Clean Air Act Operating Permit Program; Petition for Objection to State Operating Permit for Public Service Company of Colorado dba Xcel Energy-Cherokee Power Station, 66286 [2011-27734]
Download as PDF
66286
Federal Register / Vol. 76, No. 207 / Wednesday, October 26, 2011 / Notices
requirements in regard to carbon
dioxide (CO2) emissions.
On September 29, 2011, the
Administrator issued an Administrative
Order denying the Petition. The Order
explains the reasons behind EPA’s
conclusions.
the Final Order for Public Service
Company of Colorado—Cherokee Power
Station is available electronically at:
https://www.epa.gov/region07/air/title5/
petitiondb/petitions/
xcel_cherokee_response2011.pdf.
Dated: October 19, 2011.
James B. Martin,
Regional Administrator, Region 8.
FOR FURTHER INFORMATION CONTACT:
Donald Law, Air Program (8P–AR), EPA
Region 8, 1595 Wynkoop Street, Denver,
Colorado 80202–1129. Phone: (303)312–
7015. E-mail: law.donald@epa.gov.
[FR Doc. 2011–27725 Filed 10–25–11; 8:45 am]
BILLING CODE 6560–50–P
The Act
affords EPA a 45-day period to review
and object to, as appropriate, a title V
operating permit proposed by State
permitting authorities. Section 505(b)(2)
of the Act authorizes any person to
petition the EPA Administrator, within
60 days after the expiration of this
review period, to object to a title V
operating permit if EPA has not done so.
Petitions must be based only on
objections to the permit that were raised
with reasonable specificity during the
public comment period provided by the
State, unless the petitioner demonstrates
that it was impracticable to raise these
issues during the comment period or the
grounds for the issues arose after this
period. EPA received a petition from
WildEarth Guardians dated April 1,
2010, requesting that EPA object to the
issuance of the title V operating permit
to Public Service Company of Colorado
for the operation of the Cherokee Power
Station. The Petition alleges that the
Permit does not comply with 40 CFR
part 70 in that it fails to assure
compliance with: (I) A compliance plan
for opacity monitoring requirements;
(II) applicable opacity requirements; (III)
particulate matter (PM) limits applicable
to the coal-fired boiler; (IV) CAA section
112(j) for air toxics; and (V) PSD
requirements in regard to carbon
dioxide (CO2) emissions.
On September 29, 2011, the
Administrator issued an Administrative
Order denying the Petition. The Order
explains the reasons behind EPA’s
conclusions.
SUPPLEMENTARY INFORMATION:
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9483–2]
Clean Air Act Operating Permit
Program; Petition for Objection to
State Operating Permit for Public
Service Company of Colorado dba Xcel
Energy—Cherokee Power Station
Environmental Protection
Agency (EPA).
ACTION: Notice of final action.
AGENCY:
This document announces
that the EPA Administrator has
responded to a citizen petition asking
EPA to object to an operating permit
issued by the Colorado Department of
Public Health and Environment
(CDPHE). Specifically, the
Administrator has denied the April 1,
2010, Petition, submitted by WildEarth
Guardians (Petitioner), to object to
CDPHE’s April 1, 2010, title V permit
issued to Public Service Company of
Colorado dba Xcel Energy (Xcel)—
Cherokee Power Station.
Pursuant to section 505(b)(2) of the
Clean Air Act (Act or CAA), Petitioners
may seek judicial review of those
portions of the petition that EPA denied
in the United States Court of Appeals
for the appropriate circuit. Any petition
for review shall be filed within 60 days
from the date this notice appears in the
Federal Register, pursuant to section
307 of the Act.
ADDRESSES: You may review copies of
the Final Order, the Petition, and other
supporting information at the EPA
Region 8 Office, 1595 Wynkoop Street,
Denver, Colorado 80202–1129. EPA
requests that if at all possible, you
contact the individual listed in the FOR
FURTHER INFORMATION CONTACT section to
view the copies of the Final Order, the
Petition, and other supporting
information. You may view the hard
copies Monday through Friday, 8 a.m. to
4 p.m., excluding Federal holidays. If
you wish to examine these documents,
you should make an appointment at
least 24 hours in advance. Additionally,
jlentini on DSK4TPTVN1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
16:53 Oct 25, 2011
Jkt 226001
Dated: October 19, 2011.
James B. Martin,
Regional Administrator, Region 8.
[FR Doc. 2011–27734 Filed 10–25–11; 8:45 am]
BILLING CODE 6560–50–P
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OW–2008–0517; FRL–9483–4]
RIN 2040–AF06
Notice of Final 2010 Effluent
Guidelines Program Plan
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
This notice presents the final
2010 Effluent Guidelines Program
Plan(‘‘final 2010 Plan’’), which, as
required under the Clean Water Act
(CWA), identifies any new or existing
industrial dischargers, both those
discharging directly to surface waters
and those discharging to publicly
owned treatment works (POTWs),
selected for effluent guidelines
rulemaking and provides a schedule for
such rulemakings. CWA section 304(m)
requires EPA to biennially publish such
a plan after public notice and comment.
The Agency published the preliminary
2010 Plan on December 28, 2009 (74 FR
68599) and solicited comments from the
public for 60 days.
After considering rulemakings already
in development, the 2010 reviews, the
preliminary Plan and public comments
and input to determine what, if any,
new rulemakings should be initiated,
EPA has decided to develop effluent
guidelines and standards for the
discharge of wastewater from the
Coalbed Methane Extraction (CBM)
industry and will develop pretreatments
requirements for discharges of mercury
from the Dental industry, and for the
discharges of wastewater from the Shale
Gas Extraction (SGE) industry.
EPA is also issuing the detailed study
report for the Coalbed Methane
Extraction and the preliminary study
report of the Ore Mining and Dressing
industry.
This notice also solicits public
comments on EPA’s 2011 reviews
pursuant to the authority of CWA
sections 304(b), 304(g), 301(d) and
307(b).
DATES: Submit comments on or before
November 25, 2011.
ADDRESSES: Submit your comments on
the final 2010 Plan, identified by Docket
ID No. EPA–HQ–OW–2008–0517, by
one of the following methods:
(1) https://www.regulations.gov.
Follow the on-line instructions for
submitting comments.
(2) E-mail: OW–Docket@epa.gov,
Attention Docket ID No. EPA–HQ–OW–
2008–0517.
(3) Mail: Water Docket, Environmental
Protection Agency, Mailcode: 4203M,
SUMMARY:
E:\FR\FM\26OCN1.SGM
26OCN1
Agencies
[Federal Register Volume 76, Number 207 (Wednesday, October 26, 2011)]
[Notices]
[Page 66286]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-27734]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[FRL-9483-2]
Clean Air Act Operating Permit Program; Petition for Objection to
State Operating Permit for Public Service Company of Colorado dba Xcel
Energy--Cherokee Power Station
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of final action.
-----------------------------------------------------------------------
SUMMARY: This document announces that the EPA Administrator has
responded to a citizen petition asking EPA to object to an operating
permit issued by the Colorado Department of Public Health and
Environment (CDPHE). Specifically, the Administrator has denied the
April 1, 2010, Petition, submitted by WildEarth Guardians (Petitioner),
to object to CDPHE's April 1, 2010, title V permit issued to Public
Service Company of Colorado dba Xcel Energy (Xcel)--Cherokee Power
Station.
Pursuant to section 505(b)(2) of the Clean Air Act (Act or CAA),
Petitioners may seek judicial review of those portions of the petition
that EPA denied in the United States Court of Appeals for the
appropriate circuit. Any petition for review shall be filed within 60
days from the date this notice appears in the Federal Register,
pursuant to section 307 of the Act.
ADDRESSES: You may review copies of the Final Order, the Petition, and
other supporting information at the EPA Region 8 Office, 1595 Wynkoop
Street, Denver, Colorado 80202-1129. EPA requests that if at all
possible, you contact the individual listed in the FOR FURTHER
INFORMATION CONTACT section to view the copies of the Final Order, the
Petition, and other supporting information. You may view the hard
copies Monday through Friday, 8 a.m. to 4 p.m., excluding Federal
holidays. If you wish to examine these documents, you should make an
appointment at least 24 hours in advance. Additionally, the Final Order
for Public Service Company of Colorado--Cherokee Power Station is
available electronically at: https://www.epa.gov/region07/air/title5/petitiondb/petitions/xcel_cherokee_response2011.pdf.
FOR FURTHER INFORMATION CONTACT: Donald Law, Air Program (8P-AR), EPA
Region 8, 1595 Wynkoop Street, Denver, Colorado 80202-1129. Phone:
(303)312-7015. E-mail: law.donald@epa.gov.
SUPPLEMENTARY INFORMATION: The Act affords EPA a 45-day period to
review and object to, as appropriate, a title V operating permit
proposed by State permitting authorities. Section 505(b)(2) of the Act
authorizes any person to petition the EPA Administrator, within 60 days
after the expiration of this review period, to object to a title V
operating permit if EPA has not done so. Petitions must be based only
on objections to the permit that were raised with reasonable
specificity during the public comment period provided by the State,
unless the petitioner demonstrates that it was impracticable to raise
these issues during the comment period or the grounds for the issues
arose after this period. EPA received a petition from WildEarth
Guardians dated April 1, 2010, requesting that EPA object to the
issuance of the title V operating permit to Public Service Company of
Colorado for the operation of the Cherokee Power Station. The Petition
alleges that the Permit does not comply with 40 CFR part 70 in that it
fails to assure compliance with: (I) A compliance plan for opacity
monitoring requirements; (II) applicable opacity requirements; (III)
particulate matter (PM) limits applicable to the coal-fired boiler;
(IV) CAA section 112(j) for air toxics; and (V) PSD requirements in
regard to carbon dioxide (CO2) emissions.
On September 29, 2011, the Administrator issued an Administrative
Order denying the Petition. The Order explains the reasons behind EPA's
conclusions.
Dated: October 19, 2011.
James B. Martin,
Regional Administrator, Region 8.
[FR Doc. 2011-27734 Filed 10-25-11; 8:45 am]
BILLING CODE 6560-50-P