BOST5 Hydroelectric Company, LLC, (BOST5); Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests, 785-786 [2012-5]
Download as PDF
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
c. Submission of Paper Applications by
Hand Delivery
If you submit your new application or
revisions to a previously submitted
application by hand delivery, you (or a
courier service) must deliver the
original and two copies of your new
application or revisions to a previously
submitted application by hand, on or
before the application deadline date, to
the Department at the following address:
U.S. Department of Education,
Application Control Center, Attention:
(CFDA Number: 84.372A), 550 12th
Street SW., Room 7041, Potomac Center
Plaza, Washington, DC 20202–4260. The
Application Control Center accepts
hand deliveries daily between 8 a.m.
and 4:30 p.m., Washington, DC time,
except Saturdays, Sundays, and Federal
holidays.
Note for Mail or Hand Delivery of Paper
Applications: If you mail or hand deliver
your new application or revisions to a
previously submitted application to the
Department—
(1) You must indicate on the envelope—if
not provided by the Department—in Item 11
of the SF 424 the CFDA number, including
suffix letter, if any, of the competition under
which you are submitting your application;
and
(2) The Application Control Center will
mail to you a notification of receipt of your
grant application. If you do not receive this
notification within 15 business days from the
application deadline date, you should call
the U.S. Department of Education
Application Control Center at (202) 245–
6288.
pmangrum on DSK3VPTVN1PROD with NOTICES
FOR FURTHER INFORMATION CONTACT:
Emily Anthony, U.S. Department of
Education, National Center for
Education Statistics, 1990 K Street NW.,
room 9083, Washington, DC 20006–
5651. Telephone: (202) 502–7495 or via
Internet: Emily.Anthony@ed.gov.
If you use a telecommunications
device for the deaf (TDD), call the
Federal Relay Service (FRS), toll-free, at
1–(800) 877–8339. Individuals with
disabilities may obtain this notice in an
accessible format (e.g., braille, large
print, audiotape, or computer diskette)
on request to the contact person listed
in this section.
Electronic Access to This Document:
The official version of this document is
the document published in the Federal
Register. Free Internet access to the
official edition of the Federal Register is
available via the Federal Digital System
at https://www.gpo.gov/fdsys. At this site
you can view this document, as well as
all other documents of this Department
published in the Federal Register, in
text or Adobe Portable Document
Format (PDF). To use PDF you must
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
have Adobe Acrobat Reader, which is
available free at this site.
You may also access documents of the
Department published in the Federal
Register by using the article search
feature at https://www.federalregister.
gov. Specifically, through the advanced
search feature at this site, you can limit
your search to documents published by
the Department.
Program Authority: 20 U.S.C. 9607.
Dated: January 3, 2012.
John Q. Easton,
Director, Institute of Education Sciences.
[FR Doc. 2012–76 Filed 1–5–12; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12758–003]
BOST5 Hydroelectric Company, LLC,
(BOST5); Notice of Application
Accepted for Filing and Soliciting
Motions To Intervene and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12758–003.
c. Date filed: March 28, 2011.
d. Applicant: BOST5 Hydroelectric
Company, LLC (BOST5).
e. Name of Project: Red River Lock &
Dam No. 5 Hydroelectric Project.
f. Location: The proposed project
would be located at the existing Army
Corps of Engineer’s (Corps) Red River
Lock & Dam No. 5 on the Red River, in
Bassier Parish near the Town of Ninock,
Louisiana.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Douglas A.
Spalding, BOST5 Hydroelectric
Company, LLC, 8441 Wayzata Blvd.,
Suite 101, Golden Valley, MN 55426;
(952) 544–8133.
i. FERC Contact: Jeanne Edwards
(202) 502–6181, or by email at
jeanne.edwards@ferc.gov.
j. Deadline for filing motions to
intervene and protests: 60 days from the
issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
PO 00000
Frm 00011
Fmt 4703
Sfmt 4703
785
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, or toll
free at 1–(866) 208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedures require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing, but is not ready for
environmental analysis at this time.
l. The proposed project would utilize
the existing U.S. Army Corps of
Engineers (Corps) Red River Lock and
Dam No. 5, and operate consistent with
the Corps current operation policy. The
proposed project would consist of: (1)
An excavated 416-foot-long headrace
channel to convey water from the
upstream Pool No. 5 of the Red River to
a 301-foot-long by 90-foot-wide concrete
powerhouse located northeast of the end
of the existing overflow weir; (2) an
excavated 495-foot-long tailrace channel
to discharge water from the powerhouse
to the downstream Pool No. 4 of the Red
River; (3) one 28.1-megawatt (MW)
horizontal Kaplan bulb turbine/
generator unit; (4) one 7-mile-long, 34.5kilovolt (kV) overhead transmission line
leading from the project’s powerhouse
and connecting to Central Louisiana
Electric Company’s new substation; and
(5) appurtenant facilities. The proposed
project would generate about 129,400
megawatt-hours (MWh) annually which
would be sold to a local utility.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
E:\FR\FM\06JAN1.SGM
06JAN1
pmangrum on DSK3VPTVN1PROD with NOTICES
786
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application,
or a notice of intent to file such an
application. Submission of a timely
notice of intent allows an interested
person to file the competing
development application no later than
120 days after the specified intervention
deadline date. Applications for
preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
unequivocal statement of intent to
submit a development application. A
notice of intent must be served on the
applicant(s) named in this public notice.
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
When the application is ready for
environmental analysis, the
Commission will issue a public notice
requesting comments,
recommendations, terms and
conditions, or prescriptions.
All filings must (1) Bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE,’’ ‘‘NOTICE
OF INTENT TO FILE COMPETING
APPLICATION,’’ or ‘‘COMPETING
APPLICATION;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. Agencies
may obtain copies of the application
directly from the applicant. A copy of
any protest or motion to intervene must
be served upon each representative of
the applicant specified in the particular
application.
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
Dated: December 29, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–5 Filed 1–5–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12757–003
BOST4 Hydroelectric Company, LLC,
(BOST4); Notice of Application
Accepted for Filing and Soliciting
Motions To Intervene and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12757–003.
c. Date filed: February 24, 2011.
d. Applicant: BOST4 Hydroelectric
Company, LLC (BOST4).
e. Name of Project: Red River Lock &
Dam No. 4 Hydroelectric Project.
f. Location: The proposed project
would be located at the existing Army
Corps of Engineer’s (Corps) Red River
Lock & Dam No. 4 on the Red River, in
Red River Parish near the Town of
Coushatta, Louisiana.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Mr. Douglas A.
Spalding, BOST4 Hydroelectric
Company, LLC, 8441 Wayzata Blvd.,
Suite 101, Golden Valley, MN 55426;
(952) 544–8133.
i. FERC Contact: Jeanne Edwards
(202) 502–6181, or by email at jeanne.
edwards@ferc.gov.
j. Deadline for filing motions to
intervene and protests: 60 days from the
issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://www.ferc.
gov/docs-filing/ecomment.asp. You
must include your name and contact
information at the end of your
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, or toll
free at 1–(866) 208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
PO 00000
Frm 00012
Fmt 4703
Sfmt 4703
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedures require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing, but is not ready for
environmental analysis at this time.
l. The proposed project would utilize
the existing U.S. Army Corps of
Engineers (Corps) Red River Lock and
Dam No. 4, and operate consistent with
the Corps current operation policy. The
proposed project would consist of: (1)
An excavated 385-foot-long headrace
channel to convey water from the
upstream Pool No. 4 of the Red River to
a 301-foot-long by 90-foot-wide concrete
powerhouse located southwest of the
end of the existing overflow weir; (2) an
excavated 477-foot-long tailrace channel
to discharge water from the powerhouse
to the downstream Pool No. 3 of the Red
River; (3) one 28.1-megawatt (MW)
horizontal Kaplan bulb turbine/
generator unit; (4) one 3.0 mile-long,
34.5-kilovolt (kV) overhead
transmission line leading from a project
substation located at the project’s
powerhouse and connecting to Central
Louisiana Electric Company’s existing
34.5-kV transmission line; and (5)
appurtenant facilities. The proposed
project would generate about 128,532
megawatt-hours (MWh) annually which
would be sold to a local utility.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
E:\FR\FM\06JAN1.SGM
06JAN1
Agencies
[Federal Register Volume 77, Number 4 (Friday, January 6, 2012)]
[Notices]
[Pages 785-786]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-5]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12758-003]
BOST5 Hydroelectric Company, LLC, (BOST5); Notice of Application
Accepted for Filing and Soliciting Motions To Intervene and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: P-12758-003.
c. Date filed: March 28, 2011.
d. Applicant: BOST5 Hydroelectric Company, LLC (BOST5).
e. Name of Project: Red River Lock & Dam No. 5 Hydroelectric
Project.
f. Location: The proposed project would be located at the existing
Army Corps of Engineer's (Corps) Red River Lock & Dam No. 5 on the Red
River, in Bassier Parish near the Town of Ninock, Louisiana.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Douglas A. Spalding, BOST5 Hydroelectric
Company, LLC, 8441 Wayzata Blvd., Suite 101, Golden Valley, MN 55426;
(952) 544-8133.
i. FERC Contact: Jeanne Edwards (202) 502-6181, or by email at
jeanne.edwards@ferc.gov.
j. Deadline for filing motions to intervene and protests: 60 days
from the issuance date of this notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, or toll free at 1-(866) 208-
3676, or for TTY, (202) 502-8659. Although the Commission strongly
encourages electronic filing, documents may also be paper-filed. To
paper-file, mail an original and seven copies to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426.
The Commission's Rules of Practice and Procedures require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application has been accepted for filing, but is not ready
for environmental analysis at this time.
l. The proposed project would utilize the existing U.S. Army Corps
of Engineers (Corps) Red River Lock and Dam No. 5, and operate
consistent with the Corps current operation policy. The proposed
project would consist of: (1) An excavated 416-foot-long headrace
channel to convey water from the upstream Pool No. 5 of the Red River
to a 301-foot-long by 90-foot-wide concrete powerhouse located
northeast of the end of the existing overflow weir; (2) an excavated
495-foot-long tailrace channel to discharge water from the powerhouse
to the downstream Pool No. 4 of the Red River; (3) one 28.1-megawatt
(MW) horizontal Kaplan bulb turbine/generator unit; (4) one 7-mile-
long, 34.5-kilovolt (kV) overhead transmission line leading from the
project's powerhouse and connecting to Central Louisiana Electric
Company's new substation; and (5) appurtenant facilities. The proposed
project would generate about 129,400 megawatt-hours (MWh) annually
which would be sold to a local utility.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
[[Page 786]]
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Any qualified applicant desiring to file a competing application
must submit to the Commission, on or before the specified intervention
deadline date, a competing development application, or a notice of
intent to file such an application. Submission of a timely notice of
intent allows an interested person to file the competing development
application no later than 120 days after the specified intervention
deadline date. Applications for preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the exact name, business address,
and telephone number of the prospective applicant, and must include an
unequivocal statement of intent to submit a development application. A
notice of intent must be served on the applicant(s) named in this
public notice.
Anyone may submit a protest or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210, 385.211, and 385.214. In determining the appropriate action to
take, the Commission will consider all protests filed, but only those
who file a motion to intervene in accordance with the Commission's
Rules may become a party to the proceeding. Any protests or motions to
intervene must be received on or before the specified deadline date for
the particular application.
When the application is ready for environmental analysis, the
Commission will issue a public notice requesting comments,
recommendations, terms and conditions, or prescriptions.
All filings must (1) Bear in all capital letters the title
``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in
the heading the name of the applicant and the project number of the
application to which the filing responds; (3) furnish the name,
address, and telephone number of the person protesting or intervening;
and (4) otherwise comply with the requirements of 18 CFR 385.2001
through 385.2005. Agencies may obtain copies of the application
directly from the applicant. A copy of any protest or motion to
intervene must be served upon each representative of the applicant
specified in the particular application.
Dated: December 29, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-5 Filed 1-5-12; 8:45 am]
BILLING CODE 6717-01-P