DEPARTMENT OF HOUSING AND
URBAN DEVELOPMENT
24 CFR Part 905
[Docket No. FR–5507–P–01]
RIN 2577–AC84
Public Housing Energy Audits
Office of the Assistant
Secretary for Public and Indian
Housing, HUD.
ACTION: Proposed rule.
AGENCY:
This rule proposes to revise
HUD’s energy audit requirements
applicable to HUD’s public housing
program for the purpose of clarifying
such requirements, as well as
identifying energy-efficient measures
that need to be addressed in the audit
and procedures for improved
coordination with physical needs
assessments. In addition, the rule moves
the energy audit requirements to a
different part of HUD’s title of the Code
of Federal Regulations.
DATES: Comment Due Date: January 17,
2012.
ADDRESSES: Interested persons are
invited to submit comments regarding
this proposed rule to the Regulations
Division, Office of General Counsel,
Department of Housing and Urban
Development, 451 7th Street SW., Room
10276, Washington, DC 20410–0500.
Communications must refer to the above
docket number and title. There are two
methods for submitting public
comments. All submissions must refer
to the above docket number and title.
1. Submission of Comments by Mail.
Comments may be submitted by mail to
the Regulations Division, Office of
General Counsel, Department of
Housing and Urban Development, 451
7th Street SW., Room 10276,
Washington, DC 20410–0500.
2. Electronic Submission of
Comments. Interested persons may
submit comments electronically through
the Federal eRulemaking Portal at
https://www.regulations.gov. HUD
strongly encourages commenters to
submit comments electronically.
Electronic submission of comments
allows the commenter maximum time to
prepare and submit a comment, ensures
timely receipt by HUD, and enables
HUD to make them immediately
available to the public. Comments
submitted electronically through the
https://www.regulations.gov Web site can
be viewed by other commenters and
interested members of the public.
Commenters should follow the
instructions provided on that site to
submit comments electronically.
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
SUMMARY:
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
No Facsimile Comments. Facsimile
(fax) comments are not acceptable.
Public Inspection of Public
Comments. All properly submitted
comments and communications
submitted to HUD will be available for
public inspection and copying between
8 a.m. and 5 p.m. weekdays at the above
address. Due to security measures at the
HUD Headquarters building, an advance
appointment to review the public
comments must be scheduled by calling
the Regulations Division at (202) 402–
3055 (this is not a toll-free number).
Individuals with speech or hearing
impairments may access this number
via TTY by calling the Federal Relay
Service, toll-free, at (800) 877–8339.
Copies of all comments submitted are
available for inspection and
downloading at https://
www.regulations.gov.
FOR FURTHER INFORMATION CONTACT:
Jeffrey Riddel, Director, Office of Capital
Improvements, Office of Public and
Indian Housing, Department of Housing
and Urban Development, 451 7th Street
SW., Washington, DC 20410–8000;
telephone number (202) 402–7378 (this
is not a toll-free number). Hearing- or
speech-impaired individuals may access
this number through TTY by calling the
toll-free Federal Relay Service at (800)
877–8339.
SUPPLEMENTARY INFORMATION:
I. Background
Because of the increasing importance
of energy conservation, HUD is taking a
more proactive approach toward
encouraging energy efficiency in its
housing programs. In order for public
housing agencies (PHAs) to improve
their capital planning processes, HUD
determined that there is a need for
stronger energy audit data.
Under existing regulations, all PHAs
must complete an energy audit for each
PHA-owned project under management
at least once every 5 years. The existing
regulations also require that standards
for energy audits be equivalent to state
standards. However, state standards for
energy audits are variable or nonexistent
(see, for example, the map of state
energy codes by the Department of
Energy at https://www.energycodes.gov/
states/). Accordingly, it is HUD’s view
that energy audit standards present an
area where additional guidance will
produce more useful results.
In this rule, HUD proposes the energy
conservation measures (ECMs) that a
PO 00000
Frm 00017
Fmt 4702
Sfmt 4702
71287
PHA must consider at a minimum when
performing an energy audit. This rule
also proposes certain minimum
qualifications for energy auditors
procured by PHAs to perform energy
audits.
While this rule proposes ECMs that
must be considered, as well as certain
standards for energy audits and
minimum qualifications for energy
auditors, HUD specifically seeks public
comment on whether there are other
standards and qualifications that HUD
should consider adopting.
HUD will be publishing separately a
proposed rule on physical needs
assessments (PNAs) that will require the
completion of PNAs in conjunction with
energy audits in order to integrate the
audit properly with the PNA. The PNA
rule proposes to require data derived
from the energy audit to be included in
a PNA, to facilitate the identification of
cost-effective ECMs. ECMs also include
water-related efficiency measures. If a
PNA and energy audit are performed
together, there could be cost savings to
PHAs to the extent that many of the
same components are reviewed for each.
Through this rule and the PNA rule,
HUD seeks to have PHAs move toward
coordinating the performance of PNAs
and energy audits with each other, to
maximize the effective use of this type
of information.
HUD specifically seeks comments
from PHAs and other interested parties
as to an appropriate time frame for
performance and submission
requirements.
Coordination between an energy
auditor and PNA provider is considered
to be important in the capital
improvement decision-making process.
As the consulting industry that services
PHAs and the public housing program
is introduced to coordinated or
integrated PNAs and energy audits, the
costs associated with performing both of
these assessments may be reduced.
Since energy conservation products are
often newer technology whose prices
tend to be reduced over time and
because utility costs are more volatile
than general costs, 2 years is considered
by HUD to be the maximum time frame
between the performance of an energy
audit and a PNA that maintains cost and
pricing alignment. In addition,
coordination between an energy auditor
and PNA provider is considered to be
important for the evaluation of technical
issues in the selection of component
products and the sequencing of
improvements. Coordination of the
timing of these activities may reduce the
possibility of additional cost to the PHA
for consulting services outside of the
contract cycle of professional providers.
E:\FR\FM\17NOP1.SGM
17NOP1
71288
Federal Register / Vol. 76, No. 222 / Thursday, November 17, 2011 / Proposed Rules
HUD is interested in receiving
feedback concerning the feasibility of
requiring PHAs to coordinate the
performance of energy audits and PNAs.
HUD specifically invites comment on
the potential benefits, feasibility, or
challenges of preparing energy audits in
conjunction with PNAs. HUD also
specifically seeks public comment on
how quickly energy audit information
becomes obsolete for cost projection and
strategic planning in a PNA.
II. This Proposed Rule
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
A. Overview of Changes
This proposed rule moves the
regulations pertaining to energy audit
requirements, which are currently
codified in 24 CFR 965.302, to 24 CFR
905.300(b)(10)–905.300(b)(15), and
clarifies HUD’s requirements for energy
audits performed in conjunction with
PNAs.
Also through this rule, HUD proposes
to modify these regulations to:
(1) Define an energy audit, ECMs, and
‘‘green’’ measures.
(2) Establish content and submission
requirements for an energy audit, and
facilitate the integration of the energy
audit with the PNA that PHAs are
required to conduct every 5 years. While
many states have not adopted auditing
standards (see https://
www.energycodes.gov/states/), the PHA
would still be required to comply with
standards adopted for their state, where
applicable. HUD is not at this time
prescribing a specific energy audit form,
so long as the required data is collected,
and so long as energy auditing systems
and formats are available from a number
of sources, including the Department of
Energy, Building Performance Institute
(BPI), and the Residential Energy
Services Network (RESNET).
(3) Define Core ECMs that must be
considered and require further
evaluation of those ECMs that have the
potential for cost-effective
implementation. Core ECMs generally
represent commonplace conservation
measures that have demonstrated track
records of reducing energy and water
consumption in a cost-effective manner
and that can be routinely evaluated by
an energy auditor. This rule defines
Core ECMs in broad categories.
Examples within the categories include:
Changes to the building envelope such
as insulation; energy-efficient
mechanical equipment; low-flow water
devices and other water conservation
measures; energy-efficient lighting
systems, including compact fluorescent
lighting and motion controls; and
Energy Star-certified appliances. As
technology advances over time, HUD
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
will provide further examples of ECMs
in guidance.
(4) Recognize Advanced ECMs that
may be addressed. PHAs are
encouraged, but not required to consider
Advanced ECMs, which represent
alternative measures comprising
advanced or experimental technology
which, compared to the Core ECMs, can
be more challenging to evaluate and
implement. These are not alternatives
that auditors would normally consider
unless directed to do so, or unless there
were local precedents that caused the
measures to become commonly
accepted local alternatives. Examples of
Advanced ECMs include renewable
energy technologies, such as solar and
geothermal power, and green
construction.
(5) Require that ECMs identified in
the energy audit as cost-effective be
organized into those with: Paybacks of
12 years or less, paybacks of greater than
12 and less than or equal to 20 years,
and paybacks of more than 20 years.
The 12-year and 20-year benchmarks
correspond with the benchmarks for an
Energy Performance Contract (EPC).
(6) Establish minimum qualifications
for an energy auditor, and
(7) Provide for extension of the
requirement to complete an initial
energy audit in instances where
industry capacity is a constraint.
This rule would not require PHAs to
implement particular ECMs; however,
the energy audit must provide PHAs
with accurate information about ECMs
for the PHAs to consider. It is HUD’s
position that when PHAs capture the
cost-effectiveness data for ECMs, PHAs
will implement the measures more
frequently.
The proposed rule would require
payback analysis for Core ECMs.
Current guidance for a payback analysis
is contained in the HUD publication
‘‘Energy Conservation for Housing—A
Workbook,’’ dated September, 1998
(available at https://portal.hud.gov/
hudportal/HUD?src=/program_offices/
public_indian_housing/programs/ph/
phecc/resources), and this proposed
rule would clarify and modify that
guidance. The payback analysis in the
proposed rule would recognize that for
a replacement component, the
incremental cost of a more efficient
component should be used to determine
cost-effectiveness. For example, if an
Energy Star appliance costs $100 more
than a standard appliance with the same
estimated life and the component has to
be replaced, in order for the Energy Star
appliance to be cost-effective, it must
cost $100 less to operate than the
standard component over the designated
payback period.
PO 00000
Frm 00018
Fmt 4702
Sfmt 4702
The result of a payback analysis
would be considered in the context of
this rule as a threshold for further
evaluation of an ECM. A more detailed
cost analysis may be conducted that
includes complete lifecycle cost
analysis; however, the baseline audit
requires only that those lifecycle costs
be generally identified, not that they be
subjected to detailed cost analysis.
The proposed rule would not prevent
PHAs from pursuing more advanced
utility conservation and green measures,
at their option. In making the
distinction between Core ECMs and
Advanced ECMs, HUD is recognizing
extensive opportunities in public
housing for simple cost-effective energy
conservation improvements, while
acknowledging that more advanced
work may be possible in certain
circumstances. The engineering and
implementation costs of advanced
technologies often make them
impractical outside of the context of a
comprehensive redevelopment,
remodeling, or incentivized program,
such as an EPC or targeted grant
program. HUD’s view is that it is
preferable to concentrate limited
funding on improvements that have
been proven to be generally costeffective and broadly available to PHAs.
PHAs have different priorities and local
requirements with respect to utility
conservation and green improvements.
Many improvements, while not
providing monetary cost effectiveness,
provide benefits in the form of an
improved living environment for
residents or a contribution to broader
societal environmental goals. HUD
recognizes those benefits, and
encourages PHAs to consider a wide
variety of measures. HUD’s Office of
Healthy Homes and Lead Hazard
Control and the Environmental
Protection Agency’s Indoor Air Quality
Standards, as well as Office of Public
and Indian Housing (PIH) notices on
green building, are useful resources for
a PHA that is considering a program of
green improvements.
While it is HUD’s position that the
performance of the energy audit at the
same time as the PNA would be more
efficient for PHAs, particularly in
circumstances where a single provider
can perform both services, HUD also
recognizes that circumstances may not
allow a PHA to perform both services
together. Accordingly, this rule does not
require the performance of the energy
audit simultaneously with the PNA.
HUD recognizes circumstances where
an energy audit would be performed
outside the 5-year cycle, such as an
energy audit performed in relation to an
EPC or another development project, or
E:\FR\FM\17NOP1.SGM
17NOP1
71289
Federal Register / Vol. 76, No. 222 / Thursday, November 17, 2011 / Proposed Rules
to meet another HUD requirement. As in
the case of a PNA, the first energy audit
under the new final rule resulting from
this proposed rule is likely to be the
most costly and require the most
intensive effort, with subsequent
updates benefitting from the
information collected in prior audits.
HUD also recognizes that the capacity of
the energy auditing industry might be
limited in some areas, and allows for a
delay in the performance of the audit in
cases where local shortages in these
professional services exist.
The rule does not propose to require
an investment grade energy audit such
as one that might be prepared for an
energy performance contract or in order
to evaluate a financial transaction. HUD
is especially interested in receiving
comments about appropriate energy
audit requirements, as well as
certification requirements and
professional standards for energy
auditors. HUD is interested in hearing
from both the energy auditing industry
and entities that have experience
managing a real estate portfolio and
have integrated energy audits into their
planning process. HUD is also interested
in receiving comments about any
multiple purposes for which portfolio
managers have used energy audits. HUD
also invites comments about the
proposed categories of ECMs that
should be addressed in an energy audit,
and conservation measures that are
appropriate for use on a nationwide
basis. HUD further invites comments
from public housing and other
interested parties on the needed
capacity for performing integrated
energy audits and PNAs.
Paperwork Reduction Act
The information collection
requirements contained in this proposed
rule have been submitted to the Office
of Management and Budget (OMB)
under the Paperwork Reduction Act of
1995 (44 U.S.C. 3501–3520). In
accordance with the Paperwork
Reduction Act, an agency may not
conduct or sponsor, and a person is not
required to respond to, a collection of
information, unless the collection
displays a currently valid OMB control
number.
The burden of the information
collections in this proposed rule is
estimated as follows:
Reporting and Recordkeeping Burden:
Number of
responses per
respondent
Number of
respondents
Section reference
III. Findings and Certifications
Estimated
average time
for requirement (in
hours)
Estimated
annual burden
(in hours)
620
620
62
62
1
1
1
1
65
25
45
45
40,300
15,500
2,790
2,790
Total Paperwork Burden for the New Rule ..............................................
Total Burden from Previous Rule (24 CFR 965.302) 5 ............................
........................
........................
........................
........................
........................
........................
61,380
29,440
Total additional burden as a result of this rule .........................................
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
905.300(b)(10) 1 ...............................................................................................
905.300(b)(14) 2 ...............................................................................................
905.300(b)(14)(vii) 3 .........................................................................................
900.300(b)(15) 4 ...............................................................................................
........................
........................
........................
31,940
In accordance with 5 CFR
1320.8(d)(1), HUD is soliciting
comments from members of the public
and affected agencies concerning this
collection of information to:
(1) Evaluate whether the proposed
collection of information is necessary
for the proper performance of the
functions of the agency, including
whether the information will have
practical utility;
(2) Evaluate the accuracy of the
agency’s estimate of the burden of the
proposed collection of information;
(3) Enhance the quality, utility, and
clarity of the information to be
collected; and
(4) Minimize the burden of the
collection of information on those who
are to respond, including through the
use of appropriate automated collection
techniques or other forms of information
technology; e.g., permittingelectronic
submission of responses.
1 Burden of energy audit performed once every 5
years for each of 3,200 PHAs, including data
collection and site inspection.
2 Burden of analysis and comprehensive report.
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
Interested persons are invited to
submit comments regarding the
information collection requirements in
this rule. Under the provisions of 5 CFR
part 1320, OMB is required to make a
decision concerning this collection of
information between 30 and 60 days
after today’s publication date. Therefore,
a comment on the information
collection requirements is best assured
of having its full effect if OMB receives
the comment within 30 days of today’s
publication. This time frame does not
affect the deadline for comments to the
agency on the proposed rule, however.
Comments must refer to the proposal by
name and docket number (FR–5361) and
must be sent to:
HUD Desk Officer, Office of
Management and Budget, New
Executive Office Building,
Washington, DC 20503, Fax number:
(202) 395–6947, and
3 Optional burden of expanded analysis as
directed by PHA, estimated to be exercised by 10
percent of respondents.
4 Optional burden of considering green measures
as directed by PHA, estimated to be exercised by
10 percent of respondents.
5 OMB Control No. 2577–0062.
PO 00000
Frm 00019
Fmt 4702
Sfmt 4702
Collette Pollard, Reports Liaison Officer,
Department of Housing and Urban
Development, 451 7th Street, SW.,
Room 4160, Washington, DC 20410.
Interested persons may submit
comments regarding the information
collection requirements electronically
through the Federal eRulemaking Portal
at https://www.regulations.gov. HUD
strongly encourages commenters to
submit comments electronically.
Electronic submission of comments
allows the commenter maximum time to
prepare and submit a comment, ensures
timely receipt by HUD, and enables
HUD to make them immediately
available to the public. Comments
submitted electronically through the
https://www.regulations.gov Web site can
be viewed by other commenters and
interested members of the public.
Commenters should follow the
instructions provided on that site to
submit comments electronically.
Regulatory Planning and Review
OMB reviewed this proposed rule
under Executive Order 12866 (entitled
‘‘Regulatory Planning and Review’’).
This rule was determined to be a
E:\FR\FM\17NOP1.SGM
17NOP1
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
71290
Federal Register / Vol. 76, No. 222 / Thursday, November 17, 2011 / Proposed Rules
‘‘significant regulatory action,’’ as
defined in 3(f) of the order (although not
an economically significant regulatory
action, as provided under section 3(f)(1)
of the order). The docket file is available
for public inspection between the hours
of 8 a.m. and 5 p.m. weekdays in the
Regulations Division, Office of General
Counsel, Department of Housing and
Urban Development, 451 7th Street SW.,
Room 10276, Washington, DC 20410–
0500. Due to security measures at the
HUD Headquarters building, an advance
appointment to review the docket file
must be scheduled by calling the
Regulations Division at (202) 708–3055
(this is not a toll-free number). Hearingor speech-impaired individuals may
access this number through TTY by
calling the toll-free Federal Information
Relay Service at (800) 877–8339.
This proposed rule would revise
HUD’s energy audit requirements
applicable to HUD’s public housing
program for the purpose of clarifying
such requirements and defining energyefficient measures and audit procedures.
It is estimated that the cost burden to
PHAs could be up to $40 million every
5 years or $8 million annually.
Notwithstanding the relatively modest
cost to perform energy audits, there is a
potential for PHAs to realize substantial
savings. Each year, about $1.2 billion is
budgeted for utilities for housing
authorities. Assuming that this rule is
effective and energy audits are
successfully translated into energy
savings, where, for example, only 10
percent efficiency and cost were
achieved, it would translate into about
$120 million in budget savings annually
that could be affected to other uses.
When tenant-paid utilities are included,
the annual savings may be up to $173
million under the same conditions.
Notwithstanding the potential benefit,
this proposed rule is not economically
significant as defined by Executive
Order 12866 and OMB Circular A–4.
The potential costs of the rule are as
follows. The new Energy Audit Rule
does not change the current requirement
that all PHAs perform an energy audit
at least once every 5 years. However,
there will be an economic impact to the
extent that the new standards for
performance exceed the standard of
performance for the state in which each
PHA is located.
The cost to perform the enhanced
energy audit can be approximated using
existing examples and HUD’s own
experience. HUD’s Office of Affordable
Housing Preservation (OAHP) manages
the Green Retrofit Program (GRP), which
involves OAHP direct engagement of
providers to perform Physical Needs
Assessment and Energy Audits for
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
affordable housing projects. The GRP
energy audit includes all of the
components generally understood to be
found in a baseline energy audit. HUD
is using the GRP format as a source for
the development of energy audit
standards to be used in public housing,
and the energy audit standards in the
new rule will be comparable in
complexity/comprehensiveness. OAHP
has shared a summary of its costs to
perform PNAs during Fiscal Year 2009/
10 using its format for a set of 66
projects nationwide. These projects
averaged 96 units per project. The
average cost for the energy audit portion
of the GRP for these projects was
reported as $3,314 per project or $32.86
per unit.
In the absence of detailed cost figures
for the energy audits currently being
performed by PHAs, the most
conservative approach to estimating the
burden is to use the GRP figure of
$32.86 per unit. Even without a
mitigating adjustment for the current
economic investment that PHAs are
making to this activity, the economic
burden to PHAs would be $39,864,536
($32.86 × 1,213,163) every 5 years, or
$7,972,907 annually. A mitigating
adjustment of 50 percent to account for
the existing burden is not an
unreasonable assumption. Such an
adjustment would reduce the 5-year and
annual additional burden to
$19,932,268 and $3,986,453,
respectively.
There are also benefits to the rule.
Nationwide, PHA-paid utility costs total
around $1.3 billion annually, or about
25 percent of the costs to operate public
housing. It is estimated that an
additional $430 million in utility costs
are paid by residents, but indirectly are
paid by PHAs in the form of utility
allowances that reduce resident rents.
Assuming that this rule is effective and,
for example, only 10 percent efficiency
were achieved, that would translate into
about $173 million in budget savings
annually that could be realized and
affected to other uses.
Unfunded Mandates Reform Act
Title II of the Unfunded Mandates
Reform Act of 1995 (2 U.S.C. 1531–
1538) (UMRA) establishes requirements
for federal agencies to assess the effects
of their regulatory actions on state,
local, and tribal governments and the
private sector. This rule does not
impose any federal mandate on any
state, local, or tribal government or the
private sector within the meaning of
UMRA.
PO 00000
Frm 00020
Fmt 4702
Sfmt 4702
Environmental Impact
This proposed rule that does not
direct, provide for assistance or loan
and mortgage insurance for, or
otherwise govern, or regulate, real
property acquisition, disposition,
leasing, rehabilitation, alteration,
demolition, or new construction, or
establish, revise or provide for standards
for construction or construction
materials, manufactured housing, or
occupancy. Accordingly, under 24 CFR
50.19(c)(1), this proposed rule is
categorically excluded from
environmental review under the
National Environmental Policy Act of
1969 (42 U.S.C. 4321).
Regulatory Flexibility Act
The Regulatory Flexibility Act (RFA)
(5 U.S.C. 601 et seq.) generally requires
an agency to conduct a regulatory
flexibility analysis of any rule subject to
notice and comment rulemaking
requirements, unless the agency certifies
that the rule will not have a significant
economic impact on a substantial
number of small entities. All PHAs have
been required to complete energy
audits, which essentially review
building systems for the purpose of
assessing whether the project would
benefit from energy conservation
measures. This rule also clarifies the
scope of the energy audit that would be
made pursuant to the existing energy
audit requirements, rather than creating
a new requirement for PHAs. To the
extent that the standards for the energy
audit pursuant to this rule are more
burdensome than the current state
standards required for energy audits,
there may be some incremental cost to
some PHAs to perform audits to this
standard. However, this cost would be
miniscule fraction of each PHA’s capital
grant, and so would not be a significant
economic impact. For example, making
the most conservative assumption—that
each small PHA would be required to
hire an independent auditor rather than
using existing staff time—the
incremental cost would be $32.86 per
unit per 5 years, or $6.57 per unit per
year. The capital fund grant averages
$1595 per unit, per year, so that the cost
as a percentage of capital grant is only
0.4 percent. In actuality, the costs may
be lower, because at least some small
PHAs will have the staff resources to
perform the audit in-house.
Notwithstanding the determination
that this rule would not have a
significant impact on PHAs, HUD
specifically invites any comments
regarding any less burdensome
alternatives to this rule that will meet
E:\FR\FM\17NOP1.SGM
17NOP1
Federal Register / Vol. 76, No. 222 / Thursday, November 17, 2011 / Proposed Rules
HUD’s objectives as described in this
preamble.
Executive Order 13132, Federalism
Executive Order 13132 (entitled
‘‘Federalism’’) prohibits, to the extent
practicable and permitted by law, an
agency from promulgating a regulation
that has federalism implications and
either imposes substantial direct
compliance costs on state and local
governments and is not required by
statute or preempts state law, unless the
relevant requirements of section 6 of the
Executive Order are met. This rule does
not have federalism implications and
does not impose substantial direct
compliance costs on state and local
governments or preempt state law
within the meaning of the Executive
Order.
Catalog of Federal Domestic Assistance
Number
The Catalog of Federal Domestic
Assistance number for 24 CFR part 905
is 14.872.
List of Subjects in 24 CFR 905
Grant programs—housing and
community development, Public
housing, Reporting and recordkeeping
requirements.
Accordingly, for the reasons stated in
the preamble, HUD proposes to amend
24 CFR part 905, as proposed to be
revised at 76 FR 6661, February 7, 2011,
as follows:
PART 905—THE PUBLIC HOUSING
CAPITAL FUND PROGRAM
1. The authority statement for part
905 continues to read as follows:
Authority: 42 U.S.C. 1437g, 42 U.S.C.
1437z–2, and 3535(d).
Subpart C—General Program
Requirements
2. Amend § 905.300 by adding
paragraphs (b)(10) through (b)(15) to
read as follows:
§ 905.300 Capital Fund submission
requirements.
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
*
*
*
*
*
(b) * * *
(10) Energy audits. All PHAs shall
complete an energy audit for each PHAowned project under management, not
less than once every 5 years, unless
otherwise specified in this part.
(i) Energy audits consist of reviews of
building systems to evaluate and
identify projected costs, savings, and
payback periods related to
implementing any of a variety of
potential energy conservation measures.
Energy audits required by this part may,
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
but are not required to, also identify
green measures, or measures that do not
result in energy savings, but which
instead result in environmental benefits,
such as improving indoor air quality.
(ii) The purpose of this subpart is to
provide minimum standards with
respect to the performance of energy
audits. PHAs are not required to
implement any specific energy
conservation measure identified in an
energy audit, except to the extent
required by other statutes, rules, or
regulations. An energy audit, however,
must provide PHA staff with accurate
information about the condition of the
PHA’s properties with respect to energy
conservation measures and to the
payback associated with energy
conservation measures. The audit may
also provide information about the
environmental or potential health
benefits of green measures.
(iii) PHAs shall integrate utility
management with capital planning, to
maximize energy conservation and
efficiency measures in a comprehensive
approach to building design,
development, and maintenance. Energy
audits shall be conducted in
conjunction with HUD’s required PNA.
Any planned, ongoing, or completed
energy, utility, and green improvements
must be captured in the PNA in a form
and manner prescribed by HUD.
(iv) PHAs shall not be required to
complete an energy audit for any project
that is less than 5 years old at the time
the PHA is required to complete the
energy audit. PHAs shall not be required
to complete an energy audit for any
project for which a removal from the
public housing inventory has been
approved by HUD, such as a demolition,
disposition, conversion to
homeownership, or other conversion
action.
(v) The first two energy audits
completed under this section shall be
completed in accordance with a time
frame delineated by HUD.
(vi) When a PHA is required to submit
an energy audit pursuant to this part for
the first time, a PHA has the option of
submitting an existing audit completed
within the last 2 years if:
(A) The audit meets the data
requirements under this section; and
(B) The audit was completed by an
auditor that meets the requirements of
this section.
(vii) When a PHA is required to
complete and submit an energy audit for
the first time, a PHA may request an
additional 2 years to submit the audit if
it cannot find a qualified auditor. To
obtain HUD’s approval, a PHA must
provide documentation to its field office
that demonstrates it issued a well-
PO 00000
Frm 00021
Fmt 4702
Sfmt 4702
71291
structured Request for Proposal (RFP) in
accordance with 24 CFR 85.36, and
received no bids from qualified
respondents.
(11) Energy and water conservation
measures (ECMs). ECMs are devices,
systems, or processes that may reduce
utility and energy consumption. For the
purposes of this subpart, ECMs include
‘‘Core ECMs’’ and ‘‘Advanced ECMs.’’
(12) Core ECMs are defined as broadly
available energy conservation measures
that have proven track records of
reducing energy and water consumption
in a cost-effective manner. Core ECMs
include, but are not limited to, the
following ECM categories:
(i) Building envelope (ECMs such as,
but not limited to, wall or attic
insulation, roofs, storm doors,
weatherization, radiant barriers, and
windows);
(ii) Heating, cooling, and other
mechanical equipment systems and
controls (ECMs such as, but not limited
to, energy efficient furnaces, air
handlers, fans, condensers, boilers, hot
water heaters, programmable
thermostats, equipment refurbishment
and commissioning, duct sealing, duct
insulation, pipe insulation, water
heating controls, and ventilation);
(iii) Water conservation (ECMs such
as, but not limited to, low flow toilets,
faucets, showerheads, and alternate
irrigation);
(iv) Power, lighting systems, and
controls (ECMs such as, but not limited
to, compact fluorescent lighting, LED
fixtures and exit signage, photocell
controls, and motion controls);
(v) Appliances (ECMs such as, but not
limited, to Energy Star-rated
refrigerators, clothes washers, and
dishwashers).
(13) Advanced ECMs are defined as
alternative measures comprising
advanced or experimental technology
which, compared to Core ECMs, can be
more challenging to evaluate and
implement. These are not alternatives
that auditors would normally consider
unless directed to do so, or unless there
were local precedents that caused the
measures to become commonly
accepted local alternatives. Advanced
ECMs include, but are not limited to:
(i) Fuel conversions;
(ii) Conservation technologies (e.g.,
green construction techniques, building
energy management systems, and
xeriscaping 6); and
6 Xeriscaping is the conservation of landscape
irrigation water through creative and efficient
landscape design.
E:\FR\FM\17NOP1.SGM
17NOP1
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
71292
Federal Register / Vol. 76, No. 222 / Thursday, November 17, 2011 / Proposed Rules
(iii) Energy generating technologies
and renewable energy systems (e.g.,
solar, geothermal, and cogeneration 7).
(14) Energy audit technical
requirements and reporting. (i) An
energy audit shall analyze utility
consumption, review property and
building data, and evaluate Core ECMs
that could result in cost-effective energy
and water conservation. At the option of
the PHA, an energy audit may also
evaluate Advanced ECMs and green
measures.
(ii) Energy audits for public housing
shall at a minimum consider the Core
ECMs and provide a comprehensive
assessment report that includes:
(A) A summary review of the findings
of any previous energy audits;
(B) An assessment of the existing
property physical components affecting
energy consumption, including an
evaluation of the performance and
condition of components within the
Core ECM categories.
(C) An assessment of building
operations, maintenance, and resident
education as it relates to energy
conservation and green practices;
(D) Analysis of fuel, electricity, and
water bills and usage for at least the
PHA-held accounts for trend analysis
and industry benchmarking, and for
tenant-held accounts where usage
information is in the possession of the
PHA;
(E) Identification and evaluation of all
energy conservation measures
considered, which shall include at least
those that have the potential for costeffective implementation;
(F) Categorization of recommended
energy conservation measures into
improvements with payback periods of
12 years or less, greater than 12 and less
than or equal to 20 years, and more than
20 years;
(G) Projected cost of ECMs, and where
a standard (less energy-efficient)
building component is available, the
projected cost of the standard
component and the incremental cost of
the ECM;
(H) Projected annual savings in water
consumption;
(I) Projected annual energy
consumption savings in the appropriate
unit of measurement (i.e., kilowatthours, British Thermal Unit (BTU),8
7 Cogeneration is the use of the byproduct of
energy generation, primarily thermal energy, for
other purposes that would normally require
additional energy.
8 A BTU is defined as the amount of heat required
to raise the temperature of 1 pound (0.454 kg) of
liquid water by 1 °F (0.556 °C) at a constant
pressure of one atmosphere.
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
gallons, cubic feet etc.) for
recommended ECMs;
(J) Projected annual savings in dollars
for recommended ECMs;
(K) Expected useful life of all ECMs
and green measures;
(L) Identification of life cycle costs or
savings of ECMs and green measures,
including disposal costs and
maintenance costs; and
(M) Energy auditor recommendations
for optimal sequencing of ECM
implementation for maximum benefit.
(iii) The energy audit will identify
related physical work items that must be
implemented at the same time to assure
that a specific ECM can provide the
maximum savings calculated, as well as
to maintain health and safety (e.g., the
installation of an energy-efficient boiler
may require that new, wider
distribution lines be installed or
rerouted to maximize the potential
savings that could be realized from the
boiler; and a weatherization project may
require adjustments to ventilation
systems to maintain adequate fresh air
exchange). These complementary
activities should be viewed as part of an
improvement package required to
achieve the overall energy savings.
(iv) Data and findings from prior
energy audits that are deemed reliable
and remain valid may be carried over to
subsequent audits.
(v) Where ECMs would replace
existing components at the end of their
useful life, the payback period shall be
calculated by dividing the incremental
cost of replacement with an ECM as
compared with a standard component,
by the projected annual savings of the
ECM as compared with a standard
component. Where ECMs would replace
existing components before the end of
their useful life (early replacement), the
payback period calculation shall be
modified to add the value of the
remaining useful life of the component
being replaced to the incremental cost of
the ECM. This payback period
calculation shall be modified in a
manner acceptable to HUD. Where
ECMs would improve a project by
adding new systems or new
functionality, such as in the case of
energy-generating equipment, the
payback period shall be calculated by
dividing the total cost of the ECM by the
projected annual savings.
(vi) The energy audit shall
differentiate between activities that are
routine operating and maintenance
activities and ECMs that are capital
expenditures and can be financed with
capital funds. Cleaning or changing air
filters on certain mechanical equipment
is a routine operational maintenance
function that may result in energy
PO 00000
Frm 00022
Fmt 4702
Sfmt 4702
conservation but is not an eligible
capital expense.
(vii) For purposes of this part, the
potential for cost-effective
implementation of an energy
conservation measure must be evaluated
when the payback period is equal to or
less than the estimated useful life of the
component or 12 years, whichever is
less. Complete lifecycle cost analysis to
refine cost impacts of energy
conservation measures is recommended
for those measures initially determined
to be cost-effective.
(viii) The energy auditor shall report
on a project-level basis. The energy
auditor shall submit a baseline report to
the PHA and may submit an expanded
report, as noted below. The report shall
include the elements in
§ 905.300(b)(14)(i) for at least the ECMs
identified in § 905.300(b)(14)(i)(D). The
baseline report shall include a
recommendation as to whether the PHA
should complete more extensive
engineering reviews to determine
whether consideration of Advanced
ECMs or others would be warranted.
The energy auditor’s recommendation
shall be based upon the potential
lifecycle cost savings of the ECMs, the
complexity associated with
implementing the ECMs, and the age
and condition of the project as a whole.
If the PHA directs the energy auditor to
complete additional analysis on these
ECMs, the energy audit shall be
expanded to include that analysis.
(ix) There may be occasions outside of
the 5-year cycle when an energy audit
is appropriate and necessary to comply
with state-specific energy policies,
participate in local utility company
incentive programs, pursue an energy
performance contract, or evaluate the
financial condition of a project. Nothing
in this subpart is to be construed as
prohibiting an energy audit at any time
that the PHA determines it to be in the
interest of the project.
(x) Capital or operating funds may be
used for energy audits whenever they
are performed.
(xi) Energy audits required in this
section do not need to be investment
grade energy audits,9 but must cover all
projects, and be sufficient to determine
projected savings and to prioritize
potential work based on the goals and
objectives identified by the PHA (e.g.,
quickest payback, largest payback,
speed of implementation, etc.). Any
energy audit may rely on data from a
HUD-required prior energy audit (such
as described in part § 905.300(b)(14)(i)
9 Investment Grade Energy Audits are prepared
specifically to support a financial transaction such
as an energy performance contract.
E:\FR\FM\17NOP1.SGM
17NOP1
pmangrum on DSK3VPTVN1PROD with PROPOSALS-1
Federal Register / Vol. 76, No. 222 / Thursday, November 17, 2011 / Proposed Rules
or performed in relation to an energy
performance contract) conducted on the
same property, if the previous audit was
completed within 2 years of the time of
a required PNA or energy audit, and if
the previous audit meets the data
requirements of the audits prescribed by
this section.
(xii) While the timing of an energy
audit is coordinated with a PNA, there
are several instances when HUD may
require a current or updated energy
audit. These include but are not limited
to:
(A) When requesting HUD permission
to transfer excess cash from one project
to another;
(B) At the direction of HUD, when
HUD energy consumption data or
industry benchmarks indicate that a
project’s energy consumption levels are
excessive when compared to similar
projects within the project’s climatic
zone;
(C) When required to substantiate an
exception to the Total Development
Cost Limit in reference to 24 CFR
941.306; and
(D) When the PHA is substandard
under any applicable performance
rating system used by HUD to assess
project-level performance both in terms
of operations and financial condition.
(xiii) The energy auditor shall be
experienced in the performance of
residential building energy audits and
shall hold a current, valid certification
from a state energy audit certifying
agency for the state where the property
is located or a nationally recognized
energy audit certification provider, or
hold other certification acceptable to
HUD or expressed in HUD guidance.
(15) Green measures. (i) Green
measures are products, systems or
processes that do not necessarily
conserve energy, but result in other
environmental benefits. These include,
for example: use of low volatility or
nonvolatile organic compound cabinets,
flooring, paints, or sealants; physical
changes required to effectively
implement integrated pest management;
and hazardous waste or construction
debris removal processes.
(ii) An energy audit shall identify
green measures if the PHA directs the
energy auditor to include them in the
energy audit, but they are not required
to be included. Where an energy audit
includes green measures, it shall
identify the projected cost of the green
measure, and where a standard building
component is available, it shall identify
the projected cost for the standard
component and the incremental cost of
the green measure.
VerDate Mar<15>2010
14:57 Nov 16, 2011
Jkt 226001
Dated: October 21, 2011.
Sandra B. Henriquez,
Assistant Secretary for Public and Indian
Housing.
[FR Doc. 2011–29640 Filed 11–16–11; 8:45 am]
BILLING CODE 4210–67–P
DEPARTMENT OF THE TREASURY
Office of the Secretary
31 CFR Part 1
RIN 1505–AC37
Privacy Act; Implementation
Office of the Secretary,
Treasury.
ACTION: Proposed rule.
AGENCY:
In accordance with the
requirements of the Privacy Act of 1974,
as amended, the Department of the
Treasury (Treasury) amends this part to
partially exempt a new Internal Revenue
Service (IRS) system of records entitled
‘‘Treasury/IRS 37.111—Preparer Tax
Identification Number Records’’ from
certain provisions of the Privacy Act.
DATES: Comments must be received no
later than December 19, 2011.
ADDRESSES: Please submit comments to
David R. Williams, Director, Return
Preparer Office, 1111 Constitution Ave.
NW., Washington, DC 20224. Phone:
(202) 927–6428 (not a toll-free number).
Comments will be made available for
inspection at the IRS Freedom of
Information Reading Room (Room
1621), at the above address. The
telephone number for the Reading Room
is (202) 622–5164 (not a toll-free
number). You may also submit
comments through the Federal
rulemaking portal at https://
www.regulations.gov (follow the
instructions for submitting comments).
FOR FURTHER INFORMATION CONTACT:
David R. Williams, Director, Return
Preparer Office, 1111 Constitution Ave.
NW., Washington, DC 20224.
SUPPLEMENTARY INFORMATION: Under 5
U.S.C. 552a(k)(2), the head of an agency
may promulgate rules to exempt a
system of records from certain
provisions of 5 U.S.C. 552a if the system
is investigatory material compiled for
law enforcement purposes. Treasury is
hereby giving notice of a proposed rule
to exempt ‘‘Treasury/IRS 37.111—
Preparer Tax Identification Number
Records’’ from certain provisions of the
Privacy Act of 1974, pursuant to 5
U.S.C. 552a(k)(2). The proposed
exemption pursuant to 5 U.S.C.
552a(k)(2) is from provisions (c)(3),
(d)(1)–(4), (e)(1), (e)(4)(G)–(I), and (f)
SUMMARY:
PO 00000
Frm 00023
Fmt 4702
Sfmt 4702
71293
because the system contains
investigatory material compiled for law
enforcement purposes. The following
are the reasons why this system of
records maintained by the IRS is exempt
pursuant to 5 U.S.C. 552a(k)(2) of the
Privacy Act of 1974:
(1) 5 U.S.C. 552a(c)(3). These
provisions of the Privacy Act provide
for the release of the disclosure
accounting required by 5 U.S.C.
552a(c)(1) and (2) to the individual
named in the record at his/her request.
The reasons for exempting this system
of records from the foregoing provisions
are:
(i) The release of disclosure
accounting would put the subject of an
investigation on notice that an
investigation exists and that such
person is the subject of that
investigation.
(ii) Such release would provide the
subject of an investigation with an
accurate accounting of the date, nature,
and purpose of each disclosure and the
name and address of the person or
agency to which disclosure was made.
The release of such information to the
subject of an investigation would
provide the subject with significant
information concerning the nature of the
investigation and could result in the
alteration or destruction of documentary
evidence, the improper influencing of
witnesses, and other activities that
could impede or compromise the
investigation.
(iii) Release to the individual of the
disclosure accounting would alert the
individual as to which agencies were
investigating the subject and the scope
of the investigation and could aid the
individual in impeding or
compromising investigations by those
agencies.
(2) 5 U.S.C. 552a(d)(1)–(4), (e)(4)(G),
(e)(4)(H), and (f). These provisions of the
Privacy Act relate to an individual’s
right to be notified of:
(i) The existence of records pertaining
to such individual,
(ii) Requirements for identifying an
individual who requested access to
records,
(iii) The agency procedures relating to
access to and amendment of records,
(iv) The content of the information
contained in such records, and
(v) The civil remedies available to the
individual in the event of an adverse
determination by an agency concerning
access to or amendment of information
contained in record systems.
The reasons for exempting this system
of records from the foregoing provisions
are that notifying an individual (at the
individual’s request) of the existence of
an investigative file pertaining to such
E:\FR\FM\17NOP1.SGM
17NOP1
Agencies
[Federal Register Volume 76, Number 222 (Thursday, November 17, 2011)]
[Proposed Rules]
[Pages 71287-71293]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-29640]
[[Page 71287]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT
24 CFR Part 905
[Docket No. FR-5507-P-01]
RIN 2577-AC84
Public Housing Energy Audits
AGENCY: Office of the Assistant Secretary for Public and Indian
Housing, HUD.
ACTION: Proposed rule.
-----------------------------------------------------------------------
SUMMARY: This rule proposes to revise HUD's energy audit requirements
applicable to HUD's public housing program for the purpose of
clarifying such requirements, as well as identifying energy-efficient
measures that need to be addressed in the audit and procedures for
improved coordination with physical needs assessments. In addition, the
rule moves the energy audit requirements to a different part of HUD's
title of the Code of Federal Regulations.
DATES: Comment Due Date: January 17, 2012.
ADDRESSES: Interested persons are invited to submit comments regarding
this proposed rule to the Regulations Division, Office of General
Counsel, Department of Housing and Urban Development, 451 7th Street
SW., Room 10276, Washington, DC 20410-0500. Communications must refer
to the above docket number and title. There are two methods for
submitting public comments. All submissions must refer to the above
docket number and title.
1. Submission of Comments by Mail. Comments may be submitted by
mail to the Regulations Division, Office of General Counsel, Department
of Housing and Urban Development, 451 7th Street SW., Room 10276,
Washington, DC 20410-0500.
2. Electronic Submission of Comments. Interested persons may submit
comments electronically through the Federal eRulemaking Portal at
https://www.regulations.gov. HUD strongly encourages commenters to
submit comments electronically. Electronic submission of comments
allows the commenter maximum time to prepare and submit a comment,
ensures timely receipt by HUD, and enables HUD to make them immediately
available to the public. Comments submitted electronically through the
https://www.regulations.gov Web site can be viewed by other commenters
and interested members of the public. Commenters should follow the
instructions provided on that site to submit comments electronically.
Note: To receive consideration as public comments, comments
must be submitted through one of the two methods specified above.
Again, all submissions must refer to the docket number and title of
the rule.
No Facsimile Comments. Facsimile (fax) comments are not acceptable.
Public Inspection of Public Comments. All properly submitted
comments and communications submitted to HUD will be available for
public inspection and copying between 8 a.m. and 5 p.m. weekdays at the
above address. Due to security measures at the HUD Headquarters
building, an advance appointment to review the public comments must be
scheduled by calling the Regulations Division at (202) 402-3055 (this
is not a toll-free number). Individuals with speech or hearing
impairments may access this number via TTY by calling the Federal Relay
Service, toll-free, at (800) 877-8339. Copies of all comments submitted
are available for inspection and downloading at https://www.regulations.gov.
FOR FURTHER INFORMATION CONTACT: Jeffrey Riddel, Director, Office of
Capital Improvements, Office of Public and Indian Housing, Department
of Housing and Urban Development, 451 7th Street SW., Washington, DC
20410-8000; telephone number (202) 402-7378 (this is not a toll-free
number). Hearing- or speech-impaired individuals may access this number
through TTY by calling the toll-free Federal Relay Service at (800)
877-8339.
SUPPLEMENTARY INFORMATION:
I. Background
Because of the increasing importance of energy conservation, HUD is
taking a more proactive approach toward encouraging energy efficiency
in its housing programs. In order for public housing agencies (PHAs) to
improve their capital planning processes, HUD determined that there is
a need for stronger energy audit data.
Under existing regulations, all PHAs must complete an energy audit
for each PHA-owned project under management at least once every 5
years. The existing regulations also require that standards for energy
audits be equivalent to state standards. However, state standards for
energy audits are variable or nonexistent (see, for example, the map of
state energy codes by the Department of Energy at https://www.energycodes.gov/states/). Accordingly, it is HUD's view that energy
audit standards present an area where additional guidance will produce
more useful results.
In this rule, HUD proposes the energy conservation measures (ECMs)
that a PHA must consider at a minimum when performing an energy audit.
This rule also proposes certain minimum qualifications for energy
auditors procured by PHAs to perform energy audits.
While this rule proposes ECMs that must be considered, as well as
certain standards for energy audits and minimum qualifications for
energy auditors, HUD specifically seeks public comment on whether there
are other standards and qualifications that HUD should consider
adopting.
HUD will be publishing separately a proposed rule on physical needs
assessments (PNAs) that will require the completion of PNAs in
conjunction with energy audits in order to integrate the audit properly
with the PNA. The PNA rule proposes to require data derived from the
energy audit to be included in a PNA, to facilitate the identification
of cost-effective ECMs. ECMs also include water-related efficiency
measures. If a PNA and energy audit are performed together, there could
be cost savings to PHAs to the extent that many of the same components
are reviewed for each. Through this rule and the PNA rule, HUD seeks to
have PHAs move toward coordinating the performance of PNAs and energy
audits with each other, to maximize the effective use of this type of
information.
HUD specifically seeks comments from PHAs and other interested
parties as to an appropriate time frame for performance and submission
requirements.
Coordination between an energy auditor and PNA provider is
considered to be important in the capital improvement decision-making
process. As the consulting industry that services PHAs and the public
housing program is introduced to coordinated or integrated PNAs and
energy audits, the costs associated with performing both of these
assessments may be reduced. Since energy conservation products are
often newer technology whose prices tend to be reduced over time and
because utility costs are more volatile than general costs, 2 years is
considered by HUD to be the maximum time frame between the performance
of an energy audit and a PNA that maintains cost and pricing alignment.
In addition, coordination between an energy auditor and PNA provider is
considered to be important for the evaluation of technical issues in
the selection of component products and the sequencing of improvements.
Coordination of the timing of these activities may reduce the
possibility of additional cost to the PHA for consulting services
outside of the contract cycle of professional providers.
[[Page 71288]]
HUD is interested in receiving feedback concerning the feasibility
of requiring PHAs to coordinate the performance of energy audits and
PNAs. HUD specifically invites comment on the potential benefits,
feasibility, or challenges of preparing energy audits in conjunction
with PNAs. HUD also specifically seeks public comment on how quickly
energy audit information becomes obsolete for cost projection and
strategic planning in a PNA.
II. This Proposed Rule
A. Overview of Changes
This proposed rule moves the regulations pertaining to energy audit
requirements, which are currently codified in 24 CFR 965.302, to 24 CFR
905.300(b)(10)-905.300(b)(15), and clarifies HUD's requirements for
energy audits performed in conjunction with PNAs.
Also through this rule, HUD proposes to modify these regulations
to:
(1) Define an energy audit, ECMs, and ``green'' measures.
(2) Establish content and submission requirements for an energy
audit, and facilitate the integration of the energy audit with the PNA
that PHAs are required to conduct every 5 years. While many states have
not adopted auditing standards (see https://www.energycodes.gov/states/
), the PHA would still be required to comply with standards adopted for
their state, where applicable. HUD is not at this time prescribing a
specific energy audit form, so long as the required data is collected,
and so long as energy auditing systems and formats are available from a
number of sources, including the Department of Energy, Building
Performance Institute (BPI), and the Residential Energy Services
Network (RESNET).
(3) Define Core ECMs that must be considered and require further
evaluation of those ECMs that have the potential for cost-effective
implementation. Core ECMs generally represent commonplace conservation
measures that have demonstrated track records of reducing energy and
water consumption in a cost-effective manner and that can be routinely
evaluated by an energy auditor. This rule defines Core ECMs in broad
categories. Examples within the categories include: Changes to the
building envelope such as insulation; energy-efficient mechanical
equipment; low-flow water devices and other water conservation
measures; energy-efficient lighting systems, including compact
fluorescent lighting and motion controls; and Energy Star-certified
appliances. As technology advances over time, HUD will provide further
examples of ECMs in guidance.
(4) Recognize Advanced ECMs that may be addressed. PHAs are
encouraged, but not required to consider Advanced ECMs, which represent
alternative measures comprising advanced or experimental technology
which, compared to the Core ECMs, can be more challenging to evaluate
and implement. These are not alternatives that auditors would normally
consider unless directed to do so, or unless there were local
precedents that caused the measures to become commonly accepted local
alternatives. Examples of Advanced ECMs include renewable energy
technologies, such as solar and geothermal power, and green
construction.
(5) Require that ECMs identified in the energy audit as cost-
effective be organized into those with: Paybacks of 12 years or less,
paybacks of greater than 12 and less than or equal to 20 years, and
paybacks of more than 20 years. The 12-year and 20-year benchmarks
correspond with the benchmarks for an Energy Performance Contract
(EPC).
(6) Establish minimum qualifications for an energy auditor, and
(7) Provide for extension of the requirement to complete an initial
energy audit in instances where industry capacity is a constraint.
This rule would not require PHAs to implement particular ECMs;
however, the energy audit must provide PHAs with accurate information
about ECMs for the PHAs to consider. It is HUD's position that when
PHAs capture the cost-effectiveness data for ECMs, PHAs will implement
the measures more frequently.
The proposed rule would require payback analysis for Core ECMs.
Current guidance for a payback analysis is contained in the HUD
publication ``Energy Conservation for Housing--A Workbook,'' dated
September, 1998 (available at https://portal.hud.gov/hudportal/HUD?src=/program_offices/public_indian_housing/programs/ph/phecc/resources),
and this proposed rule would clarify and modify that guidance. The
payback analysis in the proposed rule would recognize that for a
replacement component, the incremental cost of a more efficient
component should be used to determine cost-effectiveness. For example,
if an Energy Star appliance costs $100 more than a standard appliance
with the same estimated life and the component has to be replaced, in
order for the Energy Star appliance to be cost-effective, it must cost
$100 less to operate than the standard component over the designated
payback period.
The result of a payback analysis would be considered in the context
of this rule as a threshold for further evaluation of an ECM. A more
detailed cost analysis may be conducted that includes complete
lifecycle cost analysis; however, the baseline audit requires only that
those lifecycle costs be generally identified, not that they be
subjected to detailed cost analysis.
The proposed rule would not prevent PHAs from pursuing more
advanced utility conservation and green measures, at their option. In
making the distinction between Core ECMs and Advanced ECMs, HUD is
recognizing extensive opportunities in public housing for simple cost-
effective energy conservation improvements, while acknowledging that
more advanced work may be possible in certain circumstances. The
engineering and implementation costs of advanced technologies often
make them impractical outside of the context of a comprehensive
redevelopment, remodeling, or incentivized program, such as an EPC or
targeted grant program. HUD's view is that it is preferable to
concentrate limited funding on improvements that have been proven to be
generally cost-effective and broadly available to PHAs. PHAs have
different priorities and local requirements with respect to utility
conservation and green improvements. Many improvements, while not
providing monetary cost effectiveness, provide benefits in the form of
an improved living environment for residents or a contribution to
broader societal environmental goals. HUD recognizes those benefits,
and encourages PHAs to consider a wide variety of measures. HUD's
Office of Healthy Homes and Lead Hazard Control and the Environmental
Protection Agency's Indoor Air Quality Standards, as well as Office of
Public and Indian Housing (PIH) notices on green building, are useful
resources for a PHA that is considering a program of green
improvements.
While it is HUD's position that the performance of the energy audit
at the same time as the PNA would be more efficient for PHAs,
particularly in circumstances where a single provider can perform both
services, HUD also recognizes that circumstances may not allow a PHA to
perform both services together. Accordingly, this rule does not require
the performance of the energy audit simultaneously with the PNA. HUD
recognizes circumstances where an energy audit would be performed
outside the 5-year cycle, such as an energy audit performed in relation
to an EPC or another development project, or
[[Page 71289]]
to meet another HUD requirement. As in the case of a PNA, the first
energy audit under the new final rule resulting from this proposed rule
is likely to be the most costly and require the most intensive effort,
with subsequent updates benefitting from the information collected in
prior audits. HUD also recognizes that the capacity of the energy
auditing industry might be limited in some areas, and allows for a
delay in the performance of the audit in cases where local shortages in
these professional services exist.
The rule does not propose to require an investment grade energy
audit such as one that might be prepared for an energy performance
contract or in order to evaluate a financial transaction. HUD is
especially interested in receiving comments about appropriate energy
audit requirements, as well as certification requirements and
professional standards for energy auditors. HUD is interested in
hearing from both the energy auditing industry and entities that have
experience managing a real estate portfolio and have integrated energy
audits into their planning process. HUD is also interested in receiving
comments about any multiple purposes for which portfolio managers have
used energy audits. HUD also invites comments about the proposed
categories of ECMs that should be addressed in an energy audit, and
conservation measures that are appropriate for use on a nationwide
basis. HUD further invites comments from public housing and other
interested parties on the needed capacity for performing integrated
energy audits and PNAs.
III. Findings and Certifications
Paperwork Reduction Act
The information collection requirements contained in this proposed
rule have been submitted to the Office of Management and Budget (OMB)
under the Paperwork Reduction Act of 1995 (44 U.S.C. 3501-3520). In
accordance with the Paperwork Reduction Act, an agency may not conduct
or sponsor, and a person is not required to respond to, a collection of
information, unless the collection displays a currently valid OMB
control number.
The burden of the information collections in this proposed rule is
estimated as follows:
Reporting and Recordkeeping Burden:
----------------------------------------------------------------------------------------------------------------
Estimated
Number of average time Estimated
Section reference Number of responses per for annual burden
respondents respondent requirement (in hours)
(in hours)
----------------------------------------------------------------------------------------------------------------
905.300(b)(10) \1\.............................. 620 1 65 40,300
905.300(b)(14) \2\.............................. 620 1 25 15,500
905.300(b)(14)(vii) \3\......................... 62 1 45 2,790
900.300(b)(15) \4\.............................. 62 1 45 2,790
---------------------------------------------------------------
Total Paperwork Burden for the New Rule..... .............. .............. .............. 61,380
Total Burden from Previous Rule (24 CFR .............. .............. .............. 29,440
965.302) \5\...............................
---------------------------------------------------------------
Total additional burden as a result of this .............. .............. .............. 31,940
rule.......................................
----------------------------------------------------------------------------------------------------------------
In accordance with 5 CFR 1320.8(d)(1), HUD is soliciting comments
from members of the public and affected agencies concerning this
collection of information to:
(1) Evaluate whether the proposed collection of information is
necessary for the proper performance of the functions of the agency,
including whether the information will have practical utility;
(2) Evaluate the accuracy of the agency's estimate of the burden of
the proposed collection of information;
(3) Enhance the quality, utility, and clarity of the information to
be collected; and
(4) Minimize the burden of the collection of information on those
who are to respond, including through the use of appropriate automated
collection techniques or other forms of information technology; e.g.,
permitting electronic submission of responses.
---------------------------------------------------------------------------
\1\ Burden of energy audit performed once every 5 years for each
of 3,200 PHAs, including data collection and site inspection.
\2\ Burden of analysis and comprehensive report.
\3\ Optional burden of expanded analysis as directed by PHA,
estimated to be exercised by 10 percent of respondents.
\4\ Optional burden of considering green measures as directed by
PHA, estimated to be exercised by 10 percent of respondents.
\5\ OMB Control No. 2577-0062.
---------------------------------------------------------------------------
Interested persons are invited to submit comments regarding the
information collection requirements in this rule. Under the provisions
of 5 CFR part 1320, OMB is required to make a decision concerning this
collection of information between 30 and 60 days after today's
publication date. Therefore, a comment on the information collection
requirements is best assured of having its full effect if OMB receives
the comment within 30 days of today's publication. This time frame does
not affect the deadline for comments to the agency on the proposed
rule, however. Comments must refer to the proposal by name and docket
number (FR-5361) and must be sent to:
HUD Desk Officer, Office of Management and Budget, New Executive Office
Building, Washington, DC 20503, Fax number: (202) 395-6947, and
Collette Pollard, Reports Liaison Officer, Department of Housing and
Urban Development, 451 7th Street, SW., Room 4160, Washington, DC
20410.
Interested persons may submit comments regarding the information
collection requirements electronically through the Federal eRulemaking
Portal at https://www.regulations.gov. HUD strongly encourages
commenters to submit comments electronically. Electronic submission of
comments allows the commenter maximum time to prepare and submit a
comment, ensures timely receipt by HUD, and enables HUD to make them
immediately available to the public. Comments submitted electronically
through the https://www.regulations.gov Web site can be viewed by other
commenters and interested members of the public. Commenters should
follow the instructions provided on that site to submit comments
electronically.
Regulatory Planning and Review
OMB reviewed this proposed rule under Executive Order 12866
(entitled ``Regulatory Planning and Review''). This rule was determined
to be a
[[Page 71290]]
``significant regulatory action,'' as defined in 3(f) of the order
(although not an economically significant regulatory action, as
provided under section 3(f)(1) of the order). The docket file is
available for public inspection between the hours of 8 a.m. and 5 p.m.
weekdays in the Regulations Division, Office of General Counsel,
Department of Housing and Urban Development, 451 7th Street SW., Room
10276, Washington, DC 20410-0500. Due to security measures at the HUD
Headquarters building, an advance appointment to review the docket file
must be scheduled by calling the Regulations Division at (202) 708-3055
(this is not a toll-free number). Hearing- or speech-impaired
individuals may access this number through TTY by calling the toll-free
Federal Information Relay Service at (800) 877-8339.
This proposed rule would revise HUD's energy audit requirements
applicable to HUD's public housing program for the purpose of
clarifying such requirements and defining energy-efficient measures and
audit procedures. It is estimated that the cost burden to PHAs could be
up to $40 million every 5 years or $8 million annually. Notwithstanding
the relatively modest cost to perform energy audits, there is a
potential for PHAs to realize substantial savings. Each year, about
$1.2 billion is budgeted for utilities for housing authorities.
Assuming that this rule is effective and energy audits are successfully
translated into energy savings, where, for example, only 10 percent
efficiency and cost were achieved, it would translate into about $120
million in budget savings annually that could be affected to other
uses. When tenant-paid utilities are included, the annual savings may
be up to $173 million under the same conditions. Notwithstanding the
potential benefit, this proposed rule is not economically significant
as defined by Executive Order 12866 and OMB Circular A-4.
The potential costs of the rule are as follows. The new Energy
Audit Rule does not change the current requirement that all PHAs
perform an energy audit at least once every 5 years. However, there
will be an economic impact to the extent that the new standards for
performance exceed the standard of performance for the state in which
each PHA is located.
The cost to perform the enhanced energy audit can be approximated
using existing examples and HUD's own experience. HUD's Office of
Affordable Housing Preservation (OAHP) manages the Green Retrofit
Program (GRP), which involves OAHP direct engagement of providers to
perform Physical Needs Assessment and Energy Audits for affordable
housing projects. The GRP energy audit includes all of the components
generally understood to be found in a baseline energy audit. HUD is
using the GRP format as a source for the development of energy audit
standards to be used in public housing, and the energy audit standards
in the new rule will be comparable in complexity/comprehensiveness.
OAHP has shared a summary of its costs to perform PNAs during Fiscal
Year 2009/10 using its format for a set of 66 projects nationwide.
These projects averaged 96 units per project. The average cost for the
energy audit portion of the GRP for these projects was reported as
$3,314 per project or $32.86 per unit.
In the absence of detailed cost figures for the energy audits
currently being performed by PHAs, the most conservative approach to
estimating the burden is to use the GRP figure of $32.86 per unit. Even
without a mitigating adjustment for the current economic investment
that PHAs are making to this activity, the economic burden to PHAs
would be $39,864,536 ($32.86 x 1,213,163) every 5 years, or $7,972,907
annually. A mitigating adjustment of 50 percent to account for the
existing burden is not an unreasonable assumption. Such an adjustment
would reduce the 5-year and annual additional burden to $19,932,268 and
$3,986,453, respectively.
There are also benefits to the rule. Nationwide, PHA-paid utility
costs total around $1.3 billion annually, or about 25 percent of the
costs to operate public housing. It is estimated that an additional
$430 million in utility costs are paid by residents, but indirectly are
paid by PHAs in the form of utility allowances that reduce resident
rents. Assuming that this rule is effective and, for example, only 10
percent efficiency were achieved, that would translate into about $173
million in budget savings annually that could be realized and affected
to other uses.
Unfunded Mandates Reform Act
Title II of the Unfunded Mandates Reform Act of 1995 (2 U.S.C.
1531-1538) (UMRA) establishes requirements for federal agencies to
assess the effects of their regulatory actions on state, local, and
tribal governments and the private sector. This rule does not impose
any federal mandate on any state, local, or tribal government or the
private sector within the meaning of UMRA.
Environmental Impact
This proposed rule that does not direct, provide for assistance or
loan and mortgage insurance for, or otherwise govern, or regulate, real
property acquisition, disposition, leasing, rehabilitation, alteration,
demolition, or new construction, or establish, revise or provide for
standards for construction or construction materials, manufactured
housing, or occupancy. Accordingly, under 24 CFR 50.19(c)(1), this
proposed rule is categorically excluded from environmental review under
the National Environmental Policy Act of 1969 (42 U.S.C. 4321).
Regulatory Flexibility Act
The Regulatory Flexibility Act (RFA) (5 U.S.C. 601 et seq.)
generally requires an agency to conduct a regulatory flexibility
analysis of any rule subject to notice and comment rulemaking
requirements, unless the agency certifies that the rule will not have a
significant economic impact on a substantial number of small entities.
All PHAs have been required to complete energy audits, which
essentially review building systems for the purpose of assessing
whether the project would benefit from energy conservation measures.
This rule also clarifies the scope of the energy audit that would be
made pursuant to the existing energy audit requirements, rather than
creating a new requirement for PHAs. To the extent that the standards
for the energy audit pursuant to this rule are more burdensome than the
current state standards required for energy audits, there may be some
incremental cost to some PHAs to perform audits to this standard.
However, this cost would be miniscule fraction of each PHA's capital
grant, and so would not be a significant economic impact. For example,
making the most conservative assumption--that each small PHA would be
required to hire an independent auditor rather than using existing
staff time--the incremental cost would be $32.86 per unit per 5 years,
or $6.57 per unit per year. The capital fund grant averages $1595 per
unit, per year, so that the cost as a percentage of capital grant is
only 0.4 percent. In actuality, the costs may be lower, because at
least some small PHAs will have the staff resources to perform the
audit in-house.
Notwithstanding the determination that this rule would not have a
significant impact on PHAs, HUD specifically invites any comments
regarding any less burdensome alternatives to this rule that will meet
[[Page 71291]]
HUD's objectives as described in this preamble.
Executive Order 13132, Federalism
Executive Order 13132 (entitled ``Federalism'') prohibits, to the
extent practicable and permitted by law, an agency from promulgating a
regulation that has federalism implications and either imposes
substantial direct compliance costs on state and local governments and
is not required by statute or preempts state law, unless the relevant
requirements of section 6 of the Executive Order are met. This rule
does not have federalism implications and does not impose substantial
direct compliance costs on state and local governments or preempt state
law within the meaning of the Executive Order.
Catalog of Federal Domestic Assistance Number
The Catalog of Federal Domestic Assistance number for 24 CFR part
905 is 14.872.
List of Subjects in 24 CFR 905
Grant programs--housing and community development, Public housing,
Reporting and recordkeeping requirements.
Accordingly, for the reasons stated in the preamble, HUD proposes
to amend 24 CFR part 905, as proposed to be revised at 76 FR 6661,
February 7, 2011, as follows:
PART 905--THE PUBLIC HOUSING CAPITAL FUND PROGRAM
1. The authority statement for part 905 continues to read as
follows:
Authority: 42 U.S.C. 1437g, 42 U.S.C. 1437z-2, and 3535(d).
Subpart C--General Program Requirements
2. Amend Sec. 905.300 by adding paragraphs (b)(10) through (b)(15)
to read as follows:
Sec. 905.300 Capital Fund submission requirements.
* * * * *
(b) * * *
(10) Energy audits. All PHAs shall complete an energy audit for
each PHA-owned project under management, not less than once every 5
years, unless otherwise specified in this part.
(i) Energy audits consist of reviews of building systems to
evaluate and identify projected costs, savings, and payback periods
related to implementing any of a variety of potential energy
conservation measures. Energy audits required by this part may, but are
not required to, also identify green measures, or measures that do not
result in energy savings, but which instead result in environmental
benefits, such as improving indoor air quality.
(ii) The purpose of this subpart is to provide minimum standards
with respect to the performance of energy audits. PHAs are not required
to implement any specific energy conservation measure identified in an
energy audit, except to the extent required by other statutes, rules,
or regulations. An energy audit, however, must provide PHA staff with
accurate information about the condition of the PHA's properties with
respect to energy conservation measures and to the payback associated
with energy conservation measures. The audit may also provide
information about the environmental or potential health benefits of
green measures.
(iii) PHAs shall integrate utility management with capital
planning, to maximize energy conservation and efficiency measures in a
comprehensive approach to building design, development, and
maintenance. Energy audits shall be conducted in conjunction with HUD's
required PNA. Any planned, ongoing, or completed energy, utility, and
green improvements must be captured in the PNA in a form and manner
prescribed by HUD.
(iv) PHAs shall not be required to complete an energy audit for any
project that is less than 5 years old at the time the PHA is required
to complete the energy audit. PHAs shall not be required to complete an
energy audit for any project for which a removal from the public
housing inventory has been approved by HUD, such as a demolition,
disposition, conversion to homeownership, or other conversion action.
(v) The first two energy audits completed under this section shall
be completed in accordance with a time frame delineated by HUD.
(vi) When a PHA is required to submit an energy audit pursuant to
this part for the first time, a PHA has the option of submitting an
existing audit completed within the last 2 years if:
(A) The audit meets the data requirements under this section; and
(B) The audit was completed by an auditor that meets the
requirements of this section.
(vii) When a PHA is required to complete and submit an energy audit
for the first time, a PHA may request an additional 2 years to submit
the audit if it cannot find a qualified auditor. To obtain HUD's
approval, a PHA must provide documentation to its field office that
demonstrates it issued a well-structured Request for Proposal (RFP) in
accordance with 24 CFR 85.36, and received no bids from qualified
respondents.
(11) Energy and water conservation measures (ECMs). ECMs are
devices, systems, or processes that may reduce utility and energy
consumption. For the purposes of this subpart, ECMs include ``Core
ECMs'' and ``Advanced ECMs.''
(12) Core ECMs are defined as broadly available energy conservation
measures that have proven track records of reducing energy and water
consumption in a cost-effective manner. Core ECMs include, but are not
limited to, the following ECM categories:
(i) Building envelope (ECMs such as, but not limited to, wall or
attic insulation, roofs, storm doors, weatherization, radiant barriers,
and windows);
(ii) Heating, cooling, and other mechanical equipment systems and
controls (ECMs such as, but not limited to, energy efficient furnaces,
air handlers, fans, condensers, boilers, hot water heaters,
programmable thermostats, equipment refurbishment and commissioning,
duct sealing, duct insulation, pipe insulation, water heating controls,
and ventilation);
(iii) Water conservation (ECMs such as, but not limited to, low
flow toilets, faucets, showerheads, and alternate irrigation);
(iv) Power, lighting systems, and controls (ECMs such as, but not
limited to, compact fluorescent lighting, LED fixtures and exit
signage, photocell controls, and motion controls);
(v) Appliances (ECMs such as, but not limited, to Energy Star-rated
refrigerators, clothes washers, and dishwashers).
(13) Advanced ECMs are defined as alternative measures comprising
advanced or experimental technology which, compared to Core ECMs, can
be more challenging to evaluate and implement. These are not
alternatives that auditors would normally consider unless directed to
do so, or unless there were local precedents that caused the measures
to become commonly accepted local alternatives. Advanced ECMs include,
but are not limited to:
(i) Fuel conversions;
(ii) Conservation technologies (e.g., green construction
techniques, building energy management systems, and xeriscaping \6\);
and
---------------------------------------------------------------------------
\6\ Xeriscaping is the conservation of landscape irrigation
water through creative and efficient landscape design.
---------------------------------------------------------------------------
[[Page 71292]]
(iii) Energy generating technologies and renewable energy systems
(e.g., solar, geothermal, and cogeneration \7\).
---------------------------------------------------------------------------
\7\ Cogeneration is the use of the byproduct of energy
generation, primarily thermal energy, for other purposes that would
normally require additional energy.
---------------------------------------------------------------------------
(14) Energy audit technical requirements and reporting. (i) An
energy audit shall analyze utility consumption, review property and
building data, and evaluate Core ECMs that could result in cost-
effective energy and water conservation. At the option of the PHA, an
energy audit may also evaluate Advanced ECMs and green measures.
(ii) Energy audits for public housing shall at a minimum consider
the Core ECMs and provide a comprehensive assessment report that
includes:
(A) A summary review of the findings of any previous energy audits;
(B) An assessment of the existing property physical components
affecting energy consumption, including an evaluation of the
performance and condition of components within the Core ECM categories.
(C) An assessment of building operations, maintenance, and resident
education as it relates to energy conservation and green practices;
(D) Analysis of fuel, electricity, and water bills and usage for at
least the PHA-held accounts for trend analysis and industry
benchmarking, and for tenant-held accounts where usage information is
in the possession of the PHA;
(E) Identification and evaluation of all energy conservation
measures considered, which shall include at least those that have the
potential for cost-effective implementation;
(F) Categorization of recommended energy conservation measures into
improvements with payback periods of 12 years or less, greater than 12
and less than or equal to 20 years, and more than 20 years;
(G) Projected cost of ECMs, and where a standard (less energy-
efficient) building component is available, the projected cost of the
standard component and the incremental cost of the ECM;
(H) Projected annual savings in water consumption;
(I) Projected annual energy consumption savings in the appropriate
unit of measurement (i.e., kilowatt-hours, British Thermal Unit
(BTU),\8\ gallons, cubic feet etc.) for recommended ECMs;
---------------------------------------------------------------------------
\8\ A BTU is defined as the amount of heat required to raise the
temperature of 1 pound (0.454 kg) of liquid water by 1[emsp14][deg]F
(0.556 [deg]C) at a constant pressure of one atmosphere.
---------------------------------------------------------------------------
(J) Projected annual savings in dollars for recommended ECMs;
(K) Expected useful life of all ECMs and green measures;
(L) Identification of life cycle costs or savings of ECMs and green
measures, including disposal costs and maintenance costs; and
(M) Energy auditor recommendations for optimal sequencing of ECM
implementation for maximum benefit.
(iii) The energy audit will identify related physical work items
that must be implemented at the same time to assure that a specific ECM
can provide the maximum savings calculated, as well as to maintain
health and safety (e.g., the installation of an energy-efficient boiler
may require that new, wider distribution lines be installed or rerouted
to maximize the potential savings that could be realized from the
boiler; and a weatherization project may require adjustments to
ventilation systems to maintain adequate fresh air exchange). These
complementary activities should be viewed as part of an improvement
package required to achieve the overall energy savings.
(iv) Data and findings from prior energy audits that are deemed
reliable and remain valid may be carried over to subsequent audits.
(v) Where ECMs would replace existing components at the end of
their useful life, the payback period shall be calculated by dividing
the incremental cost of replacement with an ECM as compared with a
standard component, by the projected annual savings of the ECM as
compared with a standard component. Where ECMs would replace existing
components before the end of their useful life (early replacement), the
payback period calculation shall be modified to add the value of the
remaining useful life of the component being replaced to the
incremental cost of the ECM. This payback period calculation shall be
modified in a manner acceptable to HUD. Where ECMs would improve a
project by adding new systems or new functionality, such as in the case
of energy-generating equipment, the payback period shall be calculated
by dividing the total cost of the ECM by the projected annual savings.
(vi) The energy audit shall differentiate between activities that
are routine operating and maintenance activities and ECMs that are
capital expenditures and can be financed with capital funds. Cleaning
or changing air filters on certain mechanical equipment is a routine
operational maintenance function that may result in energy conservation
but is not an eligible capital expense.
(vii) For purposes of this part, the potential for cost-effective
implementation of an energy conservation measure must be evaluated when
the payback period is equal to or less than the estimated useful life
of the component or 12 years, whichever is less. Complete lifecycle
cost analysis to refine cost impacts of energy conservation measures is
recommended for those measures initially determined to be cost-
effective.
(viii) The energy auditor shall report on a project-level basis.
The energy auditor shall submit a baseline report to the PHA and may
submit an expanded report, as noted below. The report shall include the
elements in Sec. 905.300(b)(14)(i) for at least the ECMs identified in
Sec. 905.300(b)(14)(i)(D). The baseline report shall include a
recommendation as to whether the PHA should complete more extensive
engineering reviews to determine whether consideration of Advanced ECMs
or others would be warranted. The energy auditor's recommendation shall
be based upon the potential lifecycle cost savings of the ECMs, the
complexity associated with implementing the ECMs, and the age and
condition of the project as a whole. If the PHA directs the energy
auditor to complete additional analysis on these ECMs, the energy audit
shall be expanded to include that analysis.
(ix) There may be occasions outside of the 5-year cycle when an
energy audit is appropriate and necessary to comply with state-specific
energy policies, participate in local utility company incentive
programs, pursue an energy performance contract, or evaluate the
financial condition of a project. Nothing in this subpart is to be
construed as prohibiting an energy audit at any time that the PHA
determines it to be in the interest of the project.
(x) Capital or operating funds may be used for energy audits
whenever they are performed.
(xi) Energy audits required in this section do not need to be
investment grade energy audits,\9\ but must cover all projects, and be
sufficient to determine projected savings and to prioritize potential
work based on the goals and objectives identified by the PHA (e.g.,
quickest payback, largest payback, speed of implementation, etc.). Any
energy audit may rely on data from a HUD-required prior energy audit
(such as described in part Sec. 905.300(b)(14)(i)
[[Page 71293]]
or performed in relation to an energy performance contract) conducted
on the same property, if the previous audit was completed within 2
years of the time of a required PNA or energy audit, and if the
previous audit meets the data requirements of the audits prescribed by
this section.
---------------------------------------------------------------------------
\9\ Investment Grade Energy Audits are prepared specifically to
support a financial transaction such as an energy performance
contract.
---------------------------------------------------------------------------
(xii) While the timing of an energy audit is coordinated with a
PNA, there are several instances when HUD may require a current or
updated energy audit. These include but are not limited to:
(A) When requesting HUD permission to transfer excess cash from one
project to another;
(B) At the direction of HUD, when HUD energy consumption data or
industry benchmarks indicate that a project's energy consumption levels
are excessive when compared to similar projects within the project's
climatic zone;
(C) When required to substantiate an exception to the Total
Development Cost Limit in reference to 24 CFR 941.306; and
(D) When the PHA is substandard under any applicable performance
rating system used by HUD to assess project-level performance both in
terms of operations and financial condition.
(xiii) The energy auditor shall be experienced in the performance
of residential building energy audits and shall hold a current, valid
certification from a state energy audit certifying agency for the state
where the property is located or a nationally recognized energy audit
certification provider, or hold other certification acceptable to HUD
or expressed in HUD guidance.
(15) Green measures. (i) Green measures are products, systems or
processes that do not necessarily conserve energy, but result in other
environmental benefits. These include, for example: use of low
volatility or nonvolatile organic compound cabinets, flooring, paints,
or sealants; physical changes required to effectively implement
integrated pest management; and hazardous waste or construction debris
removal processes.
(ii) An energy audit shall identify green measures if the PHA
directs the energy auditor to include them in the energy audit, but
they are not required to be included. Where an energy audit includes
green measures, it shall identify the projected cost of the green
measure, and where a standard building component is available, it shall
identify the projected cost for the standard component and the
incremental cost of the green measure.
Dated: October 21, 2011.
Sandra B. Henriquez,
Assistant Secretary for Public and Indian Housing.