DCP Midstream, LP; Notice of Application, 63915-63916 [2011-26567]
Download as PDF
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 76, No. 199 / Friday, October 14, 2011 / Notices
Mr. James Pratt, Executive Director,
Sabine River Authority, State of
Louisiana, 15091 Texas Highway,
Many, Louisiana 71449–5718, 318–
256–4112;
jimpratt@dotd.louisiana.gov.
Mr. Charles R. Sensiba, Van Ness
Feldman, P.C., 1050 Thomas Jefferson
Street, NW., Washington, DC 20007,
202–298–1800.
i. FERC Contact: Alan Mitchnick at
(202) 502–6074 or e-mail at
alan.mitchnick@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. The Project Description: The
existing Toledo Bend Project (figure 2)
consists of: (1) A rolled, earth-fill
embankment, approximately 11,250 feet
long (including saddle dikes) with a top
width of 25 feet and maximum height of
approximately 112 feet; (2) an
approximately 185,000-surface acre, 85mile-long reservoir, with an active
storage capacity of 4,477,000 acre-feet at
full pool (172 feet) and 1,200 miles of
shoreline; (3) a 838-foot-long spillway
located along the north dam abutment
in Louisiana, comprised of a concrete,
gravity-type, gated weir with a concrete
chute and stilling basin and a discharge
channel on the left abutment with
eleven 40-foot by 28-foot tainter gates;
(4) a 80-foot-wide, 55-foot-high
powerhouse located in the right
abutment, containing two vertical
Kaplan turbines with an authorized
installed capacity of 81 megawatts
(MW); and (5) a 220-foot-long, concrete
tailrace segment leading into a 2-milelong, excavated channel that eventually
merges with the Sabine River; (6) a 138kilovolt, primary transmission line
leading from the powerhouse to the
project switchyard, located immediately
adjacent to the tailrace; and (7) a station
transformer, located to the immediate
south of and adjacent to the
powerhouse. The Sabine River
Authorities propose to construct a 1.3–
MW minimum flow turbine-generator at
the project spillway.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
VerDate Mar<15>2010
15:20 Oct 13, 2011
Jkt 226001
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Notice of Acceptance/Notice
of Ready for Environmental Analysis .................
Filing of recommendations,
preliminary terms and conditions, and fishway prescriptions ...........................
Commission issues Draft EIS
Comments on Draft EIS due
Modified Terms and Conditions due ...........................
Commission Issues Final EIS
11/29/2011
1/28/2012
7/26/2012
9/24/2012
11/23/2012
2/21/2013
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: October 7, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–26600 Filed 10–13–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–549–000]
DCP Midstream, LP; Notice of
Application
Take notice that on September 23,
2011, DCP Midstream, LP (DCP), filed
an application pursuant to Section 7(c)
of the Natural Gas Act and Part 157 of
the Commission’s Regulations, for a
limited jurisdiction certificate
authorizing DCP to construct and
operate an eleven-mile, 12-inch
diameter pipeline (the LaSalle Residue
Line) connecting DCP’s new nonjurisdictional natural gas processing
facilities (the LaSalle System) with an
interstate system, located in Weld
County, Colorado. DCP also requests for
waivers of regulatory requirements
regarding the proposed LaSalle Residue
Line. The filing may also be viewed on
the Web at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
63915
document. For assistance, contact FERC
at FERCOnlineSupport@gerc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
DCP is a non-jurisdictional gas
gathering company having facilities in
Texas, Oklahoma, New Mexico,
Louisiana, Colorado, Kansas, Arkansas,
and Wyoming. DCP generally operates
these facilities to deliver raw gas to
processing plants. To address the new
development of Niobrara Shale in the
Denver-Julesburg Basin (DJ Basin), DCP
proposes to construct the LaSalle
Residue Line connecting the LaSalle
System with an interstate system,
Colorado Interstate Gas Company (CIG).
The LaSalle Residue Line has a design
capacity of 230 MMcf/day and will be
used for transportation of natural gas
solely on behalf of DCP without
payment of any additional charge for the
service. DCP does not intend to
transport gas through the LaSalle
Residue Line for shippers other than
DCP. The pipeline will be constructed
entirely inside DCP’s right of way and
costs approximately $12 million.
Any questions regarding this
application should be directed to Katie
Rice, DCP Midstream, LP, 370 17th
Street, Suite 2500, Denver, Colorado
80202. Telephone 303–605–2166, fax
303–605–2226, and e-mail:
kerice@dcpmidstream.com.
Any person wishing to obtain legal
status by becoming a party to the
proceedings for this project should, on
or before the below listed comment
date, file with the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426, a
motion to intervene in accordance with
the requirements of the Commission’s
Rules of Practice and Procedure (18 CFR
385.214 or 385.211) and the Regulations
under the NGA (18 CFR 157.10). A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies of all documents
filed by the applicant and by all other
parties. A party must submit original
and 7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
Motions to intervene, protests and
comments may be filed electronically
via the Internet in lieu of paper; see 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
electronic filings.
Comment Date: October 27, 2011.
E:\FR\FM\14OCN1.SGM
14OCN1
63916
Federal Register / Vol. 76, No. 199 / Friday, October 14, 2011 / Notices
Dated: October 6, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–26567 Filed 10–13–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–551–000]
tkelley on DSK3SPTVN1PROD with NOTICES
Transcontinental Gas Pipe Line
Company, LLC; Notice of Application
Take notice that on September 29,
2011, Transcontinental Gas Pipe Line
Company, LLC (Transco), P.O. Box
1396, Houston, Texas 77251–1396, filed
in Docket No. CP11–551–000 an
application pursuant to Section 7(b) and
7(c) of the Natural Gas Act (NGA) and
Part 157 of the Commission’s
regulations for permission and approval
to abandon Caverns 1, 2, 3, and 4 and
the associated storage deliverability and
capacity at the Eminence Storage Field
(Eminence) in Covington County,
Mississippi, all as more fully set forth in
the application, which is on file with
the Commission and open to public
inspection. This filing may also be
viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Transco states that it has experienced
structural integrity problems with four
of its seven caverns at Eminence. On
December 26, 2010, a large, unexpected
pressure drop occurred in Cavern 3.
Subsequently, Transco experienced
problems with Caverns 1 and 2 and
began to reduce the pressure in those
caverns by withdrawing gas. Cavern 4
has been out of service since 2004 due
to collapsed casing which is not
connected to the December incident.
Transco seeks permission and approval
to abandon Caverns 1, 2, 3, and 4, and
reduce deliverability and capacity from
20.5 Bcf to 15.025 Bcf in Caverns 5, 6,
and 7. Transco also seeks to partially
abandon the total storage capacity and
deliverability quantities Transco
provides to its customers under Rate
Schedules ESS and EESWS. Transco
further seeks to reduce the total capacity
and deliverability quantities available to
Transco for system flexibility.
Contingent upon receiving approval of
its request from the Commission,
Transco and its Rate Schedules ESS and
VerDate Mar<15>2010
15:20 Oct 13, 2011
Jkt 226001
EESWS customers would amend their
applicable service agreements to reflect
their revised Storage Capacity Quantity
and the Storage Demand Capacity.
Transco states that it intends to reflect
the rate impact of the reduction in at the
Eminence Storage Field’s deliverability
and capacity, as well as any costs
incurred thus far, in Transco’s next
section 4 general rate case which will be
filed no later than August 31, 2012.
Transco estimates that it has already
expended $76,000,000 as part of its
emergency response to the events at
Eminence.
Any questions regarding this
application should be directed to Ingrid
Germany, Staff Regulatory Analyst,
Transcontinental Gas Pipe Line
Company, P.O. Box 1396, Houston,
Texas 77251–1396, at (713) 215–4015.
Pursuant to section 157.9 of the
Commission’s regulations, 18 CFR
157.9, within 90 days of this Notice, the
Commission’s staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission’s staff issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to reach a final
decision on a request for federal
authorization within 90 days of the date
of issuance of the Commission staff’s
EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
PO 00000
Frm 00016
Fmt 4703
Sfmt 9990
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 14 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. See,
18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Comment Date: October 27, 2011.
Dated: October 6, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–26573 Filed 10–13–11; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\14OCN1.SGM
14OCN1
Agencies
[Federal Register Volume 76, Number 199 (Friday, October 14, 2011)]
[Notices]
[Pages 63915-63916]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-26567]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP11-549-000]
DCP Midstream, LP; Notice of Application
Take notice that on September 23, 2011, DCP Midstream, LP (DCP),
filed an application pursuant to Section 7(c) of the Natural Gas Act
and Part 157 of the Commission's Regulations, for a limited
jurisdiction certificate authorizing DCP to construct and operate an
eleven-mile, 12-inch diameter pipeline (the LaSalle Residue Line)
connecting DCP's new non-jurisdictional natural gas processing
facilities (the LaSalle System) with an interstate system, located in
Weld County, Colorado. DCP also requests for waivers of regulatory
requirements regarding the proposed LaSalle Residue Line. The filing
may also be viewed on the Web at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC at FERCOnlineSupport@gerc.gov or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
DCP is a non-jurisdictional gas gathering company having facilities
in Texas, Oklahoma, New Mexico, Louisiana, Colorado, Kansas, Arkansas,
and Wyoming. DCP generally operates these facilities to deliver raw gas
to processing plants. To address the new development of Niobrara Shale
in the Denver-Julesburg Basin (DJ Basin), DCP proposes to construct the
LaSalle Residue Line connecting the LaSalle System with an interstate
system, Colorado Interstate Gas Company (CIG). The LaSalle Residue Line
has a design capacity of 230 MMcf/day and will be used for
transportation of natural gas solely on behalf of DCP without payment
of any additional charge for the service. DCP does not intend to
transport gas through the LaSalle Residue Line for shippers other than
DCP. The pipeline will be constructed entirely inside DCP's right of
way and costs approximately $12 million.
Any questions regarding this application should be directed to
Katie Rice, DCP Midstream, LP, 370 17th Street, Suite 2500, Denver,
Colorado 80202. Telephone 303-605-2166, fax 303-605-2226, and e-mail:
kerice@dcpmidstream.com.
Any person wishing to obtain legal status by becoming a party to
the proceedings for this project should, on or before the below listed
comment date, file with the Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426, a motion to intervene in
accordance with the requirements of the Commission's Rules of Practice
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
NGA (18 CFR 157.10). A person obtaining party status will be placed on
the service list maintained by the Secretary of the Commission and will
receive copies of all documents filed by the applicant and by all other
parties. A party must submit original and 7 copies of filings made with
the Commission and must mail a copy to the applicant and to every other
party in the proceeding. Only parties to the proceeding can ask for
court review of Commission orders in the proceeding.
Motions to intervene, protests and comments may be filed
electronically via the Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Comment Date: October 27, 2011.
[[Page 63916]]
Dated: October 6, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-26567 Filed 10-13-11; 8:45 am]
BILLING CODE 6717-01-P