Draft Environmental Assessment and Draft Finding of No Significant Impact Related to the Proposed License Amendment To Increase the Maximum Reactor Power Level: Florida Power & Light Company, St. Lucie Plant, Units 1 and 2, 813-822 [2012-32]
Download as PDF
pmangrum on DSK3VPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
protection device. These labels will
warn miners not to change or alter the
sealed short-circuit settings.
(12) The haulage roads, locations of
trailing cable anchoring points, and
locations of the belt tailpiece or feeder
will be arranged to:
(a) Prevent the shuttle cars from
running over their trailing cables.
(b) Minimize the need for secondary
(temporary) trailing cable anchoring
points.
(c) Minimize back spooling.
(13) The alternative method will not
be implemented until all miners
designated to examine the integrity of
the seals and verify the short-circuit
settings have received task training in
the proper procedures for examining
trailing cables for defects and damage.
(14) Within 60 days after this
proposed decision and order becomes
final, the proposed revisions for the
petitioner’s approved 30 CFR part 48
training plan will be submitted to the
District Manager. The revisions will
specify task training for miners
designated to verify that the shortcircuit settings of the circuit
interrupting device(s) that protect the
affected trailing cables do not exceed
the specified setting(s). The training
plan will include the following:
(a) The hazards of setting the shortcircuit interrupting device(s) too high to
adequately protect the trailing cables.
(b) How to verify that the circuit
interrupting device(s) protecting the
trailing cable(s) are properly set and
maintained.
(c) Mining methods and operating
procedures that will protect the trailing
cable(s) against mechanical damage.
(d) Proper procedures for examining
the affected trailing cable(s) to ensure
that the cables are in safe operating
condition.
The petitioner further states that
procedures specified in 30 CFR 48.3 for
proposed revisions to already approved
training plans will apply.
The petitioner asserts that the
alternative method will provide at all
times a measure of protection for the
miners equal to or greater than that of
the existing standard.
Dated: December 30, 2011.
Patricia W. Silvey,
Certifying Officer.
[FR Doc. 2011–33861 Filed 1–5–12; 8:45 am]
BILLING CODE 4510–43–P
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–335 and 50–389; NRC–
2011–0302]
Draft Environmental Assessment and
Draft Finding of No Significant Impact
Related to the Proposed License
Amendment To Increase the Maximum
Reactor Power Level: Florida Power &
Light Company, St. Lucie Plant, Units
1 and 2
Nuclear Regulatory
Commission.
ACTION: Draft environmental assessment
and finding of no significant impact;
opportunity to comment.
AGENCY:
Comments must be filed by
February 6, 2012. Any potential party as
defined in Title 10 of the Code of
Federal Regulations (10 CFR) 2.4 who
believes access to Sensitive Unclassified
Non-Safeguards Information and/or
Safeguards Information is necessary to
respond to this notice must request
document access by January 17, 2012.
ADDRESSES: Please include Docket ID
NRC–2011–0302 in the subject line of
your comments. For additional
instructions on submitting comments
and instructions on accessing
documents related to this action, see
‘‘Submitting Comments and Accessing
Information’’ in the SUPPLEMENTARY
INFORMATION section of this document.
You may submit comments by any one
of the following methods:
• Federal Rulemaking Web Site: Go to
https://www.regulations.gov and search
for documents filed under Docket ID
NRC–2011–0302. Address questions
about NRC dockets to Carol Gallagher,
telephone: (301) 492–3668; email: Carol.
Gallagher@nrc.gov.
• Mail comments to: Cindy Bladey,
Chief, Rules, Announcements, and
Directives Branch (RADB), Office of
Administration, Mail Stop: TWB–05–
B01M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
• Fax comments to: RADB at (301)
492–3446.
SUPPLEMENTARY INFORMATION:
DATES:
Submitting Comments and Accessing
Information
Comments submitted in writing or in
electronic form will be posted on the
NRC Web site and on the Federal
rulemaking Web site, https://www.
regulations.gov. Because your comments
will not be edited to remove any
identifying or contact information, the
NRC cautions you against including any
information in your submission that you
do not want to be publicly disclosed.
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
813
The NRC requests that any party
soliciting or aggregating comments
received from other persons for
submission to the NRC inform those
persons that the NRC will not edit their
comments to remove any identifying or
contact information, and therefore, they
should not include any information in
their comments that they do not want
publicly disclosed.
You can access publicly available
documents related to this document
using the following methods:
• NRC’s Public Document Room
(PDR): The public may examine and
have copied, for a fee, publicly available
documents at the NRC’s PDR, O1–F21,
One White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): Publicly available documents
created or received at the NRC are
available online in the NRC Library at
https://www.nrc.gov/reading-rm/adams.
html. From this page, the public can
gain entry into ADAMS, which provides
text and image files of the NRC’s public
documents. If you do not have access to
ADAMS or if there are problems in
accessing the documents located in
ADAMS, contact the NRC’s PDR
reference staff at 1–(800) 397–4209,
(301) 415–4737, or by email to pdr.
resource@nrc.gov. The application for
amendment, dated November 22, 2010,
contains proprietary information and,
accordingly, those portions are being
withheld from public disclosure. A
redacted version of the application for
amendment, dated December 15, 2010,
is available electronically under
ADAMS Accession No. ML103560415.
• Federal Rulemaking Web Site:
Public comments and supporting
materials related to this notice can be
found at https://www.regulations.gov by
searching on Docket ID NRC–2011–
0302.
FOR FURTHER INFORMATION CONTACT:
Tracy Orf, Project Manager, Plant
Licensing Branch II–2, Division of
Operating Reactor Licensing, Office of
Nuclear Reactor Regulation, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001.
Telephone: (301) 415–2788; Fax
number: (301) 415–1222; email:
Tracy.Orf@nrc.gov.
I. Introduction
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of an amendment for Renewed
Facility Operating License Nos. DPR–67
and NPF–16, issued to Florida Power &
Light Company (FPL, the licensee) for
operation of St. Lucie Plant, Units 1 and
E:\FR\FM\06JAN1.SGM
06JAN1
814
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
pmangrum on DSK3VPTVN1PROD with NOTICES
2 (St. Lucie 1 and 2), for a license
amendment to increase the maximum
thermal power from 2,700 megawatts
thermal (MWt) to 3,020 MWt for each
unit. In accordance with 10 CFR Section
51.21, the NRC has prepared this draft
Environment Assessment (EA) and draft
Finding of No Significant Impact
(FONSI) for the proposed action. This
represents a power increase of 11.85
percent over the current licensed
thermal power. In 1981, FPL received
approval from the NRC to increase its
power by 5.47 percent to the current
power level of 2,700 MWt.
The NRC staff did not identify any
significant environmental impact
associated with the proposed action
based on its evaluation of the
information provided in the licensee’s
application and other available
information. The draft EA and draft
FONSI are being published in the
Federal Register with a 30-day public
comment period ending February 6,
2012.
II. Environmental Assessment
Plant Site and Environs: St. Lucie
Nuclear Plant consists of approximately
1,130 acres (457 hectares) in Sections 16
and 17, Township 36 South, Range 41
East on Hutchinson Island in
unincorporated St. Lucie County,
Florida. The St. Lucie Nuclear Plant is
located between the Atlantic Ocean to
the east and a tidally influenced estuary,
the Indian River Lagoon, to the west.
The plant is located on Hutchinson
Island between Big Mud Creek to the
north and Indian River to the south on
an area previously degraded through
flooding, drainage, and channelization
for mosquito control projects. The
nearest towns from the plant site on the
Atlantic coast are Port St. Lucie,
approximately 2.5 miles (mi) (4
kilometers (km)) southwest, and Fort
Pierce, approximately 4 mi (6.4 km)
northwest of the plant. The St. Lucie
Nuclear Plant has two light-water
reactors (Units 1 and 2), each designed
by Combustion Engineering for a net
electrical power output of 839
megawatts electric. FPL fully owns St.
Lucie Unit 1 and has operated it since
March 1, 1976. FPL also solely operates
St. Lucie Unit 2, which began
operations on April 6, 1983, and is coowned by FPL, Orlando Utilities
Commission, and Florida Municipal
Power Agency.
The St. Lucie Nuclear Plant
withdraws cooling water from the
Atlantic Ocean through three offshore
cooling water intakes with velocity
caps. The ocean water is drawn through
buried pipes into the plant’s L-shaped
intake canal to the eight intake pumps
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
that circulate the non-contact cooling
water through the plant. Two mesh
barrier nets, one net of 5-inches (in)
(12.7-centimeters (cm)) mesh size and
the other of 8-in (20.3-cm) mesh size,
and one rigid barrier located
sequentially in the intake canal reduce
the potential loss of large marine
organisms, mostly sea turtles. Water
passes through a trash rack made of 7.6
cm (3 in) spaced vertical bars and a 1cm (3⁄8-in) mesh size traveling screen,
against which marine organisms that
have passed through the nets are
impinged, and into eight separate intake
wells (four per unit) where it is pumped
to a circulating-water system and an
auxiliary cooling water system at each
unit. The majority of the water goes to
a once-through circulating-water system
to cool the main plant condensers. The
system has a nominal total capacity of
968,000 gallons per minute (gpm)
(61,070 liters per second (L/s)). The
auxiliary cooling water systems for St.
Lucie Units 1 and 2 are also oncethrough cooling systems, but use much
less water [up to 58,000 gpm (3,660 L/
s)] than the circulating-water systems.
Marine life that passes through the
screens becomes entrained in the water
that passes through the plant and is
subject to thermal and mechanical
stresses. The plant is also equipped with
an emergency cooling water intake canal
on the west side that can withdraw
Indian River Lagoon water through Big
Mud Creek, but this pathway is closed
during normal plant operation.
The heated water from the cooling
water systems flows to a discharge canal
and then through two offshore discharge
pipes beneath the beach and dune
system back to the Atlantic Ocean. One
12-foot (ft) (3.6-meter (m))-diameter
discharge pipe extends approximately
1,500 ft (457 m) offshore and terminates
in a two-port ‘‘Y’’ diffuser. A second 16ft (4.9-m)-diameter discharge pipe
extends about 3,400 ft (1,040 m) from
the shoreline and terminates with a
multiport diffuser. This second pipe has
fifty-eight 16-in (41-cm)-diameter ports
spaced 24 ft (7.3 m) apart along the last
1,400 ft (430 m) of pipe farthest
offshore. The discharge of heated water
through the diffusers on the discharge
pipes ensures distribution over a wide
area and rapid and efficient mixing with
ocean water.
Background Information on the
Proposed Action
By application dated November 22,
2010 (Unit 1), and February 25, 2011
(Unit 2), the licensee requested an
amendment for an extended power
uprate (EPU) for St. Lucie Nuclear Plant
to increase the licensed thermal power
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
level from 2,700 MWt to 3,020 MWt for
each unit, which represents an increase
of 11.85 percent above the current
licensed thermal power. This proposed
change in core thermal level requires an
NRC federal action to consider
amending the facility’s operating license
prior to the licensee implementing the
EPU. The NRC considers the proposed
action an EPU because it exceeds the
typical 7-percent power increase that
can be accommodated with only minor
plant changes. EPUs typically involve
extensive modifications to the nuclear
steam supply system contained within
the plant buildings.
Although not part of the NRC federal
action, changes from the current
operations at St. Lucie Nuclear Plant
would occur if the NRC approves the
EPU. FPL plans to make the physical
changes to the non-nuclear plant
components that are needed in order to
implement the proposed EPU. The
modifications are scheduled to be
implemented for Unit 1 during the fall
2011 outage starting in November 2011
and are expected to be completed by the
spring of 2012. Unit 2 modifications are
scheduled to be implemented during the
summer 2012 outage starting in June
2012 and are expected to be completed
by the fall of 2012. The outage durations
for both units are expected to be longer
than for a routine 35-day outage. The
actual power uprate, if approved by the
NRC, constitutes a 12 percent power
uprate and includes an additional 1.7
percent measurement uncertainty
recapture for each unit. As part of the
proposed EPU project, FPL would
release heated water with a proposed
temperature increase of 2 degrees
Fahrenheit (°F) (1.1 degrees Celsius (°C))
above the current discharge temperature
through the discharge structures into the
Atlantic Ocean.
Approximately 800 people are
currently employed at St. Lucie Units 1
and 2 on a full-time basis. FPL estimates
this workforce will be augmented by an
additional 1,000 construction workers
on average per outage during the
proposed EPU-related activities with a
potential peak of 1,400 additional
construction workers. The increase of
workers would be larger than the
number of workers required for a
routine outage; however, the peak
construction workforce would be
smaller than the FPL reported peak
workforce for previous outages
involving replacement of major
components.
The Need for the Proposed Action
FPL states in its environmental report
that the proposed action is intended to
provide an additional supply of electric
E:\FR\FM\06JAN1.SGM
06JAN1
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
pmangrum on DSK3VPTVN1PROD with NOTICES
generation in the State of Florida
without the need to site and construct
new facilities, or to impose new sources
of air or water discharges to the
environment. FPL has determined that
increasing the electrical output of St.
Lucie 1 and 2 is the most cost-effective
option to meet the demand for electrical
energy while enhancing fuel diversity
and minimizing environmental impacts,
including the avoidance of greenhouse
gas emissions.
Environmental Impacts of the Proposed
Action
As part of the licensing process for St.
Lucie Units 1 and 2, the U.S. Atomic
Energy Commission published a Final
Environmental Statement (FES) in 1973
for Unit 1, and the NRC published an
FES in 1982 for Unit 2 (NUREG–0842).
In the two FESs, the NRC staff
considered the best data available to the
NRC at the time to predict the
environmental impacts that could result
from the operation of St. Lucie Units 1
and 2 over their licensed lifetimes. In
addition, the NRC published an
Environmental Impact Statement (EIS)
in May 2003 associated with the license
renewal for St. Lucie Units 1 and 2. The
2003 EIS evaluated the environmental
impacts of operating the St. Lucie
Nuclear Plant for an additional 20 years
beyond its then-current operating
license, extending the operational life of
Unit 1 until 2036 and Unit 2 until 2043.
The NRC determined that the
environmental impacts of license
renewal would be small. The NRC staff’s
evaluation is contained in NUREG–
1437, ‘‘Generic Environmental Impact
Statement for License Renewal of
Nuclear Plants, Supplement 11,
Regarding St. Lucie Units 1 and 2’’
(Supplemental EIS–11 (SEIS–11))
[Agencywide Documents Access and
Management System (ADAMS)
Accession No. ML031360705]. The NRC
staff used information from FPL’s
license amendment request (LAR)
(ADAMS Accession No. ML103560419)
and SEIS–11 to perform this EA for the
proposed EPU.
FPL’s application states that it would
implement the proposed EPU without
extensive changes to buildings or to
other plant areas outside of buildings.
FPL proposes to perform all necessary
physical plant modifications in existing
buildings at St. Lucie Units 1 and 2 or
along the existing electrical
transmission line right of way (ROW).
With the exception of the high-pressure
turbine rotor replacement, the required
plant modifications would be generally
small in scope. Other plant
modifications would include installing
a new digital turbine control system;
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
providing additional cooling for some
plant systems; modifying feedwater and
condensate systems; accommodating
greater steam and condensate flow rates;
adjusting the current onsite power
system to compensate for increases in
electrical loading; and upgrading
instrumentation to include minor items
such as replacing parts, changing
setpoints, and modifying software.
FPL would use a vehicle and
helicopter for transmission line
modifications proposed along the
existing overhead electrical
transmission line ROW. The vehicle
would transport personnel and a spool
of overhead wire as a helicopter holds
and moves the wire into place for the
stringing activities. Although the
modifications are part of the proposed
EPU, this type and extent of activity
along the ROW is included in existing
maintenance permits and licenses.
Nonradiological Impacts
Land Use and Aesthetic Impacts
Potential land use and aesthetic
impacts from the proposed EPU include
proposed plant modifications at St.
Lucie Nuclear Plant. While FPL
proposes some plant modifications,
most plant changes related to the
proposed EPU would occur within
existing structures, with the exception
of modifications along the electrical
transmission line ROW. As described in
the licensee’s application, the proposed
electrical transmission modifications
would include the addition of
subconductor spacers, an overhead
wire, and replacement of relay
protection electronics. The overhead
wire would function as a ground for
relay protection of the transmission
lines. FPL would install these
transmission line modifications via
helicopter. The only land use activity
FPL expects to occur on the ground
along the ROW would be the periodic
need to park a truck or trailer containing
a spool of wire that would be strung but
would not extend outside of the existing
ROW area. The NRC expects little or no
observable change in the appearance of
the transmission lines as a result of the
electrical transmission line
modifications. Maintenance of the
electrical transmission line ROW (tree
trimming, mowing, and herbicide
application) would continue after EPU
implementation. The NRC does not
expect land use or aesthetic changes for
the proposed EPU along the
transmission line ROW.
No new construction would occur
outside of existing plant areas, and no
expansion of buildings, roads, parking
lots, equipment lay-down areas, or
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
815
storage areas are required to support the
proposed EPU. FPL would use existing
parking lots, road access, equipment
lay-down areas, offices, workshops,
warehouses, and restrooms during plant
modifications. Therefore, land use
conditions and visual aesthetics would
not change significantly at St. Lucie
Nuclear Plant, and the NRC expects no
significant impact from EPU-related
plant modifications on land use and
aesthetic resources in the vicinity of St.
Lucie Nuclear Plant.
Air Quality Impacts
Because of its coastal location,
meteorological conditions conducive to
high air pollution are infrequent at the
St. Lucie Nuclear Plant. The plant is
located within the South Florida
Intrastate Air Quality Control Region. In
addition, the Central Florida Intrastate
Air Quality Control Region and the
Southwest Florida Intrastate Air Quality
Control Region are within 50 mi (80.5
km) of the St. Lucie Nuclear Plant.
These regions are designated as being in
attainment or unclassifiable for all
criteria pollutants in the U.S.
Environmental Protection Agency’s
(EPA) 40 CFR 81.310.
Diesel generators, boilers, and other
activities and facilities associated with
St. Lucie Units 1 and 2 emit pollutants.
The Florida Department of
Environmental Protection (FDEP)
regulates emissions from these sources
under Air Permit 1110071–006–AF. The
FDEP reported no violations at the St.
Lucie Nuclear Plant in the last 5 years.
The NRC expects no changes to the
emissions from these sources because of
the EPU.
During EPU implementation, some
minor and short duration air quality
impacts would occur from other nonregulated sources. Vehicles of the
additional outage workers needed for
EPU implementation would generate the
majority of air emissions during the
proposed EPU-related modifications.
FPL plans to complete the construction
activities associated with the EPU, if
approved by the NRC, by the spring of
2012 for Unit 1 and by the fall of 2012
for Unit 2. The outage durations for both
units are expected to be longer than for
a routine 35-day outage. The NRC
expects air emissions from the EPU
workforce, truck deliveries, and
construction/modification activities
would not be significantly greater than
previous modification activities or
refueling outages at the St. Lucie
Nuclear Plant. In addition, FPL would
perform the majority of the EPU work
inside existing buildings and would not
result in changes to outside air quality.
The NRC expects no significant impacts
E:\FR\FM\06JAN1.SGM
06JAN1
816
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
to regional air quality from the proposed
EPU beyond those air impacts evaluated
for SEIS–11 including potential minor
and temporary impacts from worker
activity.
Water Use Impacts
Groundwater
FPL has approval from the City of Fort
Pierce and the Fort Pierce Utilities
Authority to use freshwater for potable
and sanitary purposes. Although this
freshwater comes from groundwater
sources pumped from the mainland, St.
Lucie Nuclear Plant does not use
groundwater in any of its cooling
systems and has no plans for
groundwater use as part of plant
operations in the future. The plant
currently uses approximately 131,500
gallons (498 m3) of freshwater per day
and uses seawater from the Atlantic
Ocean for noncontact cooling water. No
production wells are present on the
plant site for either domestic-type water
uses or industrial use. FPL does not
discharge to groundwater at the plant
site or on the mainland, and the plant’s
industrial wastewater facility permit
(IWFP) does not apply to groundwater.
Under the EPU, FPL does not expect
to significantly change the amount of
freshwater use or supply source. With
an average estimated increase of 1,000
workers supporting EPU construction
activities, the NRC expects potable
water use to increase during the outage
and return back to the regular operating
levels after EPU implementation. It is
unlikely this potential increase in
temporary groundwater use during the
EPU construction activities would have
any effect on other local and regional
groundwater users. FPL has no use
restrictions on the amount of water
supplied by the City of Fort Pierce and
the Fort Pierce Utilities Authority. The
NRC expects no significant impact on
groundwater resources during proposed
EPU construction activities or following
EPU implementation.
pmangrum on DSK3VPTVN1PROD with NOTICES
Surface Water
The NRC staff evaluated the potential
effects of releasing heated water with a
proposed temperature increase of 2 °F
(1.1 °C) above the current discharge
temperature through the discharge pipes
into the Atlantic Ocean as part of the
proposed EPU project. FDEP regulates
the Florida Surface Water Quality
Standards through an IWFP, which also
establishes the maximum area subject to
temperature increase (mixing zone),
maximum discharge temperatures, and
chemical monitoring requirements with
limits specified.
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
The plant injects chlorine in the form
of sodium hypochlorate into seawater
upstream of the intake cooling water
system in regulated quantities to control
microorganisms. Because FDEP
regulates discharges and requires
chemical monitoring, the NRC expects
that the authorized discharges will not
exceed the IWFP limitations after EPU
implementation.
In the IWFP, FDEP has issued the
plant a temporary variance for a
temperature increase of heated water
discharge from 113 °F (45 °C) above
ambient temperature to the proposed
thermal discharge of 115 °F (46.1 °C)
above ambient temperature after EPU
completion for Units 1 and 2 on the
condition that no adverse affects are
found based on FPL study results. The
proposed EPU will not result in an
increase in the amount or rate of water
withdrawn from or discharged to the
Atlantic Ocean. FPL conducted a
thermal discharge study for the
proposed EPU-related increase in
discharge water temperature (ADAMS
Accession No. ML100830443) that
predicts an increase in the extent of the
thermal plume (mixing zone). The
ambient water affected by the absolute
temperature increase beyond the
existing mixing zone would be less than
25 ft (7.6 m) vertically or horizontally
for the two-port ‘‘Y’’ diffuser and less
than 6 ft (1.8 m) in any direction for the
multiport diffuser.
As part of its operating license
renewal, FPL consulted with the Florida
Department of Community Affairs
(FDCA) for a review of coastal zone
consistency. Based on the information
FDCA reviewed, it determined that the
licensing renewal action would be
consistent with the Florida Coastal
Management Program (FCMP). FDCA, in
partnership with the FDEP, administers
the FCMP and has the authority to
review the proposed EPU action for
coastal zone consistency.
Aquatic Resource Impacts
The potential impacts to aquatic biota
from the proposed action could include
impingement of aquatic life on barrier
nets, trash racks, and traveling screens;
entrainment of aquatic life through the
cooling water intake structures and into
the cooling water systems; and effects
from the discharge of chemicals and
heated water.
Because the proposed EPU will not
result in an increase in the amount or
velocity of water being withdrawn from
or discharged to the Atlantic Ocean, the
NRC expects no increase in aquatic
impacts from impingement and
entrainment beyond the current impact
levels: all organisms impinged on the
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
trash racks and traveling screens would
be killed, as would most, if not all,
entrained organisms. FPL would
continue to rescue and release sea
turtles and other endangered species
trapped by the barrier nets in the intake
canal. In addition, FPL’s IWFP requires
FPL to monitor aquatic organism
entrapment in the intake canal, and, if
unusually large numbers of organisms
are entrapped, to submit to the FDEP a
plan to mitigate such entrapment.
The predicted 2 °F (1.1 °C)
temperature increase from the diffusers
and increased size of the mixing zone
because of the proposed EPU would
increase thermal exposure to aquatic
biota at the St. Lucie Nuclear Plant in
the vicinity of the discharge locations.
The thermal discharge study conducted
for the proposed EPU predicts no
increase in temperature higher than 96
°F (35.5 °C) within 6 ft (1.8 m) of the
bottom of the ocean floor and within 24
ft (7.3 m) from the ocean surface
because of heated water discharged from
the multiport diffuser. The same study
also predicts that heated water
discharged from the ‘‘Y’’ diffuser would
not increase the ocean water
temperature higher than 96 °F (35.5 °C)
within 2 ft (0.6 m) of the bottom of the
ocean floor and within 25 ft (17 m) from
the ocean surface. Based on this
analysis, surface water temperature
would remain below 94 °F (34.4 °C).
Thermal studies conducted for the St.
Lucie Nuclear Plant prior to its
operation and summarized in SEIS–11
predicted there would be minimal
impacts to aquatic biota from diffuser
discharges that result in a surface
temperature less than 97 °F (36.1 °C).
Because the NRC expects the surface
water temperature not to exceed 94 °F
(34.4 °C) because of the proposed EPU,
the NRC staff concludes that there are
no significant impacts to aquatic biota
from the proposed EPU.
Although the proposed increase in
temperature after EPU implementation
would exceed the Florida Surface Water
Quality Standards regulated by FDEP,
FDEP is continuing to assess this action
by requiring FPL to conduct studies as
part of an IWFP variance. If the study
results are insufficient to adequately
evaluate environmental changes, or if
the data indicates a significant
degradation to aquatic resources by
exceeding Florida Surface Water Quality
Standards or is inconsistent with the
FCMP, FDEP could enforce additional
abatement or mitigation measures to
reduce the environmental impacts to
acceptable levels. If the NRC approves
the proposed EPU, the NRC does not
expect aquatic resource impacts
significantly greater than current
E:\FR\FM\06JAN1.SGM
06JAN1
817
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
operations because state agencies will
continue to assess study results and the
effectiveness of current FPL
environmental controls. FDEP could
impose additional limits and controls
on FPL if the impacts are larger than
expected. If FDCA and FDEP review the
study results and allow FPL to operate
at the proposed EPU level, the NRC has
reasonable confidence as discussed
above that the increase in thermal
discharge will not result in significant
impacts on aquatic resources beyond the
current impacts that occur during plant
operations.
Terrestrial Resources Impacts
The St. Lucie Nuclear Plant is on a
relatively flat, sheltered area of
Hutchinson Island with red mangrove
swamps on the western side of the
island that gradually slope downward to
a mangrove fringe bordering the
intertidal shoreline of the Indian River
Lagoon. East of the facility, land rises
from the ocean shore to form dunes and
ridges approximately 15 ft (4.5 m) above
mean low water. Tropical hammock
areas are present north of the discharge
canal, and additional red mangrove
swamps are present north of Big Mud
Creek. Habitat in the electrical
transmission line ROW is a mixture of
human-altered areas, sand pine scrub,
prairie/pine flatwoods, wet prairie, and
isolated marshes.
Impacts that could potentially affect
terrestrial resources include disturbance
or loss of habitat, construction and EPUrelated noise and lighting, and sediment
transport or erosion. FPL plans to
conduct electrical transmission line
modifications that would require a
periodic need to park a truck or trailer
containing a spool of wire that would be
strung. The NRC concluded in SEIS–11
that no bird mortalities were reported
up to that time associated with the
electrical transmission lines and
predicted that FPL maintenance
practices along the ROW would likely
have little or no detrimental impact on
the species potentially present in or
near the electrical transmission ROW.
Because FPL proposes a similar type
and extent of land disturbance during
typical maintenance of the electrical
transmission line ROW for the EPU
modifications, the NRC expects the
proposed transmission line
modifications would not result in any
significant changes to land use or
increase habitat loss or disturbance,
sediment transport, or erosion beyond
typical maintenance impacts. Noise and
lighting would not adversely affect
terrestrial species beyond effects
experienced during previous outages
because construction EPU modification
activities would take place during
outage periods, which are typically
periods of heightened activity. Thus, the
NRC expects no significant impacts on
terrestrial biota associated with the
proposed action.
Threatened and Endangered Species
Impacts
A number of species in St. Lucie
County are listed as threatened or
endangered under the Federal
Endangered Species Act, and other
species are designated as meriting
special protection or consideration.
These include birds, fish, aquatic and
terrestrial mammals, flowering plants,
insects, and reptiles that could occur on
or near St. Lucie Units 1 and 2 facility
areas and possibly along the electrical
transmission line ROW. The most
common occurrences of threatened or
endangered species near St. Lucie Units
1 and 2 are five species of sea turtles
that nest on Hutchinson Island beaches:
loggerhead turtles (Caretta caretta),
Atlantic green turtles (Chelonia mydas),
Kemp’s ridley turtles (Lepidochelys
kempii), leatherback turtles
(Dermochelys coriacea), and hawksbill
turtles (Eretmochelys imbricata). FPL
has a mitigation and monitoring
program in place for the capture-release
and protection of sea turtles that enter
the intake canal. The West Indian
manatee (Trichechus manatus) also has
been documented at the St. Lucie
Nuclear Plant. Designated critical
habitat for the West Indian manatee is
located along the Indian River west of
Hutchinson Island. The NRC staff
assessed potential impacts on the West
Indian manatee from St. Lucie Nuclear
Plant in SEIS–11. No other critical
habitat areas for endangered, threatened,
or candidate species are located at the
St. Lucie Nuclear Plant site or along the
transmission line ROW.
The following table identifies the
species that the NRC considered in this
EA that were not previously assessed for
SEIS–11 because the species were not
listed at that time.
TABLE OF FEDERALLY LISTED SPECIES OCCURRING IN ST. LUCIE COUNTY NOT PREVIOUSLY ASSESSED IN SEIS–11
Scientific name
ESA status (a)
Common name
Birds:
Calidris canutus ssp. Rufa .................................................
Charadrius melodus ...........................................................
Dendroica kirtlandii .............................................................
Grus americana ..................................................................
Fish:
Pristis pectinata ..................................................................
Mammals:
Puma concolor ....................................................................
Reptiles:
Crocodylus acutus ..............................................................
Gopherus polyphemus .......................................................
red knot ....................................................................................
piping plover .............................................................................
Kirtland’s warbler ......................................................................
whooping Crane (b) ...................................................................
Candidate.
T.
E.
EXPN, XN.
smalltooth sawfish ....................................................................
E.
Puma ........................................................................................
T/SA.
American crocodile ...................................................................
gopher tortoise (c) .....................................................................
T.
Candidate.
(a) E
= endangered; T = threatened; T/SA = threatened due to similarity of appearance; EXPN, XN = experimental, nonessential.
nonessential populations of endangered species (e.g., red wolf) are treated as threatened species on public land, for consultation purposes, and as species proposed for listing on private land.
(c) The gopher tortoise is not listed by the FWS as occurring in St. Lucie County. The core of the species’ current distribution in the eastern
portion of its range occurs in central and north Florida (76 FR 45130), and FPL has reported the species’ occurrence on the site and in the electrical transmission line right-of-way.
Source: U.S. Fish and Wildlife Service.
pmangrum on DSK3VPTVN1PROD with NOTICES
(b) Experimental,
The NRC has consulted with the
National Marine Fisheries Service
(NMFS) since 1982 regarding sea turtle
kills, captures, or incidental takes. A
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
2001 NMFS biological opinion analyzed
the effects of the circulating cooling
water system on certain sea turtles at the
St. Lucie Nuclear Plant. The 2001 NMFS
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
biological opinion provides for limited
incidental takes of threatened or
endangered sea turtles. Correspondence
between the licensee, U.S. Fish and
E:\FR\FM\06JAN1.SGM
06JAN1
pmangrum on DSK3VPTVN1PROD with NOTICES
818
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
Wildlife Service, and NMFS in
connection with the 2003 license
renewal environmental review indicated
that effects to federal endangered,
threatened, or candidate species,
including a variety of sea turtles and
manatees, would not significantly
change as a result of issuing a license
renewal for the St. Lucie Nuclear Plant.
The NRC reinitiated formal consultation
with NMFS in 2005 after the incidental
take of a smalltooth sawfish (Pristis
pectinata). The NRC added sea turtles to
the reinitiation of formal consultation
with NMFS in 2006 after the St. Lucie
Nuclear Plant exceeded the annual
incidental take limit for sea turtles. The
NRC provided NMFS with a biological
assessment in 2007 (ADAMS Accession
No. ML071700161) as an update
regarding effects on certain sea turtle
species up to that time. The NRC
expects a biological opinion from NMFS
in response to ongoing consultation, but
does not expect the biological opinion
to affect the conclusions in this draft
EA.
As described in the Aquatic Resources
Impacts section, the expected
temperature increase of plant water
discharged to the Atlantic Ocean could
increase thermal exposure to aquatic
biota, including the threatened and
endangered sea turtles found at the site.
The NRC expects the FPL capturerelease and monitoring program for sea
turtles and NRC interactions with NMFS
regarding incidental takes to continue
under the terms and conditions of the
new biological opinion. Therefore, the
NRC expects the proposed EPU would
not change the effects of plant operation
on threatened and endangered species.
Planned construction-related
activities associated with the proposed
EPU primarily involve changes to
existing structures, systems, and
components internal to existing
buildings and would not involve earth
disturbance, with the exception of
planned electrical transmission line
modifications. Traffic and worker
activity in the developed parts of the
plant site during the combined refueling
outages and EPU modifications would
be somewhat greater than a normal
refueling outage. As described in the
Terrestrial Resources Impacts section,
electrical transmission line
modifications may require truck use
within the transmission line ROW. The
NRC concluded in SEIS–11 that
transmission line maintenance practices
for the FPL license renewal would not
lower terrestrial habitat quality or cause
significant changes in wildlife
populations. Because the proposed EPU
operations would not result in any
significant changes to the expected
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
transmission maintenance activities
evaluated for the operating license
renewal, the proposed EPU transmission
modifications also should have little
effect on threatened and endangered
terrestrial species. The effects of
changes to the terrestrial wildlife habitat
on the St. Lucie Nuclear Plant site from
the proposed EPU should not exceed
those potential effects on terrestrial
wildlife evaluated in SEIS–11, including
potential minor and temporary impacts
from worker activity.
Historic and Archaeological Resources
Impacts
Records at the Florida Master File in
the Florida Division of Historical
Resources identify five known
archaeological sites located on or
immediately adjacent to the property
boundaries for the St. Lucie Nuclear
Plant, although no archaeological and
historic architectural finds have been
recorded on the site. None of these sites
are listed on the National Register for
Historic Places (NRHP). The NRHP lists
sixteen properties in St. Lucie County
including one historic district. The
Captain Hammond House in White City,
approximately 6 mi (10 km) from St.
Lucie Nuclear Plant, is the nearest
property listed on the NRHP.
A moderate to high likelihood for the
presence of significant prehistoric
archaeological remains occurs along
Blind Creek and the northern end of the
St. Lucie Nuclear Plant boundary. As
previously discussed, all EPU-related
modifications would take place within
existing buildings and facilities and the
electrical transmission line ROW, which
are not located near Blind Creek or the
northern FPL property boundary.
Because no change in ground
disturbance or construction-related
activities would occur outside of
previously disturbed areas and existing
electrical transmission line ROW, the
NRC expects no significant impact from
the proposed EPU-related modifications
on historic and archaeological
resources.
Socioeconomic Impacts
Potential socioeconomic impacts from
the proposed EPU include temporary
increases in the size of the workforce at
St. Lucie Units 1 and 2, and associated
increased demand for goods, public
services, and housing in the region. The
proposed EPU also could generate
increased tax revenues for the state and
surrounding counties.
Currently, approximately 800 fulltime employees work at the St. Lucie
Nuclear Plant. FPL estimates a
temporary increase in the size of the
workforce during the fall 2011 and
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
summer 2012 refueling outages. During
the refueling outages, FPL expects the
average number of workers to peak by
as many as 1,400 construction workers
per day to implement the EPU for each
unit. The outage durations for both units
are expected to be longer than for a
routine 35-day outage. Once EPUrelated plant modifications have been
completed, the size of the refueling
outage workforce at St. Lucie Nuclear
Plant would return to normal levels and
would remain similar to pre-EPU levels,
with no significant increases during
future refueling outages. The size of the
regular plant operations workforce
would be unaffected by the proposed
EPU.
The NRC expects most of the EPU
plant modification workers to relocate
temporarily to communities in St. Lucie,
Martin, Indian River, and Palm Beach
Counties, resulting in short-term
increases in the local population along
with increased demands for public
services and housing. Because plant
modification work would be temporary,
most workers would stay in available
rental homes, apartments, mobile
homes, and camper-trailers. The 2010
American Community Survey 1-year
estimate for vacant housing units
reported 32,056 vacant housing units in
St. Lucie County; 18,042 in Martin
County; 23,236 in Indian River County;
and 147,910 in Palm Beach County that
could potentially ease the demand for
local rental housing. Therefore, the NRC
expects a temporary increase in plant
employment for a short duration that
would have little or no noticeable effect
on the availability of housing in the
region.
The additional number of refueling
outage workers and truck material and
equipment deliveries needed to support
EPU-related plant modifications would
cause short-term level of service impacts
(restricted traffic flow and higher
incident rates) on secondary roads in
the immediate vicinity of St. Lucie
Nuclear Plant. FPL expects increased
traffic volumes necessary to support
implementation of the EPU-related
modifications during the refueling
outage. The NRC predicted
transportation service impacts for
refueling outages at St. Lucie Nuclear
Plant during its license renewal term
would be small and would not require
mitigation. However, the number of
temporary construction workers the
NRC evaluated for SEIS–11 was less
than the number of temporary
construction workers required for the
proposed EPU. Based on this
information and that EPU-related plant
modifications would occur during a
normal refueling outage, there could be
E:\FR\FM\06JAN1.SGM
06JAN1
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
pmangrum on DSK3VPTVN1PROD with NOTICES
noticeable short-term (during certain
hours of the day) level-of-service traffic
impacts beyond what is experienced
during normal outages. During periods
of high traffic volume (i.e., morning and
afternoon shift changes), work
schedules could be staggered and
employees and/or local police officials
could be used to direct traffic entering
and leaving St. Lucie Nuclear Plant to
minimize level-of-service impacts.
The St. Lucie Nuclear Plant currently
pays annual real estate property taxes to
the St. Lucie County school district, the
County Board of Commissioners, the
County fire district, and the South
Florida Water Management District. The
annual amount of future property taxes
the St. Lucie Nuclear Plant would pay
could take into account the increased
value of St. Lucie Units 1 and 2 as a
result of the EPU and increased power
generation.
Due to the short duration of EPUrelated plant modification activities,
there would be little or no noticeable
effect on tax revenues generated by
temporary workers residing in St. Lucie
County. Therefore, the NRC expects no
significant socioeconomic impacts from
EPU-related plant modifications and
operations under EPU conditions in the
vicinity of St. Lucie Nuclear Plant.
Environmental Justice Impact Analysis
The environmental justice impact
analysis evaluates the potential for
disproportionately high and adverse
human health and environmental effects
on minority and low-income
populations that could result from
activities associated with the proposed
EPU at St. Lucie Nuclear Plant. Such
effects may include biological, cultural,
economic, or social impacts. Minority
and low-income populations are subsets
of the general public residing in the
vicinity of St. Lucie Nuclear Plant, and
all are exposed to the same health and
environmental effects generated from
activities at St. Lucie Units 1 and 2.
The NRC considered the demographic
composition of the area within a 50-mi
(80.5-km) radius of St. Lucie Units 1 and
2 to determine the location of minority
and low-income populations and
whether the proposed action may affect
them. The NRC examined the
geographic distribution of minority and
low-income populations within 50 mi
(80.5 km) of the St. Lucie Units 1 and
2 using the U.S. Census Bureau (USCB)
data for 2000. Although the 2010 census
occurred, the data is not yet available in
a format that provides the population
information within a specified radius of
the site.
According to the U.S. Census Bureau
(USCB) data for 2000 on minority
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
populations in the vicinity of St. Lucie
Units 1 and 2, an estimated 1.2 million
people live within a 50-mi (80.5-km)
radius of the plant located within parts
of nine counties. Minority populations
within 50 mi (80.5 km) comprise 27
percent (274,500 persons). The largest
minority group was African-American
(approximately 135,250 persons or 13.3
percent), followed by Hispanic or Latino
(approximately 111,000 persons or 11
percent). The 2000 census block groups
containing minority populations were
concentrated in Gifford (Indian River
County), Fort Pierce (St. Lucie County),
Pahokee (Palm Beach County near Lake
Okeechobee), the agricultural areas
around Lake Okeechobee, and Hobe
Sound (Martin County).
The NRC examined low-income
populations using the USCB data for
2000 and the 2010 American
Community Survey 1–Year Estimate.
According to the 2000 census data,
approximately 11 percent of the
population (111,000 persons) residing
within 50 mi (80.5 km) of the St. Lucie
Nuclear Plant were considered lowincome, living below the 2000 federal
poverty threshold of $8,350 per
individual. According to the 2010
census estimate, approximately 14.1
percent of families and 18 percent of
individuals were determined to be
living below the Federal poverty
threshold in St. Lucie County. The 2010
federal poverty threshold was $22,050
for a family of four and $10,830 for an
individual. The median household
income for St. Lucie County was
approximately $38,671 and 13 percent
lower than the median household
income (approximately $44,409) for
Florida.
Environmental Justice Impact
Potential impacts to minority and
low-income populations would mostly
consist of environmental and
socioeconomic effects (e.g., noise, dust,
traffic, employment, and housing
impacts). Radiation doses from plant
operations after the EPU are expected to
continue to remain well below
regulatory limits.
Noise and dust impacts would be
temporary and limited to onsite
activities. Minority and low-income
populations residing along site access
roads could experience increased
commuter vehicle traffic during shift
changes. Increased demand for
inexpensive rental housing during the
EPU-related plant modifications could
disproportionately affect low-income
populations; however, due to the short
duration of the EPU-related work and
the availability of housing properties,
impacts to minority and low-income
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
819
populations would be of short duration
and limited. According to the 2010
census information, there were
approximately 221,244 vacant housing
units in St. Lucie County and the
surrounding three counties combined.
Based on this information and the
analysis of human health and
environmental impacts presented in this
EA, the proposed EPU would not have
disproportionately high and adverse
human health and environmental effects
on minority and low-income
populations residing in the St. Lucie
Nuclear Plant vicinity.
Nonradiological Cumulative Impacts
The NRC considered potential
cumulative impacts on the environment
resulting from the incremental impact of
the proposed EPU when added to other
past, present, and reasonably
foreseeable future actions in the vicinity
of St. Lucie Nuclear Plant. For the
purposes of this analysis, past actions
are related to the construction and
licensing of St. Lucie Units 1 and 2,
present actions are related to current
operations, and future actions are those
that are reasonably foreseeable through
the end of station operations including
operations under the EPU.
The NRC concluded that there would
be no significant cumulative impacts to
the resource areas air quality,
groundwater, threatened and
endangered species, historical and
archaeological resources in the vicinity
of St. Lucie Units 1 and 2 because the
contributory effect of ongoing actions
within a region are regulated and
monitored through a permitting process
(e.g., National Pollutant Discharge
Elimination System and 401/404
permits under the Clean Water Act)
under State or Federal authority. In
these cases, impacts are managed as
long as these actions are in compliance
with their respective permits and
conditions of certification.
Surface water and aquatic resources
were examined for potential cumulative
impacts. The geographic boundary for
potential cumulative impacts is the area
of the post-EPU thermal mixing zone. If
the proposed EPU is approved and is
implemented, St. Lucie Units 1 and 2
are predicted to have a slightly larger
and hotter mixing zone than pre-uprate
conditions during full flow and
capacity. The NRC anticipates that St.
Lucie Units 1 and 2 will continue to
operate post EPU in full compliance
with the requirements of the FDEP
IWFP. FDEP would evaluate FPL
compliance with the IWFP.
Proposed EPU-related modifications
for the electrical transmission line ROW
at the St. Lucie Nuclear Plant could
E:\FR\FM\06JAN1.SGM
06JAN1
820
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
affect land use, aesthetics, and
terrestrial species. Improvements and
maintenance would be conducted
according to Federal and State
regulations, permit conditions, existing
procedures, and established best
management practices to minimize
impacts to these resources.
Nevertheless, terrestrial wildlife and
habitat may be lost, displaced, or
disturbed by noise and human presence
during EPU-related work in the
electrical transmission line ROW. Less
mobile animals, such as reptiles,
amphibians, and small mammals, would
incur greater impacts than more mobile
animals, such as birds. The proposed
electrical transmission line
modifications would neither change
land use activities expected during
current operations nor change the
current aesthetic resources within view
of the electrical transmission lines.
The greatest socioeconomic impacts
from the proposed EPU and continued
operation of St. Lucie Units 1 and 2
would occur during the fall 2011 and
summer 2012 fuel outages. The increase
in EPU-related construction workforces
would have a temporary effect on
socioeconomic conditions in local
communities from the increased
demand for temporary housing, public
services (e.g., public schools), and
increased traffic.
Nonradiological Impacts Summary
As discussed previously, the
proposed EPU would not result in any
significant nonradiological impacts.
Table 1 summarizes the nonradiological
environmental impacts of the proposed
EPU at St. Lucie Units 1 and 2.
TABLE 1—SUMMARY OF NONRADIOLOGICAL ENVIRONMENTAL IMPACTS
Land Use .........................................
Air Quality .......................................
Water Use .......................................
Aquatic Resources ..........................
Terrestrial Resources ......................
Threatened and Endangered Species.
Historic and Archaeological Resources.
Socioeconomics ..............................
Environmental Justice .....................
Cumulative Impacts ........................
Proposed EPU-related activities are not expected to cause significant impacts on land use conditions and
aesthetic resources in the vicinity of St. Lucie Units 1 and 2.
Temporary air quality impacts from vehicle emissions related to EPU construction workforce is not expected to cause significant impacts to air quality.
Water use changes resulting from the proposed EPU are not expected to cause impacts greater than current operations. No significant impact on groundwater or surface water resources.
The NRC expects no significant changes to impacts caused by current operation due to impingement, entrainment, and thermal discharges.
The NRC expects no significant impacts to terrestrial resources.
The proposed EPU would change impacts from those caused by current operations. The NRC expects a
NMFS to issue a biological opinion on sea turtles and the smalltooth sawfish in the near future.
No significant impact to historic and archaeological resources on site or in the vicinity of St. Lucie Units 1
and 2.
No significant socioeconomic impacts from EPU-related temporary increase in workforce.
No disproportionately high or adverse human health and environmental effects on minority and low-income
populations in the vicinity of St. Lucie Units 1 and 2.
The proposed EPU would not cause impacts significantly greater than current operations. To address potential cumulative impacts for surface water and aquatic resources, a NMFS biological opinion is expected with the authority to impose limits on nonradiological discharges to abate any significant water
quality and ecology impacts.
Radiological Impacts
Radioactive Gaseous and Liquid
Effluents, Direct Radiation Shine, and
Solid Waste
St. Lucie Units 1 and 2 use waste
treatment systems to collect, process,
recycle, and dispose of gaseous, liquid,
and solid wastes that contain
radioactive material in a safe and
controlled manner within NRC and EPA
radiation safety standards. The
licensee’s evaluation of plant operation
under proposed EPU conditions predict
that no physical changes would be
needed to the radioactive gaseous,
liquid, or solid waste systems.
pmangrum on DSK3VPTVN1PROD with NOTICES
Radioactive Gaseous Effluents
Radioactive gaseous wastes are
principally activation gases and fission
product radioactive noble gases
resulting from process operations,
including continuous cleanup of the
reactor coolant system, gases used for
tank cover gas, and gases collected
during venting. The licensee’s
evaluation determined that
implementation of the proposed EPU
would not significantly increase the
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
inventory of nonradioactive carrier
gases normally processed in the gaseous
waste management system, because
plant system functions are not changing
and the volume inputs remain the same.
The licensee’s analysis also showed that
the proposed EPU would result in an
increase (a bounding maximum, as
expected, of 13.2 percent for all noble
gases, particulates, radioiodines, and
tritium) in the equilibrium radioactivity
in the reactor coolant, which in turn
increases the radioactivity in the waste
disposal systems and radioactive gases
released from the plant.
The licensee’s evaluation concluded
that the proposed EPU would not
change the radioactive gaseous waste
system design function and reliability to
safely control and process the waste.
The existing equipment and plant
procedures that control radioactive
releases to the environment will
continue to be used to maintain
radioactive gaseous releases within the
dose limits of 10 CFR 20.1302 and the
as low as is reasonably achievable
(ALARA) dose objectives in 10 CFR part
50, Appendix I.
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
Radioactive Liquid Effluents
Radioactive liquid wastes include
liquids from reactor process systems
and liquids that have become
contaminated. The licensee’s evaluation
shows that the proposed EPU
implementation would not significantly
increase the inventory of liquid
normally processed by the liquid waste
management system. This is because the
system functions are not changing and
the volume inputs remain the same. The
proposed EPU would result in an
increase in the equilibrium radioactivity
in the reactor coolant (12.2 percent),
which in turn would impact the
concentrations of radioactive nuclides
in the waste disposal systems.
Because the NRC does not expect the
composition of the radioactive material
in the waste and the volume of
radioactive material processed through
the system to significantly change, the
current design and operation of the
radioactive liquid waste system will
accommodate the effects of the
proposed EPU. The existing equipment
and plant procedures that control
radioactive releases to the environment
will continue to be used to maintain
E:\FR\FM\06JAN1.SGM
06JAN1
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
radioactive liquid releases within the
dose limits of 10 CFR 20.1302 and
ALARA dose standards in 10 CFR part
50, Appendix I.
pmangrum on DSK3VPTVN1PROD with NOTICES
Occupational Radiation Dose Under
EPU Conditions
The licensee stated that the in-plant
radiation sources are expected to
increase approximately linearly with the
proposed increase in core power level of
12.2 percent. For the radiological impact
analyses, the licensee conservatively
assumed an increase to the licensed
thermal power level from 2,700 MWt to
3,030 MWt or 12.2 percent, although the
EPU request is for an increase to the
licensed thermal power level to 3,020
MWt, or 11.85 percent. To protect the
workers, the plant radiation protection
program monitors radiation levels
throughout the plant to establish
appropriate work controls, training,
temporary shielding, and protective
equipment requirements so that worker
doses will remain within the dose limits
of 10 CFR part 20 and ALARA.
In addition to the work controls
implemented by the radiation protection
program, shielding is used throughout
St. Lucie Units 1 and 2 to protect plant
personnel against radiation from the
reactor and auxiliary systems. The
licensee determined that the current
shielding design, which uses
conservative analytical techniques to
establish the shielding requirements, is
adequate to offset the increased
radiation levels that are expected to
occur from the proposed EPU. The
proposed EPU is not expected to
significantly affect radiation levels
within the plant, and therefore there
would not be a significant radiological
impact to the workers.
Offsite Doses at EPU Conditions
The primary sources of offsite dose to
members of the public from St. Lucie
Units 1 and 2 are radioactive gaseous
and liquid effluents. The licensee
predicts that maximum annual total and
organ doses from liquid effluent releases
would increase by 12.2 percent. As
discussed previously, operation under
the proposed EPU conditions will not
change the ability of the radioactive
gaseous and liquid waste management
systems to perform their intended
functions. Also, there would be no
change to the radiation monitoring
system and procedures used to control
the release of radioactive effluents in
accordance with NRC radiation
protection standards in 10 CFR part 20
and 10 CFR part 50, Appendix I.
Based on the previous information,
the offsite radiation dose to members of
the public would continue to be within
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
regulatory limits and therefore would
not be significant.
Radioactive Solid Wastes
Solid radioactive waste streams
include solids recovered from the
reactor coolant systems, solids that
come into contact with the radioactive
liquids or gases, and solids used in the
reactor coolant system operation. The
licensee evaluated the potential effects
of the proposed EPU on the solid waste
management system. The largest volume
of radioactive solid waste is low-level
radioactive waste, which includes bead
resin, spent filters, and dry active waste
(DAW) that result from routine plant
operation, outages, and routine
maintenance. DAW includes paper,
plastic, wood, rubber, glass, floor
sweepings, cloth, metal, and other types
of waste generated during routine
maintenance and outages.
The licensee states that the proposed
EPU would not have a significant effect
on the generation of radioactive solid
waste volume from the primary reactor
coolant and secondary side systems
because system functions are not
changing and the volume inputs remain
consistent with historical generation
rates. The waste can be handled by the
solid waste management system without
modification. The equipment is
designed and operated to process the
waste into a form that minimizes
potential harm to the workers and the
environment. Waste processing areas are
monitored for radiation, and safety
features are in place to ensure worker
doses are maintained within regulatory
limits. The proposed EPU would not
generate a new type of waste or create
a new waste stream. Therefore, the
impact from the proposed EPU on
radioactive solid waste would not be
significant.
Spent Nuclear Fuel
Spent fuel from St. Lucie Units 1 and
2 is stored in a plant spent fuel pool. St.
Lucie Units 1 and 2 are currently
licensed to use uranium-dioxide fuel
that has a maximum enrichment of 4.5
percent by weight uranium-235. The
average fuel assembly discharge burnup
for the proposed EPU is expected to be
limited to 49,000 megawatt days per
metric ton uranium (MWd/MTU) with
no fuel pins exceeding the maximum
fuel rod burnup limit of 62,000 MWd/
MTU for Unit 1 and 60,000 MWd/MTU
for Unit 2. The licensee’s fuel reload
design goals will maintain the St. Lucie
Units 1 and 2 fuel cycles within the
limits bounded by the impacts analyzed
in 10 CFR part 51, Table S–3, ‘‘Uranium
Fuel Cycle Environmental Data’’ and
Table S–4, ‘‘Environmental Impact of
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
821
Transportation of Fuel and Waste to and
From One Light-Water-Cooled Nuclear
Power Reactor,’’ as supplemented by
NUREG–1437, Volume 1, Addendum 1,
‘‘Generic Environmental Impact
Statement for License Renewal of
Nuclear Plants, Main Report, Section
6.3—Transportation Table 9.1,
Summary of findings on NEPA issues
for license renewal of nuclear power
plants.’’ Therefore, there would be no
significant impacts resulting from spent
nuclear fuel.
Postulated Design-Basis Accident Doses
Postulated design-basis accidents are
evaluated by both the licensee and the
NRC to ensure that St. Lucie Units 1 and
2 can withstand normal and abnormal
transients and a broad spectrum of
postulated accidents without undue
hazard to the health and safety of the
public.
On November 22, 2010, the licensee
submitted the St. Lucie Unit 1 EPU LAR
to the NRC to increase the licensed core
power level from 2,700 MWt to 3,020
MWt. On February 25, 2011, the
licensee submitted the St. Lucie Unit 2
EPU LAR to the NRC requesting the
same increase in licensed core power
level. Analyses were performed by the
licensee according to the Alternative
Radiological Source Term methodology
updated with input and assumptions
consistent with the proposed EPU. For
each design-basis accident radiological
consequence analyses were performed
using the guidance in NRC Regulatory
Guide 1.183, ‘‘Alternative Source Terms
for Evaluating Design Basis Accidents at
Nuclear Power Reactors.’’ Accidentspecific total effective dose equivalent
was determined at the exclusion area
boundary, at the low-population zone,
and in the control room. The analyses
also include the evaluation of the waste
gas decay tank rupture event. The
licensee concluded that the calculated
doses meet the acceptance criteria
specified in 10 CFR 50.67 and 10 CFR
part 50, Appendix A, General Design
Criterion 19.
The NRC is evaluating the licensee’s
LARs to independently determine
whether they are acceptable to approve.
The results of the NRC evaluation and
conclusion will be documented in a
Safety Evaluation Report that will be
publicly available on the NRC ADAMS.
If the NRC approves the LARs, then the
proposed EPU will not have a
significant impact with respect to the
radiological consequences of design
basis accidents.
Radiological Cumulative Impacts
The cumulative impacts associated
with the proposed EPU for St. Lucie
E:\FR\FM\06JAN1.SGM
06JAN1
822
Federal Register / Vol. 77, No. 4 / Friday, January 6, 2012 / Notices
Unit 1 are considered in conjunction
with the operation of St. Lucie Unit 2,
which is located next to Unit 1 on the
site property. The radiological dose
limits for protection of the public and
workers have been developed by the
NRC and EPA to address the cumulative
impact of acute and long-term exposure
to radiation and radioactive material.
These dose limits are codified in 10 CFR
part 20 and 40 CFR part 190.
The cumulative radiation doses to the
public and workers are required to be
within the limits of the regulations. The
public dose limit of 0.25 millisievert (25
millirem) in 40 CFR part 190 applies to
all reactors that may be on a site and
also includes any other nearby nuclear
power reactor facilities. No other
nuclear power reactor or uranium fuel
cycle facility is located near St. Lucie
Units 1 and 2. The staff reviewed
several years of radiation dose data
contained in the licensee’s annual
radioactive effluent release reports for
St. Lucie Units 1 and 2. The data
demonstrate that the dose to members of
the public from radioactive effluents is
well within the limits of 10 CFR part 20
and 40 CFR part 190. To evaluate the
projected dose at EPU conditions for St.
Lucie Units 1 and 2, the NRC increased
the actual dose data contained in the
reports by 12 percent. The projected
doses at EPU conditions remained well
within regulatory limits. Therefore, the
staff concludes that there would not be
a significant cumulative radiological
impact to members of the public from
increased radioactive effluents from St.
Lucie Units 1 and 2 at the proposed EPU
operation.
As previously evaluated, the licensee
has a radiation protection program that
maintains worker doses within the dose
limits in 10 CFR part 20 during all
phases of St. Lucie Units 1 and 2
operations. The NRC expects continued
compliance with regulatory dose limits
during operation at the proposed EPU
power level. Therefore, the NRC
concludes that there would not be a
significant cumulative radiological
impact to plant workers from operation
of St. Lucie Units 1 and 2 at the
proposed EPU levels.
Radiological Impacts Summary
As discussed previously, the
proposed EPU would not result in any
significant radiological impacts. Table 2
summarizes the radiological
environmental impacts of the proposed
EPU at St. Lucie Units 1 and 2.
TABLE 2—SUMMARY OF RADIOLOGICAL ENVIRONMENTAL IMPACTS
Radioactive Gaseous Effluents .......
Radioactive Liquid Effluents ...........
Occupational Radiation Doses .......
Offsite Radiation Doses ..................
Radioactive Solid Waste .................
Spent Nuclear Fuel .........................
Postulated Design-Basis Accident
Doses.
Cumulative Radiological .................
Amount of additional radioactive gaseous effluents generated would be handled by the existing system.
Amount of additional radioactive liquid effluents generated would be handled by the existing system.
Occupational doses would continue to be maintained within NRC limits.
Radiation doses to members of the public would remain below NRC and EPA radiation protection standards.
Amount of additional radioactive solid waste generated would be handled by the existing system.
The spent fuel characteristics will remain within the bounding criteria used in the impact analysis in 10
CFR part 51, Table S–3 and Table S–4.
Calculated doses for postulated design-basis accidents would remain within NRC limits.
Radiation doses to the public and plant workers would remain below NRC and EPA radiation protection
standards.
pmangrum on DSK3VPTVN1PROD with NOTICES
Alternatives to the Proposed Action
Alternative Use of Resources
As an alternative to the proposed
action, the NRC considered denial of the
proposed EPU (i.e., the ‘‘no-action’’
alternative). Denial of the application
would result in no change in the current
environmental impacts. However, if the
EPU was not approved for St. Lucie Unit
1, other agencies and electric power
organizations may be required to pursue
other means, such as fossil fuel or
alternative fuel power generation, in
order to provide electric generation
capacity to offset future demand.
Construction and operation of such a
fossil-fueled or alternative-fueled
facility may create impacts in air
quality, land use, and waste
management significantly greater than
those identified for the proposed EPU at
St. Lucie Units 1 and 2. Furthermore,
the proposed EPU does not involve
environmental impacts that are
significantly different from those
originally indentified in the St. Lucie
Units 1 and 2 FESs, NUREG–1437, and
SEIS–11.
This action does not involve the use
of any different resources than those
previously considered in the FESs or
SEIS–11.
VerDate Mar<15>2010
14:40 Jan 05, 2012
Jkt 226001
Agencies and Persons Consulted
In accordance with its stated policy,
on December 8, 2011, the NRC
consulted with the State of Florida
official regarding the environmental
impact of the proposed action. The State
official had no comments.
III. Draft Finding of No Significant
Impact
On the basis of the EA, the NRC
concludes that granting the proposed
EPU license amendment is not expected
to cause impacts significantly greater
than current operations. Therefore, the
proposed action of implementing the
EPU for St. Lucie Units 1 and 2 will not
have a significant effect on the quality
of the human environment because no
significant permanent changes are
involved and the temporary impacts are
within previously disturbed areas at the
site and the capacity of the plant
systems. Accordingly, the NRC has
PO 00000
Frm 00048
Fmt 4703
Sfmt 9990
determined it is not necessary to
prepare an environmental impact
statement for the proposed action. A
final determination to prepare an
environmental impact statement or a
final finding of no significant impact
will not be made until the public
comment period closes.
For further details on the proposed
action, see the licensee’s application
dated November 22, 2010, for Unit 1
and February 25, 2011, for Unit 2.
For the Nuclear Regulatory Commission.
Dated at Rockville, Maryland, this 28th day
of December 2011.
Siva P. Lingam,
Chief (Acting), Plant Licensing Branch II–2,
Division of Operating Reactor Licensing,
Office of Nuclear Reactor Regulation.
[FR Doc. 2012–32 Filed 1–5–12; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\06JAN1.SGM
06JAN1
Agencies
[Federal Register Volume 77, Number 4 (Friday, January 6, 2012)]
[Notices]
[Pages 813-822]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-32]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-335 and 50-389; NRC-2011-0302]
Draft Environmental Assessment and Draft Finding of No
Significant Impact Related to the Proposed License Amendment To
Increase the Maximum Reactor Power Level: Florida Power & Light
Company, St. Lucie Plant, Units 1 and 2
AGENCY: Nuclear Regulatory Commission.
ACTION: Draft environmental assessment and finding of no significant
impact; opportunity to comment.
-----------------------------------------------------------------------
DATES: Comments must be filed by February 6, 2012. Any potential party
as defined in Title 10 of the Code of Federal Regulations (10 CFR) 2.4
who believes access to Sensitive Unclassified Non-Safeguards
Information and/or Safeguards Information is necessary to respond to
this notice must request document access by January 17, 2012.
ADDRESSES: Please include Docket ID NRC-2011-0302 in the subject line
of your comments. For additional instructions on submitting comments
and instructions on accessing documents related to this action, see
``Submitting Comments and Accessing Information'' in the SUPPLEMENTARY
INFORMATION section of this document. You may submit comments by any
one of the following methods:
Federal Rulemaking Web Site: Go to https://www.regulations.gov and search for documents filed under Docket ID NRC-
2011-0302. Address questions about NRC dockets to Carol Gallagher,
telephone: (301) 492-3668; email: Carol.Gallagher@nrc.gov.
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: TWB-05-B01M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
Fax comments to: RADB at (301) 492-3446.
SUPPLEMENTARY INFORMATION:
Submitting Comments and Accessing Information
Comments submitted in writing or in electronic form will be posted
on the NRC Web site and on the Federal rulemaking Web site, https://www.regulations.gov. Because your comments will not be edited to remove
any identifying or contact information, the NRC cautions you against
including any information in your submission that you do not want to be
publicly disclosed.
The NRC requests that any party soliciting or aggregating comments
received from other persons for submission to the NRC inform those
persons that the NRC will not edit their comments to remove any
identifying or contact information, and therefore, they should not
include any information in their comments that they do not want
publicly disclosed.
You can access publicly available documents related to this
document using the following methods:
NRC's Public Document Room (PDR): The public may examine
and have copied, for a fee, publicly available documents at the NRC's
PDR, O1-F21, One White Flint North, 11555 Rockville Pike, Rockville,
Maryland 20852.
NRC's Agencywide Documents Access and Management System
(ADAMS): Publicly available documents created or received at the NRC
are available online in the NRC Library at https://www.nrc.gov/reading-rm/adams.html. From this page, the public can gain entry into ADAMS,
which provides text and image files of the NRC's public documents. If
you do not have access to ADAMS or if there are problems in accessing
the documents located in ADAMS, contact the NRC's PDR reference staff
at 1-(800) 397-4209, (301) 415-4737, or by email to
pdr.resource@nrc.gov. The application for amendment, dated November 22,
2010, contains proprietary information and, accordingly, those portions
are being withheld from public disclosure. A redacted version of the
application for amendment, dated December 15, 2010, is available
electronically under ADAMS Accession No. ML103560415.
Federal Rulemaking Web Site: Public comments and
supporting materials related to this notice can be found at https://www.regulations.gov by searching on Docket ID NRC-2011-0302.
FOR FURTHER INFORMATION CONTACT: Tracy Orf, Project Manager, Plant
Licensing Branch II-2, Division of Operating Reactor Licensing, Office
of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001. Telephone: (301) 415-2788; Fax number: (301)
415-1222; email: Tracy.Orf@nrc.gov.
I. Introduction
The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an amendment for Renewed Facility Operating License Nos.
DPR-67 and NPF-16, issued to Florida Power & Light Company (FPL, the
licensee) for operation of St. Lucie Plant, Units 1 and
[[Page 814]]
2 (St. Lucie 1 and 2), for a license amendment to increase the maximum
thermal power from 2,700 megawatts thermal (MWt) to 3,020 MWt for each
unit. In accordance with 10 CFR Section 51.21, the NRC has prepared
this draft Environment Assessment (EA) and draft Finding of No
Significant Impact (FONSI) for the proposed action. This represents a
power increase of 11.85 percent over the current licensed thermal
power. In 1981, FPL received approval from the NRC to increase its
power by 5.47 percent to the current power level of 2,700 MWt.
The NRC staff did not identify any significant environmental impact
associated with the proposed action based on its evaluation of the
information provided in the licensee's application and other available
information. The draft EA and draft FONSI are being published in the
Federal Register with a 30-day public comment period ending February 6,
2012.
II. Environmental Assessment
Plant Site and Environs: St. Lucie Nuclear Plant consists of
approximately 1,130 acres (457 hectares) in Sections 16 and 17,
Township 36 South, Range 41 East on Hutchinson Island in unincorporated
St. Lucie County, Florida. The St. Lucie Nuclear Plant is located
between the Atlantic Ocean to the east and a tidally influenced
estuary, the Indian River Lagoon, to the west. The plant is located on
Hutchinson Island between Big Mud Creek to the north and Indian River
to the south on an area previously degraded through flooding, drainage,
and channelization for mosquito control projects. The nearest towns
from the plant site on the Atlantic coast are Port St. Lucie,
approximately 2.5 miles (mi) (4 kilometers (km)) southwest, and Fort
Pierce, approximately 4 mi (6.4 km) northwest of the plant. The St.
Lucie Nuclear Plant has two light-water reactors (Units 1 and 2), each
designed by Combustion Engineering for a net electrical power output of
839 megawatts electric. FPL fully owns St. Lucie Unit 1 and has
operated it since March 1, 1976. FPL also solely operates St. Lucie
Unit 2, which began operations on April 6, 1983, and is co-owned by
FPL, Orlando Utilities Commission, and Florida Municipal Power Agency.
The St. Lucie Nuclear Plant withdraws cooling water from the
Atlantic Ocean through three offshore cooling water intakes with
velocity caps. The ocean water is drawn through buried pipes into the
plant's L-shaped intake canal to the eight intake pumps that circulate
the non-contact cooling water through the plant. Two mesh barrier nets,
one net of 5-inches (in) (12.7-centimeters (cm)) mesh size and the
other of 8-in (20.3-cm) mesh size, and one rigid barrier located
sequentially in the intake canal reduce the potential loss of large
marine organisms, mostly sea turtles. Water passes through a trash rack
made of 7.6 cm (3 in) spaced vertical bars and a 1-cm (\3/8\-in) mesh
size traveling screen, against which marine organisms that have passed
through the nets are impinged, and into eight separate intake wells
(four per unit) where it is pumped to a circulating-water system and an
auxiliary cooling water system at each unit. The majority of the water
goes to a once-through circulating-water system to cool the main plant
condensers. The system has a nominal total capacity of 968,000 gallons
per minute (gpm) (61,070 liters per second (L/s)). The auxiliary
cooling water systems for St. Lucie Units 1 and 2 are also once-through
cooling systems, but use much less water [up to 58,000 gpm (3,660 L/s)]
than the circulating-water systems. Marine life that passes through the
screens becomes entrained in the water that passes through the plant
and is subject to thermal and mechanical stresses. The plant is also
equipped with an emergency cooling water intake canal on the west side
that can withdraw Indian River Lagoon water through Big Mud Creek, but
this pathway is closed during normal plant operation.
The heated water from the cooling water systems flows to a
discharge canal and then through two offshore discharge pipes beneath
the beach and dune system back to the Atlantic Ocean. One 12-foot (ft)
(3.6-meter (m))-diameter discharge pipe extends approximately 1,500 ft
(457 m) offshore and terminates in a two-port ``Y'' diffuser. A second
16-ft (4.9-m)-diameter discharge pipe extends about 3,400 ft (1,040 m)
from the shoreline and terminates with a multiport diffuser. This
second pipe has fifty-eight 16-in (41-cm)-diameter ports spaced 24 ft
(7.3 m) apart along the last 1,400 ft (430 m) of pipe farthest
offshore. The discharge of heated water through the diffusers on the
discharge pipes ensures distribution over a wide area and rapid and
efficient mixing with ocean water.
Background Information on the Proposed Action
By application dated November 22, 2010 (Unit 1), and February 25,
2011 (Unit 2), the licensee requested an amendment for an extended
power uprate (EPU) for St. Lucie Nuclear Plant to increase the licensed
thermal power level from 2,700 MWt to 3,020 MWt for each unit, which
represents an increase of 11.85 percent above the current licensed
thermal power. This proposed change in core thermal level requires an
NRC federal action to consider amending the facility's operating
license prior to the licensee implementing the EPU. The NRC considers
the proposed action an EPU because it exceeds the typical 7-percent
power increase that can be accommodated with only minor plant changes.
EPUs typically involve extensive modifications to the nuclear steam
supply system contained within the plant buildings.
Although not part of the NRC federal action, changes from the
current operations at St. Lucie Nuclear Plant would occur if the NRC
approves the EPU. FPL plans to make the physical changes to the non-
nuclear plant components that are needed in order to implement the
proposed EPU. The modifications are scheduled to be implemented for
Unit 1 during the fall 2011 outage starting in November 2011 and are
expected to be completed by the spring of 2012. Unit 2 modifications
are scheduled to be implemented during the summer 2012 outage starting
in June 2012 and are expected to be completed by the fall of 2012. The
outage durations for both units are expected to be longer than for a
routine 35-day outage. The actual power uprate, if approved by the NRC,
constitutes a 12 percent power uprate and includes an additional 1.7
percent measurement uncertainty recapture for each unit. As part of the
proposed EPU project, FPL would release heated water with a proposed
temperature increase of 2 degrees Fahrenheit ([deg]F) (1.1 degrees
Celsius ([deg]C)) above the current discharge temperature through the
discharge structures into the Atlantic Ocean.
Approximately 800 people are currently employed at St. Lucie Units
1 and 2 on a full-time basis. FPL estimates this workforce will be
augmented by an additional 1,000 construction workers on average per
outage during the proposed EPU-related activities with a potential peak
of 1,400 additional construction workers. The increase of workers would
be larger than the number of workers required for a routine outage;
however, the peak construction workforce would be smaller than the FPL
reported peak workforce for previous outages involving replacement of
major components.
The Need for the Proposed Action
FPL states in its environmental report that the proposed action is
intended to provide an additional supply of electric
[[Page 815]]
generation in the State of Florida without the need to site and
construct new facilities, or to impose new sources of air or water
discharges to the environment. FPL has determined that increasing the
electrical output of St. Lucie 1 and 2 is the most cost-effective
option to meet the demand for electrical energy while enhancing fuel
diversity and minimizing environmental impacts, including the avoidance
of greenhouse gas emissions.
Environmental Impacts of the Proposed Action
As part of the licensing process for St. Lucie Units 1 and 2, the
U.S. Atomic Energy Commission published a Final Environmental Statement
(FES) in 1973 for Unit 1, and the NRC published an FES in 1982 for Unit
2 (NUREG-0842). In the two FESs, the NRC staff considered the best data
available to the NRC at the time to predict the environmental impacts
that could result from the operation of St. Lucie Units 1 and 2 over
their licensed lifetimes. In addition, the NRC published an
Environmental Impact Statement (EIS) in May 2003 associated with the
license renewal for St. Lucie Units 1 and 2. The 2003 EIS evaluated the
environmental impacts of operating the St. Lucie Nuclear Plant for an
additional 20 years beyond its then-current operating license,
extending the operational life of Unit 1 until 2036 and Unit 2 until
2043. The NRC determined that the environmental impacts of license
renewal would be small. The NRC staff's evaluation is contained in
NUREG-1437, ``Generic Environmental Impact Statement for License
Renewal of Nuclear Plants, Supplement 11, Regarding St. Lucie Units 1
and 2'' (Supplemental EIS-11 (SEIS-11)) [Agencywide Documents Access
and Management System (ADAMS) Accession No. ML031360705]. The NRC staff
used information from FPL's license amendment request (LAR) (ADAMS
Accession No. ML103560419) and SEIS-11 to perform this EA for the
proposed EPU.
FPL's application states that it would implement the proposed EPU
without extensive changes to buildings or to other plant areas outside
of buildings. FPL proposes to perform all necessary physical plant
modifications in existing buildings at St. Lucie Units 1 and 2 or along
the existing electrical transmission line right of way (ROW). With the
exception of the high-pressure turbine rotor replacement, the required
plant modifications would be generally small in scope. Other plant
modifications would include installing a new digital turbine control
system; providing additional cooling for some plant systems; modifying
feedwater and condensate systems; accommodating greater steam and
condensate flow rates; adjusting the current onsite power system to
compensate for increases in electrical loading; and upgrading
instrumentation to include minor items such as replacing parts,
changing setpoints, and modifying software.
FPL would use a vehicle and helicopter for transmission line
modifications proposed along the existing overhead electrical
transmission line ROW. The vehicle would transport personnel and a
spool of overhead wire as a helicopter holds and moves the wire into
place for the stringing activities. Although the modifications are part
of the proposed EPU, this type and extent of activity along the ROW is
included in existing maintenance permits and licenses.
Nonradiological Impacts
Land Use and Aesthetic Impacts
Potential land use and aesthetic impacts from the proposed EPU
include proposed plant modifications at St. Lucie Nuclear Plant. While
FPL proposes some plant modifications, most plant changes related to
the proposed EPU would occur within existing structures, with the
exception of modifications along the electrical transmission line ROW.
As described in the licensee's application, the proposed electrical
transmission modifications would include the addition of subconductor
spacers, an overhead wire, and replacement of relay protection
electronics. The overhead wire would function as a ground for relay
protection of the transmission lines. FPL would install these
transmission line modifications via helicopter. The only land use
activity FPL expects to occur on the ground along the ROW would be the
periodic need to park a truck or trailer containing a spool of wire
that would be strung but would not extend outside of the existing ROW
area. The NRC expects little or no observable change in the appearance
of the transmission lines as a result of the electrical transmission
line modifications. Maintenance of the electrical transmission line ROW
(tree trimming, mowing, and herbicide application) would continue after
EPU implementation. The NRC does not expect land use or aesthetic
changes for the proposed EPU along the transmission line ROW.
No new construction would occur outside of existing plant areas,
and no expansion of buildings, roads, parking lots, equipment lay-down
areas, or storage areas are required to support the proposed EPU. FPL
would use existing parking lots, road access, equipment lay-down areas,
offices, workshops, warehouses, and restrooms during plant
modifications. Therefore, land use conditions and visual aesthetics
would not change significantly at St. Lucie Nuclear Plant, and the NRC
expects no significant impact from EPU-related plant modifications on
land use and aesthetic resources in the vicinity of St. Lucie Nuclear
Plant.
Air Quality Impacts
Because of its coastal location, meteorological conditions
conducive to high air pollution are infrequent at the St. Lucie Nuclear
Plant. The plant is located within the South Florida Intrastate Air
Quality Control Region. In addition, the Central Florida Intrastate Air
Quality Control Region and the Southwest Florida Intrastate Air Quality
Control Region are within 50 mi (80.5 km) of the St. Lucie Nuclear
Plant. These regions are designated as being in attainment or
unclassifiable for all criteria pollutants in the U.S. Environmental
Protection Agency's (EPA) 40 CFR 81.310.
Diesel generators, boilers, and other activities and facilities
associated with St. Lucie Units 1 and 2 emit pollutants. The Florida
Department of Environmental Protection (FDEP) regulates emissions from
these sources under Air Permit 1110071-006-AF. The FDEP reported no
violations at the St. Lucie Nuclear Plant in the last 5 years. The NRC
expects no changes to the emissions from these sources because of the
EPU.
During EPU implementation, some minor and short duration air
quality impacts would occur from other non-regulated sources. Vehicles
of the additional outage workers needed for EPU implementation would
generate the majority of air emissions during the proposed EPU-related
modifications. FPL plans to complete the construction activities
associated with the EPU, if approved by the NRC, by the spring of 2012
for Unit 1 and by the fall of 2012 for Unit 2. The outage durations for
both units are expected to be longer than for a routine 35-day outage.
The NRC expects air emissions from the EPU workforce, truck deliveries,
and construction/modification activities would not be significantly
greater than previous modification activities or refueling outages at
the St. Lucie Nuclear Plant. In addition, FPL would perform the
majority of the EPU work inside existing buildings and would not result
in changes to outside air quality. The NRC expects no significant
impacts
[[Page 816]]
to regional air quality from the proposed EPU beyond those air impacts
evaluated for SEIS-11 including potential minor and temporary impacts
from worker activity.
Water Use Impacts
Groundwater
FPL has approval from the City of Fort Pierce and the Fort Pierce
Utilities Authority to use freshwater for potable and sanitary
purposes. Although this freshwater comes from groundwater sources
pumped from the mainland, St. Lucie Nuclear Plant does not use
groundwater in any of its cooling systems and has no plans for
groundwater use as part of plant operations in the future. The plant
currently uses approximately 131,500 gallons (498 m\3\) of freshwater
per day and uses seawater from the Atlantic Ocean for noncontact
cooling water. No production wells are present on the plant site for
either domestic-type water uses or industrial use. FPL does not
discharge to groundwater at the plant site or on the mainland, and the
plant's industrial wastewater facility permit (IWFP) does not apply to
groundwater.
Under the EPU, FPL does not expect to significantly change the
amount of freshwater use or supply source. With an average estimated
increase of 1,000 workers supporting EPU construction activities, the
NRC expects potable water use to increase during the outage and return
back to the regular operating levels after EPU implementation. It is
unlikely this potential increase in temporary groundwater use during
the EPU construction activities would have any effect on other local
and regional groundwater users. FPL has no use restrictions on the
amount of water supplied by the City of Fort Pierce and the Fort Pierce
Utilities Authority. The NRC expects no significant impact on
groundwater resources during proposed EPU construction activities or
following EPU implementation.
Surface Water
The NRC staff evaluated the potential effects of releasing heated
water with a proposed temperature increase of 2 [deg]F (1.1 [deg]C)
above the current discharge temperature through the discharge pipes
into the Atlantic Ocean as part of the proposed EPU project. FDEP
regulates the Florida Surface Water Quality Standards through an IWFP,
which also establishes the maximum area subject to temperature increase
(mixing zone), maximum discharge temperatures, and chemical monitoring
requirements with limits specified.
The plant injects chlorine in the form of sodium hypochlorate into
seawater upstream of the intake cooling water system in regulated
quantities to control microorganisms. Because FDEP regulates discharges
and requires chemical monitoring, the NRC expects that the authorized
discharges will not exceed the IWFP limitations after EPU
implementation.
In the IWFP, FDEP has issued the plant a temporary variance for a
temperature increase of heated water discharge from 113 [deg]F (45
[deg]C) above ambient temperature to the proposed thermal discharge of
115 [deg]F (46.1 [deg]C) above ambient temperature after EPU completion
for Units 1 and 2 on the condition that no adverse affects are found
based on FPL study results. The proposed EPU will not result in an
increase in the amount or rate of water withdrawn from or discharged to
the Atlantic Ocean. FPL conducted a thermal discharge study for the
proposed EPU-related increase in discharge water temperature (ADAMS
Accession No. ML100830443) that predicts an increase in the extent of
the thermal plume (mixing zone). The ambient water affected by the
absolute temperature increase beyond the existing mixing zone would be
less than 25 ft (7.6 m) vertically or horizontally for the two-port
``Y'' diffuser and less than 6 ft (1.8 m) in any direction for the
multiport diffuser.
As part of its operating license renewal, FPL consulted with the
Florida Department of Community Affairs (FDCA) for a review of coastal
zone consistency. Based on the information FDCA reviewed, it determined
that the licensing renewal action would be consistent with the Florida
Coastal Management Program (FCMP). FDCA, in partnership with the FDEP,
administers the FCMP and has the authority to review the proposed EPU
action for coastal zone consistency.
Aquatic Resource Impacts
The potential impacts to aquatic biota from the proposed action
could include impingement of aquatic life on barrier nets, trash racks,
and traveling screens; entrainment of aquatic life through the cooling
water intake structures and into the cooling water systems; and effects
from the discharge of chemicals and heated water.
Because the proposed EPU will not result in an increase in the
amount or velocity of water being withdrawn from or discharged to the
Atlantic Ocean, the NRC expects no increase in aquatic impacts from
impingement and entrainment beyond the current impact levels: all
organisms impinged on the trash racks and traveling screens would be
killed, as would most, if not all, entrained organisms. FPL would
continue to rescue and release sea turtles and other endangered species
trapped by the barrier nets in the intake canal. In addition, FPL's
IWFP requires FPL to monitor aquatic organism entrapment in the intake
canal, and, if unusually large numbers of organisms are entrapped, to
submit to the FDEP a plan to mitigate such entrapment.
The predicted 2 [deg]F (1.1 [deg]C) temperature increase from the
diffusers and increased size of the mixing zone because of the proposed
EPU would increase thermal exposure to aquatic biota at the St. Lucie
Nuclear Plant in the vicinity of the discharge locations. The thermal
discharge study conducted for the proposed EPU predicts no increase in
temperature higher than 96 [deg]F (35.5 [deg]C) within 6 ft (1.8 m) of
the bottom of the ocean floor and within 24 ft (7.3 m) from the ocean
surface because of heated water discharged from the multiport diffuser.
The same study also predicts that heated water discharged from the
``Y'' diffuser would not increase the ocean water temperature higher
than 96 [deg]F (35.5 [deg]C) within 2 ft (0.6 m) of the bottom of the
ocean floor and within 25 ft (17 m) from the ocean surface. Based on
this analysis, surface water temperature would remain below 94 [deg]F
(34.4 [deg]C). Thermal studies conducted for the St. Lucie Nuclear
Plant prior to its operation and summarized in SEIS-11 predicted there
would be minimal impacts to aquatic biota from diffuser discharges that
result in a surface temperature less than 97 [deg]F (36.1 [deg]C).
Because the NRC expects the surface water temperature not to exceed 94
[deg]F (34.4 [deg]C) because of the proposed EPU, the NRC staff
concludes that there are no significant impacts to aquatic biota from
the proposed EPU.
Although the proposed increase in temperature after EPU
implementation would exceed the Florida Surface Water Quality Standards
regulated by FDEP, FDEP is continuing to assess this action by
requiring FPL to conduct studies as part of an IWFP variance. If the
study results are insufficient to adequately evaluate environmental
changes, or if the data indicates a significant degradation to aquatic
resources by exceeding Florida Surface Water Quality Standards or is
inconsistent with the FCMP, FDEP could enforce additional abatement or
mitigation measures to reduce the environmental impacts to acceptable
levels. If the NRC approves the proposed EPU, the NRC does not expect
aquatic resource impacts significantly greater than current
[[Page 817]]
operations because state agencies will continue to assess study results
and the effectiveness of current FPL environmental controls. FDEP could
impose additional limits and controls on FPL if the impacts are larger
than expected. If FDCA and FDEP review the study results and allow FPL
to operate at the proposed EPU level, the NRC has reasonable confidence
as discussed above that the increase in thermal discharge will not
result in significant impacts on aquatic resources beyond the current
impacts that occur during plant operations.
Terrestrial Resources Impacts
The St. Lucie Nuclear Plant is on a relatively flat, sheltered area
of Hutchinson Island with red mangrove swamps on the western side of
the island that gradually slope downward to a mangrove fringe bordering
the intertidal shoreline of the Indian River Lagoon. East of the
facility, land rises from the ocean shore to form dunes and ridges
approximately 15 ft (4.5 m) above mean low water. Tropical hammock
areas are present north of the discharge canal, and additional red
mangrove swamps are present north of Big Mud Creek. Habitat in the
electrical transmission line ROW is a mixture of human-altered areas,
sand pine scrub, prairie/pine flatwoods, wet prairie, and isolated
marshes.
Impacts that could potentially affect terrestrial resources include
disturbance or loss of habitat, construction and EPU-related noise and
lighting, and sediment transport or erosion. FPL plans to conduct
electrical transmission line modifications that would require a
periodic need to park a truck or trailer containing a spool of wire
that would be strung. The NRC concluded in SEIS-11 that no bird
mortalities were reported up to that time associated with the
electrical transmission lines and predicted that FPL maintenance
practices along the ROW would likely have little or no detrimental
impact on the species potentially present in or near the electrical
transmission ROW. Because FPL proposes a similar type and extent of
land disturbance during typical maintenance of the electrical
transmission line ROW for the EPU modifications, the NRC expects the
proposed transmission line modifications would not result in any
significant changes to land use or increase habitat loss or
disturbance, sediment transport, or erosion beyond typical maintenance
impacts. Noise and lighting would not adversely affect terrestrial
species beyond effects experienced during previous outages because
construction EPU modification activities would take place during outage
periods, which are typically periods of heightened activity. Thus, the
NRC expects no significant impacts on terrestrial biota associated with
the proposed action.
Threatened and Endangered Species Impacts
A number of species in St. Lucie County are listed as threatened or
endangered under the Federal Endangered Species Act, and other species
are designated as meriting special protection or consideration. These
include birds, fish, aquatic and terrestrial mammals, flowering plants,
insects, and reptiles that could occur on or near St. Lucie Units 1 and
2 facility areas and possibly along the electrical transmission line
ROW. The most common occurrences of threatened or endangered species
near St. Lucie Units 1 and 2 are five species of sea turtles that nest
on Hutchinson Island beaches: loggerhead turtles (Caretta caretta),
Atlantic green turtles (Chelonia mydas), Kemp's ridley turtles
(Lepidochelys kempii), leatherback turtles (Dermochelys coriacea), and
hawksbill turtles (Eretmochelys imbricata). FPL has a mitigation and
monitoring program in place for the capture-release and protection of
sea turtles that enter the intake canal. The West Indian manatee
(Trichechus manatus) also has been documented at the St. Lucie Nuclear
Plant. Designated critical habitat for the West Indian manatee is
located along the Indian River west of Hutchinson Island. The NRC staff
assessed potential impacts on the West Indian manatee from St. Lucie
Nuclear Plant in SEIS-11. No other critical habitat areas for
endangered, threatened, or candidate species are located at the St.
Lucie Nuclear Plant site or along the transmission line ROW.
The following table identifies the species that the NRC considered
in this EA that were not previously assessed for SEIS-11 because the
species were not listed at that time.
Table of Federally Listed Species Occurring in St. Lucie County Not
Previously Assessed in SEIS-11
------------------------------------------------------------------------
Scientific name Common name ESA status \(a)\
------------------------------------------------------------------------
Birds:
Calidris canutus ssp. red knot............ Candidate.
Rufa.
Charadrius melodus...... piping plover....... T.
Dendroica kirtlandii.... Kirtland's warbler.. E.
Grus americana.......... whooping Crane \(b)\ EXPN, XN.
Fish:
Pristis pectinata....... smalltooth sawfish.. E.
Mammals:
Puma concolor........... Puma................ T/SA.
Reptiles:
Crocodylus acutus....... American crocodile.. T.
Gopherus polyphemus..... gopher tortoise Candidate.
\(c)\.
------------------------------------------------------------------------
\(a)\ E = endangered; T = threatened; T/SA = threatened due to
similarity of appearance; EXPN, XN = experimental, nonessential.
\(b)\ Experimental, nonessential populations of endangered species
(e.g., red wolf) are treated as threatened species on public land, for
consultation purposes, and as species proposed for listing on private
land.
\(c)\ The gopher tortoise is not listed by the FWS as occurring in St.
Lucie County. The core of the species' current distribution in the
eastern portion of its range occurs in central and north Florida (76
FR 45130), and FPL has reported the species' occurrence on the site
and in the electrical transmission line right-of-way.
Source: U.S. Fish and Wildlife Service.
The NRC has consulted with the National Marine Fisheries Service
(NMFS) since 1982 regarding sea turtle kills, captures, or incidental
takes. A 2001 NMFS biological opinion analyzed the effects of the
circulating cooling water system on certain sea turtles at the St.
Lucie Nuclear Plant. The 2001 NMFS biological opinion provides for
limited incidental takes of threatened or endangered sea turtles.
Correspondence between the licensee, U.S. Fish and
[[Page 818]]
Wildlife Service, and NMFS in connection with the 2003 license renewal
environmental review indicated that effects to federal endangered,
threatened, or candidate species, including a variety of sea turtles
and manatees, would not significantly change as a result of issuing a
license renewal for the St. Lucie Nuclear Plant. The NRC reinitiated
formal consultation with NMFS in 2005 after the incidental take of a
smalltooth sawfish (Pristis pectinata). The NRC added sea turtles to
the reinitiation of formal consultation with NMFS in 2006 after the St.
Lucie Nuclear Plant exceeded the annual incidental take limit for sea
turtles. The NRC provided NMFS with a biological assessment in 2007
(ADAMS Accession No. ML071700161) as an update regarding effects on
certain sea turtle species up to that time. The NRC expects a
biological opinion from NMFS in response to ongoing consultation, but
does not expect the biological opinion to affect the conclusions in
this draft EA.
As described in the Aquatic Resources Impacts section, the expected
temperature increase of plant water discharged to the Atlantic Ocean
could increase thermal exposure to aquatic biota, including the
threatened and endangered sea turtles found at the site. The NRC
expects the FPL capture-release and monitoring program for sea turtles
and NRC interactions with NMFS regarding incidental takes to continue
under the terms and conditions of the new biological opinion.
Therefore, the NRC expects the proposed EPU would not change the
effects of plant operation on threatened and endangered species.
Planned construction-related activities associated with the
proposed EPU primarily involve changes to existing structures, systems,
and components internal to existing buildings and would not involve
earth disturbance, with the exception of planned electrical
transmission line modifications. Traffic and worker activity in the
developed parts of the plant site during the combined refueling outages
and EPU modifications would be somewhat greater than a normal refueling
outage. As described in the Terrestrial Resources Impacts section,
electrical transmission line modifications may require truck use within
the transmission line ROW. The NRC concluded in SEIS-11 that
transmission line maintenance practices for the FPL license renewal
would not lower terrestrial habitat quality or cause significant
changes in wildlife populations. Because the proposed EPU operations
would not result in any significant changes to the expected
transmission maintenance activities evaluated for the operating license
renewal, the proposed EPU transmission modifications also should have
little effect on threatened and endangered terrestrial species. The
effects of changes to the terrestrial wildlife habitat on the St. Lucie
Nuclear Plant site from the proposed EPU should not exceed those
potential effects on terrestrial wildlife evaluated in SEIS-11,
including potential minor and temporary impacts from worker activity.
Historic and Archaeological Resources Impacts
Records at the Florida Master File in the Florida Division of
Historical Resources identify five known archaeological sites located
on or immediately adjacent to the property boundaries for the St. Lucie
Nuclear Plant, although no archaeological and historic architectural
finds have been recorded on the site. None of these sites are listed on
the National Register for Historic Places (NRHP). The NRHP lists
sixteen properties in St. Lucie County including one historic district.
The Captain Hammond House in White City, approximately 6 mi (10 km)
from St. Lucie Nuclear Plant, is the nearest property listed on the
NRHP.
A moderate to high likelihood for the presence of significant
prehistoric archaeological remains occurs along Blind Creek and the
northern end of the St. Lucie Nuclear Plant boundary. As previously
discussed, all EPU-related modifications would take place within
existing buildings and facilities and the electrical transmission line
ROW, which are not located near Blind Creek or the northern FPL
property boundary. Because no change in ground disturbance or
construction-related activities would occur outside of previously
disturbed areas and existing electrical transmission line ROW, the NRC
expects no significant impact from the proposed EPU-related
modifications on historic and archaeological resources.
Socioeconomic Impacts
Potential socioeconomic impacts from the proposed EPU include
temporary increases in the size of the workforce at St. Lucie Units 1
and 2, and associated increased demand for goods, public services, and
housing in the region. The proposed EPU also could generate increased
tax revenues for the state and surrounding counties.
Currently, approximately 800 full-time employees work at the St.
Lucie Nuclear Plant. FPL estimates a temporary increase in the size of
the workforce during the fall 2011 and summer 2012 refueling outages.
During the refueling outages, FPL expects the average number of workers
to peak by as many as 1,400 construction workers per day to implement
the EPU for each unit. The outage durations for both units are expected
to be longer than for a routine 35-day outage. Once EPU-related plant
modifications have been completed, the size of the refueling outage
workforce at St. Lucie Nuclear Plant would return to normal levels and
would remain similar to pre-EPU levels, with no significant increases
during future refueling outages. The size of the regular plant
operations workforce would be unaffected by the proposed EPU.
The NRC expects most of the EPU plant modification workers to
relocate temporarily to communities in St. Lucie, Martin, Indian River,
and Palm Beach Counties, resulting in short-term increases in the local
population along with increased demands for public services and
housing. Because plant modification work would be temporary, most
workers would stay in available rental homes, apartments, mobile homes,
and camper-trailers. The 2010 American Community Survey 1-year estimate
for vacant housing units reported 32,056 vacant housing units in St.
Lucie County; 18,042 in Martin County; 23,236 in Indian River County;
and 147,910 in Palm Beach County that could potentially ease the demand
for local rental housing. Therefore, the NRC expects a temporary
increase in plant employment for a short duration that would have
little or no noticeable effect on the availability of housing in the
region.
The additional number of refueling outage workers and truck
material and equipment deliveries needed to support EPU-related plant
modifications would cause short-term level of service impacts
(restricted traffic flow and higher incident rates) on secondary roads
in the immediate vicinity of St. Lucie Nuclear Plant. FPL expects
increased traffic volumes necessary to support implementation of the
EPU-related modifications during the refueling outage. The NRC
predicted transportation service impacts for refueling outages at St.
Lucie Nuclear Plant during its license renewal term would be small and
would not require mitigation. However, the number of temporary
construction workers the NRC evaluated for SEIS-11 was less than the
number of temporary construction workers required for the proposed EPU.
Based on this information and that EPU-related plant modifications
would occur during a normal refueling outage, there could be
[[Page 819]]
noticeable short-term (during certain hours of the day) level-of-
service traffic impacts beyond what is experienced during normal
outages. During periods of high traffic volume (i.e., morning and
afternoon shift changes), work schedules could be staggered and
employees and/or local police officials could be used to direct traffic
entering and leaving St. Lucie Nuclear Plant to minimize level-of-
service impacts.
The St. Lucie Nuclear Plant currently pays annual real estate
property taxes to the St. Lucie County school district, the County
Board of Commissioners, the County fire district, and the South Florida
Water Management District. The annual amount of future property taxes
the St. Lucie Nuclear Plant would pay could take into account the
increased value of St. Lucie Units 1 and 2 as a result of the EPU and
increased power generation.
Due to the short duration of EPU-related plant modification
activities, there would be little or no noticeable effect on tax
revenues generated by temporary workers residing in St. Lucie County.
Therefore, the NRC expects no significant socioeconomic impacts from
EPU-related plant modifications and operations under EPU conditions in
the vicinity of St. Lucie Nuclear Plant.
Environmental Justice Impact Analysis
The environmental justice impact analysis evaluates the potential
for disproportionately high and adverse human health and environmental
effects on minority and low-income populations that could result from
activities associated with the proposed EPU at St. Lucie Nuclear Plant.
Such effects may include biological, cultural, economic, or social
impacts. Minority and low-income populations are subsets of the general
public residing in the vicinity of St. Lucie Nuclear Plant, and all are
exposed to the same health and environmental effects generated from
activities at St. Lucie Units 1 and 2.
The NRC considered the demographic composition of the area within a
50-mi (80.5-km) radius of St. Lucie Units 1 and 2 to determine the
location of minority and low-income populations and whether the
proposed action may affect them. The NRC examined the geographic
distribution of minority and low-income populations within 50 mi (80.5
km) of the St. Lucie Units 1 and 2 using the U.S. Census Bureau (USCB)
data for 2000. Although the 2010 census occurred, the data is not yet
available in a format that provides the population information within a
specified radius of the site.
According to the U.S. Census Bureau (USCB) data for 2000 on
minority populations in the vicinity of St. Lucie Units 1 and 2, an
estimated 1.2 million people live within a 50-mi (80.5-km) radius of
the plant located within parts of nine counties. Minority populations
within 50 mi (80.5 km) comprise 27 percent (274,500 persons). The
largest minority group was African-American (approximately 135,250
persons or 13.3 percent), followed by Hispanic or Latino (approximately
111,000 persons or 11 percent). The 2000 census block groups containing
minority populations were concentrated in Gifford (Indian River
County), Fort Pierce (St. Lucie County), Pahokee (Palm Beach County
near Lake Okeechobee), the agricultural areas around Lake Okeechobee,
and Hobe Sound (Martin County).
The NRC examined low-income populations using the USCB data for
2000 and the 2010 American Community Survey 1-Year Estimate. According
to the 2000 census data, approximately 11 percent of the population
(111,000 persons) residing within 50 mi (80.5 km) of the St. Lucie
Nuclear Plant were considered low-income, living below the 2000 federal
poverty threshold of $8,350 per individual. According to the 2010
census estimate, approximately 14.1 percent of families and 18 percent
of individuals were determined to be living below the Federal poverty
threshold in St. Lucie County. The 2010 federal poverty threshold was
$22,050 for a family of four and $10,830 for an individual. The median
household income for St. Lucie County was approximately $38,671 and 13
percent lower than the median household income (approximately $44,409)
for Florida.
Environmental Justice Impact
Potential impacts to minority and low-income populations would
mostly consist of environmental and socioeconomic effects (e.g., noise,
dust, traffic, employment, and housing impacts). Radiation doses from
plant operations after the EPU are expected to continue to remain well
below regulatory limits.
Noise and dust impacts would be temporary and limited to onsite
activities. Minority and low-income populations residing along site
access roads could experience increased commuter vehicle traffic during
shift changes. Increased demand for inexpensive rental housing during
the EPU-related plant modifications could disproportionately affect
low-income populations; however, due to the short duration of the EPU-
related work and the availability of housing properties, impacts to
minority and low-income populations would be of short duration and
limited. According to the 2010 census information, there were
approximately 221,244 vacant housing units in St. Lucie County and the
surrounding three counties combined.
Based on this information and the analysis of human health and
environmental impacts presented in this EA, the proposed EPU would not
have disproportionately high and adverse human health and environmental
effects on minority and low-income populations residing in the St.
Lucie Nuclear Plant vicinity.
Nonradiological Cumulative Impacts
The NRC considered potential cumulative impacts on the environment
resulting from the incremental impact of the proposed EPU when added to
other past, present, and reasonably foreseeable future actions in the
vicinity of St. Lucie Nuclear Plant. For the purposes of this analysis,
past actions are related to the construction and licensing of St. Lucie
Units 1 and 2, present actions are related to current operations, and
future actions are those that are reasonably foreseeable through the
end of station operations including operations under the EPU.
The NRC concluded that there would be no significant cumulative
impacts to the resource areas air quality, groundwater, threatened and
endangered species, historical and archaeological resources in the
vicinity of St. Lucie Units 1 and 2 because the contributory effect of
ongoing actions within a region are regulated and monitored through a
permitting process (e.g., National Pollutant Discharge Elimination
System and 401/404 permits under the Clean Water Act) under State or
Federal authority. In these cases, impacts are managed as long as these
actions are in compliance with their respective permits and conditions
of certification.
Surface water and aquatic resources were examined for potential
cumulative impacts. The geographic boundary for potential cumulative
impacts is the area of the post-EPU thermal mixing zone. If the
proposed EPU is approved and is implemented, St. Lucie Units 1 and 2
are predicted to have a slightly larger and hotter mixing zone than
pre-uprate conditions during full flow and capacity. The NRC
anticipates that St. Lucie Units 1 and 2 will continue to operate post
EPU in full compliance with the requirements of the FDEP IWFP. FDEP
would evaluate FPL compliance with the IWFP.
Proposed EPU-related modifications for the electrical transmission
line ROW at the St. Lucie Nuclear Plant could
[[Page 820]]
affect land use, aesthetics, and terrestrial species. Improvements and
maintenance would be conducted according to Federal and State
regulations, permit conditions, existing procedures, and established
best management practices to minimize impacts to these resources.
Nevertheless, terrestrial wildlife and habitat may be lost, displaced,
or disturbed by noise and human presence during EPU-related work in the
electrical transmission line ROW. Less mobile animals, such as
reptiles, amphibians, and small mammals, would incur greater impacts
than more mobile animals, such as birds. The proposed electrical
transmission line modifications would neither change land use
activities expected during current operations nor change the current
aesthetic resources within view of the electrical transmission lines.
The greatest socioeconomic impacts from the proposed EPU and
continued operation of St. Lucie Units 1 and 2 would occur during the
fall 2011 and summer 2012 fuel outages. The increase in EPU-related
construction workforces would have a temporary effect on socioeconomic
conditions in local communities from the increased demand for temporary
housing, public services (e.g., public schools), and increased traffic.
Nonradiological Impacts Summary
As discussed previously, the proposed EPU would not result in any
significant nonradiological impacts. Table 1 summarizes the
nonradiological environmental impacts of the proposed EPU at St. Lucie
Units 1 and 2.
Table 1--Summary of Nonradiological Environmental Impacts
------------------------------------------------------------------------
------------------------------------------------------------------------
Land Use.......................... Proposed EPU-related activities are
not expected to cause significant
impacts on land use conditions and
aesthetic resources in the vicinity
of St. Lucie Units 1 and 2.
Air Quality....................... Temporary air quality impacts from
vehicle emissions related to EPU
construction workforce is not
expected to cause significant
impacts to air quality.
Water Use......................... Water use changes resulting from the
proposed EPU are not expected to
cause impacts greater than current
operations. No significant impact
on groundwater or surface water
resources.
Aquatic Resources................. The NRC expects no significant
changes to impacts caused by
current operation due to
impingement, entrainment, and
thermal discharges.
Terrestrial Resources............. The NRC expects no significant
impacts to terrestrial resources.
Threatened and Endangered Species. The proposed EPU would change
impacts from those caused by
current operations. The NRC expects
a NMFS to issue a biological
opinion on sea turtles and the
smalltooth sawfish in the near
future.
Historic and Archaeological No significant impact to historic
Resources. and archaeological resources on
site or in the vicinity of St.
Lucie Units 1 and 2.
Socioeconomics.................... No significant socioeconomic impacts
from EPU-related temporary increase
in workforce.
Environmental Justice............. No disproportionately high or
adverse human health and
environmental effects on minority
and low-income populations in the
vicinity of St. Lucie Units 1 and
2.
Cumulative Impacts................ The proposed EPU would not cause
impacts significantly greater than
current operations. To address
potential cumulative impacts for
surface water and aquatic
resources, a NMFS biological
opinion is expected with the
authority to impose limits on
nonradiological discharges to abate
any significant water quality and
ecology impacts.
------------------------------------------------------------------------
Radiological Impacts
Radioactive Gaseous and Liquid Effluents, Direct Radiation Shine, and
Solid Waste
St. Lucie Units 1 and 2 use waste treatment systems to collect,
process, recycle, and dispose of gaseous, liquid, and solid wastes that
contain radioactive material in a safe and controlled manner within NRC
and EPA radiation safety standards. The licensee's evaluation of plant
operation under proposed EPU conditions predict that no physical
changes would be needed to the radioactive gaseous, liquid, or solid
waste systems.
Radioactive Gaseous Effluents
Radioactive gaseous wastes are principally activation gases and
fission product radioactive noble gases resulting from process
operations, including continuous cleanup of the reactor coolant system,
gases used for tank cover gas, and gases collected during venting. The
licensee's evaluation determined that implementation of the proposed
EPU would not significantly increase the inventory of nonradioactive
carrier gases normally processed in the gaseous waste management
system, because plant system functions are not changing and the volume
inputs remain the same. The licensee's analysis also showed that the
proposed EPU would result in an increase (a bounding maximum, as
expected, of 13.2 percent for all noble gases, particulates,
radioiodines, and tritium) in the equilibrium radioactivity in the
reactor coolant, which in turn increases the radioactivity in the waste
disposal systems and radioactive gases released from the plant.
The licensee's evaluation concluded that the proposed EPU would not
change the radioactive gaseous waste system design function and
reliability to safely control and process the waste. The existing
equipment and plant procedures that control radioactive releases to the
environment will continue to be used to maintain radioactive gaseous
releases within the dose limits of 10 CFR 20.1302 and the as low as is
reasonably achievable (ALARA) dose objectives in 10 CFR part 50,
Appendix I.
Radioactive Liquid Effluents
Radioactive liquid wastes include liquids from reactor process
systems and liquids that have become contaminated. The licensee's
evaluation shows that the proposed EPU implementation would not
significantly increase the inventory of liquid normally processed by
the liquid waste management system. This is because the system
functions are not changing and the volume inputs remain the same. The
proposed EPU would result in an increase in the equilibrium
radioactivity in the reactor coolant (12.2 percent), which in turn
would impact the concentrations of radioactive nuclides in the waste
disposal systems.
Because the NRC does not expect the composition of the radioactive
material in the waste and the volume of radioactive material processed
through the system to significantly change, the current design and
operation of the radioactive liquid waste system will accommodate the
effects of the proposed EPU. The existing equipment and plant
procedures that control radioactive releases to the environment will
continue to be used to maintain
[[Page 821]]
radioactive liquid releases within the dose limits of 10 CFR 20.1302
and ALARA dose standards in 10 CFR part 50, Appendix I.
Occupational Radiation Dose Under EPU Conditions
The licensee stated that the in-plant radiation sources are
expected to increase approximately linearly with the proposed increase
in core power level of 12.2 percent. For the radiological impact
analyses, the licensee conservatively assumed an increase to the
licensed thermal power level from 2,700 MWt to 3,030 MWt or 12.2
percent, although the EPU request is for an increase to the licensed
thermal power level to 3,020 MWt, or 11.85 percent. To protect the
workers, the plant radiation protection program monitors radiation
levels throughout the plant to establish appropriate work controls,
training, temporary shielding, and protective equipment requirements so
that worker doses will remain within the dose limits of 10 CFR part 20
and ALARA.
In addition to the work controls implemented by the radiation
protection program, shielding is used throughout St. Lucie Units 1 and
2 to protect plant personnel against radiation from the reactor and
auxiliary systems. The licensee determined that the current shielding
design, which uses conservative analytical techniques to establish the
shielding requirements, is adequate to offset the increased radiation
levels that are expected to occur from the proposed EPU. The proposed
EPU is not expected to significantly affect radiation levels within the
plant, and therefore there would not be a significant radiological
impact to the workers.
Offsite Doses at EPU Conditions
The primary sources of offsite dose to members of the public from
St. Lucie Units 1 and 2 are radioactive gaseous and liquid effluents.
The licensee predicts that maximum annual total and organ doses from
liquid effluent releases would increase by 12.2 percent. As discussed
previously, operation under the proposed EPU conditions will not change
the ability of the radioactive gaseous and liquid waste management
systems to perform their intended functions. Also, there would be no
change to the radiation monitoring system and procedures used to
control the release of radioactive effluents in accordance with NRC
radiation protection standards in 10 CFR part 20 and 10 CFR part 50,
Appendix I.
Based on the previous information, the offsite radiation dose to
members of the public would continue to be within regulatory limits and
therefore would not be significant.
Radioactive Solid Wastes
Solid radioactive waste streams include solids recovered from the
reactor coolant systems, solids that come into contact with the
radioactive liquids or gases, and solids used in the reactor coolant
system operation. The licensee evaluated the potential effects of the
proposed EPU on the solid waste management system. The largest volume
of radioactive solid waste is low-level radioactive waste, which
includes bead resin, spent filters, and dry active waste (DAW) that
result from routine plant operation, outages, and routine maintenance.
DAW includes paper, plastic, wood, rubber, glass, floor sweepings,
cloth, metal, and other types of waste generated during routine
maintenance and outages.
The licensee states that the proposed EPU would not have a
significant effect on the generation of radioactive solid waste volume
from the primary reactor coolant and secondary side systems because
system functions are not changing and the volume inputs remain
consistent with historical generation rates. The waste can be handled
by the solid waste management system without modification. The
equipment is designed and operated to process the waste into a form
that minimizes potential harm to the workers and the environment. Waste
processing areas are monitored for radiation, and safety features are
in place to ensure worker doses are maintained within regulatory
limits. The proposed EPU would not generate a new type of waste or
create a new waste stream. Therefore, the impact from the proposed EPU
on radioactive solid waste would not be significant.
Spent Nuclear Fuel
Spent fuel from St. Lucie Units 1 and 2 is stored in a plant spent
fuel pool. St. Lucie Units 1 and 2 are currently licensed to use
uranium-dioxide fuel that has a maximum enrichment of 4.5 percent by
weight uranium-235. The average fuel assembly discharge burnup for the
proposed EPU is expected to be limited to 49,000 megawatt days per
metric ton uranium (MWd/MTU) with no fuel pins exceeding the maximum
fuel rod burnup limit of 62,000 MWd/MTU for Unit 1 and 60,000 MWd/MTU
for Unit 2. The licensee's fuel reload design goals will maintain the
St. Lucie Units 1 and 2 fuel cycles within the limits bounded by the
impacts analyzed in 10 CFR part 51, Table S-3, ``Uranium Fuel Cycle
Environmental Data'' and Table S-4, ``Environmental Impact of
Transportation of Fuel and Waste to and From One Light-Water-Cooled
Nuclear Power Reactor,'' as supplemented by NUREG-1437, Volume 1,
Addendum 1, ``Generic Environmental Impact Statement for License
Renewal of Nuclear Plants, Main Report, Section 6.3--Transportation
Table 9.1, Summary of findings on NEPA issues for license renewal of
nuclear power plants.'' Therefore, there would be no significant
impacts resulting from spent nuclear fuel.
Postulated Design-Basis Accident Doses
Postulated design-basis accidents are evaluated by both the
licensee and the NRC to ensure that St. Lucie Units 1 and 2 can
withstand normal and abnormal transients and a broad spectrum of
postulated accidents without undue hazard to the health and safety of
the public.
On November 22, 2010, the licensee submitted the St. Lucie Unit 1
EPU LAR to the NRC to increase the licensed core power level from 2,700
MWt to 3,020 MWt. On February 25, 2011, the licensee submitted the St.
Lucie Unit 2 EPU LAR to the NRC requesting the same increase in
licensed core power level. Analyses were performed by the licensee
according to the Alternative Radiological Source Term methodology
updated with input and assumptions consistent with the proposed EPU.
For each design-basis accident radiological consequence analyses were
performed using the guidance in NRC Regulatory Guide 1.183,
``Alternative Source Terms for Evaluating Design Basis Accidents at
Nuclear Power Reactors.'' Accident-specific total effective dose
equivalent was determined at the exclusion area boundary, at the low-
population zone, and in the control room. The analyses also include the
evaluation of the waste gas decay tank rupture event. The licensee
concluded that the calculated doses meet the acceptance criteria
specified in 10 CFR 50.67 and 10 CFR part 50, Appendix A, General
Design Criterion 19.
The NRC is evaluating the licensee's LARs to independently
determine whether they are acceptable to approve. The results of the
NRC evaluation and conclusion will be documented in a Safety Evaluation
Report that will be publicly available on the NRC ADAMS. If the NRC
approves the LARs, then the proposed EPU will not have a significant
impact with respect to the radiological consequences of design basis
accidents.
Radiological Cumulative Impacts
The cumulative impacts associated with the proposed EPU for St.
Lucie
[[Page 822]]
Unit 1 are considered in conjunction with the operation of St. Lucie
Unit 2, which is located next to Unit 1 on the site property. The
radiological dose limits for protection of the public and workers have