren Road, P.O. Box 350,
Dillingham, AK 99576; phone: (907)
842–6315.
FERC Contact: Jennifer Harper;
phone: (202) 502–6136.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
E:\FR\FM\27FEN1.SGM
27FEN1
Agencies
[Federal Register Volume 77, Number 38 (Monday, February 27, 2012)]
[Notices]
[Pages 11527-11529]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-4405]
[[Page 11527]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP12-51-000]
Bluewater Gas Storage, LLC; Notice of Intent To Prepare an
Environmental Assessment for the Proposed St. Clair River Crossing
Replacement Project, Request for Comments on Environmental Issues, and
Notice of Onsite Environmental Review
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Bluewater Gas Storage, LLC
(Bluewater) St. Clair River Crossing Replacement Project (Project)
involving the construction of the United States portion of the U.S.-
Canada cross-border pipeline facilities from St. Clair County, Michigan
to the international boundary within the St. Clair River for the
import-export of up to 300 million cubic feet per day (MMCf/d) of
natural gas. This EA will be used by the Commission in its decision-
making process to determine whether the project is in the public
convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. Your input will help the Commission staff
determine what issues need to be evaluated in the EA. Please note that
the project scoping period will close on March 17, 2012. Further
details on how to submit written comments are provided in the Public
Participation section of this notice.
The office of Energy Projects staff will conduct an onsite
environmental review of the project area to gather data for its
environmental analysis of the proposed project. Viewing of the project
area is anticipated to be from Bluewater's property along River Road.
Those attending should meet at the following location and time: FERC
Onsite Environmental Review, St. Clair River Crossing Replacement
Project, February 28, 2012 at 9 a.m. Eastern Time, 1060 River Road,
Marysville, Michigan 48040-1510.
This notice is being sent to the Commission's current environmental
mailing list for this project as described under the Environmental
Mailing List Section of this notice. The notice is also being sent to
those landowners outside of the immediate construction work areas who
could potentially be affected during construction from secondary,
short-term construction-related noise and/or visual impacts. State and
local government representatives are asked to notify their constituents
of this proposed project and encourage them to comment on their areas
of concern.
If you are a landowner receiving this notice, and you are contacted
by a representative of Bluewater about the acquisition of an easement
to construct, operate, and maintain the proposed facilities, please
note that the company would seek to negotiate a mutually acceptable
agreement. However, if the project is approved by the Commission, that
approval conveys with it the right of eminent domain. Therefore, if
easement negotiations fail to produce an agreement, the company could
initiate condemnation proceedings where compensation would be
determined in accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' was attached to the
project notice Bluewater provided to landowners. This fact sheet
addresses a number of typically-asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
It is also available for viewing on the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
Bluewater proposes to construct and operate a new natural gas
pipeline directionally drilled underneath the St. Clair River from
Bluewater's header system in St. Clair County, Michigan to the
International Border. The proposed Project would consist of:
The construction and operation of approximately 1,500 feet
of 20-inch-diameter pipeline directionally drilled underneath the St.
Clair River to the international border (Cross Border Facilities)
within the St. Clair River and construction of approximately 345 feet
of 20-inch-diameter replacement pipeline facilities \1\ to connect the
Cross-Border Facilities to Bluewater's existing 30-mile, 20-inch-
diameter pipeline header system in Marysville, St. Clair County,
Michigan;
---------------------------------------------------------------------------
\1\ Requested under Bluewater's existing National Gas Act
Section 7 Blanket Certificate.
---------------------------------------------------------------------------
A Presidential Permit authorizing Bluewater to install,
construct, own, operate and maintain the U.S. portion of the cross-
border facilities, pursuant to Part 153, Subpart C of the Commission's
regulations, and Executive Order No. 10,485, as amended by Executive
Order No. 12,038;
Vacating an existing Section 3 Authorization and
Presidential Permit with respect to leased facilities with Nova
Chemicals;
Remove approximately 245 feet of 20-inch-diameter pipeline
and 30 feet of 12-inch-diameter pipeline; \2\ and
---------------------------------------------------------------------------
\2\ Ibid.
---------------------------------------------------------------------------
Modify an existing meter station to increase its
measurement capacity.\2\
The general location of the Project facilities is shown in appendix
1.
Land Requirements for Construction
Construction of the Project pipeline facilities would be conducted
by the horizontal directional drilling method (HDD) from a location
approximately 425 feet on the U.S. inland side of the St. Clair River
(entry point) to the U.S.-Canada international border within the river
(Appendix 1). The Project would permanently disturb about 0.95 acres of
land.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\3\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. All comments
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------
\3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
Land use;
Water resources, fisheries, and wetlands;
Cultural resources;
Vegetation and wildlife;
Air quality and noise;
Endangered and threatened species; and
Public safety.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
Our independent analysis of the issues will be presented in the EA.
The
[[Page 11528]]
EA will be placed in the public record and, depending on the comments
received during the scoping process, may be published and distributed
to the public. A comment period will be allotted if the EA is published
for review. We will consider all comments on the EA before we make our
recommendations to the Commission. To ensure your comments are
considered, please carefully follow the instructions in the Public
Participation section of this notice.
With this notice, we are asking agencies with jurisdiction and/or
special expertise with respect to environmental issues to formally
cooperate with us in the preparation of the EA. These agencies may
choose to participate once they have evaluated the proposal relative to
their responsibilities. Agencies that would like to request cooperating
agency status should follow the instructions for filing comments
provided under the Public Participation section of this notice.
Consultations Under Section 106 of the Natural Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the Natural Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Office(s) (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO(s) as the project
is further developed. On natural gas facility projects, the APE at a
minimum encompasses all areas subject to ground disturbance (examples
include construction right-of-way, contractor/pipe storage yards,
compressor stations, and access roads). Our EA would document our
findings on the potential project impacts on historic properties and
summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the Natural Register of Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that they will be received in Washington, DC on or before March 17,
2012.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP12-51-000) with your submission.
The Commission encourages electronic filing of comments and has expert
eFiling staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's Web site at www.ferc.gov
under the link to Documents and Filings. An eComment is an easy method
for interested persons to submit brief, text-only comments on a
project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at www.ferc.gov
under the link to Documents and Filings. With eFiling, you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making. A comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You may file a paper copy of your comments at the following
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room 1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials; Native
American Tribes; environmental and public interest groups; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. In this notice we have also included
landowners that could be inadvertently affected by construction noise
or visual impacts. We will update the environmental mailing list as the
analysis proceeds to ensure that we send the information related to
this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket number field (i.e., CP12-
51). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/
[[Page 11529]]
EventCalendar/EventsList.aspx along with other related information.
Dated: February 16, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-4405 Filed 2-24-12; 8:45 am]
BILLING CODE 6717-01-P