NortHydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 62060 [2011-25838]
Download as PDF
62060
Federal Register / Vol. 76, No. 194 / Thursday, October 6, 2011 / Notices
representative of the applicant specified
in the particular application. If an
intervener files comments or documents
with the Commission relating to the
merits of an issue that may affect the
responsibilities of a particular resource
agency, they must also serve a copy of
the document on that resource agency.
A copy of all other filings in reference
to this application must be accompanied
by proof of service on all persons listed
in the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: September 29, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–25835 Filed 10–5–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No., 14238–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
NortHydro, LLC; Notice of Preliminary
Permit Application Accepted for Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
On July 29, 2011, NortHydro, LLC
(NortHydro or applicant) filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Scooteney Wasteway
Hydroelectric project (project) near
Richland in Franklin County,
Washington. The wasteway was
constructed by the U.S. Bureau of
Reclamation as part of the Columbia
Basin Project, and is situated within and
operated by the South Columbia Basin
Irrigation District. The wasteway
functions as a diversion of surplus water
from the irrigation system to the existing
Scooteney reservoir. The sole purpose of
a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The project would collect all surplus
flows below the Scooteney wasteway
outlet structure. The following new
facilities are proposed: (1) A 63-inch,
2,850-foot-long underground penstock
that would collect water from the
Scooteney wasteway; (2) a powerhouse
containing one turbine/generator unit
with a capacity of 1,110 kilowatts; (3) a
VerDate Mar<15>2010
16:07 Oct 05, 2011
Jkt 226001
4.2-mile-long, 115-kilovolt transmission
line connecting to the existing Ringold
substation; and (4) appurtenant
facilities. The estimated annual
generation of the project would be 4.8
gigawatt-hours.
Applicant Contact: Mr. Darius Ruen,
P.E., NortHydro, LLC, 3201 Huetter
Road, Suite 102, Coeur d’Alene, Idaho
83814; phone (208) 292–0820.
FERC Contact: Patrick Murphy; phone
(202) 502–8755.
Deadline for Filing Comments,
Motions to Intervene, Competing
Applications (Without Notices of
Intent), or Notices of Intent to File
Competing Applications: 60 days from
the issuance of this notice. Competing
applications and notices of intent must
meet the requirements of 18 CFR 4.36.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14238–000) in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
Dated: September 29, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–25838 Filed 10–5–11; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[ Project No., 14237–000]
NortHydro, LLC.; Notice of Preliminary
Permit Application Accepted for Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
On July 29, 2011, NortHydro, LLC
(NortHydro or applicant) filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the 46A Wasteway
Hydroelectric project (project) near
Richland in Franklin County,
Washington. The wasteway was
constructed by the U.S. Bureau of
Reclamation as part of the Columbia
Basin Project, and is situated within and
operated by the South Columbia Basin
Irrigation District. The wasteway
functions as a diversion of surplus water
from the irrigation system. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The project would collect all excess
flows below the 46A wasteway outlet
structure. The following new facilities
are proposed: (1) A diversion structure
that would collect water from the
wasteway; (2) two 63-inch-diameter,
750-foot-long underground penstocks
connecting the diversion structure with
a powerhouse; (3) two turbine/generator
units with a combined capacity of 1,600
kilowatts; (4) a 7.5-mile-long, 115kilovolt transmission line connecting to
the existing Ringold substation; and (5)
appurtenant facilities. The estimated
annual generation of the project would
be 6.75 gigawatt-hours.
Applicant Contact: Mr. Darius Ruen,
P.E., NortHydro, LLC, 3201 Huetter
Road, Suite 102, Coeur d’Alene, Idaho
83814; phone (208) 292–0820.
FERC Contact: Patrick Murphy; phone
(202) 502–8755.
Deadline for Filing Comments,
Motions to Intervene, Competing
Applications (Without Notices of
Intent), or Notices of Intent to File
Competing Applications: 60 days from
the issuance of this notice. Competing
applications and notices of intent must
meet the requirements of 18 CFR 4.36.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
E:\FR\FM\06OCN1.SGM
06OCN1
Agencies
[Federal Register Volume 76, Number 194 (Thursday, October 6, 2011)]
[Notices]
[Page 62060]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-25838]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No., 14238-000]
NortHydro, LLC; Notice of Preliminary Permit Application Accepted
for Filing and Soliciting Comments, Motions To Intervene, and Competing
Applications
On July 29, 2011, NortHydro, LLC (NortHydro or applicant) filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of the
Scooteney Wasteway Hydroelectric project (project) near Richland in
Franklin County, Washington. The wasteway was constructed by the U.S.
Bureau of Reclamation as part of the Columbia Basin Project, and is
situated within and operated by the South Columbia Basin Irrigation
District. The wasteway functions as a diversion of surplus water from
the irrigation system to the existing Scooteney reservoir. The sole
purpose of a preliminary permit, if issued, is to grant the permit
holder priority to file a license application during the permit term. A
preliminary permit does not authorize the permit holder to perform any
land-disturbing activities or otherwise enter upon lands or waters
owned by others without the owners' express permission.
The project would collect all surplus flows below the Scooteney
wasteway outlet structure. The following new facilities are proposed:
(1) A 63-inch, 2,850-foot-long underground penstock that would collect
water from the Scooteney wasteway; (2) a powerhouse containing one
turbine/generator unit with a capacity of 1,110 kilowatts; (3) a 4.2-
mile-long, 115-kilovolt transmission line connecting to the existing
Ringold substation; and (4) appurtenant facilities. The estimated
annual generation of the project would be 4.8 gigawatt-hours.
Applicant Contact: Mr. Darius Ruen, P.E., NortHydro, LLC, 3201
Huetter Road, Suite 102, Coeur d'Alene, Idaho 83814; phone (208) 292-
0820.
FERC Contact: Patrick Murphy; phone (202) 502-8755.
Deadline for Filing Comments, Motions to Intervene, Competing
Applications (Without Notices of Intent), or Notices of Intent to File
Competing Applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14238-000) in the docket number field to
access the document. For assistance, contact FERC Online Support.
Dated: September 29, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-25838 Filed 10-5-11; 8:45 am]