Issuance of a Loan Guarantee to Tonopah Solar Energy, LLC, for the Crescent Dunes Solar Energy Project, 60475-60477 [2011-25049]
Download as PDF
Federal Register / Vol. 76, No. 189 / Thursday, September 29, 2011 / Notices
ACTION:
Notice of Intent.
The U.S. Army Corps of
Engineers, Charleston District intends to
prepare a Draft Environmental Impact
Statement (DEIS) to assess the potential
social, economic and environmental
effects of the proposed construction and
operation of a gold mine in order to
extract and process gold from the Haile
ore body in wetlands and streams
associated with Haile Gold Mine Creek,
by Haile Gold Mine, Inc. (Haile) in the
vicinity of Kershaw, in Lancaster
County, South Carolina. The DEIS will
assess potential effects of a range of
alternatives.
DATES: General Public Scoping Meeting:
One Public Scoping meeting is planned
for Thursday October 27, 2011
beginning at 5 p.m. EDT at the Andrew
Jackson Recreation Center, 6354 N
Matson St, Kershaw, SC 29067.
FOR FURTHER INFORMATION CONTACT: For
further information and/or questions
about the proposed project and DEIS,
please contact Dr. Richard L. Darden,
Project Manager, by telephone: 843–
329–8043 or toll free 1–866–329–8187,
or by mail:
CESAC–RE–P, 69–A Hagood Avenue,
Charleston, SC 29403. For inquiries
from the media, please contact the
Corps, Charleston District Corporate
Communications Officer (CCO), Ms.
Glenn Jeffries by telephone: (843) 329–
8123.
SUPPLEMENTARY INFORMATION: An
application for a Department of the
Army permit was submitted by Haile
pursuant to Section 404 of the Clean
Water Act (33 U.S.C. 1344) on January
12, 2011 and was advertized in a Joint
Public Notice, P/N # SAC 1992–24211–
4_Lancaster_County on January 28,
2011. The public notice is available on
Charleston District’s public Web site at:
https://www.sac.usace.army.mil/
?action=publicnotices.pn2011.
1. Description of Proposed Project.
The project proposed by Haile is to
reactivate the existing Haile Gold Mine
near Kershaw, SC for the development
of gold resources, to expand the area for
open pit mining, and to construct
associated facilities. The Haile Gold
Mine Site encompasses approximately
4,231 acres. Mining will occur in phases
involving eight open mining pits over a
twelve-year period, with pit depths
ranging from 110 to 840 feet deep. The
proposed work includes the mechanized
land clearing, grubbing, temporary
stockpiling, filling, and excavation that
will impact 161.81 acres of
jurisdictional, freshwater wetlands and
38,775 linear feet of streams.
Construction drawings provided by the
tkelley on DSKG8SOYB1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
15:29 Sep 28, 2011
Jkt 223001
applicant are included in the original
joint public notice of January 28, 2011,
and are available on Charleston
District’s public Web site at https://
www.sac.usace.army.mil/
?action=publicnotices.pn2011.
2. Alternatives. A range of alternatives
to the proposed action will be
identified, and those found to be
reasonable alternatives will be fully
evaluated in the DEIS, including: The
no-action alternative, the applicant’s
proposed alternative, alternative mine
locations and mine plans, alternative
mining methods and processes,
alternatives that may result in avoidance
and minimization of impacts, and
mitigation measures not in the proposed
action. However, this list is not
exclusive and additional alternatives
may be considered for inclusion.
3. Scoping and Public Involvement
Process. A scoping meeting will be
conducted to gather information on the
scope of the project and alternatives to
be addressed in the DEIS. Additional
public and agency involvement will be
sought through the implementation of a
public involvement plan and through an
agency coordination team.
4. Significant Issues. Issues associated
with the proposed project to be given
detailed analysis in the DEIS are likely
to include, but are not necessarily
limited to, the potential impacts of the
proposed Haile Gold Mine on surface
and groundwater quality, aquatic habitat
and biota, wetlands and stream habitats,
federal and state listed species of
concern, indirect and cumulative
impacts, drinking water supplies,
mitigation, emergency response and
contingency plans, mine closure and
rehabilitation, conservation, economics,
aesthetics, general environmental
concerns, historic properties, fish and
wildlife values, flood hazards, land use,
recreation, water supply and
conservation, water quality, energy
needs, safety, and the needs and welfare
of the people.
5. Additional Review and
Consultation. Additional review and
consultation which will be incorporated
into the preparation of this DEIS will
include, but will not necessarily be
limited to, Section 401 of Clean Water
Act; Essential Fish Habitat (EFH)
consultation requirements of the
Magnuson-Stevens Fishery
Conservation and Management Act; the
National Environmental Policy Act; the
Endangered Species Act; and the
National Historic Preservation Act.
6. Availability of the Draft
Environmental Impact Statement. The
Draft Environmental Impact Statement
(DEIS) is anticipated to be available late
in 2012. A Public Hearing will be
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
60475
conducted following the release of the
DEIS.
Edward P. Chamberlayne,
Commander, U.S. Army Corps of Engineers,
Charleston District.
[FR Doc. 2011–25140 Filed 9–28–11; 8:45 am]
BILLING CODE 3720–58–P
DEPARTMENT OF ENERGY
Issuance of a Loan Guarantee to
Tonopah Solar Energy, LLC, for the
Crescent Dunes Solar Energy Project
U.S. Department of Energy.
Record of decision.
AGENCY:
ACTION:
The U.S. Department of
Energy (DOE) announces its decision to
issue a Federal loan guarantee under
Title XVII of the Energy Policy Act of
2005 (EPAct 05), as amended by Section
406 of the American Recovery and
Reinvestment Act of 2009 (Recovery
Act), to Tonopah Solar Energy, LLC
(TSE), for construction and start-up of
the Crescent Dunes Solar Energy Project
(the Project). The Project is a proposed
110-megawatt solar power generating
facility based on concentrating solar
power technology, using mirrors and a
central receiver, on approximately 2,250
acres of U.S. Bureau of Land
Management (BLM)-administered lands
in Nye County, Nevada. The
environmental impacts of construction
and start-up of the Project were
analyzed in the Final Environmental
Impact Statement for the Tonopah Solar
Energy, LLC, Crescent Dunes Solar
Energy Project, Nye County, Nevada (75
FR 70917, November 19, 2010) (FEIS),
prepared by BLM with DOE as a
cooperating agency. BLM consulted
DOE during the preparation of this EIS,
DOE provided comments, and BLM
addressed those comments in the FEIS.
DOE subsequently determined that the
Project analyzed in the FEIS was
substantially the same as the Project that
would be covered by the DOE loan
guarantee, and DOE adopted the FEIS
(76 FR 7844; February 11, 2011).
ADDRESSES: Copies of this Record of
Decision (ROD) and the FEIS may be
obtained by contacting Angela
Colamaria, DOE National Environmental
Policy Act (NEPA) Document Manager,
Environmental Compliance Division,
Loan Programs Office (LP–10), U.S.
Department of Energy, 1000
Independence Avenue, SW.,
Washington, DC 20585; telephone (202)
287–5387; or e-mail at
Angela.Colamaria@hq.doe.gov, or by
accessing these documents on the DOE
NEPA Web site at https://
SUMMARY:
E:\FR\FM\29SEN1.SGM
29SEN1
60476
Federal Register / Vol. 76, No. 189 / Thursday, September 29, 2011 / Notices
nepa.energy.gov and at the Loan
Programs Office Web site at https://
www.lgprogram.energy.gov/
NEPA_EIS.html.
FOR FURTHER INFORMATION CONTACT:
Angela Colamaria, as indicated in the
section above. For general
information on the DOE NEPA process,
contact Carol Borgstrom, Director, Office
of NEPA Policy and Compliance (GC–
54), U.S. Department of Energy, 1000
Independence Avenue, SW.,
Washington, DC 20585; telephone (202)
586–4600; leave a message at (800) 472–
2756; or e-mail AskNEPA@hq.doe.gov.
Information about DOE NEPA activities
and access to DOE NEPA documents are
available on the DOE NEPA Web site at
https://nepa.energy.gov.
SUPPLEMENTARY INFORMATION:
tkelley on DSKG8SOYB1PROD with NOTICES
ADDRESSES
Project Background
The Project is a proposed 110megawatt solar power generating facility
based on concentrating solar power
technology. This technology uses
heliostats (reflecting mirrors) to redirect
sunlight onto a receiver erected in the
center of a solar field (called the central
receiver). The proposed solar power
facility is to be located on
approximately 2,250 acres of BLMmanaged lands in south-central Nevada,
roughly 13.5 miles northwest of
Tonopah, in Nye County, and located
within the southern portion of the Big
Smoky Valley, north of US Highway 95/
6 along Pole Line Road (State Highway
89). The proposed facility will consist of
up to approximately 17,500 heliostats/
reflecting mirrors occupying about 1,600
acres of the total project area. Each
heliostat will be approximately 670
square feet, together yielding a total
reflecting surface of about 12,000,000
square feet (275.48 acres). The
arrangement of the heliostats within the
array will be optimized to maximize the
amount of solar energy that could be
collected by the field. The solar
collecting tower/central receiver system
will generate electric power from
sunlight by focusing concentrated solar
radiation onto a tower-mounted
receiver. The solar collecting tower will
be a total of 653 feet high, including a
100-foot tall cylindrical receiver
mounted on the top of the tower. The
central receiver system will consist of a
series of tubes through which a liquid
salt passes and is heated by the
concentrated solar energy. The heated
salt will be routed to a large insulated
tank where it will be stored with
minimal energy loss. To generate
electricity, the heated salt will be
circulated through a series of heat
exchangers to generate high-pressure,
VerDate Mar<15>2010
15:29 Sep 28, 2011
Jkt 223001
superheated steam that will be used to
power a conventional Rankine cycle
steam turbine/generator. Energy
produced from the facility will connect
to the electrical grid through a new 6.9mile 230 kilovolt (kV) transmission line
that will follow a path west to an
existing transmission alignment. A 40acre borrow pit will be needed to extract
aggregate for construction of the access
road and the base of the proposed
facility. A paved, two-lane access road
will extend approximately 1,500 feet
from Pole Line Road to the proposed
facility.
DOE’s offer of a loan guarantee for the
Project is authorized under Title XVII of
the Energy Policy Act of 2005, as
amended by Section 406 of the Recovery
Act. Title XVII as amended authorizes a
program for rapid deployment of
renewable energy and electric power
transmission projects (the Section 1705
Program).
Before applying for a loan guarantee,
TSE filed an application with BLM for
a land use right-of-way pursuant to Title
V of the Federal Land Policy and
Management Act (43 U.S.C. 1761),
which authorizes BLM to issue right-ofway (ROW) lease/grants for renewable
energy projects on BLM land. The
issuance of this ROW lease/grant was
considered a major Federal action as
defined by NEPA, and preparation of an
EIS was initiated by BLM.
NEPA Review
BLM was the lead Federal agency in
the preparation of the EIS, and DOE was
a cooperating agency pursuant to a
Memorandum of Understanding
between BLM and DOE signed in
February 2009. DOE reviewed the
content of the EIS, and provided
comments to BLM to ensure that
information required by DOE NEPA
regulations (10 CFR Part 1021) was
included, and that the analyzed
alternatives encompassed DOE’s
proposed loan guarantee for
construction and start-up of the Project.
On November 24, 2009, BLM
published the ‘‘Notice of Intent to
Prepare an Environmental Impact
Statement for the Proposed Tonopah
Solar Energy, LLC, Crescent Dunes Solar
Energy Project, Nye County, Nevada’’ in
the Federal Register (74 FR 225). Both
the Environmental Protection Agency
(EPA) and BLM published Notices of
Availability of the Draft Environmental
Impact Statement (DEIS) in the Federal
Register on September 3, 2010 (75 FR
54145 and 75 FR 54177, respectively).
The DEIS was available for a 45-day
public comment period, which closed
on October 18, 2010. Two open house
public meetings were held to provide
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
further public involvement: One in Las
Vegas, Nevada, on September 22, 2010,
and the other in Tonopah, Nevada, on
September 23, 2010. During the
comment period for the DEIS, BLM
received 23 comment letters. Comments
received on the DEIS were addressed in
the FEIS, and resulted in the addition of
clarifying text.
BLM completed the Project FEIS in
cooperation with the United States Air
Force, DOE, the Nevada Department of
Wildlife, Nye County, Esmeralda
County, and the Town of Tonopah; EPA
published a Notice of Availability for
the FEIS in the Federal Register on
November 19, 2010 (75 FR 70917). The
FEIS analyzed the environmental
impacts that would be associated with
construction and operation of the
Project, and addressed public
comments.
On December 20, 2010, BLM decided
to allow a solar energy ROW lease/grant
to TSE for the Project to be constructed
on BLM-managed land in Nye County,
Nevada. BLM identified its Selected
Alternative and the Secretary of the
Interior issued Secretarial Approval of
this decision. The environmental
mitigation measures for the Project were
specified in BLM’s ROD (75 FR 81307;
December 27, 2010). Links to these
documents can be found at the BLM
Web site: https://www.blm.gov/nv/st/en/
fo/battle_mountain_field/blm_
information/national_environmental/
crescent_dunes_solar.html.
After independently reviewing the
BLM FEIS, DOE determined that the
issues raised by commenters have been
adequately addressed in the FEIS. On
January 31, 2011, DOE adopted the FEIS
(DOE/EIS–0454) to meet its NEPA
obligations related to its proposal to
provide up to $737 million in a loan
guarantee to support the financing of the
Project. The Notice of Adoption was
published by EPA in the Federal
Register on February 11, 2011 (76 FR
7844).
Alternatives Considered
BLM considered three site locations
that would occupy nearly equal acreage
on lands administered by BLM and
would use the same concentrating solar
power technology. BLM’s Proposed
Action would eliminate 1,374 acres of
Nevada oryctes (a state protected plant)
habitat and 1,466 acres of pale kangaroo
mouse (a state protected species)
habitat. The Proposed Action would be
located to the south of the Crescent
Dunes Special Recreation Management
Area (SRMA), but would not encroach
on the SRMA. It would have potential
conflicts with the Air Force radar testing
E:\FR\FM\29SEN1.SGM
29SEN1
tkelley on DSKG8SOYB1PROD with NOTICES
Federal Register / Vol. 76, No. 189 / Thursday, September 29, 2011 / Notices
mission at the nearby Nevada Test and
Training Range.
BLM’s Alternative 1 would encroach
on 130 acres of a ROW avoidance area
for the Crescent Dunes SRMA, thus
creating the need for an amendment to
the Tonopah Resource Management
Plan. This alternative would eliminate
803 acres of Nevada oryctes habitat,
1,191 acres of pale kangaroo mouse
habitat, and 7 acres of habitat for several
endemic species of scarab beetles (BLM
sensitive species). Alternative 1 would
minimize potential conflicts with
military operations for the Air Force
radar testing mission.
BLM’s Preferred Alternative, which it
selected in its ROD, is Alternative 2.
Alternative 2 is situated on low or norelief public land. This alternative
encompasses 2,250.27 acres of public
lands. However, the proposed project
facility would only utilize
approximately 2,094.27 acres, of which
1,620 acres would be disturbed.
Alternative 2 is located to the west of
the Crescent Dunes SRMA and
eliminates or reduces environmental
impacts overall, such as visual impacts
to recreational users of the SRMA. The
site would disturb 434 acres of habitat
for the Nevada oryctes and the pale
kangaroo mouse, and there would be no
impacts to habitat for the endemic
species of scarab beetles. The site also
minimizes potential conflicts with
military operations for the Air Force
radar testing mission. Finally, the site is
located closer to an access road and an
existing transmission line, and would
therefore reduce the amount of
necessary surface disturbance.
BLM also examined the impacts
resulting from a No Action Alternative,
under which the Project would not be
constructed. All of these alternatives
were described in detail and fully
analyzed in the FEIS.
DOE’s decision is whether or not to
issue a loan guarantee to Tonopah Solar
Energy, LLC, for $737 million to support
construction and startup of the Project
as selected in the BLM ROD.
Accordingly, the DOE alternatives are to
issue the loan guarantee to TSE for
construction and start-up of the Project
under Alternative 2, which BLM
selected in its ROD, and the No Action
Alternative. Under the No Action
Alternative, DOE would not issue a loan
guarantee for the Project and it is not
likely that TSE would implement the
Project as currently planned.
Environmentally Preferred Alternative
BLM identified Alterative 2 as the
Environmentally Preferred Alternative.
This Alternative has the least impacts to
special status plants and wildlife
VerDate Mar<15>2010
15:29 Sep 28, 2011
Jkt 223001
species, stays within the existing
transmission corridor and reduces the
length of the transmission line needed.
It does not encroach upon the Crescent
Dunes SRMA.
DOE has decided that its alternative to
issue a loan guarantee for construction
and start-up of the Project, as selected
in the BLM ROD, is environmentally
preferable. DOE has determined that the
Project offers substantial environmental
benefits due to reductions in greenhouse
gas emissions, as described in the FEIS.
DOE has also determined that all
practicable means to avoid or minimize
environmental harm, as described in the
BLM ROD, have been adopted as
mitigation measures by BLM.
Consultation
As the lead Federal agency for the
Crescent Dunes Solar Energy Project,
BLM complied with section 106 of the
National Historic Preservation Act,
section 7 of the Endangered Species Act,
and the Bald and Golden Eagle
Protection Act, and entered into
government-to-government
consultations with Native American
tribes. The mitigation measures
included in the BLM decision resulted
from these consultations and are
addressed in the FEIS and BLM ROD.
Specifically, the Nevada State Historic
Preservation Office (SHPO) reviewed
this project under section 106 of the
National Historic Preservation Act, and
concurred with BLM’s determinations of
site eligibility to the National Register of
Historic Places (NRHP) of nine eligible
properties that will be affected by this
project. A Historic Properties Treatment
Plan describing mitigation measures
that will be employed to resolve any
adverse effect to the nine NRHP eligible
sites has been prepared. A
Memorandum of Agreement between
the BLM and Nevada SHPO has been
implemented to ensure the Historic
Properties Treatment Plan will mitigate
any adverse effect to these NRHPeligible sites. Furthermore, an
Endangered Species Act section 7
consultation was completed by BLM
during the NEPA process, and a Wildlife
Mitigation and Monitoring Plan was
included in the FEIS. Finally, BLM
conducted and completed Tribal
consultation with Federally-Recognized
Indian Tribes, and consulted with the
Nevada SHPO.
Decision
DOE has decided to issue a loan
guarantee for construction and start-up
of the Crescent Dunes Solar Energy
Project, as selected in the BLM ROD.
Approval of the loan guarantee for the
Project responds to DOE’s purpose and
PO 00000
Frm 00031
Fmt 4703
Sfmt 9990
60477
need pursuant to Title XVII of EPAct 05,
as amended by section 406 of the
Recovery Act, which authorizes a new
program for rapid deployment of
renewable energy projects. The primary
purposes of the Recovery Act are job
preservation and creation, infrastructure
investment, energy efficiency and
science, assistance to the unemployed,
and state and local fiscal stabilization.
The Section 1705 Program is designed
to address the current economic
conditions of the Nation, in part,
through renewable energy, transmission,
and leading-edge biofuels projects.
Eligible projects must commence
construction no later than September
30, 2011.
In reaching this decision, DOE
reviewed the Project NEPA
documentation and considered the
potential impacts of the selected
alternative, including implementation of
the stipulated mitigation measures. DOE
prepared this ROD in accordance with
the Council on Environmental Quality
regulations for implementing NEPA and
DOE’s NEPA Implementing Procedures.
Mitigation
The Project that will be supported by
issuance of the DOE loan guarantee
includes all mitigation conditions
applied by BLM in its ROD. BLM is the
Federal lead agency for the Project
under NEPA, and is responsible for
ensuring compliance with all adopted
mitigation measures for the Project set
out in its ROD. A description of the
mitigation measures is provided in the
BLM ROD and in BLM’s ROW lease/
grant (Appendix A to the BLM ROD).
BLM has incorporated these mitigation
measures into the ROW lease/grant as
terms and conditions (Exhibit B to the
ROW lease/grant).
The DOE loan guarantee agreement
requires the applicant to comply with
all applicable laws and the terms of the
ROW lease/grant, including its
mitigation measures. An applicant’s
failure to comply with applicable laws
and the ROW lease/grant would
constitute a default. Upon the
continuance of a default, DOE would
have the right under the loan guarantee
agreement between it and the applicant
to exercise usual and customary
remedies. To ensure that the applicant
so performs, the DOE Loan Programs
Office proactively monitors all operative
loan guarantee transactions.
Issued in Washington, DC, on September
23, 2011.
Jonathan M. Silver,
Executive Director, Loan Programs Office.
[FR Doc. 2011–25049 Filed 9–28–11; 8:45 am]
BILLING CODE 6450–10–P
E:\FR\FM\29SEN1.SGM
29SEN1
Agencies
[Federal Register Volume 76, Number 189 (Thursday, September 29, 2011)]
[Notices]
[Pages 60475-60477]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-25049]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Issuance of a Loan Guarantee to Tonopah Solar Energy, LLC, for
the Crescent Dunes Solar Energy Project
AGENCY: U.S. Department of Energy.
ACTION: Record of decision.
-----------------------------------------------------------------------
SUMMARY: The U.S. Department of Energy (DOE) announces its decision to
issue a Federal loan guarantee under Title XVII of the Energy Policy
Act of 2005 (EPAct 05), as amended by Section 406 of the American
Recovery and Reinvestment Act of 2009 (Recovery Act), to Tonopah Solar
Energy, LLC (TSE), for construction and start-up of the Crescent Dunes
Solar Energy Project (the Project). The Project is a proposed 110-
megawatt solar power generating facility based on concentrating solar
power technology, using mirrors and a central receiver, on
approximately 2,250 acres of U.S. Bureau of Land Management (BLM)-
administered lands in Nye County, Nevada. The environmental impacts of
construction and start-up of the Project were analyzed in the Final
Environmental Impact Statement for the Tonopah Solar Energy, LLC,
Crescent Dunes Solar Energy Project, Nye County, Nevada (75 FR 70917,
November 19, 2010) (FEIS), prepared by BLM with DOE as a cooperating
agency. BLM consulted DOE during the preparation of this EIS, DOE
provided comments, and BLM addressed those comments in the FEIS. DOE
subsequently determined that the Project analyzed in the FEIS was
substantially the same as the Project that would be covered by the DOE
loan guarantee, and DOE adopted the FEIS (76 FR 7844; February 11,
2011).
ADDRESSES: Copies of this Record of Decision (ROD) and the FEIS may be
obtained by contacting Angela Colamaria, DOE National Environmental
Policy Act (NEPA) Document Manager, Environmental Compliance Division,
Loan Programs Office (LP-10), U.S. Department of Energy, 1000
Independence Avenue, SW., Washington, DC 20585; telephone (202) 287-
5387; or e-mail at Angela.Colamaria@hq.doe.gov, or by accessing these
documents on the DOE NEPA Web site at https://
[[Page 60476]]
nepa.energy.gov and at the Loan Programs Office Web site at https://www.lgprogram.energy.gov/NEPA_EIS.html.
FOR FURTHER INFORMATION CONTACT: Angela Colamaria, as indicated in the
ADDRESSES section above. For general information on the DOE NEPA
process, contact Carol Borgstrom, Director, Office of NEPA Policy and
Compliance (GC-54), U.S. Department of Energy, 1000 Independence
Avenue, SW., Washington, DC 20585; telephone (202) 586-4600; leave a
message at (800) 472-2756; or e-mail AskNEPA@hq.doe.gov. Information
about DOE NEPA activities and access to DOE NEPA documents are
available on the DOE NEPA Web site at https://nepa.energy.gov.
SUPPLEMENTARY INFORMATION:
Project Background
The Project is a proposed 110-megawatt solar power generating
facility based on concentrating solar power technology. This technology
uses heliostats (reflecting mirrors) to redirect sunlight onto a
receiver erected in the center of a solar field (called the central
receiver). The proposed solar power facility is to be located on
approximately 2,250 acres of BLM-managed lands in south-central Nevada,
roughly 13.5 miles northwest of Tonopah, in Nye County, and located
within the southern portion of the Big Smoky Valley, north of US
Highway 95/6 along Pole Line Road (State Highway 89). The proposed
facility will consist of up to approximately 17,500 heliostats/
reflecting mirrors occupying about 1,600 acres of the total project
area. Each heliostat will be approximately 670 square feet, together
yielding a total reflecting surface of about 12,000,000 square feet
(275.48 acres). The arrangement of the heliostats within the array will
be optimized to maximize the amount of solar energy that could be
collected by the field. The solar collecting tower/central receiver
system will generate electric power from sunlight by focusing
concentrated solar radiation onto a tower-mounted receiver. The solar
collecting tower will be a total of 653 feet high, including a 100-foot
tall cylindrical receiver mounted on the top of the tower. The central
receiver system will consist of a series of tubes through which a
liquid salt passes and is heated by the concentrated solar energy. The
heated salt will be routed to a large insulated tank where it will be
stored with minimal energy loss. To generate electricity, the heated
salt will be circulated through a series of heat exchangers to generate
high-pressure, superheated steam that will be used to power a
conventional Rankine cycle steam turbine/generator. Energy produced
from the facility will connect to the electrical grid through a new
6.9-mile 230 kilovolt (kV) transmission line that will follow a path
west to an existing transmission alignment. A 40-acre borrow pit will
be needed to extract aggregate for construction of the access road and
the base of the proposed facility. A paved, two-lane access road will
extend approximately 1,500 feet from Pole Line Road to the proposed
facility.
DOE's offer of a loan guarantee for the Project is authorized under
Title XVII of the Energy Policy Act of 2005, as amended by Section 406
of the Recovery Act. Title XVII as amended authorizes a program for
rapid deployment of renewable energy and electric power transmission
projects (the Section 1705 Program).
Before applying for a loan guarantee, TSE filed an application with
BLM for a land use right-of-way pursuant to Title V of the Federal Land
Policy and Management Act (43 U.S.C. 1761), which authorizes BLM to
issue right-of-way (ROW) lease/grants for renewable energy projects on
BLM land. The issuance of this ROW lease/grant was considered a major
Federal action as defined by NEPA, and preparation of an EIS was
initiated by BLM.
NEPA Review
BLM was the lead Federal agency in the preparation of the EIS, and
DOE was a cooperating agency pursuant to a Memorandum of Understanding
between BLM and DOE signed in February 2009. DOE reviewed the content
of the EIS, and provided comments to BLM to ensure that information
required by DOE NEPA regulations (10 CFR Part 1021) was included, and
that the analyzed alternatives encompassed DOE's proposed loan
guarantee for construction and start-up of the Project.
On November 24, 2009, BLM published the ``Notice of Intent to
Prepare an Environmental Impact Statement for the Proposed Tonopah
Solar Energy, LLC, Crescent Dunes Solar Energy Project, Nye County,
Nevada'' in the Federal Register (74 FR 225). Both the Environmental
Protection Agency (EPA) and BLM published Notices of Availability of
the Draft Environmental Impact Statement (DEIS) in the Federal Register
on September 3, 2010 (75 FR 54145 and 75 FR 54177, respectively). The
DEIS was available for a 45-day public comment period, which closed on
October 18, 2010. Two open house public meetings were held to provide
further public involvement: One in Las Vegas, Nevada, on September 22,
2010, and the other in Tonopah, Nevada, on September 23, 2010. During
the comment period for the DEIS, BLM received 23 comment letters.
Comments received on the DEIS were addressed in the FEIS, and resulted
in the addition of clarifying text.
BLM completed the Project FEIS in cooperation with the United
States Air Force, DOE, the Nevada Department of Wildlife, Nye County,
Esmeralda County, and the Town of Tonopah; EPA published a Notice of
Availability for the FEIS in the Federal Register on November 19, 2010
(75 FR 70917). The FEIS analyzed the environmental impacts that would
be associated with construction and operation of the Project, and
addressed public comments.
On December 20, 2010, BLM decided to allow a solar energy ROW
lease/grant to TSE for the Project to be constructed on BLM-managed
land in Nye County, Nevada. BLM identified its Selected Alternative and
the Secretary of the Interior issued Secretarial Approval of this
decision. The environmental mitigation measures for the Project were
specified in BLM's ROD (75 FR 81307; December 27, 2010). Links to these
documents can be found at the BLM Web site: https://www.blm.gov/nv/st/en/fo/battle_mountain_field/blm_information/national_environmental/crescent_dunes_solar.html.
After independently reviewing the BLM FEIS, DOE determined that the
issues raised by commenters have been adequately addressed in the FEIS.
On January 31, 2011, DOE adopted the FEIS (DOE/EIS-0454) to meet its
NEPA obligations related to its proposal to provide up to $737 million
in a loan guarantee to support the financing of the Project. The Notice
of Adoption was published by EPA in the Federal Register on February
11, 2011 (76 FR 7844).
Alternatives Considered
BLM considered three site locations that would occupy nearly equal
acreage on lands administered by BLM and would use the same
concentrating solar power technology. BLM's Proposed Action would
eliminate 1,374 acres of Nevada oryctes (a state protected plant)
habitat and 1,466 acres of pale kangaroo mouse (a state protected
species) habitat. The Proposed Action would be located to the south of
the Crescent Dunes Special Recreation Management Area (SRMA), but would
not encroach on the SRMA. It would have potential conflicts with the
Air Force radar testing
[[Page 60477]]
mission at the nearby Nevada Test and Training Range.
BLM's Alternative 1 would encroach on 130 acres of a ROW avoidance
area for the Crescent Dunes SRMA, thus creating the need for an
amendment to the Tonopah Resource Management Plan. This alternative
would eliminate 803 acres of Nevada oryctes habitat, 1,191 acres of
pale kangaroo mouse habitat, and 7 acres of habitat for several endemic
species of scarab beetles (BLM sensitive species). Alternative 1 would
minimize potential conflicts with military operations for the Air Force
radar testing mission.
BLM's Preferred Alternative, which it selected in its ROD, is
Alternative 2. Alternative 2 is situated on low or no-relief public
land. This alternative encompasses 2,250.27 acres of public lands.
However, the proposed project facility would only utilize approximately
2,094.27 acres, of which 1,620 acres would be disturbed. Alternative 2
is located to the west of the Crescent Dunes SRMA and eliminates or
reduces environmental impacts overall, such as visual impacts to
recreational users of the SRMA. The site would disturb 434 acres of
habitat for the Nevada oryctes and the pale kangaroo mouse, and there
would be no impacts to habitat for the endemic species of scarab
beetles. The site also minimizes potential conflicts with military
operations for the Air Force radar testing mission. Finally, the site
is located closer to an access road and an existing transmission line,
and would therefore reduce the amount of necessary surface disturbance.
BLM also examined the impacts resulting from a No Action
Alternative, under which the Project would not be constructed. All of
these alternatives were described in detail and fully analyzed in the
FEIS.
DOE's decision is whether or not to issue a loan guarantee to
Tonopah Solar Energy, LLC, for $737 million to support construction and
startup of the Project as selected in the BLM ROD. Accordingly, the DOE
alternatives are to issue the loan guarantee to TSE for construction
and start-up of the Project under Alternative 2, which BLM selected in
its ROD, and the No Action Alternative. Under the No Action
Alternative, DOE would not issue a loan guarantee for the Project and
it is not likely that TSE would implement the Project as currently
planned.
Environmentally Preferred Alternative
BLM identified Alterative 2 as the Environmentally Preferred
Alternative. This Alternative has the least impacts to special status
plants and wildlife species, stays within the existing transmission
corridor and reduces the length of the transmission line needed. It
does not encroach upon the Crescent Dunes SRMA.
DOE has decided that its alternative to issue a loan guarantee for
construction and start-up of the Project, as selected in the BLM ROD,
is environmentally preferable. DOE has determined that the Project
offers substantial environmental benefits due to reductions in
greenhouse gas emissions, as described in the FEIS. DOE has also
determined that all practicable means to avoid or minimize
environmental harm, as described in the BLM ROD, have been adopted as
mitigation measures by BLM.
Consultation
As the lead Federal agency for the Crescent Dunes Solar Energy
Project, BLM complied with section 106 of the National Historic
Preservation Act, section 7 of the Endangered Species Act, and the Bald
and Golden Eagle Protection Act, and entered into government-to-
government consultations with Native American tribes. The mitigation
measures included in the BLM decision resulted from these consultations
and are addressed in the FEIS and BLM ROD. Specifically, the Nevada
State Historic Preservation Office (SHPO) reviewed this project under
section 106 of the National Historic Preservation Act, and concurred
with BLM's determinations of site eligibility to the National Register
of Historic Places (NRHP) of nine eligible properties that will be
affected by this project. A Historic Properties Treatment Plan
describing mitigation measures that will be employed to resolve any
adverse effect to the nine NRHP eligible sites has been prepared. A
Memorandum of Agreement between the BLM and Nevada SHPO has been
implemented to ensure the Historic Properties Treatment Plan will
mitigate any adverse effect to these NRHP-eligible sites. Furthermore,
an Endangered Species Act section 7 consultation was completed by BLM
during the NEPA process, and a Wildlife Mitigation and Monitoring Plan
was included in the FEIS. Finally, BLM conducted and completed Tribal
consultation with Federally-Recognized Indian Tribes, and consulted
with the Nevada SHPO.
Decision
DOE has decided to issue a loan guarantee for construction and
start-up of the Crescent Dunes Solar Energy Project, as selected in the
BLM ROD.
Approval of the loan guarantee for the Project responds to DOE's
purpose and need pursuant to Title XVII of EPAct 05, as amended by
section 406 of the Recovery Act, which authorizes a new program for
rapid deployment of renewable energy projects. The primary purposes of
the Recovery Act are job preservation and creation, infrastructure
investment, energy efficiency and science, assistance to the
unemployed, and state and local fiscal stabilization. The Section 1705
Program is designed to address the current economic conditions of the
Nation, in part, through renewable energy, transmission, and leading-
edge biofuels projects. Eligible projects must commence construction no
later than September 30, 2011.
In reaching this decision, DOE reviewed the Project NEPA
documentation and considered the potential impacts of the selected
alternative, including implementation of the stipulated mitigation
measures. DOE prepared this ROD in accordance with the Council on
Environmental Quality regulations for implementing NEPA and DOE's NEPA
Implementing Procedures.
Mitigation
The Project that will be supported by issuance of the DOE loan
guarantee includes all mitigation conditions applied by BLM in its ROD.
BLM is the Federal lead agency for the Project under NEPA, and is
responsible for ensuring compliance with all adopted mitigation
measures for the Project set out in its ROD. A description of the
mitigation measures is provided in the BLM ROD and in BLM's ROW lease/
grant (Appendix A to the BLM ROD). BLM has incorporated these
mitigation measures into the ROW lease/grant as terms and conditions
(Exhibit B to the ROW lease/grant).
The DOE loan guarantee agreement requires the applicant to comply
with all applicable laws and the terms of the ROW lease/grant,
including its mitigation measures. An applicant's failure to comply
with applicable laws and the ROW lease/grant would constitute a
default. Upon the continuance of a default, DOE would have the right
under the loan guarantee agreement between it and the applicant to
exercise usual and customary remedies. To ensure that the applicant so
performs, the DOE Loan Programs Office proactively monitors all
operative loan guarantee transactions.
Issued in Washington, DC, on September 23, 2011.
Jonathan M. Silver,
Executive Director, Loan Programs Office.
[FR Doc. 2011-25049 Filed 9-28-11; 8:45 am]
BILLING CODE 6450-10-P