Ocean Renewable Power Company, LLC; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Fishway Prescriptions, and Waiving the Timing Requirement for Filing Competing Development Applications, 63917-63918 [2011-26569]

Download as PDF Federal Register / Vol. 76, No. 199 / Friday, October 14, 2011 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12711–005] Ocean Renewable Power Company, LLC; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Fishway Prescriptions, and Waiving the Timing Requirement for Filing Competing Development Applications tkelley on DSK3SPTVN1PROD with NOTICES Take notice that the following hydrokinetic pilot project license application has been filed with the Commission and is available for public inspection. a. Type of Application: Pilot Project License. b. Project No.: 12711–005. c. Date Filed: September 1, 2011. d. Applicant: Ocean Renewable Power Company, LLC. e. Name of Project: Cobscook Bay Tidal Energy Project. f. Location: The proposed project would be located in Cobscook Bay, in Washington County, Maine. The project does not affect federal lands. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–828(c). h. Applicant Contact: Christopher R. Sauer, Ocean Renewable Power Company, LLC, 120 Exchange Street, Suite 508, Portland, Maine 04101, (207) 772–7707. i. FERC Contact: Timothy Konnert, telephone (202) 502–6359, and e-mail timothy.konnert@ferc.gov. j. Deadline for Filing Motions to Intervene and Protests, Comments, Recommendations, Terms and Conditions, and Fishway Prescriptions: 30 days from the issuance of this notice; reply comments are due 60 days from the issuance date of this notice. Motions to intervene, protests, comments, recommendations, terms and conditions, and fishway prescriptions may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll VerDate Mar<15>2010 15:20 Oct 13, 2011 Jkt 226001 free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted for filing and is now ready for environmental analysis. l. The Project Description: The primary project facilities would include: (1) A single, approximately 98.5-footlong, cross-flow Kinetic System turbine generator unit (TGU) mounted on a bottom support frame, with a rated capacity of 60 kilowatts (kW), in Phase 1; (2) four, approximately 98.5-foot-long, cross-flow Kinetic System TGUs mounted on bottom support frames, with a rated capacity of 60 kW each, in Phase 2; (3) a direct current power and data cable approximately 3,800 feet long (3,600 feet underwater and 200 feet on shore) extending from the TGUs to the onshore station house; (4) an on-shore building 32 feet wide by 35 feet long, housing the SatCon power inverter and the supervisory control and data acquisition (SCADA) system; and (5) appurtenant facilities for navigation safety and operation. The project would have a total rated capacity of 300 kW, with an estimated annual generation between 1,200,000 and 1,300,000 kilowatt-hours. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 63917 n. Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. All filings must (1) bear in all capital letters the title ‘‘PROTEST,’’ ‘‘MOTION TO INTERVENE,’’ ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘FISHWAY PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b) except to the extent that this notice establishes deadlines different from those in the regulation. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. o. Procedural Schedule: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule may be made as appropriate. Milestone Target date Filing of recommendations, terms and conditions, and fishway prescriptions. Commission issues Single EA. Comments on EA .......... November 5, 2011. January 4, 2012. February 3, 2012. p. Waiver of deadline to file competing applications filed pursuant to an NOI: E:\FR\FM\14OCN1.SGM 14OCN1 63918 Federal Register / Vol. 76, No. 199 / Friday, October 14, 2011 / Notices Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application or a notice of intent to file such an application. Section 4.36(b)(2) of the Commission’s regulations, which allows 120 days from the specified intervention deadline date for interested parties to file competing development applications in which timely notice of intents have been submitted, is hereby waived. Due to the expedited nature of the pilot project licensing procedures, the submission of a timely notice of intent will instead allow an interested person to file the competing development application no later than 30 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice. A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant named in this public notice. Dated: October 6, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–26569 Filed 10–13–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. OR12–2–000] tkelley on DSK3SPTVN1PROD with NOTICES ConocoPhillips Company v. SFPP, L.P.; Notice of Complaint Take notice that on October 5, 2011, pursuant to Rule 206 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (Commission), 18 CFR 385.206 (2011), section 343.2 of the Procedural Rules Applicable to Oil Pipeline Proceedings, 18 CFR 343.2, and section 13(1) of the Interstate Commerce Act (ICA), 49 USC App. 13(1), ConocoPhillips Company (Complainant) filed a formal complaint against SFPP, L.P. (Respondent), challenging the lawfulness of the indexed increases in ceiling rates filed by the Respondent on September 20, 2011 in Docket No. IS11–585–000 and alleging that the Respondent will violate the ICA by applying the increased ceiling rates which are unjust and unreasonable for Respondent’s jurisdictional interstate service. The VerDate Mar<15>2010 15:20 Oct 13, 2011 Jkt 226001 Complainant stated that copies of the complaint have been served on the Respondent as listed on the Commission’s list of Corporate Officials. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on October 25, 2011. Dated: October 6, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–26571 Filed 10–13–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. OR12–3–000] Tesoro Refining and Marketing Company v. SFPP, L.P.; Notice of Complaint Take notice that on October 5, 2011, pursuant to Rule 206 of the Rules of Practice and Procedure of the Federal PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 Energy Regulatory Commission (Commission), 18 CFR 385.206; the Procedural Rules Applicable to Oil Pipeline Proceedings, 18 CFR 343.2; and section 1(13) of the Interstate Commerce Act (ICA), 49 U.S.C. App. 13(1), Tesoro Refining and Marketing Company (Complainant) filed a formal complaint against SFPP L.P. (Respondent), challenging the lawfulness of the indexed increases in ceiling rates filed by the Respondent on September 20, 2011 in Docket No. IS11–585–000 and alleging that the Respondent will violate the ICA by applying the increased ceiling rates which are unjust and unreasonable for the Respondent’s jurisdictional interstate service. The Complainant stated that copies of the complaint have been served on the Respondent as listed on the Commission’s list of Corporate Officials. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on October 26, 2011. E:\FR\FM\14OCN1.SGM 14OCN1

Agencies

[Federal Register Volume 76, Number 199 (Friday, October 14, 2011)]
[Notices]
[Pages 63917-63918]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-26569]



[[Page 63917]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12711-005]


Ocean Renewable Power Company, LLC; Notice of Application 
Accepted for Filing, Soliciting Motions To Intervene and Protests, 
Ready for Environmental Analysis, and Soliciting Comments, 
Recommendations, Terms and Conditions, and Fishway Prescriptions, and 
Waiving the Timing Requirement for Filing Competing Development 
Applications

    Take notice that the following hydrokinetic pilot project license 
application has been filed with the Commission and is available for 
public inspection.

    a. Type of Application: Pilot Project License.
    b. Project No.: 12711-005.
    c. Date Filed: September 1, 2011.
    d. Applicant: Ocean Renewable Power Company, LLC.
    e. Name of Project: Cobscook Bay Tidal Energy Project.
    f. Location: The proposed project would be located in Cobscook Bay, 
in Washington County, Maine. The project does not affect federal lands.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-828(c).
    h. Applicant Contact: Christopher R. Sauer, Ocean Renewable Power 
Company, LLC, 120 Exchange Street, Suite 508, Portland, Maine 04101, 
(207) 772-7707.
    i. FERC Contact: Timothy Konnert, telephone (202) 502-6359, and e-
mail timothy.konnert@ferc.gov.
    j. Deadline for Filing Motions to Intervene and Protests, Comments, 
Recommendations, Terms and Conditions, and Fishway Prescriptions: 30 
days from the issuance of this notice; reply comments are due 60 days 
from the issuance date of this notice.
    Motions to intervene, protests, comments, recommendations, terms 
and conditions, and fishway prescriptions may be filed electronically 
via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions 
on the Commission's Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, 
(202) 502-8659. Although the Commission strongly encourages electronic 
filing, documents may also be paper-filed. To paper-file, mail an 
original and seven copies to: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. The Project Description: The primary project facilities would 
include: (1) A single, approximately 98.5-foot-long, cross-flow Kinetic 
System turbine generator unit (TGU) mounted on a bottom support frame, 
with a rated capacity of 60 kilowatts (kW), in Phase 1; (2) four, 
approximately 98.5-foot-long, cross-flow Kinetic System TGUs mounted on 
bottom support frames, with a rated capacity of 60 kW each, in Phase 2; 
(3) a direct current power and data cable approximately 3,800 feet long 
(3,600 feet underwater and 200 feet on shore) extending from the TGUs 
to the onshore station house; (4) an on-shore building 32 feet wide by 
35 feet long, housing the SatCon power inverter and the supervisory 
control and data acquisition (SCADA) system; and (5) appurtenant 
facilities for navigation safety and operation. The project would have 
a total rated capacity of 300 kW, with an estimated annual generation 
between 1,200,000 and 1,300,000 kilowatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, .214. In determining the appropriate action to 
take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the proceeding. Any 
comments, protests, or motions to intervene must be received on or 
before the specified comment date for the particular application.
    All filings must (1) bear in all capital letters the title 
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,'' 
``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or ``FISHWAY 
PRESCRIPTIONS;'' (2) set forth in the heading the name of the applicant 
and the project number of the application to which the filing responds; 
(3) furnish the name, address, and telephone number of the person 
protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, 
recommendations, terms and conditions or prescriptions must set forth 
their evidentiary basis and otherwise comply with the requirements of 
18 CFR 4.34(b) except to the extent that this notice establishes 
deadlines different from those in the regulation. Agencies may obtain 
copies of the application directly from the applicant. A copy of any 
protest or motion to intervene must be served upon each representative 
of the applicant specified in the particular application. A copy of all 
other filings in reference to this application must be accompanied by 
proof of service on all persons listed in the service list prepared by 
the Commission in this proceeding, in accordance with 18 CFR 4.34(b) 
and 385.2010.
    o. Procedural Schedule:
    The application will be processed according to the following Hydro 
Licensing Schedule. Revisions to the schedule may be made as 
appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Filing of recommendations, terms and    November 5, 2011.
 conditions, and fishway prescriptions.
Commission issues Single EA...........  January 4, 2012.
Comments on EA........................  February 3, 2012.
------------------------------------------------------------------------

    p. Waiver of deadline to file competing applications filed pursuant 
to an NOI:

[[Page 63918]]

    Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application or a notice of 
intent to file such an application. Section 4.36(b)(2) of the 
Commission's regulations, which allows 120 days from the specified 
intervention deadline date for interested parties to file competing 
development applications in which timely notice of intents have been 
submitted, is hereby waived. Due to the expedited nature of the pilot 
project licensing procedures, the submission of a timely notice of 
intent will instead allow an interested person to file the competing 
development application no later than 30 days after the specified 
intervention deadline date. Applications for preliminary permits will 
not be accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant named in this public 
notice.

    Dated: October 6, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-26569 Filed 10-13-11; 8:45 am]
BILLING CODE 6717-01-P