During the first phase of the
temporary deviation, the SR127 Bridge
may remain in the closed position from
February 15, 2012 through March 8,
2012, to replace bridge stringers. At the
end of the first phase the bridge will
return to its regular operating schedule.
During the second phase of the
temporary deviation, the bridge may
remain in the closed position from
March 12, 2012 through April 10, 2012,
to rehabilitate the bridge operating
machinery. At the end of the second
phase the bridge will return to its
regular operating schedule.
The Gloucester Harbor Master and the
local marinas were notified and no
objections were received.
In accordance with 33 CFR 117.35(e),
the bridge must return to its regular
operating schedule immediately at the
end of the designated time periods. This
deviation from the operating regulations
is authorized under 33 CFR 117.35.
Dated: January 25, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard
District.
[FR Doc. 2012–2780 Filed 2–6–12; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[USCG–2012–0017]
Drawbridge Operation Regulations;
Cheesequake Creek, Morgan, NJ
Coast Guard, DHS.
Notice of temporary deviation
from regulations.
AGENCY:
ACTION:
The Commander, First Coast
Guard District, has issued a temporary
deviation from the regulation governing
the operation of the New Jersey Transit
Rail Operation (NJTRO) Railroad Bridge
across Cheesequake Creek, mile 0.2, at
Morgan, New Jersey. Under this
temporary deviation, the bridge may
remain in the closed position for four
days to facilitate scheduled bridge
repairs.
srobinson on DSK4SPTVN1PROD with RULES
SUMMARY:
This deviation is effective from
6 a.m. on February 11, 2012 through 12
p.m. on March 4, 2012.
ADDRESSES: Documents mentioned in
this preamble as being available in the
docket are part of docket USCG–2012–
0017 and are available online at
www.regulations.gov, inserting USCG–
DATES:
VerDate Mar<15>2010
15:59 Feb 06, 2012
Jkt 226001
2012–0017 in the ‘‘Keyword’’ and then
clicking ‘‘Search’’. They are also
available for inspection or copying at
the Docket Management Facility (M–30),
U.S. Department of Transportation,
West Building Ground Floor, Room
W12–140, 1200 New Jersey Avenue SE.,
Washington, DC, 20590, between 9 a.m.
and 5 p.m., Monday through Friday,
except Federal holidays.
If
you have questions on this rule, call or
email Mr. Joe Arca, Project Officer, First
Coast Guard District,
joe.m.arca@uscg.mil, or (212) 668–7165.
If you have questions on viewing the
docket, call Renee V. Wright, Program
Manager, Docket Operations, telephone
202–366–9826.
FOR FURTHER INFORMATION CONTACT:
SUPPLEMENTARY INFORMATION:
The NJTRO railroad bridge has a
vertical clearance of 3 feet at mean high
water, and 8 feet at mean low water in
the closed position. The existing
drawbridge operating regulations are
found at 33 CFR 117.709(b).
The bridge owner, New Jersey Transit
Rail Operations (NJTRO), requested a
bridge closure to facilitate structural
track repairs at the bridge.
Under this temporary deviation, the
NJTRO railroad bridge may remain in
the closed position on two weekends
from 6 a.m. on February 11, 2012
through 12 noon on February 12, 2012
and from 6 a.m. on February 25, 2012
through 12 noon on February 26, 2012.
In the event of inclement weather the
above repairs will be undertaken on two
alternate weekends from 6 a.m. on
February 25, 2012 through 12 noon on
February 26, 2012 and from 6 a.m. on
March 3, 2012 through 12 noon on
March 4, 2012.
Cheesequake Creek is predominantly
a recreational waterway. The bridge
rarely opens in the winter months when
this temporary deviation will be in
effect.
In accordance with 33 CFR 117.35(e),
the bridge must return to its regular
operating schedule immediately at the
end of the designated repair period.
This deviation from the operating
regulations is authorized under 33 CFR
117.35.
Dated: January 25, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard
District.
[FR Doc. 2012–2778 Filed 2–6–12; 8:45 am]
BILLING CODE 9110–04–P
PO 00000
Frm 00027
Fmt 4700
Sfmt 4700
6013
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 165
[Docket No. USCG–2011–1063]
RIN 1625–AA87
Moving Security Zone Around
Escorted Vessels On the Lower
Mississippi River Between Mile Marker
90.0 Above Head of Passes to Mile
Marker 110.0 Above Head of Passes
Coast Guard, DHS.
Temporary final rule.
AGENCY:
ACTION:
The Captain of the Port of
New Orleans (COTP New Orleans) has
established moving security zones on
the Mississippi River, from mile marker
90 through mile marker 110, extending
300 yards on all sides of vessels being
escorted by one or more Coast Guard
assets or other federal, state, or local law
enforcement agency assets clearly
identifiable by lights, vessel markings,
or with agency insignia. This moving
security zone regulation is necessary to
protect vessels deemed to be in need of
escort protection by the COTP New
Orleans for security reasons. No person
or vessel is permitted to enter or transit
the security zones created by this
temporary rule without permission of
the COTP New Orleans.
DATES: This rule is effective from
January 1, 2012, through March 31,
2012.
SUMMARY:
Documents indicated in this
preamble as being available in the
docket are part of docket USCG–2011–
1063 and are available online by going
to https://www.regulations.gov, inserting
USCG–2011–1063 in the ‘‘Keyword’’
box, and then clicking ‘‘Search.’’ They
are also available for inspection or
copying at the Docket Management
Facility (M–30), U.S. Department of
Transportation, West Building Ground
Floor, Room W12–140, 1200 New Jersey
Avenue SE., Washington, DC 20590,
between 9 a.m. and 5 p.m., Monday
through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
rule, call or email Lieutenant
Commander (LCDR) Kenneth Blair,
Sector New Orleans, Coast Guard;
telephone 504–365–2392, email
Kenneth.E.Blair@uscg.mil. If you have
questions on viewing the docket, call
Renee V. Wright, Program Manager,
Docket Operations, telephone (202)
366–9826.
SUPPLEMENTARY INFORMATION:
ADDRESSES:
E:\FR\FM\07FER1.SGM
07FER1
Agencies
[Federal Register Volume 77, Number 25 (Tuesday, February 7, 2012)]
[Rules and Regulations]
[Page 6013]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-2778]
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[USCG-2012-0017]
Drawbridge Operation Regulations; Cheesequake Creek, Morgan, NJ
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulations.
-----------------------------------------------------------------------
SUMMARY: The Commander, First Coast Guard District, has issued a
temporary deviation from the regulation governing the operation of the
New Jersey Transit Rail Operation (NJTRO) Railroad Bridge across
Cheesequake Creek, mile 0.2, at Morgan, New Jersey. Under this
temporary deviation, the bridge may remain in the closed position for
four days to facilitate scheduled bridge repairs.
DATES: This deviation is effective from 6 a.m. on February 11, 2012
through 12 p.m. on March 4, 2012.
ADDRESSES: Documents mentioned in this preamble as being available in
the docket are part of docket USCG-2012-0017 and are available online
at www.regulations.gov, inserting USCG-2012-0017 in the ``Keyword'' and
then clicking ``Search''. They are also available for inspection or
copying at the Docket Management Facility (M-30), U.S. Department of
Transportation, West Building Ground Floor, Room W12-140, 1200 New
Jersey Avenue SE., Washington, DC, 20590, between 9 a.m. and 5 p.m.,
Monday through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If you have questions on this rule,
call or email Mr. Joe Arca, Project Officer, First Coast Guard
District, joe.m.arca@uscg.mil, or (212) 668-7165. If you have questions
on viewing the docket, call Renee V. Wright, Program Manager, Docket
Operations, telephone 202-366-9826.
SUPPLEMENTARY INFORMATION:
The NJTRO railroad bridge has a vertical clearance of 3 feet at
mean high water, and 8 feet at mean low water in the closed position.
The existing drawbridge operating regulations are found at 33 CFR
117.709(b).
The bridge owner, New Jersey Transit Rail Operations (NJTRO),
requested a bridge closure to facilitate structural track repairs at
the bridge.
Under this temporary deviation, the NJTRO railroad bridge may
remain in the closed position on two weekends from 6 a.m. on February
11, 2012 through 12 noon on February 12, 2012 and from 6 a.m. on
February 25, 2012 through 12 noon on February 26, 2012.
In the event of inclement weather the above repairs will be
undertaken on two alternate weekends from 6 a.m. on February 25, 2012
through 12 noon on February 26, 2012 and from 6 a.m. on March 3, 2012
through 12 noon on March 4, 2012.
Cheesequake Creek is predominantly a recreational waterway. The
bridge rarely opens in the winter months when this temporary deviation
will be in effect.
In accordance with 33 CFR 117.35(e), the bridge must return to its
regular operating schedule immediately at the end of the designated
repair period. This deviation from the operating regulations is
authorized under 33 CFR 117.35.
Dated: January 25, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.