Oliver Hydro LLC; Notice of Application Tendered for Filing With the Commission, Soliciting Additional Study Requests, and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 105 [2011-33637]
Download as PDF
Federal Register / Vol. 77, No. 1 / Tuesday, January 3, 2012 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13005–003]
pmangrum on DSK3VPTVN1PROD with NOTICES
Oliver Hydro LLC; Notice of
Application Tendered for Filing With
the Commission, Soliciting Additional
Study Requests, and Establishing
Procedural Schedule for Relicensing
and a Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: 13005–003.
c. Date Filed: December 14, 2011.
d. Applicant: Oliver Hydro LLC.
e. Name of Project: William Bacon
Oliver Lock and Dam Hydroelectric
Project.
f. Location: At the U.S. Army Corps of
Engineers’ (Corps) William Bacon Oliver
Lock and Dam on the Black Warrior
River, in Tuscaloosa County, Alabama.
The project would occupy 8.7 acres of
United States lands administered by the
Corps’ Mobile District.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Brent Smith,
Symbiotics LLC, 371 Upper Terrace,
Suite 2, Bend, OR 97702; (541) 330–
8779; or email
brent.smith@symbioticsenergy.com.
i. FERC Contact: Allan Creamer, (202)
502–8365; or via email at
Allan.Creamer@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
VerDate Mar<15>2010
15:13 Dec 30, 2011
Jkt 226001
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: February 13, 2012.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–(866) 208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
m. This application is not ready for
environmental analysis at this time.
n. The proposed project would utilize
the existing Corps’ William Bacon
Oliver Lock and Dam, and would
consist of the following new facilities:
(1) A forebay; (2) an intake structure; (3)
a powerhouse containing two generating
units with a total capacity of 11.72
megawatts (MW); (4) a 150-foot-long, 68foot-wide tailrace; (5) a proposed 1.7mile-long, 25 kilovolt (kV) transmission
line; (6) a switchyard; and (7)
appurtenant facilities. The proposed
project would have an average annual
generation of 42.6 GWh, and operate
run-of-river utilizing surplus water from
the William Bacon Oliver Lock & Dam,
as directed by the Corps.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
105
processed according to the following
Hydro Licensing Schedule. Revisions to
the schedule will be made as
appropriate.
Issue Deficiency Letter—March 2012
Issue Acceptance Letter—July 2012
Issue Scoping Document 1 for
comments—August 2012
Request Additional Information (if
necessary)—October 2012
Issue Scoping Document 2 (if
necessary)—October 2012
Notice of application is ready for
environmental analysis—February
2013
Notice of the availability of the draft
EA—October 2013
Notice of the availability of the final
EA—April 2014
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: December 23, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–33637 Filed 12–30–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG12–22–000.
Applicants: Perrin Ranch Wind, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Perrin Ranch Wind,
LLC.
Filed Date: 12/22/11.
Accession Number: 20111222–5130.
Comments Due: 5 p.m. ET 1/12/12.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2877–001.
Applicants: Cobb Electric
Membership Corp.
Description: Cobb Electric
Membership Corp. Updated Market
Power Analysis.
Filed Date: 12/20/11.
Accession Number: 20111220–5150.
Comments Due: 5 p.m. ET 2/21/12.
Docket Numbers: ER10–3254–001.
Applicants: Cooperative Energy
Incorporated (an Electric Membership
Corp).
Description: Cooperative Energy Inc
Updated Market Power Analysis.
E:\FR\FM\03JAN1.SGM
03JAN1
Agencies
[Federal Register Volume 77, Number 1 (Tuesday, January 3, 2012)]
[Notices]
[Page 105]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-33637]
[[Page 105]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13005-003]
Oliver Hydro LLC; Notice of Application Tendered for Filing With
the Commission, Soliciting Additional Study Requests, and Establishing
Procedural Schedule for Relicensing and a Deadline for Submission of
Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: 13005-003.
c. Date Filed: December 14, 2011.
d. Applicant: Oliver Hydro LLC.
e. Name of Project: William Bacon Oliver Lock and Dam Hydroelectric
Project.
f. Location: At the U.S. Army Corps of Engineers' (Corps) William
Bacon Oliver Lock and Dam on the Black Warrior River, in Tuscaloosa
County, Alabama. The project would occupy 8.7 acres of United States
lands administered by the Corps' Mobile District.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Brent Smith, Symbiotics LLC, 371 Upper
Terrace, Suite 2, Bend, OR 97702; (541) 330-8779; or email
brent.smith@symbioticsenergy.com.
i. FERC Contact: Allan Creamer, (202) 502-8365; or via email at
Allan.Creamer@ferc.gov.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: February 13, 2012.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll free at 1-(866) 208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
m. This application is not ready for environmental analysis at this
time.
n. The proposed project would utilize the existing Corps' William
Bacon Oliver Lock and Dam, and would consist of the following new
facilities: (1) A forebay; (2) an intake structure; (3) a powerhouse
containing two generating units with a total capacity of 11.72
megawatts (MW); (4) a 150-foot-long, 68-foot-wide tailrace; (5) a
proposed 1.7-mile-long, 25 kilovolt (kV) transmission line; (6) a
switchyard; and (7) appurtenant facilities. The proposed project would
have an average annual generation of 42.6 GWh, and operate run-of-river
utilizing surplus water from the William Bacon Oliver Lock & Dam, as
directed by the Corps.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following Hydro Licensing Schedule.
Revisions to the schedule will be made as appropriate.
Issue Deficiency Letter--March 2012
Issue Acceptance Letter--July 2012
Issue Scoping Document 1 for comments--August 2012
Request Additional Information (if necessary)--October 2012
Issue Scoping Document 2 (if necessary)--October 2012
Notice of application is ready for environmental analysis--February
2013
Notice of the availability of the draft EA--October 2013
Notice of the availability of the final EA--April 2014
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: December 23, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-33637 Filed 12-30-11; 8:45 am]