Federal Register / Vol. 76, No. 219 / Monday, November 14, 2011 / Notices
rebuilt South Haiwee dam having a total
storage capacity of 46,600 acre-feet and
a water surface area of 660 acres at full
pool elevation of 3,756 feet msl; (3)
approximately 13,150 feet of conduit
connecting the upper to the lower
reservoir in three different sections: A
3,000-foot-long by 18.5-foot-diameter,
concrete-lined low-pressure tunnel, a
7,850-foot-long by 18.5-foot-diameter
concrete-lined pressure shaft, and a
2,300-foot-long by 22.2-foot diameter
tailrace; and (4) an underground
powerhouse located roughly 1,500 feet
east of South Haiwee reservoir at an
elevation of 3,600 feet msl.
South Haiwee Alternative B: (1) An
upper reservoir formed by a 210-foothigh by 1,320-foot-long, RCC dam and a
25-foot-high by 800-foot-long RCC
saddle dam having a total storage
capacity of 14,235 acre-feet and a water
surface area of 241 acres at full pool
elevation of 5,000 feet msl; (2) a lower
reservoir formed by the 91-foot-high by
1,523-foot-long potentially rebuilt South
Haiwee dam having a total storage
capacity of 46,600 acre-feet and a water
surface area of 800 acres at full pool
elevation of 3,756 feet msl; (3)
approximately 14,700 feet of conduit
connecting the upper to the lower
reservoir in three different sections: a
5,100-foot-long by 18.9-foot-diameter,
concrete-lined low-pressure tunnel, a
5,600-foot-long by 18.9-foot-diameter
concrete-lined pressure shaft, and a
4,000-foot-long by 22.7-foot diameter
tailrace; and (4) an underground
powerhouse located roughly 3,300 feet
southeast of South Haiwee reservoir at
an elevation of 3,580 feet msl.
New Reservoir Alternative: (1) An
upper reservoir formed by a 210-foothigh by 1,320-foot-long, RCC dam
having a total storage capacity of 14,235
acre-feet and a water surface area of 241
acres at full pool elevation of 5,000 feet
msl; (2) a lower reservoir formed by a
60-foot-high by 10,600-foot-long RCC
dam having a total storage capacity of
46,600 acre-feet and a water surface area
of 800 acres at full pool elevation of
3,756 feet above msl; (3) approximately
12,500 feet of conduit connecting the
upper to the lower reservoir in three
different sections: a 3,750-foot-long by
17.5-foot-diameter, concrete-lined lowpressure tunnel, a 6,300-foot-long by
17.5-foot-diameter concrete-lined
pressure shaft, and a 2,500-foot-long by
21-foot diameter tailrace; and (4) an
underground located roughly 8,500 feet
southwest of South Haiwee reservoir at
an elevation of 3,400 feet msl.
All of the alternatives would consist
of 4 reversible pump-turbines with a
capacity of 500 megawatts (MW) (4
units x 125 MW unit). Annual energy
VerDate Mar<15>2010
19:40 Nov 10, 2011
Jkt 226001
output would be approximately
1,533,000 mega-watt-hours.
Interconnection would exist at the Los
Angeles Department of Water & Power’s
230-kilovolt (kV) Owens George-Rinaldi
transmission line via a 0.9-mile-long
interconnection, or with Southern
California Edison’s 115-kV ControlInyokern transmission line via a new
0.9- to 2.3-mile-long interconnection,
depending on constructed option. A 70foot-long by 280-foot-wide by 120-foothigh underground power house would
be the same for all of the project
alternatives.
Applicant Contact: Mr. Matthew
Shapiro, Haiwee Ridge Hydro, LLC.,
1210 W. Franklin St., Ste. 2, Boise, ID
83702; phone (208) 246–9925.
FERC Contact: Brian Csernak; phone:
(202) 502–6144.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–(866) 208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14286–000) in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
70441
Dated: November 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–29247 Filed 11–10–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP12–10–000]
Saltville Gas Storage Company LLC;
Notice of Request Under Blanket
Authorization
Take notice that on October 21, 2011
Saltville Gas Storage Company LLC
(Saltville), 5400 Westheimer Court,
Houston, Texas 77056, filed in Docket
No. CP12–10–000, a prior notice request
pursuant to sections 157.205 and
157.216 of the Commission’s
Regulations under the Natural Gas Act
(NGA) for authorization to abandon one
injection/withdrawal well in
Washington County, Virginia.
Specifically, Saltville proposes to
permanently plug and abandon the EH
123 wellbore and remove associated
wellhead and approximately 75 feet of
two-inch facility piping. Saltville states
that the proposed abandonment will not
result in the termination of any services
to Saltville’s customers, all as more fully
set forth in the application which is on
file with the Commission and open to
public inspection. The filing may also
be viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding this
Application should be directed to Lisa
A. Connolly, General Manager, Rates
and Certificates, Saltville Gas Storage
Company LLC, P.O. Box 1642, Houston,
Texas 77251, or call (713) 627–4102, or
fax (713) 627–5947, or by email:
laconnolly@spectraenergy.com.
Any person may, within 60 days after
the issuance of the instant notice by the
Commission, file pursuant to Rule 214
of the Commission’s Procedural Rules
(18 CFR 385.214) a motion to intervene
or notice of intervention. Any person
filing to intervene or the Commission’s
staff may, pursuant to section 157.205 of
the Commission’s Regulations under the
NGA (18 CFR 157.205) file a protest to
the request. If no protest is filed within
the time allowed therefore, the proposed
activity shall be deemed to be
E:\FR\FM\14NON1.SGM
14NON1
70442
Federal Register / Vol. 76, No. 219 / Monday, November 14, 2011 / Notices
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request shall be
treated as an application for
authorization pursuant to section 7 of
the NGA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with he Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the Internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
Dated: November 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–29244 Filed 11–10–11; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9491–1]
Clean Water Act Section 303(d):
Availability of 28 Total Maximum Daily
Loads (TMDLs) in Louisiana
Environmental Protection
Agency (EPA).
ACTION: Notice of availability.
AGENCY:
This notice announces the
availability for comment on the
administrative record files and the
calculations of 28 TMDLs prepared by
EPA Region 6. This notice covers waters
in the State of Louisiana’s Lake
Pontchartrain Basin that were identified
as impaired on the State’s Section
303(d) list. These TMDLs were
completed in response to a court order
in the lawsuit styled Sierra Club, et al.
v. Clifford, et al., No. 96–0527, (E.D.
La.).
DATES: Comments must be submitted in
writing to EPA on or before December
29, 2011.
ADDRESSES: Comments on the 28
TMDLs should be sent to Diane Smith,
Environmental Protection Specialist,
SUMMARY:
Water Quality Protection Division, U.S.
Environmental Protection Agency
Region 6, 1445 Ross Ave., Dallas, TX
75202–2733 or email:
smith.diane@epa.gov. For further
information, contact Diane Smith at
(214) 665–2145 or fax (214) 665–7373.
The administrative record files for the
28 TMDLs are available for public
inspection at this address as well.
Documents from the administrative
record files may be viewed at https://
www.epa.gov/earth1r6/6wq/npdes/
tmdl/index.htm, or obtained by calling
or writing Ms. Smith at the above
address. Please contact Ms. Smith to
schedule an inspection.
FOR FURTHER INFORMATION CONTACT:
Diane Smith at (214) 665–2145.
In 1996,
two Louisiana environmental groups,
the Sierra Club and Louisiana
Environmental Action Network
(plaintiffs), filed a lawsuit in Federal
Court against the EPA, styled Sierra
Club, et al. v. Clifford, et al., No. 96–
0527, (E.D. La.). Among other claims,
plaintiffs alleged that EPA failed to
establish Louisiana TMDLs in a timely
manner. EPA proposes these 28 TMDLs
pursuant to a consent decree entered in
this lawsuit.
SUPPLEMENTARY INFORMATION:
EPA Seeks Comment on 28 TMDLs
By this notice EPA is seeking
comment on the following 28 TMDLs
for waters located within Louisiana:
Subsegment
Waterbody name
040102 .....................................................
Comite River—Wilson-Clinton Hwy to entrance of White Bayou (East Baton
Rouge Parish) (Scenic).
Comite River—Entrance of White Bayou to Amite River .........................................
Bayou Manchac—Headwaters to Amite River .........................................................
Amite River—LA Hwy 37 to Amite River Diversion Canal .......................................
Grays Creek—Headwaters to Amite River ..............................................................
Colyell Creek System (includes Colyell Bay) ...........................................................
Natalbany River—Headwaters to Tickfaw River ......................................................
Yellow Water River—Origin to Ponchatoula Creek .................................................
Ponchatoula Creek and Ponchatoula River .............................................................
Selsers Creek—Origin to South Slough ...................................................................
Big Creek and Tributaries—Headwaters to confluence with Tangipahoia River .....
W–14 Main Diversion Canal—From its origin in the north end of the City of Slidell
to its junction with Salt Bayou.
Salt Bayou—Headwaters to Lake Pontchartrain (Estuarine) ...................................
Lake Pontchartrain Drainage Canals .......................................................................
New Orleans East Leveed Waterbodies (Estuarine) ...............................................
Tickfaw River—From MS State Line to LA Hwy 42 (Scenic) ..................................
Yellow Water River—Origin to Ponchatoula Creek .................................................
Amite River—MS State Line to LA Hwy 37 (Scenic) ...............................................
Blind River—From Amite River Diversion Canal to mouth at Lake Maurepas
(Scenic).
Bayou Cane—Headwaters to U.S. Hwy 190 (Scenic) .............................................
Amite River—Amite River Diversion Canal to Lake Maurepas ...............................
Blind River—From Amite River Diversion Canal to mouth at Lake Maurepas
(Scenic).
Blind River—Source to confluence with Amite River Diversion Canal (Scenic) ......
Tickfaw River—From MS State Line to LA Hwy 42 (Scenic) ..................................
Tangipahoa River—MS State Line to Interstate Hwy 1–12 (Scenic) ......................
mstockstill on DSK4VPTVN1PROD with NOTICES
040103
040201
040302
040304
040305
040503
040504
040505
040603
040703
040909
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
040910
041302
041401
040501
040504
040301
040401
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
.....................................................
040903 .....................................................
040303 .....................................................
040401 .....................................................
040403 .....................................................
040501 .....................................................
040701 .....................................................
VerDate Mar<15>2010
19:40 Nov 10, 2011
Jkt 226001
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
E:\FR\FM\14NON1.SGM
Pollutant
14NON1
Fecal Coliform.
Fecal
Fecal
Fecal
Fecal
Fecal
Fecal
Fecal
Fecal
Fecal
Fecal
Fecal
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Coliform.
Fecal Coliform.
Fecal Coliform.
Fecal Coliform.
TDS.
TDS.
TSS.
TSS.
TSS.
Mercury.
Mercury.
Mercury.
Mercury
Mercury.
Agencies
[Federal Register Volume 76, Number 219 (Monday, November 14, 2011)]
[Notices]
[Pages 70441-70442]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-29244]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP12-10-000]
Saltville Gas Storage Company LLC; Notice of Request Under
Blanket Authorization
Take notice that on October 21, 2011 Saltville Gas Storage Company
LLC (Saltville), 5400 Westheimer Court, Houston, Texas 77056, filed in
Docket No. CP12-10-000, a prior notice request pursuant to sections
157.205 and 157.216 of the Commission's Regulations under the Natural
Gas Act (NGA) for authorization to abandon one injection/withdrawal
well in Washington County, Virginia. Specifically, Saltville proposes
to permanently plug and abandon the EH 123 wellbore and remove
associated wellhead and approximately 75 feet of two-inch facility
piping. Saltville states that the proposed abandonment will not result
in the termination of any services to Saltville's customers, all as
more fully set forth in the application which is on file with the
Commission and open to public inspection. The filing may also be viewed
on the web at https://www.ferc.gov using the ``eLibrary'' link. Enter
the docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or TTY,
(202) 502-8659.
Any questions regarding this Application should be directed to Lisa
A. Connolly, General Manager, Rates and Certificates, Saltville Gas
Storage Company LLC, P.O. Box 1642, Houston, Texas 77251, or call (713)
627-4102, or fax (713) 627-5947, or by email:
laconnolly@spectraenergy.com.
Any person may, within 60 days after the issuance of the instant
notice by the Commission, file pursuant to Rule 214 of the Commission's
Procedural Rules (18 CFR 385.214) a motion to intervene or notice of
intervention. Any person filing to intervene or the Commission's staff
may, pursuant to section 157.205 of the Commission's Regulations under
the NGA (18 CFR 157.205) file a protest to the request. If no protest
is filed within the time allowed therefore, the proposed activity shall
be deemed to be
[[Page 70442]]
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request shall be treated as
an application for authorization pursuant to section 7 of the NGA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenter's will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with he Commission's environmental review process.
Environmental commenter's will not be required to serve copies of filed
documents on all other parties. However, the non-party commentary, will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests, and interventions via the Internet in lieu of paper. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov) under the ``e-Filing'' link.
Dated: November 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-29244 Filed 11-10-11; 8:45 am]