Reissuance of Nationwide Permits, 10184-10290 [2012-3687]
Download as PDF
10184
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
DEPARTMENT OF DEFENSE
Department of the Army, Corps of
Engineers
RIN 0710–AA71
Reissuance of Nationwide Permits
Army Corps of Engineers, DoD.
Final notice.
AGENCY:
ACTION:
The U.S. Army Corps of
Engineers (Corps) is reissuing 48 of the
49 existing nationwide permits (NWPs),
general conditions, and definitions,
with some modifications. The Corps is
also issuing two new NWPs, three new
general conditions, and three new
definitions. The effective date for the
new and reissued NWPs will be March
19, 2012. These NWPs will expire on
March 18, 2017. The NWPs will protect
the aquatic environment and the public
interest while effectively authorizing
activities that have minimal individual
and cumulative adverse effects on the
aquatic environment.
DATES: The NWPs and general
conditions will become effective on
March 19, 2012.
ADDRESSES: U.S. Army Corps of
Engineers, Attn: CECW–CO–R, 441 G
Street NW., Washington, DC 20314–
1000.
SUMMARY:
Mr.
David Olson at 202–761–4922 or by
email at david.b.olson@usace.army.mil
or access the U.S. Army Corps of
Engineers Regulatory Home Page at
https://www.usace.army.mil/CECW/
Pages/cecwo_reg.aspx.
SUPPLEMENTARY INFORMATION:
FOR FURTHER INFORMATION CONTACT:
sroberts on DSK5SPTVN1PROD with NOTICES
Executive Summary
The U.S. Army Corps of Engineers
(Corps) issues nationwide permits
(NWPs) to authorize certain activities
that require Department of the Army
permits under Section 404 of the Clean
Water Act and/or Section 10 of the
Rivers and Harbors Act of 1899. The
purpose of this regulatory action is to
reissue 48 existing NWPs and issue two
new NWPs. In addition, three new
general conditions and three new
definitions will be issued. The NWPs
may be issued for a period of no more
than five years. Therefore, the Corps
must reissue the NWPs every five years
to continue to authorize these activities.
These 50 NWPs will go into effect on
March 19, 2012.
The NWPs authorize activities that
have minimal individual and
cumulative adverse effects on the
aquatic environment. The NWPs
authorize a variety of activities, such as
aids to navigation, utility lines, bank
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
stabilization activities, road crossings,
stream and wetland restoration
activities, residential developments,
mining activities, commercial shellfish
aquaculture activities, and agricultural
activities. Some NWP activities may
proceed without notifying the Corps, as
long as those activities satisfy the terms
and conditions of the NWPs. Other
NWP activities cannot proceed until the
project proponent has submitted a preconstruction notification to the Corps,
and for most NWPs the Corps has 45
days to notify the project proponent
whether the activity is authorized by
NWP.
Background
In the February 16, 2011, issue of the
Federal Register (76 FR 9174), the U.S.
Army Corps of Engineers (Corps)
published its proposal to reissue 48
existing nationwide permits (NWPs),
issue two new NWPs, and not reissue
one NWP. The Corps also proposed to
reissue its general conditions and add
two new general conditions.
After evaluating the comments
received in response to the February 16,
2011, proposal, we have made a number
of changes to the NWPs, general
conditions, and definitions to further
clarify the permits, general conditions,
and definitions, facilitate their
administration, and strengthen
environmental protection. Examples of
improved environmental protection
include: imposing limits on surface coal
mining activities authorized by NWP 21;
modifying NWP 27 to authorize
additional aquatic resource restoration
and enhancement activities such as the
rehabilitation and enhancement of tidal
streams, wetlands, and open waters; and
providing flexibility in designing
crossings of streams and other
waterbodies so that movements of
aquatic species can be maintained after
taking into account the characteristics of
the stream or waterbody and the
surrounding landscape (see general
condition 2, aquatic life movements).
These changes are discussed in the
preamble.
The Corps is reissuing 48 existing
NWPs, issuing two new NWPs,
reissuing 28 existing general conditions,
and issuing three new general
conditions. The Corps is also reissuing
all of the NWP definitions, and adding
three new definitions. The Corps is also
splitting one existing definition into two
definitions as they relate to single and
complete projects. The effective date for
these NWPs, general conditions, and
definitions is March 19, 2012. These
NWPs, general conditions, and
definitions expire on March 18, 2017.
PO 00000
Frm 00002
Fmt 4701
Sfmt 4703
Grandfather Provision for Expiring
NWPs
In accordance with 33 CFR part
330.6(b), activities authorized by the
current NWPs issued on March 12,
2007, that have commenced or are
under contract to commence by March
18, 2012, will have until March 18,
2013, to complete the activity under the
terms and conditions of the current
NWPs. Nationwide permit 21 activities
that were authorized by the 2007 NWP
21 may be reauthorized without
applying the new limits imposed on
NWP 21, provided the permittee
submits a written request for
reauthorization to the district engineer
by February 1, 2013, and the district
engineer determines that the on-going
surface coal mining activity will result
in minimal adverse effects on the
aquatic environment and notifies the
permittee in writing that the activity is
authorized under the 2012 NWP 21.
Clean Water Act Section 401 Water
Quality Certifications (WQC) and
Coastal Zone Management Act (CZMA)
Consistency Determinations
The NWPs issued today will become
effective on March 19, 2012. This
Federal Register notice begins the 60day Clean Water Act Section 401 water
quality certification (WQC) and the 90day Coastal Zone Management Act
(CZMA) consistency determination
processes.
After the 60-day period, the latest
version of any written position taken by
a state, Indian tribe, or EPA on its WQC
for any of the NWPs will be accepted as
the state’s, Indian tribe’s, or EPA’s final
position on those NWPs. If the state,
Indian tribe, or EPA takes no action by
April 23, 2012, WQC will be considered
waived for those NWPs.
After the 90-day period, the latest
version of any written position taken by
a state on its CZMA consistency
determination for any of the NWPs will
be accepted as the state’s final position
on those NWPs. If the state takes no
action by May 21, 2012, CZMA
concurrence will be presumed for those
NWPs.
While the states, Indian Tribes, and
EPA complete their WQC processes and
the states complete their CZMA
consistency determination processes,
the use of an NWP to authorize a
discharge into waters of the United
States is contingent upon obtaining
individual water quality certification or
a case-specific WQC waiver. Likewise,
the use of an NWP to authorize an
activity within a state’s coastal zone, or
outside a state’s coastal zone that will
affect land or water uses or natural
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
resources of that state’s coastal zone, is
contingent upon obtaining an individual
CZMA consistency determination, or a
case-specific presumption of CZMA
concurrence. We are taking this
approach to reduce the hardships on the
regulated public that would be caused
by a substantial gap in NWP coverage if
we were to wait until the WQC 60-day
period and the CZMA 90-day period
ended before these NWPs would
become effective.
Discussion of Public Comments
I. Overview
In response to the February 16, 2011,
Federal Register notice, we received
more than 26,600 comment letters, of
which approximately 26,300 were form
letters pertaining to NWP 21. The nonform letters we received contained a few
thousand comments on various
components of the NWPs and NWP
Program implementation. We reviewed
and fully considered all comments
received in response to the proposed
rule.
sroberts on DSK5SPTVN1PROD with NOTICES
General Comments
Many commenters expressed support
for the proposed permits. Some
commenters stated that the changes are
a step forward in improving consistency
in the NWP program. Many commenters
endorsed the fundamentals of the NWP
program, stating that the permits could
have a beneficial impact to conducting
infrastructure and mining projects
important to the country. Some stated
that permitting delays and an increase
in individual permits would result
without the NWP program, creating a
backlog for the Corps and resource
agencies, while placing a burden on
regulated industries. Another
commenter urged the Corps to increase
flexibility to allow for project
modifications when needed due to
unanticipated challenges encountered
during construction. Some commenters
stated that further streamlining is
needed for increased efficiency and
reducing administrative burden while
maintaining a high level of
environmental protection. One
commenter said the Corps should
maximize rather than limit use of the
NWP program in light of the current
economic situation, Federal budget cuts,
and presidential efforts to streamline
regulations. Another commenter was
pleased to see the Corps hold the line
against further restrictions on the NWP
program. Many commenters emphasized
that a timely, efficient, and consistent
permitting system is critical to the
nation’s economy.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
The NWP Program provides flexibility
to readily authorize project
modifications if the NWP activity
cannot be constructed in accordance
with the approved plans, as long as any
modifications would still meet the terms
and conditions of applicable NWP(s)
and qualify for NWP authorization. In
cases where the district engineer has
issued an NWP verification letter, the
permittee should contact the district as
soon as he or she finds that the activity
cannot be constructed in accordance
with the approved plans. The district
engineer will then determine if
authorization by NWP is still
appropriate. If it is not, then the
permittee will be instructed on the most
appropriate mechanism for permitting
the modified activity.
We believe the final permits issued
today maintain a proper balance
between efficiently authorizing
activities with minimal individual and
cumulative adverse environmental
effects and protecting the aquatic
environment. The NWPs provide a
streamlined authorization process that
is consistent with the principles of
Executive Order 13563, Improving
Regulation and Regulatory Review.
In contrast, many other commenters
expressed general opposition to the
proposal, and said that the proposed
rule weakens protection for waters and
should be withdrawn. Some
commenters said that the proposal
threatens to undermine the important
and statutorily mandated function of the
NWPs and the Clean Water Act, and is
contrary to Congressional intent. One
commenter expressed opposition to the
issuance of the NWPs, stating that they
will result in an increase in the number
of activities that can be permitted and
a reduction in the opportunity for
public review and comment. Many of
these commenters objected to the goals
of ‘‘streamlining’’ or ‘‘improving
regulatory efficiency,’’ and they said
that the focus of the NWPs should be on
compliance with the Clean Water Act.
Another commenter was concerned that
the proposed NWPs do not support the
‘‘no overall net loss’’ goal for wetlands,
and that the Corps analysis predicts that
the NWPs will result in a decrease of
waters of the United States, including
wetlands.
As discussed below, those NWPs that
authorize discharges of dredged or fill
material into waters of the United States
comply with the Clean Water Act and
the environmental criteria provided in
its implementing regulations, the
404(b)(1) Guidelines at 40 CFR part 230.
The NWPs authorize minor activities
that result in minimal adverse effects on
the aquatic environment that would
PO 00000
Frm 00003
Fmt 4701
Sfmt 4703
10185
likely generate little, if any, public
comment if they were evaluated through
the standard permit process with a full
public notice. Through the adoption of
Section 404(e) of the Clean Water Act in
1977, Congress approved the use of
general permits as an important tool to
keep the Corps Regulatory Program
manageable from a resources and
manpower perspective, while protecting
the aquatic environment. The Corps first
adopted the concept of general permits
in its final rule published on July 25,
1975 (see 40 FR 31321). The NWP
program also continues to support the
national goal of ‘‘no overall net loss’’ for
wetlands, and wetlands compensatory
mitigation will be required when
appropriate and practicable to offset
losses of wetland area and functions.
The ‘‘no overall net loss’’ goal applies
only to wetlands, and for other waters
of the United States the goal is to avoid
and minimize losses of those waters and
to provide compensatory mitigation to
offset those losses if it is appropriate
and practicable to do so. Stream
mitigation is becoming more
commonplace as the science and
practical applications become further
developed.
Some commenters stated that the
NWPs should require consideration of
less damaging alternatives or
demonstrate that NWP activities result
in minimal adverse environmental
effects. One commenter said that there
is not sufficient emphasis on avoidance
of impacts to waters of the United
States. Another commenter objected to
using NWPs to expand existing projects,
stating that it discourages avoidance and
minimization.
Those NWPs that authorize discharges
of dredged or fill material into waters of
the United States comply with the
provisions of the 404(b)(1) Guidelines
that address the issuance of general
permits (see 40 CFR 230.7). A decision
document is prepared for each NWP to
provide information to show that the
NWP will authorize only those activities
that result in minimal adverse effects on
the aquatic environment and other
public interest review factors.
Supplemental decision documents are
prepared at a regional level to support
the decision on whether to add regional
conditions to an NWP or suspend or
revoke the use of that NWP in a specific
waterbody, category of waters, or
geographic area to ensure that only
activities that result in minimal adverse
effects on the aquatic environment and
other public interest review factors are
authorized by the NWP. In response to
a pre-construction notification or a
request to verify that an activity is
authorized by NWP, a district engineer
E:\FR\FM\21FEN2.SGM
21FEN2
10186
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
may add activity-specific conditions to
the NWP authorization or suspend or
revoke the NWP authorization if he or
she determines that the proposed
activity would result in more than
minimal adverse effects.
Paragraph (a) of general condition 23,
mitigation, requires permittees to avoid
and minimize adverse effects to waters
of the United States to the maximum
extent practicable on the project site.
The use of NWPs to authorize the
expansion of existing projects does not
discourage avoidance and minimization
because this general condition applies
equally to all NWP authorizations,
including those that authorize
expansion of existing projects. The
consideration of practicable alternatives
in accordance with 40 CFR 230.10(a)
does not apply directly to discharges of
dredged or fill material into waters of
the United States authorized by general
permits (see 40 CFR 230.7(b)(1)).
Compliance With Section 404(e) of the
Clean Water Act
Several commenters said that the
proposed NWPs are contrary to the
Clean Water Act and violate Section
404(e) of that Act. Many commenters
asserted that the NWPs result in more
than minimal adverse effects on the
aquatic environment, individually and
cumulatively. These commenters stated
that the NWPs do not protect vitally
important functions of wetlands and
streams, and that the proposal does not
satisfy the Corps legal obligation to limit
general permits to activities that cause
minimal adverse impacts, individually
and cumulatively. They also said the
Corps lacks the data to show that the
effects of the authorized activities are in
fact minimal. Some commenters
expressed concern regarding the
potential overuse of these permits
without the inclusion of acreage, linear
feet, watershed or regional limitations.
Another commenter said that the NWPs
fail to describe similarly covered
activities in precise terms.
The Corps disagrees with these
comments. The NWPs comply with the
Clean Water Act and the environmental
criteria provided in its implementing
regulations, the 404(b)(1) Guidelines at
40 CFR part 230. Section 404(e) of the
Clean Water Act states that the Chief of
Engineers may issue, after publishing a
notice and providing an opportunity a
public hearing, general permits on a
nationwide basis for any category of
activities involving discharges of
dredged or fill material into waters of
the United States, if it is determined
that the activities in each category are
similar in nature and result in minimal
individual and cumulative adverse
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
environmental effects. The issuance of
the NWPs is consistent with these
requirements and therefore complies
with the intent of the Clean Water Act.
As discussed above, national decision
documents and supplemental decision
documents are prepared to demonstrate
that an NWP will authorize only those
activities that have minimal individual
and cumulative adverse effects on the
aquatic environment and other public
interest review factors. The decision
documents use available data and other
information to support their
conclusions.
Where appropriate and necessary,
certain NWPs have acreage, linear foot,
or cubic yard limits, or combinations of
those limits, to ensure that authorized
activities result in minimal individual
and cumulative adverse effects on the
aquatic environment. Specifically,
NWPs have acreage limitations, NWPs
have linear foot limitations, and NWPs
have cubic yard limitations. Many other
NWPs have qualitative limitations in the
form of specific activities or situations
that are not authorized, or for which a
PCN is required to allow the Corps to
ensure on a case-by-case basis that the
adverse effects on the aquatic
environment of the project are truly
minimal. A few NWPs have no explicit
limits, but this is limited to those that
authorize activities that provide benefits
to the aquatic environment (e.g., NWP
27, which authorizes aquatic habitat
restoration, establishment, and
enhancement activities, and NWP 41,
which authorizes activities for
reshaping drainage ditches to improve
water quality), or those for which the
nature of the authorized activity
inherently ensures that effects will be
minimal (e.g., NWP 10, which
authorizes non-commercial, single boat,
mooring buoys). Division engineers may
impose regional conditions on the
NWPs to add acreage, linear foot, or
cubic yard limits, or reduce those limits
when the NWPs have specified limits in
their terms and conditions, to ensure
those NWPs authorize only those
activities that result in minimal adverse
effects on the aquatic environment.
The NWPs comply with the
requirement in Section 404(e) of the
Clean Water Act to authorize categories
of activities that are similar in nature.
Each NWP authorizes a specific category
of activities, which may be broadly
defined for some NWPs to keep the
NWP program manageable. The Act
does not require that activities
authorized by an NWP be identical, only
that they be similar in nature. The
permits meet this requirement and are
consistent with the Corps’ longstanding
practice regarding the appropriate level
PO 00000
Frm 00004
Fmt 4701
Sfmt 4703
of detail with which to specify what
constitutes activities that are similar in
nature.
Compliance With the Section 404(b)(1)
Guidelines
Several commenters said that the
NWPs do not comply with the 404(b)(1)
Guidelines. One commenter said that
the Corps has no factual basis to
conclude that significant degradation of
waters of the United States has not
occurred, which is required to be in
compliance with the Guidelines. This
commenter recommended withdrawing
the NWPs or replacing them with state
program general permits. One
commenter stated that the NWPs do not
comply with the 404(b)(1) Guidelines
because they authorize discharges into
special aquatic sites.
When we issue the NWPs, we fully
comply with the requirements of the
404(b)(1) Guidelines at 40 CFR 230.7,
which govern the issuance of general
permits under Section 404 of the Clean
Water Act. For each NWP that
authorizes discharges of dredged or fill
material into waters of the United
States, the decision document contains
a 404(b)(1) Guidelines analysis. Section
230.7(b) of the 404(b)(1) Guidelines
requires a ‘‘written evaluation of the
potential individual and cumulative
impacts of the categories of activities to
be regulated under the general permit.’’
Since the required evaluation must be
completed before the NWP is issued, the
analysis is predictive in nature. The
estimates of potential individual and
cumulative impacts, as well as the
projected compensatory mitigation that
will be required, are based on the best
available data from the Corps district
offices, including the past use of NWPs.
In our decision documents, we also
used readily available national data on
the status of wetlands and other aquatic
habitats in the United States, and the
foreseeable impacts of the NWPs on
those waters.
The process for issuing state
programmatic general permits is similar
to the process for issuing NWPs,
including the use of information to
support decisions. The 404(b)(1)
Guidelines analysis for state
programmatic general permits is also
predictive. Given those similarities,
compliance with the 404(b)(1)
Guidelines is not different for state
programmatic general permits versus
NWPs.
Despite the fact that many NWPs
authorize discharges of dredged or fill
material into special aquatic sites, they
are still in compliance with the
404(b)(1) Guidelines. Section 230.7 of
the 404(b)(1) Guidelines does not
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
prohibit the use of NWPs to authorize
discharges of dredged or fill material
into special aquatic sites. Many NWPs
contain additional provisions to protect
special aquatic sites. For example,
several NWPs specifically require preconstruction notification for proposed
discharges of dredged or fill material
into special aquatic sites (e.g., NWP 13
for bank stabilization activities, NWP 14
for linear transportation projects, NWP
18 for minor discharges). As another
example, NWP 19 for minor dredging
activities, does not authorize dredging
in coral reefs or dredging activities that
cause siltation that degrades coral reefs.
General condition 22, designated critical
resource waters, applies the
prohibitions in paragraph (a) and the
notification requirement in paragraph
(b) to wetlands (a special aquatic site)
adjacent to critical resource waters.
Compliance With the National
Environmental Policy Act
Three commenters stated that the
NWPs do not satisfy the requirements of
the National Environmental Policy Act
(NEPA), as they do not adequately
consider indirect and cumulative effects
on global warming. One commenter said
that degradation in air quality from
burning coal from mining projects must
be addressed in an environmental
impact statement, and that the Corps
has to address the implications of
climate change on aquatic ecosystems.
Another commenter stated that the
scientific consensus on the impacts of
climate change has to be considered in
the renewal of the NWPs. One
commenter said the NWPs should take
into account ongoing federal efforts to
address the effects of climate change
through federal programs. These federal
programs address mitigation of climate
change (e.g., through reduction of
greenhouse gas emissions) and
adaptation to climate change (e.g., by
adjustments made to reduce
vulnerability resulting from changing
climate).
Although the Council on
Environmental Quality has made
available draft guidance on the
consideration of the effects of climate
change and greenhouse gas emissions,
and sought public comment on that
draft guidance, they have not issued any
final guidance specifically on how to
consider, in NEPA documents, the
indirect and cumulative effects Federal
agency actions have on climate change.
In the Council on Environmental
Quality’s October 2011 Progress Report
of the Interagency Climate Change
Adaptation Task Force entitled ‘‘Federal
Actions for a Climate Resilient Nation’’
adaptation is defined as ‘‘adjustment in
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
natural or human systems to a new or
changing environment that exploits
beneficial opportunities or moderates
negative effects.’’
A major cause of climate change is
emissions of greenhouse gases.
Activities authorized by NWPs have
little direct, indirect, or cumulative
effects on climate change and the
emission of greenhouse gases. There
may be brief emissions of greenhouse
gases during the construction of
activities authorized by NWP,
specifically discharges of dredged or fill
material into waters of the United States
or structures or work in navigable
waters of the United States. Any
greenhouse gas emissions that occur
other than as a result of the discharge of
dredged or fill materials are outside of
the Corps NEPA scope of analysis
because the Corps does not have the
legal authority to control those
emissions. The degradation of air
quality caused by burning coal is not the
result of a discharge of dredged or fill
material and therefore is outside the
Corps legal authority. The issuance of a
Corps permit is designed to ensure that
any discharges of dredged or fill
material into waters of the United States
associated with such mining comply
with the Clean Water Act. A Corps
permit does not authorize coal mining
per se, and therefore the effects of coal
mining that do not result from a
discharge of dredge or fill material to
waters of the United States generally are
beyond the Corps NEPA scope of
analysis.
The effects of climate change on
aquatic ecosystems are a much broader
issue than the effects on the aquatic
environment caused by activities
authorized by NWPs. The effects of
climate change on hydrology and
extreme events are difficult to project.
The effects will vary by location and the
sensitivity of resources to changes in
hydrology and extreme events. The
timeframe used to project hydrologic
changes will also affect the evaluation.
For activities with minimal adverse
effects on the aquatic environment that
are eligible for authorization by the
NWPs, the Corps believes that any
necessary adaptation to climate change
is appropriately addressed through land
use planning and zoning, which is the
primary responsibility of state, tribal,
and local governments. Activities
authorized by NWPs may be part of
state, tribal, or local adaptation efforts to
mitigate the effects of climate change.
On October 1, 2011, the Corps issued
updated guidance on sea level change
considerations for Civil Works Program
(Engineer Circular 1165–2–211). The
current Engineer Circular applies to
PO 00000
Frm 00005
Fmt 4701
Sfmt 4703
10187
Corps Civil Works activities, but not to
the Regulatory Program. As stated on
page 25 of its ‘‘Climate Change
Adaptation Plan and Report 2011’’
(available at: https://
www.corpsclimate.us/
adaptationpolicy.cfm), the Corps
expects to make larger changes in the
next update of the Engineer Circular,
‘‘and the regulatory program will be
added following appropriate
consultation.’’
Compliance With the Endangered
Species Act
One commenter acknowledged the
Corps 2007 efforts to pursue
programmatic consultation for the NWP
program with the U.S. Fish and Wildlife
Service and the National Marine
Fisheries Service to ensure compliance
with the Endangered Species Act (ESA),
stating that failure to complete
consultation violates the ESA, as well as
Section 404(e) of the Clean Water Act.
Two commenters stated that the Corps
has a requirement to complete these
consultations prior to the issuance of
the NWPs.
We have reinitiated programmatic
Section 7 Endangered Species Act
consultation for the NWPs. If this
consultation is not completed prior to
the effective date of these NWPs, district
engineers will consult, as necessary on
a case-by-case basis with the U.S. Fish
and Wildlife Service and National
Marine Fisheries Service in accordance
with general condition 18, endangered
species. Division engineers may also
impose regional conditions on any of
the NWPs to facilitate compliance with
the requirements of the Endangered
Species Act.
Compliance With Section 304(d) of the
National Marine Sanctuaries Act
One commenter stated that the
proposed NWPs must comply with
Section 304(d) of the National Marine
Sanctuaries Act (NMSA). Section
304(d)(1))(A) of the NMSA states that
‘‘Federal agency actions internal or
external to a national marine sanctuary,
including private activities authorized
by licenses, leases, or permits, that are
likely to destroy, cause the loss of, or
injure any sanctuary resource are
subject to consultation with the
Secretary.’’ The regulations for
implementing section 304(d) are found
at 15 CFR 922.187, and those
regulations state that the Federal agency
consultation should be conducted with
the Director of the marine sanctuary.
The consultation may be conducted
with Endangered Species Act section 7
consultation.
E:\FR\FM\21FEN2.SGM
21FEN2
10188
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
District engineers that have NOAAdesignated marine sanctuaries within
their geographic area of responsibility
should consult with the Director of the
marine sanctuary to determine which
NWP activities require activity-specific
consultation under Section 304(d) of the
NMSA. Regional conditions should be
adopted where necessary to ensure
compliance with the requirements of
section 304(d).
New Nationwide Permits
We received several suggestions for
the establishment of new NWPs for
various activities. Two commenters
suggested developing an NWP to
authorize activities associated with
linear gas facility infrastructure based
on the Federal Energy Regulatory
Commission’s (FERC) blanket
certification program that would allow
the industry to undertake routine
activities without the need to obtain a
case-specific authorization from FERC
for each project. One commenter
recommended issuing an NWP to
authorize activities associated with
controlling nuisance and exotic plant
species and another NWP to authorize
activities for innovative mitigation
proposals. One commenter said that an
NWP should be developed to authorize
the beneficial reuse of dredged material,
for up to 10,000 cubic yards of material.
Another commenter recommended
adding an NWP to authorize discharges
of dredged or fill material to raise dam
elevations to increase pool elevations of
public water supply reservoirs to
increase potable water supplies and
wetlands.
We believe that existing NWPs such
as NWPs 12, 3, and 39 are sufficient to
provide general permit authorization for
gas utility lines and associated
infrastructure. Discharges of dredged or
fill material into waters of the United
States or work in navigable waters of the
United States associated with the
removal of nuisance or exotic plant
species may be authorized by NWP 27,
aquatic habitat restoration,
establishment, and enhancement
activities. Innovative mitigation
proposals may also be authorized by
NWP 27, as long as those activities
result in net increases in aquatic
resource functions and services and
satisfy the other terms and conditions of
that NWP. We believe that the beneficial
reuse of dredged material, especially at
such large quantities, is more
appropriately evaluated through the
individual permit process, to more
thoroughly consider effects on existing
aquatic resource functions already being
provided in the waters where the reused
dredged material might be placed.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
Waivers of Certain NWP Limits
We proposed to modify the language
concerning the use of waivers in NWPs
13, 29, 36, 39, 40, 42, and 43 by
clarifying that a waiver may be granted
only after the district engineer makes a
written determination concluding that
the discharge will result in minimal
adverse effects and sets forth the basis
for that determination. We also
proposed to apply the modified waiver
language to NWPs 21, 44, and 50, as
well as to the two proposed new NWPs.
Some commenters supported the
proposed modifications.
Many commenters said the proposed
changes would allow district engineers
too much discretion, and there should
be no waivers of NWP limits. One
commenter stated there was not a need
for waivers because many of the NWPs
already require pre-construction
notification and the changes make the
NWPs more difficult to obtain. The
commenter said the waivers create an
additional paperwork burden and
provide no environmental benefits.
Many commenters objected to the
proposed waivers, stating that they
imply that ephemeral and intermittent
streams are considered lower in their
function and value to the aquatic
environment and are provided less
protection than perennial streams.
These commenters discussed the
importance of ephemeral and
intermittent streams to overall
watershed integrity and to water quality
and stated there is no scientific
evidence to support the position that the
use of waivers will result in only
minimal impacts. One commenter said
that before a waiver is issued, there
should be analysis of cumulative effects
to the watershed. Several commenters
stated that the use of waivers in states
with arid and semi-arid ecosystems does
not properly take into account the
importance of headwater streams in
these ecosystems and could result in
more than minimal individual and
cumulative effects.
The basic requirement for general
permits, including NWPs, is that they
may only authorize activities that result
in minimal individual and cumulative
adverse effects on the aquatic
environment. Section 404(e) of the
Clean Water Act and the regulations
relevant to the issuance of the NWPs
(e.g., 33 CFR part 330 and 40 CFR 230.7)
do not mandate a single approach to
satisfying that basic requirement. The
terms and conditions of the NWPs,
including acreage, linear foot, and cubic
yard limits and allowing the use of
certain NWPs in specific types of
waters, are intended to limit NWPs
PO 00000
Frm 00006
Fmt 4701
Sfmt 4703
activities so that they do not result in
more than minimal adverse effects on
the aquatic environment. Division
engineers have the authority to impose
regional conditions on NWPs to restrict
or prohibit their use in certain waters or
other geographic areas. Another
important tool is pre-construction
notification, which provides for district
engineers to review proposed NWP
activities to ensure that they will result
in minimal adverse effects. In response
to a pre-construction notification, a
district engineer may add activityspecific conditions to the NWP
authorization to further minimize
adverse effects to the aquatic
environment. For those NWPs that
allow district engineers review preconstruction notifications and issue
written waivers of certain limits, such as
the 300 linear foot limit for the loss of
intermittent and ephemeral stream bed,
the NWP activity must still satisfy the
statutory and regulatory requirements
for general permits. The waiver process
does not make the NWP process more
difficult. Instead, it provides an
important tool for districts to efficiently
authorize activities with minimal
adverse effects on the aquatic
environment after making a written
determination that the activity satisfies
the NWP requirements.
We recognize the importance of
intermittent and ephemeral streams and
the waiver process for certain NWPs
requires district engineers to make
activity-specific evaluations of the
intermittent or ephemeral streams
proposed to be filled or excavated before
deciding whether to waive the 300
linear foot limit. To issue a waiver, the
district engineer must make, and
document, a minimal adverse effects
determination, which as discussed
above, is consistent with the statutory
and regulatory requirements for general
permits. As part of the analysis, the
district engineer must consider the
individual and cumulative adverse
effects on the aquatic environment on a
watershed basis, or for another
appropriate geographic area, such as an
ecoregion. For those activities in arid
and semi-arid regions, district engineers
will use local criteria as well as their
knowledge of arid and semi-arid
ecosystems to make decisions on preconstruction notifications for proposed
activities that might be eligible for
waivers. The basis for any waiver,
including appropriate consideration of
individual and cumulative effects, will
be documented in the district engineer’s
written determination.
Several commenters noted concern
with the 45-day pre-construction
notification review period to provide a
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
decision whether to grant or deny the
waiver. One commenter noted the
applicant can proceed without
authorization if the Corps fails to
respond to a waiver request within the
45 day time limit. Several commenters
expressed concern with the additional
time and the expense that could be
incurred by the applicant who must
wait for the waiver decision and written
determination.
We believe that the 45-day preconstruction notification review period
is sufficient for district engineers to
make their written determinations on
whether to issue waivers of the
applicable limits for certain NWPs. The
text of the NWPs that allow waivers of
certain limits clearly states that the
waivers must be made by the district
engineer in writing. In addition,
paragraph (a)(2) of general condition 31,
pre-construction notification, says that
if a proposed activity requires a written
waiver to exceed specified limits of an
NWP, the permittee may not begin that
activity until the district engineer issues
the waiver. The 45-day pre-construction
notification review period still applies
to pre-construction notifications that
involve requests to waive specific limits
of an NWP, but the project proponent
may not proceed with the NWP activity
if a written waiver is needed and the
district engineer did not provide a
written waiver by the time the 45-day
review period ends. The Corps will
make every effort to act on waiver
requests within the 45-day review
period. If a prospective permittee is
concerned that a written waiver will not
be issued within the 45-day preconstruction notification review period,
then he or she has the option of
modifying the proposed activity so that
it does not exceed any specified limit of
the applicable NWP and does not
require a written waiver.
Many commenters said that specific
criteria should be applied to the waiver
process to ensure proposed activities
result in minimal individual or
cumulative adverse effects on the
aquatic environment. One commenter
stated that the waivers provide little
incentive to minimize impacts. Another
commenter said that water quality
certification cannot be issued for NWPs
that have limits that can be waived by
district engineers because the state
cannot certify that those activities meet
state water quality standards. One
commenter said that when waivers are
issued by district engineers, the district
engineer must include a fact-specific
basis to support his or her finding.
The criteria that are to be applied to
requested waivers of specified limits for
certain NWPs are the same general
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
criteria that are to be used to make any
minimal adverse effects determination
for the NWPs. Criteria that are to be
used to make minimal adverse effects
determinations are provided in
paragraph (1) of Section D, District
Engineer’s Decision. The waivers still
provide incentives to minimize impacts
because the NWP authorization
threshold (i.e., activities must result in
minimal individual and cumulative
adverse effects on the aquatic
environment) is lower than the
authorization threshold for individual
permits (e.g., the proposed activity is
not contrary to the public interest and,
if it involves discharges of dredged or
fill material into waters of the United
States, it complies with the 404(b)(1)
Guidelines). In other words, a waiver
cannot be granted if the activity does
not meet the minimal effects threshold,
and applicant cannot proceed without
the Corps’ written determination.
Applicants who submit waiver requests
run the risk that the waiver will be
denied, and valuable time will be lost in
obtaining Department of the Army
authorization. Thus, it is in the
applicant’s interest to modify the
proposed activity if possible to avoid
exceeding a threshold that requires a
waiver, and especially to avoid
submitting waiver requests for projects
that will in fact have more than minimal
adverse effects. States can issue water
quality certifications for NWPs based on
the specified acreage, linear foot, or
cubic yard limits, and require
individual water quality certifications
for losses of waters of the United States
that exceed the specified limits and
must be waived in writing by district
engineers. The written waiver
determinations prepared by the district
engineer have to be activity-specific,
and explain the factual basis of the
waiver.
Several commenters said that the
additional information required for a
request for a waiver and the requirement
to use of a functional assessment
method that is available and practicable
would impose a significant
documentation obligation on Corps
staff.
The NWPs do not impose additional
information requirements for requests
for waivers of specific limits of NWPs.
In addition, there is no requirement to
use functional assessments to make
decisions on waiver requests. The
sentence in paragraph (1) of Section D,
District Engineer’s Decision, on the use
of functional assessments to make
minimal effects determinations, states
that those methods ‘‘may’’ be used if
they are available and practicable to use.
However, the Corps does agree that
PO 00000
Frm 00007
Fmt 4701
Sfmt 4703
10189
there must be a factual basis for the
waiver (which may entail the use of a
functional assessment methodology,
among other possible approaches) and
documenting this does impose an
additional obligation on the Corps.
Applicants should provide the district
engineer as much factual information as
possible to support the waiver request
and facilitate the district engineer’s
determination.
Several commenters supported the
proposed changes requiring agency
coordination and a written decision.
Several commenters said that all
appropriate state and Federal resource
agencies should be provided an
opportunity to comment on requests for
waivers. One commenter stated there is
no need for additional agency
coordination unless specific resource
issues are identified, such as
compliance with the Endangered
Species Act or the National Historic
Preservation Act.
We have modified the proposed
provision requiring agency coordination
for pre-construction notifications
involving losses of greater than 1,000
linear feet of intermittent and ephemeral
stream bed, to require agency
coordination for all pre-construction
notifications requesting a waiver of the
300 linear foot limit for filling or
excavating intermittent or ephemeral
streams (see paragraph (d)(2) of general
condition 31, pre-construction
notification). Under this agency
coordination process, district engineers
will solicit comments from the agencies
to assist in making the written minimal
adverse effects determination necessary
for a waiver of the 300 linear foot limit
to take effect. Compliance with the
Endangered Species Act and the
National Historic Preservation Act is
addressed by general conditions 18 and
20, respectively.
One commenter said that the loss of
stream bed should be defined and the
300 linear foot limit should be reduced
to 150 linear feet of loss of stream bed
for those NWPs. Another commenter
suggested reducing the linear foot limit
for loss of stream bed to 50 linear feet.
One commenter stated that the 300
linear foot limit should not apply to
ephemeral streams. One commenter said
that waivers should be allowed for
losses of perennial streams if the
adverse effects are determined to be
minimal and the perennial stream is
limited in its aquatic function.
The loss of stream bed is defined in
‘‘loss of waters of the United States’’ as
the linear feet of stream bed that is filled
or excavated. We believe the 300 linear
foot limit is appropriate to ensure that
losses of stream beds result in minimal
E:\FR\FM\21FEN2.SGM
21FEN2
10190
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
404 of the Clean Water Act and reflect
the Corps and EPA’s flawed broad
interpretation of what constitutes a
water of the United States, specifically
for ephemeral streams. Most
commenters said the proposed NWPs
would result in an expansion of Clean
Water Act authority and jurisdiction
that would have a negative impact on
the nation’s economy by creating
excessive burdens on developers,
farmers, and Corps staff. Another
commenter said the Corps should not
assert jurisdiction over isolated mining
pits.
The NWPs do not assert jurisdiction
over waters and wetlands. Rather, the
NWPs are a form of Department of the
Army authorization to comply with the
permit requirements of Section 404 of
the Clean Water Act and/or Section 10
of the Rivers and Harbors Act of 1899.
Nationwide permits issued under the
authority of Section 404 of the Clean
Water Act authorize discharges of
dredged or fill material into waters of
the United States. Nationwide permits
issued under the authority of Section 10
of the Rivers and Harbors Act of 1899
authorize structures or work in
navigable waters of the United States.
Determining the geographic jurisdiction
under the Clean Water Act (i.e.,
identifying waters and wetlands that are
waters of the United States) is a separate
process than the NWP authorization
process. Likewise, identifying navigable
waters of the United States for the
purposes of geographic jurisdiction
under Section 10 of the Rivers and
Harbors Act of 1899 is a different
process than the NWP authorization
process. These NWPs do not expand
either geographic jurisdiction or
activities-based jurisdiction under the
Clean Water Act. Activity-based
jurisdiction under the Clean Water Act
is determined by applying the
appropriate regulations from 33 CFR
part 323. These NWPs continue to
provide a streamlined process for
obtaining authorization for activities
that require Department of the Army
permits under either Section 404 of the
Clean Water Act and/or Section 10 of
the Rivers and Harbors Act of 1899.
Determining whether isolated mining
pits are subject to Clean Water Act
Clean Water Act Jurisdiction
jurisdiction is a case-specific inquiry to
be made by applying the appropriate
Many commenters cited the U.S.
Supreme Court decisions issued in 2001 regulations and guidance. A project
proponent or landowner may contact
and 2006, for Solid Waste Agency of
the Corps district office that has the
Northern Cook County v. U.S. Army
responsibility for that region of the
Corps of Engineers and Rapanos v.
United States (Rapanos), as well as other country and request a jurisdictional
determination for an isolated mining pit
court decisions, and said that the
or any other area that might be
proposed NWPs exceed the Corps
considered a water or wetland. The
jurisdictional authority under Section
sroberts on DSK5SPTVN1PROD with NOTICES
adverse effects on the aquatic
environment. Division engineers may
add regional conditions to an NWP to
reduce the linear foot limit to an amount
less than 300 linear feet. The 300 linear
foot limit should not be waived for
losses of perennial streams because they
function differently than intermittent
and ephemeral streams, and we believe
it will generally not be the case that
losses of more than 300 linear feet of a
perennial stream would constitute a
minimal adverse effect. We believe it
would not be a good use of Corps or
applicant resources to allow waiver
requests for perennial streams on the
remote chance that the adverse effects of
such an activity would be found to be
minimal. The functions provided by
perennial streams, intermittent streams,
and ephemeral streams differ, in terms
of ecological processes and duration.
Perennial streams provide aquatic
habitat functions year-round, while
intermittent streams provide aquatic
habitat during the months when water
is flowing in the stream channel, and
when hyporheic flow occurs during
drier months. Ephemeral streams
provide aquatic habitat functions only
for brief periods, because they have
flowing water only during, and briefly
after, precipitation events. Other
important stream functions, such as
sediment transport, nutrient cycling,
and energy transport also depend on the
presence of flowing water and, for some
of those functions, the presence of
aquatic organisms inhabiting those
waters. The other stream functions are
present year-round for perennial
streams, and for much of the year for
intermittent streams. In ephemeral
streams, sediment transport, nutrient
cycling, and energy transport functions
occur during brief periods or are absent.
The functional differences exhibited by
perennial, intermittent, and ephemeral
streams provide a scientific basis for not
allowing a waiver for perennial streams.
District engineers will make written
case-specific determinations on whether
to waive the 300-linear foot limit for
losses of intermittent and ephemeral
stream bed, based in part on the
considerations listed in paragraph (1) of
Section D, ‘‘District Engineer’s
Decision.’’
VerDate Mar<15>2010
20:03 Feb 17, 2012
Jkt 226001
PO 00000
Frm 00008
Fmt 4701
Sfmt 4703
Corps district will respond to that
request and inform the project
proponent or landowner of the status of
that water with respect to Clean Water
Act jurisdiction.
Comments on Administrative
Requirements
Executive Order 13211
One commenter stated that these
proposed regulations will cause coal
mines to cease operations and believe
the proposal is subject to Executive
Order 13211, Actions Concerning
Regulations That Significantly Affect
Energy Supply, Distribution, or Use.
Although we have made substantial
changes to NWP 21, some surface coal
mining activities will still be authorized
by this NWP. The changes to NWP 21
will not cause coal mines to cease
operations, because there are other
forms of Department of the Army
authorization available if the coal
mining activity involves discharges of
dredged or fill material into waters of
the United States. Project proponents
may apply for individual permits to
obtain Department of the Army
authorization for such activities. Any
activity that could have previously been
authorized under earlier versions of
NWP 21 would still be eligible for
authorization under an individual
permit. Thus, while there may be
additional paperwork burden for mine
operators, the Corps does not believe
that the changes in these permits will
have a significant impact on the supply,
distribution, or use of energy (e.g., coal).
Executive Order 13563
Several commenters stated that the
proposed NWPs are not consistent with
EO 13563 for ‘‘Improving Regulation
and Regulatory Review’’ because the
modifications to the NWPs would
impose numerous onerous conditions
and limitations on applicants.
The NWPs continue to provide a
streamlined process for authorizing
activities that require Department of the
Army permits under Section 404 of the
Clean Water Act and/or Section 10 of
the Rivers and Harbors Act of 1899. The
average processing times for standard
permit applications in Fiscal Year 2010
was 221 days, while the average
processing time for NWP preconstruction notifications and voluntary
requests for NWP verifications was 32
days. The terms and conditions of the
NWPs are necessary to ensure that the
NWPs comply with applicable statutes
and regulations, including the
requirement that only activities with
minimal adverse effects, both
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
individually and cumulatively, be
authorized by NWPs.
Water Quality Certification Issues
One commenter said that the Corps
should provide an opportunity for state
and Tribal water quality certification
agencies to participate early in the NWP
reissuance process, to reduce potential
conflicts during the water quality
certification process. Another
commenter asked for clarification
regarding enforcement of the NWPs, in
cases where a provisional NWP
verification is issued, but the permittee
proceeds with work without receiving
the individual water quality
certification. This commenter asked
whether the Corps or the state would
initiate an enforcement action. One
commenter objected to use of
provisional NWP verifications in cases
where water quality certification has not
yet been issued for a particular NWP
activity.
The current NWP reissuance process
provides sufficient opportunity to
reduce potential conflicts during the
water quality certification process.
States and Tribes begin their water
quality certification processes when the
proposal to reissue the existing NWPs
and issue new NWPs is published in the
Federal Register for public comment.
Water quality certification agencies are
encouraged to submit comments on the
NWP proposal. But it is important to
remember that each state and Tribe is
likely to have different water quality
standards, and the national terms and
conditions for the NWPs cannot address
those regional variations.
After the comments received in
response to the proposal are reviewed,
the final NWPs are developed. Once the
final NWPs are published in the Federal
Register, States and Tribes have another
opportunity to decide whether to issue
or deny water quality certification for
the NWPs. States and Tribes will have
90 days to make their water quality
certification decisions.
If water quality certification was
denied for an NWP, then the permittee
must obtain an individual water quality
certification or a waiver, even if the
Corps issued a provisional NWP
verification. The provisional NWP
verification merely informs the
prospective permittee that the Corps has
determined that the proposed activity
qualifies for NWP authorization, as long
as the permittee receives an individual
water quality certification or waiver.
The prospective permittee should
provide a copy of the individual water
quality certification to the Corps
district. The Corps has full authority to
pursue an enforcement action for not
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
obtaining an individual water quality
certification or waiver, which is a
violation of the terms of the permit.
Case-specific decisions on appropriate
enforcement actions are at the Corps
discretion. The provision for NWP
verification is an important tool to be
responsive to users of the NWPs, and to
inform them of their need to work with
the water quality certification agency to
comply with the requirements of
Section 401 of the Clean Water Act. The
provisional verification serves to inform
the applicant that all other requirements
for NWP verification have been satisfied
and allows the applicant to focus on
obtaining the required state
certifications.
Discussion of Comments
Nationwide Permits
NWP 1. Aids to Navigation. There
were no changes proposed for this NWP,
and no comments were received. This
NWP is reissued without change.
NWP 2. Structures in Artificial
Canals. There were no changes
proposed for this NWP. One commenter
recommended not reissuing this NWP
because a state will deny water quality
certification.
The potential for a state to deny water
quality certification for an NWP is not
a sufficient basis for not reissuing an
NWP. The water quality certification
process is independent of the decision
on whether to issue or reissue an NWP.
This NWP is reissued without change.
NWP 3. Maintenance. We proposed to
modify this NWP to clarify that stream
channel excavation immediately
adjacent to the structure or fill being
maintained is authorized under
paragraph (a) and does not require a
PCN. We also proposed to replace the
word ‘‘and’’ with ‘‘and/or’’ in paragraph
(b) to indicate that the activity does not
need to include the placement of new or
additional riprap to qualify for this
NWP.
Several commenters supported the
change to paragraph (a) to allow
excavation in a stream channel
immediately adjacent to a structure or
fill as part of the maintenance activity,
without requiring pre-construction
notification. Some commenters
specifically supported the ability to do
minor excavation within stream
channels to install a larger culvert or
bridge that would improve fish passage
without a pre-construction notification.
Two commenters asked which types of
stream channel modifications could be
authorized under paragraph (a). Another
commenter said that the proposed
modification does not adequately clarify
that a pre-construction notification is
PO 00000
Frm 00009
Fmt 4701
Sfmt 4703
10191
not required for stream channel
modification as discussed in the
proposed rule. This commenter
recommended that paragraph (a) state
that stream channel modification
immediately adjacent to the structure or
fill being maintained is authorized
without pre-construction notification.
One commenter suggested that
paragraph (a) include the removal of
material from within existing structures.
One commenter indicated that the scope
of activities considered as stream
channel modifications should be
clarified, because certain stream
channel modifications such as sediment
or debris removal and reestablishment
of the original bridge-stream alignment
are needed to maintain a safe crossing
with sufficient hydraulic capacity.
Another commenter indicated that
while stream channel modification is
restricted to the minimum necessary,
there should be a 300 linear foot impact
limit. One commenter did not support
the proposed modification, stating that
pre-construction notification should be
required for stream channel excavation
near a structure because excavation has
the potential to uncover unknown
archeological resources.
We have changed the text of
paragraphs (a) and (b) to clarify which
stream modifications fall under
paragraph (a) and which fall under
paragraph (b). The removal of material
from waters within, or immediately
adjacent to, the structure or fill are
authorized under paragraph (a) and do
not require pre-construction
notification. The removal of material
from waters that are not immediately
adjacent to the structure or fill, but
within the limits in paragraph (b), may
be authorized under paragraph (b). This
NWP authorizes only activities that
repair or return an activity to previously
existing conditions. We do not believe
it is necessary to place additional limits
on this NWP because the current limits
are sufficient to ensure minimal effects.
Paragraph (a) only authorizes minor
stream channel modifications necessary
to repair, replace, or rehabilitate the
structure or fill, which may include
minor deviations to account for changes
in materials, construction techniques,
requirements of other regulatory
agencies, or current construction codes
or safety standards. Such minor
deviations could be done to improve
conditions to facilitate aquatic species
movements. General conditions 20 and
21 address the protection of historic
properties and actions to be taken if
previously unknown remains or artifacts
are discovered during the maintenance
activity.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10192
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Several commenters recommended
adding the word ‘‘or stabilization’’ after
‘‘repair, rehabilitation, replacement’’ in
paragraph (a) to clarify that stabilization
activities are included in paragraph (a).
Two commenters requested that
practicability be considered with the
‘‘minimum necessary.’’ One commenter
requested that the NWP include the
requirements of other regulatory
agencies as a reason for allowing minor
deviations in a structure’s configuration
or filled area.
We do not believe it would be
appropriate to include stabilization
activities under paragraph (a) since
some stabilization activities may result
in more than a minor deviation in the
structure’s configuration or filled area.
District engineers already consider what
is practicable when reviewing proposed
NWP 3 activities, and we do not believe
it is necessary to provide additional
clarification. We agree that the
requirements of other regulatory
agencies is an appropriate basis for
making minor changes in a structure or
filled area during maintenance,
especially if those regulatory
requirements help protect aquatic
resources.
Several commenters stated that the
placement of new or additional riprap to
protect small structures be included in
paragraph (a). A commenter requested
clarification that the placement of pipe
liners and concrete repairs to flow lines
of pipes are examples of maintenance
activities authorized by this NWP. One
commenter expressed concern that
authorizing the expansion of existing
projects into waters of the United States
discourages avoidance and
minimization of adverse impacts and
violates the 404(b)(1) Guidelines.
Another commenter indicated that work
that is immediately adjacent to the
project is not maintenance and that the
work should be limited to the extent of
the original project.
The placement of riprap to protect a
structure or fill is more appropriately
authorized by paragraph (b) of this
NWP, after the district engineer reviews
the pre-construction notification. If the
installation of pipe liners or concrete
repairs to flow lines are necessary and
result only in a minor deviation to the
structure’s configuration or filled area, it
may be authorized under paragraph (a).
Paragraph (a) only authorizes minor
deviations to the structure or filled area
that are necessary to conduct the repair,
rehabilitation, or replacement activity,
and complies with the general condition
requiring on-site avoidance and
minimization.
One commenter said that the permit
should require that the Corps be
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
notified, within 12 months of the date
of the damage, for activities involving
the repair, rehabilitation, or replacement
of structures or fills destroyed or
damaged by storms, floods, fire or other
discrete events.
The repair, rehabilitation, or
replacement of structures or fills
destroyed or damaged by these types of
events does not require pre-construction
notification. This is because restoring a
structure or fill to its pre-event
configuration will not result in more
than minimal adverse effects relative to
the pre-event status quo. If a project
proponent wants a waiver of the twoyear limit, the district engineer can
issue a waiver if warranted, without
reviewing a pre-construction
notification.
Some commenters expressed
opposition over the proposed change
from ‘‘and’’ to ‘‘and/or’’ under
paragraph (b). They recommended
retaining the current language because
they indicated that making the change
to ‘‘and/or’’ would cause confusion as to
which provision of this NWP would be
used to authorize riprap placement. The
commenters also said that this change
would result in the regulation of
excavation activities that do not result
in more than incidental fallback.
Another commenter was concerned that
the change to ‘‘and/or’’ suggested that
the addition of riprap triggered preconstruction notification.
The use of the term ‘‘and/or’’ means
that paragraph (b) authorizes the
removal of accumulated sediments or
debris, the placement of new or
additional riprap to protect the
structure, or both activities. This NWP
authorizes the removal of accumulated
sediment and debris if that activity
involves a regulated discharge of
dredged or fill material. This NWP also
authorizes the removal of accumulated
sediments and debris in the vicinity of
existing structures from section 10
waters. If a project proponent seeks
authorization to place new or additional
riprap near the structure, then preconstruction notification is required in
accordance with paragraph (b) of this
NWP.
One commenter said that the use of
riprap should be discouraged and only
authorized if other options are not
possible. Another commenter suggested
placing a limit on the amount of riprap
that can be placed under paragraph (b).
One commenter stated that the
placement of new or additional riprap is
not maintenance and should not be
authorized by NWP 3. One commenter
recommended requiring mitigation
techniques, such as weep holes, when
PO 00000
Frm 00010
Fmt 4701
Sfmt 4703
steel sheet piling is used for the
maintenance activity.
Riprap may be necessary to protect
the integrity of these structures. We
have modified the next to last sentence
of paragraph (b) to clarify that new or
additional riprap may be placed to
protect the structure or ensure the safety
of the structure. In response to a preconstruction notification (which is
required for all placement of new or
additional riprap under paragraph (b) of
this NWP), best management practices
or other mitigation measures may be
required by the district engineer to
minimize adverse effect to the aquatic
environment.
One commenter said that this NWP
should not authorize maintenance
dredging and that NWP 19 should be
used instead. This commenter also
recommended adding a cubic yard limit
for the amount of dredging that is
authorized. Another commenter
recommended that the removal of
sediment should be limited to 100 feet
instead of 200 feet. One commenter
suggested increasing the linear foot limit
to 500 feet. One commenter also
suggested that the applicant be required
to provide information to ensure that
sediments proposed to be removed are
not contaminated.
Paragraph (b) may be used to
authorize the removal of accumulated
sediment and debris from section 10
waters, and the 200 linear foot limit is
appropriate to ensure minimal adverse
effects. District and division engineers
can condition this NWP to reduce the
limit to less than 200 linear feet.
Maintenance dredging for the purposes
of navigation may be authorized by
NWP 19 and may not be authorized by
this NWP. The only excavation
authorized by this NWP is excavation
necessary for the maintenance, repair,
rehabilitation, or replacement of the
structure, and then only within the
limits established in the permit. It is not
necessary to require contaminant testing
for the sediments to be removed as a
general condition of the permit, because
for many cases there is reason to believe
that no contaminants are present in the
material. If there is reason to believe
that contaminants are present, the
district engineer may require
contaminant testing and/or best
management practices to control the
release of contaminants on a casespecific basis.
One commenter objected to the
proposed removal of the words ‘‘[w]here
maintenance dredging is proposed’’
from the ‘‘Notification’’ paragraph.
Another commenter said that preconstruction notification should only be
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
required when maintenance dredging is
contemplated.
Pre-construction notification is
required for all activities covered under
paragraph (b). When a permittee
submits the pre-construction
notification for activities covered under
paragraph (b), they also must submit
information regarding the original
design capacities and configurations of
the outfalls, intakes, small
impoundments, and canals. The deleted
phrase is meant to clarify the
‘‘Notification’’ provision.
A commenter asked if the term
‘‘upland’’ means ‘‘above the ordinary
high water mark.’’ That commenter also
requested clarification as to what
constitutes ‘‘temporary’’ in terms of how
long temporary fills can be kept in
place. Another commenter asked for a
definition of ‘‘minor deviations’’ and
two commenters recommended that
‘‘immediately adjacent’’ be defined.
There may be wetlands landward of
the ordinary high water mark of a river
or other water of the United States, so
it would not be appropriate to define
‘‘uplands’’ as suggested in the previous
paragraph. Since some waters and
wetlands are not subject to Clean Water
Act jurisdiction, we have changed the
text of paragraph (b) to require all
dredged or excavated materials to be
deposited and retained in an area that
has no waters of the United States,
unless otherwise specifically approved
by the district engineer under separate
authorization. Waters of the United
States will be identified in accordance
with applicable laws, regulations, and
guidance, as discussed above, and is not
affected by the issuance of these NWPs.
What constitutes a temporary fill is at
the discretion of the district engineer.
Determining what is a minor deviation
and immediately adjacent is also at the
discretion of the district engineer. The
Corps believes this is appropriate
because it is difficult to identify bright
line definitions for these terms that are
applicable in all circumstances. If an
applicant is unsure whether a specific
activity qualifies, he or she should
consult the appropriate Corps district
office.
Several commenters said that preconstruction notification should not be
required for activities authorized by
paragraph (b), to reduce delays. Other
commenters requested removal of the
pre-construction notification
requirements for sediment and debris
removal, because the work is often
conducted immediately after storm
events when a timely response is critical
to public safety. Another commenter
also requested that no pre-construction
notification be required for activities
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
under paragraph (b), if the waters are
ephemeral or intermittent streams.
Other commenters said that preconstruction notification should be
required for all activities authorized by
this NWP.
We believe that the pre-construction
notification requirements for this NWP
are appropriate. Pre-construction
notification is required for those
activities that may have the potential to
cause more than minimal adverse effects
on the aquatic environment. Activities
authorized by paragraph (b) usually
involve larger impacts than those
authorized by paragraph (a) and
therefore warrant pre-construction
notification to ensure that those
activities will result in minimal adverse
effects on the aquatic environment.
One commenter suggested that this
NWP should require the use of best
management practices to avoid
sediment loading of waters. One
commenter suggested that paragraph (c)
should be conditioned to protect
downstream water quality and prohibit
sediment discharges. Two commenters
said that general condition 2 should not
apply to NWP 3 activities.
General condition 12 requires the use
of sediment and erosion controls to
minimize sediment inputs during
construction. General condition 2 does
apply to this NWP, to ensure that
aquatic life movements can continue
after the maintenance activity is
conducted.
One commenter said that Tribes
should be notified to avoid impacts to
tribal treaty natural resources and
cultural resources. Two commenters
said that this NWP should be
conditioned to allow fish migration to
continue. One of these commenters also
stated that these activities should not
restrict water flows or constrict
channels. One commenter said that this
NWP should be conditioned to address
slope stability to prevent overburden
material from going into the water.
Another commenter recommended that
all stream crossings span the bankfull
width and, in cases where the structures
have a bottom, the structure bottom
shall match stream slope.
District engineers have conducted
government-to-government consultation
with Tribes to determine which NWP
activities should be subject to projectspecific consultation to protect Tribal
treaty natural resources and cultural
resources. General Condition 18
specifies that no activity or its operation
may impair reserved tribal rights,
including, but not limited to, reserved
water rights and treaty fishing and
hunting rights. General condition 2
requires that NWP activities be
PO 00000
Frm 00011
Fmt 4701
Sfmt 4703
10193
constructed to maintain aquatic life
movements, and general condition 9
requires that water flows be maintained
to the maximum extent practicable. The
appropriate size for stream crossings
will be determined on a case-by-case
basis, to comply with the applicable
general conditions.
A commenter recommended an
addition to the ‘‘Note’’, which
references the section 404(f) exemption
for maintenance. This commenter
suggested that the note include
clarification as to who can use the
exemption for maintenance of irrigation
and drainage ditches.
The section 404(f) exemption for
maintenance of irrigation ditches and
drainage ditches can be used by anyone
that qualifies for the exemption. If a
particular activity does not qualify for
the exemption because of the recapture
provision in section 404(f)(2) or for any
other reason, NWP 3 may be used to
authorize the maintenance activity, if it
meets the terms and conditions of the
NWP.
This NWP is reissued with the
modifications discussed above.
NWP 4. Fish and Wildlife Harvesting,
Enhancement, and Attraction Devices
and Activities. There were no changes
proposed for this NWP. One commenter
suggested adding fish aggregating
devices to the list of devices and
activities authorized by this NWP. Fish
aggregating devices are man-made
objects used to attract ocean-going
pelagic fish. Before these devices,
commercial fishing used purse seining
to target surface-visible aggregations of
birds and dolphins, which were used as
a signal of the presence of tuna schools
below. However, the by-catch of
dolphins became a significant issue. The
demand for dolphin-safe tuna was a
driving force for fish aggregating
devices. Therefore, we concur with the
comment and have added that device to
this NWP. This NWP is reissued with
the modification discussed above.
NWP 5. Scientific Measurement
Devices. We proposed to modify this
NWP to require the removal of the
device and any associated structures or
fills at the conclusion of the study. We
also proposed to add meteorological
stations to the list of examples of the
types of devices authorized by this
NWP, as well as current gages and
biological observation devices.
One commenter suggested that each of
the listed devices be defined and have
footprint and height limitations.
Another commenter said that
meteorological stations should not be
authorized by this NWP. One
commenter supported adding
meteorological stations, current gages,
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10194
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
and biological observation devices as
examples of the types of devices
authorized by this NWP. Another
commenter stated the Corps should
define a maximum period required for
a meteorological tower study.
We do not believe it is necessary to
provide definitions for each of these
devices and add limits. These devices
are usually small in size and since most
of them are structures they do not
typically result in a loss of waters of the
United States. This NWP already has a
25 cubic yard limit for weirs and
flumes. Division engineers can
regionally condition this NWP to
establish additional limits, including
maximum time frames for studies. In
response to an NWP verification
request, district engineers may also
place limits on these devices and their
use.
One commenter suggests the Corps
clarify the requirements for the removal
of a scientific measurement device, and
suggested that the NWP not require
excavation to remove the entire
structure. This commenter also said that
cutting off the structure near the
substrate of the waterbody and leaving
the buried foundation may result in less
environmental damage during removal.
Another commenter said that where
meteorological towers are used for longterm data collection and preliminary
testing for wind turbines, those
meteorological towers would be
removed during the wind energy facility
decommissioning process. One
commenter stated that the device should
be removed ‘‘upon completion of the
use of the device to measure and record
scientific data.’’
We have modified the provision in
the NWP to require the removal of the
device when it will no longer be used
to measure and record scientific data.
Meteorological towers used in wind
energy generation facility preliminary
testing and operations could be left in
place until the facility is
decommissioned. We have also changed
the text to state that structures or fills
must be removed to the maximum
extent practicable, which would allow
the foundation to remain if removing
the foundation would cause more
adverse effects to the waters or wetlands
than leaving the foundation in place.
We also added the word ‘‘foundation’’
to the examples of structures or fills that
may be associated with a scientific
measurement device.
This NWP is reissued with the
modifications discussed above.
NWP 6. Survey Activities. We
proposed to modify this NWP to specify
how exploratory trenches are backfilled
by stating the work ‘‘must not drain a
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
water of the United States’’ and to
replace the 25 cubic yard limit for
temporary pads with a 1⁄10-acre limit.
Several commenters supported
changing the limit from 25 cubic yards
to 1⁄10-acre. Two commenters expressed
concern that removing the 25 cubic yard
limit would result in more than minimal
cumulative effects to aquatic resources.
One commenter recommended adding
wetland delineation sampling activities
to the list of examples of activities
authorized by this NWP. Several others
recommended adding conditions to
require removal of the temporary fills
and re-establishment of pre-construction
contours and reseeding of affected areas
after completion of work. One
commenter requested a definition of
‘‘temporary pad.’’ One commenter
recommended that exploratory
trenching should not be authorized
below the ordinary high water mark of
any waters of the United States.
We are changing the limit of this NWP
from 25 cubic yards to 1⁄10-acre. We
have added ‘‘sample plots or transects
for wetland delineations’’ as an example
of an activity authorized by this NWP.
General condition 13, removal of
temporary fills, requires temporary fills
to be removed in their entirety and the
area revegetated, as appropriate. We do
not believe it is necessary to define
‘‘temporary pad’’ for purposes of this
NWP, since it is simply a temporary fill
that must be removed upon completion
of the survey activity. We do not agree
that exploratory trenching should be
prohibited below the ordinary high
water mark since these activities result
in temporary impacts to the aquatic
environment.
This NWP is reissued with the
modification discussed above.
NWP 7. Outfall Structures and
Associated Intake Structures. We did
not propose any changes to NWP. One
commenter objected to the reissuance of
this NWP, stating that these activities
adversely affect aquatic vegetation or
areas designated as critical habitat for
fish foraging and spawning, through
increases in turbidity, discharges of
nutrients and contaminants, alteration
of near-shore areas, and scouring
vegetation within the plume. Another
commenter recommended that outfall
structures not be placed in wetlands or
constructed in such a manner that
would create shoreline pockets capable
of trapping debris. One commenter
recommended conditioning this NWP to
ensure that the outfall structure not
extend into the receiving water and
impair navigation. One commenter
suggested that for activities proposed to
occur on state-owned submerged lands,
PO 00000
Frm 00012
Fmt 4701
Sfmt 4703
a separate authorization would be
required from that state.
In waters that have been designated as
Essential Fish Habitat in accordance
with the Magnuson-Stevens Fishery
Conservation and Management Act,
consultation with the National Marine
Fisheries Service will be conducted for
proposed activities that may adversely
affect Essential Fish Habitat. That
consultation will often result in
conservation recommendations that will
protect habitat for fish foraging and
spawning. General condition 22,
designated critical resource waters, will
also reduce adverse effects to fish
foraging and spawning areas caused by
NWP activities in those critical resource
waters. Division engineers may
regionally condition this NWP to restrict
or prohibit its use in specific waters,
including those that provide important
habitat. In response to a preconstruction notification, district
engineers may also exercise
discretionary authority if the proposed
activity would result in more than
minimal adverse effects on the aquatic
environment, including vegetated
shallows and fish spawning and feeding
areas. These structures may be designed
so that they do not trap debris. General
condition 14, proper maintenance,
requires authorized structures and fills
to be properly maintained, which may
include periodic removal of debris from
outfall structures and associated intake
structures, to ensure that these
structures continue to function
properly, do not trap debris, and do not
cause more than minimal adverse effects
to nearshore aquatic environments.
Compliance with general condition 1,
navigation, will prevent adverse impacts
to navigation. Permittees are responsible
for obtaining any other Federal, state or
local permits that may be required.
The NWP is reissued without change.
NWP 8. Oil and Gas Structures on the
Outer Continental Shelf. We proposed
to modify this NWP to update the name
of the former Minerals Management
Service to the Bureau of Ocean Energy
Management Regulation, and
Enforcement (BOEMRE).
One commenter expressed support for
the proposed modification. One
commenter recommended that no oil
and gas structures or activities be
authorized through the nationwide
permit process.
After the proposal to reissue this NWP
was published, the Bureau of Ocean
Energy Management (BOEM) became
the agency responsible for issuing leases
for oil and gas structures on the outer
continental shelf. We have modified the
text of NWP 8 to reflect this change.
This NWP only authorizes structures
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
erected within areas of the outer
continental shelf leased by the Bureau
of Ocean Energy Management. The
general environmental concerns are
addressed in the required NEPA
documentation prepared by BOEM prior
to issuing a lease. The Corps role is
limited to reviewing impacts on
navigation and national security, as
stated in 33 CFR part 322.5(f).
This NWP is reissued as proposed.
NWP 9. Structures in Fleeting and
Anchorage Areas. There were no
changes proposed for this NWP, and no
comments were received. This NWP is
reissued without change.
NWP 10. Mooring Buoys. There were
no changes proposed for this NWP. One
commenter stated a notice to Tribes
needs to be provided to avoid adverse
effects to Tribal treaty fishing access.
One commenter recommends
prohibiting the use of this NWP in
‘‘downgraded shellfish harvest areas.’’
Another commenter said that the permit
should be conditioned to require
permittee’s to provide information on
the location of the mooring buoy,
including a site plan drawn to scale that
shows the distance of the buoy from the
shore, mark the Corps permit number on
the buoy, and a statement that the buoy
satisfies U.S. Coast Guard requirements.
One commenter suggested adding a
limit on the number of buoys installed
per acre, based on the number and size
of the moored vessels.
Division engineers can regionally
condition this NWP to prohibit its use
in areas where mooring buoys may
impact access to Tribal treating fishing
areas. General condition 18 states that
NWP activities cannot impair reserved
tribal rights. Division engineers can
impose regional conditions to restrict or
prohibit its use in shellfish harvesting
areas. We do not agree that preconstruction notification for the
activities authorized by this NWP is
necessary, to require prospective
permittees to submit detailed
information on the location of the
proposed mooring buoy, a detailed site
plan, and a statement that it complies
with U.S. Coast Guard requirements. All
applicable Coast Guard regulations must
be complied with independent of the
conditions in this NWP. We believe that
it is not necessary to limit this NWP, at
the national level, to install a particular
number of mooring buoys per acre.
Division engineers may also regionally
condition this NWP to impose such
restrictions.
This NWP is reissued without change.
NWP 11. Temporary Recreational
Structures. There were no changes
proposed for this NWP. One commenter
recommended requiring that structures
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
authorized under this NWP be removed
immediately after use ceases, instead of
the 30 days specified in the NWP.
The Corps believes that the current
requirements for the removal of
temporary structures are sufficient.
Where necessary, shorter time periods
for removal can be imposed through
regional conditioning or through special
conditions provided in activity-specific
NWP verifications.
The NWP is reissued without change.
NWP 12. Utility Line Activities. We
proposed to modify this NWP to clarify
how to calculate the loss of waters of the
United States for a single and complete
project that involves an access road.
This proposed change was intended as
a clarification of long-standing practice,
not a substantive revision.
Several commenters supported the
proposed change to this NWP. Another
commenter stated the proposed
clarification would severely restrict the
use of NWP 12, because it changes the
definition of single and complete
project. One commenter requested
further clarification of the intent and
applicability of the term ‘‘single and
complete’’ and suggested we replace it
with ‘‘single and complete linear
projects’’ wherever the former phrase is
found in NWP 12 since the NWP applies
to linear projects and their associated
facilities and activities. Two
commenters requested confirmation that
the calculation of impacts for purposes
of satisfying the NWP 12 threshold is
done separately for each crossing.
Another commenter objected to the
definition of ‘‘single and complete
project’’ at 33 CFR 330.2(i) and the NWP
definitions section and stated mitigation
should be required for utility lines that
result in the loss of greater than 1⁄2-acre.
This modification of the NWP does
not change the definition of single and
complete project and does not affect its
implementation, except to clarify that
only losses of waters of the United
States associated with a single and
complete project would be considered
when determining whether the acreage
limit or pre-construction notification
threshold is exceeded. However, it is
correct that the Corps long-standing
practice (which we are not changing)
has been to generally calculate impacts
for purposes of satisfying the 1⁄2-acre
threshold separately for each separate
and distant crossing, and we have
clarified this in the definitions section
by adding separate definitions that
explain how single and complete
projects are determined for linear and
non-linear projects. We do not agree that
in the text of this NWP the term ‘‘single
and complete project’’ should be
replaced with ‘‘single and complete
PO 00000
Frm 00013
Fmt 4701
Sfmt 4703
10195
linear project.’’ Although the vast
majority of utility lines are linear
projects where the crossings are at
separate and distant locations, and thus
considered separate single and complete
projects, there may be circumstances
where the separate crossings of a
waterbody are too close together to be
considered separate single and complete
projects, and one NWP authorization
would be evaluated for those closelyspaced crossings. Therefore, we have
retained the more generic term ‘‘single
and complete project’’ in the text of this
NWP. Other supporting components of
a utility line, such as substations, may
not be considered linear projects in
some circumstances. District engineers
may exercise discretionary authority
and require compensatory mitigation for
utility line activities that require preconstruction notification and result in
the loss of aquatic resources.
One commenter stated the Corps
should clarify that the only relevant
activity for purposes of NWP 12 is a
discharge of dredged or fill material into
waters of the United States. One
commenter said that no discharges
should be authorized in waters below
the ordinary high water mark or in areas
that provide fish habitat functions. This
commenter also said that utility lines
should be buried at least six feet below
the authorized federal channel depth.
One commenter stated that mechanized
land clearing of forested wetlands for
installation of utility lines should not be
authorized by NWP 12.
The activities authorized by this NWP
are not limited to discharges of dredged
or fill material. This NWP also
authorizes structures or work in
navigable waters of the United States
that require authorization under Section
10 of the Rivers and Harbors Act of
1899. We do not agree that discharges
should be prohibited in open waters,
below the ordinary high water mark.
Such activities often result in minimal
adverse effects on the aquatic
environment and qualify for general
permit authorization. Division engineers
can restrict or prohibit use of this NWP
in certain waters, through the approval
of regional conditions. The appropriate
depth a utility line should be buried
below a federal channel should be
determined on a case-by-case basis.
Mechanized landclearing of a forested
wetland in a utility line right-of-way
may only result in a conversion of
wetland type, and not result in
permanent loss of waters of the United
States. District engineers may require
compensatory mitigation to offset
permanent losses of wetland functions
when such mechanized landclearing
occurs in forested wetlands.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10196
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
One commenter stated that
authorizing the loss of 1⁄2-acre of waters
of the United States for each crossing
results in more than minimal adverse
environmental effects. Another
commenter said that the 1⁄2-acre limit
should apply to the entire utility line
project, because the cumulative effects
of the utility line must be considered.
One commenter stated that this NWP
should also limit stream impacts to 300
linear feet. Several commenters asked
whether the conversion of a forested
wetland to a scrub-shrub wetland
counts toward the 1⁄2-acre limit.
The 1⁄2-acre limit applies to each
crossing that is considered to be a
separate single and complete project,
because they are sited at distant
locations from other crossings that
constitute the linear project. Each
separate and distant crossing should be
evaluated to determine if it meets the
terms and conditions of the NWP, and
cumulative effects of the overall utility
line should be evaluated to determine if
the adverse cumulative effects on the
aquatic environment are more than
minimal and therefore do not qualify for
NWP authorization. Separate utility line
crossings are usually on different water
bodies, and may also be in widely
separated watersheds. Such factors
should be considered when assessing
cumulative impacts. The ‘‘Definitions’’
section provides further clarification on
single and complete projects. The
conversion of a forested wetland to a
scrub shrub wetland does not constitute
a permanent loss of waters of the United
States, and thus does not count towards
the acreage limit, even though it may
result in the permanent loss of certain
functions, which may require
compensatory mitigation.
One commenter said that some utility
lines and associated renewable energy
projects may have unintended negative
impacts on the Department of Defense
mission. For example, high voltage
transmission lines could potentially
interfere with long-range radar
surveillance, homeland defense, testing,
and training missions. This commenter
requested that pre-construction
notifications for NWP 12 activities
involving the construction of overhead
utility lines in waters of the United
States be coordinated with the
Department of Defense, by sending a
copy of the pre-construction notification
to the Department of Defense Siting
Clearinghouse. Department of Defense
Siting Clearinghouse staff will review
the pre-construction notification and
contact the project proponent if they
identify potential negative impacts to
Department of Defense operations,
testing, and training missions.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
We have added Note 4 to this NWP,
which states that a copy of the preconstruction notification will be
provided to the Department of Defense
Siting Clearinghouse if the proposed
activity involves an overhead utility line
constructed in waters of the United
States. This coordination process will
not interfere or delay the district
engineer’s decision on the preconstruction notification, which must
be made within the timeframes
specified in the NWP general
conditions. The coordination process
will consist of districts sending the
Department of Defense Siting
Clearinghouse copies of preconstruction notifications and NWP
verifications, and Clearinghouse staff
will work with project proponents to
address effects to military operations.
One commenter stated that the
definition of a utility line in the NWP
is too expansive and should not include
liquescent or slurry substances. This
commenter asked if utility lines could
also be used to transport waste
products. One commenter stated that
terms and conditions of the NWP
should require projects to use existing
trenches or cables whenever possible,
and require that sidecast material be put
back in place within 24 hours. One
commenter requested that temporary fill
be defined and that compensatory
mitigation should be required for
temporary fills left in place for two
years. One commenter said that
enforcing the time periods for temporary
side casting is too difficult. One
commenter requested more detail
regarding the circumstances under
which a district engineer would extend
the period of temporary side casting up
to a total of 180 days. One commenter
stated the side casting in areas with
known or probable sediment
contamination should be prohibited.
One commenter stated the placement of
excavated materials into any waterway
should be prohibited.
Water or sewer lines are generally
recognized to be utility lines, and are
used to transport liquid or slurry
substances. They may also be used to
transport waste products, such as
sewage or industrial byproducts. We do
not agree that existing trenches or cable
should be a requirement of this NWP,
since many new utility lines
constructed in waters of the United
States result in minimal adverse effects
on the aquatic environment. However,
project sponsors should consider the
use of existing trenches and cables
where practicable as one way of
avoiding or minimizing adverse impacts
to the aquatic environment, which is
required by general condition 23,
PO 00000
Frm 00014
Fmt 4701
Sfmt 4703
mitigation. It is not practicable to
require side cast material to be put back
into the original trench or pit within 24
hours, and we have retained the current
language concerning temporary side
casting. It is the district engineer’s
discretion on whether to extend the
period of temporary side casting. That
discretion would be based on the sitespecific environmental conditions, the
activity, practicability considerations,
and other factors. District engineers can
restrict or prohibit side casting in areas
where sediment contamination may be
a concern. Excavated materials are
generally not placed in flowing waters,
and should be retained in areas outside
of flowing waters with proper sediment
and erosion controls.
One commenter objected to
authorizing the expansion of utility line
substations, stating that those activities
should require individual permits and a
finding of compliance with the Clean
Water Act Section 404(b)(1) Guidelines
and public interest review.
The expansion of utility line
substations does not generally warrant a
full public interest review and activityspecific Section 404(b)(1) Guidelines
analysis since it is an expansion of an
existing facility. In response to a preconstruction notification, the district
engineer will review the proposed
expansion of a substation and exercise
discretionary authority if it would result
in more than minimal individual and
cumulative adverse effects on the
aquatic environment.
Two commenters stated the
construction of temporary access roads
will require a submerged lands
authorization and would require a
submerged land lease for long-term use.
The use of NWP 12 does not obviate
the need for the project proponent to
obtain any other federal, state, or local
permits that may be required, including
permits from states that hold title to
submerged lands.
One commenter said that this NWP
should have fewer pre-construction
notification thresholds to expedite
pipeline safety repairs and
infrastructure projects. One commenter
supported retaining the 1⁄10-acre
threshold pre-construction notification.
We believe all of the current preconstruction notification thresholds are
necessary because of the variety of
utility line activities authorized by NWP
12 (i.e., utility line construction,
maintenance, repair, and removal, the
construction, maintenance, or
expansion of utility line substations, the
construction or maintenance of
foundations for overhead transmission
lines, and the construction of access
roads) and to allow district engineers
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
the opportunity to review those
activities to determine whether they
will result in minimal adverse effects on
the aquatic environment. Pipeline
maintenance may be authorized by
NWP 3 or NWP 12, and use of NWP 3
would not usually trigger a preconstruction notification requirement.
Many pipeline maintenance activities
may also be authorized by NWP 12,
without pre-construction notification.
The 1⁄10-acre pre-construction
notification threshold remains in this
NWP.
One commenter recommended that
this NWP require the use of specific
equipment such as low ground pressure
equipment and wide tires to minimize
adverse effects to wetlands. Another
commenter said that this NWP should
be conditioned to require the use of best
management practices to reduce
sediment loads into waters. One
commenter stated that this NWP does
not require sufficient avoidance and
minimization of waters of the United
States. One commenter suggested
requiring the installation of barriers next
to utility line trenches to prevent
amphibians and reptiles from falling
into the trench and to reduce sediment
transport into waters of the United
States during precipitation events. One
commenter said that pipes installed
over rivers and streams should have
shut-off valves to minimize the potential
for discharges to occur if the pipe is
breached.
The use of equipment that minimizes
adverse effects to waters of the United
States is addressed by general condition
11, equipment, which requires
permittees to take measures to minimize
soil disturbance, such as placing heavy
equipment on mats when working in
wetlands, mudflats, or other waters.
Division or district engineers may
condition this NWP, either through the
regional conditioning process or
through activity-specific conditions
added to an NWP 12 authorization, to
require the use of best management
practices. General condition 23,
mitigation, requires permittees to design
and construct their activities to avoid
and minimize adverse effects to waters
of the United States. A requirement to
install barriers next to utility line
trenches, or the use of shut-off valves in
pipes constructed over waters, is more
appropriately addressed through the
regional conditioning process or
through activity-specific conditions
added to an NWP 12 authorization
during the review of a pre-construction
notification or NWP verification request.
One commenter stated that this NWP
could streamline the authorization of
offshore wind energy generation
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
facilities, but two of the terms and
conditions may be problematic. The first
is the prohibition against side casting
when sediments would be dispersed by
currents or other forces. The second is
the 1⁄2-acre limit, which may prohibit
use of this NWP to authorize the
installation of cables that transfer the
energy generated by wind turbines.
The transmission cable that runs from
an offshore wind energy generation
facility to a land-based facility or
distribution system may be constructed
so that the trench for the cable is
backfilled immediately after the cable is
laid into the trench. That immediate
backfilling would minimize dispersion
by currents or other forces in those
waters. The placing of a power
transmission cable on the sea bed is
considered a structure under our
regulations for implementing Section 10
of the Rivers and Harbors Act of 1899
(see 33 CFR 322.2(b)), and not a loss of
waters of the United States subject to
the 1⁄2-acre limit in NWP 12.
One commenter recommended
requiring coordination with Tribes to
avoid impacts to Tribal treaty natural
resources and cultural resources.
Another commenter said that
coordination with State Historic
Preservation Officers should be required
to protect historic properties.
Division engineers can regionally
condition this NWP to require
coordination with Tribes, to ensure that
this NWP does not adversely affect
Tribal treaty natural resources and
cultural resources. General condition
20, historic properties, addresses
compliance with the National Historic
Preservation Act, which requires
consultation for activities that have the
potential to cause effects to historic
properties, including tribal resources
that meet the definition of ‘‘historic
property.’’ General condition 17, tribal
rights, requires that no NWP activity or
its operation may impair reserved treaty
rights, such as reserved water rights and
treaty fishing and hunting rights.
One commenter requested
clarification that individual permits are
not automatically required for NWP 12
activities when a Corps district
participates as a cooperating agency for
an environmental impact statement.
Even though an environmental impact
statement may be prepared for a
particular utility line, the National
Environmental Policy Act process does
not prohibit the Corps from using NWP
12 to authorize the construction,
maintenance, repair, and removal of
utility lines and associated facilities in
waters of the United States, as long as
the activity complies with all applicable
terms and conditions and results in
PO 00000
Frm 00015
Fmt 4701
Sfmt 4703
10197
minimal individual and cumulative
adverse effects on the aquatic
environment. NEPA requires
consideration of all environmental
impacts, not only those to aquatic
resources, so there may well be
situations where aquatic impacts are
minimal even though environmental
impacts more generally are not. These
other environmental impacts would be
addressed by the lead agency preparing
the environmental impact statement.
The district engineer will exercise
discretionary authority to require an
individual permit for any utility line
activity that he or she determines does
not meet the terms and conditions of
NWP 12.
One commenter suggested modifying
Note 1 to limit submission of NWP 12
pre-construction notifications and
verifications to the National Oceanic
and Atmospheric Administration’s
National Ocean Service (NOS), since
NOS only produces charts for waters in
the coastal United States, Great Lakes,
and United States territories.
We have modified Note 1 to require
district engineers to send copies of NWP
12 pre-construction notifications and
verifications to NOS in those regions of
the country.
This NWP is reissued with the
modifications discussed above.
NWP 13. Bank Stabilization. We
proposed modifying this NWP by
removing the waiver provision in
paragraph (c) that allowed district
engineers to authorize bank stabilization
fills that exceeded one cubic yard per
running foot below the ordinary high
water mark or high tide line to
encourage the use of bioengineered
techniques for bank stabilization. To
conform with the proposed change to in
paragraph (c), we proposed to remove
the third pre-construction notification
threshold for bank stabilization fills that
exceeded one cubic yard per running
foot, since these fills would no longer be
allowed. We also proposed changing
this NWP to authorize temporary
structures and fills necessary for the
construction of bank stabilization
activities.
Many commenters recommended that
this NWP not be reissued, and stated
that all bank stabilization should be
evaluated under individual permit
procedures. One commenter asserted
that bank stabilization activities should
be authorized with NWP 3 in man-made
ditches and canals and NWP 13 in
natural waterways. Two commenters
said this NWP should not authorize new
bank stabilization activities. Some
commenters recommended modifying
this NWP so that it would not authorize
new vertical bulkheads and seawalls.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10198
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
One commenter stated that this NWP
does not result in minimal individual
and cumulative adverse effects on the
aquatic environment because these
activities accelerate coastal erosion and
retreat. Additional commenters said that
these activities result in more than
minimal individual and cumulative
effects. Some of these commenters said
that this NWP has more than minimal
adverse effects on low-order ephemeral
and intermittent streams. One
commenter said that this NWP should
not be applicable to both riverine and
lacustrine systems and recommended
that separate NWPs be developed that
would address the different erosional
processes in those systems. Several
commenters stated that this NWP
should not be reissued because of
adverse effects to coastal environments,
as well as sea turtles and other
endangered species and their habitats.
Another commenter recommended that
bank stabilization only be permitted by
this NWP if it is part of a habitat
improvement project or has other net
improvements in aquatic function.
The terms and conditions for this
NWP are appropriate for limiting bank
stabilization activities so that they have
minimal individual and cumulative
effects on the aquatic environment,
while allowing landowners and other
entities to protect their property and
safety. NWP 3 only authorizes minor
amounts of rip rap associated with
maintenance activities. It is more
appropriate to authorize bank
stabilization activities in man-made
waterways through NWP 13. In many
coastal waters and rivers it is necessary
to utilize hard bank protection
structures, because wave energy and
currents are too strong for
bioengineering or other techniques to
successfully prevent or reduce erosion.
We do not agree that there should be
separate NWPs developed to authorize
bank stabilization activities in riverine
and lacustrine waters. Bank stabilization
that may affect endangered or
threatened species require preconstruction notification and
compliance with general condition 18,
endangered species. We also do not
agree that this NWP should be limited
to habitat improvement projects,
because it is often necessary to install
bank stabilization structures and fills to
protect property and safety.
Two commenters said that NWP 13
should not be reissued because it
authorizes activities that may prevent
retreat that would be necessary to adapt
to sea level rise caused by climate
change. These commenters also said
that sea level rise needs to be
considered in the decision on whether
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
to reissue this NWP. These commenters
also stated that the structures and fills
authorized by NWP 13 exacerbate
erosion in areas where sea level rise will
occur.
Coastal and riparian areas are
dynamic landscapes. They are
constantly changing as a result of
erosional and depositional processes.
Landowners seek Department of the
Army authorization for bank
stabilization activities to protect their
property and provide safety. The
purpose of NWP 13 activities is to
protect land on which residences,
commercial buildings, infrastructure,
and other features are located. The
Corps regulations recognize that a
riparian landowner has a right to protect
his or her property from erosion (see 33
CFR 320.4(g)(3)). When a district
engineer evaluates a permit application
for bank stabilization activities,
including pre-construction notifications
for NWP 13 activities, he or she
considers the current environmental
conditions at the site of the proposed
activity, as well as the reasonably
foreseeable direct, indirect, and
cumulative effects that might be caused
by the proposed activity. At the present
time, there is a considerable amount of
uncertainty surrounding climate change,
and any associated sea level rise that
may occur as a result of climate change.
To the extent there is reliable
information about projected sea level
rise during the reasonably foreseeable
future in the vicinity of a proposed
activity, the district engineer will take
that information into account when
determining whether a proposed NWP
13 activity will have minimal individual
and cumulative adverse effects on the
aquatic environment. We do not agree
that the structures and fills authorized
by NWP 13 will accelerate erosion in
areas affected by changing sea level rise
caused by climate change. The bank
stabilization structures and fills
authorized by this NWP must be
properly designed, so that they have
minimal individual and cumulative
adverse effects on coastal and riparian
erosion and deposition processes. As
sea level rise occurs, bank stabilization
activities may no longer be effective,
and it may be necessary for landowners
to relocate.
Two commenters suggested limiting
all projects to a maximum length of 500
linear feet, except for allowing
bioengineering projects to exceed that
length on a case-specific basis if the
district engineer waives that limit. One
commenter recommended not allowing
vertical bulkheads longer than 500 feet.
One commenter recommended limiting
replacement of vertical bulkheads and
PO 00000
Frm 00016
Fmt 4701
Sfmt 4703
seawalls to a maximum length of 200
feet. Another commenter recommended
a 300 linear foot maximum project
length for shoreline protection on
coastal areas or lakes. One commenter
suggested a 300 linear foot maximum
length for bioengineering projects and a
150 foot maximum length for all other
bank stabilization projects. Two
commenters requested clarification
regarding project length in paragraph (b)
as it relates to activities that stabilize
both banks (left and right) of a stream.
Many commenters supported the
district engineer waiver for the 500
linear foot limit for any projects.
The limits in this NWP are sufficient
to ensure that the NWP authorizes only
those activities that have minimal
adverse effects on the aquatic
environment, although division
engineers may regionally condition the
NWP to reduce those limits to account
for local environmental conditions and
the ecological functions and services
provided by waters of the United States
in those areas. For streams, the linear
foot limit in paragraph (b) applies to a
single and complete project for the bank
stabilization activity measured along the
length of the stream segment, which
may involve discharging dredged or fill
material along either one or both stream
banks. We have retained the ability for
district engineers to waive the 500
linear foot limit.
One commenter requested a definition
for bank stabilization. Many
commenters asked for a definition of
bioengineering. One commenter said
that bioengineering techniques should
include living plant material and soil as
the primary structural components to
reinforce soil and to stabilize slopes.
One commenter recommended requiring
native vegetation in bioengineering
projects where vegetation is the primary
or secondary component of a project.
We do not believe that a definition of
bioengineering is necessary because
there is a wide variety of bioengineering
techniques and project proponents and
district engineers generally understand
what it means in a local context. It is not
possible at the national level to envision
every possible variation of technique
and materials that would reasonably fit
within the meaning of this term, but
generally bioengineering involves the
use of a combination of vegetation and
hard materials instead of only hard
materials such as rip-rap for bank
stabilization. Also, as explained below,
the final NWP does not make a
distinction between bioengineering and
other bank stabilization techniques. We
agree that bioengineering, for the
purposes of bank stabilization, includes
providing protection from erosion and
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
providing habitat for aquatic species.
We also agree that bioengineered
techniques can slow erosion rates and
can have beneficial effects on habitat for
macroinvertebrates and fish which is
why we proposed to modify this NWP
to encourage greater use of this
technique.
Several commenters recommended
the NWP encourage the use of natural
materials over riprap. One commenter
said that only native plant species
should be used for bioengineered bank
stabilization. Another commenter
recommended using natural stream
design methods for erosion prevention.
Several commenters objected to the
placement of plant material in waters of
the United States, and also objected to
the planting of willows and similar
species in and along waterways because
these types of woody plants clog
waterways and cause maintenance
problems at bridge and culvert
crossings.
Division engineers can regionally
condition this NWP to encourage
bioengineering or the use of natural
materials for bank stabilization in
waters subject to lower energy waves
and currents. The use of plant materials
as a component of a bank stabilization
activity can have beneficial
environmental effects, such as providing
shading and habitat for near-shore
organisms, or for riparian ecosystems.
Proper maintenance should be done to
remove plants that colonize waterways,
especially at culverts or bridges. We
have added a provision to this NWP
stating that if bioengineering or
vegetative bank stabilization is used,
invasive plant species should not be
used, because Executive Order 13112,
Invasive Species, states that agencies
should not ‘‘authorize, fund, or carry
out actions that it believes are likely to
cause or promote the introduction or
spread of invasive species in the United
States or elsewhere.’’ The Executive
Order states there are economic,
ecological, and human health impacts
that are caused by invasive species, and
we believe that invasive species should
not be used for bioengineering bank
stabilization activities authorized by
this NWP because of the adverse
environmental effects those species can
cause.
Many commenters supported the
proposed modification of paragraph (c)
to only allow bioengineering projects to
exceed one cubic yard per running foot,
and to not allow waivers from the
district engineer for other types of
projects. Many other commenters
objected to limiting that flexibility to
bioengineering techniques, stating that
bank protection structures are necessary
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
in high energy coastal and riverine
environments, and said that the waiver
in the 2007 NWP 13 should be
reinstated. Some commenters suggested
removing paragraph (c) entirely. Several
of these commenters thought the
proposal would encourage
bioengineering methods for achieving
the necessary bank stabilization. Many
commenters stated that the waiver to the
cubic yard limit should be removed
from paragraph (c) to ensure that the
NWP authorizes only those activities
with minimal adverse effects on the
aquatic environment. Many commenters
asserted that bioengineering methods for
bank stabilization are unproven and not
as effective at preventing erosion as
hard structures. A few commenters
suggested that the preference for
bioengineering would be a hardship on
local governments. Another commenter
suggested that bioengineering
techniques are rarely successful in arid
areas and in ephemeral waterways.
Another commenter added that the
hydraulic forces in large rivers and tidal
areas require the use of large stone, the
size of which exceeds the one cubic
yard per running foot average size, and
are not conducive to bioengineering.
Several commenters said that
bioengineering is not always
appropriate for protecting infrastructure
such as roads and bridges, and
requested that the one cubic yard per
foot waiver be left in place to protect
these structures. One commenter
suggested modifying the NWP to require
alternatives analyses for each proposed
project using an established hierarchy,
beginning with bioengineering as the
most preferable bank stabilization
method and ending with the hard bank
stabilization structures. One commenter
observed that bank stabilization using
bioengineering or any other method will
still result in adverse effects, and
suggested all bank stabilization
activities should be located landward of
the ordinary high water mark.
In response to the many commenters
that objected to removing the provision
allowing district engineers to waive,
after reviewing a pre-construction
notification, the one cubic yard per
running foot limit, we have reinstated
that provision in this NWP. We have
also reinstated the third preconstruction notification threshold that
was in the 2007 version of NWP, which
requires pre-construction notification
for discharges exceeding one cubic yard
per running foot along the bank below
the plan of the ordinary high water mark
or the high tide line. We acknowledge
that bioengineering may not be
appropriate in all waters, because it may
PO 00000
Frm 00017
Fmt 4701
Sfmt 4703
10199
not result in effective bank stabilization.
We have thus determined that it is not
appropriate to establish a hierarchy of
preferred bank stabilization options
because such decisions are best left to
district engineers that review projectspecific pre-construction notifications,
and can take into account the
characteristics of the waterbody and the
surrounding area, and determine which
bank stabilization method would be
most effective and environmentally
preferable. We agree, however, that
bioengineering techniques may be
environmentally preferable in many
situations and that project proponents
should consider such techniques where
practicable in order to comply with the
general requirement to avoid and
minimize adverse effects to the aquatic
environment. It is not practicable to
require all bank stabilization activities
to be located landward of the ordinary
high water mark.
One commenter asked if the volume
of fill buried deeply below
bioengineering or turf reinforcement
mats could be exempted from the
volume of fill that counts towards the
one cubic yard per running foot limit in
paragraph (b). Another commenter said
that buried stone does not meet the
regulatory definition of fill material, and
said the volume of stone buried below
the ordinary high water mark should not
count towards the one cubic yard per
running foot limit. One commenter
suggested replacing the words ‘‘below
the plane of’’ with ‘‘within the’’ when
describing the ordinary high water mark
in paragraph (c).
The definition of ‘‘fill’’ found in 33
CFR part 323.2 clearly states that rock
is fill material, and burying rock in a
waterway constitutes a discharge of fill
material. The volume of the buried
stone, along with all other fill material,
must be determined and that volume
placed below the plane of the ordinary
high water mark or high tide line is
considered when reviewing the
proposed project. We have retained the
language in NWP because the phrase
‘‘below the plane of ’’ more accurately
describes the Corps jurisdiction in
waters of the United States. To the
extent that the location and type of fill
placed below the plane of the ordinary
high water mark affects the potential for
adverse effects to the aquatic
environment, the district engineer
would consider such factors in deciding
whether to grant a waiver request.
Several commenters said that
paragraph (d) should prohibit fills in
special aquatic sites, including
wetlands. One commenter opposes
removing the waiver provision in
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10200
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
paragraph (d) for work in special aquatic
sites.
We believe that the pre-construction
notification process affords the district
engineer an appropriate opportunity to
review proposed activities in special
aquatic sites. Many streams and
shorelines include, or are bordered by,
special aquatic sites, and precluding use
of this permit in these areas severely
limits its usefulness for projects that
have no more than minimal adverse
effects on the aquatic environment.
Additionally, it may be beneficial in
some watersheds to stabilize eroding
banks, even though small amounts of
special aquatic sites may be impacted by
a bank stabilization activity. Paragraph
(d) requires a written determination
concluding that the activity will result
in minimal adverse effects. If a written
waiver is not issued by the district
engineer, then this NWP does not
authorize such activities and the project
proponent will have to obtain another
form of DA authorization.
Several commenters expressed
support for inclusion of temporary fills
required to accomplish work authorized
under this NWP. One commenter said
that temporary fills should remain in
place if their removal would do more
damage than allowing them to remain in
place. One commenter requested a list
of mandatory best management
practices developed for temporary fills
authorized by this NWP.
If the district engineer determines that
temporary fills should remain in place
those fills may be authorized by another
NWP, a regional general permit, or
individual permit. We do not agree that
specifically requiring best management
practices is appropriate, although
division engineers may regionally
condition this NWP to add appropriate
best management practices. District
engineers may also add conditions to
the NWP to require specific best
management practices for a particular
activity.
Several commenters stated that preconstruction notification should be
required for all activities authorized by
this NWP. One commenter requested
that no pre-construction notification be
required for any bank stabilization
exceeding one cubic yard per running
foot in ephemeral and intermittent
waters. One commenter suggested
removing all pre-construction
notification requirements from work
done under this NWP in man-made
waterways. One agency recommended
lowering a pre-construction notification
threshold to 100 feet for hard bank
stabilization projects such as riprap, and
300 feet for bioengineering projects. One
commenter claimed it would be
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
burdensome and costly to submit a preconstruction notification for every bank
stabilization project.
We do not agree that it is necessary
to require pre-construction notification
for all activities authorized by this
NWP. A large number of small bank
stabilization activities are conducted
each year that result in minimal adverse
effects on the aquatic environment. We
believe that the existing preconstruction notification thresholds are
sufficient for satisfying the minimal
adverse effects requirement for general
permits, and division engineers can
regionally condition this NWP to
impose lower pre-construction
notification thresholds, including
requiring pre-construction notification
for all activities.
Two commenters said that bank
stabilization activities must avoid
impacting tribal rights, tribal natural
resources, and tribal cultural resources.
Many commenters said that while bank
stabilization projects may reduce
erosion at a site, they may transfer or
accelerate erosion in other areas of a
waterbody.
General condition 17, tribal rights,
prohibits the impairment of all reserved
tribal rights. We acknowledge that bank
stabilization activities may cause
indirect effects in other areas of the
waterbody and those indirect effects
should be evaluated during the review
of a pre-construction notification, if it is
required. Activities that do not require
a pre-construction notification have
minimal adverse effects on the aquatic
environment.
Some commenters asked that
compensatory mitigation be required for
all activities authorized by this NWP. A
few commenters remarked that
compensatory mitigation should be
required for adverse effects on high
quality riparian areas. Another
commenter said that mitigation should
be required when sheet piling is used to
stabilize banks.
We do not believe compensatory
mitigation should be required for all
bank stabilization activities. District
engineers will determine when
compensatory mitigation is necessary to
ensure that an activity results in
minimal individual and cumulative
adverse effects on the aquatic
environment.
This NWP is reissued with the
modifications discussed above.
NWP 14. Linear Transportation
Projects. There were no changes
proposed for this NWP. One commenter
suggested that this NWP should
authorize only the maintenance of
existing linear transportation projects
because the construction of new linear
PO 00000
Frm 00018
Fmt 4701
Sfmt 4703
transportation projects results in more
than minimal adverse environmental
effects. One commenter said that this
NWP should not authorize parking lots.
One commenter stated that activities in
tidal waters should not be authorized by
this NWP because any proposed linear
transportation project impacting tidal
wetlands require an individual permit
to more thoroughly assess impacts on
those aquatic habitats.
This NWP should not be limited to
authorizing the maintenance of existing
linear transportation projects. The terms
and conditions of this NWP, including
its acreage limits and pre-construction
notification thresholds, provide an
effective means for authorizing linear
transportation projects with minimal
individual and cumulative adverse
effects on the aquatic environment.
Parking lots may be an integral part of
a single and complete linear
transportation project and may be
authorized under this NWP. Small
linear transportation projects
constructed or maintained in tidal
waters may be authorized by this NWP,
if they comply with appropriate
thresholds and result in minimal
adverse effects on the aquatic
environment. Division engineers can
regionally condition this NWP to restrict
or prohibit the use of this NWP to
authorize structures or fills in tidal
waters where necessary.
Most commenters suggested adding a
linear foot limit to this NWP to ensure
that it only authorizes activities with
minimal adverse effects on the aquatic
environment, stating that the current
NWP authorizes large amounts of small
streams to be permanently lost or
significantly altered. One commenter
recommended a 100 linear foot limit for
the loss of perennial, intermittent, and
ephemeral streams. One commenter said
that the 1⁄2-acre limit is too large when
compared to other NWPs that limit
impacts to 1⁄10-acre. One commenter
suggested limiting private roads to 200
feet in length, with a maximum width
of 16 feet. One commenter
recommended that public road projects
with multiple crossings should have a
maximum cumulative limit of two acres
for all crossings associated with that
project.
We believe the 1⁄2-acre and 1⁄3-acre
limits are appropriate for ensuring that
the NWP authorizes only those linear
transportation projects that result in
minimal individual and cumulative
adverse effects on the aquatic
environment. Division engineers can
regionally condition this NWP to
decrease these acreage limits or impose
linear foot limits to provide additional
protection for wetlands and other waters
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
in a particular district or region. We do
not agree that public and private
crossings should have different acreage
limits. The environmental effects are not
dependent on the status of the entity
who proposes to construct the project. A
200 linear foot limit was removed from
NWP 14 in 2007 to simplify this NWP.
The Corps is not aware of situations
where this change resulted in projects
being authorized that had more than
minimal adverse effects.
One commenter asserted that using
this NWP prevents the public from
commenting on large transportation
projects. Another commenter said that
this NWP should not authorize
expansion of existing projects, because
it discourages avoidance and
minimization and is contrary to the
404(b)(1) Guidelines. One commenter
stated that use of this NWP for the
expansion, modification, or
improvement of previously authorized
projects could result in cumulative
impacts that exceed the acreage limits
and said the impacts of previously
authorized projects should count
towards the acreage limit.
Linear transportation projects that
involve small losses of waters of the
United States and result in minimal
adverse effects on the aquatic
environment would not generally
generate substantive public comments
in response to a public notice and
should not require public notices. It is
appropriate to authorize expansions,
modifications, or improvements to
existing projects, as long as those
activities comply with the terms and
conditions of the NWP, including the
applicable acreage limit. An expansion,
modification, or improvement of an
existing project has few practicable
alternatives available because it is a
change to a previously constructed
project. Alternatives that would involve
relocating an existing project are likely
to result in more adverse effects to the
aquatic environment. An expansion,
modification, or improvement of a
previously authorized single and
complete linear transportation project
should include the previously
authorized losses of waters of the
United States when determining
whether the acreage limit would be
exceeded by the expanded, modified, or
improved project, if the expansion,
modification, or improvement is not a
separate single and complete project.
Factors that may affect this
determination include the length of time
between the original project and the
expansion, modification or
improvement; the degree of
independent utility of the original
project and the expansion, modification
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
or improvement; and the degree to
which the expansion, modification or
improvement may have been already
envisioned, or planning might already
have begun, at the time the original
project was authorized. Under no
circumstance will district engineers
allow ‘‘piecemealing’’ of projects (for
this or any other NWP) in order to meet
thresholds.
One commenter requested that the
term ‘‘minimum necessary’’ used in the
first paragraph of this NWP be defined.
One commenter asked if temporary fill
may be put in place for up to two years
without requiring any mitigation, and
another commenter requested a
definition for ‘‘temporary.’’ One
commenter suggested that culverts or
other appropriate measures should be
required to maintain existing drainage
patterns, all stream crossings should
span the bankfull width of a stream, and
in cases where bottomless culverts or
bridge structures are not used, the
bottom of the structure should match
stream slope. Another commenter
suggested that the NWP should require
the use of best management practices to
avoid sediment loading of waters and
that best management practices should
be used in upland areas and within
waters to protect downstream water
quality.
The decision as to whether a stream
channel modification is the ‘‘minimum
necessary’’ and whether a fill is
‘‘temporary’’ is to be determined on a
case-by-case basis, after considering the
specifics of the proposed activity and
the types of aquatic resources proposed
to be impacted by the linear
transportation project. General
condition 2, aquatic life movements,
and general condition 9, management of
water flows, require that linear
transportation projects be designed to
sustain corridors for aquatic life
movements and maintain, to the
maximum extent practicable, the preconstruction course, condition,
capacity, and location of streams and
other open waters. General condition
12, soil erosion and sediment controls,
requires permittees to take appropriate
measures to reduce or prevent
movements of sediment into waters
during construction. Water quality
management measures may also be
required by district engineers on a caseby-case basis after evaluating a preconstruction notification.
One commenter said that preconstruction notification should be
required for stream impacts that exceed
100 linear feet. Another commenter
stated that any stream channel
modifications should require preconstruction notification. One
PO 00000
Frm 00019
Fmt 4701
Sfmt 4703
10201
commenter suggested requiring low
ground pressure equipment, wide tires,
rubberized racks, lightweight
equipment, and the use of varied paths
to avoid repeatedly crossing wetlands at
the same location, to protect wetlands.
One commenter suggested sending preconstruction notifications to tribes to
avoid impacts to tribal treaty natural
and cultural resources. One commenter
recommended that the Corps consult
with the Federal Highway
Administration to streamline projects
and align with their efforts.
The present pre-construction
notification thresholds provide
sufficient protection for streams, and
division engineers can regionally
condition this NWP to require preconstruction notification for proposed
losses of stream beds that would exceed
a specified amount. Streams with riffle
and pool complexes are considered to
be special aquatic sites under the
404(b)(1) Guidelines and would require
pre-construction notification. General
condition 11, equipment, establishes
requirements for equipment working in
wetlands or mudflats and we believe
this general condition provides
sufficient protection for those types of
construction impacts. Division
engineers can regionally condition this
NWP to require pre-construction
notification for activities that may affect
tribal treaty resources, and consult with
those tribes before making a decision on
whether the activity is authorized by
this NWP. This NWP, as well as other
NWPs such as NWP 23, provides a
means for streamlining the
authorization of linear transportation
projects and working cooperatively with
the Federal Highway Administration
and state departments of transportation.
The NWP is reissued without change.
NWP 15. U.S. Coast Guard Approved
Bridges. We proposed to modify this
NWP by removing reference to the U.S.
Coast Guard authorizing the discharge
of dredged or fill material into waters of
the United States as part of their bridge
permit. We also proposed to reference
the U.S. Coast Guard’s bridge permitting
authority under Section 9 of the Rivers
and Harbors Act of 1899 and other
applicable laws. We proposed to add
section 10 to the regulatory authorities
so that discharges authorized under
Section 404 of the Clean Water Act
would be also authorized under the
Rivers and Harbors Act.
One commenter agreed with adding
section 10 authority to this NWP, which
they believed would help clarify a
sometimes confusing permitting
scenario. Another commenter objected
to adding section 10 authority, stating
that the section 9 permits issued by the
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10202
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
U.S. Coast Guard for bridge and
causeway construction satisfy all
requirements of the Rivers and Harbors
Act of 1899 and adding section 10
authorization is not necessary. One
commenter requested clarification
regarding the applicability of section 10
to the U.S. Coast Guard approved
bridges over both navigable-in-fact and
historically navigable waters of the
United States. One commenter
requested definitions of the terms
‘‘causeway’’ and ‘‘approach fills.’’
We agree that the U.S. Coast Guard’s
section 9 permit satisfies the permit
requirements of the Rivers and Harbors
Act and have removed the reference to
section 10 from the NWP. Discharges of
dredged or fill material associated with
the construction of bridges across
navigable waters of the United States
require separate authorization under
Section 404 of the Clean Water Act,
since navigable waters of the United
States are also considered waters of the
United States under the Clean Water
Act, and discharges of dredged or fill
material into waters of the United States
require section 404 permits, unless they
are eligible for an exemption from
permit requirements. Historically
navigable waters of the United States
may still be subject to jurisdiction under
Rivers and Harbors Act of 1899,
depending on the case-specific
circumstances. We do not believe it is
necessary to define what causeways and
approach fills are, since they would be
identified in the specific plans approved
by the U.S. Coast Guard as part of their
section 9 permit.
This NWP is reissued with the
modification discussed above.
NWP 16. Return Water From Upland
Contained Disposal Areas. We did not
propose any changes to this NWP. This
NWP provides section 404 authorization
for the discharge of return water from a
dredged material placement facility
located in uplands, because that
discharge of return water into waters of
the United States has been
administratively defined as a ‘‘discharge
of dredged material’’ (see 33 CFR
323.2(d)(1)(ii)). One commenter said the
NWP should address both the technical
requirements and water quality of the
return water due to the potential for the
return water to degrade water quality for
natural heritage resources. One
commenter said that pre-construction
notification should be required for
activities authorized by this NWP to
ensure that suspended contaminated
sediments do not reenter waterways and
impact state submerged lands.
The water quality certification issued
for a specific dredging project should
address any water quality concerns for
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
natural heritage resources. We do not
agree that pre-construction notification
should be required for this NWP
because any required sediment testing
would identify contaminants. The
sediment testing and potential impacts
to water quality are more appropriately
considered through the water quality
certification process. We have modified
this NWP to clarify that disposal of
dredged material in an area that has no
waters of the United States does not
require a section 404 permit, because
disposal of dredged material may occur
in non-jurisdictional wetlands and
waters, not just uplands.
The NWP is reissued with the
modification discussed above.
NWP 17. Hydropower Projects. No
changes were proposed for this NWP.
Several commenters said that this
category of activities is inappropriate for
authorization under an NWP because of
the scope and scale of these projects.
One commenter stated that these
activities result in more than minimal
adverse effects on the aquatic
environment, especially downstream
effects such as the loss of riffle and pool
complexes and degradation of water
quality through increased sediment
loads.
This NWP authorizes small
hydropower projects that have minimal
adverse effects on the aquatic
environment. All activities authorized
by this NWP require pre-construction
notification, so that district engineers
can review each proposed hydropower
project and make a case-specific
determination whether the minimal
effects requirement has been met.
Discretionary authority will be
exercised, and another form of
Department of the Army authorization
would be required, if the district
engineer determines that a particular
hydropower project would result in
more than minimal individual and
cumulative adverse effects to the aquatic
environment or any other public interest
review factor. District engineers may
also require compensatory mitigation to
offset losses of aquatic resource
functions.
This NWP is issued without change.
NWP 18. Minor Discharges. We did
not propose modifications to this NWP.
Several commenters expressed support
for the reissuance of this NWP. A few
commenters said that this NWP does not
comply with the ‘‘similar in nature’’
requirement for general permits. Other
commenters asserted that the
cumulative impacts resulting from the
use of this NWP would be more than
minimal. Another commenter said that
this NWP should not authorize
discharges into waters that provide
PO 00000
Frm 00020
Fmt 4701
Sfmt 4703
forage fish habitat or that contain
aquatic vegetation. One commenter
stated that the NWP should not be used
to authorize discharges in rare aquatic
environments such as vernal pools.
We believe that the small discharges
of dredged or fill material authorized by
this NWP comply with the similar in
nature requirement for general permits.
District engineers will review preconstruction notifications and may
assert discretionary authority to add
activity-specific conditions to the NWP
authorization to ensure that the activity
results in minimal adverse
environmental effects. Division
engineers may regionally condition this
NWP to restrict or prohibit its use in
specific waters or categories of waters,
including fish foraging areas, vegetated
shallows, or vernal pools.
One commenter stated that the limit
for this NWP should only be expressed
in terms of area filled (i.e., up to 1⁄10acre) and not include the volumetric
limit (i.e., 25 cubic yards). Another
commenter said that all discharged
material should consist of clean,
uncontaminated sand, crushed rock, or
stone. One commenter recommended
adding language requiring that the
discharge will not result in significant
changes to stream geomorphology or
hydrology, and that the discharge will
not impede navigation.
The 25 cubic yard limit for regulated
excavation activities and the 1⁄10-acre
limit for losses of waters of the United
States caused by discharges of dredged
or fill material are both necessary to
ensure that this NWP authorizes only
those activities that have minimal
individual and cumulative adverse
effects on the aquatic environment.
General condition 6, suitable material,
prohibits the use of unsuitable fill
material. The fill material must not have
toxic pollutants that are present in toxic
amounts. Compliance with general
condition 9, management of water
flows, will ensure that the activity does
not cause more than minimal adverse
effects to stream geomorphology or
hydrology. General condition 1,
navigation, states that NWP activities
cannot cause a more than minimal
adverse effect to navigation.
This NWP is reissued without change.
NWP 19. Minor Dredging. There were
no changes proposed for this NWP. One
commenter recommended that the NWP
include a cumulative volume limit for
multiple single and complete dredging
projects. One commenter recommended
modifying the NWP to require that
dredge material be limited to a
maximum of 25 cubic yards from a
1,000 square foot area, not disturb
sediments in an area known or
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
suspected to contain toxic pollutants,
and the disposal of dredged material at
an upland location. Another commenter
said that pre-construction notification
should be required for all activities to
ensure that sediments are not
contaminated and do not cause impacts
to state owned land. One commenter
stated that the activities authorized by
this NWP are not similar in nature and
do not result in cumulative minimal
adverse environmental effects.
This NWP may be used only once for
each single and complete project (see
general condition 15, single and
complete project). Therefore, each single
and complete dredging project is subject
to the 25 cubic yard limit. District
engineers will also review preconstruction notifications and other
requests for NWP verifications, and will
exercise discretionary authority if they
determine that the use of this NWP in
a particular region is resulting in more
than minimal cumulative adverse effects
on the aquatic environment. We believe
that the 25 cubic yard limit is sufficient
to satisfy the minimal adverse
environmental effects requirement for
general permits, and that an areal limit,
such as the 1,000 square feet
recommended above, is not necessary.
Division engineers may impose regional
conditions on this NWP to restrict or
prohibit its use in waters known to have
contaminated sediments or in waters
where there is sufficient reason to
believe that there are contaminated
sediments, that would cause more than
minimal adverse effects to water quality
if they were disturbed by these minor
dredging activities. A separate
Department of the Army authorization
must be obtained if the project
proponent plans to deposit the dredged
material into waters of the United
States, including jurisdictional
wetlands. Absent such authorization,
the dredged material must be deposited
in an upland area or an approved
dredged material disposal facility.
This NWP is reauthorized without
change.
NWP 20. Response Operations for Oil
and Hazardous Substances. We
proposed to change the name of this
NWP, and modify its terms and
conditions to authorize a wider set of
activities, such as containment and
mitigation actions, to more effectively
authorize efforts to manage releases of
oil or hazardous substances. We also
proposed to authorize training exercises
for the cleanup of oil and hazardous
substances, including those that involve
temporary structures or fills.
Five commenters expressed support
for the proposed changes to this NWP.
One commenter objected to the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
proposed modifications, stating that the
NWP could authorize large dredge and
fill operations that would result in net
adverse effects on the aquatic
environment that would be more than
minimal. One commenter stated that the
NWP should be limited to interim
response activities and that a separate
permit should be required for final
restoration response. Another
commenter said that there should be a
requirement to remove temporary
structures and fill. This commenter also
recommended that the NWP include
criteria for temporary structures or fills,
such as a requirement to restore
wetlands to the maximum extent
practicable, to ensure there are no
lasting impacts from these activities. A
commenter said that this NWP should
require coordination with the
appropriate state wetland or water
resources program.
This NWP authorizes activities in
waters of the United States to remediate
spills of oil and hazardous substances,
which normally results in
environmental benefits. We do not agree
that the NWP should be limited to
interim responses. It should also
authorize the final response activity that
results in the removal of the oil or
hazardous substances, as well as the
authorization to remove any temporary
structures or fills, to the extent that a
Department of the Army permit is
required to remove such temporary
structures or fills. General condition 13,
removal of temporary fills, requires
temporary fills to be removed in their
entirety, and the affected areas
revegetated, if necessary. We do not
agree that this NWP should require
coordination with state wetland or
water resource agencies, since those
agencies are likely to have an
independent authority to regulate such
response activities, as well as their own
procedures for reviewing and approving
those activities. As a practical matter,
such remediation efforts almost always
involve coordination among multiple
agencies.
This NWP is reissued as proposed.
NWP 21. Surface Coal Mining
Activities. We proposed three options
concerning this NWP. The first option
was not to reissue NWP 21 and to let it
expire on March 18, 2012. The other
two options consisted of reissuing the
NWP with modifications. Option 2 was
to reissue NWP 21 with a 1⁄2-acre limit,
including a 300 linear foot limit for the
loss of stream bed. Under Option 2,
NWP 21 would not authorize discharges
of dredged or fill material into waters of
the United States to construct valley
fills. Option 3 was similar to Option 2,
but under Option 3 NWP 21 could
PO 00000
Frm 00021
Fmt 4701
Sfmt 4703
10203
authorize discharges of dredged or fill
material into waters of the United States
to construct valley fills. In the February
16, 2011, proposal, Option 2 was
identified as the Corps preferred option.
Both Options 2 and 3 require a preconstruction notification for activities
authorized by NWP 21, and permittees
would have to receive written
authorization from the district engineer
prior to commencing the activity.
A large majority of commenters
supported Option 1 and opposed the
reissuance of NWP 21, including any
modification of that NWP. Over 26,000
of those comments were form letters.
Several commenters recommended
adopting Option 2. Two commenters
supported Option 3. Many commenters
stated that NWP 21 should be reissued
without change from the NWP issued in
2007.
While some commenters expressed
support for Option 1, they also said that
if NWP 21 is to be reissued, Option 2
should be selected and modified to
remove the provision allowing district
engineers to waive the 300 linear foot
limit for the loss of intermittent or
ephemeral stream bed. Another
commenter stated that if NWP 21 is
reissued, it should not authorize any
losses of intermittent or perennial
streams.
We believe that district engineers
should have the ability to waive the 300
linear foot limit for the loss of
ephemeral or intermittent stream bed if
they make a case-specific determination
that the proposed activity will result in
minimal individual and cumulative
adverse effects on the aquatic
environment. For proposed activities
under paragraph (b) of NWP 21 that
would result in the loss of greater than
300 linear feet of intermittent or
ephemeral stream bed, district engineers
will coordinate the pre-construction
notifications with the resource agencies,
to solicit their comments (see paragraph
(d) of general condition 31). Those
comments will be used by the district
engineer in making his or her minimal
adverse effects determination. The loss
of intermittent or perennial streams
caused by NWP 21 activities may still
result in minimal individual and
cumulative adverse effects on the
aquatic environment, and in such cases
authorization by NWP is appropriate.
Note that the 300 linear foot limit may
not be waived for perennial streams.
Activities authorized under paragraph
(a) of NWP 21 do not require agency
coordination because paragraph (a) does
not authorize any expansion of surface
coal mining activities in waters of the
United States and the district engineer
previously determined, and must again
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10204
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
confirm in writing, that those activities
will result in minimal individual and
cumulative adverse effects and qualify
for NWP authorization. Many of the
surface coal mining activities authorized
under the 2007 NWP 21 already had
agency coordination because they
resulted in the loss of greater than 1⁄2acre of waters of the United States.
Many commenters stated their
preference for Option 2 because it
would not allow valley fills for surface
coal mining activities, which they
believe substantially alter watersheds
and associated headwater streams, and
generally are alleged to cause more than
minimal adverse effects on the aquatic
environment. One commenter suggested
adding a provision that would prohibit
the use of NWP 21 for activities
associated with mountain-top removal
mining.
We have selected Option 2 for the
reissuance of NWP 21, and have made
some additional modifications to reduce
hardships on permittees who previously
obtained authorization under the NWP
21 issued on March 12, 2007, and
invested substantial resources in
reliance on that NWP authorization.
These modifications are discussed in
greater detail below. In addition, we
have added a definition of ‘‘valley fill’’
to the NWP to clarify the activities to
which the valley fill prohibition applies.
For the purposes of this NWP, a ‘‘hollow
fill’’ is considered a valley fill. This
NWP authorizes discharges of dredged
or fill material into waters of the United
States when those discharges are
associated with surface coal mining
activities. The Corps review is focused
on the individual and cumulative
adverse effects to the aquatic
environment, and determining
appropriate mitigation that may be
needed to ensure that the adverse effects
on the aquatic environment are
minimal, individually and
cumulatively. It does not extend to the
mining operation as a whole. The
Surface Mining Control and
Reclamation Act of 1977 (SMCRA), 30
U.S.C. 1201 et seq., and its
implementing regulations address the
environmental impacts of proposed
surface coal mining operations as a
whole, including adverse effects to
uplands and changes in land use.
SMCRA is administered by the Office of
Surface Mining Reclamation and
Enforcement and states with approved
regulatory programs under SMCRA.
Two commenters supported Option 3,
and they said the production of energy
from all sources, including surfacemined coal, is vitally important to the
short-term economic recovery of the
United States and the long-term energy
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
independence and economic prosperity
of our country. Another commenter said
there is no need to limit NWP 21 to 1⁄2acre and 300 linear feet and prohibit
valley fills, because district engineers
review every pre-construction
notification and can require an
individual permit if necessary.
We have adopted Option 2 because it
provides greater assurance that NWP 21
will authorize only those discharges of
dredged or fill material into waters of
the United States that have minimal
individual and cumulative adverse
effects on the aquatic environment.
Surface coal mining activities that
involve discharges of dredged or fill
material that require section 404 permits
but do not qualify for NWP 21 may be
authorized by other forms of
Department of the Army authorization,
such as individual permits or regional
general permits. We have added the 1⁄2acre limit, and the 300 linear foot limit
for the loss of stream bed, to make this
NWP consistent with many of the other
NWPs (e.g., NWPs 29, 39, 40, 42, 43, 44,
and 51). We have also added a
prohibition against using this NWP to
authorize discharges of dredged or fill
material into waters of the United States
to construct valley fills. Such limits are
necessary to constrain the adverse
effects to the aquatic environment, to
ensure compliance with the statutory
requirement that general permits,
including NWPs, may only authorize
those activities that have minimal
individual and cumulative adverse
effects on the aquatic environment. We
do not believe it is efficient to rely on
the pre-construction notification process
alone to ensure minimal adverse
environmental effects. Many other
NWPs use a combination of acreage
and/or linear foot limits and preconstruction notification requirements
to ensure compliance with Section
404(e) of the Clean Water Act, as well
as 33 CFR 322.2(f) and 33 CFR 323.2(h).
Previous versions of NWP 21 did not
have any acreage or linear foot limits,
and relied solely on the preconstruction notification review process
and permit conditions to reduce adverse
effects on the aquatic environment to
satisfy the minimal adverse
environmental effects requirement for
general permits. We believe that
approach is no longer appropriate
because of the inconsistency with other
NWPs, the possibility that larger losses
of waters of the United States might be
authorized, and the difficulty of
documenting minimal adverse effect
determinations for losses of aquatic
resource area and functions that exceed
those allowed in other NWPs. We note
that part of the basis for the earlier
PO 00000
Frm 00022
Fmt 4701
Sfmt 4703
approach was the environmental review
that occurs in connection with obtaining
a SMCRA permit, and that the SMCRA
regulations related to stream protection
have changed since the previous NWP
21 was issued.1 The new acreage and
linear foot limits will ensure that this
NWP contributes no more than minimal
individual and cumulative adverse
effects to the aquatic environment, by
limiting the amount of waters of the
United States that can be filled by each
NWP 21 activity.
Many commenters said the Corps
should fulfill its June 2009
determination to prohibit the use of
NWP 21 to authorize surface coal
mining activities in six states in
Appalachia because these activities
result in more than minimal adverse
effects to the aquatic environment,
individually and cumulatively. Some
commenters said the proposed
reissuance of NWP 21 is contrary to the
Corps June 18, 2010, decision to
suspend NWP in the Appalachian
region of Kentucky, Ohio, Pennsylvania,
Tennessee, Virginia, and West Virginia,
which stated that continued use of this
NWP may result in more than minimal
adverse effects to aquatic resources.
Many commenters stated that surface
coal mining activities in Appalachia
have resulted in the loss of a couple of
thousand miles of streams, substantially
degraded water quality, and are harmful
to the health and drinking water of
Appalachian citizens. They also said the
Corps should follow science and stop
issuing permits, including individual
permits, for surface coal mining
activities in these six Appalachian states
because those activities cause
significant degradation of waters of the
United States, and this region cannot
afford to lose more of its vital natural
resources.
In accordance with the June 11, 2009,
memorandum of agreement
implementing the interagency action
plan on Appalachian Surface Coal
Mining, which was signed by the
Department of the Army, the
Department of Interior, and the U.S.
Environmental Protection Agency, the
Corps issued a proposal in the Federal
Register on July 15, 2009, to modify
NWP 21 so that it would not authorize
discharges of dredged or fill material
into waters of the United States in the
Appalachian region of Kentucky, Ohio,
Pennsylvania, Tennessee, Virginia, and
1 The Office of Surface Mining has announced its
intention to further revise these requirements
however such revisions will not be in place at the
time the NWPs are reissued. The Corps may
reconsider these limits in future promulgations of
the NWPs based on its experience and any changes
in the broader regulatory context.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
West Virginia (see 74 FR 34311). In the
June 18, 2010, issue of the Federal
Register (75 FR 34711), the Corps
announced the suspension of NWP 21
in the Appalachian region of six states
(i.e., Kentucky, Ohio, Pennsylvania,
Tennessee, Virginia, and West Virginia)
and said that it would consider
modifying NWP 21.
As a result of our review of the
comments received in response to the
February 16, 2011, proposal we have
determined that it would be appropriate
to adopt Option 2 and substantially
modify NWP 21 by imposing acreage
and linear foot limits, as well as
prohibiting its use to authorize
discharges of dredged or fill material
into waters of the United States to
construct valley fills associated with
surface coal mining activities, to ensure
that the NWP authorizes only those
activities that result in minimal
individual and cumulative adverse
effects on the aquatic environment. The
1⁄2-acre and 300 linear foot limits will
substantially reduce the amount of
stream bed and other waters lost as a
result of activities authorized by this
NWP, and limit this NWP to minor fills
associated with surface coal mining
activities, such as the construction of
sediment ponds. Issues relating to the
use of individual permits to authorize
discharges of dredged or fill material
into waters of the United States
associated with surface coal mining
activities are outside the scope of the
NWP reissuance process and are not
addressed in this rule.
The proposed reissuance of NWP 21,
as well as the selection of Option 2 to
reissue the NWP with 1⁄2-acre and 300
linear foot limits and a prohibition
against authorizing discharges of
dredged or fill material into waters of
the United States to construct valley
fills, is not contrary to the suspension of
NWP 21 in the Appalachian region of
these six states. The NWP reissued
today has been substantially modified
from the 2007 version of NWP 21, with
paragraph (a) authorizing Corps district
engineers to re-authorize activities that
were previously verified under the 2007
NWP 21 authorization where that would
be appropriate, and paragraph (b)
imposing the acreage and linear foot
limits stated above, as well as the
condition prohibiting its use for the
construction of valley fills in waters of
the United States, on new NWP 21
activities. The substantial changes in the
terms and conditions of the reissued
NWP 21 will ensure that the activities
authorized by this NWP result in
minimal individual and cumulative
adverse effects on the aquatic
environment. District engineers will
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
review pre-construction notifications for
activities authorized under paragraph
(b) of this NWP and may require
compensatory mitigation to offset losses
of waters of the United States and
ensure the adverse effects on the aquatic
environment are minimal, individually
and cumulatively. Compensatory
mitigation required for activities
verified under the 2007 NWP 21 will
continue to be required, and may be
augmented if the district engineer
determines that they do not adequately
compensate for losses of aquatic
resource function and ensure minimal
individual and cumulative adverse
effects. Suspension of an NWP is an
interim measure to be taken if there are
substantive concerns that an NWP
activity is potentially causing more than
minimal adverse environmental effects,
while the Corps collects additional
information and considers
modifications to that NWP to satisfy
statutory or regulatory requirements for
general permits, such as compliance
with Section 404(e) of the Clean Water
Act. We fully considered the comments
received in response to the July 15,
2009, proposal to suspend NWP 21 and
used those comments to develop the
three options presented in the February
16, 2011, proposal to reissue NWP 21.
We have now determined that adopting
Option 2 addresses the concern that led
to our previous suspension of NWP 21
in the six Appalachian states, but in a
more effective and equitable way. It is
not the geographic location of activities,
but rather the nature of these activities
and their associated discharges that may
lead to more than minimal adverse
effects. By prohibiting the use of NWP
21 for discharges associated with valley
fills and activities exceeding
appropriate thresholds, which are
consistent with the thresholds used for
many other NWPs, we can ensure that
activities that may result in more than
minimal individual and cumulative
adverse effects obtain individual
permits, and those activities that will
not result in more than minimal adverse
effects can be authorized by an NWP,
regardless of the region of the country
in which they occur.
Only those surface coal mining
activities involving discharges into
waters of the United States that received
written authorization under the 2007
NWP 21 may be eligible for
authorization under paragraph (a) of this
NWP. Activities that were subject to the
June 18, 2010, suspension of NWP 21 in
the Appalachian region of the six states
may be eligible for NWP 21
authorization under paragraph (b) if
they do not result in the loss of greater
PO 00000
Frm 00023
Fmt 4701
Sfmt 4703
10205
than 1⁄2-acre of waters of the United
States, do not result in the loss of greater
than 300 linear feet of stream bed
(unless that 300 linear foot limit for
intermittent and ephemeral streams is
waived by the district engineer after
agency coordination and making a
written determination that the activity
will result in minimal individual and
cumulative adverse effects on the
aquatic environment), and do not
involve discharges of dredged or fill
material into waters of the United States
to construct valley fills.
One commenter objected to the
proposed reissuance of NWP 21, stating
that it authorizes impacts for activities
that are not similar in nature, such as
mining operations, impoundments,
processing plants, and road crossings.
The commenter said that the Corps
decision documents do not recognize
that impoundments can cause massive
spills or contaminate well water.
We do not agree that this NWP
authorizes activities that are not similar
in nature. This NWP authorizes surface
coal mining activities, a broad category
that includes a variety of features that
may be constructed by discharging
dredged or fill material into waters of
the United States, the activities
regulated by the Corps under Section
404 of the Clean Water Act. Discharges
of dredged or fill material into waters of
the United States may be used to
construct sediment ponds, road
crossings, etc. that are necessary to
conduct surface coal mining activities,
or they may occur while coal is being
mined (e.g., mine-throughs).
Impoundments constructed in waters of
the United States should be properly
maintained (see general condition 14,
proper maintenance). District engineers
may also require non-Federal permittees
to demonstrate that those impoundment
structures comply with applicable dam
safety criteria (see general condition 24,
safety of impoundment structures).
One commenter said that if NWP 21
was reissued and could be used to
authorize valley fills, the Corps would
violate the requirement in the 404(b)(1)
Guidelines that no discharge of dredged
or fill material shall be permitted which
will cause or contribute to significant
degradation of waters of the United
States. This commenter also stated that
the proposed 300 linear foot limit for
the loss of stream bed would not
prevent significant degradation of
streams, and objected to the proposed
waiver of that limit for intermittent and
ephemeral streams, if the district
engineer determined that such a loss
would result in minimal adverse effects
on the aquatic environment.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10206
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
The NWP 21 reissued today does not
authorize discharges of dredged or fill
material into waters of the United States
to construct valley fills, unless under
paragraph (a) the activity was
previously verified under the 2007 NWP
21 and the district engineer has
determined that those activities still
qualify for NWP 21 authorization under
the 2012 NWP general conditions,
applicable regional conditions, and any
activity-specific conditions such as
compensatory mitigation requirements.
For those previously authorized surface
coal mining activities, the district
engineer determined that the adverse
effects on the aquatic environment are
minimal, individually and
cumulatively. To re-verify the NWP
authorization under the 2012 NWP 21,
the district engineer must determine
that the activity continues to result in
minimal individual and cumulative
adverse effects on the aquatic
environment. Surface coal mining
activities that involve discharges of
dredged or fill material into waters of
the United States for the construction of
valley fills that were not previously
verified under the 2007 NWP 21 are
subject to paragraph (b) of the 2012
NWP 21 and cannot be authorized by
NWP 21. Discharges of dredged or fill
material into waters of the United States
authorized by NWP 21 require water
quality certification. If water quality
certification is not obtained or waived,
that activity is not authorized by NWP
21. The water quality certifications
issued by states are to be considered by
district engineers to be conclusive
regarding water quality issues, unless
the Regional Administrator of the U.S.
Environmental Protection Agency
advises the district engineer of other
water quality concerns that need to be
taken into consideration. The
construction of impoundments
authorized by NWP 21 is generally a
minor cause of changes to water quality.
Most of the changes to water quality are
due to the overall surface coal mining
activity and the change in land use
(including uplands) that occurs as a
result of those mining activities. The
discharges of dredged or fill material
into waters of the United States
authorized by NWP 21 constitute a
small proportion of the overall fill
placed in a watershed to dispose of the
rock, soil, and other materials that are
produced by the surface coal mining
activity. As water percolates through the
larger overall fill that has been placed in
uplands and streams, the water
chemistry changes. The effluent
discharged from impoundments
constructed to trap sediments and other
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
materials to reduce their transport to
downstream waters is regulated under
Section 402 of the Clean Water Act, and
requires a National Pollutant Discharge
Elimination System (NPDES) permit.
The NPDES permit is issued by states
that have approved programs or the U.S.
EPA.
One commenter said the Corps has
ignored cumulative impacts from
discharges of dredged or fill material
previously authorized by NWP 21 in
proposing Option 2 as a preferred
alternative. The commenter also stated
that the draft decision documents fail to
provide any evidence that would
support a minimal effects determination
and that the Corps only considers
cumulative effects during the five year
period the NWP is in effect and this
ignores the fact that valley fills bury
streams permanently, whether
authorized by past nationwide or
individual permits, or in the future. The
commenter also said that Option 2
ignores the cumulative amount of
stream loss or acreage in a watershed
from multiple permits.
We have taken into account
cumulative impacts from discharges of
dredged or fill material previously
authorized by NWP 21, and cumulative
effects of discharges of dredged or fill
material previously authorized by
individual permits, when developing
the proposal to reissue NWP 21,
including Option 2. For NWP 21
activities that were not previously
authorized by the 2007 NWP 21,
paragraph (b) of NWP 21 imposes a 1⁄2acre limit on NWP 21, as well as a 300
linear foot limit for losses of stream bed,
and does not authorize discharges of
dredged or fill material into waters of
the United States to construct valley
fills. These changes will reduce the
number of surface coal mining activities
authorized by NWP 21, when compared
to previous versions of NWP 21, which
had no acreage or linear foot limits, and
could be used to authorize discharges of
dredged or fill material into waters of
the United States to construct valley
fills. We determined that these limits
will ensure that the adverse effects of
discharges authorized by NWP 21 are
minimal, both individually and
cumulatively. Under the National
Environmental Policy Act, an
assessment of cumulative effects has to
consider the past, present, and
reasonably foreseeable future actions
regardless of what agency (Federal or
non-federal) or person undertakes such
actions (see 40 CFR 1508.7). In addition,
the 404(b)(1) Guidelines require a
different approach to cumulative effects
analysis for the issuance of a general
permit, such as NWP 21. The 404(b)(1)
PO 00000
Frm 00024
Fmt 4701
Sfmt 4703
Guidelines require the Corps or other
permitting authority to predict
cumulative effects by evaluating the
number of individual discharges of
dredged or fill material into waters of
the United States expected to be
authorized by that general permit until
it expires (see 40 CFR 230.7(b)(3)).
The decision document for this NWP
includes evaluations of cumulative
effects under both approaches, and
concludes that the reissuance of this
NWP, including the imposition of the
1⁄2-acre limit, 300 linear foot limit, and
prohibition against authorizing valley
fills on activities that were not
previously authorized under the 2007
NWP 21, as well as the pre-construction
notification requirements and other
procedural safeguards, will authorize
only those activities with minimal
individual and cumulative adverse
effects on the aquatic environment.
Activities authorized under the 2007
NWP 21 were already determined by
district engineers to result in minimal
individual and cumulative adverse
effects on the aquatic environment. The
other procedural safeguards include the
authority for division engineers to
modify, suspend, or revoke NWP 21
authorizations on a regional basis, and
the authority for district engineers to
modify NWP 21 authorizations by
adding conditions, such as
compensatory mitigation requirements,
to ensure minimal individual and
cumulative adverse effects on the
aquatic environment. District engineers
may also assert discretionary authority
to require individual permits in cases
where the adverse effects will be more
than minimal.
Under the National Environmental
Policy Act approach to assessing
cumulative effects, the decision
document discusses, in general terms,
the various activities (Federal, nonFederal, and private actions) that may
adversely affect the quantity and quality
of aquatic resources in a watershed or
other geographic region used for
cumulative effects analysis, regardless
of whether those activities occurred in
the past or are expected to occur in the
present or reasonably foreseeable future.
Under the 404(b)(1) Guidelines
approach for assessing cumulative
effects of the issuance of a general
permit such as NWP 21, the decision
document evaluates the number of
discharges of dredged or fill material
into waters of the United States
expected to occur during the five-year
period the NWP would be in effect, as
well as the estimated loss of waters of
the United States and compensatory
mitigation. District and division
engineers are to supplement these
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
analyses when they prepare
supplemental decision documents for
this NWP, and these supplemental
decision documents are to include
cumulative effects analyses at a regional
level. which can be highly informative
regarding impacts at a local watershed
level. The appropriate geographic scope
of those cumulative effects analyses are
at the discretion of the division or
district engineers.
The Corps considers and addresses
cumulative environmental effects of
NWP 21 (and other NWPs) in two
distinct ways. First, when Corps
Headquarters evaluates and proposes to
issue or re-issue a NWP (such as NWP
21), we evaluate cumulative effects at
the national level, using available
national information on aquatic
resource status and trends and the
general effects human activities have on
aquatic resources. The cumulative
effects analyses presented in the
Headquarters decision documents
reflect these national-scale evaluations
and conclusions supporting the
promulgation of the NWP from Corps
Headquarters.
Second, division and district
engineers monitor the use of the NWPs
on a regional level, and will modify,
suspend, or revoke applicable NWPs
when necessary if the use of those
NWPs is likely to result in more than
minimal individual and cumulative
adverse effects on the aquatic
environment within a particular
watershed, ecoregion, state, county, or
other appropriate geographic area. To
address regional and site-specific
environmental considerations, we rely
on the Corps district offices that receive
pre-construction notifications required
by the terms and conditions of the NWP
to evaluate the relevant regional and
site-specific environmental
considerations. The Corps district may
add conditions to the NWP
authorization, including compensatory
mitigation requirements, to ensure that
the individual and cumulative adverse
effects on the aquatic environment
caused by the NWP activity are
minimal, and therefore qualify for NWP
authorization. If conditions cannot be
added to the NWP authorization to
ensure that minimal individual and
cumulative adverse effects on the
aquatic environment occur, the district
engineer will exercise discretionary
authority and notify the applicant that
an individual permit is required.
One commenter said there is
insufficient support for the Corps
position that the required compensatory
mitigation will attenuate cumulative
impacts on the Nation’s aquatic
resources by providing aquatic resource
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
functions and services, so the net effects
will be minimal. Another commenter
stated that the Corps relies heavily on
mitigation, such as stream creation,
restoration, and enhancement, but there
is no evidence that stream creation
works. The commenter also indicated
that the 404(b)(1) Guidelines provide
that no permit may rely on mitigation
techniques unless they have been
demonstrated to be effective in
circumstances similar to those under
consideration, and that the 2008
compensatory mitigation rule requires
that the district engineer assess the
likelihood for ecological success. The
commenter said the Corps cannot issue
an NWP without assessing mitigation
effectiveness and success in the specific
context in which the mitigation
technique would be used. The
commenter concluded that the Corps
mitigation analysis fails to contain any
discussion of stream functions that
would be lost from potential NWP
activities and whether compensatory
mitigation can replace those functions.
Compensatory mitigation can be an
effective means of offsetting losses of
aquatic resource functions caused by
activities authorized by Department of
the Army permits, including NWP 21
activities, if it is thoughtfully planned,
implemented, and monitored.
Compensatory mitigation projects must
be carefully sited, planned, and
designed to be ecologically successful in
providing stream or wetland functions.
Site selection is a critical step in
developing and implementing an
ecologically successful compensatory
mitigation project. With the
promulgation of 33 CFR part 332 on
April 10, 2008 (73 FR 19594), the Corps
Regulatory Program adopted
requirements and standards to improve
compensatory mitigation practices for
offsetting losses of aquatic resource
functions. Under the 2008 rule, a
watershed approach should be used for
establishing compensatory mitigation
requirements that will successfully
provide aquatic resource functions to
offset losses of those functions caused
by permitted activities.
The 2008 rule identifies streams as
‘‘difficult-to-replace’’ resources and
states that if further avoidance and
minimization of stream impacts is not
practicable, the required compensatory
mitigation should be provided through
stream rehabilitation, enhancement, or
preservation since those techniques
have a greater certainty of success (see
33 CFR 332.3(e)(3)). The preamble to the
2008 rule includes a detailed discussion
of the scientific status of stream
restoration and concludes that there has
been success with stream rehabilitation,
PO 00000
Frm 00025
Fmt 4701
Sfmt 4703
10207
enhancement, and preservation
activities (see 73 FR 19596–19598). In
accordance with the 2008 rule, the
Corps is not relying on stream creation
as a mechanism to provide
compensatory mitigation for NWP 21
activities. In cases where compensatory
mitigation is required for NWP 21
activities, those compensatory
mitigation requirements will be
specified as activity-specific conditions
of NWP 21 authorizations. The required
components of a compensatory
mitigation plan are specified at 33 CFR
332.4(c)(2)–(14), and the district
engineer will evaluate each
compensatory mitigation proposal to
assess its potential for ecological
success, and consider the relevant
factors provided in 33 CFR 332.3. The
compensatory mitigation plan must be
approved by the district engineer and
monitoring will be required to assess
whether the compensatory mitigation
project is meeting its objectives and is
successfully meeting its ecological
performance standards. The district
engineer will review monitoring reports,
and if the compensatory mitigation
project is not meeting its ecological
performance standards, he or she will
require the responsible party to identify
and implement adaptive management
measures to make changes to provide a
successful mitigation project. If adaptive
management is not likely to result in an
ecologically successful compensatory
mitigation project that will be sufficient
for offsetting lost aquatic resource
functions that result from the permitted
activity, alternative compensatory
mitigation may be required. Financial
assurances may also be required to help
ensure the success of the required
compensatory mitigation.
The 404(b)(1) Guidelines, which
address habitat development and
restoration as a means of minimizing
adverse effects to plant and animal
populations (40 CFR 230.75(d)),
recommend the use of techniques that
have been demonstrated to be effective.
That provision is consistent with the
section on difficult-to-replace resources
(33 CFR 332.3(e)(3)/40 CFR
230.93(e)(3)), which states that
rehabilitation, enhancement, and
preservation should be used to provide
the required compensatory mitigation to
offset permitted impacts to such
resources because there is greater
certainty that such stream rehabilitation,
enhancement, and preservation will be
ecologically successful and offset those
permitted impacts. The decision
document for this NWP contains a
general discussion of the functions
provided by streams, as well as general
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10208
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
citations supporting our position that
stream rehabilitation and enhancement
can provide stream functions to offset
functions lost as a result of permitted
activities. It is not necessary for the
decision document to provide a
comprehensive analysis of the state of
stream restoration success. The
approach discussed above, and in 33
CFR part 332, is consistent with the
Council on Environmental Quality’s
January 14, 2011, guidance on the
‘‘Appropriate Use of Mitigation and
Monitoring and Clarifying the
Appropriate Use of Mitigated Findings
of No Significant Impact.’’ That
guidance advocates the use of adaptive
management to take corrective actions if
the required mitigation fails to achieve
projected environmental outcomes,
which is also required by the Corps
compensatory mitigation regulations in
33 CFR part 332.
One commenter said that the Corps
has failed to analyze whether surface
coal mining activities authorized by
NWP 21 will cause significant
degradation to ‘‘special aquatic sites,’’
such as riffle and pool complexes. This
commenter asserted that valley fills and
mining through streams frequently
buries riffle and pool complexes, and
these special aquatic sites are protected
by stringent restrictions on discharges of
fill material into such sites. The
commenter also stated that practicable
alternatives that do not involve burying
riffles and pools are presumed to be
available unless clearly demonstrated
otherwise and such alternatives are
presumed to have less adverse impacts
on the aquatic ecosystem. This
commenter said the Corps should deny
a permit if it lacks sufficient information
to determine whether the proposed
discharge complies with the Guidelines.
The activities authorized by this NWP
comply with the 404(b)(1) Guidelines,
even though it authorizes discharges of
dredged or fill material into waters of
the United States that may be classified
as special aquatic sites such as riffle and
pool complexes. Each activity
authorized by an NWP does not require
a project-specific 404(b)(1) Guidelines
analysis—that analysis is done before
the NWP or any other type of general
permit is issued (see 40 CFR 230.7). The
404(b)(1) Guidelines do not prohibit the
use of general permits to authorize
discharges of dredged or fill material
into special aquatic sites. A
determination of significant degradation
does not focus simply on the loss of a
special aquatic site caused by the
discharge of dredged or fill material. It
requires a broader analysis. The process
for determining whether significant
degradation occurs consists of applying
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
the provisions of the 404(b)(1)
Guidelines holistically, and assessing
the effects of the proposed discharge of
pollutants on human health and
welfare; aquatic life and wildlife;
aquatic ecosystem diversity,
productivity, and stability; and
recreational, aesthetic, and economic
values. For activities authorized by
general permits, the evaluation of
alternatives in accordance with 40 CFR
230.10(a) does not directly apply (see 40
CFR 230.7(b)(1)). Paragraph (a) of
general condition 23, mitigation,
requires project proponents to design
and construct NWP activities to avoid
and minimize adverse effects to the
aquatic environment to the maximum
extent practicable on the project site.
Several commenters stated that
surface coal mines are already heavily
regulated under SMCRA, which
includes a variety of requirements to
protect waters of the United States, so
additional requirements are not needed
to ensure that adverse effects to the
aquatic environment are minimal. Two
of these commenters stated NWP 21
should be reissued without change
because of SMCRA requirements. One
commenter said the authority to
authorize stream and wetland impacts
caused by mining activities should rest
solely with the SMCRA regulatory
authority.
There is often more than one Federal
law that regulates surface coal mining
activities, especially in cases where
those activities involve discharges of
dredged or fill material into waters of
the United States. While most aspects of
surface coal mining are regulated under
SMCRA, surface coal mining and
reclamation activities involving
discharges of dredged or fill material
into waters of the United States also
require permits issued under Section
404 of the Clean Water Act. The
statutory and regulatory standards
established under SMCRA are different
than those established under Section
404 of the Clean Water Act, including
section 404(e) which authorizes the
Corps to issue general permits. One of
the objectives of SMCRA is to ensure
that surface coal mining activities are
conducted in an environmentally
responsible manner and that the land
disturbed by mining is adequately
reclaimed. One of the objectives of the
Clean Water Act is to ‘‘restore and
maintain the physical, chemical, and
biological integrity of the Nation’s
waters.’’ Under the regulations
implementing SMCRA, surface coal
mining and reclamation activities must
be conducted in a manner that will
‘‘minimize the disturbance of the
hydrologic balance within the permit
PO 00000
Frm 00026
Fmt 4701
Sfmt 4703
and adjacent areas’’ and that will
‘‘prevent material damage to the
hydrologic balance outside the permit
area.’’ As part of the SMCRA permitting
process, potential changes to the quality
and quantity of surface and groundwater
are evaluated to ensure that material
damage to the hydrologic balance
outside the permit area will not occur.
Other factors considered under SMCRA
include: pre- and post-mining land uses,
backfilling and grading activities,
disposal of excess spoil, and the
protection or replacement of water
supplies.
Under Section 404 of the Clean Water
Act, the 404(b)(1) Guidelines provide
the substantive criteria for evaluating
the environmental effects of proposed
discharges of dredged or fill material
into waters of the United States. The
404(b)(1) Guidelines are not focused on
considering effects to water quality and
quantity. The 404(b)(1) Guidelines also
require examination of the effects that
discharges of dredged or fill material
will have on physical, chemical, and
biological attributes of waters of the
United States. The 404(b)(1) Guidelines
at 40 CFR part 230 require the Corps to
evaluate the effects of discharges of
dredged or fill material, including
general permits that authorize such
discharges, on the applicable criteria
listed in subparts C through F. Examples
of criteria in those subparts are:
Substrate; suspended particulates/
turbidity; water; current patterns and
water circulation; normal water
fluctuations; threatened and endangered
species; fish, crustaceans, mollusks, and
other aquatic organisms in the food web;
other wildlife; wetlands; riffle and pool
complexes; municipal and private water
supplies; recreational and commercial
fisheries; water-related recreation; and
aesthetics. The threshold for issuance of
general permits such as NWP 21 is a
determination that the authorized
activities would result in no more than
minimal individual or cumulative
adverse environmental effects.
There is no corresponding threshold
under SMCRA and its implementing
regulations, which do not require that
permit applications be evaluated in
terms of the 404(b)(1) Guidelines.
Instead, section 507(b)(11) of SMCRA
requires that the permit applicant
prepare a determination of the probable
hydrologic consequences of the
proposed operation with respect to the
hydrologic regime and the quantity and
quality of water in surface and ground
water systems. Section 510(b)(3) of
SMCRA requires that the regulatory
authority use this determination and
other available information to prepare
an assessment of the probable
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
cumulative impact of all anticipated
mining in the area on the hydrologic
balance. The SMCRA regulatory
authority may not issue a permit unless
it first finds that the operation has been
designed to prevent material damage to
the hydrologic balance outside the
permit area. While there is some
overlap, the thresholds for permit
issuance under SMCRA are not the same
as the thresholds under Section 404 of
the Clean Water Act. Given the different
permit issuance thresholds of SMCRA
and Section 404 of the Clean Water Act,
NWP 21 authorizations cannot only rely
on the environmental reviews
conducted under SMCRA to satisfy the
minimal effects requirement.
Section 404 of the Clean Water Act
applies to all discharges of dredged or
fill material into waters of the United
States, unless those activities qualify for
an exemption under Section 404(f) of
the Clean Water Act. Section 404(f) does
not specifically exempt surface coal
mining activities. For those activities
that do not qualify for an exemption
from the permit requirements of the
CWA, the Corps must evaluate
applications for Department of the Army
permits, including general permits, and
either apply the 404(b)(1) Guidelines (if
an individual permit is required) or
determine whether the proposed
activity qualifies for NWP authorization.
This NWP provides an efficient means
of authorizing discharges of dredged or
fill material into waters of the United
States that result in minimal individual
and cumulative adverse effects on the
aquatic environment. Corps districts
work with SMCRA regulatory
authorities to reduce duplication, but
each agency must still ensure that
proposed activities comply with their
respective statutes and implementing
regulations.
Two commenters stated the primary
effect of adopting any of the three
options proposed for NWP 21 in the
February 16, 2011, Federal Register
notice would be to require proposed
surface coal mining activities involving
discharges of dredged or fill material
into waters of the United States to be
evaluated under the individual permit
process. This would cause an
unnecessary additional delay and
expense to mine operators and require
the Corps to get additional personnel
and funding to process additional
individual permit applications in a
timely manner. One commenter
suggested that NWP 21 should be
reissued as it was in 2007, and that
regional conditions should be used in
Appalachia to ensure those activities
result in minimal adverse effects on the
aquatic environment. This commenter
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
said this approach would allow western
coal producers to continue their
operations without negative
consequences.
We acknowledge that reissuing NWP
21 with a 1⁄2-acre limit, a 300 linear foot
limit for the loss of stream bed, and not
authorizing discharges of dredged or fill
material into waters of the United States
to construct valley fills, will result in
more surface coal mining activities
requiring Clean Water Act Section 404
individual permits. To provide an
equitable and less burdensome
transition to the new limits to NWP 21,
under paragraph (a) NWP 21 continues
to authorize surface coal mining
activities that were previously
authorized under the 2007 NWP 21
without those new limits. Under
paragraph (b), the 1⁄2-acre and 300 linear
foot limits, as well as the prohibition
against authorizing discharges of
dredged or fill material into waters of
the United States to construct valley
fills, apply to surface coal mining
activities that were not authorized by
the 2007 NWP 21. Expansions of
activities that were previously verified
under the 2007 NWP 21 do not qualify
for paragraph (a) of NWP 21.
Continuing to authorize surface coal
mining activities that were verified
under the 2007 NWP 21 will reduce
burdens on the regulated public while
protecting the aquatic environment in
accordance with the requirements of
Section 404(e) of the Clean Water Act.
These project proponents who received
verifications under the 2007 NWP 21
expended substantial resources to
obtain their authorizations. If they
cannot comply with the new limits
imposed on NWP 21 it would impose a
significant hardship to require those
operators to cease surface coal mining
activities in waters of the United States
while they apply for individual permits
and wait for a decision. We estimate
that there are approximately 70 surface
coal mining activities across the country
that were authorized by the 2007 NWP
21 that may qualify for authorization
under paragraph (a) of NWP 21 when it
goes into effect on March 19, 2012. To
obtain authorization under paragraph (a)
of the 2012 NWP 21, these project
proponents do not need to submit a preconstruction notification since they
already did so under the 2007 NWP 21
and that notification will be on file at
the district office. Instead, those project
proponents only need submit a letter to
the district engineer requesting
verification under the 2012 NWP 21.
That letter should be sent to the district
engineer by February 1, 2013, although
that deadline may be extended in
writing by the district engineer. This
PO 00000
Frm 00027
Fmt 4701
Sfmt 4703
10209
date allows the district engineer
approximately 45 days for review of the
letter before the expiration of the oneyear period that is allowed for
completion of activities authorized
under the 2007 NWP 21. Any changes
to the previously authorized surface
coal mining activity must also be
described in that letter, so that the
district engineer can determine whether
the activity still results in minimal
individual and cumulative adverse
effects on the aquatic environment and
is eligible for authorization under
paragraph (a) of NWP 21. The district
engineer will review such requests and
notify the permittee whether the activity
is authorized by the 2012 NWP 21.
There will be no agency coordination of
these previously authorized NWP 21
activities. Any currently applicable
regional conditions and any activityspecific conditions, such as
compensatory mitigation requirements,
would apply to the NWP authorization.
The district engineer may also revise
such conditions and requirements if the
existing ones are determined not to be
adequate to ensure minimal adverse
effects. If the permittee does not receive
a written verification from the district
engineer prior to the expiration of the
one-year period provided in 33 CFR
330.6(b), the permittee must cease all
activities until such verification is
received because that one-year period
cannot be extended. The surface coal
mine activity must be authorized under
the 2012 NWP 21 or another form of
Department of the Army authorization
to discharge dredged or fill material into
waters of the United States after the oneyear period ends on March 18, 2013.
The district engineer may also extend
the February 1, 2013, deadline by
notifying the permittee in writing, if he
or she needs less than 45 days to make
a decision on the 2012 NWP 21
authorization. The Corps encourages
operators who received a 2007 NWP 21
verification and plan to operate past
March 18, 2013, to submit their letter as
soon as possible to allow for
uninterrupted NWP 21 permit coverage.
Expansions of previously verified NWP
21 activities that result in greater losses
of waters of the United States are not
authorized under paragraph (a) will
require a different form of Department
of the Army authorization if they do not
qualify for authorization under
paragraph (b) of NWP 21. If the surface
coal mining activity involving
discharges of dredged or fill material
into waters of the United States
authorized under paragraph (a) cannot
be completed by the time the 2012 NWP
21 expires, then the project proponent
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10210
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
will have to obtain an individual permit
or regional general permit, if the activity
does not qualify for an applicable NWP
issued in 2017. The Corps recommends
that any projects that will extend
beyond March 18, 2017, that do not
meet the new limits in NWP 21 apply
for an individual permit and allow
sufficient time for the Corps to process
their application to allow uninterrupted
coverage when the new NWP 21 expires
in 2017.
The limits added to paragraph (b) of
NWP 21 will ensure that this NWP
authorizes only those activities that
have minimal adverse effects on the
aquatic environment, individually and
cumulatively. These limits will also
result in more new projects needing to
obtain individual permits. The Corps
has the resources necessary to process
those individual permit applications in
a timely manner. It is important for coal
mine operators to consider the
advantages of obtaining individual
permits for surface coal mining
activities. In accordance with Section
404(e) of the Clean Water Act, general
permits, including NWPs, can be issued
for a period of no more than five years.
Individual permits can be issued for
longer periods of time—the expiration
date for an individual permit is at the
discretion of the district engineer, who
will take into account the characteristics
of the proposed activity and the amount
of time expected to be needed to
complete the regulated activities.
Therefore, it would often be
advantageous for a surface coal mine
operator to obtain an individual permit
that would authorize discharges of
dredged or fill material into waters of
the United States for the expected
operational timeframe for that particular
coal mine. Under NWP 21, no
authorization could be issued for a time
period of more than five years. If the
NWP 21 activity is not completed by the
expiration date of the NWP
authorization then the project
proponent would have to notify the
district engineer and obtain another
NWP verification.
Nationwide permit NWP 21 preconstruction notifications require
substantial resources to evaluate
proposed activities and determine
whether they result in minimal
individual and cumulative adverse
effects on the aquatic environment, and
whether compensatory mitigation is
needed to comply with the minimal
adverse environmental effects
requirement for general permits. Under
the 2007 NWP 21, the project proponent
could not proceed until he or she
obtained an NWP 21 verification. The
substantial amount of review required
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
for both NWP 21 pre-construction
notifications and individual permit
applications both involve considerable
amounts of resources from the Corps, so
we do not expect a significant increase
in workload or processing times to
occur through the implementation of
Option 2 and the modifications we
made to that option for the final NWP.
In response to the NWP 21 proposal,
one commenter said the Corps was
attempting to decide on behalf of the
United States government how much
coal mining should take place, or what
scale of mining operations is
appropriate. The commenter suggested
that the Corps only concern should be
the scale of the regulated activity and
not the scale of the mining operation.
The commenter stated that the Corps
evaluation of surface coal mining
activities should be focused on impacts
to aquatic resources. One commenter
said the proposed changes to NWP 21
would have a significant effect on
energy supply, since the ability to
obtain permits in a timely manner is
essential to the production of coal,
which provides over 30 percent of
America’s electric power.
The three options provided in the
February 16, 2011, Federal Register
notice were intended to solicit comment
to assist the Corps in identifying an
option for the reissuance of NWP 21 that
would comply with the statutory and
regulatory requirements for general
permits. Those options were developed
to determine which terms and
conditions (if any) should be established
to ensure that NWP 21 authorizes only
those activities that result in minimal
adverse effects on the aquatic
environment. The proposal does not
affect how much coal mining may take
place, nor does it have a significant
effect on energy supply, because those
surface coal mining activities that do
not qualify for NWP 21 authorization
may be authorized by individual
permits or general permits, if such
general permits are available. The Corps
review is focused on adverse effects to
aquatic resources, as well as other
public interest review factors. The limits
on the use of NWP 21 are expressed in
terms of impacts to the aquatic
environment, not the scale of the mining
operation. Other aspects of surface coal
mining activities are regulated by
OSMRE or delegated states under
SMCRA.
One commenter said that NWP 21
should not apply to ephemeral waters
because they are not jurisdictional
waters of the United States. Several
commenters stated that NWP 21
encourages operators to design their
projects within the scope of the NWP
PO 00000
Frm 00028
Fmt 4701
Sfmt 4703
rather than seek an individual permit,
thereby reducing impacts. These
commenters said that there may be a net
gain of wetland acreages because of
reclamation practices at surface coal
mines.
Ephemeral streams are waters of the
United States if they meet the definition
of ‘‘waters of the United States’’ at 33
CFR part 328 and applicable guidance
on Clean Water Act jurisdiction, such as
the guidance issued in 2008 entitled
‘‘Clean Water Act Jurisdiction Following
the U.S. Supreme Court’s Decision in
Rapanos v. United States and Carabell
v. United States.’’ The NWP 21 issued
in 2007 did not have any acreage or
linear foot limits, which are the primary
tools used to encourage avoidance and
minimization to qualify for NWP
authorization. Except for those
previously verified 2007 NWP 21
activities authorized under paragraph
(a), the NWP 21 reissued today has a 1⁄2acre limit and a 300-linear foot limit for
losses of stream bed, which will be more
effective in encouraging project
proponents to avoid and minimize
losses of waters of the United States to
quality for NWP 21 authorization. We
acknowledge that there may be net gains
in wetland acreage at some surface coal
mining reclamation sites, but we have
imposed limits on NWP 21 because of
concerns about losses of stream bed and
the potential for surface coal mining
activities to have more than minimal
adverse effects on the aquatic
environment, individually and
cumulatively.
One commenter disagreed with the
Corps assertion that valley fills
substantially alter watersheds and result
in adverse impacts on the aquatic
environment. This commenter also said
that Options 2 and 3 do not allow the
Corps the flexibility to increase the
amount of stream bed loss above the 300
linear foot limit. The commenter also
objected to the proposed interagency
coordination for activities resulting in a
loss of greater than 1,000 linear feet of
intermittent and ephemeral stream beds,
and said the Corps has not suggested
any reasons for this restrictive
provision.
Surface coal mining activities
involving the construction of valley fills
result in substantial changes to the
watersheds of the headwater streams
that are primarily impacted by these
activities. Those watersheds are
changed by the large amounts of land
clearing and earthmoving that occur
during the mining activity. The
construction of the valley fill itself
causes changes to the geomorphology of
the watershed, which affects water
quality and watershed hydrologic
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
functions, such as water collection,
transport, and storage. It is well
documented in the scientific literature
that changes in land use affect the
quantity and quality of streams,
wetlands, and other aquatic resources.
Examples of such scientific studies are
cited in the decision document for this
NWP. The 300 linear foot limit for
losses of stream bed is generally
necessary to ensure that NWP 21
authorizes only those activities that
result in minimal adverse effects on the
aquatic environment. However, that 300
linear foot limit may be waived by the
district engineer if the proposed activity
involves filling or excavating
intermittent or ephemeral stream beds
and the district engineer determines, in
writing, that that activity will result in
minimal individual and cumulative
adverse effects on the aquatic
environment. Agency coordination for
proposed losses of greater than 300
linear feet of intermittent or ephemeral
stream bed is intended to provide
information that will assist the district
engineer in making his or her minimal
adverse effects determination.
One commenter said all Corps
divisions and districts should add
regional modification alternatives to
address differences in aquatic resources
functions. This commenter also stated
that the proposal provides that the
cumulative impact analysis for an NWP
21 is not limited to assessing impacts of
the use of the NWP 21 on a national
basis and is not limited to activities
authorized by NWPs or other
Department of Army permits. The
commenter acknowledged that the
Corps considers activities not regulated
by the Corps, including private actions
and those resulting in changes in the
use of uplands next to or near wetlands,
streams, or other aquatic resources
during the cumulative effects analysis.
It is at the division engineer’s
discretion whether to add regional
conditions to an NWP to ensure that the
NWP authorizes only those activities
that have minimal individual and
cumulative adverse effects on the
aquatic environment. In addition,
district engineers may modify NWP
authorizations by adding activityspecific conditions to minimize adverse
environmental effects. The decision
documents comply with the two
relevant approaches for conducting
cumulative effects analyses: (1) The
approach provided in the Council on
Environmental Quality’s definition of
‘‘cumulative impact’’ provided in their
National Environmental Policy Act
regulations at 40 CFR 1508.7, and (2) the
approach indicated in the 404(b)(1)
Guidelines at 40 CFR 230.7(b).
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
One commenter said the proposed
changes to NWP 21 will actually
increase impacts because mining
operators will need to increase the size
of their mining sites to make the
individual permit process cost effective.
The commenter said operators will no
longer be able to afford to mine the
smaller reserve areas, so larger mine
areas would need to be permitted.
The changes to NWP 21 are
appropriate to help ensure that this
NWP complies with the statutory
requirements for general permits, in that
it may only authorize activities that
have minimal individual and
cumulative adverse environmental
effects. Surface coal mining activities
involving discharges of dredged or fill
material into waters of the United States
that do not qualify for NWP
authorization will be evaluated as
individual permits if applicable regional
general permits are not available.
Activities authorized by individual
permits must comply with the 404(b)(1)
Guidelines and undergo an alternatives
analysis. A public interest review will
also be conducted during the individual
permit review process. Mining
companies will have to make their own
decisions on whether it is economically
viable to mine smaller reserve areas, and
apply for Department of the Army
authorization if proposed activities
involve discharges of dredged or fill
material into waters of the United
States.
One commenter said that if Option 2
is adopted, it should include a
definition of valley fill. A commenter
stated that the utility of NWP 21 would
be substantially reduced because losses
of waters of the United States caused by
the construction of attendant features
such as ponds and roads would be
counted towards the 1⁄2-acre and 300
linear foot limits. Another commenter
indicated that the 1⁄2-acre limit would
only authorize small sediment ponds.
This commenter stated that small
sediment ponds would not be able to
effectively service a typical mine site.
One commenter requested clarification
on whether the amount of stream that is
impounded for sediment ponds will be
counted as a loss of waters of the United
States and whether these ponds will
have to be removed upon completion of
the mining.
We have added a definition of the
term ‘‘valley fill’’ to the text of this
NWP. While fewer surface coal mining
activities involving discharges of
dredged or fill material into waters of
the United States would be authorized
by NWP 21 when compared to previous
issued versions of this NWP, the new
terms and conditions of this NWP,
PO 00000
Frm 00029
Fmt 4701
Sfmt 4703
10211
including the 1⁄2-acre and 300 linear foot
limits, are necessary to ensure that this
NWP authorizes only those activities
that have minimal individual and
cumulative adverse effects on the
aquatic environment. If the construction
of larger sediment ponds does not
qualify for NWP 21 authorization,
activities may be authorized by
individual permits or applicable
regional general permits. In the
definition of ‘‘loss of waters of the
United States’’ the loss of stream bed is
determined by the amount of linear feet
of stream bed that is filled or excavated.
As to whether sediment ponds would
have to be removed upon completion of
the mining operation, that would be a
case-specific determination made by the
district engineer after taking into
account requirements of the SMCRA
authority.
One commenter asked how many
surface coal mining activities may be
authorized each year with NWP 21 if
Option 2 is selected. One commenter
said the proposed changes to NWP 21
would be costly to small businesses and
disagreed with the Corps statement that
the revised NWPs will not impose
substantially higher costs on small
entities than those of existing permits.
Another commenter indicated that the
proposed changes to NWP 21 would
result in more environmental impact
statements being required because of the
amount of wetlands in their area.
In section 6.2.2 of the decision
document for this NWP, we provide
estimates of the number of times we
predict NWP 21 will be used each year.
Under paragraph (b), we estimate that
NWP 21 will be used approximately 11
times per year, although more activities
may qualify for NWP 21 authorization if
project proponents do additional
avoidance and minimization to reduce
losses of waters of the United States to
satisfy the acreage and linear foot limits.
As discussed above, we estimate that,
across the country, approximately 70
NWP 21 activities verified under the
2007 NWP 21 might be re-verified under
paragraph (a) of the 2012 NWP 21. The
estimate provided in the decision
document was based on an analysis of
past use of NWP 21, and it is a rough
estimate because NWP 21 did not have
an acreage or linear foot limit and we
cannot predict how many activities can
be modified to comply with the new
limits. Therefore, it is difficult to
accurately predict how often project
proponents will qualify for
authorization under the NWP 21 issued
today. Since fewer surface coal mining
activities are likely to qualify for NWP
21 authorization, and more will require
individual permits, we acknowledge
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10212
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
that there will be greater compliance
costs for small businesses. In the
preamble to the proposal, where we
discuss compliance with the Regulatory
Flexibility Act, we state that the
proposed NWPs would not result in a
significant impact on a substantial
number of small entities. That statement
was made in the context of considering
all of the 48 NWPs proposed to be
reissued and the two proposed new
NWPs. Some NWPs, such as NWP 48,
will require fewer pre-construction
notifications and other requirements on
small entities while other NWPs, such
as NWP 21, will have more stringent
requirements to satisfy the minimal
adverse environmental effects standard
and will authorize fewer activities. We
do not agree that these changes to NWP
21 will result in significantly more
environmental impact statements. The
threshold for NWP authorization, as
well as for other general permits, is
minimal adverse environmental effects.
The threshold for preparing an
environmental impact statement is that
the activity constitutes a major Federal
action significantly affecting the quality
of the human environment. Since the
threshold that triggers the requirement
to prepare an environmental impact
statement is greater than the minimal
adverse environmental effects threshold
for NWP activities, activities that were
previously authorized by NWP should
generally not require an environmental
impact statement if they are instead
evaluated through the individual permit
process. Environmental assessments
should suffice to provide National
Environmental Policy Act compliance
for most, if not all, of those activities. If
the adverse effects on the aquatic
environment for a proposed NWP
activity are determined by the district
engineer to be more than minimal
individually and cumulatively, then
discretionary authority should be
exercised and the proposed activity
evaluated through the individual permit
process.
Many commenters said that that it
would be more appropriate to establish
different NWP terms and conditions for
different areas of the United States,
because of vast differences in geological,
topographical, climatologically and
ecological regimes in areas where coal
resources are located across the country.
One of these commenters recommended
focusing on the use of regional
conditions to address regional
differences in coal mining techniques
and issues, instead of modifying NWP
21.
An NWP is developed to authorize
specific categories of activities across
the country that have minimal
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
individual and cumulative adverse
effects on the aquatic environment and
is issued by Corps Headquarters. There
must be a national decision document
for each NWP, and to issue that NWP,
there must be a finding that the NWP
will authorize only those activities that
have minimal individual and
cumulative adverse effects on the
aquatic environment. Division and
districts prepare supplemental decision
documents to explain whether regional
conditions are needed to satisfy the
minimal adverse effects requirement.
Regional conditions are added to an
NWP at a division engineer’s discretion
and Corps Headquarters cannot mandate
the adoption of regional conditions.
The national decision documents
acknowledge that regional conditions
approved by division engineers and
activity-specific conditions added to
NWP authorizations are procedures to
be relied upon to satisfy the minimal
adverse environmental effects
requirement. In those areas of the
country where surface coal mining
activities result in minimal individual
and cumulative adverse effects on the
aquatic environment but exceed the
limits of NWP 21, division and district
engineers may issue regional general
permits that have different terms and
conditions than NWP 21, including
larger acreage or linear foot limits.
Those regional general permits are a
more appropriate mechanism for
considering local geologic, topographic,
climatologic, and ecological
characteristics.
Some commenters stated that
Executive Order 13563, ‘‘Improving
Regulation and Regulatory Review’’ asks
federal agencies to tailor regulations to
impose the least burden on society,
including individuals, businesses of
differing sizes, and other entities. These
commenters said that adding additional
redundant review by Federal agencies
violates this Executive Order and
threatens energy supplies. One of these
commenters said the proposal to reissue
NWP 21 with modifications is contrary
to the objectives of Executive Order
13563 because it fails to use the best,
most innovative and least burdensome
tools for achieving regulatory ends and
that the proposed limits in NWP 21 are
redundant, inconsistent, or overlapping
with other regulations.
As explicitly recognized in Executive
Order 13563 itself, an Executive Order
does not supersede Federal laws, such
as the requirements in the Clean Water
Act, the Rivers and Harbors Act of 1899,
the Endangered Species Act, and the
National Historic Preservation Act.
Section 404(e) of the Clean Water Act
states that general permits (including
PO 00000
Frm 00030
Fmt 4701
Sfmt 4703
NWPs) authorize categories of activities
that are similar in nature and result only
in minimal individual and cumulative
adverse environmental effects. The
Corps complied with Section 2 of
Executive Order 13563 by seeking
public comment on the proposal to
reissue NWP 21 with modifications, for
a 60-day comment period. The Corps
has determined that the changes to NWP
21 are necessary to comply with the
requirements of Section 404(e) of the
Clean Water Act. We have modified
Option 2 by authorizing activities
verified under the 2007 NWP 21 (see
paragraph (a) of NWP 21), to provide an
equitable transition to the new limits in
NWP 21 and reduce burdens on the
regulated public. The authority for the
district engineer to waive the linear foot
limit for losses of intermittent and
ephemeral streams if the impacts are not
more than minimal is also intended to
minimize regulatory burden. As
discussed earlier in this section, the
terms and conditions of NWP 21 are not
duplicative with the requirements of
other Federal agencies. While surface
coal mining activities are more broadly
regulated under the Surface Mining
Control and Reclamation Act by the
Office of Surface Mining Reclamation
and Enforcement or approved states, the
Corps regulates discharges of dredged or
fill material into waters of the United
States, and focuses its evaluation on the
effects those discharges have on the
aquatic environment or its other public
interest review factors (see 33 CFR
330.1(d) and (e)(2)). Those activities that
do not qualify for NWP authorization
may be authorized by other forms of
Department of the Army authorization,
such as individual permits or regional
general permits. The standards the
Corps uses to ensure compliance with
the Clean Water Act differ from the
standards used by the Office of Surface
Mining Reclamation and Enforcement or
approved states to ensure compliance
with the Surface Mining Control and
Reclamation Act, and those standards
are not redundant.
A commenter disagreed with the
Corps statement that the proposed
NWPs are not a significant energy action
as defined by Executive Order 13211
because of the proposed changes to
NWP 21. The commenter said the Corps
must prepare a Statement of Energy
Effects as required by the Executive
Order, including a description of the
adverse impacts expected to the
production of coal, the nation’s primary
electrical generation fuel supply. One
commenter said that the time frames for
evaluating NWP 21 pre-construction
notifications should be similar to those
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
of other NWPS, and NWP 21 should not
require the project proponent to wait
until he or she receives a written NWP
verification even if the 45-day review
period has passed.
The changes to NWP 21 are
appropriate and help to ensure that the
NWP authorizes only those discharges
of dredged or fill materials into waters
of the United States that have minimal
adverse effects on the aquatic
environment, individually and
cumulatively. Surface coal mining
activities that involve discharges of
dredged or fill material into waters of
the United States that do not qualify for
NWP authorization may be authorized
by individual permits or, if available,
applicable regional general permits,
which would still support the
production of coal to supply the
nation’s energy needs. Given the
adverse environmental effects
associated with surface coal mining
activities involving discharges of
dredged or fill material into waters of
the United States, which are discussed
in the decision document for this NWP,
we believe it is necessary to retain the
existing requirement that the project
proponent may not proceed with the
NWP 21 activity until after he or she has
obtained a written NWP 21 verification.
Project proponents are already
accustomed to complying with this
requirement and plan accordingly.
One commenter suggested
establishing a grandfathering period for
surface coal mining activities authorized
by the NWP 21 issued in 2007, to allow
permittees to complete their currently
approved mitigation plans without an
added burden of updating permits.
Another commenter asked how project
proponents are expected to transition
from the current 2007 NWP 21 to one
of the selected options for reissuing
NWP 21, if NWP 21 is reissued under
either Option 2 or 3.
As discussed above, we have revised
NWP 21 to continue the NWP
authorization for surface coal mining
activities that were verified under the
2007 NWP 21, to provide project
proponents until March 18, 2017, to
complete those activities under NWP
21. The acreage limits, linear foot limits,
and prohibition against discharges of
dredged or fill material into waters of
the United States to construct valley
fills apply to those surface coal mining
activities that were not previously
authorized by the 2007 NWP 21. We
believe this approach for transitioning
to the new NWP 21 limits provides both
protection to the aquatic environment
and is equitable to those members of the
regulated public who made substantial
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
investments in reliance on a previously
verified NWP 21 authorization.
One commenter said that a preconstruction notification should be
required for all NWP 21 activities, so
plans and permit conditions could be
reviewed to ensure that contaminated
water being generated during these
activities is not later reaching open
water and impacting state-owned lands.
One commenter expressed concern that
historic resources impacts are not
considered under SMCRA in cases
where the program has been delegated
to states.
To be authorized by this NWP, the
project proponent must submit a preconstruction notification, so that the
district engineer can evaluate the
proposed activity and ensure that it
qualifies for NWP authorization.
Activities authorized by this NWP must
comply with general condition 20,
historic properties. If the proposed
activity has the potential to cause effects
to historic properties, consultation
under Section 106 of the National
Historic Preservation Act will be
conducted before the district engineer
determines whether the activity is
authorized by NWP.
This NWP is reissued with the
modifications discussed above.
NWP 22. Removal of Vessels. There
were no changes proposed for this NWP,
and no comments were received. This
NWP is reissued without change.
NWP 23. Approved Categorical
Exclusions. There were no changes
proposed for this NWP. One commenter
requested that this NWP be limited to
federal applicants only. One commenter
requested that the NWP be modified to
allow any agency with categorical
exclusions to use this NWP, not just
those that have been approved by the
Office of the Chief of Engineers. One
commenter recommended adding
references to requirements to comply
with other applicable federal laws, such
as Section 106 of the National Historic
Preservation Act. One commenter stated
that this NWP does not take into
consideration the actions that may
impact Tribal treaty cultural or natural
resources and requested that
notification be provided to affected
tribes regardless if considered a
categorical exclusion.
This NWP applies only to those
activities ‘‘undertaken, assisted,
authorized, regulated, funded or
financed, in whole or in part, by another
Federal agency or department.’’ In
certain instances, another agency, such
as a state department of transportation,
may legally assume the responsibility
for categorical exclusion determinations
for a Federal entity. To ensure
PO 00000
Frm 00031
Fmt 4701
Sfmt 4703
10213
compliance with the requirements for
general permits, it is necessary for the
Office of the Chief of Engineers to
review and approve agency categorical
exclusions for use with this NWP. In
cases where the Federal agency is
responsible for compliance with the
National Historic Preservation Act, the
Endangered Species Act, or other
Federal laws, the Corps can accept their
compliance, as long as it adequately
covers the activity authorized by the
NWP. The same principle applies for
Tribal treaty natural or cultural
resources: If the agency issuing the
categorical exclusion that qualifies for
NWP 23 authorization has sufficiently
addressed the Tribal treaty resources,
then the Corps district can accept that
as a basis for compliance with general
condition 17, tribal rights.
One commenter stated that this NWP
authorizes activities that are not similar
in nature, and its use does not result in
minimal adverse effects on the aquatic
environment. One commenter said that
the approved categorical exclusions
need to be reassessed to ensure that they
still meet the minimal adverse
environmental effects requirement for
general permit activities. One
commenter said that pre-construction
notification should be required for all
NWP 23 activities to ensure adequate
interagency coordination. Another
commenter said that reporting to the
Corps should be required for any
activity that affects wetlands,
encroaches on a regulatory floodway,
affects the water level of a 100-year
flood event, or affects waters designated
as critical resource waters.
This NWP, along with the Regulatory
Guidance Letter listing the approved
categorical exclusions, authorizes
activities that are similar in nature. The
Corps believes that their eligibility for
NEPA compliance using a categorical
exclusion is an appropriate basis of
‘‘similarity’’ for their authorization
under this NWP. Based on the NEPA
requirements for use of categorical
exclusions, the Corps has determined
that these activities will result in
minimal individual and cumulative
adverse effects on the aquatic
environment, and division engineers
have the authority to regionally
condition this NWP to restrict or
prohibit its use if they determine that
these activities are resulting in more
than minimal adverse environmental
effects. We do not agree that the
approved categorical exclusions need to
be re-evaluated because of the length of
time that has passed since they were
originally approved. Agencies have an
on-going responsibility to review their
categorical exclusions and ensure that
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10214
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
the activities they authorize still qualify
for this type of NEPA compliance.
Division engineers may also regionally
condition this NWP to require agency
coordination for specific categorical
exclusions that have been approved for
use with this NWP. We do not agree that
reporting or pre-construction
notification should be required for all
activities that may affect wetlands.
Activities that encroach upon regulatory
floodways or affect 100-year flood
elevations are more appropriately
addressed through applicable Federal
Emergency Management Agencyapproved state or local floodplain
management requirements (see general
condition 10). General condition 22,
designated critical resource waters,
requires pre-construction notification
for any NWP 23 activity that is proposed
in designated critical resource waters
and wetlands adjacent to those waters.
The proposed NWP is reissued with
no changes.
NWP 24. Indian Tribe or State
Administered Section 404 Programs.
There were no changes proposed for this
NWP, and no comments were received.
This NWP is reissued without change.
NWP 25. Structural Discharges. We
did not propose any changes to this
NWP. One commenter stated that
concrete should be cured for a full seven
days before coming in contact with
water. One commenter stated structures
constructed by such discharges on stateowned lands may require a ‘‘use
authorization’’ from the state.
Specific requirements for the curing
of concrete are more appropriately
addressed as regional conditions or
activity-specific conditions added to an
NWP 25 authorization. Project
proponents are responsible for obtaining
any other federal, state, or local permits
that may be required for a particular
activity.
The NWP is reissued without change.
NWP 27. Aquatic Habitat Restoration,
Establishment, and Enhancement
Activities. We proposed to modify this
NWP by adding ‘‘the removal of small
dams’’ to the list of examples of
activities authorized by this NWP. We
also proposed to remove the phrase
‘‘that has not been abandoned’’ that
modifies the term ‘‘prior converted
cropland.’’ We proposed to change
‘‘Notification’’ provisions (1) and (2) so
that certain stream restoration,
rehabilitation, and enhancement
activities would be subject to the
reporting provision instead of requiring
pre-construction notification. Lastly, we
proposed to modify ‘‘Notification’’
provision (1) by adding the U.S. Forest
Service to the list of Federal agencies
that can develop stream or wetland
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
enhancement, restoration, or
establishment agreements.
Many commenters supported the
addition of removal of small dams to the
list of examples of activities authorized
by this NWP. One commenter said that
if this NWP is modified to authorize the
removal of small dams, the NWP should
also authorize discharges of dredged or
fill material to re-establish appropriate
stream channel configurations, with a
1⁄2-acre limit for the stream channel
reconfiguration. Some of these
commenters requested clarification as to
what constitutes a ‘‘small dam.’’ One
commenter agreed with the addition of
removing small dams but expressed
concern regarding potential impacts to
water quality when a small dam is
removed. One commenter
recommended requiring sediment
testing before authorizing the removal of
small dams.
After further consideration, we have
determined that since the NWP 27
issued in 2007 authorized the
installation, removal, and maintenance
of small water control structures (which
clearly includes small dams), it is not
necessary to modify this NWP by adding
the removal of small dams to the list of
examples of activities authorized by
NWP 27, so we have not made this
proposed change. We agree that the
NWP should also authorize the
restoration of the stream channel that
were affected by the construction of a
small water control structure, if that
water control structure is to be removed.
We do not agree that such activities
should be limited to 1⁄2-acre, since this
NWP authorizes only aquatic resource
restoration, establishment, and
enhancement activities that result in net
increases in aquatic resource functions
and services. Aquatic resource habitat
restoration and enhancement activities
involving the removal of small water
control structures should be designed
and implemented to prevent or
minimize the movement of pollutants,
including chemical compounds
adsorbed to sediments that have
accumulated in the impoundment, from
the impounded area once the small
water control structure is removed.
Sediment testing may be required on a
case-by-case basis if there are
substantive concerns about potential
contaminants.
Several commenters suggested that
NWP 27 activities be subject to strict
technical guidelines and enforceable
success criteria commensurate with the
scope of the activity being undertaken.
A number of commenters expressed
concern that some of the activities
authorized by NWP 27 may result in a
loss of waters rather than a net gain.
PO 00000
Frm 00032
Fmt 4701
Sfmt 4703
One commenter said that aquatic
resource restoration, establishment, and
enhancement activities should have
management plans that include goals
and objectives, baseline conditions,
effective monitoring requirements, and
adaptive management plans. This
commenter stated that without this level
of documentation, the effectiveness of
any restoration, establishment, or
enhancement activity cannot be
effectively evaluated for success. One
commenter recommended adding a
requirement for performance bonds to
ensure that these activities are
monitored and are achieving their goals
and objectives.
For those NWP 27 activities that
require pre-construction notification,
the prospective permittee is required to
submit a complete pre-construction
notification, with the information listed
in paragraph (b) of general condition 31.
Activities conducted in accordance with
agreements with other Federal or state
agencies should be adequately
documented to determine whether there
will be net increases in aquatic resource
functions and services. When Corps
districts review the reports required for
activities conducted under agency
agreements, they will assess whether
those activities will satisfy the terms
and conditions of this NWP. If a
particular activity does not, then the
district will notify the project proponent
within 30 days of when the report was
submitted to the district engineer. This
NWP requires authorized activities to
result in net increases in aquatic
resource functions and services, which
will generally add acreage to the
nation’s aquatic habitat base. Although
there may be some NWP 27 activities
that result in a decrease in aquatic
resource area to increase the functional
capacity of those aquatic habitats, such
changes are acceptable because it is the
ecosystem functions, and the benefits
people derive from those functions, that
are important to society. To provide
better information to assess whether
there will be a net increase in aquatic
resource functions and services, we
have added a provision to the reporting
requirement that requires the
prospective permittee to provide
information on the baseline ecological
conditions at the project site, such as a
delineation of wetlands, streams, and/or
other aquatic habitats. Unless the
activities authorized by this NWP are to
be used as compensatory mitigation for
Department of the Army permits (e.g.,
mitigation banks or in-lieu fee projects),
the project proponent is not required to
submit mitigation plans that comply
with 33 CFR 332.4. The aquatic resource
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
restoration, establishment, or
enhancement activity should be
sufficiently documented to help district
engineers decide whether the terms and
conditions of this NWP are satisfied.
Performance bonds or other types of
financial assurances may be required on
a case-by-case basis, if such assurances
are necessary to provide funding to be
used for remediation or adaptive
management.
One commenter requested that this
NWP authorize the rehabilitation or
enhancement of tidal streams, stating
that such activities would result in net
increases in the functions and services
provided by existing tidal aquatic
resources and would not be contrary to
the provision that prohibits the
relocation of tidal waters or the
conversion of tidal waters to other
aquatic uses. One commenter pointed
out that NWP 27 covers a wide range of
habitat restoration and enhancement
activities and there should be greater
flexibility to allow resource managers to
plan for sea level rise. This commenter
recommended adding the beneficial use
of dredged material as a thin layer
application to provide sediment to
sediment starved marshes, which may
provide substrate to maintain those
marshes as local sea levels rise. One
commenter suggested modifying this
NWP by clarifying that it authorizes
activities that involve removing or
modifying existing drainage ditches and
structures, to establish or re-establish
wetland or stream hydrology. Another
commenter suggested adding the reestablishment of submerged aquatic
vegetation or emergent tidal wetlands in
areas where those plant communities
previously existed. One commenter
supported the inclusion of mechanized
land clearing to remove non-native
invasive species in this NWP.
We agree that the rehabilitation or
enhancement of tidal streams should be
authorized by this NWP and have
modified the first paragraph to include
this category of activities. The
enhancement of tidal wetlands may be
accomplished by minor additions of
sediment to facilitate changes in tidal
marsh elevation that may successfully
track sea level rise. We agree with
providing more clarity concerning the
types of ditch manipulations that can be
used for restoring wetland hydrology
and have removed the phrase ‘‘and
drainage ditches’’ after ‘‘the backfilling
of artificial channels’’ and replaced it
with ‘‘such as drainage tiles, and the
filling, blocking, or reshaping of
drainage ditches to restore wetland
hydrology’’ after ‘‘the removal of
existing drainage structures.’’ We also
agree that the re-establishment of
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
submerged aquatic vegetation or
emergent tidal wetlands should be
authorized by this NWP, as long as
those shallow water habitat and wetland
types previously existed in the project
area. Such re-establishment activities
would not constitute a conversion of
tidal waters to other aquatic uses;
instead it would be a form of
rehabilitation of those habitat types. We
have retained the provision authorizing
mechanized land clearing to remove
non-native, invasive plant species.
One commenter requested that the
terms ‘‘type’’ and ‘‘natural wetland’’ be
defined in the paragraph that describes
the activities that are not authorized by
this NWP. Another commenter
supported the provision that prohibits
the conversion of natural wetlands to
another aquatic use and recommended
that this prohibition also be applied to
the conversion of one type of aquatic
habitat to another. One commenter said
that the NWP should clearly state that
wetlands with documented hydrologic
alterations are not ‘‘natural’’ wetlands
and that hydrologic restoration of these
wetlands is not to be considered a
conversion of a natural wetland to
another ‘‘type’’ but instead it should be
considered as wetland rehabilitation.
One commenter stated that a provision
should be added to this NWP to clarify
that compensatory mitigation is not
required for activities authorized by this
NWP since they must result in net
increases in aquatic resource functions
and services.
As indicated by the parenthetical in
the first sentence of the referenced
paragraph, the term ‘‘type’’ as used for
the purposes of this NWP refers to the
general category of aquatic resource,
such as wetland or stream. We do not
believe it would be appropriate to
define the term ‘‘natural wetland’’
except to contrast it with constructed
wetlands, such as those that are often
used to treat wastewater. District
engineer have the discretion to
determine what constitutes a ‘‘natural
wetland’’ for the purposes of this NWP.
We have added a sentence to this
paragraph to clarify that changes in
wetland plant communities that are
caused by restoring wetland hydrology
are to be considered wetland
rehabilitation activities that are
authorized by this NWP. Such wetland
rehabilitation activities are not to be
considered conversions to another
aquatic habitat type. We concur that
compensatory mitigation should not be
required for NWP 27 activities and have
added a sentence to the text of the NWP
to clearly state this stipulation.
One commenter said that the NWP
should prohibit the relocation of
PO 00000
Frm 00033
Fmt 4701
Sfmt 4703
10215
naturally occurring non-tidal aquatic
resources. One commenter suggested
changing the conversion provision to
state that no wetlands may be converted
to open water impoundments rather
than limiting the prohibition to tidal
wetlands. Another commenter stated
that while they understand the need for
language to clarify that conversion from
‘‘streams to wetlands’’ is not desirable,
there are some areas that have been
drained or ditched to create water flow
away from agricultural land, where
there was previously a wetland. This
commenter asked whether
reestablishing wetlands on the site
could be authorized by this NWP. The
commenter said that the NWP is too
restrictive and has the potential to
prohibit activities that may result in
aquatic resources that are more
appropriately integrated into the
landscape.
The relocation of non-tidal waters and
wetlands on a project site, including
relocation activities that convert open
water impoundments to non-tidal
wetlands and vice versa, can result in
net increases in aquatic resource
functions and services when viewed in
a watershed context. Therefore, we do
not agree that it is appropriate to
exclude such activity from coverage
under this NWP if it meets all other
conditions, including a net increase in
resource functions and services. Ditches
that were constructed in wetlands to
drain those wetlands are not considered
streams for the purposes of this
provision of the NWP. As discussed
earlier, this NWP authorizes the filling,
blocking, or reshaping of drainage
ditches to restore wetland hydrology.
One commenter asked if the removal
of bulkheads, derelict structures, and
pilings, can be authorized by this NWP
while another suggested that the NWP
allow for the temporary use of spat (e.g.,
larval oysters) collecting devices for the
purpose of shellfish restoration.
The removal of structures in navigable
waters of the United States is authorized
by this NWP if it is a part of an aquatic
habitat restoration or enhancement
activity. The temporary use of spat
devices for oyster habitat restoration is
more appropriately authorized by NWP
4.
One commenter said that the
provisions concerning shellfish seeding
are not clear and asked if the intent of
the NWP is to authorize shellfish
seeding activities to enhance threatened
shellfish populations. This commenter
also said that shellfish enhancement
activities should be limited to native
species. One commenter recommended
authorizing shellfish restoration
activities without requiring pre-
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10216
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
construction notification when such
activities are conducted or approved by
a government agency with resource
management oversight. One commenter
requested we not include shellfish
restoration activities in this NWP,
because these activities alter existing
substrate and benthic habitat and
should be reviewed under the
individual permit evaluation process.
This commenter also recommended
imposing a one-acre limit for the
placement of scattered shell.
This NWP authorizes shellfish
seeding activities, which may help
increase shellfish populations in
specific waters. Division engineers may
regionally condition this NWP to limit
shellfish seeding activities to native
species. Further, in response to a preconstruction notification or report, a
district engineer may exercise
discretionary authority and condition a
specific NWP authorization to limit it to
the seeding of native shellfish species.
We do not agree that there should be no
pre-construction notification
requirement if there is oversight by
another government entity with the
responsibility for managing shellfish
resources. Since these activities occur in
navigable waters, the Corps needs to
review them on a case-by-case basis to
ensure that they result in minimal
individual and cumulative adverse
effects on the aquatic environment and
navigation and provide net increases in
aquatic resource functions and services.
Shellfish restoration activities should be
authorized by this NWP because
shellfish provide important ecosystem
services in aquatic ecosystems,
including the improvement of water
quality. In most cases, the changes to
benthic habitat are minor when
compared to the ecosystem services
provided by the shellfish. We also do
not agree that there should be a one-acre
limit for the placement of shell to
construct oyster habitat because larger
oyster habitat construction activities can
still result in a net increase in aquatic
resource functions and services.
One commenter said that stream
restoration projects should be limited to
500 linear feet. One commenter stated
that the construction of small nesting
islands and the alteration of rare or
imperiled wetlands should be not be
authorized by this NWP. This
commenter also suggested acreage limits
for categories of activities authorized by
this NWP, such as limiting excavation of
wetlands to provide shallow water
habitat for wildlife to 1⁄2-acre in altered
wetlands; excavating no more than 11⁄2acre of wetlands that have been
regularly farmed within the past five
years or wetlands documented to be
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
dominated by invasive species; a 3-acre
limit for excavation activities; and
limiting the placement of fill for the
construction of dikes, berms, or water
control structures to two acres. This
commenter also recommended limiting
impoundments to a maximum height of
six feet, with a maximum impounded
area of no more than five acres during
a design flood. This commenter also
said that enhancement of hydrology
should not be authorized unless a state
agency concurs that the wetland has
been farmed within the last five years or
is dominated by invasive species.
Since this NWP authorizes only those
aquatic habitat restoration,
establishment, and enhancement
activities that result in net increases in
aquatic resource functions and services,
we do not agree that the recommended
limits should be added to this NWP.
Division engineers can regionally
condition this NWP to restrict or
prohibit its use over specific geographic
areas or categories of waters. In response
to a pre-construction notification,
district engineers can add conditions to
the NWP authorization to ensure that
the NWP authorizes only those activities
that result in minimal adverse effects on
the aquatic environment.
Two commenters supported the
addition of the United States Forest
Service as a federal agency that can
develop agreements for the restoration,
enhancement, or establishment of
streams and wetlands. One commenter
recommended removing the reversion
provision of NWP 27. Another
commenter said that the reversion
provision should be eliminated or
significantly modified because it is
inconsistent with other NWPs. Two
commenters stated that the reversion of
wetlands should not be authorized if the
wetlands were being used for
compensatory mitigation. One
commenter asked how many acres of
wetlands could be reverted under this
NWP. One commenter asked whether a
‘‘USDA Technical Service Provider’’
includes county soil and water
conservation districts.
The reversion provision is necessary
for those aquatic resource restoration,
enhancement, or establishment
activities that are done in accordance
with binding agreements, voluntary
actions, or permits, where those
agreements, actions, or permits allow
the project proponent to revert the
affected lands to its prior condition. If
the reversion provision is removed, it
would create a disincentive to do
certain aquatic restoration,
enhancement, or establishment
activities that could provide some
aquatic resource functions and services
PO 00000
Frm 00034
Fmt 4701
Sfmt 4703
for a substantial period of time and
benefit the watershed. Nationwide
permit 27 differs from the other NWPs
because of the types of activities it
authorizes. As stated in the Note at the
end of NWP 27, reversion of an area
used as a compensatory mitigation
project is not authorized by this NWP.
We do not track the acreage of wetland
or stream restoration and enhancement
activities, or of wetland establishment
activities, that were authorized by NWP
27 and might be eligible for reversion.
There is no limit on the amount of
wetlands that can be reverted under a
single authorization, provided all
conditions of the NWP are met. County
soil and water conservation districts can
register with the U.S. Department of
Agriculture to be a technical service
provider.
One commenter said that preconstruction notifications should
include photographs, a description of
pre-project site conditions, and a
discussion of general aquatic resource
functions and services anticipated to be
provided by the activity. Another
commenter stated that pre-construction
notification should be required for all
activities.
Paragraph (b) of general condition 31,
pre-construction notification, requires
prospective permittees to submit
documentation that describes the
proposed activity, including the
anticipated loss of waters of the United
States and, if appropriate, sketches that
help clarify the project. The preconstruction notification also must
include a delineation of wetlands, other
special aquatic sites, and other aquatic
habitats. We do not agree that preconstruction notification should be
required for all activities. The reporting
requirements for those activities that do
not require pre-construction notification
provide sufficient opportunity for
district engineers to notify a project
proponent if the proposed work does
not comply with the terms and
conditions of the NWP. We have
modified the ‘‘Reporting’’ provision of
this NWP to require the permittee to
submit information on the baseline
ecological conditions at the project site,
such as a delineation of wetlands,
streams, and/or other aquatic habitats.
We have also changed the
‘‘Notification’’ provision of this NWP by
replacing the phrase ‘‘the activity’’ with
‘‘any activity’’ to clarify that any activity
that does not require reporting requires
a pre-construction notification. The last
sentence of this NWP has been changed
to clarify that appropriate
documentation concerning the
agreement, voluntary action, or Surface
Mining Control and Reclamation Act
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
permit is to be provided to the district
engineer to fulfill the reporting
requirement.
One commenter said the NWP should
require the use of best management
practices to avoid sediment loading of
waters especially when mechanized
land clearing or work is conducted in
waters of the United States. The
commenter stated that best management
practices, such as floating barriers,
should also be used in upland areas to
protect downstream water quality. One
commenter stated that Tribes should be
notified to ensure that NWP 27 activities
avoid impacts to tribal treaty natural
resources and cultural resources.
General condition 12, soil erosion and
sediment controls, requires permittees
to implement appropriate soil and
erosion and sediment controls during
the work. In response to a preconstruction notification, district
engineers can add conditions to the
NWP authorization to require more
specific sediment and erosion controls.
Division engineers can impose regional
condition on this NWP to require
notification of the appropriate Tribe or
Tribes if a proposed activity might affect
tribal treaty natural resources and
cultural resources. General condition
17, Tribal rights, requires that no NWP
activity or its operation impair reserved
treaty rights, including treaty fishing
and hunting rights. Cultural resources
are protected through the requirements
of general condition 20, historic
properties, and general condition 21,
discovery of previously unknown
remains and artifacts.
This NWP is reissued with the
modifications discussed above.
NWP 28. Modifications of Existing
Marinas. There were no changes
proposed for this NWP. Two
commenters recommended adding a
condition to ensure the modification
does not encroach upon additional
waters. One commenter suggested
adding a condition to require a
minimum maneuvering distance for an
outside slip to the boundary of the
marina’s riparian interest area. One
commenter stated that modifications for
marinas on state-owned aquatic lands
should require pre-construction
notification.
This NWP clearly states that it does
not authorize expansions of existing
marinas. Since the NWP does not
authorize expansions of existing
marinas, it is not necessary to add a
condition to provide a minimum
maneuvering distance. Concerns about
modifications to marinas constructed on
state-owned submerged lands are more
appropriately addressed through a state
authorization process.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
This NWP is reissued without change.
NWP 29. Residential Developments.
We proposed to modify this NWP by
changing the waiver provision for
activities resulting in the loss of greater
than 300 linear feet of intermittent and
ephemeral stream bed, to clarify that the
district engineer will only issue the
waiver after making a project-specific
written determination that the activity
will result in minimal adverse effects.
One commenter said that this NWP
should not be reissued. One commenter
suggested revoking this NWP because of
the large scale of these projects and
associated impacts to waters and said
that individual permits should be
required for these activities. Two
commenters stated that the use of this
NWP permit to authorize 1⁄2-acre losses
of waters of the United States would
result in more than minimal adverse
effects on an individual and cumulative
basis. Two commenters said that this
NWP should not authorize residential
subdivisions, and should be limited to
single family homes. Four commenters
recommended decreasing the acreage
limit for losses of waters of the United
States to 1/4-acre. Two commenters
suggested increasing the acreage limit to
1 acre. One commenter requested
clarification on whether the acreage
limits are applied cumulatively when
there is any subsequent expansion of a
residential development.
We do not agree that this NWP should
not be reissued or limited to single
family homes. The construction of
residential developments, including
multiple unit residential developments,
may have minimal individual and
cumulative adverse effects on the
aquatic environment, and is appropriate
for NWP authorization if it meets the
conditions of this NWP. Provided the
limits are met, the effects to waters of
the United States are similar whether
single family homes or groups of single
family homes are constructed as a result
of using this NWP to authorize
discharges of dredged or fill material
into waters of the United States. The 1⁄2acre limit, as well as the other terms and
conditions of this NWP, is consistent
with longstanding limits on this and
other NWPs, and is appropriate for
ensuring that this NWP authorizes only
those activities with minimal adverse
effects on the aquatic environment.
Division engineers can regionally
condition this NWP to reduce the
acreage limit or restrict or prohibit its
use in specific regions or waters. In
response to a pre-construction
notification, district engineers may
exercise discretionary authority to add
conditions to the NWP authorization or
require an individual permit. The 1⁄2-
PO 00000
Frm 00035
Fmt 4701
Sfmt 4703
10217
acre and 300 linear foot limits apply to
single and complete projects. If a project
proponent requests NWP authorization
to conduct additional discharges of
dredged or fill material into waters of
the United States and modify a
previously authorized single and
complete residential development
project, both the previously authorized
losses and the additional losses are
applied to the 1⁄2-acre and/or 300 linear
foot limits. If the modification to the
residential development is a separate
single and complete project with
independent utility from the previously
authorized residential development,
then a separate NWP authorization may
be issued. The ‘‘Definitions’’ section
includes further clarification regarding
single and complete projects.
Several commenters objected to
providing district engineers with the
authority to waive the 300 linear foot
limit for the loss of intermittent and
ephemeral stream bed on a case-by-case
basis after reviewing a pre-construction
notification and determining that the
proposed activity results in minimal
adverse environmental effects. One
commenter said that the waiver
provision would result in more than
minimal cumulative adverse effects on a
watershed basis. Another commenter
stated that use of the waiver would
authorize the losses of large amounts of
headwater streams. A few commenters
suggested the waiver provision should
be removed from this NWP. Three
commenters recommended increasing
the linear foot limit for the loss of
stream bed to 500 feet. Two commenters
supported the clarification that a finding
of minimal adverse environmental
effects would be required to issue a
waiver.
Responses to comments regarding the
300 linear foot limit for losses of stream
bed and the waiver provision for the
loss of greater than 300 linear feet of
intermittent and ephemeral stream beds
are discussed in a previous section of
this preamble. We are retaining the 300
linear foot limit for stream bed impacts,
as well as the ability for district
engineers to provide written waivers of
the 300 linear foot limit for losses of
intermittent and ephemeral stream beds.
One commenter recommended that
compensatory mitigation be required for
all unavoidable impacts to wetlands
authorized under this NWP. Several
commenters said that the NWP should
require permittees to minimize on-and
off-site impacts and avoid flooding,
because the general conditions do not
adequately address flooding or water
quality impacts. Several commenters
said that this NWP should not authorize
residential subdivisions unless the
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10218
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
project proponents can demonstrate
those subdivisions will not cause an
increased flood hazard on other
properties.
We do not agree that it is necessary
to require compensatory mitigation for
all activities authorized by this NWP to
satisfy the minimal adverse
environmental effects requirement for a
general permit. For many small losses of
waters of the United States authorized
by this NWP, it is not practicable to
require compensatory mitigation to
offset those losses, especially in areas
where there are no mitigation bank or
in-lieu fee program credits available.
The requirements for permitteeresponsible mitigation in 33 CFR 332.1
through 332.7 impose substantial
documentation and planning
requirements that affect the
practicability of providing ecologically
successful permittee-responsible
mitigation, especially for small losses of
waters of the United States.
Compensatory mitigation for NWP
activities is only necessary in cases
where the district engineer makes a
project-specific determination that
compensatory mitigation is needed to
ensure that the activity results in
minimal individual and cumulative
adverse effects on the aquatic
environment (see 33 CFR 330.1(e)(3)).
General condition 23, mitigation,
requires permittees to avoid and
minimize adverse effects to waters of
the United States on the project site, to
the maximum extent practicable.
Concerns about adverse effects on
floodplains and floodways are more
appropriately addressed by the state and
local agencies that have the primary
responsibility for floodplain
management. General condition 10, fills
within 100-year floodplains, requires
permittees to comply with applicable
Federal Emergency Management
Agency-approved state or local
floodplain management requirements.
Most floodplains are uplands, not
waters of the United States, and the
Clean Water Act Section 404 permit
program cannot be used to manage
floodplain impacts, except for
discharges of dredged or fill material or
other pollutants into wetlands and other
jurisdictional waters that are located in
floodplains. Residential developments,
whether they are single units or
multiple-unit subdivisions, must
comply with all terms and conditions of
this NWP, including the requirement
that they result in minimal adverse
environmental effects.
One commenter said that this NWP
should not authorize activities that
result in adverse impacts to state or
federally listed threatened or
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
endangered species or their habitats, or
where there are rare or imperiled habitat
types. One stated that this NWP should
not authorize discharges of dredged or
fill material below the ordinary high
water mark of any water of the United
States or areas of fish habitat. One
commenter said that attendant features
should be limited to a garage, a
driveway no more than 16 feet wide,
parking or vehicle turn areas, lawns that
are no more than 15 feet from the
building pad, septic fields, utilities,
deck foundations, and access paths. One
commenter suggested modifying this
NWP to require culverts and other
measures to maintain pre-construction
drainage patterns on the site. One
commenter said this NWP should
require on-site sewage treatment
systems.
Compliance with the federal
Endangered Species Act is addressed by
general condition 18. Compliance with
state or local threatened or endangered
species laws or ordinances, or state or
local requirements to avoid rare or
imperiled habitats, is the responsibility
of the permittee. Since all activities
authorized by this NWP require preconstruction notification, district
engineers will review proposed
activities that involve discharging
dredged or fill material into open
waters, including fish habitat, to ensure
that those activities result in minimal
adverse effects on the aquatic
environment. The text of the NWP
provides examples of the types of
attendant features that may be
authorized. Further restrictions on those
attendant features may be provided
through regional conditions imposed by
Division engineers or activity-specific
conditions added to an NWP 29
authorization by a District engineer.
General condition 9, management of
water flows, requires permittees to
maintain, to the maximum extent
practicable, the pre-construction course,
condition, capacity, and location of
open waters, such as streams, except
under certain situations identified in the
text of the general condition. Sewage
treatment system requirements for
residential developments are the
primary responsibility of state or local
governments.
One commenter requested
clarification on whether this NWP can
be used to authorize phased
development projects. Several
commenters suggested limiting this
NWP to a single use.
General condition 15, single and
complete project, states that the same
NWP can only be used once for the
same single and complete project. If a
particular phase of a phased
PO 00000
Frm 00036
Fmt 4701
Sfmt 4703
development project is a single and
complete project with independent
utility, a separate NWP 29 authorization
can be used to authorize that single and
complete non-linear project.
Two commenters said that the NWP
should require vegetated buffers. One
commenter stated that district engineers
have too much discretion regarding
buffers and the general condition
restricts buffers so that they are not as
effective as they could be.
Compensatory mitigation for activities
authorized by NWP 29 may be provided
through the establishment and
maintenance of riparian areas next to
open waters. Paragraph (f) of general
condition 23 addresses the use of
riparian areas as compensatory
mitigation, with recommended widths.
The recommended widths are based in
part on the minimum width necessary
for riparian areas to help protect or
improve water quality, and in part on
the principle that the amount of
compensatory mitigation must be
roughly proportional to the permitted
impacts (see 33 CFR 320.4(r)(2)). Since
the NWP has an acreage limit of 1⁄2-acre,
any required compensatory mitigation
must be roughly proportional to the
authorized loss of waters of the United
States.
This NWP is reissued as proposed.
NWP 30. Moist Soil Management for
Wildlife. No changes were proposed for
this NWP and no comments were
received. This NWP is reissued without
change.
NWP 31. Maintenance of Existing
Flood Control Facilities. We proposed to
modify this NWP to authorize, in cases
where a section 404 and/or section 10
permit would be required, the removal
of vegetation from levees associated
with a flood control project.
Several commenters supported the
proposed modification and said that
vegetation removal is a critical
component of the maintenance of a
flood control project to ensure
continued effectiveness and integrity of
levees and other flood control facilities.
Two commenters objected to the
proposed modification. One commenter
opposed the removal of vegetation from
flood control facilities, stating the
vegetation has ecological importance.
One commenter said that vegetation
removal is not regulated by the Corps.
One commenter stated that if the plant
species proposed to be removed have
cultural and medicinal Native American
traditional uses, consultation with the
Tribe or another type of permit should
be required for the activity.
We have retained the proposed
language in this NWP, to authorize the
removal of vegetation from a levee,
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
when that activity involves a discharge
of dredged or fill material into waters of
the United States or is considered to be
work in navigable waters of the United
States for the purposes of Section 10 of
the Rivers and Harbors Act of 1899. We
agree that vegetation removal that does
not involve such a discharge does not
require a DA permit. Division engineers
can regionally condition this NWP to
identify plant species that have cultural
and medicinal uses by Tribes, and to
require government-to-government
consultation to address impacts to such
species. General condition 17, Tribal
rights, protects reserved treaty rights,
including reserved water rights and
treaty fishing and hunting rights.
Natural or cultural tribal trust resource
concerns can still be addressed through
the NWP decisionmaking process, and
would not necessarily result in
requiring an individual permit.
Several commenters said that
vegetation may strengthen the integrity
of levees and stated that individual
permits should be required for
vegetation removal. One commenter
stated that vegetation on levees should
be allowed or retained as part of levee
management and that the vegetation
should be removed only if specific levee
maintenance or safety concerns are
identified. One commenter stated that
not allowing flood control districts to
remove vegetation from levees would
put them into non-compliance with
their permits and with other state and
local approvals. One commenter said
that the removal of vegetation from a
levee should only be authorized after
Endangered Species Act consultation
has been completed.
The decision on whether vegetation
needs to be removed from a levee to
maintain its functional and structural
integrity is more appropriately made by
those entities that are responsible for
ensuring the integrity and functional
effectiveness of that levee. That decision
is not the responsibility of the Corps
Regulatory Program or its staff. The
NWP is only a means to provide
Department of the Army authorization
for such activities, if a section 404 and/
or section 10 permit is required. If the
vegetation removal may affect a listed
species under the Endangered Species
Act, and a Department of the Army
permit is required, the Corps will
conduct section 7 consultation in
accordance with general condition 18,
endangered species, unless another
Federal agency has already fulfilled the
section 7 requirements, or the project
proponent has complied with the
Endangered Species Act and received an
Endangered Species Act Section 10
permit.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
Several commenters said that there
should be an acreage limit for vegetation
removal. Another commenter
recommended imposing a linear foot
limit on vegetation removal. One
commenter recommended revoking this
NWP in California.
Since this NWP authorizes
maintenance activities, we do not
believe there should be an acreage or
linear foot limit on vegetation removal.
Division engineers may also add
regional conditions to this NWP to
impose acreage or linear foot limits on
vegetation removal.
One commenter stated that many
NWP authorizations are related to the
maintenance baseline and the NWP
should provide more details about the
maintenance baseline approval process.
This commenter suggested that the NWP
specify: the deadline for completion, the
responsible party, the regulating entity
that approves the maintenance baseline,
etc. One commenter requested
clarification on the timeframe for
approval of the maintenance baseline.
The current terms and conditions of
the NWP provide sufficient details on
what is needed to establish the
maintenance baseline. Approval of the
maintenance baseline is to be made
within the 45-day review period, which
begins once a complete pre-construction
notification is received by the
appropriate Corps district office. The
pre-construction notification must
include a description of the
maintenance baseline.
Many commenters expressed concern
about the mitigation provision of this
NWP, especially the one-time limit for
mitigation per facility regardless of the
number of times maintenance occurs.
These commenters said that limiting
compensatory mitigation may result in
more than minimal adverse
environmental effects, including
adverse impacts to floodplains and
increased flood risk. These commenters
recommended requiring mitigation for
each maintenance activity. One
commenter stated that vegetation
removal should not be authorized
because effective compensatory
mitigation cannot be provided. One
commenter said that certain riparian
functions, such as shading, and losses of
aesthetic values, cannot be provided
through off-site mitigation.
We do not agree that compensatory
mitigation should be required for each
maintenance activity. On-going
maintenance of flood control facilities is
necessary to ensure that those projects
fulfill their intended purposes. Any
compensatory mitigation that was
required when the maintenance baseline
was established is sufficient to offset
PO 00000
Frm 00037
Fmt 4701
Sfmt 4703
10219
losses of aquatic resource functions. If
maintenance is done in a timely
manner, there is likely to be little in
terms of increases in aquatic resource
functions between maintenance
activities. The purpose of maintaining
these flood control facilities is to reduce
flood risk. Riparian functions that
increased between maintenance
activities do not need to be replaced by
imposing compensatory mitigation
requirements on this NWP.
Several commenters said that the use
of this NWP results in more than
minimal individual and cumulative
impacts, and may also inhibit
comprehensive basin-wide flood risk
management planning and restoration
approaches.
We do not agree that these
maintenance activities cause more than
minimal adverse effects on the aquatic
environment, on an individual or
cumulative basis. This NWP is intended
as a tool to support appropriate flood
management activities, including
comprehensive flood risk management
planning and restoration processes,
where maintenance of existing flood
control structures is required.
One commenter recommended
modifying the pre-construction
notification provision to require a
topographic map identifying the
disposal site. One commenter said that
the 1996 Water Resources Development
Act allows for regional variations in
vegetation management on levees.
The NWP already requires the
prospective permittee to submit
information concerning the location of
the dredged material disposal site.
There are a variety of maps that could
be used to provide that information, and
we do not believe it should be restricted
to topographic maps. We have modified
this NWP to state that all dredged
material must be placed in an area that
has no waters of the United States or in
a separately authorized disposal site,
since the disposal of dredged material
into non-jurisdictional waters and
wetlands, as well as uplands, does not
require DA authorization. As stated
above, the decision on whether to
remove vegetation is the responsibility
of the entity charged with managing and
maintaining the flood control facility.
This NWP is reissued with the
modifications discussed above.
NWP 32. Completed Enforcement
Actions. There were no changes
proposed for this NWP. One commenter
recommended adding a condition to the
NWP requiring that the state be a party
to any lawsuit, or have an opportunity
to review the consent or settlement
agreement. Another commenter
requested coordination with any
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10220
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
affected Tribes prior to administering an
enforcement action to ensure that Tribal
treaty resources are protected.
This NWP only provides Federal
authorization under Section 10 of the
Rivers and Harbors Act of 1899 and
Section 404 of the Clean Water Act, and
it is not appropriate to modify this NWP
to require state involvement in these
actions. States are often involved as coregulators in enforcement activities,
under various authorities, and this NWP
in no way undercuts those authorities.
General condition 17, tribal rights, states
that no activity or its operation may
impair reserved tribal rights.
This NWP is reissued as proposed.
NWP 33. Temporary Construction,
Access, and Dewatering. We did not
propose any changes to this NWP.
Several commenters recommended that
the Corps define the term ‘‘temporary.’’
One commenter said that ‘‘temporary’’
should be less than two years, another
stated that one year should be the limit,
and a third commenter suggested 90
days as the limit for what constitutes a
temporary structure or fill. Several
commenters stated that the NWP should
require a specific timeframe and
deadline for completion of revegetation
activities. Other commenters said that
any revegetation should use only native
plant species associated with the
general habitat type that had existed
prior to construction.
The term ‘‘temporary’’ should be
determined by district engineers on a
case-by-case basis, after considering
factors such as the type of project, the
waters affected by the activity, the
construction techniques and equipment
used, etc. In response to a preconstruction notification, district
engineers can add conditions to the
NWP authorization to impose specific
time frames for revegetating affected
areas. Activity-specific conditions may
also be added to the NWP authorization
to specify the plant species to be used
at the site.
One commenter asked why the NWP
would state that a separate section 10
permit is required if a structure is left
in place in navigable waters of the
United States after completion of
construction, especially if the
waterbody is not a section 10 water.
This commenter wondered how a
‘‘structure’’ constructed in a nonSection 10 water could be left in place
and still qualify as a temporary
structure.
In some cases, it may be more
environmentally beneficial to leave part
of a structure in place in navigable
waters of the United States, when
complete removal of the structure is
expected to result in substantial adverse
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
environmental effects. For example, a
structure may be cut near the ocean
bottom, but part of the structure and its
foundation left in place, because
removing the entire structure and its
foundation would result in substantial
disturbance of the ocean bottom.
Leaving those portions of the original
structure and foundation in place
requires a permit under Section 10 of
the Rivers and Harbors Act of 1899
because it constitutes an obstruction
that may alter the course, condition, or
capacity of navigable waters of the
United States. A structure left in place
in a waterbody subject only to section
404 jurisdiction does not require section
10 authorization. Such a structure
would not require a section 404 permit
unless it meets the definition of fill
material (see 33 CFR 323.3(c)).
One commenter asked why NWP 33
activities require pre-construction
notification for temporary structures,
work, and discharges while these types
of activities may be authorized under
NWPs 3, 12, 13, and 14 without a preconstruction notification.
While temporary structures, work,
and fills are authorized by NWPs 3, 12,
13, and 14, those NWPs have terms and
conditions to help ensure that those
activities result in minimal adverse
effects on the aquatic environment.
Since NWP 33 can be used to authorize
temporary structures, work, and
discharges done in association with a
wide variety of other categories of
activities, that uncertainty makes it
necessary to require pre-construction
notification for all activities authorized
by NWP 33. Such a requirement allows
the Corps to review the temporary and
permanent impacts that are likely to
occur as a result of the overall activity.
One commenter stated that the NWP
should never authorize temporary fills
that impact more than 1,000 square feet
or discharge more than 25 cubic yards
into waters of the U.S., and temporary
structures or construction mats shall not
impact more than 1⁄10-acre. One
commenter stated that the NWP should
require that geotextile fabric be installed
prior to placement of fill material, and
two commenters suggested that
temporary culverts and bridges in
streams should be required to match the
bankfull width and stream slope.
Another commenter stated that all
slurry resulting from dewatering
operation should be discharged through
a filter bag or pumped to a sump located
away from wetlands and surface waters
and allowed to filter through natural
upland vegetation, gravel filters, or
other engineered devices for a sufficient
distance and/or period of time necessary
to remove sediment or suspended
PO 00000
Frm 00038
Fmt 4701
Sfmt 4703
particles. One commenter stated that
cofferdams should be required to be
maintained in good working order
throughout the duration of the project.
We do not agree that there should be
acreage, linear foot, or cubic yard limits
on this NWP since it authorizes
temporary structures, work, or
discharges, and all activities require preconstruction notification. In response to
a pre-construction notification, district
engineers can add activity-specific
conditions to the NWP authorization to
impose limits or require specific best
management practices or specific
construction techniques to minimize
adverse effects to the aquatic
environment where necessary.
We have modified this NWP to state
that temporary fill must be entirely
removed to an area that has no waters
of the United States, since the
placement of fill material into nonjurisdictional waters and wetlands, as
well as uplands, does not require DA
authorization.
The NWP is reissued with the
modification discussed above.
NWP 34. Cranberry Production
Activities. We did not propose any
changes to the NWP. One commenter
said that this NWP should not authorize
losses of wetland functions. Two
commenters expressed concern that the
10-acre limit would allow significant
losses of wetland acreage and functions
and values, if the 10-acre limit is
applied only to the five year period the
NWP is in effect. These commenters
proposed making the 10-acre limit apply
to future activities. One commenter
suggested limiting the NWP
authorization to a single cranberry
production unit. One commenter said
that this NWP should not be reissued.
This NWP does not authorize
discharges of dredged or fill material
that would result in a net loss of waters
of the United States. While there would
be some loss of wetland function as
wetlands are converted for cranberry
production, the NWP requires wetland
acreage to be maintained. There would
be no loss of wetland acreage over time
due to future activities since the NWP
does not authorize discharges of
dredged or fill material that would
result in permanent losses of wetland
acres. This NWP applies to single and
complete cranberry production
activities, which would be identified by
district engineers during the review of
pre-construction notifications.
This NWP is reissued without change.
NWP 35. Maintenance Dredging of
Existing Basins. There were no changes
proposed for this NWP. Two
commenters recommended adding
limits to this NWP. Two commenters
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
said this NWP should not be used in
areas with suspected sediment
contamination, especially in areas
where there might be contamination
from fuel. Another commenter stated
the applicant should demonstrate that
the sediment is not contaminated. One
commenter asked that the term
‘‘upland’’ be clarified to state that it
means land located above the ordinary
high water mark. One commenter stated
that this NWP would have greater utility
if it authorized beneficial use of dredged
material, such as wetland restoration,
enhancement, or establishment
activities.
Since this NWP authorizes only
maintenance dredging activities in
existing marina basins, we do not
believe it is necessary to add an acreage
limit or other type of quantitative limit.
Division engineers can regionally
condition this NWP to require
notification to the district engineer. This
NWP is limited to maintenance
dredging in marina basins, access
channels to marinas, and boat slips,
which are likely to have some degree of
contaminated sediment in the substrate
because of past and present boat use,
especially in larger marinas. Removal of
such contaminated sediments, and
complying with the requirement in the
NWP to deposit the dredged material in
an upland site, will help ensure the
activity results in minimal adverse
effects on the aquatic environment.
Defining the term ‘‘upland’’ to mean
lands located above an ordinary high
water mark would be incorrect. There
may be wetlands landward of the
ordinary high water mark. We have
modified this NWP to state that dredged
material must be placed in an area that
has no waters of the United States, since
the disposal of dredged material into
non-jurisdictional waters and wetlands,
as well as uplands, does not require DA
authorization. The district engineer may
issue a separate Department of the Army
authorization to a project proponent
who wants to use the dredged material
to restore, enhance, or establish
wetlands.
One commenter stated that
precautions should be taken to ensure
that dredging equipment does not
entrain or kill any Federally-listed
species and recommend that preemptive
trawling around the dredge head be
conducted to capture or relocate state or
federally listed species.
General condition 18 addresses
compliance with the Endangered
Species Act, and section 7 consultation
is required for any activity that may
affect listed species or is located in
designated critical habitat.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
This NWP is reissued with the
modification discussed above.
NWP 36. Boat Ramps. We did not
propose any changes to this NWP. One
commenter said that boat ramps should
not be authorized by NWPs because
they cause significant environmental
impacts, including impacts to Tribal
treaty fishing activities and access. One
commenter stated that this NWP should
be limited to individual riparian lot
owners and not authorize commercial
boat ramps. One commenter said that
the NWP should require notification to
the state agency responsible for
managing state-owned submerged lands.
The terms and conditions of this NWP
(specifically the limits on fill volume
and ramp width) will ensure that the
NWP authorizes only those activities
that result in minimal adverse effects on
the aquatic environment. Division
engineers may regionally condition this
NWP to restrict or prohibit its use in
specific waters or geographic areas if
they have concerns that more than
minimal individual and cumulative
adverse environmental effects may
occur. In response to a pre-construction
notification, district engineer may add
activity-specific conditions to the NWP
authorization to satisfy the minimal
adverse environmental effects
requirement. We do not agree that this
NWP should be limited to private land
owners. Commercial boat ramps that
comply with the terms and conditions
of this NWP will also result in minimal
adverse environmental effects. The
potential for adverse effects is based on
the footprint of the ramp, which is
limited by the conditions of this NWP,
not its ownership. State agencies
responsible for managing submerged
lands may develop their own
procedures for regulating and
authorizing the construction of boat
ramps on submerged lands. The Corps
has neither the authority nor the
resources to enforce any state
requirements with respect to such lands.
Two commenters recommended
reducing the pre-construction
notification thresholds for this NWP.
One commenter suggested limiting
discharges of dredged or fill material to
25 cubic yards, with a maximum boat
ramp width of 12 feet. Another
commenter said that the quantitative
limits for this NWP should not be
waived. One commenter stated that the
current 50 cubic yard limit is too small
and should be increased to authorize
larger boat ramps.
The pre-construction notification
thresholds are sufficient for ensuring
that this NWP authorizes activities with
minimal individual and cumulative
adverse effects on the aquatic
PO 00000
Frm 00039
Fmt 4701
Sfmt 4703
10221
environment. We have retained the
provision authorizing district engineers
to issue written waivers to the 50 cubic
yard and/or 20 foot width limits, if a
proposed activity is determined to result
in minimal adverse environmental
effects. The waiver provision may be
used to authorize larger boat ramps, as
long as they are determined by the
district engineer to result in minimal
adverse environmental effects.
One commenter asked for clarification
on what is meant by placement in the
upland. One commenter said that these
activities may affect historic properties
and the activity should not be
authorized unless the state concurs that
there are no documented resources
within the permit area.
We have modified paragraph (d) to
clarify that all excavated material must
be removed to an area that has no waters
of the United States, because some
wetlands and waters are not subject to
Clean Water Act jurisdiction and section
404 permits are not required to
discharge dredged or fill material into
those non-jurisdictional wetlands and
waters. A separate Department of the
Army authorization is required if the
project proponent wants to deposit the
excavated material into waters of the
United States. Activities authorized by
this NWP must comply with general
condition 20, historic properties, as well
as general condition 21, discovery of
previously unknown remains and
artifacts. District engineers will conduct
National Historic Preservation Act
Section 106 consultation if they
determine the proposed activity has the
potential to cause effects to any historic
property.
This NWP is reissued as proposed.
NWP 37. Emergency Watershed
Protection and Rehabilitation. No
changes were proposed for this NWP.
Two commenters stated that in their
region, flood control activities including
those authorized by this NWP, are
important and suggested reducing the
45-day waiting period for preconstruction notifications to 21 days.
Two commenters expressed support for
allowing district engineers to waive the
pre-construction notification
requirements in cases where there is an
unacceptable hazard to life or a
significant loss of property or economic
hardship will occur. One commenter
said that although this NWP is intended
to authorize watershed protection and
rehabilitation, these activities may
result in a net loss of waters and
appropriate mitigation should be
required.
We do not believe it would be
appropriate to reduce the preconstruction notification review period
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10222
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
for this NWP from 45 days to 21 days.
The NWP provides flexibility for the
emergency watershed protection and
rehabilitation activities to proceed
immediately if there is an unacceptable
hazard to life or a significant loss of
property or economic hardship will
occur. The NWP does not allow the
district engineer to waive the preconstruction notification requirement in
cases where there would be
unacceptable hazards to life or
significant losses of property or
economic hardships. If a project
proponent wants to use NWP 37 to
authorize an emergency watershed
protection and rehabilitation activity,
pre-construction notification is
required. This is a minimally
burdensome requirement that can be
complied with quickly which allows the
district engineer to verify that there is a
genuine emergency. In addition, in
response to a pre-construction
notification, the district engineer may
condition the NWP authorization to
require compensatory mitigation to
offset losses of aquatic resources and
ensure that the adverse effects on the
aquatic environment are minimal (see
33 CFR 330.1(e)(3) and general
condition 23, mitigation).
The NWP is reissued without change.
NWP 38. Cleanup of Hazardous and
Toxic Waste. We did not propose any
changes for this NWP. One commenter
stated the NWP should be revoked
because hazardous waste cleanup from
aquatic areas has the potential to cause
significant adverse environment effects
during and after the cleanup activities.
This commenter said that these
activities require site-specific review
and should not be authorized by NWP.
Another commenter recommended
adding a condition to the NWP to
require minimization, to the maximum
extent possible, of impacts to waters and
wetlands, and require restoration of the
affected areas.
The cleanup of hazardous and toxic
wastes, if conducted properly, will
improve the aquatic environment by
removing harmful chemicals and other
substances that are likely to degrade the
quality of wetlands, streams, and other
aquatic resources, as well as the
functions they provide. This NWP
requires pre-construction notification,
which will provide the district engineer
the opportunity to review the proposed
activity, including available site-specific
information, to determine if that activity
qualifies for NWP authorization. This
NWP authorizes cleanup activities
conducted, ordered, or sponsored by
other government agencies, which have
also reviewed those activities. In some
cases these activities need to be
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
commenced quickly and it could cause
additional harm to the aquatic
environment if they had to wait for an
individual permit to be issued. The
district engineer may also add activityspecific conditions to the NWP
authorization to require compensatory
mitigation, including restoration or
rehabilitation of affected aquatic
resources (see 33 CFR 330.1(e)(3) and
general condition 23, mitigation) to
satisfy the minimal adverse
environmental effects requirement for
general permits.
This NWP is reissued without change.
NWP 39. Commercial and
Institutional Developments. We
proposed to modify this NWP by
changing the waiver provision for
activities resulting in the loss of greater
than 300 linear feet of intermittent and
ephemeral stream bed, to clarify that the
district engineer will only issue the
waiver after making a project-specific
written determination that the activity
will result in minimal adverse effects.
Two commenters expressed support
for the proposed modification. One
commenter said that intermittent
streams should be removed from the
waiver provision so that the 300 linear
foot limit could be waived only for
losses of ephemeral streams. One
commenter recommended removing the
waiver provision.
We have retained the provision
allowing the 300 linear foot limit to be
waived for losses of intermittent stream
bed, since such activities may, in some
cases, result in minimal adverse effects
on the aquatic environment. General
comments concerning the 300 linear
foot limit to the loss of stream bed are
discussed in a separate section of the
preamble.
One commenter urged the elimination
of the pre-construction notification
because that requirement results in
delays and increases in cost. One
commenter recommended conducting a
natural heritage database search if a
waiver determination is made that the
activity will result in minimal adverse
effects.
The pre-construction notification
requirement is necessary so that all of
these activities are reviewed by district
engineers to ensure that those activities
result in minimal adverse effects on the
aquatic environment. District engineers
may add conditions to the NWP
authorization to require compensatory
mitigation or other measures to comply
with the minimal adverse
environmental effects requirement
established for general permits. District
engineers may consider information
from state natural heritage databases
where appropriate when evaluating a
PO 00000
Frm 00040
Fmt 4701
Sfmt 4703
pre-construction notification involving a
proposed waiver of the 300 linear foot
limit.
Two commenters suggested increasing
the acreage limit from 1⁄2 to one acre.
Another said that acreage limits should
be established on a regional or
watershed basis, instead of a single
national acreage limit. Two commenters
suggested increasing the linear foot limit
to 500 feet. One commenter stated that
the NWP should not authorize activities
that are not water dependent.
We believe that both the 1⁄2-acre limit
and the 300 linear foot limit are
necessary to ensure that this NWP
authorizes activities that result only in
minimal individual and cumulative
adverse effects on the aquatic
environment. Division engineers can
regionally condition this NWP to further
ensure only minimal adverse effects to
the aquatic environment occur in a
particular area or region, based on
region specific conditions. District
engineers can also add specific
conditions to an NWP authorization to
ensure minimal individual or
cumulative adverse effects. The
statutory basis for authorizing activities
by general permits is that they have
minimal adverse effects, individually
and cumulatively, not that they be water
dependent.
One commenter said that commercial
and institutional developments are
typically phased developments, are
larger in scale than other projects, and
should not be authorized by NWP. One
commenter said that this NWP should
not be reissued because these activities
result in more than minimal cumulative
adverse effects to wetlands and streams.
One commenter suggested requiring
compensatory mitigation for all
activities authorized by this NWP. Two
commenters said that this NWP should
include a requirement to establish
buffers next to waters of the United
States, clarification that the limits apply
to the project site and not to multiple
applicants, and a provision requiring
flood protections. One commenter
stated industrial facilities that may be
authorized by this NWP cause indirect
impacts to water quality that could be
significant and suggested not reissuing
this NWP.
Phased developments may be
authorized by general permits, as long
as they comply with all applicable terms
and conditions of those general permits.
In particular, an NWP may only be used
once for each single and complete
project. The limits in this NWP, which
are consistent with those in many other
NWPs, will generally ensure minimal
adverse effects. In specific watersheds
or other geographic areas where a
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
district engineer is concerned that the
use of NWP 39 may result in more than
minimal cumulative adverse effects to
the aquatic environment, the division
engineer may regionally condition this
NWP to restrict or prohibit its use to
ensure that the threshold for minimal
individual and cumulative adverse
effects on the aquatic environment is
not exceeded. We do not agree that
compensatory mitigation should be
required for all activities authorized by
this NWP. District engineers will add
activity-specific conditions to the NWP
authorization to require compensatory
mitigation in accordance with general
condition 23, mitigation (also see 33
CFR 330.1(e)(3)), where necessary to
ensure minimal effects. The
establishment and maintenance of
riparian areas next to open waters, or
buffers next to wetlands, may be
required as compensatory mitigation, in
accordance with general condition 23,
mitigation, and the regulations at 33
CFR part 332. The acreage limits of this
NWP apply to single and complete
projects, even though a single and
complete project may have more than
one project proponent. In general, a
commercial development project in
which a developer prepares a large site
and then markets individual lots to
individual builders would be
considered one single and complete
project and the acreage limits would
apply to the development as a whole.
See the definition of ‘‘single and
complete non-linear project’’ for further
information. General condition 10, fills
in 100-year floodplains, requires
permittees to comply with applicable
state or local floodplain management
requirements that have been approved
by the Federal Emergency Management
Agency. District engineers will review
pre-construction notifications
requesting NWP 39 authorization for
industrial facilities to ensure that
adverse effects to water quality caused
by the NWP activity are minimal,
individually and cumulatively.
One commenter objected to
authorizing the expansion of
commercial and institutional
developments into waters of the United
States, stating that it discourages
avoidance and minimization and is
contrary to the 404(b)(1) Guidelines.
One commenter requested clarification
whether this NWP applies to new
project construction or existing
construction projects so the acreage
limits are applied cumulatively for both
the original construction and any
subsequent expansion of the
development. One commenter asked
whether certain categories of activities
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
that were not authorized by the 2007
version of NWP 39, specifically new golf
courses, new ski areas, or oil or gas
wells, could be expanded through the
authorization provided by this NWP.
Three commenters suggested
eliminating the exclusion for the
construction of oil and gas wells and
attendant features.
The expansion of commercial and
institutional developments into waters
of the United States may qualify for
NWP authorization, as long as it
complies with all applicable terms and
conditions of the NWP and results in
minimal individual and cumulative
adverse effects on the aquatic
environment. This NWP complies with
the 404(b)(1) Guidelines, especially 40
CFR 230.7, which addresses the
issuance of general permits. The acreage
limit applies to a single and complete
project. The expansion of an existing
commercial or institutional
development may only be authorized
under a separate NWP authorization if
it is a separate single and complete
project with independent utility. For
example, one or more phased
components of a commercial or
institutional development may have
independent utility and may be
authorized as separate single and
complete projects. The expansion of
existing golf courses or ski areas may be
authorized by this NWP. We agree that
the construction of pads for oil and gas
wells is a type of commercial
development that would be appropriate
for inclusion in this NWP. District
engineers may add conditions to NWP
39 authorizations to require the removal
of these pads and restoration of the site
once oil or gas extraction operations
have ceased and the wells will no longer
be used.
One commenter said that this NWP
could be used to authorize activities
associated with wind energy generating
structures, solar towers, or overhead
utility lines, which have the potential to
interfere with Department of Defense’s
long range surveillance, homeland
defense, testing, and training missions.
This commenter requested that copies of
NWP 39 pre-construction notifications
and NWP verification letters for these
activities be provided to the Department
of Defense Siting Clearinghouse, so that
the Department of Defense could have
an opportunity to coordinate with the
project proponent to ensure that long
range surveillance, homeland defense,
testing, and training missions are not
adversely affected by these activities.
We have added a Note at the end of
this NWP to require district engineers to
send pre-construction notifications and
NWP verification letters to the
PO 00000
Frm 00041
Fmt 4701
Sfmt 4703
10223
Department of Defense Siting
Clearinghouse if NWP 39 is proposed to
be used, and is used, to authorize the
construction of wind energy generating
structures, solar towers, or overhead
transmission lines. The Department of
Defense Siting Clearinghouse is
responsible for coordinating with the
project proponent and resolving any
potential effects on Department of
Defense long range surveillance,
homeland defense, testing, and training
missions.
This permit is reissued with the
modification discussed above.
NWP 40. Agricultural Activities. We
proposed to modify this NWP so the 300
linear foot limit applies to all stream
losses, not just drainage ditches
constructed in streams. To waive the
300 linear foot limit for losses of
intermittent or ephemeral stream bed,
the district engineer would have to
make a project-specific written
determination that the activity will
result in minimal adverse effects.
Two commenters support the changes
and said the modification would ensure
NWP 40 authorizes activities with
minimal adverse effects on the aquatic
environment. One commenter opposed
expanding the 300 linear foot limit to all
stream losses, stating that the NWP
should not authorize the loss of natural
streams. Another commenter
recommended removing intermittent
streams from the waiver provision to
limit it to ephemeral streams. One
commenter said that waivers for the loss
of greater than 300 linear feet of
intermittent and ephemeral streams
should not be issued until a natural
heritage database search was completed.
Two commenters stated that the acreage
limit and the ability to waive the 300
linear foot limit do not adequately
address cumulative impacts and
requested the waiver provision be
removed.
Comments concerning the 300 linear
foot limits for the loss of stream bed and
the waiver process are discussed in a
previous section of the preamble. We
are adopting the proposed language for
the waiver provision. We are retaining
the provision allowing the 300 linear
foot limit to be waived for losses of
ephemeral and intermittent stream bed,
since such activities may result in
minimal adverse effects on the aquatic
environment. District engineers may
consider information from state natural
heritage databases when evaluating a
pre-construction notification involving a
proposed waiver of the 300 linear foot
limit. We believe that both the 1⁄2-acre
limit and 300 linear foot limit for stream
bed losses, along with the division
engineer’s authority to add regional
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10224
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
conditions to this NWP and the district
engineer’s authority to add activityspecific conditions to an NWP
authorization, will ensure that the NWP
authorizes activities with minimal
individual and cumulative adverse
effects on the aquatic environment.
Division engineers may also suspend or
revoke this NWP in watersheds or other
geographic areas if they find that use of
the NWP would result in more than
minimal cumulative adverse
environmental effects.
One commenter stated the 1⁄2-acre
limit should be based on farm tract and
asserted NWP 40 allows for the
incremental fill of agricultural wetlands.
One commenter stated that roadside
stands should not be considered farm
buildings for authorization under this
permit. Another commenter
recommended farm building pads be
limited to areas that have been in
existing, ongoing, agricultural
production since at least 1980. One
commenter remarked concern that this
NWP allows fills in waters for nonwater dependent uses. Another
commenter asserted this NWP should
not authorize farm ponds in wetlands.
The 1⁄2-acre limit applies to a single
and complete project. The district
engineer will determine, after
considering the specific circumstances
for a pre-construction notification,
whether the single and complete project
should be based on a farm tract,
property boundary, or other appropriate
geographic area. Road stands may be
considered farm buildings for the
purposes of this NWP. We do not agree
that building pads for farm buildings
should be limited to existing
agricultural areas, or that they should be
treated differently than building pads
authorized by NWPs 29 or 39. General
permits, including NWPs, may
authorize activities that are not waterdependent, as long as the general permit
is issued in accordance with the
requirements in the 404(b)(1) Guidelines
at 40 CFR 230.7.
This NWP is reissued as proposed.
NWP 41. Reshaping Existing Drainage
Ditches. There were no changes
proposed for this NWP. Several
commenters requested adding more
terms and conditions to this NWP to
provide requirements concerning slope
stability, conducting a natural heritage
database search, limiting the NWP to
reshaping no more than one mile of
drainage ditch, and placing the
excavated material in uplands. One
commenter suggested replacing the
phrase ‘‘for the purpose of improving
water quality’’ with ‘‘for the purpose of
improving water quality or public
safety.’’ This commenter also said the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
NWP should authorize drainage
improvements beyond the original asbuilt capacity. One commenter stated
that this NWP should not be exempt
from compensatory mitigation
requirements even though the activity is
designed to improve water quality.
We do not agree that the suggested
additional terms and conditions are
necessary to ensure that this NWP
authorizes ditch reshaping activities
that have minimal adverse effects on the
aquatic environment. The drainage
ditch slope is more appropriately
determined on a case-by-case basis.
District engineers have the discretion to
consult state natural heritage databases
while reviewing pre-construction
notifications. The authorized activities
are intended to improve water quality,
so there is no need to impose a one mile
limit or require compensatory
mitigation. Reshaping a drainage ditch
to improve water quality may involve
discharging dredged or fill material into
jurisdictional waters within the ditch.
This NWP was originally issued to
encourage activities that would help
improve water quality within a
watershed, not to provide for public
safety. Discharging dredged or fill
material into waters of the United States
to reshape existing drainage ditches
primarily for the purposes of public
safety may be authorized by other
NWPs, regional general permits, or
individual permits.
This NWP is reissued as proposed.
NWP 42. Recreational Facilities. We
proposed to modify this NWP by
changing the waiver provision for
activities resulting in the loss of greater
than 300 linear feet of intermittent and
ephemeral stream bed, to clarify that the
district engineer will only issue the
waiver after making a project-specific
written determination that the activity
will result in minimal adverse effects.
Two commenters said that the 1⁄2-acre
limit of this NWP does not ensure
minimal adverse effects, and one of
these commenters stated that the 300
linear foot limit for stream bed losses
does not ensure minimal adverse effects
either. Several commenters supported
the proposed waiver provision, since it
emphasizes that the appropriate test is
that the activity results in minimal
adverse effects. One commenter
suggested removing intermittent streams
from the waiver provision because of
the potential for significant impacts to
intermittent streams.
The 1⁄2-acre limit is the appropriate
limit to ensure that the activities
authorized by this NWP result in
minimal adverse effects on the aquatic
environment. This limit has been in
place over several permit terms and
PO 00000
Frm 00042
Fmt 4701
Sfmt 4703
multiple NWPs and we are not aware of
evidence that it has allowed projects
that do not meet the minimal effects
requirement to be authorized, nor have
commenters provided such evidence.
Division engineers may regionally
condition this NWP to reduce the
acreage limit or revoke the NWP if its
use would result in more than minimal
individual and cumulative adverse
effects on the aquatic environment. The
300 linear foot limit for losses of stream
bed is also necessary to ensure minimal
adverse environmental effects. The
waiver provision is discussed in a
separate section of the preamble. We are
retaining the 300 linear foot limit for
stream bed impacts, as well as the
ability for district engineers to provide
written waivers of the 300 linear foot
limit for losses of intermittent and
ephemeral stream beds.
One commenter suggested adding a
condition to this NWP to limit fill
pathways on public lands to six feet
wide, with a maximum length of 200
feet, and require open pile or floating
boardwalks/docks by prohibiting the
discharges below the ordinary high
water mark of inland lakes, streams, or
the Great Lakes, or areas that otherwise
provide fish habitat functions of any
kind.
We do not believe the recommended
restrictions are necessary to ensure that
the NWP authorizes only those activities
that result in minimal adverse effects on
the aquatic environment. Division
engineers may add regional conditions
to this NWP to limit certain activities or
require specific construction
techniques. Division engineers may also
restrict or prohibit the use of this NWP
in certain waters to protect important
resources, such as fish habitat.
One commenter supports requiring
pre-construction notification for all
activities authorized by this NWP. One
commenter said that the activities
authorized by this NWP are not similar
in nature. One commenter suggested
adding a condition requiring
recreational facilities to be integrated
into the natural landscape and not
substantially change pre-construction
grades or deviate from natural landscape
contours. One commenter requested
clarification as to when an easement
will not be required.
We have retained the requirement that
all project proponents who want to use
this NWP must submit a preconstruction notification. This NWP
authorizes a specific category of
activities (i.e., recreational facilities)
and complies with the ‘‘similar in
nature’’ requirement of Section 404(e) of
the Clean Water Act. We do not agree
that it is necessary to require
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
recreational facilities to be integrated
into the natural landscape and not
substantially change pre-construction
grades. The 1⁄2-acre and 300 linear foot
limits, as well as the requirement to
avoid and minimize adverse effects to
waters of the United States to the
maximum extent practicable on the
project site (see general condition 23,
mitigation), help ensure that the NWP
authorizes activities that result in
minimal adverse effects. Conservation
easements or other appropriate longterm protection instruments will only be
required, if necessary, for areas that are
used to provide compensatory
mitigation for activities authorized by
this NWP.
This permit is reissued as proposed.
NWP 43. Stormwater Management
Facilities. We proposed to modify this
NWP by adding low impact
development stormwater management
features to the examples of types of
stormwater management facilities that
may be authorized by this NWP. We
also proposed to modify this NWP by
changing the waiver provision for
activities resulting in the loss of greater
than 300 linear feet of intermittent and
ephemeral stream bed, to clarify that the
district engineer will only issue the
waiver after making a project-specific
written determination that the activity
will result in minimal adverse effects.
One commenter expressed support for
the proposed modifications. One
commenter suggested that the acreage
limit should be increased from 1⁄2-acre
to one acre to increase the utility and
usefulness of this NWP. Several
commenters said this NWP should not
authorize new stormwater management
facilities. One commenter stated that the
NWP should only authorize the
construction of an outfall structure. A
couple of commenters said that this
NWP should be changed to clarify that
only constructed wetlands may be used
to detain, retain, or treat stormwater.
We do not agree that the acreage limit
for this NWP should be increased from
1⁄2-acre to one acre. The 1⁄2-acre limit is
necessary to ensure that this NWP
authorizes only those activities that
result in minimal individual and
cumulative adverse effects on the
aquatic environment. The construction
of new stormwater management
facilities may be authorized by this
NWP (if all other conditions are met),
because those activities often result in
minimal adverse environmental effects
and help protect the aquatic
environment by preventing or reducing
the amount of pollutants that enter
streams, coastal waters, and other
aquatic habitats. Stormwater
management facilities are an important
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
tool for fulfilling the objective of the
Clean Water Act, by protecting and
restoring the physical, chemical, and
biological integrity of our Nation’s
waters. The construction of stormwater
management facilities may involve
discharges of dredged or fill material
into jurisdictional wetlands, so it would
not be appropriate to limit this NWP to
constructed wetlands for the detention,
retention, or treatment of stormwater.
We have substantially modified the
first paragraph of this NWP to clarify
how construction and maintenance
activities may be authorized by this
NWP, including the application of the
waste treatment system exclusion at 33
CFR 328.3(a)(8). Section 328.3(a)(8)
states that ‘‘[w]aste treatment systems,
including treatment ponds or lagoons
designed to meet the requirements of’’
the Clean Water Act are not waters of
the United States. The first half of this
paragraph provides examples of the
types of stormwater management
facilities that may be authorized by this
NWP, if the construction of those
facilities involves discharges of dredged
or fill material into waters of the United
States. The second half of this paragraph
states that to the extent that a section
404 permit is required, this NWP also
authorizes discharges of dredged or fill
material into waters of the United States
for the maintenance of stormwater
management facilities. Therefore, this
NWP authorizes maintenance activities
involving discharges of dredged or fill
material if the stormwater management
facility is not eligible for the waste
treatment system exclusion. A section
404 permit is not required for a
discharge of dredged or fill material into
a waste treatment system that qualifies
for the waste treatment system
exclusion at 33 CFR 328.3(a)(8).
Several commenters supported the
addition of low impact development
stormwater management features to the
examples of activities authorized by this
NWP. One commenter said that while
the construction of low impact
development stormwater management
features may need a Department of the
Army permit in some circumstances, the
maintenance of low impact
development stormwater management
features does not require a section 404
permit. This commenter also stated that
requiring Department of the Army
permits for maintenance activities in
watersheds that have total maximum
daily load requirements would result in
needless paperwork without any
environmental benefits. One commenter
requested an explanation of the value of
low impact development stormwater
management facilities and examples of
those facilities that may be authorized
PO 00000
Frm 00043
Fmt 4701
Sfmt 4703
10225
by this NWP. One commenter expressed
concern that areas not subject to Clean
Water Act jurisdiction, such as swales
and upland areas holding waters only
for short periods of time, may be
considered to be waters of the United
States if they are used for low impact
development stormwater management
features. Several commenters requested
a definition for ‘‘low impact
development stormwater features’’ in
the definitions section. One commenter
asked whether hybrid or combined bank
protection and stormwater management
techniques are authorized by this NWP
or authorized by other NWPs.
We have modified the text of this
NWP to clarify that the construction of
low impact development integrated
management features is authorized by
this NWP, if the construction involves
discharges of dredged or fill material
into waters of the United States. We
have also provided examples of the
types of low impact development
integrated management features that
may be authorized by this NWP, such as
bioretention facilities (e.g., rain
gardens), vegetated filter strips, grassed
swales, and infiltration trenches. After
these low impact development
integrated management features are
constructed, they may not be waters of
the United States and subsequent
maintenance may not require further
Department of the Army authorization.
The jurisdictional status of these
features will be determined by district
engineers on a case-by-case basis, after
applying the appropriate regulations
and guidance. The Corps of Engineers
wetland delineation manual and the
applicable regional supplement will be
used to determine whether a particular
feature is a wetland under the definition
at 33 CFR 328.3(b). Many low impact
development integrated management
features may not have wetland
hydrology because they are designed to
improve water infiltration. By
modifying this NWP to make it clear
that it can be used to authorize
discharges of dredged or fill material to
construct low impact development
integrated management features, we are
providing general permit authorization
for activities that will help state and
local entities comply with the total daily
maximum loads established for a
watershed or watershed. We do not
believe it is necessary to define the term
‘‘low impact development stormwater
management features’’ in the Definitions
section of the NWPs because the text of
the NWP provides examples of those
features. This NWP may authorize some
minor bank stabilization associated with
the construction of a stormwater
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10226
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
management facility. Bank protection
may be authorized by this NWP or
another appropriate NWP.
One commenter asked whether this
NWP authorizes discharges of dredged
or fill material for the construction of
new stormwater facilities in intermittent
or ephemeral streams that are waters of
the United States. One commenter
recommended prohibiting the
construction of new stormwater
management facilities in intermittent
streams to avoid impacts to numerous
rare and threatened and endangered
species. Another commenter said this
NWP should only authorize activities in
ephemeral streams.
We do not believe it is necessary to
limit the construction of new
stormwater management facilities to
ephemeral streams. District engineers
will review pre-construction
notifications and determine whether the
proposed activities will have minimal
adverse effects on intermittent and
ephemeral streams. Activities
authorized by this NWP must also
comply with general condition 18,
Endangered Species. State-listed rare
species may be further protected
through the establishment of regional
conditions by division engineers, after a
public notice and comment process.
Several commenters objected to
allowing the district engineer to waive
the 300 foot limit for the loss of
intermittent or ephemeral stream bed.
Another commenter suggested
increasing the linear limit for the loss of
stream beds to 500 feet before requiring
a waiver, to authorize more activities.
Several commenters stated the waiver
provision should be removed and losses
of waters of the United States should be
limited to 1⁄2-acre or 300 linear feet of
stream bed. Another commenter stated
that no waivers should be allowed
under any circumstances. One
commenter suggested that waivers for
losses of intermittent and ephemeral
stream beds not be issued until the
appropriate natural heritage resources
database is consulted to inform the
minimal adverse impact determination.
We are retaining the provision
allowing district engineers to waive the
300 linear foot limit for the loss of
intermittent and ephemeral streams,
upon making a written determination
that the discharge will result in minimal
adverse effects. The 300 linear foot limit
should not be increased to 500 linear
feet, to ensure that any loss of perennial
stream bed results in no more than
minimal individual and cumulative
adverse effects on the aquatic
environment. District engineers may use
available information, including state or
local natural heritage resources
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
databases, to help make the minimal
adverse effects determination.
Some commenters suggested
combining the maintenance component
of this NWP with NWP 3 since both
include maintenance activities. Another
commenter suggested limiting this NWP
to authorizing only the maintenance of
stormwater management facilities
constructed and used for the primary
purpose of providing stormwater
detention, retention and treatment.
As discussed above, we have
modified this NWP to clarify that Clean
Water Act Section 404 permits would
not be required for maintenance
activities (or other discharges of dredged
or fill materials) involving stormwater
management facilities that qualify for
the waste treatment system exclusion at
33 CFR 328.3(a)(8) because these are
excluded from the definition of waters
of the United States. We do not believe
it is necessary to combine maintenance
authorized by NWP 43 with the
maintenance activities authorized by
NWP 3, since NWP 3 authorizes a
variety of maintenance activities. Some
stormwater management facilities may
have purposes or uses other than
stormwater detention, retention or
treatment, so maintenance should still
be authorized by this NWP, if a section
404 permit is required and the activity
results in minimal adverse effects on the
aquatic environment.
One commenter suggested that if a
development project is required to
install stormwater management
facilities, the entire development should
be treated as the ‘‘area of potential
effects’’ for the purposes of compliance
with Section 106 of the National
Historic Preservation Act. One
commenter recommended requiring any
contaminated materials to be properly
handled and disposed of.
The permit area for section 106
compliance will be determined by
applying the criteria in Appendix C of
33 CFR part 325, the Corps Regulatory
Program’s procedures for the protection
of historic properties, as well as the
interim guidance issued on April 25,
2005, and January 31, 2007. In general,
as is made clear in these regulations and
guidance, the Corps does not agree that
the area of potential effects for an NWP
that is needed for a discharge involving
one aspect of a development project
necessarily encompasses the entire
project, though this may be true in
individual cases depending on the facts
and circumstances. Compliance with
general condition 20, Historic
Properties, is required for activities
authorized by this NWP. In response to
a pre-construction notification, the
district engineer may add activity-
PO 00000
Frm 00044
Fmt 4701
Sfmt 4703
specific conditions to the NWP
authorization to protect waters of the
United States from adverse effects due
to contaminated materials.
This NWP is reissued with the
modifications discussed above.
NWP 44. Mining Activities. We
proposed to add the 300 linear foot limit
for the loss of stream bed, which for
intermittent and ephemeral stream beds
can be waived by the district engineer
if he or she makes a written
determination concluding that the
activity will result in minimal adverse
effects.
One commenter requested the NWP
be revoked due to the large scale of
these activities and their impacts on
water quality. One commenter said this
NWP should only authorize mining
activities that have been permitted by
state agencies. This commenter also
stated that this NWP should not
authorize peat mining or in-stream
gravel mining. One commenter
recommended expanding the categories
of applicable waters to include tidal
waters, since the term ‘‘adjacent’’ has
not been adequately defined.
The terms and conditions of this
NWP, including the addition of the 300
linear foot limit for the loss of stream
bed, help ensure that the NWP
authorizes only those activities that
have minimal individual and
cumulative adverse effects on the
aquatic environment. Division engineers
can regionally condition this NWP to
restrict or prohibit its use in specific
waters or categories of waters, or in
particular geographic regions. After
reviewing a pre-construction
notification, the district engineer may
add activity-specific conditions to the
NWP authorization to require water
quality management measures so that
the activity causes only minimal
degradation of water quality (see general
condition 25, water quality), or he or
she may exercise discretionary authority
and require an individual permit if it is
not possible to reduce the adverse
effects so that they are no more than
minimal. Division engineers may also
regionally condition this NWP to
prohibit or restrict peat mining or instream gravel mining. We do not agree
that the NWP should be expanded to
authorize discharges of dredged or fill
material into tidal waters, since such
activities may result in more than
minimal adverse effects on the aquatic
environment. The term ‘‘adjacent’’ is
defined in the Corps regulations at 33
CFR 328.3(c) and is used to identify
wetlands that are waters of the United
States by virtue of being adjacent to
jurisdictional waters.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Many commenters opposed adding
the 300 linear foot limit for the loss of
stream bed and stated that the 300 linear
foot limit should not apply to smaller
tributaries. One commenter
recommended increasing the linear foot
limit to 500 feet. One commenter said
the proposed linear foot limit would
have the effect of preventing mining of
more than one million tons of mineable
reserves. One commenter stated that
waivers to the 300 linear foot limit
should not be issued without evaluating
documented natural heritage resources
located in the project area.
As stated above, the 300 linear foot
limit is being added to help ensure that
the NWP authorizes only those activities
that result in minimal adverse effects on
the aquatic environment and other
applicable public interest review
factors. Increasing the linear foot limit
for the loss of stream bed to 500 feet
increases the likelihood that these
mining activities would result in more
than minimal adverse effects and
therefore not comply with the
requirements of Section 404(e) of the
Clean Water Act. Mining activities that
do not qualify for NWP authorization
may be authorized by individual
permits or other general permits, such
as regional general permits issued by
district engineers. District engineers will
evaluate appropriate information before
waiving the 300 linear foot for losses of
intermittent or ephemeral stream bed,
which may include state natural
heritage resource databases. In areas
where district engineers have
designated state natural heritage sites as
critical resources, compliance with
general condition 22, designated critical
resource waters will protect those
natural heritage sites.
This NWP is reissued as proposed.
NWP 45. Repair of Uplands Damaged
by Discrete Events. We proposed to
modify this NWP to clarify that it does
not authorize beach restoration. We also
proposed to change the Note, to make it
clear that the NWP authorizes
discharges of dredged or fill material
into waters of the United States
associated with the restoration of
uplands.
One commenter requested that a 1⁄2acre limit be placed on activities
authorized under this NWP. One
commenter said that authorizing
activities under this NWP within
channel migration zones can have more
than minimal adverse environmental
effects and impair stream functions if
those activities attempt to force a stream
back into previously occupied channels.
This commenter said the NWP should
be conditioned to prohibit fills that
would attempt to move the stream
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
channel to a previous course within the
stream channel migration zone. One
commenter suggested modifying this
NWP to limit it to reconfiguring the
affected area, and not authorize
increases to the size of structures or
fills. Another commenter supported
allowing dredging or excavation in all
waters of the United States under this
NWP in conjunction with the repair of
uplands.
We do not believe that it is necessary
to impose a 1⁄2-acre limit to this NWP,
because it limits the repair of uplands
to the contours, or ordinary high water
mark, that existed before the damage
occurred. This NWP also limits
dredging to the minimum necessary to
restore the damaged uplands, and does
not authorize significant alterations to
pre-event bottom contours of the
waterbody. The minor fills authorized
by this NWP are unlikely to
substantially alter stream migration.
Because this NWP is limited to restoring
uplands to pre-event configurations, it
does not authorize more than minimal
changes in the size of structures or fills
that may be constructed on or near
uplands.
One commenter said that fills should
be limited to the post-event ordinary
high water mark. Another commenter
made a similar recommendation, but
suggested that an exception should be
provided in cases where there is a need
to respond to immediate threats to a
primary structure or to infrastructure.
We do not agree that fills should be
limited to the post-event ordinary high
water mark. The purpose of this NWP is
to authorize discharges of dredged or fill
material into waters of the United States
for the repair of uplands that have been
damaged by discrete events and have
minimal adverse effects on the aquatic
environment. In some cases, it may not
be practicable to limit fills to where the
new ordinary high water mark is
located, in cases where the discrete
event changes the location of the
ordinary high water mark.
One commenter said that Tribes
should be notified to avoid impacts to
Tribal treaty natural resources and
cultural resources. Two commenters
supported the proposed changes to the
Note. One commenter stated that all
bank stabilization authorized by this
NWP must also satisfy the terms and
conditions of NWP 13.
Division engineers can regionally
condition this NWP to identify areas
where there are Tribal treaty natural and
cultural resources, so that consultation
can be conducted with those Tribes to
ensure that impacts to those resources
are appropriately considered during
review of pre-construction notifications.
PO 00000
Frm 00045
Fmt 4701
Sfmt 4703
10227
General condition 17, Tribal rights,
prohibits the impairment of reserved
tribal rights such as reserved water
rights and treaty fishing and hunting
rights. We have retained the proposed
changes to the Note at the end of this
NWP. This NWP provides separate
authorization for discharges of dredged
or fill material that are necessary to
repair uplands that have been damaged
by discrete events, including the
placement of fills necessary to stabilize
the bank. Unlike NWP 13, this NWP
limits bank stabilization so that it does
not exceed the land contours that
existed before the damage occurred.
Nationwide permit 13 may be used in
conjunction with this NWP to authorize
bank stabilization for restored uplands
in cases where it is not practicable to
limit bank stabilization to the pre-event
ordinary high water mark or contours.
The NWP is reissued as proposed.
NWP 46. Discharges in Ditches. We
did not propose any changes to this
NWP. Most commenters asked why this
permit was needed since upland ditches
are not subject to Clean Water Act
jurisdiction, and any discharges of
dredged or fill material into these
ditches are exempt by statute under
Section 404(f) of the Clean Water Act.
Some commenters noted that the Corps
does not assert Clean Water Act
jurisdiction over many upland ditches
and should not attempt to regulate these
ditches by reissuing this NWP.
This NWP authorizes discharges of
dredged or fill material into a specific
category of ditches (i.e., those non-tidal
ditches that meet all four criteria in the
first paragraph of the NWP), if those
ditches have been determined to be
waters of the United States. Section
404(f) of the Clean Water Act only
exempts discharges of dredged or fill
material for the construction or
maintenance of irrigation ditches, or the
maintenance of drainage ditches, while
this NWP authorizes a different set of
activities which would require a Section
404 permit. For example, this NWP
authorizes discharges of dredged or fill
material that may completely fill the
specific category of upland ditch
described in the NWP, if that ditch is
determined to be a water of the United
States after either the Corps or EPA
makes a jurisdictional determination.
We recognize that many ditches
constructed in uplands are not waters of
the United States, but there are some
ditches constructed in uplands that may
be determined to be waters of the
United States after evaluating the
specific characteristics of those ditches.
The preamble to the Corps November
13, 1986, final rule states the non-tidal
drainage and irrigation ditches
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10228
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
excavated on dry land are generally not
considered to be waters of the United
States, but the Corps and EPA reserve
the right on a case-by-case basis to
determine whether a particular
waterbody is a water of the United
States (see 51 FR 41217). Joint guidance
issued in December 2008 by EPA and
the Corps provides additional
clarification as to when ditches are and
are not considered to be waters of the
United States (see https://water.epa.gov/
lawsregs/guidance/wetlands/upload/
2008_12_3_
wetlands_CWA_Jurisdiction_
Following_Rapanos120208.pdf; p. 12).
Some commenters said there are
impacts to upland ditches that could
impair water quality downstream and
that compensatory mitigation should be
required to minimize adverse effects
caused by activities authorized by this
NWP. One commenter recommended
that district engineers evaluate impacts
to natural heritage resources during
their review of pre-construction
notifications.
For those activities authorized by this
NWP, the district engineer will review
the pre-construction notification and
determine whether the activity results
in only minimal adverse effects,
including whether compensatory
mitigation is necessary to ensure that
the authorized activity results in
minimal adverse effects on the aquatic
environment, including water quality.
During the review of a pre-construction
notification, the district engineer may
consult natural heritage resource
databases to more effectively evaluate
the potential adverse effects on the
aquatic environment.
This NWP is reissued as proposed.
NWP 47. Pipeline Safety Program
Designated Time Sensitive Inspections
and Repairs. We proposed to not
reauthorize this NWP because it was
issued in 2007 in reliance on the
development of the Pipeline Repair and
Environmental Guidance System
(PREGS) by the Pipeline and Hazardous
Materials Safety Administration. Since
PREGS was not developed and
deployed, and paragraph (h) of the NWP
required permittees to use PREGS to
submit post-construction reports, no
activity could be authorized by NWP 47.
Two commenters asked why this
NWP was not proposed to be reissued.
Three commenters agreed with allowing
the NWP to expire and supported the
Corps position that designated time
sensitive inspections and repairs can be
authorized under NWP 3, Maintenance
and NWP 12, Utility Line Activities.
One commenter said that there should
be an NWP to authorize emergency
repair activities to fix natural gas
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
pipeline leaks, pressure malfunctions,
natural disaster damage, terrorist
threats, or other events that pose a
danger to public safety. One commenter
suggested issuing a new NWP to
authorize activities licensed by the
Federal Energy Regulatory
Commission’s blanket certificate
program.
Existing NWPs, such as NWPs 3 and
12, may be used to authorize discharges
of dredged or fill material or structures
or work in navigable waters of the
United States associated with pipeline
inspections and repairs. Some of these
activities do not require preconstruction notification to qualify for
NWP authorization. There are other
approaches available, such as
emergency permitting procedures, to
allow emergency repair activities that
do not qualify for general permit
authorization to proceed if there is ‘‘an
unacceptable hazard to life, a significant
loss of property, or an immediate,
unforeseen, and significant economic
hardship’’ (see 33 CFR 325.2(e)(4)). We
do not believe it is necessary to develop
a new NWP to authorize activities that
are granted blanket certificates by the
Federal Energy Regulatory Commission.
Many of these activities may be
authorized by existing NWPs, such as
NWPs 3 and 12.
This NWP is not reissued.
NWP 48. Commercial Shellfish
Aquaculture Activities. We proposed to
modify this NWP by removing the
reporting requirement, which applied to
all activities that did not require preconstruction notification. We also
proposed to add the information
previously required in that report to the
PCN information requirements. This
information includes: A map showing
the boundaries of the project area, with
latitude and longitude coordinates for
each corner of the project area; the
name(s) of the cultivated species; and
whether canopy predator nets are being
used. In addition, we proposed to
remove the pre-construction notification
requirement for changes in species
cultivated, as long as those species had
been previously cultivated in the
waterbody. We proposed to modify this
NWP to authorize activities associated
with the expansion of existing
commercial shellfish aquaculture
operations. We requested comments on
modifying this NWP or issuing a new
NWP to authorize new commercial
shellfish aquaculture activities.
Many commenters said the NWP
should be reissued, and recommended
many changes. Several commenters
stated that this NWP should not be
reissued. Most commenters expressed
support for removing the reporting
PO 00000
Frm 00046
Fmt 4701
Sfmt 4703
requirements for all activities that did
not require pre-construction
notification, stating that the paperwork
was unnecessary given the current
regulation of the industry by other
entities, such as state and local
governments. One commenter said that
the reporting requirements should be
maintained to ensure protection of
resources. Other commenters suggested
that pre-construction notification
should be required for all activities.
Several commenters said that the NWP
should only authorize maintenance
activities. One commenter stated that
shellfish aquaculture methods are
sufficiently different for the species
cultivated that issuing a single NWP to
authorize these activities is
inappropriate. Another commenter said
that all commercial shellfish
aquaculture activities should be
authorized under one NWP. Two
commenters stated that the NWP should
only authorize harvesting that occurs by
hand. One commenter stated that these
activities may impact tribal fishery
access and fishing rights, and
coordination with the affected tribes
should be required.
We have reissued this NWP and made
several changes. Properly sited,
operated, and maintained commercial
shellfish aquaculture activities support
populations of shellfish that provide
important ecological functions and
services for coastal waters, and should
be authorized by a single NWP. We have
removed the reporting requirements for
this NWP and substantially reduced the
number of pre-construction notification
thresholds. Division engineers may
regionally condition this NWP to
establish additional pre-construction
notification thresholds if necessary to
ensure that this NWP authorizes only
those activities that have minimal
adverse effects on the aquatic
environment. We do not agree that preconstruction notification should be
required for all activities authorized by
this NWP, because these activities are
regulated by a number of other
government agencies, especially at the
federal and state government levels. In
addition, the discharges of dredged or
fill material into waters of the United
States authorized by this NWP will
result in minimal adverse
environmental effects to the
environmental criteria established
under the Clean Water Act. The
shellfish populations supported by the
activities authorized by this NWP help
support the objective of the Clean Water
Act because they improve water quality
through the conversion of nutrients into
biomass (i.e., shellfish growth) and the
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
removal of suspended materials through
filter feeding. Commercially grown
shellfish also provide some habitat
functions for the aquatic environment.
Impacts to submerged aquatic vegetation
will, in many cases, be evaluated
through the pre-construction
notification review process. For
commercial shellfish aquaculture
activities in new project areas, adverse
effects to submerged aquatic vegetation
will be minimal because of the 1⁄2-acre
limit. Impacts to coastal aquatic habitat
and species of concern in those habitats
are more appropriately addressed
through consultation conducted under
the Essential Fish Habitat provisions of
the Magnuson-Stevens Fishery
Conservation and Management Act and/
or Section 7 of the Endangered Species
Act.
We do not agree that the NWP should
be limited to hand harvesting activities.
We have retained the pre-construction
notification requirement for activities
involving dredge harvesting, tilling, or
harrowing in areas inhabited by
submerged aquatic vegetation. General
condition 17, tribal rights, states that
NWP activities may not impair reserved
tribal rights, including treaty fishing and
hunting rights. In addition, division
engineers may regionally condition this
NWP to identify areas where Tribes
must be notified of these activities and
government-to-government consultation
conducted to avoid or minimize impacts
to tribal fishery access and fishing
rights.
One commenter said that the
restoration of indigenous species would
be prevented if cultivation was limited
to only those species that were
previously commercially cultivated.
Another commenter recommended
requiring pre-construction notification if
there were a proposed change in species
cultivated that was not part of a stateapproved list. Some commenters
suggested that pre-construction
notification should not be required for
changes in harvesting methods. Another
commenter said that pre-construction
notification should be required if the
culture method changed from bottom
culture to floating or suspended culture
to allow district engineers to evaluate
potential navigation issues. One
commenter indicated that the NWP
should authorize demonstration projects
less than one acre in size and another
said that non-commercial shellfish
aquaculture activities should be
authorized, since states, local
governments, and non-governmental
organizations engage in recreational and
commercial aquaculture. One
commenter recommended adding a
provision that would require the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
permittee to implement measures to
prevent the spread of aquatic nuisance
species, such as prohibiting the transfer
of materials used for commercial
shellfish aquaculture activities from one
project site to another unless
appropriate measures have been taken
to ensure that those materials are free of
aquatic nuisance species. This
commenter said a note should be added
to the NWP, to prohibit the transfer of
equipment used in commercial shellfish
aquaculture activities from one
waterbody to another waterbody, unless
that equipment has been allowed to dry
out for a minimum of 90 days or treated
in accordance with a regional aquatic
nuisance control plan, to prevent the
introduction of aquatic nuisance species
into the other waterbody.
We have modified this NWP to
provide more flexibility in the species
cultivated, specifically, to allow the
cultivation of nonindigenous species as
long as those species have been
previously cultivated in the waterbody.
We recognize that there has been
commercial production of
nonindigenous species over many years
in certain waterbodies, and activities
requiring Department of the Army
authorization associated with those
commercial operations should be
authorized by this NWP. We have
retained the prohibitions against
cultivating aquatic nuisance species
defined by the Nonindigenous Aquatic
Nuisance Prevention and Control Act of
1990. We have also added Note 2 to the
NWP, to reduce the risk of introducing
aquatic nuisance species by requiring
treatment of materials taken from one
waterbody to another in accordance
with the applicable regional aquatic
nuisance species management plan.
Division engineers may add regional
conditions to the NWP to make
permittees aware of the regional aquatic
nuisance species management plan that
may be applicable to NWP 48 activities.
We agree that pre-construction
notification should not be required for
changes in harvesting methods because
harvesting methods have temporary
impacts and result in minimal adverse
effects. A possible exception is dredge
harvesting in areas inhabited by
submerged aquatic vegetation, which
still requires pre-construction
notification. We also agree that preconstruction notification should be
required if the grower proposes to
change from bottom culture to floating
or suspended culture in a project area,
or if it is an activity in a new project
area that requires the installation and
use of floating or suspended gear, so
that effects to navigation can be
evaluated. This NWP authorizes
PO 00000
Frm 00047
Fmt 4701
Sfmt 4703
10229
commercial shellfish aquaculture
activities undertaken by states, local
governments, and non-governmental
organizations. Shellfish seeding
activities to improve shellfish
populations may be authorized by NWP
27. Small recreational shellfish
aquaculture activities may be authorized
by other applicable NWPs, such as NWP
4. Other recreational shellfish
aquaculture activities may be authorized
by regional general permits or
individual permits. Restoration
aquaculture activities may be authorized
by NWP 27.
One commenter stated that the
structures and fill activities authorized
by the NWP were too broad and should
be refined. This commenter
recommended prohibiting the long-term
use of trays if sediment is compacted
and diversity is diminished. One
commenter said that structures and fill
should be limited to shell spat only,
while another commenter stated that
shell planting should be allowed on any
size parcel without pre-construction
notification.
The structures and fills authorized by
this NWP are limited to those necessary
to conduct commercial shellfish
aquaculture activities. We have retained
the provision that states that the NWP
does not authorize attendant features
such as docks, piers, boat ramps,
stockpiles or staging areas, or the
deposition of shell material back into
waters of the United States as waste. We
have removed the pre-construction
notification threshold for commercial
shellfish aquaculture activities that are
more than 100 acres in size, because we
do not believe it is necessary to require
pre-construction notification for existing
operations with a valid lease, permit, or
other appropriate instrument that has
been approved by the appropriate state
or local government agency, unless the
activity triggers any of the preconstruction notification thresholds.
One commenter requested changes to
the definition of shell seeding, citing
concerns over the use of potentially
environmentally damaging materials.
Another commenter supported the use
of terms such as ‘‘suitable substrate’’
and ‘‘appropriate materials’’ due to the
decreasing availability of shell cultch
and new research and development
regarding materials. One commenter
said that use of the term ‘‘submerged
aquatic vegetation’’ allowed for the
destruction of eelgrass, because eelgrass
is often not inundated with tidal waters.
One commenter asked whether
traditional oyster culture practices were
of special concern.
The definition of the term ‘‘shellfish
seeding’’ in the Definitions section of
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10230
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
the NWP provides examples of
appropriate materials that may be used
for shellfish seeding activities. Through
the issuance of regional conditions,
division engineers can restrict or
prohibit the use of certain materials for
shellfish seeding. In response to a preconstruction notification, district
engineers may add activity-specific
conditions to an NWP authorization to
prohibit the use of certain materials for
shellfish seeding. Eelgrass is commonly
considered to be a species of submerged
aquatic vegetation and we intend it to be
covered by the provisions regarding
submerged aquatic vegetation,
regardless of whether it is fully
submerged in all tidal conditions or not.
Many commenters requested
clarification as to when pre-construction
notification is required and what
constitutes a project area for the
purposes of this NWP. Several
commenters recommended that preconstruction notifications should only
be required once and not for each
subsequent reissuance of this NWP if
the commercial shellfish aquaculture
operation has not changed. One
commenter asked if the lease holder is
required to provide pre-construction
notifications annually if the lease covers
an area greater than 100 acres. One
commenter inquired whether preconstruction notification is required
when the operator is only working on 30
acres of a 200-acre project site. One
commenter said that multiple preconstruction notifications should not be
required from a lease holder that has
multiple 100-acre leases; instead, one
pre-construction notification should
cover all those leases.
We have reduced the number of preconstruction notification thresholds in
this NWP. The pre-construction
notification thresholds in this NWP
focus on those activities that should be
reviewed by district engineers to:
(1) Ensure that floating or suspended
aquaculture facilities do not cause more
than minimal adverse effects on
navigation or, (2) ensure that both
cultivating species that have not been
previously cultivated in the waterbody
and dredge harvesting, tilling, or
harrowing in areas of submerged aquatic
vegetation do not cause more than
minimal adverse effects on the aquatic
environment.
To support our objective to be more
consistent with state and local agencies
that regulate commercial shellfish
aquaculture activities, we have
redefined project area so that it is based
on leases or permits issued by an
appropriate state or local government
agency that is responsible for allocating
subtidal or intertidal lands for
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
commercial shellfish production. The
project area may also be based on rights
to conduct shellfish aquaculture that are
established by treaty, such as treaties
executed between the United States
Government and Indian Tribes. Project
area may also be identified through an
easement, lease, deed, or contract which
establishes an enforceable property
interest to conduct aquaculture
activities on subtidal or intertidal lands.
We have removed the preconstruction notification requirement
for relocating existing operations into
portions of the project area not
previously used for aquaculture
activities, since the permit or lease
issued by the state or local government
agency has already authorized that area
for use in commercial shellfish
aquaculture. There is no need to address
expansions in this NWP if the proposed
expansions are within the project area
authorized by the state or local
government lease or other appropriate
instrument. For example, preconstruction notification is not required
if an operator who is only working on
30 acres of a 200-acre project area
decides to conduct operations beyond
those 30 acres within the 200 acre
project area.
We have removed the preconstruction notification threshold for
project areas greater than 100 acres.
Since we have limited the preconstruction notification thresholds to
focus on activities that may adversely
affect submerged aquatic vegetation and
changes in operations that may
adversely affect navigation or involve
species not previously cultivated in the
waterbody, most on-going activities will
not require pre-construction
notification, thereby substantially
decreasing the paperwork burden on
current commercial shellfish
aquaculture operators. The lease holder
is not required to provide a preconstruction notification annually no
matter what the size of the project area
as long as the lease holder has a valid
lease, permit, or other appropriate
instrument that has been approved by
the appropriate state or local
government agency for the project area,
and none of the pre-construction
notification thresholds are triggered. For
example, pre-construction notification
is not required if the lease holder is only
working within an existing authorized
200-acre project area no matter how
much or little of that area is cultivated.
However, if the lease holder proposes to
cultivate a species of oyster in the 200acre project area not currently present in
the waterbody, pre-construction
notification would be required. The
activities also do not require pre-
PO 00000
Frm 00048
Fmt 4701
Sfmt 4703
construction notification unless the
activities involve dredge harvesting,
tilling, or harrowing in areas of
submerged aquatic vegetation. If the
lease holder’s operations within the
200-acre project area change from one
on-bottom technique to another onbottom technique, pre-construction
notification is not required. However, if
the operations are proposed to change
from an on-bottom culture method to a
floating or suspended culture method,
pre-construction notification is
required. Lastly, if an operator obtains a
lease for a new project area and wishes
to conduct any commercial shellfish
aquaculture activities in the new project
area, pre-construction notification is
required.
One commenter said that requiring
pre-construction notification for
aquaculture relocation and expansion is
unnecessary if the area is already leased
but transferred to another owner.
Another commenter recommended that
any NWP authorizations should still be
valid when the lease is transferred to
another operator and use has not
changed. One commenter stated that
pre-construction notification should not
be required for expansions into newly
leased areas since the site conditions are
usually the same.
Pre-construction notification is not
required for expansions of commercial
shellfish activities as long as the
expansion occurs within the project area
specified by an permit, lease, or other
instrument issued by the appropriate
state or local agency, and as long as
none of the pre-construction notification
thresholds are triggered. This would
apply to an activity in a new location
within the project area, or to an activity
that would utilize a larger acreage of the
project area, as long as none of those
activities require pre-construction
notification. If an activity is proposed by
an operator in a new project area,
however, pre-construction notification
is required. An NWP verification can be
transferred to a new project proponent,
if he or she has obtained an interest in
the subtidal or intertidal lands,
provided appropriate procedures are
followed for the transfer of the NWP
verification (see general condition 29,
transfer of nationwide permit
verifications).
One commenter asked whether or not
an NWP verification can be issued prior
to a state issuing a lease. Another
commenter said that NWP 48 should be
delegated to the states who issue leases
to reduce duplicative paperwork. One
commenter stated that pre-construction
notification should not be required
when a state already evaluates impacts
to submerged aquatic vegetation prior to
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
granting leases. Another commenter
said that certain states do not issue
leases in areas with submerged aquatic
vegetation, so it is not necessary for the
Corps to address that issue.
The district engineer may issue an
NWP verification before the state makes
its decision on a lease application. It is
necessary to respond to a complete preconstruction notification within 45 days
to retain the authority to add activityspecific conditions, which would
ensure that the NWP activity results in
minimal adverse effects on the aquatic
environment. Since there is not
consistent regulation of commercial
shellfish aquaculture activities among
all of the states, we do not agree that
certain Federal interests, such as
navigation and impacts to special
aquatic sites, should be delegated to the
states. In evaluating a pre-construction
notification triggered by potential
impacts to submerged aquatic
vegetation, the district engineer would
consider any evaluation of such impacts
that had been previously conducted by
the state if this is submitted with the
PCN.
Many commenters expressed
concerns regarding impacts to species
protected under the Endangered Species
Act, designated critical habitat, and
essential fish habitat. One commenter
asked if compliance with the
Endangered Species Act was required
for both existing and new activities.
Another recommended that a detailed
eelgrass, macroalgae, and forage fish
survey should be required for each preconstruction notification. One
commenter stated that NWP
authorization should not be granted in
areas adjacent to forage fish or critical
habitat.
Activities authorized by this NWP
must comply with general condition 18,
endangered species. Any new or
existing activity that involves discharges
of dredged or fill material or structures
or work in navigable waters of the
United States that might affect listed
species or designated critical habitat
require pre-construction notification to
the district engineer, so that Section 7
consultation can be conducted. We do
not agree that pre-construction
notifications should include surveys for
eelgrass, microalgae, or forage fishes.
The district engineer may request
additional information from the project
sponsor if needed to conduct Section 7
consultation. An activity may be
authorized in critical habitat if a section
7 biological opinion is issued and
impacts to critical habitat are
authorized.
One commenter recommended that
the Corps work closely with the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
National Oceanic and Atmospheric
Administration to streamline the review
and approval of aquaculture projects.
Some commenters said that the
commercial shellfish aquaculture
industry is not sufficiently regulated at
the local, state, or federal level. One
commenter said that enforceable
conditions need to be added to NWP 48
authorizations to protect the aquatic
environment. One commenter
recommended implementing a regional
ecosystem-based management approach.
We have worked closely with the
National Oceanic and Atmospheric
Administration and other Federal
agencies to develop this NWP, and we
disagree that there is not already
sufficient government oversight of these
activities at the various levels of
government. In response to a preconstruction notification, the district
engineer may add activity-specific
conditions to the NWP authorization to
ensure that the authorized activity
results in minimal adverse effects on the
aquatic environment, individually and
cumulatively. A regional ecosystembased management approach is more
appropriately undertaken by Corps
districts and interested Federal, State,
and local government agencies, not at
the national level.
Many commenters expressed concern
regarding the environmental impacts
associated with expansions of
commercial shellfish aquaculture
activities and for new activities. One
commenter said that expansion
proposals should not be reviewed as
restoration activities since non-native
species are a serious threat. Several
commenters stated that the
environmental benefits do not offset the
environmental impacts, introduction of
invasive species, impacts to native
species such as flatfish and other sandy
bottom species, reduction of species
diversity, elimination of native animal
and plant species, harassment and
destruction of migrating birds, and the
introduction of plastics. Other
commenters expressed concern
regarding impacts from geoduck
cultivation and harvesting on the
environment as well as on wild geoduck
populations, and the cultivation and
harvesting of other non-native species.
Two commenters stated that geoduck
cultivation and harvesting has only
minimal impacts.
When properly sited, operated, and
maintained, commercial shellfish
aquaculture activities generally result in
minimal adverse effects on the aquatic
environment and in many cases provide
environmental benefits by improving
water quality and wildlife habitat, and
providing nutrient cycling functions.
PO 00000
Frm 00049
Fmt 4701
Sfmt 4703
10231
These activities are subjected to an
extensive amount of regulation at the
Federal and state government levels,
and often the local government level.
The introduction of invasive species can
occur through many mechanisms, and
the types of species approved for
commercial aquaculture activities are
regulated. This NWP does not authorize
discharges of dredged or fill material or
structures or work in navigable waters
of the United States associated with the
cultivation of nonindigenous species
that have not been previously cultivated
in the waterbody or the cultivation of
aquatic nuisance species as defined in
the Nonindigenous Aquatic Nuisance
Prevention and Control Act of 1990.
Furthermore, division engineers may
add regional conditions to the NWP to
require permittees to use specific
practices that will prevent the spread of
aquatic nuisance species. Such
measures may vary, depending on the
species of concern and which
techniques would be the most effective
means to prevent the spread of such
species. Adverse effects that may result
from geoduck cultivation are more
appropriately addressed by Corps
districts, since this activity is limited in
geographic scope. Division engineers
may regionally condition this NWP to
restrict or prohibit its use to authorize
discharges of dredged or fill material
into waters of the United States or
structures or work in navigable waters
of the United States associated with
geoduck production.
Several commenters stated that the
expansion of commercial shellfish
aquaculture activities will result in
more than minimal cumulative adverse
effects and should not be authorized by
NWP. One commenter said that all
activities authorized by this NWP
should require reporting to assess
cumulative effects. Another commenter
suggested that cumulative effects on
water quality should be evaluated for
water bodies with multiple aquaculture
facilities.
As stated above, commercial shellfish
aquaculture activities provide habitat,
water quality, and nutrient cycling
functions and when properly sited,
operated, and maintained are unlikely
to result in more than minimal
cumulative adverse effects on the
aquatic environment. Division engineers
may restrict or prohibit use of this NWP
in geographic regions or specific
waterbodies where more than minimal
cumulative adverse effects may occur.
One commenter stated that shellfish
aquaculture activities have economic
impacts that were not sufficiently
addressed in the draft decision
documents. For example, county and
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10232
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
state health agencies are required to
regulate water quality, which costs
taxpayer money. This commenter said
that changes to aesthetics associated
with expansion of these activities, such
as noise, odor, and viewshed impacts
should also be considered. Impacts to
recreational uses of the affected
waterbodies could occur if expansions
greater than 100 acres in size are
authorized. This commenter also said
that new and expanded operations
should not be proposed in national
parks or historic monuments, but
existing operations should be allowed to
continue. The commenter also stated
that any projects in river delta regions
should be carefully evaluated due to the
sensitive nature of these brackish
environments.
The draft decision documents briefly
discuss economics as one of the public
interest review factors that are
considered before the Corps issues a
permit, including a general permit.
Shellfish aquaculture activities, in
general, help improve water quality
because many of the commercially
cultivated species are filter feeders that
remove nutrients and suspended
materials from the water column. By
removing nutrients, eutrophication and
similar water quality problems are
lessened. Water quality benefits
provided by commercially grown
shellfish help reduce costs of
remediating local water quality
problems. Commercial shellfish
aquaculture activities have minimal
adverse effects to aesthetics, and are
likely to result in little change in local
baseline levels of noise, odor, or views
when compared to other waterfront uses
in coastal residential areas, such as
private and commercial boats, as well as
the piers, wharves, marinas, and
anchorage or mooring areas where those
vessels are kept. Coastal areas are used
by a wide variety of people. Effects on
recreational uses of the waterbody
should also be considered during the
review of specific commercial shellfish
aquaculture activities. Division
engineers may regionally condition this
NWP to restrict or prohibit its use to
authorize new project areas and/or new
activities in existing project areas in
national parks or in the vicinity of
historic monuments. The protection of
waters near river deltas or other
categories of waters is more
appropriately accomplished through
regional conditions imposed by division
engineers.
One commenter stated that because
commercial shellfish aquaculture may
be limited by farm runoff, increasing
production could require farmland to
cease in operation. Another commenter
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
stated that shellfish farming is a good
gauge of water quality in an area since
poor water quality necessitates closure
of shellfish farms. In contrast, another
commenter said the potential for
aquaculture operations to harvest
continuously as farm size increased
would result in permanently suspended
particulates and increased turbidity
which would damage ecosystems.
Changes in farming operations that
may be related to commercial shellfish
aquaculture activities in nearby waters
is outside of the Corps regulatory
authority. Such issues are more
appropriately addressed by state or local
governments, who have the primary
responsibility for land use decisions.
We recognize that commercial shellfish
aquaculture can help improve water
quality. Harvesting operations may
increase turbidity, but we believe such
impacts are temporary and minor.
We received many comments in
response to our proposal to consider
issuing a new NWP or modifying NWP
48 to authorize new commercial
shellfish aquaculture activities. Many
commenters supported modifying NWP
48 to authorize new activities, and
suggested terms and conditions. One
commenter recommended limiting new
activities to ten acres or less. One
commenter stated that there should be
no limits on new activities because
shellfish aquaculture has only minimal,
short-term adverse environmental
impacts, and the shellfish themselves
provide valuable ecological services.
Two commenters stated that all new
shellfish aquaculture activities except
floating culture should be authorized
under the NWP, because floating
facilities have potential to impact
navigation. One commenter said
limitations on new activities should be
imposed on NWP 48 and reconsidered
when the proposal to reissue the NWPs
is developed in 2016. Other commenters
said that new activities should not be
authorized by NWP because of their
environmental impacts. Another
commenter stated that new activities
should not be authorized by NWP
unless bottom culture methods are used
(except for grow-out bags), harvesting is
done by hand, and only native species
are cultivated. One commenter stated
that baseline habitat assessments should
be provided and no operations should
occur within 180 feet of marine
vegetation, eelgrass, or sand dollar beds.
We are modifying NWP 48 to
authorize commercial shellfish
aquaculture activities in new project
areas, provided the project proponent
obtains a valid authorization (e.g., a
lease or permit from the appropriate
state or local government agency
PO 00000
Frm 00050
Fmt 4701
Sfmt 4703
responsible for granting such leases or
permits) and the activity will not
directly affect more than 1⁄2-acre of
submerged aquatic vegetation beds. Preconstruction notification is required for
all commercial shellfish aquaculture
activities in new project areas. Preconstruction notification is also
required for activities in a project area
if they involve dredge harvesting,
tilling, or harrowing in areas inhabited
by submerged aquatic vegetation or if
the activities involve the change from
bottom culture to floating or suspended
culture in order to assess potential
impacts to navigation. In addition,
general condition 14, proper
maintenance, requires the permittee to
properly maintain any authorized
structure or fill. Therefore, any
authorized commercial shellfish
aquaculture activity and its associated
equipment shall be properly maintained
so as to not pose a hazard to navigation.
The pre-construction notification
thresholds will provide an opportunity
for district engineers to evaluate the
potential adverse effects to navigation
and vegetated shallows, conservation,
and other applicable public interest
review factors, and ensure that those
adverse effects are minimal. We agree
that commercial shellfish aquaculture
activities can provide important
functions and services to the aquatic
environment and should be authorized
by NWP, with appropriate notification
thresholds and limits. Division
engineers may regionally condition this
NWP to restrict or prohibit its use in
specific waters or geographic areas, if
there are concerns that these activities
may have more than minimal adverse
effects on certain species or specific
types of aquatic resources.
This NWP is reissued with the
modifications discussed above.
NWP 49. Coal Remining Activities.
We proposed to clarify how the 40
percent of newly mined area is
determined. We also proposed to
modify the pre-construction notification
provision to require the prospective
permittee to submit documentation
describing how the overall mine plan
will result in a net increase in aquatic
resource functions.
Several commenters supported the
reissuance of NWP 49 and said no
restrictions should be imposed because
remining permits are one of the most
significant tools to alleviate the
environmental effects of past mining
activities. Many commenters said this
NWP should not be reissued. Some of
these commenters stated that these
activities result in more than minimal
cumulative adverse effects. Many
commenters objected to the lack of
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
limits for filling stream channels and
said this NWP should not authorize the
construction of valley fills or refuse fills.
Other commenters stated that the
functional increase associated with remining will still be insufficient to offset
adverse effects of filling stream beds and
that stream mitigation will not
effectively replace lost stream functions.
We believe authorizing remining of an
unreclaimed site and requiring actions
to restore unreclaimed areas is one of
the most effective ways to reverse
degraded water quality in a watershed.
Therefore, we have not imposed any
new limits or restrictions on this NWP.
All activities authorized by this NWP
must result in net increases in aquatic
resource functions, which will help
manage cumulative effects on a
watershed basis. Cumulative effects
assessments have revealed the reduction
in acid mine drainage and/or
sedimentation in downstream segments
of stream channels has resulted in
functional improvements in many
watersheds. The states of Ohio,
Pennsylvania, Virginia, and West
Virginia frequently use remining
activities to reduce acid mine drainage
and sedimentation and have data to
demonstrate these improvements.
We do not believe this permit should
have linear foot or acreage limits, since
this NWP authorizes discharges of
dredged or fill material into waters of
the United States to reclaim previously
mined sites that were unreclaimed,
abandoned, forfeited, and typically
exhibit poor water quality and present
safety hazards. These unreclaimed
mines may have unreclaimed highwalls,
unvegetated mine spoil, disconnected
stream segments, and/or pit
impoundments. We, as well as other
state and federal agencies, recognize
that remining and reclaiming these areas
is one of the most successful means for
improving water quality, because these
activities reduce sedimentation and acid
mine drainage. Due to advances in
mining technology and equipment, it is
now economically viable to remove coal
from these unreclaimed and abandoned
mine sites. These sites can be combined
with adjacent unmined areas to develop
a project that is economically viable. In
many cases the net result of combining
remining of a previously mined site
with new surface coal mining activities
in adjacent areas is to facilitate
reclamation of the older mine site and
reduce acid mine drainage and sediment
from the older mine site to downstream
stream segments. Furthermore, this
NWP provides an incentive to remine
degraded areas, similar to the 1987
Rahall Amendments to the Clean Water
Act, which enables mine operators to
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
apply for the U.S. Environmental
Protection Agency’s modified effluent
limits developed specifically for
remining projects.
Project proponents who want to use
this NWP must submit pre-construction
notifications. The pre-construction
notification describes how the overall
mining plan will result in a net increase
in aquatic resource functions. If there is
an appropriate functional assessment
protocol available for the types of
aquatic resources in that geographic
area, project proponents are encouraged
to use that functional assessment
protocol to demonstrate how the activity
will result in a net increase in aquatic
resource functions. The description of
the proposed project required by
paragraph (b)(3) of general condition 31
should describe the restoration that will
take place on the project site. District
engineers may add activity-specific
conditions to this NWP to require more
detailed restoration plans prior to
discharging dredged or fill material into
waters of the United States, as well as
monitoring plans that will be used to
assess whether the remining and
associated reclamation activities are
resulting in net increases in aquatic
resource functions. Supplemental
compensatory mitigation may be
required in some instances, such as the
implementation of mitigation projects
near the project site, to remove or
reduce causes of aquatic resource
impairment and ensure that the overall
activity not only results in minimal
individual and cumulative adverse
effects on the aquatic environment but
in a net increase in aquatic resource
functions, as required by this NWP.
Several commenters indicated the
general public should have the right to
comment on the proposal before the
district engineer issues the NWP
verification. One commenter said all
activities associated with remining
should require individual permits and
another commenter objected to
combining unmined lands required for
restoration with previously mined lands
because that would categorize unmined
land as unreclaimed land, and result in
additional adverse environmental
effects. One commenter stated that
slurry impoundments should not be
authorized by this NWP.
We believe these activities are
appropriate for general permit
authorization and should not require a
public notice and comment process.
District engineers may assert
discretionary authority and require an
individual permit for proposed
activities if they believe those activities
will result in more than minimal
adverse effects on the aquatic
PO 00000
Frm 00051
Fmt 4701
Sfmt 4703
10233
environment. It is appropriate to
authorize discharges of dredged or fill
material into waters of the United States
for some new mining activities, to
provide an incentive to restore
unreclaimed mine lands, and provide
net increases in aquatic resource
functions. Impacts to the newly mined
area would not be categorized as
remining. Adverse effects to waters of
the United States associated with the
new mining would be subject to the
general condition 23, mitigation, and
the district engineer may add conditions
to the NWP authorization to require
mitigation located near the project site
or out-of-kind mitigation to compensate
for losses of aquatic resource functions.
Typical surface coal mining projects,
including remining, do not include
slurry impoundments, as these
impoundments are typically associated
with the wastewater resulting from coal
processing plants. This NWP does not
authorize the construction of coal
processing plants.
Many commenters said the Corps is
making the review process associated
with NWP 49 more onerous, which will
decrease the utility of the NWP, and
should focus on the environmental
benefits that can be realized from this
nationwide permit.
The proposed changes to this NWP,
which we are adopting, do not make it
more difficult to use NWP 49. The
requirement to provide information
with the pre-construction notification to
explain how the overall activity will
result in net increases in aquatic
resource functions is necessary to
ensure compliance with the terms and
conditions of the NWP. Clarification of
how to apply the 40 percent provision
to determine how much new area could
be mined will provide consistency in
implementation. For example, a site
may be proposed to be remined under
this NWP. If 30 acres of the site has been
previously mined and is proposed to be
remined, and 30 acres of the site is
unmined and is necessary to make it
economically feasible to reclaim the
remined area, then 40% of the
combined acreage of the remined and
reclaimed areas, or 40% of 60 acres
which equals 24 acres, can be newly
mined. In another example, if you have
a 1,000-acre site, and 600 acres are
affected by previously unreclaimed
mining activities and 200 acres are
needed to reclaim the 600 acres, then
40% of 800 acres (the summation of the
previously unreclaimed mining
activities site and the site needed to
reclaim the previously mined site), or
320 acres may be newly mined. As there
are only 200 acres remaining at the
1,000-acre site, those 200 acres may be
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10234
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
authorized under NWP 49 for newly
mined activities.
One commenter said they did not
understand the rationale for establishing
the threshold for newly mined areas at
40 percent, if removing the small
amount of remaining coal reserves will
be far more attractive to coal mine
operators if the percentage was
increased to allow mining on larger
areas of unmined lands. One commenter
said the 40 percent limitation becomes
an obstacle when the remaining coal
seam is deep within the hillside and
large amounts of overburden require
removal. This commenter suggested
increasing the limit for newly mined
areas to 50 or 60 percent to encourage
more restoration of unreclaimed areas.
The commenter recommended adding a
provision allowing district engineers to
waive the 40 percent threshold in
certain situations, such as when the
operator receives an approved pollution
abatement plan with best management
practices, the remining activity is
located in a completed Acid Mine
Drainage Abatement Treatment
watershed area, and watersheds with
established total daily maximum loads.
Several commenters objected to the
provision stating that the Corps would
consider the SMCRA agency’s decision
regarding the amount of currently
undisturbed adjacent lands needed to
facilitate the remining and reclamation
of the previously mined area, stating
that it creates duplicative and
potentially conflicting layers of
regulation to an already highly regulated
industry.
The 40 percent limit was established
when NWP 49 was first issued in 2007,
and was based on the recognition that
some new coal mining may have to be
conducted to provide incentives to
remine and reclaim previously mined
lands. The 40 percent limit is intended
to facilitate compliance with the
minimal adverse effects requirement for
the NWPs. We do not agree that it
would be appropriate to add a provision
allowing district engineers to waive the
40 percent limit. Remining and
reclamation activities involving
discharges of dredged or fill material
into waters of the United States that
require larger proportions of newly
mined areas may be authorized by
individual permits. The expertise
provided by the agencies responsible for
implementing SMCRA is necessary to
help the Corps make its determination
of compliance with the terms and
conditions of this NWP.
One commenter stated this NWP
should look holistically at overall water
and site improvements, improvement in
the safety of the area by the elimination
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
of pits and highwalls, and reclamation
of sites without the use of public funds.
We have focused this NWP on
authorizing those activities that provide
net increases in aquatic resource
functions. The consideration of overall
site improvements, increased safety, and
the lack of use of public funds is more
appropriately addressed by other
agencies or programs.
This NWP is reissued as proposed.
NWP 50. Underground Coal Mining
Activities. We proposed to place a 1⁄2acre limit on this NWP, as well as a 300linear foot limit for losses of stream bed.
We also proposed a provision that
allows district engineers to waive the
300 linear foot limit for losses of
intermittent or ephemeral stream bed by
making a written determination
concluding that the discharge of
dredged or fill material will result in
minimal adverse effects.
Several commenters objected to the
reissuance of this NWP, stating that it
authorizes activities with more than
minimal individual and cumulative
adverse effects on the aquatic
environment. Several commenters
stated that activities authorized by this
NWP will result in the loss of stream
functions and adversely impact water
quality downstream of the mine site.
Several commenters said this NWP does
not comply with the Section 404(b)(1)
Guidelines and that the cumulative
impacts analysis is too general and fails
to consider past actions.
We have imposed a 1⁄2-acre limit on
this NWP, as well as a 300 linear foot
limit for the loss of stream bed. Preconstruction notification is required for
all activities authorized by this NWP,
and the permittee may not begin work
in waters of the United States until an
NWP verification is issued by the
district engineer. These requirements, as
well as the ability of district engineers
to exercise discretionary authority and
modify the NWP authorization by
imposing activity-specific conditions,
will help ensure that the NWP
authorizes only those activities with
minimal individual and cumulative
adverse effects on the aquatic
environment. Division engineers may
regionally condition this NWP to restrict
or prohibit its use in specific geographic
regions, waters, or watersheds if the use
of this NWP would authorize activities
with more than minimal individual and
cumulative adverse effects. When
reviewing pre-construction
notifications, district engineers will also
evaluate whether the proposed activity
will cause more than minimal direct
and indirect adverse effects to water
quality downstream of the mine site.
The issuance of this NWP complies with
PO 00000
Frm 00052
Fmt 4701
Sfmt 4703
the 404(b)(1) Guidelines, and we have
complied with the requirements at 40
CFR 230.7. The cumulative effects
analysis provided in the decision
document in accordance with the
National Environmental Policy Act
considers the effects of past actions, to
the extent that they have continuing
effects on the aquatic environment.
Under the 404(b)(1) Guidelines, the
cumulative effects analysis involves
prediction of the number of discharges
likely to be regulated by a general
permit until its expiration (see 40 CFR
230.7(b)(3)). That regulation, as well as
40 CFR 230.11(g), does not state that the
effects of past actions have to be
considered for the purposes of the
404(b)(1) Guidelines analysis, although,
as stated above, we have considered
such effects in connection with our
NEPA analysis.
Several commenters stated that NWP
50 should not have any acreage and/or
linear foot limitations as these limits
would essentially render the permit
unusable for underground mining
operations.
We do not agree that the 1⁄2-acre limit
and the 300 linear foot limit for stream
bed losses make this NWP unusable.
This NWP authorizes discharges of
dredged or fill material into waters of
the United States for underground coal
mining activities, provided those
activities result in minimal adverse
effects on the aquatic environment.
Since these coal mining activities occur
underground, losses of waters of the
United States are usually small in size
because they are limited to discharges of
dredged or fill material in waters of the
United States to construct infrastructure
and impoundments to support those
mining activities. Underground coal
mining activities that result in the loss
of greater than 1⁄2-acre of waters of the
United States, or more than 300 linear
feet of perennial stream bed, may be
authorized by individual permits or, if
available, regional general permits.
One commenter stated that districts
have incorrectly classified perennial
streams and that impacts to special
aquatic sites (e.g., riffle and pool
complexes) have not been properly
considered. Another commenter said
that Clean Water Act jurisdiction does
not extend to ephemeral and
intermittent streams. Several
commenters indicated stream mitigation
measures are not effective and the Corps
has failed to provide a rational
explanation as to how mitigation will
attenuate cumulative effects.
Classifying a stream as perennial,
intermittent, or ephemeral is done by
district engineers by evaluating
available information on stream flow,
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
including information that may be
submitted by a project proponent in
support of a pre-construction
notification. A site visit may also be
conducted to identify perennial,
intermittent, or ephemeral stream
segments. Impacts to special aquatic
sites such as riffle and pool complexes
will be considered when reviewing a
pre-construction notification, and
discretionary authority will be asserted
if the district engineer determines that
the adverse effects on the aquatic
environment are more than minimal.
Both intermittent and ephemeral
streams are subject to Clean Water Act
jurisdiction if they are determined by
district engineers to be waters of the
United States after applying the
appropriate regulations and guidance.
Stream rehabilitation and enhancement
activities have been shown to improve
the ecological functions provided by
those aquatic ecosystems. Stream
compensatory mitigation projects must
comply with the applicable
requirements provided in general
condition 23, mitigation, and the
compensatory mitigation regulations at
33 CFR 320.4(r) and 33 CFR part 332.
District engineers will review and
approve mitigation plans, and will
require alternative or additional
compensatory mitigation if they
determine the proposed compensatory
mitigation will not be sufficient to
successfully offset the losses of aquatic
resources caused by the permitted
activity. Compensatory mitigation
projects must be implemented in
accordance with their approved
mitigation plans. District engineers will
also require monitoring of these
compensatory mitigation projects, and
require remediation and adaptive
management if those mitigation projects
are not providing the intended aquatic
resource functions. If a district engineer
determines that a compensatory
mitigation project is not ecologically
successful and fails to fulfill its
objectives, district engineers may
require alternative compensatory
mitigation to comply with the
mitigation requirements established
through conditions added to the NWP
authorization.
Several commenters indicated the
activities regulated by this NWP are also
heavily regulated by SMCRA, the
Federal Mine Safety and Health Act
(MSHA), and the state mining and water
resource programs; therefore, no limits
should be imposed on the permit. One
commenter said the limits and the
waiver process is highly subjective and
results in uncertainty in the Regulatory
Program. One commenter stated that
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
limitations imposed on this NWP could
potentially require applicants to seek
individual permits for all underground
mining actions, which may result in a
requirement to prepare an
environmental impact statement. This
commenter said that there should be a
transition period without acreage or
linear foot limits so that underground
coal mining activities could continue to
be authorized by this NWP until an
individual permit can be obtained. One
commenter said that reissuing NWP 50
with the 1⁄2-acre and 300 linear foot
limits would result in significant job
losses for their company, which consists
of Native Americans who comprise 62
percent of their workforce. One
commenter said that the new limits on
this NWP would also increase the Corps
workload.
This NWP provides authorization
required under Section 404 of the Clean
Water Act, for discharges of dredged or
fill material into waters of the United
States. The acreage and linear foot limits
of this NWP are necessary to ensure that
authorized activities result in minimal
adverse effects on the aquatic
environment. Compliance with other
laws may be required for surface coal
mining activities, but those decisions
are made by the agencies responsible for
administering those laws. District
engineers will consider the criteria in
paragraph (1) of section D, ‘‘District
Engineer’s Decision’’ and other
appropriate criteria, when making a
minimal effects determination for a
proposed NWP activity. Activities that
result in the loss of greater than 1⁄2-acre
of waters of the United States require
individual permits, unless those
activities qualify for applicable regional
general permits. If an individual permit
is required, district engineers will
determine whether an environmental
impact statement is necessary to comply
with the requirements of the National
Environmental Policy Act. We do not
agree that there should be a transition
period for these activities, because the
acreage and linear foot limits are
necessary to comply with Section 404(e)
of the Clean Water Act, and past use of
this NWP indicates that the average loss
of waters of the United States was 0.21
acre per NWP 50 activity. While there
might be an increase in the number of
individual permits, we do not believe it
will be a large workload increase. As
with all NWPs, an activity that was
authorized under the 2007 NWPs has
until March 18, 2013, to be completed
under this authorization.
One state agency indicated
implementation of the limits would
result in increased workload for their
staff and requested that funding be
PO 00000
Frm 00053
Fmt 4701
Sfmt 4703
10235
provided to their office to mitigate this
increase. One commenter stated that
sites which contain reclaimed and
abandoned mines associated with deep
mining operations with portals and/or
bat habitat should be assessed for bat
use.
Any workload increase due to the
addition of the 1⁄2-acre and 300 linear
foot limits would be borne primarily by
the Corps districts. It does not directly
impose additional workload on state
agencies. The SMCRA permits required
for all mining activities must go through
advanced coordination with the U.S.
Fish and Wildlife Service regarding
endangered bat species and with the
State natural resources agencies
regarding state listed bat species. Effects
to wildlife, including bats, that are not
federally-listed as endangered or
threatened, or state-listed bat species,
will also be addressed through the
SMCRA permit process. For federallylisted bat species, activities authorized
by this NWP must also comply with
general condition 18, endangered
species.
This NWP is reissued as proposed.
NWP 51. Land-Based Renewable
Energy Generation Facilities. This NWP
was proposed as NWP A to authorize
the discharges of dredged or fill material
into non-tidal waters of the United
States, excluding non-tidal wetlands
adjacent to tidal waters, for the
construction, expansion, or
modification of land-based renewable
energy production facilities. Examples
include infrastructure to generate solar
(concentrating solar power and
photovoltaic), biomass, wind or
geothermal energy and their collection
systems. Attendant features may
include, but are not limited to roads,
parking lots, utility lines, and
stormwater management facilities. We
proposed a 1⁄2-acre limit for this NWP,
including the loss of no more than 300
linear feet of stream bed, unless for
intermittent and ephemeral stream beds
the district engineer waives this 300
linear foot limit by making a written
determination concluding that the
discharge will result in minimal adverse
effects.
Several commenters objected to the
issuance of this NWP, stating that the
Corps had failed to explain why the
direct and indirect impacts resulting
from the land-based renewable energy
projects authorized by this NWP would
be minimal, including the impacts
caused by construction and operation of
these facilities. These commenters said
that individual permits should be
required for these facilities. One of these
commenters said that biomass facilities
will significantly add to greenhouse gas
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10236
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
emissions and expressed the belief that
biomass facilities will lead to increased
land-clearing for harvest, planting and
re-planting of trees. Several commenters
stated that wind turbines will cause
direct mortality on birds and bats and
adversely affect critical avian and bat
habitat. Two commenters stated that
wind-generated energy facilities should
incorporate guidelines developed by the
U.S. Fish and Wildlife Service to
minimize impacts to avian and bat
species. One commenter stated that
land-based wind and solar renewable
energy facilities are not water
dependent and should always require
individual permits to allow for a
thorough alternatives analysis for site
selection. Several commenters stated
that the activities authorized by this
NWP are not similar in nature, since
they involve various types of renewable
energy facilities that have different
adverse environmental effects.
This NWP authorizes discharges of
dredged or fill material into waters of
the United States for the construction,
expansion, or modification of landbased renewable energy facilities.
Unless the operation of these facilities
involves discharges of dredged or fill
material into waters of the United
States, the Corps does not authorize, or
have any Federal control or
responsibility over, their operation. We
believe that the construction, expansion,
or modification of these facilities has
minimal adverse effects on the aquatic
environment, individually and
cumulatively. Division engineers can
regionally condition this NWP to restrict
or prohibit its use in waters of the
United States, where the discharges of
dredged or fill material are likely to
result in more than minimal adverse
effects on the aquatic environment.
While there may be emissions of
greenhouse gases during construction
activities involving discharges of
dredged or fill material into waters of
the United States, those direct emissions
will generally not exceed de minimus
levels of a criteria pollutant or its
precursors and are exempted by 40 CFR
93.153. Emissions of greenhouse gases
that occur from the operation of a landbased renewable energy generation
facility, as well as emissions that occur
when harvesting plant material for
biomass energy production and
operating the energy generation facility,
are outside the Corps scope of analysis
under the National Environmental
Policy Act, because the Corps does not
have the legal authority to control such
emissions. The 404(b)(1) Guidelines do
not include any requirements to assess
effects of proposed discharges of
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
dredged or fill material into waters of
the United States on greenhouse gas
emissions. Land clearing that may be
conducted for the harvesting, planting,
and replanting of trees that provide fuel
for biomass energy facilities is not
authorized by this NWP, and if such
activities involve discharges of dredged
or fill material into waters of the United
States, a separate Department of the
Army permit is required.
If the construction, expansion, or
modification of a land-based renewable
energy facility involves discharges of
dredged or fill material into waters of
the United States, and that activity may
affect an endangered or threatened
species, or is located in designated
critical habitat, Endangered Species Act
Section 7 consultation is required, and
the activity cannot proceed until section
7 consultation is completed. We have
added general condition 19, migratory
birds and bald and golden eagles, to
clarify that if an activity regulated by
the Corps will result in the ‘‘take’’ of a
migratory bird or a Bald or Golden
Eagle, and a ‘‘take’’ permit is required
from the U.S. Fish and Wildlife Service,
it is the responsibility of the permittee
to apply for, and obtain, the appropriate
‘‘take’’ permits from the U.S. Fish and
Wildlife Service. The draft Land-based
Wind Turbine Guidelines developed by
the U.S. Fish and Wildlife Service are
voluntary guidelines that project
proponents may incorporate into their
land-based wind energy projects. The
Corps does not have the authority to
condition this NWP to incorporate the
recommendations provided in those
guidelines. Water dependency is not a
requirement for authorization by general
permit, including nationwide permits.
The water dependency test in the
404(b)(1) Guidelines guides the
alternatives analysis for activities that
require individual permits under
Section 404 of the Clean Water Act.
The activities authorized by this NWP
(i.e., discharges of dredged or fill
material into waters of the United States
for the construction, expansion, or
modification of land-based renewable
energy facilities) are similar in nature.
The Corps interprets the ‘‘similar in
nature’’ requirement in Section 404(e) of
the Clean Water Act broadly, to cover
general categories of activities. The
discharges of dredged or fill material
authorized by this NWP will have
similar effects on the aquatic
environment, by replacing waters of the
United States with dry land, or altering
their characteristics, when renewable
energy facilities are constructed,
modified, or expanded.
Two commenters expressed concern
that if NWP A is issued, all land-based
PO 00000
Frm 00054
Fmt 4701
Sfmt 4703
renewable energy facilities will require
pre-construction notification because
they could only be authorized by this
NWP. Several commenters stated that
NWP A should not be issued because all
types of land-based renewable energy
facilities can be authorized by existing
NWPs, such as NWPs 12, 14, 18, 25, and
39, and it is not necessary to issue a new
NWP that requires pre-construction
notification for all activities. They also
said that the issuance of NWP A would
contradict the Corps stated goals of
reducing administrative burdens on the
regulated public, and utilizing its
resources to focus on those projects that
could be more environmentally
damaging. One commenter stated that
the pre-construction notification
requirement would cause an
unnecessary burden on project
proponents, especially the requirement
to provide a delineation of waters of the
United States in the project area.
We are retaining the requirement that
all activities authorized by this NWP
require pre-construction notification, so
that district engineers can evaluate these
activities and add activity-specific
conditions, if necessary, to ensure that
they result in minimal individual and
cumulative adverse effects on the
aquatic environment. Other NWPs may
be used to authorize discharges of
dredged or fill material into waters of
the United States for activities that may
be associated with land-based
renewable energy facilities. We do not
intend issuance of this NWP to restrict
currently available options for use of
other NWPs to authorize any such
discharges. For example, NWP 12 may
be used to authorize discharges of
dredged or fill material associated with
the construction, maintenance, repair,
or removal of utility lines for land-based
renewable energy facilities. Likewise,
NWP 14 may be used to authorize road
crossings in waters of the United States
within a land-based renewable energy
facility. Project proponents may specify
which NWP they wish to use to provide
the requisite Department of the Army
authorization under Section 404 of the
Clean Water Act and/or Section 10 of
the Rivers and Harbors Act of 1899. If
the proposed activity qualifies for
authorization under that particular
NWP, the district engineer will issue a
verification letter. This NWP fulfills the
objectives of the NWP program, since
many land-based renewable energy
projects require discharges of dredge or
fill material into waters of the United
States that would not qualify for NWPs
12 or 14, or other NWPs that do not
require pre-construction notification.
One commenter suggested changing
the pre-construction notification
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
threshold to 1⁄10-acre, so that
compensatory mitigation would not be
required for activities resulting in the
loss of less than 1⁄10-acre of waters of the
United States. Another commenter said
that requiring pre-construction
notification for losses of less than 1⁄10acre removes incentives to minimize
losses of waters of the United States to
less than 1⁄10-acre. Two commenters
stated that increasing the preconstruction notification threshold to
1⁄10-acre would be more consistent with
Executive Order 13212, Actions To
Expedite Energy-Related Projects.
We do not agree that the preconstruction notification threshold
should be increased to 1⁄10-acre to match
the pre-construction notification
thresholds for NWP 12 or 14, since
utility lines or road crossings may be
only partial components of a land-based
renewable energy generation facility. It
should be noted that NWP 14 requires
pre-construction notification for any
discharge into a special aquatic site,
including wetlands, which means that
many NWP 14 activities that result in a
loss of less than 1⁄10-acre require preconstruction notification. Nationwide
permit 12 should be used when the only
activities that require Department of the
Army authorization are discharges of
dredged or fill material to construct,
maintain, repair, or remove utility lines.
Therefore, in Note 1 we state that NWP
12 is to be used to authorize those
utility line activities, as long as those
activities comply with the terms and
conditions of NWP 12, including
applicable regional conditions and any
case-specific conditions imposed by the
district engineer. This NWP authorizes
building pads for the renewable energy
generation devices and attendant
features associated with those devices,
such as parking lots and stormwater
management facilities. If more than one
NWP is used to authorize a land-based
renewable energy generation facility, the
activity must comply with general
condition 28, use of multiple
nationwide permits, which states that
the loss of waters of the United States
cannot exceed the acreage limit of the
NWP with the highest specified acreage
limit. Compensatory mitigation is at the
discretion of the district engineer, and
will be required when necessary to
ensure that the authorized activity
results in minimal individual and
cumulative adverse effects on the
aquatic environment. Paragraph (a) of
general condition 23, mitigation,
requires permittees to avoid both
temporary and permanent adverse
effects to waters of the United States on
the project site. The issuance of this
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
NWP supports the objective of
Executive Order 13212, by providing
NWP authorization for some activities
that would otherwise require individual
permits because they do not qualify for
any of the existing NWPs.
Two commenters agreed that NWP A
is needed but said that many land-based
renewable energy projects would not
qualify because the losses of waters of
the United States frequently exceed the
acreage or linear foot limits. One
commenter suggested increasing the
acreage limit to one acre and the linear
foot limit to 500 linear feet of stream
bed, and allow the district engineer to
waive the 500 linear foot limit if he or
she determines that the activity will
result in minimal adverse
environmental effects. One commenter
stated that NWP A should not allow
waivers for stream bed losses in excess
of 300 linear feet.
We believe that there will be a
sufficient number of land-based
renewable energy generation facilities
authorized by this NWP to warrant its
issuance. As with all general permits,
this NWP will also provide an incentive
for project proponents to reduce losses
of waters of the United States to qualify
for NWP authorization, instead of
having to apply for individual permit
authorization, if there are no regional
general permits available to authorize
these activities. The 1⁄2-acre and 300
linear foot limits are necessary to ensure
that this NWP authorizes only those
activities that have minimal individual
and cumulative adverse effects on the
aquatic environment, and are consistent
with the limits in many other NWPs.
Division engineers can regionally
condition this NWP to reduce the
acreage limit or linear foot limits, or
revoke this NWP in specific waters or
geographic areas where the adverse
effects on the aquatic environment may
be more than minimal. In response to a
pre-construction notification, the
district engineer may add activityspecific conditions to the NWP
authorization to impose requirements to
satisfy the minimal adverse
environmental effect requirement. The
300 linear foot limit for the loss of
intermittent and ephemeral stream bed
can only be waived when the district
engineer makes a written determination
that the loss of that stream bed will
result in minimal adverse
environmental effects, after evaluating
the site-specific characteristics of the
project.
Several commenters said that all preconstruction notifications should be
coordinated with other Federal and state
agencies. One commenter stated that
agency coordination should be required
PO 00000
Frm 00055
Fmt 4701
Sfmt 4703
10237
whenever a request for a waiver of the
300 linear foot limit is being evaluated
by the district engineer. One commenter
stated that this NWP should not include
the waiver provision because of
potential impacts to cultural resources
and historic properties.
We do not believe it is necessary to
coordinate all activities authorized by
this NWP with Federal and state
agencies. District engineers will
carefully evaluate these preconstruction notifications and
determine whether the proposed
activities qualify for NWP authorization.
Agency coordination is required for preconstruction notifications for proposed
activities resulting in the loss of
intermittent or ephemeral stream bed in
excess of 300 linear feet. Activities
authorized by this NWP must also
comply with general condition 20,
historic properties and district engineers
will conduct section 106 consultation if
a proposed activity may have the
potential to cause effects to any historic
properties listed, or eligible for listing,
on the National Register of Historic
Places.
Several commenters requested
clarification on whether land-based
renewable energy facilities would be
considered as single and complete
linear projects or single and complete
non-linear projects. Several commenters
asked if the linear features of these
facilities, such as roads, utilities, and
transmission lines, could be categorized
as linear projects, while the
construction of other components of the
project, such as parking lots and
buildings, would be considered as nonlinear projects. A few commenters said
terms and conditions should be added
to the NWP to specify that the definition
of single and complete linear project
would always be used for linear
components of the overall facility. One
commenter stated that the activities
authorized by this NWP should be
considered one single and complete
project because all renewable energy
devices and their attendant features,
including both linear and non-linear
components, are required for the facility
to have independent utility.
We have added Note 1 to this NWP
to clarify that the NWP authorizes
discharges of dredged or fill material
into waters of the United States for the
construction, expansion, or
modification of a land-based renewable
energy generation facility, including
attendant features within that facility,
and that utility lines that are used to
transfer energy from the renewable
energy generation facility to a
distribution system, regional grid, or
other facility are generally considered to
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10238
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
be separate single and complete linear
projects. Those utility lines may be
authorized by NWP 12 or other
Department of the Army authorization.
A similar approach should be used for
roads or other types of utility lines (e.g.,
sewage or water lines) constructed to
provide access to, or service, the landbased renewable energy generation
facility. We are using the term
‘‘generally’’ in Note 1 because crossings
of waters of the United States have to be
at separate and distant locations to be a
single and complete project. Crossings
that are close together would not be
considered separate single and complete
projects. Since the configuration of
land-based renewable energy generation
facilities can vary substantially, district
engineers will use their discretion to
determine which activities are single
and complete linear projects and which
activities are single and complete nonlinear projects, after evaluating the
specific circumstances of a particular
project. For example, the devices used
to collect wind or solar energy may be
arranged in a grid or in a linear
configuration.
One commenter asked how the permit
area would be determined for landbased renewable energy facilities.
Specifically, the commenter asked
whether the permit area would be the
entire area bound by the perimeter of
the facility, or just those areas within
the facility where there are discharges of
fill material into waters of the United
States.
Identifying the permit area for the
purposes of compliance with general
condition 20, historic properties, is
accomplished by applying the criteria in
Appendix C to 33 CFR part 325,
specifically paragraph 1(g), as well as
the interim guidance issued on April 25,
2005 (paragraph 6(d)). The permit area
will be determined by district engineers
after considering the project-specific
circumstances.
Several commenters stated that this
NWP should not authorize activities in
certain geographic areas, such as the
Great Lakes. One commenter said that
approval may be required for facilities
that would impact state-owned waters
or submerged lands.
Division engineers have the authority
to suspend or revoke this NWP in
specific waters or geographic areas.
Division engineers may also add
regional conditions to restrict or
prohibit its use in certain waters or
regions. In response to a preconstruction notification, district
engineers may add activity-specific
conditions to the NWP authorization to
ensure that the activity results in
minimal adverse effects on the aquatic
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
environment. Project proponents must
obtain all applicable Federal, state, or
local authorizations, such as state
permits to authorize activities on stateowned waters or submerged lands.
One commenter said that this NWP
could be used to authorize activities
associated with wind energy generating
structures, solar towers, or overhead
transmission lines, which have the
potential to interfere with Department of
Defense’s long range surveillance,
homeland defense, testing, and training
missions. This commenter requested
that copies of pre-construction
notifications and NWP verification
letters for these activities be provided to
the Department of Defense Siting
Clearinghouse, so that the Department
of Defense could have an opportunity to
coordinate with the project proponent to
ensure that long range surveillance,
homeland defense, testing, and training
missions are not adversely affected by
these activities.
We have added Note 2 to this NWP
to require district engineers to send preconstruction notifications and NWP
verification letters to the Department of
Defense Siting Clearinghouse if this
NWP is proposed to be used to
authorize the construction of wind
energy generating structures, solar
towers, or overhead transmission lines.
The Department of Defense Siting
Clearinghouse is responsible for
coordinating with the project proponent
and resolving any potential effects on
Department of Defense long range
surveillance, homeland defense, testing,
and training missions.
Proposed NWP A is issued as NWP
51, with the changes discussed above.
NWP 52. Water-Based Renewable
Energy Generation Pilot Projects. This
NWP was proposed as NWP B to
authorize structures or work in
navigable waters of the United States
and discharges of dredged or fill
material into waters of the United
States, for the construction, expansion,
or modification of water-based wind or
hydrokinetic renewable energy
generation pilot projects and their
attendant features. Attendant features
may include, but are not limited to landbased distribution facilities, roads,
parking lots, utility lines, and
stormwater management facilities. We
proposed a 1⁄2-acre limit for this NWP,
including the loss of no more than 300
linear feet of stream bed, unless for
intermittent and ephemeral stream beds
the district engineer waives this 300
linear foot limit by making a written
determination concluding that the
discharge will result in minimal adverse
effects.
PO 00000
Frm 00056
Fmt 4701
Sfmt 4703
Several commenters supported the
issuance of this NWP. Some of these
commenters provided suggestions to
improve the NWP. Two commenters
said the acreage limit should be
increased from 1⁄2-acre to one acre and
the linear foot limit be increased from
300 linear feet to 500 linear feet. One
commenter stated that the NWP limits
impacts to 1⁄2-acre without taking into
consideration the aggregate capacity of
the facility, only the number of
generation units. One commenter said
the pre-construction notification
threshold should be increased to 1⁄10acre to be consistent with the preconstruction notification threshold of
some of the other NWPs that authorize
similar activities, such as NWP 12. This
commenter asked why activities
associated with water-based renewable
energy projects should be subject to
closer scrutiny than other energy-related
activities.
We are issuing this NWP with the 1⁄2acre and 300 linear foot limits, and
restricting its use to pilot projects, to
ensure that this NWP authorizes only
those activities that have minimal
adverse effects on the aquatic
environment. Division engineers can
impose regional conditions on this NWP
to decrease these limits, if there is
potential for these activities to result in
more than minimal adverse effects on
the aquatic environment in a particular
waterbody or geographic area.
Individual permits, with a public notice
and comment process, should be
required for larger-scale water-based
renewable energy generation facilities
that are not pilot projects and involve
activities that require Department of the
Army authorization. Use of technologies
other than wind or hydrokinetic devices
for water-based renewable energy
generation facilities may be authorized
by other forms of Department of the
Army permits, if such permits are
required for the construction,
expansion, modification, or removal of
those devices. We are requiring preconstruction notification for all
activities authorized by this NWP, so
that district engineers can evaluate the
proposed work and make a projectspecific determination that the adverse
effects on navigation, the aquatic
environment, and other public interest
review factors would be minimal,
individually and cumulatively. It
should be noted that NWP 12 only
authorizes discharges of dredged or fill
material, or structures or work in
navigable waters of the United States,
for the construction, maintenance, or
repair of utility lines, and that all NWP
12 activities in section 10 waters require
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
pre-construction notification. Therefore,
there are few differences in preconstruction notification thresholds for
this NWP and other NWPs that may
authorize similar activities. However, as
with NWP 51, it is not our intent to
limit any currently available options for
use of other applicable NWPs to cover
discharges of dredge or fill material
associated with activities involved in
the construction of water-based
renewable energy generation pilot
projects. Rather, this NWP provides an
additional option for authorization of
such discharges that are not currently
covered by any other NWP.
Several commenters also stated that
the limit of 10 generation units should
either be eliminated or further defined.
Several commenters said the 10
generation unit limit should be removed
to allow projects that employ different
technologies to be authorized by this
NWP. Several commenters said that the
total number of generation units should
be defined as the total number of units
per each single and complete project.
We believe the 10-unit limit is
necessary to ensure that these pilot
projects are small in scope, to ensure
they would not have significant adverse
environmental effects. The 10-unit limit,
as well as the 1⁄2-acre and 300 linear foot
limits, apply to single and complete
projects. The information collected
during these pilot projects will be useful
in evaluating the potential productivity,
feasibility, and environmental effects of
larger scale water-based renewable
energy generation facilities, which will
require other types of authorization if
they require DA permits.
Numerous commenters objected to the
issuance of this NWP. Most of these
commenters said that these activities
will result in more than minimal
individual and cumulative adverse
effects on the aquatic environment.
Several commenters said that there is
not sufficient understanding of the
environmental effects of these activities
to warrant issuance of an NWP. Some
commenters stated that these activities
should be authorized by individual
permits, with a full public notice and
comment process and National
Environmental Policy Act
documentation. A few commenters said
this NWP should not be used to
authorize activities in the Great Lakes.
The terms and conditions of this
NWP, including the 1⁄2-acre limit, the
300 linear foot limit, and the 10-unit
limit will ensure that this NWP
authorizes only those activities with
minimal adverse effects on the aquatic
environment. All activities authorized
by this NWP require pre-construction
notification, which provides district
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
engineers with the opportunity to
review each proposed activity and
determine whether the adverse effects
on the aquatic environment will be
minimal. District engineers may add
activity-specific conditions to the NWP
authorization which require actions to
mitigate adverse environmental effects.
District engineers may also exercise
discretionary authority to require an
individual permit if permit conditions
will not be sufficient to comply with the
minimal adverse environmental effects
requirement for general permits.
Division engineers may impose regional
conditions to restrict or prohibit the use
of this NWP in certain waters or specific
geographic areas, including the Great
Lakes.
Several commenters requested a
definition of the term ‘‘pilot project.’’
Some of these commenters said that this
term could be interpreted broadly, in
part because much of the technology
used for water-based renewable energy
generation facilities is in the early stages
of development. In contrast, another
commenter stated that not defining the
term ‘‘pilot project’’ would restrict the
applicability of this NWP. One
commenter suggested that this NWP not
be limited to pilot projects. One
commenter recommended limiting pilot
projects to those that will be used as
demonstration projects or test projects
to determine the practicability of waterbased renewable energy generation at a
particular site. One commenter said that
this NWP should not be limited to small
offshore wind energy pilot projects, and
that this NWP should authorize offshore
wind energy projects of any duration to
encourage the development of
renewable energy technologies.
We have added a provision to this
NWP that defines the term ‘‘pilot
project.’’ The definition is similar to
how the Federal Energy Regulatory
Commission describes hydrokinetic
pilot projects in their April 2008 white
paper on licensing hydrokinetic pilot
projects. The definition in the NWP
focuses on the experimental nature of
pilot projects, and their use in collecting
data on the performance of the device in
generating energy for other uses and the
effects of the devices on the
environment, including the aquatic
environment. Due to the recent
development of this technology, we
believe it is necessary to limit these
water-based renewable energy
generation facilities to pilot projects, to
provide more information on potential
adverse effects to the aquatic
environment. In a future reissuance of
the NWPs, we may consider expanding
the scope of this NWP to authorize other
small-scale water-based renewable
PO 00000
Frm 00057
Fmt 4701
Sfmt 4703
10239
energy generation facilities. A waterbased renewable energy generation
facility that is not a pilot project and
does not qualify for an applicable
regional general permit is more
appropriately evaluated through the
standard permit process, including a
full public interest review.
One commenter stated that even pilot
projects may result in more than
minimal adverse effects on the aquatic
environment because of indirect effects
caused by blade strikes on birds and
potential obstructions to navigation
when these pilot projects are sited in
navigable rivers. One commenter said
the 10 generation unit limit may not be
effective in ensuring that single and
complete projects do not cause more
than minimal adverse environmental
effects on a cumulative basis or comply
with monitoring requirements.
District engineers will review preconstruction notifications and
determine whether the proposed
activity complies with all terms and
conditions of the NWP and may add
activity-specific conditions, such as
authorizing less than 10 units, to
minimize adverse effects to navigation,
the aquatic environment, and other
public interest review factors such as
impacts to fish and wildlife values.
Indirect effects caused by the operation
of these pilot projects, such as wind
turbine blade strikes on birds, should be
addressed through compliance with the
appropriate Federal laws, such as the
Endangered Species Act, Migratory Bird
Treaty Act, or Bald and Golden Eagle
Protection Act. Compliance with the
Endangered Species Act is addressed
through general condition 18. As stated
in general condition 19, project
proponents are responsible for obtaining
any take permits that may be required
under the Migratory Bird Treaty Act or
the Bald and Golden Eagle Protection
Act. The project proponent should
contact the local office of the U.S. Fish
and Wildlife Service to determine
whether a take permit is required for
that project. Impacts to fish or other
aquatic organisms caused by
hydrokinetic energy units should be
considered by district engineers when
reviewing pre-construction notifications
for activities authorized by this NWP.
District engineers may also suspend or
revoke NWP authorizations if they
determine those activities are causing
more than minimal adverse
environmental effects to the aquatic
environment. Division engineers may
impose regional conditions on this NWP
to reduce the number of units
authorized by this NWP, or restrict or
prohibit its use in specific waters or
other geographic areas.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10240
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Several commenters requested
clarification of applicability of the 300
linear foot stream limit to the ocean
floor or the Great Lakes because those
waters are not characterized as streams.
A few commenters suggested that the
300 linear foot limit does not apply to
water-based renewable energy
generation pilot projects in the ocean or
large rivers, since activities in those
waters does not result in a loss of stream
bed.
We agree that the 300 linear foot limit
does not apply to the construction,
expansion, modification, or removal of
water-based wind or hydrokinetic
renewable energy devices in the ocean,
Great Lakes, or large navigable rivers,
since those activities do not result in
loss of stream bed. The 300 linear foot
limit also does not apply to the
installation or removal of transmission
lines on the ocean floor, the bottom of
the Great Lakes, or the substrate of large
navigable rivers. Transmission lines
placed on the bottom of navigable
waters are generally considered to be
structures, not fill. District engineers
will evaluate the techniques used to
place transmission lines on the bottom
of navigable waters and determine
whether there is a discharge of dredged
or fill material, and whether that
discharge of dredged or fill results in a
loss of waters of the United States
subject to the 300 linear foot limit. The
installation of transmission lines in
these navigable waters in trenches that
are backfilled constitutes a temporary
impact and is not applied to the 300
linear foot limit for the loss of stream
bed. The 300 linear foot limit for the
loss of stream bed applies primarily to
the construction of land-based attendant
features, such as distribution facilities,
control facilities, roads, parking lots,
and stormwater management facilities.
We have added a provision to this NWP
to clarify that the placement of a
transmission line on the bed of a
navigable water of the United States
from the renewable energy generation
unit(s) to a land-based collection facility
is considered a structure regulated
under Section 10 of the Rivers and
Harbors Act of 1899, and not a discharge
of fill material under Section 404 of the
Clean Water Act. The placement of the
transmission line on the bed of the
navigable water is not considered a loss
of waters of the United States that
applies towards the 1⁄2-acre limit or 300
linear foot limit of the NWP.
Several commenters requested the
addition of more categories of sensitive
habitat where this NWP could not be
used to authorize structures or work in
navigable waters of the United States or
discharges of dredged or fill material
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
into waters of the United States for
water-based renewable energy
generation pilot projects. Two
commenters suggested adding coral
reefs to the list of prohibited areas.
Another commenter suggested adding
National wildlife refuges, state parks,
state wildlife management areas,
designated significant coastal areas,
critical habitats for Federally-listed
endangered and threatened species,
important bird areas, or any sensitive
environmental area. One commenter
recommended adding eelgrass beds,
seagrass beds, kelp beds, macro-algae
beds, vegetated shallows, and shellfish
beds to the list of excluded areas.
The proposed NWP B stated that it
did not authorize activities in coral
reefs. This NWP is also subject to
general condition 22, designated critical
resource waters, which prohibits using
this NWP to authorize discharges of
dredged or fill material into critical
resource waters and their adjacent
wetlands. Critical resource waters
include marine sanctuaries and marine
monuments managed by the National
Oceanic and Atmospheric
Administration, and National Estuarine
Research Reserves. District engineers
may designate additional critical
resource waters, after notice and an
opportunity for public comment.
Division engineers may also impose
regional conditions to restrict or
prohibit the use of this NWP in specific
categories of waters or in certain
geographic areas. In response to a preconstruction notification, district
engineers may exercise discretionary
authority and require an individual
permit if the proposed activity will
result in more than minimal adverse
effects on the aquatic environment.
One commenter said that district
engineers should not be authorized to
waive the 300 linear foot limit for the
loss of intermittent and ephemeral
stream bed. One commenter suggested
that all pre-construction notifications
requesting a waiver of the 300 linear
foot limit should be coordinated with
the Federal and state resource agencies.
For those losses of more than 300
linear feet of intermittent and ephemeral
stream bed that result in minimal
adverse effects on the aquatic
environment, it is appropriate for
district engineers to have the authority
to waive the 300 linear foot limit. This
approach is consistent with the
statutory requirement that activities
authorized by general permits,
including NWPs, result in minimal
individual and cumulative adverse
environmental effects. Agency
coordination is required for proposed
PO 00000
Frm 00058
Fmt 4701
Sfmt 4703
losses of greater than 300 linear feet of
intermittent and ephemeral stream bed.
Two commenters recommended
adding a provision to this NWP that
requires the removal of structures
associated with any activity authorized
under this NWP, once the pilot project
has been completed. One commenter
suggested adding more examples of
attendant features that may be
authorized by this NWP, such as control
rooms, trailers, vaults and sheds since
these are common features of land-based
distribution facilities.
We have added a paragraph to this
NWP that requires the permittee to
remove the generation units,
transmission lines, and other structures
or fills associated with the pilot project
once the pilot project is completed,
unless they are authorized by a separate
Department of the Army authorization,
such as another NWP, an individual
permit, or a regional general permit.
Pilot units may be integrated into a
permanent water-based renewable
energy generation facility after the
experimental phase has been completed,
and the permanent facility has been
authorized by any required Department
of the Army permits. We have also
added ‘‘removal’’ to the first sentence of
this NWP, to clarify that the NWP also
authorizes the removal of structures and
fills associated with water-based
renewable energy generation pilot
projects, if, for example, the removal of
structures or fills from navigable waters
of the United States would require
authorization under Section 10 of the
Rivers and Harbors Act of 1899.
Furthermore, we added a clarification of
‘‘completion of the pilot project,’’ which
will be identified as the date of
expiration of the FERC (Federal Energy
Regulatory Commission) license, or the
expiration date of the NWP
authorization if no FERC license is
issued. If the project proponent wants to
continue operating the pilot project after
the expiration of the FERC license, he or
she should apply for another form of DA
permit, such as an individual permit. If
the pilot project was only authorized by
NWP 52, it may be verified under a
reissued NWP 52, if NWP 52 is reissued
in 2017. Reauthorization under a
reissued NWP 52 may require
submission of a new pre-construction
notification, to ensure that the pilot
project still meets the terms and
conditions of the reissued NWP 52. We
have added ‘‘control facilities’’ to the
list of examples of attendant features.
One commenter recommended adding
a note to the NWP to require a mutual
agreement between the Corps, the
United States Coast Guard, and a
prospective permittee to ensure
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
navigational safety. One commenter
stated that the NWP should include a
provision requiring compliance with
state permit requirements to ensure a
consistent and thorough environmental
review. One commenter said that this
NWP should require project proponents
to comply with the Department of the
Interior’s suggested practices for avian
protection to protect birds from
electrocution.
We do not agree that it is necessary
to require the execution of agreements
between the Corps, United States Coast
Guard, and the prospective permittee to
ensure navigation safety. District
engineers will review pre-construction
notifications and exercise discretionary
authority if the proposed activity will
have more than minimal adverse effects
on navigation. The permittee must
comply with applicable United States
Coast Guard requirements to mark or
light structures in navigable waters. It is
the permittee’s responsibility to obtain
any other Federal, state, or local
authorizations that may be required for
the water-based renewable energy
generation pilot project. The permittee
may voluntarily incorporate into his or
her project the Department of the
Interior’s recommended practices for
protecting birds from electrocution. If
the proposed NWP activity may affect
endangered or threatened bird species,
Endangered Species Act Section 7
consultation will be conducted, which
may also address potential effects to
those species caused by electrocution.
In accordance with general condition
19, migratory birds and bald and golden
eagles, it is the permittee’s
responsibility to obtain any ‘‘take’’
permits that may be required under the
U.S. Fish and Wildlife Service’s
regulations governing compliance with
the Migratory Bird Treaty Act and the
Bald and Golden Eagle Protection Act.
One commenter said that this NWP
could be used to authorize activities
associated with wind energy generating
structures, solar towers, or overhead
transmission lines, which have the
potential to interfere with Department of
Defense’s long range surveillance,
homeland defense, testing, and training
missions. This commenter requested
that copies of pre-construction
notifications and NWP verification
letters for these activities be provided to
the Department of Defense Siting
Clearinghouse, so that the Department
of Defense could have an opportunity to
coordinate with the project proponent to
ensure that long range surveillance,
homeland defense, testing, and training
missions are not adversely affected by
these activities.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
We have added Note 4 to this NWP
to require district engineers to send preconstruction notifications and NWP
verification letters to the Department of
Defense Siting Clearinghouse if this
NWP is proposed to be used to
authorize the construction of wind
energy generating structures, solar
towers, or overhead transmission lines.
The Department of Defense Siting
Clearinghouse is responsible for
coordinating with the project proponent
and resolving any potential effects on
Department of Defense long range
surveillance, homeland defense, testing,
and training missions.
Proposed NWP B is issued as NWP
52, with the changes discussed above.
General Conditions
One commenter suggested reordering
the general conditions to better
aggregate concepts based on importance
to permittees and the resources
potentially affected. One commenter
recommended placing general
conditions 14 and 20 together because
they both address cultural resources.
One commenter said that proposed
general condition 30, pre-construction
notification, should become general
condition 1 because of its importance
for potential users of the NWPs, in terms
of the pre-construction notification
requirements.
With one exception, we have retained
the order of the general conditions
because we believe they are in a logical
order. We have moved proposed general
condition 14, discovery of previously
unknown remains and artifacts, to
become general condition 21 so that it
follows general condition 20, historic
properties. We have retained the preconstruction notification general
condition in its place as the last general
condition (as general condition 31),
because the text of the NWPs state
which activities require preconstruction notification.
Two commenters suggested new
general conditions to minimize
construction impacts. One suggestion
was to require flagging construction
limits to protect nearby aquatic areas
and the other recommended a general
condition to address temporary
crossings or structures.
Requirements to flag construction
limits are more appropriately addressed
through activity-specific conditions
added to an NWP authorization, when
the district engineer determines such
flagging is necessary to ensure the
authorized activity results in minimal
adverse effects on the aquatic
environment. General condition 13,
removal of temporary fills, and general
condition 9, management of water
PO 00000
Frm 00059
Fmt 4701
Sfmt 4703
10241
flows, adequately address the concerns
about temporary crossings and
structures.
One commenter said the phrase ‘‘as
appropriate’’ should be deleted from the
Note at the beginning of Section C,
Nationwide Permit General Conditions.
We have changed this phrase to ‘‘as
applicable’’ to clarify that a permittee is
responsible for complying with general
conditions that are pertinent to a
particular NWP activity.
Comments on Specific General
Conditions
GC 1. Navigation. We did not propose
any changes to this general condition
and no comments were received. The
general condition is adopted as
proposed.
GC 2. Aquatic Life Movements. We
proposed to modify this general
condition to provide added protection
to the aquatic environment by
promoting the use of bottomless
culverts, when it is practicable to use
those types of culverts to maintain
movements of aquatic organisms.
Two commenters supported the
proposed changes to this general
condition. One commenter said that all
crossings should be designed by using a
stream simulation technique. Another
commenter stated that requirements for
bottomless culverts should only apply
to new activities. Many commenters
said that culverts that are installed with
their bottoms below the grade of the
stream bed can be as effective as
bottomless culverts in improving
conditions for aquatic life movement
while still being cost effective and
providing the intended function of
allowing movement of aquatic
organisms.
Many commenters objected to the
proposed changes to this general
condition, and most of these
commenters requested that the reference
to the use of bottomless culverts be
removed, stating that in many cases that
bottomless culverts are not practicable
or cannot be used in many locations. A
large number of commenters expressed
concern that requiring the use of
bottomless culverts would significantly
increase costs and would not be
feasible. Several commenters disagreed
that the use of bottomless or buried
culverts reduces overall impacts to
streams, and some commenters said that
use of bottomless culverts can cause
adverse effects to streams by increasing
erosion and head cuts. One commenter
recommended promoting the use of
alternative measures or techniques to
maintain aquatic life movements. Some
commenters said that the proposed
changes to this general condition would
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10242
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
result in all affected activities requiring
pre-construction notification.
After evaluating the large number of
comments received in response to the
proposed changes to this general
condition, we have generally reverted
back to the text that was in the 2007
general condition, with a few minor
changes. We have modified the last
sentence of the 2007 general condition
to make it clear that the general
condition applies to both temporary and
permanent crossings, and that those
crossings should be designed and
constructed to maintain low flows to
sustain the movement of indigenous
aquatic species. We have not adopted
the provision that would have required
bottomless culverts to be used where
practicable. In addition, we have not
incorporated the sentence that explains
some of the circumstances where
bottomless culverts may not be
practicable. In response to a preconstruction notification, the district
engineer may evaluate the proposed
crossing to determine whether it
complies with this general condition.
The district engineer may add
conditions to the NWP authorization to
require measures to sustain aquatic life
movements, including bottomless
culverts, if appropriate.
Many commenters said that
bottomless culverts require complex
designs that require pile supported
footings and many local and county
governments do not have the resources
available to design, construct, and
maintain bottomless culverts in a
manner that ensures roadway safety.
Many commenters stated that
bottomless culverts need more longterm maintenance and will increase
costs and delays. One commenter noted
that construction techniques required to
install bottomless culverts may result in
unsuitable conditions for aquatic life
movement. Several commenters
expressed concern that footings may
deteriorate and undermine the integrity
of the structure and increase the
possibility of collapse during high flow
conditions. Several commenters said
bottomless culverts cannot be installed
in areas with highly erodible or weak
soils. One commenter asserted that
bottomless culverts generally cannot
support load conditions created by rail
traffic.
Because of the various factors that
determine appropriate culvert designs
for a particular waterbody, we are not
adopting the proposed language
concerning bottomless culverts. The
general condition requires permanent
and temporary crossings to be suitably
culverted, bridged, or otherwise
designed and constructed to fulfill the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
objective of the general condition,
which is to sustain the movements of
aquatic species indigenous to the
waterbody, both during and after
completion of the activity.
Several commenters stated that
requiring bottomless culverts or bottoms
of culverts to be below the grade of the
stream bed restricts design flexibility
that reflects site specific conditions.
One commenter said it is not practicable
to install the bottoms of culverts below
grade in all circumstances. One
commenter said that the appropriate
structure to allow aquatic life
movements to continue should be
determined by considering the land
cover within the watershed, the
variability of stream flow, and the
presence or absence of aquatic life. One
commenter indicated that it is not
possible to bury pre-cast culverts
because the bed material would be
difficult to place. This commenter also
said that below grade structures collect
more debris and increase erosion on the
downstream side of the culvert. This
commenter expressed concern that
culvert bottoms installed below grade
would cause water to pool and provide
habitat for pests such as mosquitoes.
One commenter said that below grade
culverts direct high velocity flows and
create scour holes at the outlet and
destabilize the banks. Another
commenter stated that sinking a culvert
below grade drains land used for row
crops and accumulates silt that blocks
aquatic life movements.
We have also removed the provision
requiring the bottoms of culverts to be
installed below the grade of the stream
bed unless the stream bed consists of
bedrock or boulders. The modified
general condition merely states that
permanent and temporary crossings of
waterbodies must be suitably culverted,
bridged, or otherwise designed or
constructed, to provide flexibility for
using a crossing that is appropriate for
the site conditions, while sustaining the
movements of aquatic species
indigenous to the waterbody.
Many commenters said that the use of
bottomless culverts should be limited to
perennial streams. A number of
commenters stated that many ephemeral
and intermittent streams are not capable
of supporting aquatic life or do not have
sufficient aquatic life movement to
justify the expense and technical design
requirements for bottomless culverts.
Several commenters said this general
condition should not apply to
ephemeral streams. One commenter
stated that bottomless culverts should
only be used in waters that support
special status aquatic life species. One
commenter said the bottomless culvert
PO 00000
Frm 00060
Fmt 4701
Sfmt 4703
requirement should be limited to
streams and not required for ditches or
other waters. Another commenter
expressed concern that installing the
bottom of the culvert below grade will
tend to dewater wetlands.
The general condition has been
reworded to provide flexibility to
determine appropriate culvert design
based on site-specific characteristics.
Crossings of perennial, intermittent, and
ephemeral streams must be
appropriately designed and constructed
to sustain the movement of indigenous
aquatic species.
Many commenters requested a
definition of the term ‘‘practicable’’ as
used in the context of the proposed
general condition. One commenter said
that regional variability should be
considered when determining if it is
practicable to use a bottomless culvert.
Several commenters asked for more
examples of when it would be
impractical to use a bottomless culvert.
One commenter requested clarification
as to who would determine if use of a
bottomless culvert is practicable. Many
commenters said cost should be a
primary factor used to determine if it is
practicable to use a bottomless culvert.
One commenter stated that there would
be additional paperwork requirements
necessary to evaluate the practicability
of using bottomless culverts.
The proposed provision requiring the
use of bottomless culverts where
practicable has not been adopted into
the final general condition. The term
‘‘practicable’’ is defined in the 404(b)(1)
Guidelines at 40 CFR 230.3(q) as
‘‘available and capable of being done
after taking into consideration cost,
existing technology, and logistics in
light of overall project purposes.’’
However, it is no longer used in this
general condition.
One commenter said the general
condition should include criteria to be
used to determine whether there is a
substantial disruption to aquatic life
movement. Two commenters asked
what threshold would be used to
identify a substantial disruption.
Another commenter stated that the
general condition should list the species
that would be covered. One commenter
said this general condition would not
sustain aquatic life movements during
future high flows that are expected as a
result of global climate change.
Determining compliance with this
general condition is at the discretion of
the district engineer. It is not possible to
define, on a national basis, what
constitutes a substantial disruption of
the necessary life cycle movements of
aquatic species indigenous to the
waterbody. It is not appropriate to
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
provide a national list of such species,
but this condition generally applies to
all indigenous species in the waterbody
whose life-cycle movement may be
affected by the project. How global
climate change might affect the flow
patterns and volumes of particular
streams, rivers, or other waterbodies
cannot be predicted with a reasonable
degree of certainty. Crossing designs
should be based on present conditions,
and the crossing may be modified at a
later time to accommodate changes in
flow patterns and volumes that occur as
environmental conditions change.
One commenter stated that additional
requirements for proper culvert sizing
should be added to this general
condition to ensure fish passage and
reduce failure. This commenter said that
natural bankfull capacity of the stream
channel should be maintained. One
commenter also recommended that
culverts have a width of 1.2 times the
bankfull width of the stream, and be
embedded a minimum of two feet to
maintain connected habitat and a stable
stream bed. Another commenter stated
that stream crossings should maintain
natural flows, substrate, and stream
grade from upstream to downstream of
the culvert. This commenter suggested
adding a provision that states that
bridges or bottomless culverts are to be
used when practicable.
The proper sizing of culverts is more
appropriately addressed through an
evaluation of the site for the proposed
NWP activity and the surrounding area.
The general condition focuses on
maintaining the necessary life cycle
movements of aquatic species
indigenous to the waterbody, not the
geomorphic characteristics of the
waterbody. Maintenance of water flows,
including the proper width and height
of culverts, bridges, and other crossings,
is more appropriately addressed by
general condition 9, management of
water flows. We have modified this
general condition to require permanent
and temporary crossings to be suitably
culverted, bridged, or otherwise
designed and constructed to maintain
low flows to sustain the movement of
indigenous aquatic species.
Two commenters requested that, if the
proposed changes to this general
condition are adopted, sufficient time
should be provided for state, county,
and local governments to update their
design requirements to include
bottomless culverts. One commenter
stated it would take approximately two
years to develop standards for
bottomless and buried culvert
installation. Another commenter
expressed concern about the expense
and time required to revise the plans
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
and specifications for projects nearly
ready for construction.
We do not believe it is necessary to
provide a grandfathering provision for
the implementation of this general
condition. The general condition
provides substantial flexibility to design
permanent and temporary crossings,
and uses a results-driven approach to
help ensure that NWP activities have
only minimal adverse effects on the
movement of indigenous species of
aquatic organisms. Existing construction
and design standards can be used to
satisfy the objective of this general
condition.
The general condition is adopted with
the modifications discussed above.
GC 3. Spawning Areas. We did not
propose any changes to this general
condition. One commenter said this
general condition should be removed,
and replaced with regional conditions
that require buffers for spawning areas.
This commenter reasoned that local
buffer requirements would be more
appropriate for satisfying the
requirements of the Endangered Species
Act. Two commenters stated that only
requiring avoidance of spawning areas
to the maximum extent practicable is
not sufficient, and one of those
commenters said that the destruction of
spawning areas should not be allowed
under any circumstances. One
commenter recommended modifying
this general condition to prohibit
activities that adversely affected all
spawning areas. One commenter
suggested explicitly including forage
fish habitat and submerged aquatic
vegetation as protected resources in this
general condition.
We are retaining this general
condition because spawning areas are
important components of the aquatic
environment and should be addressed at
the national level to ensure that NWP
activities result in minimal adverse
effects on the aquatic environment.
Division engineers may impose regional
conditions on this NWP to establish
buffers to protect spawning areas for
particular species. Activities authorized
by NWPs must also comply with general
condition 18, endangered species. The
intent of this general condition is to
minimize adverse effects to spawning
areas caused by NWP activities, and it
is not feasible to completely prohibit
activities that may affect spawning
areas. In areas where there are
documented concerns for fish forage
habitat or submerged aquatic vegetation,
division engineers can add regional
conditions to the NWPs to restrict or
prohibit activities in those areas.
This general condition is adopted as
proposed.
PO 00000
Frm 00061
Fmt 4701
Sfmt 4703
10243
GC 4. Migratory Bird Breeding Areas.
We did not propose any changes to this
general condition. One commenter said
this general condition should be
removed and regional conditions should
be used instead to establish buffers for
migratory bird breeding areas. This
commenter also stated that the
requirement that NWP activities avoid
breeding areas for migratory birds to the
maximum extent practicable is not
sufficient to protect those areas. One
commenter said buffers established
through regional conditions would
satisfy Endangered Species Act
requirements more effectively.
This general condition addresses a
national concern for breeding areas for
migratory birds, and establishes a
consistent, national requirement for
regulated activities to avoid these areas
to the maximum extent practicable.
Nationwide permit activities that may
affect migratory birds that are listed as
endangered or threatened under the
Endangered Species Act, or that may
affect designated critical habitat, must
comply with general condition 18,
endangered species.
This general condition is adopted as
proposed.
GC 5. Shellfish Beds. We did not
propose any changes to this general
condition. One commenter said the term
‘‘concentrated shellfish populations’’
should be defined to specify a method
to be used to identify such areas,
because in some states shellfish beds are
prominent features in waterways.
Another commenter suggested changing
the text of the general condition to state
that shellfish beds created as habitat
cannot be used for harvesting, and
NWPs 4 and 48 could not authorize
activities in those areas. One commenter
recommended adding restoration
projects authorized by NWP 27 to this
general condition.
The identification of concentrated
shellfish populations for the purposes of
determining compliance with this
general condition is more appropriately
conducted by district engineers using
local criteria and methods. Shellfish
beds established through habitat
restoration projects may be used for
growing shellfish for consumption and
other uses, and the decision on whether
harvesting in those areas should be
allowed is at the discretion of Federal,
state, and/or local authorities. We have
added shellfish seeding or habitat
restoration activities authorized by NWP
27 to the list of NWP activities that may
occur in areas of concentrated shellfish
populations, since NWP 27 activities
may improve habitat quality and further
increase shellfish populations.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10244
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
This general condition is adopted
with the modification discussed above.
GC 6. Suitable Material. We did not
propose any changes to this general
condition. One commenter
recommended that this general
condition should explicitly prohibit the
use of tires as fill material, because tires
can leach toxic amounts of chemicals
that are harmful to aquatic species. One
commenter said the general condition
should be changed so that only
environmentally suitable or stable
material may be used as fill, because
many plastics are unstable when
exposed to ultraviolet light or
temperature changes. One commenter
stated that contaminated sediments
should not be used as fill material. One
commenter recommended modifying
this general condition to minimize
impacts to habitat and species caused by
the leaching of heavy metals, pesticides,
and polycyclic aromatic hydrocarbons.
We do not believe it is necessary to
add tires or plastics to the list of
examples of unsuitable materials.
Prohibiting the use of unsuitable
materials is more effective and
enforceable than stating that only
environmental suitable or stable
materials may be used. It is impractical,
for the purposes of the NWP program,
to establish what would constitute an
environmentally suitable material since
we are not aware of any Federal
standards that could be applied, other
than those covered under Section 307 of
the Clean Water Act. A similar problem
exists for identifying stable materials,
because the timeframe that might be
used to determine whether a particular
material is ‘‘stable’’ would vary by the
material. The district engineer will
make a case-by-case determination of
what constitutes unsuitable material.
The current text of the general condition
prohibits the use of contaminated
sediment as fill material, if it contains
toxic pollutants in toxic amounts. The
general condition also prohibits the use
of materials that contain heavy metals,
pesticides, and polycyclic aromatic
hydrocarbons in toxic amounts, in
accordance with Section 307 of the
Clean Water Act.
This general condition is adopted as
proposed.
GC 7. Water Supply Intakes. We did
not propose any changes to this general
condition and no comments were
received. The general condition is
adopted as proposed.
GC 8. Adverse Effects from
Impoundments. We did not propose any
changes to this general condition. One
commenter said the general condition
should include specific examples of
how to reduce impacts associated with
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
accelerating passage of water and how
to prevent the restriction of normal
water flows. Another commenter asked
for a definition for the term ‘‘maximum
extent practicable.’’ Two commenters
stated that impoundments that cause
adverse effects to the aquatic
environment by changing water flows
should not be authorized by NWPs and
should instead require individual
permits with agency coordination.
Specific measures for reducing
impacts caused by accelerated water
flows or restricted water flows have to
be determined on a case-by-case basis
after considering the environmental
characteristics of the site of the NWP
activity. It would not be appropriate to
establish such measures at a national
level. An activity-specific evaluation
would also have to be done to determine
whether the minimization of these
adverse effects has been accomplished
to the maximum extent practicable.
District engineers will use their
discretion to determine compliance
with this general condition. The term
‘‘practicable’’ is defined in the 404(b)(1)
Guidelines at 40 CFR 230.3(q) as
‘‘available and capable of being done
after taking into consideration cost,
existing technology, and logistics in
light of overall project purposes.’’ We do
not agree that all impoundments should
require individual permits;
impoundments may be authorized by
general permits, including NWPs, as
long as they have minimal individual
and cumulative adverse effects on the
aquatic environment and comply with
the applicable terms and conditions,
including any general conditions,
regional conditions, and activityspecific conditions, of an NWP
authorization.
This general condition is adopted as
proposed.
GC 9. Management of Water Flows.
We did not propose any changes to this
general condition. One commenter
asked for a definition of the term
‘‘expected high flows’’ and said the
possibility of high flow events should be
anticipated during project
implementation. One commenter stated
that this general condition should be
modified to prohibit changes to stream
channels in intertidal areas. One
commenter stated that shoreline
structures and fills, such as seawalls,
bulkheads, and revetments, reflect wave
energy that causes deep scouring of the
shore, and over-steepened local shore
faces. These induced hydraulic effects
substantially alter the flow patterns in
intertidal features such as ocean and
estuarine beaches, wetlands and
mudflats.
PO 00000
Frm 00062
Fmt 4701
Sfmt 4703
It would be inappropriate to attempt
to define the term ‘‘expected high
flows’’ since it would depend on the
environmental setting of the NWP
activity. To comply with this general
condition, the activity should not be
substantially damaged by an expected
high flow. Activities in stream channels
located in intertidal areas are subject to
this general condition and if a proposed
NWP activity involves the alteration of
intertidal stream channels and requires
pre-construction notification, the
district engineer will evaluate the
proposed activity and determine
whether it will result in minimal
adverse effects on the aquatic
environment. Bank stabilization
activities should be designed and
constructed to withstand expected high
flows. Adverse effects to littoral or
fluvial processes, or adverse effects
caused by deflections of wave energy,
should be considered by district
engineers when evaluating preconstruction notifications for proposed
bank stabilization activities.
This general condition is adopted
without change.
GC 10. Fills Within 100-Year
Floodplains. We did not propose any
changes to this general condition.
Several commenters explained the
benefits of fully functional natural
floodplains. Most of the commenters
seemed to indicate that the Corps has
regulatory jurisdiction over non-wetland
floodplains. Several commenters
objected to the general condition simply
requiring compliance with Federal
Emergency Management Agency
(FEMA) approved state or local
floodplain management requirements.
Several commenters said that fills in
floodplains identified by state or local
FEMA-approved floodplain maps
should only be authorized by individual
permits, to ensure that state or local
floodplain managers are aware of these
activities. Two commenters stated that
FEMA-approved standards are designed
to ensure the public is reasonably safe
from flooding, but these standards
provide insufficient protection to
waterways, floodplains, and other
aquatic resources. One commenter said
the Corps has an independent obligation
to protect waters of the United States
and this obligation extends to protection
of floodplain resources.
We acknowledge that floodplains
provide important ecological functions
and services, but it must also be
understood that most areas within 100year floodplains are not subject to Clean
Water Act jurisdiction, because a large
proportion of the area within 100-year
floodplains consists of uplands. The
Corps regulatory authority in 100-year
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
floodplains is usually limited to
discharges of dredged or fill material
into waters of the United States,
including jurisdictional wetlands. The
protection of floodplains is more
appropriately addressed through land
use planning and zoning, which is
primarily the responsibility of state and
local governments, as well as tribal
governments. Land use planning and
zoning can provide the holistic
approach needed to protect floodplain
functions and services, reduce economic
losses through flood damage reduction,
and protect human health and welfare.
If state, local, or tribal governments have
zoned areas of 100-year floodplains for
residential developments or other uses,
and if those activities involve discharges
of dredged or fill material into waters of
the United States and meet the terms
and conditions of an applicable NWP,
and the NWP activity results in minimal
adverse effects on the aquatic
environment or other relevant public
interest review factors, then
authorization by NWP is appropriate.
This general condition also recognizes
that FEMA, in partnership with state
and local governments, is the more
appropriate authority for floodplain
management. It is not the responsibility
of the Corps to ensure that project
proponents seek any required
authorizations from state or local
floodplain managers. Such a
requirement would not constitute a
condition that could be enforced by the
Corps. We are not relying on FEMAapproved state or local floodplain
management requirements to protect
waters of the United States located in
100-year floodplains. The NWP program
utilizes other tools, such as regional
conditions, the district engineer’s ability
to exercise discretionary authority to
revoke, suspend, or modify an NWP
authorization, and add activity-specific
conditions to ensure that activities
authorized by the NWP results in
minimal individual and cumulative
adverse effects on the aquatic
environment and other public interest
review factors.
Two commenters stated that fills in
100-year floodplains result in more than
minimal adverse environmental effects
and should not be authorized by NWP.
One commenter suggested that the
Corps evaluate NWP activities in
floodplains and riparian areas in a more
holistic manner than it did in previous
NWP rulemaking efforts. One
commenter said that authorizing
discharges of fill material in waters of
the United States in floodplains affects
the ability to manage floodplains so that
there are no adverse impacts. One
commenter stated that coordination
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
with the resource agencies should be
required to protect habitat and
biodiversity in floodplains.
Discharges of dredged or fill material
into waters of the United States located
in 100-year floodplains often have
minimal adverse effects on the aquatic
environment, individually and
cumulatively. Division engineers can
impose regional conditions on one or
more NWPs to restrict or prohibit their
use in waters of the United States
within 100-year floodplains if those
NWP activities would result in more
that minimal adverse effects on the
aquatic environment. In response to a
pre-construction notification, district
engineers may exercise discretionary
authority and require an individual
permit if the adverse effects on the
aquatic environment would be more
than minimal. District engineers may
also add activity-specific conditions to
an NWP authorization to require
measures to minimize adverse effects on
the aquatic environment caused by
NWP activities. Since the Corps
Regulatory Program only regulates
discharges of dredged or fill material
into waters of the United States and
structures or work in navigable waters
of the United States, and most areas of
100-year floodplains are not wetlands as
defined at 33 CFR 328.3(b) or otherwise
waters of the United States under 33
CFR 328.3(a) and associated guidance,
the Corps does not have the authority to
take a holistic approach to floodplain
management. In areas of the country
where 100-year floodplains consist
mostly of uplands, construction
activities in these uplands may have a
substantial adverse impact on these 100year floodplains. We do not agree that
agency coordination should be required
for fills in 100-year floodplains, because
district engineers have the necessary
expertise to evaluate pre-construction
notifications for potential adverse
effects to habitat and biodiversity in
these areas.
Two commenters said the general
condition should inform permittees of
their responsibility to apply for a
Conditional Letter of Map Revision from
FEMA if they are discharging dredged or
fill material into waters of the United
States within 100-year floodplains. One
commenter recognized that although
proposed development projects must
comply with all applicable Federal,
state, regional and local regulatory
requirements, many project proponents
do not apply for all required permits.
One commenter said that this general
condition should be modified to require
documentation of compliance with
applicable FEMA-approved state or
local floodplain management
PO 00000
Frm 00063
Fmt 4701
Sfmt 4703
10245
requirements. One commenter stated
that FEMA-approved state or local
floodplain management requirements do
not adequately protect communities and
resources from flood risks.
We do not believe it is the Corps
responsibility to notify a prospective
permittee of his or her responsibility to
apply for a Conditional Letter of Map
Revision from FEMA if the overall
project would modify the existing
regulatory floodway, the effective base
flood elevations, or a special flood
hazard area. The discharge of dredged or
fill material authorized by NWP is likely
to be only a small proportion of the
overall construction project within the
100-year floodplain. Section E, Further
Information, states that obtaining an
NWP authorization does not obviate the
need to obtain other Federal, state, or
local permits, approvals, or
authorizations required by law. Building
permits to authorize the construction of
the overall project are the responsibility
of the state or local government, and
should be based on compliance with the
applicable FEMA-approved state or
local floodplain management
requirements. It is not the Corps
responsibility to ensure that project
proponents have complied with the
applicable FEMA-approved state or
local floodplain management
requirements; the state or local
governments responsible for floodplain
management should enforce the
requirements they established to qualify
the community for the National Flood
Insurance Program. If the floodplain
management requirements developed by
state or local governments are not
adequately protecting communities from
flood risks, then the agency that
approved those requirements is the
appropriate entity to reexamine those
requirements.
One commenter requested that the
Corps report the extent to which NWPs
are being used in floodplains,
particularly in areas that have
experienced repeated flood damages.
Two commenters stated that this general
condition ignores the Corps own public
interest review processes and does not
comply with Executive Order 11988.
The Corps does not track the number
of NWP activities that have occurred in
floodplains, since our statutory
authorities are focused on activities
involving discharges of dredged or fill
material into waters of the United States
and/or structures or work in navigable
waters of the United States. As stated
above, many areas of 100-year
floodplains are uplands and not waters
of the United States. In addition, there
is no consistent national coverage in
floodplain maps, since such maps are
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10246
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
either not available for some areas of the
country or the existing maps are
outdated. This general condition is
consistent with our regulations on the
public interest review, specifically 33
CFR 320.4(g), consideration of property
ownership, 33 CFR 320.4(j), other
Federal, state, or local requirements,
and 33 CFR 320.4(l), floodplain
management. Section 320.4(g)(1) states
that an ‘‘inherent aspect of property
ownership is the right to reasonable
private use.’’ Section 320.4(j)(2) states
that the primary responsibility for land
use planning and zoning is with state
and local governments. Section 320.4(l)
requires consideration of whether
practicable alternatives to floodplain
development are available, and if there
are no practicable alternatives, then
impacts to human health, safety, and
welfare, risks of flood losses, and
impacts to natural and beneficial
aspects of floodplains should be
minimized to the maximum extent
practicable. This NWP general
condition, as well as the other terms and
conditions of the NWPs, such as the
acreage and linear foot limits for losses
of waters of the United States, are
consistent with the principles in these
regulations because they require
avoidance and minimization of adverse
effects on the aquatic environment.
Executive Order 11988 states that
Federal agencies are to consider
alternatives to ‘‘avoid adverse effects’’ to
floodplains, and ‘‘minimize potential
harm to or within the floodplain’’. The
Executive Order also says that agencies
should also consider flood hazards in
the permit programs they administer.
The adoption of general condition 10
into the NWP program is consistent
with Executive Order 11988. It is also
consistent with Executive Order 13132,
Federalism, because it recognizes the
cooperative approach the Federal
government has taken with state and
local governments for floodplain
management (i.e., federal review, by
FEMA, of state or local floodplain
management requirements).
Two commenters suggested
reinstating the provisions in the 2002
NWPs that prohibited discharges of
dredged or fill material into waters of
the United States within mapped 100year floodplains that would result in
above-grade fills for residential,
commercial and institutional
developments, agriculture activities,
recreational facilities, stormwater
management facilities, and mining
activities.
We do not agree that the approach
taken in the 2002 NWPs for fills in 100year floodplains should be reinstated.
There are sufficient safeguards in the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
NWPs, including the terms and
conditions, pre-construction notification
requirements, and the authority for
district engineers to exercise
discretionary authority and either
require individual permits or add
conditions to NWP authorizations, to
ensure that NWP activities have
minimal adverse effects on the aquatic
environment, including public interest
review factors such as floodplain values
and flood hazards.
Three commenters said that using
NWPs to authorize discharges of
dredged of fill material into waters of
the United States will result in
increased flood damages in coastal and
riparian areas by reducing the amount of
aquatic area available to absorb future
floods that will likely be larger and
more frequent due to climate change.
They suggested increasing the
application fee for NWPs to cover the
estimated cost of permit processing and
to offset future economic impacts of
authorizing floodplain development.
The flood storage capacity of a coastal
or inland floodplain is dependent
primarily on its topographic
characteristics, including the amount of
land area available for storing flood
waters. Uplands also provide important
ecological services such as flood storage.
Flood damage reduction is more
effectively accomplished through land
use planning and zoning, which as
discussed above, is primarily the
responsibility of state, local, and tribal
governments. Charging application fees
for NWP pre-construction notifications
or verification requests is not being
considered at this time.
This general condition is adopted as
proposed.
GC 11. Equipment. We did not
propose any changes to this general
condition. One commenter stated that
the condition should be changed to
include streams, and not be limited to
wetlands or mudflats.
The intent of this general condition is
to ensure that heavy equipment used in
special aquatic sites such as wetlands
and mudflats does not cause more than
minimal disturbances to their soils. The
substrate of stream beds is generally not
considered to be soil, and other general
conditions such as general condition 12,
soil and sediment controls, are more
appropriate to control the movement
and disturbance of stream bed
sediments. District engineers may also
add activity-specific conditions to NWP
authorizations, such as requirements to
use best management practices, to
minimize disturbances to stream beds.
This general condition is adopted as
proposed.
PO 00000
Frm 00064
Fmt 4701
Sfmt 4703
GC 12. Soil Erosion and Sediment
Controls. We did not propose any
changes to this general condition. One
commenter said the general condition
should provide specific steps that will
ensure protection of downstream water
quality during the construction of
permitted activities. Two commenters
suggested adding requirements to
prevent the erosion of sediments
resulting from harvesting shellfish. One
commenter stated that disturbed areas
should be stabilized and vegetated areas
should be restored to pre-construction
conditions or improved conditions.
Specific best management practices
and other measures to protect
downstream water quality are more
appropriately addressed by considering
the activity-specific environmental
setting and adopting practices and
measures that will control soil erosion
and sediment loads on the site of the
authorized activity. District engineers
may add conditions to the NWP
authorizations to require permittees to
use specific best management practices
or other techniques to minimize soil
erosion and reduce transport of
sediment to waters and wetlands. We do
not believe it is necessary to modify this
general condition to address sediment
movement that may occur during
shellfish harvesting activities, because
such movements are usually minor and
temporary and have minimal adverse
effects on the aquatic environment. The
restoration of areas where temporary
fills have been placed, including
revegetating those areas, is more
appropriately addressed by general
condition 13, removal of temporary fills.
This general condition is adopted
without change.
GC 13. Removal of Temporary Fills.
We did not propose any changes to this
general condition. One commenter said
the general condition should require the
removal of temporary fills during
periods of low-flow or no-flow so that
there will be little or no downstream
transport of the fill material.
It would be inappropriate to require
that temporary fills be removed only
during periods of low-flow or no-flow
because it is not always practicable to
wait until water flows are low or absent.
In addition, more adverse effects to the
aquatic environment may occur if the
permittee is required to wait until low
flow or no flow conditions exist. It is
usually best to remove temporary fills as
soon as possible to minimize sediment
loads to downstream waters or to nearby
wetlands. However, general condition
12, soil erosion and sediment controls,
encourages permittees to work in waters
of the United States during periods of
low or no flow, when possible.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
This general condition is adopted as
proposed.
GC 14. Proper Maintenance. We did
not propose any changes to this general
condition. One commenter
recommended changing the general
condition to ensure that maintenance
activities minimize impacts to waters
and maintain downstream water quality.
Another commenter suggested adding a
provision that would require proper
maintenance to ensure compliance with
applicable NWP general conditions as
well as conditions added to an NWP
verification.
The original intent of this general
condition was to ensure that NWP
activities are maintained so that they do
not endanger public safety. There are
other general conditions that more
directly address minimization (e.g.,
general condition 23, mitigation) and
water quality (e.g., general condition 12,
soil erosion and sediment controls, and
general condition 25, water quality). We
agree that proper maintenance should
also be required to comply with the
terms and conditions of an NWP
authorization, including any activityspecific conditions added to an NWP
authorization by the district engineer.
For example, road crossings should be
properly maintained to continue
complying with general condition 2,
aquatic life movements.
This general condition is adopted
with the change discussed above.
GC 15. Single and Complete Project.
We did not propose any changes to this
general condition. Two commenters
recommend removing the term single
and complete project. Two commenters
said the definition of ‘‘single and
complete project’’ is flawed and that the
acreage limit of an NWP should apply
to the entire project, not just each single
and complete project. One commenter
suggested changing the general
condition to state that an NWP activity
cannot be expanded or modified at a
later date. Two commenters said the
general condition may allow
piecemealing under the NWPs.
It has been a long-standing principle
in the NWP program that the NWPs
authorize single and complete projects.
This general condition was added to the
NWPs in 2007 to make that clear to
users of the NWPs. The general
condition is consistent with the NWP
regulations at 33 CFR part 330 that were
last revised in 1991, especially the
definition at 33 CFR 330.2(i). Some of
the NWPs issued in the past included
terms and conditions stating the NWP
authorized single and complete projects.
In 2007, we added a general condition
to make it clear that all NWPs authorize
single and complete projects. As long as
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
any proposed expansions or
modifications of a previously authorized
NWP activity comply with the terms of
the NWPs, they can be authorized by
NWP. Expansions or modifications that
are not separate single and complete
projects from the previously authorized
activity have to comply with the terms
and conditions of the NWP, including
any acreage or linear foot limits that
would apply to both the previously
authorized activity and the NWP
activity included in the expansion or
modification. If the expansion or
modification is determined by the
district engineer to be a separate single
and complete project, then that
expansion or modification activity may
qualify for separate NWP authorization.
We do not agree that this general
condition results in piecemealing,
because the NWP authorization applies
to each single and complete project.
District engineers will exercise
discretionary authority and require
other forms of Department of the Army
authorization if the use of the NWP to
authorize activities in a watershed or
other geographic area will result in more
than minimal cumulative adverse effects
on the aquatic environment.
This general condition is adopted
without change.
GC 16. Wild and Scenic Rivers. We
proposed to modify this general
condition to clarify that information on
these rivers should be obtained from the
specific Federal land management
agency responsible for the designated
Wild and Scenic River or study river.
One commenter supported reissuing the
general condition.
The general condition is adopted as
proposed.
GC 17. Tribal Rights. We did not
propose any changes to this general
condition. One commenter stated that
the use of the NWPs will be in violation
of tribal treaty rights, tribal water
quality standards, and the Clean Water
Act, and threaten salmon recovery
efforts in the Pacific Northwest.
Division engineers may impose
regional conditions on the NWPs to
restrict or prohibit their use in waters
where NWP activities may result in
more than minimal adverse effects on
the aquatic environment or any other
public interest review factor, including
fish and wildlife values. We have
directed our districts to initiate
government-to-government consultation
with Tribes to develop and propose
regional conditions to protect tribal
treaty resources and other resources of
importance to Tribes. Under this general
condition, no activity may be authorized
by NWP if it impairs reserved tribal
rights, such as reserved water rights or
PO 00000
Frm 00065
Fmt 4701
Sfmt 4703
10247
treaty fishing and hunting rights. The
regional conditioning process helps
identify those rights on a geographic
basis, so that prospective users of the
NWPs and Corps districts are aware of
those tribal rights. Nationwide permit
activities must also comply with Tribal
water quality standards, if those
activities involve discharges into waters
covered by Tribal water quality
standards. Activities authorized by
NWPs must also comply with general
condition 18, endangered species,
which will help support the recovery of
listed salmon species.
The general condition is adopted as
proposed.
GC 18. Endangered Species. We
proposed to modify paragraph (a) of this
general condition to clarify that both
direct and indirect effects are to be
taken into account when assessing
whether an activity may jeopardize the
continued existence of a threatened or
endangered species or a species
proposed for such designation, or
destroy or adversely modify the critical
habitat of such species. In addition, we
proposed to modify paragraph (e) to
include definitions of ‘‘take’’ and
‘‘harm.’’ Another proposed change was
to add a new paragraph (f) to provide
prospective permittees with guidance
on where they can obtain information
on the locations of listed species and
their critical habitat. One commenter
expressed support for the proposed
modifications.
Several commenters requested
clarification and definitions for the
terms ‘‘directly’’ and ‘‘indirectly’’ as
used in paragraph (a). In addition,
several commenters objected to the
addition of ‘‘indirectly’’ into the general
condition, because they believe only
direct effects should be considered.
Several commenters expressed concern
that this will result in the Corps
evaluating direct and indirect effects
that are far from the NWP activity.
To provide clarification on the use of
the terms ‘‘direct’’ and ‘‘indirect’’ in the
context of general condition 18 and the
NWPs in general, we are adding
definitions of ‘‘direct effects’’ and
‘‘indirect effects.’’ The definitions were
adapted from the definitions provided
in the Council of Environmental
Quality’s National Environmental Policy
Act regulations at 40 CFR 1508.8. The
definition of ‘‘indirect effect’’ is also
generally consistent with the Services’
definition within the definition of
‘‘effects of the action’’ at 50 CFR 402.02.
The addition of indirect effects to
paragraph (a) of the general condition is
consistent with the U.S. Fish and
Wildlife Service’s and National Marine
Fisheries Service’s Endangered Species
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10248
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Act Section 7 regulations for
considering whether a proposed activity
may jeopardize the continued existence
of a listed species or may result in the
destruction or adverse modification of
critical habitat (see the definitions of
‘‘destruction or adverse modification’’
and ‘‘jeopardize the continued existence
of’’ at 50 CFR 402.02). The Corps is
obligated by the section 7 consultation
regulations to consider indirect effects
caused by proposed NWP activities, and
appropriate distances for such indirect
effects will have to be determined on a
case-by-case basis by district engineers.
One commenter stated that the district
engineer should evaluate the
Endangered Species Act (ESA)
compliance documentation provided by
the Federal agency, and determine
whether or not it is sufficient to address
ESA compliance for the NWP activity,
or whether additional ESA consultation
is necessary. Two commenters
recommended modifying paragraph (b)
to clarify that documentation of
compliance with the Endangered
Species Act provided by a Federal
agency will be sufficient and that Corps
review and concurrence with that
section 7 consultation is not required.
One commenter said that paragraph (b)
should make it clear that a state agency
operating under federal funding can also
provide the section 7 compliance
documentation obtained by the Federal
agency that oversees its activities, and
not have to reinitiate consultation.
Another commenter stated that when a
non-Federal permittee is operating on
behalf of a Federal agency, they should
follow paragraph (b) of this general
condition instead of paragraph (c).
We have added a sentence to
paragraph (b) to state that the district
engineer will review the other Federal
agencies’ documentation of compliance
with the Endangered Species Act and
determine whether that compliance is
sufficient for the NWP activity, or
whether additional ESA consultation is
necessary before the activity can be
authorized by NWP. We believe this
provision is necessary to address
situations where the consultation
conducted by the other Federal agency
does not adequately cover the direct and
indirect effects on listed species or
designated critical habitat caused by the
NWP activity. For similar reasons, we
do not agree that it would be
appropriate to modify paragraph (b) to
explicitly state that state agencies may
rely on ESA compliance documentation
obtained by the Federal agency that
provides them with funding for an
activity. District engineers will generally
accept another Federal agency’s
compliance with section 7, but there
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
may be situations where that agency’s
section 7 compliance does not
adequately address the activities
authorized by an NWP and their effects
on listed species or designated critical
habitat. In those situations, the district
engineer may conduct additional
section 7 consultation to satisfy the
requirements of the Endangered Species
Act. If it is not sufficient, then the nonFederal permittee has to follow
paragraph (c) of this general condition
instead.
One commenter said that this general
condition places the responsibility for
determining whether a proposed
activity may affect listed species in the
hands of the permittee. One commenter
requested clarification on how the
‘‘might be affected’’ threshold in the
first sentence is to be determined by an
applicant, because it is unclear and
leaves room for broad interpretation.
One commenter stated that the word
‘‘might’’ in the second sentence of
paragraph (c) should be changed to
‘‘may.’’
It is the Corps’ responsibility to make
‘‘may affect’’ determinations for the
purposes of the ESA, and the ‘‘might be
affected’’ threshold is intended to be a
cautionary threshold to give district
engineers the opportunity to evaluate
proposed activities and make their effect
determinations. Prospective permittees
are required to submit pre-construction
notifications if the proposed NWP
activity has the potential to affect a
listed species, is in the vicinity of a
listed species, or is located in
designated critical habitat. If the Corps
determines there will be no effect on
listed species or designated critical
habitat, then ESA section 7 consultation
is not necessary. If the district engineer
determines there will be an effect that
requires ESA section 7 consultation,
then he or she will initiate either formal
or informal consultation with the U.S.
Fish and Wildlife Service and/or the
National Marine Fisheries Service, as
appropriate.
One commenter said paragraph (c)
should clearly state that a preconstruction notification is to be
submitted if any listed species or
designated critical habitat might be
affected or is in the vicinity of the
project, to ensure that another form of
notification is not used. Two
commenters stated that 30 days is
sufficient for the Corps to notify the
applicant of its ‘‘may affect’’
determination and asked why the
general condition allows 45 days. Two
commenters suggested modifying this
general condition to state that if the
prospective permittee does not receive a
response from the Corps within 45 days,
PO 00000
Frm 00066
Fmt 4701
Sfmt 4703
then he or she can assume that the
Corps has determined that there is ‘‘no
effect’’ on a listed species. In addition,
one of these commenters said that for
projects that ‘‘may affect’’ a listed
species, if the section 7 consultation is
not concluded within 135 calendar days
of initiation, the activity would be
authorized to proceed as if a ‘‘no effect’’
determination has been made.
We have modified the first sentence of
paragraph (c) to state that non-Federal
permittees must submit a preconstruction notification if the
notification requirement is triggered.
The 45-day period in paragraph (c) of
this general condition is intended to be
consistent with the 45-day review
period for pre-construction notifications
provided in paragraph (a) of general
condition 31, pre-construction
notification. Under paragraph (a) of
general condition 31, a prospective
permittee may not begin an NWP
activity that requires pre-construction
notification until he or she has been
notified in writing that the activity may
proceed under the NWP, or 45 calendar
days have passed since the district
engineer received a complete preconstruction notification and no written
notice has been provided to the
applicant by the district or division
engineer. However, if pre-construction
notification was required by paragraph
(c) of general condition 18, the
prospective permittee may not proceed
with the NWP activity until notified by
the Corps, even if the 45 calendar days
have passed, because the Corps
regulations at 33 CFR 330.4(f)(2) state
that NWP activities cannot commence
until the requirements of the ESA have
been satisfied and the district engineer
has notified the applicant that the
activity is authorized by NWP. It may
take more than 135 days to complete
section 7 consultation, and the NWP
activity may not proceed until after
consultation has been completed.
Two commenters requested
clarification on what work the
prospective permittee is prohibited from
conducting prior to the Corps making a
determination of ‘‘no effect’’ or until
section 7 consultation is completed.
Two commenters requested clarification
of the term ‘‘vicinity’’ in this general
condition.
The work covered by the general
condition and the Corps regulations at
33 CFR 330.2(f) depends on the scope of
analysis for the ESA section 7
consultation. The Corps follows the U.S.
Fish and Wildlife Service’s and National
Marine Fisheries Service’s regulations at
50 CFR part 402 and Endangered
Species Consultation Handbook to
determine the section 7 scope of
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
analysis. The scope of analysis includes
the direct and indirect effects of the
NWP activity, as well as the effects of
other activities that are interrelated and
interdependent with that activity (see 50
CFR 402.02). The section 7 scope of
analysis will be determined by district
engineers on a case-by-case basis.
Generally, the applicant cannot begin
any work for which a Department of the
Army permit is required until the
applicable ESA provisions have been
satisfied. The term ‘‘vicinity’’ cannot be
defined at a national level, since the
extent of the vicinity depends on a
variety of factors, including the species
that might be affected, the proposed
activity, and the environmental setting.
One commenter said pre-construction
notification should not be required for
NWP activities that require section 7
compliance, if they would not otherwise
require a pre-construction notification.
This commenter stated that the
prospective permittee should only be
required to submit the appropriate
documentation for section 7
consultation. One commenter stated that
this general condition should also apply
to state-listed threatened and
endangered species.
This general condition is consistent
with the NWP regulations at 33 CFR
330.4(f)(2), which requires the
prospective permittee to notify the
district engineer if any Federally-listed
endangered or threatened species, or
critical habitat, might be affected or is
in the vicinity of the project. The
prospective permittee must submit the
information required for a preconstruction notification, so that the
district engineer will have sufficient
information to commence evaluation of
the proposed activity and its effects on
listed species or critical habitat. It
would be inappropriate to expand the
scope of this general condition to cover
state-listed endangered and threatened
species, since that is a regional issue
that is best addressed through state laws
and regulations. If a state is concerned
about the potential impacts of one or
more NWPs on state-listed species, the
state may ask the Corps district to
consider adding regional conditions to
help protect state-listed endangered or
threatened species.
Two commenters recommended
removal of the definitions of ‘‘take’’ and
‘‘harm’’ from this general condition and
replacing those definitions with a
reference to the Endangered Species
Act, to reduce the potential for
inconsistencies. One commenter said
the Corps should instead use the U.S.
Fish and Wildlife Service’s regulations
to determine what constitutes an effect
or jeopardizes any threatened or
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
endangered species or their critical
habitat.
The definition of ‘‘take’’ is identical to
the definition in the Endangered
Species Act (see 16 U.S.C. 1532(19)).
The definition of ‘‘harm’’ is the same as
the definition in the U.S. Fish and
Wildlife Service’s regulations (50 CFR
17.3) and the National Marine Fisheries
Service’s regulations (50 CFR 222.102).
The definitions of ‘‘take’’ and ‘‘harm’’
were added to this condition to provide
clarification for users of the NWPs, and
facilitate compliance with the
Endangered Species Act.
One commenter stated that paragraph
(f) should provide web links to the
Services’ ESA Section 7 regulations and
other documents. Another commenter
said the Corps should defer to the U.S.
Fish and Wildlife Service on effects
determinations.
Paragraph (f) provides links to web
sites for the U.S. Fish and Wildlife
Service and the National Marine
Fisheries Service to assist prospective
permittees with obtaining information
on listed species and other ESA
documents. We do not believe it is
necessary to provide a link to the
Services’ section 7 consultation
regulations at 50 CFR part 402 since it
is the Corps responsibility to conduct
section 7 consultation. It is also the
Corps responsibility to make ‘‘may
effect’’ determinations for the purposes
of the ESA and district engineers have
the option of soliciting advice from the
U.S. Fish and Wildlife and/or the
National Marine Fisheries Service prior
to making their determinations.
One commenter recommended that
surveys be conducted for state- and
Federally-listed species prior to the start
of construction. Another commenter
said the lack of a requirement for
surveys makes the pre-construction
notification requirement in this general
condition ineffective. One commenter
said that ‘‘objective science’’ is needed
to identify habitats and species that may
be affected by activities authorized by
NWPs. One commenter stated that the
Corps must consider the effects of
climate change during the consultation
process.
The need for surveys for Federally
listed species is to be determined by the
district engineer on a case-by-case basis.
It is not possible to require surveys for
the tens of thousands of activities
authorized by NWP each year. Project
proponents are encouraged, but not
required to contact the U.S. Fish and
Wildlife Service or the National Marine
Fisheries Service for assistance in
determining whether listed species or
critical habitat might be affected by the
proposed activity. The effects of climate
PO 00000
Frm 00067
Fmt 4701
Sfmt 4703
10249
change on endangered and threatened
species and their critical habitat is more
appropriately addressed through the
section 7 consultation process, since
those effects are likely to be sitespecific.
The general condition is adopted with
the modifications discussed above.
GC 19. Migratory Bird and Bald and
Golden Eagle Permits. We are adding
this new general condition to clarify
that permittees are responsible for
complying with the Migratory Bird
Treaty Act and the Bald and Golden
Eagle Protection Act, and obtaining any
‘‘take’’ permits that may be required
under the U.S. Fish and Wildlife
Service’s regulations issued under those
two statutes. The Migratory Bird Treaty
Act and the Bald and Golden Eagle
Protection Act differ from the
Endangered Species Act in that those
two statutes and their implementing
regulations establish the project
proponent as the responsible party who
has to apply to the U.S. Fish and
Wildlife Service for take permits, if such
permits are required.
The U.S. Fish and Wildlife Service’s
implementing regulations that establish
general permit requirements for
migratory birds permits at 50 CFR part
21 state that ‘‘[n]o person may take,
possess, import, export, transport, sell,
purchase, barter, or offer for sale,
purchase, or barter, any migratory bird,
or the parts, nests, or eggs of such bird
except as may be permitted under the
terms of a valid permit issued pursuant
to the provisions of this part and part 13
of this chapter, or as permitted by
regulations in this part, or part 20 of this
subchapter (the hunting regulations), or
part 92 of subchapter G of this chapter
(the Alaska subsistence harvest
regulations).’’ The term ‘‘person’’ is
defined at 50 CFR 10.12 as ‘‘any
individual, firm, corporation,
association, partnership, club, or private
body, any one or all, as the context
requires.’’ These regulations do not
identify a federal permitting agency as
a ‘‘person’’ responsible for obtaining a
take permit, where that federal agency is
not actually carrying out the activity
that may result in the ‘‘take’’ of a
migratory bird. Likewise, the U.S. Fish
and Wildlife Service’s implementing
regulations for the Bald and Golden
Eagle Protection Act at 50 CFR part 22
do not include any provisions stating
that Federal permitting agencies are
responsible for assisting project
proponents in obtaining permits to
authorize the taking, possession, and
transportation within the United States
of bald eagles and golden eagles and
their parts, nests, and eggs.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10250
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Executive Order 13186 discusses the
responsibilities of Federal agencies to
protect migratory bird for the purposes
of the Migratory Bird Treaty Act. The
Executive Order applies only to those
actions that are directly carried out by
Federal agencies (see Section 2,
paragraph (h)). Actions carried out by
non-Federal entities with Federal
assistance are not subject to the
Executive Order. Department of the
Army permits can be considered a form
of Federal assistance since they provide
authorization to non-Federal entities to
comply with Federal laws such as
Section 404 of the Clean Water Act and
Section 10 of the Rivers and Harbors Act
of 1899.
This general condition is adopted.
GC 20. Historic Properties. We
proposed to modify paragraph (c) of this
general condition to make a more
general reference to the Corps
Regulatory Program’s current
procedures for compliance with Section
106 of the National Historic
Preservation Act, since we are using
Appendix C to 33 CFR part 325, as well
as various guidance documents to
address the Advisory Council on
Historic Preservation’s revised
regulations at 36 CFR part 800.
In response to the February 16, 2011,
proposal to reissue the NWPs, including
the proposed modification of this
general condition, we received
comments on the Corps use of
Appendix C and the current guidance.
Concerns regarding the use of Appendix
C and the current guidance are outside
the scope of the NWP rule, and are not
addressed in this rule.
Several commenters asked whether an
NWP authorization or verification
would be issued before a State Historic
Preservation Officer concurs to an effect
determination or formalizes an
agreement regarding historic properties.
One commenter stated that although the
NWP regulations provide that the Corps
may issue an NWP before a
memorandum of agreement is executed,
district engineers have, in some cases,
not issued NWP verifications without
State Historic Preservation Officer
concurrence.
This general condition requires nonFederal permittees to submit preconstruction notifications if the NWP
activity may have the potential to cause
effects to historic properties. In such
cases, the district engineer will initiate
section 106 consultation with the
appropriate State Historic Preservation
Officer or Tribal Historic Preservation
Officer. Further consultation may be
conducted with the Advisory Council
on Historic Preservation, if necessary.
The prospective permittee may not
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
begin the NWP activity until the district
engineer notifies him or her that the
section 106 consultation has been
completed (which may include
execution of a memorandum of
agreement to address adverse effects or
the concurrence of the State or Tribal
Historic Preservation Officer), or the
activity has no potential to cause effects
to historic properties.
One commenter said the Corps should
more closely follow paragraph (b) of the
general condition and not require
redundant section 106 review on
projects that are being undertaken by
another Federal agency. Three
commenters suggested that the Corps
section 106 responsibilities should be
satisfied if another Federal agency
formally accepts responsibility for
conducting section 106 consultation and
is the lead for this responsibility
through either a programmatic
agreement or on a project-by-project
basis. One commenter said that
duplicate regulatory efforts are
unnecessary, particularly when another
Federal agency has a lead role.
District engineers will generally
accept another Federal agency’s
compliance with section 106, but there
may be situations where that agency’s
section 106 compliance does not
adequately address the activities
authorized by an NWP and their effects
on historic properties. In those
situations, the district engineer may
conduct additional section 106
consultation to satisfy the requirements
of the National Historic Preservation
Act. We have added a sentence to
paragraph (b) to address these
situations.
One commenter said the general
condition does not clearly specify who
is responsible for the identification and
evaluation of historic properties and
determination of effects. Another
commenter stated that the general
condition does not adequately ensure
section 106 compliance because the
Corps may not receive enough
information from permittees to fully
take into account the effect a project
may have on a historic property. This
commenter also said that while
paragraph (c) states that prospective
permittees may seek assistance from the
State or Tribal Historic Preservation
Officer and from the National Register of
Historic Places, there is no requirement
that an applicant consult with these
parties or that an applicant coordinate
an effect determination with a qualified
professional with relevant historic
properties experience.
The Corps is ultimately responsible
for determining compliance with the
requirements of Section 106 of the
PO 00000
Frm 00068
Fmt 4701
Sfmt 4703
National Historic Preservation Act. NonFederal permittees are required to
submit pre-construction notifications if
an NWP activity may have the potential
to cause effects to historic properties,
and the district engineer will evaluate
those pre-construction notifications to
determine if section 106 consultation is
necessary. The general condition also
states that district engineers will make
reasonable and good faith efforts to
identify historic properties and effects
on those properties. The district
engineer may request additional
information from the applicant where
necessary to evaluate potential effects of
the activity on historic properties or to
initiate section 106 consultation. We
cannot require prospective permittees to
seek assistance from a State Historic
Preservation Officer or a Tribal Historic
Preservation Officer, search the National
Register of Historic Preservation, or
consult with qualified historic property
professionals. However, this general
condition requires prospective
permittees to provide a list of ‘‘ * * *
any historic properties listed,
determined to be eligible for listing on,
or potentially eligible for listing on the
National Register of Historic Places,
including previously unidentified
properties,’’ if these properties may be
affected. The permittee may obtain such
information from the State Historic
Preservation Officer or Tribal Historic
Preservation Officer, the National
Register of Historic Places, or other
sources of information on historic
properties.
One commenter recommended
providing language to clearly state when
a pre-construction notification is or is
not required based on the presence or
absence of known historic properties.
This commenter suggested that if a
prospective permittee independently
determines that no historic properties
exist within the boundaries of the
project area, then pre-construction
notification is not necessary. The
commenter also said that if the district
engineer has to be notified because of
potential effects to historic properties,
the notification should not be in the
form of a pre-construction notification.
We do not agree that the general
condition should be modified to
explicitly state that prospective
permittees do not have to submit preconstruction notifications if they
determine there are no known historic
properties within the boundaries of the
project area. Such a provision would be
inappropriate, because there could be
visual or noise effects to historic
properties outside of the project area
that have to be evaluated through the
section 106 consultation process. The
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
current general condition is the proper
approach, in which the prospective
permittee seeking NWP authorization is
required to submit a pre-construction
notification if the proposed activity
might have the potential to cause effects
to any historic property listed in, or
eligible for listing in, the National
Register of Historic Places, including
previously unidentified properties. A
pre-construction notification is the
appropriate mechanism to notify the
district engineer, because it contains
information necessary to begin the
evaluation process, to determine
whether the proposed activity qualifies
for NWP authorization.
One commenter requested
clarification of what constitutes the
permit area for the purposes of
consultation under Section 106 of the
National Historic Preservation Act. One
commenter asked if a permittee is
obligated to have the Corps review an
archaeologist’s determination that an
activity will not impact an historic site.
One commenter stated that the general
condition is unreasonable and violates
federalism.
The criteria for identifying the permit
area for the purposes of section 106 are
provided in paragraph 1(g) of Appendix
C to 33 CFR part 325, in addition to
paragraph 6(d) of the April 25, 2005,
interim guidance. The permit area will
be determined on a case-by-case basis
by the district engineer. When a
professional cultural resource manager
or archaeologist performs an
investigation or makes an effect
determination, the Corps will generally
consider the qualifications of the
professional and will review any
documentation provided for the
purposes of section 106 compliance.
This general condition is required
because the NWP program must comply
with the National Historic Preservation
Act, a Federal law. Even though most
NWP activities occur on private land,
compliance with applicable Federal
laws is necessary. This general
condition would not interfere with any
state or local authorities.
This general condition is adopted
with the modifications discussed above.
GC 21. Discovery of Previously
Unknown Remains and Artifacts. We
proposed this new general condition to
address circumstances where previously
unknown or unidentified historical or
archaeological remains are discovered
while conducting the NWP activity.
Several commenters expressed
support for adding this general
condition to the NWPs. Two
commenters said the condition should
refer to the district engineer instead of
‘‘this office’’ or ‘‘we.’’ We have made
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
these changes to be consistent with the
language found in other general
conditions.
One commenter stated that the
proposed condition relies on the
permittee, who is generally not qualified
to make determinations concerning
remains and artifacts discovered during
construction activities. This commenter
said that this general condition should
require all work to cease immediately
and a qualified Corps archaeologist
should initiate required consultation.
We believe the revised language in the
condition clearly indicates that the
Corps will initiate consultation in such
instances where a previously unknown
historic or archaeological remain is
discovered during construction
activities. The Corps does not have the
authority to prohibit all construction
activities on the site in these cases.
Several commenters expressed
concern with the use of the term
‘‘artifact’’ in this general condition, and
some of them stated that it can have too
broad of a definition. One commenter
requested clarification as to what
constitutes an ‘‘artifact.’’ Another
commenter said that this general
condition should have thresholds to
protect significant artifact deposits
while allowing work to continue when
only minor artifacts are discovered. One
commenter suggested that we qualify
‘‘artifacts’’ by adding ‘‘artifacts that are
potentially eligible for the National
Register of Historic Places.’’
The use of the term artifact is
consistent with the definition of
‘‘historic property’’ at 36 CFR 800.16,
which states that historic properties
include ‘‘ * * * artifacts, records, and
remains that are related to and located
within [historic] properties.’’ Procedures
for the protection of historic properties
address all properties that may be
eligible for inclusion in the National
Register of Historic Places, and do not
establish quantitative thresholds for
when section 106 consultation must
occur. The consultation threshold is an
effects-based threshold. We do not
believe it is necessary to add text
clarifying that artifacts are those ‘‘that
are potentially eligible for the National
Register of Historic Places.’’ Eligibility
determinations will be made after the
discovery of artifacts and remains.
Three commenters stated that the
proposed general condition is more
restrictive than general condition 3
provided in Appendix A to 33 CFR part
325, the permit form for individual
permits. These commenters said the
NWP general condition should not be
more restrictive than the standard
permit condition. Two commenters
suggested deleting this general
PO 00000
Frm 00069
Fmt 4701
Sfmt 4703
10251
condition because provisions for the
discovery of unknown historic or
archaeological remains are already
codified in the NWP regulations and in
the Corps Regulatory Program’s
implementing regulations for Section
106 of the National Historic
Preservation Act.
The proposed general condition is
similar to general condition 3 in
Appendix A of 33 CFR part 325. For this
new NWP general condition, we have
taken the text of general condition 3 in
Appendix A and modified it to include
Tribes. We have also modified it by
adding a provision requiring, to the
maximum extent practicable, avoidance
of construction activities that could
affect the remains and artifacts. We
believe the latter provision is necessary
to protect those artifacts and remains as
much as possible. The addition of
Tribes to the condition reflects current
section 106 procedures. This general
condition can be more restrictive than
the standard permit condition in
Appendix A because the NWPs may
only be used to authorize activities with
minimal adverse effects on the aquatic
environment and other applicable
public interest review factors. While 33
CFR 330.4(g)(3) contains a similar
provision, we believe the general
condition is needed to comply with
applicable cultural resource laws.
Several commenters expressed
concern with requiring the permittee to
stop work once previously unknown
historic or archaeological remains are
found. One commenter said this
provision is too unpredictable and may
result in significant delays. One
commenter suggested adding time
frames to this general condition to
provide predictability and assure
permittees that the Corps will
proactively seek to resolve any
outstanding historic property issues.
One commenter recommended
clarifying this general condition to state
that if a discovery occurs, work should
cease only in the area containing
remains or artifacts. One commenter
objected to the work stoppage provision,
stating that once construction begins,
substantial investment has been made
and the requirement to stop
construction indefinitely upon the
discovery of a potentially insignificant
archaeological resource represents an
unacceptable financial risk. This
commenter recommended that if we
keep this provision as proposed, we
impose time frames on identification
and consultation in order to provide
some predictability to the process.
We believe it is necessary to include
a provision in this general condition to
require the permittee, once any
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10252
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
previously unknown historic, cultural,
or archeological remains or artifacts are
found while conducting the NWP
activity, to avoid construction activities
that could affect those remains and
artifacts, to the maximum extent
practicable. We recognize that in some
circumstances it may not be possible to
avoid further construction activities that
might affect the remains and artifacts,
because those construction activities
may have to be completed for safety or
minimizing erosion and sedimentation.
In addition, the Corps does not have the
legal authority to stop construction
activities. We have replaced the phrase
‘‘stop activities that would adversely
affect those’’ with ‘‘avoid construction
activities that could affect the’’ to
protect those remains and artifacts as
much as possible while preventing other
adverse environmental effects from
occurring, such as the installation of
sediment and erosion control devices to
reduce or eliminate sediment inputs to
wetlands, streams, and other waters
while the necessary Federal, Tribal, and
state coordination is conducted. It
would not be appropriate to impose
timeframes in this general condition,
because the amount of time to complete
coordination will vary across the
country and from case to case. We
cannot remove the provision for
avoiding construction activities that
could affect the remains and artifacts,
because Section 106 of the National
Historic Preservation Act and other
cultural resource laws impose binding
requirements on the Corps and other
federal agencies.
A few commenters said this general
condition should not apply to other
Federal agencies with section 106
responsibilities if they are the
permittees, since their implementing
regulations already contain provisions
for the discovery of previously
unknown historic or archaeological
remains during construction.
We agree that in cases where another
federal agency is the lead Federal
agency for purposes of compliance with
Section 106 of the National Historic
Preservation Act, that Federal agency
should follow its procedures for
addressing post-review discoveries.
However, the Corps also has section 106
responsibilities if the NWP activity has
the potential to cause effects to an
historic property. As long as the lead
Federal agency is in compliance with
section 106 requirements and this
compliance satisfies section 106
requirements for the NWP
authorization, the Corps can rely on the
lead Federal agency’s compliance
efforts. Upon notification, the district
engineer will let the other Federal
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
agency know if any further action by the
Corps is necessary.
This general condition is adopted
with the modifications discussed above.
GC 22. Designated Critical Resource
Waters. We proposed to modify this
general condition to clarify the types of
waters subject to the general condition
by changing how NOAA’s marine
sanctuaries are described, which
categories of critical resource waters are
always subject to this general condition,
and how additional critical resource
waters can be designated by a district
engineer after a public notice and
comment process. We also proposed to
add proposed new NWPs A and B, now
designated NWPs 51 and 52,
respectively, to the list of NWPs in
paragraph (a).
Several commenters objected to
allowing state-designated outstanding
national resource waters to be
automatically included as designated
critical resource waters because of
varying designations and criteria across
the states. These commenters also said
that a state’s process to designate such
waters may not include the opportunity
for public comment and that the
designations carry no legal basis. In
addition, commenters indicated there
are inconsistent approaches by different
agencies within the same state for
designating outstanding national
resource waters. Some commenters said
that other state programs, such as those
that are responsible for Clean Water Act
Section 401 water quality certifications,
are capable of adequately addressing the
effects of the activity to these state
designated waters. One commenter
requested a definition of outstanding
national resource waters. Two
commenters said such waters should
have a particular environmental or
ecological significance. Two
commenters objected to including
outstanding national resource waters
automatically because that designation
may be based only on recreational
characteristics. Three commenters
suggested that the general condition
should be changed to require the district
engineer to designate such waters only
after issuing a public notice and
soliciting comment, and then obtaining
concurrence from the state.
This general condition was first
adopted in the NWPs issued on March
9, 2000 (see 65 FR 12872). In the
preamble to the 2000 NWPs, we stated
that ‘‘ * * * outstanding national
resource waters must be identified and
approved by the district engineer after
public notice and opportunity for
comment’’ (65 FR 12873, third column).
In that notice, we also said that state or
local officials should not be able to
PO 00000
Frm 00070
Fmt 4701
Sfmt 4703
designate additional waters as critical
resource waters without the district
engineer providing an opportunity for
public notice and comment. We are
modifying this general condition to
return to our original approach, since
there is much disparity across the
country in how outstanding national
resource waters are identified and
designated. Because of the
inconsistency in how outstanding
national resource waters are designated,
we believe it is necessary to provide the
public with the opportunity to review
and comment on those waters before
they become adopted as designated
critical resource waters for the purposes
of this general condition. Outstanding
national resource waters should have
environmental and ecological
significance, and their designation
should not be based solely on
recreational uses or characteristics.
Three commenters expressed concern
that providing district engineers the
ability to designate, after notice and
opportunity to comment, additional
waters officially designated by a state as
having particular environmental or
ecological significance would lead large
areas of state-designated waters of all
types to be removed from being eligible
for the NWPs. One commenter said this
general condition should be removed
because it violates the principles of
federalism in Executive Order 13132.
This commenter said a district engineer
could use state stream designations to
identify critical resource waters and
override the rights of states to interpret
and enforce their own laws.
We are retaining the provision that
allows district engineers to designate
additional critical resource waters after
notice and opportunity for public
comment. That process is not
substantially different from using the
regional conditioning process to restrict
or prohibit the use of NWPs in specific
waters or geographic areas, which can
be delegated by division engineers to
district engineers. This general
condition is not contrary to Executive
Order 13132. The general condition
helps support the objective of the Clean
Water Act, which is to restore and
maintain the physical, chemical, and
biological integrity of the Nation’s
waters. In addition, this general
condition helps ensure that the NWPs
authorize only those activities that have
minimal individual and cumulative
adverse effects on the aquatic
environment. This general condition
only applies to waters and wetlands that
are both waters of the United States and
designated critical resource waters.
One commenter objected to removing
state natural heritage sites from
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
automatic inclusion in the general
condition due to their interest in
maintaining the existing protection the
general condition provides to areas of
unique ecological significance. Another
commenter supported the proposed
change. One commenter said state
natural heritage sites should not be
automatically considered critical
resource waters because the term is
undefined. Another commenter
suggested that state natural heritage
sites should be limited to those sites
that are identified through state
legislation. One commenter opposed
including state natural heritage sites as
potentially being classified as critical
resource waters and suggested that the
Corps continue to defer to State
Historical Preservation Officers to
determine effects on historic sites.
While we understand the perspective
that state natural heritage sites should
be automatically subject to this general
condition, we also understand the need
for transparency and clarity for the
regulated public. Given the variability
in waters and wetlands that may be
designated as state natural heritage sites,
and the different processes that may be
used by states to designate their natural
heritage sites, we believe it is necessary
to provide a public notice and comment
process before including state natural
heritage sites as designated critical
resource waters under this general
condition. This approach will help
improve compliance with the NWP
conditions, because it will make project
proponents aware of certain restrictions
for the use of specific NWPs. The
protection of historic properties is more
appropriately addressed through general
condition 20, historic properties.
One commenter said the use of an
NWP should not be prohibited in
critical resource waters when the agency
responsible for managing those critical
resource waters is conducting the
activity. This commenter also suggested
that the general condition should not
prohibit the use of NWPs, but instead
the NWPs listed in paragraph (a) should
be moved to the notification provision
of paragraph (b) and also require the
approval of the agency that manages the
designated critical resource water,
similar to the approach taking in general
condition 16, wild and scenic rivers.
One commenter supported protecting
critical resource waters but suggested
that protection can be provided instead
by requiring prior written approval
through a state’s water quality agency.
Another recommended requiring water
quality certifications for the NWPs
listed in paragraph (b) instead of preconstruction notifications, to ensure that
the activities authorized by those NWPs
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
result in minimal adverse effects on
designated critical resource waters and
adjacent wetlands.
The purpose of the prohibition in
paragraph (a) of this general condition is
to exclude the use of those NWPs in
critical resource waters that have the
potential to result in more than minimal
adverse effects on the aquatic
environment. The status of the entity
who would be conducting the proposed
discharge of dredged or fill material is
not relevant to the minimal adverse
effects determination; instead, it is the
environmental effects of the discharge
that have to be considered. Discharges
of dredged or fill material into waters of
the United States that are designated
critical resource waters, as well as their
adjacent wetlands, may be authorized
by other forms of Department of the
Army permits, such as individual
permits or regional general permits.
Wild and Scenic Rivers referenced in
general condition 16 are those waters
that have been designated as such in
accordance with the Wild and Scenic
Rivers Act of 1968, a federal law.
Similar to state-listed threatened and
endangered species, the NWP program
cannot be used to ensure compliance
with other state or local laws. However,
an NWP authorization does not obviate
the need for the permittee to obtain
other federal, state, or local
authorizations, including specific
authorizations related to state-protected
critical resource waters. The water
quality certification process would not
be an appropriate alternative to the preconstruction notification requirement in
paragraph (b) of this general condition
because the evaluation of an NWP preconstruction notification involves
consideration of more than water
quality issues.
One commenter suggested that preconstruction notifications for NWP
activities listed in paragraph (b)
proposed in waters identified as critical
resources through state processes,
should only be coordinated with state
authorities. This commenter said the
pre-construction notification for simple
maintenance and improvement projects
creates unnecessary work for the project
proponent and the Corps. One
commenter recommended adding a list
of conservation areas to the general
condition, with a requirement that
permittees must be in compliance with
the site specific management plan of the
conservation area.
The district engineer will evaluate the
pre-construction notification for an
NWP listed in paragraph (b) of this
general condition, to determine if the
proposed activity will result in minimal
adverse effects on the aquatic
PO 00000
Frm 00071
Fmt 4701
Sfmt 4703
10253
environment, including the critical
resource water and its adjacent
wetlands. Agency coordination is only
required for NWP activities that result
in the loss of greater than 1⁄2-acre of
waters of the United States. None of the
NWPs listed in paragraph (b) have the
300 linear foot limit for the loss of
stream beds, so the agency coordination
threshold for requests for written
waivers for the loss of greater than 300
linear feet of intermittent or ephemeral
stream bed would not be triggered. We
do not agree that conservation areas
should be added to the general
condition at the national level, because
what constitutes a ‘‘conservation area’’
is likely to vary across the country.
District engineers may add specific
aquatic conservation areas that meet the
definition of critical resource waters to
this general condition after a public
notice and comment process.
The general condition is adopted as
proposed.
GC 23. Mitigation. We proposed to
modify paragraph (g) to be more
consistent with the compensatory
mitigation regulations at 33 CFR part
332, by replacing the word
‘‘arrangements’’ with ‘‘programs’’ in
describing in-lieu fee programs and
replacing the phrase ‘‘activity-specific’’
with ‘‘permittee-responsible’’ when
referring to compensatory mitigation
implemented by the permittee. In
addition, we proposed to add a
provision stating that for activities
resulting in the loss of marine or
estuarine resources, permitteeresponsible compensatory mitigation
may be environmentally preferable if
there are no mitigation banks or in-lieu
fee programs in the area that have
marine or estuarine credits available for
sale or transfer to the permittee. Finally,
we proposed to revise the last sentence
of paragraph (g) to state that the party
responsible for providing the required
permittee-responsible mitigation,
including any required long-term
management, is to be identified in
conditions added to the NWP
authorization. Several commenters
supported these proposed changes. One
commenter commended the Corps for
the flexibility in determining
compensatory mitigation requirements.
One commenter stated that paragraph
(a) should indicate that when another
Federal agency has determined that the
activity has been designed to avoid and
minimize impacts the district engineer
will defer to that agency’s
determination. Several commenters said
this general condition does not
adequately stress avoidance of aquatic
resources before compensatory
mitigation is considered. One
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10254
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
commenter also said the general
condition should refer to the measures
provided in the 404(b)(1) Guidelines for
details on avoiding and minimizing
impacts. This commenter also suggested
that the prospective permittee should be
required to document the steps taken to
avoid and minimize impacts, and
describe them in the pre-construction
notification. In addition, the commenter
said that the NWPs should only
authorize discharges of dredged or fill
material into special aquatic sites when
the activity is water dependent or in
cases where the prospective permittee
clearly demonstrates there are no
practicable alternatives available. One
commenter stated that the practicable
alternative test in the Section 404(b)(1)
Guidelines should be used for NWP
activities.
The district engineer determines
compliance with the terms and
conditions of the NWPs, including
whether the permittee has avoided and
minimized adverse effects to waters of
the United States to the maximum
extent practicable on the project site.
The general condition imposes
substantive requirements to avoid and
minimize adverse effects to waters of
the United States, and district engineers
will review pre-construction
notifications and determine whether
project proponents have satisfied the
avoidance and minimization
requirement, as well as other applicable
provisions of this general condition.
District engineers will also determine if
proposed activities result in minimal
adverse effects on the aquatic
environment and qualify for NWP
authorization. General permits only
need to comply with section 230.7 of
the 404(b)(1) Guidelines, which
provides the evaluation process for the
issuance of Clean Water Act Section 404
general permits, including NWPs.
Individual activities that qualify for
NWP authorization do not have to
implement the avoidance and
minimization measures provided
elsewhere in the 404(b)(1) Guidelines,
although they must still comply with
the avoidance and minimization
provisions of this general condition,
which are designed to ensure that the
NWPs collectively comply with the
404(b)(1) Guidelines. Requiring the
permittee to provide documentation of
avoidance and minimization measures
taken would result in unnecessary
paperwork requirements, and the
current information requirements for
complete pre-construction notifications
are sufficient. Section 230.7(b)(1) of the
404(b)(1) Guidelines states that the
alternatives analyses required by section
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
230.10(a) are not directly applicable to
general permits.
One commenter stated the general
condition should address other aspects
of mitigation, such as performance
standards, monitoring, and contingency
actions. One commenter said the general
condition does not comply with 33 CFR
part 332 because it does not provide any
criteria or performance standards for
compensatory mitigation. One
commenter indicated that monitoring
must be required for all mitigation.
We have made several changes to this
general condition to make it consistent
with the applicable provisions in 33
CFR part 332. We have also added a
sentence to paragraph (c)(1) of this
general condition to state that
compensatory mitigation projects to
offset losses of aquatic resources must
comply with the applicable provisions
of 33 CFR part 332. The general
condition provides basic requirements,
since the specific details for
compensatory mitigation projects (e.g.,
objectives, ecological performance
standards, monitoring requirements,
and site protection) are determined on
a case-by-case basis by district
engineers. We acknowledge that
monitoring is required for all
compensatory mitigation projects, in
accordance with 33 CFR 332.6.
Two commenters stated that the
district engineer should have discretion
to determine what, if any, compensatory
mitigation is required for projects
impacting more than 1⁄10-acre of
wetlands, as in some cases,
compensatory mitigation may not be
necessary, and mitigation ratios of less
than one-for-one may be adequate. One
commenter said that the Corps cannot
require mitigation for NWP activities
that result in minimal adverse
environmental effects, even if there are
wetland losses greater than 1⁄10-acre, and
requested that the Corps change the first
sentence of paragraph (c) to state that
the mitigation requirement can be
waived if the district engineer
determines that the impacts of the
proposed activity are minimal or some
other form of mitigation would be more
environmentally appropriate. Several
commenters stated that compensatory
mitigation should be required for all
NWP activities, and all resource types,
regardless of the amount of impact.
The 2008 compensatory mitigation
rule (33 CFR part 332, as published in
the April 10, 2008, edition of the
Federal Register (73 FR 19594))
established standards and criteria for all
compensatory mitigation projects
required to offset losses of aquatic
resources. The standards and criteria
apply to all sources of compensatory
PO 00000
Frm 00072
Fmt 4701
Sfmt 4703
mitigation, including permitteeresponsible mitigation, mitigation
banks, and in-lieu fee programs. As
stated in 33 CFR 332.1(b), the 2008 rule
does not change the circumstances
under which compensatory mitigation is
required. The NWP regulations at 33
CFR 330.1(e)(3) stipulate when
compensatory mitigation is to be
required for NWP activities—that is,
when the district engineer determines
the individual and cumulative adverse
environmental effects are more than
minimal. The requirements at 33 CFR
part 332 may affect the practicability of
providing compensatory mitigation for
all NWP activities that result in the loss
of 1⁄10-acre to 1⁄2-acre and require preconstruction notification, especially if
the NWP activity is not in the service
area of an approved mitigation bank or
in-lieu fee program with released or
advance credits available at the time the
NWP pre-construction notification is
being evaluated by the district engineer.
In the 2008 mitigation rule, we also
discussed our concerns about the failure
rates of on-site compensatory
mitigation, which are often not
ecologically successful because of
nearby changes in land use (see 73 FR
19601). We believe it would be
inappropriate to require users of the
NWP to provide small on-site
compensatory mitigation projects to
offset losses caused by NWP activities if
they are likely to fail. If the district
engineer determines that on-site
mitigation is likely to be ecologically
successful, he or she may require that
compensatory mitigation. It may not be
practicable to provide off-site
compensatory mitigation if the activity
is not in the service area of an approved
mitigation bank or in-lieu fee program
with available credits. It is also
important to recognize that not all areas
of the country have approved mitigation
banks or in-lieu fee programs. If the
district engineer determines that
compensatory mitigation is necessary to
ensure than an NWP activity results in
minimal individual and cumulative
adverse effects on the aquatic
environment, and there are no
practicable and ecologically successful
compensatory mitigation options
available, then he or she will exercise
discretionary authority and notify the
project proponent that another form of
Department of the Army authorization is
required, such as an individual permit.
To be consistent with 33 CFR
330.1(e)(3), and to take into account
how the requirements of 33 CFR part
332 affect the practicability for
providing compensatory mitigation for
small wetland losses, we have modified
paragraph (c) of this general condition
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
to state that the district engineer will
evaluate the pre-construction
notification and may not require
compensatory mitigation for losses of
greater than 1⁄10-acre of wetlands if he or
she determines that either alternative
mitigation (such as additional avoidance
and minimization of impacts to waters
of the United States on the project site)
would ensure that the NWP activity
results in minimal individual and
cumulative adverse effects on the
aquatic environment, or the impacts of
the proposed activity are minimal
without compensatory mitigation and
determines the compensatory mitigation
would not be required. We do not agree
that compensatory mitigation should be
required for all activities authorized by
NWPs. For example, compensatory
mitigation may not be needed to ensure
that the authorized activity results in
minimal adverse effects on the aquatic
environment. In addition, not all NWP
activities require pre-construction
notification, and the pre-construction
notification thresholds are established
so that those NWP activities that
generally do not result in more than
minimal adverse effects on the aquatic
environment can proceed without
review by the district engineer. To
address exceptions in specific waters or
geographic areas, division engineers
may add regional conditions to an NWP
to lower its pre-construction notification
threshold or require pre-construction
notification for all activities authorized
by that NWP.
One commenter stated that greater
than one-for-one mitigation ratios must
be required, stream mitigation ratios
should address both areal and linear
extent, and waivers of the mitigation
ratio should not be allowed. One
commenter stated that stream or open
water mitigation should have a
mandatory mitigation ratio of one-forone for in-kind replacement and twofor-one riparian habitat improvement for
any impacts exceeding 50 feet of any
stream or waterbody. One commenter
stated that mitigation should be
required for all stream impacts that
exceed 100 feet. One commenter stated
that appropriate in-kind mitigation
should be provided for any wetland or
stream impacts. One commenter also
stated that out-of-kind mitigation
contradicts the no-net-loss policy.
The amount of compensatory
mitigation necessary to ensure that the
NWP activity results in minimal adverse
effects on the aquatic environment is
determined by the district engineer on
a case-by-case basis by applying the
provisions at 33 CFR 332.3(f). The
district engineer will determine whether
compensatory mitigation for losses of
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
stream bed should be required for a
particular NWP activity. We do not
agree that losses of stream bed should
have a threshold for determining when
compensatory mitigation should be
required for those losses. We have
modified paragraph (d) of this general
condition by replacing the word
‘‘restoration’’ with ‘‘rehabilitation,
enhancement, or preservation’’ to be
consistent with 33 CFR 332.3(e)(3),
which recognizes streams as ‘‘difficultto-replace’’ resources.
Out-of-kind mitigation does not
contradict the ‘‘no overall net loss’’ goal
for wetlands, since out-of-kind wetlands
mitigation may be environmentally
preferable if another wetland type
provided as compensatory mitigation
would benefit the watershed more than
simply providing in-kind replacement
of the wetland being lost as a result of
the NWP activity.
One commenter also requested that
consideration be given to the
cumulative impacts of wetland and
stream disturbance. Several commenters
said that mitigation cannot be used to
bring the adverse effects of the NWPs to
a minimal level. Some of these
commenters stated that mitigation is not
predictable and in many cases is not
successful. Two commenters stated that
if an NWP activity requires mitigation,
then by definition it has more than
minimal adverse environmental effects.
Cumulative effects to wetlands and
streams are evaluated in the decision
documents that are prepared for each
NWP by Corps Headquarters, as well as
the supplemental decision documents
approved by division engineers.
Wetland restoration, enhancement,
establishment, and preservation
activities, and stream rehabilitation,
enhancement, and preservation
activities (including and riparian area
restoration, enhancement, and
preservation) can offset losses of aquatic
resource functions provided by waters
of the United States that are impacted
by activities authorized by NWPs.
District engineers evaluate
compensatory mitigation proposals
provided by prospective permittees, to
determine whether the compensatory
mitigation project will be ecologically
successful and be sufficient to offset
losses of waters of the United States to
ensure that the net adverse effects on
the aquatic environment are minimal.
The approved mitigation plan must
include the applicable components
listed in 33 CFR 332.4(c)(2)–(14),
including ecological performance
standards used to determine if the
compensatory mitigation project is
achieving its objectives.
PO 00000
Frm 00073
Fmt 4701
Sfmt 4703
10255
The party responsible for providing
the compensatory mitigation must
implement the approved mitigation
plan, and if it is determined that
changes are needed to improve
ecological success, request approval of
those modifications. After the approved
compensatory mitigation project is
implemented, monitoring is required on
a regular basis and monitoring reports
must be submitted to the district
engineer. The monitoring reports are
reviewed by the district engineer and if
there are deficiencies in the
compensatory mitigation project, the
district engineer will work with the
responsible party to determine what
actions are necessary to fix the
compensatory mitigation project so that
it will meet its original objectives or
comparable objectives that are
acceptable to the district engineer. If it
is not possible to take adaptive
management measures to remediate the
compensatory mitigation project, then
the district engineer may require
alternative compensatory mitigation.
Several commenters said that
applicants should be required to submit
detailed mitigation plans with their preconstruction notifications and
conceptual mitigation proposals are not
sufficient. Several commenters also
stated that the public should be
provided the opportunity to review
mitigation plans and provide comments
on whether the impacts will be
minimal.
We have added a new paragraph (c)(1)
to state that the prospective permittee is
responsible for proposing an
appropriate compensatory mitigation
option, if the district engineer
determines that compensatory
mitigation is needed to ensure that the
activity results in minimal adverse
effects on the aquatic environment.
Another new provision, paragraph (c)(3)
of this general condition, states that the
mitigation plan may be conceptual or
detailed, which is consistent with the
Corps regulations at 33 CFR
332.4(c)(1)(ii). We do not believe that
public review of compensatory
mitigation proposals is necessary.
District engineers have the expertise to
review compensatory mitigation plans,
evaluate their potential for ecological
success, and determine whether they
will offset losses of aquatic resource
functions so that the NWP activity, after
considering the required compensatory
mitigation, will result in minimal
individual and cumulative adverse
effects on the aquatic environment.
One commenter asked whether
functional assessments used to assess
aquatic resources must be approved by
the Corps. One commenter said the
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10256
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
general condition should provide
clearer requirements to reduce the
amount of discretion to be exercised by
district engineers. One commenter
stated that compensatory mitigation
should be linked to the impacts of the
project, and both the compensatory
mitigation project and the monitoring
requirements should last as long as the
authorized impacts.
Functional assessments do not have to
be formally approved by the Corps,
although district engineers may
determine that a functional assessment
method proposed to be used for a
particular aquatic resource or activity is
not appropriate. This general condition
provides basic principles for addressing
mitigation requirements for NWP
activities, because it is not possible to
cover all possible mitigation options
and requirements at the national level.
Most activities authorized by NWPs
result in the permanent loss of waters of
the United States, and it is not practical
or necessary to require permanent
monitoring of compensatory mitigation
projects. The Corps regulations require
long-term protection of compensatory
mitigation project sites (see 33 CFR
332.7(a)(1), and compensatory
mitigation projects should be selfsustaining. Some compensatory
mitigation projects may require longterm management, if the district
engineer determines that long-term
management is appropriate and
practicable.
One commenter said that paragraph
(f) should be revised to include the
option of restoring riparian areas next to
open waters. In addition, the commenter
stated that the restoration or
establishment of riparian areas should
not be required on both banks of a
stream, because in some cases the
permittee may not have authority or
legal interest in the land to restore or
establish riparian areas on both sides of
the stream. This commenter noted that
there may be conflicting easements,
roads, levees, or other structures in the
proposed riparian area, or the area may
not support riparian vegetation. One
commenter stated that the Corps is
inconsistent with use of the term buffer
and riparian areas and that buffer is
more inclusive and should be used in
the general condition instead of riparian
areas.
We have added the term ‘‘restoration’’
to the first sentence of paragraph (f) to
make it clear that the riparian area may
either be restored or established next to
open waters. The general condition does
not require riparian areas to be
established on both sides of a stream.
The fifth sentence of this paragraph
provides a recommended width for
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
riparian areas, based on a presumption
that the project proponent can restore or
establish riparian areas on both sides of
the stream. If it is not possible to
establish a riparian area on both sides of
a stream, or if the waterbody is a lake
or coastal waters, then restoring or
establishing a riparian area along a
single bank or shoreline may be
sufficient, and we have added language
to paragraph (f) of general condition 23
to clarify that this can be acceptable
compensatory mitigation. The proposal
did not use the term ‘‘buffer’’ and
paragraph (f) focuses on providing
mitigation next to open waters through
the restoration or establishment,
maintenance, and legal protection of
riparian areas.
One commenter requested that we
include the phrase ‘‘for resource losses’’
at the end of the parenthetical in
paragraph (b) to be consistent with 33
CFR part 320.4(r)(1). Two commenters
stated that it is difficult to provide longterm maintenance of mitigation sites for
weed control and invasive species. One
commenter asked that definitions for
rectifying and reducing be added to the
general condition.
We have added ‘‘for resource losses’’
after the word ‘‘compensating’’ in
paragraph (b). Before requiring longterm management for compensatory
mitigation sites, district engineers will
evaluate whether such a requirement
would be practicable, as well as
appropriate and necessary. We
recognize that it may not be appropriate
and practical to require long-term
management for small permitteeresponsible compensatory mitigation
project sites, so we have modified
paragraph (g) to make it clear that longterm management is necessary only
when the district engineer adds
conditions to an NWP authorization to
require long-term management for the
compensatory mitigation project. We do
not believe it is necessary to provide
definitions of the terms ‘‘rectifying’’ and
‘‘reducing’’ since the commonly
understood definitions of these terms
are sufficient.
One commenter requested the
removal of paragraph (h), stating that it
creates confusion and sometimes results
in mitigation being required for nonjurisdictional activities, such as nonmechanized, above-ground landclearing
for overhead electric transmission lines.
Another commenter said that paragraph
(h) implies that the Corps has authority
over activities it does not regulate, such
as the removal of woody vegetation from
a wetland when there is no discharge of
dredged or fill material into waters of
the United States. One commenter
requested clarification of the
PO 00000
Frm 00074
Fmt 4701
Sfmt 4703
circumstances under which the Corps
would require compensatory mitigation
for the conversion of forested and scrub
shrub wetlands, and said the phase
‘‘may be required’’ should be changed to
‘‘shall be required.’’ This commenter
also said that no waivers should be
allowed for mitigation for projects
within a utility right of way for forested
and scrub shrub wetlands that are
permanently converted to emergent
wetlands.
Paragraph (h) is being retained, to
make it clear that district engineers may
require compensatory mitigation for
permanent losses of specific aquatic
resource functions that are caused by
discharges of dredged or fill material
into waters of the United States or other
regulated activities. Paragraph (h) is part
of a general condition that applies only
to activities authorized by NWPs. We do
not agree that the phrase ‘‘may be
required’’ should be replaced with
‘‘shall be required’’ because it is the
district engineer’s discretion whether to
require compensatory mitigation for
losses of specific aquatic resource
functions.
One commenter recommended adding
a new paragraph to this general
condition to clarify that any mitigation
requirements must be limited to a single
and complete linear project. This
commenter said that compensatory
mitigation should only be required if a
specific crossing of a waterbody triggers
paragraph (c), (d), or (f) of this general
condition, not for other crossings that
do not trigger pre-construction
notification requirements or mitigation
requirements.
We do not believe such an addition to
this general condition would be
appropriate or necessary. As discussed
elsewhere in this notice, district
engineers evaluate the entire linear
project, even though each separate and
distant crossing of waters of the United
States may qualify for a separate NWP
authorization. District engineers may
require compensatory mitigation for all
temporary and permanent losses of
waters of the United States. District
engineers are required to consider
cumulative adverse effects in reviewing
NWP pre-construction notifications, not
just adverse effects from the specific
single and complete project to which
the notification applies.
One commenter stated that this
general condition does not adequately
convey the hierarchy of mitigation
preference established by 33 CFR part
332. One commenter stated that in-lieu
fee arrangements must not be used
unless the arrangements comply with
the requirements of the in-lieu fee
guidance. One commenter stated that
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
remining of lands results in a net benefit
to the aquatic resources, and the Corps
should consider this remining as
adequate compensatory mitigation and
should consider if it is appropriate to
create an in-lieu fee program for
remining of previously mined areas.
We do not believe it is necessary to
include the mitigation options
evaluation framework provided in 33
CFR 332.3(b), since that regulation
applies to all forms of Department of the
Army permits, and the general
condition explicitly states that
mitigation must comply with part 332.
In-lieu fee programs used to provide
compensatory mitigation for NWP
activities must comply with the
applicable provisions in 33 CFR 332.8,
unless the district engineer determined
that they qualified for the extension of
the grandfathering provision provided at
33 CFR 332.8(v)(2). District engineers
will determine on a case-by-case basis
whether compensatory mitigation
should be required for remining
activities authorized by NWP.
This general condition is adopted
with the modifications discussed above.
GC 24. Safety of Impoundment
Structures. We proposed to add this
new general condition to the NWPs. We
received no comments on the proposed
general condition. The general
condition is adopted as proposed.
GC 25. Water Quality. We did not
propose any changes to the general
condition. Two commenters
recommended modifying this general
condition to state that activities are not
authorized by NWP if the state denies
water quality certification, unless the
project proponent obtains an individual
water quality certification or water
quality certification is waived. One
commenter suggested adding a
provision to state that the district
engineer will determine, after a
reasonable amount of time (generally 60
days) from the date an application for an
individual water quality certification
was submitted by the project proponent,
that water quality certification is waived
unless the Corps and the water quality
certification agency agree that
additional time is needed. A few
commenters said that individual
permits should be required for activities
in any waters identified as 303(d) listed
streams.
We believe that the current wording
of this general condition is sufficient to
make it clear that an individual water
quality certification or waiver must be
obtained if the state, Tribe, or EPA had
not previously issued water quality
certification for an NWP. We also do not
believe it is necessary to provide a
specific timeframe in the general
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
condition to reflect the language in 33
CFR 330.4(c)(6), since those timeframes
may vary by Corps district because of
local agreements with water quality
certification agencies. There are a
variety of causes of stream impairment
for 303(d) listings other than discharges
of dredged or fill material (e.g.,
nutrients, metals, sedimentation,
temperature, bacteria, pH, toxics).
Reversing those causes of impairment is
more appropriately addressed through
other Clean Water Act programs.
This general condition is adopted as
proposed.
GC 26. Coastal Zone Management. We
received no comments on the proposed
general condition. The general
condition is adopted as proposed.
GC 27. Regional and Case-by-Case
Conditions. We received no comments
on the proposed general condition. The
general condition is adopted as
proposed.
GC 28. Use of Multiple Nationwide
Permits. We received no comments on
the proposed general condition. The
general condition is adopted as
proposed.
GC 29. Transfer of Nationwide Permit
Verifications. We received no comments
on the proposed general condition. The
general condition is adopted as
proposed.
GC 30. Compliance Certification. We
proposed a minor change to this general
condition to clarify that we will provide
the permittee with the necessary
documentation to complete and return
to the Corps as the signed certification.
One commenter expressed support for
the proposed change.
Two commenters recommended
including regional conditions to the list
of conditions under paragraph (a). One
commenter suggested that a separate
compliance certification be required for
mitigation projects, because permittees
submit the compliance certification
when the work is completed, not when
the compensatory mitigation project is
completed. Two commenters said the
general condition should be modified to
clarify that the success of the required
compensatory mitigation would be
addressed separately, after evaluation of
monitoring reports demonstrates
achievement of the performance
standards for the compensatory
mitigation project.
We have modified paragraph (a) to
require the statement to read that the
authorized work has been done in
accordance with any general, regional
and activity-specific conditions to cover
all of the conditions that may be
applicable to an NWP authorization. We
have also changed the first paragraph of
this general condition by adding a
PO 00000
Frm 00075
Fmt 4701
Sfmt 4703
10257
sentence to state that the success of any
required permittee-responsible
mitigation, including the achievement
of ecological performance standards,
will be addressed separately by the
district engineer. Paragraph (b) has also
been revised by adding a sentence to
address the use of mitigation bank and
in-lieu fee program credits to fulfill
compensatory mitigation requirements
in NWP authorizations. This new
sentence states that if mitigation bank
credits or in-lieu fee program credits are
used, the permittee must submit the
documentation required by 33 CFR
332.3(l)(3) to confirm that he or she has
secured the appropriate number and
resource type of credits from the
mitigation bank or in-lieu fee program.
One commenter suggested adding
language similar to that provided in
NWP 32, to state that it is necessary to
comply with all terms and conditions of
the NWP, and that the NWP
authorization is automatically revoked if
the permittee does not comply with all
terms and conditions. One commenter
suggested that additional funding be
allocated to do more on-site compliance
inspections. One commenter said there
are insufficient monitoring and
compliance procedures in the NWPs.
One commenter stated that it should be
the permittee’s responsibility to provide
the required proof that the authorized
activity was conducted to comply with
the terms and conditions of the NWP.
The Note at the beginning of Section
C, Nationwide Permit General
Conditions, adequately addresses the
requirement to comply with all
applicable terms and conditions of the
NWPs. Funding for compliance
inspections is outside of the scope of
this rule. Corps districts are required,
through our performance measures, to
conduct initial compliance inspections
for a minimum percentage of the total
number of all general permit (including
NWP) verifications issued during the
preceding fiscal year where authorized
work is underway. The purposes of this
general condition is for the permittee to
submit documentation to the district
engineer demonstrating that the
authorized activity has been
implemented in accordance with the
conditions of the NWP authorization.
Each permittee who receives an NWP
verification letter from the Corps must
provide a signed certification
documenting completion of the
authorized activity and any required
compensatory mitigation.
This general condition is adopted
with the modification listed above.
GC 31. Pre-Construction Notification.
We proposed to modify paragraph (d)(2)
to clarify that all NWP activities
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10258
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
resulting in the loss of greater than 1⁄2acre of waters of the United States
require agency coordination. We also
proposed to require agency coordination
for certain NWPs when the proposed
activity would result in the loss of
greater than 1,000 linear feet of
intermittent and ephemeral stream bed,
in cases where the district engineer is
considering waiving the 300 linear foot
limit. Another proposed change was to
clarify that the district engineer will
consider direct and indirect effects
caused by the NWP activity when
making a minimal adverse effects
determination. We also proposed to
provide a list of factors to be considered
when making minimal effects
determinations for the purposes of the
NWPs. One commenter supported the
proposed list of factors.
One commenter objected to adding
more pre-construction notification
requirements, stating that it takes
several days to weeks for an applicant
to prepare pre-construction notification
at the high level of detail required by
district offices. Several commenters
stated that they did not have the time
and resources to prepare a preconstruction notifications for all
activities. One commenter said the
proposed changes that require preconstruction notifications for additional
activities would add to the workload of
the Corps for projects that are minor in
nature.
We have not substantially increased
the number of activities that require preconstruction notification. We have
issued two new NWPs, and although
both of those NWPs require preconstruction notification for all
activities, some of the activities
authorized by those NWPs may also be
authorized by other NWPs that do not
require pre-construction notification. A
prospective permittee may request
authorization under a specific NWP, if
the proposed activity qualifies for
authorization under that NWP. District
engineers have been instructed, through
Regulatory Program Standard Operating
Procedures, to use the most efficient
permit process wherever possible, to
make timely permit decisions while
protecting the aquatic environment. The
two new NWPs issued today will
provide a more efficient means of
authorizing renewable energy
generation facilities and pilot projects,
in cases where those activities did not
previously qualify for NWP
authorization and required individual
permits instead.
One commenter expressed concern
with delays associated with the preconstruction notification process.
Several commenters said some districts
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
make requests for additional
information after the 30-day preconstruction notification completeness
determination period ends, and
suggested adding a provision to
paragraph (a) to state that all requests
for additional information must be made
within 30 days of receipt of a complete
pre-construction notification and that
districts are limited to one request for
additional information. One commenter
said the phrase ‘‘as a general rule’’
should be deleted from paragraph (a).
Several commenters said that in many
cases, the district engineer fails to
describe the specific information that is
needed for a pre-construction
notification to be deemed complete.
Two commenters requested clarification
as to whether the activity is authorized
by an NWP 30 or 45 days after
submitting a complete pre-construction
notification.
We have added text to the second
sentence of paragraph (a) to state that
district engineers must notify
prospective permittees within the 30day completeness review period if the
pre-construction notification is
incomplete and additional information
has to be provided to the district
engineer to make the pre-construction
notification complete. We have also
added a sentence that directs the district
engineer to specify, in his or her request
for additional information, what
information is needed to make the preconstruction notification complete. We
have retained the phrase ‘‘as a general
rule’’ in the new fourth sentence, which
states that district engineers will request
additional information only once,
because there may be occasions where
it is necessary to make an additional
request for information. It should be
noted that the 30-day period only
applies to information necessary to
make the PCN complete, which is listed
in paragraph (c) of this general
condition. Other types of information
may also be needed to make a decision
on whether the proposed activity
qualifies for NWP authorization, such as
a conceptual or detailed compensatory
mitigation plan, if the applicant only
provided a mitigation statement to
satisfy the requirement in paragraph
(b)(5). A conceptual or detailed
mitigation plan is needed to determine
whether the proposed compensatory
mitigation will be suitable for ensuring
compliance with general condition 23,
and may be requested after the 30-day
completeness review period, but before
the 45-day pre-construction notification
review period ends. Another example is
request for additional information
necessary to complete either
PO 00000
Frm 00076
Fmt 4701
Sfmt 4703
Endangered Species Act Section 7
consultation under general condition 18
or National Historic Preservation Act
Section 106 consultation under general
condition 20. Past rulemaking activities
for the NWPs have established a 45-day
pre-construction notification review
period for the NWPs, and today’s final
rule retains that time period. Exceptions
are for compliance with general
condition 18, endangered species, and
general condition 20, historic
properties. Under those two general
conditions, activities that may affect
endangered or threatened species or
critical habitat, or have the potential to
cause effects to historic properties, are
not authorized until the required
consultations are completed. Another
exception is NWP 21, for which
activities are not authorized until the
applicant receives written verification
from the Corps.
One commenter said that ‘‘he or she’’
be removed from paragraph (a)(1) as it
is the only location in which personal
pronouns are used. Another commenter
recommended changing paragraph (a)(2)
to state that if the permittee does not
receive any written notification from the
district engineer within 45 days of
submitting a complete pre-construction
notification, then the permittee can
assume that the district engineer has
made a ‘‘no effect’’ determination for
endangered species or historic
properties.
The use of ‘‘he or she’’ is appropriate
in paragraph (a)(1) because it refers to
the prospective permittee, who may be
an individual, corporation, or other
entity. The NWP regulations (see 33
CFR 330.4(f)(2) for Endangered Species
Act compliance and 33 CFR 330.4(g)(2)
for National Historic Preservation Act
compliance), as well as general
conditions 18 and 20, state that the
activity is not authorized by NWP until
the requirements of the Endangered
Species Act and/or the National Historic
Preservation Act have been satisfied.
Those two provisions in the Corps NWP
regulations do not allow a prospective
permittee to conclude that there is a ‘‘no
effect’’ finding for the purposes of
compliance with the Endangered
Species Act or a ‘‘no potential to cause
effect’’ finding for the purposes of
compliance with Section 106 of the
National Historic Preservation Act if the
district engineer does not respond to the
pre-construction notification within 45days in which the applicant stated there
might be effects to listed species or
designated critical habitat or there may
be potential to cause effects to historic
properties.
One commenter requested
clarification whether the seven items
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
identified in paragraph (b) of this
general condition are a complete list
and should not be supplemented. One
commenter said that if additional
requirements are added to the NWP
authorization by the district engineer
after the evaluation of the preconstruction notification, those
requirements should be subject to
public notice and comment.
The seven items listed in paragraphs
(b)(1) through (7) of this general
condition are required for a preconstruction notification. Additional
information may be needed by the
district engineer to make a decision on
the NWP pre-construction notification,
such as a compensatory mitigation
proposal if the district engineer
disagrees with the prospective
permittee’s statement that compensatory
mitigation is not necessary to ensure the
activity results in minimal adverse
environmental effects, or information
needed to conduct Endangered Species
Act Section 7 or National Historic
Preservation Act Section 106
consultation. Permit conditions added
to an NWP authorization by a district
engineer do not need to go through a
public notice and comment process
because they are incorporated into the
authorization to ensure compliance with
regulatory and statutory requirements
that general permits only authorize
activities that have minimal adverse
effects on the aquatic environment and
other applicable public interest review
factors. The Corps regulations do not
require public notice and comment for
any conditions added to Department of
the Army permits, including standard
permits, letters of permission, and all
categories of general permits.
Two commenters stated that
applicants should be required to submit
detailed mitigation plans with their preconstruction notifications and
conceptual mitigation proposals are not
sufficient. One commenter said
paragraph (e)(2) should be revised to
require the prospective permittee to
submit a compensatory mitigation
proposal if the activity will result in the
loss of greater than 1⁄10-acre of wetlands.
Paragraph (b)(5) requires the
prospective permittee to submit a
statement explaining how the mitigation
requirement will be satisfied or why the
adverse effects of the proposed activity
on the aquatic environment are minimal
without mitigation. A detailed or
conceptual mitigation plan may be
submitted with the pre-construction
notification, and a conceptual
mitigation plan is usually sufficient for
making the minimal adverse effects
determination. If the proposed
mitigation shown in the conceptual
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
mitigation plan is acceptable, a detailed
mitigation plan that complies with the
requirements of 33 CFR 332.4(c)(2)–(14)
will be required and must be approved
by the district engineer before work
begins in waters of the United States
unless the district engineer determines
such prior approval is not practicable or
necessary (see paragraph (c)(3) of
general condition 23, mitigation).
One commenter said that state
agencies operating under Federal
funding should be added to paragraphs
(b)(6) and (b)(7), for the submittal of
documentation demonstrating
compliance with Section 7 of the
Endangered Species Act or Section 106
of the National Historic Preservation
Act. This commenter also stated that
pre-construction notifications should be
provided electronically as well. One
commenter said that a pre-construction
notification should include information
demonstrating that a project complies
with applicable federal and state
requirements.
A state agency operating under
Federal funding, where the Federal
agency has conducted Endangered
Species Act Section 7 consultation or
National Historic Preservation Act
Section 106 consultation for the activity
that is being provided Federal funds,
may provide that documentation to the
district engineer as part of its preconstruction notification, but the
district engineer will determine whether
that consultation is sufficient for the
NWP activity. The NWP regulations at
33 CFR 330.1(e)(1) state that preconstruction notifications must be in
writing. We have modified paragraph
(d)(4) to state that prospective
permittees may also provide electronic
files of pre-construction notifications to
expedite agency coordination.
Compliance with other Federal, state, or
local requirements is the responsibility
of the permittee, and the Corps does not
have the authority to enforce the
regulatory requirements of programs
administered by other agencies.
Several commenters objected to the
requirement for a delineation of special
aquatic sites and other waters of the
United States under paragraph (b)(4) of
this general condition, because
requiring a full delineation has become
a significant cause of delays and
increased costs due to uncertainties
regarding the extent of Federal
jurisdictional waters under U.S.
Supreme Court decisions in 2001 and
2006. One commenter said that in the
second sentence of paragraph (b)(4) the
term ‘‘wetland delineation’’ should be
replaced with ‘‘delineation of waters of
the United States,’’ because the
requirement is for not only a delineation
PO 00000
Frm 00077
Fmt 4701
Sfmt 4703
10259
of wetlands but also of other waters of
the United States. One commenter
suggested modifying paragraph (b)(4) to
clarify that a jurisdictional
determination is not required with the
submittal of a complete pre-construction
notification, just a delineation of waters
of the United States, which would be
completed by either the prospective
permittee or the Corps.
We have modified paragraph (b)(4) to
state that a pre-construction notification
must include a delineation of wetlands,
other special aquatic sites, and other
aquatic habitats (e.g., perennial,
intermittent, and ephemeral streams,
and lakes and ponds) on the project site,
instead of a delineation of special
aquatic sites and other waters of the
United States. Use of the term ‘‘waters
of the United States’’ in this paragraph
implies that an approved jurisdictional
determination would have to be done
for a NWP pre-construction notification.
An approved jurisdictional
determination is an official Corps
determination that jurisdictional
‘‘waters of the United States’’ or
‘‘navigable waters of the United States,’’
or both, are either present or absent on
a particular site, and precisely identifies
the limits of those waters on the project
site that are determined to be
jurisdictional under the Clean Water Act
or Sections 9 and 10 of the Rivers and
Harbors Act of 1899 (see Regulatory
Guidance Letter 08–02). We understand
that many users of the NWPs do not
want to obtain an approved
jurisdictional determination, and that
preliminary jurisdictional
determinations may be appropriate for
the purposes of NWP authorizations.
Under a preliminary jurisdictional
determination, the wetlands, other
special aquatic sites, and other aquatic
habitats on the project site are presumed
to be waters of the United States for the
purposes of the NWP authorization, and
any compensatory mitigation that may
be required. A project proponent has the
option of requesting an approved
jurisdictional determination if he or she
believes that some or all of the
wetlands, special aquatic sites, or other
aquatic habitats are not waters of the
United States, and wants an official
jurisdictional determination from the
Corps. A request for an approved
jurisdictional determination should be
submitted to the Corps in advance of
submitting a pre-construction
notification, because the Corps may not
be able to make an approved
jurisdictional determination within the
45-day pre-construction notification
review period, and this NWP rule does
not contain a provision stating that
approved jurisdictional determinations
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10260
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
are necessary to make a decision on an
NWP pre-construction notification.
Several commenters suggested
modifying the general condition to
allow the applicant to satisfy the preconstruction notification requirement by
demonstrating that consultation under
the National Historic Preservation Act
(NHPA) and/or Endangered Species Act
(ESA) has been completed and has
resulted in a finding that the project
would not adversely affect resources
protected under those statutes. One of
the commenters also stated that
paragraph (e)(1) is incorrect, because the
condition refers to a limit of 300 feet,
but NWP 13 has a limit of 500 feet that
can be waived. One commenter stated
that submittal of a pre-construction
notification should be required for any
NWPs within 303(d) impaired waters
and that the applicant should prepare a
statement identifying how the project
avoids contributing to existing water
quality impairments and maintains
consistency with any existing Total
Daily Maximum Loads (TMDLs).
Pre-construction notification is
required for NWP activities that might
affect endangered or threatened species
listed, or proposed for listing, under the
Endangered Species Act (see 33 CFR
330.4(f)(2)). Likewise, pre-construction
notification is required for NWP
activities that may affect historic
properties (see 33 CFR 330.4(g)(2)). It is
the Corps responsibility to make effect
determinations for the purposes of the
NWP authorizations. Information
provided by the project proponent for
Endangered Species Act or National
Historic Preservation Act compliance
will be fully considered by the district
engineer, but it is the district engineer’s
decision as to whether the requirements
of those acts have been complied with
for the NWP authorizations. We have
determined that modification of
paragraph (e)(1) (which has been moved
to paragraph 1 of Section D, District
Engineer’s Decision) is not necessary, as
the 500 linear foot limit for the request
for a waiver of NWP 13 is ‘‘an otherwise
applicable limit’’ as specified in this
text. The state agency that makes water
quality certifications for the NWPs has
the authority to determine whether an
NWP should authorize discharges into
303(d) impaired waters, so we do not
believe pre-construction notification
should be categorically required for all
such discharges. As noted previously,
many waters are impaired for pollutants
not related to discharges of dredge or fill
material.
Two commenters said that under
paragraph (c) of this general condition,
there are problems with using ENG 4345
for pre-construction notifications,
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
because the standard permit form
requires information that is not listed in
paragraphs (b)(2) through (b)(7), and
those paragraphs also cite information
that is not required by ENG 4345.
The standard permit form, ENG 4345,
may be used for pre-construction
notifications, and it is not necessary to
fill out those fields in ENG 4345 that are
not relevant to paragraphs (b)(2) through
(b)(7). The prospective permittee must
supplement ENG 4345 if the NWP preconstruction notification must include
information that is not specifically
required by ENG 4345. A permittee is
not required to use ENG 4345 for preconstruction notification as long as all
required information is included.
Several commenters said that the
threshold for agency coordination
should be increased, or that interagency
coordination is not necessary. In
contrast, several commenters stated that
the thresholds for agency coordination
should be decreased. One commenter
said agency coordination should be
required for any activity potentially
impacting approved mitigation banks,
other mitigation areas, or local, state, or
Federal public properties. One
commenter suggested requiring agency
coordination for NWP 12 activities,
because they could result in the loss of
greater than 1⁄2-acre of waters of the
United States.
We believe the agency coordination
thresholds established in paragraph
(d)(2) of this general condition are
appropriate, and focus on those
activities where it would be helpful to
solicit the views of the listed agencies
prior to making a decision on an NWP
pre-construction notification. Potential
impacts to mitigation banks, other
compensatory mitigation project sites,
or other public properties are more
appropriately addressed through the
district engineer’s review, and do not
require additional agency coordination
under the NWP program. However,
agency coordination may be required
under other regulations, such as 33 CFR
332.8, which has an interagency review
process for the establishment and
operation of mitigation banks and inlieu fee programs. A proposed activity
that may directly affect an approved
mitigation bank or in-lieu fee project
site may require the district engineer to
consult with an interagency review team
before making a decision on that
activity. The limits for NWP 12 apply to
single and complete projects, and for
each single and complete project the
NWP 12 activity may not result in the
loss of greater than 1⁄2-acre of waters of
the United States. As discussed
elsewhere in this final rule, in response
to pre-construction notifications for
PO 00000
Frm 00078
Fmt 4701
Sfmt 4703
NWP 12 activities that are linear
projects, district engineers will evaluate
the cumulative effects of those linear
projects on the aquatic environment
when determining whether
authorization by NWP is appropriate.
We do not believe it is necessary to
require agency coordination for those
linear projects.
This general condition is adopted
with the modifications discussed above.
District Engineer’s Decision
We have established a new Section D,
District Engineer’s Decision, by moving
paragraph (e) of the proposed general
condition 30 (now designated as general
condition 31) to a separate section of the
NWPs. We believe this is appropriate
because the proposed paragraph (e) does
not require compliance on the part of
the permittee. Therefore, the criteria
that district engineers use to determine
whether a particular activity is
authorized by NWP should not be in the
general conditions. The comments
received in response to the proposed
paragraph (e) of the pre-construction
notification general condition have been
moved to this new section.
Two commenters objected to the
language which states that the district
engineer must determine that the
proposed NWP activity is not contrary
to the public interest. One of these
commenters said that Section 404(e) of
the Clean Water Act does not require
such a public interest review for NWP
activities, and this provision should be
deleted because it conflicts with other
Corps regulations.
The NWP regulations clearly state that
the district engineer may exercise
discretionary authority if he or she
identifies concerns for the aquatic
environment under the 404(b)(1)
Guidelines or for any factor of the
public interest (see 33 CFR 330.1(d)). In
addition, the NWP regulations also
require the district engineer to review
pre-construction notifications and add
conditions to the NWP authorization if
necessary to ensure that the activity
results in minimal individual and
cumulative adverse effects on the
aquatic environment and the public
interest (see 33 CFR 330.1(e)(2)). The
Corps issued those regulations under its
authority under Section 404 of the Clean
Water Act and Section 10 of the Rivers
and Harbors Act of 1899.
One commenter suggested adding
definitions of the terms ‘‘direct’’ and
‘‘indirect’’ to the NWPs. Two
commenters requested clarification on
when a district engineer can exercise
discretionary authority for the purposes
of the NWP authorization, particularly
for those circumstances where pre-
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
construction notification is not required
by the NWP. Several commenters said
that the district engineer should also
evaluate the environmental benefits of a
project.
We have added definitions for the
terms ‘‘direct effects’’ and ‘‘indirect
effects’’ to the ‘‘Definitions’’ section of
the NWPs. District engineers have the
authority to modify, suspend, or revoke
any NWP authorization (see 33 CFR
330.1(d) and 33 CFR 330.4(e)(2)) when
he or she has identified sufficient
concerns for the environment or other
factors of the public interest. District
engineers may also consider
environmental benefits that may result
when making a decision as to whether
an NWP activity results in minimal
individual and cumulative adverse
effects to the aquatic environment.
One commenter stated that the factors
required for a district engineer to make
a minimal effects determination on a
request for a waiver of the limits of any
NWP suggests a level of analysis that is
more comparable to the individual
permit process, which threatens the
availability of the NWPs for prospective
permittees.
The evaluation of a request for a
waiver of the 300 linear foot limit for
the loss of intermittent or ephemeral
stream bed, or any other limit that can
be waived by the district engineer, is an
important tool for maintaining
flexibility in the NWP, and authorizing
activities that result in minimal
individual and cumulative adverse
effects on the aquatic environment. The
waiver review process is not comparable
to the individual permit review process,
because it does not require a public
notice, National Environmental Policy
Act documentation, and a projectspecific 404(b)(1) Guidelines analysis.
In response to the proposed
considerations for making minimal
effects determination, one commenter
suggested adding the type of resource
that will be affected by the NWP. This
commenter also recommended defining
the term ‘‘minimal effects’’ as those
effects that constitute relatively small
changes in the affected environment and
insignificant changes in ecological
function or hydrology. This commenter
said the minimal effects decision may
also depend on whether the proposed
activity will occur in a special aquatic
site, its proximity to nesting or
spawning areas, the presence of state- or
federally-listed species of concern other
than endangered or threatened species,
and the amount of permitted or
unpermitted aquatic resource loss in the
same watershed, stream reach, and/or
bay or estuary.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
We agree that adding the resource
type is appropriate, because the
minimal effects threshold may be
different for a difficult-to-replace
resource such as a stream, bog, fen, or
spring. We do not agree that a finding
of minimal effects should be based on
small changes to the affected
environment, ecological function, or
hydrology. While the NWPs have
acreage or linear foot limits, or inherent
limits based on the type of activity
authorized, at a small scale those
activities result in complete losses of
ecological function or hydrology
because most discharges of dredged or
fill material into waters of the United
States replace aquatic areas with dry
land. These complete losses of waters of
the United States often have minimal
individual and cumulative adverse
effects on the aquatic environment. It is
the environmental setting and other
factors listed in the proposed paragraph
(e)(1) (which has been changed to
paragraph (1) of Section D) that are more
appropriate for making the minimal
effects determination. It is also the
broader watershed or landscape context
that is important for determining
whether minimal adverse effects on the
aquatic environment will result.
Proximity to nesting or spawning areas
is more appropriately addressed through
compliance with general condition 4,
migratory bird breeding areas, and
general condition 3, spawning areas.
Division engineers may impose regional
conditions to restrict or prohibit the use
of NWPs to authorize activities that may
affect state- or federally-listed species of
concern if they determine, after the
public notice and comment process, it is
in the public interest to add such
regional conditions to ensure minimal
adverse effects. The Corps is required to
consider effects within a wetland,
stream reach, or coastal waterbody that
are caused either by an individual
activity, or cumulatively by many such
activities authorized by the same NWP,
and to determine that such effects are
minimal before use of an NWP can be
authorized.
We have made additional
modifications to the text of this
provision of the NWPs. In the first
paragraph, we have added a sentence
stating that for linear projects, the
district engineer will evaluate the
individual crossings to determine if they
satisfy the terms and conditions of the
applicable NWP(s), as well as the
cumulative effects of all the crossings
authorized by NWPs. This sentence is
consistent with the preamble for the
NWP final regulation published in the
November 22, 1991, issue of the Federal
PO 00000
Frm 00079
Fmt 4701
Sfmt 4703
10261
Register, in which the definition of
‘‘single and complete project’’ at 33 CFR
330.2(i) was promulgated (see 56 FR
59114).
In paragraphs (2) and (3) of Section D,
we have added text to be consistent
with the mitigation rule at 33 CFR part
332, with a focus on adding activityspecific conditions to the NWP
authorization for compensatory
mitigation requirements. We have also
added a provision to the end of
paragraph (3) stating that the district
engineer may determine that prior
approval of a mitigation plan is not
practicable or not necessary to ensure
timely completion of the required
compensatory mitigation. This
provision is consistent with 33 CFR
332.3(k)(3).
Definitions
Best management practices (BMPs).
We did not receive any comments on
the proposed definition. The definition
is adopted as proposed.
Compensatory mitigation. We
proposed to modify this definition to
make it consistent with the definition of
this term found in 33 CFR 332.2. We did
not receive any comments on the
proposed definition and the definition
is adopted as proposed.
Currently serviceable. We did not
proposed any changes for this
definition. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Direct effects. In response to several
comments, we are adding a definition of
‘‘direct effects’’ to provide clarification
to be used with paragraph (1) of Section
D, District Engineer’s Decision. We have
adapted this definition from the Council
of Environmental Quality’s definition in
their National Environmental Policy Act
regulations at 40 CFR 1508.8(a).
Discharge. The proposed definition
included the phrase ‘‘and any activity
that causes or results in such a
discharge.’’
One commenter said that that phrase
should be removed because it is
inconsistent with court decisions on the
definition of ‘‘discharge of dredged
material.’’ We inadvertently included
the language in the proposal, and are
removing it from the definition.
This definition is adopted with the
modification discussed above.
Enhancement. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Ephemeral stream. We did not
propose any changes to the definition.
One commenter said the definition
should be modified to state that for
ephemeral streams, flow is also derived
from snow melt as well as rainfall. One
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10262
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
commenter requested clarification that
the definition of ephemeral stream did
not include roadside ditches.
While snow melt may contribute to
the flow of ephemeral streams, snow
melt also contributes to the flow of
intermittent and perennial streams,
especially in areas with deep snow
packs. The proposed definition
appropriately focuses on the duration of
flow, and melting snow should not be
considered a precipitation event since
the development of snow pack occurs
over the course of a winter season.
Therefore, we are not making the
suggested change. Ephemeral streams
may, in some circumstances, be
channelized or relocated to become
roadside ditches, so we do not agree that
recommended change should be made.
The definition is adopted as
proposed.
Establishment (creation). We did not
receive any comments on the proposed
definition. The definition is adopted as
proposed.
High Tide Line. We proposed to add
this as a new definition, based on the
definition at 33 CFR 328.3(d). One
commenter suggested expanding the
definition of storm surges to include
build up of water against a coast or a
bay by flood waters which cause water
levels to exceed spring high tide levels.
We do not agree that the suggested
change should be made to this
definition, because it would make the
definition inconsistent with 33 CFR
328.3(d), which states that storm surges
are not to be used to identify the high
tide line.
The definition is adopted as
proposed.
Historic property. We did not receive
any comments on the proposed
definition. The definition is adopted as
proposed.
Independent utility. We proposed to
add ‘‘non-linear’’ in the first sentence
after ‘‘complete’’ and before project to
reflect the independent utility test only
applies to single and complete nonlinear projects.
One commenter requested that the
term ‘‘independent utility’’ be
eliminated from the nationwide permit
program because it discourages
assessment of a project’s total impacts.
Another commenter asked whether the
term independent utility applied to both
single and complete non-linear projects
and single and complete linear projects.
The concept of ‘‘independent utility’’
is important for the implementation of
the NWP program because it provides a
useful test to help determine whether
proposed activities requiring
Department of the Army authorization
should be evaluated together for one
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
permit authorization, or may be
evaluated separately to determine if
each activity qualifies for its own permit
authorization. Despite the independent
utility test, the cumulative effects of
NWP activities must still be evaluated
by district engineers when they review
pre-construction notifications or other
NWP verification requests. The
modified definition makes it clear that
the independent utility test only applies
to single and complete non-linear
projects; however, separate linear
projects may have independent utility.
This definition is adopted as
proposed.
Indirect effects. In response to several
comments, we are adding a definition of
‘‘indirect effects’’ to provide
clarification to be used with paragraph
(1) of Section D, District Engineer’s
Decision. We have adapted this
definition from the Council on
Environmental Quality’s definition in
their National Environmental Policy Act
regulations at 40 CFR 1508.8(b).
Intermittent stream. We did not
receive any comments on the proposed
definition. The definition is adopted as
proposed.
Loss of waters of the United States.
We did not propose any changes to the
definition. One commenter said the loss
of stream bed should be defined. One
commenter suggested revising this
definition to state that waters of United
States temporarily filled, flooded,
excavated, or drained, but restored to
pre-construction contours and
elevations after construction, are not
included in the measurement of loss of
waters of the United States, especially
as it relates to utility line construction.
Another commenter said that
clarification should be provided to state
that for the purposes of the NWPs, the
loss of waters of the United States
generally does not include the cleared
area along the utility line right-of-way
between two poles or towers supporting
overhead power transmission lines. One
commenter requested clarification of
application of this definition to
activities in the ocean, bays, and Great
Lakes, especially in the context of NWP
52 activities. This commenter
recommended stating, for the purposes
of NWP 52, that the loss only applies to
the area of the ocean, bay, or Great
Lakes occupied by wind towers and
associated structures such as
meteorological towers and transformers.
The proposed definition stated that
the loss of stream bed results from
filling or excavating the stream bed, and
we do not believe it is necessary to
change that definition. The proposed
definition also stated that waters of the
United States temporarily filled,
PO 00000
Frm 00080
Fmt 4701
Sfmt 4703
flooded, excavated, or drained, but
restored to pre-construction contours
and elevations after construction, are
not included in the measurement of loss
of waters of the United States. That
provision may apply to temporary
impacts to waters of the United States
caused by utility lines activities, or to
any other activity involving temporary
filling, flooding, excavation, or drainage.
While the presence of an overhead
utility line above waters of the United
States does not constitute a ‘‘loss of
waters of the United States,’’ the
construction of a utility line right-ofway for overhead transmission lines
may result in losses of waters of the
United States if it involves discharges of
dredged or fill material into waters of
the United States that cause permanent
conversions of aquatic areas to dry land
or permanent increases to the bottom
elevation of a waterbody.
The application of this definition to
renewable energy generation facilities in
coastal waters and the Great Lakes
depends on the type of activity. A
structure installed in these waters is
generally not considered to result in a
loss of waters of the United States,
unless it is a pile supported structure
that is constructed by placing a series of
piles so closely together that they have
the effect of fill (see 33 CFR 323.3(c)).
If the construction of these facilities and
associated structures involves the
placement of materials that meet either
the definition of ‘‘discharge of dredged
material’’ at 33 CFR 323.2(d) or
‘‘discharge of fill material’’ at 33 CFR
323.2(f), such as the placement of riprap
at the base of a pile supported structure,
then the area of sea bed or lake bed
covered by that dredged or fill material
would be counted towards the ‘‘loss of
waters of the United States’’ for that
activity.
The definition is adopted as
proposed.
Non-tidal wetland. We did not receive
any comments on the proposed
definition. The definition is adopted as
proposed.
Open water. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Ordinary high water mark. We did not
propose any changes to the definition.
One commenter said the definition
should state that, for flowing waters, the
term ordinary high water mark includes
the bankfull stage or elevation, since
this indicator can be readily delineated
at most locations.
The bankfull elevation is not a useful
tool for identifying the ordinary high
water marks of streams or rivers in some
parts of the country, especially the arid
west. In the arid west, the Corps
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
examines stream geomorphology and
vegetation that is responsive to the
dominant stream discharge to identify
the ordinary high water mark for
intermittent and ephemeral streams (see
‘‘A Field Guide to the Identification of
the Ordinary High Water Mark (OHWM)
in the Arid West Region of the Western
United States: A Delineation Manual’’
published by the Corps Engineer
Research and Development Center,
report number ERDC/CRREL TR–08–12,
dated August 2008).
The definition is adopted as
proposed.
Perennial stream. We did not receive
any comments on the proposed
definition. The definition is adopted as
proposed.
Practicable. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Pre-construction notification. We did
not receive any comments on the
proposed definition. The definition is
adopted as proposed.
Preservation. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Re-establishment. We proposed to
modify this definition by adding ‘‘and
functions’’ to the end of the last
sentence in order to be consistent with
the definition of this term found in 33
CFR 332.2.
Two commenters objected to the
proposed change. The addition of the
phrase ‘‘and functions’’ makes this
definition consistent with the definition
at 33 CFR 332.2, which was
promulgated in 2008. The objective of
re-establishing aquatic resources is to
provide aquatic resource functions.
The definition is adopted as
proposed.
Rehabilitation. We did not propose
any changes to this definition. One
commenter expressed support of this
definition. The definition is adopted as
proposed.
Restoration. We did not propose any
changes to this definition. One
commenter expressed support of this
definition. The definition is adopted as
proposed.
Riffle and pool complex. We did not
receive any comments on the proposed
definition. The definition is adopted as
proposed.
Riparian areas. We did not propose
any changes to this definition, and we
did not receive any comments on the
proposed definition. We have changed
this definition to more accurately
describe where riparian areas occur, and
what types of features may be found in
riparian areas. We have replaced the
word ‘‘waterbody’’ with the phrase
‘‘riverine, lacustrine, estuarine, and
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
marine waters,’’ since the definition of
‘‘waterbody’’ includes wetlands and
wetlands by themselves do not have
riparian areas. We have also added
‘‘wetlands, non-wetland waters, or’’
between the words ‘‘adjacent’’ and
‘‘uplands’’ since riparian areas are not
limited to uplands. There may be
wetlands and non-wetland (open)
waters such as oxbow lakes and ponds
within a riparian area. The definition is
adopted with the modifications
discussed above.
Shellfish seeding. We did not receive
any comments on the proposed
definition. The definition is adopted as
proposed.
Single and complete linear project
and single and complete non-linear
project. We proposed to take the
definition of ‘‘single and complete
project’’ and split it into two definitions
to clarify the use the term ‘‘single and
complete project’’ for linear and nonlinear projects. Our proposal was based
on the definition for ‘‘single and
complete project’’ at 33 CFR 330.2(i)
that was provided in the November 22,
1991, final rule (56 FR 59113).
Many commenters expressed support
for the proposal. Most of these
commenters also agreed that the
independent utility test does not apply
to single and complete linear projects.
They said the proposed definitions will
remove some of the uncertainty and
inconsistencies that currently exist with
respect to how multiple stream and
wetland crossings are evaluated for
linear projects as opposed to non-linear
projects. One commenter asked for
assurance that these new definitions
would not materially affect how the
Corps evaluates separate crossings of
tributaries for the purposes the NWP
program.
These two definitions are consistent
with the NWP regulations and are not
expected to have an effect on the Corps
current practices for implementing the
NWP program for both linear and nonlinear projects.
One commenter opposed
differentiating between linear and nonlinear projects for the purposes of the
definition of single and complete
project. One commenter said that
references to single and complete linear
projects and single and complete nonlinear projects should be removed from
the NWPs. One commenter stated that
these two definitions would complicate
the water quality certification process.
The separate definitions established
in today’s rule will help provide
consistent implementation of the NWP
program by clarifying how the term
‘‘single and complete project’’ should be
applied for different types of activities
PO 00000
Frm 00081
Fmt 4701
Sfmt 4703
10263
authorized by NWP. These definitions
are important for efficient
implementation of the Corps Regulatory
Program and determining whether a
particular regulated activity and any
related regulated activities qualify for
NWP authorization. Therefore, we do
not agree that these terms should be
removed from the NWP program. The
definition of ‘‘single and complete
project’’ for the NWPs has been in place
since 1991 and the separate definitions
provided in today’s final rule are
consistent with the 1991 definition.
Therefore, the use of these definitions
should not complicate the water quality
certification process.
One commenter requested the
addition of examples, such as utility
lines, to the definition of single and
complete linear project. One commenter
asked for clarification on whether the
term independent utility only applies to
non-linear single and complete projects.
Several commenters said the definition
of single and complete linear project
should preclude district engineers from
evaluating separate crossings
cumulatively.
The new definitions distinguish
between linear and non-linear projects
and reflect the fact that while each
single and complete non-linear project
must have independent utility, each
single and complete linear project need
not have independent utility within the
overall linear project. However, separate
linear projects may have independent
utility. To clarify what a linear project
is, we have added a sentence to the
definition of single and complete linear
project to state that a linear project is a
project constructed for the purpose of
getting people, goods, or services from
a point of origin to a terminal point. A
linear project may involve multiple
crossings of streams, wetlands, or other
types of waters from the point of origin
to the terminal point. Roads and
pipelines are examples of linear
projects. While each separate and
distant crossing of a waterbody
associated with a linear project would
be considered a separate single and
complete project for the purposes of the
NWPs, district engineers will also
evaluate the cumulative effects of those
crossings to determine whether they
qualify for NWP authorization.
One commenter said that for an
overall linear project the sum total of
the losses of waters of the United States
associated with that linear project
cannot exceed the acreage or linear foot
limits for an NWP. Several commenters
stated that it was inappropriate to use
multiple NWPs to authorize multiple
crossings associated with one overall
linear project, because it would be
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10264
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
impossible for the district engineer to
determine if the overall project had
minimal adverse effects on the
environment or prevent the Corps from
assessing the cumulative effects caused
by the overall project. One commenter
said these two proposed definitions may
conflict with the NWP general
conditions.
For single and complete linear
projects, each separate and distant
crossing of a waterbody, as well as each
crossing of other waterbodies along the
corridor for the linear project may be
permitted by separate NWP
authorizations. The acreage and other
applicable limits for an NWP would be
applied to each crossing, as long as
those crossings are far enough apart to
be considered separate and distant.
District engineers will evaluate the
cumulative effects of those linear
projects when determining whether
authorization by NWP is appropriate.
The approach to cumulative effects
analysis for linear projects is little
different than the cumulative effects
analysis for other types of NWP
activities, including those
circumstances in which more than one
NWP is used to authorize a single and
complete non-linear project, because
cumulative effects are evaluated on a
regional basis. Cumulative effects
analysis may be done on a watershed
basis, or by using a different type of
geographic area, such as an ecoregion.
One commenter asked how offshore
wind energy projects would be
evaluated in accordance with these
definitions, especially how the turbines,
substations, cables, and associated
infrastructure would be considered as
either single and complete linear
projects or single and complete nonlinear projects.
Deciding which definition to apply to
a particular project depends on the
configuration of the project relative to
the locations of waters of the United
States within the project boundaries.
For offshore wind energy projects, the
turbines would be located on structures
in a single waterbody as would the
transmission cables that transfer the
energy from the turbines to a land-based
substation, while land-based attendant
features might be constructed in
separate waterbodies located within a
tract of land. The off-shore turbine
structures and land-based attendant
features may be considered as a single
and complete non-linear project, while
as discussed above for NWPs 51 and 52,
the utility lines that transfer the energy
from the renewable energy generation
facilities to a distribution system,
regional grid, or other facility may be
considered to be separate single and
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
complete linear projects and may be
authorized under a separate NWP, such
as NWP 12. The district engineer will
have to consider the activity-specific
circumstances when determining which
definition to apply and which NWPs are
appropriate to use.
One commenter asked whether
district engineers have the authority to
change the definitions of single and
complete project or independent utility.
Two commenters said the term
‘‘distant’’ should be defined in ‘‘single
and complete linear project.’’
The definitions provided in today’s
final rule cannot be changed by district
engineers, but those definitions will be
subject to interpretation after these
NWPs go into effect and they are
implemented. It is not practical to
provide specific definition of ‘‘distant’’
since that must be a judgment call by
the district engineer because of the
substantial variability in landscapes and
environmental conditions across the
country.
The definition for ‘‘single and
complete linear project’’ is adopted with
the modification discussed above. The
definition for ‘‘single and complete nonlinear project’’ is adopted as proposed.
Stormwater management. We did not
receive any comments on the proposed
definition. The definition is adopted as
proposed.
Stormwater management facilities.
We did not receive any comments on
the proposed definition. The definition
is adopted as proposed.
Stream bed. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Stream channelization. We did not
receive any comments on the proposed
definition. The definition is adopted as
proposed.
Structure. We did not propose any
changes to the definition. One
commenter requested that we include
bridges and culverts in the definition of
structures.
Depending on how a bridge or culvert
is constructed, and its effects on the
aquatic environment, it may be
considered a structure or fill. The bridge
supports (i.e., bents) may be considered
to be a structure for the purposes of this
definition. However, placement of a
culvert in a water of the United States
can have the effect of raising the bottom
elevation and thus should be regulated
as fill. Accordingly, we are retaining the
definition of structure as is presently
proposed.
Tidal wetland. We did not receive any
comments on the proposed definition.
The definition is adopted as proposed.
Vegetated shallows. We did not
receive any comments on the proposed
PO 00000
Frm 00082
Fmt 4701
Sfmt 4703
definition. The definition is adopted as
proposed.
Waterbody. We did not receive any
comments on the proposed definition,
but we believe some modification of the
definition is necessary to make it
simpler and clearer. The revised
definition simply says that, for the
purposes of the NWPs, a waterbody is
a jurisdictional water of the United
States. We have removed the text
referring to the presence of standing or
flowing water above ground and the
statement that an ordinary high water
mark is an indicator of jurisdiction. The
ordinary high water mark indicates the
lateral extent of jurisdiction for a nonwetland waterbody in the absence of
adjacent wetlands (see 33 CFR
328.4(c)(1)); the jurisdictional status of
the waterbody is determined by
applying the appropriate regulatory or
legal criteria. In cases where the
waterbody is a wetland, the lateral
extent of the waterbody is the wetland
boundary. Likewise, we have revised
the last sentence of this definition by
removing the phrase ‘‘a jurisdictional
waterbody displaying an OHWM or
other indicators of jurisdiction’’ and
replacing it with ‘‘a waterbody
determined to be a water of the United
States under 33 CFR 328.3(a)(1)–(6)’’.
The definition is adopted with the
modifications discussed above.
In addition to the comments
submitted on definitions provided in
the proposed rule, we received a
number of comments suggesting the
addition of more definitions to the
‘‘Definitions’’ section of the NWPs.
One commenter requested that we
define ‘‘discrete event’’ as it pertains to
NWP 3 and NWP 45. One commenter
asked for a definition of mechanized
land clearing as it relates to the first preconstruction notification threshold in
NWP 12, to make it clear whether
activities that only involve the cutting
or removal of vegetation above the
ground are, or are not, regulated
activities. One commenter said that the
definition of fill should be provided in
the NWPs to clarify the types of
materials allowed or prohibited by the
NWPs.
What constitutes a ‘‘discrete event’’
for the purposes of NWPs 3 and 45 is
at the discretion of the district engineer,
and in both NWPs we provide examples
that give context to the term ‘‘discrete
event.’’ In NWP 3, storms, floods, and
fire are examples of discrete events. For
NWP 45, storms and floods provide
examples of discrete events. The
definition of ‘‘discharge of dredged
material’’ at 33 CFR 323.2(d) is used to
determine whether mechanized
landclearing involves a discharge of
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
dredged material that is regulated under
Section 404 of the Clean Water Act.
Project proponents are encouraged to
contact the district engineer to
determine whether a particular activity
involving mechanized clearing of a
utility line right-of-way in a forested
wetland constitutes a regulated activity,
because the equipment and techniques
used are important considerations. The
definition of the term ‘‘fill material’’ is
provided in the Corps regulations at 33
CFR 323.2(e). Nationwide permit
activities must comply with general
condition 6, suitable material, and it is
not feasible to provide a comprehensive
list of the types of materials that may be
used as fill material for NWP activities.
One commenter suggested adding a
definition of ‘‘special aquatic sites’’ in
the NWPs. One commenter said the
definition of special aquatic sites should
include glides, side channels,
floodplains, and other types of habitats
that create and maintain habitat for
salmon and other fish species.
The NWPs have a definition for one
of the special aquatic sites listed in the
404(b)(1) Guidelines, specifically riffle
and pool complexes and vegetated
shallows. Definitions for the other
special aquatic sites, that is, sanctuaries
and refuges, wetlands, mud flats, and
coral reefs, are found at sections 230.40,
230.41, 230.42, and 230.44 of 40 CFR
part 230, respectively. Glides, side
channels, floodplains, and salmon and
fish habitat are not considered special
aquatic sites unless they satisfy the
criteria at 40 CFR 230.40 through
230.45.
help the public find the home page of
the appropriate Corps district office.
Regional Conditioning of the
Nationwide Permits
Concurrent with this Federal Register
notice, district engineers are issuing
local public notices. In addition to the
changes to some NWPs and NWP
conditions required by the Chief of
Engineers, division and district
engineers may propose regional
conditions or propose revocation of
NWP authorization for all, some, or
portions of the NWPs. Regional
conditions may also be required by state
or Tribal water quality certification or
for state Coastal Zone Management Act
consistency. District engineers will
announce regional conditions or
revocations by issuing local public
notices. Information on regional
conditions and revocation can be
obtained from the appropriate district
engineer, as indicated below.
Furthermore, this and additional
information can be obtained on the
Internet at https://
www.saj.usace.army.mil/Divisions/
Regulatory/HQAvatar.htm which will
Delaware
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
10265
Illinois
Contact Information for Corps District
Engineers
Rock Island District Engineer, ATTN:
CEMVR–OD–P, P.O. Box 2004, Rock
Island, IL 61204–2004
Alabama
Indiana
Mobile District Engineer, ATTN:
CESAM–RD, 109 St. Joseph Street,
Mobile, AL 36602–3630
Louisville District Engineer, ATTN:
CELRL–OP–F, P.O. Box 59, Louisville,
KY 40201–0059
Alaska
Iowa
Alaska District Engineer, ATTN:
CEPOA–RD, P.O. Box 6898,
Elmendorf AFB, AK 99506–6898
Rock Island District Engineer, ATTN:
CEMVR–OD–P, P.O. Box 2004, Rock
Island, IL 61204–2004
Arizona
Kansas
Los Angeles District Engineer, ATTN:
CESPL–RG–R, P.O. Box 532711, Los
Angeles, CA 90053–2325
Kansas City District Engineer, ATTN:
CENWK–OD–R, 635 Federal Building,
601 E. 12th Street, Kansas City, MO
64106–2896
Arkansas
Little Rock District Engineer, ATTN:
CESWL–RD, P.O. Box 867, Little
Rock, AR 72203–0867
California
Sacramento District Engineer, ATTN:
CESPK–RD, 1325 J Street,
Sacramento, CA 95814–2922
Colorado
Albuquerque District Engineer, ATTN:
CESPA–OD–R, 4101 Jefferson Plaza
NE., Albuquerque, NM 87109–3435
Connecticut
New England District Engineer, ATTN:
CENAE–R, 696 Virginia Road,
Concord, MA 01742–2751
Philadelphia District Engineer, ATTN:
CENAP–OP–R, Wannamaker
Building, 100 Penn Square East
Philadelphia, PA 19107–3390
Kentucky
Louisville District Engineer, ATTN:
CELRL–OP–F, P.O. Box 59, Louisville,
KY 40201–0059
Louisiana
New Orleans District Engineer, ATTN:
CEMVN–OD–S, P.O. Box 60267, New
Orleans, LA 70160–0267
Maine
New England District Engineer, ATTN:
CENAE–R, 696 Virginia Road,
Concord, MA 01742–2751
Maryland
Baltimore District Engineer, ATTN:
CENAB–OP–R, P.O. Box 1715,
Baltimore, MD 21203–1715
Massachusetts
New England District Engineer, ATTN:
CENAE–R, 696 Virginia Road,
Concord, MA 01742–2751
Florida
Michigan
Jacksonville District Engineer, ATTN:
CESAJ–RD, P. O. Box 4970,
Jacksonville, FL 32232–0019
Detroit District Engineer, ATTN:
CELRE–RG, 477 Michigan Avenue,
Detroit, MI 48226–2550
Georgia
Minnesota
Savannah District Engineer, ATTN:
CESAS–RD, 100 West Oglethorpe
Avenue, Savannah, GA 31401–3640
St. Paul District Engineer, ATTN:
CEMVP–OP–R, 180 Fifth Street East,
Suite 700, St. Paul, MN 55101–1678
Hawaii
Mississippi
Honolulu District Engineer, ATTN:
CEPOH–EC–R, Building 230, Fort
Shafter, Honolulu, HI 96858–5440
Vicksburg District Engineer, ATTN:
CEMVK–OD–F, 4155 Clay Street,
Vicksburg, MS 39183–3435
Idaho
Missouri
Walla Walla District Engineer, ATTN:
CENWW–RD, 201 North Third
Avenue, Walla Walla, WA 99362–
1876
Kansas City District Engineer, ATTN:
CENWK–OD–R, 635 Federal Building,
601 E. 12th Street, Kansas City, MO
64106–2896
PO 00000
Frm 00083
Fmt 4701
Sfmt 4703
E:\FR\FM\21FEN2.SGM
21FEN2
10266
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Montana
Omaha District Engineer, ATTN:
CENWO–OD–R, 1616 Capitol Avenue,
Omaha, NE 68102–4901
South Carolina
Charleston District Engineer, ATTN:
CESAC–CO–P, P.O. Box 919,
Charleston, SC 29402–0919
Nebraska
Omaha District Engineer, ATTN:
CENWO–OD–R, 1616 Capitol Avenue,
Omaha, NE 68102–4901
South Dakota
Omaha District Engineer, ATTN:
CENWO–OD–R, 1616 Capitol Avenue,
Omaha, NE 68102–4901
Nevada
Sacramento District Engineer, ATTN:
CESPK–CO–R, 1325 J Street,
Sacramento, CA 95814–2922
Tennessee
Nashville District Engineer, ATTN:
CELRN–OP–F, 3701 Bell Road,
Nashville, TN 37214
New Hampshire
New England District Engineer, ATTN:
CENAE–R, 696 Virginia Road,
Concord, MA 01742–2751
Texas
Galveston District Engineer, ATTN:
CESWG–PE–R, P.O. Box 1229,
Galveston, TX 77553–1229
New Jersey
Philadelphia District Engineer, ATTN:
CENAP–OP–R, Wannamaker
Building, 100 Penn Square East,
Philadelphia, PA 19107–3390
Utah
Sacramento District Engineer, ATTN:
CESPK–RD, 1325 J Street, CA 95814–
2922
New Mexico
Albuquerque District Engineer, ATTN:
CESPA–OD–R, 4101 Jefferson Plaza
NE., Albuquerque, NM 87109–3435
New York
New York District Engineer, ATTN:
CENAN–OP–R, 26 Federal Plaza, New
York, NY 10278–0090
North Carolina
Wilmington District Engineer, ATTN:
CESAW–RG, P.O. Box 1890,
Wilmington, NC 28402–1890
North Dakota
Omaha District Engineer, ATTN:
CENWO–OD–R, 1616 Capitol Avenue,
Omaha, NE 68102–4901
Ohio
Huntington District Engineer, ATTN:
CELRH–OR–F, 502 8th Street,
Huntington, WV 25701–2070
Oklahoma
Tulsa District Engineer, ATTN: CESWT–
RO, 1645 S. 101st East Ave., Tulsa,
OK 74128–4609
Virginia
Norfolk District Engineer, ATTN:
CENAO–WR–R, 803 Front Street,
Norfolk, VA 23510–1096
Washington
Seattle District Engineer, ATTN:
CENWS–OP–RG, P.O. Box 3755,
Seattle, WA 98124–3755
West Virginia
Huntington District Engineer, ATTN:
CELRH–OR–F, 502 8th Street,
Huntington, WV 25701–2070
Wisconsin
St. Paul District Engineer, ATTN:
CEMVP–OP–R, 180 Fifth Street East,
Suite 700, St. Paul, MN 55101–1678
Wyoming
Omaha District Engineer, ATTN:
CENWO–OD–R, 1616 Capitol Avenue,
Omaha, NE 68102–4901
Pennsylvania
Baltimore District Engineer, ATTN:
CENAB–OP–R, P.O. Box 1715,
Baltimore, MD 21203–1715
District of Columbia
Baltimore District Engineer, ATTN:
CENAB–OP–R, P.O. Box 1715,
Baltimore, MD 21203–1715
Pacific Territories (American Samoa,
Guam, & Commonwealth of the
Northern Mariana Islands)
Honolulu District Engineer, ATTN:
CEPOH–EC–R, Building 230, Fort
Shafter, Honolulu, HI 96858–5440
Rhode Island
New England District Engineer, ATTN:
CENAE–R, 696 Virginia Road,
Concord, MA 01742–2751
Puerto Rico and Virgin Islands
Jacksonville District Engineer, ATTN:
CESAJ–RD, P.O. Box 4970,
Jacksonville, FL 32232–0019
Oregon
Portland District Engineer, ATTN:
CENWP–OD–G, P.O. Box 2946,
Portland, OR 97208–2946
sroberts on DSK5SPTVN1PROD with NOTICES
Vermont
New England District Engineer, ATTN:
CENAE–R, 696 Virginia Road,
Concord, MA 01742–2751
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
PO 00000
Frm 00084
Fmt 4701
Sfmt 4703
Administrative Requirements
Plain Language
In compliance with the principles in
the President’s Memorandum of June 1,
1998, (63 FR 31855) regarding plain
language, this preamble is written using
plain language. The use of ‘‘we’’ in this
notice refers to the Corps. We have also
used the active voice, short sentences,
and common everyday terms except for
necessary technical terms.
Paperwork Reduction Act
These NWPs will result in a net
decrease in the number of permittees
who are required to submit a preconstruction notification, especially
because of the changes to NWP 48. The
content of the pre-construction
notification is not changed from the
current NWPs, and the paperwork
burden will decrease because of the
reduced number of pre-construction
notifications submitted. The Corps
estimates the decreased paperwork
burden to be 4,005 hours per year. This
is based on an average burden to
complete and submit a pre-construction
notification of 11 hours, and an
estimated 45 NWP 48 activities that will
still require pre-construction
notifications, rather than 3,150 NWP 48
activities that were previously estimated
to require either reporting or preconstruction notification. Prospective
permittees who are required to submit a
pre-construction notification for a
particular NWP, or who are requesting
verification that a particular activity
qualifies for NWP authorization, may
use the current standard Department of
the Army permit application form or
submit the required information in a
letter. The total burden for filing preconstruction notifications is estimated
at 330,000 hours per year (11 hours
times 30,000 activities per year
requiring pre-construction notification).
An agency may not conduct or
sponsor, and a person is not required to
respond to, a collection of information
unless it displays a currently valid
Office of Management and Budget
(OMB) control number. For the Corps
Regulatory Program under Section 10 of
the Rivers and Harbors Act of 1899,
Section 404 of the Clean Water Act, and
Section 103 of the Marine Protection,
Research and Sanctuaries Act of 1972,
the current OMB approval number for
information collection requirements is
maintained by the Corps of Engineers
(OMB approval number 0710–0003,
which expires on August 31, 2012).
Executive Orders 12866 and 13563
Under Executive Order 12866 (58 FR
51735, October 4, 1993) and 13563 (76
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
FR 3821), we must determine whether
the regulatory action is ‘‘significant’’
and therefore subject to review by OMB
and the requirements of the Executive
Orders. The Executive Orders define
‘‘significant regulatory action’’ as one
that is likely to result in a rule that may:
(1) Have an annual effect on the
economy of $100 million or more or
adversely affect in a material way the
economy, a sector of the economy,
productivity, competition, jobs, the
environment, public health or safety, or
State, local, or tribal governments or
communities;
(2) Create a serious inconsistency or
otherwise interfere with an action taken
or planned by another agency;
(3) Materially alter the budgetary
impact of entitlements, grants, user fees,
or loan programs or the rights and
obligations of recipients thereof; or
(4) Raise novel legal or policy issues
arising out of legal mandates, the
President’s priorities, or the principles
set forth in the Executive Order.
Pursuant to the terms of Executive
Orders 12866 and 13563, we determined
that this action is a ‘‘significant
regulatory action’’ and it was submitted
to OMB for review. It is a significant
regulatory action because it meets the
fourth criterion in the Executive Order.
The most substantive changes to these
NWPs are the additional limits imposed
on NWP 21, which authorizes
discharges of dredged or fill material
into waters of the United States
associated with surface coal mining
activities, the issuance of NWPs 51 and
52, which authorize activities associated
with renewable energy generation
facilities, and the modifications to NWP
48 which authorize existing and new
commercial shellfish aquaculture
activities.
The changes to the NWPs that are
most likely to result in additional
economic costs are the changes to NWP
21, especially the 1⁄2-acre and 300 linear
foot limits and the prohibition against
discharges of dredged or fill material to
construct valley fills. We have prepared
a brief economic analysis to estimate the
additional costs that will be imposed on
the regulated public as a result of the
change to the NWPs. It is available in
the docket for this action at
www.regulations.gov, docket number
COE–2010–0035.
The issuance of NWPs 51 and 52 will
reduce the number of renewable energy
generation facilities involving activities
regulated under section 404 and/or
section 10 requiring individual permits.
While some components of land-based
renewable energy generation facilities,
such as road crossings, utility lines, and
building pads involving discharges of
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
dredged or fill material into waters of
the United States, have been authorized
by NWPs such as NWPs 14, 12, and 39
in the past, the new NWP 51 will
provide DA authorization for all
components of land-based renewable
energy generation facilities that involve
discharges of dredged or fill material
into waters of the United States. There
was no NWP authorization available for
water-based renewable energy
generation pilot projects, so the new
NWP 52 will reduce the number of
those activities that require individual
permits.
The NWPs support the goals of
Executive Order 13563, ‘‘Improving
Regulation and Regulatory Review’’ by
reducing burdens on the regulated
public through a streamlined process for
obtaining Department of the Army
authorization for activities that will
result in minimal individual and
cumulative adverse effects on the
aquatic environment. The NWPs
reissued today, when considered as an
overall package of NWPs, will authorize
more activities than were previously
authorized by NWP, such as waterbased renewable energy pilot projects
and new commercial shellfish
aquaculture activities.
Executive Order 13132
Executive Order 13132, entitled
‘‘Federalism’’ (64 FR 43255, August 10,
1999), requires the Corps to develop an
accountable process to ensure
‘‘meaningful and timely input by State
and local officials in the development of
regulatory policies that have federalism
implications.’’ The issuance of NWPs
does not have federalism implications.
We do not believe that the NWPs will
have substantial direct effects on the
States, on the relationship between the
Federal government and the States, or
on the distribution of power and
responsibilities among the various
levels of government. The NWPs will
not impose any additional substantive
obligations on State or local
governments. Therefore, Executive
Order 13132 does not apply to these
final NWPs.
Regulatory Flexibility Act, as Amended
by the Small Business Regulatory
Enforcement Fairness Act of 1996, 5
U.S.C. 601 et seq.
The Regulatory Flexibility Act
generally requires an agency to prepare
a regulatory flexibility analysis of any
rule subject to notice-and-comment
rulemaking requirements under the
Administrative Procedure Act or any
other statute unless the agency certifies
that the rule will not have a significant
economic impact on a substantial
PO 00000
Frm 00085
Fmt 4701
Sfmt 4703
10267
number of small entities. Small entities
include small businesses, small
organizations, and small governmental
jurisdictions.
For purposes of assessing the impacts
of the proposed issuance and
modification of NWPs on small entities,
a small entity is defined as: (1) A small
business based on Small Business
Administration size standards; (2) a
small governmental jurisdiction that is a
government of a city, county, town,
school district, or special district with a
population of less than 50,000; or (3) a
small organization that is any not-forprofit enterprise which is independently
owned and operated and is not
dominant in its field.
The statutes under which the Corps
issues, reissues, or modifies NWPs are
Section 404(e) of the Clean Water Act
(33 U.S.C. 1344(e)) and Section 10 of the
Rivers and Harbors Act of 1899 (33
U.S.C. 403). Under section 404,
Department of the Army (DA) permits
are required for discharges of dredged or
fill material into waters of the United
States. Under section 10, DA permits are
required for any structures or other
work that affect the course, location, or
condition of navigable waters of the
United States. Small entities proposing
to discharge dredged or fill material into
waters of the United States and/or
conduct work in navigable waters of the
United States must obtain DA permits to
conduct those activities, unless a
particular activity is exempt from those
permit requirements. Individual permits
and general permits can be issued by the
Corps to satisfy the permit requirements
of these two statutes. Nationwide
permits are a form of general permit
issued by the Chief of Engineers.
Nationwide permits automatically
expire and become null and void if they
are not modified or reissued within five
years of their effective date (see 33 CFR
330.6(b)). Furthermore, Section 404(e) of
the Clean Water Act states that general
permits, including NWPs, can be issued
for no more than five years. If the
current NWPs are not reissued small
entities and other project proponents
would be required to obtain alternative
forms of DA permits (i.e., standard
permits, letters of permission, or
regional general permits) for activities
involving discharges of dredged or fill
material into waters of the United States
or structures or work in navigable
waters of the United States. Regional
general permits that authorize similar
activities as the NWPs may be available
in some geographic areas, so small
entities conducting regulated activities
outside those geographic areas would
have to obtain individual permits for
activities that require DA permits.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10268
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Nationwide permits help relieve
regulatory burdens on small entities
who need to obtain DA permits. They
provide an expedited form of
authorization, as long as the project
proponent meets all terms and
conditions of the NWPs. In FY 2010, the
Corps issued 32,029 NWP verifications,
with an average processing time of 32
days. Those numbers do not include
activities that are authorized by NWP,
where the project proponent was not
required to submit a pre-construction
notification or did not voluntarily seek
verification that an activity qualified for
NWP authorization. The average
processing time for the 2,085 standard
permits issued during FY 2010 was 221
days. The NWPs issued and reissued
today are expected to result in a slight
increase in the numbers of activities
potentially qualifying for NWP
authorization. The estimated numbers of
activities qualifying for NWP
authorization are provided in the
decision documents that were prepared
for each NWP. The NWPs issued and
reissued today are not expected to
significantly increase cost or paperwork
burden for authorized activities (relative
to the NWPs issued in 2007), including
those conducted by small businesses.
The costs for obtaining coverage
under an NWP are low. We estimate the
average time to prepare and file a preconstruction notification, for those
activities where a pre-construction
notification is required, is 11 hours. We
do not believe this constitutes a
‘‘significant economic impact’’ on
project proponents, including small
businesses.
Another requirement of Section 404(e)
of the Clean Water Act is that general
permits, including NWPs, authorize
only those activities that result in
minimal adverse environmental effects,
individually and cumulatively. The
terms and conditions of the NWPs, such
as acreage or linear foot limits, are
imposed to ensure that the NWPs
authorize only those activities that
result in minimal adverse effects on the
aquatic environment and other public
interest review factors. In addition to
the paperwork burden of filing a preconstruction notification, many NWPs
require that low-cost, commonsense
practices be used to minimize adverse
effects. These requirements also do not
constitute ‘‘significant economic
impacts.’’
After considering the economic
impacts of these NWPs on small
entities, I certify that this action will not
have a significant impact on a
substantial number of small entities.
Small entities may obtain required DA
authorizations through the NWPs, in
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
cases where there are applicable NWPs
authorizing those activities and the
proposed work will result in minimal
adverse effects on the aquatic
environment and other public interest
review factors. The terms and
conditions of these NWPs will not
generally impose significant economic
costs on small entities, and do not
generally impose higher costs on small
entities than those of the previous
NWPs. If an NWP is not available to
authorize a particular activity, then
another form of DA authorization, such
as an individual permit or regional
general permit, must be secured.
However, as noted above, we expect a
slight increase in the number of
activities that can be authorized through
these NWPs, because we are issuing two
new NWPs and making substantial
changes to NWP 48. The changes to
NWP 48, commercial shellfish
aquaculture activities, will result in
fewer project proponents having to
submit pre-construction notifications or
reports to Corps districts. We have also
modified NWP 48 to authorize new
commercial shellfish aquaculture
activities, which were not previously
authorized by NWP. While we are
making substantial changes to NWP 21,
we are also providing NWP 21
authorization without the new limits for
surface coal mining activities previously
authorized under the 2007 NWP 21, to
have an equitable transition for those
surface coal mining activities that
cannot complete the authorized work by
March 18, 2013. For new NWP 21
activities subject to the new limits and
prohibition against valley fills, where
the project proponent is considered a
small entity, the changes to that NWP
will not result in a significant economic
impact because the costs for obtaining
an NWP 21 authorization is generally
higher when compared to other NWPs,
and approach the costs for obtaining an
individual permit.
Unfunded Mandates Reform Act
Title II of the Unfunded Mandates
Reform Act of 1995 (UMRA), Public
Law 104–4, establishes requirements for
Federal agencies to assess the effects of
their regulatory actions on State, local,
and tribal governments and the private
sector. Under Section 202 of the UMRA,
the agencies generally must prepare a
written statement, including a costbenefit analysis, for proposed and final
rules with ‘‘federal mandates’’ that may
result in expenditures to State, local,
and tribal governments, in the aggregate,
or to the private sector, of $100 million
or more in any one year. Before
promulgating a rule for which a written
statement is needed, Section 205 of the
PO 00000
Frm 00086
Fmt 4701
Sfmt 4703
UMRA generally requires the agencies
to identify and consider a reasonable
number of regulatory alternatives and
adopt the least costly, most costeffective, or least burdensome
alternative that achieves the objectives
of the rule. The provisions of section
205 do not apply when they are
inconsistent with applicable law.
Moreover, section 205 allows an agency
to adopt an alternative other than the
least costly, most cost-effective, or least
burdensome alternative if the agency
publishes with the final rule an
explanation why that alternative was
not adopted. Before an agency
establishes any regulatory requirements
that may significantly or uniquely affect
small governments, including tribal
governments, it must have developed,
under Section 203 of the UMRA, a small
government agency plan. The plan must
provide for notifying potentially
affected small governments, enabling
officials of affected small governments
to have meaningful and timely input in
the development of regulatory proposals
with significant federal
intergovernmental mandates, and
informing, educating, and advising
small governments on compliance with
the regulatory requirements.
We have determined that the NWPs
issued today do not contain a Federal
mandate that may result in expenditures
of $100 million or more for State, local,
and Tribal governments, in the
aggregate, or the private sector in any
one year. The NWPs are generally
consistent with current agency practice,
do not impose new substantive
requirements and therefore do not
contain a Federal mandate that may
result in expenditures of $100 million or
more for State, local, and Tribal
governments, in the aggregate, or the
private sector in any one year.
Therefore, the NWPs issued today are
not subject to the requirements of
Sections 202 and 205 of the UMRA. For
the same reasons, we have determined
that the NWPs contains no regulatory
requirements that might significantly or
uniquely affect small governments.
Therefore, the issuance of NWPs is not
subject to the requirements of Section
203 of UMRA.
Executive Order 13045
Executive Order 13045, ‘‘Protection of
Children from Environmental Health
Risks and Safety Risks’’ (62 FR 19885,
April 23, 1997), applies to any rule that:
(1) Is determined to be ‘‘economically
significant’’ as defined under Executive
Order 12866, and (2) concerns an
environmental health or safety risk that
we have reason to believe may have a
disproportionate effect on children. If
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
the regulatory action meets both criteria,
we must evaluate the environmental
health or safety effects of the proposed
rule on children, and explain why the
regulation is preferable to other
potentially effective and reasonably
feasible alternatives.
The NWPs issued today are not
subject to this Executive Order because
they are not economically significant as
defined in Executive Order 12866. In
addition, these NWPs do not concern an
environmental or safety risk that we
have reason to believe may have a
disproportionate effect on children.
Executive Order 13175
Executive Order 13175, entitled
‘‘Consultation and Coordination with
Indian Tribal Governments’’ (65 FR
67249, November 6, 2000), requires
agencies to develop an accountable
process to ensure ‘‘meaningful and
timely input by tribal officials in the
development of regulatory policies that
have tribal implications.’’ The phrase
‘‘policies that have tribal implications’’
is defined in the Executive Order to
include regulations that have
‘‘substantial direct effects on one or
more Indian tribes, on the relationship
between the Federal government and
the Indian tribes, or on the distribution
of power and responsibilities between
the Federal government and Indian
tribes.’’
The NWPs issued today do not have
tribal implications. They are generally
consistent with current agency practice
and will not have substantial direct
effects on tribal governments, on the
relationship between the Federal
government and the Indian tribes, or on
the distribution of power and
responsibilities between the Federal
government and Indian tribes.
Therefore, Executive Order 13175 does
not apply to this proposal. Corps
districts are conducting government-togovernment consultation with Indian
tribes to develop regional conditions
that help protect tribal rights and trust
resources, and to facilitate compliance
with general condition 17, Tribal Rights.
sroberts on DSK5SPTVN1PROD with NOTICES
Environmental Documentation
A decision document, which includes
an environmental assessment and
Finding of No Significant Impact
(FONSI), has been prepared for each
NWP. These decision documents are
available at: https://www.regulations.gov
(docket ID number COE–2010–0035).
They are also available by contacting
Headquarters, U.S. Army Corps of
Engineers, Operations and Regulatory
Community of Practice, 441 G Street
NW., Washington, DC 20314–1000.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
Congressional Review Act
The Congressional Review Act, 5
U.S.C. 801 et seq., as added by the Small
Business Regulatory Enforcement
Fairness Act of 1996, generally provides
that before a rule may take effect, the
agency promulgating the rule must
submit a rule report, which includes a
copy of the rule, to each House of the
Congress and to the Comptroller General
of the United States. We will submit a
report containing the final NWPs and
other required information to the U.S.
Senate, the U.S. House of
Representatives, and the Comptroller
General of the United States. A major
rule cannot take effect until 60 days
after it is published in the Federal
Register. The proposed NWPs are not a
‘‘major rule’’ as defined by 5 U.S.C.
804(2).
Executive Order 12898
Executive Order 12898 requires that,
to the greatest extent practicable and
permitted by law, each Federal agency
must make achieving environmental
justice part of its mission. Executive
Order 12898 provides that each federal
agency conduct its programs, policies,
and activities that substantially affect
human health or the environment in a
manner that ensures that such programs,
policies, and activities do not have the
effect of excluding persons (including
populations) from participation in,
denying persons (including
populations) the benefits of, or
subjecting persons (including
populations) to discrimination under
such programs, policies, and activities
because of their race, color, or national
origin.
The NWPs issued today are not
expected to negatively impact any
community, and therefore are not
expected to cause any
disproportionately high and adverse
impacts to minority or low-income
communities.
Executive Order 13211
The NWPs are not a ‘‘significant
energy action’’ as defined in Executive
Order 13211, ‘‘Actions Concerning
Regulations That Significantly Affect
Energy Supply, Distribution, or Use’’ (66
FR 28355, May 22, 2001) because it is
not likely to have a significant adverse
effect on the supply, distribution, or use
of energy. Some of the NWPs authorize
activities that support the supply and
distribution of energy.
Authority
We are issuing new NWPs and
reissuing existing NWPs under the
authority of Section 404(e) of the Clean
Water Act (33 U.S.C. 1344) and Section
PO 00000
Frm 00087
Fmt 4701
Sfmt 4703
10269
10 of the Rivers and Harbors Act of 1899
(33 U.S.C. 401 et seq.).
Dated: February 13, 2012.
Michael J. Walsh,
Major General, US Army, Deputy
Commanding General for Civil and
Emergency Operations.
Nationwide Permits, Conditions,
Further Information, and Definitions
A. Index of Nationwide Permits,
Conditions, District Engineer’s Decision,
Further Information, and Definitions
Nationwide Permits
1. Aids to Navigation
2. Structures in Artificial Canals
3. Maintenance
4. Fish and Wildlife Harvesting,
Enhancement, and Attraction Devices
and Activities
5. Scientific Measurement Devices
6. Survey Activities
7. Outfall Structures and Associated
Intake Structures
8. Oil and Gas Structures on the Outer
Continental Shelf
9. Structures in Fleeting and Anchorage
Areas
10. Mooring Buoys
11. Temporary Recreational Structures
12. Utility Line Activities
13. Bank Stabilization
14. Linear Transportation Projects
15. U.S. Coast Guard Approved Bridges
16. Return Water From Upland
Contained Disposal Areas
17. Hydropower Projects
18. Minor Discharges
19. Minor Dredging
20. Response Operations for Oil and
Hazardous Substances
21. Surface Coal Mining Activities
22. Removal of Vessels
23. Approved Categorical Exclusions
24. Indian Tribe or State Administered
Section 404 Programs
25. Structural Discharges
26. [Reserved]
27. Aquatic Habitat Restoration,
Establishment, and Enhancement
Activities
28. Modifications of Existing Marinas
29. Residential Developments
30. Moist Soil Management for Wildlife
31. Maintenance of Existing Flood
Control Facilities
32. Completed Enforcement Actions
33. Temporary Construction, Access,
and Dewatering
34. Cranberry Production Activities
35. Maintenance Dredging of Existing
Basins
36. Boat Ramps
37. Emergency Watershed Protection
and Rehabilitation
38. Cleanup of Hazardous and Toxic
Waste
E:\FR\FM\21FEN2.SGM
21FEN2
10270
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
39. Commercial and Institutional
Developments
40. Agricultural Activities
41. Reshaping Existing Drainage Ditches
42. Recreational Facilities
43. Stormwater Management Facilities
44. Mining Activities
45. Repair of Uplands Damaged by
Discrete Events
46. Discharges in Ditches
47. [Reserved]
48. Commercial Shellfish Aquaculture
Activities
49. Coal Remining Activities
50. Underground Coal Mining Activities
51. Land-Based Renewable Energy
Generation Facilities
52. Water-Based Renewable Energy
Generation Pilot Projects
Nationwide Permit General Conditions
1. Navigation
2. Aquatic Life Movements
3. Spawning Areas
4. Migratory Bird Breeding Areas
5. Shellfish Beds
6. Suitable Material
7. Water Supply Intakes
8. Adverse Effects From Impoundments
9. Management of Water Flows
10. Fills Within 100–Year Floodplains
11. Equipment
12. Soil Erosion and Sediment Controls
13. Removal of Temporary Fills
14. Proper Maintenance
15. Single and Complete Project
16. Wild and Scenic Rivers
17. Tribal Rights
18. Endangered Species
19. Migratory Bird and Bald and Golden
Eagle Permits
20. Historic Properties
21. Discovery of Previously Unknown
Remains and Artifacts
22. Designated Critical Resource Waters
23. Mitigation
24. Safety of Impoundment Structures
25. Water Quality
26. Coastal Zone Management
27. Regional and Case-by-Case
Conditions
28. Use of Multiple Nationwide Permits
29. Transfer of Nationwide Permit
Verifications
30. Compliance Certification
31. Pre-Construction Notification
District Engineer’s Decision
Further Information
sroberts on DSK5SPTVN1PROD with NOTICES
Definitions
Best management practices (BMPs)
Compensatory mitigation
Currently serviceable
Direct effects
Discharge
Enhancement
Ephemeral stream
Establishment (creation)
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
High Tide Line
Historic property
Independent utility
Indirect effects
Intermittent stream
Loss of waters of the United States
Non-tidal wetland
Open water
Ordinary high water mark
Perennial stream
Practicable
Pre-construction notification
Preservation
Re-establishment
Rehabilitation
Restoration
Riffle and pool complex
Riparian areas
Shellfish seeding
Single and complete linear project
Single and complete non-linear project
Stormwater management
Stormwater management facilities
Stream bed
Stream channelization
Structure
Tidal wetland
Vegetated shallows
Waterbody
B. Nationwide Permits
1. Aids to Navigation. The placement
of aids to navigation and regulatory
markers which are approved by and
installed in accordance with the
requirements of the U.S. Coast Guard
(see 33 CFR, chapter I, subchapter C,
part 66). (Section 10)
2. Structures in Artificial Canals.
Structures constructed in artificial
canals within principally residential
developments where the connection of
the canal to a navigable water of the
United States has been previously
authorized (see 33 CFR 322.5(g)).
(Section 10)
3. Maintenance. (a) The repair,
rehabilitation, or replacement of any
previously authorized, currently
serviceable structure, or fill, or of any
currently serviceable structure or fill
authorized by 33 CFR 330.3, provided
that the structure or fill is not to be put
to uses differing from those uses
specified or contemplated for it in the
original permit or the most recently
authorized modification. Minor
deviations in the structure’s
configuration or filled area, including
those due to changes in materials,
construction techniques, requirements
of other regulatory agencies, or current
construction codes or safety standards
that are necessary to make the repair,
rehabilitation, or replacement are
authorized. Any stream channel
modification is limited to the minimum
necessary for the repair, rehabilitation,
or replacement of the structure or fill;
PO 00000
Frm 00088
Fmt 4701
Sfmt 4703
such modifications, including the
removal of material from the stream
channel, must be immediately adjacent
to the project or within the boundaries
of the structure or fill. This NWP also
authorizes the repair, rehabilitation, or
replacement of those structures or fills
destroyed or damaged by storms, floods,
fire or other discrete events, provided
the repair, rehabilitation, or replacement
is commenced, or is under contract to
commence, within two years of the date
of their destruction or damage. In cases
of catastrophic events, such as
hurricanes or tornadoes, this two-year
limit may be waived by the district
engineer, provided the permittee can
demonstrate funding, contract, or other
similar delays.
(b) This NWP also authorizes the
removal of accumulated sediments and
debris in the vicinity of existing
structures (e.g., bridges, culverted road
crossings, water intake structures, etc.)
and/or the placement of new or
additional riprap to protect the
structure. The removal of sediment is
limited to the minimum necessary to
restore the waterway in the vicinity of
the structure to the approximate
dimensions that existed when the
structure was built, but cannot extend
farther than 200 feet in any direction
from the structure. This 200 foot limit
does not apply to maintenance dredging
to remove accumulated sediments
blocking or restricting outfall and intake
structures or to maintenance dredging to
remove accumulated sediments from
canals associated with outfall and intake
structures. All dredged or excavated
materials must be deposited and
retained in an area that has no waters of
the United States unless otherwise
specifically approved by the district
engineer under separate authorization.
The placement of new or additional
riprap must be the minimum necessary
to protect the structure or to ensure the
safety of the structure. Any bank
stabilization measures not directly
associated with the structure will
require a separate authorization from
the district engineer.
(c) This NWP also authorizes
temporary structures, fills, and work
necessary to conduct the maintenance
activity. Appropriate measures must be
taken to maintain normal downstream
flows and minimize flooding to the
maximum extent practicable, when
temporary structures, work, and
discharges, including cofferdams, are
necessary for construction activities,
access fills, or dewatering of
construction sites. Temporary fills must
consist of materials, and be placed in a
manner, that will not be eroded by
expected high flows. Temporary fills
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
must be removed in their entirety and
the affected areas returned to preconstruction elevations. The areas
affected by temporary fills must be
revegetated, as appropriate.
(d) This NWP does not authorize
maintenance dredging for the primary
purpose of navigation. This NWP does
not authorize beach restoration. This
NWP does not authorize new stream
channelization or stream relocation
projects.
Notification: For activities authorized
by paragraph (b) of this NWP, the
permittee must submit a preconstruction notification to the district
engineer prior to commencing the
activity (see general condition 31). The
pre-construction notification must
include information regarding the
original design capacities and
configurations of the outfalls, intakes,
small impoundments, and canals.
(Sections 10 and 404)
sroberts on DSK5SPTVN1PROD with NOTICES
Note: This NWP authorizes the repair,
rehabilitation, or replacement of any
previously authorized structure or fill that
does not qualify for the Clean Water Act
Section 404(f) exemption for maintenance.
4. Fish and Wildlife Harvesting,
Enhancement, and Attraction Devices
and Activities. Fish and wildlife
harvesting devices and activities such as
pound nets, crab traps, crab dredging,
eel pots, lobster traps, duck blinds, and
clam and oyster digging, fish aggregating
devices, and small fish attraction
devices such as open water fish
concentrators (sea kites, etc.). This NWP
does not authorize artificial reefs or
impoundments and semiimpoundments of waters of the United
States for the culture or holding of
motile species such as lobster, or the use
of covered oyster trays or clam racks.
(Sections 10 and 404)
5. Scientific Measurement Devices.
Devices, whose purpose is to measure
and record scientific data, such as staff
gages, tide and current gages,
meteorological stations, water recording
and biological observation devices,
water quality testing and improvement
devices, and similar structures. Small
weirs and flumes constructed primarily
to record water quantity and velocity are
also authorized provided the discharge
is limited to 25 cubic yards. Upon
completion of the use of the device to
measure and record scientific data, the
measuring device and any other
structures or fills associated with that
device (e.g., foundations, anchors,
buoys, lines, etc.) must be removed to
the maximum extent practicable and the
site restored to pre-construction
elevations. (Sections 10 and 404)
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
6. Survey Activities. Survey activities,
such as core sampling, seismic
exploratory operations, plugging of
seismic shot holes and other
exploratory-type bore holes, exploratory
trenching, soil surveys, sampling,
sample plots or transects for wetland
delineations, and historic resources
surveys. For the purposes of this NWP,
the term ‘‘exploratory trenching’’ means
mechanical land clearing of the upper
soil profile to expose bedrock or
substrate, for the purpose of mapping or
sampling the exposed material. The area
in which the exploratory trench is dug
must be restored to its pre-construction
elevation upon completion of the work
and must not drain a water of the
United States. In wetlands, the top 6 to
12 inches of the trench should normally
be backfilled with topsoil from the
trench. This NWP authorizes the
construction of temporary pads,
provided the discharge does not exceed
1⁄10-acre in waters of the U.S. Discharges
and structures associated with the
recovery of historic resources are not
authorized by this NWP. Drilling and
the discharge of excavated material from
test wells for oil and gas exploration are
not authorized by this NWP; the
plugging of such wells is authorized.
Fill placed for roads and other similar
activities is not authorized by this NWP.
The NWP does not authorize any
permanent structures. The discharge of
drilling mud and cuttings may require a
permit under Section 402 of the Clean
Water Act. (Sections 10 and 404)
7. Outfall Structures and Associated
Intake Structures. Activities related to
the construction or modification of
outfall structures and associated intake
structures, where the effluent from the
outfall is authorized, conditionally
authorized, or specifically exempted by,
or otherwise in compliance with
regulations issued under the National
Pollutant Discharge Elimination System
Program (Section 402 of the Clean Water
Act). The construction of intake
structures is not authorized by this
NWP, unless they are directly associated
with an authorized outfall structure.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
8. Oil and Gas Structures on the Outer
Continental Shelf. Structures for the
exploration, production, and
transportation of oil, gas, and minerals
on the outer continental shelf within
areas leased for such purposes by the
Department of Interior, Bureau of Ocean
Energy Management. Such structures
shall not be placed within the limits of
any designated shipping safety fairway
PO 00000
Frm 00089
Fmt 4701
Sfmt 4703
10271
or traffic separation scheme, except
temporary anchors that comply with the
fairway regulations in 33 CFR 322.5(l).
The district engineer will review such
proposals to ensure compliance with the
provisions of the fairway regulations in
33 CFR 322.5(l). Any Corps review
under this NWP will be limited to the
effects on navigation and national
security in accordance with 33 CFR
322.5(f), as well as 33 CFR 322.5(l) and
33 CFR part 334. Such structures will
not be placed in established danger
zones or restricted areas as designated
in 33 CFR part 334, nor will such
structures be permitted in EPA or Corps
designated dredged material disposal
areas.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Section 10)
9. Structures in Fleeting and
Anchorage Areas. Structures, buoys,
floats and other devices placed within
anchorage or fleeting areas to facilitate
moorage of vessels where the U.S. Coast
Guard has established such areas for
that purpose. (Section 10)
10. Mooring Buoys. Non-commercial,
single-boat, mooring buoys. (Section 10)
11. Temporary Recreational
Structures. Temporary buoys, markers,
small floating docks, and similar
structures placed for recreational use
during specific events such as water
skiing competitions and boat races or
seasonal use, provided that such
structures are removed within 30 days
after use has been discontinued. At
Corps of Engineers reservoirs, the
reservoir manager must approve each
buoy or marker individually. (Section
10)
12. Utility Line Activities. Activities
required for the construction,
maintenance, repair, and removal of
utility lines and associated facilities in
waters of the United States, provided
the activity does not result in the loss
of greater than 1⁄2-acre of waters of the
United States for each single and
complete project.
Utility lines: This NWP authorizes the
construction, maintenance, or repair of
utility lines, including outfall and
intake structures, and the associated
excavation, backfill, or bedding for the
utility lines, in all waters of the United
States, provided there is no change in
pre-construction contours. A ‘‘utility
line’’ is defined as any pipe or pipeline
for the transportation of any gaseous,
liquid, liquescent, or slurry substance,
for any purpose, and any cable, line, or
wire for the transmission for any
purpose of electrical energy, telephone,
and telegraph messages, and radio and
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10272
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
television communication. The term
‘‘utility line’’ does not include activities
that drain a water of the United States,
such as drainage tile or french drains,
but it does apply to pipes conveying
drainage from another area.
Material resulting from trench
excavation may be temporarily sidecast
into waters of the United States for no
more than three months, provided the
material is not placed in such a manner
that it is dispersed by currents or other
forces. The district engineer may extend
the period of temporary side casting for
no more than a total of 180 days, where
appropriate. In wetlands, the top 6 to 12
inches of the trench should normally be
backfilled with topsoil from the trench.
The trench cannot be constructed or
backfilled in such a manner as to drain
waters of the United States (e.g.,
backfilling with extensive gravel layers,
creating a french drain effect). Any
exposed slopes and stream banks must
be stabilized immediately upon
completion of the utility line crossing of
each waterbody.
Utility line substations: This NWP
authorizes the construction,
maintenance, or expansion of substation
facilities associated with a power line or
utility line in non-tidal waters of the
United States, provided the activity, in
combination with all other activities
included in one single and complete
project, does not result in the loss of
greater than 1⁄2-acre of waters of the
United States. This NWP does not
authorize discharges into non-tidal
wetlands adjacent to tidal waters of the
United States to construct, maintain, or
expand substation facilities.
Foundations for overhead utility line
towers, poles, and anchors: This NWP
authorizes the construction or
maintenance of foundations for
overhead utility line towers, poles, and
anchors in all waters of the United
States, provided the foundations are the
minimum size necessary and separate
footings for each tower leg (rather than
a larger single pad) are used where
feasible.
Access roads: This NWP authorizes
the construction of access roads for the
construction and maintenance of utility
lines, including overhead power lines
and utility line substations, in non-tidal
waters of the United States, provided
the activity, in combination with all
other activities included in one single
and complete project, does not cause the
loss of greater than 1⁄2-acre of non-tidal
waters of the United States. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters
for access roads. Access roads must be
the minimum width necessary (see Note
2, below). Access roads must be
constructed so that the length of the
VerDate Mar<15>2010
20:03 Feb 17, 2012
Jkt 226001
road minimizes any adverse effects on
waters of the United States and must be
as near as possible to pre-construction
contours and elevations (e.g., at grade
corduroy roads or geotextile/gravel
roads). Access roads constructed above
pre-construction contours and
elevations in waters of the United States
must be properly bridged or culverted to
maintain surface flows.
This NWP may authorize utility lines
in or affecting navigable waters of the
United States even if there is no
associated discharge of dredged or fill
material (See 33 CFR Part 322).
Overhead utility lines constructed over
section 10 waters and utility lines that
are routed in or under section 10 waters
without a discharge of dredged or fill
material require a section 10 permit.
This NWP also authorizes temporary
structures, fills, and work necessary to
conduct the utility line activity.
Appropriate measures must be taken to
maintain normal downstream flows and
minimize flooding to the maximum
extent practicable, when temporary
structures, work, and discharges,
including cofferdams, are necessary for
construction activities, access fills, or
dewatering of construction sites.
Temporary fills must consist of
materials, and be placed in a manner,
that will not be eroded by expected high
flows. Temporary fills must be removed
in their entirety and the affected areas
returned to pre-construction elevations.
The areas affected by temporary fills
must be revegetated, as appropriate.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity if any of the
following criteria are met: (1) The
activity involves mechanized land
clearing in a forested wetland for the
utility line right-of-way; (2) a section 10
permit is required; (3) the utility line in
waters of the United States, excluding
overhead lines, exceeds 500 feet; (4) the
utility line is placed within a
jurisdictional area (i.e., water of the
United States), and it runs parallel to or
along a stream bed that is within that
jurisdictional area; (5) discharges that
result in the loss of greater than 1⁄10-acre
of waters of the United States; (6)
permanent access roads are constructed
above grade in waters of the United
States for a distance of more than 500
feet; or (7) permanent access roads are
constructed in waters of the United
States with impervious materials. (See
general condition 31.) (Sections 10 and
404)
Note 1: Where the proposed utility line is
constructed or installed in navigable waters
of the United States (i.e., section 10 waters)
within the coastal United States, the Great
Lakes, and United States territories, copies of
PO 00000
Frm 00090
Fmt 4701
Sfmt 4703
the pre-construction notification and NWP
verification will be sent by the Corps to the
National Oceanic and Atmospheric
Administration (NOAA), National Ocean
Service (NOS), for charting the utility line to
protect navigation.
Note 2: Access roads used for both
construction and maintenance may be
authorized, provided they meet the terms and
conditions of this NWP. Access roads used
solely for construction of the utility line must
be removed upon completion of the work, in
accordance with the requirements for
temporary fills.
Note 3: Pipes or pipelines used to transport
gaseous, liquid, liquescent, or slurry
substances over navigable waters of the
United States are considered to be bridges,
not utility lines, and may require a permit
from the U.S. Coast Guard pursuant to
Section 9 of the Rivers and Harbors Act of
1899. However, any discharges of dredged or
fill material into waters of the United States
associated with such pipelines will require a
section 404 permit (see NWP 15).
Note 4: For overhead utility lines
authorized by this NWP, a copy of the PCN
and NWP verification will be provided to the
Department of Defense Siting Clearinghouse,
which will evaluate potential effects on
military activities.
13. Bank Stabilization. Bank
stabilization activities necessary for
erosion prevention, provided the
activity meets all of the following
criteria:
(a) No material is placed in excess of
the minimum needed for erosion
protection;
(b) The activity is no more than 500
feet in length along the bank, unless the
district engineer waives this criterion by
making a written determination
concluding that the discharge will result
in minimal adverse effects;
(c) The activity will not exceed an
average of one cubic yard per running
foot placed along the bank below the
plane of the ordinary high water mark
or the high tide line, unless the district
engineer waives this criterion by making
a written determination concluding that
the discharge will result in minimal
adverse effects;
(d) The activity does not involve
discharges of dredged or fill material
into special aquatic sites, unless the
district engineer waives this criterion by
making a written determination
concluding that the discharge will result
in minimal adverse effects;
(e) No material is of a type, or is
placed in any location, or in any
manner, that will impair surface water
flow into or out of any waters of the
United States;
(f) No material is placed in a manner
that will be eroded by normal or
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
expected high flows (properly anchored
trees and treetops may be used in low
energy areas); and,
(g) The activity is not a stream
channelization activity.
This NWP also authorizes temporary
structures, fills, and work necessary to
construct the bank stabilization activity.
Appropriate measures must be taken to
maintain normal downstream flows and
minimize flooding to the maximum
extent practicable, when temporary
structures, work, and discharges,
including cofferdams, are necessary for
construction activities, access fills, or
dewatering of construction sites.
Temporary fills must consist of
materials, and be placed in a manner,
that will not be eroded by expected high
flows. Temporary fills must be removed
in their entirety and the affected areas
returned to pre-construction elevations.
The areas affected by temporary fills
must be revegetated, as appropriate.
Invasive plant species shall not be
used for bioengineering or vegetative
bank stabilization.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity if the bank
stabilization activity: (1) Involves
discharges into special aquatic sites; or
(2) is in excess of 500 feet in length; or
(3) will involve the discharge of greater
than an average of one cubic yard per
running foot along the bank below the
plane of the ordinary high water mark
or the high tide line. (See general
condition 31.) (Sections 10 and 404)
14. Linear Transportation Projects.
Activities required for the construction,
expansion, modification, or
improvement of linear transportation
projects (e.g., roads, highways, railways,
trails, airport runways, and taxiways) in
waters of the United States. For linear
transportation projects in non-tidal
waters, the discharge cannot cause the
loss of greater than 1⁄2-acre of waters of
the United States. For linear
transportation projects in tidal waters,
the discharge cannot cause the loss of
greater than 1/3-acre of waters of the
United States. Any stream channel
modification, including bank
stabilization, is limited to the minimum
necessary to construct or protect the
linear transportation project; such
modifications must be in the immediate
vicinity of the project.
This NWP also authorizes temporary
structures, fills, and work necessary to
construct the linear transportation
project. Appropriate measures must be
taken to maintain normal downstream
flows and minimize flooding to the
maximum extent practicable, when
temporary structures, work, and
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
discharges, including cofferdams, are
necessary for construction activities,
access fills, or dewatering of
construction sites. Temporary fills must
consist of materials, and be placed in a
manner, that will not be eroded by
expected high flows. Temporary fills
must be removed in their entirety and
the affected areas returned to preconstruction elevations. The areas
affected by temporary fills must be
revegetated, as appropriate.
This NWP cannot be used to authorize
non-linear features commonly
associated with transportation projects,
such as vehicle maintenance or storage
buildings, parking lots, train stations, or
aircraft hangars.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity if: (1) The loss
of waters of the United States exceeds
1⁄10-acre; or (2) there is a discharge in a
special aquatic site, including wetlands.
(See general condition 31.) (Sections 10
and 404)
Note: Some discharges for the construction
of farm roads or forest roads, or temporary
roads for moving mining equipment, may
qualify for an exemption under Section 404(f)
of the Clean Water Act (see 33 CFR 323.4).
15. U.S. Coast Guard Approved
Bridges. Discharges of dredged or fill
material incidental to the construction
of a bridge across navigable waters of
the United States, including cofferdams,
abutments, foundation seals, piers, and
temporary construction and access fills,
provided the construction of the bridge
structure has been authorized by the
U.S. Coast Guard under Section 9 of the
Rivers and Harbors Act of 1899 and
other applicable laws. Causeways and
approach fills are not included in this
NWP and will require a separate section
404 permit. (Section 404)
16. Return Water From Upland
Contained Disposal Areas. Return water
from an upland contained dredged
material disposal area. The return water
from a contained disposal area is
administratively defined as a discharge
of dredged material by 33 CFR 323.2(d),
even though the disposal itself occurs in
an area that has no waters of the United
States and does not require a section
404 permit. This NWP satisfies the
technical requirement for a section 404
permit for the return water where the
quality of the return water is controlled
by the state through the section 401
certification procedures. The dredging
activity may require a section 404
permit (33 CFR 323.2(d)), and will
require a section 10 permit if located in
navigable waters of the United States.
(Section 404)
PO 00000
Frm 00091
Fmt 4701
Sfmt 4703
10273
17. Hydropower Projects. Discharges
of dredged or fill material associated
with hydropower projects having: (a)
Less than 5000 kW of total generating
capacity at existing reservoirs, where
the project, including the fill, is licensed
by the Federal Energy Regulatory
Commission (FERC) under the Federal
Power Act of 1920, as amended; or (b)
a licensing exemption granted by the
FERC pursuant to Section 408 of the
Energy Security Act of 1980 (16 U.S.C.
2705 and 2708) and Section 30 of the
Federal Power Act, as amended.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Section 404)
18. Minor Discharges. Minor
discharges of dredged or fill material
into all waters of the United States,
provided the activity meets all of the
following criteria:
(a) The quantity of discharged
material and the volume of area
excavated do not exceed 25 cubic yards
below the plane of the ordinary high
water mark or the high tide line;
(b) The discharge will not cause the
loss of more than 1⁄10-acre of waters of
the United States; and
(c) The discharge is not placed for the
purpose of a stream diversion.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity if: (1) The
discharge or the volume of area
excavated exceeds 10 cubic yards below
the plane of the ordinary high water
mark or the high tide line, or (2) the
discharge is in a special aquatic site,
including wetlands. (See general
condition 31.) (Sections 10 and 404)
19. Minor Dredging. Dredging of no
more than 25 cubic yards below the
plane of the ordinary high water mark
or the mean high water mark from
navigable waters of the United States
(i.e., section 10 waters). This NWP does
not authorize the dredging or
degradation through siltation of coral
reefs, sites that support submerged
aquatic vegetation (including sites
where submerged aquatic vegetation is
documented to exist but may not be
present in a given year), anadromous
fish spawning areas, or wetlands, or the
connection of canals or other artificial
waterways to navigable waters of the
United States (see 33 CFR 322.5(g)).
(Sections 10 and 404)
20. Response Operations for Oil and
Hazardous Substances. Activities
conducted in response to a discharge or
release of oil and hazardous substances
that are subject to the National Oil and
Hazardous Substances Pollution
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10274
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Contingency Plan (40 CFR part 300)
including containment, cleanup, and
mitigation efforts, provided that the
activities are done under either: (1) The
Spill Control and Countermeasure Plan
required by 40 CFR 112.3; (2) the
direction or oversight of the federal onscene coordinator designated by 40 CFR
part 300; or (3) any approved existing
state, regional or local contingency plan
provided that the Regional Response
Team (if one exists in the area) concurs
with the proposed response efforts. This
NWP also authorizes activities required
for the cleanup of oil releases in waters
of the United States from electrical
equipment that are governed by EPA’s
polychlorinated biphenyl spill response
regulations at 40 CFR part 761. This
NWP also authorizes the use of
temporary structures and fills in waters
of the U.S. for spill response training
exercises. (Sections 10 and 404)
21. Surface Coal Mining Activities.
Discharges of dredged or fill material
into waters of the United States
associated with surface coal mining and
reclamation operations.
(a) Previously Authorized Surface
Coal Mining Activities. Surface coal
mining activities that were previously
authorized by the NWP 21 issued on
March 12, 2007 (see 72 FR 11092), are
authorized by this NWP, provided the
following criteria are met:
(1) The activities are already
authorized, or are currently being
processed by states with approved
programs under Title V of the Surface
Mining Control and Reclamation Act of
1977 or as part of an integrated permit
processing procedure by the Department
of Interior, Office of Surface Mining
Reclamation and Enforcement;
(2) The permittee must submit a letter
to the district engineer requesting reverification of the NWP 21
authorization. The letter must describe
any changes from the previous NWP 21
verification. The letter must be
submitted to the district engineer by
February 1, 2013;
(3) The loss of waters of the United
States is not greater than the loss of
waters of the United States previously
verified by the district engineer under
the NWP 21 issued on March 12, 2007
(i.e., there are no proposed expansions
of surface coal mining activities in
waters of the United States);
(4) The district engineer provides
written verification that those activities
will result in minimal individual and
cumulative adverse effects and are
authorized by NWP 21, including
currently applicable regional conditions
and any activity-specific conditions
added to the NWP authorization by the
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
district engineer, such as compensatory
mitigation requirements; and
(5) If the permittee does not receive a
written verification from the district
engineer prior to March 18, 2013, the
permittee must cease all activities until
such verification is received. The
district engineer may extend the
February 1, 2013, deadline by so
notifying the permittee in writing, but
the permittee must still cease all
activities if he or she has not received
written verification from the Corps by
March 18, 2013, until such verification
is received.
(b) Other Surface Coal Mining
Activities. Surface coal mining activities
that were not previously authorized by
the NWP 21 issued on March 12, 2007,
are authorized by this NWP, provided
the following criteria are met:
(1) The activities are already
authorized, or are currently being
processed by states with approved
programs under Title V of the Surface
Mining Control and Reclamation Act of
1977 or as part of an integrated permit
processing procedure by the Department
of Interior, Office of Surface Mining
Reclamation and Enforcement;
(2) The discharge must not cause the
loss of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal individual and cumulative
adverse effects. This NWP does not
authorize discharges into tidal waters or
non-tidal wetlands adjacent to tidal
waters; and
(3) The discharge is not associated
with the construction of valley fills. A
‘‘valley fill’’ is a fill structure that is
typically constructed within valleys
associated with steep, mountainous
terrain, associated with surface coal
mining activities.
Notification: For activities under
paragraph (b) of this NWP, the permittee
must submit a pre-construction
notification to the district engineer and
receive written authorization prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
22. Removal of Vessels. Temporary
structures or minor discharges of
dredged or fill material required for the
removal of wrecked, abandoned, or
disabled vessels, or the removal of manmade obstructions to navigation. This
NWP does not authorize maintenance
dredging, shoal removal, or riverbank
snagging.
Notification: The permittee must
submit a pre-construction notification to
PO 00000
Frm 00092
Fmt 4701
Sfmt 4703
the district engineer prior to
commencing the activity if: (1) The
vessel is listed or eligible for listing in
the National Register of Historic Places;
or (2) the activity is conducted in a
special aquatic site, including coral
reefs and wetlands. (See general
condition 31.) If condition 1 above is
triggered, the permittee cannot
commence the activity until informed
by the district engineer that compliance
with the ‘‘Historic Properties’’ general
condition is completed. (Sections 10
and 404)
Note 1: If a removed vessel is disposed of
in waters of the United States, a permit from
the U.S. EPA may be required (see 40 CFR
229.3). If a Department of the Army permit
is required for vessel disposal in waters of
the United States, separate authorization will
be required.
Note 2: Compliance with general condition
18, Endangered Species, and general
condition 20, Historic Properties, is required
for all NWPs. The concern with historic
properties is emphasized in the notification
requirements for this NWP because of the
likelihood that submerged vessels may be
historic properties.
23. Approved Categorical Exclusions.
Activities undertaken, assisted,
authorized, regulated, funded, or
financed, in whole or in part, by another
Federal agency or department where:
(a) That agency or department has
determined, pursuant to the Council on
Environmental Quality’s implementing
regulations for the National
Environmental Policy Act (40 CFR part
1500 et seq.), that the activity is
categorically excluded from
environmental documentation, because
it is included within a category of
actions which neither individually nor
cumulatively have a significant effect on
the human environment; and
(b) The Office of the Chief of
Engineers (Attn: CECW–CO) has
concurred with that agency’s or
department’s determination that the
activity is categorically excluded and
approved the activity for authorization
under NWP 23.
The Office of the Chief of Engineers
may require additional conditions,
including pre-construction notification,
for authorization of an agency’s
categorical exclusions under this NWP.
Notification: Certain categorical
exclusions approved for authorization
under this NWP require the permittee to
submit a pre-construction notification to
the district engineer prior to
commencing the activity (see general
condition 31). The activities that require
pre-construction notification are listed
in the appropriate Regulatory Guidance
Letters. (Sections 10 and 404)
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
Note: The agency or department may
submit an application for an activity believed
to be categorically excluded to the Office of
the Chief of Engineers (Attn: CECW–CO).
Prior to approval for authorization under this
NWP of any agency’s activity, the Office of
the Chief of Engineers will solicit public
comment. As of the date of issuance of this
NWP, agencies with approved categorical
exclusions are the: Bureau of Reclamation,
Federal Highway Administration, and U.S.
Coast Guard. Activities approved for
authorization under this NWP as of the date
of this notice are found in Corps Regulatory
Guidance Letter 05–07, which is available at:
https://www.usace.army.mil/Missions/
CivilWorks/RegulatoryProgramandPermits/
GuidanceLetters.aspx. Any future approved
categorical exclusions will be announced in
Regulatory Guidance Letters and posted on
this same Web site.
24. Indian Tribe or State
Administered Section 404 Programs.
Any activity permitted by a state or
Indian Tribe administering its own
section 404 permit program pursuant to
33 U.S.C. 1344(g)–(l) is permitted
pursuant to Section 10 of the Rivers and
Harbors Act of 1899. (Section 10)
Note 1: As of the date of the promulgation
of this NWP, only New Jersey and Michigan
administer their own section 404 permit
programs.
sroberts on DSK5SPTVN1PROD with NOTICES
Note 2: Those activities that do not involve
an Indian Tribe or State section 404 permit
are not included in this NWP, but certain
structures will be exempted by Section 154
of Public Law 94–587, 90 Stat. 2917 (33
U.S.C. 591) (see 33 CFR 322.4(b)).
25. Structural Discharges. Discharges
of material such as concrete, sand, rock,
etc., into tightly sealed forms or cells
where the material will be used as a
structural member for standard pile
supported structures, such as bridges,
transmission line footings, and
walkways, or for general navigation,
such as mooring cells, including the
excavation of bottom material from
within the form prior to the discharge of
concrete, sand, rock, etc. This NWP
does not authorize filled structural
members that would support buildings,
building pads, homes, house pads,
parking areas, storage areas and other
such structures. The structure itself may
require a separate section 10 permit if
located in navigable waters of the
United States. (Section 404)
26. [Reserved]
27. Aquatic Habitat Restoration,
Establishment, and Enhancement
Activities. Activities in waters of the
United States associated with the
restoration, enhancement, and
establishment of tidal and non-tidal
wetlands and riparian areas, the
restoration and enhancement of nontidal streams and other non-tidal open
waters, and the rehabilitation or
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
enhancement of tidal streams, tidal
wetlands, and tidal open waters,
provided those activities result in net
increases in aquatic resource functions
and services.
To the extent that a Corps permit is
required, activities authorized by this
NWP include, but are not limited to:
The removal of accumulated sediments;
the installation, removal, and
maintenance of small water control
structures, dikes, and berms, as well as
discharges of dredged or fill material to
restore appropriate stream channel
configurations after small water control
structures, dikes, and berms, are
removed; the installation of current
deflectors; the enhancement,
restoration, or establishment of riffle
and pool stream structure; the
placement of in-stream habitat
structures; modifications of the stream
bed and/or banks to restore or establish
stream meanders; the backfilling of
artificial channels; the removal of
existing drainage structures, such as
drain tiles, and the filling, blocking, or
reshaping of drainage ditches to restore
wetland hydrology; the installation of
structures or fills necessary to establish
or re-establish wetland or stream
hydrology; the construction of small
nesting islands; the construction of open
water areas; the construction of oyster
habitat over unvegetated bottom in tidal
waters; shellfish seeding; activities
needed to reestablish vegetation,
including plowing or discing for seed
bed preparation and the planting of
appropriate wetland species; reestablishment of submerged aquatic
vegetation in areas where those plant
communities previously existed; reestablishment of tidal wetlands in tidal
waters where those wetlands previously
existed; mechanized land clearing to
remove non-native invasive, exotic, or
nuisance vegetation; and other related
activities. Only native plant species
should be planted at the site.
This NWP authorizes the relocation of
non-tidal waters, including non-tidal
wetlands and streams, on the project
site provided there are net increases in
aquatic resource functions and services.
Except for the relocation of non-tidal
waters on the project site, this NWP
does not authorize the conversion of a
stream or natural wetlands to another
aquatic habitat type (e.g., stream to
wetland or vice versa) or uplands.
Changes in wetland plant communities
that occur when wetland hydrology is
more fully restored during wetland
rehabilitation activities are not
considered a conversion to another
aquatic habitat type. This NWP does not
authorize stream channelization. This
NWP does not authorize the relocation
PO 00000
Frm 00093
Fmt 4701
Sfmt 4703
10275
of tidal waters or the conversion of tidal
waters, including tidal wetlands, to
other aquatic uses, such as the
conversion of tidal wetlands into open
water impoundments.
Compensatory mitigation is not
required for activities authorized by this
NWP since these activities must result
in net increases in aquatic resource
functions and services.
Reversion. For enhancement,
restoration, and establishment activities
conducted: (1) In accordance with the
terms and conditions of a binding
stream or wetland enhancement or
restoration agreement, or a wetland
establishment agreement, between the
landowner and the U.S. Fish and
Wildlife Service (FWS), the Natural
Resources Conservation Service (NRCS),
the Farm Service Agency (FSA), the
National Marine Fisheries Service
(NMFS), the National Ocean Service
(NOS), U.S. Forest Service (USFS), or
their designated state cooperating
agencies; (2) as voluntary wetland
restoration, enhancement, and
establishment actions documented by
the NRCS or USDA Technical Service
Provider pursuant to NRCS Field Office
Technical Guide standards; or (3) on
reclaimed surface coal mine lands, in
accordance with a Surface Mining
Control and Reclamation Act permit
issued by the Office of Surface Mining
Reclamation and Enforcement (OSMRE)
or the applicable state agency, this NWP
also authorizes any future discharge of
dredged or fill material associated with
the reversion of the area to its
documented prior condition and use
(i.e., prior to the restoration,
enhancement, or establishment
activities). The reversion must occur
within five years after expiration of a
limited term wetland restoration or
establishment agreement or permit, and
is authorized in these circumstances
even if the discharge occurs after this
NWP expires. The five-year reversion
limit does not apply to agreements
without time limits reached between the
landowner and the FWS, NRCS, FSA,
NMFS, NOS, USFS, or an appropriate
state cooperating agency. This NWP also
authorizes discharges of dredged or fill
material in waters of the United States
for the reversion of wetlands that were
restored, enhanced, or established on
prior-converted cropland or on uplands,
in accordance with a binding agreement
between the landowner and NRCS, FSA,
FWS, or their designated state
cooperating agencies (even though the
restoration, enhancement, or
establishment activity did not require a
section 404 permit). The prior condition
will be documented in the original
agreement or permit, and the
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10276
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
determination of return to prior
conditions will be made by the Federal
agency or appropriate state agency
executing the agreement or permit.
Before conducting any reversion activity
the permittee or the appropriate Federal
or state agency must notify the district
engineer and include the documentation
of the prior condition. Once an area has
reverted to its prior physical condition,
it will be subject to whatever the Corps
Regulatory requirements are applicable
to that type of land at the time. The
requirement that the activity results in
a net increase in aquatic resource
functions and services does not apply to
reversion activities meeting the above
conditions. Except for the activities
described above, this NWP does not
authorize any future discharge of
dredged or fill material associated with
the reversion of the area to its prior
condition. In such cases a separate
permit would be required for any
reversion.
Reporting. For those activities that do
not require pre-construction
notification, the permittee must submit
to the district engineer a copy of: (1) The
binding stream enhancement or
restoration agreement or wetland
enhancement, restoration, or
establishment agreement, or a project
description, including project plans and
location map; (2) the NRCS or USDA
Technical Service Provider
documentation for the voluntary stream
enhancement or restoration action or
wetland restoration, enhancement, or
establishment action; or (3) the SMCRA
permit issued by OSMRE or the
applicable state agency. The report must
also include information on baseline
ecological conditions on the project site,
such as a delineation of wetlands,
streams, and/or other aquatic habitats.
These documents must be submitted to
the district engineer at least 30 days
prior to commencing activities in waters
of the United States authorized by this
NWP.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing any activity (see general
condition 31), except for the following
activities:
(1) Activities conducted on nonFederal public lands and private lands,
in accordance with the terms and
conditions of a binding stream
enhancement or restoration agreement
or wetland enhancement, restoration, or
establishment agreement between the
landowner and the U.S. FWS, NRCS,
FSA, NMFS, NOS, USFS or their
designated state cooperating agencies;
(2) Voluntary stream or wetland
restoration or enhancement action, or
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
wetland establishment action,
documented by the NRCS or USDA
Technical Service Provider pursuant to
NRCS Field Office Technical Guide
standards; or
(3) The reclamation of surface coal
mine lands, in accordance with an
SMCRA permit issued by the OSMRE or
the applicable state agency.
However, the permittee must submit a
copy of the appropriate documentation
to the district engineer to fulfill the
reporting requirement. (Sections 10 and
404)
Note: This NWP can be used to authorize
compensatory mitigation projects, including
mitigation banks and in-lieu fee projects.
However, this NWP does not authorize the
reversion of an area used for a compensatory
mitigation project to its prior condition, since
compensatory mitigation is generally
intended to be permanent.
28. Modifications of Existing Marinas.
Reconfiguration of existing docking
facilities within an authorized marina
area. No dredging, additional slips, dock
spaces, or expansion of any kind within
waters of the United States is authorized
by this NWP. (Section 10)
29. Residential Developments.
Discharges of dredged or fill material
into non-tidal waters of the United
States for the construction or expansion
of a single residence, a multiple unit
residential development, or a residential
subdivision. This NWP authorizes the
construction of building foundations
and building pads and attendant
features that are necessary for the use of
the residence or residential
development. Attendant features may
include but are not limited to roads,
parking lots, garages, yards, utility lines,
storm water management facilities,
septic fields, and recreation facilities
such as playgrounds, playing fields, and
golf courses (provided the golf course is
an integral part of the residential
development).
The discharge must not cause the loss
of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
Subdivisions: For residential
subdivisions, the aggregate total loss of
waters of United States authorized by
this NWP cannot exceed 1⁄2-acre. This
includes any loss of waters of the
United States associated with
development of individual subdivision
lots.
PO 00000
Frm 00094
Fmt 4701
Sfmt 4703
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
30. Moist Soil Management for
Wildlife. Discharges of dredged or fill
material into non-tidal waters of the
United States and maintenance
activities that are associated with moist
soil management for wildlife for the
purpose of continuing ongoing, sitespecific, wildlife management activities
where soil manipulation is used to
manage habitat and feeding areas for
wildlife. Such activities include, but are
not limited to, plowing or discing to
impede succession, preparing seed beds,
or establishing fire breaks. Sufficient
riparian areas must be maintained
adjacent to all open water bodies,
including streams, to preclude water
quality degradation due to erosion and
sedimentation. This NWP does not
authorize the construction of new dikes,
roads, water control structures, or
similar features associated with the
management areas. The activity must
not result in a net loss of aquatic
resource functions and services. This
NWP does not authorize the conversion
of wetlands to uplands, impoundments,
or other open water bodies. (Section
404)
Note: The repair, maintenance, or
replacement of existing water control
structures or the repair or maintenance of
dikes may be authorized by NWP 3. Some
such activities may qualify for an exemption
under Section 404(f) of the Clean Water Act
(see 33 CFR 323.4).
31. Maintenance of Existing Flood
Control Facilities. Discharges of dredged
or fill material resulting from activities
associated with the maintenance of
existing flood control facilities,
including debris basins, retention/
detention basins, levees, and channels
that: (i) Were previously authorized by
the Corps by individual permit, general
permit, or 33 CFR 330.3, or did not
require a permit at the time they were
constructed, or (ii) were constructed by
the Corps and transferred to a nonFederal sponsor for operation and
maintenance. Activities authorized by
this NWP are limited to those resulting
from maintenance activities that are
conducted within the ‘‘maintenance
baseline,’’ as described in the definition
below. Discharges of dredged or fill
materials associated with maintenance
activities in flood control facilities in
any watercourse that have previously
been determined to be within the
maintenance baseline are authorized
under this NWP. To the extent that a
Corps permit is required, this NWP
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
authorizes the removal of vegetation
from levees associated with the flood
control project. This NWP does not
authorize the removal of sediment and
associated vegetation from natural water
courses except when these activities
have been included in the maintenance
baseline. All dredged material must be
placed in an area that has no waters of
the United States or a separately
authorized disposal site in waters of the
United States, and proper siltation
controls must be used.
Maintenance Baseline: The
maintenance baseline is a description of
the physical characteristics (e.g., depth,
width, length, location, configuration, or
design flood capacity, etc.) of a flood
control project within which
maintenance activities are normally
authorized by NWP 31, subject to any
case-specific conditions required by the
district engineer. The district engineer
will approve the maintenance baseline
based on the approved or constructed
capacity of the flood control facility,
whichever is smaller, including any
areas where there are no constructed
channels but which are part of the
facility. The prospective permittee will
provide documentation of the physical
characteristics of the flood control
facility (which will normally consist of
as-built or approved drawings) and
documentation of the approved and
constructed design capacities of the
flood control facility. If no evidence of
the constructed capacity exists, the
approved capacity will be used. The
documentation will also include best
management practices to ensure that the
impacts to the aquatic environment are
minimal, especially in maintenance
areas where there are no constructed
channels. (The Corps may request
maintenance records in areas where
there has not been recent maintenance.)
Revocation or modification of the final
determination of the maintenance
baseline can only be done in accordance
with 33 CFR 330.5. Except in
emergencies as described below, this
NWP cannot be used until the district
engineer approves the maintenance
baseline and determines the need for
mitigation and any regional or activityspecific conditions. Once determined,
the maintenance baseline will remain
valid for any subsequent reissuance of
this NWP. This NWP does not authorize
maintenance of a flood control facility
that has been abandoned. A flood
control facility will be considered
abandoned if it has operated at a
significantly reduced capacity without
needed maintenance being
accomplished in a timely manner.
Mitigation: The district engineer will
determine any required mitigation one-
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
time only for impacts associated with
maintenance work at the same time that
the maintenance baseline is approved.
Such one-time mitigation will be
required when necessary to ensure that
adverse environmental impacts are no
more than minimal, both individually
and cumulatively. Such mitigation will
only be required once for any specific
reach of a flood control project.
However, if one-time mitigation is
required for impacts associated with
maintenance activities, the district
engineer will not delay needed
maintenance, provided the district
engineer and the permittee establish a
schedule for identification, approval,
development, construction and
completion of any such required
mitigation. Once the one-time
mitigation described above has been
completed, or a determination made
that mitigation is not required, no
further mitigation will be required for
maintenance activities within the
maintenance baseline. In determining
appropriate mitigation, the district
engineer will give special consideration
to natural water courses that have been
included in the maintenance baseline
and require compensatory mitigation
and/or best management practices as
appropriate.
Emergency Situations: In emergency
situations, this NWP may be used to
authorize maintenance activities in
flood control facilities for which no
maintenance baseline has been
approved. Emergency situations are
those which would result in an
unacceptable hazard to life, a significant
loss of property, or an immediate,
unforeseen, and significant economic
hardship if action is not taken before a
maintenance baseline can be approved.
In such situations, the determination of
mitigation requirements, if any, may be
deferred until the emergency has been
resolved. Once the emergency has
ended, a maintenance baseline must be
established expeditiously, and
mitigation, including mitigation for
maintenance conducted during the
emergency, must be required as
appropriate.
Notification: The permittee must
submit a pre-construction notification to
the district engineer before any
maintenance work is conducted (see
general condition 31). The preconstruction notification may be for
activity-specific maintenance or for
maintenance of the entire flood control
facility by submitting a five-year (or
less) maintenance plan. The preconstruction notification must include a
description of the maintenance baseline
and the dredged material disposal site.
(Sections 10 and 404)
PO 00000
Frm 00095
Fmt 4701
Sfmt 4703
10277
32. Completed Enforcement Actions.
Any structure, work, or discharge of
dredged or fill material remaining in
place or undertaken for mitigation,
restoration, or environmental benefit in
compliance with either:
(i) The terms of a final written Corps
non-judicial settlement agreement
resolving a violation of Section 404 of
the Clean Water Act and/or Section 10
of the Rivers and Harbors Act of 1899;
or the terms of an EPA 309(a) order on
consent resolving a violation of Section
404 of the Clean Water Act, provided
that:
(a) The unauthorized activity affected
no more than 5 acres of non-tidal waters
or 1 acre of tidal waters;
(b) The settlement agreement provides
for environmental benefits, to an equal
or greater degree, than the
environmental detriments caused by the
unauthorized activity that is authorized
by this NWP; and
(c) The district engineer issues a
verification letter authorizing the
activity subject to the terms and
conditions of this NWP and the
settlement agreement, including a
specified completion date; or
(ii) The terms of a final Federal court
decision, consent decree, or settlement
agreement resulting from an
enforcement action brought by the
United States under Section 404 of the
Clean Water Act and/or Section 10 of
the Rivers and Harbors Act of 1899; or
(iii) The terms of a final court
decision, consent decree, settlement
agreement, or non-judicial settlement
agreement resulting from a natural
resource damage claim brought by a
trustee or trustees for natural resources
(as defined by the National Contingency
Plan at 40 CFR subpart G) under Section
311 of the Clean Water Act, Section 107
of the Comprehensive Environmental
Response, Compensation and Liability
Act, Section 312 of the National Marine
Sanctuaries Act, Section 1002 of the Oil
Pollution Act of 1990, or the Park
System Resource Protection Act at 16
U.S.C. 19jj, to the extent that a Corps
permit is required.
Compliance is a condition of the NWP
itself. Any authorization under this
NWP is automatically revoked if the
permittee does not comply with the
terms of this NWP or the terms of the
court decision, consent decree, or
judicial/non-judicial settlement
agreement. This NWP does not apply to
any activities occurring after the date of
the decision, decree, or agreement that
are not for the purpose of mitigation,
restoration, or environmental benefit.
Before reaching any settlement
agreement, the Corps will ensure
compliance with the provisions of 33
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10278
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
CFR part 326 and 33 CFR 330.6(d)(2)
and (e). (Sections 10 and 404)
33. Temporary Construction, Access,
and Dewatering. Temporary structures,
work, and discharges, including
cofferdams, necessary for construction
activities or access fills or dewatering of
construction sites, provided that the
associated primary activity is authorized
by the Corps of Engineers or the U.S.
Coast Guard. This NWP also authorizes
temporary structures, work, and
discharges, including cofferdams,
necessary for construction activities not
otherwise subject to the Corps or U.S.
Coast Guard permit requirements.
Appropriate measures must be taken to
maintain near normal downstream flows
and to minimize flooding. Fill must
consist of materials, and be placed in a
manner, that will not be eroded by
expected high flows. The use of dredged
material may be allowed if the district
engineer determines that it will not
cause more than minimal adverse effects
on aquatic resources. Following
completion of construction, temporary
fill must be entirely removed to an area
that has no waters of the United States,
dredged material must be returned to its
original location, and the affected areas
must be restored to pre-construction
elevations. The affected areas must also
be revegetated, as appropriate. This
permit does not authorize the use of
cofferdams to dewater wetlands or other
aquatic areas to change their use.
Structures left in place after
construction is completed require a
separate section 10 permit if located in
navigable waters of the United States.
(See 33 CFR part 322.)
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity (see general
condition 31). The pre-construction
notification must include a restoration
plan showing how all temporary fills
and structures will be removed and the
area restored to pre-project conditions.
(Sections 10 and 404)
34. Cranberry Production Activities.
Discharges of dredged or fill material for
dikes, berms, pumps, water control
structures or leveling of cranberry beds
associated with expansion,
enhancement, or modification activities
at existing cranberry production
operations. The cumulative total acreage
of disturbance per cranberry production
operation, including but not limited to,
filling, flooding, ditching, or clearing,
must not exceed 10 acres of waters of
the United States, including wetlands.
The activity must not result in a net loss
of wetland acreage. This NWP does not
authorize any discharge of dredged or
fill material related to other cranberry
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
production activities such as
warehouses, processing facilities, or
parking areas. For the purposes of this
NWP, the cumulative total of 10 acres
will be measured over the period that
this NWP is valid.
Notification: The permittee must
submit a pre-construction notification to
the district engineer once during the
period that this NWP is valid, and the
NWP will then authorize discharges of
dredge or fill material at an existing
operation for the permit term, provided
the 10-acre limit is not exceeded. (See
general condition 31.) (Section 404)
35. Maintenance Dredging of Existing
Basins. Excavation and removal of
accumulated sediment for maintenance
of existing marina basins, access
channels to marinas or boat slips, and
boat slips to previously authorized
depths or controlling depths for ingress/
egress, whichever is less, provided the
dredged material is deposited at an area
that has no waters of the United States
site and proper siltation controls are
used. (Section 10)
36. Boat Ramps. Activities required
for the construction of boat ramps,
provided the activity meets all of the
following criteria:
(a) The discharge into waters of the
United States does not exceed 50 cubic
yards of concrete, rock, crushed stone or
gravel into forms, or in the form of precast concrete planks or slabs, unless the
district engineer waives the 50 cubic
yard limit by making a written
determination concluding that the
discharge will result in minimal adverse
effects;
(b) The boat ramp does not exceed 20
feet in width, unless the district
engineer waives this criterion by making
a written determination concluding that
the discharge will result in minimal
adverse effects;
(c) The base material is crushed stone,
gravel or other suitable material;
(d) The excavation is limited to the
area necessary for site preparation and
all excavated material is removed to an
area that has no waters of the United
States; and,
(e) No material is placed in special
aquatic sites, including wetlands.
The use of unsuitable material that is
structurally unstable is not authorized.
If dredging in navigable waters of the
United States is necessary to provide
access to the boat ramp, the dredging
must be authorized by another NWP, a
regional general permit, or an individual
permit.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity if: (1) The
discharge into waters of the United
PO 00000
Frm 00096
Fmt 4701
Sfmt 4703
States exceeds 50 cubic yards, or (2) the
boat ramp exceeds 20 feet in width. (See
general condition 31.) (Sections 10 and
404)
37. Emergency Watershed Protection
and Rehabilitation. Work done by or
funded by:
(a) The Natural Resources
Conservation Service for a situation
requiring immediate action under its
emergency Watershed Protection
Program (7 CFR part 624);
(b) The U.S. Forest Service under its
Burned-Area Emergency Rehabilitation
Handbook (FSH 2509.13);
(c) The Department of the Interior for
wildland fire management burned area
emergency stabilization and
rehabilitation (DOI Manual part 620, Ch.
3);
(d) The Office of Surface Mining, or
states with approved programs, for
abandoned mine land reclamation
activities under Title IV of the Surface
Mining Control and Reclamation Act (30
CFR Subchapter R), where the activity
does not involve coal extraction; or
(e) The Farm Service Agency under its
Emergency Conservation Program (7
CFR part 701).
In general, the prospective permittee
should wait until the district engineer
issues an NWP verification or 45
calendar days have passed before
proceeding with the watershed
protection and rehabilitation activity.
However, in cases where there is an
unacceptable hazard to life or a
significant loss of property or economic
hardship will occur, the emergency
watershed protection and rehabilitation
activity may proceed immediately and
the district engineer will consider the
information in the pre-construction
notification and any comments received
as a result of agency coordination to
decide whether the NWP 37
authorization should be modified,
suspended, or revoked in accordance
with the procedures at 33 CFR 330.5.
Notification: Except in cases where
there is an unacceptable hazard to life
or a significant loss of property or
economic hardship will occur, the
permittee must submit a preconstruction notification to the district
engineer prior to commencing the
activity (see general condition 31).
(Sections 10 and 404)
38. Cleanup of Hazardous and Toxic
Waste. Specific activities required to
effect the containment, stabilization, or
removal of hazardous or toxic waste
materials that are performed, ordered, or
sponsored by a government agency with
established legal or regulatory authority.
Court ordered remedial action plans or
related settlements are also authorized
by this NWP. This NWP does not
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
authorize the establishment of new
disposal sites or the expansion of
existing sites used for the disposal of
hazardous or toxic waste.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
Note: Activities undertaken entirely on a
Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA)
site by authority of CERCLA as approved or
required by EPA, are not required to obtain
permits under Section 404 of the Clean Water
Act or Section 10 of the Rivers and Harbors
Act.
sroberts on DSK5SPTVN1PROD with NOTICES
39. Commercial and Institutional
Developments. Discharges of dredged or
fill material into non-tidal waters of the
United States for the construction or
expansion of commercial and
institutional building foundations and
building pads and attendant features
that are necessary for the use and
maintenance of the structures.
Attendant features may include, but are
not limited to, roads, parking lots,
garages, yards, utility lines, storm water
management facilities, and recreation
facilities such as playgrounds and
playing fields. Examples of commercial
developments include retail stores,
industrial facilities, restaurants,
business parks, and shopping centers.
Examples of institutional developments
include schools, fire stations,
government office buildings, judicial
buildings, public works buildings,
libraries, hospitals, and places of
worship. The construction of new golf
courses and new ski areas is not
authorized by this NWP.
The discharge must not cause the loss
of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
Note: For any activity that involves the
construction of a wind energy generating
structure, solar tower, or overhead
transmission line, a copy of the PCN and
NWP verification will be provided to the
Department of Defense Siting Clearinghouse,
which will evaluate potential effects on
military activities.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
40. Agricultural Activities. Discharges
of dredged or fill material into non-tidal
waters of the United States for
agricultural activities, including the
construction of building pads for farm
buildings. Authorized activities include
the installation, placement, or
construction of drainage tiles, ditches,
or levees; mechanized land clearing;
land leveling; the relocation of existing
serviceable drainage ditches constructed
in waters of the United States; and
similar activities.
This NWP also authorizes the
construction of farm ponds in non-tidal
waters of the United States, excluding
perennial streams, provided the farm
pond is used solely for agricultural
purposes. This NWP does not authorize
the construction of aquaculture ponds.
This NWP also authorizes discharges
of dredged or fill material into non-tidal
waters of the United States to relocate
existing serviceable drainage ditches
constructed in non-tidal streams.
The discharge must not cause the loss
of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Section 404)
Note: Some discharges for agricultural
activities may qualify for an exemption under
Section 404(f) of the Clean Water Act (see 33
CFR 323.4). This NWP authorizes the
construction of farm ponds that do not
qualify for the Clean Water Act Section
404(f)(1)(C) exemption because of the
recapture provision at Section 404(f)(2).
41. Reshaping Existing Drainage
Ditches. Discharges of dredged or fill
material into non-tidal waters of the
United States, excluding non-tidal
wetlands adjacent to tidal waters, to
modify the cross-sectional configuration
of currently serviceable drainage ditches
constructed in waters of the United
States, for the purpose of improving
water quality by regrading the drainage
ditch with gentler slopes, which can
reduce erosion, increase growth of
vegetation, and increase uptake of
nutrients and other substances by
vegetation. The reshaping of the ditch
cannot increase drainage capacity
beyond the original as-built capacity nor
can it expand the area drained by the
ditch as originally constructed (i.e., the
PO 00000
Frm 00097
Fmt 4701
Sfmt 4703
10279
capacity of the ditch must be the same
as originally constructed and it cannot
drain additional wetlands or other
waters of the United States).
Compensatory mitigation is not required
because the work is designed to improve
water quality.
This NWP does not authorize the
relocation of drainage ditches
constructed in waters of the United
States; the location of the centerline of
the reshaped drainage ditch must be
approximately the same as the location
of the centerline of the original drainage
ditch. This NWP does not authorize
stream channelization or stream
relocation projects.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity, if more than
500 linear feet of drainage ditch will be
reshaped. (See general condition 31.)
(Section 404)
42. Recreational Facilities. Discharges
of dredged or fill material into non-tidal
waters of the United States for the
construction or expansion of
recreational facilities. Examples of
recreational facilities that may be
authorized by this NWP include playing
fields (e.g., football fields, baseball
fields), basketball courts, tennis courts,
hiking trails, bike paths, golf courses,
ski areas, horse paths, nature centers,
and campgrounds (excluding
recreational vehicle parks). This NWP
also authorizes the construction or
expansion of small support facilities,
such as maintenance and storage
buildings and stables that are directly
related to the recreational activity, but it
does not authorize the construction of
hotels, restaurants, racetracks, stadiums,
arenas, or similar facilities.
The discharge must not cause the loss
of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Section 404)
43. Stormwater Management
Facilities. Discharges of dredged or fill
material into non-tidal waters of the
United States for the construction of
stormwater management facilities,
including stormwater detention basins
and retention basins and other
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10280
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
stormwater management facilities; the
construction of water control structures,
outfall structures and emergency
spillways; and the construction of low
impact development integrated
management features such as
bioretention facilities (e.g., rain
gardens), vegetated filter strips, grassed
swales, and infiltration trenches. This
NWP also authorizes, to the extent that
a section 404 permit is required,
discharges of dredged or fill material
into non-tidal waters of the United
States for the maintenance of
stormwater management facilities. Note
that stormwater management facilities
that are determined to be waste
treatment systems under 33 CFR
328.3(a)(8) are not waters of the United
States, and maintenance of these waste
treatment systems generally does not
require a section 404 permit.
The discharge must not cause the loss
of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
This NWP does not authorize discharges
of dredged or fill material for the
construction of new stormwater
management facilities in perennial
streams.
Notification: For the construction of
new stormwater management facilities,
or the expansion of existing stormwater
management facilities, the permittee
must submit a pre-construction
notification to the district engineer prior
to commencing the activity. (See general
condition 31.) Maintenance activities do
not require pre-construction notification
if they are limited to restoring the
original design capacities of the
stormwater management facility.
(Section 404)
44. Mining Activities. Discharges of
dredged or fill material into non-tidal
waters of the United States for mining
activities, except for coal mining
activities. The discharge must not cause
the loss of greater than 1⁄2-acre of nontidal waters of the United States,
including the loss of no more than 300
linear feet of stream bed, unless for
intermittent and ephemeral stream beds
the district engineer waives the 300
linear foot limit by making a written
determination concluding that the
discharge will result in minimal adverse
effects. This NWP does not authorize
discharges into non-tidal wetlands
adjacent to tidal waters.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) If reclamation is required
by other statutes, then a copy of the
reclamation plan must be submitted
with the pre-construction notification.
(Sections 10 and 404)
45. Repair of Uplands Damaged by
Discrete Events. This NWP authorizes
discharges of dredged or fill material,
including dredging or excavation, into
all waters of the United States for
activities associated with the restoration
of upland areas damaged by storms,
floods, or other discrete events. This
NWP authorizes bank stabilization to
protect the restored uplands. The
restoration of the damaged areas,
including any bank stabilization, must
not exceed the contours, or ordinary
high water mark, that existed before the
damage occurred. The district engineer
retains the right to determine the extent
of the pre-existing conditions and the
extent of any restoration work
authorized by this NWP. The work must
commence, or be under contract to
commence, within two years of the date
of damage, unless this condition is
waived in writing by the district
engineer. This NWP cannot be used to
reclaim lands lost to normal erosion
processes over an extended period.
This NWP does not authorize beach
restoration or nourishment.
Minor dredging is limited to the
amount necessary to restore the
damaged upland area and should not
significantly alter the pre-existing
bottom contours of the waterbody.
Notification: The permittee must
submit a pre-construction notification to
the district engineer (see general
condition 31) within 12-months of the
date of the damage. The preconstruction notification should include
documentation, such as a recent
topographic survey or photographs, to
justify the extent of the proposed
restoration. (Sections 10 and 404)
Note: The uplands themselves that are lost
as a result of a storm, flood, or other discrete
event can be replaced without a section 404
permit, if the uplands are restored to the
ordinary high water mark (in non-tidal
waters) or high tide line (in tidal waters).
(See also 33 CFR 328.5.) This NWP
authorizes discharges of dredged or fill
material into waters of the United States
associated with the restoration of uplands.
46. Discharges in Ditches. Discharges
of dredged or fill material into non-tidal
ditches that are: (1) Constructed in
uplands, (2) receive water from an area
determined to be a water of the United
States prior to the construction of the
ditch, (3) divert water to an area
PO 00000
Frm 00098
Fmt 4701
Sfmt 4703
determined to be a water of the United
States prior to the construction of the
ditch, and (4) are determined to be
waters of the United States. The
discharge must not cause the loss of
greater than one acre of waters of the
United States. This NWP does not
authorize discharges of dredged or fill
material into ditches constructed in
streams or other waters of the United
States, or in streams that have been
relocated in uplands. This NWP does
not authorize discharges of dredged or
fill material that increase the capacity of
the ditch and drain those areas
determined to be waters of the United
States prior to construction of the ditch.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Section 404)
47. [Reserved]
48. Commercial Shellfish Aquaculture
Activities. Discharges of dredged or fill
material in waters of the United States
or structures or work in navigable
waters of the United States necessary for
commercial shellfish aquaculture
operations in authorized project areas.
For the purposes of this NWP, the
project area is the area in which the
operator is currently authorized to
conduct commercial shellfish
aquaculture activities, as identified
through a lease or permit issued by an
appropriate state or local government
agency, a treaty, or any other easement,
lease, deed, or contract which
establishes an enforceable property
interest for the operator. This NWP
authorizes the installation of buoys,
floats, racks, trays, nets, lines, tubes,
containers, and other structures into
navigable waters of the United States.
This NWP also authorizes discharges of
dredged or fill material into waters of
the United States necessary for shellfish
seeding, rearing, cultivating,
transplanting, and harvesting activities.
Rafts and other floating structures must
be securely anchored and clearly
marked. This NWP does not authorize:
(a) The cultivation of a nonindigenous
species unless that species has been
previously cultivated in the waterbody;
(b) The cultivation of an aquatic
nuisance species as defined in the
Nonindigenous Aquatic Nuisance
Prevention and Control Act of 1990; or,
(c) Attendant features such as docks,
piers, boat ramps, stockpiles, or staging
areas, or the deposition of shell material
back into waters of the United States as
waste.
This NWP also authorizes commercial
shellfish aquaculture activities in new
project areas, provided the project
proponent has obtained a valid
E:\FR\FM\21FEN2.SGM
21FEN2
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
authorization, such as a lease or permit
issued by an appropriate state or local
government agency, and those activities
do not directly affect more than 1⁄2-acre
of submerged aquatic vegetation beds.
Notification: The permittee must
submit a pre-construction notification to
the district engineer if: (1) Dredge
harvesting, tilling, or harrowing is
conducted in areas inhabited by
submerged aquatic vegetation; (2) the
activity will include a species not
previously cultivated in the waterbody;
(3) the activity involves a change from
bottom culture to floating or suspended
culture; or (4) the activity occurs in a
new project area. (See general condition
31.)
In addition to the information
required by paragraph (b) of general
condition 31, the pre-construction
notification must also include the
following information: (1) A map
showing the boundaries of the project
area, with latitude and longitude
coordinates for each corner of the
project area; (2) the name(s) of the
cultivated species; and (3) whether
canopy predator nets are being used.
(Sections 10 and 404)
Note 1: The permittee should notify the
applicable U.S. Coast Guard office regarding
the project.
Note 2: To prevent introduction of aquatic
nuisance species, no material that has been
taken from a different waterbody may be
reused in the current project area, unless it
has been treated in accordance with the
applicable regional aquatic nuisance species
management plan.
sroberts on DSK5SPTVN1PROD with NOTICES
Note 3: The Nonindigenous Aquatic
Nuisance Prevention and Control Act of 1990
defines ‘‘aquatic nuisance species’’ as ‘‘a
nonindigenous species that threatens the
diversity or abundance of native species or
the ecological stability of infested waters, or
commercial, agricultural, aquacultural, or
recreational activities dependent on such
waters.’’
49. Coal Remining Activities.
Discharges of dredged or fill material
into non-tidal waters of the United
States associated with the remining and
reclamation of lands that were
previously mined for coal. The activities
must already be authorized, or they
must currently be in process as part of
an integrated permit processing
procedure, by the Department of Interior
Office of Surface Mining Reclamation
and Enforcement, or by states with
approved programs under Title IV or
Title V of the Surface Mining Control
and Reclamation Act (SMCRA) of 1977.
Areas previously mined include
reclaimed mine sites, abandoned mine
land areas, or lands under bond
forfeiture contracts.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
As part of the project, the permittee
may conduct new coal mining activities
in conjunction with the remining
activities when he or she clearly
demonstrates to the district engineer
that the overall mining plan will result
in a net increase in aquatic resource
functions. The Corps will consider the
SMCRA agency’s decision regarding the
amount of currently undisturbed
adjacent lands needed to facilitate the
remining and reclamation of the
previously mined area. The total area
disturbed by new mining must not
exceed 40 percent of the total acreage
covered by both the remined area and
the additional area necessary to carry
out the reclamation of the previously
mined area.
Notification: The permittee must
submit a pre-construction notification
and a document describing how the
overall mining plan will result in a net
increase in aquatic resource functions to
the district engineer and receive written
authorization prior to commencing the
activity. (See general condition 31.)
(Sections 10 and 404)
50. Underground Coal Mining
Activities. Discharges of dredged or fill
material into non-tidal waters of the
United States associated with
underground coal mining and
reclamation operations provided the
activities are authorized, or are
currently being processed as part of an
integrated permit processing procedure,
by the Department of Interior, Office of
Surface Mining Reclamation and
Enforcement, or by states with approved
programs under Title V of the Surface
Mining Control and Reclamation Act of
1977.
The discharge must not cause the loss
of greater than 1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This NWP
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
This NWP does not authorize coal
preparation and processing activities
outside of the mine site.
Notification: The permittee must
submit a pre-construction notification to
the district engineer and receive written
authorization prior to commencing the
activity. (See general condition 31.) If
reclamation is required by other
statutes, then a copy of the reclamation
plan must be submitted with the preconstruction notification. (Sections 10
and 404)
PO 00000
Frm 00099
Fmt 4701
Sfmt 4703
10281
Note: Coal preparation and processing
activities outside of the mine site may be
authorized by NWP 21.
51. Land-Based Renewable Energy
Generation Facilities. Discharges of
dredged or fill material into non-tidal
waters of the United States for the
construction, expansion, or
modification of land-based renewable
energy production facilities, including
attendant features. Such facilities
include infrastructure to collect solar
(concentrating solar power and
photovoltaic), wind, biomass, or
geothermal energy. Attendant features
may include, but are not limited to
roads, parking lots, and stormwater
management facilities within the landbased renewable energy generation
facility.
The discharge must not cause the loss
of greater than1⁄2-acre of non-tidal
waters of the United States, including
the loss of no more than 300 linear feet
of stream bed, unless for intermittent
and ephemeral stream beds the district
engineer waives the 300 linear foot limit
by making a written determination
concluding that the discharge will result
in minimal adverse effects. This permit
does not authorize discharges into nontidal wetlands adjacent to tidal waters.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
Note 1: Utility lines constructed to transfer
the energy from the land-based renewable
generation facility to a distribution system,
regional grid, or other facility are generally
considered to be linear projects and each
separate and distant crossing of a waterbody
is eligible for treatment as a separate and
complete linear project. Those utility lines
may be authorized by NWP 12 or another
Department of the Army authorization. If the
only activities associated with the
construction, expansion, or modification of a
land-based renewable energy generation
facility that require Department of the Army
authorization are discharges of dredged or fill
material into waters of the United States to
construct, maintain, repair, and/or remove
utility lines, then NWP 12 shall be used if
those activities meet the terms and
conditions of NWP 12, including any
applicable regional conditions and any casespecific conditions imposed by the district
engineer.
Note 2: For any activity that involves the
construction of a wind energy generating
structure, solar tower, or overhead
transmission line, a copy of the PCN and
NWP verification will be provided to the
Department of Defense Siting Clearinghouse,
which will evaluate potential effects on
military activities.
52. Water-Based Renewable Energy
Generation Pilot Projects. Structures and
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10282
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
work in navigable waters of the United
States and discharges of dredged or fill
material into waters of the United States
for the construction, expansion,
modification, or removal of water-based
wind or hydrokinetic renewable energy
generation pilot projects and their
attendant features. Attendant features
may include, but are not limited to,
land-based collection and distribution
facilities, control facilities, roads,
parking lots, and stormwater
management facilities.
For the purposes of this NWP, the
term ‘‘pilot project’’ means an
experimental project where the
renewable energy generation units will
be monitored to collect information on
their performance and environmental
effects at the project site.
The discharge must not cause the loss
of greater than 1⁄2-acre of waters of the
United States, including the loss of no
more than 300 linear feet of stream bed,
unless for intermittent and ephemeral
stream beds the district engineer waives
the 300 linear foot limit by making a
written determination concluding that
the discharge will result in minimal
adverse effects. The placement of a
transmission line on the bed of a
navigable water of the United States
from the renewable energy generation
unit(s) to a land-based collection and
distribution facility is considered a
structure under Section 10 of the Rivers
and Harbors Act of 1899 (see 33 CFR
322.2(b)), and the placement of the
transmission line on the bed of a
navigable water of the United States is
not a loss of waters of the United States
for the purposes of applying the 1⁄2-acre
or 300 linear foot limits.
For each single and complete project,
no more than 10 generation units (e.g.,
wind turbines or hydrokinetic devices)
are authorized.
This NWP does not authorize
activities in coral reefs. Structures in an
anchorage area established by the U.S.
Coast Guard must comply with the
requirements in 33 CFR 322.5(l)(2).
Structures may not be placed in
established danger zones or restricted
areas as designated in 33 CFR part 334,
Federal navigation channels, shipping
safety fairways or traffic separation
schemes established by the U.S. Coast
Guard (see 33 CFR 322.5(l)(1)), or EPA
or Corps designated open water dredged
material disposal areas.
Upon completion of the pilot project,
the generation units, transmission lines,
and other structures or fills associated
with the pilot project must be removed
to the maximum extent practicable
unless they are authorized by a separate
Department of the Army authorization,
such as another NWP, an individual
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
permit, or a regional general permit.
Completion of the pilot project will be
identified as the date of expiration of
the Federal Energy Regulatory
Commission (FERC) license, or the
expiration date of the NWP
authorization if no FERC license is
issued.
Notification: The permittee must
submit a pre-construction notification to
the district engineer prior to
commencing the activity. (See general
condition 31.) (Sections 10 and 404)
Note 1: Utility lines constructed to transfer
the energy from the land-based collection
facility to a distribution system, regional grid,
or other facility are generally considered to
be linear projects and each separate and
distant crossing of a waterbody is eligible for
treatment as a separate and complete linear
project. Those utility lines may be authorized
by NWP 12 or another Department of the
Army authorization.
Note 2: An activity that is located on an
existing locally or federally maintained U.S.
Army Corps of Engineers project requires
separate approval from the Chief of Engineers
under 33 U.S.C. 408.
Note 3: If the pilot project, including any
transmission lines, is placed in navigable
waters of the United States (i.e., section 10
waters) within the coastal United States, the
Great Lakes, and United States territories,
copies of the pre-construction notification
and NWP verification will be sent by the
Corps to the National Oceanic and
Atmospheric Administration, National Ocean
Service, for charting the generation units and
associated transmission line(s) to protect
navigation.
Note 4: For any activity that involves the
construction of a wind energy generating
structure, solar tower, or overhead
transmission line, a copy of the PCN and
NWP verification will be provided to the
Department of Defense Siting Clearinghouse,
which will evaluate potential effects on
military activities.
C. Nationwide Permit General
Conditions
Note: To qualify for NWP authorization,
the prospective permittee must comply with
the following general conditions, as
applicable, in addition to any regional or
case-specific conditions imposed by the
division engineer or district engineer.
Prospective permittees should contact the
appropriate Corps district office to determine
if regional conditions have been imposed on
an NWP. Prospective permittees should also
contact the appropriate Corps district office
to determine the status of Clean Water Act
Section 401 water quality certification and/
or Coastal Zone Management Act consistency
for an NWP. Every person who may wish to
obtain permit authorization under one or
more NWPs, or who is currently relying on
an existing or prior permit authorization
under one or more NWPs, has been and is on
PO 00000
Frm 00100
Fmt 4701
Sfmt 4703
notice that all of the provisions of 33 CFR
330.1 through 330.6 apply to every NWP
authorization. Note especially 33 CFR 330.5
relating to the modification, suspension, or
revocation of any NWP authorization.
1. Navigation. (a) No activity may
cause more than a minimal adverse
effect on navigation.
(b) Any safety lights and signals
prescribed by the U.S. Coast Guard,
through regulations or otherwise, must
be installed and maintained at the
permittee’s expense on authorized
facilities in navigable waters of the
United States.
(c) The permittee understands and
agrees that, if future operations by the
United States require the removal,
relocation, or other alteration, of the
structure or work herein authorized, or
if, in the opinion of the Secretary of the
Army or his authorized representative,
said structure or work shall cause
unreasonable obstruction to the free
navigation of the navigable waters, the
permittee will be required, upon due
notice from the Corps of Engineers, to
remove, relocate, or alter the structural
work or obstructions caused thereby,
without expense to the United States.
No claim shall be made against the
United States on account of any such
removal or alteration.
2. Aquatic Life Movements. No
activity may substantially disrupt the
necessary life cycle movements of those
species of aquatic life indigenous to the
waterbody, including those species that
normally migrate through the area,
unless the activity’s primary purpose is
to impound water. All permanent and
temporary crossings of waterbodies
shall be suitably culverted, bridged, or
otherwise designed and constructed to
maintain low flows to sustain the
movement of those aquatic species.
3. Spawning Areas. Activities in
spawning areas during spawning
seasons must be avoided to the
maximum extent practicable. Activities
that result in the physical destruction
(e.g., through excavation, fill, or
downstream smothering by substantial
turbidity) of an important spawning area
are not authorized.
4. Migratory Bird Breeding Areas.
Activities in waters of the United States
that serve as breeding areas for
migratory birds must be avoided to the
maximum extent practicable.
5. Shellfish Beds. No activity may
occur in areas of concentrated shellfish
populations, unless the activity is
directly related to a shellfish harvesting
activity authorized by NWPs 4 and 48,
or is a shellfish seeding or habitat
restoration activity authorized by NWP
27.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
6. Suitable Material. No activity may
use unsuitable material (e.g., trash,
debris, car bodies, asphalt, etc.).
Material used for construction or
discharged must be free from toxic
pollutants in toxic amounts (see Section
307 of the Clean Water Act).
7. Water Supply Intakes. No activity
may occur in the proximity of a public
water supply intake, except where the
activity is for the repair or improvement
of public water supply intake structures
or adjacent bank stabilization.
8. Adverse Effects From
Impoundments. If the activity creates an
impoundment of water, adverse effects
to the aquatic system due to accelerating
the passage of water, and/or restricting
its flow must be minimized to the
maximum extent practicable.
9. Management of Water Flows. To the
maximum extent practicable, the preconstruction course, condition,
capacity, and location of open waters
must be maintained for each activity,
including stream channelization and
storm water management activities,
except as provided below. The activity
must be constructed to withstand
expected high flows. The activity must
not restrict or impede the passage of
normal or high flows, unless the
primary purpose of the activity is to
impound water or manage high flows.
The activity may alter the preconstruction course, condition,
capacity, and location of open waters if
it benefits the aquatic environment (e.g.,
stream restoration or relocation
activities).
10. Fills Within 100–Year
Floodplains. The activity must comply
with applicable FEMA-approved state or
local floodplain management
requirements.
11. Equipment. Heavy equipment
working in wetlands or mudflats must
be placed on mats, or other measures
must be taken to minimize soil
disturbance.
12. Soil Erosion and Sediment
Controls. Appropriate soil erosion and
sediment controls must be used and
maintained in effective operating
condition during construction, and all
exposed soil and other fills, as well as
any work below the ordinary high water
mark or high tide line, must be
permanently stabilized at the earliest
practicable date. Permittees are
encouraged to perform work within
waters of the United States during
periods of low-flow or no-flow.
13. Removal of Temporary Fills.
Temporary fills must be removed in
their entirety and the affected areas
returned to pre-construction elevations.
The affected areas must be revegetated,
as appropriate.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
14. Proper Maintenance. Any
authorized structure or fill shall be
properly maintained, including
maintenance to ensure public safety and
compliance with applicable NWP
general conditions, as well as any
activity-specific conditions added by
the district engineer to an NWP
authorization.
15. Single and Complete Project. The
activity must be a single and complete
project. The same NWP cannot be used
more than once for the same single and
complete project.
16. Wild and Scenic Rivers. No
activity may occur in a component of
the National Wild and Scenic River
System, or in a river officially
designated by Congress as a ‘‘study
river’’ for possible inclusion in the
system while the river is in an official
study status, unless the appropriate
Federal agency with direct management
responsibility for such river, has
determined in writing that the proposed
activity will not adversely affect the
Wild and Scenic River designation or
study status. Information on Wild and
Scenic Rivers may be obtained from the
appropriate Federal land management
agency responsible for the designated
Wild and Scenic River or study river
(e.g., National Park Service, U.S. Forest
Service, Bureau of Land Management,
U.S. Fish and Wildlife Service).
17. Tribal Rights. No activity or its
operation may impair reserved tribal
rights, including, but not limited to,
reserved water rights and treaty fishing
and hunting rights.
18. Endangered Species. (a) No
activity is authorized under any NWP
which is likely to directly or indirectly
jeopardize the continued existence of a
threatened or endangered species or a
species proposed for such designation,
as identified under the Federal
Endangered Species Act (ESA), or
which will directly or indirectly destroy
or adversely modify the critical habitat
of such species. No activity is
authorized under any NWP which ‘‘may
affect’’ a listed species or critical
habitat, unless Section 7 consultation
addressing the effects of the proposed
activity has been completed.
(b) Federal agencies should follow
their own procedures for complying
with the requirements of the ESA.
Federal permittees must provide the
district engineer with the appropriate
documentation to demonstrate
compliance with those requirements.
The district engineer will review the
documentation and determine whether
it is sufficient to address ESA
compliance for the NWP activity, or
whether additional ESA consultation is
necessary.
PO 00000
Frm 00101
Fmt 4701
Sfmt 4703
10283
(c) Non-federal permittees must
submit a pre-construction notification to
the district engineer if any listed species
or designated critical habitat might be
affected or is in the vicinity of the
project, or if the project is located in
designated critical habitat, and shall not
begin work on the activity until notified
by the district engineer that the
requirements of the ESA have been
satisfied and that the activity is
authorized. For activities that might
affect Federally listed endangered or
threatened species or designated critical
habitat, the pre-construction notification
must include the name(s) of the
endangered or threatened species that
might be affected by the proposed work
or that utilize the designated critical
habitat that might be affected by the
proposed work. The district engineer
will determine whether the proposed
activity ‘‘may affect’’ or will have ‘‘no
effect’’ to listed species and designated
critical habitat and will notify the nonFederal applicant of the Corps’
determination within 45 days of receipt
of a complete pre-construction
notification. In cases where the nonFederal applicant has identified listed
species or critical habitat that might be
affected or is in the vicinity of the
project, and has so notified the Corps,
the applicant shall not begin work until
the Corps has provided notification the
proposed activities will have ‘‘no effect’’
on listed species or critical habitat, or
until Section 7 consultation has been
completed. If the non-Federal applicant
has not heard back from the Corps
within 45 days, the applicant must still
wait for notification from the Corps.
(d) As a result of formal or informal
consultation with the FWS or NMFS the
district engineer may add speciesspecific regional endangered species
conditions to the NWPs.
(e) Authorization of an activity by a
NWP does not authorize the ‘‘take’’ of a
threatened or endangered species as
defined under the ESA. In the absence
of separate authorization (e.g., an ESA
Section 10 Permit, a Biological Opinion
with ‘‘incidental take’’ provisions, etc.)
from the U.S. FWS or the NMFS, The
Endangered Species Act prohibits any
person subject to the jurisdiction of the
United States to take a listed species,
where ‘‘take’’ means to harass, harm,
pursue, hunt, shoot, wound, kill, trap,
capture, or collect, or to attempt to
engage in any such conduct. The word
‘‘harm’’ in the definition of ‘‘take’’
means an act which actually kills or
injures wildlife. Such an act may
include significant habitat modification
or degradation where it actually kills or
injures wildlife by significantly
impairing essential behavioral patterns,
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10284
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
including breeding, feeding or
sheltering.
(f) Information on the location of
threatened and endangered species and
their critical habitat can be obtained
directly from the offices of the U.S. FWS
and NMFS or their world wide web
pages at https://www.fws.gov/ or https://
www.fws.gov/ipac and https://
www.noaa.gov/fisheries.html
respectively.
19. Migratory Birds and Bald and
Golden Eagles. The permittee is
responsible for obtaining any ‘‘take’’
permits required under the U.S. Fish
and Wildlife Service’s regulations
governing compliance with the
Migratory Bird Treaty Act or the Bald
and Golden Eagle Protection Act. The
permittee should contact the
appropriate local office of the U.S. Fish
and Wildlife Service to determine if
such ‘‘take’’ permits are required for a
particular activity.
20. Historic Properties. (a) In cases
where the district engineer determines
that the activity may affect properties
listed, or eligible for listing, in the
National Register of Historic Places, the
activity is not authorized, until the
requirements of Section 106 of the
National Historic Preservation Act
(NHPA) have been satisfied.
(b) Federal permittees should follow
their own procedures for complying
with the requirements of Section 106 of
the National Historic Preservation Act.
Federal permittees must provide the
district engineer with the appropriate
documentation to demonstrate
compliance with those requirements.
The district engineer will review the
documentation and determine whether
it is sufficient to address section 106
compliance for the NWP activity, or
whether additional section 106
consultation is necessary.
(c) Non-federal permittees must
submit a pre-construction notification to
the district engineer if the authorized
activity may have the potential to cause
effects to any historic properties listed
on, determined to be eligible for listing
on, or potentially eligible for listing on
the National Register of Historic Places,
including previously unidentified
properties. For such activities, the preconstruction notification must state
which historic properties may be
affected by the proposed work or
include a vicinity map indicating the
location of the historic properties or the
potential for the presence of historic
properties. Assistance regarding
information on the location of or
potential for the presence of historic
resources can be sought from the State
Historic Preservation Officer or Tribal
Historic Preservation Officer, as
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
appropriate, and the National Register of
Historic Places (see 33 CFR 330.4(g)).
When reviewing pre-construction
notifications, district engineers will
comply with the current procedures for
addressing the requirements of Section
106 of the National Historic
Preservation Act. The district engineer
shall make a reasonable and good faith
effort to carry out appropriate
identification efforts, which may
include background research,
consultation, oral history interviews,
sample field investigation, and field
survey. Based on the information
submitted and these efforts, the district
engineer shall determine whether the
proposed activity has the potential to
cause an effect on the historic
properties. Where the non-Federal
applicant has identified historic
properties on which the activity may
have the potential to cause effects and
so notified the Corps, the non-Federal
applicant shall not begin the activity
until notified by the district engineer
either that the activity has no potential
to cause effects or that consultation
under Section 106 of the NHPA has
been completed.
(d) The district engineer will notify
the prospective permittee within 45
days of receipt of a complete preconstruction notification whether NHPA
Section 106 consultation is required.
Section 106 consultation is not required
when the Corps determines that the
activity does not have the potential to
cause effects on historic properties (see
36 CFR 800.3(a)). If NHPA section 106
consultation is required and will occur,
the district engineer will notify the nonFederal applicant that he or she cannot
begin work until Section 106
consultation is completed. If the nonFederal applicant has not heard back
from the Corps within 45 days, the
applicant must still wait for notification
from the Corps.
(e) Prospective permittees should be
aware that section 110k of the NHPA (16
U.S.C. 470h–2(k)) prevents the Corps
from granting a permit or other
assistance to an applicant who, with
intent to avoid the requirements of
Section 106 of the NHPA, has
intentionally significantly adversely
affected a historic property to which the
permit would relate, or having legal
power to prevent it, allowed such
significant adverse effect to occur,
unless the Corps, after consultation with
the Advisory Council on Historic
Preservation (ACHP), determines that
circumstances justify granting such
assistance despite the adverse effect
created or permitted by the applicant. If
circumstances justify granting the
assistance, the Corps is required to
PO 00000
Frm 00102
Fmt 4701
Sfmt 4703
notify the ACHP and provide
documentation specifying the
circumstances, the degree of damage to
the integrity of any historic properties
affected, and proposed mitigation. This
documentation must include any views
obtained from the applicant, SHPO/
THPO, appropriate Indian tribes if the
undertaking occurs on or affects historic
properties on tribal lands or affects
properties of interest to those tribes, and
other parties known to have a legitimate
interest in the impacts to the permitted
activity on historic properties.
21. Discovery of Previously Unknown
Remains and Artifacts. If you discover
any previously unknown historic,
cultural or archeological remains and
artifacts while accomplishing the
activity authorized by this permit, you
must immediately notify the district
engineer of what you have found, and
to the maximum extent practicable,
avoid construction activities that may
affect the remains and artifacts until the
required coordination has been
completed. The district engineer will
initiate the Federal, Tribal and state
coordination required to determine if
the items or remains warrant a recovery
effort or if the site is eligible for listing
in the National Register of Historic
Places.
22. Designated Critical Resource
Waters. Critical resource waters include,
NOAA-managed marine sanctuaries and
marine monuments, and National
Estuarine Research Reserves. The
district engineer may designate, after
notice and opportunity for public
comment, additional waters officially
designated by a state as having
particular environmental or ecological
significance, such as outstanding
national resource waters or state natural
heritage sites. The district engineer may
also designate additional critical
resource waters after notice and
opportunity for public comment.
(a) Discharges of dredged or fill
material into waters of the United States
are not authorized by NWPs 7, 12, 14,
16, 17, 21, 29, 31, 35, 39, 40, 42, 43, 44,
49, 50, 51, and 52 for any activity
within, or directly affecting, critical
resource waters, including wetlands
adjacent to such waters.
(b) For NWPs 3, 8, 10, 13, 15, 18, 19,
22, 23, 25, 27, 28, 30, 33, 34, 36, 37, and
38, notification is required in
accordance with general condition 31,
for any activity proposed in the
designated critical resource waters
including wetlands adjacent to those
waters. The district engineer may
authorize activities under these NWPs
only after it is determined that the
impacts to the critical resource waters
will be no more than minimal.
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
23. Mitigation. The district engineer
will consider the following factors when
determining appropriate and practicable
mitigation necessary to ensure that
adverse effects on the aquatic
environment are minimal:
(a) The activity must be designed and
constructed to avoid and minimize
adverse effects, both temporary and
permanent, to waters of the United
States to the maximum extent
practicable at the project site (i.e., on
site).
(b) Mitigation in all its forms
(avoiding, minimizing, rectifying,
reducing, or compensating for resource
losses) will be required to the extent
necessary to ensure that the adverse
effects to the aquatic environment are
minimal.
(c) Compensatory mitigation at a
minimum one-for-one ratio will be
required for all wetland losses that
exceed 1⁄10-acre and require preconstruction notification, unless the
district engineer determines in writing
that either some other form of mitigation
would be more environmentally
appropriate or the adverse effects of the
proposed activity are minimal, and
provides a project-specific waiver of this
requirement. For wetland losses of 1⁄10acre or less that require pre-construction
notification, the district engineer may
determine on a case-by-case basis that
compensatory mitigation is required to
ensure that the activity results in
minimal adverse effects on the aquatic
environment. Compensatory mitigation
projects provided to offset losses of
aquatic resources must comply with the
applicable provisions of 33 CFR part
332.
(1) The prospective permittee is
responsible for proposing an
appropriate compensatory mitigation
option if compensatory mitigation is
necessary to ensure that the activity
results in minimal adverse effects on the
aquatic environment.
(2) Since the likelihood of success is
greater and the impacts to potentially
valuable uplands are reduced, wetland
restoration should be the first
compensatory mitigation option
considered.
(3) If permittee-responsible mitigation
is the proposed option, the prospective
permittee is responsible for submitting a
mitigation plan. A conceptual or
detailed mitigation plan may be used by
the district engineer to make the
decision on the NWP verification
request, but a final mitigation plan that
addresses the applicable requirements
of 33 CFR 332.4(c)(2)–(14) must be
approved by the district engineer before
the permittee begins work in waters of
the United States, unless the district
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
engineer determines that prior approval
of the final mitigation plan is not
practicable or not necessary to ensure
timely completion of the required
compensatory mitigation (see 33 CFR
332.3(k)(3)).
(4) If mitigation bank or in-lieu fee
program credits are the proposed
option, the mitigation plan only needs
to address the baseline conditions at the
impact site and the number of credits to
be provided.
(5) Compensatory mitigation
requirements (e.g., resource type and
amount to be provided as compensatory
mitigation, site protection, ecological
performance standards, monitoring
requirements) may be addressed
through conditions added to the NWP
authorization, instead of components of
a compensatory mitigation plan.
(d) For losses of streams or other open
waters that require pre-construction
notification, the district engineer may
require compensatory mitigation, such
as stream rehabilitation, enhancement,
or preservation, to ensure that the
activity results in minimal adverse
effects on the aquatic environment.
(e) Compensatory mitigation will not
be used to increase the acreage losses
allowed by the acreage limits of the
NWPs. For example, if an NWP has an
acreage limit of 1⁄2-acre, it cannot be
used to authorize any project resulting
in the loss of greater than 1⁄2-acre of
waters of the United States, even if
compensatory mitigation is provided
that replaces or restores some of the lost
waters. However, compensatory
mitigation can and should be used, as
necessary, to ensure that a project
already meeting the established acreage
limits also satisfies the minimal impact
requirement associated with the NWPs.
(f) Compensatory mitigation plans for
projects in or near streams or other open
waters will normally include a
requirement for the restoration or
establishment, maintenance, and legal
protection (e.g., conservation easements)
of riparian areas next to open waters. In
some cases, riparian areas may be the
only compensatory mitigation required.
Riparian areas should consist of native
species. The width of the required
riparian area will address documented
water quality or aquatic habitat loss
concerns. Normally, the riparian area
will be 25 to 50 feet wide on each side
of the stream, but the district engineer
may require slightly wider riparian
areas to address documented water
quality or habitat loss concerns. If it is
not possible to establish a riparian area
on both sides of a stream, or if the
waterbody is a lake or coastal waters,
then restoring or establishing a riparian
area along a single bank or shoreline
PO 00000
Frm 00103
Fmt 4701
Sfmt 4703
10285
may be sufficient. Where both wetlands
and open waters exist on the project
site, the district engineer will determine
the appropriate compensatory
mitigation (e.g., riparian areas and/or
wetlands compensation) based on what
is best for the aquatic environment on
a watershed basis. In cases where
riparian areas are determined to be the
most appropriate form of compensatory
mitigation, the district engineer may
waive or reduce the requirement to
provide wetland compensatory
mitigation for wetland losses.
(g) Permittees may propose the use of
mitigation banks, in-lieu fee programs,
or separate permittee-responsible
mitigation. For activities resulting in the
loss of marine or estuarine resources,
permittee-responsible compensatory
mitigation may be environmentally
preferable if there are no mitigation
banks or in-lieu fee programs in the area
that have marine or estuarine credits
available for sale or transfer to the
permittee. For permittee-responsible
mitigation, the special conditions of the
NWP verification must clearly indicate
the party or parties responsible for the
implementation and performance of the
compensatory mitigation project, and, if
required, its long-term management.
(h) Where certain functions and
services of waters of the United States
are permanently adversely affected,
such as the conversion of a forested or
scrub-shrub wetland to a herbaceous
wetland in a permanently maintained
utility line right-of-way, mitigation may
be required to reduce the adverse effects
of the project to the minimal level.
24. Safety of Impoundment
Structures. To ensure that all
impoundment structures are safely
designed, the district engineer may
require non-Federal applicants to
demonstrate that the structures comply
with established state dam safety
criteria or have been designed by
qualified persons. The district engineer
may also require documentation that the
design has been independently
reviewed by similarly qualified persons,
and appropriate modifications made to
ensure safety.
25. Water Quality. Where States and
authorized Tribes, or EPA where
applicable, have not previously certified
compliance of an NWP with CWA
Section 401, individual 401 Water
Quality Certification must be obtained
or waived (see 33 CFR 330.4(c)). The
district engineer or State or Tribe may
require additional water quality
management measures to ensure that the
authorized activity does not result in
more than minimal degradation of water
quality.
E:\FR\FM\21FEN2.SGM
21FEN2
10286
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
provide a signed certification
documenting completion of the
authorized activity and any required
compensatory mitigation. The success of
any required permittee-responsible
mitigation, including the achievement
of ecological performance standards,
will be addressed separately by the
district engineer. The Corps will
provide the permittee the certification
document with the NWP verification
letter. The certification document will
include:
(a) A statement that the authorized
work was done in accordance with the
NWP authorization, including any
general, regional, or activity-specific
conditions;
(b) A statement that the
implementation of any required
compensatory mitigation was completed
in accordance with the permit
conditions. If credits from a mitigation
bank or in-lieu fee program are used to
satisfy the compensatory mitigation
requirements, the certification must
include the documentation required by
33 CFR 332.3(l)(3) to confirm that the
permittee secured the appropriate
number and resource type of credits;
and
(c) The signature of the permittee
certifying the completion of the work
and mitigation.
31. Pre-Construction Notification—(a)
Timing. Where required by the terms of
the NWP, the prospective permittee
must notify the district engineer by
submitting a pre-construction
notification (PCN) as early as possible.
The district engineer must determine if
the PCN is complete within 30 calendar
days of the date of receipt and, if the
PCN is determined to be incomplete,
notify the prospective permittee within
that 30 day period to request the
additional information necessary to
make the PCN complete. The request
must specify the information needed to
make the PCN complete. As a general
rule, district engineers will request
additional information necessary to
‘‘When the structures or work authorized
by this nationwide permit are still in
make the PCN complete only once.
existence at the time the property is
However, if the prospective permittee
transferred, the terms and conditions of this
does not provide all of the requested
nationwide permit, including any special
information, then the district engineer
conditions, will continue to be binding on
will notify the prospective permittee
the new owner(s) of the property. To validate
the transfer of this nationwide permit and the that the PCN is still incomplete and the
PCN review process will not commence
associated liabilities associated with
until all of the requested information
compliance with its terms and conditions,
has been received by the district
have the transferee sign and date below.’’
lllllllllllllllllllll engineer. The prospective permittee
(Transferee)
shall not begin the activity until either:
lllllllllllllllllllll
(1) He or she is notified in writing by
(Date)
the district engineer that the activity
may proceed under the NWP with any
30. Compliance Certification. Each
special conditions imposed by the
permittee who receives an NWP
district or division engineer; or
verification letter from the Corps must
sroberts on DSK5SPTVN1PROD with NOTICES
26. Coastal Zone Management. In
coastal states where an NWP has not
previously received a state coastal zone
management consistency concurrence,
an individual state coastal zone
management consistency concurrence
must be obtained, or a presumption of
concurrence must occur (see 33 CFR
330.4(d)). The district engineer or a
State may require additional measures
to ensure that the authorized activity is
consistent with state coastal zone
management requirements.
27. Regional and Case-By-Case
Conditions. The activity must comply
with any regional conditions that may
have been added by the Division
Engineer (see 33 CFR 330.4(e)) and with
any case specific conditions added by
the Corps or by the state, Indian Tribe,
or U.S. EPA in its section 401 Water
Quality Certification, or by the state in
its Coastal Zone Management Act
consistency determination.
28. Use of Multiple Nationwide
Permits. The use of more than one NWP
for a single and complete project is
prohibited, except when the acreage loss
of waters of the United States
authorized by the NWPs does not
exceed the acreage limit of the NWP
with the highest specified acreage limit.
For example, if a road crossing over
tidal waters is constructed under NWP
14, with associated bank stabilization
authorized by NWP 13, the maximum
acreage loss of waters of the United
States for the total project cannot exceed
1⁄3-acre.
29. Transfer of Nationwide Permit
Verifications. If the permittee sells the
property associated with a nationwide
permit verification, the permittee may
transfer the nationwide permit
verification to the new owner by
submitting a letter to the appropriate
Corps district office to validate the
transfer. A copy of the nationwide
permit verification must be attached to
the letter, and the letter must contain
the following statement and signature:
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
PO 00000
Frm 00104
Fmt 4701
Sfmt 4703
(2) 45 calendar days have passed from
the district engineer’s receipt of the
complete PCN and the prospective
permittee has not received written
notice from the district or division
engineer. However, if the permittee was
required to notify the Corps pursuant to
general condition 18 that listed species
or critical habitat might be affected or in
the vicinity of the project, or to notify
the Corps pursuant to general condition
20 that the activity may have the
potential to cause effects to historic
properties, the permittee cannot begin
the activity until receiving written
notification from the Corps that there is
‘‘no effect’’ on listed species or ‘‘no
potential to cause effects’’ on historic
properties, or that any consultation
required under Section 7 of the
Endangered Species Act (see 33 CFR
330.4(f)) and/or Section 106 of the
National Historic Preservation (see 33
CFR 330.4(g)) has been completed. Also,
work cannot begin under NWPs 21, 49,
or 50 until the permittee has received
written approval from the Corps. If the
proposed activity requires a written
waiver to exceed specified limits of an
NWP, the permittee may not begin the
activity until the district engineer issues
the waiver. If the district or division
engineer notifies the permittee in
writing that an individual permit is
required within 45 calendar days of
receipt of a complete PCN, the permittee
cannot begin the activity until an
individual permit has been obtained.
Subsequently, the permittee’s right to
proceed under the NWP may be
modified, suspended, or revoked only in
accordance with the procedure set forth
in 33 CFR 330.5(d)(2).
(b) Contents of Pre-Construction
Notification: The PCN must be in
writing and include the following
information:
(1) Name, address and telephone
numbers of the prospective permittee;
(2) Location of the proposed project;
(3) A description of the proposed
project; the project’s purpose; direct and
indirect adverse environmental effects
the project would cause, including the
anticipated amount of loss of water of
the United States expected to result
from the NWP activity, in acres, linear
feet, or other appropriate unit of
measure; any other NWP(s), regional
general permit(s), or individual
permit(s) used or intended to be used to
authorize any part of the proposed
project or any related activity. The
description should be sufficiently
detailed to allow the district engineer to
determine that the adverse effects of the
project will be minimal and to
determine the need for compensatory
mitigation. Sketches should be provided
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
when necessary to show that the activity
complies with the terms of the NWP.
(Sketches usually clarify the project and
when provided results in a quicker
decision. Sketches should contain
sufficient detail to provide an
illustrative description of the proposed
activity (e.g., a conceptual plan), but do
not need to be detailed engineering
plans);
(4) The PCN must include a
delineation of wetlands, other special
aquatic sites, and other waters, such as
lakes and ponds, and perennial,
intermittent, and ephemeral streams, on
the project site. Wetland delineations
must be prepared in accordance with
the current method required by the
Corps. The permittee may ask the Corps
to delineate the special aquatic sites and
other waters on the project site, but
there may be a delay if the Corps does
the delineation, especially if the project
site is large or contains many waters of
the United States. Furthermore, the 45
day period will not start until the
delineation has been submitted to or
completed by the Corps, as appropriate;
(5) If the proposed activity will result
in the loss of greater than 1⁄10-acre of
wetlands and a PCN is required, the
prospective permittee must submit a
statement describing how the mitigation
requirement will be satisfied, or
explaining why the adverse effects are
minimal and why compensatory
mitigation should not be required. As an
alternative, the prospective permittee
may submit a conceptual or detailed
mitigation plan.
(6) If any listed species or designated
critical habitat might be affected or is in
the vicinity of the project, or if the
project is located in designated critical
habitat, for non-Federal applicants the
PCN must include the name(s) of those
endangered or threatened species that
might be affected by the proposed work
or utilize the designated critical habitat
that may be affected by the proposed
work. Federal applicants must provide
documentation demonstrating
compliance with the Endangered
Species Act; and
(7) For an activity that may affect a
historic property listed on, determined
to be eligible for listing on, or
potentially eligible for listing on, the
National Register of Historic Places, for
non-Federal applicants the PCN must
state which historic property may be
affected by the proposed work or
include a vicinity map indicating the
location of the historic property. Federal
applicants must provide documentation
demonstrating compliance with Section
106 of the National Historic
Preservation Act.
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
(c) Form of Pre-Construction
Notification: The standard individual
permit application form (Form ENG
4345) may be used, but the completed
application form must clearly indicate
that it is a PCN and must include all of
the information required in paragraphs
(b)(1) through (7) of this general
condition. A letter containing the
required information may also be used.
(d) Agency Coordination: (1) The
district engineer will consider any
comments from Federal and state
agencies concerning the proposed
activity’s compliance with the terms
and conditions of the NWPs and the
need for mitigation to reduce the
project’s adverse environmental effects
to a minimal level.
(2) For all NWP activities that require
pre-construction notification and result
in the loss of greater than 1⁄2-acre of
waters of the United States, for NWP 21,
29, 39, 40, 42, 43, 44, 50, 51, and 52
activities that require pre-construction
notification and will result in the loss of
greater than 300 linear feet of
intermittent and ephemeral stream bed,
and for all NWP 48 activities that
require pre-construction notification,
the district engineer will immediately
provide (e.g., via email, facsimile
transmission, overnight mail, or other
expeditious manner) a copy of the
complete PCN to the appropriate
Federal or state offices (U.S. FWS, state
natural resource or water quality
agency, EPA, State Historic Preservation
Officer (SHPO) or Tribal Historic
Preservation Office (THPO), and, if
appropriate, the NMFS). With the
exception of NWP 37, these agencies
will have 10 calendar days from the date
the material is transmitted to telephone
or fax the district engineer notice that
they intend to provide substantive, sitespecific comments. The comments must
explain why the agency believes the
adverse effects will be more than
minimal. If so contacted by an agency,
the district engineer will wait an
additional 15 calendar days before
making a decision on the preconstruction notification. The district
engineer will fully consider agency
comments received within the specified
time frame concerning the proposed
activity’s compliance with the terms
and conditions of the NWPs, including
the need for mitigation to ensure the net
adverse environmental effects to the
aquatic environment of the proposed
activity are minimal. The district
engineer will provide no response to the
resource agency, except as provided
below. The district engineer will
indicate in the administrative record
associated with each pre-construction
notification that the resource agencies’
PO 00000
Frm 00105
Fmt 4701
Sfmt 4703
10287
concerns were considered. For NWP 37,
the emergency watershed protection and
rehabilitation activity may proceed
immediately in cases where there is an
unacceptable hazard to life or a
significant loss of property or economic
hardship will occur. The district
engineer will consider any comments
received to decide whether the NWP 37
authorization should be modified,
suspended, or revoked in accordance
with the procedures at 33 CFR 330.5.
(3) In cases of where the prospective
permittee is not a Federal agency, the
district engineer will provide a response
to NMFS within 30 calendar days of
receipt of any Essential Fish Habitat
conservation recommendations, as
required by Section 305(b)(4)(B) of the
Magnuson-Stevens Fishery
Conservation and Management Act.
(4) Applicants are encouraged to
provide the Corps with either electronic
files or multiple copies of preconstruction notifications to expedite
agency coordination.
D. District Engineer’s Decision
1. In reviewing the PCN for the
proposed activity, the district engineer
will determine whether the activity
authorized by the NWP will result in
more than minimal individual or
cumulative adverse environmental
effects or may be contrary to the public
interest. For a linear project, this
determination will include an
evaluation of the individual crossings to
determine whether they individually
satisfy the terms and conditions of the
NWP(s), as well as the cumulative
effects caused by all of the crossings
authorized by NWP. If an applicant
requests a waiver of the 300 linear foot
limit on impacts to intermittent or
ephemeral streams or of an otherwise
applicable limit, as provided for in
NWPs 13, 21, 29, 36, 39, 40, 42, 43, 44,
50, 51 or 52, the district engineer will
only grant the waiver upon a written
determination that the NWP activity
will result in minimal adverse effects.
When making minimal effects
determinations the district engineer will
consider the direct and indirect effects
caused by the NWP activity. The district
engineer will also consider site specific
factors, such as the environmental
setting in the vicinity of the NWP
activity, the type of resource that will be
affected by the NWP activity, the
functions provided by the aquatic
resources that will be affected by the
NWP activity, the degree or magnitude
to which the aquatic resources perform
those functions, the extent that aquatic
resource functions will be lost as a
result of the NWP activity (e.g., partial
or complete loss), the duration of the
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
10288
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
adverse effects (temporary or
permanent), the importance of the
aquatic resource functions to the region
(e.g., watershed or ecoregion), and
mitigation required by the district
engineer. If an appropriate functional
assessment method is available and
practicable to use, that assessment
method may be used by the district
engineer to assist in the minimal
adverse effects determination. The
district engineer may add case-specific
special conditions to the NWP
authorization to address site-specific
environmental concerns.
2. If the proposed activity requires a
PCN and will result in a loss of greater
than 1⁄10-acre of wetlands, the
prospective permittee should submit a
mitigation proposal with the PCN.
Applicants may also propose
compensatory mitigation for projects
with smaller impacts. The district
engineer will consider any proposed
compensatory mitigation the applicant
has included in the proposal in
determining whether the net adverse
environmental effects to the aquatic
environment of the proposed activity
are minimal. The compensatory
mitigation proposal may be either
conceptual or detailed. If the district
engineer determines that the activity
complies with the terms and conditions
of the NWP and that the adverse effects
on the aquatic environment are
minimal, after considering mitigation,
the district engineer will notify the
permittee and include any activityspecific conditions in the NWP
verification the district engineer deems
necessary. Conditions for compensatory
mitigation requirements must comply
with the appropriate provisions at 33
CFR 332.3(k). The district engineer must
approve the final mitigation plan before
the permittee commences work in
waters of the United States, unless the
district engineer determines that prior
approval of the final mitigation plan is
not practicable or not necessary to
ensure timely completion of the
required compensatory mitigation. If the
prospective permittee elects to submit a
compensatory mitigation plan with the
PCN, the district engineer will
expeditiously review the proposed
compensatory mitigation plan. The
district engineer must review the
proposed compensatory mitigation plan
within 45 calendar days of receiving a
complete PCN and determine whether
the proposed mitigation would ensure
no more than minimal adverse effects
on the aquatic environment. If the net
adverse effects of the project on the
aquatic environment (after
consideration of the compensatory
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
mitigation proposal) are determined by
the district engineer to be minimal, the
district engineer will provide a timely
written response to the applicant. The
response will state that the project can
proceed under the terms and conditions
of the NWP, including any activityspecific conditions added to the NWP
authorization by the district engineer.
3. If the district engineer determines
that the adverse effects of the proposed
work are more than minimal, then the
district engineer will notify the
applicant either: (a) That the project
does not qualify for authorization under
the NWP and instruct the applicant on
the procedures to seek authorization
under an individual permit; (b) that the
project is authorized under the NWP
subject to the applicant’s submission of
a mitigation plan that would reduce the
adverse effects on the aquatic
environment to the minimal level; or (c)
that the project is authorized under the
NWP with specific modifications or
conditions. Where the district engineer
determines that mitigation is required to
ensure no more than minimal adverse
effects occur to the aquatic
environment, the activity will be
authorized within the 45-day PCN
period, with activity-specific conditions
that state the mitigation requirements.
The authorization will include the
necessary conceptual or detailed
mitigation or a requirement that the
applicant submit a mitigation plan that
would reduce the adverse effects on the
aquatic environment to the minimal
level. When mitigation is required, no
work in waters of the United States may
occur until the district engineer has
approved a specific mitigation plan or
has determined that prior approval of a
final mitigation plan is not practicable
or not necessary to ensure timely
completion of the required
compensatory mitigation.
E. Further Information
1. District Engineers have authority to
determine if an activity complies with
the terms and conditions of an NWP.
2. NWPs do not obviate the need to
obtain other federal, state, or local
permits, approvals, or authorizations
required by law.
3. NWPs do not grant any property
rights or exclusive privileges.
4. NWPs do not authorize any injury
to the property or rights of others.
5. NWPs do not authorize interference
with any existing or proposed Federal
project.
F. Definitions
Best management practices (BMPs):
Policies, practices, procedures, or
structures implemented to mitigate the
PO 00000
Frm 00106
Fmt 4701
Sfmt 4703
adverse environmental effects on
surface water quality resulting from
development. BMPs are categorized as
structural or non-structural.
Compensatory mitigation: The
restoration (re-establishment or
rehabilitation), establishment (creation),
enhancement, and/or in certain
circumstances preservation of aquatic
resources for the purposes of offsetting
unavoidable adverse impacts which
remain after all appropriate and
practicable avoidance and minimization
has been achieved.
Currently serviceable: Useable as is or
with some maintenance, but not so
degraded as to essentially require
reconstruction.
Direct effects: Effects that are caused
by the activity and occur at the same
time and place.
Discharge: The term ‘‘discharge’’
means any discharge of dredged or fill
material.
Enhancement: The manipulation of
the physical, chemical, or biological
characteristics of an aquatic resource to
heighten, intensify, or improve a
specific aquatic resource function(s).
Enhancement results in the gain of
selected aquatic resource function(s),
but may also lead to a decline in other
aquatic resource function(s).
Enhancement does not result in a gain
in aquatic resource area.
Ephemeral stream: An ephemeral
stream has flowing water only during,
and for a short duration after,
precipitation events in a typical year.
Ephemeral stream beds are located
above the water table year-round.
Groundwater is not a source of water for
the stream. Runoff from rainfall is the
primary source of water for stream flow.
Establishment (creation): The
manipulation of the physical, chemical,
or biological characteristics present to
develop an aquatic resource that did not
previously exist at an upland site.
Establishment results in a gain in
aquatic resource area.
High Tide Line: The line of
intersection of the land with the water’s
surface at the maximum height reached
by a rising tide. The high tide line may
be determined, in the absence of actual
data, by a line of oil or scum along shore
objects, a more or less continuous
deposit of fine shell or debris on the
foreshore or berm, other physical
markings or characteristics, vegetation
lines, tidal gages, or other suitable
means that delineate the general height
reached by a rising tide. The line
encompasses spring high tides and other
high tides that occur with periodic
frequency but does not include storm
surges in which there is a departure
from the normal or predicted reach of
E:\FR\FM\21FEN2.SGM
21FEN2
sroberts on DSK5SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
the tide due to the piling up of water
against a coast by strong winds such as
those accompanying a hurricane or
other intense storm.
Historic Property: Any prehistoric or
historic district, site (including
archaeological site), building, structure,
or other object included in, or eligible
for inclusion in, the National Register of
Historic Places maintained by the
Secretary of the Interior. This term
includes artifacts, records, and remains
that are related to and located within
such properties. The term includes
properties of traditional religious and
cultural importance to an Indian tribe or
Native Hawaiian organization and that
meet the National Register criteria (36
CFR part 60).
Independent utility: A test to
determine what constitutes a single and
complete non-linear project in the Corps
regulatory program. A project is
considered to have independent utility
if it would be constructed absent the
construction of other projects in the
project area. Portions of a multi-phase
project that depend upon other phases
of the project do not have independent
utility. Phases of a project that would be
constructed even if the other phases
were not built can be considered as
separate single and complete projects
with independent utility.
Indirect effects: Effects that are caused
by the activity and are later in time or
farther removed in distance, but are still
reasonably foreseeable.
Intermittent stream: An intermittent
stream has flowing water during certain
times of the year, when groundwater
provides water for stream flow. During
dry periods, intermittent streams may
not have flowing water. Runoff from
rainfall is a supplemental source of
water for stream flow.
Loss of waters of the United States:
Waters of the United States that are
permanently adversely affected by
filling, flooding, excavation, or drainage
because of the regulated activity.
Permanent adverse effects include
permanent discharges of dredged or fill
material that change an aquatic area to
dry land, increase the bottom elevation
of a waterbody, or change the use of a
waterbody. The acreage of loss of waters
of the United States is a threshold
measurement of the impact to
jurisdictional waters for determining
whether a project may qualify for an
NWP; it is not a net threshold that is
calculated after considering
compensatory mitigation that may be
used to offset losses of aquatic functions
and services. The loss of stream bed
includes the linear feet of stream bed
that is filled or excavated. Waters of the
United States temporarily filled,
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
flooded, excavated, or drained, but
restored to pre-construction contours
and elevations after construction, are
not included in the measurement of loss
of waters of the United States. Impacts
resulting from activities eligible for
exemptions under Section 404(f) of the
Clean Water Act are not considered
when calculating the loss of waters of
the United States.
Non-tidal wetland: A non-tidal
wetland is a wetland that is not subject
to the ebb and flow of tidal waters. The
definition of a wetland can be found at
33 CFR 328.3(b). Non-tidal wetlands
contiguous to tidal waters are located
landward of the high tide line (i.e.,
spring high tide line).
Open water: For purposes of the
NWPs, an open water is any area that in
a year with normal patterns of
precipitation has water flowing or
standing above ground to the extent that
an ordinary high water mark can be
determined. Aquatic vegetation within
the area of standing or flowing water is
either non-emergent, sparse, or absent.
Vegetated shallows are considered to be
open waters. Examples of ‘‘open waters’’
include rivers, streams, lakes, and
ponds.
Ordinary High Water Mark: An
ordinary high water mark is a line on
the shore established by the fluctuations
of water and indicated by physical
characteristics, or by other appropriate
means that consider the characteristics
of the surrounding areas (see 33 CFR
328.3(e)).
Perennial stream: A perennial stream
has flowing water year-round during a
typical year. The water table is located
above the stream bed for most of the
year. Groundwater is the primary source
of water for stream flow. Runoff from
rainfall is a supplemental source of
water for stream flow.
Practicable: Available and capable of
being done after taking into
consideration cost, existing technology,
and logistics in light of overall project
purposes.
Pre-construction notification: A
request submitted by the project
proponent to the Corps for confirmation
that a particular activity is authorized
by nationwide permit. The request may
be a permit application, letter, or similar
document that includes information
about the proposed work and its
anticipated environmental effects. Preconstruction notification may be
required by the terms and conditions of
a nationwide permit, or by regional
conditions. A pre-construction
notification may be voluntarily
submitted in cases where preconstruction notification is not required
and the project proponent wants
PO 00000
Frm 00107
Fmt 4701
Sfmt 4703
10289
confirmation that the activity is
authorized by nationwide permit.
Preservation: The removal of a threat
to, or preventing the decline of, aquatic
resources by an action in or near those
aquatic resources. This term includes
activities commonly associated with the
protection and maintenance of aquatic
resources through the implementation
of appropriate legal and physical
mechanisms. Preservation does not
result in a gain of aquatic resource area
or functions.
Re-establishment: The manipulation
of the physical, chemical, or biological
characteristics of a site with the goal of
returning natural/historic functions to a
former aquatic resource. Reestablishment results in rebuilding a
former aquatic resource and results in a
gain in aquatic resource area and
functions.
Rehabilitation: The manipulation of
the physical, chemical, or biological
characteristics of a site with the goal of
repairing natural/historic functions to a
degraded aquatic resource.
Rehabilitation results in a gain in
aquatic resource function, but does not
result in a gain in aquatic resource area.
Restoration: The manipulation of the
physical, chemical, or biological
characteristics of a site with the goal of
returning natural/historic functions to a
former or degraded aquatic resource. For
the purpose of tracking net gains in
aquatic resource area, restoration is
divided into two categories: reestablishment and rehabilitation.
Riffle and pool complex: Riffle and
pool complexes are special aquatic sites
under the 404(b)(1) Guidelines. Riffle
and pool complexes sometimes
characterize steep gradient sections of
streams. Such stream sections are
recognizable by their hydraulic
characteristics. The rapid movement of
water over a course substrate in riffles
results in a rough flow, a turbulent
surface, and high dissolved oxygen
levels in the water. Pools are deeper
areas associated with riffles. A slower
stream velocity, a streaming flow, a
smooth surface, and a finer substrate
characterize pools.
Riparian areas: Riparian areas are
lands adjacent to streams, lakes, and
estuarine-marine shorelines. Riparian
areas are transitional between terrestrial
and aquatic ecosystems, through which
surface and subsurface hydrology
connects riverine, lacustrine, estuarine,
and marine waters with their adjacent
wetlands, non-wetland waters, or
uplands. Riparian areas provide a
variety of ecological functions and
services and help improve or maintain
local water quality. (See general
condition 23.)
E:\FR\FM\21FEN2.SGM
21FEN2
10290
Federal Register / Vol. 77, No. 34 / Tuesday, February 21, 2012 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
Shellfish seeding: The placement of
shellfish seed and/or suitable substrate
to increase shellfish production.
Shellfish seed consists of immature
individual shellfish or individual
shellfish attached to shells or shell
fragments (i.e., spat on shell). Suitable
substrate may consist of shellfish shells,
shell fragments, or other appropriate
materials placed into waters for
shellfish habitat.
Single and complete linear project: A
linear project is a project constructed for
the purpose of getting people, goods, or
services from a point of origin to a
terminal point, which often involves
multiple crossings of one or more
waterbodies at separate and distant
locations. The term ‘‘single and
complete project’’ is defined as that
portion of the total linear project
proposed or accomplished by one
owner/developer or partnership or other
association of owners/developers that
includes all crossings of a single water
of the United States (i.e., a single
waterbody) at a specific location. For
linear projects crossing a single or
multiple waterbodies several times at
separate and distant locations, each
crossing is considered a single and
complete project for purposes of NWP
authorization. However, individual
channels in a braided stream or river, or
individual arms of a large, irregularly
shaped wetland or lake, etc., are not
separate waterbodies, and crossings of
such features cannot be considered
separately.
Single and complete non-linear
project: For non-linear projects, the term
‘‘single and complete project’’ is defined
at 33 CFR 330.2(i) as the total project
proposed or accomplished by one
owner/developer or partnership or other
association of owners/developers. A
single and complete non-linear project
VerDate Mar<15>2010
18:29 Feb 17, 2012
Jkt 226001
must have independent utility (see
definition of ‘‘independent utility’’).
Single and complete non-linear projects
may not be ‘‘piecemealed’’ to avoid the
limits in an NWP authorization.
Stormwater management: Stormwater
management is the mechanism for
controlling stormwater runoff for the
purposes of reducing downstream
erosion, water quality degradation, and
flooding and mitigating the adverse
effects of changes in land use on the
aquatic environment.
Stormwater management facilities:
Stormwater management facilities are
those facilities, including but not
limited to, stormwater retention and
detention ponds and best management
practices, which retain water for a
period of time to control runoff and/or
improve the quality (i.e., by reducing
the concentration of nutrients,
sediments, hazardous substances and
other pollutants) of stormwater runoff.
Stream bed: The substrate of the
stream channel between the ordinary
high water marks. The substrate may be
bedrock or inorganic particles that range
in size from clay to boulders. Wetlands
contiguous to the stream bed, but
outside of the ordinary high water
marks, are not considered part of the
stream bed.
Stream channelization: The
manipulation of a stream’s course,
condition, capacity, or location that
causes more than minimal interruption
of normal stream processes. A
channelized stream remains a water of
the United States.
Structure: An object that is arranged
in a definite pattern of organization.
Examples of structures include, without
limitation, any pier, boat dock, boat
ramp, wharf, dolphin, weir, boom,
breakwater, bulkhead, revetment,
riprap, jetty, artificial island, artificial
PO 00000
Frm 00108
Fmt 4701
Sfmt 9990
reef, permanent mooring structure,
power transmission line, permanently
moored floating vessel, piling, aid to
navigation, or any other manmade
obstacle or obstruction.
Tidal wetland: A tidal wetland is a
wetland (i.e., water of the United States)
that is inundated by tidal waters. The
definitions of a wetland and tidal waters
can be found at 33 CFR 328.3(b) and 33
CFR 328.3(f), respectively. Tidal waters
rise and fall in a predictable and
measurable rhythm or cycle due to the
gravitational pulls of the moon and sun.
Tidal waters end where the rise and fall
of the water surface can no longer be
practically measured in a predictable
rhythm due to masking by other waters,
wind, or other effects. Tidal wetlands
are located channelward of the high tide
line, which is defined at 33 CFR
328.3(d).
Vegetated shallows: Vegetated
shallows are special aquatic sites under
the 404(b)(1) Guidelines. They are areas
that are permanently inundated and
under normal circumstances have
rooted aquatic vegetation, such as
seagrasses in marine and estuarine
systems and a variety of vascular rooted
plants in freshwater systems.
Waterbody: For purposes of the
NWPs, a waterbody is a jurisdictional
water of the United States. If a
jurisdictional wetland is adjacent—
meaning bordering, contiguous, or
neighboring—to a waterbody
determined to be a water of the United
States under 33 CFR 328.3(a)(1)–(6), that
waterbody and its adjacent wetlands are
considered together as a single aquatic
unit (see 33 CFR 328.4(c)(2)). Examples
of ‘‘waterbodies’’ include streams,
rivers, lakes, ponds, and wetlands.
[FR Doc. 2012–3687 Filed 2–17–12; 8:45 am]
BILLING CODE 3720–58–P
E:\FR\FM\21FEN2.SGM
21FEN2
Agencies
[Federal Register Volume 77, Number 34 (Tuesday, February 21, 2012)]
[Notices]
[Pages 10184-10290]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-3687]
[[Page 10183]]
Vol. 77
Tuesday,
No. 34
February 21, 2012
Part III
Department of Defense
-----------------------------------------------------------------------
Department of the Army, Corps of Engineers
-----------------------------------------------------------------------
Reissuance of Nationwide Permits; Notice
Federal Register / Vol. 77 , No. 34 / Tuesday, February 21, 2012 /
Notices
[[Page 10184]]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers
RIN 0710-AA71
Reissuance of Nationwide Permits
AGENCY: Army Corps of Engineers, DoD.
ACTION: Final notice.
-----------------------------------------------------------------------
SUMMARY: The U.S. Army Corps of Engineers (Corps) is reissuing 48 of
the 49 existing nationwide permits (NWPs), general conditions, and
definitions, with some modifications. The Corps is also issuing two new
NWPs, three new general conditions, and three new definitions. The
effective date for the new and reissued NWPs will be March 19, 2012.
These NWPs will expire on March 18, 2017. The NWPs will protect the
aquatic environment and the public interest while effectively
authorizing activities that have minimal individual and cumulative
adverse effects on the aquatic environment.
DATES: The NWPs and general conditions will become effective on March
19, 2012.
ADDRESSES: U.S. Army Corps of Engineers, Attn: CECW-CO-R, 441 G Street
NW., Washington, DC 20314-1000.
FOR FURTHER INFORMATION CONTACT: Mr. David Olson at 202-761-4922 or by
email at david.b.olson@usace.army.mil or access the U.S. Army Corps of
Engineers Regulatory Home Page at https://www.usace.army.mil/CECW/Pages/cecwo_reg.aspx.
SUPPLEMENTARY INFORMATION:
Executive Summary
The U.S. Army Corps of Engineers (Corps) issues nationwide permits
(NWPs) to authorize certain activities that require Department of the
Army permits under Section 404 of the Clean Water Act and/or Section 10
of the Rivers and Harbors Act of 1899. The purpose of this regulatory
action is to reissue 48 existing NWPs and issue two new NWPs. In
addition, three new general conditions and three new definitions will
be issued. The NWPs may be issued for a period of no more than five
years. Therefore, the Corps must reissue the NWPs every five years to
continue to authorize these activities. These 50 NWPs will go into
effect on March 19, 2012.
The NWPs authorize activities that have minimal individual and
cumulative adverse effects on the aquatic environment. The NWPs
authorize a variety of activities, such as aids to navigation, utility
lines, bank stabilization activities, road crossings, stream and
wetland restoration activities, residential developments, mining
activities, commercial shellfish aquaculture activities, and
agricultural activities. Some NWP activities may proceed without
notifying the Corps, as long as those activities satisfy the terms and
conditions of the NWPs. Other NWP activities cannot proceed until the
project proponent has submitted a pre-construction notification to the
Corps, and for most NWPs the Corps has 45 days to notify the project
proponent whether the activity is authorized by NWP.
Background
In the February 16, 2011, issue of the Federal Register (76 FR
9174), the U.S. Army Corps of Engineers (Corps) published its proposal
to reissue 48 existing nationwide permits (NWPs), issue two new NWPs,
and not reissue one NWP. The Corps also proposed to reissue its general
conditions and add two new general conditions.
After evaluating the comments received in response to the February
16, 2011, proposal, we have made a number of changes to the NWPs,
general conditions, and definitions to further clarify the permits,
general conditions, and definitions, facilitate their administration,
and strengthen environmental protection. Examples of improved
environmental protection include: imposing limits on surface coal
mining activities authorized by NWP 21; modifying NWP 27 to authorize
additional aquatic resource restoration and enhancement activities such
as the rehabilitation and enhancement of tidal streams, wetlands, and
open waters; and providing flexibility in designing crossings of
streams and other waterbodies so that movements of aquatic species can
be maintained after taking into account the characteristics of the
stream or waterbody and the surrounding landscape (see general
condition 2, aquatic life movements). These changes are discussed in
the preamble.
The Corps is reissuing 48 existing NWPs, issuing two new NWPs,
reissuing 28 existing general conditions, and issuing three new general
conditions. The Corps is also reissuing all of the NWP definitions, and
adding three new definitions. The Corps is also splitting one existing
definition into two definitions as they relate to single and complete
projects. The effective date for these NWPs, general conditions, and
definitions is March 19, 2012. These NWPs, general conditions, and
definitions expire on March 18, 2017.
Grandfather Provision for Expiring NWPs
In accordance with 33 CFR part 330.6(b), activities authorized by
the current NWPs issued on March 12, 2007, that have commenced or are
under contract to commence by March 18, 2012, will have until March 18,
2013, to complete the activity under the terms and conditions of the
current NWPs. Nationwide permit 21 activities that were authorized by
the 2007 NWP 21 may be reauthorized without applying the new limits
imposed on NWP 21, provided the permittee submits a written request for
reauthorization to the district engineer by February 1, 2013, and the
district engineer determines that the on-going surface coal mining
activity will result in minimal adverse effects on the aquatic
environment and notifies the permittee in writing that the activity is
authorized under the 2012 NWP 21.
Clean Water Act Section 401 Water Quality Certifications (WQC) and
Coastal Zone Management Act (CZMA) Consistency Determinations
The NWPs issued today will become effective on March 19, 2012. This
Federal Register notice begins the 60-day Clean Water Act Section 401
water quality certification (WQC) and the 90-day Coastal Zone
Management Act (CZMA) consistency determination processes.
After the 60-day period, the latest version of any written position
taken by a state, Indian tribe, or EPA on its WQC for any of the NWPs
will be accepted as the state's, Indian tribe's, or EPA's final
position on those NWPs. If the state, Indian tribe, or EPA takes no
action by April 23, 2012, WQC will be considered waived for those NWPs.
After the 90-day period, the latest version of any written position
taken by a state on its CZMA consistency determination for any of the
NWPs will be accepted as the state's final position on those NWPs. If
the state takes no action by May 21, 2012, CZMA concurrence will be
presumed for those NWPs.
While the states, Indian Tribes, and EPA complete their WQC
processes and the states complete their CZMA consistency determination
processes, the use of an NWP to authorize a discharge into waters of
the United States is contingent upon obtaining individual water quality
certification or a case-specific WQC waiver. Likewise, the use of an
NWP to authorize an activity within a state's coastal zone, or outside
a state's coastal zone that will affect land or water uses or natural
[[Page 10185]]
resources of that state's coastal zone, is contingent upon obtaining an
individual CZMA consistency determination, or a case-specific
presumption of CZMA concurrence. We are taking this approach to reduce
the hardships on the regulated public that would be caused by a
substantial gap in NWP coverage if we were to wait until the WQC 60-day
period and the CZMA 90-day period ended before these NWPs would become
effective.
Discussion of Public Comments
I. Overview
In response to the February 16, 2011, Federal Register notice, we
received more than 26,600 comment letters, of which approximately
26,300 were form letters pertaining to NWP 21. The non-form letters we
received contained a few thousand comments on various components of the
NWPs and NWP Program implementation. We reviewed and fully considered
all comments received in response to the proposed rule.
General Comments
Many commenters expressed support for the proposed permits. Some
commenters stated that the changes are a step forward in improving
consistency in the NWP program. Many commenters endorsed the
fundamentals of the NWP program, stating that the permits could have a
beneficial impact to conducting infrastructure and mining projects
important to the country. Some stated that permitting delays and an
increase in individual permits would result without the NWP program,
creating a backlog for the Corps and resource agencies, while placing a
burden on regulated industries. Another commenter urged the Corps to
increase flexibility to allow for project modifications when needed due
to unanticipated challenges encountered during construction. Some
commenters stated that further streamlining is needed for increased
efficiency and reducing administrative burden while maintaining a high
level of environmental protection. One commenter said the Corps should
maximize rather than limit use of the NWP program in light of the
current economic situation, Federal budget cuts, and presidential
efforts to streamline regulations. Another commenter was pleased to see
the Corps hold the line against further restrictions on the NWP
program. Many commenters emphasized that a timely, efficient, and
consistent permitting system is critical to the nation's economy.
The NWP Program provides flexibility to readily authorize project
modifications if the NWP activity cannot be constructed in accordance
with the approved plans, as long as any modifications would still meet
the terms and conditions of applicable NWP(s) and qualify for NWP
authorization. In cases where the district engineer has issued an NWP
verification letter, the permittee should contact the district as soon
as he or she finds that the activity cannot be constructed in
accordance with the approved plans. The district engineer will then
determine if authorization by NWP is still appropriate. If it is not,
then the permittee will be instructed on the most appropriate mechanism
for permitting the modified activity.
We believe the final permits issued today maintain a proper balance
between efficiently authorizing activities with minimal individual and
cumulative adverse environmental effects and protecting the aquatic
environment. The NWPs provide a streamlined authorization process that
is consistent with the principles of Executive Order 13563, Improving
Regulation and Regulatory Review.
In contrast, many other commenters expressed general opposition to
the proposal, and said that the proposed rule weakens protection for
waters and should be withdrawn. Some commenters said that the proposal
threatens to undermine the important and statutorily mandated function
of the NWPs and the Clean Water Act, and is contrary to Congressional
intent. One commenter expressed opposition to the issuance of the NWPs,
stating that they will result in an increase in the number of
activities that can be permitted and a reduction in the opportunity for
public review and comment. Many of these commenters objected to the
goals of ``streamlining'' or ``improving regulatory efficiency,'' and
they said that the focus of the NWPs should be on compliance with the
Clean Water Act. Another commenter was concerned that the proposed NWPs
do not support the ``no overall net loss'' goal for wetlands, and that
the Corps analysis predicts that the NWPs will result in a decrease of
waters of the United States, including wetlands.
As discussed below, those NWPs that authorize discharges of dredged
or fill material into waters of the United States comply with the Clean
Water Act and the environmental criteria provided in its implementing
regulations, the 404(b)(1) Guidelines at 40 CFR part 230. The NWPs
authorize minor activities that result in minimal adverse effects on
the aquatic environment that would likely generate little, if any,
public comment if they were evaluated through the standard permit
process with a full public notice. Through the adoption of Section
404(e) of the Clean Water Act in 1977, Congress approved the use of
general permits as an important tool to keep the Corps Regulatory
Program manageable from a resources and manpower perspective, while
protecting the aquatic environment. The Corps first adopted the concept
of general permits in its final rule published on July 25, 1975 (see 40
FR 31321). The NWP program also continues to support the national goal
of ``no overall net loss'' for wetlands, and wetlands compensatory
mitigation will be required when appropriate and practicable to offset
losses of wetland area and functions. The ``no overall net loss'' goal
applies only to wetlands, and for other waters of the United States the
goal is to avoid and minimize losses of those waters and to provide
compensatory mitigation to offset those losses if it is appropriate and
practicable to do so. Stream mitigation is becoming more commonplace as
the science and practical applications become further developed.
Some commenters stated that the NWPs should require consideration
of less damaging alternatives or demonstrate that NWP activities result
in minimal adverse environmental effects. One commenter said that there
is not sufficient emphasis on avoidance of impacts to waters of the
United States. Another commenter objected to using NWPs to expand
existing projects, stating that it discourages avoidance and
minimization.
Those NWPs that authorize discharges of dredged or fill material
into waters of the United States comply with the provisions of the
404(b)(1) Guidelines that address the issuance of general permits (see
40 CFR 230.7). A decision document is prepared for each NWP to provide
information to show that the NWP will authorize only those activities
that result in minimal adverse effects on the aquatic environment and
other public interest review factors. Supplemental decision documents
are prepared at a regional level to support the decision on whether to
add regional conditions to an NWP or suspend or revoke the use of that
NWP in a specific waterbody, category of waters, or geographic area to
ensure that only activities that result in minimal adverse effects on
the aquatic environment and other public interest review factors are
authorized by the NWP. In response to a pre-construction notification
or a request to verify that an activity is authorized by NWP, a
district engineer
[[Page 10186]]
may add activity-specific conditions to the NWP authorization or
suspend or revoke the NWP authorization if he or she determines that
the proposed activity would result in more than minimal adverse
effects.
Paragraph (a) of general condition 23, mitigation, requires
permittees to avoid and minimize adverse effects to waters of the
United States to the maximum extent practicable on the project site.
The use of NWPs to authorize the expansion of existing projects does
not discourage avoidance and minimization because this general
condition applies equally to all NWP authorizations, including those
that authorize expansion of existing projects. The consideration of
practicable alternatives in accordance with 40 CFR 230.10(a) does not
apply directly to discharges of dredged or fill material into waters of
the United States authorized by general permits (see 40 CFR
230.7(b)(1)).
Compliance With Section 404(e) of the Clean Water Act
Several commenters said that the proposed NWPs are contrary to the
Clean Water Act and violate Section 404(e) of that Act. Many commenters
asserted that the NWPs result in more than minimal adverse effects on
the aquatic environment, individually and cumulatively. These
commenters stated that the NWPs do not protect vitally important
functions of wetlands and streams, and that the proposal does not
satisfy the Corps legal obligation to limit general permits to
activities that cause minimal adverse impacts, individually and
cumulatively. They also said the Corps lacks the data to show that the
effects of the authorized activities are in fact minimal. Some
commenters expressed concern regarding the potential overuse of these
permits without the inclusion of acreage, linear feet, watershed or
regional limitations. Another commenter said that the NWPs fail to
describe similarly covered activities in precise terms.
The Corps disagrees with these comments. The NWPs comply with the
Clean Water Act and the environmental criteria provided in its
implementing regulations, the 404(b)(1) Guidelines at 40 CFR part 230.
Section 404(e) of the Clean Water Act states that the Chief of
Engineers may issue, after publishing a notice and providing an
opportunity a public hearing, general permits on a nationwide basis for
any category of activities involving discharges of dredged or fill
material into waters of the United States, if it is determined that the
activities in each category are similar in nature and result in minimal
individual and cumulative adverse environmental effects. The issuance
of the NWPs is consistent with these requirements and therefore
complies with the intent of the Clean Water Act. As discussed above,
national decision documents and supplemental decision documents are
prepared to demonstrate that an NWP will authorize only those
activities that have minimal individual and cumulative adverse effects
on the aquatic environment and other public interest review factors.
The decision documents use available data and other information to
support their conclusions.
Where appropriate and necessary, certain NWPs have acreage, linear
foot, or cubic yard limits, or combinations of those limits, to ensure
that authorized activities result in minimal individual and cumulative
adverse effects on the aquatic environment. Specifically, NWPs have
acreage limitations, NWPs have linear foot limitations, and NWPs have
cubic yard limitations. Many other NWPs have qualitative limitations in
the form of specific activities or situations that are not authorized,
or for which a PCN is required to allow the Corps to ensure on a case-
by-case basis that the adverse effects on the aquatic environment of
the project are truly minimal. A few NWPs have no explicit limits, but
this is limited to those that authorize activities that provide
benefits to the aquatic environment (e.g., NWP 27, which authorizes
aquatic habitat restoration, establishment, and enhancement activities,
and NWP 41, which authorizes activities for reshaping drainage ditches
to improve water quality), or those for which the nature of the
authorized activity inherently ensures that effects will be minimal
(e.g., NWP 10, which authorizes non-commercial, single boat, mooring
buoys). Division engineers may impose regional conditions on the NWPs
to add acreage, linear foot, or cubic yard limits, or reduce those
limits when the NWPs have specified limits in their terms and
conditions, to ensure those NWPs authorize only those activities that
result in minimal adverse effects on the aquatic environment.
The NWPs comply with the requirement in Section 404(e) of the Clean
Water Act to authorize categories of activities that are similar in
nature. Each NWP authorizes a specific category of activities, which
may be broadly defined for some NWPs to keep the NWP program
manageable. The Act does not require that activities authorized by an
NWP be identical, only that they be similar in nature. The permits meet
this requirement and are consistent with the Corps' longstanding
practice regarding the appropriate level of detail with which to
specify what constitutes activities that are similar in nature.
Compliance With the Section 404(b)(1) Guidelines
Several commenters said that the NWPs do not comply with the
404(b)(1) Guidelines. One commenter said that the Corps has no factual
basis to conclude that significant degradation of waters of the United
States has not occurred, which is required to be in compliance with the
Guidelines. This commenter recommended withdrawing the NWPs or
replacing them with state program general permits. One commenter stated
that the NWPs do not comply with the 404(b)(1) Guidelines because they
authorize discharges into special aquatic sites.
When we issue the NWPs, we fully comply with the requirements of
the 404(b)(1) Guidelines at 40 CFR 230.7, which govern the issuance of
general permits under Section 404 of the Clean Water Act. For each NWP
that authorizes discharges of dredged or fill material into waters of
the United States, the decision document contains a 404(b)(1)
Guidelines analysis. Section 230.7(b) of the 404(b)(1) Guidelines
requires a ``written evaluation of the potential individual and
cumulative impacts of the categories of activities to be regulated
under the general permit.'' Since the required evaluation must be
completed before the NWP is issued, the analysis is predictive in
nature. The estimates of potential individual and cumulative impacts,
as well as the projected compensatory mitigation that will be required,
are based on the best available data from the Corps district offices,
including the past use of NWPs. In our decision documents, we also used
readily available national data on the status of wetlands and other
aquatic habitats in the United States, and the foreseeable impacts of
the NWPs on those waters.
The process for issuing state programmatic general permits is
similar to the process for issuing NWPs, including the use of
information to support decisions. The 404(b)(1) Guidelines analysis for
state programmatic general permits is also predictive. Given those
similarities, compliance with the 404(b)(1) Guidelines is not different
for state programmatic general permits versus NWPs.
Despite the fact that many NWPs authorize discharges of dredged or
fill material into special aquatic sites, they are still in compliance
with the 404(b)(1) Guidelines. Section 230.7 of the 404(b)(1)
Guidelines does not
[[Page 10187]]
prohibit the use of NWPs to authorize discharges of dredged or fill
material into special aquatic sites. Many NWPs contain additional
provisions to protect special aquatic sites. For example, several NWPs
specifically require pre-construction notification for proposed
discharges of dredged or fill material into special aquatic sites
(e.g., NWP 13 for bank stabilization activities, NWP 14 for linear
transportation projects, NWP 18 for minor discharges). As another
example, NWP 19 for minor dredging activities, does not authorize
dredging in coral reefs or dredging activities that cause siltation
that degrades coral reefs. General condition 22, designated critical
resource waters, applies the prohibitions in paragraph (a) and the
notification requirement in paragraph (b) to wetlands (a special
aquatic site) adjacent to critical resource waters.
Compliance With the National Environmental Policy Act
Three commenters stated that the NWPs do not satisfy the
requirements of the National Environmental Policy Act (NEPA), as they
do not adequately consider indirect and cumulative effects on global
warming. One commenter said that degradation in air quality from
burning coal from mining projects must be addressed in an environmental
impact statement, and that the Corps has to address the implications of
climate change on aquatic ecosystems. Another commenter stated that the
scientific consensus on the impacts of climate change has to be
considered in the renewal of the NWPs. One commenter said the NWPs
should take into account ongoing federal efforts to address the effects
of climate change through federal programs. These federal programs
address mitigation of climate change (e.g., through reduction of
greenhouse gas emissions) and adaptation to climate change (e.g., by
adjustments made to reduce vulnerability resulting from changing
climate).
Although the Council on Environmental Quality has made available
draft guidance on the consideration of the effects of climate change
and greenhouse gas emissions, and sought public comment on that draft
guidance, they have not issued any final guidance specifically on how
to consider, in NEPA documents, the indirect and cumulative effects
Federal agency actions have on climate change. In the Council on
Environmental Quality's October 2011 Progress Report of the Interagency
Climate Change Adaptation Task Force entitled ``Federal Actions for a
Climate Resilient Nation'' adaptation is defined as ``adjustment in
natural or human systems to a new or changing environment that exploits
beneficial opportunities or moderates negative effects.''
A major cause of climate change is emissions of greenhouse gases.
Activities authorized by NWPs have little direct, indirect, or
cumulative effects on climate change and the emission of greenhouse
gases. There may be brief emissions of greenhouse gases during the
construction of activities authorized by NWP, specifically discharges
of dredged or fill material into waters of the United States or
structures or work in navigable waters of the United States. Any
greenhouse gas emissions that occur other than as a result of the
discharge of dredged or fill materials are outside of the Corps NEPA
scope of analysis because the Corps does not have the legal authority
to control those emissions. The degradation of air quality caused by
burning coal is not the result of a discharge of dredged or fill
material and therefore is outside the Corps legal authority. The
issuance of a Corps permit is designed to ensure that any discharges of
dredged or fill material into waters of the United States associated
with such mining comply with the Clean Water Act. A Corps permit does
not authorize coal mining per se, and therefore the effects of coal
mining that do not result from a discharge of dredge or fill material
to waters of the United States generally are beyond the Corps NEPA
scope of analysis.
The effects of climate change on aquatic ecosystems are a much
broader issue than the effects on the aquatic environment caused by
activities authorized by NWPs. The effects of climate change on
hydrology and extreme events are difficult to project. The effects will
vary by location and the sensitivity of resources to changes in
hydrology and extreme events. The timeframe used to project hydrologic
changes will also affect the evaluation. For activities with minimal
adverse effects on the aquatic environment that are eligible for
authorization by the NWPs, the Corps believes that any necessary
adaptation to climate change is appropriately addressed through land
use planning and zoning, which is the primary responsibility of state,
tribal, and local governments. Activities authorized by NWPs may be
part of state, tribal, or local adaptation efforts to mitigate the
effects of climate change.
On October 1, 2011, the Corps issued updated guidance on sea level
change considerations for Civil Works Program (Engineer Circular 1165-
2-211). The current Engineer Circular applies to Corps Civil Works
activities, but not to the Regulatory Program. As stated on page 25 of
its ``Climate Change Adaptation Plan and Report 2011'' (available at:
https://www.corpsclimate.us/adaptationpolicy.cfm), the Corps expects to
make larger changes in the next update of the Engineer Circular, ``and
the regulatory program will be added following appropriate
consultation.''
Compliance With the Endangered Species Act
One commenter acknowledged the Corps 2007 efforts to pursue
programmatic consultation for the NWP program with the U.S. Fish and
Wildlife Service and the National Marine Fisheries Service to ensure
compliance with the Endangered Species Act (ESA), stating that failure
to complete consultation violates the ESA, as well as Section 404(e) of
the Clean Water Act. Two commenters stated that the Corps has a
requirement to complete these consultations prior to the issuance of
the NWPs.
We have reinitiated programmatic Section 7 Endangered Species Act
consultation for the NWPs. If this consultation is not completed prior
to the effective date of these NWPs, district engineers will consult,
as necessary on a case-by-case basis with the U.S. Fish and Wildlife
Service and National Marine Fisheries Service in accordance with
general condition 18, endangered species. Division engineers may also
impose regional conditions on any of the NWPs to facilitate compliance
with the requirements of the Endangered Species Act.
Compliance With Section 304(d) of the National Marine Sanctuaries Act
One commenter stated that the proposed NWPs must comply with
Section 304(d) of the National Marine Sanctuaries Act (NMSA). Section
304(d)(1))(A) of the NMSA states that ``Federal agency actions internal
or external to a national marine sanctuary, including private
activities authorized by licenses, leases, or permits, that are likely
to destroy, cause the loss of, or injure any sanctuary resource are
subject to consultation with the Secretary.'' The regulations for
implementing section 304(d) are found at 15 CFR 922.187, and those
regulations state that the Federal agency consultation should be
conducted with the Director of the marine sanctuary. The consultation
may be conducted with Endangered Species Act section 7 consultation.
[[Page 10188]]
District engineers that have NOAA-designated marine sanctuaries
within their geographic area of responsibility should consult with the
Director of the marine sanctuary to determine which NWP activities
require activity-specific consultation under Section 304(d) of the
NMSA. Regional conditions should be adopted where necessary to ensure
compliance with the requirements of section 304(d).
New Nationwide Permits
We received several suggestions for the establishment of new NWPs
for various activities. Two commenters suggested developing an NWP to
authorize activities associated with linear gas facility infrastructure
based on the Federal Energy Regulatory Commission's (FERC) blanket
certification program that would allow the industry to undertake
routine activities without the need to obtain a case-specific
authorization from FERC for each project. One commenter recommended
issuing an NWP to authorize activities associated with controlling
nuisance and exotic plant species and another NWP to authorize
activities for innovative mitigation proposals. One commenter said that
an NWP should be developed to authorize the beneficial reuse of dredged
material, for up to 10,000 cubic yards of material. Another commenter
recommended adding an NWP to authorize discharges of dredged or fill
material to raise dam elevations to increase pool elevations of public
water supply reservoirs to increase potable water supplies and
wetlands.
We believe that existing NWPs such as NWPs 12, 3, and 39 are
sufficient to provide general permit authorization for gas utility
lines and associated infrastructure. Discharges of dredged or fill
material into waters of the United States or work in navigable waters
of the United States associated with the removal of nuisance or exotic
plant species may be authorized by NWP 27, aquatic habitat restoration,
establishment, and enhancement activities. Innovative mitigation
proposals may also be authorized by NWP 27, as long as those activities
result in net increases in aquatic resource functions and services and
satisfy the other terms and conditions of that NWP. We believe that the
beneficial reuse of dredged material, especially at such large
quantities, is more appropriately evaluated through the individual
permit process, to more thoroughly consider effects on existing aquatic
resource functions already being provided in the waters where the
reused dredged material might be placed.
Waivers of Certain NWP Limits
We proposed to modify the language concerning the use of waivers in
NWPs 13, 29, 36, 39, 40, 42, and 43 by clarifying that a waiver may be
granted only after the district engineer makes a written determination
concluding that the discharge will result in minimal adverse effects
and sets forth the basis for that determination. We also proposed to
apply the modified waiver language to NWPs 21, 44, and 50, as well as
to the two proposed new NWPs. Some commenters supported the proposed
modifications.
Many commenters said the proposed changes would allow district
engineers too much discretion, and there should be no waivers of NWP
limits. One commenter stated there was not a need for waivers because
many of the NWPs already require pre-construction notification and the
changes make the NWPs more difficult to obtain. The commenter said the
waivers create an additional paperwork burden and provide no
environmental benefits. Many commenters objected to the proposed
waivers, stating that they imply that ephemeral and intermittent
streams are considered lower in their function and value to the aquatic
environment and are provided less protection than perennial streams.
These commenters discussed the importance of ephemeral and intermittent
streams to overall watershed integrity and to water quality and stated
there is no scientific evidence to support the position that the use of
waivers will result in only minimal impacts. One commenter said that
before a waiver is issued, there should be analysis of cumulative
effects to the watershed. Several commenters stated that the use of
waivers in states with arid and semi-arid ecosystems does not properly
take into account the importance of headwater streams in these
ecosystems and could result in more than minimal individual and
cumulative effects.
The basic requirement for general permits, including NWPs, is that
they may only authorize activities that result in minimal individual
and cumulative adverse effects on the aquatic environment. Section
404(e) of the Clean Water Act and the regulations relevant to the
issuance of the NWPs (e.g., 33 CFR part 330 and 40 CFR 230.7) do not
mandate a single approach to satisfying that basic requirement. The
terms and conditions of the NWPs, including acreage, linear foot, and
cubic yard limits and allowing the use of certain NWPs in specific
types of waters, are intended to limit NWPs activities so that they do
not result in more than minimal adverse effects on the aquatic
environment. Division engineers have the authority to impose regional
conditions on NWPs to restrict or prohibit their use in certain waters
or other geographic areas. Another important tool is pre-construction
notification, which provides for district engineers to review proposed
NWP activities to ensure that they will result in minimal adverse
effects. In response to a pre-construction notification, a district
engineer may add activity-specific conditions to the NWP authorization
to further minimize adverse effects to the aquatic environment. For
those NWPs that allow district engineers review pre-construction
notifications and issue written waivers of certain limits, such as the
300 linear foot limit for the loss of intermittent and ephemeral stream
bed, the NWP activity must still satisfy the statutory and regulatory
requirements for general permits. The waiver process does not make the
NWP process more difficult. Instead, it provides an important tool for
districts to efficiently authorize activities with minimal adverse
effects on the aquatic environment after making a written determination
that the activity satisfies the NWP requirements.
We recognize the importance of intermittent and ephemeral streams
and the waiver process for certain NWPs requires district engineers to
make activity-specific evaluations of the intermittent or ephemeral
streams proposed to be filled or excavated before deciding whether to
waive the 300 linear foot limit. To issue a waiver, the district
engineer must make, and document, a minimal adverse effects
determination, which as discussed above, is consistent with the
statutory and regulatory requirements for general permits. As part of
the analysis, the district engineer must consider the individual and
cumulative adverse effects on the aquatic environment on a watershed
basis, or for another appropriate geographic area, such as an
ecoregion. For those activities in arid and semi-arid regions, district
engineers will use local criteria as well as their knowledge of arid
and semi-arid ecosystems to make decisions on pre-construction
notifications for proposed activities that might be eligible for
waivers. The basis for any waiver, including appropriate consideration
of individual and cumulative effects, will be documented in the
district engineer's written determination.
Several commenters noted concern with the 45-day pre-construction
notification review period to provide a
[[Page 10189]]
decision whether to grant or deny the waiver. One commenter noted the
applicant can proceed without authorization if the Corps fails to
respond to a waiver request within the 45 day time limit. Several
commenters expressed concern with the additional time and the expense
that could be incurred by the applicant who must wait for the waiver
decision and written determination.
We believe that the 45-day pre-construction notification review
period is sufficient for district engineers to make their written
determinations on whether to issue waivers of the applicable limits for
certain NWPs. The text of the NWPs that allow waivers of certain limits
clearly states that the waivers must be made by the district engineer
in writing. In addition, paragraph (a)(2) of general condition 31, pre-
construction notification, says that if a proposed activity requires a
written waiver to exceed specified limits of an NWP, the permittee may
not begin that activity until the district engineer issues the waiver.
The 45-day pre-construction notification review period still applies to
pre-construction notifications that involve requests to waive specific
limits of an NWP, but the project proponent may not proceed with the
NWP activity if a written waiver is needed and the district engineer
did not provide a written waiver by the time the 45-day review period
ends. The Corps will make every effort to act on waiver requests within
the 45-day review period. If a prospective permittee is concerned that
a written waiver will not be issued within the 45-day pre-construction
notification review period, then he or she has the option of modifying
the proposed activity so that it does not exceed any specified limit of
the applicable NWP and does not require a written waiver.
Many commenters said that specific criteria should be applied to
the waiver process to ensure proposed activities result in minimal
individual or cumulative adverse effects on the aquatic environment.
One commenter stated that the waivers provide little incentive to
minimize impacts. Another commenter said that water quality
certification cannot be issued for NWPs that have limits that can be
waived by district engineers because the state cannot certify that
those activities meet state water quality standards. One commenter said
that when waivers are issued by district engineers, the district
engineer must include a fact-specific basis to support his or her
finding.
The criteria that are to be applied to requested waivers of
specified limits for certain NWPs are the same general criteria that
are to be used to make any minimal adverse effects determination for
the NWPs. Criteria that are to be used to make minimal adverse effects
determinations are provided in paragraph (1) of Section D, District
Engineer's Decision. The waivers still provide incentives to minimize
impacts because the NWP authorization threshold (i.e., activities must
result in minimal individual and cumulative adverse effects on the
aquatic environment) is lower than the authorization threshold for
individual permits (e.g., the proposed activity is not contrary to the
public interest and, if it involves discharges of dredged or fill
material into waters of the United States, it complies with the
404(b)(1) Guidelines). In other words, a waiver cannot be granted if
the activity does not meet the minimal effects threshold, and applicant
cannot proceed without the Corps' written determination. Applicants who
submit waiver requests run the risk that the waiver will be denied, and
valuable time will be lost in obtaining Department of the Army
authorization. Thus, it is in the applicant's interest to modify the
proposed activity if possible to avoid exceeding a threshold that
requires a waiver, and especially to avoid submitting waiver requests
for projects that will in fact have more than minimal adverse effects.
States can issue water quality certifications for NWPs based on the
specified acreage, linear foot, or cubic yard limits, and require
individual water quality certifications for losses of waters of the
United States that exceed the specified limits and must be waived in
writing by district engineers. The written waiver determinations
prepared by the district engineer have to be activity-specific, and
explain the factual basis of the waiver.
Several commenters said that the additional information required
for a request for a waiver and the requirement to use of a functional
assessment method that is available and practicable would impose a
significant documentation obligation on Corps staff.
The NWPs do not impose additional information requirements for
requests for waivers of specific limits of NWPs. In addition, there is
no requirement to use functional assessments to make decisions on
waiver requests. The sentence in paragraph (1) of Section D, District
Engineer's Decision, on the use of functional assessments to make
minimal effects determinations, states that those methods ``may'' be
used if they are available and practicable to use. However, the Corps
does agree that there must be a factual basis for the waiver (which may
entail the use of a functional assessment methodology, among other
possible approaches) and documenting this does impose an additional
obligation on the Corps. Applicants should provide the district
engineer as much factual information as possible to support the waiver
request and facilitate the district engineer's determination.
Several commenters supported the proposed changes requiring agency
coordination and a written decision. Several commenters said that all
appropriate state and Federal resource agencies should be provided an
opportunity to comment on requests for waivers. One commenter stated
there is no need for additional agency coordination unless specific
resource issues are identified, such as compliance with the Endangered
Species Act or the National Historic Preservation Act.
We have modified the proposed provision requiring agency
coordination for pre-construction notifications involving losses of
greater than 1,000 linear feet of intermittent and ephemeral stream
bed, to require agency coordination for all pre-construction
notifications requesting a waiver of the 300 linear foot limit for
filling or excavating intermittent or ephemeral streams (see paragraph
(d)(2) of general condition 31, pre-construction notification). Under
this agency coordination process, district engineers will solicit
comments from the agencies to assist in making the written minimal
adverse effects determination necessary for a waiver of the 300 linear
foot limit to take effect. Compliance with the Endangered Species Act
and the National Historic Preservation Act is addressed by general
conditions 18 and 20, respectively.
One commenter said that the loss of stream bed should be defined
and the 300 linear foot limit should be reduced to 150 linear feet of
loss of stream bed for those NWPs. Another commenter suggested reducing
the linear foot limit for loss of stream bed to 50 linear feet. One
commenter stated that the 300 linear foot limit should not apply to
ephemeral streams. One commenter said that waivers should be allowed
for losses of perennial streams if the adverse effects are determined
to be minimal and the perennial stream is limited in its aquatic
function.
The loss of stream bed is defined in ``loss of waters of the United
States'' as the linear feet of stream bed that is filled or excavated.
We believe the 300 linear foot limit is appropriate to ensure that
losses of stream beds result in minimal
[[Page 10190]]
adverse effects on the aquatic environment. Division engineers may add
regional conditions to an NWP to reduce the linear foot limit to an
amount less than 300 linear feet. The 300 linear foot limit should not
be waived for losses of perennial streams because they function
differently than intermittent and ephemeral streams, and we believe it
will generally not be the case that losses of more than 300 linear feet
of a perennial stream would constitute a minimal adverse effect. We
believe it would not be a good use of Corps or applicant resources to
allow waiver requests for perennial streams on the remote chance that
the adverse effects of such an activity would be found to be minimal.
The functions provided by perennial streams, intermittent streams, and
ephemeral streams differ, in terms of ecological processes and
duration. Perennial streams provide aquatic habitat functions year-
round, while intermittent streams provide aquatic habitat during the
months when water is flowing in the stream channel, and when hyporheic
flow occurs during drier months. Ephemeral streams provide aquatic
habitat functions only for brief periods, because they have flowing
water only during, and briefly after, precipitation events. Other
important stream functions, such as sediment transport, nutrient
cycling, and energy transport also depend on the presence of flowing
water and, for some of those functions, the presence of aquatic
organisms inhabiting those waters. The other stream functions are
present year-round for perennial streams, and for much of the year for
intermittent streams. In ephemeral streams, sediment transport,
nutrient cycling, and energy transport functions occur during brief
periods or are absent. The functional differences exhibited by
perennial, intermittent, and ephemeral streams provide a scientific
basis for not allowing a waiver for perennial streams. District
engineers will make written case-specific determinations on whether to
waive the 300-linear foot limit for losses of intermittent and
ephemeral stream bed, based in part on the considerations listed in
paragraph (1) of Section D, ``District Engineer's Decision.''
Clean Water Act Jurisdiction
Many commenters cited the U.S. Supreme Court decisions issued in
2001 and 2006, for Solid Waste Agency of Northern Cook County v. U.S.
Army Corps of Engineers and Rapanos v. United States (Rapanos), as well
as other court decisions, and said that the proposed NWPs exceed the
Corps jurisdictional authority under Section 404 of the Clean Water Act
and reflect the Corps and EPA's flawed broad interpretation of what
constitutes a water of the United States, specifically for ephemeral
streams. Most commenters said the proposed NWPs would result in an
expansion of Clean Water Act authority and jurisdiction that would have
a negative impact on the nation's economy by creating excessive burdens
on developers, farmers, and Corps staff. Another commenter said the
Corps should not assert jurisdiction over isolated mining pits.
The NWPs do not assert jurisdiction over waters and wetlands.
Rather, the NWPs are a form of Department of the Army authorization to
comply with the permit requirements of Section 404 of the Clean Water
Act and/or Section 10 of the Rivers and Harbors Act of 1899. Nationwide
permits issued under the authority of Section 404 of the Clean Water
Act authorize discharges of dredged or fill material into waters of the
United States. Nationwide permits issued under the authority of Section
10 of the Rivers and Harbors Act of 1899 authorize structures or work
in navigable waters of the United States. Determining the geographic
jurisdiction under the Clean Water Act (i.e., identifying waters and
wetlands that are waters of the United States) is a separate process
than the NWP authorization process. Likewise, identifying navigable
waters of the United States for the purposes of geographic jurisdiction
under Section 10 of the Rivers and Harbors Act of 1899 is a different
process than the NWP authorization process. These NWPs do not expand
either geographic jurisdiction or activities-based jurisdiction under
the Clean Water Act. Activity-based jurisdiction under the Clean Water
Act is determined by applying the appropriate regulations from 33 CFR
part 323. These NWPs continue to provide a streamlined process for
obtaining authorization for activities that require Department of the
Army permits under either Section 404 of the Clean Water Act and/or
Section 10 of the Rivers and Harbors Act of 1899. Determining whether
isolated mining pits are subject to Clean Water Act jurisdiction is a
case-specific inquiry to be made by applying the appropriate
regulations and guidance. A project proponent or landowner may contact
the Corps district office that has the responsibility for that region
of the country and request a jurisdictional determination for an
isolated mining pit or any other area that might be considered a water
or wetland. The Corps district will respond to that request and inform
the project proponent or landowner of the status of that water with
respect to Clean Water Act jurisdiction.
Comments on Administrative Requirements
Executive Order 13211
One commenter stated that these proposed regulations will cause
coal mines to cease operations and believe the proposal is subject to
Executive Order 13211, Actions Concerning Regulations That
Significantly Affect Energy Supply, Distribution, or Use.
Although we have made substantial changes to NWP 21, some surface
coal mining activities will still be authorized by this NWP. The
changes to NWP 21 will not cause coal mines to cease operations,
because there are other forms of Department of the Army authorization
available if the coal mining activity involves discharges of dredged or
fill material into waters of the United States. Project proponents may
apply for individual permits to obtain Department of the Army
authorization for such activities. Any activity that could have
previously been authorized under earlier versions of NWP 21 would still
be eligible for authorization under an individual permit. Thus, while
there may be additional paperwork burden for mine operators, the Corps
does not believe that the changes in these permits will have a
significant impact on the supply, distribution, or use of energy (e.g.,
coal).
Executive Order 13563
Several commenters stated that the proposed NWPs are not consistent
with EO 13563 for ``Improving Regulation and Regulatory Review''
because the modifications to the NWPs would impose numerous onerous
conditions and limitations on applicants.
The NWPs continue to provide a streamlined process for authorizing
activities that require Department of the Army permits under Section
404 of the Clean Water Act and/or Section 10 of the Rivers and Harbors
Act of 1899. The average processing times for standard permit
applications in Fiscal Year 2010 was 221 days, while the average
processing time for NWP pre-construction notifications and voluntary
requests for NWP verifications was 32 days. The terms and conditions of
the NWPs are necessary to ensure that the NWPs comply with applicable
statutes and regulations, including the requirement that only
activities with minimal adverse effects, both
[[Page 10191]]
individually and cumulatively, be authorized by NWPs.
Water Quality Certification Issues
One commenter said that the Corps should provide an opportunity for
state and Tribal water quality certification agencies to participate
early in the NWP reissuance process, to reduce potential conflicts
during the water quality certification process. Another commenter asked
for clarification regarding enforcement of the NWPs, in cases where a
provisional NWP verification is issued, but the permittee proceeds with
work without receiving the individual water quality certification. This
commenter asked whether the Corps or the state would initiate an
enforcement action. One commenter objected to use of provisional NWP
verifications in cases where water quality certification has not yet
been issued for a particular NWP activity.
The current NWP reissuance process provides sufficient opportunity
to reduce potential conflicts during the water quality certification
process. States and Tribes begin their water quality certification
processes when the proposal to reissue the existing NWPs and issue new
NWPs is published in the Federal Register for public comment. Water
quality certification agencies are encouraged to submit comments on the
NWP proposal. But it is important to remember that each state and Tribe
is likely to have different water quality standards, and the national
terms and conditions for the NWPs cannot address those regional
variations.
After the comments received in response to the proposal are
reviewed, the final NWPs are developed. Once the final NWPs are
published in the Federal Register, States and Tribes have another
opportunity to decide whether to issue or deny water quality
certification for the NWPs. States and Tribes will have 90 days to make
their water quality certification decisions.
If water quality certification was denied for an NWP, then the
permittee must obtain an individual water quality certification or a
waiver, even if the Corps issued a provisional NWP verification. The
provisional NWP verification merely informs the prospective permittee
that the Corps has determined that the proposed activity qualifies for
NWP authorization, as long as the permittee receives an individual
water quality certification or waiver. The prospective permittee should
provide a copy of the individual water quality certification to the
Corps district. The Corps has full authority to pursue an enforcement
action for not obtaining an individual water quality certification or
waiver, which is a violation of the terms of the permit. Case-specific
decisions on appropriate enforcement actions are at the Corps
discretion. The provision for NWP verification is an important tool to
be responsive to users of the NWPs, and to inform them of their need to
work with the water quality certification agency to comply with the
requirements of Section 401 of the Clean Water Act. The provisional
verification serves to inform the applicant that all other requirements
for NWP verification have been satisfied and allows the applicant to
focus on obtaining the required state certifications.
Discussion of Comments
Nationwide Permits
NWP 1. Aids to Navigation. There were no changes proposed for this
NWP, and no comments were received. This NWP is reissued without
change.
NWP 2. Structures in Artificial Canals. There were no changes
proposed for this NWP. One commenter recommended not reissuing this NWP
because a state will deny water quality certification.
The potential for a state to deny water quality certification for
an NWP is not a sufficient basis for not reissuing an NWP. The water
quality certification process is independent of the decision on whether
to issue or reissue an NWP. This NWP is reissued without change.
NWP 3. Maintenance. We proposed to modify this NWP to clarify that
stream channel excavation immediately adjacent to the structure or fill
being maintained is authorized under paragraph (a) and does not require
a PCN. We also proposed to replace the word ``and'' with ``and/or'' in
paragraph (b) to indicate that the activity does not need to include
the placement of new or additional riprap to qualify for this NWP.
Several commenters supported the change to paragraph (a) to allow
excavation in a stream channel immediately adjacent to a structure or
fill as part of the maintenance activity, without requiring pre-
construction notification. Some commenters specifically supported the
ability to do minor excavation within stream channels to install a
larger culvert or bridge that would improve fish passage without a pre-
construction notification. Two commenters asked which types of stream
channel modifications could be authorized under paragraph (a). Another
commenter said that the proposed modification does not adequately
clarify that a pre-construction notification is not required for stream
channel modification as discussed in the proposed rule. This commenter
recommended that paragraph (a) state that stream channel modification
immediately adjacent to the structure or fill being maintained is
authorized without pre-construction notification. One commenter
suggested that paragraph (a) include the removal of material from
within existing structures. One commenter indicated that the scope of
activities considered as stream channel modifications should be
clarified, because certain stream channel modifications such as
sediment or debris removal and reestablishment of the original bridge-
stream alignment are needed to maintain a safe crossing with sufficient
hydraulic capacity. Another commenter indicated that while stream
channel modification is restricted to the minimum necessary, there
should be a 300 linear foot impact limit. One commenter did not support
the proposed modification, stating that pre-construction notification
should be required for stream channel excavation near a structure
because excavation has the potential to uncover unknown archeological
resources.
We have changed the text of paragraphs (a) and (b) to clarify which
stream modifications fall under paragraph (a) and which fall under
paragraph (b). The removal of material from waters within, or
immediately adjacent to, the structure or fill are authorized under
paragraph (a) and do not require pre-construction notification. The
removal of material from waters that are not immediately adjacent to
the structure or fill, but within the limits in paragraph (b), may be
authorized under paragraph (b). This NWP authorizes only activities
that repair or return an activity to previously existing conditions. We
do not believe it is necessary to place additional limits on this NWP
because the current limits are sufficient to ensure minimal effects.
Paragraph (a) only authorizes minor stream channel modifications
necessary to repair, replace, or rehabilitate the structure or fill,
which may include minor deviations to account for changes in materials,
construction techniques, requirements of other regulatory agencies, or
current construction codes or safety standards. Such minor deviations
could be done to improve conditions to facilitate aquatic species
movements. General conditions 20 and 21 address the protection of
historic properties and actions to be taken if previously unknown
remains or artifacts are discovered during the maintenance activity.
[[Page 10192]]
Several commenters recommended adding the word ``or stabilization''
after ``repair, rehabilitation, replacement'' in paragraph (a) to
clarify that stabilization activities are included in paragraph (a).
Two commenters requested that practicability be considered with the
``minimum necessary.'' One commenter requested that the NWP include the
requirements of other regulatory agencies as a reason for allowing
minor deviations in a structure's configuration or filled area.
We do not believe it would be appropriate to include stabilization
activities under paragraph (a) since some stabilization activities may
result in more than a minor deviation in the structure's configuration
or filled area. District engineers already consider what is practicable
when reviewing proposed NWP 3 activities, and we do not believe it is
necessary to provide additional clarification. We agree that the
requirements of other regulatory agencies is an appropriate basis for
making minor changes in a structure or filled area during maintenance,
especially if those regulatory requirements help protect aquatic
resources.
Several commenters stated that the placement of new or additional
riprap to protect small structures be included in paragraph (a). A
commenter requested clarification that the placement of pipe liners and
concrete repairs to flow lines of pipes are examples of maintenance
activities authorized by this NWP. One commenter expressed concern that
authorizing the expansion of existing projects into waters of the
United States discourages avoidance and minimization of adverse impacts
and violates the 404(b)(1) Guidelines. Another commenter indicated that
work that is immediately adjacent to the project is not maintenance and
that the work should be limited to the extent of the original project.
The placement of riprap to protect a structure or fill is more
appropriately authorized by paragraph (b) of this NWP, after the
district engineer reviews the pre-construction notification. If the
installation of pipe liners or concrete repairs to flow lines are
necessary and result only in a minor deviation to the structure's
configuration or filled area, it may be authorized under paragraph (a).
Paragraph (a) only authorizes minor deviations to the structure or
filled area that are necessary to conduct the repair, rehabilitation,
or replacement activity, and complies with the general condition
requiring on-site avoidance and minimization.
One commenter said that the permit should require that the Corps be
notified, within 12 months of the date of the damage, for activities
involving the repair, rehabilitation, or replacement of structures or
fills destroyed or damaged by storms, floods, fire or other discrete
events.
The repair, rehabilitation, or replacement of structures or fills
destroyed or damaged by these types of events does not require pre-
construction notification. This is because restoring a structure or
fill to its pre-event configuration will not result in more than
minimal adverse effects relative to the pre-event status quo. If a
project proponent wants a waiver of the two-year limit, the district
engineer can issue a waiver if warranted, without reviewing a pre-
construction notification.
Some commenters expressed opposition over the proposed change from
``and'' to ``and/or'' under paragraph (b). They recommended retaining
the current language because they indicated that making the change to
``and/or'' would cause confusion as to which provision of this NWP
would be used to authorize riprap placement. The commenters also said
that this change would result in the regulation of excavation
activities that do not result in more than incidental fallback. Another
commenter was concerned that the change to ``and/or'' suggested that
the addition of riprap triggered pre-construction notification.
The use of the term ``and/or'' means that paragraph (b) authorizes
the removal of accumulated sediments or debris, the placement of new or
additional riprap to protect the structure, or both activities. This
NWP authorizes the removal of accumulated sediment and debris if that
activity involves a regulated discharge of dredged or fill material.
This NWP also authorizes the removal of accumulated sediments and
debris in the vicinity of existing structures from section 10 waters.
If a project proponent seeks authorization to place new or additional
riprap near the structure, then pre-construction notification is
required in accordance with paragraph (b) of this NWP.
One commenter said that the use of riprap should be discouraged and
only authorized if other options are not possible. Another commenter
suggested placing a limit on the amount of riprap that can be placed
under paragraph (b). One commenter stated that the placement of new or
additional riprap is not maintenance and should not be authorized by
NWP 3. One commenter recommended requiring mitigation techniques, such
as weep holes, when steel sheet piling is used for the maintenance
activity.
Riprap may be necessary to protect the integrity of these
structures. We have modified the next to last sentence of paragraph (b)
to clarify that new or additional riprap may be placed to protect the
structure or ensure the safety of the structure. In response to a pre-
construction notification (which is required for all placement of new
or additional riprap under paragraph (b) of this NWP), best management
practices or other mitigation measures may be required by the district
engineer to minimize adverse effect to the aquatic environment.
One commenter said that this NWP should not authorize maintenance
dredging and that NWP 19 should be used instead. This commenter also
recommended adding a cubic yard limit for the amount of dredging that
is authorized. Another commenter recommended that the removal of
sediment should be limited to 100 feet instead of 200 feet. One
commenter suggested increasing the linear foot limit to 500 feet. One
commenter also suggested that the applicant be required to provide
information to ensure that sediments proposed to be removed are not
contaminated.
Paragraph (b) may be used to authorize the removal of accumulated
sediment and debris from section 10 waters, and the 200 linear foot
limit is appropriate to ensure minimal adverse effects. District and
division engineers can condition this NWP to reduce the limit to less
than 200 linear feet. Maintenance dredging for the purposes of
navigation may be authorized by NWP 19 and may not be authorized by
this NWP. The only excavation authorized by this NWP is excavation
necessary for the maintenance, repair, rehabilitation, or replacement
of the structure, and then only within the limits established in the
permit. It is not necessary to require contaminant testing for the
sediments to be removed as a general condition of the permit, because
for many cases there is reason to believe that no contaminants are
present in the material. If there is reason to believe that
contaminants are present, the district engineer may require contaminant
testing and/or best management practices to control the release of
contaminants on a case-specific basis.
One commenter objected to the proposed removal of the words
``[w]here maintenance dredging is proposed'' from the ``Notification''
paragraph. Another commenter said that pre-construction notification
should only be
[[Page 10193]]
required when maintenance dredging is contemplated.
Pre-construction notification is required for all activities
covered under paragraph (b). When a permittee submits the pre-
construction notification for activities covered under paragraph (b),
they also must submit information regarding the original design
capacities and configurations of the outfalls, intakes, small
impoundments, and canals. The deleted phrase is meant to clarify the
``Notification'' provision.
A commenter asked if the term ``upland'' means ``above the ordinary
high water mark.'' That commenter also requested clarification as to
what constitutes ``temporary'' in terms of how long temporary fills can
be kept in place. Another commenter asked for a definition of ``minor
deviations'' and two commenters recommended that ``immediately
adjacent'' be defined.
There may be wetlands landward of the ordinary high water mark of a
river or other water of the United States, so it would not be
appropriate to define ``uplands'' as suggested in the previous
paragraph. Since some waters and wetlands are not subject to Clean
Water Act jurisdiction, we have changed the text of paragraph (b) to
require all dredged or excavated materials to be deposited and retained
in an area that has no waters of the United States, unless otherwise
specifically approved by the district engineer under separate
authorization. Waters of the United States will be identified in
accordance with applicable laws, regulations, and guidance, as
discussed above, and is not affected by the issuance of these NWPs.
What constitutes a temporary fill is at the discretion of the district
engineer. Determining what is a minor deviation and immediately
adjacent is also at the discretion of the district engineer. The Corps
believes this is appropriate because it is difficult to identify bright
line definitions for these terms that are applicable in all
circumstances. If an applicant is unsure whether a specific activity
qualifies, he or she should consult the appropriate Corps district
office.
Several commenters said that pre-construction notification should
not be required for activities authorized by paragraph (b), to reduce
delays. Other commenters requested removal of the pre-construction
notification requirements for sediment and debris removal, because the
work is often conducted immediately after storm events when a timely
response is critical to public safety. Another commenter also requested
that no pre-construction notification be required for activities under
paragraph (b), if the waters are ephemeral or intermittent streams.
Other commenters said that pre-construction notification should be
required for all activities authorized by this NWP.
We believe that the pre-construction notification requirements for
this NWP are appropriate. Pre-construction notification is required for
those activities that may have the potential to cause more than minimal
adverse effects on the aquatic environment. Activities authorized by
paragraph (b) usually involve larger impacts than those authorized by
paragraph (a) and therefore warrant pre-construction notification to
ensure that those activities will result in minimal adverse effects on
the aquatic environment.
One commenter suggested that this NWP should require the use of
best management practices to avoid sediment loading of waters. One
commenter suggested that paragraph (c) should be conditioned to protect
downstream water quality and prohibit sediment discharges. Two
commenters said that general condition 2 should not apply to NWP 3
activities.
General condition 12 requires the use of sediment and erosion
controls to minimize sediment inputs during construction. General
condition 2 does apply to this NWP, to ensure that aquatic life
movements can continue after the maintenance activity is conducted.
One commenter said that Tribes should be notified to avoid impacts
to tribal treaty natural resources and cultural resources. Two
commenters said that this NWP should be conditioned to allow fish
migration to continue. One of these commenters also stated that these
activities should not restrict water flows or constrict channels. One
commenter said that this NWP should be conditioned to address slope
stability to prevent overburden material from going into the water.
Another commenter recommended that all stream crossings span the
bankfull width and, in cases where the structures have a bottom, the
structure bottom shall match stream slope.
District engineers have conducted government-to-government
consultation with Tribes to determine which NWP activities should be
subject to project-specific consultation to protect Tribal treaty
natural resources and cultural resources. General Condition 18
specifies that no activity or its operation may impair reserved tribal
rights, including, but not limited to, reserved water rights and treaty
fishing and hunting rights. General condition 2 requires that NWP
activities be constructed to maintain aquatic life movements, and
general condition 9 requires that water flows be maintained to the
maximum extent practicable. The appropriate size for stream crossings
will be determined on a case-by-case basis, to comply with the
applicable general conditions.
A commenter recommended an addition to the ``Note'', which
references the section 404(f) exemption for maintenance. This commenter
suggested that the note include clarification as to who can use the
exemption for maintenance of irrigation and drainage ditches.
The section 404(f) exemption for maintenance of irrigation ditches
and drainage ditches can be used by anyone that qualifies for the
exemption. If a particular activity does not qualify for the exemption
because of the recapture provision in section 404(f)(2) or for any
other reason, NWP 3 may be used to authorize the maintenance activity,
if it meets the terms and conditions of the NWP.
This NWP is reissued with the modifications discussed above.
NWP 4. Fish and Wildlife Harvesting, Enhancement, and Attraction
Devices and Activities. There were no changes proposed for this NWP.
One commenter suggested adding fish aggregating devices to the list of
devices and activities authorized by this NWP. Fish aggregating devices
are man-made objects used to attract ocean-going pelagic fish. Before
these devices, commercial fishing used purse seining to target surface-
visible aggregations of birds and dolphins, which were used as a signal
of the presence of tuna schools below. However, the by-catch of
dolphins became a significant issue. The demand for dolphin-safe tuna
was a driving force for fish aggregating devices. Therefore, we concur
with the comment and have added that device to this NWP. This NWP is
reissued with the modification discussed above.
NWP 5. Scientific Measurement Devices. We proposed to modify this
NWP to require the removal of the device and any associated structures
or fills at the conclusion of the study. We also proposed to add
meteorological stations to the list of examples of the types of devices
authorized by this NWP, as well as current gages and biological
observation devices.
One commenter suggested that each of the listed devices be defined
and have footprint and height limitations. Another commenter said that
meteorological stations should not be authorized by this NWP. One
commenter supported adding meteorological stations, current gages,
[[Page 10194]]
and biological observation devices as examples of the types of devices
authorized by this NWP. Another commenter stated the Corps should
define a maximum period required for a meteorological tower study.
We do not believe it is necessary to provide definitions for each
of these devices and add limits. These devices are usually small in
size and since most of them are structures they do not typically result
in a loss of waters of the United States. This NWP already has a 25
cubic yard limit for weirs and flumes. Division engineers can
regionally condition this NWP to establish additional limits, including
maximum time frames for studies. In response to an NWP verification
request, district engineers may also place limits on these devices and
their use.
One commenter suggests the Corps clarify the requirements for the
removal of a scientific measurement device, and suggested that the NWP
not require excavation to remove the entire structure. This commenter
also said that cutting off the structure near the substrate of the
waterbody and leaving the buried foundation may result in less
environmental damage during removal. Another commenter said that where
meteorological towers are used for long-term data collection and
preliminary testing for wind turbines, those meteorological towers
would be removed during the wind energy facility decommissioning
process. One commenter stated that the device should be removed ``upon
completion of the use of the device to measure and record scientific
data.''
We have modified the provision in the NWP to require the removal of
the device when it will no longer be used to measure and record
scientific data. Meteorological towers used in wind energy generation
facility preliminary testing and operations could be left in place
until the facility is decommissioned. We have also changed the text to
state that structures or fills must be removed to the maximum extent
practicable, which would allow the foundation to remain if removing the
foundation would cause more adverse effects to the waters or wetlands
than leaving the foundation in place. We also added the word
``foundation'' to the examples of structures or fills that may be
associated with a scientific measurement device.
This NWP is reissued with the modifications discussed above.
NWP 6. Survey Activities. We proposed to modify this NWP to specify
how exploratory trenches are backfilled by stating the work ``must not
drain a water of the United States'' and to replace the 25 cubic yard
limit for temporary pads with a \1/10\-acre limit.
Several commenters supported changing the limit from 25 cubic yards
to \1/10\-acre. Two commenters expressed concern that removing the 25
cubic yard limit would result in more than minimal cumulative effects
to aquatic resources. One commenter recommended adding wetland
delineation sampling activities to the list of examples of activities
authorized by this NWP. Several others recommended adding conditions to
require removal of the temporary fills and re-establishment of pre-
construction contours and reseeding of affected areas after completion
of work. One commenter requested a definition of ``temporary pad.'' One
commenter recommended that exploratory trenching should not be
authorized below the ordinary high water mark of any waters of the
United States.
We are changing the limit of this NWP from 25 cubic yards to \1/
10\-acre. We have added ``sample plots or transects for wetland
delineations'' as an example of an activity authorized by this NWP.
General condition 13, removal of temporary fills, requires temporary
fills to be removed in their entirety and the area revegetated, as
appropriate. We do not believe it is necessary to define ``temporary
pad'' for purposes of this NWP, since it is simply a temporary fill
that must be removed upon completion of the survey activity. We do not
agree that exploratory trenching should be prohibited below the
ordinary high water mark since these activities result in temporary
impacts to the aquatic environment.
This NWP is reissued with the modification discussed above.
NWP 7. Outfall Structures and Associated Intake Structures. We did
not propose any changes to NWP. One commenter objected to the
reissuance of this NWP, stating that these activities adversely affect
aquatic vegetation or areas designated as critical habitat for fish
foraging and spawning, through increases in turbidity, discharges of
nutrients and contaminants, alteration of near-shore areas, and
scouring vegetation within the plume. Another commenter recommended
that outfall structures not be placed in wetlands or constructed in
such a manner that would create shoreline pockets capable of trapping
debris. One commenter recommended conditioning this NWP to ensure that
the outfall structure not extend into the receiving water and impair
navigation. One commenter suggested that for activities proposed to
occur on state-owned submerged lands, a separate authorization would be
required from that state.
In waters that have been designated as Essential Fish Habitat in
accordance with the Magnuson-Stevens Fishery Conservation and
Management Act, consultation with the National Marine Fisheries Service
will be conducted for proposed activities that may adversely affect
Essential Fish Habitat. That consultation will often result in
conservation recommendations that will protect habitat for fish
foraging and spawning. General condition 22, designated critical
resource waters, will also reduce adverse effects to fish foraging and
spawning areas caused by NWP activities in those critical resource
waters. Division engineers may regionally condition this NWP to
restrict or prohibit its use in specific waters, including those that
provide important habitat. In response to a pre-construction
notification, district engineers may also exercise discretionary
authority if the proposed activity would result in more than minimal
adverse effects on the aquatic environment, including vegetated
shallows and fish spawning and feeding areas. These structures may be
designed so that they do not trap debris. General condition 14, proper
maintenance, requires authorized structures and fills to be properly
maintained, which may include periodic removal of debris from outfall
structures and associated intake structures, to ensure that these
structures continue to function properly, do not trap debris, and do
not cause more than minimal adverse effects to nearshore aquatic
environments. Compliance with general condition 1, navigation, will
prevent adverse impacts to navigation. Permittees are responsible for
obtaining any other Federal, state or local permits that may be
required.
The NWP is reissued without change.
NWP 8. Oil and Gas Structures on the Outer Continental Shelf. We
proposed to modify this NWP to update the name of the former Minerals
Management Service to the Bureau of Ocean Energy Management Regulation,
and Enforcement (BOEMRE).
One commenter expressed support for the proposed modification. One
commenter recommended that no oil and gas structures or activities be
authorized through the nationwide permit process.
After the proposal to reissue this NWP was published, the Bureau of
Ocean Energy Management (BOEM) became the agency responsible for
issuing leases for oil and gas structures on the outer continental
shelf. We have modified the text of NWP 8 to reflect this change. This
NWP only authorizes structures
[[Page 10195]]
erected within areas of the outer continental shelf leased by the
Bureau of Ocean Energy Management. The general environmental concerns
are addressed in the required NEPA documentation prepared by BOEM prior
to issuing a lease. The Corps role is limited to reviewing impacts on
navigation and national security, as stated in 33 CFR part 322.5(f).
This NWP is reissued as proposed.
NWP 9. Structures in Fleeting and Anchorage Areas. There were no
changes proposed for this NWP, and no comments were received. This NWP
is reissued without change.
NWP 10. Mooring Buoys. There were no changes proposed for this NWP.
One commenter stated a notice to Tribes needs to be provided to avoid
adverse effects to Tribal treaty fishing access. One commenter
recommends prohibiting the use of this NWP in ``downgraded shellfish
harvest areas.'' Another commenter said that the permit should be
conditioned to require permittee's to provide information on the
location of the mooring buoy, including a site plan drawn to scale that
shows the distance of the buoy from the shore, mark the Corps permit
number on the buoy, and a statement that the buoy satisfies U.S. Coast
Guard requirements. One commenter suggested adding a limit on the
number of buoys installed per acre, based on the number and size of the
moored vessels.
Division engineers can regionally condition this NWP to prohibit
its use in areas where mooring buoys may impact access to Tribal
treating fishing areas. General condition 18 states that NWP activities
cannot impair reserved tribal rights. Division engineers can impose
regional conditions to restrict or prohibit its use in shellfish
harvesting areas. We do not agree that pre-construction notification
for the activities authorized by this NWP is necessary, to require
prospective permittees to submit detailed information on the location
of the proposed mooring buoy, a detailed site plan, and a statement
that it complies with U.S. Coast Guard requirements. All applicable
Coast Guard regulations must be complied with independent of the
conditions in this NWP. We believe that it is not necessary to limit
this NWP, at the national level, to install a particular number of
mooring buoys per acre. Division engineers may also regionally
condition this NWP to impose such restrictions.
This NWP is reissued without change.
NWP 11. Temporary Recreational Structures. There were no changes
proposed for this NWP. One commenter recommended requiring that
structures authorized under this NWP be removed immediately after use
ceases, instead of the 30 days specified in the NWP.
The Corps believes that the current requirements for the removal of
temporary structures are sufficient. Where necessary, shorter time
periods for removal can be imposed through regional conditioning or
through special conditions provided in activity-specific NWP
verifications.
The NWP is reissued without change.
NWP 12. Utility Line Activities. We proposed to modify this NWP to
clarify how to calculate the loss of waters of the United States for a
single and complete project that involves an access road. This proposed
change was intended as a clarification of long-standing practice, not a
substantive revision.
Several commenters supported the proposed change to this NWP.
Another commenter stated the proposed clarification would severely
restrict the use of NWP 12, because it changes the definition of single
and complete project. One commenter requested further clarification of
the intent and applicability of the term ``single and complete'' and
suggested we replace it with ``single and complete linear projects''
wherever the former phrase is found in NWP 12 since the NWP applies to
linear projects and their associated facilities and activities. Two
commenters requested confirmation that the calculation of impacts for
purposes of satisfying the NWP 12 threshold is done separately for each
crossing. Another commenter objected to the definition of ``single and
complete project'' at 33 CFR 330.2(i) and the NWP definitions section
and stated mitigation should be required for utility lines that result
in the loss of greater than \1/2\-acre.
This modification of the NWP does not change the definition of
single and complete project and does not affect its implementation,
except to clarify that only losses of waters of the United States
associated with a single and complete project would be considered when
determining whether the acreage limit or pre-construction notification
threshold is exceeded. However, it is correct that the Corps long-
standing practice (which we are not changing) has been to generally
calculate impacts for purposes of satisfying the \1/2\-acre threshold
separately for each separate and distant crossing, and we have
clarified this in the definitions section by adding separate
definitions that explain how single and complete projects are
determined for linear and non-linear projects. We do not agree that in
the text of this NWP the term ``single and complete project'' should be
replaced with ``single and complete linear project.'' Although the vast
majority of utility lines are linear projects where the crossings are
at separate and distant locations, and thus considered separate single
and complete projects, there may be circumstances where the separate
crossings of a waterbody are too close together to be considered
separate single and complete projects, and one NWP authorization would
be evaluated for those closely-spaced crossings. Therefore, we have
retained the more generic term ``single and complete project'' in the
text of this NWP. Other supporting components of a utility line, such
as substations, may not be considered linear projects in some
circumstances. District engineers may exercise discretionary authority
and require compensatory mitigation for utility line activities that
require pre-construction notification and result in the loss of aquatic
resources.
One commenter stated the Corps should clarify that the only
relevant activity for purposes of NWP 12 is a discharge of dredged or
fill material into waters of the United States. One commenter said that
no discharges should be authorized in waters below the ordinary high
water mark or in areas that provide fish habitat functions. This
commenter also said that utility lines should be buried at least six
feet below the authorized federal channel depth. One commenter stated
that mechanized land clearing of forested wetlands for installation of
utility lines should not be authorized by NWP 12.
The activities authorized by this NWP are not limited to discharges
of dredged or fill material. This NWP also authorizes structures or
work in navigable waters of the United States that require
authorization under Section 10 of the Rivers and Harbors Act of 1899.
We do not agree that discharges should be prohibited in open waters,
below the ordinary high water mark. Such activities often result in
minimal adverse effects on the aquatic environment and qualify for
general permit authorization. Division engineers can restrict or
prohibit use of this NWP in certain waters, through the approval of
regional conditions. The appropriate depth a utility line should be
buried below a federal channel should be determined on a case-by-case
basis. Mechanized landclearing of a forested wetland in a utility line
right-of-way may only result in a conversion of wetland type, and not
result in permanent loss of waters of the United States. District
engineers may require compensatory mitigation to offset permanent
losses of wetland functions when such mechanized landclearing occurs in
forested wetlands.
[[Page 10196]]
One commenter stated that authorizing the loss of \1/2\-acre of
waters of the United States for each crossing results in more than
minimal adverse environmental effects. Another commenter said that the
\1/2\-acre limit should apply to the entire utility line project,
because the cumulative effects of the utility line must be considered.
One commenter stated that this NWP should also limit stream impacts to
300 linear feet. Several commenters asked whether the conversion of a
forested wetland to a scrub-shrub wetland counts toward the \1/2\-acre
limit.
The \1/2\-acre limit applies to each crossing that is considered to
be a separate single and complete project, because they are sited at
distant locations from other crossings that constitute the linear
project. Each separate and distant crossing should be evaluated to
determine if it meets the terms and conditions of the NWP, and
cumulative effects of the overall utility line should be evaluated to
determine if the adverse cumulative effects on the aquatic environment
are more than minimal and therefore do not qualify for NWP
authorization. Separate utility line crossings are usually on different
water bodies, and may also be in widely separated watersheds. Such
factors should be considered when assessing cumulative impacts. The
``Definitions'' section provides further clarification on single and
complete projects. The conversion of a forested wetland to a scrub
shrub wetland does not constitute a permanent loss of waters of the
United States, and thus does not count towards the acreage limit, even
though it may result in the permanent loss of certain functions, which
may require compensatory mitigation.
One commenter said that some utility lines and associated renewable
energy projects may have unintended negative impacts on the Department
of Defense mission. For example, high voltage transmission lines could
potentially interfere with long-range radar surveillance, homeland
defense, testing, and training missions. This commenter requested that
pre-construction notifications for NWP 12 activities involving the
construction of overhead utility lines in waters of the United States
be coordinated with the Department of Defense, by sending a copy of the
pre-construction notification to the Department of Defense Siting
Clearinghouse. Department of Defense Siting Clearinghouse staff will
review the pre-construction notification and contact the project
proponent if they identify potential negative impacts to Department of
Defense operations, testing, and training missions.
We have added Note 4 to this NWP, which states that a copy of the
pre-construction notification will be provided to the Department of
Defense Siting Clearinghouse if the proposed activity involves an
overhead utility line constructed in waters of the United States. This
coordination process will not interfere or delay the district
engineer's decision on the pre-construction notification, which must be
made within the timeframes specified in the NWP general conditions. The
coordination process will consist of districts sending the Department
of Defense Siting Clearinghouse copies of pre-construction
notifications and NWP verifications, and Clearinghouse staff will work
with project proponents to address effects to military operations.
One commenter stated that the definition of a utility line in the
NWP is too expansive and should not include liquescent or slurry
substances. This commenter asked if utility lines could also be used to
transport waste products. One commenter stated that terms and
conditions of the NWP should require projects to use existing trenches
or cables whenever possible, and require that sidecast material be put
back in place within 24 hours. One commenter requested that temporary
fill be defined and that compensatory mitigation should be required for
temporary fills left in place for two years. One commenter said that
enforcing the time periods for temporary side casting is too difficult.
One commenter requested more detail regarding the circumstances under
which a district engineer would extend the period of temporary side
casting up to a total of 180 days. One commenter stated the side
casting in areas with known or probable sediment contamination should
be prohibited. One commenter stated the placement of excavated
materials into any waterway should be prohibited.
Water or sewer lines are generally recognized to be utility lines,
and are used to transport liquid or slurry substances. They may also be
used to transport waste products, such as sewage or industrial
byproducts. We do not agree that existing trenches or cable should be a
requirement of this NWP, since many new utility lines constructed in
waters of the United States result in minimal adverse effects on the
aquatic environment. However, project sponsors should consider the use
of existing trenches and cables where practicable as one way of
avoiding or minimizing adverse impacts to the aquatic environment,
which is required by general condition 23, mitigation. It is not
practicable to require side cast material to be put back into the
original trench or pit within 24 hours, and we have retained the
current language concerning temporary side casting. It is the district
engineer's discretion on whether to extend the period of temporary side
casting. That discretion would be based on the site-specific
environmental conditions, the activity, practicability considerations,
and other factors. District engineers can restrict or prohibit side
casting in areas where sediment contamination may be a concern.
Excavated materials are generally not placed in flowing waters, and
should be retained in areas outside of flowing waters with proper
sediment and erosion controls.
One commenter objected to authorizing the expansion of utility line
substations, stating that those activities should require individual
permits and a finding of compliance with the Clean Water Act Section
404(b)(1) Guidelines and public interest review.
The expansion of utility line substations does not generally
warrant a full public interest review and activity-specific Section
404(b)(1) Guidelines analysis since it is an expansion of an existing
facility. In response to a pre-construction notification, the district
engineer will review the proposed expansion of a substation and
exercise discretionary authority if it would result in more than
minimal individual and cumulative adverse effects on the aquatic
environment.
Two commenters stated the construction of temporary access roads
will require a submerged lands authorization and would require a
submerged land lease for long-term use.
The use of NWP 12 does not obviate the need for the project
proponent to obtain any other federal, state, or local permits that may
be required, including permits from states that hold title to submerged
lands.
One commenter said that this NWP should have fewer pre-construction
notification thresholds to expedite pipeline safety repairs and
infrastructure projects. One commenter supported retaining the \1/10\-
acre threshold pre-construction notification.
We believe all of the current pre-construction notification
thresholds are necessary because of the variety of utility line
activities authorized by NWP 12 (i.e., utility line construction,
maintenance, repair, and removal, the construction, maintenance, or
expansion of utility line substations, the construction or maintenance
of foundations for overhead transmission lines, and the construction of
access roads) and to allow district engineers
[[Page 10197]]
the opportunity to review those activities to determine whether they
will result in minimal adverse effects on the aquatic environment.
Pipeline maintenance may be authorized by NWP 3 or NWP 12, and use of
NWP 3 would not usually trigger a pre-construction notification
requirement. Many pipeline maintenance activities may also be
authorized by NWP 12, without pre-construction notification. The \1/
10\-acre pre-construction notification threshold remains in this NWP.
One commenter recommended that this NWP require the use of specific
equipment such as low ground pressure equipment and wide tires to
minimize adverse effects to wetlands. Another commenter said that this
NWP should be conditioned to require the use of best management
practices to reduce sediment loads into waters. One commenter stated
that this NWP does not require sufficient avoidance and minimization of
waters of the United States. One commenter suggested requiring the
installation of barriers next to utility line trenches to prevent
amphibians and reptiles from falling into the trench and to reduce
sediment transport into waters of the United States during
precipitation events. One commenter said that pipes installed over
rivers and streams should have shut-off valves to minimize the
potential for discharges to occur if the pipe is breached.
The use of equipment that minimizes adverse effects to waters of
the United States is addressed by general condition 11, equipment,
which requires permittees to take measures to minimize soil
disturbance, such as placing heavy equipment on mats when working in
wetlands, mudflats, or other waters. Division or district engineers may
condition this NWP, either through the regional conditioning process or
through activity-specific conditions added to an NWP 12 authorization,
to require the use of best management practices. General condition 23,
mitigation, requires permittees to design and construct their
activities to avoid and minimize adverse effects to waters of the
United States. A requirement to install barriers next to utility line
trenches, or the use of shut-off valves in pipes constructed over
waters, is more appropriately addressed through the regional
conditioning process or through activity-specific conditions added to
an NWP 12 authorization during the review of a pre-construction
notification or NWP verification request.
One commenter stated that this NWP could streamline the
authorization of offshore wind energy generation facilities, but two of
the terms and conditions may be problematic. The first is the
prohibition against side casting when sediments would be dispersed by
currents or other forces. The second is the \1/2\-acre limit, which may
prohibit use of this NWP to authorize the installation of cables that
transfer the energy generated by wind turbines.
The transmission cable that runs from an offshore wind energy
generation facility to a land-based facility or distribution system may
be constructed so that the trench for the cable is backfilled
immediately after the cable is laid into the trench. That immediate
backfilling would minimize dispersion by currents or other forces in
those waters. The placing of a power transmission cable on the sea bed
is considered a structure under our regulations for implementing
Section 10 of the Rivers and Harbors Act of 1899 (see 33 CFR 322.2(b)),
and not a loss of waters of the United States subject to the \1/2\-acre
limit in NWP 12.
One commenter recommended requiring coordination with Tribes to
avoid impacts to Tribal treaty natural resources and cultural
resources. Another commenter said that coordination with State Historic
Preservation Officers should be required to protect historic
properties.
Division engineers can regionally condition this NWP to require
coordination with Tribes, to ensure that this NWP does not adversely
affect Tribal treaty natural resources and cultural resources. General
condition 20, historic properties, addresses compliance with the
National Historic Preservation Act, which requires consultation for
activities that have the potential to cause effects to historic
properties, including tribal resources that meet the definition of
``historic property.'' General condition 17, tribal rights, requires
that no NWP activity or its operation may impair reserved treaty
rights, such as reserved water rights and treaty fishing and hunting
rights.
One commenter requested clarification that individual permits are
not automatically required for NWP 12 activities when a Corps district
participates as a cooperating agency for an environmental impact
statement.
Even though an environmental impact statement may be prepared for a
particular utility line, the National Environmental Policy Act process
does not prohibit the Corps from using NWP 12 to authorize the
construction, maintenance, repair, and removal of utility lines and
associated facilities in waters of the United States, as long as the
activity complies with all applicable terms and conditions and results
in minimal individual and cumulative adverse effects on the aquatic
environment. NEPA requires consideration of all environmental impacts,
not only those to aquatic resources, so there may well be situations
where aquatic impacts are minimal even though environmental impacts
more generally are not. These other environmental impacts would be
addressed by the lead agency preparing the environmental impact
statement. The district engineer will exercise discretionary authority
to require an individual permit for any utility line activity that he
or she determines does not meet the terms and conditions of NWP 12.
One commenter suggested modifying Note 1 to limit submission of NWP
12 pre-construction notifications and verifications to the National
Oceanic and Atmospheric Administration's National Ocean Service (NOS),
since NOS only produces charts for waters in the coastal United States,
Great Lakes, and United States territories.
We have modified Note 1 to require district engineers to send
copies of NWP 12 pre-construction notifications and verifications to
NOS in those regions of the country.
This NWP is reissued with the modifications discussed above.
NWP 13. Bank Stabilization. We proposed modifying this NWP by
removing the waiver provision in paragraph (c) that allowed district
engineers to authorize bank stabilization fills that exceeded one cubic
yard per running foot below the ordinary high water mark or high tide
line to encourage the use of bioengineered techniques for bank
stabilization. To conform with the proposed change to in paragraph (c),
we proposed to remove the third pre-construction notification threshold
for bank stabilization fills that exceeded one cubic yard per running
foot, since these fills would no longer be allowed. We also proposed
changing this NWP to authorize temporary structures and fills necessary
for the construction of bank stabilization activities.
Many commenters recommended that this NWP not be reissued, and
stated that all bank stabilization should be evaluated under individual
permit procedures. One commenter asserted that bank stabilization
activities should be authorized with NWP 3 in man-made ditches and
canals and NWP 13 in natural waterways. Two commenters said this NWP
should not authorize new bank stabilization activities. Some commenters
recommended modifying this NWP so that it would not authorize new
vertical bulkheads and seawalls.
[[Page 10198]]
One commenter stated that this NWP does not result in minimal
individual and cumulative adverse effects on the aquatic environment
because these activities accelerate coastal erosion and retreat.
Additional commenters said that these activities result in more than
minimal individual and cumulative effects. Some of these commenters
said that this NWP has more than minimal adverse effects on low-order
ephemeral and intermittent streams. One commenter said that this NWP
should not be applicable to both riverine and lacustrine systems and
recommended that separate NWPs be developed that would address the
different erosional processes in those systems. Several commenters
stated that this NWP should not be reissued because of adverse effects
to coastal environments, as well as sea turtles and other endangered
species and their habitats. Another commenter recommended that bank
stabilization only be permitted by this NWP if it is part of a habitat
improvement project or has other net improvements in aquatic function.
The terms and conditions for this NWP are appropriate for limiting
bank stabilization activities so that they have minimal individual and
cumulative effects on the aquatic environment, while allowing
landowners and other entities to protect their property and safety. NWP
3 only authorizes minor amounts of rip rap associated with maintenance
activities. It is more appropriate to authorize bank stabilization
activities in man-made waterways through NWP 13. In many coastal waters
and rivers it is necessary to utilize hard bank protection structures,
because wave energy and currents are too strong for bioengineering or
other techniques to successfully prevent or reduce erosion. We do not
agree that there should be separate NWPs developed to authorize bank
stabilization activities in riverine and lacustrine waters. Bank
stabilization that may affect endangered or threatened species require
pre-construction notification and compliance with general condition 18,
endangered species. We also do not agree that this NWP should be
limited to habitat improvement projects, because it is often necessary
to install bank stabilization structures and fills to protect property
and safety.
Two commenters said that NWP 13 should not be reissued because it
authorizes activities that may prevent retreat that would be necessary
to adapt to sea level rise caused by climate change. These commenters
also said that sea level rise needs to be considered in the decision on
whether to reissue this NWP. These commenters also stated that the
structures and fills authorized by NWP 13 exacerbate erosion in areas
where sea level rise will occur.
Coastal and riparian areas are dynamic landscapes. They are
constantly changing as a result of erosional and depositional
processes. Landowners seek Department of the Army authorization for
bank stabilization activities to protect their property and provide
safety. The purpose of NWP 13 activities is to protect land on which
residences, commercial buildings, infrastructure, and other features
are located. The Corps regulations recognize that a riparian landowner
has a right to protect his or her property from erosion (see 33 CFR
320.4(g)(3)). When a district engineer evaluates a permit application
for bank stabilization activities, including pre-construction
notifications for NWP 13 activities, he or she considers the current
environmental conditions at the site of the proposed activity, as well
as the reasonably foreseeable direct, indirect, and cumulative effects
that might be caused by the proposed activity. At the present time,
there is a considerable amount of uncertainty surrounding climate
change, and any associated sea level rise that may occur as a result of
climate change. To the extent there is reliable information about
projected sea level rise during the reasonably foreseeable future in
the vicinity of a proposed activity, the district engineer will take
that information into account when determining whether a proposed NWP
13 activity will have minimal individual and cumulative adverse effects
on the aquatic environment. We do not agree that the structures and
fills authorized by NWP 13 will accelerate erosion in areas affected by
changing sea level rise caused by climate change. The bank
stabilization structures and fills authorized by this NWP must be
properly designed, so that they have minimal individual and cumulative
adverse effects on coastal and riparian erosion and deposition
processes. As sea level rise occurs, bank stabilization activities may
no longer be effective, and it may be necessary for landowners to
relocate.
Two commenters suggested limiting all projects to a maximum length
of 500 linear feet, except for allowing bioengineering projects to
exceed that length on a case-specific basis if the district engineer
waives that limit. One commenter recommended not allowing vertical
bulkheads longer than 500 feet. One commenter recommended limiting
replacement of vertical bulkheads and seawalls to a maximum length of
200 feet. Another commenter recommended a 300 linear foot maximum
project length for shoreline protection on coastal areas or lakes. One
commenter suggested a 300 linear foot maximum length for bioengineering
projects and a 150 foot maximum length for all other bank stabilization
projects. Two commenters requested clarification regarding project
length in paragraph (b) as it relates to activities that stabilize both
banks (left and right) of a stream. Many commenters supported the
district engineer waiver for the 500 linear foot limit for any
projects.
The limits in this NWP are sufficient to ensure that the NWP
authorizes only those activities that have minimal adverse effects on
the aquatic environment, although division engineers may regionally
condition the NWP to reduce those limits to account for local
environmental conditions and the ecological functions and services
provided by waters of the United States in those areas. For streams,
the linear foot limit in paragraph (b) applies to a single and complete
project for the bank stabilization activity measured along the length
of the stream segment, which may involve discharging dredged or fill
material along either one or both stream banks. We have retained the
ability for district engineers to waive the 500 linear foot limit.
One commenter requested a definition for bank stabilization. Many
commenters asked for a definition of bioengineering. One commenter said
that bioengineering techniques should include living plant material and
soil as the primary structural components to reinforce soil and to
stabilize slopes. One commenter recommended requiring native vegetation
in bioengineering projects where vegetation is the primary or secondary
component of a project.
We do not believe that a definition of bioengineering is necessary
because there is a wide variety of bioengineering techniques and
project proponents and district engineers generally understand what it
means in a local context. It is not possible at the national level to
envision every possible variation of technique and materials that would
reasonably fit within the meaning of this term, but generally
bioengineering involves the use of a combination of vegetation and hard
materials instead of only hard materials such as rip-rap for bank
stabilization. Also, as explained below, the final NWP does not make a
distinction between bioengineering and other bank stabilization
techniques. We agree that bioengineering, for the purposes of bank
stabilization, includes providing protection from erosion and
[[Page 10199]]
providing habitat for aquatic species. We also agree that bioengineered
techniques can slow erosion rates and can have beneficial effects on
habitat for macroinvertebrates and fish which is why we proposed to
modify this NWP to encourage greater use of this technique.
Several commenters recommended the NWP encourage the use of natural
materials over riprap. One commenter said that only native plant
species should be used for bioengineered bank stabilization. Another
commenter recommended using natural stream design methods for erosion
prevention. Several commenters objected to the placement of plant
material in waters of the United States, and also objected to the
planting of willows and similar species in and along waterways because
these types of woody plants clog waterways and cause maintenance
problems at bridge and culvert crossings.
Division engineers can regionally condition this NWP to encourage
bioengineering or the use of natural materials for bank stabilization
in waters subject to lower energy waves and currents. The use of plant
materials as a component of a bank stabilization activity can have
beneficial environmental effects, such as providing shading and habitat
for near-shore organisms, or for riparian ecosystems. Proper
maintenance should be done to remove plants that colonize waterways,
especially at culverts or bridges. We have added a provision to this
NWP stating that if bioengineering or vegetative bank stabilization is
used, invasive plant species should not be used, because Executive
Order 13112, Invasive Species, states that agencies should not
``authorize, fund, or carry out actions that it believes are likely to
cause or promote the introduction or spread of invasive species in the
United States or elsewhere.'' The Executive Order states there are
economic, ecological, and human health impacts that are caused by
invasive species, and we believe that invasive species should not be
used for bioengineering bank stabilization activities authorized by
this NWP because of the adverse environmental effects those species can
cause.
Many commenters supported the proposed modification of paragraph
(c) to only allow bioengineering projects to exceed one cubic yard per
running foot, and to not allow waivers from the district engineer for
other types of projects. Many other commenters objected to limiting
that flexibility to bioengineering techniques, stating that bank
protection structures are necessary in high energy coastal and riverine
environments, and said that the waiver in the 2007 NWP 13 should be
reinstated. Some commenters suggested removing paragraph (c) entirely.
Several of these commenters thought the proposal would encourage
bioengineering methods for achieving the necessary bank stabilization.
Many commenters stated that the waiver to the cubic yard limit should
be removed from paragraph (c) to ensure that the NWP authorizes only
those activities with minimal adverse effects on the aquatic
environment. Many commenters asserted that bioengineering methods for
bank stabilization are unproven and not as effective at preventing
erosion as hard structures. A few commenters suggested that the
preference for bioengineering would be a hardship on local governments.
Another commenter suggested that bioengineering techniques are rarely
successful in arid areas and in ephemeral waterways. Another commenter
added that the hydraulic forces in large rivers and tidal areas require
the use of large stone, the size of which exceeds the one cubic yard
per running foot average size, and are not conducive to bioengineering.
Several commenters said that bioengineering is not always appropriate
for protecting infrastructure such as roads and bridges, and requested
that the one cubic yard per foot waiver be left in place to protect
these structures. One commenter suggested modifying the NWP to require
alternatives analyses for each proposed project using an established
hierarchy, beginning with bioengineering as the most preferable bank
stabilization method and ending with the hard bank stabilization
structures. One commenter observed that bank stabilization using
bioengineering or any other method will still result in adverse
effects, and suggested all bank stabilization activities should be
located landward of the ordinary high water mark.
In response to the many commenters that objected to removing the
provision allowing district engineers to waive, after reviewing a pre-
construction notification, the one cubic yard per running foot limit,
we have reinstated that provision in this NWP. We have also reinstated
the third pre-construction notification threshold that was in the 2007
version of NWP, which requires pre-construction notification for
discharges exceeding one cubic yard per running foot along the bank
below the plan of the ordinary high water mark or the high tide line.
We acknowledge that bioengineering may not be appropriate in all
waters, because it may not result in effective bank stabilization. We
have thus determined that it is not appropriate to establish a
hierarchy of preferred bank stabilization options because such
decisions are best left to district engineers that review project-
specific pre-construction notifications, and can take into account the
characteristics of the waterbody and the surrounding area, and
determine which bank stabilization method would be most effective and
environmentally preferable. We agree, however, that bioengineering
techniques may be environmentally preferable in many situations and
that project proponents should consider such techniques where
practicable in order to comply with the general requirement to avoid
and minimize adverse effects to the aquatic environment. It is not
practicable to require all bank stabilization activities to be located
landward of the ordinary high water mark.
One commenter asked if the volume of fill buried deeply below
bioengineering or turf reinforcement mats could be exempted from the
volume of fill that counts towards the one cubic yard per running foot
limit in paragraph (b). Another commenter said that buried stone does
not meet the regulatory definition of fill material, and said the
volume of stone buried below the ordinary high water mark should not
count towards the one cubic yard per running foot limit. One commenter
suggested replacing the words ``below the plane of'' with ``within
the'' when describing the ordinary high water mark in paragraph (c).
The definition of ``fill'' found in 33 CFR part 323.2 clearly
states that rock is fill material, and burying rock in a waterway
constitutes a discharge of fill material. The volume of the buried
stone, along with all other fill material, must be determined and that
volume placed below the plane of the ordinary high water mark or high
tide line is considered when reviewing the proposed project. We have
retained the language in NWP because the phrase ``below the plane of ''
more accurately describes the Corps jurisdiction in waters of the
United States. To the extent that the location and type of fill placed
below the plane of the ordinary high water mark affects the potential
for adverse effects to the aquatic environment, the district engineer
would consider such factors in deciding whether to grant a waiver
request.
Several commenters said that paragraph (d) should prohibit fills in
special aquatic sites, including wetlands. One commenter opposes
removing the waiver provision in
[[Page 10200]]
paragraph (d) for work in special aquatic sites.
We believe that the pre-construction notification process affords
the district engineer an appropriate opportunity to review proposed
activities in special aquatic sites. Many streams and shorelines
include, or are bordered by, special aquatic sites, and precluding use
of this permit in these areas severely limits its usefulness for
projects that have no more than minimal adverse effects on the aquatic
environment. Additionally, it may be beneficial in some watersheds to
stabilize eroding banks, even though small amounts of special aquatic
sites may be impacted by a bank stabilization activity. Paragraph (d)
requires a written determination concluding that the activity will
result in minimal adverse effects. If a written waiver is not issued by
the district engineer, then this NWP does not authorize such activities
and the project proponent will have to obtain another form of DA
authorization.
Several commenters expressed support for inclusion of temporary
fills required to accomplish work authorized under this NWP. One
commenter said that temporary fills should remain in place if their
removal would do more damage than allowing them to remain in place. One
commenter requested a list of mandatory best management practices
developed for temporary fills authorized by this NWP.
If the district engineer determines that temporary fills should
remain in place those fills may be authorized by another NWP, a
regional general permit, or individual permit. We do not agree that
specifically requiring best management practices is appropriate,
although division engineers may regionally condition this NWP to add
appropriate best management practices. District engineers may also add
conditions to the NWP to require specific best management practices for
a particular activity.
Several commenters stated that pre-construction notification should
be required for all activities authorized by this NWP. One commenter
requested that no pre-construction notification be required for any
bank stabilization exceeding one cubic yard per running foot in
ephemeral and intermittent waters. One commenter suggested removing all
pre-construction notification requirements from work done under this
NWP in man-made waterways. One agency recommended lowering a pre-
construction notification threshold to 100 feet for hard bank
stabilization projects such as riprap, and 300 feet for bioengineering
projects. One commenter claimed it would be burdensome and costly to
submit a pre-construction notification for every bank stabilization
project.
We do not agree that it is necessary to require pre-construction
notification for all activities authorized by this NWP. A large number
of small bank stabilization activities are conducted each year that
result in minimal adverse effects on the aquatic environment. We
believe that the existing pre-construction notification thresholds are
sufficient for satisfying the minimal adverse effects requirement for
general permits, and division engineers can regionally condition this
NWP to impose lower pre-construction notification thresholds, including
requiring pre-construction notification for all activities.
Two commenters said that bank stabilization activities must avoid
impacting tribal rights, tribal natural resources, and tribal cultural
resources. Many commenters said that while bank stabilization projects
may reduce erosion at a site, they may transfer or accelerate erosion
in other areas of a waterbody.
General condition 17, tribal rights, prohibits the impairment of
all reserved tribal rights. We acknowledge that bank stabilization
activities may cause indirect effects in other areas of the waterbody
and those indirect effects should be evaluated during the review of a
pre-construction notification, if it is required. Activities that do
not require a pre-construction notification have minimal adverse
effects on the aquatic environment.
Some commenters asked that compensatory mitigation be required for
all activities authorized by this NWP. A few commenters remarked that
compensatory mitigation should be required for adverse effects on high
quality riparian areas. Another commenter said that mitigation should
be required when sheet piling is used to stabilize banks.
We do not believe compensatory mitigation should be required for
all bank stabilization activities. District engineers will determine
when compensatory mitigation is necessary to ensure that an activity
results in minimal individual and cumulative adverse effects on the
aquatic environment.
This NWP is reissued with the modifications discussed above.
NWP 14. Linear Transportation Projects. There were no changes
proposed for this NWP. One commenter suggested that this NWP should
authorize only the maintenance of existing linear transportation
projects because the construction of new linear transportation projects
results in more than minimal adverse environmental effects. One
commenter said that this NWP should not authorize parking lots. One
commenter stated that activities in tidal waters should not be
authorized by this NWP because any proposed linear transportation
project impacting tidal wetlands require an individual permit to more
thoroughly assess impacts on those aquatic habitats.
This NWP should not be limited to authorizing the maintenance of
existing linear transportation projects. The terms and conditions of
this NWP, including its acreage limits and pre-construction
notification thresholds, provide an effective means for authorizing
linear transportation projects with minimal individual and cumulative
adverse effects on the aquatic environment. Parking lots may be an
integral part of a single and complete linear transportation project
and may be authorized under this NWP. Small linear transportation
projects constructed or maintained in tidal waters may be authorized by
this NWP, if they comply with appropriate thresholds and result in
minimal adverse effects on the aquatic environment. Division engineers
can regionally condition this NWP to restrict or prohibit the use of
this NWP to authorize structures or fills in tidal waters where
necessary.
Most commenters suggested adding a linear foot limit to this NWP to
ensure that it only authorizes activities with minimal adverse effects
on the aquatic environment, stating that the current NWP authorizes
large amounts of small streams to be permanently lost or significantly
altered. One commenter recommended a 100 linear foot limit for the loss
of perennial, intermittent, and ephemeral streams. One commenter said
that the \1/2\-acre limit is too large when compared to other NWPs that
limit impacts to \1/10\-acre. One commenter suggested limiting private
roads to 200 feet in length, with a maximum width of 16 feet. One
commenter recommended that public road projects with multiple crossings
should have a maximum cumulative limit of two acres for all crossings
associated with that project.
We believe the \1/2\-acre and \1/3\-acre limits are appropriate for
ensuring that the NWP authorizes only those linear transportation
projects that result in minimal individual and cumulative adverse
effects on the aquatic environment. Division engineers can regionally
condition this NWP to decrease these acreage limits or impose linear
foot limits to provide additional protection for wetlands and other
waters
[[Page 10201]]
in a particular district or region. We do not agree that public and
private crossings should have different acreage limits. The
environmental effects are not dependent on the status of the entity who
proposes to construct the project. A 200 linear foot limit was removed
from NWP 14 in 2007 to simplify this NWP. The Corps is not aware of
situations where this change resulted in projects being authorized that
had more than minimal adverse effects.
One commenter asserted that using this NWP prevents the public from
commenting on large transportation projects. Another commenter said
that this NWP should not authorize expansion of existing projects,
because it discourages avoidance and minimization and is contrary to
the 404(b)(1) Guidelines. One commenter stated that use of this NWP for
the expansion, modification, or improvement of previously authorized
projects could result in cumulative impacts that exceed the acreage
limits and said the impacts of previously authorized projects should
count towards the acreage limit.
Linear transportation projects that involve small losses of waters
of the United States and result in minimal adverse effects on the
aquatic environment would not generally generate substantive public
comments in response to a public notice and should not require public
notices. It is appropriate to authorize expansions, modifications, or
improvements to existing projects, as long as those activities comply
with the terms and conditions of the NWP, including the applicable
acreage limit. An expansion, modification, or improvement of an
existing project has few practicable alternatives available because it
is a change to a previously constructed project. Alternatives that
would involve relocating an existing project are likely to result in
more adverse effects to the aquatic environment. An expansion,
modification, or improvement of a previously authorized single and
complete linear transportation project should include the previously
authorized losses of waters of the United States when determining
whether the acreage limit would be exceeded by the expanded, modified,
or improved project, if the expansion, modification, or improvement is
not a separate single and complete project. Factors that may affect
this determination include the length of time between the original
project and the expansion, modification or improvement; the degree of
independent utility of the original project and the expansion,
modification or improvement; and the degree to which the expansion,
modification or improvement may have been already envisioned, or
planning might already have begun, at the time the original project was
authorized. Under no circumstance will district engineers allow
``piecemealing'' of projects (for this or any other NWP) in order to
meet thresholds.
One commenter requested that the term ``minimum necessary'' used in
the first paragraph of this NWP be defined. One commenter asked if
temporary fill may be put in place for up to two years without
requiring any mitigation, and another commenter requested a definition
for ``temporary.'' One commenter suggested that culverts or other
appropriate measures should be required to maintain existing drainage
patterns, all stream crossings should span the bankfull width of a
stream, and in cases where bottomless culverts or bridge structures are
not used, the bottom of the structure should match stream slope.
Another commenter suggested that the NWP should require the use of best
management practices to avoid sediment loading of waters and that best
management practices should be used in upland areas and within waters
to protect downstream water quality.
The decision as to whether a stream channel modification is the
``minimum necessary'' and whether a fill is ``temporary'' is to be
determined on a case-by-case basis, after considering the specifics of
the proposed activity and the types of aquatic resources proposed to be
impacted by the linear transportation project. General condition 2,
aquatic life movements, and general condition 9, management of water
flows, require that linear transportation projects be designed to
sustain corridors for aquatic life movements and maintain, to the
maximum extent practicable, the pre-construction course, condition,
capacity, and location of streams and other open waters. General
condition 12, soil erosion and sediment controls, requires permittees
to take appropriate measures to reduce or prevent movements of sediment
into waters during construction. Water quality management measures may
also be required by district engineers on a case-by-case basis after
evaluating a pre-construction notification.
One commenter said that pre-construction notification should be
required for stream impacts that exceed 100 linear feet. Another
commenter stated that any stream channel modifications should require
pre-construction notification. One commenter suggested requiring low
ground pressure equipment, wide tires, rubberized racks, lightweight
equipment, and the use of varied paths to avoid repeatedly crossing
wetlands at the same location, to protect wetlands. One commenter
suggested sending pre-construction notifications to tribes to avoid
impacts to tribal treaty natural and cultural resources. One commenter
recommended that the Corps consult with the Federal Highway
Administration to streamline projects and align with their efforts.
The present pre-construction notification thresholds provide
sufficient protection for streams, and division engineers can
regionally condition this NWP to require pre-construction notification
for proposed losses of stream beds that would exceed a specified
amount. Streams with riffle and pool complexes are considered to be
special aquatic sites under the 404(b)(1) Guidelines and would require
pre-construction notification. General condition 11, equipment,
establishes requirements for equipment working in wetlands or mudflats
and we believe this general condition provides sufficient protection
for those types of construction impacts. Division engineers can
regionally condition this NWP to require pre-construction notification
for activities that may affect tribal treaty resources, and consult
with those tribes before making a decision on whether the activity is
authorized by this NWP. This NWP, as well as other NWPs such as NWP 23,
provides a means for streamlining the authorization of linear
transportation projects and working cooperatively with the Federal
Highway Administration and state departments of transportation.
The NWP is reissued without change.
NWP 15. U.S. Coast Guard Approved Bridges. We proposed to modify
this NWP by removing reference to the U.S. Coast Guard authorizing the
discharge of dredged or fill material into waters of the United States
as part of their bridge permit. We also proposed to reference the U.S.
Coast Guard's bridge permitting authority under Section 9 of the Rivers
and Harbors Act of 1899 and other applicable laws. We proposed to add
section 10 to the regulatory authorities so that discharges authorized
under Section 404 of the Clean Water Act would be also authorized under
the Rivers and Harbors Act.
One commenter agreed with adding section 10 authority to this NWP,
which they believed would help clarify a sometimes confusing permitting
scenario. Another commenter objected to adding section 10 authority,
stating that the section 9 permits issued by the
[[Page 10202]]
U.S. Coast Guard for bridge and causeway construction satisfy all
requirements of the Rivers and Harbors Act of 1899 and adding section
10 authorization is not necessary. One commenter requested
clarification regarding the applicability of section 10 to the U.S.
Coast Guard approved bridges over both navigable-in-fact and
historically navigable waters of the United States. One commenter
requested definitions of the terms ``causeway'' and ``approach fills.''
We agree that the U.S. Coast Guard's section 9 permit satisfies the
permit requirements of the Rivers and Harbors Act and have removed the
reference to section 10 from the NWP. Discharges of dredged or fill
material associated with the construction of bridges across navigable
waters of the United States require separate authorization under
Section 404 of the Clean Water Act, since navigable waters of the
United States are also considered waters of the United States under the
Clean Water Act, and discharges of dredged or fill material into waters
of the United States require section 404 permits, unless they are
eligible for an exemption from permit requirements. Historically
navigable waters of the United States may still be subject to
jurisdiction under Rivers and Harbors Act of 1899, depending on the
case-specific circumstances. We do not believe it is necessary to
define what causeways and approach fills are, since they would be
identified in the specific plans approved by the U.S. Coast Guard as
part of their section 9 permit.
This NWP is reissued with the modification discussed above.
NWP 16. Return Water From Upland Contained Disposal Areas. We did
not propose any changes to this NWP. This NWP provides section 404
authorization for the discharge of return water from a dredged material
placement facility located in uplands, because that discharge of return
water into waters of the United States has been administratively
defined as a ``discharge of dredged material'' (see 33 CFR
323.2(d)(1)(ii)). One commenter said the NWP should address both the
technical requirements and water quality of the return water due to the
potential for the return water to degrade water quality for natural
heritage resources. One commenter said that pre-construction
notification should be required for activities authorized by this NWP
to ensure that suspended contaminated sediments do not reenter
waterways and impact state submerged lands.
The water quality certification issued for a specific dredging
project should address any water quality concerns for natural heritage
resources. We do not agree that pre-construction notification should be
required for this NWP because any required sediment testing would
identify contaminants. The sediment testing and potential impacts to
water quality are more appropriately considered through the water
quality certification process. We have modified this NWP to clarify
that disposal of dredged material in an area that has no waters of the
United States does not require a section 404 permit, because disposal
of dredged material may occur in non-jurisdictional wetlands and
waters, not just uplands.
The NWP is reissued with the modification discussed above.
NWP 17. Hydropower Projects. No changes were proposed for this NWP.
Several commenters said that this category of activities is
inappropriate for authorization under an NWP because of the scope and
scale of these projects. One commenter stated that these activities
result in more than minimal adverse effects on the aquatic environment,
especially downstream effects such as the loss of riffle and pool
complexes and degradation of water quality through increased sediment
loads.
This NWP authorizes small hydropower projects that have minimal
adverse effects on the aquatic environment. All activities authorized
by this NWP require pre-construction notification, so that district
engineers can review each proposed hydropower project and make a case-
specific determination whether the minimal effects requirement has been
met. Discretionary authority will be exercised, and another form of
Department of the Army authorization would be required, if the district
engineer determines that a particular hydropower project would result
in more than minimal individual and cumulative adverse effects to the
aquatic environment or any other public interest review factor.
District engineers may also require compensatory mitigation to offset
losses of aquatic resource functions.
This NWP is issued without change.
NWP 18. Minor Discharges. We did not propose modifications to this
NWP. Several commenters expressed support for the reissuance of this
NWP. A few commenters said that this NWP does not comply with the
``similar in nature'' requirement for general permits. Other commenters
asserted that the cumulative impacts resulting from the use of this NWP
would be more than minimal. Another commenter said that this NWP should
not authorize discharges into waters that provide forage fish habitat
or that contain aquatic vegetation. One commenter stated that the NWP
should not be used to authorize discharges in rare aquatic environments
such as vernal pools.
We believe that the small discharges of dredged or fill material
authorized by this NWP comply with the similar in nature requirement
for general permits. District engineers will review pre-construction
notifications and may assert discretionary authority to add activity-
specific conditions to the NWP authorization to ensure that the
activity results in minimal adverse environmental effects. Division
engineers may regionally condition this NWP to restrict or prohibit its
use in specific waters or categories of waters, including fish foraging
areas, vegetated shallows, or vernal pools.
One commenter stated that the limit for this NWP should only be
expressed in terms of area filled (i.e., up to \1/10\-acre) and not
include the volumetric limit (i.e., 25 cubic yards). Another commenter
said that all discharged material should consist of clean,
uncontaminated sand, crushed rock, or stone. One commenter recommended
adding language requiring that the discharge will not result in
significant changes to stream geomorphology or hydrology, and that the
discharge will not impede navigation.
The 25 cubic yard limit for regulated excavation activities and the
\1/10\-acre limit for losses of waters of the United States caused by
discharges of dredged or fill material are both necessary to ensure
that this NWP authorizes only those activities that have minimal
individual and cumulative adverse effects on the aquatic environment.
General condition 6, suitable material, prohibits the use of unsuitable
fill material. The fill material must not have toxic pollutants that
are present in toxic amounts. Compliance with general condition 9,
management of water flows, will ensure that the activity does not cause
more than minimal adverse effects to stream geomorphology or hydrology.
General condition 1, navigation, states that NWP activities cannot
cause a more than minimal adverse effect to navigation.
This NWP is reissued without change.
NWP 19. Minor Dredging. There were no changes proposed for this
NWP. One commenter recommended that the NWP include a cumulative volume
limit for multiple single and complete dredging projects. One commenter
recommended modifying the NWP to require that dredge material be
limited to a maximum of 25 cubic yards from a 1,000 square foot area,
not disturb sediments in an area known or
[[Page 10203]]
suspected to contain toxic pollutants, and the disposal of dredged
material at an upland location. Another commenter said that pre-
construction notification should be required for all activities to
ensure that sediments are not contaminated and do not cause impacts to
state owned land. One commenter stated that the activities authorized
by this NWP are not similar in nature and do not result in cumulative
minimal adverse environmental effects.
This NWP may be used only once for each single and complete project
(see general condition 15, single and complete project). Therefore,
each single and complete dredging project is subject to the 25 cubic
yard limit. District engineers will also review pre-construction
notifications and other requests for NWP verifications, and will
exercise discretionary authority if they determine that the use of this
NWP in a particular region is resulting in more than minimal cumulative
adverse effects on the aquatic environment. We believe that the 25
cubic yard limit is sufficient to satisfy the minimal adverse
environmental effects requirement for general permits, and that an
areal limit, such as the 1,000 square feet recommended above, is not
necessary. Division engineers may impose regional conditions on this
NWP to restrict or prohibit its use in waters known to have
contaminated sediments or in waters where there is sufficient reason to
believe that there are contaminated sediments, that would cause more
than minimal adverse effects to water quality if they were disturbed by
these minor dredging activities. A separate Department of the Army
authorization must be obtained if the project proponent plans to
deposit the dredged material into waters of the United States,
including jurisdictional wetlands. Absent such authorization, the
dredged material must be deposited in an upland area or an approved
dredged material disposal facility.
This NWP is reauthorized without change.
NWP 20. Response Operations for Oil and Hazardous Substances. We
proposed to change the name of this NWP, and modify its terms and
conditions to authorize a wider set of activities, such as containment
and mitigation actions, to more effectively authorize efforts to manage
releases of oil or hazardous substances. We also proposed to authorize
training exercises for the cleanup of oil and hazardous substances,
including those that involve temporary structures or fills.
Five commenters expressed support for the proposed changes to this
NWP. One commenter objected to the proposed modifications, stating that
the NWP could authorize large dredge and fill operations that would
result in net adverse effects on the aquatic environment that would be
more than minimal. One commenter stated that the NWP should be limited
to interim response activities and that a separate permit should be
required for final restoration response. Another commenter said that
there should be a requirement to remove temporary structures and fill.
This commenter also recommended that the NWP include criteria for
temporary structures or fills, such as a requirement to restore
wetlands to the maximum extent practicable, to ensure there are no
lasting impacts from these activities. A commenter said that this NWP
should require coordination with the appropriate state wetland or water
resources program.
This NWP authorizes activities in waters of the United States to
remediate spills of oil and hazardous substances, which normally
results in environmental benefits. We do not agree that the NWP should
be limited to interim responses. It should also authorize the final
response activity that results in the removal of the oil or hazardous
substances, as well as the authorization to remove any temporary
structures or fills, to the extent that a Department of the Army permit
is required to remove such temporary structures or fills. General
condition 13, removal of temporary fills, requires temporary fills to
be removed in their entirety, and the affected areas revegetated, if
necessary. We do not agree that this NWP should require coordination
with state wetland or water resource agencies, since those agencies are
likely to have an independent authority to regulate such response
activities, as well as their own procedures for reviewing and approving
those activities. As a practical matter, such remediation efforts
almost always involve coordination among multiple agencies.
This NWP is reissued as proposed.
NWP 21. Surface Coal Mining Activities. We proposed three options
concerning this NWP. The first option was not to reissue NWP 21 and to
let it expire on March 18, 2012. The other two options consisted of
reissuing the NWP with modifications. Option 2 was to reissue NWP 21
with a \1/2\-acre limit, including a 300 linear foot limit for the loss
of stream bed. Under Option 2, NWP 21 would not authorize discharges of
dredged or fill material into waters of the United States to construct
valley fills. Option 3 was similar to Option 2, but under Option 3 NWP
21 could authorize discharges of dredged or fill material into waters
of the United States to construct valley fills. In the February 16,
2011, proposal, Option 2 was identified as the Corps preferred option.
Both Options 2 and 3 require a pre-construction notification for
activities authorized by NWP 21, and permittees would have to receive
written authorization from the district engineer prior to commencing
the activity.
A large majority of commenters supported Option 1 and opposed the
reissuance of NWP 21, including any modification of that NWP. Over
26,000 of those comments were form letters. Several commenters
recommended adopting Option 2. Two commenters supported Option 3. Many
commenters stated that NWP 21 should be reissued without change from
the NWP issued in 2007.
While some commenters expressed support for Option 1, they also
said that if NWP 21 is to be reissued, Option 2 should be selected and
modified to remove the provision allowing district engineers to waive
the 300 linear foot limit for the loss of intermittent or ephemeral
stream bed. Another commenter stated that if NWP 21 is reissued, it
should not authorize any losses of intermittent or perennial streams.
We believe that district engineers should have the ability to waive
the 300 linear foot limit for the loss of ephemeral or intermittent
stream bed if they make a case-specific determination that the proposed
activity will result in minimal individual and cumulative adverse
effects on the aquatic environment. For proposed activities under
paragraph (b) of NWP 21 that would result in the loss of greater than
300 linear feet of intermittent or ephemeral stream bed, district
engineers will coordinate the pre-construction notifications with the
resource agencies, to solicit their comments (see paragraph (d) of
general condition 31). Those comments will be used by the district
engineer in making his or her minimal adverse effects determination.
The loss of intermittent or perennial streams caused by NWP 21
activities may still result in minimal individual and cumulative
adverse effects on the aquatic environment, and in such cases
authorization by NWP is appropriate. Note that the 300 linear foot
limit may not be waived for perennial streams. Activities authorized
under paragraph (a) of NWP 21 do not require agency coordination
because paragraph (a) does not authorize any expansion of surface coal
mining activities in waters of the United States and the district
engineer previously determined, and must again
[[Page 10204]]
confirm in writing, that those activities will result in minimal
individual and cumulative adverse effects and qualify for NWP
authorization. Many of the surface coal mining activities authorized
under the 2007 NWP 21 already had agency coordination because they
resulted in the loss of greater than \1/2\-acre of waters of the United
States.
Many commenters stated their preference for Option 2 because it
would not allow valley fills for surface coal mining activities, which
they believe substantially alter watersheds and associated headwater
streams, and generally are alleged to cause more than minimal adverse
effects on the aquatic environment. One commenter suggested adding a
provision that would prohibit the use of NWP 21 for activities
associated with mountain-top removal mining.
We have selected Option 2 for the reissuance of NWP 21, and have
made some additional modifications to reduce hardships on permittees
who previously obtained authorization under the NWP 21 issued on March
12, 2007, and invested substantial resources in reliance on that NWP
authorization. These modifications are discussed in greater detail
below. In addition, we have added a definition of ``valley fill'' to
the NWP to clarify the activities to which the valley fill prohibition
applies. For the purposes of this NWP, a ``hollow fill'' is considered
a valley fill. This NWP authorizes discharges of dredged or fill
material into waters of the United States when those discharges are
associated with surface coal mining activities. The Corps review is
focused on the individual and cumulative adverse effects to the aquatic
environment, and determining appropriate mitigation that may be needed
to ensure that the adverse effects on the aquatic environment are
minimal, individually and cumulatively. It does not extend to the
mining operation as a whole. The Surface Mining Control and Reclamation
Act of 1977 (SMCRA), 30 U.S.C. 1201 et seq., and its implementing
regulations address the environmental impacts of proposed surface coal
mining operations as a whole, including adverse effects to uplands and
changes in land use. SMCRA is administered by the Office of Surface
Mining Reclamation and Enforcement and states with approved regulatory
programs under SMCRA.
Two commenters supported Option 3, and they said the production of
energy from all sources, including surface-mined coal, is vitally
important to the short-term economic recovery of the United States and
the long-term energy independence and economic prosperity of our
country. Another commenter said there is no need to limit NWP 21 to \1/
2\-acre and 300 linear feet and prohibit valley fills, because district
engineers review every pre-construction notification and can require an
individual permit if necessary.
We have adopted Option 2 because it provides greater assurance that
NWP 21 will authorize only those discharges of dredged or fill material
into waters of the United States that have minimal individual and
cumulative adverse effects on the aquatic environment. Surface coal
mining activities that involve discharges of dredged or fill material
that require section 404 permits but do not qualify for NWP 21 may be
authorized by other forms of Department of the Army authorization, such
as individual permits or regional general permits. We have added the
\1/2\-acre limit, and the 300 linear foot limit for the loss of stream
bed, to make this NWP consistent with many of the other NWPs (e.g.,
NWPs 29, 39, 40, 42, 43, 44, and 51). We have also added a prohibition
against using this NWP to authorize discharges of dredged or fill
material into waters of the United States to construct valley fills.
Such limits are necessary to constrain the adverse effects to the
aquatic environment, to ensure compliance with the statutory
requirement that general permits, including NWPs, may only authorize
those activities that have minimal individual and cumulative adverse
effects on the aquatic environment. We do not believe it is efficient
to rely on the pre-construction notification process alone to ensure
minimal adverse environmental effects. Many other NWPs use a
combination of acreage and/or linear foot limits and pre-construction
notification requirements to ensure compliance with Section 404(e) of
the Clean Water Act, as well as 33 CFR 322.2(f) and 33 CFR 323.2(h).
Previous versions of NWP 21 did not have any acreage or linear foot
limits, and relied solely on the pre-construction notification review
process and permit conditions to reduce adverse effects on the aquatic
environment to satisfy the minimal adverse environmental effects
requirement for general permits. We believe that approach is no longer
appropriate because of the inconsistency with other NWPs, the
possibility that larger losses of waters of the United States might be
authorized, and the difficulty of documenting minimal adverse effect
determinations for losses of aquatic resource area and functions that
exceed those allowed in other NWPs. We note that part of the basis for
the earlier approach was the environmental review that occurs in
connection with obtaining a SMCRA permit, and that the SMCRA
regulations related to stream protection have changed since the
previous NWP 21 was issued.\1\ The new acreage and linear foot limits
will ensure that this NWP contributes no more than minimal individual
and cumulative adverse effects to the aquatic environment, by limiting
the amount of waters of the United States that can be filled by each
NWP 21 activity.
---------------------------------------------------------------------------
\1\ The Office of Surface Mining has announced its intention to
further revise these requirements however such revisions will not be
in place at the time the NWPs are reissued. The Corps may reconsider
these limits in future promulgations of the NWPs based on its
experience and any changes in the broader regulatory context.
---------------------------------------------------------------------------
Many commenters said the Corps should fulfill its June 2009
determination to prohibit the use of NWP 21 to authorize surface coal
mining activities in six states in Appalachia because these activities
result in more than minimal adverse effects to the aquatic environment,
individually and cumulatively. Some commenters said the proposed
reissuance of NWP 21 is contrary to the Corps June 18, 2010, decision
to suspend NWP in the Appalachian region of Kentucky, Ohio,
Pennsylvania, Tennessee, Virginia, and West Virginia, which stated that
continued use of this NWP may result in more than minimal adverse
effects to aquatic resources. Many commenters stated that surface coal
mining activities in Appalachia have resulted in the loss of a couple
of thousand miles of streams, substantially degraded water quality, and
are harmful to the health and drinking water of Appalachian citizens.
They also said the Corps should follow science and stop issuing
permits, including individual permits, for surface coal mining
activities in these six Appalachian states because those activities
cause significant degradation of waters of the United States, and this
region cannot afford to lose more of its vital natural resources.
In accordance with the June 11, 2009, memorandum of agreement
implementing the interagency action plan on Appalachian Surface Coal
Mining, which was signed by the Department of the Army, the Department
of Interior, and the U.S. Environmental Protection Agency, the Corps
issued a proposal in the Federal Register on July 15, 2009, to modify
NWP 21 so that it would not authorize discharges of dredged or fill
material into waters of the United States in the Appalachian region of
Kentucky, Ohio, Pennsylvania, Tennessee, Virginia, and
[[Page 10205]]
West Virginia (see 74 FR 34311). In the June 18, 2010, issue of the
Federal Register (75 FR 34711), the Corps announced the suspension of
NWP 21 in the Appalachian region of six states (i.e., Kentucky, Ohio,
Pennsylvania, Tennessee, Virginia, and West Virginia) and said that it
would consider modifying NWP 21.
As a result of our review of the comments received in response to
the February 16, 2011, proposal we have determined that it would be
appropriate to adopt Option 2 and substantially modify NWP 21 by
imposing acreage and linear foot limits, as well as prohibiting its use
to authorize discharges of dredged or fill material into waters of the
United States to construct valley fills associated with surface coal
mining activities, to ensure that the NWP authorizes only those
activities that result in minimal individual and cumulative adverse
effects on the aquatic environment. The \1/2\-acre and 300 linear foot
limits will substantially reduce the amount of stream bed and other
waters lost as a result of activities authorized by this NWP, and limit
this NWP to minor fills associated with surface coal mining activities,
such as the construction of sediment ponds. Issues relating to the use
of individual permits to authorize discharges of dredged or fill
material into waters of the United States associated with surface coal
mining activities are outside the scope of the NWP reissuance process
and are not addressed in this rule.
The proposed reissuance of NWP 21, as well as the selection of
Option 2 to reissue the NWP with \1/2\-acre and 300 linear foot limits
and a prohibition against authorizing discharges of dredged or fill
material into waters of the United States to construct valley fills, is
not contrary to the suspension of NWP 21 in the Appalachian region of
these six states. The NWP reissued today has been substantially
modified from the 2007 version of NWP 21, with paragraph (a)
authorizing Corps district engineers to re-authorize activities that
were previously verified under the 2007 NWP 21 authorization where that
would be appropriate, and paragraph (b) imposing the acreage and linear
foot limits stated above, as well as the condition prohibiting its use
for the construction of valley fills in waters of the United States, on
new NWP 21 activities. The substantial changes in the terms and
conditions of the reissued NWP 21 will ensure that the activities
authorized by this NWP result in minimal individual and cumulative
adverse effects on the aquatic environment. District engineers will
review pre-construction notifications for activities authorized under
paragraph (b) of this NWP and may require compensatory mitigation to
offset losses of waters of the United States and ensure the adverse
effects on the aquatic environment are minimal, individually and
cumulatively. Compensatory mitigation required for activities verified
under the 2007 NWP 21 will continue to be required, and may be
augmented if the district engineer determines that they do not
adequately compensate for losses of aquatic resource function and
ensure minimal individual and cumulative adverse effects. Suspension of
an NWP is an interim measure to be taken if there are substantive
concerns that an NWP activity is potentially causing more than minimal
adverse environmental effects, while the Corps collects additional
information and considers modifications to that NWP to satisfy
statutory or regulatory requirements for general permits, such as
compliance with Section 404(e) of the Clean Water Act. We fully
considered the comments received in response to the July 15, 2009,
proposal to suspend NWP 21 and used those comments to develop the three
options presented in the February 16, 2011, proposal to reissue NWP 21.
We have now determined that adopting Option 2 addresses the concern
that led to our previous suspension of NWP 21 in the six Appalachian
states, but in a more effective and equitable way. It is not the
geographic location of activities, but rather the nature of these
activities and their associated discharges that may lead to more than
minimal adverse effects. By prohibiting the use of NWP 21 for
discharges associated with valley fills and activities exceeding
appropriate thresholds, which are consistent with the thresholds used
for many other NWPs, we can ensure that activities that may result in
more than minimal individual and cumulative adverse effects obtain
individual permits, and those activities that will not result in more
than minimal adverse effects can be authorized by an NWP, regardless of
the region of the country in which they occur.
Only those surface coal mining activities involving discharges into
waters of the United States that received written authorization under
the 2007 NWP 21 may be eligible for authorization under paragraph (a)
of this NWP. Activities that were subject to the June 18, 2010,
suspension of NWP 21 in the Appalachian region of the six states may be
eligible for NWP 21 authorization under paragraph (b) if they do not
result in the loss of greater than \1/2\-acre of waters of the United
States, do not result in the loss of greater than 300 linear feet of
stream bed (unless that 300 linear foot limit for intermittent and
ephemeral streams is waived by the district engineer after agency
coordination and making a written determination that the activity will
result in minimal individual and cumulative adverse effects on the
aquatic environment), and do not involve discharges of dredged or fill
material into waters of the United States to construct valley fills.
One commenter objected to the proposed reissuance of NWP 21,
stating that it authorizes impacts for activities that are not similar
in nature, such as mining operations, impoundments, processing plants,
and road crossings. The commenter said that the Corps decision
documents do not recognize that impoundments can cause massive spills
or contaminate well water.
We do not agree that this NWP authorizes activities that are not
similar in nature. This NWP authorizes surface coal mining activities,
a broad category that includes a variety of features that may be
constructed by discharging dredged or fill material into waters of the
United States, the activities regulated by the Corps under Section 404
of the Clean Water Act. Discharges of dredged or fill material into
waters of the United States may be used to construct sediment ponds,
road crossings, etc. that are necessary to conduct surface coal mining
activities, or they may occur while coal is being mined (e.g., mine-
throughs). Impoundments constructed in waters of the United States
should be properly maintained (see general condition 14, proper
maintenance). District engineers may also require non-Federal
permittees to demonstrate that those impoundment structures comply with
applicable dam safety criteria (see general condition 24, safety of
impoundment structures).
One commenter said that if NWP 21 was reissued and could be used to
authorize valley fills, the Corps would violate the requirement in the
404(b)(1) Guidelines that no discharge of dredged or fill material
shall be permitted which will cause or contribute to significant
degradation of waters of the United States. This commenter also stated
that the proposed 300 linear foot limit for the loss of stream bed
would not prevent significant degradation of streams, and objected to
the proposed waiver of that limit for intermittent and ephemeral
streams, if the district engineer determined that such a loss would
result in minimal adverse effects on the aquatic environment.
[[Page 10206]]
The NWP 21 reissued today does not authorize discharges of dredged
or fill material into waters of the United States to construct valley
fills, unless under paragraph (a) the activity was previously verified
under the 2007 NWP 21 and the district engineer has determined that
those activities still qualify for NWP 21 authorization under the 2012
NWP general conditions, applicable regional conditions, and any
activity-specific conditions such as compensatory mitigation
requirements. For those previously authorized surface coal mining
activities, the district engineer determined that the adverse effects
on the aquatic environment are minimal, individually and cumulatively.
To re-verify the NWP authorization under the 2012 NWP 21, the district
engineer must determine that the activity continues to result in
minimal individual and cumulative adverse effects on the aquatic
environment. Surface coal mining activities that involve discharges of
dredged or fill material into waters of the United States for the
construction of valley fills that were not previously verified under
the 2007 NWP 21 are subject to paragraph (b) of the 2012 NWP 21 and
cannot be authorized by NWP 21. Discharges of dredged or fill material
into waters of the United States authorized by NWP 21 require water
quality certification. If water quality certification is not obtained
or waived, that activity is not authorized by NWP 21. The water quality
certifications issued by states are to be considered by district
engineers to be conclusive regarding water quality issues, unless the
Regional Administrator of the U.S. Environmental Protection Agency
advises the district engineer of other water quality concerns that need
to be taken into consideration. The construction of impoundments
authorized by NWP 21 is generally a minor cause of changes to water
quality. Most of the changes to water quality are due to the overall
surface coal mining activity and the change in land use (including
uplands) that occurs as a result of those mining activities. The
discharges of dredged or fill material into waters of the United States
authorized by NWP 21 constitute a small proportion of the overall fill
placed in a watershed to dispose of the rock, soil, and other materials
that are produced by the surface coal mining activity. As water
percolates through the larger overall fill that has been placed in
uplands and streams, the water chemistry changes. The effluent
discharged from impoundments constructed to trap sediments and other
materials to reduce their transport to downstream waters is regulated
under Section 402 of the Clean Water Act, and requires a National
Pollutant Discharge Elimination System (NPDES) permit. The NPDES permit
is issued by states that have approved programs or the U.S. EPA.
One commenter said the Corps has ignored cumulative impacts from
discharges of dredged or fill material previously authorized by NWP 21
in proposing Option 2 as a preferred alternative. The commenter also
stated that the draft decision documents fail to provide any evidence
that would support a minimal effects determination and that the Corps
only considers cumulative effects during the five year period the NWP
is in effect and this ignores the fact that valley fills bury streams
permanently, whether authorized by past nationwide or individual
permits, or in the future. The commenter also said that Option 2
ignores the cumulative amount of stream loss or acreage in a watershed
from multiple permits.
We have taken into account cumulative impacts from discharges of
dredged or fill material previously authorized by NWP 21, and
cumulative effects of discharges of dredged or fill material previously
authorized by individual permits, when developing the proposal to
reissue NWP 21, including Option 2. For NWP 21 activities that were not
previously authorized by the 2007 NWP 21, paragraph (b) of NWP 21
imposes a \1/2\-acre limit on NWP 21, as well as a 300 linear foot
limit for losses of stream bed, and does not authorize discharges of
dredged or fill material into waters of the United States to construct
valley fills. These changes will reduce the number of surface coal
mining activities authorized by NWP 21, when compared to previous
versions of NWP 21, which had no acreage or linear foot limits, and
could be used to authorize discharges of dredged or fill material into
waters of the United States to construct valley fills. We determined
that these limits will ensure that the adverse effects of discharges
authorized by NWP 21 are minimal, both individually and cumulatively.
Under the National Environmental Policy Act, an assessment of
cumulative effects has to consider the past, present, and reasonably
foreseeable future actions regardless of what agency (Federal or non-
federal) or person undertakes such actions (see 40 CFR 1508.7). In
addition, the 404(b)(1) Guidelines require a different approach to
cumulative effects analysis for the issuance of a general permit, such
as NWP 21. The 404(b)(1) Guidelines require the Corps or other
permitting authority to predict cumulative effects by evaluating the
number of individual discharges of dredged or fill material into waters
of the United States expected to be authorized by that general permit
until it expires (see 40 CFR 230.7(b)(3)).
The decision document for this NWP includes evaluations of
cumulative effects under both approaches, and concludes that the
reissuance of this NWP, including the imposition of the \1/2\-acre
limit, 300 linear foot limit, and prohibition against authorizing
valley fills on activities that were not previously authorized under
the 2007 NWP 21, as well as the pre-construction notification
requirements and other procedural safeguards, will authorize only those
activities with minimal individual and cumulative adverse effects on
the aquatic environment. Activities authorized under the 2007 NWP 21
were already determined by district engineers to result in minimal
individual and cumulative adverse effects on the aquatic environment.
The other procedural safeguards include the authority for division
engineers to modify, suspend, or revoke NWP 21 authorizations on a
regional basis, and the authority for district engineers to modify NWP
21 authorizations by adding conditions, such as compensatory mitigation
requirements, to ensure minimal individual and cumulative adverse
effects on the aquatic environment. District engineers may also assert
discretionary authority to require individual permits in cases where
the adverse effects will be more than minimal.
Under the National Environmental Policy Act approach to assessing
cumulative effects, the decision document discusses, in general terms,
the various activities (Federal, non-Federal, and private actions) that
may adversely affect the quantity and quality of aquatic resources in a
watershed or other geographic region used for cumulative effects
analysis, regardless of whether those activities occurred in the past
or are expected to occur in the present or reasonably foreseeable
future. Under the 404(b)(1) Guidelines approach for assessing
cumulative effects of the issuance of a general permit such as NWP 21,
the decision document evaluates the number of discharges of dredged or
fill material into waters of the United States expected to occur during
the five-year period the NWP would be in effect, as well as the
estimated loss of waters of the United States and compensatory
mitigation. District and division engineers are to supplement these
[[Page 10207]]
analyses when they prepare supplemental decision documents for this
NWP, and these supplemental decision documents are to include
cumulative effects analyses at a regional level. which can be highly
informative regarding impacts at a local watershed level. The
appropriate geographic scope of those cumulative effects analyses are
at the discretion of the division or district engineers.
The Corps considers and addresses cumulative environmental effects
of NWP 21 (and other NWPs) in two distinct ways. First, when Corps
Headquarters evaluates and proposes to issue or re-issue a NWP (such as
NWP 21), we evaluate cumulative effects at the national level, using
available national information on aquatic resource status and trends
and the general effects human activities have on aquatic resources. The
cumulative effects analyses presented in the Headquarters decision
documents reflect these national-scale evaluations and conclusions
supporting the promulgation of the NWP from Corps Headquarters.
Second, division and district engineers monitor the use of the NWPs
on a regional level, and will modify, suspend, or revoke applicable
NWPs when necessary if the use of those NWPs is likely to result in
more than minimal individual and cumulative adverse effects on the
aquatic environment within a particular watershed, ecoregion, state,
county, or other appropriate geographic area. To address regional and
site-specific environmental considerations, we rely on the Corps
district offices that receive pre-construction notifications required
by the terms and conditions of the NWP to evaluate the relevant
regional and site-specific environmental considerations. The Corps
district may add conditions to the NWP authorization, including
compensatory mitigation requirements, to ensure that the individual and
cumulative adverse effects on the aquatic environment caused by the NWP
activity are minimal, and therefore qualify for NWP authorization. If
conditions cannot be added to the NWP authorization to ensure that
minimal individual and cumulative adverse effects on the aquatic
environment occur, the district engineer will exercise discretionary
authority and notify the applicant that an individual permit is
required.
One commenter said there is insufficient support for the Corps
position that the required compensatory mitigation will attenuate
cumulative impacts on the Nation's aquatic resources by providing
aquatic resource functions and services, so the net effects will be
minimal. Another commenter stated that the Corps relies heavily on
mitigation, such as stream creation, restoration, and enhancement, but
there is no evidence that stream creation works. The commenter also
indicated that the 404(b)(1) Guidelines provide that no permit may rely
on mitigation techniques unless they have been demonstrated to be
effective in circumstances similar to those under consideration, and
that the 2008 compensatory mitigation rule requires that the district
engineer assess the likelihood for ecological success. The commenter
said the Corps cannot issue an NWP without assessing mitigation
effectiveness and success in the specific context in which the
mitigation technique would be used. The commenter concluded that the
Corps mitigation analysis fails to contain any discussion of stream
functions that would be lost from potential NWP activities and whether
compensatory mitigation can replace those functions.
Compensatory mitigation can be an effective means of offsetting
losses of aquatic resource functions caused by activities authorized by
Department of the Army permits, including NWP 21 activities, if it is
thoughtfully planned, implemented, and monitored. Compensatory
mitigation projects must be carefully sited, planned, and designed to
be ecologically successful in providing stream or wetland functions.
Site selection is a critical step in developing and implementing an
ecologically successful compensatory mitigation project. With the
promulgation of 33 CFR part 332 on April 10, 2008 (73 FR 19594), the
Corps Regulatory Program adopted requirements and standards to improve
compensatory mitigation practices for offsetting losses of aquatic
resource functions. Under the 2008 rule, a watershed approach should be
used for establishing compensatory mitigation requirements that will
successfully provide aquatic resource functions to offset losses of
those functions caused by permitted activities.
The 2008 rule identifies streams as ``difficult-to-replace''
resources and states that if further avoidance and minimization of
stream impacts is not practicable, the required compensatory mitigation
should be provided through stream rehabilitation, enhancement, or
preservation since those techniques have a greater certainty of success
(see 33 CFR 332.3(e)(3)). The preamble to the 2008 rule includes a
detailed discussion of the scientific status of stream restoration and
concludes that there has been success with stream rehabilitation,
enhancement, and preservation activities (see 73 FR 19596-19598). In
accordance with the 2008 rule, the Corps is not relying on stream
creation as a mechanism to provide compensatory mitigation for NWP 21
activities. In cases where compensatory mitigation is required for NWP
21 activities, those compensatory mitigation requirements will be
specified as activity-specific conditions of NWP 21 authorizations. The
required components of a compensatory mitigation plan are specified at
33 CFR 332.4(c)(2)-(14), and the district engineer will evaluate each
compensatory mitigation proposal to assess its potential for ecological
success, and consider the relevant factors provided in 33 CFR 332.3.
The compensatory mitigation plan must be approved by the district
engineer and monitoring will be required to assess whether the
compensatory mitigation project is meeting its objectives and is
successfully meeting its ecological performance standards. The district
engineer will review monitoring reports, and if the compensatory
mitigation project is not meeting its ecological performance standards,
he or she will require the responsible party to identify and implement
adaptive management measures to make changes to provide a successful
mitigation project. If adaptive management is not likely to result in
an ecologically successful compensatory mitigation project that will be
sufficient for offsetting lost aquatic resource functions that result
from the permitted activity, alternative compensatory mitigation may be
required. Financial assurances may also be required to help ensure the
success of the required compensatory mitigation.
The 404(b)(1) Guidelines, which address habitat development and
restoration as a means of minimizing adverse effects to plant and
animal populations (40 CFR 230.75(d)), recommend the use of techniques
that have been demonstrated to be effective. That provision is
consistent with the section on difficult-to-replace resources (33 CFR
332.3(e)(3)/40 CFR 230.93(e)(3)), which states that rehabilitation,
enhancement, and preservation should be used to provide the required
compensatory mitigation to offset permitted impacts to such resources
because there is greater certainty that such stream rehabilitation,
enhancement, and preservation will be ecologically successful and
offset those permitted impacts. The decision document for this NWP
contains a general discussion of the functions provided by streams, as
well as general
[[Page 10208]]
citations supporting our position that stream rehabilitation and
enhancement can provide stream functions to offset functions lost as a
result of permitted activities. It is not necessary for the decision
document to provide a comprehensive analysis of the state of stream
restoration success. The approach discussed above, and in 33 CFR part
332, is consistent with the Council on Environmental Quality's January
14, 2011, guidance on the ``Appropriate Use of Mitigation and
Monitoring and Clarifying the Appropriate Use of Mitigated Findings of
No Significant Impact.'' That guidance advocates the use of adaptive
management to take corrective actions if the required mitigation fails
to achieve projected environmental outcomes, which is also required by
the Corps compensatory mitigation regulations in 33 CFR part 332.
One commenter said that the Corps has failed to analyze whether
surface coal mining activities authorized by NWP 21 will cause
significant degradation to ``special aquatic sites,'' such as riffle
and pool complexes. This commenter asserted that valley fills and
mining through streams frequently buries riffle and pool complexes, and
these special aquatic sites are protected by stringent restrictions on
discharges of fill material into such sites. The commenter also stated
that practicable alternatives that do not involve burying riffles and
pools are presumed to be available unless clearly demonstrated
otherwise and such alternatives are presumed to have less adverse
impacts on the aquatic ecosystem. This commenter said the Corps should
deny a permit if it lacks sufficient information to determine whether
the proposed discharge complies with the Guidelines.
The activities authorized by this NWP comply with the 404(b)(1)
Guidelines, even though it authorizes discharges of dredged or fill
material into waters of the United States that may be classified as
special aquatic sites such as riffle and pool complexes. Each activity
authorized by an NWP does not require a project-specific 404(b)(1)
Guidelines analysis--that analysis is done before the NWP or any other
type of general permit is issued (see 40 CFR 230.7). The 404(b)(1)
Guidelines do not prohibit the use of general permits to authorize
discharges of dredged or fill material into special aquatic sites. A
determination of significant degradation does not focus simply on the
loss of a special aquatic site caused by the discharge of dredged or
fill material. It requires a broader analysis. The process for
determining whether significant degradation occurs consists of applying
the provisions of the 404(b)(1) Guidelines holistically, and assessing
the effects of the proposed discharge of pollutants on human health and
welfare; aquatic life and wildlife; aquatic ecosystem diversity,
productivity, and stability; and recreational, aesthetic, and economic
values. For activities authorized by general permits, the evaluation of
alternatives in accordance with 40 CFR 230.10(a) does not directly
apply (see 40 CFR 230.7(b)(1)). Paragraph (a) of general condition 23,
mitigation, requires project proponents to design and construct NWP
activities to avoid and minimize adverse effects to the aquatic
environment to the maximum extent practicable on the project site.
Several commenters stated that surface coal mines are already
heavily regulated under SMCRA, which includes a variety of requirements
to protect waters of the United States, so additional requirements are
not needed to ensure that adverse effects to the aquatic environment
are minimal. Two of these commenters stated NWP 21 should be reissued
without change because of SMCRA requirements. One commenter said the
authority to authorize stream and wetland impacts caused by mining
activities should rest solely with the SMCRA regulatory authority.
There is often more than one Federal law that regulates surface
coal mining activities, especially in cases where those activities
involve discharges of dredged or fill material into waters of the
United States. While most aspects of surface coal mining are regulated
under SMCRA, surface coal mining and reclamation activities involving
discharges of dredged or fill material into waters of the United States
also require permits issued under Section 404 of the Clean Water Act.
The statutory and regulatory standards established under SMCRA are
different than those established under Section 404 of the Clean Water
Act, including section 404(e) which authorizes the Corps to issue
general permits. One of the objectives of SMCRA is to ensure that
surface coal mining activities are conducted in an environmentally
responsible manner and that the land disturbed by mining is adequately
reclaimed. One of the objectives of the Clean Water Act is to ``restore
and maintain the physical, chemical, and biological integrity of the
Nation's waters.'' Under the regulations implementing SMCRA, surface
coal mining and reclamation activities must be conducted in a manner
that will ``minimize the disturbance of the hydrologic balance within
the permit and adjacent areas'' and that will ``prevent material damage
to the hydrologic balance outside the permit area.'' As part of the
SMCRA permitting process, potential changes to the quality and quantity
of surface and groundwater are evaluated to ensure that material damage
to the hydrologic balance outside the permit area will not occur. Other
factors considered under SMCRA include: pre- and post-mining land uses,
backfilling and grading activities, disposal of excess spoil, and the
protection or replacement of water supplies.
Under Section 404 of the Clean Water Act, the 404(b)(1) Guidelines
provide the substantive criteria for evaluating the environmental
effects of proposed discharges of dredged or fill material into waters
of the United States. The 404(b)(1) Guidelines are not focused on
considering effects to water quality and quantity. The 404(b)(1)
Guidelines also require examination of the effects that discharges of
dredged or fill material will have on physical, chemical, and
biological attributes of waters of the United States. The 404(b)(1)
Guidelines at 40 CFR part 230 require the Corps to evaluate the effects
of discharges of dredged or fill material, including general permits
that authorize such discharges, on the applicable criteria listed in
subparts C through F. Examples of criteria in those subparts are:
Substrate; suspended particulates/turbidity; water; current patterns
and water circulation; normal water fluctuations; threatened and
endangered species; fish, crustaceans, mollusks, and other aquatic
organisms in the food web; other wildlife; wetlands; riffle and pool
complexes; municipal and private water supplies; recreational and
commercial fisheries; water-related recreation; and aesthetics. The
threshold for issuance of general permits such as NWP 21 is a
determination that the authorized activities would result in no more
than minimal individual or cumulative adverse environmental effects.
There is no corresponding threshold under SMCRA and its
implementing regulations, which do not require that permit applications
be evaluated in terms of the 404(b)(1) Guidelines. Instead, section
507(b)(11) of SMCRA requires that the permit applicant prepare a
determination of the probable hydrologic consequences of the proposed
operation with respect to the hydrologic regime and the quantity and
quality of water in surface and ground water systems. Section 510(b)(3)
of SMCRA requires that the regulatory authority use this determination
and other available information to prepare an assessment of the
probable
[[Page 10209]]
cumulative impact of all anticipated mining in the area on the
hydrologic balance. The SMCRA regulatory authority may not issue a
permit unless it first finds that the operation has been designed to
prevent material damage to the hydrologic balance outside the permit
area. While there is some overlap, the thresholds for permit issuance
under SMCRA are not the same as the thresholds under Section 404 of the
Clean Water Act. Given the different permit issuance thresholds of
SMCRA and Section 404 of the Clean Water Act, NWP 21 authorizations
cannot only rely on the environmental reviews conducted under SMCRA to
satisfy the minimal effects requirement.
Section 404 of the Clean Water Act applies to all discharges of
dredged or fill material into waters of the United States, unless those
activities qualify for an exemption under Section 404(f) of the Clean
Water Act. Section 404(f) does not specifically exempt surface coal
mining activities. For those activities that do not qualify for an
exemption from the permit requirements of the CWA, the Corps must
evaluate applications for Department of the Army permits, including
general permits, and either apply the 404(b)(1) Guidelines (if an
individual permit is required) or determine whether the proposed
activity qualifies for NWP authorization. This NWP provides an
efficient means of authorizing discharges of dredged or fill material
into waters of the United States that result in minimal individual and
cumulative adverse effects on the aquatic environment. Corps districts
work with SMCRA regulatory authorities to reduce duplication, but each
agency must still ensure that proposed activities comply with their
respective statutes and implementing regulations.
Two commenters stated the primary effect of adopting any of the
three options proposed for NWP 21 in the February 16, 2011, Federal
Register notice would be to require proposed surface coal mining
activities involving discharges of dredged or fill material into waters
of the United States to be evaluated under the individual permit
process. This would cause an unnecessary additional delay and expense
to mine operators and require the Corps to get additional personnel and
funding to process additional individual permit applications in a
timely manner. One commenter suggested that NWP 21 should be reissued
as it was in 2007, and that regional conditions should be used in
Appalachia to ensure those activities result in minimal adverse effects
on the aquatic environment. This commenter said this approach would
allow western coal producers to continue their operations without
negative consequences.
We acknowledge that reissuing NWP 21 with a \1/2\-acre limit, a 300
linear foot limit for the loss of stream bed, and not authorizing
discharges of dredged or fill material into waters of the United States
to construct valley fills, will result in more surface coal mining
activities requiring Clean Water Act Section 404 individual permits. To
provide an equitable and less burdensome transition to the new limits
to NWP 21, under paragraph (a) NWP 21 continues to authorize surface
coal mining activities that were previously authorized under the 2007
NWP 21 without those new limits. Under paragraph (b), the \1/2\-acre
and 300 linear foot limits, as well as the prohibition against
authorizing discharges of dredged or fill material into waters of the
United States to construct valley fills, apply to surface coal mining
activities that were not authorized by the 2007 NWP 21. Expansions of
activities that were previously verified under the 2007 NWP 21 do not
qualify for paragraph (a) of NWP 21.
Continuing to authorize surface coal mining activities that were
verified under the 2007 NWP 21 will reduce burdens on the regulated
public while protecting the aquatic environment in accordance with the
requirements of Section 404(e) of the Clean Water Act. These project
proponents who received verifications under the 2007 NWP 21 expended
substantial resources to obtain their authorizations. If they cannot
comply with the new limits imposed on NWP 21 it would impose a
significant hardship to require those operators to cease surface coal
mining activities in waters of the United States while they apply for
individual permits and wait for a decision. We estimate that there are
approximately 70 surface coal mining activities across the country that
were authorized by the 2007 NWP 21 that may qualify for authorization
under paragraph (a) of NWP 21 when it goes into effect on March 19,
2012. To obtain authorization under paragraph (a) of the 2012 NWP 21,
these project proponents do not need to submit a pre-construction
notification since they already did so under the 2007 NWP 21 and that
notification will be on file at the district office. Instead, those
project proponents only need submit a letter to the district engineer
requesting verification under the 2012 NWP 21. That letter should be
sent to the district engineer by February 1, 2013, although that
deadline may be extended in writing by the district engineer. This date
allows the district engineer approximately 45 days for review of the
letter before the expiration of the one-year period that is allowed for
completion of activities authorized under the 2007 NWP 21. Any changes
to the previously authorized surface coal mining activity must also be
described in that letter, so that the district engineer can determine
whether the activity still results in minimal individual and cumulative
adverse effects on the aquatic environment and is eligible for
authorization under paragraph (a) of NWP 21. The district engineer will
review such requests and notify the permittee whether the activity is
authorized by the 2012 NWP 21. There will be no agency coordination of
these previously authorized NWP 21 activities. Any currently applicable
regional conditions and any activity-specific conditions, such as
compensatory mitigation requirements, would apply to the NWP
authorization. The district engineer may also revise such conditions
and requirements if the existing ones are determined not to be adequate
to ensure minimal adverse effects. If the permittee does not receive a
written verification from the district engineer prior to the expiration
of the one-year period provided in 33 CFR 330.6(b), the permittee must
cease all activities until such verification is received because that
one-year period cannot be extended. The surface coal mine activity must
be authorized under the 2012 NWP 21 or another form of Department of
the Army authorization to discharge dredged or fill material into
waters of the United States after the one-year period ends on March 18,
2013. The district engineer may also extend the February 1, 2013,
deadline by notifying the permittee in writing, if he or she needs less
than 45 days to make a decision on the 2012 NWP 21 authorization. The
Corps encourages operators who received a 2007 NWP 21 verification and
plan to operate past March 18, 2013, to submit their letter as soon as
possible to allow for uninterrupted NWP 21 permit coverage. Expansions
of previously verified NWP 21 activities that result in greater losses
of waters of the United States are not authorized under paragraph (a)
will require a different form of Department of the Army authorization
if they do not qualify for authorization under paragraph (b) of NWP 21.
If the surface coal mining activity involving discharges of dredged or
fill material into waters of the United States authorized under
paragraph (a) cannot be completed by the time the 2012 NWP 21 expires,
then the project proponent
[[Page 10210]]
will have to obtain an individual permit or regional general permit, if
the activity does not qualify for an applicable NWP issued in 2017. The
Corps recommends that any projects that will extend beyond March 18,
2017, that do not meet the new limits in NWP 21 apply for an individual
permit and allow sufficient time for the Corps to process their
application to allow uninterrupted coverage when the new NWP 21 expires
in 2017.
The limits added to paragraph (b) of NWP 21 will ensure that this
NWP authorizes only those activities that have minimal adverse effects
on the aquatic environment, individually and cumulatively. These limits
will also result in more new projects needing to obtain individual
permits. The Corps has the resources necessary to process those
individual permit applications in a timely manner. It is important for
coal mine operators to consider the advantages of obtaining individual
permits for surface coal mining activities. In accordance with Section
404(e) of the Clean Water Act, general permits, including NWPs, can be
issued for a period of no more than five years. Individual permits can
be issued for longer periods of time--the expiration date for an
individual permit is at the discretion of the district engineer, who
will take into account the characteristics of the proposed activity and
the amount of time expected to be needed to complete the regulated
activities. Therefore, it would often be advantageous for a surface
coal mine operator to obtain an individual permit that would authorize
discharges of dredged or fill material into waters of the United States
for the expected operational timeframe for that particular coal mine.
Under NWP 21, no authorization could be issued for a time period of
more than five years. If the NWP 21 activity is not completed by the
expiration date of the NWP authorization then the project proponent
would have to notify the district engineer and obtain another NWP
verification.
Nationwide permit NWP 21 pre-construction notifications require
substantial resources to evaluate proposed activities and determine
whether they result in minimal individual and cumulative adverse
effects on the aquatic environment, and whether compensatory mitigation
is needed to comply with the minimal adverse environmental effects
requirement for general permits. Under the 2007 NWP 21, the project
proponent could not proceed until he or she obtained an NWP 21
verification. The substantial amount of review required for both NWP 21
pre-construction notifications and individual permit applications both
involve considerable amounts of resources from the Corps, so we do not
expect a significant increase in workload or processing times to occur
through the implementation of Option 2 and the modifications we made to
that option for the final NWP.
In response to the NWP 21 proposal, one commenter said the Corps
was attempting to decide on behalf of the United States government how
much coal mining should take place, or what scale of mining operations
is appropriate. The commenter suggested that the Corps only concern
should be the scale of the regulated activity and not the scale of the
mining operation. The commenter stated that the Corps evaluation of
surface coal mining activities should be focused on impacts to aquatic
resources. One commenter said the proposed changes to NWP 21 would have
a significant effect on energy supply, since the ability to obtain
permits in a timely manner is essential to the production of coal,
which provides over 30 percent of America's electric power.
The three options provided in the February 16, 2011, Federal
Register notice were intended to solicit comment to assist the Corps in
identifying an option for the reissuance of NWP 21 that would comply
with the statutory and regulatory requirements for general permits.
Those options were developed to determine which terms and conditions
(if any) should be established to ensure that NWP 21 authorizes only
those activities that result in minimal adverse effects on the aquatic
environment. The proposal does not affect how much coal mining may take
place, nor does it have a significant effect on energy supply, because
those surface coal mining activities that do not qualify for NWP 21
authorization may be authorized by individual permits or general
permits, if such general permits are available. The Corps review is
focused on adverse effects to aquatic resources, as well as other
public interest review factors. The limits on the use of NWP 21 are
expressed in terms of impacts to the aquatic environment, not the scale
of the mining operation. Other aspects of surface coal mining
activities are regulated by OSMRE or delegated states under SMCRA.
One commenter said that NWP 21 should not apply to ephemeral waters
because they are not jurisdictional waters of the United States.
Several commenters stated that NWP 21 encourages operators to design
their projects within the scope of the NWP rather than seek an
individual permit, thereby reducing impacts. These commenters said that
there may be a net gain of wetland acreages because of reclamation
practices at surface coal mines.
Ephemeral streams are waters of the United States if they meet the
definition of ``waters of the United States'' at 33 CFR part 328 and
applicable guidance on Clean Water Act jurisdiction, such as the
guidance issued in 2008 entitled ``Clean Water Act Jurisdiction
Following the U.S. Supreme Court's Decision in Rapanos v. United States
and Carabell v. United States.'' The NWP 21 issued in 2007 did not have
any acreage or linear foot limits, which are the primary tools used to
encourage avoidance and minimization to qualify for NWP authorization.
Except for those previously verified 2007 NWP 21 activities authorized
under paragraph (a), the NWP 21 reissued today has a \1/2\-acre limit
and a 300-linear foot limit for losses of stream bed, which will be
more effective in encouraging project proponents to avoid and minimize
losses of waters of the United States to quality for NWP 21
authorization. We acknowledge that there may be net gains in wetland
acreage at some surface coal mining reclamation sites, but we have
imposed limits on NWP 21 because of concerns about losses of stream bed
and the potential for surface coal mining activities to have more than
minimal adverse effects on the aquatic environment, individually and
cumulatively.
One commenter disagreed with the Corps assertion that valley fills
substantially alter watersheds and result in adverse impacts on the
aquatic environment. This commenter also said that Options 2 and 3 do
not allow the Corps the flexibility to increase the amount of stream
bed loss above the 300 linear foot limit. The commenter also objected
to the proposed interagency coordination for activities resulting in a
loss of greater than 1,000 linear feet of intermittent and ephemeral
stream beds, and said the Corps has not suggested any reasons for this
restrictive provision.
Surface coal mining activities involving the construction of valley
fills result in substantial changes to the watersheds of the headwater
streams that are primarily impacted by these activities. Those
watersheds are changed by the large amounts of land clearing and
earthmoving that occur during the mining activity. The construction of
the valley fill itself causes changes to the geomorphology of the
watershed, which affects water quality and watershed hydrologic
[[Page 10211]]
functions, such as water collection, transport, and storage. It is well
documented in the scientific literature that changes in land use affect
the quantity and quality of streams, wetlands, and other aquatic
resources. Examples of such scientific studies are cited in the
decision document for this NWP. The 300 linear foot limit for losses of
stream bed is generally necessary to ensure that NWP 21 authorizes only
those activities that result in minimal adverse effects on the aquatic
environment. However, that 300 linear foot limit may be waived by the
district engineer if the proposed activity involves filling or
excavating intermittent or ephemeral stream beds and the district
engineer determines, in writing, that that activity will result in
minimal individual and cumulative adverse effects on the aquatic
environment. Agency coordination for proposed losses of greater than
300 linear feet of intermittent or ephemeral stream bed is intended to
provide information that will assist the district engineer in making
his or her minimal adverse effects determination.
One commenter said all Corps divisions and districts should add
regional modification alternatives to address differences in aquatic
resources functions. This commenter also stated that the proposal
provides that the cumulative impact analysis for an NWP 21 is not
limited to assessing impacts of the use of the NWP 21 on a national
basis and is not limited to activities authorized by NWPs or other
Department of Army permits. The commenter acknowledged that the Corps
considers activities not regulated by the Corps, including private
actions and those resulting in changes in the use of uplands next to or
near wetlands, streams, or other aquatic resources during the
cumulative effects analysis.
It is at the division engineer's discretion whether to add regional
conditions to an NWP to ensure that the NWP authorizes only those
activities that have minimal individual and cumulative adverse effects
on the aquatic environment. In addition, district engineers may modify
NWP authorizations by adding activity-specific conditions to minimize
adverse environmental effects. The decision documents comply with the
two relevant approaches for conducting cumulative effects analyses: (1)
The approach provided in the Council on Environmental Quality's
definition of ``cumulative impact'' provided in their National
Environmental Policy Act regulations at 40 CFR 1508.7, and (2) the
approach indicated in the 404(b)(1) Guidelines at 40 CFR 230.7(b).
One commenter said the proposed changes to NWP 21 will actually
increase impacts because mining operators will need to increase the
size of their mining sites to make the individual permit process cost
effective. The commenter said operators will no longer be able to
afford to mine the smaller reserve areas, so larger mine areas would
need to be permitted.
The changes to NWP 21 are appropriate to help ensure that this NWP
complies with the statutory requirements for general permits, in that
it may only authorize activities that have minimal individual and
cumulative adverse environmental effects. Surface coal mining
activities involving discharges of dredged or fill material into waters
of the United States that do not qualify for NWP authorization will be
evaluated as individual permits if applicable regional general permits
are not available. Activities authorized by individual permits must
comply with the 404(b)(1) Guidelines and undergo an alternatives
analysis. A public interest review will also be conducted during the
individual permit review process. Mining companies will have to make
their own decisions on whether it is economically viable to mine
smaller reserve areas, and apply for Department of the Army
authorization if proposed activities involve discharges of dredged or
fill material into waters of the United States.
One commenter said that if Option 2 is adopted, it should include a
definition of valley fill. A commenter stated that the utility of NWP
21 would be substantially reduced because losses of waters of the
United States caused by the construction of attendant features such as
ponds and roads would be counted towards the \1/2\-acre and 300 linear
foot limits. Another commenter indicated that the \1/2\-acre limit
would only authorize small sediment ponds. This commenter stated that
small sediment ponds would not be able to effectively service a typical
mine site. One commenter requested clarification on whether the amount
of stream that is impounded for sediment ponds will be counted as a
loss of waters of the United States and whether these ponds will have
to be removed upon completion of the mining.
We have added a definition of the term ``valley fill'' to the text
of this NWP. While fewer surface coal mining activities involving
discharges of dredged or fill material into waters of the United States
would be authorized by NWP 21 when compared to previous issued versions
of this NWP, the new terms and conditions of this NWP, including the
\1/2\-acre and 300 linear foot limits, are necessary to ensure that
this NWP authorizes only those activities that have minimal individual
and cumulative adverse effects on the aquatic environment. If the
construction of larger sediment ponds does not qualify for NWP 21
authorization, activities may be authorized by individual permits or
applicable regional general permits. In the definition of ``loss of
waters of the United States'' the loss of stream bed is determined by
the amount of linear feet of stream bed that is filled or excavated. As
to whether sediment ponds would have to be removed upon completion of
the mining operation, that would be a case-specific determination made
by the district engineer after taking into account requirements of the
SMCRA authority.
One commenter asked how many surface coal mining activities may be
authorized each year with NWP 21 if Option 2 is selected. One commenter
said the proposed changes to NWP 21 would be costly to small businesses
and disagreed with the Corps statement that the revised NWPs will not
impose substantially higher costs on small entities than those of
existing permits. Another commenter indicated that the proposed changes
to NWP 21 would result in more environmental impact statements being
required because of the amount of wetlands in their area.
In section 6.2.2 of the decision document for this NWP, we provide
estimates of the number of times we predict NWP 21 will be used each
year. Under paragraph (b), we estimate that NWP 21 will be used
approximately 11 times per year, although more activities may qualify
for NWP 21 authorization if project proponents do additional avoidance
and minimization to reduce losses of waters of the United States to
satisfy the acreage and linear foot limits. As discussed above, we
estimate that, across the country, approximately 70 NWP 21 activities
verified under the 2007 NWP 21 might be re-verified under paragraph (a)
of the 2012 NWP 21. The estimate provided in the decision document was
based on an analysis of past use of NWP 21, and it is a rough estimate
because NWP 21 did not have an acreage or linear foot limit and we
cannot predict how many activities can be modified to comply with the
new limits. Therefore, it is difficult to accurately predict how often
project proponents will qualify for authorization under the NWP 21
issued today. Since fewer surface coal mining activities are likely to
qualify for NWP 21 authorization, and more will require individual
permits, we acknowledge
[[Page 10212]]
that there will be greater compliance costs for small businesses. In
the preamble to the proposal, where we discuss compliance with the
Regulatory Flexibility Act, we state that the proposed NWPs would not
result in a significant impact on a substantial number of small
entities. That statement was made in the context of considering all of
the 48 NWPs proposed to be reissued and the two proposed new NWPs. Some
NWPs, such as NWP 48, will require fewer pre-construction notifications
and other requirements on small entities while other NWPs, such as NWP
21, will have more stringent requirements to satisfy the minimal
adverse environmental effects standard and will authorize fewer
activities. We do not agree that these changes to NWP 21 will result in
significantly more environmental impact statements. The threshold for
NWP authorization, as well as for other general permits, is minimal
adverse environmental effects. The threshold for preparing an
environmental impact statement is that the activity constitutes a major
Federal action significantly affecting the quality of the human
environment. Since the threshold that triggers the requirement to
prepare an environmental impact statement is greater than the minimal
adverse environmental effects threshold for NWP activities, activities
that were previously authorized by NWP should generally not require an
environmental impact statement if they are instead evaluated through
the individual permit process. Environmental assessments should suffice
to provide National Environmental Policy Act compliance for most, if
not all, of those activities. If the adverse effects on the aquatic
environment for a proposed NWP activity are determined by the district
engineer to be more than minimal individually and cumulatively, then
discretionary authority should be exercised and the proposed activity
evaluated through the individual permit process.
Many commenters said that that it would be more appropriate to
establish different NWP terms and conditions for different areas of the
United States, because of vast differences in geological,
topographical, climatologically and ecological regimes in areas where
coal resources are located across the country. One of these commenters
recommended focusing on the use of regional conditions to address
regional differences in coal mining techniques and issues, instead of
modifying NWP 21.
An NWP is developed to authorize specific categories of activities
across the country that have minimal individual and cumulative adverse
effects on the aquatic environment and is issued by Corps Headquarters.
There must be a national decision document for each NWP, and to issue
that NWP, there must be a finding that the NWP will authorize only
those activities that have minimal individual and cumulative adverse
effects on the aquatic environment. Division and districts prepare
supplemental decision documents to explain whether regional conditions
are needed to satisfy the minimal adverse effects requirement. Regional
conditions are added to an NWP at a division engineer's discretion and
Corps Headquarters cannot mandate the adoption of regional conditions.
The national decision documents acknowledge that regional
conditions approved by division engineers and activity-specific
conditions added to NWP authorizations are procedures to be relied upon
to satisfy the minimal adverse environmental effects requirement. In
those areas of the country where surface coal mining activities result
in minimal individual and cumulative adverse effects on the aquatic
environment but exceed the limits of NWP 21, division and district
engineers may issue regional general permits that have different terms
and conditions than NWP 21, including larger acreage or linear foot
limits. Those regional general permits are a more appropriate mechanism
for considering local geologic, topographic, climatologic, and
ecological characteristics.
Some commenters stated that Executive Order 13563, ``Improving
Regulation and Regulatory Review'' asks federal agencies to tailor
regulations to impose the least burden on society, including
individuals, businesses of differing sizes, and other entities. These
commenters said that adding additional redundant review by Federal
agencies violates this Executive Order and threatens energy supplies.
One of these commenters said the proposal to reissue NWP 21 with
modifications is contrary to the objectives of Executive Order 13563
because it fails to use the best, most innovative and least burdensome
tools for achieving regulatory ends and that the proposed limits in NWP
21 are redundant, inconsistent, or overlapping with other regulations.
As explicitly recognized in Executive Order 13563 itself, an
Executive Order does not supersede Federal laws, such as the
requirements in the Clean Water Act, the Rivers and Harbors Act of
1899, the Endangered Species Act, and the National Historic
Preservation Act. Section 404(e) of the Clean Water Act states that
general permits (including NWPs) authorize categories of activities
that are similar in nature and result only in minimal individual and
cumulative adverse environmental effects. The Corps complied with
Section 2 of Executive Order 13563 by seeking public comment on the
proposal to reissue NWP 21 with modifications, for a 60-day comment
period. The Corps has determined that the changes to NWP 21 are
necessary to comply with the requirements of Section 404(e) of the
Clean Water Act. We have modified Option 2 by authorizing activities
verified under the 2007 NWP 21 (see paragraph (a) of NWP 21), to
provide an equitable transition to the new limits in NWP 21 and reduce
burdens on the regulated public. The authority for the district
engineer to waive the linear foot limit for losses of intermittent and
ephemeral streams if the impacts are not more than minimal is also
intended to minimize regulatory burden. As discussed earlier in this
section, the terms and conditions of NWP 21 are not duplicative with
the requirements of other Federal agencies. While surface coal mining
activities are more broadly regulated under the Surface Mining Control
and Reclamation Act by the Office of Surface Mining Reclamation and
Enforcement or approved states, the Corps regulates discharges of
dredged or fill material into waters of the United States, and focuses
its evaluation on the effects those discharges have on the aquatic
environment or its other public interest review factors (see 33 CFR
330.1(d) and (e)(2)). Those activities that do not qualify for NWP
authorization may be authorized by other forms of Department of the
Army authorization, such as individual permits or regional general
permits. The standards the Corps uses to ensure compliance with the
Clean Water Act differ from the standards used by the Office of Surface
Mining Reclamation and Enforcement or approved states to ensure
compliance with the Surface Mining Control and Reclamation Act, and
those standards are not redundant.
A commenter disagreed with the Corps statement that the proposed
NWPs are not a significant energy action as defined by Executive Order
13211 because of the proposed changes to NWP 21. The commenter said the
Corps must prepare a Statement of Energy Effects as required by the
Executive Order, including a description of the adverse impacts
expected to the production of coal, the nation's primary electrical
generation fuel supply. One commenter said that the time frames for
evaluating NWP 21 pre-construction notifications should be similar to
those
[[Page 10213]]
of other NWPS, and NWP 21 should not require the project proponent to
wait until he or she receives a written NWP verification even if the
45-day review period has passed.
The changes to NWP 21 are appropriate and help to ensure that the
NWP authorizes only those discharges of dredged or fill materials into
waters of the United States that have minimal adverse effects on the
aquatic environment, individually and cumulatively. Surface coal mining
activities that involve discharges of dredged or fill material into
waters of the United States that do not qualify for NWP authorization
may be authorized by individual permits or, if available, applicable
regional general permits, which would still support the production of
coal to supply the nation's energy needs. Given the adverse
environmental effects associated with surface coal mining activities
involving discharges of dredged or fill material into waters of the
United States, which are discussed in the decision document for this
NWP, we believe it is necessary to retain the existing requirement that
the project proponent may not proceed with the NWP 21 activity until
after he or she has obtained a written NWP 21 verification. Project
proponents are already accustomed to complying with this requirement
and plan accordingly.
One commenter suggested establishing a grandfathering period for
surface coal mining activities authorized by the NWP 21 issued in 2007,
to allow permittees to complete their currently approved mitigation
plans without an added burden of updating permits. Another commenter
asked how project proponents are expected to transition from the
current 2007 NWP 21 to one of the selected options for reissuing NWP
21, if NWP 21 is reissued under either Option 2 or 3.
As discussed above, we have revised NWP 21 to continue the NWP
authorization for surface coal mining activities that were verified
under the 2007 NWP 21, to provide project proponents until March 18,
2017, to complete those activities under NWP 21. The acreage limits,
linear foot limits, and prohibition against discharges of dredged or
fill material into waters of the United States to construct valley
fills apply to those surface coal mining activities that were not
previously authorized by the 2007 NWP 21. We believe this approach for
transitioning to the new NWP 21 limits provides both protection to the
aquatic environment and is equitable to those members of the regulated
public who made substantial investments in reliance on a previously
verified NWP 21 authorization.
One commenter said that a pre-construction notification should be
required for all NWP 21 activities, so plans and permit conditions
could be reviewed to ensure that contaminated water being generated
during these activities is not later reaching open water and impacting
state-owned lands. One commenter expressed concern that historic
resources impacts are not considered under SMCRA in cases where the
program has been delegated to states.
To be authorized by this NWP, the project proponent must submit a
pre-construction notification, so that the district engineer can
evaluate the proposed activity and ensure that it qualifies for NWP
authorization. Activities authorized by this NWP must comply with
general condition 20, historic properties. If the proposed activity has
the potential to cause effects to historic properties, consultation
under Section 106 of the National Historic Preservation Act will be
conducted before the district engineer determines whether the activity
is authorized by NWP.
This NWP is reissued with the modifications discussed above.
NWP 22. Removal of Vessels. There were no changes proposed for this
NWP, and no comments were received. This NWP is reissued without
change.
NWP 23. Approved Categorical Exclusions. There were no changes
proposed for this NWP. One commenter requested that this NWP be limited
to federal applicants only. One commenter requested that the NWP be
modified to allow any agency with categorical exclusions to use this
NWP, not just those that have been approved by the Office of the Chief
of Engineers. One commenter recommended adding references to
requirements to comply with other applicable federal laws, such as
Section 106 of the National Historic Preservation Act. One commenter
stated that this NWP does not take into consideration the actions that
may impact Tribal treaty cultural or natural resources and requested
that notification be provided to affected tribes regardless if
considered a categorical exclusion.
This NWP applies only to those activities ``undertaken, assisted,
authorized, regulated, funded or financed, in whole or in part, by
another Federal agency or department.'' In certain instances, another
agency, such as a state department of transportation, may legally
assume the responsibility for categorical exclusion determinations for
a Federal entity. To ensure compliance with the requirements for
general permits, it is necessary for the Office of the Chief of
Engineers to review and approve agency categorical exclusions for use
with this NWP. In cases where the Federal agency is responsible for
compliance with the National Historic Preservation Act, the Endangered
Species Act, or other Federal laws, the Corps can accept their
compliance, as long as it adequately covers the activity authorized by
the NWP. The same principle applies for Tribal treaty natural or
cultural resources: If the agency issuing the categorical exclusion
that qualifies for NWP 23 authorization has sufficiently addressed the
Tribal treaty resources, then the Corps district can accept that as a
basis for compliance with general condition 17, tribal rights.
One commenter stated that this NWP authorizes activities that are
not similar in nature, and its use does not result in minimal adverse
effects on the aquatic environment. One commenter said that the
approved categorical exclusions need to be reassessed to ensure that
they still meet the minimal adverse environmental effects requirement
for general permit activities. One commenter said that pre-construction
notification should be required for all NWP 23 activities to ensure
adequate interagency coordination. Another commenter said that
reporting to the Corps should be required for any activity that affects
wetlands, encroaches on a regulatory floodway, affects the water level
of a 100-year flood event, or affects waters designated as critical
resource waters.
This NWP, along with the Regulatory Guidance Letter listing the
approved categorical exclusions, authorizes activities that are similar
in nature. The Corps believes that their eligibility for NEPA
compliance using a categorical exclusion is an appropriate basis of
``similarity'' for their authorization under this NWP. Based on the
NEPA requirements for use of categorical exclusions, the Corps has
determined that these activities will result in minimal individual and
cumulative adverse effects on the aquatic environment, and division
engineers have the authority to regionally condition this NWP to
restrict or prohibit its use if they determine that these activities
are resulting in more than minimal adverse environmental effects. We do
not agree that the approved categorical exclusions need to be re-
evaluated because of the length of time that has passed since they were
originally approved. Agencies have an on-going responsibility to review
their categorical exclusions and ensure that
[[Page 10214]]
the activities they authorize still qualify for this type of NEPA
compliance. Division engineers may also regionally condition this NWP
to require agency coordination for specific categorical exclusions that
have been approved for use with this NWP. We do not agree that
reporting or pre-construction notification should be required for all
activities that may affect wetlands. Activities that encroach upon
regulatory floodways or affect 100-year flood elevations are more
appropriately addressed through applicable Federal Emergency Management
Agency-approved state or local floodplain management requirements (see
general condition 10). General condition 22, designated critical
resource waters, requires pre-construction notification for any NWP 23
activity that is proposed in designated critical resource waters and
wetlands adjacent to those waters.
The proposed NWP is reissued with no changes.
NWP 24. Indian Tribe or State Administered Section 404 Programs.
There were no changes proposed for this NWP, and no comments were
received. This NWP is reissued without change.
NWP 25. Structural Discharges. We did not propose any changes to
this NWP. One commenter stated that concrete should be cured for a full
seven days before coming in contact with water. One commenter stated
structures constructed by such discharges on state-owned lands may
require a ``use authorization'' from the state.
Specific requirements for the curing of concrete are more
appropriately addressed as regional conditions or activity-specific
conditions added to an NWP 25 authorization. Project proponents are
responsible for obtaining any other federal, state, or local permits
that may be required for a particular activity.
The NWP is reissued without change.
NWP 27. Aquatic Habitat Restoration, Establishment, and Enhancement
Activities. We proposed to modify this NWP by adding ``the removal of
small dams'' to the list of examples of activities authorized by this
NWP. We also proposed to remove the phrase ``that has not been
abandoned'' that modifies the term ``prior converted cropland.'' We
proposed to change ``Notification'' provisions (1) and (2) so that
certain stream restoration, rehabilitation, and enhancement activities
would be subject to the reporting provision instead of requiring pre-
construction notification. Lastly, we proposed to modify
``Notification'' provision (1) by adding the U.S. Forest Service to the
list of Federal agencies that can develop stream or wetland
enhancement, restoration, or establishment agreements.
Many commenters supported the addition of removal of small dams to
the list of examples of activities authorized by this NWP. One
commenter said that if this NWP is modified to authorize the removal of
small dams, the NWP should also authorize discharges of dredged or fill
material to re-establish appropriate stream channel configurations,
with a \1/2\-acre limit for the stream channel reconfiguration. Some of
these commenters requested clarification as to what constitutes a
``small dam.'' One commenter agreed with the addition of removing small
dams but expressed concern regarding potential impacts to water quality
when a small dam is removed. One commenter recommended requiring
sediment testing before authorizing the removal of small dams.
After further consideration, we have determined that since the NWP
27 issued in 2007 authorized the installation, removal, and maintenance
of small water control structures (which clearly includes small dams),
it is not necessary to modify this NWP by adding the removal of small
dams to the list of examples of activities authorized by NWP 27, so we
have not made this proposed change. We agree that the NWP should also
authorize the restoration of the stream channel that were affected by
the construction of a small water control structure, if that water
control structure is to be removed. We do not agree that such
activities should be limited to \1/2\-acre, since this NWP authorizes
only aquatic resource restoration, establishment, and enhancement
activities that result in net increases in aquatic resource functions
and services. Aquatic resource habitat restoration and enhancement
activities involving the removal of small water control structures
should be designed and implemented to prevent or minimize the movement
of pollutants, including chemical compounds adsorbed to sediments that
have accumulated in the impoundment, from the impounded area once the
small water control structure is removed. Sediment testing may be
required on a case-by-case basis if there are substantive concerns
about potential contaminants.
Several commenters suggested that NWP 27 activities be subject to
strict technical guidelines and enforceable success criteria
commensurate with the scope of the activity being undertaken. A number
of commenters expressed concern that some of the activities authorized
by NWP 27 may result in a loss of waters rather than a net gain. One
commenter said that aquatic resource restoration, establishment, and
enhancement activities should have management plans that include goals
and objectives, baseline conditions, effective monitoring requirements,
and adaptive management plans. This commenter stated that without this
level of documentation, the effectiveness of any restoration,
establishment, or enhancement activity cannot be effectively evaluated
for success. One commenter recommended adding a requirement for
performance bonds to ensure that these activities are monitored and are
achieving their goals and objectives.
For those NWP 27 activities that require pre-construction
notification, the prospective permittee is required to submit a
complete pre-construction notification, with the information listed in
paragraph (b) of general condition 31. Activities conducted in
accordance with agreements with other Federal or state agencies should
be adequately documented to determine whether there will be net
increases in aquatic resource functions and services. When Corps
districts review the reports required for activities conducted under
agency agreements, they will assess whether those activities will
satisfy the terms and conditions of this NWP. If a particular activity
does not, then the district will notify the project proponent within 30
days of when the report was submitted to the district engineer. This
NWP requires authorized activities to result in net increases in
aquatic resource functions and services, which will generally add
acreage to the nation's aquatic habitat base. Although there may be
some NWP 27 activities that result in a decrease in aquatic resource
area to increase the functional capacity of those aquatic habitats,
such changes are acceptable because it is the ecosystem functions, and
the benefits people derive from those functions, that are important to
society. To provide better information to assess whether there will be
a net increase in aquatic resource functions and services, we have
added a provision to the reporting requirement that requires the
prospective permittee to provide information on the baseline ecological
conditions at the project site, such as a delineation of wetlands,
streams, and/or other aquatic habitats. Unless the activities
authorized by this NWP are to be used as compensatory mitigation for
Department of the Army permits (e.g., mitigation banks or in-lieu fee
projects), the project proponent is not required to submit mitigation
plans that comply with 33 CFR 332.4. The aquatic resource
[[Page 10215]]
restoration, establishment, or enhancement activity should be
sufficiently documented to help district engineers decide whether the
terms and conditions of this NWP are satisfied. Performance bonds or
other types of financial assurances may be required on a case-by-case
basis, if such assurances are necessary to provide funding to be used
for remediation or adaptive management.
One commenter requested that this NWP authorize the rehabilitation
or enhancement of tidal streams, stating that such activities would
result in net increases in the functions and services provided by
existing tidal aquatic resources and would not be contrary to the
provision that prohibits the relocation of tidal waters or the
conversion of tidal waters to other aquatic uses. One commenter pointed
out that NWP 27 covers a wide range of habitat restoration and
enhancement activities and there should be greater flexibility to allow
resource managers to plan for sea level rise. This commenter
recommended adding the beneficial use of dredged material as a thin
layer application to provide sediment to sediment starved marshes,
which may provide substrate to maintain those marshes as local sea
levels rise. One commenter suggested modifying this NWP by clarifying
that it authorizes activities that involve removing or modifying
existing drainage ditches and structures, to establish or re-establish
wetland or stream hydrology. Another commenter suggested adding the re-
establishment of submerged aquatic vegetation or emergent tidal
wetlands in areas where those plant communities previously existed. One
commenter supported the inclusion of mechanized land clearing to remove
non-native invasive species in this NWP.
We agree that the rehabilitation or enhancement of tidal streams
should be authorized by this NWP and have modified the first paragraph
to include this category of activities. The enhancement of tidal
wetlands may be accomplished by minor additions of sediment to
facilitate changes in tidal marsh elevation that may successfully track
sea level rise. We agree with providing more clarity concerning the
types of ditch manipulations that can be used for restoring wetland
hydrology and have removed the phrase ``and drainage ditches'' after
``the backfilling of artificial channels'' and replaced it with ``such
as drainage tiles, and the filling, blocking, or reshaping of drainage
ditches to restore wetland hydrology'' after ``the removal of existing
drainage structures.'' We also agree that the re-establishment of
submerged aquatic vegetation or emergent tidal wetlands should be
authorized by this NWP, as long as those shallow water habitat and
wetland types previously existed in the project area. Such re-
establishment activities would not constitute a conversion of tidal
waters to other aquatic uses; instead it would be a form of
rehabilitation of those habitat types. We have retained the provision
authorizing mechanized land clearing to remove non-native, invasive
plant species.
One commenter requested that the terms ``type'' and ``natural
wetland'' be defined in the paragraph that describes the activities
that are not authorized by this NWP. Another commenter supported the
provision that prohibits the conversion of natural wetlands to another
aquatic use and recommended that this prohibition also be applied to
the conversion of one type of aquatic habitat to another. One commenter
said that the NWP should clearly state that wetlands with documented
hydrologic alterations are not ``natural'' wetlands and that hydrologic
restoration of these wetlands is not to be considered a conversion of a
natural wetland to another ``type'' but instead it should be considered
as wetland rehabilitation. One commenter stated that a provision should
be added to this NWP to clarify that compensatory mitigation is not
required for activities authorized by this NWP since they must result
in net increases in aquatic resource functions and services.
As indicated by the parenthetical in the first sentence of the
referenced paragraph, the term ``type'' as used for the purposes of
this NWP refers to the general category of aquatic resource, such as
wetland or stream. We do not believe it would be appropriate to define
the term ``natural wetland'' except to contrast it with constructed
wetlands, such as those that are often used to treat wastewater.
District engineer have the discretion to determine what constitutes a
``natural wetland'' for the purposes of this NWP. We have added a
sentence to this paragraph to clarify that changes in wetland plant
communities that are caused by restoring wetland hydrology are to be
considered wetland rehabilitation activities that are authorized by
this NWP. Such wetland rehabilitation activities are not to be
considered conversions to another aquatic habitat type. We concur that
compensatory mitigation should not be required for NWP 27 activities
and have added a sentence to the text of the NWP to clearly state this
stipulation.
One commenter said that the NWP should prohibit the relocation of
naturally occurring non-tidal aquatic resources. One commenter
suggested changing the conversion provision to state that no wetlands
may be converted to open water impoundments rather than limiting the
prohibition to tidal wetlands. Another commenter stated that while they
understand the need for language to clarify that conversion from
``streams to wetlands'' is not desirable, there are some areas that
have been drained or ditched to create water flow away from
agricultural land, where there was previously a wetland. This commenter
asked whether reestablishing wetlands on the site could be authorized
by this NWP. The commenter said that the NWP is too restrictive and has
the potential to prohibit activities that may result in aquatic
resources that are more appropriately integrated into the landscape.
The relocation of non-tidal waters and wetlands on a project site,
including relocation activities that convert open water impoundments to
non-tidal wetlands and vice versa, can result in net increases in
aquatic resource functions and services when viewed in a watershed
context. Therefore, we do not agree that it is appropriate to exclude
such activity from coverage under this NWP if it meets all other
conditions, including a net increase in resource functions and
services. Ditches that were constructed in wetlands to drain those
wetlands are not considered streams for the purposes of this provision
of the NWP. As discussed earlier, this NWP authorizes the filling,
blocking, or reshaping of drainage ditches to restore wetland
hydrology.
One commenter asked if the removal of bulkheads, derelict
structures, and pilings, can be authorized by this NWP while another
suggested that the NWP allow for the temporary use of spat (e.g.,
larval oysters) collecting devices for the purpose of shellfish
restoration.
The removal of structures in navigable waters of the United States
is authorized by this NWP if it is a part of an aquatic habitat
restoration or enhancement activity. The temporary use of spat devices
for oyster habitat restoration is more appropriately authorized by NWP
4.
One commenter said that the provisions concerning shellfish seeding
are not clear and asked if the intent of the NWP is to authorize
shellfish seeding activities to enhance threatened shellfish
populations. This commenter also said that shellfish enhancement
activities should be limited to native species. One commenter
recommended authorizing shellfish restoration activities without
requiring pre-
[[Page 10216]]
construction notification when such activities are conducted or
approved by a government agency with resource management oversight. One
commenter requested we not include shellfish restoration activities in
this NWP, because these activities alter existing substrate and benthic
habitat and should be reviewed under the individual permit evaluation
process. This commenter also recommended imposing a one-acre limit for
the placement of scattered shell.
This NWP authorizes shellfish seeding activities, which may help
increase shellfish populations in specific waters. Division engineers
may regionally condition this NWP to limit shellfish seeding activities
to native species. Further, in response to a pre-construction
notification or report, a district engineer may exercise discretionary
authority and condition a specific NWP authorization to limit it to the
seeding of native shellfish species. We do not agree that there should
be no pre-construction notification requirement if there is oversight
by another government entity with the responsibility for managing
shellfish resources. Since these activities occur in navigable waters,
the Corps needs to review them on a case-by-case basis to ensure that
they result in minimal individual and cumulative adverse effects on the
aquatic environment and navigation and provide net increases in aquatic
resource functions and services. Shellfish restoration activities
should be authorized by this NWP because shellfish provide important
ecosystem services in aquatic ecosystems, including the improvement of
water quality. In most cases, the changes to benthic habitat are minor
when compared to the ecosystem services provided by the shellfish. We
also do not agree that there should be a one-acre limit for the
placement of shell to construct oyster habitat because larger oyster
habitat construction activities can still result in a net increase in
aquatic resource functions and services.
One commenter said that stream restoration projects should be
limited to 500 linear feet. One commenter stated that the construction
of small nesting islands and the alteration of rare or imperiled
wetlands should be not be authorized by this NWP. This commenter also
suggested acreage limits for categories of activities authorized by
this NWP, such as limiting excavation of wetlands to provide shallow
water habitat for wildlife to \1/2\-acre in altered wetlands;
excavating no more than 1\1/2\-acre of wetlands that have been
regularly farmed within the past five years or wetlands documented to
be dominated by invasive species; a 3-acre limit for excavation
activities; and limiting the placement of fill for the construction of
dikes, berms, or water control structures to two acres. This commenter
also recommended limiting impoundments to a maximum height of six feet,
with a maximum impounded area of no more than five acres during a
design flood. This commenter also said that enhancement of hydrology
should not be authorized unless a state agency concurs that the wetland
has been farmed within the last five years or is dominated by invasive
species.
Since this NWP authorizes only those aquatic habitat restoration,
establishment, and enhancement activities that result in net increases
in aquatic resource functions and services, we do not agree that the
recommended limits should be added to this NWP. Division engineers can
regionally condition this NWP to restrict or prohibit its use over
specific geographic areas or categories of waters. In response to a
pre-construction notification, district engineers can add conditions to
the NWP authorization to ensure that the NWP authorizes only those
activities that result in minimal adverse effects on the aquatic
environment.
Two commenters supported the addition of the United States Forest
Service as a federal agency that can develop agreements for the
restoration, enhancement, or establishment of streams and wetlands. One
commenter recommended removing the reversion provision of NWP 27.
Another commenter said that the reversion provision should be
eliminated or significantly modified because it is inconsistent with
other NWPs. Two commenters stated that the reversion of wetlands should
not be authorized if the wetlands were being used for compensatory
mitigation. One commenter asked how many acres of wetlands could be
reverted under this NWP. One commenter asked whether a ``USDA Technical
Service Provider'' includes county soil and water conservation
districts.
The reversion provision is necessary for those aquatic resource
restoration, enhancement, or establishment activities that are done in
accordance with binding agreements, voluntary actions, or permits,
where those agreements, actions, or permits allow the project proponent
to revert the affected lands to its prior condition. If the reversion
provision is removed, it would create a disincentive to do certain
aquatic restoration, enhancement, or establishment activities that
could provide some aquatic resource functions and services for a
substantial period of time and benefit the watershed. Nationwide permit
27 differs from the other NWPs because of the types of activities it
authorizes. As stated in the Note at the end of NWP 27, reversion of an
area used as a compensatory mitigation project is not authorized by
this NWP. We do not track the acreage of wetland or stream restoration
and enhancement activities, or of wetland establishment activities,
that were authorized by NWP 27 and might be eligible for reversion.
There is no limit on the amount of wetlands that can be reverted under
a single authorization, provided all conditions of the NWP are met.
County soil and water conservation districts can register with the U.S.
Department of Agriculture to be a technical service provider.
One commenter said that pre-construction notifications should
include photographs, a description of pre-project site conditions, and
a discussion of general aquatic resource functions and services
anticipated to be provided by the activity. Another commenter stated
that pre-construction notification should be required for all
activities.
Paragraph (b) of general condition 31, pre-construction
notification, requires prospective permittees to submit documentation
that describes the proposed activity, including the anticipated loss of
waters of the United States and, if appropriate, sketches that help
clarify the project. The pre-construction notification also must
include a delineation of wetlands, other special aquatic sites, and
other aquatic habitats. We do not agree that pre-construction
notification should be required for all activities. The reporting
requirements for those activities that do not require pre-construction
notification provide sufficient opportunity for district engineers to
notify a project proponent if the proposed work does not comply with
the terms and conditions of the NWP. We have modified the ``Reporting''
provision of this NWP to require the permittee to submit information on
the baseline ecological conditions at the project site, such as a
delineation of wetlands, streams, and/or other aquatic habitats. We
have also changed the ``Notification'' provision of this NWP by
replacing the phrase ``the activity'' with ``any activity'' to clarify
that any activity that does not require reporting requires a pre-
construction notification. The last sentence of this NWP has been
changed to clarify that appropriate documentation concerning the
agreement, voluntary action, or Surface Mining Control and Reclamation
Act
[[Page 10217]]
permit is to be provided to the district engineer to fulfill the
reporting requirement.
One commenter said the NWP should require the use of best
management practices to avoid sediment loading of waters especially
when mechanized land clearing or work is conducted in waters of the
United States. The commenter stated that best management practices,
such as floating barriers, should also be used in upland areas to
protect downstream water quality. One commenter stated that Tribes
should be notified to ensure that NWP 27 activities avoid impacts to
tribal treaty natural resources and cultural resources.
General condition 12, soil erosion and sediment controls, requires
permittees to implement appropriate soil and erosion and sediment
controls during the work. In response to a pre-construction
notification, district engineers can add conditions to the NWP
authorization to require more specific sediment and erosion controls.
Division engineers can impose regional condition on this NWP to require
notification of the appropriate Tribe or Tribes if a proposed activity
might affect tribal treaty natural resources and cultural resources.
General condition 17, Tribal rights, requires that no NWP activity or
its operation impair reserved treaty rights, including treaty fishing
and hunting rights. Cultural resources are protected through the
requirements of general condition 20, historic properties, and general
condition 21, discovery of previously unknown remains and artifacts.
This NWP is reissued with the modifications discussed above.
NWP 28. Modifications of Existing Marinas. There were no changes
proposed for this NWP. Two commenters recommended adding a condition to
ensure the modification does not encroach upon additional waters. One
commenter suggested adding a condition to require a minimum maneuvering
distance for an outside slip to the boundary of the marina's riparian
interest area. One commenter stated that modifications for marinas on
state-owned aquatic lands should require pre-construction notification.
This NWP clearly states that it does not authorize expansions of
existing marinas. Since the NWP does not authorize expansions of
existing marinas, it is not necessary to add a condition to provide a
minimum maneuvering distance. Concerns about modifications to marinas
constructed on state-owned submerged lands are more appropriately
addressed through a state authorization process.
This NWP is reissued without change.
NWP 29. Residential Developments. We proposed to modify this NWP by
changing the waiver provision for activities resulting in the loss of
greater than 300 linear feet of intermittent and ephemeral stream bed,
to clarify that the district engineer will only issue the waiver after
making a project-specific written determination that the activity will
result in minimal adverse effects.
One commenter said that this NWP should not be reissued. One
commenter suggested revoking this NWP because of the large scale of
these projects and associated impacts to waters and said that
individual permits should be required for these activities. Two
commenters stated that the use of this NWP permit to authorize \1/2\-
acre losses of waters of the United States would result in more than
minimal adverse effects on an individual and cumulative basis. Two
commenters said that this NWP should not authorize residential
subdivisions, and should be limited to single family homes. Four
commenters recommended decreasing the acreage limit for losses of
waters of the United States to 1/4-acre. Two commenters suggested
increasing the acreage limit to 1 acre. One commenter requested
clarification on whether the acreage limits are applied cumulatively
when there is any subsequent expansion of a residential development.
We do not agree that this NWP should not be reissued or limited to
single family homes. The construction of residential developments,
including multiple unit residential developments, may have minimal
individual and cumulative adverse effects on the aquatic environment,
and is appropriate for NWP authorization if it meets the conditions of
this NWP. Provided the limits are met, the effects to waters of the
United States are similar whether single family homes or groups of
single family homes are constructed as a result of using this NWP to
authorize discharges of dredged or fill material into waters of the
United States. The \1/2\-acre limit, as well as the other terms and
conditions of this NWP, is consistent with longstanding limits on this
and other NWPs, and is appropriate for ensuring that this NWP
authorizes only those activities with minimal adverse effects on the
aquatic environment. Division engineers can regionally condition this
NWP to reduce the acreage limit or restrict or prohibit its use in
specific regions or waters. In response to a pre-construction
notification, district engineers may exercise discretionary authority
to add conditions to the NWP authorization or require an individual
permit. The \1/2\-acre and 300 linear foot limits apply to single and
complete projects. If a project proponent requests NWP authorization to
conduct additional discharges of dredged or fill material into waters
of the United States and modify a previously authorized single and
complete residential development project, both the previously
authorized losses and the additional losses are applied to the \1/2\-
acre and/or 300 linear foot limits. If the modification to the
residential development is a separate single and complete project with
independent utility from the previously authorized residential
development, then a separate NWP authorization may be issued. The
``Definitions'' section includes further clarification regarding single
and complete projects.
Several commenters objected to providing district engineers with
the authority to waive the 300 linear foot limit for the loss of
intermittent and ephemeral stream bed on a case-by-case basis after
reviewing a pre-construction notification and determining that the
proposed activity results in minimal adverse environmental effects. One
commenter said that the waiver provision would result in more than
minimal cumulative adverse effects on a watershed basis. Another
commenter stated that use of the waiver would authorize the losses of
large amounts of headwater streams. A few commenters suggested the
waiver provision should be removed from this NWP. Three commenters
recommended increasing the linear foot limit for the loss of stream bed
to 500 feet. Two commenters supported the clarification that a finding
of minimal adverse environmental effects would be required to issue a
waiver.
Responses to comments regarding the 300 linear foot limit for
losses of stream bed and the waiver provision for the loss of greater
than 300 linear feet of intermittent and ephemeral stream beds are
discussed in a previous section of this preamble. We are retaining the
300 linear foot limit for stream bed impacts, as well as the ability
for district engineers to provide written waivers of the 300 linear
foot limit for losses of intermittent and ephemeral stream beds.
One commenter recommended that compensatory mitigation be required
for all unavoidable impacts to wetlands authorized under this NWP.
Several commenters said that the NWP should require permittees to
minimize on-and off-site impacts and avoid flooding, because the
general conditions do not adequately address flooding or water quality
impacts. Several commenters said that this NWP should not authorize
residential subdivisions unless the
[[Page 10218]]
project proponents can demonstrate those subdivisions will not cause an
increased flood hazard on other properties.
We do not agree that it is necessary to require compensatory
mitigation for all activities authorized by this NWP to satisfy the
minimal adverse environmental effects requirement for a general permit.
For many small losses of waters of the United States authorized by this
NWP, it is not practicable to require compensatory mitigation to offset
those losses, especially in areas where there are no mitigation bank or
in-lieu fee program credits available. The requirements for permittee-
responsible mitigation in 33 CFR 332.1 through 332.7 impose substantial
documentation and planning requirements that affect the practicability
of providing ecologically successful permittee-responsible mitigation,
especially for small losses of waters of the United States.
Compensatory mitigation for NWP activities is only necessary in cases
where the district engineer makes a project-specific determination that
compensatory mitigation is needed to ensure that the activity results
in minimal individual and cumulative adverse effects on the aquatic
environment (see 33 CFR 330.1(e)(3)). General condition 23, mitigation,
requires permittees to avoid and minimize adverse effects to waters of
the United States on the project site, to the maximum extent
practicable. Concerns about adverse effects on floodplains and
floodways are more appropriately addressed by the state and local
agencies that have the primary responsibility for floodplain
management. General condition 10, fills within 100-year floodplains,
requires permittees to comply with applicable Federal Emergency
Management Agency-approved state or local floodplain management
requirements. Most floodplains are uplands, not waters of the United
States, and the Clean Water Act Section 404 permit program cannot be
used to manage floodplain impacts, except for discharges of dredged or
fill material or other pollutants into wetlands and other
jurisdictional waters that are located in floodplains. Residential
developments, whether they are single units or multiple-unit
subdivisions, must comply with all terms and conditions of this NWP,
including the requirement that they result in minimal adverse
environmental effects.
One commenter said that this NWP should not authorize activities
that result in adverse impacts to state or federally listed threatened
or endangered species or their habitats, or where there are rare or
imperiled habitat types. One stated that this NWP should not authorize
discharges of dredged or fill material below the ordinary high water
mark of any water of the United States or areas of fish habitat. One
commenter said that attendant features should be limited to a garage, a
driveway no more than 16 feet wide, parking or vehicle turn areas,
lawns that are no more than 15 feet from the building pad, septic
fields, utilities, deck foundations, and access paths. One commenter
suggested modifying this NWP to require culverts and other measures to
maintain pre-construction drainage patterns on the site. One commenter
said this NWP should require on-site sewage treatment systems.
Compliance with the federal Endangered Species Act is addressed by
general condition 18. Compliance with state or local threatened or
endangered species laws or ordinances, or state or local requirements
to avoid rare or imperiled habitats, is the responsibility of the
permittee. Since all activities authorized by this NWP require pre-
construction notification, district engineers will review proposed
activities that involve discharging dredged or fill material into open
waters, including fish habitat, to ensure that those activities result
in minimal adverse effects on the aquatic environment. The text of the
NWP provides examples of the types of attendant features that may be
authorized. Further restrictions on those attendant features may be
provided through regional conditions imposed by Division engineers or
activity-specific conditions added to an NWP 29 authorization by a
District engineer. General condition 9, management of water flows,
requires permittees to maintain, to the maximum extent practicable, the
pre-construction course, condition, capacity, and location of open
waters, such as streams, except under certain situations identified in
the text of the general condition. Sewage treatment system requirements
for residential developments are the primary responsibility of state or
local governments.
One commenter requested clarification on whether this NWP can be
used to authorize phased development projects. Several commenters
suggested limiting this NWP to a single use.
General condition 15, single and complete project, states that the
same NWP can only be used once for the same single and complete
project. If a particular phase of a phased development project is a
single and complete project with independent utility, a separate NWP 29
authorization can be used to authorize that single and complete non-
linear project.
Two commenters said that the NWP should require vegetated buffers.
One commenter stated that district engineers have too much discretion
regarding buffers and the general condition restricts buffers so that
they are not as effective as they could be.
Compensatory mitigation for activities authorized by NWP 29 may be
provided through the establishment and maintenance of riparian areas
next to open waters. Paragraph (f) of general condition 23 addresses
the use of riparian areas as compensatory mitigation, with recommended
widths. The recommended widths are based in part on the minimum width
necessary for riparian areas to help protect or improve water quality,
and in part on the principle that the amount of compensatory mitigation
must be roughly proportional to the permitted impacts (see 33 CFR
320.4(r)(2)). Since the NWP has an acreage limit of \1/2\-acre, any
required compensatory mitigation must be roughly proportional to the
authorized loss of waters of the United States.
This NWP is reissued as proposed.
NWP 30. Moist Soil Management for Wildlife. No changes were
proposed for this NWP and no comments were received. This NWP is
reissued without change.
NWP 31. Maintenance of Existing Flood Control Facilities. We
proposed to modify this NWP to authorize, in cases where a section 404
and/or section 10 permit would be required, the removal of vegetation
from levees associated with a flood control project.
Several commenters supported the proposed modification and said
that vegetation removal is a critical component of the maintenance of a
flood control project to ensure continued effectiveness and integrity
of levees and other flood control facilities. Two commenters objected
to the proposed modification. One commenter opposed the removal of
vegetation from flood control facilities, stating the vegetation has
ecological importance. One commenter said that vegetation removal is
not regulated by the Corps. One commenter stated that if the plant
species proposed to be removed have cultural and medicinal Native
American traditional uses, consultation with the Tribe or another type
of permit should be required for the activity.
We have retained the proposed language in this NWP, to authorize
the removal of vegetation from a levee,
[[Page 10219]]
when that activity involves a discharge of dredged or fill material
into waters of the United States or is considered to be work in
navigable waters of the United States for the purposes of Section 10 of
the Rivers and Harbors Act of 1899. We agree that vegetation removal
that does not involve such a discharge does not require a DA permit.
Division engineers can regionally condition this NWP to identify plant
species that have cultural and medicinal uses by Tribes, and to require
government-to-government consultation to address impacts to such
species. General condition 17, Tribal rights, protects reserved treaty
rights, including reserved water rights and treaty fishing and hunting
rights. Natural or cultural tribal trust resource concerns can still be
addressed through the NWP decisionmaking process, and would not
necessarily result in requiring an individual permit.
Several commenters said that vegetation may strengthen the
integrity of levees and stated that individual permits should be
required for vegetation removal. One commenter stated that vegetation
on levees should be allowed or retained as part of levee management and
that the vegetation should be removed only if specific levee
maintenance or safety concerns are identified. One commenter stated
that not allowing flood control districts to remove vegetation from
levees would put them into non-compliance with their permits and with
other state and local approvals. One commenter said that the removal of
vegetation from a levee should only be authorized after Endangered
Species Act consultation has been completed.
The decision on whether vegetation needs to be removed from a levee
to maintain its functional and structural integrity is more
appropriately made by those entities that are responsible for ensuring
the integrity and functional effectiveness of that levee. That decision
is not the responsibility of the Corps Regulatory Program or its staff.
The NWP is only a means to provide Department of the Army authorization
for such activities, if a section 404 and/or section 10 permit is
required. If the vegetation removal may affect a listed species under
the Endangered Species Act, and a Department of the Army permit is
required, the Corps will conduct section 7 consultation in accordance
with general condition 18, endangered species, unless another Federal
agency has already fulfilled the section 7 requirements, or the project
proponent has complied with the Endangered Species Act and received an
Endangered Species Act Section 10 permit.
Several commenters said that there should be an acreage limit for
vegetation removal. Another commenter recommended imposing a linear
foot limit on vegetation removal. One commenter recommended revoking
this NWP in California.
Since this NWP authorizes maintenance activities, we do not believe
there should be an acreage or linear foot limit on vegetation removal.
Division engineers may also add regional conditions to this NWP to
impose acreage or linear foot limits on vegetation removal.
One commenter stated that many NWP authorizations are related to
the maintenance baseline and the NWP should provide more details about
the maintenance baseline approval process. This commenter suggested
that the NWP specify: the deadline for completion, the responsible
party, the regulating entity that approves the maintenance baseline,
etc. One commenter requested clarification on the timeframe for
approval of the maintenance baseline.
The current terms and conditions of the NWP provide sufficient
details on what is needed to establish the maintenance baseline.
Approval of the maintenance baseline is to be made within the 45-day
review period, which begins once a complete pre-construction
notification is received by the appropriate Corps district office. The
pre-construction notification must include a description of the
maintenance baseline.
Many commenters expressed concern about the mitigation provision of
this NWP, especially the one-time limit for mitigation per facility
regardless of the number of times maintenance occurs. These commenters
said that limiting compensatory mitigation may result in more than
minimal adverse environmental effects, including adverse impacts to
floodplains and increased flood risk. These commenters recommended
requiring mitigation for each maintenance activity. One commenter
stated that vegetation removal should not be authorized because
effective compensatory mitigation cannot be provided. One commenter
said that certain riparian functions, such as shading, and losses of
aesthetic values, cannot be provided through off-site mitigation.
We do not agree that compensatory mitigation should be required for
each maintenance activity. On-going maintenance of flood control
facilities is necessary to ensure that those projects fulfill their
intended purposes. Any compensatory mitigation that was required when
the maintenance baseline was established is sufficient to offset losses
of aquatic resource functions. If maintenance is done in a timely
manner, there is likely to be little in terms of increases in aquatic
resource functions between maintenance activities. The purpose of
maintaining these flood control facilities is to reduce flood risk.
Riparian functions that increased between maintenance activities do not
need to be replaced by imposing compensatory mitigation requirements on
this NWP.
Several commenters said that the use of this NWP results in more
than minimal individual and cumulative impacts, and may also inhibit
comprehensive basin-wide flood risk management planning and restoration
approaches.
We do not agree that these maintenance activities cause more than
minimal adverse effects on the aquatic environment, on an individual or
cumulative basis. This NWP is intended as a tool to support appropriate
flood management activities, including comprehensive flood risk
management planning and restoration processes, where maintenance of
existing flood control structures is required.
One commenter recommended modifying the pre-construction
notification provision to require a topographic map identifying the
disposal site. One commenter said that the 1996 Water Resources
Development Act allows for regional variations in vegetation management
on levees.
The NWP already requires the prospective permittee to submit
information concerning the location of the dredged material disposal
site. There are a variety of maps that could be used to provide that
information, and we do not believe it should be restricted to
topographic maps. We have modified this NWP to state that all dredged
material must be placed in an area that has no waters of the United
States or in a separately authorized disposal site, since the disposal
of dredged material into non-jurisdictional waters and wetlands, as
well as uplands, does not require DA authorization. As stated above,
the decision on whether to remove vegetation is the responsibility of
the entity charged with managing and maintaining the flood control
facility.
This NWP is reissued with the modifications discussed above.
NWP 32. Completed Enforcement Actions. There were no changes
proposed for this NWP. One commenter recommended adding a condition to
the NWP requiring that the state be a party to any lawsuit, or have an
opportunity to review the consent or settlement agreement. Another
commenter requested coordination with any
[[Page 10220]]
affected Tribes prior to administering an enforcement action to ensure
that Tribal treaty resources are protected.
This NWP only provides Federal authorization under Section 10 of
the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water
Act, and it is not appropriate to modify this NWP to require state
involvement in these actions. States are often involved as co-
regulators in enforcement activities, under various authorities, and
this NWP in no way undercuts those authorities. General condition 17,
tribal rights, states that no activity or its operation may impair
reserved tribal rights.
This NWP is reissued as proposed.
NWP 33. Temporary Construction, Access, and Dewatering. We did not
propose any changes to this NWP. Several commenters recommended that
the Corps define the term ``temporary.'' One commenter said that
``temporary'' should be less than two years, another stated that one
year should be the limit, and a third commenter suggested 90 days as
the limit for what constitutes a temporary structure or fill. Several
commenters stated that the NWP should require a specific timeframe and
deadline for completion of revegetation activities. Other commenters
said that any revegetation should use only native plant species
associated with the general habitat type that had existed prior to
construction.
The term ``temporary'' should be determined by district engineers
on a case-by-case basis, after considering factors such as the type of
project, the waters affected by the activity, the construction
techniques and equipment used, etc. In response to a pre-construction
notification, district engineers can add conditions to the NWP
authorization to impose specific time frames for revegetating affected
areas. Activity-specific conditions may also be added to the NWP
authorization to specify the plant species to be used at the site.
One commenter asked why the NWP would state that a separate section
10 permit is required if a structure is left in place in navigable
waters of the United States after completion of construction,
especially if the waterbody is not a section 10 water. This commenter
wondered how a ``structure'' constructed in a non-Section 10 water
could be left in place and still qualify as a temporary structure.
In some cases, it may be more environmentally beneficial to leave
part of a structure in place in navigable waters of the United States,
when complete removal of the structure is expected to result in
substantial adverse environmental effects. For example, a structure may
be cut near the ocean bottom, but part of the structure and its
foundation left in place, because removing the entire structure and its
foundation would result in substantial disturbance of the ocean bottom.
Leaving those portions of the original structure and foundation in
place requires a permit under Section 10 of the Rivers and Harbors Act
of 1899 because it constitutes an obstruction that may alter the
course, condition, or capacity of navigable waters of the United
States. A structure left in place in a waterbody subject only to
section 404 jurisdiction does not require section 10 authorization.
Such a structure would not require a section 404 permit unless it meets
the definition of fill material (see 33 CFR 323.3(c)).
One commenter asked why NWP 33 activities require pre-construction
notification for temporary structures, work, and discharges while these
types of activities may be authorized under NWPs 3, 12, 13, and 14
without a pre-construction notification.
While temporary structures, work, and fills are authorized by NWPs
3, 12, 13, and 14, those NWPs have terms and conditions to help ensure
that those activities result in minimal adverse effects on the aquatic
environment. Since NWP 33 can be used to authorize temporary
structures, work, and discharges done in association with a wide
variety of other categories of activities, that uncertainty makes it
necessary to require pre-construction notification for all activities
authorized by NWP 33. Such a requirement allows the Corps to review the
temporary and permanent impacts that are likely to occur as a result of
the overall activity.
One commenter stated that the NWP should never authorize temporary
fills that impact more than 1,000 square feet or discharge more than 25
cubic yards into waters of the U.S., and temporary structures or
construction mats shall not impact more than \1/10\-acre. One commenter
stated that the NWP should require that geotextile fabric be installed
prior to placement of fill material, and two commenters suggested that
temporary culverts and bridges in streams should be required to match
the bankfull width and stream slope. Another commenter stated that all
slurry resulting from dewatering operation should be discharged through
a filter bag or pumped to a sump located away from wetlands and surface
waters and allowed to filter through natural upland vegetation, gravel
filters, or other engineered devices for a sufficient distance and/or
period of time necessary to remove sediment or suspended particles. One
commenter stated that cofferdams should be required to be maintained in
good working order throughout the duration of the project.
We do not agree that there should be acreage, linear foot, or cubic
yard limits on this NWP since it authorizes temporary structures, work,
or discharges, and all activities require pre-construction
notification. In response to a pre-construction notification, district
engineers can add activity-specific conditions to the NWP authorization
to impose limits or require specific best management practices or
specific construction techniques to minimize adverse effects to the
aquatic environment where necessary.
We have modified this NWP to state that temporary fill must be
entirely removed to an area that has no waters of the United States,
since the placement of fill material into non-jurisdictional waters and
wetlands, as well as uplands, does not require DA authorization.
The NWP is reissued with the modification discussed above.
NWP 34. Cranberry Production Activities. We did not propose any
changes to the NWP. One commenter said that this NWP should not
authorize losses of wetland functions. Two commenters expressed concern
that the 10-acre limit would allow significant losses of wetland
acreage and functions and values, if the 10-acre limit is applied only
to the five year period the NWP is in effect. These commenters proposed
making the 10-acre limit apply to future activities. One commenter
suggested limiting the NWP authorization to a single cranberry
production unit. One commenter said that this NWP should not be
reissued.
This NWP does not authorize discharges of dredged or fill material
that would result in a net loss of waters of the United States. While
there would be some loss of wetland function as wetlands are converted
for cranberry production, the NWP requires wetland acreage to be
maintained. There would be no loss of wetland acreage over time due to
future activities since the NWP does not authorize discharges of
dredged or fill material that would result in permanent losses of
wetland acres. This NWP applies to single and complete cranberry
production activities, which would be identified by district engineers
during the review of pre-construction notifications.
This NWP is reissued without change.
NWP 35. Maintenance Dredging of Existing Basins. There were no
changes proposed for this NWP. Two commenters recommended adding limits
to this NWP. Two commenters
[[Page 10221]]
said this NWP should not be used in areas with suspected sediment
contamination, especially in areas where there might be contamination
from fuel. Another commenter stated the applicant should demonstrate
that the sediment is not contaminated. One commenter asked that the
term ``upland'' be clarified to state that it means land located above
the ordinary high water mark. One commenter stated that this NWP would
have greater utility if it authorized beneficial use of dredged
material, such as wetland restoration, enhancement, or establishment
activities.
Since this NWP authorizes only maintenance dredging activities in
existing marina basins, we do not believe it is necessary to add an
acreage limit or other type of quantitative limit. Division engineers
can regionally condition this NWP to require notification to the
district engineer. This NWP is limited to maintenance dredging in
marina basins, access channels to marinas, and boat slips, which are
likely to have some degree of contaminated sediment in the substrate
because of past and present boat use, especially in larger marinas.
Removal of such contaminated sediments, and complying with the
requirement in the NWP to deposit the dredged material in an upland
site, will help ensure the activity results in minimal adverse effects
on the aquatic environment. Defining the term ``upland'' to mean lands
located above an ordinary high water mark would be incorrect. There may
be wetlands landward of the ordinary high water mark. We have modified
this NWP to state that dredged material must be placed in an area that
has no waters of the United States, since the disposal of dredged
material into non-jurisdictional waters and wetlands, as well as
uplands, does not require DA authorization. The district engineer may
issue a separate Department of the Army authorization to a project
proponent who wants to use the dredged material to restore, enhance, or
establish wetlands.
One commenter stated that precautions should be taken to ensure
that dredging equipment does not entrain or kill any Federally-listed
species and recommend that preemptive trawling around the dredge head
be conducted to capture or relocate state or federally listed species.
General condition 18 addresses compliance with the Endangered
Species Act, and section 7 consultation is required for any activity
that may affect listed species or is located in designated critical
habitat.
This NWP is reissued with the modification discussed above.
NWP 36. Boat Ramps. We did not propose any changes to this NWP. One
commenter said that boat ramps should not be authorized by NWPs because
they cause significant environmental impacts, including impacts to
Tribal treaty fishing activities and access. One commenter stated that
this NWP should be limited to individual riparian lot owners and not
authorize commercial boat ramps. One commenter said that the NWP should
require notification to the state agency responsible for managing
state-owned submerged lands.
The terms and conditions of this NWP (specifically the limits on
fill volume and ramp width) will ensure that the NWP authorizes only
those activities that result in minimal adverse effects on the aquatic
environment. Division engineers may regionally condition this NWP to
restrict or prohibit its use in specific waters or geographic areas if
they have concerns that more than minimal individual and cumulative
adverse environmental effects may occur. In response to a pre-
construction notification, district engineer may add activity-specific
conditions to the NWP authorization to satisfy the minimal adverse
environmental effects requirement. We do not agree that this NWP should
be limited to private land owners. Commercial boat ramps that comply
with the terms and conditions of this NWP will also result in minimal
adverse environmental effects. The potential for adverse effects is
based on the footprint of the ramp, which is limited by the conditions
of this NWP, not its ownership. State agencies responsible for managing
submerged lands may develop their own procedures for regulating and
authorizing the construction of boat ramps on submerged lands. The
Corps has neither the authority nor the resources to enforce any state
requirements with respect to such lands.
Two commenters recommended reducing the pre-construction
notification thresholds for this NWP. One commenter suggested limiting
discharges of dredged or fill material to 25 cubic yards, with a
maximum boat ramp width of 12 feet. Another commenter said that the
quantitative limits for this NWP should not be waived. One commenter
stated that the current 50 cubic yard limit is too small and should be
increased to authorize larger boat ramps.
The pre-construction notification thresholds are sufficient for
ensuring that this NWP authorizes activities with minimal individual
and cumulative adverse effects on the aquatic environment. We have
retained the provision authorizing district engineers to issue written
waivers to the 50 cubic yard and/or 20 foot width limits, if a proposed
activity is determined to result in minimal adverse environmental
effects. The waiver provision may be used to authorize larger boat
ramps, as long as they are determined by the district engineer to
result in minimal adverse environmental effects.
One commenter asked for clarification on what is meant by placement
in the upland. One commenter said that these activities may affect
historic properties and the activity should not be authorized unless
the state concurs that there are no documented resources within the
permit area.
We have modified paragraph (d) to clarify that all excavated
material must be removed to an area that has no waters of the United
States, because some wetlands and waters are not subject to Clean Water
Act jurisdiction and section 404 permits are not required to discharge
dredged or fill material into those non-jurisdictional wetlands and
waters. A separate Department of the Army authorization is required if
the project proponent wants to deposit the excavated material into
waters of the United States. Activities authorized by this NWP must
comply with general condition 20, historic properties, as well as
general condition 21, discovery of previously unknown remains and
artifacts. District engineers will conduct National Historic
Preservation Act Section 106 consultation if they determine the
proposed activity has the potential to cause effects to any historic
property.
This NWP is reissued as proposed.
NWP 37. Emergency Watershed Protection and Rehabilitation. No
changes were proposed for this NWP. Two commenters stated that in their
region, flood control activities including those authorized by this
NWP, are important and suggested reducing the 45-day waiting period for
pre-construction notifications to 21 days. Two commenters expressed
support for allowing district engineers to waive the pre-construction
notification requirements in cases where there is an unacceptable
hazard to life or a significant loss of property or economic hardship
will occur. One commenter said that although this NWP is intended to
authorize watershed protection and rehabilitation, these activities may
result in a net loss of waters and appropriate mitigation should be
required.
We do not believe it would be appropriate to reduce the pre-
construction notification review period
[[Page 10222]]
for this NWP from 45 days to 21 days. The NWP provides flexibility for
the emergency watershed protection and rehabilitation activities to
proceed immediately if there is an unacceptable hazard to life or a
significant loss of property or economic hardship will occur. The NWP
does not allow the district engineer to waive the pre-construction
notification requirement in cases where there would be unacceptable
hazards to life or significant losses of property or economic
hardships. If a project proponent wants to use NWP 37 to authorize an
emergency watershed protection and rehabilitation activity, pre-
construction notification is required. This is a minimally burdensome
requirement that can be complied with quickly which allows the district
engineer to verify that there is a genuine emergency. In addition, in
response to a pre-construction notification, the district engineer may
condition the NWP authorization to require compensatory mitigation to
offset losses of aquatic resources and ensure that the adverse effects
on the aquatic environment are minimal (see 33 CFR 330.1(e)(3) and
general condition 23, mitigation).
The NWP is reissued without change.
NWP 38. Cleanup of Hazardous and Toxic Waste. We did not propose
any changes for this NWP. One commenter stated the NWP should be
revoked because hazardous waste cleanup from aquatic areas has the
potential to cause significant adverse environment effects during and
after the cleanup activities. This commenter said that these activities
require site-specific review and should not be authorized by NWP.
Another commenter recommended adding a condition to the NWP to require
minimization, to the maximum extent possible, of impacts to waters and
wetlands, and require restoration of the affected areas.
The cleanup of hazardous and toxic wastes, if conducted properly,
will improve the aquatic environment by removing harmful chemicals and
other substances that are likely to degrade the quality of wetlands,
streams, and other aquatic resources, as well as the functions they
provide. This NWP requires pre-construction notification, which will
provide the district engineer the opportunity to review the proposed
activity, including available site-specific information, to determine
if that activity qualifies for NWP authorization. This NWP authorizes
cleanup activities conducted, ordered, or sponsored by other government
agencies, which have also reviewed those activities. In some cases
these activities need to be commenced quickly and it could cause
additional harm to the aquatic environment if they had to wait for an
individual permit to be issued. The district engineer may also add
activity-specific conditions to the NWP authorization to require
compensatory mitigation, including restoration or rehabilitation of
affected aquatic resources (see 33 CFR 330.1(e)(3) and general
condition 23, mitigation) to satisfy the minimal adverse environmental
effects requirement for general permits.
This NWP is reissued without change.
NWP 39. Commercial and Institutional Developments. We proposed to
modify this NWP by changing the waiver provision for activities
resulting in the loss of greater than 300 linear feet of intermittent
and ephemeral stream bed, to clarify that the district engineer will
only issue the waiver after making a project-specific written
determination that the activity will result in minimal adverse effects.
Two commenters expressed support for the proposed modification. One
commenter said that intermittent streams should be removed from the
waiver provision so that the 300 linear foot limit could be waived only
for losses of ephemeral streams. One commenter recommended removing the
waiver provision.
We have retained the provision allowing the 300 linear foot limit
to be waived for losses of intermittent stream bed, since such
activities may, in some cases, result in minimal adverse effects on the
aquatic environment. General comments concerning the 300 linear foot
limit to the loss of stream bed are discussed in a separate section of
the preamble.
One commenter urged the elimination of the pre-construction
notification because that requirement results in delays and increases
in cost. One commenter recommended conducting a natural heritage
database search if a waiver determination is made that the activity
will result in minimal adverse effects.
The pre-construction notification requirement is necessary so that
all of these activities are reviewed by district engineers to ensure
that those activities result in minimal adverse effects on the aquatic
environment. District engineers may add conditions to the NWP
authorization to require compensatory mitigation or other measures to
comply with the minimal adverse environmental effects requirement
established for general permits. District engineers may consider
information from state natural heritage databases where appropriate
when evaluating a pre-construction notification involving a proposed
waiver of the 300 linear foot limit.
Two commenters suggested increasing the acreage limit from \1/2\ to
one acre. Another said that acreage limits should be established on a
regional or watershed basis, instead of a single national acreage
limit. Two commenters suggested increasing the linear foot limit to 500
feet. One commenter stated that the NWP should not authorize activities
that are not water dependent.
We believe that both the \1/2\-acre limit and the 300 linear foot
limit are necessary to ensure that this NWP authorizes activities that
result only in minimal individual and cumulative adverse effects on the
aquatic environment. Division engineers can regionally condition this
NWP to further ensure only minimal adverse effects to the aquatic
environment occur in a particular area or region, based on region
specific conditions. District engineers can also add specific
conditions to an NWP authorization to ensure minimal individual or
cumulative adverse effects. The statutory basis for authorizing
activities by general permits is that they have minimal adverse
effects, individually and cumulatively, not that they be water
dependent.
One commenter said that commercial and institutional developments
are typically phased developments, are larger in scale than other
projects, and should not be authorized by NWP. One commenter said that
this NWP should not be reissued because these activities result in more
than minimal cumulative adverse effects to wetlands and streams. One
commenter suggested requiring compensatory mitigation for all
activities authorized by this NWP. Two commenters said that this NWP
should include a requirement to establish buffers next to waters of the
United States, clarification that the limits apply to the project site
and not to multiple applicants, and a provision requiring flood
protections. One commenter stated industrial facilities that may be
authorized by this NWP cause indirect impacts to water quality that
could be significant and suggested not reissuing this NWP.
Phased developments may be authorized by general permits, as long
as they comply with all applicable terms and conditions of those
general permits. In particular, an NWP may only be used once for each
single and complete project. The limits in this NWP, which are
consistent with those in many other NWPs, will generally ensure minimal
adverse effects. In specific watersheds or other geographic areas where
a
[[Page 10223]]
district engineer is concerned that the use of NWP 39 may result in
more than minimal cumulative adverse effects to the aquatic
environment, the division engineer may regionally condition this NWP to
restrict or prohibit its use to ensure that the threshold for minimal
individual and cumulative adverse effects on the aquatic environment is
not exceeded. We do not agree that compensatory mitigation should be
required for all activities authorized by this NWP. District engineers
will add activity-specific conditions to the NWP authorization to
require compensatory mitigation in accordance with general condition
23, mitigation (also see 33 CFR 330.1(e)(3)), where necessary to ensure
minimal effects. The establishment and maintenance of riparian areas
next to open waters, or buffers next to wetlands, may be required as
compensatory mitigation, in accordance with general condition 23,
mitigation, and the regulations at 33 CFR part 332. The acreage limits
of this NWP apply to single and complete projects, even though a single
and complete project may have more than one project proponent. In
general, a commercial development project in which a developer prepares
a large site and then markets individual lots to individual builders
would be considered one single and complete project and the acreage
limits would apply to the development as a whole. See the definition of
``single and complete non-linear project'' for further information.
General condition 10, fills in 100-year floodplains, requires
permittees to comply with applicable state or local floodplain
management requirements that have been approved by the Federal
Emergency Management Agency. District engineers will review pre-
construction notifications requesting NWP 39 authorization for
industrial facilities to ensure that adverse effects to water quality
caused by the NWP activity are minimal, individually and cumulatively.
One commenter objected to authorizing the expansion of commercial
and institutional developments into waters of the United States,
stating that it discourages avoidance and minimization and is contrary
to the 404(b)(1) Guidelines. One commenter requested clarification
whether this NWP applies to new project construction or existing
construction projects so the acreage limits are applied cumulatively
for both the original construction and any subsequent expansion of the
development. One commenter asked whether certain categories of
activities that were not authorized by the 2007 version of NWP 39,
specifically new golf courses, new ski areas, or oil or gas wells,
could be expanded through the authorization provided by this NWP. Three
commenters suggested eliminating the exclusion for the construction of
oil and gas wells and attendant features.
The expansion of commercial and institutional developments into
waters of the United States may qualify for NWP authorization, as long
as it complies with all applicable terms and conditions of the NWP and
results in minimal individual and cumulative adverse effects on the
aquatic environment. This NWP complies with the 404(b)(1) Guidelines,
especially 40 CFR 230.7, which addresses the issuance of general
permits. The acreage limit applies to a single and complete project.
The expansion of an existing commercial or institutional development
may only be authorized under a separate NWP authorization if it is a
separate single and complete project with independent utility. For
example, one or more phased components of a commercial or institutional
development may have independent utility and may be authorized as
separate single and complete projects. The expansion of existing golf
courses or ski areas may be authorized by this NWP. We agree that the
construction of pads for oil and gas wells is a type of commercial
development that would be appropriate for inclusion in this NWP.
District engineers may add conditions to NWP 39 authorizations to
require the removal of these pads and restoration of the site once oil
or gas extraction operations have ceased and the wells will no longer
be used.
One commenter said that this NWP could be used to authorize
activities associated with wind energy generating structures, solar
towers, or overhead utility lines, which have the potential to
interfere with Department of Defense's long range surveillance,
homeland defense, testing, and training missions. This commenter
requested that copies of NWP 39 pre-construction notifications and NWP
verification letters for these activities be provided to the Department
of Defense Siting Clearinghouse, so that the Department of Defense
could have an opportunity to coordinate with the project proponent to
ensure that long range surveillance, homeland defense, testing, and
training missions are not adversely affected by these activities.
We have added a Note at the end of this NWP to require district
engineers to send pre-construction notifications and NWP verification
letters to the Department of Defense Siting Clearinghouse if NWP 39 is
proposed to be used, and is used, to authorize the construction of wind
energy generating structures, solar towers, or overhead transmission
lines. The Department of Defense Siting Clearinghouse is responsible
for coordinating with the project proponent and resolving any potential
effects on Department of Defense long range surveillance, homeland
defense, testing, and training missions.
This permit is reissued with the modification discussed above.
NWP 40. Agricultural Activities. We proposed to modify this NWP so
the 300 linear foot limit applies to all stream losses, not just
drainage ditches constructed in streams. To waive the 300 linear foot
limit for losses of intermittent or ephemeral stream bed, the district
engineer would have to make a project-specific written determination
that the activity will result in minimal adverse effects.
Two commenters support the changes and said the modification would
ensure NWP 40 authorizes activities with minimal adverse effects on the
aquatic environment. One commenter opposed expanding the 300 linear
foot limit to all stream losses, stating that the NWP should not
authorize the loss of natural streams. Another commenter recommended
removing intermittent streams from the waiver provision to limit it to
ephemeral streams. One commenter said that waivers for the loss of
greater than 300 linear feet of intermittent and ephemeral streams
should not be issued until a natural heritage database search was
completed. Two commenters stated that the acreage limit and the ability
to waive the 300 linear foot limit do not adequately address cumulative
impacts and requested the waiver provision be removed.
Comments concerning the 300 linear foot limits for the loss of
stream bed and the waiver process are discussed in a previous section
of the preamble. We are adopting the proposed language for the waiver
provision. We are retaining the provision allowing the 300 linear foot
limit to be waived for losses of ephemeral and intermittent stream bed,
since such activities may result in minimal adverse effects on the
aquatic environment. District engineers may consider information from
state natural heritage databases when evaluating a pre-construction
notification involving a proposed waiver of the 300 linear foot limit.
We believe that both the \1/2\-acre limit and 300 linear foot limit for
stream bed losses, along with the division engineer's authority to add
regional
[[Page 10224]]
conditions to this NWP and the district engineer's authority to add
activity-specific conditions to an NWP authorization, will ensure that
the NWP authorizes activities with minimal individual and cumulative
adverse effects on the aquatic environment. Division engineers may also
suspend or revoke this NWP in watersheds or other geographic areas if
they find that use of the NWP would result in more than minimal
cumulative adverse environmental effects.
One commenter stated the \1/2\-acre limit should be based on farm
tract and asserted NWP 40 allows for the incremental fill of
agricultural wetlands. One commenter stated that roadside stands should
not be considered farm buildings for authorization under this permit.
Another commenter recommended farm building pads be limited to areas
that have been in existing, ongoing, agricultural production since at
least 1980. One commenter remarked concern that this NWP allows fills
in waters for non-water dependent uses. Another commenter asserted this
NWP should not authorize farm ponds in wetlands.
The \1/2\-acre limit applies to a single and complete project. The
district engineer will determine, after considering the specific
circumstances for a pre-construction notification, whether the single
and complete project should be based on a farm tract, property
boundary, or other appropriate geographic area. Road stands may be
considered farm buildings for the purposes of this NWP. We do not agree
that building pads for farm buildings should be limited to existing
agricultural areas, or that they should be treated differently than
building pads authorized by NWPs 29 or 39. General permits, including
NWPs, may authorize activities that are not water-dependent, as long as
the general permit is issued in accordance with the requirements in the
404(b)(1) Guidelines at 40 CFR 230.7.
This NWP is reissued as proposed.
NWP 41. Reshaping Existing Drainage Ditches. There were no changes
proposed for this NWP. Several commenters requested adding more terms
and conditions to this NWP to provide requirements concerning slope
stability, conducting a natural heritage database search, limiting the
NWP to reshaping no more than one mile of drainage ditch, and placing
the excavated material in uplands. One commenter suggested replacing
the phrase ``for the purpose of improving water quality'' with ``for
the purpose of improving water quality or public safety.'' This
commenter also said the NWP should authorize drainage improvements
beyond the original as-built capacity. One commenter stated that this
NWP should not be exempt from compensatory mitigation requirements even
though the activity is designed to improve water quality.
We do not agree that the suggested additional terms and conditions
are necessary to ensure that this NWP authorizes ditch reshaping
activities that have minimal adverse effects on the aquatic
environment. The drainage ditch slope is more appropriately determined
on a case-by-case basis. District engineers have the discretion to
consult state natural heritage databases while reviewing pre-
construction notifications. The authorized activities are intended to
improve water quality, so there is no need to impose a one mile limit
or require compensatory mitigation. Reshaping a drainage ditch to
improve water quality may involve discharging dredged or fill material
into jurisdictional waters within the ditch. This NWP was originally
issued to encourage activities that would help improve water quality
within a watershed, not to provide for public safety. Discharging
dredged or fill material into waters of the United States to reshape
existing drainage ditches primarily for the purposes of public safety
may be authorized by other NWPs, regional general permits, or
individual permits.
This NWP is reissued as proposed.
NWP 42. Recreational Facilities. We proposed to modify this NWP by
changing the waiver provision for activities resulting in the loss of
greater than 300 linear feet of intermittent and ephemeral stream bed,
to clarify that the district engineer will only issue the waiver after
making a project-specific written determination that the activity will
result in minimal adverse effects.
Two commenters said that the \1/2\-acre limit of this NWP does not
ensure minimal adverse effects, and one of these commenters stated that
the 300 linear foot limit for stream bed losses does not ensure minimal
adverse effects either. Several commenters supported the proposed
waiver provision, since it emphasizes that the appropriate test is that
the activity results in minimal adverse effects. One commenter
suggested removing intermittent streams from the waiver provision
because of the potential for significant impacts to intermittent
streams.
The \1/2\-acre limit is the appropriate limit to ensure that the
activities authorized by this NWP result in minimal adverse effects on
the aquatic environment. This limit has been in place over several
permit terms and multiple NWPs and we are not aware of evidence that it
has allowed projects that do not meet the minimal effects requirement
to be authorized, nor have commenters provided such evidence. Division
engineers may regionally condition this NWP to reduce the acreage limit
or revoke the NWP if its use would result in more than minimal
individual and cumulative adverse effects on the aquatic environment.
The 300 linear foot limit for losses of stream bed is also necessary to
ensure minimal adverse environmental effects. The waiver provision is
discussed in a separate section of the preamble. We are retaining the
300 linear foot limit for stream bed impacts, as well as the ability
for district engineers to provide written waivers of the 300 linear
foot limit for losses of intermittent and ephemeral stream beds.
One commenter suggested adding a condition to this NWP to limit
fill pathways on public lands to six feet wide, with a maximum length
of 200 feet, and require open pile or floating boardwalks/docks by
prohibiting the discharges below the ordinary high water mark of inland
lakes, streams, or the Great Lakes, or areas that otherwise provide
fish habitat functions of any kind.
We do not believe the recommended restrictions are necessary to
ensure that the NWP authorizes only those activities that result in
minimal adverse effects on the aquatic environment. Division engineers
may add regional conditions to this NWP to limit certain activities or
require specific construction techniques. Division engineers may also
restrict or prohibit the use of this NWP in certain waters to protect
important resources, such as fish habitat.
One commenter supports requiring pre-construction notification for
all activities authorized by this NWP. One commenter said that the
activities authorized by this NWP are not similar in nature. One
commenter suggested adding a condition requiring recreational
facilities to be integrated into the natural landscape and not
substantially change pre-construction grades or deviate from natural
landscape contours. One commenter requested clarification as to when an
easement will not be required.
We have retained the requirement that all project proponents who
want to use this NWP must submit a pre-construction notification. This
NWP authorizes a specific category of activities (i.e., recreational
facilities) and complies with the ``similar in nature'' requirement of
Section 404(e) of the Clean Water Act. We do not agree that it is
necessary to require
[[Page 10225]]
recreational facilities to be integrated into the natural landscape and
not substantially change pre-construction grades. The \1/2\-acre and
300 linear foot limits, as well as the requirement to avoid and
minimize adverse effects to waters of the United States to the maximum
extent practicable on the project site (see general condition 23,
mitigation), help ensure that the NWP authorizes activities that result
in minimal adverse effects. Conservation easements or other appropriate
long-term protection instruments will only be required, if necessary,
for areas that are used to provide compensatory mitigation for
activities authorized by this NWP.
This permit is reissued as proposed.
NWP 43. Stormwater Management Facilities. We proposed to modify
this NWP by adding low impact development stormwater management
features to the examples of types of stormwater management facilities
that may be authorized by this NWP. We also proposed to modify this NWP
by changing the waiver provision for activities resulting in the loss
of greater than 300 linear feet of intermittent and ephemeral stream
bed, to clarify that the district engineer will only issue the waiver
after making a project-specific written determination that the activity
will result in minimal adverse effects.
One commenter expressed support for the proposed modifications. One
commenter suggested that the acreage limit should be increased from \1/
2\-acre to one acre to increase the utility and usefulness of this NWP.
Several commenters said this NWP should not authorize new stormwater
management facilities. One commenter stated that the NWP should only
authorize the construction of an outfall structure. A couple of
commenters said that this NWP should be changed to clarify that only
constructed wetlands may be used to detain, retain, or treat
stormwater.
We do not agree that the acreage limit for this NWP should be
increased from \1/2\-acre to one acre. The \1/2\-acre limit is
necessary to ensure that this NWP authorizes only those activities that
result in minimal individual and cumulative adverse effects on the
aquatic environment. The construction of new stormwater management
facilities may be authorized by this NWP (if all other conditions are
met), because those activities often result in minimal adverse
environmental effects and help protect the aquatic environment by
preventing or reducing the amount of pollutants that enter streams,
coastal waters, and other aquatic habitats. Stormwater management
facilities are an important tool for fulfilling the objective of the
Clean Water Act, by protecting and restoring the physical, chemical,
and biological integrity of our Nation's waters. The construction of
stormwater management facilities may involve discharges of dredged or
fill material into jurisdictional wetlands, so it would not be
appropriate to limit this NWP to constructed wetlands for the
detention, retention, or treatment of stormwater.
We have substantially modified the first paragraph of this NWP to
clarify how construction and maintenance activities may be authorized
by this NWP, including the application of the waste treatment system
exclusion at 33 CFR 328.3(a)(8). Section 328.3(a)(8) states that
``[w]aste treatment systems, including treatment ponds or lagoons
designed to meet the requirements of'' the Clean Water Act are not
waters of the United States. The first half of this paragraph provides
examples of the types of stormwater management facilities that may be
authorized by this NWP, if the construction of those facilities
involves discharges of dredged or fill material into waters of the
United States. The second half of this paragraph states that to the
extent that a section 404 permit is required, this NWP also authorizes
discharges of dredged or fill material into waters of the United States
for the maintenance of stormwater management facilities. Therefore,
this NWP authorizes maintenance activities involving discharges of
dredged or fill material if the stormwater management facility is not
eligible for the waste treatment system exclusion. A section 404 permit
is not required for a discharge of dredged or fill material into a
waste treatment system that qualifies for the waste treatment system
exclusion at 33 CFR 328.3(a)(8).
Several commenters supported the addition of low impact development
stormwater management features to the examples of activities authorized
by this NWP. One commenter said that while the construction of low
impact development stormwater management features may need a Department
of the Army permit in some circumstances, the maintenance of low impact
development stormwater management features does not require a section
404 permit. This commenter also stated that requiring Department of the
Army permits for maintenance activities in watersheds that have total
maximum daily load requirements would result in needless paperwork
without any environmental benefits. One commenter requested an
explanation of the value of low impact development stormwater
management facilities and examples of those facilities that may be
authorized by this NWP. One commenter expressed concern that areas not
subject to Clean Water Act jurisdiction, such as swales and upland
areas holding waters only for short periods of time, may be considered
to be waters of the United States if they are used for low impact
development stormwater management features. Several commenters
requested a definition for ``low impact development stormwater
features'' in the definitions section. One commenter asked whether
hybrid or combined bank protection and stormwater management techniques
are authorized by this NWP or authorized by other NWPs.
We have modified the text of this NWP to clarify that the
construction of low impact development integrated management features
is authorized by this NWP, if the construction involves discharges of
dredged or fill material into waters of the United States. We have also
provided examples of the types of low impact development integrated
management features that may be authorized by this NWP, such as
bioretention facilities (e.g., rain gardens), vegetated filter strips,
grassed swales, and infiltration trenches. After these low impact
development integrated management features are constructed, they may
not be waters of the United States and subsequent maintenance may not
require further Department of the Army authorization. The
jurisdictional status of these features will be determined by district
engineers on a case-by-case basis, after applying the appropriate
regulations and guidance. The Corps of Engineers wetland delineation
manual and the applicable regional supplement will be used to determine
whether a particular feature is a wetland under the definition at 33
CFR 328.3(b). Many low impact development integrated management
features may not have wetland hydrology because they are designed to
improve water infiltration. By modifying this NWP to make it clear that
it can be used to authorize discharges of dredged or fill material to
construct low impact development integrated management features, we are
providing general permit authorization for activities that will help
state and local entities comply with the total daily maximum loads
established for a watershed or watershed. We do not believe it is
necessary to define the term ``low impact development stormwater
management features'' in the Definitions section of the NWPs because
the text of the NWP provides examples of those features. This NWP may
authorize some minor bank stabilization associated with the
construction of a stormwater
[[Page 10226]]
management facility. Bank protection may be authorized by this NWP or
another appropriate NWP.
One commenter asked whether this NWP authorizes discharges of
dredged or fill material for the construction of new stormwater
facilities in intermittent or ephemeral streams that are waters of the
United States. One commenter recommended prohibiting the construction
of new stormwater management facilities in intermittent streams to
avoid impacts to numerous rare and threatened and endangered species.
Another commenter said this NWP should only authorize activities in
ephemeral streams.
We do not believe it is necessary to limit the construction of new
stormwater management facilities to ephemeral streams. District
engineers will review pre-construction notifications and determine
whether the proposed activities will have minimal adverse effects on
intermittent and ephemeral streams. Activities authorized by this NWP
must also comply with general condition 18, Endangered Species. State-
listed rare species may be further protected through the establishment
of regional conditions by division engineers, after a public notice and
comment process.
Several commenters objected to allowing the district engineer to
waive the 300 foot limit for the loss of intermittent or ephemeral
stream bed. Another commenter suggested increasing the linear limit for
the loss of stream beds to 500 feet before requiring a waiver, to
authorize more activities. Several commenters stated the waiver
provision should be removed and losses of waters of the United States
should be limited to \1/2\-acre or 300 linear feet of stream bed.
Another commenter stated that no waivers should be allowed under any
circumstances. One commenter suggested that waivers for losses of
intermittent and ephemeral stream beds not be issued until the
appropriate natural heritage resources database is consulted to inform
the minimal adverse impact determination.
We are retaining the provision allowing district engineers to waive
the 300 linear foot limit for the loss of intermittent and ephemeral
streams, upon making a written determination that the discharge will
result in minimal adverse effects. The 300 linear foot limit should not
be increased to 500 linear feet, to ensure that any loss of perennial
stream bed results in no more than minimal individual and cumulative
adverse effects on the aquatic environment. District engineers may use
available information, including state or local natural heritage
resources databases, to help make the minimal adverse effects
determination.
Some commenters suggested combining the maintenance component of
this NWP with NWP 3 since both include maintenance activities. Another
commenter suggested limiting this NWP to authorizing only the
maintenance of stormwater management facilities constructed and used
for the primary purpose of providing stormwater detention, retention
and treatment.
As discussed above, we have modified this NWP to clarify that Clean
Water Act Section 404 permits would not be required for maintenance
activities (or other discharges of dredged or fill materials) involving
stormwater management facilities that qualify for the waste treatment
system exclusion at 33 CFR 328.3(a)(8) because these are excluded from
the definition of waters of the United States. We do not believe it is
necessary to combine maintenance authorized by NWP 43 with the
maintenance activities authorized by NWP 3, since NWP 3 authorizes a
variety of maintenance activities. Some stormwater management
facilities may have purposes or uses other than stormwater detention,
retention or treatment, so maintenance should still be authorized by
this NWP, if a section 404 permit is required and the activity results
in minimal adverse effects on the aquatic environment.
One commenter suggested that if a development project is required
to install stormwater management facilities, the entire development
should be treated as the ``area of potential effects'' for the purposes
of compliance with Section 106 of the National Historic Preservation
Act. One commenter recommended requiring any contaminated materials to
be properly handled and disposed of.
The permit area for section 106 compliance will be determined by
applying the criteria in Appendix C of 33 CFR part 325, the Corps
Regulatory Program's procedures for the protection of historic
properties, as well as the interim guidance issued on April 25, 2005,
and January 31, 2007. In general, as is made clear in these regulations
and guidance, the Corps does not agree that the area of potential
effects for an NWP that is needed for a discharge involving one aspect
of a development project necessarily encompasses the entire project,
though this may be true in individual cases depending on the facts and
circumstances. Compliance with general condition 20, Historic
Properties, is required for activities authorized by this NWP. In
response to a pre-construction notification, the district engineer may
add activity-specific conditions to the NWP authorization to protect
waters of the United States from adverse effects due to contaminated
materials.
This NWP is reissued with the modifications discussed above.
NWP 44. Mining Activities. We proposed to add the 300 linear foot
limit for the loss of stream bed, which for intermittent and ephemeral
stream beds can be waived by the district engineer if he or she makes a
written determination concluding that the activity will result in
minimal adverse effects.
One commenter requested the NWP be revoked due to the large scale
of these activities and their impacts on water quality. One commenter
said this NWP should only authorize mining activities that have been
permitted by state agencies. This commenter also stated that this NWP
should not authorize peat mining or in-stream gravel mining. One
commenter recommended expanding the categories of applicable waters to
include tidal waters, since the term ``adjacent'' has not been
adequately defined.
The terms and conditions of this NWP, including the addition of the
300 linear foot limit for the loss of stream bed, help ensure that the
NWP authorizes only those activities that have minimal individual and
cumulative adverse effects on the aquatic environment. Division
engineers can regionally condition this NWP to restrict or prohibit its
use in specific waters or categories of waters, or in particular
geographic regions. After reviewing a pre-construction notification,
the district engineer may add activity-specific conditions to the NWP
authorization to require water quality management measures so that the
activity causes only minimal degradation of water quality (see general
condition 25, water quality), or he or she may exercise discretionary
authority and require an individual permit if it is not possible to
reduce the adverse effects so that they are no more than minimal.
Division engineers may also regionally condition this NWP to prohibit
or restrict peat mining or in-stream gravel mining. We do not agree
that the NWP should be expanded to authorize discharges of dredged or
fill material into tidal waters, since such activities may result in
more than minimal adverse effects on the aquatic environment. The term
``adjacent'' is defined in the Corps regulations at 33 CFR 328.3(c) and
is used to identify wetlands that are waters of the United States by
virtue of being adjacent to jurisdictional waters.
[[Page 10227]]
Many commenters opposed adding the 300 linear foot limit for the
loss of stream bed and stated that the 300 linear foot limit should not
apply to smaller tributaries. One commenter recommended increasing the
linear foot limit to 500 feet. One commenter said the proposed linear
foot limit would have the effect of preventing mining of more than one
million tons of mineable reserves. One commenter stated that waivers to
the 300 linear foot limit should not be issued without evaluating
documented natural heritage resources located in the project area.
As stated above, the 300 linear foot limit is being added to help
ensure that the NWP authorizes only those activities that result in
minimal adverse effects on the aquatic environment and other applicable
public interest review factors. Increasing the linear foot limit for
the loss of stream bed to 500 feet increases the likelihood that these
mining activities would result in more than minimal adverse effects and
therefore not comply with the requirements of Section 404(e) of the
Clean Water Act. Mining activities that do not qualify for NWP
authorization may be authorized by individual permits or other general
permits, such as regional general permits issued by district engineers.
District engineers will evaluate appropriate information before waiving
the 300 linear foot for losses of intermittent or ephemeral stream bed,
which may include state natural heritage resource databases. In areas
where district engineers have designated state natural heritage sites
as critical resources, compliance with general condition 22, designated
critical resource waters will protect those natural heritage sites.
This NWP is reissued as proposed.
NWP 45. Repair of Uplands Damaged by Discrete Events. We proposed
to modify this NWP to clarify that it does not authorize beach
restoration. We also proposed to change the Note, to make it clear that
the NWP authorizes discharges of dredged or fill material into waters
of the United States associated with the restoration of uplands.
One commenter requested that a \1/2\-acre limit be placed on
activities authorized under this NWP. One commenter said that
authorizing activities under this NWP within channel migration zones
can have more than minimal adverse environmental effects and impair
stream functions if those activities attempt to force a stream back
into previously occupied channels. This commenter said the NWP should
be conditioned to prohibit fills that would attempt to move the stream
channel to a previous course within the stream channel migration zone.
One commenter suggested modifying this NWP to limit it to reconfiguring
the affected area, and not authorize increases to the size of
structures or fills. Another commenter supported allowing dredging or
excavation in all waters of the United States under this NWP in
conjunction with the repair of uplands.
We do not believe that it is necessary to impose a \1/2\-acre limit
to this NWP, because it limits the repair of uplands to the contours,
or ordinary high water mark, that existed before the damage occurred.
This NWP also limits dredging to the minimum necessary to restore the
damaged uplands, and does not authorize significant alterations to pre-
event bottom contours of the waterbody. The minor fills authorized by
this NWP are unlikely to substantially alter stream migration. Because
this NWP is limited to restoring uplands to pre-event configurations,
it does not authorize more than minimal changes in the size of
structures or fills that may be constructed on or near uplands.
One commenter said that fills should be limited to the post-event
ordinary high water mark. Another commenter made a similar
recommendation, but suggested that an exception should be provided in
cases where there is a need to respond to immediate threats to a
primary structure or to infrastructure.
We do not agree that fills should be limited to the post-event
ordinary high water mark. The purpose of this NWP is to authorize
discharges of dredged or fill material into waters of the United States
for the repair of uplands that have been damaged by discrete events and
have minimal adverse effects on the aquatic environment. In some cases,
it may not be practicable to limit fills to where the new ordinary high
water mark is located, in cases where the discrete event changes the
location of the ordinary high water mark.
One commenter said that Tribes should be notified to avoid impacts
to Tribal treaty natural resources and cultural resources. Two
commenters supported the proposed changes to the Note. One commenter
stated that all bank stabilization authorized by this NWP must also
satisfy the terms and conditions of NWP 13.
Division engineers can regionally condition this NWP to identify
areas where there are Tribal treaty natural and cultural resources, so
that consultation can be conducted with those Tribes to ensure that
impacts to those resources are appropriately considered during review
of pre-construction notifications. General condition 17, Tribal rights,
prohibits the impairment of reserved tribal rights such as reserved
water rights and treaty fishing and hunting rights. We have retained
the proposed changes to the Note at the end of this NWP. This NWP
provides separate authorization for discharges of dredged or fill
material that are necessary to repair uplands that have been damaged by
discrete events, including the placement of fills necessary to
stabilize the bank. Unlike NWP 13, this NWP limits bank stabilization
so that it does not exceed the land contours that existed before the
damage occurred. Nationwide permit 13 may be used in conjunction with
this NWP to authorize bank stabilization for restored uplands in cases
where it is not practicable to limit bank stabilization to the pre-
event ordinary high water mark or contours.
The NWP is reissued as proposed.
NWP 46. Discharges in Ditches. We did not propose any changes to
this NWP. Most commenters asked why this permit was needed since upland
ditches are not subject to Clean Water Act jurisdiction, and any
discharges of dredged or fill material into these ditches are exempt by
statute under Section 404(f) of the Clean Water Act. Some commenters
noted that the Corps does not assert Clean Water Act jurisdiction over
many upland ditches and should not attempt to regulate these ditches by
reissuing this NWP.
This NWP authorizes discharges of dredged or fill material into a
specific category of ditches (i.e., those non-tidal ditches that meet
all four criteria in the first paragraph of the NWP), if those ditches
have been determined to be waters of the United States. Section 404(f)
of the Clean Water Act only exempts discharges of dredged or fill
material for the construction or maintenance of irrigation ditches, or
the maintenance of drainage ditches, while this NWP authorizes a
different set of activities which would require a Section 404 permit.
For example, this NWP authorizes discharges of dredged or fill material
that may completely fill the specific category of upland ditch
described in the NWP, if that ditch is determined to be a water of the
United States after either the Corps or EPA makes a jurisdictional
determination.
We recognize that many ditches constructed in uplands are not
waters of the United States, but there are some ditches constructed in
uplands that may be determined to be waters of the United States after
evaluating the specific characteristics of those ditches. The preamble
to the Corps November 13, 1986, final rule states the non-tidal
drainage and irrigation ditches
[[Page 10228]]
excavated on dry land are generally not considered to be waters of the
United States, but the Corps and EPA reserve the right on a case-by-
case basis to determine whether a particular waterbody is a water of
the United States (see 51 FR 41217). Joint guidance issued in December
2008 by EPA and the Corps provides additional clarification as to when
ditches are and are not considered to be waters of the United States
(see https://water.epa.gov/lawsregs/guidance/wetlands/upload/2008_12_3_wetlands_CWA_Jurisdiction_Following_Rapanos120208.pdf; p. 12).
Some commenters said there are impacts to upland ditches that could
impair water quality downstream and that compensatory mitigation should
be required to minimize adverse effects caused by activities authorized
by this NWP. One commenter recommended that district engineers evaluate
impacts to natural heritage resources during their review of pre-
construction notifications.
For those activities authorized by this NWP, the district engineer
will review the pre-construction notification and determine whether the
activity results in only minimal adverse effects, including whether
compensatory mitigation is necessary to ensure that the authorized
activity results in minimal adverse effects on the aquatic environment,
including water quality. During the review of a pre-construction
notification, the district engineer may consult natural heritage
resource databases to more effectively evaluate the potential adverse
effects on the aquatic environment.
This NWP is reissued as proposed.
NWP 47. Pipeline Safety Program Designated Time Sensitive
Inspections and Repairs. We proposed to not reauthorize this NWP
because it was issued in 2007 in reliance on the development of the
Pipeline Repair and Environmental Guidance System (PREGS) by the
Pipeline and Hazardous Materials Safety Administration. Since PREGS was
not developed and deployed, and paragraph (h) of the NWP required
permittees to use PREGS to submit post-construction reports, no
activity could be authorized by NWP 47.
Two commenters asked why this NWP was not proposed to be reissued.
Three commenters agreed with allowing the NWP to expire and supported
the Corps position that designated time sensitive inspections and
repairs can be authorized under NWP 3, Maintenance and NWP 12, Utility
Line Activities. One commenter said that there should be an NWP to
authorize emergency repair activities to fix natural gas pipeline
leaks, pressure malfunctions, natural disaster damage, terrorist
threats, or other events that pose a danger to public safety. One
commenter suggested issuing a new NWP to authorize activities licensed
by the Federal Energy Regulatory Commission's blanket certificate
program.
Existing NWPs, such as NWPs 3 and 12, may be used to authorize
discharges of dredged or fill material or structures or work in
navigable waters of the United States associated with pipeline
inspections and repairs. Some of these activities do not require pre-
construction notification to qualify for NWP authorization. There are
other approaches available, such as emergency permitting procedures, to
allow emergency repair activities that do not qualify for general
permit authorization to proceed if there is ``an unacceptable hazard to
life, a significant loss of property, or an immediate, unforeseen, and
significant economic hardship'' (see 33 CFR 325.2(e)(4)). We do not
believe it is necessary to develop a new NWP to authorize activities
that are granted blanket certificates by the Federal Energy Regulatory
Commission. Many of these activities may be authorized by existing
NWPs, such as NWPs 3 and 12.
This NWP is not reissued.
NWP 48. Commercial Shellfish Aquaculture Activities. We proposed to
modify this NWP by removing the reporting requirement, which applied to
all activities that did not require pre-construction notification. We
also proposed to add the information previously required in that report
to the PCN information requirements. This information includes: A map
showing the boundaries of the project area, with latitude and longitude
coordinates for each corner of the project area; the name(s) of the
cultivated species; and whether canopy predator nets are being used. In
addition, we proposed to remove the pre-construction notification
requirement for changes in species cultivated, as long as those species
had been previously cultivated in the waterbody. We proposed to modify
this NWP to authorize activities associated with the expansion of
existing commercial shellfish aquaculture operations. We requested
comments on modifying this NWP or issuing a new NWP to authorize new
commercial shellfish aquaculture activities.
Many commenters said the NWP should be reissued, and recommended
many changes. Several commenters stated that this NWP should not be
reissued. Most commenters expressed support for removing the reporting
requirements for all activities that did not require pre-construction
notification, stating that the paperwork was unnecessary given the
current regulation of the industry by other entities, such as state and
local governments. One commenter said that the reporting requirements
should be maintained to ensure protection of resources. Other
commenters suggested that pre-construction notification should be
required for all activities. Several commenters said that the NWP
should only authorize maintenance activities. One commenter stated that
shellfish aquaculture methods are sufficiently different for the
species cultivated that issuing a single NWP to authorize these
activities is inappropriate. Another commenter said that all commercial
shellfish aquaculture activities should be authorized under one NWP.
Two commenters stated that the NWP should only authorize harvesting
that occurs by hand. One commenter stated that these activities may
impact tribal fishery access and fishing rights, and coordination with
the affected tribes should be required.
We have reissued this NWP and made several changes. Properly sited,
operated, and maintained commercial shellfish aquaculture activities
support populations of shellfish that provide important ecological
functions and services for coastal waters, and should be authorized by
a single NWP. We have removed the reporting requirements for this NWP
and substantially reduced the number of pre-construction notification
thresholds. Division engineers may regionally condition this NWP to
establish additional pre-construction notification thresholds if
necessary to ensure that this NWP authorizes only those activities that
have minimal adverse effects on the aquatic environment. We do not
agree that pre-construction notification should be required for all
activities authorized by this NWP, because these activities are
regulated by a number of other government agencies, especially at the
federal and state government levels. In addition, the discharges of
dredged or fill material into waters of the United States authorized by
this NWP will result in minimal adverse environmental effects to the
environmental criteria established under the Clean Water Act. The
shellfish populations supported by the activities authorized by this
NWP help support the objective of the Clean Water Act because they
improve water quality through the conversion of nutrients into biomass
(i.e., shellfish growth) and the
[[Page 10229]]
removal of suspended materials through filter feeding. Commercially
grown shellfish also provide some habitat functions for the aquatic
environment. Impacts to submerged aquatic vegetation will, in many
cases, be evaluated through the pre-construction notification review
process. For commercial shellfish aquaculture activities in new project
areas, adverse effects to submerged aquatic vegetation will be minimal
because of the \1/2\-acre limit. Impacts to coastal aquatic habitat and
species of concern in those habitats are more appropriately addressed
through consultation conducted under the Essential Fish Habitat
provisions of the Magnuson-Stevens Fishery Conservation and Management
Act and/or Section 7 of the Endangered Species Act.
We do not agree that the NWP should be limited to hand harvesting
activities. We have retained the pre-construction notification
requirement for activities involving dredge harvesting, tilling, or
harrowing in areas inhabited by submerged aquatic vegetation. General
condition 17, tribal rights, states that NWP activities may not impair
reserved tribal rights, including treaty fishing and hunting rights. In
addition, division engineers may regionally condition this NWP to
identify areas where Tribes must be notified of these activities and
government-to-government consultation conducted to avoid or minimize
impacts to tribal fishery access and fishing rights.
One commenter said that the restoration of indigenous species would
be prevented if cultivation was limited to only those species that were
previously commercially cultivated. Another commenter recommended
requiring pre-construction notification if there were a proposed change
in species cultivated that was not part of a state-approved list. Some
commenters suggested that pre-construction notification should not be
required for changes in harvesting methods. Another commenter said that
pre-construction notification should be required if the culture method
changed from bottom culture to floating or suspended culture to allow
district engineers to evaluate potential navigation issues. One
commenter indicated that the NWP should authorize demonstration
projects less than one acre in size and another said that non-
commercial shellfish aquaculture activities should be authorized, since
states, local governments, and non-governmental organizations engage in
recreational and commercial aquaculture. One commenter recommended
adding a provision that would require the permittee to implement
measures to prevent the spread of aquatic nuisance species, such as
prohibiting the transfer of materials used for commercial shellfish
aquaculture activities from one project site to another unless
appropriate measures have been taken to ensure that those materials are
free of aquatic nuisance species. This commenter said a note should be
added to the NWP, to prohibit the transfer of equipment used in
commercial shellfish aquaculture activities from one waterbody to
another waterbody, unless that equipment has been allowed to dry out
for a minimum of 90 days or treated in accordance with a regional
aquatic nuisance control plan, to prevent the introduction of aquatic
nuisance species into the other waterbody.
We have modified this NWP to provide more flexibility in the
species cultivated, specifically, to allow the cultivation of
nonindigenous species as long as those species have been previously
cultivated in the waterbody. We recognize that there has been
commercial production of nonindigenous species over many years in
certain waterbodies, and activities requiring Department of the Army
authorization associated with those commercial operations should be
authorized by this NWP. We have retained the prohibitions against
cultivating aquatic nuisance species defined by the Nonindigenous
Aquatic Nuisance Prevention and Control Act of 1990. We have also added
Note 2 to the NWP, to reduce the risk of introducing aquatic nuisance
species by requiring treatment of materials taken from one waterbody to
another in accordance with the applicable regional aquatic nuisance
species management plan. Division engineers may add regional conditions
to the NWP to make permittees aware of the regional aquatic nuisance
species management plan that may be applicable to NWP 48 activities.
We agree that pre-construction notification should not be required
for changes in harvesting methods because harvesting methods have
temporary impacts and result in minimal adverse effects. A possible
exception is dredge harvesting in areas inhabited by submerged aquatic
vegetation, which still requires pre-construction notification. We also
agree that pre-construction notification should be required if the
grower proposes to change from bottom culture to floating or suspended
culture in a project area, or if it is an activity in a new project
area that requires the installation and use of floating or suspended
gear, so that effects to navigation can be evaluated. This NWP
authorizes commercial shellfish aquaculture activities undertaken by
states, local governments, and non-governmental organizations.
Shellfish seeding activities to improve shellfish populations may be
authorized by NWP 27. Small recreational shellfish aquaculture
activities may be authorized by other applicable NWPs, such as NWP 4.
Other recreational shellfish aquaculture activities may be authorized
by regional general permits or individual permits. Restoration
aquaculture activities may be authorized by NWP 27.
One commenter stated that the structures and fill activities
authorized by the NWP were too broad and should be refined. This
commenter recommended prohibiting the long-term use of trays if
sediment is compacted and diversity is diminished. One commenter said
that structures and fill should be limited to shell spat only, while
another commenter stated that shell planting should be allowed on any
size parcel without pre-construction notification.
The structures and fills authorized by this NWP are limited to
those necessary to conduct commercial shellfish aquaculture activities.
We have retained the provision that states that the NWP does not
authorize attendant features such as docks, piers, boat ramps,
stockpiles or staging areas, or the deposition of shell material back
into waters of the United States as waste. We have removed the pre-
construction notification threshold for commercial shellfish
aquaculture activities that are more than 100 acres in size, because we
do not believe it is necessary to require pre-construction notification
for existing operations with a valid lease, permit, or other
appropriate instrument that has been approved by the appropriate state
or local government agency, unless the activity triggers any of the
pre-construction notification thresholds.
One commenter requested changes to the definition of shell seeding,
citing concerns over the use of potentially environmentally damaging
materials. Another commenter supported the use of terms such as
``suitable substrate'' and ``appropriate materials'' due to the
decreasing availability of shell cultch and new research and
development regarding materials. One commenter said that use of the
term ``submerged aquatic vegetation'' allowed for the destruction of
eelgrass, because eelgrass is often not inundated with tidal waters.
One commenter asked whether traditional oyster culture practices were
of special concern.
The definition of the term ``shellfish seeding'' in the Definitions
section of
[[Page 10230]]
the NWP provides examples of appropriate materials that may be used for
shellfish seeding activities. Through the issuance of regional
conditions, division engineers can restrict or prohibit the use of
certain materials for shellfish seeding. In response to a pre-
construction notification, district engineers may add activity-specific
conditions to an NWP authorization to prohibit the use of certain
materials for shellfish seeding. Eelgrass is commonly considered to be
a species of submerged aquatic vegetation and we intend it to be
covered by the provisions regarding submerged aquatic vegetation,
regardless of whether it is fully submerged in all tidal conditions or
not.
Many commenters requested clarification as to when pre-construction
notification is required and what constitutes a project area for the
purposes of this NWP. Several commenters recommended that pre-
construction notifications should only be required once and not for
each subsequent reissuance of this NWP if the commercial shellfish
aquaculture operation has not changed. One commenter asked if the lease
holder is required to provide pre-construction notifications annually
if the lease covers an area greater than 100 acres. One commenter
inquired whether pre-construction notification is required when the
operator is only working on 30 acres of a 200-acre project site. One
commenter said that multiple pre-construction notifications should not
be required from a lease holder that has multiple 100-acre leases;
instead, one pre-construction notification should cover all those
leases.
We have reduced the number of pre-construction notification
thresholds in this NWP. The pre-construction notification thresholds in
this NWP focus on those activities that should be reviewed by district
engineers to: (1) Ensure that floating or suspended aquaculture
facilities do not cause more than minimal adverse effects on navigation
or, (2) ensure that both cultivating species that have not been
previously cultivated in the waterbody and dredge harvesting, tilling,
or harrowing in areas of submerged aquatic vegetation do not cause more
than minimal adverse effects on the aquatic environment.
To support our objective to be more consistent with state and local
agencies that regulate commercial shellfish aquaculture activities, we
have redefined project area so that it is based on leases or permits
issued by an appropriate state or local government agency that is
responsible for allocating subtidal or intertidal lands for commercial
shellfish production. The project area may also be based on rights to
conduct shellfish aquaculture that are established by treaty, such as
treaties executed between the United States Government and Indian
Tribes. Project area may also be identified through an easement, lease,
deed, or contract which establishes an enforceable property interest to
conduct aquaculture activities on subtidal or intertidal lands.
We have removed the pre-construction notification requirement for
relocating existing operations into portions of the project area not
previously used for aquaculture activities, since the permit or lease
issued by the state or local government agency has already authorized
that area for use in commercial shellfish aquaculture. There is no need
to address expansions in this NWP if the proposed expansions are within
the project area authorized by the state or local government lease or
other appropriate instrument. For example, pre-construction
notification is not required if an operator who is only working on 30
acres of a 200-acre project area decides to conduct operations beyond
those 30 acres within the 200 acre project area.
We have removed the pre-construction notification threshold for
project areas greater than 100 acres. Since we have limited the pre-
construction notification thresholds to focus on activities that may
adversely affect submerged aquatic vegetation and changes in operations
that may adversely affect navigation or involve species not previously
cultivated in the waterbody, most on-going activities will not require
pre-construction notification, thereby substantially decreasing the
paperwork burden on current commercial shellfish aquaculture operators.
The lease holder is not required to provide a pre-construction
notification annually no matter what the size of the project area as
long as the lease holder has a valid lease, permit, or other
appropriate instrument that has been approved by the appropriate state
or local government agency for the project area, and none of the pre-
construction notification thresholds are triggered. For example, pre-
construction notification is not required if the lease holder is only
working within an existing authorized 200-acre project area no matter
how much or little of that area is cultivated. However, if the lease
holder proposes to cultivate a species of oyster in the 200-acre
project area not currently present in the waterbody, pre-construction
notification would be required. The activities also do not require pre-
construction notification unless the activities involve dredge
harvesting, tilling, or harrowing in areas of submerged aquatic
vegetation. If the lease holder's operations within the 200-acre
project area change from one on-bottom technique to another on-bottom
technique, pre-construction notification is not required. However, if
the operations are proposed to change from an on-bottom culture method
to a floating or suspended culture method, pre-construction
notification is required. Lastly, if an operator obtains a lease for a
new project area and wishes to conduct any commercial shellfish
aquaculture activities in the new project area, pre-construction
notification is required.
One commenter said that requiring pre-construction notification for
aquaculture relocation and expansion is unnecessary if the area is
already leased but transferred to another owner. Another commenter
recommended that any NWP authorizations should still be valid when the
lease is transferred to another operator and use has not changed. One
commenter stated that pre-construction notification should not be
required for expansions into newly leased areas since the site
conditions are usually the same.
Pre-construction notification is not required for expansions of
commercial shellfish activities as long as the expansion occurs within
the project area specified by an permit, lease, or other instrument
issued by the appropriate state or local agency, and as long as none of
the pre-construction notification thresholds are triggered. This would
apply to an activity in a new location within the project area, or to
an activity that would utilize a larger acreage of the project area, as
long as none of those activities require pre-construction notification.
If an activity is proposed by an operator in a new project area,
however, pre-construction notification is required. An NWP verification
can be transferred to a new project proponent, if he or she has
obtained an interest in the subtidal or intertidal lands, provided
appropriate procedures are followed for the transfer of the NWP
verification (see general condition 29, transfer of nationwide permit
verifications).
One commenter asked whether or not an NWP verification can be
issued prior to a state issuing a lease. Another commenter said that
NWP 48 should be delegated to the states who issue leases to reduce
duplicative paperwork. One commenter stated that pre-construction
notification should not be required when a state already evaluates
impacts to submerged aquatic vegetation prior to
[[Page 10231]]
granting leases. Another commenter said that certain states do not
issue leases in areas with submerged aquatic vegetation, so it is not
necessary for the Corps to address that issue.
The district engineer may issue an NWP verification before the
state makes its decision on a lease application. It is necessary to
respond to a complete pre-construction notification within 45 days to
retain the authority to add activity-specific conditions, which would
ensure that the NWP activity results in minimal adverse effects on the
aquatic environment. Since there is not consistent regulation of
commercial shellfish aquaculture activities among all of the states, we
do not agree that certain Federal interests, such as navigation and
impacts to special aquatic sites, should be delegated to the states. In
evaluating a pre-construction notification triggered by potential
impacts to submerged aquatic vegetation, the district engineer would
consider any evaluation of such impacts that had been previously
conducted by the state if this is submitted with the PCN.
Many commenters expressed concerns regarding impacts to species
protected under the Endangered Species Act, designated critical
habitat, and essential fish habitat. One commenter asked if compliance
with the Endangered Species Act was required for both existing and new
activities. Another recommended that a detailed eelgrass, macroalgae,
and forage fish survey should be required for each pre-construction
notification. One commenter stated that NWP authorization should not be
granted in areas adjacent to forage fish or critical habitat.
Activities authorized by this NWP must comply with general
condition 18, endangered species. Any new or existing activity that
involves discharges of dredged or fill material or structures or work
in navigable waters of the United States that might affect listed
species or designated critical habitat require pre-construction
notification to the district engineer, so that Section 7 consultation
can be conducted. We do not agree that pre-construction notifications
should include surveys for eelgrass, microalgae, or forage fishes. The
district engineer may request additional information from the project
sponsor if needed to conduct Section 7 consultation. An activity may be
authorized in critical habitat if a section 7 biological opinion is
issued and impacts to critical habitat are authorized.
One commenter recommended that the Corps work closely with the
National Oceanic and Atmospheric Administration to streamline the
review and approval of aquaculture projects. Some commenters said that
the commercial shellfish aquaculture industry is not sufficiently
regulated at the local, state, or federal level. One commenter said
that enforceable conditions need to be added to NWP 48 authorizations
to protect the aquatic environment. One commenter recommended
implementing a regional ecosystem-based management approach.
We have worked closely with the National Oceanic and Atmospheric
Administration and other Federal agencies to develop this NWP, and we
disagree that there is not already sufficient government oversight of
these activities at the various levels of government. In response to a
pre-construction notification, the district engineer may add activity-
specific conditions to the NWP authorization to ensure that the
authorized activity results in minimal adverse effects on the aquatic
environment, individually and cumulatively. A regional ecosystem-based
management approach is more appropriately undertaken by Corps districts
and interested Federal, State, and local government agencies, not at
the national level.
Many commenters expressed concern regarding the environmental
impacts associated with expansions of commercial shellfish aquaculture
activities and for new activities. One commenter said that expansion
proposals should not be reviewed as restoration activities since non-
native species are a serious threat. Several commenters stated that the
environmental benefits do not offset the environmental impacts,
introduction of invasive species, impacts to native species such as
flatfish and other sandy bottom species, reduction of species
diversity, elimination of native animal and plant species, harassment
and destruction of migrating birds, and the introduction of plastics.
Other commenters expressed concern regarding impacts from geoduck
cultivation and harvesting on the environment as well as on wild
geoduck populations, and the cultivation and harvesting of other non-
native species. Two commenters stated that geoduck cultivation and
harvesting has only minimal impacts.
When properly sited, operated, and maintained, commercial shellfish
aquaculture activities generally result in minimal adverse effects on
the aquatic environment and in many cases provide environmental
benefits by improving water quality and wildlife habitat, and providing
nutrient cycling functions. These activities are subjected to an
extensive amount of regulation at the Federal and state government
levels, and often the local government level. The introduction of
invasive species can occur through many mechanisms, and the types of
species approved for commercial aquaculture activities are regulated.
This NWP does not authorize discharges of dredged or fill material or
structures or work in navigable waters of the United States associated
with the cultivation of nonindigenous species that have not been
previously cultivated in the waterbody or the cultivation of aquatic
nuisance species as defined in the Nonindigenous Aquatic Nuisance
Prevention and Control Act of 1990. Furthermore, division engineers may
add regional conditions to the NWP to require permittees to use
specific practices that will prevent the spread of aquatic nuisance
species. Such measures may vary, depending on the species of concern
and which techniques would be the most effective means to prevent the
spread of such species. Adverse effects that may result from geoduck
cultivation are more appropriately addressed by Corps districts, since
this activity is limited in geographic scope. Division engineers may
regionally condition this NWP to restrict or prohibit its use to
authorize discharges of dredged or fill material into waters of the
United States or structures or work in navigable waters of the United
States associated with geoduck production.
Several commenters stated that the expansion of commercial
shellfish aquaculture activities will result in more than minimal
cumulative adverse effects and should not be authorized by NWP. One
commenter said that all activities authorized by this NWP should
require reporting to assess cumulative effects. Another commenter
suggested that cumulative effects on water quality should be evaluated
for water bodies with multiple aquaculture facilities.
As stated above, commercial shellfish aquaculture activities
provide habitat, water quality, and nutrient cycling functions and when
properly sited, operated, and maintained are unlikely to result in more
than minimal cumulative adverse effects on the aquatic environment.
Division engineers may restrict or prohibit use of this NWP in
geographic regions or specific waterbodies where more than minimal
cumulative adverse effects may occur.
One commenter stated that shellfish aquaculture activities have
economic impacts that were not sufficiently addressed in the draft
decision documents. For example, county and
[[Page 10232]]
state health agencies are required to regulate water quality, which
costs taxpayer money. This commenter said that changes to aesthetics
associated with expansion of these activities, such as noise, odor, and
viewshed impacts should also be considered. Impacts to recreational
uses of the affected waterbodies could occur if expansions greater than
100 acres in size are authorized. This commenter also said that new and
expanded operations should not be proposed in national parks or
historic monuments, but existing operations should be allowed to
continue. The commenter also stated that any projects in river delta
regions should be carefully evaluated due to the sensitive nature of
these brackish environments.
The draft decision documents briefly discuss economics as one of
the public interest review factors that are considered before the Corps
issues a permit, including a general permit. Shellfish aquaculture
activities, in general, help improve water quality because many of the
commercially cultivated species are filter feeders that remove
nutrients and suspended materials from the water column. By removing
nutrients, eutrophication and similar water quality problems are
lessened. Water quality benefits provided by commercially grown
shellfish help reduce costs of remediating local water quality
problems. Commercial shellfish aquaculture activities have minimal
adverse effects to aesthetics, and are likely to result in little
change in local baseline levels of noise, odor, or views when compared
to other waterfront uses in coastal residential areas, such as private
and commercial boats, as well as the piers, wharves, marinas, and
anchorage or mooring areas where those vessels are kept. Coastal areas
are used by a wide variety of people. Effects on recreational uses of
the waterbody should also be considered during the review of specific
commercial shellfish aquaculture activities. Division engineers may
regionally condition this NWP to restrict or prohibit its use to
authorize new project areas and/or new activities in existing project
areas in national parks or in the vicinity of historic monuments. The
protection of waters near river deltas or other categories of waters is
more appropriately accomplished through regional conditions imposed by
division engineers.
One commenter stated that because commercial shellfish aquaculture
may be limited by farm runoff, increasing production could require
farmland to cease in operation. Another commenter stated that shellfish
farming is a good gauge of water quality in an area since poor water
quality necessitates closure of shellfish farms. In contrast, another
commenter said the potential for aquaculture operations to harvest
continuously as farm size increased would result in permanently
suspended particulates and increased turbidity which would damage
ecosystems.
Changes in farming operations that may be related to commercial
shellfish aquaculture activities in nearby waters is outside of the
Corps regulatory authority. Such issues are more appropriately
addressed by state or local governments, who have the primary
responsibility for land use decisions. We recognize that commercial
shellfish aquaculture can help improve water quality. Harvesting
operations may increase turbidity, but we believe such impacts are
temporary and minor.
We received many comments in response to our proposal to consider
issuing a new NWP or modifying NWP 48 to authorize new commercial
shellfish aquaculture activities. Many commenters supported modifying
NWP 48 to authorize new activities, and suggested terms and conditions.
One commenter recommended limiting new activities to ten acres or less.
One commenter stated that there should be no limits on new activities
because shellfish aquaculture has only minimal, short-term adverse
environmental impacts, and the shellfish themselves provide valuable
ecological services. Two commenters stated that all new shellfish
aquaculture activities except floating culture should be authorized
under the NWP, because floating facilities have potential to impact
navigation. One commenter said limitations on new activities should be
imposed on NWP 48 and reconsidered when the proposal to reissue the
NWPs is developed in 2016. Other commenters said that new activities
should not be authorized by NWP because of their environmental impacts.
Another commenter stated that new activities should not be authorized
by NWP unless bottom culture methods are used (except for grow-out
bags), harvesting is done by hand, and only native species are
cultivated. One commenter stated that baseline habitat assessments
should be provided and no operations should occur within 180 feet of
marine vegetation, eelgrass, or sand dollar beds.
We are modifying NWP 48 to authorize commercial shellfish
aquaculture activities in new project areas, provided the project
proponent obtains a valid authorization (e.g., a lease or permit from
the appropriate state or local government agency responsible for
granting such leases or permits) and the activity will not directly
affect more than \1/2\-acre of submerged aquatic vegetation beds. Pre-
construction notification is required for all commercial shellfish
aquaculture activities in new project areas. Pre-construction
notification is also required for activities in a project area if they
involve dredge harvesting, tilling, or harrowing in areas inhabited by
submerged aquatic vegetation or if the activities involve the change
from bottom culture to floating or suspended culture in order to assess
potential impacts to navigation. In addition, general condition 14,
proper maintenance, requires the permittee to properly maintain any
authorized structure or fill. Therefore, any authorized commercial
shellfish aquaculture activity and its associated equipment shall be
properly maintained so as to not pose a hazard to navigation. The pre-
construction notification thresholds will provide an opportunity for
district engineers to evaluate the potential adverse effects to
navigation and vegetated shallows, conservation, and other applicable
public interest review factors, and ensure that those adverse effects
are minimal. We agree that commercial shellfish aquaculture activities
can provide important functions and services to the aquatic environment
and should be authorized by NWP, with appropriate notification
thresholds and limits. Division engineers may regionally condition this
NWP to restrict or prohibit its use in specific waters or geographic
areas, if there are concerns that these activities may have more than
minimal adverse effects on certain species or specific types of aquatic
resources.
This NWP is reissued with the modifications discussed above.
NWP 49. Coal Remining Activities. We proposed to clarify how the 40
percent of newly mined area is determined. We also proposed to modify
the pre-construction notification provision to require the prospective
permittee to submit documentation describing how the overall mine plan
will result in a net increase in aquatic resource functions.
Several commenters supported the reissuance of NWP 49 and said no
restrictions should be imposed because remining permits are one of the
most significant tools to alleviate the environmental effects of past
mining activities. Many commenters said this NWP should not be
reissued. Some of these commenters stated that these activities result
in more than minimal cumulative adverse effects. Many commenters
objected to the lack of
[[Page 10233]]
limits for filling stream channels and said this NWP should not
authorize the construction of valley fills or refuse fills. Other
commenters stated that the functional increase associated with re-
mining will still be insufficient to offset adverse effects of filling
stream beds and that stream mitigation will not effectively replace
lost stream functions.
We believe authorizing remining of an unreclaimed site and
requiring actions to restore unreclaimed areas is one of the most
effective ways to reverse degraded water quality in a watershed.
Therefore, we have not imposed any new limits or restrictions on this
NWP. All activities authorized by this NWP must result in net increases
in aquatic resource functions, which will help manage cumulative
effects on a watershed basis. Cumulative effects assessments have
revealed the reduction in acid mine drainage and/or sedimentation in
downstream segments of stream channels has resulted in functional
improvements in many watersheds. The states of Ohio, Pennsylvania,
Virginia, and West Virginia frequently use remining activities to
reduce acid mine drainage and sedimentation and have data to
demonstrate these improvements.
We do not believe this permit should have linear foot or acreage
limits, since this NWP authorizes discharges of dredged or fill
material into waters of the United States to reclaim previously mined
sites that were unreclaimed, abandoned, forfeited, and typically
exhibit poor water quality and present safety hazards. These
unreclaimed mines may have unreclaimed highwalls, unvegetated mine
spoil, disconnected stream segments, and/or pit impoundments. We, as
well as other state and federal agencies, recognize that remining and
reclaiming these areas is one of the most successful means for
improving water quality, because these activities reduce sedimentation
and acid mine drainage. Due to advances in mining technology and
equipment, it is now economically viable to remove coal from these
unreclaimed and abandoned mine sites. These sites can be combined with
adjacent unmined areas to develop a project that is economically
viable. In many cases the net result of combining remining of a
previously mined site with new surface coal mining activities in
adjacent areas is to facilitate reclamation of the older mine site and
reduce acid mine drainage and sediment from the older mine site to
downstream stream segments. Furthermore, this NWP provides an incentive
to remine degraded areas, similar to the 1987 Rahall Amendments to the
Clean Water Act, which enables mine operators to apply for the U.S.
Environmental Protection Agency's modified effluent limits developed
specifically for remining projects.
Project proponents who want to use this NWP must submit pre-
construction notifications. The pre-construction notification describes
how the overall mining plan will result in a net increase in aquatic
resource functions. If there is an appropriate functional assessment
protocol available for the types of aquatic resources in that
geographic area, project proponents are encouraged to use that
functional assessment protocol to demonstrate how the activity will
result in a net increase in aquatic resource functions. The description
of the proposed project required by paragraph (b)(3) of general
condition 31 should describe the restoration that will take place on
the project site. District engineers may add activity-specific
conditions to this NWP to require more detailed restoration plans prior
to discharging dredged or fill material into waters of the United
States, as well as monitoring plans that will be used to assess whether
the remining and associated reclamation activities are resulting in net
increases in aquatic resource functions. Supplemental compensatory
mitigation may be required in some instances, such as the
implementation of mitigation projects near the project site, to remove
or reduce causes of aquatic resource impairment and ensure that the
overall activity not only results in minimal individual and cumulative
adverse effects on the aquatic environment but in a net increase in
aquatic resource functions, as required by this NWP.
Several commenters indicated the general public should have the
right to comment on the proposal before the district engineer issues
the NWP verification. One commenter said all activities associated with
remining should require individual permits and another commenter
objected to combining unmined lands required for restoration with
previously mined lands because that would categorize unmined land as
unreclaimed land, and result in additional adverse environmental
effects. One commenter stated that slurry impoundments should not be
authorized by this NWP.
We believe these activities are appropriate for general permit
authorization and should not require a public notice and comment
process. District engineers may assert discretionary authority and
require an individual permit for proposed activities if they believe
those activities will result in more than minimal adverse effects on
the aquatic environment. It is appropriate to authorize discharges of
dredged or fill material into waters of the United States for some new
mining activities, to provide an incentive to restore unreclaimed mine
lands, and provide net increases in aquatic resource functions. Impacts
to the newly mined area would not be categorized as remining. Adverse
effects to waters of the United States associated with the new mining
would be subject to the general condition 23, mitigation, and the
district engineer may add conditions to the NWP authorization to
require mitigation located near the project site or out-of-kind
mitigation to compensate for losses of aquatic resource functions.
Typical surface coal mining projects, including remining, do not
include slurry impoundments, as these impoundments are typically
associated with the wastewater resulting from coal processing plants.
This NWP does not authorize the construction of coal processing plants.
Many commenters said the Corps is making the review process
associated with NWP 49 more onerous, which will decrease the utility of
the NWP, and should focus on the environmental benefits that can be
realized from this nationwide permit.
The proposed changes to this NWP, which we are adopting, do not
make it more difficult to use NWP 49. The requirement to provide
information with the pre-construction notification to explain how the
overall activity will result in net increases in aquatic resource
functions is necessary to ensure compliance with the terms and
conditions of the NWP. Clarification of how to apply the 40 percent
provision to determine how much new area could be mined will provide
consistency in implementation. For example, a site may be proposed to
be remined under this NWP. If 30 acres of the site has been previously
mined and is proposed to be remined, and 30 acres of the site is
unmined and is necessary to make it economically feasible to reclaim
the remined area, then 40% of the combined acreage of the remined and
reclaimed areas, or 40% of 60 acres which equals 24 acres, can be newly
mined. In another example, if you have a 1,000-acre site, and 600 acres
are affected by previously unreclaimed mining activities and 200 acres
are needed to reclaim the 600 acres, then 40% of 800 acres (the
summation of the previously unreclaimed mining activities site and the
site needed to reclaim the previously mined site), or 320 acres may be
newly mined. As there are only 200 acres remaining at the 1,000-acre
site, those 200 acres may be
[[Page 10234]]
authorized under NWP 49 for newly mined activities.
One commenter said they did not understand the rationale for
establishing the threshold for newly mined areas at 40 percent, if
removing the small amount of remaining coal reserves will be far more
attractive to coal mine operators if the percentage was increased to
allow mining on larger areas of unmined lands. One commenter said the
40 percent limitation becomes an obstacle when the remaining coal seam
is deep within the hillside and large amounts of overburden require
removal. This commenter suggested increasing the limit for newly mined
areas to 50 or 60 percent to encourage more restoration of unreclaimed
areas. The commenter recommended adding a provision allowing district
engineers to waive the 40 percent threshold in certain situations, such
as when the operator receives an approved pollution abatement plan with
best management practices, the remining activity is located in a
completed Acid Mine Drainage Abatement Treatment watershed area, and
watersheds with established total daily maximum loads. Several
commenters objected to the provision stating that the Corps would
consider the SMCRA agency's decision regarding the amount of currently
undisturbed adjacent lands needed to facilitate the remining and
reclamation of the previously mined area, stating that it creates
duplicative and potentially conflicting layers of regulation to an
already highly regulated industry.
The 40 percent limit was established when NWP 49 was first issued
in 2007, and was based on the recognition that some new coal mining may
have to be conducted to provide incentives to remine and reclaim
previously mined lands. The 40 percent limit is intended to facilitate
compliance with the minimal adverse effects requirement for the NWPs.
We do not agree that it would be appropriate to add a provision
allowing district engineers to waive the 40 percent limit. Remining and
reclamation activities involving discharges of dredged or fill material
into waters of the United States that require larger proportions of
newly mined areas may be authorized by individual permits. The
expertise provided by the agencies responsible for implementing SMCRA
is necessary to help the Corps make its determination of compliance
with the terms and conditions of this NWP.
One commenter stated this NWP should look holistically at overall
water and site improvements, improvement in the safety of the area by
the elimination of pits and highwalls, and reclamation of sites without
the use of public funds.
We have focused this NWP on authorizing those activities that
provide net increases in aquatic resource functions. The consideration
of overall site improvements, increased safety, and the lack of use of
public funds is more appropriately addressed by other agencies or
programs.
This NWP is reissued as proposed.
NWP 50. Underground Coal Mining Activities. We proposed to place a
\1/2\-acre limit on this NWP, as well as a 300-linear foot limit for
losses of stream bed. We also proposed a provision that allows district
engineers to waive the 300 linear foot limit for losses of intermittent
or ephemeral stream bed by making a written determination concluding
that the discharge of dredged or fill material will result in minimal
adverse effects.
Several commenters objected to the reissuance of this NWP, stating
that it authorizes activities with more than minimal individual and
cumulative adverse effects on the aquatic environment. Several
commenters stated that activities authorized by this NWP will result in
the loss of stream functions and adversely impact water quality
downstream of the mine site. Several commenters said this NWP does not
comply with the Section 404(b)(1) Guidelines and that the cumulative
impacts analysis is too general and fails to consider past actions.
We have imposed a \1/2\-acre limit on this NWP, as well as a 300
linear foot limit for the loss of stream bed. Pre-construction
notification is required for all activities authorized by this NWP, and
the permittee may not begin work in waters of the United States until
an NWP verification is issued by the district engineer. These
requirements, as well as the ability of district engineers to exercise
discretionary authority and modify the NWP authorization by imposing
activity-specific conditions, will help ensure that the NWP authorizes
only those activities with minimal individual and cumulative adverse
effects on the aquatic environment. Division engineers may regionally
condition this NWP to restrict or prohibit its use in specific
geographic regions, waters, or watersheds if the use of this NWP would
authorize activities with more than minimal individual and cumulative
adverse effects. When reviewing pre-construction notifications,
district engineers will also evaluate whether the proposed activity
will cause more than minimal direct and indirect adverse effects to
water quality downstream of the mine site. The issuance of this NWP
complies with the 404(b)(1) Guidelines, and we have complied with the
requirements at 40 CFR 230.7. The cumulative effects analysis provided
in the decision document in accordance with the National Environmental
Policy Act considers the effects of past actions, to the extent that
they have continuing effects on the aquatic environment. Under the
404(b)(1) Guidelines, the cumulative effects analysis involves
prediction of the number of discharges likely to be regulated by a
general permit until its expiration (see 40 CFR 230.7(b)(3)). That
regulation, as well as 40 CFR 230.11(g), does not state that the
effects of past actions have to be considered for the purposes of the
404(b)(1) Guidelines analysis, although, as stated above, we have
considered such effects in connection with our NEPA analysis.
Several commenters stated that NWP 50 should not have any acreage
and/or linear foot limitations as these limits would essentially render
the permit unusable for underground mining operations.
We do not agree that the \1/2\-acre limit and the 300 linear foot
limit for stream bed losses make this NWP unusable. This NWP authorizes
discharges of dredged or fill material into waters of the United States
for underground coal mining activities, provided those activities
result in minimal adverse effects on the aquatic environment. Since
these coal mining activities occur underground, losses of waters of the
United States are usually small in size because they are limited to
discharges of dredged or fill material in waters of the United States
to construct infrastructure and impoundments to support those mining
activities. Underground coal mining activities that result in the loss
of greater than \1/2\-acre of waters of the United States, or more than
300 linear feet of perennial stream bed, may be authorized by
individual permits or, if available, regional general permits.
One commenter stated that districts have incorrectly classified
perennial streams and that impacts to special aquatic sites (e.g.,
riffle and pool complexes) have not been properly considered. Another
commenter said that Clean Water Act jurisdiction does not extend to
ephemeral and intermittent streams. Several commenters indicated stream
mitigation measures are not effective and the Corps has failed to
provide a rational explanation as to how mitigation will attenuate
cumulative effects.
Classifying a stream as perennial, intermittent, or ephemeral is
done by district engineers by evaluating available information on
stream flow,
[[Page 10235]]
including information that may be submitted by a project proponent in
support of a pre-construction notification. A site visit may also be
conducted to identify perennial, intermittent, or ephemeral stream
segments. Impacts to special aquatic sites such as riffle and pool
complexes will be considered when reviewing a pre-construction
notification, and discretionary authority will be asserted if the
district engineer determines that the adverse effects on the aquatic
environment are more than minimal. Both intermittent and ephemeral
streams are subject to Clean Water Act jurisdiction if they are
determined by district engineers to be waters of the United States
after applying the appropriate regulations and guidance. Stream
rehabilitation and enhancement activities have been shown to improve
the ecological functions provided by those aquatic ecosystems. Stream
compensatory mitigation projects must comply with the applicable
requirements provided in general condition 23, mitigation, and the
compensatory mitigation regulations at 33 CFR 320.4(r) and 33 CFR part
332. District engineers will review and approve mitigation plans, and
will require alternative or additional compensatory mitigation if they
determine the proposed compensatory mitigation will not be sufficient
to successfully offset the losses of aquatic resources caused by the
permitted activity. Compensatory mitigation projects must be
implemented in accordance with their approved mitigation plans.
District engineers will also require monitoring of these compensatory
mitigation projects, and require remediation and adaptive management if
those mitigation projects are not providing the intended aquatic
resource functions. If a district engineer determines that a
compensatory mitigation project is not ecologically successful and
fails to fulfill its objectives, district engineers may require
alternative compensatory mitigation to comply with the mitigation
requirements established through conditions added to the NWP
authorization.
Several commenters indicated the activities regulated by this NWP
are also heavily regulated by SMCRA, the Federal Mine Safety and Health
Act (MSHA), and the state mining and water resource programs;
therefore, no limits should be imposed on the permit. One commenter
said the limits and the waiver process is highly subjective and results
in uncertainty in the Regulatory Program. One commenter stated that
limitations imposed on this NWP could potentially require applicants to
seek individual permits for all underground mining actions, which may
result in a requirement to prepare an environmental impact statement.
This commenter said that there should be a transition period without
acreage or linear foot limits so that underground coal mining
activities could continue to be authorized by this NWP until an
individual permit can be obtained. One commenter said that reissuing
NWP 50 with the \1/2\-acre and 300 linear foot limits would result in
significant job losses for their company, which consists of Native
Americans who comprise 62 percent of their workforce. One commenter
said that the new limits on this NWP would also increase the Corps
workload.
This NWP provides authorization required under Section 404 of the
Clean Water Act, for discharges of dredged or fill material into waters
of the United States. The acreage and linear foot limits of this NWP
are necessary to ensure that authorized activities result in minimal
adverse effects on the aquatic environment. Compliance with other laws
may be required for surface coal mining activities, but those decisions
are made by the agencies responsible for administering those laws.
District engineers will consider the criteria in paragraph (1) of
section D, ``District Engineer's Decision'' and other appropriate
criteria, when making a minimal effects determination for a proposed
NWP activity. Activities that result in the loss of greater than \1/2\-
acre of waters of the United States require individual permits, unless
those activities qualify for applicable regional general permits. If an
individual permit is required, district engineers will determine
whether an environmental impact statement is necessary to comply with
the requirements of the National Environmental Policy Act. We do not
agree that there should be a transition period for these activities,
because the acreage and linear foot limits are necessary to comply with
Section 404(e) of the Clean Water Act, and past use of this NWP
indicates that the average loss of waters of the United States was 0.21
acre per NWP 50 activity. While there might be an increase in the
number of individual permits, we do not believe it will be a large
workload increase. As with all NWPs, an activity that was authorized
under the 2007 NWPs has until March 18, 2013, to be completed under
this authorization.
One state agency indicated implementation of the limits would
result in increased workload for their staff and requested that funding
be provided to their office to mitigate this increase. One commenter
stated that sites which contain reclaimed and abandoned mines
associated with deep mining operations with portals and/or bat habitat
should be assessed for bat use.
Any workload increase due to the addition of the \1/2\-acre and 300
linear foot limits would be borne primarily by the Corps districts. It
does not directly impose additional workload on state agencies. The
SMCRA permits required for all mining activities must go through
advanced coordination with the U.S. Fish and Wildlife Service regarding
endangered bat species and with the State natural resources agencies
regarding state listed bat species. Effects to wildlife, including
bats, that are not federally-listed as endangered or threatened, or
state-listed bat species, will also be addressed through the SMCRA
permit process. For federally-listed bat species, activities authorized
by this NWP must also comply with general condition 18, endangered
species.
This NWP is reissued as proposed.
NWP 51. Land-Based Renewable Energy Generation Facilities. This NWP
was proposed as NWP A to authorize the discharges of dredged or fill
material into non-tidal waters of the United States, excluding non-
tidal wetlands adjacent to tidal waters, for the construction,
expansion, or modification of land-based renewable energy production
facilities. Examples include infrastructure to generate solar
(concentrating solar power and photovoltaic), biomass, wind or
geothermal energy and their collection systems. Attendant features may
include, but are not limited to roads, parking lots, utility lines, and
stormwater management facilities. We proposed a \1/2\-acre limit for
this NWP, including the loss of no more than 300 linear feet of stream
bed, unless for intermittent and ephemeral stream beds the district
engineer waives this 300 linear foot limit by making a written
determination concluding that the discharge will result in minimal
adverse effects.
Several commenters objected to the issuance of this NWP, stating
that the Corps had failed to explain why the direct and indirect
impacts resulting from the land-based renewable energy projects
authorized by this NWP would be minimal, including the impacts caused
by construction and operation of these facilities. These commenters
said that individual permits should be required for these facilities.
One of these commenters said that biomass facilities will significantly
add to greenhouse gas
[[Page 10236]]
emissions and expressed the belief that biomass facilities will lead to
increased land-clearing for harvest, planting and re-planting of trees.
Several commenters stated that wind turbines will cause direct
mortality on birds and bats and adversely affect critical avian and bat
habitat. Two commenters stated that wind-generated energy facilities
should incorporate guidelines developed by the U.S. Fish and Wildlife
Service to minimize impacts to avian and bat species. One commenter
stated that land-based wind and solar renewable energy facilities are
not water dependent and should always require individual permits to
allow for a thorough alternatives analysis for site selection. Several
commenters stated that the activities authorized by this NWP are not
similar in nature, since they involve various types of renewable energy
facilities that have different adverse environmental effects.
This NWP authorizes discharges of dredged or fill material into
waters of the United States for the construction, expansion, or
modification of land-based renewable energy facilities. Unless the
operation of these facilities involves discharges of dredged or fill
material into waters of the United States, the Corps does not
authorize, or have any Federal control or responsibility over, their
operation. We believe that the construction, expansion, or modification
of these facilities has minimal adverse effects on the aquatic
environment, individually and cumulatively. Division engineers can
regionally condition this NWP to restrict or prohibit its use in waters
of the United States, where the discharges of dredged or fill material
are likely to result in more than minimal adverse effects on the
aquatic environment. While there may be emissions of greenhouse gases
during construction activities involving discharges of dredged or fill
material into waters of the United States, those direct emissions will
generally not exceed de minimus levels of a criteria pollutant or its
precursors and are exempted by 40 CFR 93.153. Emissions of greenhouse
gases that occur from the operation of a land-based renewable energy
generation facility, as well as emissions that occur when harvesting
plant material for biomass energy production and operating the energy
generation facility, are outside the Corps scope of analysis under the
National Environmental Policy Act, because the Corps does not have the
legal authority to control such emissions. The 404(b)(1) Guidelines do
not include any requirements to assess effects of proposed discharges
of dredged or fill material into waters of the United States on
greenhouse gas emissions. Land clearing that may be conducted for the
harvesting, planting, and replanting of trees that provide fuel for
biomass energy facilities is not authorized by this NWP, and if such
activities involve discharges of dredged or fill material into waters
of the United States, a separate Department of the Army permit is
required.
If the construction, expansion, or modification of a land-based
renewable energy facility involves discharges of dredged or fill
material into waters of the United States, and that activity may affect
an endangered or threatened species, or is located in designated
critical habitat, Endangered Species Act Section 7 consultation is
required, and the activity cannot proceed until section 7 consultation
is completed. We have added general condition 19, migratory birds and
bald and golden eagles, to clarify that if an activity regulated by the
Corps will result in the ``take'' of a migratory bird or a Bald or
Golden Eagle, and a ``take'' permit is required from the U.S. Fish and
Wildlife Service, it is the responsibility of the permittee to apply
for, and obtain, the appropriate ``take'' permits from the U.S. Fish
and Wildlife Service. The draft Land-based Wind Turbine Guidelines
developed by the U.S. Fish and Wildlife Service are voluntary
guidelines that project proponents may incorporate into their land-
based wind energy projects. The Corps does not have the authority to
condition this NWP to incorporate the recommendations provided in those
guidelines. Water dependency is not a requirement for authorization by
general permit, including nationwide permits. The water dependency test
in the 404(b)(1) Guidelines guides the alternatives analysis for
activities that require individual permits under Section 404 of the
Clean Water Act.
The activities authorized by this NWP (i.e., discharges of dredged
or fill material into waters of the United States for the construction,
expansion, or modification of land-based renewable energy facilities)
are similar in nature. The Corps interprets the ``similar in nature''
requirement in Section 404(e) of the Clean Water Act broadly, to cover
general categories of activities. The discharges of dredged or fill
material authorized by this NWP will have similar effects on the
aquatic environment, by replacing waters of the United States with dry
land, or altering their characteristics, when renewable energy
facilities are constructed, modified, or expanded.
Two commenters expressed concern that if NWP A is issued, all land-
based renewable energy facilities will require pre-construction
notification because they could only be authorized by this NWP. Several
commenters stated that NWP A should not be issued because all types of
land-based renewable energy facilities can be authorized by existing
NWPs, such as NWPs 12, 14, 18, 25, and 39, and it is not necessary to
issue a new NWP that requires pre-construction notification for all
activities. They also said that the issuance of NWP A would contradict
the Corps stated goals of reducing administrative burdens on the
regulated public, and utilizing its resources to focus on those
projects that could be more environmentally damaging. One commenter
stated that the pre-construction notification requirement would cause
an unnecessary burden on project proponents, especially the requirement
to provide a delineation of waters of the United States in the project
area.
We are retaining the requirement that all activities authorized by
this NWP require pre-construction notification, so that district
engineers can evaluate these activities and add activity-specific
conditions, if necessary, to ensure that they result in minimal
individual and cumulative adverse effects on the aquatic environment.
Other NWPs may be used to authorize discharges of dredged or fill
material into waters of the United States for activities that may be
associated with land-based renewable energy facilities. We do not
intend issuance of this NWP to restrict currently available options for
use of other NWPs to authorize any such discharges. For example, NWP 12
may be used to authorize discharges of dredged or fill material
associated with the construction, maintenance, repair, or removal of
utility lines for land-based renewable energy facilities. Likewise, NWP
14 may be used to authorize road crossings in waters of the United
States within a land-based renewable energy facility. Project
proponents may specify which NWP they wish to use to provide the
requisite Department of the Army authorization under Section 404 of the
Clean Water Act and/or Section 10 of the Rivers and Harbors Act of
1899. If the proposed activity qualifies for authorization under that
particular NWP, the district engineer will issue a verification letter.
This NWP fulfills the objectives of the NWP program, since many land-
based renewable energy projects require discharges of dredge or fill
material into waters of the United States that would not qualify for
NWPs 12 or 14, or other NWPs that do not require pre-construction
notification.
One commenter suggested changing the pre-construction notification
[[Page 10237]]
threshold to \1/10\-acre, so that compensatory mitigation would not be
required for activities resulting in the loss of less than \1/10\-acre
of waters of the United States. Another commenter said that requiring
pre-construction notification for losses of less than \1/10\-acre
removes incentives to minimize losses of waters of the United States to
less than \1/10\-acre. Two commenters stated that increasing the pre-
construction notification threshold to \1/10\-acre would be more
consistent with Executive Order 13212, Actions To Expedite Energy-
Related Projects.
We do not agree that the pre-construction notification threshold
should be increased to \1/10\-acre to match the pre-construction
notification thresholds for NWP 12 or 14, since utility lines or road
crossings may be only partial components of a land-based renewable
energy generation facility. It should be noted that NWP 14 requires
pre-construction notification for any discharge into a special aquatic
site, including wetlands, which means that many NWP 14 activities that
result in a loss of less than \1/10\-acre require pre-construction
notification. Nationwide permit 12 should be used when the only
activities that require Department of the Army authorization are
discharges of dredged or fill material to construct, maintain, repair,
or remove utility lines. Therefore, in Note 1 we state that NWP 12 is
to be used to authorize those utility line activities, as long as those
activities comply with the terms and conditions of NWP 12, including
applicable regional conditions and any case-specific conditions imposed
by the district engineer. This NWP authorizes building pads for the
renewable energy generation devices and attendant features associated
with those devices, such as parking lots and stormwater management
facilities. If more than one NWP is used to authorize a land-based
renewable energy generation facility, the activity must comply with
general condition 28, use of multiple nationwide permits, which states
that the loss of waters of the United States cannot exceed the acreage
limit of the NWP with the highest specified acreage limit. Compensatory
mitigation is at the discretion of the district engineer, and will be
required when necessary to ensure that the authorized activity results
in minimal individual and cumulative adverse effects on the aquatic
environment. Paragraph (a) of general condition 23, mitigation,
requires permittees to avoid both temporary and permanent adverse
effects to waters of the United States on the project site. The
issuance of this NWP supports the objective of Executive Order 13212,
by providing NWP authorization for some activities that would otherwise
require individual permits because they do not qualify for any of the
existing NWPs.
Two commenters agreed that NWP A is needed but said that many land-
based renewable energy projects would not qualify because the losses of
waters of the United States frequently exceed the acreage or linear
foot limits. One commenter suggested increasing the acreage limit to
one acre and the linear foot limit to 500 linear feet of stream bed,
and allow the district engineer to waive the 500 linear foot limit if
he or she determines that the activity will result in minimal adverse
environmental effects. One commenter stated that NWP A should not allow
waivers for stream bed losses in excess of 300 linear feet.
We believe that there will be a sufficient number of land-based
renewable energy generation facilities authorized by this NWP to
warrant its issuance. As with all general permits, this NWP will also
provide an incentive for project proponents to reduce losses of waters
of the United States to qualify for NWP authorization, instead of
having to apply for individual permit authorization, if there are no
regional general permits available to authorize these activities. The
\1/2\-acre and 300 linear foot limits are necessary to ensure that this
NWP authorizes only those activities that have minimal individual and
cumulative adverse effects on the aquatic environment, and are
consistent with the limits in many other NWPs. Division engineers can
regionally condition this NWP to reduce the acreage limit or linear
foot limits, or revoke this NWP in specific waters or geographic areas
where the adverse effects on the aquatic environment may be more than
minimal. In response to a pre-construction notification, the district
engineer may add activity-specific conditions to the NWP authorization
to impose requirements to satisfy the minimal adverse environmental
effect requirement. The 300 linear foot limit for the loss of
intermittent and ephemeral stream bed can only be waived when the
district engineer makes a written determination that the loss of that
stream bed will result in minimal adverse environmental effects, after
evaluating the site-specific characteristics of the project.
Several commenters said that all pre-construction notifications
should be coordinated with other Federal and state agencies. One
commenter stated that agency coordination should be required whenever a
request for a waiver of the 300 linear foot limit is being evaluated by
the district engineer. One commenter stated that this NWP should not
include the waiver provision because of potential impacts to cultural
resources and historic properties.
We do not believe it is necessary to coordinate all activities
authorized by this NWP with Federal and state agencies. District
engineers will carefully evaluate these pre-construction notifications
and determine whether the proposed activities qualify for NWP
authorization. Agency coordination is required for pre-construction
notifications for proposed activities resulting in the loss of
intermittent or ephemeral stream bed in excess of 300 linear feet.
Activities authorized by this NWP must also comply with general
condition 20, historic properties and district engineers will conduct
section 106 consultation if a proposed activity may have the potential
to cause effects to any historic properties listed, or eligible for
listing, on the National Register of Historic Places.
Several commenters requested clarification on whether land-based
renewable energy facilities would be considered as single and complete
linear projects or single and complete non-linear projects. Several
commenters asked if the linear features of these facilities, such as
roads, utilities, and transmission lines, could be categorized as
linear projects, while the construction of other components of the
project, such as parking lots and buildings, would be considered as
non-linear projects. A few commenters said terms and conditions should
be added to the NWP to specify that the definition of single and
complete linear project would always be used for linear components of
the overall facility. One commenter stated that the activities
authorized by this NWP should be considered one single and complete
project because all renewable energy devices and their attendant
features, including both linear and non-linear components, are required
for the facility to have independent utility.
We have added Note 1 to this NWP to clarify that the NWP authorizes
discharges of dredged or fill material into waters of the United States
for the construction, expansion, or modification of a land-based
renewable energy generation facility, including attendant features
within that facility, and that utility lines that are used to transfer
energy from the renewable energy generation facility to a distribution
system, regional grid, or other facility are generally considered to
[[Page 10238]]
be separate single and complete linear projects. Those utility lines
may be authorized by NWP 12 or other Department of the Army
authorization. A similar approach should be used for roads or other
types of utility lines (e.g., sewage or water lines) constructed to
provide access to, or service, the land-based renewable energy
generation facility. We are using the term ``generally'' in Note 1
because crossings of waters of the United States have to be at separate
and distant locations to be a single and complete project. Crossings
that are close together would not be considered separate single and
complete projects. Since the configuration of land-based renewable
energy generation facilities can vary substantially, district engineers
will use their discretion to determine which activities are single and
complete linear projects and which activities are single and complete
non-linear projects, after evaluating the specific circumstances of a
particular project. For example, the devices used to collect wind or
solar energy may be arranged in a grid or in a linear configuration.
One commenter asked how the permit area would be determined for
land-based renewable energy facilities. Specifically, the commenter
asked whether the permit area would be the entire area bound by the
perimeter of the facility, or just those areas within the facility
where there are discharges of fill material into waters of the United
States.
Identifying the permit area for the purposes of compliance with
general condition 20, historic properties, is accomplished by applying
the criteria in Appendix C to 33 CFR part 325, specifically paragraph
1(g), as well as the interim guidance issued on April 25, 2005
(paragraph 6(d)). The permit area will be determined by district
engineers after considering the project-specific circumstances.
Several commenters stated that this NWP should not authorize
activities in certain geographic areas, such as the Great Lakes. One
commenter said that approval may be required for facilities that would
impact state-owned waters or submerged lands.
Division engineers have the authority to suspend or revoke this NWP
in specific waters or geographic areas. Division engineers may also add
regional conditions to restrict or prohibit its use in certain waters
or regions. In response to a pre-construction notification, district
engineers may add activity-specific conditions to the NWP authorization
to ensure that the activity results in minimal adverse effects on the
aquatic environment. Project proponents must obtain all applicable
Federal, state, or local authorizations, such as state permits to
authorize activities on state-owned waters or submerged lands.
One commenter said that this NWP could be used to authorize
activities associated with wind energy generating structures, solar
towers, or overhead transmission lines, which have the potential to
interfere with Department of Defense's long range surveillance,
homeland defense, testing, and training missions. This commenter
requested that copies of pre-construction notifications and NWP
verification letters for these activities be provided to the Department
of Defense Siting Clearinghouse, so that the Department of Defense
could have an opportunity to coordinate with the project proponent to
ensure that long range surveillance, homeland defense, testing, and
training missions are not adversely affected by these activities.
We have added Note 2 to this NWP to require district engineers to
send pre-construction notifications and NWP verification letters to the
Department of Defense Siting Clearinghouse if this NWP is proposed to
be used to authorize the construction of wind energy generating
structures, solar towers, or overhead transmission lines. The
Department of Defense Siting Clearinghouse is responsible for
coordinating with the project proponent and resolving any potential
effects on Department of Defense long range surveillance, homeland
defense, testing, and training missions.
Proposed NWP A is issued as NWP 51, with the changes discussed
above.
NWP 52. Water-Based Renewable Energy Generation Pilot Projects.
This NWP was proposed as NWP B to authorize structures or work in
navigable waters of the United States and discharges of dredged or fill
material into waters of the United States, for the construction,
expansion, or modification of water-based wind or hydrokinetic
renewable energy generation pilot projects and their attendant
features. Attendant features may include, but are not limited to land-
based distribution facilities, roads, parking lots, utility lines, and
stormwater management facilities. We proposed a \1/2\-acre limit for
this NWP, including the loss of no more than 300 linear feet of stream
bed, unless for intermittent and ephemeral stream beds the district
engineer waives this 300 linear foot limit by making a written
determination concluding that the discharge will result in minimal
adverse effects.
Several commenters supported the issuance of this NWP. Some of
these commenters provided suggestions to improve the NWP. Two
commenters said the acreage limit should be increased from \1/2\-acre
to one acre and the linear foot limit be increased from 300 linear feet
to 500 linear feet. One commenter stated that the NWP limits impacts to
\1/2\-acre without taking into consideration the aggregate capacity of
the facility, only the number of generation units. One commenter said
the pre-construction notification threshold should be increased to \1/
10\-acre to be consistent with the pre-construction notification
threshold of some of the other NWPs that authorize similar activities,
such as NWP 12. This commenter asked why activities associated with
water-based renewable energy projects should be subject to closer
scrutiny than other energy-related activities.
We are issuing this NWP with the \1/2\-acre and 300 linear foot
limits, and restricting its use to pilot projects, to ensure that this
NWP authorizes only those activities that have minimal adverse effects
on the aquatic environment. Division engineers can impose regional
conditions on this NWP to decrease these limits, if there is potential
for these activities to result in more than minimal adverse effects on
the aquatic environment in a particular waterbody or geographic area.
Individual permits, with a public notice and comment process, should be
required for larger-scale water-based renewable energy generation
facilities that are not pilot projects and involve activities that
require Department of the Army authorization. Use of technologies other
than wind or hydrokinetic devices for water-based renewable energy
generation facilities may be authorized by other forms of Department of
the Army permits, if such permits are required for the construction,
expansion, modification, or removal of those devices. We are requiring
pre-construction notification for all activities authorized by this
NWP, so that district engineers can evaluate the proposed work and make
a project-specific determination that the adverse effects on
navigation, the aquatic environment, and other public interest review
factors would be minimal, individually and cumulatively. It should be
noted that NWP 12 only authorizes discharges of dredged or fill
material, or structures or work in navigable waters of the United
States, for the construction, maintenance, or repair of utility lines,
and that all NWP 12 activities in section 10 waters require
[[Page 10239]]
pre-construction notification. Therefore, there are few differences in
pre-construction notification thresholds for this NWP and other NWPs
that may authorize similar activities. However, as with NWP 51, it is
not our intent to limit any currently available options for use of
other applicable NWPs to cover discharges of dredge or fill material
associated with activities involved in the construction of water-based
renewable energy generation pilot projects. Rather, this NWP provides
an additional option for authorization of such discharges that are not
currently covered by any other NWP.
Several commenters also stated that the limit of 10 generation
units should either be eliminated or further defined. Several
commenters said the 10 generation unit limit should be removed to allow
projects that employ different technologies to be authorized by this
NWP. Several commenters said that the total number of generation units
should be defined as the total number of units per each single and
complete project.
We believe the 10-unit limit is necessary to ensure that these
pilot projects are small in scope, to ensure they would not have
significant adverse environmental effects. The 10-unit limit, as well
as the \1/2\-acre and 300 linear foot limits, apply to single and
complete projects. The information collected during these pilot
projects will be useful in evaluating the potential productivity,
feasibility, and environmental effects of larger scale water-based
renewable energy generation facilities, which will require other types
of authorization if they require DA permits.
Numerous commenters objected to the issuance of this NWP. Most of
these commenters said that these activities will result in more than
minimal individual and cumulative adverse effects on the aquatic
environment. Several commenters said that there is not sufficient
understanding of the environmental effects of these activities to
warrant issuance of an NWP. Some commenters stated that these
activities should be authorized by individual permits, with a full
public notice and comment process and National Environmental Policy Act
documentation. A few commenters said this NWP should not be used to
authorize activities in the Great Lakes.
The terms and conditions of this NWP, including the \1/2\-acre
limit, the 300 linear foot limit, and the 10-unit limit will ensure
that this NWP authorizes only those activities with minimal adverse
effects on the aquatic environment. All activities authorized by this
NWP require pre-construction notification, which provides district
engineers with the opportunity to review each proposed activity and
determine whether the adverse effects on the aquatic environment will
be minimal. District engineers may add activity-specific conditions to
the NWP authorization which require actions to mitigate adverse
environmental effects. District engineers may also exercise
discretionary authority to require an individual permit if permit
conditions will not be sufficient to comply with the minimal adverse
environmental effects requirement for general permits. Division
engineers may impose regional conditions to restrict or prohibit the
use of this NWP in certain waters or specific geographic areas,
including the Great Lakes.
Several commenters requested a definition of the term ``pilot
project.'' Some of these commenters said that this term could be
interpreted broadly, in part because much of the technology used for
water-based renewable energy generation facilities is in the early
stages of development. In contrast, another commenter stated that not
defining the term ``pilot project'' would restrict the applicability of
this NWP. One commenter suggested that this NWP not be limited to pilot
projects. One commenter recommended limiting pilot projects to those
that will be used as demonstration projects or test projects to
determine the practicability of water-based renewable energy generation
at a particular site. One commenter said that this NWP should not be
limited to small offshore wind energy pilot projects, and that this NWP
should authorize offshore wind energy projects of any duration to
encourage the development of renewable energy technologies.
We have added a provision to this NWP that defines the term ``pilot
project.'' The definition is similar to how the Federal Energy
Regulatory Commission describes hydrokinetic pilot projects in their
April 2008 white paper on licensing hydrokinetic pilot projects. The
definition in the NWP focuses on the experimental nature of pilot
projects, and their use in collecting data on the performance of the
device in generating energy for other uses and the effects of the
devices on the environment, including the aquatic environment. Due to
the recent development of this technology, we believe it is necessary
to limit these water-based renewable energy generation facilities to
pilot projects, to provide more information on potential adverse
effects to the aquatic environment. In a future reissuance of the NWPs,
we may consider expanding the scope of this NWP to authorize other
small-scale water-based renewable energy generation facilities. A
water-based renewable energy generation facility that is not a pilot
project and does not qualify for an applicable regional general permit
is more appropriately evaluated through the standard permit process,
including a full public interest review.
One commenter stated that even pilot projects may result in more
than minimal adverse effects on the aquatic environment because of
indirect effects caused by blade strikes on birds and potential
obstructions to navigation when these pilot projects are sited in
navigable rivers. One commenter said the 10 generation unit limit may
not be effective in ensuring that single and complete projects do not
cause more than minimal adverse environmental effects on a cumulative
basis or comply with monitoring requirements.
District engineers will review pre-construction notifications and
determine whether the proposed activity complies with all terms and
conditions of the NWP and may add activity-specific conditions, such as
authorizing less than 10 units, to minimize adverse effects to
navigation, the aquatic environment, and other public interest review
factors such as impacts to fish and wildlife values. Indirect effects
caused by the operation of these pilot projects, such as wind turbine
blade strikes on birds, should be addressed through compliance with the
appropriate Federal laws, such as the Endangered Species Act, Migratory
Bird Treaty Act, or Bald and Golden Eagle Protection Act. Compliance
with the Endangered Species Act is addressed through general condition
18. As stated in general condition 19, project proponents are
responsible for obtaining any take permits that may be required under
the Migratory Bird Treaty Act or the Bald and Golden Eagle Protection
Act. The project proponent should contact the local office of the U.S.
Fish and Wildlife Service to determine whether a take permit is
required for that project. Impacts to fish or other aquatic organisms
caused by hydrokinetic energy units should be considered by district
engineers when reviewing pre-construction notifications for activities
authorized by this NWP. District engineers may also suspend or revoke
NWP authorizations if they determine those activities are causing more
than minimal adverse environmental effects to the aquatic environment.
Division engineers may impose regional conditions on this NWP to reduce
the number of units authorized by this NWP, or restrict or prohibit its
use in specific waters or other geographic areas.
[[Page 10240]]
Several commenters requested clarification of applicability of the
300 linear foot stream limit to the ocean floor or the Great Lakes
because those waters are not characterized as streams. A few commenters
suggested that the 300 linear foot limit does not apply to water-based
renewable energy generation pilot projects in the ocean or large
rivers, since activities in those waters does not result in a loss of
stream bed.
We agree that the 300 linear foot limit does not apply to the
construction, expansion, modification, or removal of water-based wind
or hydrokinetic renewable energy devices in the ocean, Great Lakes, or
large navigable rivers, since those activities do not result in loss of
stream bed. The 300 linear foot limit also does not apply to the
installation or removal of transmission lines on the ocean floor, the
bottom of the Great Lakes, or the substrate of large navigable rivers.
Transmission lines placed on the bottom of navigable waters are
generally considered to be structures, not fill. District engineers
will evaluate the techniques used to place transmission lines on the
bottom of navigable waters and determine whether there is a discharge
of dredged or fill material, and whether that discharge of dredged or
fill results in a loss of waters of the United States subject to the
300 linear foot limit. The installation of transmission lines in these
navigable waters in trenches that are backfilled constitutes a
temporary impact and is not applied to the 300 linear foot limit for
the loss of stream bed. The 300 linear foot limit for the loss of
stream bed applies primarily to the construction of land-based
attendant features, such as distribution facilities, control
facilities, roads, parking lots, and stormwater management facilities.
We have added a provision to this NWP to clarify that the placement of
a transmission line on the bed of a navigable water of the United
States from the renewable energy generation unit(s) to a land-based
collection facility is considered a structure regulated under Section
10 of the Rivers and Harbors Act of 1899, and not a discharge of fill
material under Section 404 of the Clean Water Act. The placement of the
transmission line on the bed of the navigable water is not considered a
loss of waters of the United States that applies towards the \1/2\-acre
limit or 300 linear foot limit of the NWP.
Several commenters requested the addition of more categories of
sensitive habitat where this NWP could not be used to authorize
structures or work in navigable waters of the United States or
discharges of dredged or fill material into waters of the United States
for water-based renewable energy generation pilot projects. Two
commenters suggested adding coral reefs to the list of prohibited
areas. Another commenter suggested adding National wildlife refuges,
state parks, state wildlife management areas, designated significant
coastal areas, critical habitats for Federally-listed endangered and
threatened species, important bird areas, or any sensitive
environmental area. One commenter recommended adding eelgrass beds,
seagrass beds, kelp beds, macro-algae beds, vegetated shallows, and
shellfish beds to the list of excluded areas.
The proposed NWP B stated that it did not authorize activities in
coral reefs. This NWP is also subject to general condition 22,
designated critical resource waters, which prohibits using this NWP to
authorize discharges of dredged or fill material into critical resource
waters and their adjacent wetlands. Critical resource waters include
marine sanctuaries and marine monuments managed by the National Oceanic
and Atmospheric Administration, and National Estuarine Research
Reserves. District engineers may designate additional critical resource
waters, after notice and an opportunity for public comment. Division
engineers may also impose regional conditions to restrict or prohibit
the use of this NWP in specific categories of waters or in certain
geographic areas. In response to a pre-construction notification,
district engineers may exercise discretionary authority and require an
individual permit if the proposed activity will result in more than
minimal adverse effects on the aquatic environment.
One commenter said that district engineers should not be authorized
to waive the 300 linear foot limit for the loss of intermittent and
ephemeral stream bed. One commenter suggested that all pre-construction
notifications requesting a waiver of the 300 linear foot limit should
be coordinated with the Federal and state resource agencies.
For those losses of more than 300 linear feet of intermittent and
ephemeral stream bed that result in minimal adverse effects on the
aquatic environment, it is appropriate for district engineers to have
the authority to waive the 300 linear foot limit. This approach is
consistent with the statutory requirement that activities authorized by
general permits, including NWPs, result in minimal individual and
cumulative adverse environmental effects. Agency coordination is
required for proposed losses of greater than 300 linear feet of
intermittent and ephemeral stream bed.
Two commenters recommended adding a provision to this NWP that
requires the removal of structures associated with any activity
authorized under this NWP, once the pilot project has been completed.
One commenter suggested adding more examples of attendant features that
may be authorized by this NWP, such as control rooms, trailers, vaults
and sheds since these are common features of land-based distribution
facilities.
We have added a paragraph to this NWP that requires the permittee
to remove the generation units, transmission lines, and other
structures or fills associated with the pilot project once the pilot
project is completed, unless they are authorized by a separate
Department of the Army authorization, such as another NWP, an
individual permit, or a regional general permit. Pilot units may be
integrated into a permanent water-based renewable energy generation
facility after the experimental phase has been completed, and the
permanent facility has been authorized by any required Department of
the Army permits. We have also added ``removal'' to the first sentence
of this NWP, to clarify that the NWP also authorizes the removal of
structures and fills associated with water-based renewable energy
generation pilot projects, if, for example, the removal of structures
or fills from navigable waters of the United States would require
authorization under Section 10 of the Rivers and Harbors Act of 1899.
Furthermore, we added a clarification of ``completion of the pilot
project,'' which will be identified as the date of expiration of the
FERC (Federal Energy Regulatory Commission) license, or the expiration
date of the NWP authorization if no FERC license is issued. If the
project proponent wants to continue operating the pilot project after
the expiration of the FERC license, he or she should apply for another
form of DA permit, such as an individual permit. If the pilot project
was only authorized by NWP 52, it may be verified under a reissued NWP
52, if NWP 52 is reissued in 2017. Reauthorization under a reissued NWP
52 may require submission of a new pre-construction notification, to
ensure that the pilot project still meets the terms and conditions of
the reissued NWP 52. We have added ``control facilities'' to the list
of examples of attendant features.
One commenter recommended adding a note to the NWP to require a
mutual agreement between the Corps, the United States Coast Guard, and
a prospective permittee to ensure
[[Page 10241]]
navigational safety. One commenter stated that the NWP should include a
provision requiring compliance with state permit requirements to ensure
a consistent and thorough environmental review. One commenter said that
this NWP should require project proponents to comply with the
Department of the Interior's suggested practices for avian protection
to protect birds from electrocution.
We do not agree that it is necessary to require the execution of
agreements between the Corps, United States Coast Guard, and the
prospective permittee to ensure navigation safety. District engineers
will review pre-construction notifications and exercise discretionary
authority if the proposed activity will have more than minimal adverse
effects on navigation. The permittee must comply with applicable United
States Coast Guard requirements to mark or light structures in
navigable waters. It is the permittee's responsibility to obtain any
other Federal, state, or local authorizations that may be required for
the water-based renewable energy generation pilot project. The
permittee may voluntarily incorporate into his or her project the
Department of the Interior's recommended practices for protecting birds
from electrocution. If the proposed NWP activity may affect endangered
or threatened bird species, Endangered Species Act Section 7
consultation will be conducted, which may also address potential
effects to those species caused by electrocution. In accordance with
general condition 19, migratory birds and bald and golden eagles, it is
the permittee's responsibility to obtain any ``take'' permits that may
be required under the U.S. Fish and Wildlife Service's regulations
governing compliance with the Migratory Bird Treaty Act and the Bald
and Golden Eagle Protection Act.
One commenter said that this NWP could be used to authorize
activities associated with wind energy generating structures, solar
towers, or overhead transmission lines, which have the potential to
interfere with Department of Defense's long range surveillance,
homeland defense, testing, and training missions. This commenter
requested that copies of pre-construction notifications and NWP
verification letters for these activities be provided to the Department
of Defense Siting Clearinghouse, so that the Department of Defense
could have an opportunity to coordinate with the project proponent to
ensure that long range surveillance, homeland defense, testing, and
training missions are not adversely affected by these activities.
We have added Note 4 to this NWP to require district engineers to
send pre-construction notifications and NWP verification letters to the
Department of Defense Siting Clearinghouse if this NWP is proposed to
be used to authorize the construction of wind energy generating
structures, solar towers, or overhead transmission lines. The
Department of Defense Siting Clearinghouse is responsible for
coordinating with the project proponent and resolving any potential
effects on Department of Defense long range surveillance, homeland
defense, testing, and training missions.
Proposed NWP B is issued as NWP 52, with the changes discussed
above.
General Conditions
One commenter suggested reordering the general conditions to better
aggregate concepts based on importance to permittees and the resources
potentially affected. One commenter recommended placing general
conditions 14 and 20 together because they both address cultural
resources. One commenter said that proposed general condition 30, pre-
construction notification, should become general condition 1 because of
its importance for potential users of the NWPs, in terms of the pre-
construction notification requirements.
With one exception, we have retained the order of the general
conditions because we believe they are in a logical order. We have
moved proposed general condition 14, discovery of previously unknown
remains and artifacts, to become general condition 21 so that it
follows general condition 20, historic properties. We have retained the
pre-construction notification general condition in its place as the
last general condition (as general condition 31), because the text of
the NWPs state which activities require pre-construction notification.
Two commenters suggested new general conditions to minimize
construction impacts. One suggestion was to require flagging
construction limits to protect nearby aquatic areas and the other
recommended a general condition to address temporary crossings or
structures.
Requirements to flag construction limits are more appropriately
addressed through activity-specific conditions added to an NWP
authorization, when the district engineer determines such flagging is
necessary to ensure the authorized activity results in minimal adverse
effects on the aquatic environment. General condition 13, removal of
temporary fills, and general condition 9, management of water flows,
adequately address the concerns about temporary crossings and
structures.
One commenter said the phrase ``as appropriate'' should be deleted
from the Note at the beginning of Section C, Nationwide Permit General
Conditions.
We have changed this phrase to ``as applicable'' to clarify that a
permittee is responsible for complying with general conditions that are
pertinent to a particular NWP activity.
Comments on Specific General Conditions
GC 1. Navigation. We did not propose any changes to this general
condition and no comments were received. The general condition is
adopted as proposed.
GC 2. Aquatic Life Movements. We proposed to modify this general
condition to provide added protection to the aquatic environment by
promoting the use of bottomless culverts, when it is practicable to use
those types of culverts to maintain movements of aquatic organisms.
Two commenters supported the proposed changes to this general
condition. One commenter said that all crossings should be designed by
using a stream simulation technique. Another commenter stated that
requirements for bottomless culverts should only apply to new
activities. Many commenters said that culverts that are installed with
their bottoms below the grade of the stream bed can be as effective as
bottomless culverts in improving conditions for aquatic life movement
while still being cost effective and providing the intended function of
allowing movement of aquatic organisms.
Many commenters objected to the proposed changes to this general
condition, and most of these commenters requested that the reference to
the use of bottomless culverts be removed, stating that in many cases
that bottomless culverts are not practicable or cannot be used in many
locations. A large number of commenters expressed concern that
requiring the use of bottomless culverts would significantly increase
costs and would not be feasible. Several commenters disagreed that the
use of bottomless or buried culverts reduces overall impacts to
streams, and some commenters said that use of bottomless culverts can
cause adverse effects to streams by increasing erosion and head cuts.
One commenter recommended promoting the use of alternative measures or
techniques to maintain aquatic life movements. Some commenters said
that the proposed changes to this general condition would
[[Page 10242]]
result in all affected activities requiring pre-construction
notification.
After evaluating the large number of comments received in response
to the proposed changes to this general condition, we have generally
reverted back to the text that was in the 2007 general condition, with
a few minor changes. We have modified the last sentence of the 2007
general condition to make it clear that the general condition applies
to both temporary and permanent crossings, and that those crossings
should be designed and constructed to maintain low flows to sustain the
movement of indigenous aquatic species. We have not adopted the
provision that would have required bottomless culverts to be used where
practicable. In addition, we have not incorporated the sentence that
explains some of the circumstances where bottomless culverts may not be
practicable. In response to a pre-construction notification, the
district engineer may evaluate the proposed crossing to determine
whether it complies with this general condition. The district engineer
may add conditions to the NWP authorization to require measures to
sustain aquatic life movements, including bottomless culverts, if
appropriate.
Many commenters said that bottomless culverts require complex
designs that require pile supported footings and many local and county
governments do not have the resources available to design, construct,
and maintain bottomless culverts in a manner that ensures roadway
safety. Many commenters stated that bottomless culverts need more long-
term maintenance and will increase costs and delays. One commenter
noted that construction techniques required to install bottomless
culverts may result in unsuitable conditions for aquatic life movement.
Several commenters expressed concern that footings may deteriorate and
undermine the integrity of the structure and increase the possibility
of collapse during high flow conditions. Several commenters said
bottomless culverts cannot be installed in areas with highly erodible
or weak soils. One commenter asserted that bottomless culverts
generally cannot support load conditions created by rail traffic.
Because of the various factors that determine appropriate culvert
designs for a particular waterbody, we are not adopting the proposed
language concerning bottomless culverts. The general condition requires
permanent and temporary crossings to be suitably culverted, bridged, or
otherwise designed and constructed to fulfill the objective of the
general condition, which is to sustain the movements of aquatic species
indigenous to the waterbody, both during and after completion of the
activity.
Several commenters stated that requiring bottomless culverts or
bottoms of culverts to be below the grade of the stream bed restricts
design flexibility that reflects site specific conditions. One
commenter said it is not practicable to install the bottoms of culverts
below grade in all circumstances. One commenter said that the
appropriate structure to allow aquatic life movements to continue
should be determined by considering the land cover within the
watershed, the variability of stream flow, and the presence or absence
of aquatic life. One commenter indicated that it is not possible to
bury pre-cast culverts because the bed material would be difficult to
place. This commenter also said that below grade structures collect
more debris and increase erosion on the downstream side of the culvert.
This commenter expressed concern that culvert bottoms installed below
grade would cause water to pool and provide habitat for pests such as
mosquitoes. One commenter said that below grade culverts direct high
velocity flows and create scour holes at the outlet and destabilize the
banks. Another commenter stated that sinking a culvert below grade
drains land used for row crops and accumulates silt that blocks aquatic
life movements.
We have also removed the provision requiring the bottoms of
culverts to be installed below the grade of the stream bed unless the
stream bed consists of bedrock or boulders. The modified general
condition merely states that permanent and temporary crossings of
waterbodies must be suitably culverted, bridged, or otherwise designed
or constructed, to provide flexibility for using a crossing that is
appropriate for the site conditions, while sustaining the movements of
aquatic species indigenous to the waterbody.
Many commenters said that the use of bottomless culverts should be
limited to perennial streams. A number of commenters stated that many
ephemeral and intermittent streams are not capable of supporting
aquatic life or do not have sufficient aquatic life movement to justify
the expense and technical design requirements for bottomless culverts.
Several commenters said this general condition should not apply to
ephemeral streams. One commenter stated that bottomless culverts should
only be used in waters that support special status aquatic life
species. One commenter said the bottomless culvert requirement should
be limited to streams and not required for ditches or other waters.
Another commenter expressed concern that installing the bottom of the
culvert below grade will tend to dewater wetlands.
The general condition has been reworded to provide flexibility to
determine appropriate culvert design based on site-specific
characteristics. Crossings of perennial, intermittent, and ephemeral
streams must be appropriately designed and constructed to sustain the
movement of indigenous aquatic species.
Many commenters requested a definition of the term ``practicable''
as used in the context of the proposed general condition. One commenter
said that regional variability should be considered when determining if
it is practicable to use a bottomless culvert. Several commenters asked
for more examples of when it would be impractical to use a bottomless
culvert. One commenter requested clarification as to who would
determine if use of a bottomless culvert is practicable. Many
commenters said cost should be a primary factor used to determine if it
is practicable to use a bottomless culvert. One commenter stated that
there would be additional paperwork requirements necessary to evaluate
the practicability of using bottomless culverts.
The proposed provision requiring the use of bottomless culverts
where practicable has not been adopted into the final general
condition. The term ``practicable'' is defined in the 404(b)(1)
Guidelines at 40 CFR 230.3(q) as ``available and capable of being done
after taking into consideration cost, existing technology, and
logistics in light of overall project purposes.'' However, it is no
longer used in this general condition.
One commenter said the general condition should include criteria to
be used to determine whether there is a substantial disruption to
aquatic life movement. Two commenters asked what threshold would be
used to identify a substantial disruption. Another commenter stated
that the general condition should list the species that would be
covered. One commenter said this general condition would not sustain
aquatic life movements during future high flows that are expected as a
result of global climate change.
Determining compliance with this general condition is at the
discretion of the district engineer. It is not possible to define, on a
national basis, what constitutes a substantial disruption of the
necessary life cycle movements of aquatic species indigenous to the
waterbody. It is not appropriate to
[[Page 10243]]
provide a national list of such species, but this condition generally
applies to all indigenous species in the waterbody whose life-cycle
movement may be affected by the project. How global climate change
might affect the flow patterns and volumes of particular streams,
rivers, or other waterbodies cannot be predicted with a reasonable
degree of certainty. Crossing designs should be based on present
conditions, and the crossing may be modified at a later time to
accommodate changes in flow patterns and volumes that occur as
environmental conditions change.
One commenter stated that additional requirements for proper
culvert sizing should be added to this general condition to ensure fish
passage and reduce failure. This commenter said that natural bankfull
capacity of the stream channel should be maintained. One commenter also
recommended that culverts have a width of 1.2 times the bankfull width
of the stream, and be embedded a minimum of two feet to maintain
connected habitat and a stable stream bed. Another commenter stated
that stream crossings should maintain natural flows, substrate, and
stream grade from upstream to downstream of the culvert. This commenter
suggested adding a provision that states that bridges or bottomless
culverts are to be used when practicable.
The proper sizing of culverts is more appropriately addressed
through an evaluation of the site for the proposed NWP activity and the
surrounding area. The general condition focuses on maintaining the
necessary life cycle movements of aquatic species indigenous to the
waterbody, not the geomorphic characteristics of the waterbody.
Maintenance of water flows, including the proper width and height of
culverts, bridges, and other crossings, is more appropriately addressed
by general condition 9, management of water flows. We have modified
this general condition to require permanent and temporary crossings to
be suitably culverted, bridged, or otherwise designed and constructed
to maintain low flows to sustain the movement of indigenous aquatic
species.
Two commenters requested that, if the proposed changes to this
general condition are adopted, sufficient time should be provided for
state, county, and local governments to update their design
requirements to include bottomless culverts. One commenter stated it
would take approximately two years to develop standards for bottomless
and buried culvert installation. Another commenter expressed concern
about the expense and time required to revise the plans and
specifications for projects nearly ready for construction.
We do not believe it is necessary to provide a grandfathering
provision for the implementation of this general condition. The general
condition provides substantial flexibility to design permanent and
temporary crossings, and uses a results-driven approach to help ensure
that NWP activities have only minimal adverse effects on the movement
of indigenous species of aquatic organisms. Existing construction and
design standards can be used to satisfy the objective of this general
condition.
The general condition is adopted with the modifications discussed
above.
GC 3. Spawning Areas. We did not propose any changes to this
general condition. One commenter said this general condition should be
removed, and replaced with regional conditions that require buffers for
spawning areas. This commenter reasoned that local buffer requirements
would be more appropriate for satisfying the requirements of the
Endangered Species Act. Two commenters stated that only requiring
avoidance of spawning areas to the maximum extent practicable is not
sufficient, and one of those commenters said that the destruction of
spawning areas should not be allowed under any circumstances. One
commenter recommended modifying this general condition to prohibit
activities that adversely affected all spawning areas. One commenter
suggested explicitly including forage fish habitat and submerged
aquatic vegetation as protected resources in this general condition.
We are retaining this general condition because spawning areas are
important components of the aquatic environment and should be addressed
at the national level to ensure that NWP activities result in minimal
adverse effects on the aquatic environment. Division engineers may
impose regional conditions on this NWP to establish buffers to protect
spawning areas for particular species. Activities authorized by NWPs
must also comply with general condition 18, endangered species. The
intent of this general condition is to minimize adverse effects to
spawning areas caused by NWP activities, and it is not feasible to
completely prohibit activities that may affect spawning areas. In areas
where there are documented concerns for fish forage habitat or
submerged aquatic vegetation, division engineers can add regional
conditions to the NWPs to restrict or prohibit activities in those
areas.
This general condition is adopted as proposed.
GC 4. Migratory Bird Breeding Areas. We did not propose any changes
to this general condition. One commenter said this general condition
should be removed and regional conditions should be used instead to
establish buffers for migratory bird breeding areas. This commenter
also stated that the requirement that NWP activities avoid breeding
areas for migratory birds to the maximum extent practicable is not
sufficient to protect those areas. One commenter said buffers
established through regional conditions would satisfy Endangered
Species Act requirements more effectively.
This general condition addresses a national concern for breeding
areas for migratory birds, and establishes a consistent, national
requirement for regulated activities to avoid these areas to the
maximum extent practicable. Nationwide permit activities that may
affect migratory birds that are listed as endangered or threatened
under the Endangered Species Act, or that may affect designated
critical habitat, must comply with general condition 18, endangered
species.
This general condition is adopted as proposed.
GC 5. Shellfish Beds. We did not propose any changes to this
general condition. One commenter said the term ``concentrated shellfish
populations'' should be defined to specify a method to be used to
identify such areas, because in some states shellfish beds are
prominent features in waterways. Another commenter suggested changing
the text of the general condition to state that shellfish beds created
as habitat cannot be used for harvesting, and NWPs 4 and 48 could not
authorize activities in those areas. One commenter recommended adding
restoration projects authorized by NWP 27 to this general condition.
The identification of concentrated shellfish populations for the
purposes of determining compliance with this general condition is more
appropriately conducted by district engineers using local criteria and
methods. Shellfish beds established through habitat restoration
projects may be used for growing shellfish for consumption and other
uses, and the decision on whether harvesting in those areas should be
allowed is at the discretion of Federal, state, and/or local
authorities. We have added shellfish seeding or habitat restoration
activities authorized by NWP 27 to the list of NWP activities that may
occur in areas of concentrated shellfish populations, since NWP 27
activities may improve habitat quality and further increase shellfish
populations.
[[Page 10244]]
This general condition is adopted with the modification discussed
above.
GC 6. Suitable Material. We did not propose any changes to this
general condition. One commenter recommended that this general
condition should explicitly prohibit the use of tires as fill material,
because tires can leach toxic amounts of chemicals that are harmful to
aquatic species. One commenter said the general condition should be
changed so that only environmentally suitable or stable material may be
used as fill, because many plastics are unstable when exposed to
ultraviolet light or temperature changes. One commenter stated that
contaminated sediments should not be used as fill material. One
commenter recommended modifying this general condition to minimize
impacts to habitat and species caused by the leaching of heavy metals,
pesticides, and polycyclic aromatic hydrocarbons.
We do not believe it is necessary to add tires or plastics to the
list of examples of unsuitable materials. Prohibiting the use of
unsuitable materials is more effective and enforceable than stating
that only environmental suitable or stable materials may be used. It is
impractical, for the purposes of the NWP program, to establish what
would constitute an environmentally suitable material since we are not
aware of any Federal standards that could be applied, other than those
covered under Section 307 of the Clean Water Act. A similar problem
exists for identifying stable materials, because the timeframe that
might be used to determine whether a particular material is ``stable''
would vary by the material. The district engineer will make a case-by-
case determination of what constitutes unsuitable material. The current
text of the general condition prohibits the use of contaminated
sediment as fill material, if it contains toxic pollutants in toxic
amounts. The general condition also prohibits the use of materials that
contain heavy metals, pesticides, and polycyclic aromatic hydrocarbons
in toxic amounts, in accordance with Section 307 of the Clean Water
Act.
This general condition is adopted as proposed.
GC 7. Water Supply Intakes. We did not propose any changes to this
general condition and no comments were received. The general condition
is adopted as proposed.
GC 8. Adverse Effects from Impoundments. We did not propose any
changes to this general condition. One commenter said the general
condition should include specific examples of how to reduce impacts
associated with accelerating passage of water and how to prevent the
restriction of normal water flows. Another commenter asked for a
definition for the term ``maximum extent practicable.'' Two commenters
stated that impoundments that cause adverse effects to the aquatic
environment by changing water flows should not be authorized by NWPs
and should instead require individual permits with agency coordination.
Specific measures for reducing impacts caused by accelerated water
flows or restricted water flows have to be determined on a case-by-case
basis after considering the environmental characteristics of the site
of the NWP activity. It would not be appropriate to establish such
measures at a national level. An activity-specific evaluation would
also have to be done to determine whether the minimization of these
adverse effects has been accomplished to the maximum extent
practicable. District engineers will use their discretion to determine
compliance with this general condition. The term ``practicable'' is
defined in the 404(b)(1) Guidelines at 40 CFR 230.3(q) as ``available
and capable of being done after taking into consideration cost,
existing technology, and logistics in light of overall project
purposes.'' We do not agree that all impoundments should require
individual permits; impoundments may be authorized by general permits,
including NWPs, as long as they have minimal individual and cumulative
adverse effects on the aquatic environment and comply with the
applicable terms and conditions, including any general conditions,
regional conditions, and activity-specific conditions, of an NWP
authorization.
This general condition is adopted as proposed.
GC 9. Management of Water Flows. We did not propose any changes to
this general condition. One commenter asked for a definition of the
term ``expected high flows'' and said the possibility of high flow
events should be anticipated during project implementation. One
commenter stated that this general condition should be modified to
prohibit changes to stream channels in intertidal areas. One commenter
stated that shoreline structures and fills, such as seawalls,
bulkheads, and revetments, reflect wave energy that causes deep
scouring of the shore, and over-steepened local shore faces. These
induced hydraulic effects substantially alter the flow patterns in
intertidal features such as ocean and estuarine beaches, wetlands and
mudflats.
It would be inappropriate to attempt to define the term ``expected
high flows'' since it would depend on the environmental setting of the
NWP activity. To comply with this general condition, the activity
should not be substantially damaged by an expected high flow.
Activities in stream channels located in intertidal areas are subject
to this general condition and if a proposed NWP activity involves the
alteration of intertidal stream channels and requires pre-construction
notification, the district engineer will evaluate the proposed activity
and determine whether it will result in minimal adverse effects on the
aquatic environment. Bank stabilization activities should be designed
and constructed to withstand expected high flows. Adverse effects to
littoral or fluvial processes, or adverse effects caused by deflections
of wave energy, should be considered by district engineers when
evaluating pre-construction notifications for proposed bank
stabilization activities.
This general condition is adopted without change.
GC 10. Fills Within 100-Year Floodplains. We did not propose any
changes to this general condition. Several commenters explained the
benefits of fully functional natural floodplains. Most of the
commenters seemed to indicate that the Corps has regulatory
jurisdiction over non-wetland floodplains. Several commenters objected
to the general condition simply requiring compliance with Federal
Emergency Management Agency (FEMA) approved state or local floodplain
management requirements. Several commenters said that fills in
floodplains identified by state or local FEMA-approved floodplain maps
should only be authorized by individual permits, to ensure that state
or local floodplain managers are aware of these activities. Two
commenters stated that FEMA-approved standards are designed to ensure
the public is reasonably safe from flooding, but these standards
provide insufficient protection to waterways, floodplains, and other
aquatic resources. One commenter said the Corps has an independent
obligation to protect waters of the United States and this obligation
extends to protection of floodplain resources.
We acknowledge that floodplains provide important ecological
functions and services, but it must also be understood that most areas
within 100-year floodplains are not subject to Clean Water Act
jurisdiction, because a large proportion of the area within 100-year
floodplains consists of uplands. The Corps regulatory authority in 100-
year
[[Page 10245]]
floodplains is usually limited to discharges of dredged or fill
material into waters of the United States, including jurisdictional
wetlands. The protection of floodplains is more appropriately addressed
through land use planning and zoning, which is primarily the
responsibility of state and local governments, as well as tribal
governments. Land use planning and zoning can provide the holistic
approach needed to protect floodplain functions and services, reduce
economic losses through flood damage reduction, and protect human
health and welfare. If state, local, or tribal governments have zoned
areas of 100-year floodplains for residential developments or other
uses, and if those activities involve discharges of dredged or fill
material into waters of the United States and meet the terms and
conditions of an applicable NWP, and the NWP activity results in
minimal adverse effects on the aquatic environment or other relevant
public interest review factors, then authorization by NWP is
appropriate.
This general condition also recognizes that FEMA, in partnership
with state and local governments, is the more appropriate authority for
floodplain management. It is not the responsibility of the Corps to
ensure that project proponents seek any required authorizations from
state or local floodplain managers. Such a requirement would not
constitute a condition that could be enforced by the Corps. We are not
relying on FEMA-approved state or local floodplain management
requirements to protect waters of the United States located in 100-year
floodplains. The NWP program utilizes other tools, such as regional
conditions, the district engineer's ability to exercise discretionary
authority to revoke, suspend, or modify an NWP authorization, and add
activity-specific conditions to ensure that activities authorized by
the NWP results in minimal individual and cumulative adverse effects on
the aquatic environment and other public interest review factors.
Two commenters stated that fills in 100-year floodplains result in
more than minimal adverse environmental effects and should not be
authorized by NWP. One commenter suggested that the Corps evaluate NWP
activities in floodplains and riparian areas in a more holistic manner
than it did in previous NWP rulemaking efforts. One commenter said that
authorizing discharges of fill material in waters of the United States
in floodplains affects the ability to manage floodplains so that there
are no adverse impacts. One commenter stated that coordination with the
resource agencies should be required to protect habitat and
biodiversity in floodplains.
Discharges of dredged or fill material into waters of the United
States located in 100-year floodplains often have minimal adverse
effects on the aquatic environment, individually and cumulatively.
Division engineers can impose regional conditions on one or more NWPs
to restrict or prohibit their use in waters of the United States within
100-year floodplains if those NWP activities would result in more that
minimal adverse effects on the aquatic environment. In response to a
pre-construction notification, district engineers may exercise
discretionary authority and require an individual permit if the adverse
effects on the aquatic environment would be more than minimal. District
engineers may also add activity-specific conditions to an NWP
authorization to require measures to minimize adverse effects on the
aquatic environment caused by NWP activities. Since the Corps
Regulatory Program only regulates discharges of dredged or fill
material into waters of the United States and structures or work in
navigable waters of the United States, and most areas of 100-year
floodplains are not wetlands as defined at 33 CFR 328.3(b) or otherwise
waters of the United States under 33 CFR 328.3(a) and associated
guidance, the Corps does not have the authority to take a holistic
approach to floodplain management. In areas of the country where 100-
year floodplains consist mostly of uplands, construction activities in
these uplands may have a substantial adverse impact on these 100-year
floodplains. We do not agree that agency coordination should be
required for fills in 100-year floodplains, because district engineers
have the necessary expertise to evaluate pre-construction notifications
for potential adverse effects to habitat and biodiversity in these
areas.
Two commenters said the general condition should inform permittees
of their responsibility to apply for a Conditional Letter of Map
Revision from FEMA if they are discharging dredged or fill material
into waters of the United States within 100-year floodplains. One
commenter recognized that although proposed development projects must
comply with all applicable Federal, state, regional and local
regulatory requirements, many project proponents do not apply for all
required permits. One commenter said that this general condition should
be modified to require documentation of compliance with applicable
FEMA-approved state or local floodplain management requirements. One
commenter stated that FEMA-approved state or local floodplain
management requirements do not adequately protect communities and
resources from flood risks.
We do not believe it is the Corps responsibility to notify a
prospective permittee of his or her responsibility to apply for a
Conditional Letter of Map Revision from FEMA if the overall project
would modify the existing regulatory floodway, the effective base flood
elevations, or a special flood hazard area. The discharge of dredged or
fill material authorized by NWP is likely to be only a small proportion
of the overall construction project within the 100-year floodplain.
Section E, Further Information, states that obtaining an NWP
authorization does not obviate the need to obtain other Federal, state,
or local permits, approvals, or authorizations required by law.
Building permits to authorize the construction of the overall project
are the responsibility of the state or local government, and should be
based on compliance with the applicable FEMA-approved state or local
floodplain management requirements. It is not the Corps responsibility
to ensure that project proponents have complied with the applicable
FEMA-approved state or local floodplain management requirements; the
state or local governments responsible for floodplain management should
enforce the requirements they established to qualify the community for
the National Flood Insurance Program. If the floodplain management
requirements developed by state or local governments are not adequately
protecting communities from flood risks, then the agency that approved
those requirements is the appropriate entity to reexamine those
requirements.
One commenter requested that the Corps report the extent to which
NWPs are being used in floodplains, particularly in areas that have
experienced repeated flood damages. Two commenters stated that this
general condition ignores the Corps own public interest review
processes and does not comply with Executive Order 11988.
The Corps does not track the number of NWP activities that have
occurred in floodplains, since our statutory authorities are focused on
activities involving discharges of dredged or fill material into waters
of the United States and/or structures or work in navigable waters of
the United States. As stated above, many areas of 100-year floodplains
are uplands and not waters of the United States. In addition, there is
no consistent national coverage in floodplain maps, since such maps are
[[Page 10246]]
either not available for some areas of the country or the existing maps
are outdated. This general condition is consistent with our regulations
on the public interest review, specifically 33 CFR 320.4(g),
consideration of property ownership, 33 CFR 320.4(j), other Federal,
state, or local requirements, and 33 CFR 320.4(l), floodplain
management. Section 320.4(g)(1) states that an ``inherent aspect of
property ownership is the right to reasonable private use.'' Section
320.4(j)(2) states that the primary responsibility for land use
planning and zoning is with state and local governments. Section
320.4(l) requires consideration of whether practicable alternatives to
floodplain development are available, and if there are no practicable
alternatives, then impacts to human health, safety, and welfare, risks
of flood losses, and impacts to natural and beneficial aspects of
floodplains should be minimized to the maximum extent practicable. This
NWP general condition, as well as the other terms and conditions of the
NWPs, such as the acreage and linear foot limits for losses of waters
of the United States, are consistent with the principles in these
regulations because they require avoidance and minimization of adverse
effects on the aquatic environment. Executive Order 11988 states that
Federal agencies are to consider alternatives to ``avoid adverse
effects'' to floodplains, and ``minimize potential harm to or within
the floodplain''. The Executive Order also says that agencies should
also consider flood hazards in the permit programs they administer. The
adoption of general condition 10 into the NWP program is consistent
with Executive Order 11988. It is also consistent with Executive Order
13132, Federalism, because it recognizes the cooperative approach the
Federal government has taken with state and local governments for
floodplain management (i.e., federal review, by FEMA, of state or local
floodplain management requirements).
Two commenters suggested reinstating the provisions in the 2002
NWPs that prohibited discharges of dredged or fill material into waters
of the United States within mapped 100-year floodplains that would
result in above-grade fills for residential, commercial and
institutional developments, agriculture activities, recreational
facilities, stormwater management facilities, and mining activities.
We do not agree that the approach taken in the 2002 NWPs for fills
in 100-year floodplains should be reinstated. There are sufficient
safeguards in the NWPs, including the terms and conditions, pre-
construction notification requirements, and the authority for district
engineers to exercise discretionary authority and either require
individual permits or add conditions to NWP authorizations, to ensure
that NWP activities have minimal adverse effects on the aquatic
environment, including public interest review factors such as
floodplain values and flood hazards.
Three commenters said that using NWPs to authorize discharges of
dredged of fill material into waters of the United States will result
in increased flood damages in coastal and riparian areas by reducing
the amount of aquatic area available to absorb future floods that will
likely be larger and more frequent due to climate change. They
suggested increasing the application fee for NWPs to cover the
estimated cost of permit processing and to offset future economic
impacts of authorizing floodplain development.
The flood storage capacity of a coastal or inland floodplain is
dependent primarily on its topographic characteristics, including the
amount of land area available for storing flood waters. Uplands also
provide important ecological services such as flood storage. Flood
damage reduction is more effectively accomplished through land use
planning and zoning, which as discussed above, is primarily the
responsibility of state, local, and tribal governments. Charging
application fees for NWP pre-construction notifications or verification
requests is not being considered at this time.
This general condition is adopted as proposed.
GC 11. Equipment. We did not propose any changes to this general
condition. One commenter stated that the condition should be changed to
include streams, and not be limited to wetlands or mudflats.
The intent of this general condition is to ensure that heavy
equipment used in special aquatic sites such as wetlands and mudflats
does not cause more than minimal disturbances to their soils. The
substrate of stream beds is generally not considered to be soil, and
other general conditions such as general condition 12, soil and
sediment controls, are more appropriate to control the movement and
disturbance of stream bed sediments. District engineers may also add
activity-specific conditions to NWP authorizations, such as
requirements to use best management practices, to minimize disturbances
to stream beds.
This general condition is adopted as proposed.
GC 12. Soil Erosion and Sediment Controls. We did not propose any
changes to this general condition. One commenter said the general
condition should provide specific steps that will ensure protection of
downstream water quality during the construction of permitted
activities. Two commenters suggested adding requirements to prevent the
erosion of sediments resulting from harvesting shellfish. One commenter
stated that disturbed areas should be stabilized and vegetated areas
should be restored to pre-construction conditions or improved
conditions.
Specific best management practices and other measures to protect
downstream water quality are more appropriately addressed by
considering the activity-specific environmental setting and adopting
practices and measures that will control soil erosion and sediment
loads on the site of the authorized activity. District engineers may
add conditions to the NWP authorizations to require permittees to use
specific best management practices or other techniques to minimize soil
erosion and reduce transport of sediment to waters and wetlands. We do
not believe it is necessary to modify this general condition to address
sediment movement that may occur during shellfish harvesting
activities, because such movements are usually minor and temporary and
have minimal adverse effects on the aquatic environment. The
restoration of areas where temporary fills have been placed, including
revegetating those areas, is more appropriately addressed by general
condition 13, removal of temporary fills.
This general condition is adopted without change.
GC 13. Removal of Temporary Fills. We did not propose any changes
to this general condition. One commenter said the general condition
should require the removal of temporary fills during periods of low-
flow or no-flow so that there will be little or no downstream transport
of the fill material.
It would be inappropriate to require that temporary fills be
removed only during periods of low-flow or no-flow because it is not
always practicable to wait until water flows are low or absent. In
addition, more adverse effects to the aquatic environment may occur if
the permittee is required to wait until low flow or no flow conditions
exist. It is usually best to remove temporary fills as soon as possible
to minimize sediment loads to downstream waters or to nearby wetlands.
However, general condition 12, soil erosion and sediment controls,
encourages permittees to work in waters of the United States during
periods of low or no flow, when possible.
[[Page 10247]]
This general condition is adopted as proposed.
GC 14. Proper Maintenance. We did not propose any changes to this
general condition. One commenter recommended changing the general
condition to ensure that maintenance activities minimize impacts to
waters and maintain downstream water quality. Another commenter
suggested adding a provision that would require proper maintenance to
ensure compliance with applicable NWP general conditions as well as
conditions added to an NWP verification.
The original intent of this general condition was to ensure that
NWP activities are maintained so that they do not endanger public
safety. There are other general conditions that more directly address
minimization (e.g., general condition 23, mitigation) and water quality
(e.g., general condition 12, soil erosion and sediment controls, and
general condition 25, water quality). We agree that proper maintenance
should also be required to comply with the terms and conditions of an
NWP authorization, including any activity-specific conditions added to
an NWP authorization by the district engineer. For example, road
crossings should be properly maintained to continue complying with
general condition 2, aquatic life movements.
This general condition is adopted with the change discussed above.
GC 15. Single and Complete Project. We did not propose any changes
to this general condition. Two commenters recommend removing the term
single and complete project. Two commenters said the definition of
``single and complete project'' is flawed and that the acreage limit of
an NWP should apply to the entire project, not just each single and
complete project. One commenter suggested changing the general
condition to state that an NWP activity cannot be expanded or modified
at a later date. Two commenters said the general condition may allow
piecemealing under the NWPs.
It has been a long-standing principle in the NWP program that the
NWPs authorize single and complete projects. This general condition was
added to the NWPs in 2007 to make that clear to users of the NWPs. The
general condition is consistent with the NWP regulations at 33 CFR part
330 that were last revised in 1991, especially the definition at 33 CFR
330.2(i). Some of the NWPs issued in the past included terms and
conditions stating the NWP authorized single and complete projects. In
2007, we added a general condition to make it clear that all NWPs
authorize single and complete projects. As long as any proposed
expansions or modifications of a previously authorized NWP activity
comply with the terms of the NWPs, they can be authorized by NWP.
Expansions or modifications that are not separate single and complete
projects from the previously authorized activity have to comply with
the terms and conditions of the NWP, including any acreage or linear
foot limits that would apply to both the previously authorized activity
and the NWP activity included in the expansion or modification. If the
expansion or modification is determined by the district engineer to be
a separate single and complete project, then that expansion or
modification activity may qualify for separate NWP authorization. We do
not agree that this general condition results in piecemealing, because
the NWP authorization applies to each single and complete project.
District engineers will exercise discretionary authority and require
other forms of Department of the Army authorization if the use of the
NWP to authorize activities in a watershed or other geographic area
will result in more than minimal cumulative adverse effects on the
aquatic environment.
This general condition is adopted without change.
GC 16. Wild and Scenic Rivers. We proposed to modify this general
condition to clarify that information on these rivers should be
obtained from the specific Federal land management agency responsible
for the designated Wild and Scenic River or study river. One commenter
supported reissuing the general condition.
The general condition is adopted as proposed.
GC 17. Tribal Rights. We did not propose any changes to this
general condition. One commenter stated that the use of the NWPs will
be in violation of tribal treaty rights, tribal water quality
standards, and the Clean Water Act, and threaten salmon recovery
efforts in the Pacific Northwest.
Division engineers may impose regional conditions on the NWPs to
restrict or prohibit their use in waters where NWP activities may
result in more than minimal adverse effects on the aquatic environment
or any other public interest review factor, including fish and wildlife
values. We have directed our districts to initiate government-to-
government consultation with Tribes to develop and propose regional
conditions to protect tribal treaty resources and other resources of
importance to Tribes. Under this general condition, no activity may be
authorized by NWP if it impairs reserved tribal rights, such as
reserved water rights or treaty fishing and hunting rights. The
regional conditioning process helps identify those rights on a
geographic basis, so that prospective users of the NWPs and Corps
districts are aware of those tribal rights. Nationwide permit
activities must also comply with Tribal water quality standards, if
those activities involve discharges into waters covered by Tribal water
quality standards. Activities authorized by NWPs must also comply with
general condition 18, endangered species, which will help support the
recovery of listed salmon species.
The general condition is adopted as proposed.
GC 18. Endangered Species. We proposed to modify paragraph (a) of
this general condition to clarify that both direct and indirect effects
are to be taken into account when assessing whether an activity may
jeopardize the continued existence of a threatened or endangered
species or a species proposed for such designation, or destroy or
adversely modify the critical habitat of such species. In addition, we
proposed to modify paragraph (e) to include definitions of ``take'' and
``harm.'' Another proposed change was to add a new paragraph (f) to
provide prospective permittees with guidance on where they can obtain
information on the locations of listed species and their critical
habitat. One commenter expressed support for the proposed
modifications.
Several commenters requested clarification and definitions for the
terms ``directly'' and ``indirectly'' as used in paragraph (a). In
addition, several commenters objected to the addition of ``indirectly''
into the general condition, because they believe only direct effects
should be considered. Several commenters expressed concern that this
will result in the Corps evaluating direct and indirect effects that
are far from the NWP activity.
To provide clarification on the use of the terms ``direct'' and
``indirect'' in the context of general condition 18 and the NWPs in
general, we are adding definitions of ``direct effects'' and ``indirect
effects.'' The definitions were adapted from the definitions provided
in the Council of Environmental Quality's National Environmental Policy
Act regulations at 40 CFR 1508.8. The definition of ``indirect effect''
is also generally consistent with the Services' definition within the
definition of ``effects of the action'' at 50 CFR 402.02. The addition
of indirect effects to paragraph (a) of the general condition is
consistent with the U.S. Fish and Wildlife Service's and National
Marine Fisheries Service's Endangered Species
[[Page 10248]]
Act Section 7 regulations for considering whether a proposed activity
may jeopardize the continued existence of a listed species or may
result in the destruction or adverse modification of critical habitat
(see the definitions of ``destruction or adverse modification'' and
``jeopardize the continued existence of'' at 50 CFR 402.02). The Corps
is obligated by the section 7 consultation regulations to consider
indirect effects caused by proposed NWP activities, and appropriate
distances for such indirect effects will have to be determined on a
case-by-case basis by district engineers.
One commenter stated that the district engineer should evaluate the
Endangered Species Act (ESA) compliance documentation provided by the
Federal agency, and determine whether or not it is sufficient to
address ESA compliance for the NWP activity, or whether additional ESA
consultation is necessary. Two commenters recommended modifying
paragraph (b) to clarify that documentation of compliance with the
Endangered Species Act provided by a Federal agency will be sufficient
and that Corps review and concurrence with that section 7 consultation
is not required. One commenter said that paragraph (b) should make it
clear that a state agency operating under federal funding can also
provide the section 7 compliance documentation obtained by the Federal
agency that oversees its activities, and not have to reinitiate
consultation. Another commenter stated that when a non-Federal
permittee is operating on behalf of a Federal agency, they should
follow paragraph (b) of this general condition instead of paragraph
(c).
We have added a sentence to paragraph (b) to state that the
district engineer will review the other Federal agencies' documentation
of compliance with the Endangered Species Act and determine whether
that compliance is sufficient for the NWP activity, or whether
additional ESA consultation is necessary before the activity can be
authorized by NWP. We believe this provision is necessary to address
situations where the consultation conducted by the other Federal agency
does not adequately cover the direct and indirect effects on listed
species or designated critical habitat caused by the NWP activity. For
similar reasons, we do not agree that it would be appropriate to modify
paragraph (b) to explicitly state that state agencies may rely on ESA
compliance documentation obtained by the Federal agency that provides
them with funding for an activity. District engineers will generally
accept another Federal agency's compliance with section 7, but there
may be situations where that agency's section 7 compliance does not
adequately address the activities authorized by an NWP and their
effects on listed species or designated critical habitat. In those
situations, the district engineer may conduct additional section 7
consultation to satisfy the requirements of the Endangered Species Act.
If it is not sufficient, then the non-Federal permittee has to follow
paragraph (c) of this general condition instead.
One commenter said that this general condition places the
responsibility for determining whether a proposed activity may affect
listed species in the hands of the permittee. One commenter requested
clarification on how the ``might be affected'' threshold in the first
sentence is to be determined by an applicant, because it is unclear and
leaves room for broad interpretation. One commenter stated that the
word ``might'' in the second sentence of paragraph (c) should be
changed to ``may.''
It is the Corps' responsibility to make ``may affect''
determinations for the purposes of the ESA, and the ``might be
affected'' threshold is intended to be a cautionary threshold to give
district engineers the opportunity to evaluate proposed activities and
make their effect determinations. Prospective permittees are required
to submit pre-construction notifications if the proposed NWP activity
has the potential to affect a listed species, is in the vicinity of a
listed species, or is located in designated critical habitat. If the
Corps determines there will be no effect on listed species or
designated critical habitat, then ESA section 7 consultation is not
necessary. If the district engineer determines there will be an effect
that requires ESA section 7 consultation, then he or she will initiate
either formal or informal consultation with the U.S. Fish and Wildlife
Service and/or the National Marine Fisheries Service, as appropriate.
One commenter said paragraph (c) should clearly state that a pre-
construction notification is to be submitted if any listed species or
designated critical habitat might be affected or is in the vicinity of
the project, to ensure that another form of notification is not used.
Two commenters stated that 30 days is sufficient for the Corps to
notify the applicant of its ``may affect'' determination and asked why
the general condition allows 45 days. Two commenters suggested
modifying this general condition to state that if the prospective
permittee does not receive a response from the Corps within 45 days,
then he or she can assume that the Corps has determined that there is
``no effect'' on a listed species. In addition, one of these commenters
said that for projects that ``may affect'' a listed species, if the
section 7 consultation is not concluded within 135 calendar days of
initiation, the activity would be authorized to proceed as if a ``no
effect'' determination has been made.
We have modified the first sentence of paragraph (c) to state that
non-Federal permittees must submit a pre-construction notification if
the notification requirement is triggered. The 45-day period in
paragraph (c) of this general condition is intended to be consistent
with the 45-day review period for pre-construction notifications
provided in paragraph (a) of general condition 31, pre-construction
notification. Under paragraph (a) of general condition 31, a
prospective permittee may not begin an NWP activity that requires pre-
construction notification until he or she has been notified in writing
that the activity may proceed under the NWP, or 45 calendar days have
passed since the district engineer received a complete pre-construction
notification and no written notice has been provided to the applicant
by the district or division engineer. However, if pre-construction
notification was required by paragraph (c) of general condition 18, the
prospective permittee may not proceed with the NWP activity until
notified by the Corps, even if the 45 calendar days have passed,
because the Corps regulations at 33 CFR 330.4(f)(2) state that NWP
activities cannot commence until the requirements of the ESA have been
satisfied and the district engineer has notified the applicant that the
activity is authorized by NWP. It may take more than 135 days to
complete section 7 consultation, and the NWP activity may not proceed
until after consultation has been completed.
Two commenters requested clarification on what work the prospective
permittee is prohibited from conducting prior to the Corps making a
determination of ``no effect'' or until section 7 consultation is
completed. Two commenters requested clarification of the term
``vicinity'' in this general condition.
The work covered by the general condition and the Corps regulations
at 33 CFR 330.2(f) depends on the scope of analysis for the ESA section
7 consultation. The Corps follows the U.S. Fish and Wildlife Service's
and National Marine Fisheries Service's regulations at 50 CFR part 402
and Endangered Species Consultation Handbook to determine the section 7
scope of
[[Page 10249]]
analysis. The scope of analysis includes the direct and indirect
effects of the NWP activity, as well as the effects of other activities
that are interrelated and interdependent with that activity (see 50 CFR
402.02). The section 7 scope of analysis will be determined by district
engineers on a case-by-case basis. Generally, the applicant cannot
begin any work for which a Department of the Army permit is required
until the applicable ESA provisions have been satisfied. The term
``vicinity'' cannot be defined at a national level, since the extent of
the vicinity depends on a variety of factors, including the species
that might be affected, the proposed activity, and the environmental
setting.
One commenter said pre-construction notification should not be
required for NWP activities that require section 7 compliance, if they
would not otherwise require a pre-construction notification. This
commenter stated that the prospective permittee should only be required
to submit the appropriate documentation for section 7 consultation. One
commenter stated that this general condition should also apply to
state-listed threatened and endangered species.
This general condition is consistent with the NWP regulations at 33
CFR 330.4(f)(2), which requires the prospective permittee to notify the
district engineer if any Federally-listed endangered or threatened
species, or critical habitat, might be affected or is in the vicinity
of the project. The prospective permittee must submit the information
required for a pre-construction notification, so that the district
engineer will have sufficient information to commence evaluation of the
proposed activity and its effects on listed species or critical
habitat. It would be inappropriate to expand the scope of this general
condition to cover state-listed endangered and threatened species,
since that is a regional issue that is best addressed through state
laws and regulations. If a state is concerned about the potential
impacts of one or more NWPs on state-listed species, the state may ask
the Corps district to consider adding regional conditions to help
protect state-listed endangered or threatened species.
Two commenters recommended removal of the definitions of ``take''
and ``harm'' from this general condition and replacing those
definitions with a reference to the Endangered Species Act, to reduce
the potential for inconsistencies. One commenter said the Corps should
instead use the U.S. Fish and Wildlife Service's regulations to
determine what constitutes an effect or jeopardizes any threatened or
endangered species or their critical habitat.
The definition of ``take'' is identical to the definition in the
Endangered Species Act (see 16 U.S.C. 1532(19)). The definition of
``harm'' is the same as the definition in the U.S. Fish and Wildlife
Service's regulations (50 CFR 17.3) and the National Marine Fisheries
Service's regulations (50 CFR 222.102). The definitions of ``take'' and
``harm'' were added to this condition to provide clarification for
users of the NWPs, and facilitate compliance with the Endangered
Species Act.
One commenter stated that paragraph (f) should provide web links to
the Services' ESA Section 7 regulations and other documents. Another
commenter said the Corps should defer to the U.S. Fish and Wildlife
Service on effects determinations.
Paragraph (f) provides links to web sites for the U.S. Fish and
Wildlife Service and the National Marine Fisheries Service to assist
prospective permittees with obtaining information on listed species and
other ESA documents. We do not believe it is necessary to provide a
link to the Services' section 7 consultation regulations at 50 CFR part
402 since it is the Corps responsibility to conduct section 7
consultation. It is also the Corps responsibility to make ``may
effect'' determinations for the purposes of the ESA and district
engineers have the option of soliciting advice from the U.S. Fish and
Wildlife and/or the National Marine Fisheries Service prior to making
their determinations.
One commenter recommended that surveys be conducted for state- and
Federally-listed species prior to the start of construction. Another
commenter said the lack of a requirement for surveys makes the pre-
construction notification requirement in this general condition
ineffective. One commenter said that ``objective science'' is needed to
identify habitats and species that may be affected by activities
authorized by NWPs. One commenter stated that the Corps must consider
the effects of climate change during the consultation process.
The need for surveys for Federally listed species is to be
determined by the district engineer on a case-by-case basis. It is not
possible to require surveys for the tens of thousands of activities
authorized by NWP each year. Project proponents are encouraged, but not
required to contact the U.S. Fish and Wildlife Service or the National
Marine Fisheries Service for assistance in determining whether listed
species or critical habitat might be affected by the proposed activity.
The effects of climate change on endangered and threatened species and
their critical habitat is more appropriately addressed through the
section 7 consultation process, since those effects are likely to be
site-specific.
The general condition is adopted with the modifications discussed
above.
GC 19. Migratory Bird and Bald and Golden Eagle Permits. We are
adding this new general condition to clarify that permittees are
responsible for complying with the Migratory Bird Treaty Act and the
Bald and Golden Eagle Protection Act, and obtaining any ``take''
permits that may be required under the U.S. Fish and Wildlife Service's
regulations issued under those two statutes. The Migratory Bird Treaty
Act and the Bald and Golden Eagle Protection Act differ from the
Endangered Species Act in that those two statutes and their
implementing regulations establish the project proponent as the
responsible party who has to apply to the U.S. Fish and Wildlife
Service for take permits, if such permits are required.
The U.S. Fish and Wildlife Service's implementing regulations that
establish general permit requirements for migratory birds permits at 50
CFR part 21 state that ``[n]o person may take, possess, import, export,
transport, sell, purchase, barter, or offer for sale, purchase, or
barter, any migratory bird, or the parts, nests, or eggs of such bird
except as may be permitted under the terms of a valid permit issued
pursuant to the provisions of this part and part 13 of this chapter, or
as permitted by regulations in this part, or part 20 of this subchapter
(the hunting regulations), or part 92 of subchapter G of this chapter
(the Alaska subsistence harvest regulations).'' The term ``person'' is
defined at 50 CFR 10.12 as ``any individual, firm, corporation,
association, partnership, club, or private body, any one or all, as the
context requires.'' These regulations do not identify a federal
permitting agency as a ``person'' responsible for obtaining a take
permit, where that federal agency is not actually carrying out the
activity that may result in the ``take'' of a migratory bird. Likewise,
the U.S. Fish and Wildlife Service's implementing regulations for the
Bald and Golden Eagle Protection Act at 50 CFR part 22 do not include
any provisions stating that Federal permitting agencies are responsible
for assisting project proponents in obtaining permits to authorize the
taking, possession, and transportation within the United States of bald
eagles and golden eagles and their parts, nests, and eggs.
[[Page 10250]]
Executive Order 13186 discusses the responsibilities of Federal
agencies to protect migratory bird for the purposes of the Migratory
Bird Treaty Act. The Executive Order applies only to those actions that
are directly carried out by Federal agencies (see Section 2, paragraph
(h)). Actions carried out by non-Federal entities with Federal
assistance are not subject to the Executive Order. Department of the
Army permits can be considered a form of Federal assistance since they
provide authorization to non-Federal entities to comply with Federal
laws such as Section 404 of the Clean Water Act and Section 10 of the
Rivers and Harbors Act of 1899.
This general condition is adopted.
GC 20. Historic Properties. We proposed to modify paragraph (c) of
this general condition to make a more general reference to the Corps
Regulatory Program's current procedures for compliance with Section 106
of the National Historic Preservation Act, since we are using Appendix
C to 33 CFR part 325, as well as various guidance documents to address
the Advisory Council on Historic Preservation's revised regulations at
36 CFR part 800.
In response to the February 16, 2011, proposal to reissue the NWPs,
including the proposed modification of this general condition, we
received comments on the Corps use of Appendix C and the current
guidance. Concerns regarding the use of Appendix C and the current
guidance are outside the scope of the NWP rule, and are not addressed
in this rule.
Several commenters asked whether an NWP authorization or
verification would be issued before a State Historic Preservation
Officer concurs to an effect determination or formalizes an agreement
regarding historic properties. One commenter stated that although the
NWP regulations provide that the Corps may issue an NWP before a
memorandum of agreement is executed, district engineers have, in some
cases, not issued NWP verifications without State Historic Preservation
Officer concurrence.
This general condition requires non-Federal permittees to submit
pre-construction notifications if the NWP activity may have the
potential to cause effects to historic properties. In such cases, the
district engineer will initiate section 106 consultation with the
appropriate State Historic Preservation Officer or Tribal Historic
Preservation Officer. Further consultation may be conducted with the
Advisory Council on Historic Preservation, if necessary. The
prospective permittee may not begin the NWP activity until the district
engineer notifies him or her that the section 106 consultation has been
completed (which may include execution of a memorandum of agreement to
address adverse effects or the concurrence of the State or Tribal
Historic Preservation Officer), or the activity has no potential to
cause effects to historic properties.
One commenter said the Corps should more closely follow paragraph
(b) of the general condition and not require redundant section 106
review on projects that are being undertaken by another Federal agency.
Three commenters suggested that the Corps section 106 responsibilities
should be satisfied if another Federal agency formally accepts
responsibility for conducting section 106 consultation and is the lead
for this responsibility through either a programmatic agreement or on a
project-by-project basis. One commenter said that duplicate regulatory
efforts are unnecessary, particularly when another Federal agency has a
lead role.
District engineers will generally accept another Federal agency's
compliance with section 106, but there may be situations where that
agency's section 106 compliance does not adequately address the
activities authorized by an NWP and their effects on historic
properties. In those situations, the district engineer may conduct
additional section 106 consultation to satisfy the requirements of the
National Historic Preservation Act. We have added a sentence to
paragraph (b) to address these situations.
One commenter said the general condition does not clearly specify
who is responsible for the identification and evaluation of historic
properties and determination of effects. Another commenter stated that
the general condition does not adequately ensure section 106 compliance
because the Corps may not receive enough information from permittees to
fully take into account the effect a project may have on a historic
property. This commenter also said that while paragraph (c) states that
prospective permittees may seek assistance from the State or Tribal
Historic Preservation Officer and from the National Register of
Historic Places, there is no requirement that an applicant consult with
these parties or that an applicant coordinate an effect determination
with a qualified professional with relevant historic properties
experience.
The Corps is ultimately responsible for determining compliance with
the requirements of Section 106 of the National Historic Preservation
Act. Non-Federal permittees are required to submit pre-construction
notifications if an NWP activity may have the potential to cause
effects to historic properties, and the district engineer will evaluate
those pre-construction notifications to determine if section 106
consultation is necessary. The general condition also states that
district engineers will make reasonable and good faith efforts to
identify historic properties and effects on those properties. The
district engineer may request additional information from the applicant
where necessary to evaluate potential effects of the activity on
historic properties or to initiate section 106 consultation. We cannot
require prospective permittees to seek assistance from a State Historic
Preservation Officer or a Tribal Historic Preservation Officer, search
the National Register of Historic Preservation, or consult with
qualified historic property professionals. However, this general
condition requires prospective permittees to provide a list of `` * * *
any historic properties listed, determined to be eligible for listing
on, or potentially eligible for listing on the National Register of
Historic Places, including previously unidentified properties,'' if
these properties may be affected. The permittee may obtain such
information from the State Historic Preservation Officer or Tribal
Historic Preservation Officer, the National Register of Historic
Places, or other sources of information on historic properties.
One commenter recommended providing language to clearly state when
a pre-construction notification is or is not required based on the
presence or absence of known historic properties. This commenter
suggested that if a prospective permittee independently determines that
no historic properties exist within the boundaries of the project area,
then pre-construction notification is not necessary. The commenter also
said that if the district engineer has to be notified because of
potential effects to historic properties, the notification should not
be in the form of a pre-construction notification.
We do not agree that the general condition should be modified to
explicitly state that prospective permittees do not have to submit pre-
construction notifications if they determine there are no known
historic properties within the boundaries of the project area. Such a
provision would be inappropriate, because there could be visual or
noise effects to historic properties outside of the project area that
have to be evaluated through the section 106 consultation process. The
[[Page 10251]]
current general condition is the proper approach, in which the
prospective permittee seeking NWP authorization is required to submit a
pre-construction notification if the proposed activity might have the
potential to cause effects to any historic property listed in, or
eligible for listing in, the National Register of Historic Places,
including previously unidentified properties. A pre-construction
notification is the appropriate mechanism to notify the district
engineer, because it contains information necessary to begin the
evaluation process, to determine whether the proposed activity
qualifies for NWP authorization.
One commenter requested clarification of what constitutes the
permit area for the purposes of consultation under Section 106 of the
National Historic Preservation Act. One commenter asked if a permittee
is obligated to have the Corps review an archaeologist's determination
that an activity will not impact an historic site. One commenter stated
that the general condition is unreasonable and violates federalism.
The criteria for identifying the permit area for the purposes of
section 106 are provided in paragraph 1(g) of Appendix C to 33 CFR part
325, in addition to paragraph 6(d) of the April 25, 2005, interim
guidance. The permit area will be determined on a case-by-case basis by
the district engineer. When a professional cultural resource manager or
archaeologist performs an investigation or makes an effect
determination, the Corps will generally consider the qualifications of
the professional and will review any documentation provided for the
purposes of section 106 compliance. This general condition is required
because the NWP program must comply with the National Historic
Preservation Act, a Federal law. Even though most NWP activities occur
on private land, compliance with applicable Federal laws is necessary.
This general condition would not interfere with any state or local
authorities.
This general condition is adopted with the modifications discussed
above.
GC 21. Discovery of Previously Unknown Remains and Artifacts. We
proposed this new general condition to address circumstances where
previously unknown or unidentified historical or archaeological remains
are discovered while conducting the NWP activity.
Several commenters expressed support for adding this general
condition to the NWPs. Two commenters said the condition should refer
to the district engineer instead of ``this office'' or ``we.'' We have
made these changes to be consistent with the language found in other
general conditions.
One commenter stated that the proposed condition relies on the
permittee, who is generally not qualified to make determinations
concerning remains and artifacts discovered during construction
activities. This commenter said that this general condition should
require all work to cease immediately and a qualified Corps
archaeologist should initiate required consultation.
We believe the revised language in the condition clearly indicates
that the Corps will initiate consultation in such instances where a
previously unknown historic or archaeological remain is discovered
during construction activities. The Corps does not have the authority
to prohibit all construction activities on the site in these cases.
Several commenters expressed concern with the use of the term
``artifact'' in this general condition, and some of them stated that it
can have too broad of a definition. One commenter requested
clarification as to what constitutes an ``artifact.'' Another commenter
said that this general condition should have thresholds to protect
significant artifact deposits while allowing work to continue when only
minor artifacts are discovered. One commenter suggested that we qualify
``artifacts'' by adding ``artifacts that are potentially eligible for
the National Register of Historic Places.''
The use of the term artifact is consistent with the definition of
``historic property'' at 36 CFR 800.16, which states that historic
properties include `` * * * artifacts, records, and remains that are
related to and located within [historic] properties.'' Procedures for
the protection of historic properties address all properties that may
be eligible for inclusion in the National Register of Historic Places,
and do not establish quantitative thresholds for when section 106
consultation must occur. The consultation threshold is an effects-based
threshold. We do not believe it is necessary to add text clarifying
that artifacts are those ``that are potentially eligible for the
National Register of Historic Places.'' Eligibility determinations will
be made after the discovery of artifacts and remains.
Three commenters stated that the proposed general condition is more
restrictive than general condition 3 provided in Appendix A to 33 CFR
part 325, the permit form for individual permits. These commenters said
the NWP general condition should not be more restrictive than the
standard permit condition. Two commenters suggested deleting this
general condition because provisions for the discovery of unknown
historic or archaeological remains are already codified in the NWP
regulations and in the Corps Regulatory Program's implementing
regulations for Section 106 of the National Historic Preservation Act.
The proposed general condition is similar to general condition 3 in
Appendix A of 33 CFR part 325. For this new NWP general condition, we
have taken the text of general condition 3 in Appendix A and modified
it to include Tribes. We have also modified it by adding a provision
requiring, to the maximum extent practicable, avoidance of construction
activities that could affect the remains and artifacts. We believe the
latter provision is necessary to protect those artifacts and remains as
much as possible. The addition of Tribes to the condition reflects
current section 106 procedures. This general condition can be more
restrictive than the standard permit condition in Appendix A because
the NWPs may only be used to authorize activities with minimal adverse
effects on the aquatic environment and other applicable public interest
review factors. While 33 CFR 330.4(g)(3) contains a similar provision,
we believe the general condition is needed to comply with applicable
cultural resource laws.
Several commenters expressed concern with requiring the permittee
to stop work once previously unknown historic or archaeological remains
are found. One commenter said this provision is too unpredictable and
may result in significant delays. One commenter suggested adding time
frames to this general condition to provide predictability and assure
permittees that the Corps will proactively seek to resolve any
outstanding historic property issues. One commenter recommended
clarifying this general condition to state that if a discovery occurs,
work should cease only in the area containing remains or artifacts. One
commenter objected to the work stoppage provision, stating that once
construction begins, substantial investment has been made and the
requirement to stop construction indefinitely upon the discovery of a
potentially insignificant archaeological resource represents an
unacceptable financial risk. This commenter recommended that if we keep
this provision as proposed, we impose time frames on identification and
consultation in order to provide some predictability to the process.
We believe it is necessary to include a provision in this general
condition to require the permittee, once any
[[Page 10252]]
previously unknown historic, cultural, or archeological remains or
artifacts are found while conducting the NWP activity, to avoid
construction activities that could affect those remains and artifacts,
to the maximum extent practicable. We recognize that in some
circumstances it may not be possible to avoid further construction
activities that might affect the remains and artifacts, because those
construction activities may have to be completed for safety or
minimizing erosion and sedimentation. In addition, the Corps does not
have the legal authority to stop construction activities. We have
replaced the phrase ``stop activities that would adversely affect
those'' with ``avoid construction activities that could affect the'' to
protect those remains and artifacts as much as possible while
preventing other adverse environmental effects from occurring, such as
the installation of sediment and erosion control devices to reduce or
eliminate sediment inputs to wetlands, streams, and other waters while
the necessary Federal, Tribal, and state coordination is conducted. It
would not be appropriate to impose timeframes in this general
condition, because the amount of time to complete coordination will
vary across the country and from case to case. We cannot remove the
provision for avoiding construction activities that could affect the
remains and artifacts, because Section 106 of the National Historic
Preservation Act and other cultural resource laws impose binding
requirements on the Corps and other federal agencies.
A few commenters said this general condition should not apply to
other Federal agencies with section 106 responsibilities if they are
the permittees, since their implementing regulations already contain
provisions for the discovery of previously unknown historic or
archaeological remains during construction.
We agree that in cases where another federal agency is the lead
Federal agency for purposes of compliance with Section 106 of the
National Historic Preservation Act, that Federal agency should follow
its procedures for addressing post-review discoveries. However, the
Corps also has section 106 responsibilities if the NWP activity has the
potential to cause effects to an historic property. As long as the lead
Federal agency is in compliance with section 106 requirements and this
compliance satisfies section 106 requirements for the NWP
authorization, the Corps can rely on the lead Federal agency's
compliance efforts. Upon notification, the district engineer will let
the other Federal agency know if any further action by the Corps is
necessary.
This general condition is adopted with the modifications discussed
above.
GC 22. Designated Critical Resource Waters. We proposed to modify
this general condition to clarify the types of waters subject to the
general condition by changing how NOAA's marine sanctuaries are
described, which categories of critical resource waters are always
subject to this general condition, and how additional critical resource
waters can be designated by a district engineer after a public notice
and comment process. We also proposed to add proposed new NWPs A and B,
now designated NWPs 51 and 52, respectively, to the list of NWPs in
paragraph (a).
Several commenters objected to allowing state-designated
outstanding national resource waters to be automatically included as
designated critical resource waters because of varying designations and
criteria across the states. These commenters also said that a state's
process to designate such waters may not include the opportunity for
public comment and that the designations carry no legal basis. In
addition, commenters indicated there are inconsistent approaches by
different agencies within the same state for designating outstanding
national resource waters. Some commenters said that other state
programs, such as those that are responsible for Clean Water Act
Section 401 water quality certifications, are capable of adequately
addressing the effects of the activity to these state designated
waters. One commenter requested a definition of outstanding national
resource waters. Two commenters said such waters should have a
particular environmental or ecological significance. Two commenters
objected to including outstanding national resource waters
automatically because that designation may be based only on
recreational characteristics. Three commenters suggested that the
general condition should be changed to require the district engineer to
designate such waters only after issuing a public notice and soliciting
comment, and then obtaining concurrence from the state.
This general condition was first adopted in the NWPs issued on
March 9, 2000 (see 65 FR 12872). In the preamble to the 2000 NWPs, we
stated that `` * * * outstanding national resource waters must be
identified and approved by the district engineer after public notice
and opportunity for comment'' (65 FR 12873, third column). In that
notice, we also said that state or local officials should not be able
to designate additional waters as critical resource waters without the
district engineer providing an opportunity for public notice and
comment. We are modifying this general condition to return to our
original approach, since there is much disparity across the country in
how outstanding national resource waters are identified and designated.
Because of the inconsistency in how outstanding national resource
waters are designated, we believe it is necessary to provide the public
with the opportunity to review and comment on those waters before they
become adopted as designated critical resource waters for the purposes
of this general condition. Outstanding national resource waters should
have environmental and ecological significance, and their designation
should not be based solely on recreational uses or characteristics.
Three commenters expressed concern that providing district
engineers the ability to designate, after notice and opportunity to
comment, additional waters officially designated by a state as having
particular environmental or ecological significance would lead large
areas of state-designated waters of all types to be removed from being
eligible for the NWPs. One commenter said this general condition should
be removed because it violates the principles of federalism in
Executive Order 13132. This commenter said a district engineer could
use state stream designations to identify critical resource waters and
override the rights of states to interpret and enforce their own laws.
We are retaining the provision that allows district engineers to
designate additional critical resource waters after notice and
opportunity for public comment. That process is not substantially
different from using the regional conditioning process to restrict or
prohibit the use of NWPs in specific waters or geographic areas, which
can be delegated by division engineers to district engineers. This
general condition is not contrary to Executive Order 13132. The general
condition helps support the objective of the Clean Water Act, which is
to restore and maintain the physical, chemical, and biological
integrity of the Nation's waters. In addition, this general condition
helps ensure that the NWPs authorize only those activities that have
minimal individual and cumulative adverse effects on the aquatic
environment. This general condition only applies to waters and wetlands
that are both waters of the United States and designated critical
resource waters.
One commenter objected to removing state natural heritage sites
from
[[Page 10253]]
automatic inclusion in the general condition due to their interest in
maintaining the existing protection the general condition provides to
areas of unique ecological significance. Another commenter supported
the proposed change. One commenter said state natural heritage sites
should not be automatically considered critical resource waters because
the term is undefined. Another commenter suggested that state natural
heritage sites should be limited to those sites that are identified
through state legislation. One commenter opposed including state
natural heritage sites as potentially being classified as critical
resource waters and suggested that the Corps continue to defer to State
Historical Preservation Officers to determine effects on historic
sites.
While we understand the perspective that state natural heritage
sites should be automatically subject to this general condition, we
also understand the need for transparency and clarity for the regulated
public. Given the variability in waters and wetlands that may be
designated as state natural heritage sites, and the different processes
that may be used by states to designate their natural heritage sites,
we believe it is necessary to provide a public notice and comment
process before including state natural heritage sites as designated
critical resource waters under this general condition. This approach
will help improve compliance with the NWP conditions, because it will
make project proponents aware of certain restrictions for the use of
specific NWPs. The protection of historic properties is more
appropriately addressed through general condition 20, historic
properties.
One commenter said the use of an NWP should not be prohibited in
critical resource waters when the agency responsible for managing those
critical resource waters is conducting the activity. This commenter
also suggested that the general condition should not prohibit the use
of NWPs, but instead the NWPs listed in paragraph (a) should be moved
to the notification provision of paragraph (b) and also require the
approval of the agency that manages the designated critical resource
water, similar to the approach taking in general condition 16, wild and
scenic rivers. One commenter supported protecting critical resource
waters but suggested that protection can be provided instead by
requiring prior written approval through a state's water quality
agency. Another recommended requiring water quality certifications for
the NWPs listed in paragraph (b) instead of pre-construction
notifications, to ensure that the activities authorized by those NWPs
result in minimal adverse effects on designated critical resource
waters and adjacent wetlands.
The purpose of the prohibition in paragraph (a) of this general
condition is to exclude the use of those NWPs in critical resource
waters that have the potential to result in more than minimal adverse
effects on the aquatic environment. The status of the entity who would
be conducting the proposed discharge of dredged or fill material is not
relevant to the minimal adverse effects determination; instead, it is
the environmental effects of the discharge that have to be considered.
Discharges of dredged or fill material into waters of the United States
that are designated critical resource waters, as well as their adjacent
wetlands, may be authorized by other forms of Department of the Army
permits, such as individual permits or regional general permits. Wild
and Scenic Rivers referenced in general condition 16 are those waters
that have been designated as such in accordance with the Wild and
Scenic Rivers Act of 1968, a federal law. Similar to state-listed
threatened and endangered species, the NWP program cannot be used to
ensure compliance with other state or local laws. However, an NWP
authorization does not obviate the need for the permittee to obtain
other federal, state, or local authorizations, including specific
authorizations related to state-protected critical resource waters. The
water quality certification process would not be an appropriate
alternative to the pre-construction notification requirement in
paragraph (b) of this general condition because the evaluation of an
NWP pre-construction notification involves consideration of more than
water quality issues.
One commenter suggested that pre-construction notifications for NWP
activities listed in paragraph (b) proposed in waters identified as
critical resources through state processes, should only be coordinated
with state authorities. This commenter said the pre-construction
notification for simple maintenance and improvement projects creates
unnecessary work for the project proponent and the Corps. One commenter
recommended adding a list of conservation areas to the general
condition, with a requirement that permittees must be in compliance
with the site specific management plan of the conservation area.
The district engineer will evaluate the pre-construction
notification for an NWP listed in paragraph (b) of this general
condition, to determine if the proposed activity will result in minimal
adverse effects on the aquatic environment, including the critical
resource water and its adjacent wetlands. Agency coordination is only
required for NWP activities that result in the loss of greater than \1/
2\-acre of waters of the United States. None of the NWPs listed in
paragraph (b) have the 300 linear foot limit for the loss of stream
beds, so the agency coordination threshold for requests for written
waivers for the loss of greater than 300 linear feet of intermittent or
ephemeral stream bed would not be triggered. We do not agree that
conservation areas should be added to the general condition at the
national level, because what constitutes a ``conservation area'' is
likely to vary across the country. District engineers may add specific
aquatic conservation areas that meet the definition of critical
resource waters to this general condition after a public notice and
comment process.
The general condition is adopted as proposed.
GC 23. Mitigation. We proposed to modify paragraph (g) to be more
consistent with the compensatory mitigation regulations at 33 CFR part
332, by replacing the word ``arrangements'' with ``programs'' in
describing in-lieu fee programs and replacing the phrase ``activity-
specific'' with ``permittee-responsible'' when referring to
compensatory mitigation implemented by the permittee. In addition, we
proposed to add a provision stating that for activities resulting in
the loss of marine or estuarine resources, permittee-responsible
compensatory mitigation may be environmentally preferable if there are
no mitigation banks or in-lieu fee programs in the area that have
marine or estuarine credits available for sale or transfer to the
permittee. Finally, we proposed to revise the last sentence of
paragraph (g) to state that the party responsible for providing the
required permittee-responsible mitigation, including any required long-
term management, is to be identified in conditions added to the NWP
authorization. Several commenters supported these proposed changes. One
commenter commended the Corps for the flexibility in determining
compensatory mitigation requirements.
One commenter stated that paragraph (a) should indicate that when
another Federal agency has determined that the activity has been
designed to avoid and minimize impacts the district engineer will defer
to that agency's determination. Several commenters said this general
condition does not adequately stress avoidance of aquatic resources
before compensatory mitigation is considered. One
[[Page 10254]]
commenter also said the general condition should refer to the measures
provided in the 404(b)(1) Guidelines for details on avoiding and
minimizing impacts. This commenter also suggested that the prospective
permittee should be required to document the steps taken to avoid and
minimize impacts, and describe them in the pre-construction
notification. In addition, the commenter said that the NWPs should only
authorize discharges of dredged or fill material into special aquatic
sites when the activity is water dependent or in cases where the
prospective permittee clearly demonstrates there are no practicable
alternatives available. One commenter stated that the practicable
alternative test in the Section 404(b)(1) Guidelines should be used for
NWP activities.
The district engineer determines compliance with the terms and
conditions of the NWPs, including whether the permittee has avoided and
minimized adverse effects to waters of the United States to the maximum
extent practicable on the project site. The general condition imposes
substantive requirements to avoid and minimize adverse effects to
waters of the United States, and district engineers will review pre-
construction notifications and determine whether project proponents
have satisfied the avoidance and minimization requirement, as well as
other applicable provisions of this general condition. District
engineers will also determine if proposed activities result in minimal
adverse effects on the aquatic environment and qualify for NWP
authorization. General permits only need to comply with section 230.7
of the 404(b)(1) Guidelines, which provides the evaluation process for
the issuance of Clean Water Act Section 404 general permits, including
NWPs. Individual activities that qualify for NWP authorization do not
have to implement the avoidance and minimization measures provided
elsewhere in the 404(b)(1) Guidelines, although they must still comply
with the avoidance and minimization provisions of this general
condition, which are designed to ensure that the NWPs collectively
comply with the 404(b)(1) Guidelines. Requiring the permittee to
provide documentation of avoidance and minimization measures taken
would result in unnecessary paperwork requirements, and the current
information requirements for complete pre-construction notifications
are sufficient. Section 230.7(b)(1) of the 404(b)(1) Guidelines states
that the alternatives analyses required by section 230.10(a) are not
directly applicable to general permits.
One commenter stated the general condition should address other
aspects of mitigation, such as performance standards, monitoring, and
contingency actions. One commenter said the general condition does not
comply with 33 CFR part 332 because it does not provide any criteria or
performance standards for compensatory mitigation. One commenter
indicated that monitoring must be required for all mitigation.
We have made several changes to this general condition to make it
consistent with the applicable provisions in 33 CFR part 332. We have
also added a sentence to paragraph (c)(1) of this general condition to
state that compensatory mitigation projects to offset losses of aquatic
resources must comply with the applicable provisions of 33 CFR part
332. The general condition provides basic requirements, since the
specific details for compensatory mitigation projects (e.g.,
objectives, ecological performance standards, monitoring requirements,
and site protection) are determined on a case-by-case basis by district
engineers. We acknowledge that monitoring is required for all
compensatory mitigation projects, in accordance with 33 CFR 332.6.
Two commenters stated that the district engineer should have
discretion to determine what, if any, compensatory mitigation is
required for projects impacting more than \1/10\-acre of wetlands, as
in some cases, compensatory mitigation may not be necessary, and
mitigation ratios of less than one-for-one may be adequate. One
commenter said that the Corps cannot require mitigation for NWP
activities that result in minimal adverse environmental effects, even
if there are wetland losses greater than \1/10\-acre, and requested
that the Corps change the first sentence of paragraph (c) to state that
the mitigation requirement can be waived if the district engineer
determines that the impacts of the proposed activity are minimal or
some other form of mitigation would be more environmentally
appropriate. Several commenters stated that compensatory mitigation
should be required for all NWP activities, and all resource types,
regardless of the amount of impact.
The 2008 compensatory mitigation rule (33 CFR part 332, as
published in the April 10, 2008, edition of the Federal Register (73 FR
19594)) established standards and criteria for all compensatory
mitigation projects required to offset losses of aquatic resources. The
standards and criteria apply to all sources of compensatory mitigation,
including permittee-responsible mitigation, mitigation banks, and in-
lieu fee programs. As stated in 33 CFR 332.1(b), the 2008 rule does not
change the circumstances under which compensatory mitigation is
required. The NWP regulations at 33 CFR 330.1(e)(3) stipulate when
compensatory mitigation is to be required for NWP activities--that is,
when the district engineer determines the individual and cumulative
adverse environmental effects are more than minimal. The requirements
at 33 CFR part 332 may affect the practicability of providing
compensatory mitigation for all NWP activities that result in the loss
of \1/10\-acre to \1/2\-acre and require pre-construction notification,
especially if the NWP activity is not in the service area of an
approved mitigation bank or in-lieu fee program with released or
advance credits available at the time the NWP pre-construction
notification is being evaluated by the district engineer.
In the 2008 mitigation rule, we also discussed our concerns about
the failure rates of on-site compensatory mitigation, which are often
not ecologically successful because of nearby changes in land use (see
73 FR 19601). We believe it would be inappropriate to require users of
the NWP to provide small on-site compensatory mitigation projects to
offset losses caused by NWP activities if they are likely to fail. If
the district engineer determines that on-site mitigation is likely to
be ecologically successful, he or she may require that compensatory
mitigation. It may not be practicable to provide off-site compensatory
mitigation if the activity is not in the service area of an approved
mitigation bank or in-lieu fee program with available credits. It is
also important to recognize that not all areas of the country have
approved mitigation banks or in-lieu fee programs. If the district
engineer determines that compensatory mitigation is necessary to ensure
than an NWP activity results in minimal individual and cumulative
adverse effects on the aquatic environment, and there are no
practicable and ecologically successful compensatory mitigation options
available, then he or she will exercise discretionary authority and
notify the project proponent that another form of Department of the
Army authorization is required, such as an individual permit.
To be consistent with 33 CFR 330.1(e)(3), and to take into account
how the requirements of 33 CFR part 332 affect the practicability for
providing compensatory mitigation for small wetland losses, we have
modified paragraph (c) of this general condition
[[Page 10255]]
to state that the district engineer will evaluate the pre-construction
notification and may not require compensatory mitigation for losses of
greater than \1/10\-acre of wetlands if he or she determines that
either alternative mitigation (such as additional avoidance and
minimization of impacts to waters of the United States on the project
site) would ensure that the NWP activity results in minimal individual
and cumulative adverse effects on the aquatic environment, or the
impacts of the proposed activity are minimal without compensatory
mitigation and determines the compensatory mitigation would not be
required. We do not agree that compensatory mitigation should be
required for all activities authorized by NWPs. For example,
compensatory mitigation may not be needed to ensure that the authorized
activity results in minimal adverse effects on the aquatic environment.
In addition, not all NWP activities require pre-construction
notification, and the pre-construction notification thresholds are
established so that those NWP activities that generally do not result
in more than minimal adverse effects on the aquatic environment can
proceed without review by the district engineer. To address exceptions
in specific waters or geographic areas, division engineers may add
regional conditions to an NWP to lower its pre-construction
notification threshold or require pre-construction notification for all
activities authorized by that NWP.
One commenter stated that greater than one-for-one mitigation
ratios must be required, stream mitigation ratios should address both
areal and linear extent, and waivers of the mitigation ratio should not
be allowed. One commenter stated that stream or open water mitigation
should have a mandatory mitigation ratio of one-for-one for in-kind
replacement and two-for-one riparian habitat improvement for any
impacts exceeding 50 feet of any stream or waterbody. One commenter
stated that mitigation should be required for all stream impacts that
exceed 100 feet. One commenter stated that appropriate in-kind
mitigation should be provided for any wetland or stream impacts. One
commenter also stated that out-of-kind mitigation contradicts the no-
net-loss policy.
The amount of compensatory mitigation necessary to ensure that the
NWP activity results in minimal adverse effects on the aquatic
environment is determined by the district engineer on a case-by-case
basis by applying the provisions at 33 CFR 332.3(f). The district
engineer will determine whether compensatory mitigation for losses of
stream bed should be required for a particular NWP activity. We do not
agree that losses of stream bed should have a threshold for determining
when compensatory mitigation should be required for those losses. We
have modified paragraph (d) of this general condition by replacing the
word ``restoration'' with ``rehabilitation, enhancement, or
preservation'' to be consistent with 33 CFR 332.3(e)(3), which
recognizes streams as ``difficult-to-replace'' resources.
Out-of-kind mitigation does not contradict the ``no overall net
loss'' goal for wetlands, since out-of-kind wetlands mitigation may be
environmentally preferable if another wetland type provided as
compensatory mitigation would benefit the watershed more than simply
providing in-kind replacement of the wetland being lost as a result of
the NWP activity.
One commenter also requested that consideration be given to the
cumulative impacts of wetland and stream disturbance. Several
commenters said that mitigation cannot be used to bring the adverse
effects of the NWPs to a minimal level. Some of these commenters stated
that mitigation is not predictable and in many cases is not successful.
Two commenters stated that if an NWP activity requires mitigation, then
by definition it has more than minimal adverse environmental effects.
Cumulative effects to wetlands and streams are evaluated in the
decision documents that are prepared for each NWP by Corps
Headquarters, as well as the supplemental decision documents approved
by division engineers. Wetland restoration, enhancement, establishment,
and preservation activities, and stream rehabilitation, enhancement,
and preservation activities (including and riparian area restoration,
enhancement, and preservation) can offset losses of aquatic resource
functions provided by waters of the United States that are impacted by
activities authorized by NWPs. District engineers evaluate compensatory
mitigation proposals provided by prospective permittees, to determine
whether the compensatory mitigation project will be ecologically
successful and be sufficient to offset losses of waters of the United
States to ensure that the net adverse effects on the aquatic
environment are minimal. The approved mitigation plan must include the
applicable components listed in 33 CFR 332.4(c)(2)-(14), including
ecological performance standards used to determine if the compensatory
mitigation project is achieving its objectives.
The party responsible for providing the compensatory mitigation
must implement the approved mitigation plan, and if it is determined
that changes are needed to improve ecological success, request approval
of those modifications. After the approved compensatory mitigation
project is implemented, monitoring is required on a regular basis and
monitoring reports must be submitted to the district engineer. The
monitoring reports are reviewed by the district engineer and if there
are deficiencies in the compensatory mitigation project, the district
engineer will work with the responsible party to determine what actions
are necessary to fix the compensatory mitigation project so that it
will meet its original objectives or comparable objectives that are
acceptable to the district engineer. If it is not possible to take
adaptive management measures to remediate the compensatory mitigation
project, then the district engineer may require alternative
compensatory mitigation.
Several commenters said that applicants should be required to
submit detailed mitigation plans with their pre-construction
notifications and conceptual mitigation proposals are not sufficient.
Several commenters also stated that the public should be provided the
opportunity to review mitigation plans and provide comments on whether
the impacts will be minimal.
We have added a new paragraph (c)(1) to state that the prospective
permittee is responsible for proposing an appropriate compensatory
mitigation option, if the district engineer determines that
compensatory mitigation is needed to ensure that the activity results
in minimal adverse effects on the aquatic environment. Another new
provision, paragraph (c)(3) of this general condition, states that the
mitigation plan may be conceptual or detailed, which is consistent with
the Corps regulations at 33 CFR 332.4(c)(1)(ii). We do not believe that
public review of compensatory mitigation proposals is necessary.
District engineers have the expertise to review compensatory mitigation
plans, evaluate their potential for ecological success, and determine
whether they will offset losses of aquatic resource functions so that
the NWP activity, after considering the required compensatory
mitigation, will result in minimal individual and cumulative adverse
effects on the aquatic environment.
One commenter asked whether functional assessments used to assess
aquatic resources must be approved by the Corps. One commenter said the
[[Page 10256]]
general condition should provide clearer requirements to reduce the
amount of discretion to be exercised by district engineers. One
commenter stated that compensatory mitigation should be linked to the
impacts of the project, and both the compensatory mitigation project
and the monitoring requirements should last as long as the authorized
impacts.
Functional assessments do not have to be formally approved by the
Corps, although district engineers may determine that a functional
assessment method proposed to be used for a particular aquatic resource
or activity is not appropriate. This general condition provides basic
principles for addressing mitigation requirements for NWP activities,
because it is not possible to cover all possible mitigation options and
requirements at the national level. Most activities authorized by NWPs
result in the permanent loss of waters of the United States, and it is
not practical or necessary to require permanent monitoring of
compensatory mitigation projects. The Corps regulations require long-
term protection of compensatory mitigation project sites (see 33 CFR
332.7(a)(1), and compensatory mitigation projects should be self-
sustaining. Some compensatory mitigation projects may require long-term
management, if the district engineer determines that long-term
management is appropriate and practicable.
One commenter said that paragraph (f) should be revised to include
the option of restoring riparian areas next to open waters. In
addition, the commenter stated that the restoration or establishment of
riparian areas should not be required on both banks of a stream,
because in some cases the permittee may not have authority or legal
interest in the land to restore or establish riparian areas on both
sides of the stream. This commenter noted that there may be conflicting
easements, roads, levees, or other structures in the proposed riparian
area, or the area may not support riparian vegetation. One commenter
stated that the Corps is inconsistent with use of the term buffer and
riparian areas and that buffer is more inclusive and should be used in
the general condition instead of riparian areas.
We have added the term ``restoration'' to the first sentence of
paragraph (f) to make it clear that the riparian area may either be
restored or established next to open waters. The general condition does
not require riparian areas to be established on both sides of a stream.
The fifth sentence of this paragraph provides a recommended width for
riparian areas, based on a presumption that the project proponent can
restore or establish riparian areas on both sides of the stream. If it
is not possible to establish a riparian area on both sides of a stream,
or if the waterbody is a lake or coastal waters, then restoring or
establishing a riparian area along a single bank or shoreline may be
sufficient, and we have added language to paragraph (f) of general
condition 23 to clarify that this can be acceptable compensatory
mitigation. The proposal did not use the term ``buffer'' and paragraph
(f) focuses on providing mitigation next to open waters through the
restoration or establishment, maintenance, and legal protection of
riparian areas.
One commenter requested that we include the phrase ``for resource
losses'' at the end of the parenthetical in paragraph (b) to be
consistent with 33 CFR part 320.4(r)(1). Two commenters stated that it
is difficult to provide long-term maintenance of mitigation sites for
weed control and invasive species. One commenter asked that definitions
for rectifying and reducing be added to the general condition.
We have added ``for resource losses'' after the word
``compensating'' in paragraph (b). Before requiring long-term
management for compensatory mitigation sites, district engineers will
evaluate whether such a requirement would be practicable, as well as
appropriate and necessary. We recognize that it may not be appropriate
and practical to require long-term management for small permittee-
responsible compensatory mitigation project sites, so we have modified
paragraph (g) to make it clear that long-term management is necessary
only when the district engineer adds conditions to an NWP authorization
to require long-term management for the compensatory mitigation
project. We do not believe it is necessary to provide definitions of
the terms ``rectifying'' and ``reducing'' since the commonly understood
definitions of these terms are sufficient.
One commenter requested the removal of paragraph (h), stating that
it creates confusion and sometimes results in mitigation being required
for non-jurisdictional activities, such as non-mechanized, above-ground
landclearing for overhead electric transmission lines. Another
commenter said that paragraph (h) implies that the Corps has authority
over activities it does not regulate, such as the removal of woody
vegetation from a wetland when there is no discharge of dredged or fill
material into waters of the United States. One commenter requested
clarification of the circumstances under which the Corps would require
compensatory mitigation for the conversion of forested and scrub shrub
wetlands, and said the phase ``may be required'' should be changed to
``shall be required.'' This commenter also said that no waivers should
be allowed for mitigation for projects within a utility right of way
for forested and scrub shrub wetlands that are permanently converted to
emergent wetlands.
Paragraph (h) is being retained, to make it clear that district
engineers may require compensatory mitigation for permanent losses of
specific aquatic resource functions that are caused by discharges of
dredged or fill material into waters of the United States or other
regulated activities. Paragraph (h) is part of a general condition that
applies only to activities authorized by NWPs. We do not agree that the
phrase ``may be required'' should be replaced with ``shall be
required'' because it is the district engineer's discretion whether to
require compensatory mitigation for losses of specific aquatic resource
functions.
One commenter recommended adding a new paragraph to this general
condition to clarify that any mitigation requirements must be limited
to a single and complete linear project. This commenter said that
compensatory mitigation should only be required if a specific crossing
of a waterbody triggers paragraph (c), (d), or (f) of this general
condition, not for other crossings that do not trigger pre-construction
notification requirements or mitigation requirements.
We do not believe such an addition to this general condition would
be appropriate or necessary. As discussed elsewhere in this notice,
district engineers evaluate the entire linear project, even though each
separate and distant crossing of waters of the United States may
qualify for a separate NWP authorization. District engineers may
require compensatory mitigation for all temporary and permanent losses
of waters of the United States. District engineers are required to
consider cumulative adverse effects in reviewing NWP pre-construction
notifications, not just adverse effects from the specific single and
complete project to which the notification applies.
One commenter stated that this general condition does not
adequately convey the hierarchy of mitigation preference established by
33 CFR part 332. One commenter stated that in-lieu fee arrangements
must not be used unless the arrangements comply with the requirements
of the in-lieu fee guidance. One commenter stated that
[[Page 10257]]
remining of lands results in a net benefit to the aquatic resources,
and the Corps should consider this remining as adequate compensatory
mitigation and should consider if it is appropriate to create an in-
lieu fee program for remining of previously mined areas.
We do not believe it is necessary to include the mitigation options
evaluation framework provided in 33 CFR 332.3(b), since that regulation
applies to all forms of Department of the Army permits, and the general
condition explicitly states that mitigation must comply with part 332.
In-lieu fee programs used to provide compensatory mitigation for NWP
activities must comply with the applicable provisions in 33 CFR 332.8,
unless the district engineer determined that they qualified for the
extension of the grandfathering provision provided at 33 CFR
332.8(v)(2). District engineers will determine on a case-by-case basis
whether compensatory mitigation should be required for remining
activities authorized by NWP.
This general condition is adopted with the modifications discussed
above.
GC 24. Safety of Impoundment Structures. We proposed to add this
new general condition to the NWPs. We received no comments on the
proposed general condition. The general condition is adopted as
proposed.
GC 25. Water Quality. We did not propose any changes to the general
condition. Two commenters recommended modifying this general condition
to state that activities are not authorized by NWP if the state denies
water quality certification, unless the project proponent obtains an
individual water quality certification or water quality certification
is waived. One commenter suggested adding a provision to state that the
district engineer will determine, after a reasonable amount of time
(generally 60 days) from the date an application for an individual
water quality certification was submitted by the project proponent,
that water quality certification is waived unless the Corps and the
water quality certification agency agree that additional time is
needed. A few commenters said that individual permits should be
required for activities in any waters identified as 303(d) listed
streams.
We believe that the current wording of this general condition is
sufficient to make it clear that an individual water quality
certification or waiver must be obtained if the state, Tribe, or EPA
had not previously issued water quality certification for an NWP. We
also do not believe it is necessary to provide a specific timeframe in
the general condition to reflect the language in 33 CFR 330.4(c)(6),
since those timeframes may vary by Corps district because of local
agreements with water quality certification agencies. There are a
variety of causes of stream impairment for 303(d) listings other than
discharges of dredged or fill material (e.g., nutrients, metals,
sedimentation, temperature, bacteria, pH, toxics). Reversing those
causes of impairment is more appropriately addressed through other
Clean Water Act programs.
This general condition is adopted as proposed.
GC 26. Coastal Zone Management. We received no comments on the
proposed general condition. The general condition is adopted as
proposed.
GC 27. Regional and Case-by-Case Conditions. We received no
comments on the proposed general condition. The general condition is
adopted as proposed.
GC 28. Use of Multiple Nationwide Permits. We received no comments
on the proposed general condition. The general condition is adopted as
proposed.
GC 29. Transfer of Nationwide Permit Verifications. We received no
comments on the proposed general condition. The general condition is
adopted as proposed.
GC 30. Compliance Certification. We proposed a minor change to this
general condition to clarify that we will provide the permittee with
the necessary documentation to complete and return to the Corps as the
signed certification. One commenter expressed support for the proposed
change.
Two commenters recommended including regional conditions to the
list of conditions under paragraph (a). One commenter suggested that a
separate compliance certification be required for mitigation projects,
because permittees submit the compliance certification when the work is
completed, not when the compensatory mitigation project is completed.
Two commenters said the general condition should be modified to clarify
that the success of the required compensatory mitigation would be
addressed separately, after evaluation of monitoring reports
demonstrates achievement of the performance standards for the
compensatory mitigation project.
We have modified paragraph (a) to require the statement to read
that the authorized work has been done in accordance with any general,
regional and activity-specific conditions to cover all of the
conditions that may be applicable to an NWP authorization. We have also
changed the first paragraph of this general condition by adding a
sentence to state that the success of any required permittee-
responsible mitigation, including the achievement of ecological
performance standards, will be addressed separately by the district
engineer. Paragraph (b) has also been revised by adding a sentence to
address the use of mitigation bank and in-lieu fee program credits to
fulfill compensatory mitigation requirements in NWP authorizations.
This new sentence states that if mitigation bank credits or in-lieu fee
program credits are used, the permittee must submit the documentation
required by 33 CFR 332.3(l)(3) to confirm that he or she has secured
the appropriate number and resource type of credits from the mitigation
bank or in-lieu fee program.
One commenter suggested adding language similar to that provided in
NWP 32, to state that it is necessary to comply with all terms and
conditions of the NWP, and that the NWP authorization is automatically
revoked if the permittee does not comply with all terms and conditions.
One commenter suggested that additional funding be allocated to do more
on-site compliance inspections. One commenter said there are
insufficient monitoring and compliance procedures in the NWPs. One
commenter stated that it should be the permittee's responsibility to
provide the required proof that the authorized activity was conducted
to comply with the terms and conditions of the NWP.
The Note at the beginning of Section C, Nationwide Permit General
Conditions, adequately addresses the requirement to comply with all
applicable terms and conditions of the NWPs. Funding for compliance
inspections is outside of the scope of this rule. Corps districts are
required, through our performance measures, to conduct initial
compliance inspections for a minimum percentage of the total number of
all general permit (including NWP) verifications issued during the
preceding fiscal year where authorized work is underway. The purposes
of this general condition is for the permittee to submit documentation
to the district engineer demonstrating that the authorized activity has
been implemented in accordance with the conditions of the NWP
authorization. Each permittee who receives an NWP verification letter
from the Corps must provide a signed certification documenting
completion of the authorized activity and any required compensatory
mitigation.
This general condition is adopted with the modification listed
above.
GC 31. Pre-Construction Notification. We proposed to modify
paragraph (d)(2) to clarify that all NWP activities
[[Page 10258]]
resulting in the loss of greater than \1/2\-acre of waters of the
United States require agency coordination. We also proposed to require
agency coordination for certain NWPs when the proposed activity would
result in the loss of greater than 1,000 linear feet of intermittent
and ephemeral stream bed, in cases where the district engineer is
considering waiving the 300 linear foot limit. Another proposed change
was to clarify that the district engineer will consider direct and
indirect effects caused by the NWP activity when making a minimal
adverse effects determination. We also proposed to provide a list of
factors to be considered when making minimal effects determinations for
the purposes of the NWPs. One commenter supported the proposed list of
factors.
One commenter objected to adding more pre-construction notification
requirements, stating that it takes several days to weeks for an
applicant to prepare pre-construction notification at the high level of
detail required by district offices. Several commenters stated that
they did not have the time and resources to prepare a pre-construction
notifications for all activities. One commenter said the proposed
changes that require pre-construction notifications for additional
activities would add to the workload of the Corps for projects that are
minor in nature.
We have not substantially increased the number of activities that
require pre-construction notification. We have issued two new NWPs, and
although both of those NWPs require pre-construction notification for
all activities, some of the activities authorized by those NWPs may
also be authorized by other NWPs that do not require pre-construction
notification. A prospective permittee may request authorization under a
specific NWP, if the proposed activity qualifies for authorization
under that NWP. District engineers have been instructed, through
Regulatory Program Standard Operating Procedures, to use the most
efficient permit process wherever possible, to make timely permit
decisions while protecting the aquatic environment. The two new NWPs
issued today will provide a more efficient means of authorizing
renewable energy generation facilities and pilot projects, in cases
where those activities did not previously qualify for NWP authorization
and required individual permits instead.
One commenter expressed concern with delays associated with the
pre-construction notification process. Several commenters said some
districts make requests for additional information after the 30-day
pre-construction notification completeness determination period ends,
and suggested adding a provision to paragraph (a) to state that all
requests for additional information must be made within 30 days of
receipt of a complete pre-construction notification and that districts
are limited to one request for additional information. One commenter
said the phrase ``as a general rule'' should be deleted from paragraph
(a). Several commenters said that in many cases, the district engineer
fails to describe the specific information that is needed for a pre-
construction notification to be deemed complete. Two commenters
requested clarification as to whether the activity is authorized by an
NWP 30 or 45 days after submitting a complete pre-construction
notification.
We have added text to the second sentence of paragraph (a) to state
that district engineers must notify prospective permittees within the
30-day completeness review period if the pre-construction notification
is incomplete and additional information has to be provided to the
district engineer to make the pre-construction notification complete.
We have also added a sentence that directs the district engineer to
specify, in his or her request for additional information, what
information is needed to make the pre-construction notification
complete. We have retained the phrase ``as a general rule'' in the new
fourth sentence, which states that district engineers will request
additional information only once, because there may be occasions where
it is necessary to make an additional request for information. It
should be noted that the 30-day period only applies to information
necessary to make the PCN complete, which is listed in paragraph (c) of
this general condition. Other types of information may also be needed
to make a decision on whether the proposed activity qualifies for NWP
authorization, such as a conceptual or detailed compensatory mitigation
plan, if the applicant only provided a mitigation statement to satisfy
the requirement in paragraph (b)(5). A conceptual or detailed
mitigation plan is needed to determine whether the proposed
compensatory mitigation will be suitable for ensuring compliance with
general condition 23, and may be requested after the 30-day
completeness review period, but before the 45-day pre-construction
notification review period ends. Another example is request for
additional information necessary to complete either Endangered Species
Act Section 7 consultation under general condition 18 or National
Historic Preservation Act Section 106 consultation under general
condition 20. Past rulemaking activities for the NWPs have established
a 45-day pre-construction notification review period for the NWPs, and
today's final rule retains that time period. Exceptions are for
compliance with general condition 18, endangered species, and general
condition 20, historic properties. Under those two general conditions,
activities that may affect endangered or threatened species or critical
habitat, or have the potential to cause effects to historic properties,
are not authorized until the required consultations are completed.
Another exception is NWP 21, for which activities are not authorized
until the applicant receives written verification from the Corps.
One commenter said that ``he or she'' be removed from paragraph
(a)(1) as it is the only location in which personal pronouns are used.
Another commenter recommended changing paragraph (a)(2) to state that
if the permittee does not receive any written notification from the
district engineer within 45 days of submitting a complete pre-
construction notification, then the permittee can assume that the
district engineer has made a ``no effect'' determination for endangered
species or historic properties.
The use of ``he or she'' is appropriate in paragraph (a)(1) because
it refers to the prospective permittee, who may be an individual,
corporation, or other entity. The NWP regulations (see 33 CFR
330.4(f)(2) for Endangered Species Act compliance and 33 CFR
330.4(g)(2) for National Historic Preservation Act compliance), as well
as general conditions 18 and 20, state that the activity is not
authorized by NWP until the requirements of the Endangered Species Act
and/or the National Historic Preservation Act have been satisfied.
Those two provisions in the Corps NWP regulations do not allow a
prospective permittee to conclude that there is a ``no effect'' finding
for the purposes of compliance with the Endangered Species Act or a
``no potential to cause effect'' finding for the purposes of compliance
with Section 106 of the National Historic Preservation Act if the
district engineer does not respond to the pre-construction notification
within 45-days in which the applicant stated there might be effects to
listed species or designated critical habitat or there may be potential
to cause effects to historic properties.
One commenter requested clarification whether the seven items
[[Page 10259]]
identified in paragraph (b) of this general condition are a complete
list and should not be supplemented. One commenter said that if
additional requirements are added to the NWP authorization by the
district engineer after the evaluation of the pre-construction
notification, those requirements should be subject to public notice and
comment.
The seven items listed in paragraphs (b)(1) through (7) of this
general condition are required for a pre-construction notification.
Additional information may be needed by the district engineer to make a
decision on the NWP pre-construction notification, such as a
compensatory mitigation proposal if the district engineer disagrees
with the prospective permittee's statement that compensatory mitigation
is not necessary to ensure the activity results in minimal adverse
environmental effects, or information needed to conduct Endangered
Species Act Section 7 or National Historic Preservation Act Section 106
consultation. Permit conditions added to an NWP authorization by a
district engineer do not need to go through a public notice and comment
process because they are incorporated into the authorization to ensure
compliance with regulatory and statutory requirements that general
permits only authorize activities that have minimal adverse effects on
the aquatic environment and other applicable public interest review
factors. The Corps regulations do not require public notice and comment
for any conditions added to Department of the Army permits, including
standard permits, letters of permission, and all categories of general
permits.
Two commenters stated that applicants should be required to submit
detailed mitigation plans with their pre-construction notifications and
conceptual mitigation proposals are not sufficient. One commenter said
paragraph (e)(2) should be revised to require the prospective permittee
to submit a compensatory mitigation proposal if the activity will
result in the loss of greater than \1/10\-acre of wetlands.
Paragraph (b)(5) requires the prospective permittee to submit a
statement explaining how the mitigation requirement will be satisfied
or why the adverse effects of the proposed activity on the aquatic
environment are minimal without mitigation. A detailed or conceptual
mitigation plan may be submitted with the pre-construction
notification, and a conceptual mitigation plan is usually sufficient
for making the minimal adverse effects determination. If the proposed
mitigation shown in the conceptual mitigation plan is acceptable, a
detailed mitigation plan that complies with the requirements of 33 CFR
332.4(c)(2)-(14) will be required and must be approved by the district
engineer before work begins in waters of the United States unless the
district engineer determines such prior approval is not practicable or
necessary (see paragraph (c)(3) of general condition 23, mitigation).
One commenter said that state agencies operating under Federal
funding should be added to paragraphs (b)(6) and (b)(7), for the
submittal of documentation demonstrating compliance with Section 7 of
the Endangered Species Act or Section 106 of the National Historic
Preservation Act. This commenter also stated that pre-construction
notifications should be provided electronically as well. One commenter
said that a pre-construction notification should include information
demonstrating that a project complies with applicable federal and state
requirements.
A state agency operating under Federal funding, where the Federal
agency has conducted Endangered Species Act Section 7 consultation or
National Historic Preservation Act Section 106 consultation for the
activity that is being provided Federal funds, may provide that
documentation to the district engineer as part of its pre-construction
notification, but the district engineer will determine whether that
consultation is sufficient for the NWP activity. The NWP regulations at
33 CFR 330.1(e)(1) state that pre-construction notifications must be in
writing. We have modified paragraph (d)(4) to state that prospective
permittees may also provide electronic files of pre-construction
notifications to expedite agency coordination. Compliance with other
Federal, state, or local requirements is the responsibility of the
permittee, and the Corps does not have the authority to enforce the
regulatory requirements of programs administered by other agencies.
Several commenters objected to the requirement for a delineation of
special aquatic sites and other waters of the United States under
paragraph (b)(4) of this general condition, because requiring a full
delineation has become a significant cause of delays and increased
costs due to uncertainties regarding the extent of Federal
jurisdictional waters under U.S. Supreme Court decisions in 2001 and
2006. One commenter said that in the second sentence of paragraph
(b)(4) the term ``wetland delineation'' should be replaced with
``delineation of waters of the United States,'' because the requirement
is for not only a delineation of wetlands but also of other waters of
the United States. One commenter suggested modifying paragraph (b)(4)
to clarify that a jurisdictional determination is not required with the
submittal of a complete pre-construction notification, just a
delineation of waters of the United States, which would be completed by
either the prospective permittee or the Corps.
We have modified paragraph (b)(4) to state that a pre-construction
notification must include a delineation of wetlands, other special
aquatic sites, and other aquatic habitats (e.g., perennial,
intermittent, and ephemeral streams, and lakes and ponds) on the
project site, instead of a delineation of special aquatic sites and
other waters of the United States. Use of the term ``waters of the
United States'' in this paragraph implies that an approved
jurisdictional determination would have to be done for a NWP pre-
construction notification. An approved jurisdictional determination is
an official Corps determination that jurisdictional ``waters of the
United States'' or ``navigable waters of the United States,'' or both,
are either present or absent on a particular site, and precisely
identifies the limits of those waters on the project site that are
determined to be jurisdictional under the Clean Water Act or Sections 9
and 10 of the Rivers and Harbors Act of 1899 (see Regulatory Guidance
Letter 08-02). We understand that many users of the NWPs do not want to
obtain an approved jurisdictional determination, and that preliminary
jurisdictional determinations may be appropriate for the purposes of
NWP authorizations.
Under a preliminary jurisdictional determination, the wetlands,
other special aquatic sites, and other aquatic habitats on the project
site are presumed to be waters of the United States for the purposes of
the NWP authorization, and any compensatory mitigation that may be
required. A project proponent has the option of requesting an approved
jurisdictional determination if he or she believes that some or all of
the wetlands, special aquatic sites, or other aquatic habitats are not
waters of the United States, and wants an official jurisdictional
determination from the Corps. A request for an approved jurisdictional
determination should be submitted to the Corps in advance of submitting
a pre-construction notification, because the Corps may not be able to
make an approved jurisdictional determination within the 45-day pre-
construction notification review period, and this NWP rule does not
contain a provision stating that approved jurisdictional determinations
[[Page 10260]]
are necessary to make a decision on an NWP pre-construction
notification.
Several commenters suggested modifying the general condition to
allow the applicant to satisfy the pre-construction notification
requirement by demonstrating that consultation under the National
Historic Preservation Act (NHPA) and/or Endangered Species Act (ESA)
has been completed and has resulted in a finding that the project would
not adversely affect resources protected under those statutes. One of
the commenters also stated that paragraph (e)(1) is incorrect, because
the condition refers to a limit of 300 feet, but NWP 13 has a limit of
500 feet that can be waived. One commenter stated that submittal of a
pre-construction notification should be required for any NWPs within
303(d) impaired waters and that the applicant should prepare a
statement identifying how the project avoids contributing to existing
water quality impairments and maintains consistency with any existing
Total Daily Maximum Loads (TMDLs).
Pre-construction notification is required for NWP activities that
might affect endangered or threatened species listed, or proposed for
listing, under the Endangered Species Act (see 33 CFR 330.4(f)(2)).
Likewise, pre-construction notification is required for NWP activities
that may affect historic properties (see 33 CFR 330.4(g)(2)). It is the
Corps responsibility to make effect determinations for the purposes of
the NWP authorizations. Information provided by the project proponent
for Endangered Species Act or National Historic Preservation Act
compliance will be fully considered by the district engineer, but it is
the district engineer's decision as to whether the requirements of
those acts have been complied with for the NWP authorizations. We have
determined that modification of paragraph (e)(1) (which has been moved
to paragraph 1 of Section D, District Engineer's Decision) is not
necessary, as the 500 linear foot limit for the request for a waiver of
NWP 13 is ``an otherwise applicable limit'' as specified in this text.
The state agency that makes water quality certifications for the NWPs
has the authority to determine whether an NWP should authorize
discharges into 303(d) impaired waters, so we do not believe pre-
construction notification should be categorically required for all such
discharges. As noted previously, many waters are impaired for
pollutants not related to discharges of dredge or fill material.
Two commenters said that under paragraph (c) of this general
condition, there are problems with using ENG 4345 for pre-construction
notifications, because the standard permit form requires information
that is not listed in paragraphs (b)(2) through (b)(7), and those
paragraphs also cite information that is not required by ENG 4345.
The standard permit form, ENG 4345, may be used for pre-
construction notifications, and it is not necessary to fill out those
fields in ENG 4345 that are not relevant to paragraphs (b)(2) through
(b)(7). The prospective permittee must supplement ENG 4345 if the NWP
pre-construction notification must include information that is not
specifically required by ENG 4345. A permittee is not required to use
ENG 4345 for pre-construction notification as long as all required
information is included.
Several commenters said that the threshold for agency coordination
should be increased, or that interagency coordination is not necessary.
In contrast, several commenters stated that the thresholds for agency
coordination should be decreased. One commenter said agency
coordination should be required for any activity potentially impacting
approved mitigation banks, other mitigation areas, or local, state, or
Federal public properties. One commenter suggested requiring agency
coordination for NWP 12 activities, because they could result in the
loss of greater than \1/2\-acre of waters of the United States.
We believe the agency coordination thresholds established in
paragraph (d)(2) of this general condition are appropriate, and focus
on those activities where it would be helpful to solicit the views of
the listed agencies prior to making a decision on an NWP pre-
construction notification. Potential impacts to mitigation banks, other
compensatory mitigation project sites, or other public properties are
more appropriately addressed through the district engineer's review,
and do not require additional agency coordination under the NWP
program. However, agency coordination may be required under other
regulations, such as 33 CFR 332.8, which has an interagency review
process for the establishment and operation of mitigation banks and in-
lieu fee programs. A proposed activity that may directly affect an
approved mitigation bank or in-lieu fee project site may require the
district engineer to consult with an interagency review team before
making a decision on that activity. The limits for NWP 12 apply to
single and complete projects, and for each single and complete project
the NWP 12 activity may not result in the loss of greater than \1/2\-
acre of waters of the United States. As discussed elsewhere in this
final rule, in response to pre-construction notifications for NWP 12
activities that are linear projects, district engineers will evaluate
the cumulative effects of those linear projects on the aquatic
environment when determining whether authorization by NWP is
appropriate. We do not believe it is necessary to require agency
coordination for those linear projects.
This general condition is adopted with the modifications discussed
above.
District Engineer's Decision
We have established a new Section D, District Engineer's Decision,
by moving paragraph (e) of the proposed general condition 30 (now
designated as general condition 31) to a separate section of the NWPs.
We believe this is appropriate because the proposed paragraph (e) does
not require compliance on the part of the permittee. Therefore, the
criteria that district engineers use to determine whether a particular
activity is authorized by NWP should not be in the general conditions.
The comments received in response to the proposed paragraph (e) of the
pre-construction notification general condition have been moved to this
new section.
Two commenters objected to the language which states that the
district engineer must determine that the proposed NWP activity is not
contrary to the public interest. One of these commenters said that
Section 404(e) of the Clean Water Act does not require such a public
interest review for NWP activities, and this provision should be
deleted because it conflicts with other Corps regulations.
The NWP regulations clearly state that the district engineer may
exercise discretionary authority if he or she identifies concerns for
the aquatic environment under the 404(b)(1) Guidelines or for any
factor of the public interest (see 33 CFR 330.1(d)). In addition, the
NWP regulations also require the district engineer to review pre-
construction notifications and add conditions to the NWP authorization
if necessary to ensure that the activity results in minimal individual
and cumulative adverse effects on the aquatic environment and the
public interest (see 33 CFR 330.1(e)(2)). The Corps issued those
regulations under its authority under Section 404 of the Clean Water
Act and Section 10 of the Rivers and Harbors Act of 1899.
One commenter suggested adding definitions of the terms ``direct''
and ``indirect'' to the NWPs. Two commenters requested clarification on
when a district engineer can exercise discretionary authority for the
purposes of the NWP authorization, particularly for those circumstances
where pre-
[[Page 10261]]
construction notification is not required by the NWP. Several
commenters said that the district engineer should also evaluate the
environmental benefits of a project.
We have added definitions for the terms ``direct effects'' and
``indirect effects'' to the ``Definitions'' section of the NWPs.
District engineers have the authority to modify, suspend, or revoke any
NWP authorization (see 33 CFR 330.1(d) and 33 CFR 330.4(e)(2)) when he
or she has identified sufficient concerns for the environment or other
factors of the public interest. District engineers may also consider
environmental benefits that may result when making a decision as to
whether an NWP activity results in minimal individual and cumulative
adverse effects to the aquatic environment.
One commenter stated that the factors required for a district
engineer to make a minimal effects determination on a request for a
waiver of the limits of any NWP suggests a level of analysis that is
more comparable to the individual permit process, which threatens the
availability of the NWPs for prospective permittees.
The evaluation of a request for a waiver of the 300 linear foot
limit for the loss of intermittent or ephemeral stream bed, or any
other limit that can be waived by the district engineer, is an
important tool for maintaining flexibility in the NWP, and authorizing
activities that result in minimal individual and cumulative adverse
effects on the aquatic environment. The waiver review process is not
comparable to the individual permit review process, because it does not
require a public notice, National Environmental Policy Act
documentation, and a project-specific 404(b)(1) Guidelines analysis.
In response to the proposed considerations for making minimal
effects determination, one commenter suggested adding the type of
resource that will be affected by the NWP. This commenter also
recommended defining the term ``minimal effects'' as those effects that
constitute relatively small changes in the affected environment and
insignificant changes in ecological function or hydrology. This
commenter said the minimal effects decision may also depend on whether
the proposed activity will occur in a special aquatic site, its
proximity to nesting or spawning areas, the presence of state- or
federally-listed species of concern other than endangered or threatened
species, and the amount of permitted or unpermitted aquatic resource
loss in the same watershed, stream reach, and/or bay or estuary.
We agree that adding the resource type is appropriate, because the
minimal effects threshold may be different for a difficult-to-replace
resource such as a stream, bog, fen, or spring. We do not agree that a
finding of minimal effects should be based on small changes to the
affected environment, ecological function, or hydrology. While the NWPs
have acreage or linear foot limits, or inherent limits based on the
type of activity authorized, at a small scale those activities result
in complete losses of ecological function or hydrology because most
discharges of dredged or fill material into waters of the United States
replace aquatic areas with dry land. These complete losses of waters of
the United States often have minimal individual and cumulative adverse
effects on the aquatic environment. It is the environmental setting and
other factors listed in the proposed paragraph (e)(1) (which has been
changed to paragraph (1) of Section D) that are more appropriate for
making the minimal effects determination. It is also the broader
watershed or landscape context that is important for determining
whether minimal adverse effects on the aquatic environment will result.
Proximity to nesting or spawning areas is more appropriately addressed
through compliance with general condition 4, migratory bird breeding
areas, and general condition 3, spawning areas. Division engineers may
impose regional conditions to restrict or prohibit the use of NWPs to
authorize activities that may affect state- or federally-listed species
of concern if they determine, after the public notice and comment
process, it is in the public interest to add such regional conditions
to ensure minimal adverse effects. The Corps is required to consider
effects within a wetland, stream reach, or coastal waterbody that are
caused either by an individual activity, or cumulatively by many such
activities authorized by the same NWP, and to determine that such
effects are minimal before use of an NWP can be authorized.
We have made additional modifications to the text of this provision
of the NWPs. In the first paragraph, we have added a sentence stating
that for linear projects, the district engineer will evaluate the
individual crossings to determine if they satisfy the terms and
conditions of the applicable NWP(s), as well as the cumulative effects
of all the crossings authorized by NWPs. This sentence is consistent
with the preamble for the NWP final regulation published in the
November 22, 1991, issue of the Federal Register, in which the
definition of ``single and complete project'' at 33 CFR 330.2(i) was
promulgated (see 56 FR 59114).
In paragraphs (2) and (3) of Section D, we have added text to be
consistent with the mitigation rule at 33 CFR part 332, with a focus on
adding activity-specific conditions to the NWP authorization for
compensatory mitigation requirements. We have also added a provision to
the end of paragraph (3) stating that the district engineer may
determine that prior approval of a mitigation plan is not practicable
or not necessary to ensure timely completion of the required
compensatory mitigation. This provision is consistent with 33 CFR
332.3(k)(3).
Definitions
Best management practices (BMPs). We did not receive any comments
on the proposed definition. The definition is adopted as proposed.
Compensatory mitigation. We proposed to modify this definition to
make it consistent with the definition of this term found in 33 CFR
332.2. We did not receive any comments on the proposed definition and
the definition is adopted as proposed.
Currently serviceable. We did not proposed any changes for this
definition. We did not receive any comments on the proposed definition.
The definition is adopted as proposed.
Direct effects. In response to several comments, we are adding a
definition of ``direct effects'' to provide clarification to be used
with paragraph (1) of Section D, District Engineer's Decision. We have
adapted this definition from the Council of Environmental Quality's
definition in their National Environmental Policy Act regulations at 40
CFR 1508.8(a).
Discharge. The proposed definition included the phrase ``and any
activity that causes or results in such a discharge.''
One commenter said that that phrase should be removed because it is
inconsistent with court decisions on the definition of ``discharge of
dredged material.'' We inadvertently included the language in the
proposal, and are removing it from the definition.
This definition is adopted with the modification discussed above.
Enhancement. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Ephemeral stream. We did not propose any changes to the definition.
One commenter said the definition should be modified to state that for
ephemeral streams, flow is also derived from snow melt as well as
rainfall. One
[[Page 10262]]
commenter requested clarification that the definition of ephemeral
stream did not include roadside ditches.
While snow melt may contribute to the flow of ephemeral streams,
snow melt also contributes to the flow of intermittent and perennial
streams, especially in areas with deep snow packs. The proposed
definition appropriately focuses on the duration of flow, and melting
snow should not be considered a precipitation event since the
development of snow pack occurs over the course of a winter season.
Therefore, we are not making the suggested change. Ephemeral streams
may, in some circumstances, be channelized or relocated to become
roadside ditches, so we do not agree that recommended change should be
made.
The definition is adopted as proposed.
Establishment (creation). We did not receive any comments on the
proposed definition. The definition is adopted as proposed.
High Tide Line. We proposed to add this as a new definition, based
on the definition at 33 CFR 328.3(d). One commenter suggested expanding
the definition of storm surges to include build up of water against a
coast or a bay by flood waters which cause water levels to exceed
spring high tide levels.
We do not agree that the suggested change should be made to this
definition, because it would make the definition inconsistent with 33
CFR 328.3(d), which states that storm surges are not to be used to
identify the high tide line.
The definition is adopted as proposed.
Historic property. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Independent utility. We proposed to add ``non-linear'' in the first
sentence after ``complete'' and before project to reflect the
independent utility test only applies to single and complete non-linear
projects.
One commenter requested that the term ``independent utility'' be
eliminated from the nationwide permit program because it discourages
assessment of a project's total impacts. Another commenter asked
whether the term independent utility applied to both single and
complete non-linear projects and single and complete linear projects.
The concept of ``independent utility'' is important for the
implementation of the NWP program because it provides a useful test to
help determine whether proposed activities requiring Department of the
Army authorization should be evaluated together for one permit
authorization, or may be evaluated separately to determine if each
activity qualifies for its own permit authorization. Despite the
independent utility test, the cumulative effects of NWP activities must
still be evaluated by district engineers when they review pre-
construction notifications or other NWP verification requests. The
modified definition makes it clear that the independent utility test
only applies to single and complete non-linear projects; however,
separate linear projects may have independent utility.
This definition is adopted as proposed.
Indirect effects. In response to several comments, we are adding a
definition of ``indirect effects'' to provide clarification to be used
with paragraph (1) of Section D, District Engineer's Decision. We have
adapted this definition from the Council on Environmental Quality's
definition in their National Environmental Policy Act regulations at 40
CFR 1508.8(b).
Intermittent stream. We did not receive any comments on the
proposed definition. The definition is adopted as proposed.
Loss of waters of the United States. We did not propose any changes
to the definition. One commenter said the loss of stream bed should be
defined. One commenter suggested revising this definition to state that
waters of United States temporarily filled, flooded, excavated, or
drained, but restored to pre-construction contours and elevations after
construction, are not included in the measurement of loss of waters of
the United States, especially as it relates to utility line
construction. Another commenter said that clarification should be
provided to state that for the purposes of the NWPs, the loss of waters
of the United States generally does not include the cleared area along
the utility line right-of-way between two poles or towers supporting
overhead power transmission lines. One commenter requested
clarification of application of this definition to activities in the
ocean, bays, and Great Lakes, especially in the context of NWP 52
activities. This commenter recommended stating, for the purposes of NWP
52, that the loss only applies to the area of the ocean, bay, or Great
Lakes occupied by wind towers and associated structures such as
meteorological towers and transformers.
The proposed definition stated that the loss of stream bed results
from filling or excavating the stream bed, and we do not believe it is
necessary to change that definition. The proposed definition also
stated that waters of the United States temporarily filled, flooded,
excavated, or drained, but restored to pre-construction contours and
elevations after construction, are not included in the measurement of
loss of waters of the United States. That provision may apply to
temporary impacts to waters of the United States caused by utility
lines activities, or to any other activity involving temporary filling,
flooding, excavation, or drainage. While the presence of an overhead
utility line above waters of the United States does not constitute a
``loss of waters of the United States,'' the construction of a utility
line right-of-way for overhead transmission lines may result in losses
of waters of the United States if it involves discharges of dredged or
fill material into waters of the United States that cause permanent
conversions of aquatic areas to dry land or permanent increases to the
bottom elevation of a waterbody.
The application of this definition to renewable energy generation
facilities in coastal waters and the Great Lakes depends on the type of
activity. A structure installed in these waters is generally not
considered to result in a loss of waters of the United States, unless
it is a pile supported structure that is constructed by placing a
series of piles so closely together that they have the effect of fill
(see 33 CFR 323.3(c)). If the construction of these facilities and
associated structures involves the placement of materials that meet
either the definition of ``discharge of dredged material'' at 33 CFR
323.2(d) or ``discharge of fill material'' at 33 CFR 323.2(f), such as
the placement of riprap at the base of a pile supported structure, then
the area of sea bed or lake bed covered by that dredged or fill
material would be counted towards the ``loss of waters of the United
States'' for that activity.
The definition is adopted as proposed.
Non-tidal wetland. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Open water. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Ordinary high water mark. We did not propose any changes to the
definition. One commenter said the definition should state that, for
flowing waters, the term ordinary high water mark includes the bankfull
stage or elevation, since this indicator can be readily delineated at
most locations.
The bankfull elevation is not a useful tool for identifying the
ordinary high water marks of streams or rivers in some parts of the
country, especially the arid west. In the arid west, the Corps
[[Page 10263]]
examines stream geomorphology and vegetation that is responsive to the
dominant stream discharge to identify the ordinary high water mark for
intermittent and ephemeral streams (see ``A Field Guide to the
Identification of the Ordinary High Water Mark (OHWM) in the Arid West
Region of the Western United States: A Delineation Manual'' published
by the Corps Engineer Research and Development Center, report number
ERDC/CRREL TR-08-12, dated August 2008).
The definition is adopted as proposed.
Perennial stream. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Practicable. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Pre-construction notification. We did not receive any comments on
the proposed definition. The definition is adopted as proposed.
Preservation. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Re-establishment. We proposed to modify this definition by adding
``and functions'' to the end of the last sentence in order to be
consistent with the definition of this term found in 33 CFR 332.2.
Two commenters objected to the proposed change. The addition of the
phrase ``and functions'' makes this definition consistent with the
definition at 33 CFR 332.2, which was promulgated in 2008. The
objective of re-establishing aquatic resources is to provide aquatic
resource functions.
The definition is adopted as proposed.
Rehabilitation. We did not propose any changes to this definition.
One commenter expressed support of this definition. The definition is
adopted as proposed.
Restoration. We did not propose any changes to this definition. One
commenter expressed support of this definition. The definition is
adopted as proposed.
Riffle and pool complex. We did not receive any comments on the
proposed definition. The definition is adopted as proposed.
Riparian areas. We did not propose any changes to this definition,
and we did not receive any comments on the proposed definition. We have
changed this definition to more accurately describe where riparian
areas occur, and what types of features may be found in riparian areas.
We have replaced the word ``waterbody'' with the phrase ``riverine,
lacustrine, estuarine, and marine waters,'' since the definition of
``waterbody'' includes wetlands and wetlands by themselves do not have
riparian areas. We have also added ``wetlands, non-wetland waters, or''
between the words ``adjacent'' and ``uplands'' since riparian areas are
not limited to uplands. There may be wetlands and non-wetland (open)
waters such as oxbow lakes and ponds within a riparian area. The
definition is adopted with the modifications discussed above.
Shellfish seeding. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Single and complete linear project and single and complete non-
linear project. We proposed to take the definition of ``single and
complete project'' and split it into two definitions to clarify the use
the term ``single and complete project'' for linear and non-linear
projects. Our proposal was based on the definition for ``single and
complete project'' at 33 CFR 330.2(i) that was provided in the November
22, 1991, final rule (56 FR 59113).
Many commenters expressed support for the proposal. Most of these
commenters also agreed that the independent utility test does not apply
to single and complete linear projects. They said the proposed
definitions will remove some of the uncertainty and inconsistencies
that currently exist with respect to how multiple stream and wetland
crossings are evaluated for linear projects as opposed to non-linear
projects. One commenter asked for assurance that these new definitions
would not materially affect how the Corps evaluates separate crossings
of tributaries for the purposes the NWP program.
These two definitions are consistent with the NWP regulations and
are not expected to have an effect on the Corps current practices for
implementing the NWP program for both linear and non-linear projects.
One commenter opposed differentiating between linear and non-linear
projects for the purposes of the definition of single and complete
project. One commenter said that references to single and complete
linear projects and single and complete non-linear projects should be
removed from the NWPs. One commenter stated that these two definitions
would complicate the water quality certification process.
The separate definitions established in today's rule will help
provide consistent implementation of the NWP program by clarifying how
the term ``single and complete project'' should be applied for
different types of activities authorized by NWP. These definitions are
important for efficient implementation of the Corps Regulatory Program
and determining whether a particular regulated activity and any related
regulated activities qualify for NWP authorization. Therefore, we do
not agree that these terms should be removed from the NWP program. The
definition of ``single and complete project'' for the NWPs has been in
place since 1991 and the separate definitions provided in today's final
rule are consistent with the 1991 definition. Therefore, the use of
these definitions should not complicate the water quality certification
process.
One commenter requested the addition of examples, such as utility
lines, to the definition of single and complete linear project. One
commenter asked for clarification on whether the term independent
utility only applies to non-linear single and complete projects.
Several commenters said the definition of single and complete linear
project should preclude district engineers from evaluating separate
crossings cumulatively.
The new definitions distinguish between linear and non-linear
projects and reflect the fact that while each single and complete non-
linear project must have independent utility, each single and complete
linear project need not have independent utility within the overall
linear project. However, separate linear projects may have independent
utility. To clarify what a linear project is, we have added a sentence
to the definition of single and complete linear project to state that a
linear project is a project constructed for the purpose of getting
people, goods, or services from a point of origin to a terminal point.
A linear project may involve multiple crossings of streams, wetlands,
or other types of waters from the point of origin to the terminal
point. Roads and pipelines are examples of linear projects. While each
separate and distant crossing of a waterbody associated with a linear
project would be considered a separate single and complete project for
the purposes of the NWPs, district engineers will also evaluate the
cumulative effects of those crossings to determine whether they qualify
for NWP authorization.
One commenter said that for an overall linear project the sum total
of the losses of waters of the United States associated with that
linear project cannot exceed the acreage or linear foot limits for an
NWP. Several commenters stated that it was inappropriate to use
multiple NWPs to authorize multiple crossings associated with one
overall linear project, because it would be
[[Page 10264]]
impossible for the district engineer to determine if the overall
project had minimal adverse effects on the environment or prevent the
Corps from assessing the cumulative effects caused by the overall
project. One commenter said these two proposed definitions may conflict
with the NWP general conditions.
For single and complete linear projects, each separate and distant
crossing of a waterbody, as well as each crossing of other waterbodies
along the corridor for the linear project may be permitted by separate
NWP authorizations. The acreage and other applicable limits for an NWP
would be applied to each crossing, as long as those crossings are far
enough apart to be considered separate and distant. District engineers
will evaluate the cumulative effects of those linear projects when
determining whether authorization by NWP is appropriate. The approach
to cumulative effects analysis for linear projects is little different
than the cumulative effects analysis for other types of NWP activities,
including those circumstances in which more than one NWP is used to
authorize a single and complete non-linear project, because cumulative
effects are evaluated on a regional basis. Cumulative effects analysis
may be done on a watershed basis, or by using a different type of
geographic area, such as an ecoregion.
One commenter asked how offshore wind energy projects would be
evaluated in accordance with these definitions, especially how the
turbines, substations, cables, and associated infrastructure would be
considered as either single and complete linear projects or single and
complete non-linear projects.
Deciding which definition to apply to a particular project depends
on the configuration of the project relative to the locations of waters
of the United States within the project boundaries. For offshore wind
energy projects, the turbines would be located on structures in a
single waterbody as would the transmission cables that transfer the
energy from the turbines to a land-based substation, while land-based
attendant features might be constructed in separate waterbodies located
within a tract of land. The off-shore turbine structures and land-based
attendant features may be considered as a single and complete non-
linear project, while as discussed above for NWPs 51 and 52, the
utility lines that transfer the energy from the renewable energy
generation facilities to a distribution system, regional grid, or other
facility may be considered to be separate single and complete linear
projects and may be authorized under a separate NWP, such as NWP 12.
The district engineer will have to consider the activity-specific
circumstances when determining which definition to apply and which NWPs
are appropriate to use.
One commenter asked whether district engineers have the authority
to change the definitions of single and complete project or independent
utility. Two commenters said the term ``distant'' should be defined in
``single and complete linear project.''
The definitions provided in today's final rule cannot be changed by
district engineers, but those definitions will be subject to
interpretation after these NWPs go into effect and they are
implemented. It is not practical to provide specific definition of
``distant'' since that must be a judgment call by the district engineer
because of the substantial variability in landscapes and environmental
conditions across the country.
The definition for ``single and complete linear project'' is
adopted with the modification discussed above. The definition for
``single and complete non-linear project'' is adopted as proposed.
Stormwater management. We did not receive any comments on the
proposed definition. The definition is adopted as proposed.
Stormwater management facilities. We did not receive any comments
on the proposed definition. The definition is adopted as proposed.
Stream bed. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Stream channelization. We did not receive any comments on the
proposed definition. The definition is adopted as proposed.
Structure. We did not propose any changes to the definition. One
commenter requested that we include bridges and culverts in the
definition of structures.
Depending on how a bridge or culvert is constructed, and its
effects on the aquatic environment, it may be considered a structure or
fill. The bridge supports (i.e., bents) may be considered to be a
structure for the purposes of this definition. However, placement of a
culvert in a water of the United States can have the effect of raising
the bottom elevation and thus should be regulated as fill. Accordingly,
we are retaining the definition of structure as is presently proposed.
Tidal wetland. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Vegetated shallows. We did not receive any comments on the proposed
definition. The definition is adopted as proposed.
Waterbody. We did not receive any comments on the proposed
definition, but we believe some modification of the definition is
necessary to make it simpler and clearer. The revised definition simply
says that, for the purposes of the NWPs, a waterbody is a
jurisdictional water of the United States. We have removed the text
referring to the presence of standing or flowing water above ground and
the statement that an ordinary high water mark is an indicator of
jurisdiction. The ordinary high water mark indicates the lateral extent
of jurisdiction for a non-wetland waterbody in the absence of adjacent
wetlands (see 33 CFR 328.4(c)(1)); the jurisdictional status of the
waterbody is determined by applying the appropriate regulatory or legal
criteria. In cases where the waterbody is a wetland, the lateral extent
of the waterbody is the wetland boundary. Likewise, we have revised the
last sentence of this definition by removing the phrase ``a
jurisdictional waterbody displaying an OHWM or other indicators of
jurisdiction'' and replacing it with ``a waterbody determined to be a
water of the United States under 33 CFR 328.3(a)(1)-(6)''.
The definition is adopted with the modifications discussed above.
In addition to the comments submitted on definitions provided in
the proposed rule, we received a number of comments suggesting the
addition of more definitions to the ``Definitions'' section of the
NWPs.
One commenter requested that we define ``discrete event'' as it
pertains to NWP 3 and NWP 45. One commenter asked for a definition of
mechanized land clearing as it relates to the first pre-construction
notification threshold in NWP 12, to make it clear whether activities
that only involve the cutting or removal of vegetation above the ground
are, or are not, regulated activities. One commenter said that the
definition of fill should be provided in the NWPs to clarify the types
of materials allowed or prohibited by the NWPs.
What constitutes a ``discrete event'' for the purposes of NWPs 3
and 45 is at the discretion of the district engineer, and in both NWPs
we provide examples that give context to the term ``discrete event.''
In NWP 3, storms, floods, and fire are examples of discrete events. For
NWP 45, storms and floods provide examples of discrete events. The
definition of ``discharge of dredged material'' at 33 CFR 323.2(d) is
used to determine whether mechanized landclearing involves a discharge
of
[[Page 10265]]
dredged material that is regulated under Section 404 of the Clean Water
Act. Project proponents are encouraged to contact the district engineer
to determine whether a particular activity involving mechanized
clearing of a utility line right-of-way in a forested wetland
constitutes a regulated activity, because the equipment and techniques
used are important considerations. The definition of the term ``fill
material'' is provided in the Corps regulations at 33 CFR 323.2(e).
Nationwide permit activities must comply with general condition 6,
suitable material, and it is not feasible to provide a comprehensive
list of the types of materials that may be used as fill material for
NWP activities.
One commenter suggested adding a definition of ``special aquatic
sites'' in the NWPs. One commenter said the definition of special
aquatic sites should include glides, side channels, floodplains, and
other types of habitats that create and maintain habitat for salmon and
other fish species.
The NWPs have a definition for one of the special aquatic sites
listed in the 404(b)(1) Guidelines, specifically riffle and pool
complexes and vegetated shallows. Definitions for the other special
aquatic sites, that is, sanctuaries and refuges, wetlands, mud flats,
and coral reefs, are found at sections 230.40, 230.41, 230.42, and
230.44 of 40 CFR part 230, respectively. Glides, side channels,
floodplains, and salmon and fish habitat are not considered special
aquatic sites unless they satisfy the criteria at 40 CFR 230.40 through
230.45.
Regional Conditioning of the Nationwide Permits
Concurrent with this Federal Register notice, district engineers
are issuing local public notices. In addition to the changes to some
NWPs and NWP conditions required by the Chief of Engineers, division
and district engineers may propose regional conditions or propose
revocation of NWP authorization for all, some, or portions of the NWPs.
Regional conditions may also be required by state or Tribal water
quality certification or for state Coastal Zone Management Act
consistency. District engineers will announce regional conditions or
revocations by issuing local public notices. Information on regional
conditions and revocation can be obtained from the appropriate district
engineer, as indicated below. Furthermore, this and additional
information can be obtained on the Internet at https://www.saj.usace.army.mil/Divisions/Regulatory/HQAvatar.htm which will
help the public find the home page of the appropriate Corps district
office.
Contact Information for Corps District Engineers
Alabama
Mobile District Engineer, ATTN: CESAM-RD, 109 St. Joseph Street,
Mobile, AL 36602-3630
Alaska
Alaska District Engineer, ATTN: CEPOA-RD, P.O. Box 6898, Elmendorf AFB,
AK 99506-6898
Arizona
Los Angeles District Engineer, ATTN: CESPL-RG-R, P.O. Box 532711, Los
Angeles, CA 90053-2325
Arkansas
Little Rock District Engineer, ATTN: CESWL-RD, P.O. Box 867, Little
Rock, AR 72203-0867
California
Sacramento District Engineer, ATTN: CESPK-RD, 1325 J Street,
Sacramento, CA 95814-2922
Colorado
Albuquerque District Engineer, ATTN: CESPA-OD-R, 4101 Jefferson Plaza
NE., Albuquerque, NM 87109-3435
Connecticut
New England District Engineer, ATTN: CENAE-R, 696 Virginia Road,
Concord, MA 01742-2751
Delaware
Philadelphia District Engineer, ATTN: CENAP-OP-R, Wannamaker Building,
100 Penn Square East Philadelphia, PA 19107-3390
Florida
Jacksonville District Engineer, ATTN: CESAJ-RD, P. O. Box 4970,
Jacksonville, FL 32232-0019
Georgia
Savannah District Engineer, ATTN: CESAS-RD, 100 West Oglethorpe Avenue,
Savannah, GA 31401-3640
Hawaii
Honolulu District Engineer, ATTN: CEPOH-EC-R, Building 230, Fort
Shafter, Honolulu, HI 96858-5440
Idaho
Walla Walla District Engineer, ATTN: CENWW-RD, 201 North Third Avenue,
Walla Walla, WA 99362-1876
Illinois
Rock Island District Engineer, ATTN: CEMVR-OD-P, P.O. Box 2004, Rock
Island, IL 61204-2004
Indiana
Louisville District Engineer, ATTN: CELRL-OP-F, P.O. Box 59,
Louisville, KY 40201-0059
Iowa
Rock Island District Engineer, ATTN: CEMVR-OD-P, P.O. Box 2004, Rock
Island, IL 61204-2004
Kansas
Kansas City District Engineer, ATTN: CENWK-OD-R, 635 Federal Building,
601 E. 12th Street, Kansas City, MO 64106-2896
Kentucky
Louisville District Engineer, ATTN: CELRL-OP-F, P.O. Box 59,
Louisville, KY 40201-0059
Louisiana
New Orleans District Engineer, ATTN: CEMVN-OD-S, P.O. Box 60267, New
Orleans, LA 70160-0267
Maine
New England District Engineer, ATTN: CENAE-R, 696 Virginia Road,
Concord, MA 01742-2751
Maryland
Baltimore District Engineer, ATTN: CENAB-OP-R, P.O. Box 1715,
Baltimore, MD 21203-1715
Massachusetts
New England District Engineer, ATTN: CENAE-R, 696 Virginia Road,
Concord, MA 01742-2751
Michigan
Detroit District Engineer, ATTN: CELRE-RG, 477 Michigan Avenue,
Detroit, MI 48226-2550
Minnesota
St. Paul District Engineer, ATTN: CEMVP-OP-R, 180 Fifth Street East,
Suite 700, St. Paul, MN 55101-1678
Mississippi
Vicksburg District Engineer, ATTN: CEMVK-OD-F, 4155 Clay Street,
Vicksburg, MS 39183-3435
Missouri
Kansas City District Engineer, ATTN: CENWK-OD-R, 635 Federal Building,
601 E. 12th Street, Kansas City, MO 64106-2896
[[Page 10266]]
Montana
Omaha District Engineer, ATTN: CENWO-OD-R, 1616 Capitol Avenue, Omaha,
NE 68102-4901
Nebraska
Omaha District Engineer, ATTN: CENWO-OD-R, 1616 Capitol Avenue, Omaha,
NE 68102-4901
Nevada
Sacramento District Engineer, ATTN: CESPK-CO-R, 1325 J Street,
Sacramento, CA 95814-2922
New Hampshire
New England District Engineer, ATTN: CENAE-R, 696 Virginia Road,
Concord, MA 01742-2751
New Jersey
Philadelphia District Engineer, ATTN: CENAP-OP-R, Wannamaker Building,
100 Penn Square East, Philadelphia, PA 19107-3390
New Mexico
Albuquerque District Engineer, ATTN: CESPA-OD-R, 4101 Jefferson Plaza
NE., Albuquerque, NM 87109-3435
New York
New York District Engineer, ATTN: CENAN-OP-R, 26 Federal Plaza, New
York, NY 10278-0090
North Carolina
Wilmington District Engineer, ATTN: CESAW-RG, P.O. Box 1890,
Wilmington, NC 28402-1890
North Dakota
Omaha District Engineer, ATTN: CENWO-OD-R, 1616 Capitol Avenue, Omaha,
NE 68102-4901
Ohio
Huntington District Engineer, ATTN: CELRH-OR-F, 502 8th Street,
Huntington, WV 25701-2070
Oklahoma
Tulsa District Engineer, ATTN: CESWT-RO, 1645 S. 101st East Ave.,
Tulsa, OK 74128-4609
Oregon
Portland District Engineer, ATTN: CENWP-OD-G, P.O. Box 2946, Portland,
OR 97208-2946
Pennsylvania
Baltimore District Engineer, ATTN: CENAB-OP-R, P.O. Box 1715,
Baltimore, MD 21203-1715
Rhode Island
New England District Engineer, ATTN: CENAE-R, 696 Virginia Road,
Concord, MA 01742-2751
South Carolina
Charleston District Engineer, ATTN: CESAC-CO-P, P.O. Box 919,
Charleston, SC 29402-0919
South Dakota
Omaha District Engineer, ATTN: CENWO-OD-R, 1616 Capitol Avenue, Omaha,
NE 68102-4901
Tennessee
Nashville District Engineer, ATTN: CELRN-OP-F, 3701 Bell Road,
Nashville, TN 37214
Texas
Galveston District Engineer, ATTN: CESWG-PE-R, P.O. Box 1229,
Galveston, TX 77553-1229
Utah
Sacramento District Engineer, ATTN: CESPK-RD, 1325 J Street, CA 95814-
2922
Vermont
New England District Engineer, ATTN: CENAE-R, 696 Virginia Road,
Concord, MA 01742-2751
Virginia
Norfolk District Engineer, ATTN: CENAO-WR-R, 803 Front Street, Norfolk,
VA 23510-1096
Washington
Seattle District Engineer, ATTN: CENWS-OP-RG, P.O. Box 3755, Seattle,
WA 98124-3755
West Virginia
Huntington District Engineer, ATTN: CELRH-OR-F, 502 8th Street,
Huntington, WV 25701-2070
Wisconsin
St. Paul District Engineer, ATTN: CEMVP-OP-R, 180 Fifth Street East,
Suite 700, St. Paul, MN 55101-1678
Wyoming
Omaha District Engineer, ATTN: CENWO-OD-R, 1616 Capitol Avenue, Omaha,
NE 68102-4901
District of Columbia
Baltimore District Engineer, ATTN: CENAB-OP-R, P.O. Box 1715,
Baltimore, MD 21203-1715
Pacific Territories (American Samoa, Guam, & Commonwealth of the
Northern Mariana Islands)
Honolulu District Engineer, ATTN: CEPOH-EC-R, Building 230, Fort
Shafter, Honolulu, HI 96858-5440
Puerto Rico and Virgin Islands
Jacksonville District Engineer, ATTN: CESAJ-RD, P.O. Box 4970,
Jacksonville, FL 32232-0019
Administrative Requirements
Plain Language
In compliance with the principles in the President's Memorandum of
June 1, 1998, (63 FR 31855) regarding plain language, this preamble is
written using plain language. The use of ``we'' in this notice refers
to the Corps. We have also used the active voice, short sentences, and
common everyday terms except for necessary technical terms.
Paperwork Reduction Act
These NWPs will result in a net decrease in the number of
permittees who are required to submit a pre-construction notification,
especially because of the changes to NWP 48. The content of the pre-
construction notification is not changed from the current NWPs, and the
paperwork burden will decrease because of the reduced number of pre-
construction notifications submitted. The Corps estimates the decreased
paperwork burden to be 4,005 hours per year. This is based on an
average burden to complete and submit a pre-construction notification
of 11 hours, and an estimated 45 NWP 48 activities that will still
require pre-construction notifications, rather than 3,150 NWP 48
activities that were previously estimated to require either reporting
or pre-construction notification. Prospective permittees who are
required to submit a pre-construction notification for a particular
NWP, or who are requesting verification that a particular activity
qualifies for NWP authorization, may use the current standard
Department of the Army permit application form or submit the required
information in a letter. The total burden for filing pre-construction
notifications is estimated at 330,000 hours per year (11 hours times
30,000 activities per year requiring pre-construction notification).
An agency may not conduct or sponsor, and a person is not required
to respond to, a collection of information unless it displays a
currently valid Office of Management and Budget (OMB) control number.
For the Corps Regulatory Program under Section 10 of the Rivers and
Harbors Act of 1899, Section 404 of the Clean Water Act, and Section
103 of the Marine Protection, Research and Sanctuaries Act of 1972, the
current OMB approval number for information collection requirements is
maintained by the Corps of Engineers (OMB approval number 0710-0003,
which expires on August 31, 2012).
Executive Orders 12866 and 13563
Under Executive Order 12866 (58 FR 51735, October 4, 1993) and
13563 (76
[[Page 10267]]
FR 3821), we must determine whether the regulatory action is
``significant'' and therefore subject to review by OMB and the
requirements of the Executive Orders. The Executive Orders define
``significant regulatory action'' as one that is likely to result in a
rule that may:
(1) Have an annual effect on the economy of $100 million or more or
adversely affect in a material way the economy, a sector of the
economy, productivity, competition, jobs, the environment, public
health or safety, or State, local, or tribal governments or
communities;
(2) Create a serious inconsistency or otherwise interfere with an
action taken or planned by another agency;
(3) Materially alter the budgetary impact of entitlements, grants,
user fees, or loan programs or the rights and obligations of recipients
thereof; or
(4) Raise novel legal or policy issues arising out of legal
mandates, the President's priorities, or the principles set forth in
the Executive Order.
Pursuant to the terms of Executive Orders 12866 and 13563, we
determined that this action is a ``significant regulatory action'' and
it was submitted to OMB for review. It is a significant regulatory
action because it meets the fourth criterion in the Executive Order.
The most substantive changes to these NWPs are the additional
limits imposed on NWP 21, which authorizes discharges of dredged or
fill material into waters of the United States associated with surface
coal mining activities, the issuance of NWPs 51 and 52, which authorize
activities associated with renewable energy generation facilities, and
the modifications to NWP 48 which authorize existing and new commercial
shellfish aquaculture activities.
The changes to the NWPs that are most likely to result in
additional economic costs are the changes to NWP 21, especially the \1/
2\-acre and 300 linear foot limits and the prohibition against
discharges of dredged or fill material to construct valley fills. We
have prepared a brief economic analysis to estimate the additional
costs that will be imposed on the regulated public as a result of the
change to the NWPs. It is available in the docket for this action at
www.regulations.gov, docket number COE-2010-0035.
The issuance of NWPs 51 and 52 will reduce the number of renewable
energy generation facilities involving activities regulated under
section 404 and/or section 10 requiring individual permits. While some
components of land-based renewable energy generation facilities, such
as road crossings, utility lines, and building pads involving
discharges of dredged or fill material into waters of the United
States, have been authorized by NWPs such as NWPs 14, 12, and 39 in the
past, the new NWP 51 will provide DA authorization for all components
of land-based renewable energy generation facilities that involve
discharges of dredged or fill material into waters of the United
States. There was no NWP authorization available for water-based
renewable energy generation pilot projects, so the new NWP 52 will
reduce the number of those activities that require individual permits.
The NWPs support the goals of Executive Order 13563, ``Improving
Regulation and Regulatory Review'' by reducing burdens on the regulated
public through a streamlined process for obtaining Department of the
Army authorization for activities that will result in minimal
individual and cumulative adverse effects on the aquatic environment.
The NWPs reissued today, when considered as an overall package of NWPs,
will authorize more activities than were previously authorized by NWP,
such as water-based renewable energy pilot projects and new commercial
shellfish aquaculture activities.
Executive Order 13132
Executive Order 13132, entitled ``Federalism'' (64 FR 43255, August
10, 1999), requires the Corps to develop an accountable process to
ensure ``meaningful and timely input by State and local officials in
the development of regulatory policies that have federalism
implications.'' The issuance of NWPs does not have federalism
implications. We do not believe that the NWPs will have substantial
direct effects on the States, on the relationship between the Federal
government and the States, or on the distribution of power and
responsibilities among the various levels of government. The NWPs will
not impose any additional substantive obligations on State or local
governments. Therefore, Executive Order 13132 does not apply to these
final NWPs.
Regulatory Flexibility Act, as Amended by the Small Business Regulatory
Enforcement Fairness Act of 1996, 5 U.S.C. 601 et seq.
The Regulatory Flexibility Act generally requires an agency to
prepare a regulatory flexibility analysis of any rule subject to
notice-and-comment rulemaking requirements under the Administrative
Procedure Act or any other statute unless the agency certifies that the
rule will not have a significant economic impact on a substantial
number of small entities. Small entities include small businesses,
small organizations, and small governmental jurisdictions.
For purposes of assessing the impacts of the proposed issuance and
modification of NWPs on small entities, a small entity is defined as:
(1) A small business based on Small Business Administration size
standards; (2) a small governmental jurisdiction that is a government
of a city, county, town, school district, or special district with a
population of less than 50,000; or (3) a small organization that is any
not-for-profit enterprise which is independently owned and operated and
is not dominant in its field.
The statutes under which the Corps issues, reissues, or modifies
NWPs are Section 404(e) of the Clean Water Act (33 U.S.C. 1344(e)) and
Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403). Under
section 404, Department of the Army (DA) permits are required for
discharges of dredged or fill material into waters of the United
States. Under section 10, DA permits are required for any structures or
other work that affect the course, location, or condition of navigable
waters of the United States. Small entities proposing to discharge
dredged or fill material into waters of the United States and/or
conduct work in navigable waters of the United States must obtain DA
permits to conduct those activities, unless a particular activity is
exempt from those permit requirements. Individual permits and general
permits can be issued by the Corps to satisfy the permit requirements
of these two statutes. Nationwide permits are a form of general permit
issued by the Chief of Engineers.
Nationwide permits automatically expire and become null and void if
they are not modified or reissued within five years of their effective
date (see 33 CFR 330.6(b)). Furthermore, Section 404(e) of the Clean
Water Act states that general permits, including NWPs, can be issued
for no more than five years. If the current NWPs are not reissued small
entities and other project proponents would be required to obtain
alternative forms of DA permits (i.e., standard permits, letters of
permission, or regional general permits) for activities involving
discharges of dredged or fill material into waters of the United States
or structures or work in navigable waters of the United States.
Regional general permits that authorize similar activities as the NWPs
may be available in some geographic areas, so small entities conducting
regulated activities outside those geographic areas would have to
obtain individual permits for activities that require DA permits.
[[Page 10268]]
Nationwide permits help relieve regulatory burdens on small
entities who need to obtain DA permits. They provide an expedited form
of authorization, as long as the project proponent meets all terms and
conditions of the NWPs. In FY 2010, the Corps issued 32,029 NWP
verifications, with an average processing time of 32 days. Those
numbers do not include activities that are authorized by NWP, where the
project proponent was not required to submit a pre-construction
notification or did not voluntarily seek verification that an activity
qualified for NWP authorization. The average processing time for the
2,085 standard permits issued during FY 2010 was 221 days. The NWPs
issued and reissued today are expected to result in a slight increase
in the numbers of activities potentially qualifying for NWP
authorization. The estimated numbers of activities qualifying for NWP
authorization are provided in the decision documents that were prepared
for each NWP. The NWPs issued and reissued today are not expected to
significantly increase cost or paperwork burden for authorized
activities (relative to the NWPs issued in 2007), including those
conducted by small businesses.
The costs for obtaining coverage under an NWP are low. We estimate
the average time to prepare and file a pre-construction notification,
for those activities where a pre-construction notification is required,
is 11 hours. We do not believe this constitutes a ``significant
economic impact'' on project proponents, including small businesses.
Another requirement of Section 404(e) of the Clean Water Act is
that general permits, including NWPs, authorize only those activities
that result in minimal adverse environmental effects, individually and
cumulatively. The terms and conditions of the NWPs, such as acreage or
linear foot limits, are imposed to ensure that the NWPs authorize only
those activities that result in minimal adverse effects on the aquatic
environment and other public interest review factors. In addition to
the paperwork burden of filing a pre-construction notification, many
NWPs require that low-cost, commonsense practices be used to minimize
adverse effects. These requirements also do not constitute
``significant economic impacts.''
After considering the economic impacts of these NWPs on small
entities, I certify that this action will not have a significant impact
on a substantial number of small entities. Small entities may obtain
required DA authorizations through the NWPs, in cases where there are
applicable NWPs authorizing those activities and the proposed work will
result in minimal adverse effects on the aquatic environment and other
public interest review factors. The terms and conditions of these NWPs
will not generally impose significant economic costs on small entities,
and do not generally impose higher costs on small entities than those
of the previous NWPs. If an NWP is not available to authorize a
particular activity, then another form of DA authorization, such as an
individual permit or regional general permit, must be secured. However,
as noted above, we expect a slight increase in the number of activities
that can be authorized through these NWPs, because we are issuing two
new NWPs and making substantial changes to NWP 48. The changes to NWP
48, commercial shellfish aquaculture activities, will result in fewer
project proponents having to submit pre-construction notifications or
reports to Corps districts. We have also modified NWP 48 to authorize
new commercial shellfish aquaculture activities, which were not
previously authorized by NWP. While we are making substantial changes
to NWP 21, we are also providing NWP 21 authorization without the new
limits for surface coal mining activities previously authorized under
the 2007 NWP 21, to have an equitable transition for those surface coal
mining activities that cannot complete the authorized work by March 18,
2013. For new NWP 21 activities subject to the new limits and
prohibition against valley fills, where the project proponent is
considered a small entity, the changes to that NWP will not result in a
significant economic impact because the costs for obtaining an NWP 21
authorization is generally higher when compared to other NWPs, and
approach the costs for obtaining an individual permit.
Unfunded Mandates Reform Act
Title II of the Unfunded Mandates Reform Act of 1995 (UMRA), Public
Law 104-4, establishes requirements for Federal agencies to assess the
effects of their regulatory actions on State, local, and tribal
governments and the private sector. Under Section 202 of the UMRA, the
agencies generally must prepare a written statement, including a cost-
benefit analysis, for proposed and final rules with ``federal
mandates'' that may result in expenditures to State, local, and tribal
governments, in the aggregate, or to the private sector, of $100
million or more in any one year. Before promulgating a rule for which a
written statement is needed, Section 205 of the UMRA generally requires
the agencies to identify and consider a reasonable number of regulatory
alternatives and adopt the least costly, most cost-effective, or least
burdensome alternative that achieves the objectives of the rule. The
provisions of section 205 do not apply when they are inconsistent with
applicable law. Moreover, section 205 allows an agency to adopt an
alternative other than the least costly, most cost-effective, or least
burdensome alternative if the agency publishes with the final rule an
explanation why that alternative was not adopted. Before an agency
establishes any regulatory requirements that may significantly or
uniquely affect small governments, including tribal governments, it
must have developed, under Section 203 of the UMRA, a small government
agency plan. The plan must provide for notifying potentially affected
small governments, enabling officials of affected small governments to
have meaningful and timely input in the development of regulatory
proposals with significant federal intergovernmental mandates, and
informing, educating, and advising small governments on compliance with
the regulatory requirements.
We have determined that the NWPs issued today do not contain a
Federal mandate that may result in expenditures of $100 million or more
for State, local, and Tribal governments, in the aggregate, or the
private sector in any one year. The NWPs are generally consistent with
current agency practice, do not impose new substantive requirements and
therefore do not contain a Federal mandate that may result in
expenditures of $100 million or more for State, local, and Tribal
governments, in the aggregate, or the private sector in any one year.
Therefore, the NWPs issued today are not subject to the requirements of
Sections 202 and 205 of the UMRA. For the same reasons, we have
determined that the NWPs contains no regulatory requirements that might
significantly or uniquely affect small governments. Therefore, the
issuance of NWPs is not subject to the requirements of Section 203 of
UMRA.
Executive Order 13045
Executive Order 13045, ``Protection of Children from Environmental
Health Risks and Safety Risks'' (62 FR 19885, April 23, 1997), applies
to any rule that: (1) Is determined to be ``economically significant''
as defined under Executive Order 12866, and (2) concerns an
environmental health or safety risk that we have reason to believe may
have a disproportionate effect on children. If
[[Page 10269]]
the regulatory action meets both criteria, we must evaluate the
environmental health or safety effects of the proposed rule on
children, and explain why the regulation is preferable to other
potentially effective and reasonably feasible alternatives.
The NWPs issued today are not subject to this Executive Order
because they are not economically significant as defined in Executive
Order 12866. In addition, these NWPs do not concern an environmental or
safety risk that we have reason to believe may have a disproportionate
effect on children.
Executive Order 13175
Executive Order 13175, entitled ``Consultation and Coordination
with Indian Tribal Governments'' (65 FR 67249, November 6, 2000),
requires agencies to develop an accountable process to ensure
``meaningful and timely input by tribal officials in the development of
regulatory policies that have tribal implications.'' The phrase
``policies that have tribal implications'' is defined in the Executive
Order to include regulations that have ``substantial direct effects on
one or more Indian tribes, on the relationship between the Federal
government and the Indian tribes, or on the distribution of power and
responsibilities between the Federal government and Indian tribes.''
The NWPs issued today do not have tribal implications. They are
generally consistent with current agency practice and will not have
substantial direct effects on tribal governments, on the relationship
between the Federal government and the Indian tribes, or on the
distribution of power and responsibilities between the Federal
government and Indian tribes. Therefore, Executive Order 13175 does not
apply to this proposal. Corps districts are conducting government-to-
government consultation with Indian tribes to develop regional
conditions that help protect tribal rights and trust resources, and to
facilitate compliance with general condition 17, Tribal Rights.
Environmental Documentation
A decision document, which includes an environmental assessment and
Finding of No Significant Impact (FONSI), has been prepared for each
NWP. These decision documents are available at: https://www.regulations.gov (docket ID number COE-2010-0035). They are also
available by contacting Headquarters, U.S. Army Corps of Engineers,
Operations and Regulatory Community of Practice, 441 G Street NW.,
Washington, DC 20314-1000.
Congressional Review Act
The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the
Small Business Regulatory Enforcement Fairness Act of 1996, generally
provides that before a rule may take effect, the agency promulgating
the rule must submit a rule report, which includes a copy of the rule,
to each House of the Congress and to the Comptroller General of the
United States. We will submit a report containing the final NWPs and
other required information to the U.S. Senate, the U.S. House of
Representatives, and the Comptroller General of the United States. A
major rule cannot take effect until 60 days after it is published in
the Federal Register. The proposed NWPs are not a ``major rule'' as
defined by 5 U.S.C. 804(2).
Executive Order 12898
Executive Order 12898 requires that, to the greatest extent
practicable and permitted by law, each Federal agency must make
achieving environmental justice part of its mission. Executive Order
12898 provides that each federal agency conduct its programs, policies,
and activities that substantially affect human health or the
environment in a manner that ensures that such programs, policies, and
activities do not have the effect of excluding persons (including
populations) from participation in, denying persons (including
populations) the benefits of, or subjecting persons (including
populations) to discrimination under such programs, policies, and
activities because of their race, color, or national origin.
The NWPs issued today are not expected to negatively impact any
community, and therefore are not expected to cause any
disproportionately high and adverse impacts to minority or low-income
communities.
Executive Order 13211
The NWPs are not a ``significant energy action'' as defined in
Executive Order 13211, ``Actions Concerning Regulations That
Significantly Affect Energy Supply, Distribution, or Use'' (66 FR
28355, May 22, 2001) because it is not likely to have a significant
adverse effect on the supply, distribution, or use of energy. Some of
the NWPs authorize activities that support the supply and distribution
of energy.
Authority
We are issuing new NWPs and reissuing existing NWPs under the
authority of Section 404(e) of the Clean Water Act (33 U.S.C. 1344) and
Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 401 et
seq.).
Dated: February 13, 2012.
Michael J. Walsh,
Major General, US Army, Deputy Commanding General for Civil and
Emergency Operations.
Nationwide Permits, Conditions, Further Information, and Definitions
A. Index of Nationwide Permits, Conditions, District Engineer's
Decision, Further Information, and Definitions
Nationwide Permits
1. Aids to Navigation
2. Structures in Artificial Canals
3. Maintenance
4. Fish and Wildlife Harvesting, Enhancement, and Attraction Devices
and Activities
5. Scientific Measurement Devices
6. Survey Activities
7. Outfall Structures and Associated Intake Structures
8. Oil and Gas Structures on the Outer Continental Shelf
9. Structures in Fleeting and Anchorage Areas
10. Mooring Buoys
11. Temporary Recreational Structures
12. Utility Line Activities
13. Bank Stabilization
14. Linear Transportation Projects
15. U.S. Coast Guard Approved Bridges
16. Return Water From Upland Contained Disposal Areas
17. Hydropower Projects
18. Minor Discharges
19. Minor Dredging
20. Response Operations for Oil and Hazardous Substances
21. Surface Coal Mining Activities
22. Removal of Vessels
23. Approved Categorical Exclusions
24. Indian Tribe or State Administered Section 404 Programs
25. Structural Discharges
26. [Reserved]
27. Aquatic Habitat Restoration, Establishment, and Enhancement
Activities
28. Modifications of Existing Marinas
29. Residential Developments
30. Moist Soil Management for Wildlife
31. Maintenance of Existing Flood Control Facilities
32. Completed Enforcement Actions
33. Temporary Construction, Access, and Dewatering
34. Cranberry Production Activities
35. Maintenance Dredging of Existing Basins
36. Boat Ramps
37. Emergency Watershed Protection and Rehabilitation
38. Cleanup of Hazardous and Toxic Waste
[[Page 10270]]
39. Commercial and Institutional Developments
40. Agricultural Activities
41. Reshaping Existing Drainage Ditches
42. Recreational Facilities
43. Stormwater Management Facilities
44. Mining Activities
45. Repair of Uplands Damaged by Discrete Events
46. Discharges in Ditches
47. [Reserved]
48. Commercial Shellfish Aquaculture Activities
49. Coal Remining Activities
50. Underground Coal Mining Activities
51. Land-Based Renewable Energy Generation Facilities
52. Water-Based Renewable Energy Generation Pilot Projects
Nationwide Permit General Conditions
1. Navigation
2. Aquatic Life Movements
3. Spawning Areas
4. Migratory Bird Breeding Areas
5. Shellfish Beds
6. Suitable Material
7. Water Supply Intakes
8. Adverse Effects From Impoundments
9. Management of Water Flows
10. Fills Within 100-Year Floodplains
11. Equipment
12. Soil Erosion and Sediment Controls
13. Removal of Temporary Fills
14. Proper Maintenance
15. Single and Complete Project
16. Wild and Scenic Rivers
17. Tribal Rights
18. Endangered Species
19. Migratory Bird and Bald and Golden Eagle Permits
20. Historic Properties
21. Discovery of Previously Unknown Remains and Artifacts
22. Designated Critical Resource Waters
23. Mitigation
24. Safety of Impoundment Structures
25. Water Quality
26. Coastal Zone Management
27. Regional and Case-by-Case Conditions
28. Use of Multiple Nationwide Permits
29. Transfer of Nationwide Permit Verifications
30. Compliance Certification
31. Pre-Construction Notification
District Engineer's Decision
Further Information
Definitions
Best management practices (BMPs)
Compensatory mitigation
Currently serviceable
Direct effects
Discharge
Enhancement
Ephemeral stream
Establishment (creation)
High Tide Line
Historic property
Independent utility
Indirect effects
Intermittent stream
Loss of waters of the United States
Non-tidal wetland
Open water
Ordinary high water mark
Perennial stream
Practicable
Pre-construction notification
Preservation
Re-establishment
Rehabilitation
Restoration
Riffle and pool complex
Riparian areas
Shellfish seeding
Single and complete linear project
Single and complete non-linear project
Stormwater management
Stormwater management facilities
Stream bed
Stream channelization
Structure
Tidal wetland
Vegetated shallows
Waterbody
B. Nationwide Permits
1. Aids to Navigation. The placement of aids to navigation and
regulatory markers which are approved by and installed in accordance
with the requirements of the U.S. Coast Guard (see 33 CFR, chapter I,
subchapter C, part 66). (Section 10)
2. Structures in Artificial Canals. Structures constructed in
artificial canals within principally residential developments where the
connection of the canal to a navigable water of the United States has
been previously authorized (see 33 CFR 322.5(g)). (Section 10)
3. Maintenance. (a) The repair, rehabilitation, or replacement of
any previously authorized, currently serviceable structure, or fill, or
of any currently serviceable structure or fill authorized by 33 CFR
330.3, provided that the structure or fill is not to be put to uses
differing from those uses specified or contemplated for it in the
original permit or the most recently authorized modification. Minor
deviations in the structure's configuration or filled area, including
those due to changes in materials, construction techniques,
requirements of other regulatory agencies, or current construction
codes or safety standards that are necessary to make the repair,
rehabilitation, or replacement are authorized. Any stream channel
modification is limited to the minimum necessary for the repair,
rehabilitation, or replacement of the structure or fill; such
modifications, including the removal of material from the stream
channel, must be immediately adjacent to the project or within the
boundaries of the structure or fill. This NWP also authorizes the
repair, rehabilitation, or replacement of those structures or fills
destroyed or damaged by storms, floods, fire or other discrete events,
provided the repair, rehabilitation, or replacement is commenced, or is
under contract to commence, within two years of the date of their
destruction or damage. In cases of catastrophic events, such as
hurricanes or tornadoes, this two-year limit may be waived by the
district engineer, provided the permittee can demonstrate funding,
contract, or other similar delays.
(b) This NWP also authorizes the removal of accumulated sediments
and debris in the vicinity of existing structures (e.g., bridges,
culverted road crossings, water intake structures, etc.) and/or the
placement of new or additional riprap to protect the structure. The
removal of sediment is limited to the minimum necessary to restore the
waterway in the vicinity of the structure to the approximate dimensions
that existed when the structure was built, but cannot extend farther
than 200 feet in any direction from the structure. This 200 foot limit
does not apply to maintenance dredging to remove accumulated sediments
blocking or restricting outfall and intake structures or to maintenance
dredging to remove accumulated sediments from canals associated with
outfall and intake structures. All dredged or excavated materials must
be deposited and retained in an area that has no waters of the United
States unless otherwise specifically approved by the district engineer
under separate authorization. The placement of new or additional riprap
must be the minimum necessary to protect the structure or to ensure the
safety of the structure. Any bank stabilization measures not directly
associated with the structure will require a separate authorization
from the district engineer.
(c) This NWP also authorizes temporary structures, fills, and work
necessary to conduct the maintenance activity. Appropriate measures
must be taken to maintain normal downstream flows and minimize flooding
to the maximum extent practicable, when temporary structures, work, and
discharges, including cofferdams, are necessary for construction
activities, access fills, or dewatering of construction sites.
Temporary fills must consist of materials, and be placed in a manner,
that will not be eroded by expected high flows. Temporary fills
[[Page 10271]]
must be removed in their entirety and the affected areas returned to
pre-construction elevations. The areas affected by temporary fills must
be revegetated, as appropriate.
(d) This NWP does not authorize maintenance dredging for the
primary purpose of navigation. This NWP does not authorize beach
restoration. This NWP does not authorize new stream channelization or
stream relocation projects.
Notification: For activities authorized by paragraph (b) of this
NWP, the permittee must submit a pre-construction notification to the
district engineer prior to commencing the activity (see general
condition 31). The pre-construction notification must include
information regarding the original design capacities and configurations
of the outfalls, intakes, small impoundments, and canals. (Sections 10
and 404)
Note: This NWP authorizes the repair, rehabilitation, or
replacement of any previously authorized structure or fill that does
not qualify for the Clean Water Act Section 404(f) exemption for
maintenance.
4. Fish and Wildlife Harvesting, Enhancement, and Attraction
Devices and Activities. Fish and wildlife harvesting devices and
activities such as pound nets, crab traps, crab dredging, eel pots,
lobster traps, duck blinds, and clam and oyster digging, fish
aggregating devices, and small fish attraction devices such as open
water fish concentrators (sea kites, etc.). This NWP does not authorize
artificial reefs or impoundments and semi-impoundments of waters of the
United States for the culture or holding of motile species such as
lobster, or the use of covered oyster trays or clam racks. (Sections 10
and 404)
5. Scientific Measurement Devices. Devices, whose purpose is to
measure and record scientific data, such as staff gages, tide and
current gages, meteorological stations, water recording and biological
observation devices, water quality testing and improvement devices, and
similar structures. Small weirs and flumes constructed primarily to
record water quantity and velocity are also authorized provided the
discharge is limited to 25 cubic yards. Upon completion of the use of
the device to measure and record scientific data, the measuring device
and any other structures or fills associated with that device (e.g.,
foundations, anchors, buoys, lines, etc.) must be removed to the
maximum extent practicable and the site restored to pre-construction
elevations. (Sections 10 and 404)
6. Survey Activities. Survey activities, such as core sampling,
seismic exploratory operations, plugging of seismic shot holes and
other exploratory-type bore holes, exploratory trenching, soil surveys,
sampling, sample plots or transects for wetland delineations, and
historic resources surveys. For the purposes of this NWP, the term
``exploratory trenching'' means mechanical land clearing of the upper
soil profile to expose bedrock or substrate, for the purpose of mapping
or sampling the exposed material. The area in which the exploratory
trench is dug must be restored to its pre-construction elevation upon
completion of the work and must not drain a water of the United States.
In wetlands, the top 6 to 12 inches of the trench should normally be
backfilled with topsoil from the trench. This NWP authorizes the
construction of temporary pads, provided the discharge does not exceed
\1/10\-acre in waters of the U.S. Discharges and structures associated
with the recovery of historic resources are not authorized by this NWP.
Drilling and the discharge of excavated material from test wells for
oil and gas exploration are not authorized by this NWP; the plugging of
such wells is authorized. Fill placed for roads and other similar
activities is not authorized by this NWP. The NWP does not authorize
any permanent structures. The discharge of drilling mud and cuttings
may require a permit under Section 402 of the Clean Water Act.
(Sections 10 and 404)
7. Outfall Structures and Associated Intake Structures. Activities
related to the construction or modification of outfall structures and
associated intake structures, where the effluent from the outfall is
authorized, conditionally authorized, or specifically exempted by, or
otherwise in compliance with regulations issued under the National
Pollutant Discharge Elimination System Program (Section 402 of the
Clean Water Act). The construction of intake structures is not
authorized by this NWP, unless they are directly associated with an
authorized outfall structure.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Sections 10 and 404)
8. Oil and Gas Structures on the Outer Continental Shelf.
Structures for the exploration, production, and transportation of oil,
gas, and minerals on the outer continental shelf within areas leased
for such purposes by the Department of Interior, Bureau of Ocean Energy
Management. Such structures shall not be placed within the limits of
any designated shipping safety fairway or traffic separation scheme,
except temporary anchors that comply with the fairway regulations in 33
CFR 322.5(l). The district engineer will review such proposals to
ensure compliance with the provisions of the fairway regulations in 33
CFR 322.5(l). Any Corps review under this NWP will be limited to the
effects on navigation and national security in accordance with 33 CFR
322.5(f), as well as 33 CFR 322.5(l) and 33 CFR part 334. Such
structures will not be placed in established danger zones or restricted
areas as designated in 33 CFR part 334, nor will such structures be
permitted in EPA or Corps designated dredged material disposal areas.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Section 10)
9. Structures in Fleeting and Anchorage Areas. Structures, buoys,
floats and other devices placed within anchorage or fleeting areas to
facilitate moorage of vessels where the U.S. Coast Guard has
established such areas for that purpose. (Section 10)
10. Mooring Buoys. Non-commercial, single-boat, mooring buoys.
(Section 10)
11. Temporary Recreational Structures. Temporary buoys, markers,
small floating docks, and similar structures placed for recreational
use during specific events such as water skiing competitions and boat
races or seasonal use, provided that such structures are removed within
30 days after use has been discontinued. At Corps of Engineers
reservoirs, the reservoir manager must approve each buoy or marker
individually. (Section 10)
12. Utility Line Activities. Activities required for the
construction, maintenance, repair, and removal of utility lines and
associated facilities in waters of the United States, provided the
activity does not result in the loss of greater than \1/2\-acre of
waters of the United States for each single and complete project.
Utility lines: This NWP authorizes the construction, maintenance,
or repair of utility lines, including outfall and intake structures,
and the associated excavation, backfill, or bedding for the utility
lines, in all waters of the United States, provided there is no change
in pre-construction contours. A ``utility line'' is defined as any pipe
or pipeline for the transportation of any gaseous, liquid, liquescent,
or slurry substance, for any purpose, and any cable, line, or wire for
the transmission for any purpose of electrical energy, telephone, and
telegraph messages, and radio and
[[Page 10272]]
television communication. The term ``utility line'' does not include
activities that drain a water of the United States, such as drainage
tile or french drains, but it does apply to pipes conveying drainage
from another area.
Material resulting from trench excavation may be temporarily
sidecast into waters of the United States for no more than three
months, provided the material is not placed in such a manner that it is
dispersed by currents or other forces. The district engineer may extend
the period of temporary side casting for no more than a total of 180
days, where appropriate. In wetlands, the top 6 to 12 inches of the
trench should normally be backfilled with topsoil from the trench. The
trench cannot be constructed or backfilled in such a manner as to drain
waters of the United States (e.g., backfilling with extensive gravel
layers, creating a french drain effect). Any exposed slopes and stream
banks must be stabilized immediately upon completion of the utility
line crossing of each waterbody.
Utility line substations: This NWP authorizes the construction,
maintenance, or expansion of substation facilities associated with a
power line or utility line in non-tidal waters of the United States,
provided the activity, in combination with all other activities
included in one single and complete project, does not result in the
loss of greater than \1/2\-acre of waters of the United States. This
NWP does not authorize discharges into non-tidal wetlands adjacent to
tidal waters of the United States to construct, maintain, or expand
substation facilities.
Foundations for overhead utility line towers, poles, and anchors:
This NWP authorizes the construction or maintenance of foundations for
overhead utility line towers, poles, and anchors in all waters of the
United States, provided the foundations are the minimum size necessary
and separate footings for each tower leg (rather than a larger single
pad) are used where feasible.
Access roads: This NWP authorizes the construction of access roads
for the construction and maintenance of utility lines, including
overhead power lines and utility line substations, in non-tidal waters
of the United States, provided the activity, in combination with all
other activities included in one single and complete project, does not
cause the loss of greater than \1/2\-acre of non-tidal waters of the
United States. This NWP does not authorize discharges into non-tidal
wetlands adjacent to tidal waters for access roads. Access roads must
be the minimum width necessary (see Note 2, below). Access roads must
be constructed so that the length of the road minimizes any adverse
effects on waters of the United States and must be as near as possible
to pre-construction contours and elevations (e.g., at grade corduroy
roads or geotextile/gravel roads). Access roads constructed above pre-
construction contours and elevations in waters of the United States
must be properly bridged or culverted to maintain surface flows.
This NWP may authorize utility lines in or affecting navigable
waters of the United States even if there is no associated discharge of
dredged or fill material (See 33 CFR Part 322). Overhead utility lines
constructed over section 10 waters and utility lines that are routed in
or under section 10 waters without a discharge of dredged or fill
material require a section 10 permit.
This NWP also authorizes temporary structures, fills, and work
necessary to conduct the utility line activity. Appropriate measures
must be taken to maintain normal downstream flows and minimize flooding
to the maximum extent practicable, when temporary structures, work, and
discharges, including cofferdams, are necessary for construction
activities, access fills, or dewatering of construction sites.
Temporary fills must consist of materials, and be placed in a manner,
that will not be eroded by expected high flows. Temporary fills must be
removed in their entirety and the affected areas returned to pre-
construction elevations. The areas affected by temporary fills must be
revegetated, as appropriate.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
if any of the following criteria are met: (1) The activity involves
mechanized land clearing in a forested wetland for the utility line
right-of-way; (2) a section 10 permit is required; (3) the utility line
in waters of the United States, excluding overhead lines, exceeds 500
feet; (4) the utility line is placed within a jurisdictional area
(i.e., water of the United States), and it runs parallel to or along a
stream bed that is within that jurisdictional area; (5) discharges that
result in the loss of greater than \1/10\-acre of waters of the United
States; (6) permanent access roads are constructed above grade in
waters of the United States for a distance of more than 500 feet; or
(7) permanent access roads are constructed in waters of the United
States with impervious materials. (See general condition 31.) (Sections
10 and 404)
Note 1: Where the proposed utility line is constructed or
installed in navigable waters of the United States (i.e., section 10
waters) within the coastal United States, the Great Lakes, and
United States territories, copies of the pre-construction
notification and NWP verification will be sent by the Corps to the
National Oceanic and Atmospheric Administration (NOAA), National
Ocean Service (NOS), for charting the utility line to protect
navigation.
Note 2: Access roads used for both construction and maintenance
may be authorized, provided they meet the terms and conditions of
this NWP. Access roads used solely for construction of the utility
line must be removed upon completion of the work, in accordance with
the requirements for temporary fills.
Note 3: Pipes or pipelines used to transport gaseous, liquid,
liquescent, or slurry substances over navigable waters of the United
States are considered to be bridges, not utility lines, and may
require a permit from the U.S. Coast Guard pursuant to Section 9 of
the Rivers and Harbors Act of 1899. However, any discharges of
dredged or fill material into waters of the United States associated
with such pipelines will require a section 404 permit (see NWP 15).
Note 4: For overhead utility lines authorized by this NWP, a
copy of the PCN and NWP verification will be provided to the
Department of Defense Siting Clearinghouse, which will evaluate
potential effects on military activities.
13. Bank Stabilization. Bank stabilization activities necessary for
erosion prevention, provided the activity meets all of the following
criteria:
(a) No material is placed in excess of the minimum needed for
erosion protection;
(b) The activity is no more than 500 feet in length along the bank,
unless the district engineer waives this criterion by making a written
determination concluding that the discharge will result in minimal
adverse effects;
(c) The activity will not exceed an average of one cubic yard per
running foot placed along the bank below the plane of the ordinary high
water mark or the high tide line, unless the district engineer waives
this criterion by making a written determination concluding that the
discharge will result in minimal adverse effects;
(d) The activity does not involve discharges of dredged or fill
material into special aquatic sites, unless the district engineer
waives this criterion by making a written determination concluding that
the discharge will result in minimal adverse effects;
(e) No material is of a type, or is placed in any location, or in
any manner, that will impair surface water flow into or out of any
waters of the United States;
(f) No material is placed in a manner that will be eroded by normal
or
[[Page 10273]]
expected high flows (properly anchored trees and treetops may be used
in low energy areas); and,
(g) The activity is not a stream channelization activity.
This NWP also authorizes temporary structures, fills, and work
necessary to construct the bank stabilization activity. Appropriate
measures must be taken to maintain normal downstream flows and minimize
flooding to the maximum extent practicable, when temporary structures,
work, and discharges, including cofferdams, are necessary for
construction activities, access fills, or dewatering of construction
sites. Temporary fills must consist of materials, and be placed in a
manner, that will not be eroded by expected high flows. Temporary fills
must be removed in their entirety and the affected areas returned to
pre-construction elevations. The areas affected by temporary fills must
be revegetated, as appropriate.
Invasive plant species shall not be used for bioengineering or
vegetative bank stabilization.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
if the bank stabilization activity: (1) Involves discharges into
special aquatic sites; or (2) is in excess of 500 feet in length; or
(3) will involve the discharge of greater than an average of one cubic
yard per running foot along the bank below the plane of the ordinary
high water mark or the high tide line. (See general condition 31.)
(Sections 10 and 404)
14. Linear Transportation Projects. Activities required for the
construction, expansion, modification, or improvement of linear
transportation projects (e.g., roads, highways, railways, trails,
airport runways, and taxiways) in waters of the United States. For
linear transportation projects in non-tidal waters, the discharge
cannot cause the loss of greater than \1/2\-acre of waters of the
United States. For linear transportation projects in tidal waters, the
discharge cannot cause the loss of greater than 1/3-acre of waters of
the United States. Any stream channel modification, including bank
stabilization, is limited to the minimum necessary to construct or
protect the linear transportation project; such modifications must be
in the immediate vicinity of the project.
This NWP also authorizes temporary structures, fills, and work
necessary to construct the linear transportation project. Appropriate
measures must be taken to maintain normal downstream flows and minimize
flooding to the maximum extent practicable, when temporary structures,
work, and discharges, including cofferdams, are necessary for
construction activities, access fills, or dewatering of construction
sites. Temporary fills must consist of materials, and be placed in a
manner, that will not be eroded by expected high flows. Temporary fills
must be removed in their entirety and the affected areas returned to
pre-construction elevations. The areas affected by temporary fills must
be revegetated, as appropriate.
This NWP cannot be used to authorize non-linear features commonly
associated with transportation projects, such as vehicle maintenance or
storage buildings, parking lots, train stations, or aircraft hangars.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
if: (1) The loss of waters of the United States exceeds \1/10\-acre; or
(2) there is a discharge in a special aquatic site, including wetlands.
(See general condition 31.) (Sections 10 and 404)
Note: Some discharges for the construction of farm roads or
forest roads, or temporary roads for moving mining equipment, may
qualify for an exemption under Section 404(f) of the Clean Water Act
(see 33 CFR 323.4).
15. U.S. Coast Guard Approved Bridges. Discharges of dredged or
fill material incidental to the construction of a bridge across
navigable waters of the United States, including cofferdams, abutments,
foundation seals, piers, and temporary construction and access fills,
provided the construction of the bridge structure has been authorized
by the U.S. Coast Guard under Section 9 of the Rivers and Harbors Act
of 1899 and other applicable laws. Causeways and approach fills are not
included in this NWP and will require a separate section 404 permit.
(Section 404)
16. Return Water From Upland Contained Disposal Areas. Return water
from an upland contained dredged material disposal area. The return
water from a contained disposal area is administratively defined as a
discharge of dredged material by 33 CFR 323.2(d), even though the
disposal itself occurs in an area that has no waters of the United
States and does not require a section 404 permit. This NWP satisfies
the technical requirement for a section 404 permit for the return water
where the quality of the return water is controlled by the state
through the section 401 certification procedures. The dredging activity
may require a section 404 permit (33 CFR 323.2(d)), and will require a
section 10 permit if located in navigable waters of the United States.
(Section 404)
17. Hydropower Projects. Discharges of dredged or fill material
associated with hydropower projects having: (a) Less than 5000 kW of
total generating capacity at existing reservoirs, where the project,
including the fill, is licensed by the Federal Energy Regulatory
Commission (FERC) under the Federal Power Act of 1920, as amended; or
(b) a licensing exemption granted by the FERC pursuant to Section 408
of the Energy Security Act of 1980 (16 U.S.C. 2705 and 2708) and
Section 30 of the Federal Power Act, as amended.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Section 404)
18. Minor Discharges. Minor discharges of dredged or fill material
into all waters of the United States, provided the activity meets all
of the following criteria:
(a) The quantity of discharged material and the volume of area
excavated do not exceed 25 cubic yards below the plane of the ordinary
high water mark or the high tide line;
(b) The discharge will not cause the loss of more than \1/10\-acre
of waters of the United States; and
(c) The discharge is not placed for the purpose of a stream
diversion.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
if: (1) The discharge or the volume of area excavated exceeds 10 cubic
yards below the plane of the ordinary high water mark or the high tide
line, or (2) the discharge is in a special aquatic site, including
wetlands. (See general condition 31.) (Sections 10 and 404)
19. Minor Dredging. Dredging of no more than 25 cubic yards below
the plane of the ordinary high water mark or the mean high water mark
from navigable waters of the United States (i.e., section 10 waters).
This NWP does not authorize the dredging or degradation through
siltation of coral reefs, sites that support submerged aquatic
vegetation (including sites where submerged aquatic vegetation is
documented to exist but may not be present in a given year), anadromous
fish spawning areas, or wetlands, or the connection of canals or other
artificial waterways to navigable waters of the United States (see 33
CFR 322.5(g)). (Sections 10 and 404)
20. Response Operations for Oil and Hazardous Substances.
Activities conducted in response to a discharge or release of oil and
hazardous substances that are subject to the National Oil and Hazardous
Substances Pollution
[[Page 10274]]
Contingency Plan (40 CFR part 300) including containment, cleanup, and
mitigation efforts, provided that the activities are done under either:
(1) The Spill Control and Countermeasure Plan required by 40 CFR 112.3;
(2) the direction or oversight of the federal on-scene coordinator
designated by 40 CFR part 300; or (3) any approved existing state,
regional or local contingency plan provided that the Regional Response
Team (if one exists in the area) concurs with the proposed response
efforts. This NWP also authorizes activities required for the cleanup
of oil releases in waters of the United States from electrical
equipment that are governed by EPA's polychlorinated biphenyl spill
response regulations at 40 CFR part 761. This NWP also authorizes the
use of temporary structures and fills in waters of the U.S. for spill
response training exercises. (Sections 10 and 404)
21. Surface Coal Mining Activities. Discharges of dredged or fill
material into waters of the United States associated with surface coal
mining and reclamation operations.
(a) Previously Authorized Surface Coal Mining Activities. Surface
coal mining activities that were previously authorized by the NWP 21
issued on March 12, 2007 (see 72 FR 11092), are authorized by this NWP,
provided the following criteria are met:
(1) The activities are already authorized, or are currently being
processed by states with approved programs under Title V of the Surface
Mining Control and Reclamation Act of 1977 or as part of an integrated
permit processing procedure by the Department of Interior, Office of
Surface Mining Reclamation and Enforcement;
(2) The permittee must submit a letter to the district engineer
requesting re-verification of the NWP 21 authorization. The letter must
describe any changes from the previous NWP 21 verification. The letter
must be submitted to the district engineer by February 1, 2013;
(3) The loss of waters of the United States is not greater than the
loss of waters of the United States previously verified by the district
engineer under the NWP 21 issued on March 12, 2007 (i.e., there are no
proposed expansions of surface coal mining activities in waters of the
United States);
(4) The district engineer provides written verification that those
activities will result in minimal individual and cumulative adverse
effects and are authorized by NWP 21, including currently applicable
regional conditions and any activity-specific conditions added to the
NWP authorization by the district engineer, such as compensatory
mitigation requirements; and
(5) If the permittee does not receive a written verification from
the district engineer prior to March 18, 2013, the permittee must cease
all activities until such verification is received. The district
engineer may extend the February 1, 2013, deadline by so notifying the
permittee in writing, but the permittee must still cease all activities
if he or she has not received written verification from the Corps by
March 18, 2013, until such verification is received.
(b) Other Surface Coal Mining Activities. Surface coal mining
activities that were not previously authorized by the NWP 21 issued on
March 12, 2007, are authorized by this NWP, provided the following
criteria are met:
(1) The activities are already authorized, or are currently being
processed by states with approved programs under Title V of the Surface
Mining Control and Reclamation Act of 1977 or as part of an integrated
permit processing procedure by the Department of Interior, Office of
Surface Mining Reclamation and Enforcement;
(2) The discharge must not cause the loss of greater than \1/2\-
acre of non-tidal waters of the United States, including the loss of no
more than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal individual and cumulative adverse effects. This
NWP does not authorize discharges into tidal waters or non-tidal
wetlands adjacent to tidal waters; and
(3) The discharge is not associated with the construction of valley
fills. A ``valley fill'' is a fill structure that is typically
constructed within valleys associated with steep, mountainous terrain,
associated with surface coal mining activities.
Notification: For activities under paragraph (b) of this NWP, the
permittee must submit a pre-construction notification to the district
engineer and receive written authorization prior to commencing the
activity. (See general condition 31.) (Sections 10 and 404)
22. Removal of Vessels. Temporary structures or minor discharges of
dredged or fill material required for the removal of wrecked,
abandoned, or disabled vessels, or the removal of man-made obstructions
to navigation. This NWP does not authorize maintenance dredging, shoal
removal, or riverbank snagging.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
if: (1) The vessel is listed or eligible for listing in the National
Register of Historic Places; or (2) the activity is conducted in a
special aquatic site, including coral reefs and wetlands. (See general
condition 31.) If condition 1 above is triggered, the permittee cannot
commence the activity until informed by the district engineer that
compliance with the ``Historic Properties'' general condition is
completed. (Sections 10 and 404)
Note 1: If a removed vessel is disposed of in waters of the
United States, a permit from the U.S. EPA may be required (see 40
CFR 229.3). If a Department of the Army permit is required for
vessel disposal in waters of the United States, separate
authorization will be required.
Note 2: Compliance with general condition 18, Endangered
Species, and general condition 20, Historic Properties, is required
for all NWPs. The concern with historic properties is emphasized in
the notification requirements for this NWP because of the likelihood
that submerged vessels may be historic properties.
23. Approved Categorical Exclusions. Activities undertaken,
assisted, authorized, regulated, funded, or financed, in whole or in
part, by another Federal agency or department where:
(a) That agency or department has determined, pursuant to the
Council on Environmental Quality's implementing regulations for the
National Environmental Policy Act (40 CFR part 1500 et seq.), that the
activity is categorically excluded from environmental documentation,
because it is included within a category of actions which neither
individually nor cumulatively have a significant effect on the human
environment; and
(b) The Office of the Chief of Engineers (Attn: CECW-CO) has
concurred with that agency's or department's determination that the
activity is categorically excluded and approved the activity for
authorization under NWP 23.
The Office of the Chief of Engineers may require additional
conditions, including pre-construction notification, for authorization
of an agency's categorical exclusions under this NWP.
Notification: Certain categorical exclusions approved for
authorization under this NWP require the permittee to submit a pre-
construction notification to the district engineer prior to commencing
the activity (see general condition 31). The activities that require
pre-construction notification are listed in the appropriate Regulatory
Guidance Letters. (Sections 10 and 404)
[[Page 10275]]
Note: The agency or department may submit an application for an
activity believed to be categorically excluded to the Office of the
Chief of Engineers (Attn: CECW-CO). Prior to approval for
authorization under this NWP of any agency's activity, the Office of
the Chief of Engineers will solicit public comment. As of the date
of issuance of this NWP, agencies with approved categorical
exclusions are the: Bureau of Reclamation, Federal Highway
Administration, and U.S. Coast Guard. Activities approved for
authorization under this NWP as of the date of this notice are found
in Corps Regulatory Guidance Letter 05-07, which is available at:
https://www.usace.army.mil/Missions/CivilWorks/RegulatoryProgramandPermits/GuidanceLetters.aspx. Any future
approved categorical exclusions will be announced in Regulatory
Guidance Letters and posted on this same Web site.
24. Indian Tribe or State Administered Section 404 Programs. Any
activity permitted by a state or Indian Tribe administering its own
section 404 permit program pursuant to 33 U.S.C. 1344(g)-(l) is
permitted pursuant to Section 10 of the Rivers and Harbors Act of 1899.
(Section 10)
Note 1: As of the date of the promulgation of this NWP, only New
Jersey and Michigan administer their own section 404 permit
programs.
Note 2: Those activities that do not involve an Indian Tribe or
State section 404 permit are not included in this NWP, but certain
structures will be exempted by Section 154 of Public Law 94-587, 90
Stat. 2917 (33 U.S.C. 591) (see 33 CFR 322.4(b)).
25. Structural Discharges. Discharges of material such as concrete,
sand, rock, etc., into tightly sealed forms or cells where the material
will be used as a structural member for standard pile supported
structures, such as bridges, transmission line footings, and walkways,
or for general navigation, such as mooring cells, including the
excavation of bottom material from within the form prior to the
discharge of concrete, sand, rock, etc. This NWP does not authorize
filled structural members that would support buildings, building pads,
homes, house pads, parking areas, storage areas and other such
structures. The structure itself may require a separate section 10
permit if located in navigable waters of the United States. (Section
404)
26. [Reserved]
27. Aquatic Habitat Restoration, Establishment, and Enhancement
Activities. Activities in waters of the United States associated with
the restoration, enhancement, and establishment of tidal and non-tidal
wetlands and riparian areas, the restoration and enhancement of non-
tidal streams and other non-tidal open waters, and the rehabilitation
or enhancement of tidal streams, tidal wetlands, and tidal open waters,
provided those activities result in net increases in aquatic resource
functions and services.
To the extent that a Corps permit is required, activities
authorized by this NWP include, but are not limited to: The removal of
accumulated sediments; the installation, removal, and maintenance of
small water control structures, dikes, and berms, as well as discharges
of dredged or fill material to restore appropriate stream channel
configurations after small water control structures, dikes, and berms,
are removed; the installation of current deflectors; the enhancement,
restoration, or establishment of riffle and pool stream structure; the
placement of in-stream habitat structures; modifications of the stream
bed and/or banks to restore or establish stream meanders; the
backfilling of artificial channels; the removal of existing drainage
structures, such as drain tiles, and the filling, blocking, or
reshaping of drainage ditches to restore wetland hydrology; the
installation of structures or fills necessary to establish or re-
establish wetland or stream hydrology; the construction of small
nesting islands; the construction of open water areas; the construction
of oyster habitat over unvegetated bottom in tidal waters; shellfish
seeding; activities needed to reestablish vegetation, including plowing
or discing for seed bed preparation and the planting of appropriate
wetland species; re-establishment of submerged aquatic vegetation in
areas where those plant communities previously existed; re-
establishment of tidal wetlands in tidal waters where those wetlands
previously existed; mechanized land clearing to remove non-native
invasive, exotic, or nuisance vegetation; and other related activities.
Only native plant species should be planted at the site.
This NWP authorizes the relocation of non-tidal waters, including
non-tidal wetlands and streams, on the project site provided there are
net increases in aquatic resource functions and services.
Except for the relocation of non-tidal waters on the project site,
this NWP does not authorize the conversion of a stream or natural
wetlands to another aquatic habitat type (e.g., stream to wetland or
vice versa) or uplands. Changes in wetland plant communities that occur
when wetland hydrology is more fully restored during wetland
rehabilitation activities are not considered a conversion to another
aquatic habitat type. This NWP does not authorize stream
channelization. This NWP does not authorize the relocation of tidal
waters or the conversion of tidal waters, including tidal wetlands, to
other aquatic uses, such as the conversion of tidal wetlands into open
water impoundments.
Compensatory mitigation is not required for activities authorized
by this NWP since these activities must result in net increases in
aquatic resource functions and services.
Reversion. For enhancement, restoration, and establishment
activities conducted: (1) In accordance with the terms and conditions
of a binding stream or wetland enhancement or restoration agreement, or
a wetland establishment agreement, between the landowner and the U.S.
Fish and Wildlife Service (FWS), the Natural Resources Conservation
Service (NRCS), the Farm Service Agency (FSA), the National Marine
Fisheries Service (NMFS), the National Ocean Service (NOS), U.S. Forest
Service (USFS), or their designated state cooperating agencies; (2) as
voluntary wetland restoration, enhancement, and establishment actions
documented by the NRCS or USDA Technical Service Provider pursuant to
NRCS Field Office Technical Guide standards; or (3) on reclaimed
surface coal mine lands, in accordance with a Surface Mining Control
and Reclamation Act permit issued by the Office of Surface Mining
Reclamation and Enforcement (OSMRE) or the applicable state agency,
this NWP also authorizes any future discharge of dredged or fill
material associated with the reversion of the area to its documented
prior condition and use (i.e., prior to the restoration, enhancement,
or establishment activities). The reversion must occur within five
years after expiration of a limited term wetland restoration or
establishment agreement or permit, and is authorized in these
circumstances even if the discharge occurs after this NWP expires. The
five-year reversion limit does not apply to agreements without time
limits reached between the landowner and the FWS, NRCS, FSA, NMFS, NOS,
USFS, or an appropriate state cooperating agency. This NWP also
authorizes discharges of dredged or fill material in waters of the
United States for the reversion of wetlands that were restored,
enhanced, or established on prior-converted cropland or on uplands, in
accordance with a binding agreement between the landowner and NRCS,
FSA, FWS, or their designated state cooperating agencies (even though
the restoration, enhancement, or establishment activity did not require
a section 404 permit). The prior condition will be documented in the
original agreement or permit, and the
[[Page 10276]]
determination of return to prior conditions will be made by the Federal
agency or appropriate state agency executing the agreement or permit.
Before conducting any reversion activity the permittee or the
appropriate Federal or state agency must notify the district engineer
and include the documentation of the prior condition. Once an area has
reverted to its prior physical condition, it will be subject to
whatever the Corps Regulatory requirements are applicable to that type
of land at the time. The requirement that the activity results in a net
increase in aquatic resource functions and services does not apply to
reversion activities meeting the above conditions. Except for the
activities described above, this NWP does not authorize any future
discharge of dredged or fill material associated with the reversion of
the area to its prior condition. In such cases a separate permit would
be required for any reversion.
Reporting. For those activities that do not require pre-
construction notification, the permittee must submit to the district
engineer a copy of: (1) The binding stream enhancement or restoration
agreement or wetland enhancement, restoration, or establishment
agreement, or a project description, including project plans and
location map; (2) the NRCS or USDA Technical Service Provider
documentation for the voluntary stream enhancement or restoration
action or wetland restoration, enhancement, or establishment action; or
(3) the SMCRA permit issued by OSMRE or the applicable state agency.
The report must also include information on baseline ecological
conditions on the project site, such as a delineation of wetlands,
streams, and/or other aquatic habitats. These documents must be
submitted to the district engineer at least 30 days prior to commencing
activities in waters of the United States authorized by this NWP.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing any activity
(see general condition 31), except for the following activities:
(1) Activities conducted on non-Federal public lands and private
lands, in accordance with the terms and conditions of a binding stream
enhancement or restoration agreement or wetland enhancement,
restoration, or establishment agreement between the landowner and the
U.S. FWS, NRCS, FSA, NMFS, NOS, USFS or their designated state
cooperating agencies;
(2) Voluntary stream or wetland restoration or enhancement action,
or wetland establishment action, documented by the NRCS or USDA
Technical Service Provider pursuant to NRCS Field Office Technical
Guide standards; or
(3) The reclamation of surface coal mine lands, in accordance with
an SMCRA permit issued by the OSMRE or the applicable state agency.
However, the permittee must submit a copy of the appropriate
documentation to the district engineer to fulfill the reporting
requirement. (Sections 10 and 404)
Note: This NWP can be used to authorize compensatory mitigation
projects, including mitigation banks and in-lieu fee projects.
However, this NWP does not authorize the reversion of an area used
for a compensatory mitigation project to its prior condition, since
compensatory mitigation is generally intended to be permanent.
28. Modifications of Existing Marinas. Reconfiguration of existing
docking facilities within an authorized marina area. No dredging,
additional slips, dock spaces, or expansion of any kind within waters
of the United States is authorized by this NWP. (Section 10)
29. Residential Developments. Discharges of dredged or fill
material into non-tidal waters of the United States for the
construction or expansion of a single residence, a multiple unit
residential development, or a residential subdivision. This NWP
authorizes the construction of building foundations and building pads
and attendant features that are necessary for the use of the residence
or residential development. Attendant features may include but are not
limited to roads, parking lots, garages, yards, utility lines, storm
water management facilities, septic fields, and recreation facilities
such as playgrounds, playing fields, and golf courses (provided the
golf course is an integral part of the residential development).
The discharge must not cause the loss of greater than \1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This NWP does not authorize
discharges into non-tidal wetlands adjacent to tidal waters.
Subdivisions: For residential subdivisions, the aggregate total
loss of waters of United States authorized by this NWP cannot exceed
\1/2\-acre. This includes any loss of waters of the United States
associated with development of individual subdivision lots.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Sections 10 and 404)
30. Moist Soil Management for Wildlife. Discharges of dredged or
fill material into non-tidal waters of the United States and
maintenance activities that are associated with moist soil management
for wildlife for the purpose of continuing ongoing, site-specific,
wildlife management activities where soil manipulation is used to
manage habitat and feeding areas for wildlife. Such activities include,
but are not limited to, plowing or discing to impede succession,
preparing seed beds, or establishing fire breaks. Sufficient riparian
areas must be maintained adjacent to all open water bodies, including
streams, to preclude water quality degradation due to erosion and
sedimentation. This NWP does not authorize the construction of new
dikes, roads, water control structures, or similar features associated
with the management areas. The activity must not result in a net loss
of aquatic resource functions and services. This NWP does not authorize
the conversion of wetlands to uplands, impoundments, or other open
water bodies. (Section 404)
Note: The repair, maintenance, or replacement of existing water
control structures or the repair or maintenance of dikes may be
authorized by NWP 3. Some such activities may qualify for an
exemption under Section 404(f) of the Clean Water Act (see 33 CFR
323.4).
31. Maintenance of Existing Flood Control Facilities. Discharges of
dredged or fill material resulting from activities associated with the
maintenance of existing flood control facilities, including debris
basins, retention/detention basins, levees, and channels that: (i) Were
previously authorized by the Corps by individual permit, general
permit, or 33 CFR 330.3, or did not require a permit at the time they
were constructed, or (ii) were constructed by the Corps and transferred
to a non-Federal sponsor for operation and maintenance. Activities
authorized by this NWP are limited to those resulting from maintenance
activities that are conducted within the ``maintenance baseline,'' as
described in the definition below. Discharges of dredged or fill
materials associated with maintenance activities in flood control
facilities in any watercourse that have previously been determined to
be within the maintenance baseline are authorized under this NWP. To
the extent that a Corps permit is required, this NWP
[[Page 10277]]
authorizes the removal of vegetation from levees associated with the
flood control project. This NWP does not authorize the removal of
sediment and associated vegetation from natural water courses except
when these activities have been included in the maintenance baseline.
All dredged material must be placed in an area that has no waters of
the United States or a separately authorized disposal site in waters of
the United States, and proper siltation controls must be used.
Maintenance Baseline: The maintenance baseline is a description of
the physical characteristics (e.g., depth, width, length, location,
configuration, or design flood capacity, etc.) of a flood control
project within which maintenance activities are normally authorized by
NWP 31, subject to any case-specific conditions required by the
district engineer. The district engineer will approve the maintenance
baseline based on the approved or constructed capacity of the flood
control facility, whichever is smaller, including any areas where there
are no constructed channels but which are part of the facility. The
prospective permittee will provide documentation of the physical
characteristics of the flood control facility (which will normally
consist of as-built or approved drawings) and documentation of the
approved and constructed design capacities of the flood control
facility. If no evidence of the constructed capacity exists, the
approved capacity will be used. The documentation will also include
best management practices to ensure that the impacts to the aquatic
environment are minimal, especially in maintenance areas where there
are no constructed channels. (The Corps may request maintenance records
in areas where there has not been recent maintenance.) Revocation or
modification of the final determination of the maintenance baseline can
only be done in accordance with 33 CFR 330.5. Except in emergencies as
described below, this NWP cannot be used until the district engineer
approves the maintenance baseline and determines the need for
mitigation and any regional or activity-specific conditions. Once
determined, the maintenance baseline will remain valid for any
subsequent reissuance of this NWP. This NWP does not authorize
maintenance of a flood control facility that has been abandoned. A
flood control facility will be considered abandoned if it has operated
at a significantly reduced capacity without needed maintenance being
accomplished in a timely manner.
Mitigation: The district engineer will determine any required
mitigation one-time only for impacts associated with maintenance work
at the same time that the maintenance baseline is approved. Such one-
time mitigation will be required when necessary to ensure that adverse
environmental impacts are no more than minimal, both individually and
cumulatively. Such mitigation will only be required once for any
specific reach of a flood control project. However, if one-time
mitigation is required for impacts associated with maintenance
activities, the district engineer will not delay needed maintenance,
provided the district engineer and the permittee establish a schedule
for identification, approval, development, construction and completion
of any such required mitigation. Once the one-time mitigation described
above has been completed, or a determination made that mitigation is
not required, no further mitigation will be required for maintenance
activities within the maintenance baseline. In determining appropriate
mitigation, the district engineer will give special consideration to
natural water courses that have been included in the maintenance
baseline and require compensatory mitigation and/or best management
practices as appropriate.
Emergency Situations: In emergency situations, this NWP may be used
to authorize maintenance activities in flood control facilities for
which no maintenance baseline has been approved. Emergency situations
are those which would result in an unacceptable hazard to life, a
significant loss of property, or an immediate, unforeseen, and
significant economic hardship if action is not taken before a
maintenance baseline can be approved. In such situations, the
determination of mitigation requirements, if any, may be deferred until
the emergency has been resolved. Once the emergency has ended, a
maintenance baseline must be established expeditiously, and mitigation,
including mitigation for maintenance conducted during the emergency,
must be required as appropriate.
Notification: The permittee must submit a pre-construction
notification to the district engineer before any maintenance work is
conducted (see general condition 31). The pre-construction notification
may be for activity-specific maintenance or for maintenance of the
entire flood control facility by submitting a five-year (or less)
maintenance plan. The pre-construction notification must include a
description of the maintenance baseline and the dredged material
disposal site. (Sections 10 and 404)
32. Completed Enforcement Actions. Any structure, work, or
discharge of dredged or fill material remaining in place or undertaken
for mitigation, restoration, or environmental benefit in compliance
with either:
(i) The terms of a final written Corps non-judicial settlement
agreement resolving a violation of Section 404 of the Clean Water Act
and/or Section 10 of the Rivers and Harbors Act of 1899; or the terms
of an EPA 309(a) order on consent resolving a violation of Section 404
of the Clean Water Act, provided that:
(a) The unauthorized activity affected no more than 5 acres of non-
tidal waters or 1 acre of tidal waters;
(b) The settlement agreement provides for environmental benefits,
to an equal or greater degree, than the environmental detriments caused
by the unauthorized activity that is authorized by this NWP; and
(c) The district engineer issues a verification letter authorizing
the activity subject to the terms and conditions of this NWP and the
settlement agreement, including a specified completion date; or
(ii) The terms of a final Federal court decision, consent decree,
or settlement agreement resulting from an enforcement action brought by
the United States under Section 404 of the Clean Water Act and/or
Section 10 of the Rivers and Harbors Act of 1899; or
(iii) The terms of a final court decision, consent decree,
settlement agreement, or non-judicial settlement agreement resulting
from a natural resource damage claim brought by a trustee or trustees
for natural resources (as defined by the National Contingency Plan at
40 CFR subpart G) under Section 311 of the Clean Water Act, Section 107
of the Comprehensive Environmental Response, Compensation and Liability
Act, Section 312 of the National Marine Sanctuaries Act, Section 1002
of the Oil Pollution Act of 1990, or the Park System Resource
Protection Act at 16 U.S.C. 19jj, to the extent that a Corps permit is
required.
Compliance is a condition of the NWP itself. Any authorization
under this NWP is automatically revoked if the permittee does not
comply with the terms of this NWP or the terms of the court decision,
consent decree, or judicial/non-judicial settlement agreement. This NWP
does not apply to any activities occurring after the date of the
decision, decree, or agreement that are not for the purpose of
mitigation, restoration, or environmental benefit. Before reaching any
settlement agreement, the Corps will ensure compliance with the
provisions of 33
[[Page 10278]]
CFR part 326 and 33 CFR 330.6(d)(2) and (e). (Sections 10 and 404)
33. Temporary Construction, Access, and Dewatering. Temporary
structures, work, and discharges, including cofferdams, necessary for
construction activities or access fills or dewatering of construction
sites, provided that the associated primary activity is authorized by
the Corps of Engineers or the U.S. Coast Guard. This NWP also
authorizes temporary structures, work, and discharges, including
cofferdams, necessary for construction activities not otherwise subject
to the Corps or U.S. Coast Guard permit requirements. Appropriate
measures must be taken to maintain near normal downstream flows and to
minimize flooding. Fill must consist of materials, and be placed in a
manner, that will not be eroded by expected high flows. The use of
dredged material may be allowed if the district engineer determines
that it will not cause more than minimal adverse effects on aquatic
resources. Following completion of construction, temporary fill must be
entirely removed to an area that has no waters of the United States,
dredged material must be returned to its original location, and the
affected areas must be restored to pre-construction elevations. The
affected areas must also be revegetated, as appropriate. This permit
does not authorize the use of cofferdams to dewater wetlands or other
aquatic areas to change their use. Structures left in place after
construction is completed require a separate section 10 permit if
located in navigable waters of the United States. (See 33 CFR part
322.)
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
(see general condition 31). The pre-construction notification must
include a restoration plan showing how all temporary fills and
structures will be removed and the area restored to pre-project
conditions. (Sections 10 and 404)
34. Cranberry Production Activities. Discharges of dredged or fill
material for dikes, berms, pumps, water control structures or leveling
of cranberry beds associated with expansion, enhancement, or
modification activities at existing cranberry production operations.
The cumulative total acreage of disturbance per cranberry production
operation, including but not limited to, filling, flooding, ditching,
or clearing, must not exceed 10 acres of waters of the United States,
including wetlands. The activity must not result in a net loss of
wetland acreage. This NWP does not authorize any discharge of dredged
or fill material related to other cranberry production activities such
as warehouses, processing facilities, or parking areas. For the
purposes of this NWP, the cumulative total of 10 acres will be measured
over the period that this NWP is valid.
Notification: The permittee must submit a pre-construction
notification to the district engineer once during the period that this
NWP is valid, and the NWP will then authorize discharges of dredge or
fill material at an existing operation for the permit term, provided
the 10-acre limit is not exceeded. (See general condition 31.) (Section
404)
35. Maintenance Dredging of Existing Basins. Excavation and removal
of accumulated sediment for maintenance of existing marina basins,
access channels to marinas or boat slips, and boat slips to previously
authorized depths or controlling depths for ingress/egress, whichever
is less, provided the dredged material is deposited at an area that has
no waters of the United States site and proper siltation controls are
used. (Section 10)
36. Boat Ramps. Activities required for the construction of boat
ramps, provided the activity meets all of the following criteria:
(a) The discharge into waters of the United States does not exceed
50 cubic yards of concrete, rock, crushed stone or gravel into forms,
or in the form of pre-cast concrete planks or slabs, unless the
district engineer waives the 50 cubic yard limit by making a written
determination concluding that the discharge will result in minimal
adverse effects;
(b) The boat ramp does not exceed 20 feet in width, unless the
district engineer waives this criterion by making a written
determination concluding that the discharge will result in minimal
adverse effects;
(c) The base material is crushed stone, gravel or other suitable
material;
(d) The excavation is limited to the area necessary for site
preparation and all excavated material is removed to an area that has
no waters of the United States; and,
(e) No material is placed in special aquatic sites, including
wetlands.
The use of unsuitable material that is structurally unstable is not
authorized. If dredging in navigable waters of the United States is
necessary to provide access to the boat ramp, the dredging must be
authorized by another NWP, a regional general permit, or an individual
permit.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity
if: (1) The discharge into waters of the United States exceeds 50 cubic
yards, or (2) the boat ramp exceeds 20 feet in width. (See general
condition 31.) (Sections 10 and 404)
37. Emergency Watershed Protection and Rehabilitation. Work done by
or funded by:
(a) The Natural Resources Conservation Service for a situation
requiring immediate action under its emergency Watershed Protection
Program (7 CFR part 624);
(b) The U.S. Forest Service under its Burned-Area Emergency
Rehabilitation Handbook (FSH 2509.13);
(c) The Department of the Interior for wildland fire management
burned area emergency stabilization and rehabilitation (DOI Manual part
620, Ch. 3);
(d) The Office of Surface Mining, or states with approved programs,
for abandoned mine land reclamation activities under Title IV of the
Surface Mining Control and Reclamation Act (30 CFR Subchapter R), where
the activity does not involve coal extraction; or
(e) The Farm Service Agency under its Emergency Conservation
Program (7 CFR part 701).
In general, the prospective permittee should wait until the
district engineer issues an NWP verification or 45 calendar days have
passed before proceeding with the watershed protection and
rehabilitation activity. However, in cases where there is an
unacceptable hazard to life or a significant loss of property or
economic hardship will occur, the emergency watershed protection and
rehabilitation activity may proceed immediately and the district
engineer will consider the information in the pre-construction
notification and any comments received as a result of agency
coordination to decide whether the NWP 37 authorization should be
modified, suspended, or revoked in accordance with the procedures at 33
CFR 330.5.
Notification: Except in cases where there is an unacceptable hazard
to life or a significant loss of property or economic hardship will
occur, the permittee must submit a pre-construction notification to the
district engineer prior to commencing the activity (see general
condition 31). (Sections 10 and 404)
38. Cleanup of Hazardous and Toxic Waste. Specific activities
required to effect the containment, stabilization, or removal of
hazardous or toxic waste materials that are performed, ordered, or
sponsored by a government agency with established legal or regulatory
authority. Court ordered remedial action plans or related settlements
are also authorized by this NWP. This NWP does not
[[Page 10279]]
authorize the establishment of new disposal sites or the expansion of
existing sites used for the disposal of hazardous or toxic waste.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Sections 10 and 404)
Note: Activities undertaken entirely on a Comprehensive
Environmental Response, Compensation, and Liability Act (CERCLA)
site by authority of CERCLA as approved or required by EPA, are not
required to obtain permits under Section 404 of the Clean Water Act
or Section 10 of the Rivers and Harbors Act.
39. Commercial and Institutional Developments. Discharges of
dredged or fill material into non-tidal waters of the United States for
the construction or expansion of commercial and institutional building
foundations and building pads and attendant features that are necessary
for the use and maintenance of the structures. Attendant features may
include, but are not limited to, roads, parking lots, garages, yards,
utility lines, storm water management facilities, and recreation
facilities such as playgrounds and playing fields. Examples of
commercial developments include retail stores, industrial facilities,
restaurants, business parks, and shopping centers. Examples of
institutional developments include schools, fire stations, government
office buildings, judicial buildings, public works buildings,
libraries, hospitals, and places of worship. The construction of new
golf courses and new ski areas is not authorized by this NWP.
The discharge must not cause the loss of greater than \1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This NWP does not authorize
discharges into non-tidal wetlands adjacent to tidal waters.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Sections 10 and 404)
Note: For any activity that involves the construction of a wind
energy generating structure, solar tower, or overhead transmission
line, a copy of the PCN and NWP verification will be provided to the
Department of Defense Siting Clearinghouse, which will evaluate
potential effects on military activities.
40. Agricultural Activities. Discharges of dredged or fill material
into non-tidal waters of the United States for agricultural activities,
including the construction of building pads for farm buildings.
Authorized activities include the installation, placement, or
construction of drainage tiles, ditches, or levees; mechanized land
clearing; land leveling; the relocation of existing serviceable
drainage ditches constructed in waters of the United States; and
similar activities.
This NWP also authorizes the construction of farm ponds in non-
tidal waters of the United States, excluding perennial streams,
provided the farm pond is used solely for agricultural purposes. This
NWP does not authorize the construction of aquaculture ponds.
This NWP also authorizes discharges of dredged or fill material
into non-tidal waters of the United States to relocate existing
serviceable drainage ditches constructed in non-tidal streams.
The discharge must not cause the loss of greater than \1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This NWP does not authorize
discharges into non-tidal wetlands adjacent to tidal waters.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Section 404)
Note: Some discharges for agricultural activities may qualify
for an exemption under Section 404(f) of the Clean Water Act (see 33
CFR 323.4). This NWP authorizes the construction of farm ponds that
do not qualify for the Clean Water Act Section 404(f)(1)(C)
exemption because of the recapture provision at Section 404(f)(2).
41. Reshaping Existing Drainage Ditches. Discharges of dredged or
fill material into non-tidal waters of the United States, excluding
non-tidal wetlands adjacent to tidal waters, to modify the cross-
sectional configuration of currently serviceable drainage ditches
constructed in waters of the United States, for the purpose of
improving water quality by regrading the drainage ditch with gentler
slopes, which can reduce erosion, increase growth of vegetation, and
increase uptake of nutrients and other substances by vegetation. The
reshaping of the ditch cannot increase drainage capacity beyond the
original as-built capacity nor can it expand the area drained by the
ditch as originally constructed (i.e., the capacity of the ditch must
be the same as originally constructed and it cannot drain additional
wetlands or other waters of the United States). Compensatory mitigation
is not required because the work is designed to improve water quality.
This NWP does not authorize the relocation of drainage ditches
constructed in waters of the United States; the location of the
centerline of the reshaped drainage ditch must be approximately the
same as the location of the centerline of the original drainage ditch.
This NWP does not authorize stream channelization or stream relocation
projects.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity,
if more than 500 linear feet of drainage ditch will be reshaped. (See
general condition 31.) (Section 404)
42. Recreational Facilities. Discharges of dredged or fill material
into non-tidal waters of the United States for the construction or
expansion of recreational facilities. Examples of recreational
facilities that may be authorized by this NWP include playing fields
(e.g., football fields, baseball fields), basketball courts, tennis
courts, hiking trails, bike paths, golf courses, ski areas, horse
paths, nature centers, and campgrounds (excluding recreational vehicle
parks). This NWP also authorizes the construction or expansion of small
support facilities, such as maintenance and storage buildings and
stables that are directly related to the recreational activity, but it
does not authorize the construction of hotels, restaurants, racetracks,
stadiums, arenas, or similar facilities.
The discharge must not cause the loss of greater than \1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This NWP does not authorize
discharges into non-tidal wetlands adjacent to tidal waters.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Section 404)
43. Stormwater Management Facilities. Discharges of dredged or fill
material into non-tidal waters of the United States for the
construction of stormwater management facilities, including stormwater
detention basins and retention basins and other
[[Page 10280]]
stormwater management facilities; the construction of water control
structures, outfall structures and emergency spillways; and the
construction of low impact development integrated management features
such as bioretention facilities (e.g., rain gardens), vegetated filter
strips, grassed swales, and infiltration trenches. This NWP also
authorizes, to the extent that a section 404 permit is required,
discharges of dredged or fill material into non-tidal waters of the
United States for the maintenance of stormwater management facilities.
Note that stormwater management facilities that are determined to be
waste treatment systems under 33 CFR 328.3(a)(8) are not waters of the
United States, and maintenance of these waste treatment systems
generally does not require a section 404 permit.
The discharge must not cause the loss of greater than \1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This NWP does not authorize
discharges into non-tidal wetlands adjacent to tidal waters. This NWP
does not authorize discharges of dredged or fill material for the
construction of new stormwater management facilities in perennial
streams.
Notification: For the construction of new stormwater management
facilities, or the expansion of existing stormwater management
facilities, the permittee must submit a pre-construction notification
to the district engineer prior to commencing the activity. (See general
condition 31.) Maintenance activities do not require pre-construction
notification if they are limited to restoring the original design
capacities of the stormwater management facility. (Section 404)
44. Mining Activities. Discharges of dredged or fill material into
non-tidal waters of the United States for mining activities, except for
coal mining activities. The discharge must not cause the loss of
greater than \1/2\-acre of non-tidal waters of the United States,
including the loss of no more than 300 linear feet of stream bed,
unless for intermittent and ephemeral stream beds the district engineer
waives the 300 linear foot limit by making a written determination
concluding that the discharge will result in minimal adverse effects.
This NWP does not authorize discharges into non-tidal wetlands adjacent
to tidal waters.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) If reclamation is required by other
statutes, then a copy of the reclamation plan must be submitted with
the pre-construction notification. (Sections 10 and 404)
45. Repair of Uplands Damaged by Discrete Events. This NWP
authorizes discharges of dredged or fill material, including dredging
or excavation, into all waters of the United States for activities
associated with the restoration of upland areas damaged by storms,
floods, or other discrete events. This NWP authorizes bank
stabilization to protect the restored uplands. The restoration of the
damaged areas, including any bank stabilization, must not exceed the
contours, or ordinary high water mark, that existed before the damage
occurred. The district engineer retains the right to determine the
extent of the pre-existing conditions and the extent of any restoration
work authorized by this NWP. The work must commence, or be under
contract to commence, within two years of the date of damage, unless
this condition is waived in writing by the district engineer. This NWP
cannot be used to reclaim lands lost to normal erosion processes over
an extended period.
This NWP does not authorize beach restoration or nourishment.
Minor dredging is limited to the amount necessary to restore the
damaged upland area and should not significantly alter the pre-existing
bottom contours of the waterbody.
Notification: The permittee must submit a pre-construction
notification to the district engineer (see general condition 31) within
12-months of the date of the damage. The pre-construction notification
should include documentation, such as a recent topographic survey or
photographs, to justify the extent of the proposed restoration.
(Sections 10 and 404)
Note: The uplands themselves that are lost as a result of a
storm, flood, or other discrete event can be replaced without a
section 404 permit, if the uplands are restored to the ordinary high
water mark (in non-tidal waters) or high tide line (in tidal
waters). (See also 33 CFR 328.5.) This NWP authorizes discharges of
dredged or fill material into waters of the United States associated
with the restoration of uplands.
46. Discharges in Ditches. Discharges of dredged or fill material
into non-tidal ditches that are: (1) Constructed in uplands, (2)
receive water from an area determined to be a water of the United
States prior to the construction of the ditch, (3) divert water to an
area determined to be a water of the United States prior to the
construction of the ditch, and (4) are determined to be waters of the
United States. The discharge must not cause the loss of greater than
one acre of waters of the United States. This NWP does not authorize
discharges of dredged or fill material into ditches constructed in
streams or other waters of the United States, or in streams that have
been relocated in uplands. This NWP does not authorize discharges of
dredged or fill material that increase the capacity of the ditch and
drain those areas determined to be waters of the United States prior to
construction of the ditch.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Section 404)
47. [Reserved]
48. Commercial Shellfish Aquaculture Activities. Discharges of
dredged or fill material in waters of the United States or structures
or work in navigable waters of the United States necessary for
commercial shellfish aquaculture operations in authorized project
areas. For the purposes of this NWP, the project area is the area in
which the operator is currently authorized to conduct commercial
shellfish aquaculture activities, as identified through a lease or
permit issued by an appropriate state or local government agency, a
treaty, or any other easement, lease, deed, or contract which
establishes an enforceable property interest for the operator. This NWP
authorizes the installation of buoys, floats, racks, trays, nets,
lines, tubes, containers, and other structures into navigable waters of
the United States. This NWP also authorizes discharges of dredged or
fill material into waters of the United States necessary for shellfish
seeding, rearing, cultivating, transplanting, and harvesting
activities. Rafts and other floating structures must be securely
anchored and clearly marked. This NWP does not authorize:
(a) The cultivation of a nonindigenous species unless that species
has been previously cultivated in the waterbody;
(b) The cultivation of an aquatic nuisance species as defined in
the Nonindigenous Aquatic Nuisance Prevention and Control Act of 1990;
or,
(c) Attendant features such as docks, piers, boat ramps,
stockpiles, or staging areas, or the deposition of shell material back
into waters of the United States as waste.
This NWP also authorizes commercial shellfish aquaculture
activities in new project areas, provided the project proponent has
obtained a valid
[[Page 10281]]
authorization, such as a lease or permit issued by an appropriate state
or local government agency, and those activities do not directly affect
more than \1/2\-acre of submerged aquatic vegetation beds.
Notification: The permittee must submit a pre-construction
notification to the district engineer if: (1) Dredge harvesting,
tilling, or harrowing is conducted in areas inhabited by submerged
aquatic vegetation; (2) the activity will include a species not
previously cultivated in the waterbody; (3) the activity involves a
change from bottom culture to floating or suspended culture; or (4) the
activity occurs in a new project area. (See general condition 31.)
In addition to the information required by paragraph (b) of general
condition 31, the pre-construction notification must also include the
following information: (1) A map showing the boundaries of the project
area, with latitude and longitude coordinates for each corner of the
project area; (2) the name(s) of the cultivated species; and (3)
whether canopy predator nets are being used. (Sections 10 and 404)
Note 1: The permittee should notify the applicable U.S. Coast
Guard office regarding the project.
Note 2: To prevent introduction of aquatic nuisance species, no
material that has been taken from a different waterbody may be
reused in the current project area, unless it has been treated in
accordance with the applicable regional aquatic nuisance species
management plan.
Note 3: The Nonindigenous Aquatic Nuisance Prevention and
Control Act of 1990 defines ``aquatic nuisance species'' as ``a
nonindigenous species that threatens the diversity or abundance of
native species or the ecological stability of infested waters, or
commercial, agricultural, aquacultural, or recreational activities
dependent on such waters.''
49. Coal Remining Activities. Discharges of dredged or fill
material into non-tidal waters of the United States associated with the
remining and reclamation of lands that were previously mined for coal.
The activities must already be authorized, or they must currently be in
process as part of an integrated permit processing procedure, by the
Department of Interior Office of Surface Mining Reclamation and
Enforcement, or by states with approved programs under Title IV or
Title V of the Surface Mining Control and Reclamation Act (SMCRA) of
1977. Areas previously mined include reclaimed mine sites, abandoned
mine land areas, or lands under bond forfeiture contracts.
As part of the project, the permittee may conduct new coal mining
activities in conjunction with the remining activities when he or she
clearly demonstrates to the district engineer that the overall mining
plan will result in a net increase in aquatic resource functions. The
Corps will consider the SMCRA agency's decision regarding the amount of
currently undisturbed adjacent lands needed to facilitate the remining
and reclamation of the previously mined area. The total area disturbed
by new mining must not exceed 40 percent of the total acreage covered
by both the remined area and the additional area necessary to carry out
the reclamation of the previously mined area.
Notification: The permittee must submit a pre-construction
notification and a document describing how the overall mining plan will
result in a net increase in aquatic resource functions to the district
engineer and receive written authorization prior to commencing the
activity. (See general condition 31.) (Sections 10 and 404)
50. Underground Coal Mining Activities. Discharges of dredged or
fill material into non-tidal waters of the United States associated
with underground coal mining and reclamation operations provided the
activities are authorized, or are currently being processed as part of
an integrated permit processing procedure, by the Department of
Interior, Office of Surface Mining Reclamation and Enforcement, or by
states with approved programs under Title V of the Surface Mining
Control and Reclamation Act of 1977.
The discharge must not cause the loss of greater than \1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This NWP does not authorize
discharges into non-tidal wetlands adjacent to tidal waters. This NWP
does not authorize coal preparation and processing activities outside
of the mine site.
Notification: The permittee must submit a pre-construction
notification to the district engineer and receive written authorization
prior to commencing the activity. (See general condition 31.) If
reclamation is required by other statutes, then a copy of the
reclamation plan must be submitted with the pre-construction
notification. (Sections 10 and 404)
Note: Coal preparation and processing activities outside of the
mine site may be authorized by NWP 21.
51. Land-Based Renewable Energy Generation Facilities. Discharges
of dredged or fill material into non-tidal waters of the United States
for the construction, expansion, or modification of land-based
renewable energy production facilities, including attendant features.
Such facilities include infrastructure to collect solar (concentrating
solar power and photovoltaic), wind, biomass, or geothermal energy.
Attendant features may include, but are not limited to roads, parking
lots, and stormwater management facilities within the land-based
renewable energy generation facility.
The discharge must not cause the loss of greater than\1/2\-acre of
non-tidal waters of the United States, including the loss of no more
than 300 linear feet of stream bed, unless for intermittent and
ephemeral stream beds the district engineer waives the 300 linear foot
limit by making a written determination concluding that the discharge
will result in minimal adverse effects. This permit does not authorize
discharges into non-tidal wetlands adjacent to tidal waters.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Sections 10 and 404)
Note 1: Utility lines constructed to transfer the energy from
the land-based renewable generation facility to a distribution
system, regional grid, or other facility are generally considered to
be linear projects and each separate and distant crossing of a
waterbody is eligible for treatment as a separate and complete
linear project. Those utility lines may be authorized by NWP 12 or
another Department of the Army authorization. If the only activities
associated with the construction, expansion, or modification of a
land-based renewable energy generation facility that require
Department of the Army authorization are discharges of dredged or
fill material into waters of the United States to construct,
maintain, repair, and/or remove utility lines, then NWP 12 shall be
used if those activities meet the terms and conditions of NWP 12,
including any applicable regional conditions and any case-specific
conditions imposed by the district engineer.
Note 2: For any activity that involves the construction of a
wind energy generating structure, solar tower, or overhead
transmission line, a copy of the PCN and NWP verification will be
provided to the Department of Defense Siting Clearinghouse, which
will evaluate potential effects on military activities.
52. Water-Based Renewable Energy Generation Pilot Projects.
Structures and
[[Page 10282]]
work in navigable waters of the United States and discharges of dredged
or fill material into waters of the United States for the construction,
expansion, modification, or removal of water-based wind or hydrokinetic
renewable energy generation pilot projects and their attendant
features. Attendant features may include, but are not limited to, land-
based collection and distribution facilities, control facilities,
roads, parking lots, and stormwater management facilities.
For the purposes of this NWP, the term ``pilot project'' means an
experimental project where the renewable energy generation units will
be monitored to collect information on their performance and
environmental effects at the project site.
The discharge must not cause the loss of greater than \1/2\-acre of
waters of the United States, including the loss of no more than 300
linear feet of stream bed, unless for intermittent and ephemeral stream
beds the district engineer waives the 300 linear foot limit by making a
written determination concluding that the discharge will result in
minimal adverse effects. The placement of a transmission line on the
bed of a navigable water of the United States from the renewable energy
generation unit(s) to a land-based collection and distribution facility
is considered a structure under Section 10 of the Rivers and Harbors
Act of 1899 (see 33 CFR 322.2(b)), and the placement of the
transmission line on the bed of a navigable water of the United States
is not a loss of waters of the United States for the purposes of
applying the \1/2\-acre or 300 linear foot limits.
For each single and complete project, no more than 10 generation
units (e.g., wind turbines or hydrokinetic devices) are authorized.
This NWP does not authorize activities in coral reefs. Structures
in an anchorage area established by the U.S. Coast Guard must comply
with the requirements in 33 CFR 322.5(l)(2). Structures may not be
placed in established danger zones or restricted areas as designated in
33 CFR part 334, Federal navigation channels, shipping safety fairways
or traffic separation schemes established by the U.S. Coast Guard (see
33 CFR 322.5(l)(1)), or EPA or Corps designated open water dredged
material disposal areas.
Upon completion of the pilot project, the generation units,
transmission lines, and other structures or fills associated with the
pilot project must be removed to the maximum extent practicable unless
they are authorized by a separate Department of the Army authorization,
such as another NWP, an individual permit, or a regional general
permit. Completion of the pilot project will be identified as the date
of expiration of the Federal Energy Regulatory Commission (FERC)
license, or the expiration date of the NWP authorization if no FERC
license is issued.
Notification: The permittee must submit a pre-construction
notification to the district engineer prior to commencing the activity.
(See general condition 31.) (Sections 10 and 404)
Note 1: Utility lines constructed to transfer the energy from
the land-based collection facility to a distribution system,
regional grid, or other facility are generally considered to be
linear projects and each separate and distant crossing of a
waterbody is eligible for treatment as a separate and complete
linear project. Those utility lines may be authorized by NWP 12 or
another Department of the Army authorization.
Note 2: An activity that is located on an existing locally or
federally maintained U.S. Army Corps of Engineers project requires
separate approval from the Chief of Engineers under 33 U.S.C. 408.
Note 3: If the pilot project, including any transmission lines,
is placed in navigable waters of the United States (i.e., section 10
waters) within the coastal United States, the Great Lakes, and
United States territories, copies of the pre-construction
notification and NWP verification will be sent by the Corps to the
National Oceanic and Atmospheric Administration, National Ocean
Service, for charting the generation units and associated
transmission line(s) to protect navigation.
Note 4: For any activity that involves the construction of a
wind energy generating structure, solar tower, or overhead
transmission line, a copy of the PCN and NWP verification will be
provided to the Department of Defense Siting Clearinghouse, which
will evaluate potential effects on military activities.
C. Nationwide Permit General Conditions
Note: To qualify for NWP authorization, the prospective
permittee must comply with the following general conditions, as
applicable, in addition to any regional or case-specific conditions
imposed by the division engineer or district engineer. Prospective
permittees should contact the appropriate Corps district office to
determine if regional conditions have been imposed on an NWP.
Prospective permittees should also contact the appropriate Corps
district office to determine the status of Clean Water Act Section
401 water quality certification and/or Coastal Zone Management Act
consistency for an NWP. Every person who may wish to obtain permit
authorization under one or more NWPs, or who is currently relying on
an existing or prior permit authorization under one or more NWPs,
has been and is on notice that all of the provisions of 33 CFR 330.1
through 330.6 apply to every NWP authorization. Note especially 33
CFR 330.5 relating to the modification, suspension, or revocation of
any NWP authorization.
1. Navigation. (a) No activity may cause more than a minimal
adverse effect on navigation.
(b) Any safety lights and signals prescribed by the U.S. Coast
Guard, through regulations or otherwise, must be installed and
maintained at the permittee's expense on authorized facilities in
navigable waters of the United States.
(c) The permittee understands and agrees that, if future operations
by the United States require the removal, relocation, or other
alteration, of the structure or work herein authorized, or if, in the
opinion of the Secretary of the Army or his authorized representative,
said structure or work shall cause unreasonable obstruction to the free
navigation of the navigable waters, the permittee will be required,
upon due notice from the Corps of Engineers, to remove, relocate, or
alter the structural work or obstructions caused thereby, without
expense to the United States. No claim shall be made against the United
States on account of any such removal or alteration.
2. Aquatic Life Movements. No activity may substantially disrupt
the necessary life cycle movements of those species of aquatic life
indigenous to the waterbody, including those species that normally
migrate through the area, unless the activity's primary purpose is to
impound water. All permanent and temporary crossings of waterbodies
shall be suitably culverted, bridged, or otherwise designed and
constructed to maintain low flows to sustain the movement of those
aquatic species.
3. Spawning Areas. Activities in spawning areas during spawning
seasons must be avoided to the maximum extent practicable. Activities
that result in the physical destruction (e.g., through excavation,
fill, or downstream smothering by substantial turbidity) of an
important spawning area are not authorized.
4. Migratory Bird Breeding Areas. Activities in waters of the
United States that serve as breeding areas for migratory birds must be
avoided to the maximum extent practicable.
5. Shellfish Beds. No activity may occur in areas of concentrated
shellfish populations, unless the activity is directly related to a
shellfish harvesting activity authorized by NWPs 4 and 48, or is a
shellfish seeding or habitat restoration activity authorized by NWP 27.
[[Page 10283]]
6. Suitable Material. No activity may use unsuitable material
(e.g., trash, debris, car bodies, asphalt, etc.). Material used for
construction or discharged must be free from toxic pollutants in toxic
amounts (see Section 307 of the Clean Water Act).
7. Water Supply Intakes. No activity may occur in the proximity of
a public water supply intake, except where the activity is for the
repair or improvement of public water supply intake structures or
adjacent bank stabilization.
8. Adverse Effects From Impoundments. If the activity creates an
impoundment of water, adverse effects to the aquatic system due to
accelerating the passage of water, and/or restricting its flow must be
minimized to the maximum extent practicable.
9. Management of Water Flows. To the maximum extent practicable,
the pre-construction course, condition, capacity, and location of open
waters must be maintained for each activity, including stream
channelization and storm water management activities, except as
provided below. The activity must be constructed to withstand expected
high flows. The activity must not restrict or impede the passage of
normal or high flows, unless the primary purpose of the activity is to
impound water or manage high flows. The activity may alter the pre-
construction course, condition, capacity, and location of open waters
if it benefits the aquatic environment (e.g., stream restoration or
relocation activities).
10. Fills Within 100-Year Floodplains. The activity must comply
with applicable FEMA-approved state or local floodplain management
requirements.
11. Equipment. Heavy equipment working in wetlands or mudflats must
be placed on mats, or other measures must be taken to minimize soil
disturbance.
12. Soil Erosion and Sediment Controls. Appropriate soil erosion
and sediment controls must be used and maintained in effective
operating condition during construction, and all exposed soil and other
fills, as well as any work below the ordinary high water mark or high
tide line, must be permanently stabilized at the earliest practicable
date. Permittees are encouraged to perform work within waters of the
United States during periods of low-flow or no-flow.
13. Removal of Temporary Fills. Temporary fills must be removed in
their entirety and the affected areas returned to pre-construction
elevations. The affected areas must be revegetated, as appropriate.
14. Proper Maintenance. Any authorized structure or fill shall be
properly maintained, including maintenance to ensure public safety and
compliance with applicable NWP general conditions, as well as any
activity-specific conditions added by the district engineer to an NWP
authorization.
15. Single and Complete Project. The activity must be a single and
complete project. The same NWP cannot be used more than once for the
same single and complete project.
16. Wild and Scenic Rivers. No activity may occur in a component of
the National Wild and Scenic River System, or in a river officially
designated by Congress as a ``study river'' for possible inclusion in
the system while the river is in an official study status, unless the
appropriate Federal agency with direct management responsibility for
such river, has determined in writing that the proposed activity will
not adversely affect the Wild and Scenic River designation or study
status. Information on Wild and Scenic Rivers may be obtained from the
appropriate Federal land management agency responsible for the
designated Wild and Scenic River or study river (e.g., National Park
Service, U.S. Forest Service, Bureau of Land Management, U.S. Fish and
Wildlife Service).
17. Tribal Rights. No activity or its operation may impair reserved
tribal rights, including, but not limited to, reserved water rights and
treaty fishing and hunting rights.
18. Endangered Species. (a) No activity is authorized under any NWP
which is likely to directly or indirectly jeopardize the continued
existence of a threatened or endangered species or a species proposed
for such designation, as identified under the Federal Endangered
Species Act (ESA), or which will directly or indirectly destroy or
adversely modify the critical habitat of such species. No activity is
authorized under any NWP which ``may affect'' a listed species or
critical habitat, unless Section 7 consultation addressing the effects
of the proposed activity has been completed.
(b) Federal agencies should follow their own procedures for
complying with the requirements of the ESA. Federal permittees must
provide the district engineer with the appropriate documentation to
demonstrate compliance with those requirements. The district engineer
will review the documentation and determine whether it is sufficient to
address ESA compliance for the NWP activity, or whether additional ESA
consultation is necessary.
(c) Non-federal permittees must submit a pre-construction
notification to the district engineer if any listed species or
designated critical habitat might be affected or is in the vicinity of
the project, or if the project is located in designated critical
habitat, and shall not begin work on the activity until notified by the
district engineer that the requirements of the ESA have been satisfied
and that the activity is authorized. For activities that might affect
Federally listed endangered or threatened species or designated
critical habitat, the pre-construction notification must include the
name(s) of the endangered or threatened species that might be affected
by the proposed work or that utilize the designated critical habitat
that might be affected by the proposed work. The district engineer will
determine whether the proposed activity ``may affect'' or will have
``no effect'' to listed species and designated critical habitat and
will notify the non-Federal applicant of the Corps' determination
within 45 days of receipt of a complete pre-construction notification.
In cases where the non-Federal applicant has identified listed species
or critical habitat that might be affected or is in the vicinity of the
project, and has so notified the Corps, the applicant shall not begin
work until the Corps has provided notification the proposed activities
will have ``no effect'' on listed species or critical habitat, or until
Section 7 consultation has been completed. If the non-Federal applicant
has not heard back from the Corps within 45 days, the applicant must
still wait for notification from the Corps.
(d) As a result of formal or informal consultation with the FWS or
NMFS the district engineer may add species-specific regional endangered
species conditions to the NWPs.
(e) Authorization of an activity by a NWP does not authorize the
``take'' of a threatened or endangered species as defined under the
ESA. In the absence of separate authorization (e.g., an ESA Section 10
Permit, a Biological Opinion with ``incidental take'' provisions, etc.)
from the U.S. FWS or the NMFS, The Endangered Species Act prohibits any
person subject to the jurisdiction of the United States to take a
listed species, where ``take'' means to harass, harm, pursue, hunt,
shoot, wound, kill, trap, capture, or collect, or to attempt to engage
in any such conduct. The word ``harm'' in the definition of ``take''
means an act which actually kills or injures wildlife. Such an act may
include significant habitat modification or degradation where it
actually kills or injures wildlife by significantly impairing essential
behavioral patterns,
[[Page 10284]]
including breeding, feeding or sheltering.
(f) Information on the location of threatened and endangered
species and their critical habitat can be obtained directly from the
offices of the U.S. FWS and NMFS or their world wide web pages at
https://www.fws.gov/ or https://www.fws.gov/ipac and https://www.noaa.gov/fisheries.html respectively.
19. Migratory Birds and Bald and Golden Eagles. The permittee is
responsible for obtaining any ``take'' permits required under the U.S.
Fish and Wildlife Service's regulations governing compliance with the
Migratory Bird Treaty Act or the Bald and Golden Eagle Protection Act.
The permittee should contact the appropriate local office of the U.S.
Fish and Wildlife Service to determine if such ``take'' permits are
required for a particular activity.
20. Historic Properties. (a) In cases where the district engineer
determines that the activity may affect properties listed, or eligible
for listing, in the National Register of Historic Places, the activity
is not authorized, until the requirements of Section 106 of the
National Historic Preservation Act (NHPA) have been satisfied.
(b) Federal permittees should follow their own procedures for
complying with the requirements of Section 106 of the National Historic
Preservation Act. Federal permittees must provide the district engineer
with the appropriate documentation to demonstrate compliance with those
requirements. The district engineer will review the documentation and
determine whether it is sufficient to address section 106 compliance
for the NWP activity, or whether additional section 106 consultation is
necessary.
(c) Non-federal permittees must submit a pre-construction
notification to the district engineer if the authorized activity may
have the potential to cause effects to any historic properties listed
on, determined to be eligible for listing on, or potentially eligible
for listing on the National Register of Historic Places, including
previously unidentified properties. For such activities, the pre-
construction notification must state which historic properties may be
affected by the proposed work or include a vicinity map indicating the
location of the historic properties or the potential for the presence
of historic properties. Assistance regarding information on the
location of or potential for the presence of historic resources can be
sought from the State Historic Preservation Officer or Tribal Historic
Preservation Officer, as appropriate, and the National Register of
Historic Places (see 33 CFR 330.4(g)). When reviewing pre-construction
notifications, district engineers will comply with the current
procedures for addressing the requirements of Section 106 of the
National Historic Preservation Act. The district engineer shall make a
reasonable and good faith effort to carry out appropriate
identification efforts, which may include background research,
consultation, oral history interviews, sample field investigation, and
field survey. Based on the information submitted and these efforts, the
district engineer shall determine whether the proposed activity has the
potential to cause an effect on the historic properties. Where the non-
Federal applicant has identified historic properties on which the
activity may have the potential to cause effects and so notified the
Corps, the non-Federal applicant shall not begin the activity until
notified by the district engineer either that the activity has no
potential to cause effects or that consultation under Section 106 of
the NHPA has been completed.
(d) The district engineer will notify the prospective permittee
within 45 days of receipt of a complete pre-construction notification
whether NHPA Section 106 consultation is required. Section 106
consultation is not required when the Corps determines that the
activity does not have the potential to cause effects on historic
properties (see 36 CFR 800.3(a)). If NHPA section 106 consultation is
required and will occur, the district engineer will notify the non-
Federal applicant that he or she cannot begin work until Section 106
consultation is completed. If the non-Federal applicant has not heard
back from the Corps within 45 days, the applicant must still wait for
notification from the Corps.
(e) Prospective permittees should be aware that section 110k of the
NHPA (16 U.S.C. 470h-2(k)) prevents the Corps from granting a permit or
other assistance to an applicant who, with intent to avoid the
requirements of Section 106 of the NHPA, has intentionally
significantly adversely affected a historic property to which the
permit would relate, or having legal power to prevent it, allowed such
significant adverse effect to occur, unless the Corps, after
consultation with the Advisory Council on Historic Preservation (ACHP),
determines that circumstances justify granting such assistance despite
the adverse effect created or permitted by the applicant. If
circumstances justify granting the assistance, the Corps is required to
notify the ACHP and provide documentation specifying the circumstances,
the degree of damage to the integrity of any historic properties
affected, and proposed mitigation. This documentation must include any
views obtained from the applicant, SHPO/THPO, appropriate Indian tribes
if the undertaking occurs on or affects historic properties on tribal
lands or affects properties of interest to those tribes, and other
parties known to have a legitimate interest in the impacts to the
permitted activity on historic properties.
21. Discovery of Previously Unknown Remains and Artifacts. If you
discover any previously unknown historic, cultural or archeological
remains and artifacts while accomplishing the activity authorized by
this permit, you must immediately notify the district engineer of what
you have found, and to the maximum extent practicable, avoid
construction activities that may affect the remains and artifacts until
the required coordination has been completed. The district engineer
will initiate the Federal, Tribal and state coordination required to
determine if the items or remains warrant a recovery effort or if the
site is eligible for listing in the National Register of Historic
Places.
22. Designated Critical Resource Waters. Critical resource waters
include, NOAA-managed marine sanctuaries and marine monuments, and
National Estuarine Research Reserves. The district engineer may
designate, after notice and opportunity for public comment, additional
waters officially designated by a state as having particular
environmental or ecological significance, such as outstanding national
resource waters or state natural heritage sites. The district engineer
may also designate additional critical resource waters after notice and
opportunity for public comment.
(a) Discharges of dredged or fill material into waters of the
United States are not authorized by NWPs 7, 12, 14, 16, 17, 21, 29, 31,
35, 39, 40, 42, 43, 44, 49, 50, 51, and 52 for any activity within, or
directly affecting, critical resource waters, including wetlands
adjacent to such waters.
(b) For NWPs 3, 8, 10, 13, 15, 18, 19, 22, 23, 25, 27, 28, 30, 33,
34, 36, 37, and 38, notification is required in accordance with general
condition 31, for any activity proposed in the designated critical
resource waters including wetlands adjacent to those waters. The
district engineer may authorize activities under these NWPs only after
it is determined that the impacts to the critical resource waters will
be no more than minimal.
[[Page 10285]]
23. Mitigation. The district engineer will consider the following
factors when determining appropriate and practicable mitigation
necessary to ensure that adverse effects on the aquatic environment are
minimal:
(a) The activity must be designed and constructed to avoid and
minimize adverse effects, both temporary and permanent, to waters of
the United States to the maximum extent practicable at the project site
(i.e., on site).
(b) Mitigation in all its forms (avoiding, minimizing, rectifying,
reducing, or compensating for resource losses) will be required to the
extent necessary to ensure that the adverse effects to the aquatic
environment are minimal.
(c) Compensatory mitigation at a minimum one-for-one ratio will be
required for all wetland losses that exceed \1/10\-acre and require
pre-construction notification, unless the district engineer determines
in writing that either some other form of mitigation would be more
environmentally appropriate or the adverse effects of the proposed
activity are minimal, and provides a project-specific waiver of this
requirement. For wetland losses of \1/10\-acre or less that require
pre-construction notification, the district engineer may determine on a
case-by-case basis that compensatory mitigation is required to ensure
that the activity results in minimal adverse effects on the aquatic
environment. Compensatory mitigation projects provided to offset losses
of aquatic resources must comply with the applicable provisions of 33
CFR part 332.
(1) The prospective permittee is responsible for proposing an
appropriate compensatory mitigation option if compensatory mitigation
is necessary to ensure that the activity results in minimal adverse
effects on the aquatic environment.
(2) Since the likelihood of success is greater and the impacts to
potentially valuable uplands are reduced, wetland restoration should be
the first compensatory mitigation option considered.
(3) If permittee-responsible mitigation is the proposed option, the
prospective permittee is responsible for submitting a mitigation plan.
A conceptual or detailed mitigation plan may be used by the district
engineer to make the decision on the NWP verification request, but a
final mitigation plan that addresses the applicable requirements of 33
CFR 332.4(c)(2)-(14) must be approved by the district engineer before
the permittee begins work in waters of the United States, unless the
district engineer determines that prior approval of the final
mitigation plan is not practicable or not necessary to ensure timely
completion of the required compensatory mitigation (see 33 CFR
332.3(k)(3)).
(4) If mitigation bank or in-lieu fee program credits are the
proposed option, the mitigation plan only needs to address the baseline
conditions at the impact site and the number of credits to be provided.
(5) Compensatory mitigation requirements (e.g., resource type and
amount to be provided as compensatory mitigation, site protection,
ecological performance standards, monitoring requirements) may be
addressed through conditions added to the NWP authorization, instead of
components of a compensatory mitigation plan.
(d) For losses of streams or other open waters that require pre-
construction notification, the district engineer may require
compensatory mitigation, such as stream rehabilitation, enhancement, or
preservation, to ensure that the activity results in minimal adverse
effects on the aquatic environment.
(e) Compensatory mitigation will not be used to increase the
acreage losses allowed by the acreage limits of the NWPs. For example,
if an NWP has an acreage limit of \1/2\-acre, it cannot be used to
authorize any project resulting in the loss of greater than \1/2\-acre
of waters of the United States, even if compensatory mitigation is
provided that replaces or restores some of the lost waters. However,
compensatory mitigation can and should be used, as necessary, to ensure
that a project already meeting the established acreage limits also
satisfies the minimal impact requirement associated with the NWPs.
(f) Compensatory mitigation plans for projects in or near streams
or other open waters will normally include a requirement for the
restoration or establishment, maintenance, and legal protection (e.g.,
conservation easements) of riparian areas next to open waters. In some
cases, riparian areas may be the only compensatory mitigation required.
Riparian areas should consist of native species. The width of the
required riparian area will address documented water quality or aquatic
habitat loss concerns. Normally, the riparian area will be 25 to 50
feet wide on each side of the stream, but the district engineer may
require slightly wider riparian areas to address documented water
quality or habitat loss concerns. If it is not possible to establish a
riparian area on both sides of a stream, or if the waterbody is a lake
or coastal waters, then restoring or establishing a riparian area along
a single bank or shoreline may be sufficient. Where both wetlands and
open waters exist on the project site, the district engineer will
determine the appropriate compensatory mitigation (e.g., riparian areas
and/or wetlands compensation) based on what is best for the aquatic
environment on a watershed basis. In cases where riparian areas are
determined to be the most appropriate form of compensatory mitigation,
the district engineer may waive or reduce the requirement to provide
wetland compensatory mitigation for wetland losses.
(g) Permittees may propose the use of mitigation banks, in-lieu fee
programs, or separate permittee-responsible mitigation. For activities
resulting in the loss of marine or estuarine resources, permittee-
responsible compensatory mitigation may be environmentally preferable
if there are no mitigation banks or in-lieu fee programs in the area
that have marine or estuarine credits available for sale or transfer to
the permittee. For permittee-responsible mitigation, the special
conditions of the NWP verification must clearly indicate the party or
parties responsible for the implementation and performance of the
compensatory mitigation project, and, if required, its long-term
management.
(h) Where certain functions and services of waters of the United
States are permanently adversely affected, such as the conversion of a
forested or scrub-shrub wetland to a herbaceous wetland in a
permanently maintained utility line right-of-way, mitigation may be
required to reduce the adverse effects of the project to the minimal
level.
24. Safety of Impoundment Structures. To ensure that all
impoundment structures are safely designed, the district engineer may
require non-Federal applicants to demonstrate that the structures
comply with established state dam safety criteria or have been designed
by qualified persons. The district engineer may also require
documentation that the design has been independently reviewed by
similarly qualified persons, and appropriate modifications made to
ensure safety.
25. Water Quality. Where States and authorized Tribes, or EPA where
applicable, have not previously certified compliance of an NWP with CWA
Section 401, individual 401 Water Quality Certification must be
obtained or waived (see 33 CFR 330.4(c)). The district engineer or
State or Tribe may require additional water quality management measures
to ensure that the authorized activity does not result in more than
minimal degradation of water quality.
[[Page 10286]]
26. Coastal Zone Management. In coastal states where an NWP has not
previously received a state coastal zone management consistency
concurrence, an individual state coastal zone management consistency
concurrence must be obtained, or a presumption of concurrence must
occur (see 33 CFR 330.4(d)). The district engineer or a State may
require additional measures to ensure that the authorized activity is
consistent with state coastal zone management requirements.
27. Regional and Case-By-Case Conditions. The activity must comply
with any regional conditions that may have been added by the Division
Engineer (see 33 CFR 330.4(e)) and with any case specific conditions
added by the Corps or by the state, Indian Tribe, or U.S. EPA in its
section 401 Water Quality Certification, or by the state in its Coastal
Zone Management Act consistency determination.
28. Use of Multiple Nationwide Permits. The use of more than one
NWP for a single and complete project is prohibited, except when the
acreage loss of waters of the United States authorized by the NWPs does
not exceed the acreage limit of the NWP with the highest specified
acreage limit. For example, if a road crossing over tidal waters is
constructed under NWP 14, with associated bank stabilization authorized
by NWP 13, the maximum acreage loss of waters of the United States for
the total project cannot exceed \1/3\-acre.
29. Transfer of Nationwide Permit Verifications. If the permittee
sells the property associated with a nationwide permit verification,
the permittee may transfer the nationwide permit verification to the
new owner by submitting a letter to the appropriate Corps district
office to validate the transfer. A copy of the nationwide permit
verification must be attached to the letter, and the letter must
contain the following statement and signature:
``When the structures or work authorized by this nationwide
permit are still in existence at the time the property is
transferred, the terms and conditions of this nationwide permit,
including any special conditions, will continue to be binding on the
new owner(s) of the property. To validate the transfer of this
nationwide permit and the associated liabilities associated with
compliance with its terms and conditions, have the transferee sign
and date below.''
-----------------------------------------------------------------------
(Transferee)
-----------------------------------------------------------------------
(Date)
30. Compliance Certification. Each permittee who receives an NWP
verification letter from the Corps must provide a signed certification
documenting completion of the authorized activity and any required
compensatory mitigation. The success of any required permittee-
responsible mitigation, including the achievement of ecological
performance standards, will be addressed separately by the district
engineer. The Corps will provide the permittee the certification
document with the NWP verification letter. The certification document
will include:
(a) A statement that the authorized work was done in accordance
with the NWP authorization, including any general, regional, or
activity-specific conditions;
(b) A statement that the implementation of any required
compensatory mitigation was completed in accordance with the permit
conditions. If credits from a mitigation bank or in-lieu fee program
are used to satisfy the compensatory mitigation requirements, the
certification must include the documentation required by 33 CFR
332.3(l)(3) to confirm that the permittee secured the appropriate
number and resource type of credits; and
(c) The signature of the permittee certifying the completion of the
work and mitigation.
31. Pre-Construction Notification--(a) Timing. Where required by
the terms of the NWP, the prospective permittee must notify the
district engineer by submitting a pre-construction notification (PCN)
as early as possible. The district engineer must determine if the PCN
is complete within 30 calendar days of the date of receipt and, if the
PCN is determined to be incomplete, notify the prospective permittee
within that 30 day period to request the additional information
necessary to make the PCN complete. The request must specify the
information needed to make the PCN complete. As a general rule,
district engineers will request additional information necessary to
make the PCN complete only once. However, if the prospective permittee
does not provide all of the requested information, then the district
engineer will notify the prospective permittee that the PCN is still
incomplete and the PCN review process will not commence until all of
the requested information has been received by the district engineer.
The prospective permittee shall not begin the activity until either:
(1) He or she is notified in writing by the district engineer that
the activity may proceed under the NWP with any special conditions
imposed by the district or division engineer; or
(2) 45 calendar days have passed from the district engineer's
receipt of the complete PCN and the prospective permittee has not
received written notice from the district or division engineer.
However, if the permittee was required to notify the Corps pursuant to
general condition 18 that listed species or critical habitat might be
affected or in the vicinity of the project, or to notify the Corps
pursuant to general condition 20 that the activity may have the
potential to cause effects to historic properties, the permittee cannot
begin the activity until receiving written notification from the Corps
that there is ``no effect'' on listed species or ``no potential to
cause effects'' on historic properties, or that any consultation
required under Section 7 of the Endangered Species Act (see 33 CFR
330.4(f)) and/or Section 106 of the National Historic Preservation (see
33 CFR 330.4(g)) has been completed. Also, work cannot begin under NWPs
21, 49, or 50 until the permittee has received written approval from
the Corps. If the proposed activity requires a written waiver to exceed
specified limits of an NWP, the permittee may not begin the activity
until the district engineer issues the waiver. If the district or
division engineer notifies the permittee in writing that an individual
permit is required within 45 calendar days of receipt of a complete
PCN, the permittee cannot begin the activity until an individual permit
has been obtained. Subsequently, the permittee's right to proceed under
the NWP may be modified, suspended, or revoked only in accordance with
the procedure set forth in 33 CFR 330.5(d)(2).
(b) Contents of Pre-Construction Notification: The PCN must be in
writing and include the following information:
(1) Name, address and telephone numbers of the prospective
permittee;
(2) Location of the proposed project;
(3) A description of the proposed project; the project's purpose;
direct and indirect adverse environmental effects the project would
cause, including the anticipated amount of loss of water of the United
States expected to result from the NWP activity, in acres, linear feet,
or other appropriate unit of measure; any other NWP(s), regional
general permit(s), or individual permit(s) used or intended to be used
to authorize any part of the proposed project or any related activity.
The description should be sufficiently detailed to allow the district
engineer to determine that the adverse effects of the project will be
minimal and to determine the need for compensatory mitigation. Sketches
should be provided
[[Page 10287]]
when necessary to show that the activity complies with the terms of the
NWP. (Sketches usually clarify the project and when provided results in
a quicker decision. Sketches should contain sufficient detail to
provide an illustrative description of the proposed activity (e.g., a
conceptual plan), but do not need to be detailed engineering plans);
(4) The PCN must include a delineation of wetlands, other special
aquatic sites, and other waters, such as lakes and ponds, and
perennial, intermittent, and ephemeral streams, on the project site.
Wetland delineations must be prepared in accordance with the current
method required by the Corps. The permittee may ask the Corps to
delineate the special aquatic sites and other waters on the project
site, but there may be a delay if the Corps does the delineation,
especially if the project site is large or contains many waters of the
United States. Furthermore, the 45 day period will not start until the
delineation has been submitted to or completed by the Corps, as
appropriate;
(5) If the proposed activity will result in the loss of greater
than \1/10\-acre of wetlands and a PCN is required, the prospective
permittee must submit a statement describing how the mitigation
requirement will be satisfied, or explaining why the adverse effects
are minimal and why compensatory mitigation should not be required. As
an alternative, the prospective permittee may submit a conceptual or
detailed mitigation plan.
(6) If any listed species or designated critical habitat might be
affected or is in the vicinity of the project, or if the project is
located in designated critical habitat, for non-Federal applicants the
PCN must include the name(s) of those endangered or threatened species
that might be affected by the proposed work or utilize the designated
critical habitat that may be affected by the proposed work. Federal
applicants must provide documentation demonstrating compliance with the
Endangered Species Act; and
(7) For an activity that may affect a historic property listed on,
determined to be eligible for listing on, or potentially eligible for
listing on, the National Register of Historic Places, for non-Federal
applicants the PCN must state which historic property may be affected
by the proposed work or include a vicinity map indicating the location
of the historic property. Federal applicants must provide documentation
demonstrating compliance with Section 106 of the National Historic
Preservation Act.
(c) Form of Pre-Construction Notification: The standard individual
permit application form (Form ENG 4345) may be used, but the completed
application form must clearly indicate that it is a PCN and must
include all of the information required in paragraphs (b)(1) through
(7) of this general condition. A letter containing the required
information may also be used.
(d) Agency Coordination: (1) The district engineer will consider
any comments from Federal and state agencies concerning the proposed
activity's compliance with the terms and conditions of the NWPs and the
need for mitigation to reduce the project's adverse environmental
effects to a minimal level.
(2) For all NWP activities that require pre-construction
notification and result in the loss of greater than \1/2\-acre of
waters of the United States, for NWP 21, 29, 39, 40, 42, 43, 44, 50,
51, and 52 activities that require pre-construction notification and
will result in the loss of greater than 300 linear feet of intermittent
and ephemeral stream bed, and for all NWP 48 activities that require
pre-construction notification, the district engineer will immediately
provide (e.g., via email, facsimile transmission, overnight mail, or
other expeditious manner) a copy of the complete PCN to the appropriate
Federal or state offices (U.S. FWS, state natural resource or water
quality agency, EPA, State Historic Preservation Officer (SHPO) or
Tribal Historic Preservation Office (THPO), and, if appropriate, the
NMFS). With the exception of NWP 37, these agencies will have 10
calendar days from the date the material is transmitted to telephone or
fax the district engineer notice that they intend to provide
substantive, site-specific comments. The comments must explain why the
agency believes the adverse effects will be more than minimal. If so
contacted by an agency, the district engineer will wait an additional
15 calendar days before making a decision on the pre-construction
notification. The district engineer will fully consider agency comments
received within the specified time frame concerning the proposed
activity's compliance with the terms and conditions of the NWPs,
including the need for mitigation to ensure the net adverse
environmental effects to the aquatic environment of the proposed
activity are minimal. The district engineer will provide no response to
the resource agency, except as provided below. The district engineer
will indicate in the administrative record associated with each pre-
construction notification that the resource agencies' concerns were
considered. For NWP 37, the emergency watershed protection and
rehabilitation activity may proceed immediately in cases where there is
an unacceptable hazard to life or a significant loss of property or
economic hardship will occur. The district engineer will consider any
comments received to decide whether the NWP 37 authorization should be
modified, suspended, or revoked in accordance with the procedures at 33
CFR 330.5.
(3) In cases of where the prospective permittee is not a Federal
agency, the district engineer will provide a response to NMFS within 30
calendar days of receipt of any Essential Fish Habitat conservation
recommendations, as required by Section 305(b)(4)(B) of the Magnuson-
Stevens Fishery Conservation and Management Act.
(4) Applicants are encouraged to provide the Corps with either
electronic files or multiple copies of pre-construction notifications
to expedite agency coordination.
D. District Engineer's Decision
1. In reviewing the PCN for the proposed activity, the district
engineer will determine whether the activity authorized by the NWP will
result in more than minimal individual or cumulative adverse
environmental effects or may be contrary to the public interest. For a
linear project, this determination will include an evaluation of the
individual crossings to determine whether they individually satisfy the
terms and conditions of the NWP(s), as well as the cumulative effects
caused by all of the crossings authorized by NWP. If an applicant
requests a waiver of the 300 linear foot limit on impacts to
intermittent or ephemeral streams or of an otherwise applicable limit,
as provided for in NWPs 13, 21, 29, 36, 39, 40, 42, 43, 44, 50, 51 or
52, the district engineer will only grant the waiver upon a written
determination that the NWP activity will result in minimal adverse
effects. When making minimal effects determinations the district
engineer will consider the direct and indirect effects caused by the
NWP activity. The district engineer will also consider site specific
factors, such as the environmental setting in the vicinity of the NWP
activity, the type of resource that will be affected by the NWP
activity, the functions provided by the aquatic resources that will be
affected by the NWP activity, the degree or magnitude to which the
aquatic resources perform those functions, the extent that aquatic
resource functions will be lost as a result of the NWP activity (e.g.,
partial or complete loss), the duration of the
[[Page 10288]]
adverse effects (temporary or permanent), the importance of the aquatic
resource functions to the region (e.g., watershed or ecoregion), and
mitigation required by the district engineer. If an appropriate
functional assessment method is available and practicable to use, that
assessment method may be used by the district engineer to assist in the
minimal adverse effects determination. The district engineer may add
case-specific special conditions to the NWP authorization to address
site-specific environmental concerns.
2. If the proposed activity requires a PCN and will result in a
loss of greater than \1/10\-acre of wetlands, the prospective permittee
should submit a mitigation proposal with the PCN. Applicants may also
propose compensatory mitigation for projects with smaller impacts. The
district engineer will consider any proposed compensatory mitigation
the applicant has included in the proposal in determining whether the
net adverse environmental effects to the aquatic environment of the
proposed activity are minimal. The compensatory mitigation proposal may
be either conceptual or detailed. If the district engineer determines
that the activity complies with the terms and conditions of the NWP and
that the adverse effects on the aquatic environment are minimal, after
considering mitigation, the district engineer will notify the permittee
and include any activity-specific conditions in the NWP verification
the district engineer deems necessary. Conditions for compensatory
mitigation requirements must comply with the appropriate provisions at
33 CFR 332.3(k). The district engineer must approve the final
mitigation plan before the permittee commences work in waters of the
United States, unless the district engineer determines that prior
approval of the final mitigation plan is not practicable or not
necessary to ensure timely completion of the required compensatory
mitigation. If the prospective permittee elects to submit a
compensatory mitigation plan with the PCN, the district engineer will
expeditiously review the proposed compensatory mitigation plan. The
district engineer must review the proposed compensatory mitigation plan
within 45 calendar days of receiving a complete PCN and determine
whether the proposed mitigation would ensure no more than minimal
adverse effects on the aquatic environment. If the net adverse effects
of the project on the aquatic environment (after consideration of the
compensatory mitigation proposal) are determined by the district
engineer to be minimal, the district engineer will provide a timely
written response to the applicant. The response will state that the
project can proceed under the terms and conditions of the NWP,
including any activity-specific conditions added to the NWP
authorization by the district engineer.
3. If the district engineer determines that the adverse effects of
the proposed work are more than minimal, then the district engineer
will notify the applicant either: (a) That the project does not qualify
for authorization under the NWP and instruct the applicant on the
procedures to seek authorization under an individual permit; (b) that
the project is authorized under the NWP subject to the applicant's
submission of a mitigation plan that would reduce the adverse effects
on the aquatic environment to the minimal level; or (c) that the
project is authorized under the NWP with specific modifications or
conditions. Where the district engineer determines that mitigation is
required to ensure no more than minimal adverse effects occur to the
aquatic environment, the activity will be authorized within the 45-day
PCN period, with activity-specific conditions that state the mitigation
requirements. The authorization will include the necessary conceptual
or detailed mitigation or a requirement that the applicant submit a
mitigation plan that would reduce the adverse effects on the aquatic
environment to the minimal level. When mitigation is required, no work
in waters of the United States may occur until the district engineer
has approved a specific mitigation plan or has determined that prior
approval of a final mitigation plan is not practicable or not necessary
to ensure timely completion of the required compensatory mitigation.
E. Further Information
1. District Engineers have authority to determine if an activity
complies with the terms and conditions of an NWP.
2. NWPs do not obviate the need to obtain other federal, state, or
local permits, approvals, or authorizations required by law.
3. NWPs do not grant any property rights or exclusive privileges.
4. NWPs do not authorize any injury to the property or rights of
others.
5. NWPs do not authorize interference with any existing or proposed
Federal project.
F. Definitions
Best management practices (BMPs): Policies, practices, procedures,
or structures implemented to mitigate the adverse environmental effects
on surface water quality resulting from development. BMPs are
categorized as structural or non-structural.
Compensatory mitigation: The restoration (re-establishment or
rehabilitation), establishment (creation), enhancement, and/or in
certain circumstances preservation of aquatic resources for the
purposes of offsetting unavoidable adverse impacts which remain after
all appropriate and practicable avoidance and minimization has been
achieved.
Currently serviceable: Useable as is or with some maintenance, but
not so degraded as to essentially require reconstruction.
Direct effects: Effects that are caused by the activity and occur
at the same time and place.
Discharge: The term ``discharge'' means any discharge of dredged or
fill material.
Enhancement: The manipulation of the physical, chemical, or
biological characteristics of an aquatic resource to heighten,
intensify, or improve a specific aquatic resource function(s).
Enhancement results in the gain of selected aquatic resource
function(s), but may also lead to a decline in other aquatic resource
function(s). Enhancement does not result in a gain in aquatic resource
area.
Ephemeral stream: An ephemeral stream has flowing water only
during, and for a short duration after, precipitation events in a
typical year. Ephemeral stream beds are located above the water table
year-round. Groundwater is not a source of water for the stream. Runoff
from rainfall is the primary source of water for stream flow.
Establishment (creation): The manipulation of the physical,
chemical, or biological characteristics present to develop an aquatic
resource that did not previously exist at an upland site. Establishment
results in a gain in aquatic resource area.
High Tide Line: The line of intersection of the land with the
water's surface at the maximum height reached by a rising tide. The
high tide line may be determined, in the absence of actual data, by a
line of oil or scum along shore objects, a more or less continuous
deposit of fine shell or debris on the foreshore or berm, other
physical markings or characteristics, vegetation lines, tidal gages, or
other suitable means that delineate the general height reached by a
rising tide. The line encompasses spring high tides and other high
tides that occur with periodic frequency but does not include storm
surges in which there is a departure from the normal or predicted reach
of
[[Page 10289]]
the tide due to the piling up of water against a coast by strong winds
such as those accompanying a hurricane or other intense storm.
Historic Property: Any prehistoric or historic district, site
(including archaeological site), building, structure, or other object
included in, or eligible for inclusion in, the National Register of
Historic Places maintained by the Secretary of the Interior. This term
includes artifacts, records, and remains that are related to and
located within such properties. The term includes properties of
traditional religious and cultural importance to an Indian tribe or
Native Hawaiian organization and that meet the National Register
criteria (36 CFR part 60).
Independent utility: A test to determine what constitutes a single
and complete non-linear project in the Corps regulatory program. A
project is considered to have independent utility if it would be
constructed absent the construction of other projects in the project
area. Portions of a multi-phase project that depend upon other phases
of the project do not have independent utility. Phases of a project
that would be constructed even if the other phases were not built can
be considered as separate single and complete projects with independent
utility.
Indirect effects: Effects that are caused by the activity and are
later in time or farther removed in distance, but are still reasonably
foreseeable.
Intermittent stream: An intermittent stream has flowing water
during certain times of the year, when groundwater provides water for
stream flow. During dry periods, intermittent streams may not have
flowing water. Runoff from rainfall is a supplemental source of water
for stream flow.
Loss of waters of the United States: Waters of the United States
that are permanently adversely affected by filling, flooding,
excavation, or drainage because of the regulated activity. Permanent
adverse effects include permanent discharges of dredged or fill
material that change an aquatic area to dry land, increase the bottom
elevation of a waterbody, or change the use of a waterbody. The acreage
of loss of waters of the United States is a threshold measurement of
the impact to jurisdictional waters for determining whether a project
may qualify for an NWP; it is not a net threshold that is calculated
after considering compensatory mitigation that may be used to offset
losses of aquatic functions and services. The loss of stream bed
includes the linear feet of stream bed that is filled or excavated.
Waters of the United States temporarily filled, flooded, excavated, or
drained, but restored to pre-construction contours and elevations after
construction, are not included in the measurement of loss of waters of
the United States. Impacts resulting from activities eligible for
exemptions under Section 404(f) of the Clean Water Act are not
considered when calculating the loss of waters of the United States.
Non-tidal wetland: A non-tidal wetland is a wetland that is not
subject to the ebb and flow of tidal waters. The definition of a
wetland can be found at 33 CFR 328.3(b). Non-tidal wetlands contiguous
to tidal waters are located landward of the high tide line (i.e.,
spring high tide line).
Open water: For purposes of the NWPs, an open water is any area
that in a year with normal patterns of precipitation has water flowing
or standing above ground to the extent that an ordinary high water mark
can be determined. Aquatic vegetation within the area of standing or
flowing water is either non-emergent, sparse, or absent. Vegetated
shallows are considered to be open waters. Examples of ``open waters''
include rivers, streams, lakes, and ponds.
Ordinary High Water Mark: An ordinary high water mark is a line on
the shore established by the fluctuations of water and indicated by
physical characteristics, or by other appropriate means that consider
the characteristics of the surrounding areas (see 33 CFR 328.3(e)).
Perennial stream: A perennial stream has flowing water year-round
during a typical year. The water table is located above the stream bed
for most of the year. Groundwater is the primary source of water for
stream flow. Runoff from rainfall is a supplemental source of water for
stream flow.
Practicable: Available and capable of being done after taking into
consideration cost, existing technology, and logistics in light of
overall project purposes.
Pre-construction notification: A request submitted by the project
proponent to the Corps for confirmation that a particular activity is
authorized by nationwide permit. The request may be a permit
application, letter, or similar document that includes information
about the proposed work and its anticipated environmental effects. Pre-
construction notification may be required by the terms and conditions
of a nationwide permit, or by regional conditions. A pre-construction
notification may be voluntarily submitted in cases where pre-
construction notification is not required and the project proponent
wants confirmation that the activity is authorized by nationwide
permit.
Preservation: The removal of a threat to, or preventing the decline
of, aquatic resources by an action in or near those aquatic resources.
This term includes activities commonly associated with the protection
and maintenance of aquatic resources through the implementation of
appropriate legal and physical mechanisms. Preservation does not result
in a gain of aquatic resource area or functions.
Re-establishment: The manipulation of the physical, chemical, or
biological characteristics of a site with the goal of returning
natural/historic functions to a former aquatic resource. Re-
establishment results in rebuilding a former aquatic resource and
results in a gain in aquatic resource area and functions.
Rehabilitation: The manipulation of the physical, chemical, or
biological characteristics of a site with the goal of repairing
natural/historic functions to a degraded aquatic resource.
Rehabilitation results in a gain in aquatic resource function, but does
not result in a gain in aquatic resource area.
Restoration: The manipulation of the physical, chemical, or
biological characteristics of a site with the goal of returning
natural/historic functions to a former or degraded aquatic resource.
For the purpose of tracking net gains in aquatic resource area,
restoration is divided into two categories: re-establishment and
rehabilitation.
Riffle and pool complex: Riffle and pool complexes are special
aquatic sites under the 404(b)(1) Guidelines. Riffle and pool complexes
sometimes characterize steep gradient sections of streams. Such stream
sections are recognizable by their hydraulic characteristics. The rapid
movement of water over a course substrate in riffles results in a rough
flow, a turbulent surface, and high dissolved oxygen levels in the
water. Pools are deeper areas associated with riffles. A slower stream
velocity, a streaming flow, a smooth surface, and a finer substrate
characterize pools.
Riparian areas: Riparian areas are lands adjacent to streams,
lakes, and estuarine-marine shorelines. Riparian areas are transitional
between terrestrial and aquatic ecosystems, through which surface and
subsurface hydrology connects riverine, lacustrine, estuarine, and
marine waters with their adjacent wetlands, non-wetland waters, or
uplands. Riparian areas provide a variety of ecological functions and
services and help improve or maintain local water quality. (See general
condition 23.)
[[Page 10290]]
Shellfish seeding: The placement of shellfish seed and/or suitable
substrate to increase shellfish production. Shellfish seed consists of
immature individual shellfish or individual shellfish attached to
shells or shell fragments (i.e., spat on shell). Suitable substrate may
consist of shellfish shells, shell fragments, or other appropriate
materials placed into waters for shellfish habitat.
Single and complete linear project: A linear project is a project
constructed for the purpose of getting people, goods, or services from
a point of origin to a terminal point, which often involves multiple
crossings of one or more waterbodies at separate and distant locations.
The term ``single and complete project'' is defined as that portion of
the total linear project proposed or accomplished by one owner/
developer or partnership or other association of owners/developers that
includes all crossings of a single water of the United States (i.e., a
single waterbody) at a specific location. For linear projects crossing
a single or multiple waterbodies several times at separate and distant
locations, each crossing is considered a single and complete project
for purposes of NWP authorization. However, individual channels in a
braided stream or river, or individual arms of a large, irregularly
shaped wetland or lake, etc., are not separate waterbodies, and
crossings of such features cannot be considered separately.
Single and complete non-linear project: For non-linear projects,
the term ``single and complete project'' is defined at 33 CFR 330.2(i)
as the total project proposed or accomplished by one owner/developer or
partnership or other association of owners/developers. A single and
complete non-linear project must have independent utility (see
definition of ``independent utility''). Single and complete non-linear
projects may not be ``piecemealed'' to avoid the limits in an NWP
authorization.
Stormwater management: Stormwater management is the mechanism for
controlling stormwater runoff for the purposes of reducing downstream
erosion, water quality degradation, and flooding and mitigating the
adverse effects of changes in land use on the aquatic environment.
Stormwater management facilities: Stormwater management facilities
are those facilities, including but not limited to, stormwater
retention and detention ponds and best management practices, which
retain water for a period of time to control runoff and/or improve the
quality (i.e., by reducing the concentration of nutrients, sediments,
hazardous substances and other pollutants) of stormwater runoff.
Stream bed: The substrate of the stream channel between the
ordinary high water marks. The substrate may be bedrock or inorganic
particles that range in size from clay to boulders. Wetlands contiguous
to the stream bed, but outside of the ordinary high water marks, are
not considered part of the stream bed.
Stream channelization: The manipulation of a stream's course,
condition, capacity, or location that causes more than minimal
interruption of normal stream processes. A channelized stream remains a
water of the United States.
Structure: An object that is arranged in a definite pattern of
organization. Examples of structures include, without limitation, any
pier, boat dock, boat ramp, wharf, dolphin, weir, boom, breakwater,
bulkhead, revetment, riprap, jetty, artificial island, artificial reef,
permanent mooring structure, power transmission line, permanently
moored floating vessel, piling, aid to navigation, or any other manmade
obstacle or obstruction.
Tidal wetland: A tidal wetland is a wetland (i.e., water of the
United States) that is inundated by tidal waters. The definitions of a
wetland and tidal waters can be found at 33 CFR 328.3(b) and 33 CFR
328.3(f), respectively. Tidal waters rise and fall in a predictable and
measurable rhythm or cycle due to the gravitational pulls of the moon
and sun. Tidal waters end where the rise and fall of the water surface
can no longer be practically measured in a predictable rhythm due to
masking by other waters, wind, or other effects. Tidal wetlands are
located channelward of the high tide line, which is defined at 33 CFR
328.3(d).
Vegetated shallows: Vegetated shallows are special aquatic sites
under the 404(b)(1) Guidelines. They are areas that are permanently
inundated and under normal circumstances have rooted aquatic
vegetation, such as seagrasses in marine and estuarine systems and a
variety of vascular rooted plants in freshwater systems.
Waterbody: For purposes of the NWPs, a waterbody is a
jurisdictional water of the United States. If a jurisdictional wetland
is adjacent--meaning bordering, contiguous, or neighboring--to a
waterbody determined to be a water of the United States under 33 CFR
328.3(a)(1)-(6), that waterbody and its adjacent wetlands are
considered together as a single aquatic unit (see 33 CFR 328.4(c)(2)).
Examples of ``waterbodies'' include streams, rivers, lakes, ponds, and
wetlands.
[FR Doc. 2012-3687 Filed 2-17-12; 8:45 am]
BILLING CODE 3720-58-P