Agency Information Collection Activities: Emergency Clearance Submission for the Office of Management and Budget (OMB) Review; Comment Request, 11164-11165 [2012-4360]
Download as PDF
srobinson on DSK4SPTVN1PROD with NOTICES
11164
Federal Register / Vol. 77, No. 37 / Friday, February 24, 2012 / Notices
approach was considered the best
approach to enhance safety in the event
one (or both) fitted anchors are lost in
an emergency situation. Use of superior
holding power anchors was
subsequently approved by ABS as long
as the anchor was sufficiently tested,
proven, and held an ABS class
certificate. ABS allows up to a 25
percent reduction in weight (4,500 lbs
each) for a total weight savings of over
a ton.
The shipyard’s market research
included an ABS web based data search
for superior holding power anchors.
Approximately forty three (43)
companies world-wide were identified
that manufacture ABS approved anchors
of superior holding anchors. Of these,
only two (2) were U.S. manufacturers.
Neither company produced an anchor of
the correct size that will fit in the
ARRV’s anchor pocket. The pocket
cannot be made larger because of the
specialized hull shape of the icebreaking bow as described above.
The project’s conclusion is that there
are no U.S. manufacturers who produce
suitable superior holding power
balanced anchors that meet all of the
ARRV requirements, so an exemption
from the Buy American requirements is
necessary.
In the absence of a domestic supplier
that could provide requirementscompliant superior holding power
anchors, UAF requested that NSF issue
a Section 1605 exemption determination
with respect to the purchase of foreignsupplied, requirements-compliant
superior holding power balanced
anchors, so that the vessel will meet the
specific design and technical
requirements that, as explained above,
are necessary for this vessel to be able
to perform its mission successfully.
Furthermore, the shipyard’s market
research indicated that superior holding
power balanced anchors compliant with
the ARRV’s technical specifications and
requirements are commercially available
from foreign vendors within their
standard product lines.
NSF’s Division of Acquisition and
Cooperative Support (DACS) and other
NSF program staff reviewed the UAF
exemption request submittal, found that
it was complete, and determined that
sufficient technical information was
provided in order for NSF to evaluate
the exemption request and to conclude
that an exemption is needed and should
be granted.
III. Exemption
On February 15, 2012, based on the
finding that no domestically produced
superior holding power balanced
anchors met all of the ARRV’s technical
VerDate Mar<15>2010
18:34 Feb 23, 2012
Jkt 226001
specifications and requirements and
pursuant to section 1605(b), the NSF
Chief Financial Officer, in accordance
with a delegation order from the
Director of the agency signed on May
27, 2010, granted a limited project
exemption of the Recovery Act’s Buy
American requirements with respect to
the procurement of superior holding
power balanced anchors.
Dated: February 16, 2012.
Lawrence Rudolph,
General Counsel.
[FR Doc. 2012–4233 Filed 2–22–12; 8:45 am]
BILLING CODE 7555–01–P
NATIONAL SCIENCE FOUNDATION
Notice of Proposal Review Meetings
In accordance with the Federal
Advisory Committee Act (Pub. L. 92–
463, as amended), the National Science
Foundation (NSF) announces its intent
to hold proposal review meetings
throughout the year. The purpose of
these meetings is to provide advice and
recommendations concerning proposals
submitted to the NSF for financial
support. The agenda for each of these
meetings is to review and evaluate
proposals as part of the selection
process for awards. The review and
evaluation may also include assessment
of the progress of awarded proposals.
The majority of these meetings will take
place at NSF, 4201 Wilson, Blvd.,
Arlington, Virginia 22230.
These meetings will be closed to the
public. The proposals being reviewed
include information of a proprietary or
confidential nature, including technical
information; financial data, such as
salaries; and personal information
concerning individuals associated with
the proposals. These matters are exempt
under 5 U.S.C. 552b(c), (4) and (6) of the
Government in the Sunshine Act. NSF
will continue to review the agenda and
merits of each meeting for overall
compliance of the Federal Advisory
Committee Act.
These closed proposal review
meetings will not be announced on an
individual basis in the Federal Register.
NSF intends to publish a notice similar
to this on a quarterly basis. For an
advance listing of the closed proposal
review meetings that include the names
of the proposal review panel and the
time, date, place, and any information
on changes, corrections, or
cancellations, please visit the NSF Web
site: https://www.nsf.gov. This
information may also be requested by
telephoning, 703/292–8182.
PO 00000
Frm 00102
Fmt 4703
Sfmt 4703
Dated: February 21, 2012.
Susanne Bolton,
Committee Management Officer.
[FR Doc. 2012–4306 Filed 2–23–12; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. NRC–2012–0047]
Agency Information Collection
Activities: Emergency Clearance
Submission for the Office of
Management and Budget (OMB)
Review; Comment Request
Nuclear Regulatory
Commission.
ACTION: Notice of pending NRC action to
submit an information collection
request for emergency review to the
Office of Management and Budget
(OMB) and solicitation of public
comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) invites public
comment about our intention to request
emergency review and OMB approval of
the information collection that is
summarized below. We are required to
publish this notice in the Federal
Register under the provisions of the
Paperwork Reduction Act of 1995 (44
U.S.C. chapter 35). In compliance with
the requirement of section 3506(c)(2)(A)
of the Paperwork Reduction Act of 1995,
we have submitted to the Office of
Management and Budget (OMB) the
following requirements for emergency
review. We are requesting an emergency
review because the collection of this
information is needed before the
expiration of the normal time limits
under OMB’s regulations at 5 CFR
1320.13. This is necessary to ensure
compliance with requirements in
Section 402 of the Consolidated
Appropriations Act, 2012, ‘‘* * *’’ We
cannot reasonably comply with the
normal clearance procedures because
the use of normal clearance procedures
is reasonably likely to prevent or disrupt
the collection of information as stated in
5 CFR 1320.13(a)(2)(iii).
Information pertaining to the
requirement to be submitted:
1. Type of submission, new, revision,
or extension: New.
2. The title of the information
collection: Request for Information
Pursuant to 10 CFR 50.54(f) Regarding
Recommendations 2.1, 2.3 and 93, of the
Near-Term Task Force Review of
Insights from the Fukushima Dai-ichi
Event.
2. Current OMB approval number: Not
applicable.
SUMMARY:
E:\FR\FM\24FEN1.SGM
24FEN1
srobinson on DSK4SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 37 / Friday, February 24, 2012 / Notices
3. How often the collection is
required: One-time, on occasion.
4. Who is required or asked to report:
104 power reactor licensees.
5. The number of annual respondents:
104.
6. The number of hours needed
annually to complete the requirement or
request: The NRC estimates that it will
require 13,300 hours per power reactor
to respond to the information collection
request, for a total of 1,383,200 hours (or
461,067 hours annualized).
7. Abstract: Following the accident at
the Fukushima Dai-ichi nuclear power
plant resulting from the March 11, 2011,
¯
Great Tohoku Earthquake and
subsequent tsunami, the NRC
established the Near-Term Task Force
(NTTF). The NTTF Charter, dated
March 30, 2011, tasked the NTTF with
conducting a systematic and methodical
review of NRC processes and
regulations and determining if the
agency should make additional
improvements to its regulatory system.
Ultimately, a comprehensive set of
recommendations contained in a report
to the Commission (dated July 12, 2011,
SECY–11–0093 (Agencywide
Documents Access and Management
System (ADAMS) Accession No.
ML111861807)) was developed using a
decision rationale built around the
defense-in-depth concept in which each
level of defense-in-depth (namely
prevention, mitigation, and emergency
preparedness (EP)) is critically
evaluated for its completeness and
effectiveness in performing its safety
function.
On August 19, 2011, following
issuance of the NTTF report, the
Commission directed the NRC staff in
staff requirements memorandum (SRM)
for SECY 11–0093 (ADAMS Access No.
ML112310021), in part, to determine
which of the recommendations could
and should be implemented without
unnecessary delay.
On September 9, 2011, the NRC staff
provided SECY–11–0124 to the
Commission (ADAMS Accession No.
ML11245A158). The document
identified those actions from the NTTF
report that should be taken without
unnecessary delay. As part of the
October 18, 2011, SRM for SECY–11–
0124 (ADAMS Accession No.
ML112911571), the Commission
approved the staff’s proposed actions,
including the development of three
information requests under 10 CFR
50.54(f). The information collected
would be used to support the NRC
VerDate Mar<15>2010
18:34 Feb 23, 2012
Jkt 226001
staff’s evaluation of whether further
regulatory action was needed in the
areas of seismic and flooding design,
and emergency preparedness.
On December 23, 2011, the
Consolidated Appropriations Act,
Public Law 112–074, was signed into
law. Section 402 of the law also requires
a reevaluation of licensees’ design basis
for external hazards, and expands the
scope to include other external events.
The NRC has concluded that it
requires the information requested to
verify the compliance with design bases
at nuclear power plants and to
determine if additional regulatory
actions are appropriate. Therefore, the
NRC will issue requests for information,
pursuant to Section 182(a) of the Atomic
Energy Act of 1954, as amended, and 10
CFR 50.54(f). Addressees to the NRC
information request will be required to
confirm receipt of the request for
information within 30 days. Each
attachment to the request for
information contains a topic-specific
schedule for response. The NRC is
requesting OMB review and approval of
this collection by March 6, 2012, with
a 180-day approval period.
Throughout the development of these
letters, the NRC has solicited
stakeholder input including feedback on
the burden. The NRC made draft
versions of the letters publically
available and hosted seven public
meetings to gather stakeholder feedback.
Further, the Nuclear Energy Institute
provided feedback to the NRC on the
content of the letters, including the
associated burden. The NRC considered
all feedback in generating its burden
estimate.
Submit, by March 5, 2012, comments
that address the following questions:
1. Is the proposed collection of
information necessary for the NRC to
properly perform its functions? Does the
information have practical utility?
2. Is the burden estimate accurate?
3. Is there a way to enhance the
quality, utility, and clarity of the
information to be collected?
4. How can the burden of the
information collection be minimized,
including the use of automated
collection techniques or other forms of
information technology?
The public may examine and have
copied for a fee publicly available
documents, including the final
supporting statement, at the NRC’s
Public Document Room, Room O1–F21,
One White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852. OMB
PO 00000
Frm 00103
Fmt 4703
Sfmt 4703
11165
clearance requests are available at the
NRC Web site: https://www.nrc.gov/
public_involve/doc_comment/omb/
index.html. The document will be
available on the NRC home page site for
60 days after the signature date of this
notice.
Comments and questions should be
directed to the OMB reviewer listed
below by March 5, 2012. Comments
received after this date will be
considered if it is practical to do so, but
assurance of consideration cannot be
given to comments received after this
date.
Chad Whiteman, Desk Officer, Office of
Information and Regulatory Affairs
(3150–XXXX), NEOB–10202, Office of
Management and Budget,
Washington, DC 20503.
Comments can also be emailed to
Chad_S_Whiteman@omb.eop.gov or
submitted by telephone at (202) 395–
4718.
For additional information on the
information collections, contact G.
Edward Miller, Project Manager,
Projects Management Branch, Japan
Lessons Learned Project Directorate,
Office of Nuclear Reactor Regulation,
U.S. Nuclear Regulatory Commission,
Rockville, MD 20852. Telephone: (301)
415–2481; fax number: (301) 415–2444;
email: Edward.Miller@nrc.gov.
The NRC Clearance Officer is
Tremaine Donnell, (301) 415–6258.
Questions about the information
collection requirements may be directed
to the NRC Clearance Officer, Tremaine
Donnell (T–5 F53), U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001, by telephone at 301–
415–6258, or by email to
INFOCOLLECTS.Resource@NRC.GOV.
Dated at Rockville, Maryland, this 21st day
of February 2012.
For the Nuclear Regulatory Commission.
Tremaine Donnell,
NRC Clearance Officer, Office of Information
Services.
[FR Doc. 2012–4360 Filed 2–23–12; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2011–0157]
Order Approving Application
Regarding Proposed Corporate Merger
and Indirect Transfer of Licenses
E:\FR\FM\24FEN1.SGM
24FEN1
Agencies
[Federal Register Volume 77, Number 37 (Friday, February 24, 2012)]
[Notices]
[Pages 11164-11165]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-4360]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. NRC-2012-0047]
Agency Information Collection Activities: Emergency Clearance
Submission for the Office of Management and Budget (OMB) Review;
Comment Request
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of pending NRC action to submit an information
collection request for emergency review to the Office of Management and
Budget (OMB) and solicitation of public comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) invites public
comment about our intention to request emergency review and OMB
approval of the information collection that is summarized below. We are
required to publish this notice in the Federal Register under the
provisions of the Paperwork Reduction Act of 1995 (44 U.S.C. chapter
35). In compliance with the requirement of section 3506(c)(2)(A) of the
Paperwork Reduction Act of 1995, we have submitted to the Office of
Management and Budget (OMB) the following requirements for emergency
review. We are requesting an emergency review because the collection of
this information is needed before the expiration of the normal time
limits under OMB's regulations at 5 CFR 1320.13. This is necessary to
ensure compliance with requirements in Section 402 of the Consolidated
Appropriations Act, 2012, ``* * *'' We cannot reasonably comply with
the normal clearance procedures because the use of normal clearance
procedures is reasonably likely to prevent or disrupt the collection of
information as stated in 5 CFR 1320.13(a)(2)(iii).
Information pertaining to the requirement to be submitted:
1. Type of submission, new, revision, or extension: New.
2. The title of the information collection: Request for Information
Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1, 2.3 and 93,
of the Near-Term Task Force Review of Insights from the Fukushima Dai-
ichi Event.
2. Current OMB approval number: Not applicable.
[[Page 11165]]
3. How often the collection is required: One-time, on occasion.
4. Who is required or asked to report: 104 power reactor licensees.
5. The number of annual respondents: 104.
6. The number of hours needed annually to complete the requirement
or request: The NRC estimates that it will require 13,300 hours per
power reactor to respond to the information collection request, for a
total of 1,383,200 hours (or 461,067 hours annualized).
7. Abstract: Following the accident at the Fukushima Dai-ichi
nuclear power plant resulting from the March 11, 2011, Great
T[omacr]hoku Earthquake and subsequent tsunami, the NRC established the
Near-Term Task Force (NTTF). The NTTF Charter, dated March 30, 2011,
tasked the NTTF with conducting a systematic and methodical review of
NRC processes and regulations and determining if the agency should make
additional improvements to its regulatory system. Ultimately, a
comprehensive set of recommendations contained in a report to the
Commission (dated July 12, 2011, SECY-11-0093 (Agencywide Documents
Access and Management System (ADAMS) Accession No. ML111861807)) was
developed using a decision rationale built around the defense-in-depth
concept in which each level of defense-in-depth (namely prevention,
mitigation, and emergency preparedness (EP)) is critically evaluated
for its completeness and effectiveness in performing its safety
function.
On August 19, 2011, following issuance of the NTTF report, the
Commission directed the NRC staff in staff requirements memorandum
(SRM) for SECY 11-0093 (ADAMS Access No. ML112310021), in part, to
determine which of the recommendations could and should be implemented
without unnecessary delay.
On September 9, 2011, the NRC staff provided SECY-11-0124 to the
Commission (ADAMS Accession No. ML11245A158). The document identified
those actions from the NTTF report that should be taken without
unnecessary delay. As part of the October 18, 2011, SRM for SECY-11-
0124 (ADAMS Accession No. ML112911571), the Commission approved the
staff's proposed actions, including the development of three
information requests under 10 CFR 50.54(f). The information collected
would be used to support the NRC staff's evaluation of whether further
regulatory action was needed in the areas of seismic and flooding
design, and emergency preparedness.
On December 23, 2011, the Consolidated Appropriations Act, Public
Law 112-074, was signed into law. Section 402 of the law also requires
a reevaluation of licensees' design basis for external hazards, and
expands the scope to include other external events.
The NRC has concluded that it requires the information requested to
verify the compliance with design bases at nuclear power plants and to
determine if additional regulatory actions are appropriate. Therefore,
the NRC will issue requests for information, pursuant to Section 182(a)
of the Atomic Energy Act of 1954, as amended, and 10 CFR 50.54(f).
Addressees to the NRC information request will be required to confirm
receipt of the request for information within 30 days. Each attachment
to the request for information contains a topic-specific schedule for
response. The NRC is requesting OMB review and approval of this
collection by March 6, 2012, with a 180-day approval period.
Throughout the development of these letters, the NRC has solicited
stakeholder input including feedback on the burden. The NRC made draft
versions of the letters publically available and hosted seven public
meetings to gather stakeholder feedback. Further, the Nuclear Energy
Institute provided feedback to the NRC on the content of the letters,
including the associated burden. The NRC considered all feedback in
generating its burden estimate.
Submit, by March 5, 2012, comments that address the following
questions:
1. Is the proposed collection of information necessary for the NRC
to properly perform its functions? Does the information have practical
utility?
2. Is the burden estimate accurate?
3. Is there a way to enhance the quality, utility, and clarity of
the information to be collected?
4. How can the burden of the information collection be minimized,
including the use of automated collection techniques or other forms of
information technology?
The public may examine and have copied for a fee publicly available
documents, including the final supporting statement, at the NRC's
Public Document Room, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852. OMB clearance requests are
available at the NRC Web site: https://www.nrc.gov/public_involve/doc_comment/omb/. The document will be available on the NRC home
page site for 60 days after the signature date of this notice.
Comments and questions should be directed to the OMB reviewer
listed below by March 5, 2012. Comments received after this date will
be considered if it is practical to do so, but assurance of
consideration cannot be given to comments received after this date.
Chad Whiteman, Desk Officer, Office of Information and Regulatory
Affairs (3150-XXXX), NEOB-10202, Office of Management and Budget,
Washington, DC 20503.
Comments can also be emailed to Chad_S_Whiteman@omb.eop.gov or
submitted by telephone at (202) 395-4718.
For additional information on the information collections, contact
G. Edward Miller, Project Manager, Projects Management Branch, Japan
Lessons Learned Project Directorate, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory Commission, Rockville, MD 20852.
Telephone: (301) 415-2481; fax number: (301) 415-2444; email:
Edward.Miller@nrc.gov.
The NRC Clearance Officer is Tremaine Donnell, (301) 415-6258.
Questions about the information collection requirements may be directed
to the NRC Clearance Officer, Tremaine Donnell (T-5 F53), U.S. Nuclear
Regulatory Commission, Washington, DC 20555-0001, by telephone at 301-
415-6258, or by email to INFOCOLLECTS.Resource@NRC.GOV.
Dated at Rockville, Maryland, this 21st day of February 2012.
For the Nuclear Regulatory Commission.
Tremaine Donnell,
NRC Clearance Officer, Office of Information Services.
[FR Doc. 2012-4360 Filed 2-23-12; 8:45 am]
BILLING CODE 7590-01-P