Notice of Availability of the Record of Decision for the Tule Wind, LLC's Tule Wind Project, San Diego County, CA, 80962 [2011-33093]
Download as PDF
sroberts on DSK5SPTVN1PROD with NOTICES
80962
Federal Register / Vol. 76, No. 248 / Tuesday, December 27, 2011 / Notices
would preclude development of the
SSEP in any configuration and maintain
existing land uses in the project area.
The Final EIS also analyzed three action
alternatives, one sub-alternative, and
two options including: (1) The Proposed
Action (375-megawatt (MW) wet-cooled
concentrated solar thermal parabolic
trough facility on 3,620 acres of land);
(2) Alternative A: Reduced Water Use
(using a dry-cooling technology); (3)
Sub-alternative A1: Photovoltaic (PV) (a
300–MW PV facility occupying 2,013
acres of land); (4) Alternative B:
Reduced Footprint (a 250–MW wetcooled facility occupying 2,320 acres of
land); (5) Brine Concentrator Option
(could be added to the Proposed Action
or Alternative B to reduce wastewater);
and (6) Generation Intertie (Gen-tie)
Line Option (could be used for any
alternative to address alternate methods
and locations for crossing existing highvoltage transmission lines near the
project area).
The Preferred Alternative from the
Final EIS, including the proposed gentie line, is the Selected Alternative in
the ROD. The Selected Alternative will
allow the issuance of a ROW grant for
a PV facility capable of generating up to
300 MW of solar power on 2,013 acres
of land. The project will consist of
multiple arrays of PV panels electrically
connected to associated power inverter
units. The current from the power
inverters will be gathered by an internal
electrical collection system and
transformed to transmission voltage
prior to leaving the project area. The
Selected Alternative facilities include
the following major components or
systems: PV modules/arrays; solar
trackers and/or fixed support structures;
an electrical collection system; a step-up
transformation/on-site switchyard; a
500-kilovolt generation tie-line/utility
interconnection; administration
buildings and local warehouses; and
drainage collection and discharge
facilities. A single evaporation pond of
approximately 1 acre is required. The
PV does not use heat transfer fluid;
therefore, no land-treatment unit is
required. The Selected Alternative in
the ROD will use approximately 33 acrefeet per year of water for project
operations, mostly for washing PV
mirrors. That amounts to 1–2 percent of
the water that the original proposed
action would have used.
As described in the Final EIS, the
BLM Selected Alternative, with its
preferred gen-tie line, was developed in
response to agency and public
comments on water consumption. It was
developed after the Draft EIS, due to
advancements in technology and a
change in market conditions that
VerDate Mar<15>2010
22:00 Dec 23, 2011
Jkt 226001
allowed for a reconsideration of PV
technology as a viable alternative. The
Selected Alternative also avoids other
resource issues raised by the public and
agency cooperators, including wildlife
habitat and travel corridors, pending
Federal Emergency Management Agency
floodplains, air quality point sources
and vapor plumes, and nearby
residences.
The Notice of Availability of the Final
EIS for the SSEP was published in the
Federal Register on October 21, 2011
(76 FR 65532). Publication of the Notice
of Availability initiated a 30-day
comment period on the Final EIS. At the
close of the 30-day period on November
21, 2011, four comments had been
received. These comments and their
responses are attached to the ROD.
Because this decision is approved by
the Secretary of the Interior, it is not
subject to administrative appeal (43 CFR
4.410(a)(3)).
Authority: 40 CFR 1506.6.
Robert V. Abbey,
Director, Bureau of Land Management.
[FR Doc. 2011–33094 Filed 12–23–11; 8:45 am]
BILLING CODE 4310–32–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[CACA 49698, LLCAD07000,
L51010000.FX0000, LVRWB10B3810]
Notice of Availability of the Record of
Decision for the Tule Wind, LLC’s Tule
Wind Project, San Diego County, CA
Bureau of Land Management,
Interior.
ACTION: Notice of Availability.
AGENCY:
The Bureau of Land
Management (BLM) announces the
availability of the Record of Decision
(ROD) for the project, located in San
Diego County. The Secretary of the
Interior approved the ROD on December
19, 2011, which constitutes the
Department’s final decision.
ADDRESSES: Copies of the ROD are
available upon request from the Field
Manager, BLM El Centro Field Office,
1661 S. 4th Street, El Centro, California
92243, and the BLM California Desert
District Office, 22835 Calle San Juan de
Los Lagos, Moreno Valley, California
92553, or via the Internet at the
following Web site: https://
www.ca.blm.gov/elcentro.
FOR FURTHER INFORMATION CONTACT: Greg
Thomsen, Project Manager, telephone
(951) 697–5237; address BLM California
Desert District Office, 22835 Calle San
Juan de Los Lagos, Moreno Valley,
SUMMARY:
PO 00000
Frm 00095
Fmt 4703
Sfmt 9990
California 92553–9046; email
catulewind@blm.gov.
Tule
Wind, LLC, a wholly owned subsidiary
of Iberdrola Renewables, Inc., filed
right-of-way (ROW) application CACA–
51204 for the Tule Wind Project. The
project will consist of up to 62 wind
turbines (1.5 to 3.0 megawatts (MW)
each) with a generating capacity of up
to 186 MW, an overhead and
underground 34.5-kilovolt (kV) collector
system leading to a collector substation,
an operations and maintenance facility,
and a 138-kV transmission line as the
generation tie-in to the existing
Boulevard Substation. The Tule Wind
Project will be on 12,200 acres of BLMmanaged lands. The project site is
located in the In-Ko-Pah Mountains near
the McCain Valley in San Diego County,
north of the unincorporated community
of Boulevard.
The BLM selected the preferred
alternative that was evaluated in the
Final EIS. The Notice of Availability of
the Final EIS for the Tule Wind Project
was published in the Federal Register
on October 24, 2011 (76 FR 65746). In
addition to the Tule Wind Project, the
Final Environmental Impact Statement
(EIS)/Environmental Impact Report
evaluated a ROW application by San
Diego Gas & Electric (SDG&E) to
construct the ECO Project, which
includes a 138-kV transmission line that
would traverse approximately 1.5 miles
of public land managed by the BLM.
The BLM will issue a separate decision
on the SDG&E’s ROW application.
As a result of the ROD, access to
certain recreation areas including, but
not limited to, the Lark Canyon OHV
Area, Lark Canyon Campground,
Cottonwood Campground, Carrizo
Overlook, and Sacatone Overlook could
be reduced during construction, and in
some instances, access roads off McCain
Valley Road to these areas may be
temporarily closed (resulting in an
inability to access these areas and
facilities by vehicles) during the period
of time construction is authorized.
Specific routes and times will be
announced when a more detailed
construction schedule is completed.
Because this decision is approved by
the Secretary of the Interior, it is not
subject to administrative appeal (43 CFR
4.410(a)(3)).
SUPPLEMENTARY INFORMATION:
Authority: 40 CFR 1506.6.
Robert V. Abbey,
Director, Bureau of Land Management.
[FR Doc. 2011–33093 Filed 12–23–11; 8:45 am]
BILLING CODE 4310–40–P
E:\FR\FM\27DEN1.SGM
27DEN1
Agencies
[Federal Register Volume 76, Number 248 (Tuesday, December 27, 2011)]
[Notices]
[Page 80962]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-33093]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[CACA 49698, LLCAD07000, L51010000.FX0000, LVRWB10B3810]
Notice of Availability of the Record of Decision for the Tule
Wind, LLC's Tule Wind Project, San Diego County, CA
AGENCY: Bureau of Land Management, Interior.
ACTION: Notice of Availability.
-----------------------------------------------------------------------
SUMMARY: The Bureau of Land Management (BLM) announces the availability
of the Record of Decision (ROD) for the project, located in San Diego
County. The Secretary of the Interior approved the ROD on December 19,
2011, which constitutes the Department's final decision.
ADDRESSES: Copies of the ROD are available upon request from the Field
Manager, BLM El Centro Field Office, 1661 S. 4th Street, El Centro,
California 92243, and the BLM California Desert District Office, 22835
Calle San Juan de Los Lagos, Moreno Valley, California 92553, or via
the Internet at the following Web site: https://www.ca.blm.gov/elcentro.
FOR FURTHER INFORMATION CONTACT: Greg Thomsen, Project Manager,
telephone (951) 697-5237; address BLM California Desert District
Office, 22835 Calle San Juan de Los Lagos, Moreno Valley, California
92553-9046; email catulewind@blm.gov.
SUPPLEMENTARY INFORMATION: Tule Wind, LLC, a wholly owned subsidiary of
Iberdrola Renewables, Inc., filed right-of-way (ROW) application CACA-
51204 for the Tule Wind Project. The project will consist of up to 62
wind turbines (1.5 to 3.0 megawatts (MW) each) with a generating
capacity of up to 186 MW, an overhead and underground 34.5-kilovolt
(kV) collector system leading to a collector substation, an operations
and maintenance facility, and a 138-kV transmission line as the
generation tie-in to the existing Boulevard Substation. The Tule Wind
Project will be on 12,200 acres of BLM-managed lands. The project site
is located in the In-Ko-Pah Mountains near the McCain Valley in San
Diego County, north of the unincorporated community of Boulevard.
The BLM selected the preferred alternative that was evaluated in
the Final EIS. The Notice of Availability of the Final EIS for the Tule
Wind Project was published in the Federal Register on October 24, 2011
(76 FR 65746). In addition to the Tule Wind Project, the Final
Environmental Impact Statement (EIS)/Environmental Impact Report
evaluated a ROW application by San Diego Gas & Electric (SDG&E) to
construct the ECO Project, which includes a 138-kV transmission line
that would traverse approximately 1.5 miles of public land managed by
the BLM. The BLM will issue a separate decision on the SDG&E's ROW
application.
As a result of the ROD, access to certain recreation areas
including, but not limited to, the Lark Canyon OHV Area, Lark Canyon
Campground, Cottonwood Campground, Carrizo Overlook, and Sacatone
Overlook could be reduced during construction, and in some instances,
access roads off McCain Valley Road to these areas may be temporarily
closed (resulting in an inability to access these areas and facilities
by vehicles) during the period of time construction is authorized.
Specific routes and times will be announced when a more detailed
construction schedule is completed.
Because this decision is approved by the Secretary of the Interior,
it is not subject to administrative appeal (43 CFR 4.410(a)(3)).
Authority: 40 CFR 1506.6.
Robert V. Abbey,
Director, Bureau of Land Management.
[FR Doc. 2011-33093 Filed 12-23-11; 8:45 am]
BILLING CODE 4310-40-P