Nevada Hydro Company, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 76155 [2011-31166]

Download as PDF Federal Register / Vol. 76, No. 234 / Tuesday, December 6, 2011 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14234–000] jlentini on DSK4TPTVN1PROD with NOTICES Natural Currents Energy Services, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On August 25, 2011, Natural Currents Energy Services, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Maurice River Tidal Energy Project, which would be located on the Maurice River in Cumberland County, New Jersey. The proposed project would not use a dam or impoundment. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of: (1) Installation of 1 to 10 NC Sea Dragon or Red Hawk tidal turbines at a rated capacity of 100 kilowatts, (2) an estimated 700 meters in length of additional transmission infrastructure, and (3) appurtenant facilities. The project is estimated to have an annual minimum generation of 3,504,000 kilowatt-hours with the installation of 10 units. Applicant Contact: Mr. Roger Bason, Natural Currents Energy Services, LLC, 24 Roxanne Boulevard, Highland, New York 12561, (845) 691–4009. FERC Contact: Woohee Choi (202) 502–6336. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end VerDate Mar<15>2010 17:04 Dec 05, 2011 Jkt 226001 of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1-(866) 208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14234–000) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: November 29, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–31168 Filed 12–5–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. P–14227–000] Nevada Hydro Company, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On July 14, 2011, the Nevada Hydro Company (Nevada Hydro) filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Lake Elsinore Advanced Pumped Storage Project to be located on Lake Elsinore and San Juan Creek, in Riverside County, California. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any landdisturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) A new upper reservoir (Decker Canyon) having a 240-foot-high main dam and a gross storage volume of 5,500 feet, at a normal reservoir surface elevation of 2,830 feet above mean sea level (msl); (2) a powerhouse with two reversible pump-turbine units with a total installed capacity of 600 PO 00000 Frm 00036 Fmt 4703 Sfmt 9990 76155 megawatts; (3) the existing Lake Elsinore to be used as a lower reservoir; (4) about 32 miles of 500-kV transmission line connecting the project to an existing transmission line owned by Southern California Edison located north of the proposed project and to an existing San Diego Gas & Electric Company transmission line located to the south. Applicant Contact: Arnold B. Podgorsky and Patrick L. Morand, Wright & Talisman, P.C., 1200 G Street NW., Suite 600, Washington, DC 20005, Phone (202) 393–1200. FERC Contact: Jim Fargo; phone: (202) 502–6095. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc. gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14227–000) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: November 29, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–31166 Filed 12–5–11; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\06DEN1.SGM 06DEN1

Agencies

[Federal Register Volume 76, Number 234 (Tuesday, December 6, 2011)]
[Notices]
[Page 76155]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-31166]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. P-14227-000]


Nevada Hydro Company, Inc.; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On July 14, 2011, the Nevada Hydro Company (Nevada Hydro) filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the Lake 
Elsinore Advanced Pumped Storage Project to be located on Lake Elsinore 
and San Juan Creek, in Riverside County, California. The sole purpose 
of a preliminary permit, if issued, is to grant the permit holder 
priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would consist of the following: (1) A new 
upper reservoir (Decker Canyon) having a 240-foot-high main dam and a 
gross storage volume of 5,500 feet, at a normal reservoir surface 
elevation of 2,830 feet above mean sea level (msl); (2) a powerhouse 
with two reversible pump-turbine units with a total installed capacity 
of 600 megawatts; (3) the existing Lake Elsinore to be used as a lower 
reservoir; (4) about 32 miles of 500-kV transmission line connecting 
the project to an existing transmission line owned by Southern 
California Edison located north of the proposed project and to an 
existing San Diego Gas & Electric Company transmission line located to 
the south.
    Applicant Contact: Arnold B. Podgorsky and Patrick L. Morand, 
Wright & Talisman, P.C., 1200 G Street NW., Suite 600, Washington, DC 
20005, Phone (202) 393-1200.
    FERC Contact: Jim Fargo; phone: (202) 502-6095.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and 
competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support. Although the Commission strongly encourages electronic filing, 
documents may also be paper-filed. To paper-file, mail an original and 
seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14227-000) in the docket number field to 
access the document. For assistance, contact FERC Online Support.

    Dated: November 29, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-31166 Filed 12-5-11; 8:45 am]
BILLING CODE 6717-01-P