Liberty Energy (Midstates) Corp.; Notice of Application, 2964-2965 [2012-1079]
Download as PDF
2964
Federal Register / Vol. 77, No. 13 / Friday, January 20, 2012 / Notices
revisions.4 Revised Reliability Standard,
NUC–001–2, was filed with the
Commission by NERC in August 2009
and subsequently approved by the
Commission January 21, 2010.5
The purpose of Reliability Standard
NUC–001–2 is to require ‘‘coordination
between nuclear plant generator
operators and transmission entities for
the purpose of ensuring nuclear plant
safe operation and shutdown.’’ 6 The
Nuclear Reliability Standard applies to
nuclear plant generator operators
(generally nuclear power plant owners
and operators, including licensees) and
‘‘transmission entities,’’ defined in the
Reliability Standard as including a
FERC data collection
FERC–725F
(OMB Control No. 1902–0249)
nuclear plant’s suppliers of off-site
power and related transmission and
distribution services. To account for the
variations in nuclear plant design and
grid interconnection characteristics, the
Reliability Standard defines
transmission entities as ‘‘all entities that
are responsible for providing services
related to Nuclear Plant Interface
Requirements (NPIRs),’’ and lists eleven
types of functional entities (heretofore
described as ‘‘transmission entities’’)
that could provide services related to
NPIRs.7
Reliability Standard NUC–001–2
requires a nuclear power plant operator
and its suppliers of back-up power and
related transmission and distribution
services to coordinate concerning
nuclear licensing requirements for safe
nuclear plant operation and shutdown
and system operating limits.
Information collection requirements
include establishing and maintaining
interface agreements, including record
retention requirements.
Type of Respondents: e.g. nuclear
operators, nuclear plants, transmission
entities
Estimate of Annual Burden: 8 The
Commission estimates the Public
Reporting Burden for this information
collection as:
Number of responses
(Documents)
Average burden hours per
response
Total annual
burden hours
(1)
New agreements .....................
Number of respondents
annually
(2)
(3)
(1)*(2)*(3)
1 ............................................
Reporting: 1,080 ....................
Reporting:
32,400
Recordkeeping:
3,240
10 nuclear operators + 20
transmission entities.
Recordkeeping: 108 ..............
Modifications to agreements ...
Total .................................
65 nuclear plants + 130
transmission entities 9.
................................................
2 ............................................
Reporting: 67 (rounded) ........
................................................
Recordkeeping: 7 (rounded)
Reporting:
26,000
Recordkeeping:
2,600
Not applicable (see text for
discussion).
Not applicable ........................
Not applicable .......................
64,240
wreier-aviles on DSK5TPTVN1PROD with NOTICES
The Commission estimates the total
annual cost burden to respondents as:
• 58,400 Reporting hours × $120/
hour 10 = $7,008,000.
• 5,840 Recordkeeping hours × $28/
hour 11 = $163,520 (plus the record
storage cost: 143 entities × $15.25/year
per entity 12 = $2,181 (rounded)
Total annual cost burden to
respondents = $7,173,701.
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
4 Mandatory Reliability Standard for Nuclear
Plant Interface Coordination, Order No. 716, 125
FERC ¶ 61,065, at P 189 & n.90 (2008), order on
reh’g, Order No. 716–A, 126 FERC ¶ 61,122 (2009).
5 North American Electric Reliability Corporation,
130 FERC ¶ 61,051 (2010). When the revised
Reliability Standard was approved the Commission
did not go to OMB for approval. It is assumed that
the changes made did not substantively affect the
information collection and therefore a formal
submission to OMB was not needed.
6 See Reliability Standard NUC–001–2 at https://
www.nerc.com/files/NUC–001–2.pdf.
7 The list of functional entities consists of
transmission operators, transmission owners,
transmission planners, transmission service
providers, balancing authorities, reliability
coordinators, planning authorities, distribution
providers, load-serving entities, generator owners
and generator operators.
8 Burden is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
information to or for a Federal agency. For further
explanation of what is included in the information
collection burden, reference 5 Code of Federal
Regulations 1320.3.
9 This figure of 130 transmission entities is based
on the assumption that each agreement will be
between 1 nuclear plant and 2 transmission entities
(65 times 2 = 130). However, there is some double
counting in this figure because some transmission
entities may be party to multiple agreements with
multiple nuclear plants. The double counting does
VerDate Mar<15>2010
14:12 Jan 19, 2012
Jkt 226001
Dated: January 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–1070 Filed 1–19–12; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–41–000]
Liberty Energy (Midstates) Corp.;
Notice of Application
Take notice that on January 4, 2012,
Liberty Energy (Midstates) Corp.
(Liberty Midstates), 2845 Bristol Circle,
Oakville, Ontario, Canada L6H 7H7,
filed in Docket No. CP12–41–000, an
application pursuant to section 7(f) of
the Natural Gas Act (NGA) requesting
the determination of a service area 1
not affect the burden estimate and the correct
number of unique respondents will be reported to
OMB.
10 The $120/hour figure is a combined average of
legal, technical and administrative staff.
11 The $28/hour figure is based on a FERC staff
study that included estimating public utility
recordkeeping costs.
12 This is based on the estimated cost to service
and store 1 GB of data (based on the aggregated cost
of an IBM advanced data protection server).
1 Liberty Midstates states that it seeks a service
area determination in order to provide natural gas
service to more than 65 Missouri communities via
the Missouri distribution facilities it would acquire
from Atmos Energy Corporation (Atmos). Liberty
Midstates would also acquire a 35-foot pipeline on
E:\FR\FM\20JAN1.SGM
20JAN1
wreier-aviles on DSK5TPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 13 / Friday, January 20, 2012 / Notices
within which Liberty Midstates may,
without further Commission
authorization, enlarge or expand its
natural gas distribution facilities.
Liberty Midstates also requests: (i) A
waiver of the Commission’s accounting
and reporting requirements and other
regulatory requirements ordinarily
applicable to natural gas companies
under the NGA and the NGPA; (ii)
pregranted abandonment of this service;
and (iii) such further relief the
Commission may deem appropriate, all
as more fully set forth in the
application, which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed to
William F. Demarest, Jr., Husch
Blackwell LLP, 750 17th St. NW., Suite
900, Washington, DC 20006, or at (202)
378–2310 (telephone) or email:
william.demarest@huschblackwell.com.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
the Kansas-Missouri border, which would enable
Liberty Midstates to receive natural gas volumes
from Atmos on behalf of its Missouri distribution
customers.
VerDate Mar<15>2010
14:12 Jan 19, 2012
Jkt 226001
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link.
Comment Date: February 2, 2012.
Dated: January 12, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–1079 Filed 1–19–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2821–011]
City of Portland, Oregon; Notice of
Application for Amendment of License
and Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Capacity
Amendment of License.
b. Project No.: 2821–011.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
2965
c. Date Filed: June 27, 2011, and
supplemented November 23, 2011, and
January 11, 2012.
d. Applicant: City of Portland,
Oregon.
e. Name of Project: Portland
Hydroelectric Project.
f. Location: Approximately 25 miles
east of the City of Portland, on the Bull
Run River, in Multnomah and
Clackamas Counties, Oregon.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Frank Galida,
Portland Hydroelectric Project Manager,
Portland Water Bureau, City of Portland,
Oregon, Room 530, 1120 SW 5th
Avenue, Portland, OR 97204, (503) 823–
7517, frank.galida@portlandoregon.gov.
i. FERC Contact: Christopher Chaney,
(202) 502–6778,
christopher.chaney@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance date of this
notice. All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–(866) 208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of proposed
amendment: The licensee proposes to
modify the North Tower intake at the
Dam No. 2 Development of the Portland
Project. A multi-level intake structure
would be added to the tower to allow
for the selective withdrawal of water
E:\FR\FM\20JAN1.SGM
20JAN1
Agencies
[Federal Register Volume 77, Number 13 (Friday, January 20, 2012)]
[Notices]
[Pages 2964-2965]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-1079]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP12-41-000]
Liberty Energy (Midstates) Corp.; Notice of Application
Take notice that on January 4, 2012, Liberty Energy (Midstates)
Corp. (Liberty Midstates), 2845 Bristol Circle, Oakville, Ontario,
Canada L6H 7H7, filed in Docket No. CP12-41-000, an application
pursuant to section 7(f) of the Natural Gas Act (NGA) requesting the
determination of a service area \1\
[[Page 2965]]
within which Liberty Midstates may, without further Commission
authorization, enlarge or expand its natural gas distribution
facilities. Liberty Midstates also requests: (i) A waiver of the
Commission's accounting and reporting requirements and other regulatory
requirements ordinarily applicable to natural gas companies under the
NGA and the NGPA; (ii) pregranted abandonment of this service; and
(iii) such further relief the Commission may deem appropriate, all as
more fully set forth in the application, which is on file with the
Commission and open to public inspection. The filing may also be viewed
on the web at https://www.ferc.gov using the ``eLibrary'' link. Enter
the docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
---------------------------------------------------------------------------
\1\ Liberty Midstates states that it seeks a service area
determination in order to provide natural gas service to more than
65 Missouri communities via the Missouri distribution facilities it
would acquire from Atmos Energy Corporation (Atmos). Liberty
Midstates would also acquire a 35-foot pipeline on the Kansas-
Missouri border, which would enable Liberty Midstates to receive
natural gas volumes from Atmos on behalf of its Missouri
distribution customers.
---------------------------------------------------------------------------
Any questions regarding this application should be directed to
William F. Demarest, Jr., Husch Blackwell LLP, 750 17th St. NW., Suite
900, Washington, DC 20006, or at (202) 378-2310 (telephone) or email:
william.demarest@huschblackwell.com.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site under the ``e-Filing''
link.
Comment Date: February 2, 2012.
Dated: January 12, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-1079 Filed 1-19-12; 8:45 am]
BILLING CODE 6717-01-P