Fall River Community Hydro Project; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 10503-10504 [2012-4077]
Download as PDF
Federal Register / Vol. 77, No. 35 / Wednesday, February 22, 2012 / Notices
upon lands or waters owned by others
without the owners’ express permission.
The proposed project has two
alternatives:
Alternative 1
The proposed project would use
Reclamation’s existing Banks Lake as
the upper reservoir and Roosevelt Lake
as the lower reservoir. The proposed
project would consist of the following
new facilities: (1) An upper reservoir
inlet/outlet structure equipped with
trash racks; (2) a 1.5-mile-long penstock
consisting of a vertical shaft, power
tunnel segments, and a tailrace section,
extending between the upper reservoir
inlet/outlet and the reversible turbine/
generator units in the powerhouse; (3)
an underground powerhouse containing
four reversible turbine/generator units
rated for 250 megawatts (MW) each, for
a total installed generation of 1,000 MW,
or a powerhouse located on the shore of
Roosevelt Lake, also containing four
250–MW reversible turbine/generator
units; (4) a 2-mile-long, 500-kilovolt
(kV) transmission line extending from
the project powerhouse to an existing
500-kV substation; and (5) appurtenant
facilities. The estimated annual
generation of Alternative 1 for the Banks
Lake Project would be 2,263 gigawatthours (GWh).
srobinson on DSK4SPTVN1PROD with NOTICES
Alternative 2
The proposed project would use
Reclamation’s existing Banks Lake as
the lower reservoir. The proposed
project would consist of the following
new facilities: (1) A new 312-acre upper
reservoir constructed approximately
3,000 feet west of the existing Banks
Lake, impounded by three earth and
rockfill embankments, each with a crest
elevation of 2,300 feet above mean sea
level; (2) an upper reservoir inlet/outlet
structure equipped with trash racks; (2)
a 620-foot-long, 43-foot-diameter
vertical shaft connecting the upper
reservoir inlet/outlet structure to the
power tunnels; (3) four 1,700-foot-long,
17-foot-diameter power tunnels leading
from the vertical shaft to the
powerhouse; (4) an underground
powerhouse containing four reversible
turbine/generator units rated for 260
MW each, for a total installed generation
of 1,040 MW; (5) a 25-foot-diameter
tailrace tunnel between the powerhouse
and the existing Banks Lake; (6) a 2.4mile-long, 500-kV transmission line
extending from the project powerhouse
to a new 500-kV substation; and (7)
appurtenant facilities. The estimated
annual generation of Alternative 2 for
the Banks Lake Project would be 2,978
GWh.
VerDate Mar<15>2010
16:37 Feb 21, 2012
Jkt 226001
Applicant Contact: Mr. Ronald K.
Rodewald, Secretary-Manager, Grand
Coulee Project Hydroelectric Authority,
P.O. Box 219, Ephrata, WA 98823;
phone: (509) 754–2227.
FERC Contact: Jennifer Harper;
phone: (202) 502–6136.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
information at the end of your
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/elibrary.
asp. Enter the docket number (P–14329)
in the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: February 14, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–4010 Filed 2–21–12; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
10503
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14216–000]
Fall River Community Hydro Project;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On June 27, 2011, Fall River Valley
Community Service District, California,
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to
study the feasibility of the Fall River
Community Hydro Project to be located
on Fall River, near the town of Fall
River Mills, Shasta County, California.
The project affects federal lands
administered by the Bureau of Land
Management. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following facilities: (1) An open
conduit that would deliver water from
the Pit 1 diversion to a penstock; (2) an
existing penstock connecting the
conduit to the powerhouse; (3) two
pump-turbines totaling 900 kilowatts
(kW) (1 × 300 kW unit and 1 × 600 kW
unit) of generating capacity; and (4) an
existing 3-phase power line on site. The
project’s annual energy output would
range from 4 to 6 gigawatt hours.
Applicant Contact: Mr. John Van den
Bergh, Fall River Valley Community
Service District, P.O. Box 427, Fall River
Mills, California 96028; phone (530)
336–5263.
FERC Contact: Carolyn Templeton;
phone: (202) 502–8785.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
E:\FR\FM\22FEN1.SGM
22FEN1
10504
Federal Register / Vol. 77, No. 35 / Wednesday, February 22, 2012 / Notices
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14216–000) in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
Dated: February 15, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–4077 Filed 2–21–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13272–003]
srobinson on DSK4SPTVN1PROD with NOTICES
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing
Applications; Alaska Village Electric
Cooperative
On February 13, 2012, Alaska Village
Electric Cooperative (AVEC) filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Old Harbor
Hydroelectric Project (Old Harbor
Project or project) to be located on the
East Fork of Mountain Creek (a Lagoon
Creek tributary), near the town of Old
Harbor, Kodiak Island Borough, Alaska.
The project crosses federal lands of the
Kodiak National Wildlife Refuge. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
VerDate Mar<15>2010
16:37 Feb 21, 2012
Jkt 226001
The proposed run-of-river project
would consist of an intake, penstock,
powerhouse, tailrace and constructed
channel, access road and trail, and
transmission line. Power from this
project would be used by the residents
of the city of Old Harbor.
Intake
The intake would consist of a
diversion/cut off weir with a height
ranging from about 4 feet at the spillway
to 6 feet elsewhere and having an
overall length of approximately 100 feet.
The creek bottom is close to bedrock so
the base of the diversion wall would be
a shallow grouted or concrete footing
dug into the stream bed. The weir
would not create any significant
impoundment of water and would only
be high enough to have an intake that
pulls water from the midpoint of the
water column. This would allow
floatable objects and bottom moving
sediments to remain in the creek. A
water filtering system consisting of a
trash rack, diversion gates, and
secondary screens would be
incorporated into the weir structure as
a separate desanding box that would be
partially exposed above grade. The
project diversion and intake works
would consist of concrete, or other
suitable material, with an integral
spillway. A below grade transition with
an above ground air relief inlet pipe
would convey water to a buried High
Density Polyethylene Pipe (HDPE)
pipeline.
Penstock
A 10,100-foot-long penstock
consisting of an 18-inch-diameter HDPE
pipe, a 20-inch-diameter HDPE pipe,
and a 16-inch-diameter steel pipe would
be installed. A total of 7,250 feet of
HDPE would be installed from the
intake and 2,850 feet of steel pipe would
be installed near the powerhouse. The
pipe would be buried 1 to 3 feet
underground and follow the natural
terrain as much as possible. The
pipeline would be located such that
bends would be gradual while
minimizing the amount of excavation
and fill needed.
Powerhouse
The powerhouse would consist of a
30-foot by 35-foot (approximate) by 16foot- high metal building or similar
structure. The building would house the
turbines and associated equipment,
switchgear, controls, and tools and
would be placed on a fill pad. The
power generation equipment would
consist of two Pelton 262 kilowatt (kW)
units with a 480-volt, 3-phase
synchronous generator and switchgear
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
for each unit. Each unit would have a
hydraulic capacity of 5.9 cubic feet per
second (cfs) for a total project peak flow
rate of 11.8 cfs capable of producing 525
kW of power. A bypass flow system for
maintaining environmental flows is not
proposed at this time, since the source
creek runs dry during certain times of
the year.
Tailrace
A tailrace structure and constructed
channel would convey the project flows
approximately 700 feet from the
powerhouse to the nearby lake, known
in the city of Old Harbor as the
Swimming Pond. A culvert would
contain some of the tailrace near the
powerhouse to allow for vehicle travel
over the tailrace. The constructed
channel would convey project flows
1,100 feet from the Swimming Pond to
the headwaters of the Lagoon Creek
tributary.
Access Road and Trail
An approximately 11, 200-foot-long
intake access trail would run between
the intake and the powerhouse
following the penstock route. The 12foot-wide trail would be made of 1 to 2
feet of rock fill placed over a geo-textile
filter fabric. Two gates would be placed
along on the access trail to block the
public from accessing the Kodiak
National Wildlife Refuge on all terrain
vehicles. One gate would be located at
the powerhouse. Another gate would be
placed where an existing trail connects
to the new trail at about 7,000 feet
northwest of the powerhouse. A new
6,800-foot-long by 24-foot-wide
powerhouse access road would extend
from powerhouse to the existing
community drinking water tank access
road. The road would be open to the
public.
Transmission Line
A 6,800-foot-long (1.5-mile), 7.2-kV,
3-phase overhead power line would be
installed from the powerhouse to the
existing power distribution system in
Old Harbor. The transmission line
would follow the powerhouse access
road and drinking water tank road
alignment.
The estimated dependable capacity of
the project is 140 kW. The peak
installed capacity will primarily depend
on economics and the projected increase
in demand. AVEC has chosen to permit
the project with a peak capacity of 525
kW.
Applicant Contact: Brent Petrie;
Manager, Community Development and
Key Accounts; Alaska Village Electric
Cooperative; 4831 Eagle Street,
E:\FR\FM\22FEN1.SGM
22FEN1
Agencies
[Federal Register Volume 77, Number 35 (Wednesday, February 22, 2012)]
[Notices]
[Pages 10503-10504]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-4077]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14216-000]
Fall River Community Hydro Project; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On June 27, 2011, Fall River Valley Community Service District,
California, filed an application for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act (FPA), proposing to study the
feasibility of the Fall River Community Hydro Project to be located on
Fall River, near the town of Fall River Mills, Shasta County,
California. The project affects federal lands administered by the
Bureau of Land Management. The sole purpose of a preliminary permit, if
issued, is to grant the permit holder priority to file a license
application during the permit term. A preliminary permit does not
authorize the permit holder to perform any land-disturbing activities
or otherwise enter upon lands or waters owned by others without the
owners' express permission.
The proposed project would consist of the following facilities: (1)
An open conduit that would deliver water from the Pit 1 diversion to a
penstock; (2) an existing penstock connecting the conduit to the
powerhouse; (3) two pump-turbines totaling 900 kilowatts (kW) (1 x 300
kW unit and 1 x 600 kW unit) of generating capacity; and (4) an
existing 3-phase power line on site. The project's annual energy output
would range from 4 to 6 gigawatt hours.
Applicant Contact: Mr. John Van den Bergh, Fall River Valley
Community Service District, P.O. Box 427, Fall River Mills, California
96028; phone (530) 336-5263.
FERC Contact: Carolyn Templeton; phone: (202) 502-8785.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the
[[Page 10504]]
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
(202) 502-8659. Although the Commission strongly encourages electronic
filing, documents may also be paper-filed. To paper-file, mail an
original and seven copies to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14216-000) in the docket number field to
access the document. For assistance, contact FERC Online Support.
Dated: February 15, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-4077 Filed 2-21-12; 8:45 am]
BILLING CODE 6717-01-P