Fall River Community Hydro Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 10503-10504 [2012-4077]

Download as PDF Federal Register / Vol. 77, No. 35 / Wednesday, February 22, 2012 / Notices upon lands or waters owned by others without the owners’ express permission. The proposed project has two alternatives: Alternative 1 The proposed project would use Reclamation’s existing Banks Lake as the upper reservoir and Roosevelt Lake as the lower reservoir. The proposed project would consist of the following new facilities: (1) An upper reservoir inlet/outlet structure equipped with trash racks; (2) a 1.5-mile-long penstock consisting of a vertical shaft, power tunnel segments, and a tailrace section, extending between the upper reservoir inlet/outlet and the reversible turbine/ generator units in the powerhouse; (3) an underground powerhouse containing four reversible turbine/generator units rated for 250 megawatts (MW) each, for a total installed generation of 1,000 MW, or a powerhouse located on the shore of Roosevelt Lake, also containing four 250–MW reversible turbine/generator units; (4) a 2-mile-long, 500-kilovolt (kV) transmission line extending from the project powerhouse to an existing 500-kV substation; and (5) appurtenant facilities. The estimated annual generation of Alternative 1 for the Banks Lake Project would be 2,263 gigawatthours (GWh). srobinson on DSK4SPTVN1PROD with NOTICES Alternative 2 The proposed project would use Reclamation’s existing Banks Lake as the lower reservoir. The proposed project would consist of the following new facilities: (1) A new 312-acre upper reservoir constructed approximately 3,000 feet west of the existing Banks Lake, impounded by three earth and rockfill embankments, each with a crest elevation of 2,300 feet above mean sea level; (2) an upper reservoir inlet/outlet structure equipped with trash racks; (2) a 620-foot-long, 43-foot-diameter vertical shaft connecting the upper reservoir inlet/outlet structure to the power tunnels; (3) four 1,700-foot-long, 17-foot-diameter power tunnels leading from the vertical shaft to the powerhouse; (4) an underground powerhouse containing four reversible turbine/generator units rated for 260 MW each, for a total installed generation of 1,040 MW; (5) a 25-foot-diameter tailrace tunnel between the powerhouse and the existing Banks Lake; (6) a 2.4mile-long, 500-kV transmission line extending from the project powerhouse to a new 500-kV substation; and (7) appurtenant facilities. The estimated annual generation of Alternative 2 for the Banks Lake Project would be 2,978 GWh. VerDate Mar<15>2010 16:37 Feb 21, 2012 Jkt 226001 Applicant Contact: Mr. Ronald K. Rodewald, Secretary-Manager, Grand Coulee Project Hydroelectric Authority, P.O. Box 219, Ephrata, WA 98823; phone: (509) 754–2227. FERC Contact: Jennifer Harper; phone: (202) 502–6136. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc. gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/elibrary. asp. Enter the docket number (P–14329) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: February 14, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–4010 Filed 2–21–12; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 10503 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14216–000] Fall River Community Hydro Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On June 27, 2011, Fall River Valley Community Service District, California, filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Fall River Community Hydro Project to be located on Fall River, near the town of Fall River Mills, Shasta County, California. The project affects federal lands administered by the Bureau of Land Management. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following facilities: (1) An open conduit that would deliver water from the Pit 1 diversion to a penstock; (2) an existing penstock connecting the conduit to the powerhouse; (3) two pump-turbines totaling 900 kilowatts (kW) (1 × 300 kW unit and 1 × 600 kW unit) of generating capacity; and (4) an existing 3-phase power line on site. The project’s annual energy output would range from 4 to 6 gigawatt hours. Applicant Contact: Mr. John Van den Bergh, Fall River Valley Community Service District, P.O. Box 427, Fall River Mills, California 96028; phone (530) 336–5263. FERC Contact: Carolyn Templeton; phone: (202) 502–8785. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the E:\FR\FM\22FEN1.SGM 22FEN1 10504 Federal Register / Vol. 77, No. 35 / Wednesday, February 22, 2012 / Notices eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14216–000) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: February 15, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–4077 Filed 2–21–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13272–003] srobinson on DSK4SPTVN1PROD with NOTICES Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Alaska Village Electric Cooperative On February 13, 2012, Alaska Village Electric Cooperative (AVEC) filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Old Harbor Hydroelectric Project (Old Harbor Project or project) to be located on the East Fork of Mountain Creek (a Lagoon Creek tributary), near the town of Old Harbor, Kodiak Island Borough, Alaska. The project crosses federal lands of the Kodiak National Wildlife Refuge. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. VerDate Mar<15>2010 16:37 Feb 21, 2012 Jkt 226001 The proposed run-of-river project would consist of an intake, penstock, powerhouse, tailrace and constructed channel, access road and trail, and transmission line. Power from this project would be used by the residents of the city of Old Harbor. Intake The intake would consist of a diversion/cut off weir with a height ranging from about 4 feet at the spillway to 6 feet elsewhere and having an overall length of approximately 100 feet. The creek bottom is close to bedrock so the base of the diversion wall would be a shallow grouted or concrete footing dug into the stream bed. The weir would not create any significant impoundment of water and would only be high enough to have an intake that pulls water from the midpoint of the water column. This would allow floatable objects and bottom moving sediments to remain in the creek. A water filtering system consisting of a trash rack, diversion gates, and secondary screens would be incorporated into the weir structure as a separate desanding box that would be partially exposed above grade. The project diversion and intake works would consist of concrete, or other suitable material, with an integral spillway. A below grade transition with an above ground air relief inlet pipe would convey water to a buried High Density Polyethylene Pipe (HDPE) pipeline. Penstock A 10,100-foot-long penstock consisting of an 18-inch-diameter HDPE pipe, a 20-inch-diameter HDPE pipe, and a 16-inch-diameter steel pipe would be installed. A total of 7,250 feet of HDPE would be installed from the intake and 2,850 feet of steel pipe would be installed near the powerhouse. The pipe would be buried 1 to 3 feet underground and follow the natural terrain as much as possible. The pipeline would be located such that bends would be gradual while minimizing the amount of excavation and fill needed. Powerhouse The powerhouse would consist of a 30-foot by 35-foot (approximate) by 16foot- high metal building or similar structure. The building would house the turbines and associated equipment, switchgear, controls, and tools and would be placed on a fill pad. The power generation equipment would consist of two Pelton 262 kilowatt (kW) units with a 480-volt, 3-phase synchronous generator and switchgear PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 for each unit. Each unit would have a hydraulic capacity of 5.9 cubic feet per second (cfs) for a total project peak flow rate of 11.8 cfs capable of producing 525 kW of power. A bypass flow system for maintaining environmental flows is not proposed at this time, since the source creek runs dry during certain times of the year. Tailrace A tailrace structure and constructed channel would convey the project flows approximately 700 feet from the powerhouse to the nearby lake, known in the city of Old Harbor as the Swimming Pond. A culvert would contain some of the tailrace near the powerhouse to allow for vehicle travel over the tailrace. The constructed channel would convey project flows 1,100 feet from the Swimming Pond to the headwaters of the Lagoon Creek tributary. Access Road and Trail An approximately 11, 200-foot-long intake access trail would run between the intake and the powerhouse following the penstock route. The 12foot-wide trail would be made of 1 to 2 feet of rock fill placed over a geo-textile filter fabric. Two gates would be placed along on the access trail to block the public from accessing the Kodiak National Wildlife Refuge on all terrain vehicles. One gate would be located at the powerhouse. Another gate would be placed where an existing trail connects to the new trail at about 7,000 feet northwest of the powerhouse. A new 6,800-foot-long by 24-foot-wide powerhouse access road would extend from powerhouse to the existing community drinking water tank access road. The road would be open to the public. Transmission Line A 6,800-foot-long (1.5-mile), 7.2-kV, 3-phase overhead power line would be installed from the powerhouse to the existing power distribution system in Old Harbor. The transmission line would follow the powerhouse access road and drinking water tank road alignment. The estimated dependable capacity of the project is 140 kW. The peak installed capacity will primarily depend on economics and the projected increase in demand. AVEC has chosen to permit the project with a peak capacity of 525 kW. Applicant Contact: Brent Petrie; Manager, Community Development and Key Accounts; Alaska Village Electric Cooperative; 4831 Eagle Street, E:\FR\FM\22FEN1.SGM 22FEN1

Agencies

[Federal Register Volume 77, Number 35 (Wednesday, February 22, 2012)]
[Notices]
[Pages 10503-10504]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-4077]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14216-000]


Fall River Community Hydro Project; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On June 27, 2011, Fall River Valley Community Service District, 
California, filed an application for a preliminary permit, pursuant to 
section 4(f) of the Federal Power Act (FPA), proposing to study the 
feasibility of the Fall River Community Hydro Project to be located on 
Fall River, near the town of Fall River Mills, Shasta County, 
California. The project affects federal lands administered by the 
Bureau of Land Management. The sole purpose of a preliminary permit, if 
issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land-disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would consist of the following facilities: (1) 
An open conduit that would deliver water from the Pit 1 diversion to a 
penstock; (2) an existing penstock connecting the conduit to the 
powerhouse; (3) two pump-turbines totaling 900 kilowatts (kW) (1 x 300 
kW unit and 1 x 600 kW unit) of generating capacity; and (4) an 
existing 3-phase power line on site. The project's annual energy output 
would range from 4 to 6 gigawatt hours.
    Applicant Contact: Mr. John Van den Bergh, Fall River Valley 
Community Service District, P.O. Box 427, Fall River Mills, California 
96028; phone (530) 336-5263.
    FERC Contact: Carolyn Templeton; phone: (202) 502-8785.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and 
competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the

[[Page 10504]]

eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, 
(202) 502-8659. Although the Commission strongly encourages electronic 
filing, documents may also be paper-filed. To paper-file, mail an 
original and seven copies to: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 888 First Street NE., Washington, DC 
20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14216-000) in the docket number field to 
access the document. For assistance, contact FERC Online Support.

    Dated: February 15, 2012.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2012-4077 Filed 2-21-12; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.