Freeport LNG Development, LP; Freeport LNG Expansion, LP; FLNG Liquefaction LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Liquefaction Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting, 53440-53442 [2011-21799]
Download as PDF
53440
Federal Register / Vol. 76, No. 166 / Friday, August 26, 2011 / Notices
DEPARTMENT OF ENERGY
FERC Contact: Michael Spencer, (202)
502–6093.
Federal Energy Regulatory
Commission
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting textonly comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–12851–002, or P–14082–000) in the
docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: August 19, 2011.
Kimberly D. Bose,
Secretary.
the Liquefaction Project (Project)
involving construction and operation of
facilities proposed by Freeport LNG
Development, LP, Freeport LNG
Expansion, LP, and FLNG Liquefaction
LLC (collectively referred to as Freeport)
in Brazoria County, Texas. This EA will
be used by the Commission in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
scoping period will close on September
19, 2011.
Comments may be submitted in
written form or verbally. Further details
on how to submit written comments are
provided in the Public Participation
section of this notice. In lieu of or in
addition to sending written comments,
the Commission invites you to attend
the public scoping meeting scheduled as
follows:
FERC Public Scoping Meeting, Freeport
Liquefaction Project, 7 p.m.—
Thursday, September 8, 2011.
Lake Jackson Civic Center, 333 Highway
332 E, Lake Jackson, TX 77566, (979)
415–2600.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives are
asked to notify their constituents of this
planned project and encourage them to
comment on their areas of concern.
Summary of the Planned Project
[Project No. 12851–002; Project No. 14082–
000]
Free Flow Power Corporation;
Northland Power Mississippi River
LLC; Notice of Competing Preliminary
Permit Applications Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Competing
Applications
emcdonald on DSK2BSOYB1PROD with NOTICES
Free Flow Power Corporation (Free
Flow) and Northland Power Mississippi
River LLC (Northland) filed preliminary
permit applications, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of developing
hydropower projects hydropower on the
Mississippi River, near the town of New
Orleans, in Jefferson and Orleans
Parishes, Louisiana. Both applications
were filed electronically and given the
filing date of February 1, 2011, at 8:30
AM. The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed projects are described
as follows:
Free Flow’s hydrokinetic Project, Project
No. 12851–002 would consist of: (1) Up to
2,250 SmartTurbine generating units
installed in arrays on the bottom of the river;
(2) the total capacity of the installation would
be up to 90,000 kilowatts; (3) flexible cables
would convey each arrays power to a
metering station; and (4) a transmission line
would interconnect with the power grid. The
proposed project would have an average
annual generation of 197,100,000 kilowatthours (kWh), which would be sold to a local
utility.
Northland’s hydrokinetic Project, Project
No. 14082–000 would consist of: (1) Up to
150 TREK generating units installed in a
matrix on the bottom of the river; (2) the total
capacity of the installation would be up to
38,000 kilowatts; (3) shielded underwater
cables would convey each matrix power to a
substation; and (4) a transmission line would
interconnect with the power grid. The
proposed project would have an average
annual generation of 329,000,000 gigawatthours (GWh), which would be sold to a local
utility.
Applicants Contact: For Free Flow: Ramya
Swaminathan, Free Flow Power Corporation,
239 Causeway Street, Boston, MA 02114;
phone (978) 283–2822. For Northland: Tim
Richardson, 30 St. Clair Avenue West 17th
Floor, Toronto, Ontario, Canada; phone (416)
820–9521.
VerDate Mar<15>2010
19:37 Aug 25, 2011
Jkt 223001
[FR Doc. 2011–21813 Filed 8–25–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF11–2–000]
Freeport LNG Development, LP;
Freeport LNG Expansion, LP; FLNG
Liquefaction LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Planned Liquefaction Project,
Request for Comments on
Environmental Issues, and Notice of
Public Scoping Meeting
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
Freeport plans to add natural gas
liquefaction and exportation capabilities
to its existing liquefied natural gas
(LNG) import terminal on Quintana
Island in Brazoria County, Texas. The
Project would consist of the
construction and installation of facilities
to be used for liquefaction and export of
domestic natural gas. In addition, A
nonjurisdictional pretreatment facility
would be constructed and operated at or
near the Stratton Ridge underground
storage and meter station sites.
The planned facilities would consist
of the following components:
• Three natural gas liquefaction
refrigerant units;
• Expansion of existing Quintana
Island Terminal Facility components;
and
• The nonjurisdictional natural gas
pre-treatment systems, additional
compression, and minor modifications
in the Stratton Ridge Meter Station area.
E:\FR\FM\26AUN1.SGM
26AUN1
Federal Register / Vol. 76, No. 166 / Friday, August 26, 2011 / Notices
In addition, a second ship berthing
area, third LNG storage tank, and
additional LNG vaporization and
natural gas send-out facilities that were
previously authorized under FERC
Docket CP05–361–000 but never
constructed would be repurposed to
meet the needs of the Project.
Freeport indicates that the Project
would produce about 12.0 million
metric tons per year of LNG. This would
allow Freeport to convert domestically
produced natural gas to LNG for storage
and export. Freeport LNG plans to
commence construction in December
2012 and expects to be ready to
commence LNG exports in late- 2015.
The general location of the project
facilities is shown in Appendix 1.1
Land Requirements for Construction
Construction of the planned facilities
would disturb about 116.9 acres of land
on Quintana Island. Additional land
would be required for the pre-treatment
facilities near Stratton Ridge Meter
Station. Following construction, about
76 acres would be maintained for
permanent operation of the project’s
facilities on Quintana Island; the
remaining acreage may be restored and
allowed to revert to former uses.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. All comments
received will be considered during the
preparation of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings:
• Geology and soils;
emcdonald on DSK2BSOYB1PROD with NOTICES
1 The
appendices referenced in this notice are not
being printed in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at https://
www.ferc.gov using the link called ‘‘eLibrary’’ or
from the Commission’s Public Reference Room, 888
First Street NE., Washington, DC 20426, or call
(202) 502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Mar<15>2010
19:37 Aug 25, 2011
Jkt 223001
• Water resources, and fisheries;
• Vegetation and wildlife;
• Cultural resources;
• Socioeconomics;
• Land use;
• Air quality and noise; and
• Reliability and public safety.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
an application is filed with the FERC.
As part of our pre-filing review, we have
begun to contact some federal and state
agencies to discuss their involvement in
the scoping process and the preparation
of the EA.
Our independent analysis of the
issues will be presented in the EA. The
EA will be placed in the public record
and, depending on the comments
received during the scoping process,
may be published and distributed to the
public. A comment period will be
allotted if the EA is published for
review. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section beginning on page 5.
With this notice, we are asking
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to formally
cooperate with us in the preparation of
the EA. These agencies may choose to
participate once they have evaluated the
proposal relative to their
responsibilities. Agencies that would
like to request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
Texas State Historic Preservation Office,
and to solicit their views and those of
other government agencies, interested
Indian tribes, and the public on the
project’s potential effects on historic
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
53441
properties.3 We will define the projectspecific Area of Potential Effects (APE)
in consultation with the SHPO as the
project is further developed. On natural
gas facility projects, the APE at a
minimum encompasses all areas subject
to ground disturbance. Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
planned facilities and the
environmental information provided by
Freeport. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Air Quality
• Noise and vibration impacts
• Socioeconomic impacts
• Geology
• Wetlands and waterbodies
• Threatened and endangered species
• Public safety
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that they will be received in
Washington, DC on or before September
19, 2011.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. In all
instances, please reference the project
docket number PF11–2–000 with your
submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. An eComment
is an easy method for interested persons
3 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
E:\FR\FM\26AUN1.SGM
26AUN1
53442
Federal Register / Vol. 76, No. 166 / Friday, August 26, 2011 / Notices
to submit brief, text-only comments on
a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making. A comment on a particular
project is considered a ‘‘Comment on a
Filing’’; or
(3) You may mail a paper copy of your
comments to the Commission at the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
emcdonald on DSK2BSOYB1PROD with NOTICES
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Indian tribes; other interested
parties; and local libraries and
newspapers. This list also includes all
affected landowners (as defined in the
Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(Appendix 2).
Becoming an Intervenor
Once Freeport files its application
with the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
VerDate Mar<15>2010
19:37 Aug 25, 2011
Jkt 223001
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site. Please note that
the Commission will not accept requests
for intervenor status at this time. You
must wait until a formal application for
the project is filed with the
Commission.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (https://www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number, excluding the last three
digits in the Docket Number field (i.e.,
PF11–2–000). Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: August 18, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–21799 Filed 8–25–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER11–4326–000]
Viridian Energy MD LLC; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced proceeding of Viridian
Energy MD LLC’s application for
PO 00000
Frm 00046
Fmt 4703
Sfmt 9990
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is September 7,
2011.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
dockets(s). For assistance with any
FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: August 18, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–21792 Filed 8–25–11; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\26AUN1.SGM
26AUN1
Agencies
[Federal Register Volume 76, Number 166 (Friday, August 26, 2011)]
[Notices]
[Pages 53440-53442]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-21799]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF11-2-000]
Freeport LNG Development, LP; Freeport LNG Expansion, LP; FLNG
Liquefaction LLC; Notice of Intent To Prepare an Environmental
Assessment for the Planned Liquefaction Project, Request for Comments
on Environmental Issues, and Notice of Public Scoping Meeting
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Liquefaction Project (Project)
involving construction and operation of facilities proposed by Freeport
LNG Development, LP, Freeport LNG Expansion, LP, and FLNG Liquefaction
LLC (collectively referred to as Freeport) in Brazoria County, Texas.
This EA will be used by the Commission in its decision-making process
to determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues need to be evaluated in the EA. Please note that
the scoping period will close on September 19, 2011.
Comments may be submitted in written form or verbally. Further
details on how to submit written comments are provided in the Public
Participation section of this notice. In lieu of or in addition to
sending written comments, the Commission invites you to attend the
public scoping meeting scheduled as follows:
FERC Public Scoping Meeting, Freeport Liquefaction Project, 7 p.m.--
Thursday, September 8, 2011.
Lake Jackson Civic Center, 333 Highway 332 E, Lake Jackson, TX 77566,
(979) 415-2600.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives are asked to notify their constituents of this planned
project and encourage them to comment on their areas of concern.
Summary of the Planned Project
Freeport plans to add natural gas liquefaction and exportation
capabilities to its existing liquefied natural gas (LNG) import
terminal on Quintana Island in Brazoria County, Texas. The Project
would consist of the construction and installation of facilities to be
used for liquefaction and export of domestic natural gas. In addition,
A nonjurisdictional pretreatment facility would be constructed and
operated at or near the Stratton Ridge underground storage and meter
station sites.
The planned facilities would consist of the following components:
Three natural gas liquefaction refrigerant units;
Expansion of existing Quintana Island Terminal Facility
components; and
The nonjurisdictional natural gas pre-treatment systems,
additional compression, and minor modifications in the Stratton Ridge
Meter Station area.
[[Page 53441]]
In addition, a second ship berthing area, third LNG storage tank,
and additional LNG vaporization and natural gas send-out facilities
that were previously authorized under FERC Docket CP05-361-000 but
never constructed would be repurposed to meet the needs of the Project.
Freeport indicates that the Project would produce about 12.0
million metric tons per year of LNG. This would allow Freeport to
convert domestically produced natural gas to LNG for storage and
export. Freeport LNG plans to commence construction in December 2012
and expects to be ready to commence LNG exports in late- 2015.
The general location of the project facilities is shown in Appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of appendices were sent to
all those receiving this notice in the mail and are available at
https://www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb about 116.9
acres of land on Quintana Island. Additional land would be required for
the pre-treatment facilities near Stratton Ridge Meter Station.
Following construction, about 76 acres would be maintained for
permanent operation of the project's facilities on Quintana Island; the
remaining acreage may be restored and allowed to revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. All comments
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings:
Geology and soils;
Water resources, and fisheries;
Vegetation and wildlife;
Cultural resources;
Socioeconomics;
Land use;
Air quality and noise; and
Reliability and public safety.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before an
application is filed with the FERC. As part of our pre-filing review,
we have begun to contact some federal and state agencies to discuss
their involvement in the scoping process and the preparation of the EA.
Our independent analysis of the issues will be presented in the EA.
The EA will be placed in the public record and, depending on the
comments received during the scoping process, may be published and
distributed to the public. A comment period will be allotted if the EA
is published for review. We will consider all comments on the EA before
we make our recommendations to the Commission. To ensure your comments
are considered, please carefully follow the instructions in the Public
Participation section beginning on page 5.
With this notice, we are asking agencies with jurisdiction and/or
special expertise with respect to environmental issues to formally
cooperate with us in the preparation of the EA. These agencies may
choose to participate once they have evaluated the proposal relative to
their responsibilities. Agencies that would like to request cooperating
agency status should follow the instructions for filing comments
provided under the Public Participation section of this notice.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the Texas State Historic Preservation Office, and to solicit their
views and those of other government agencies, interested Indian tribes,
and the public on the project's potential effects on historic
properties.\3\ We will define the project-specific Area of Potential
Effects (APE) in consultation with the SHPO as the project is further
developed. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance. Our EA for this
project will document our findings on the impacts on historic
properties and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\3\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the planned facilities and
the environmental information provided by Freeport. This preliminary
list of issues may be changed based on your comments and our analysis.
Air Quality
Noise and vibration impacts
Socioeconomic impacts
Geology
Wetlands and waterbodies
Threatened and endangered species
Public safety
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that they will be received in Washington, DC on or before September 19,
2011.
For your convenience, there are three methods you can use to submit
your comments to the Commission. In all instances, please reference the
project docket number PF11-2-000 with your submission. The Commission
encourages electronic filing of comments and has expert eFiling staff
available to assist you at (202) 502-8258 or efiling@ferc.gov.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. An eComment is an
easy method for interested persons
[[Page 53442]]
to submit brief, text-only comments on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. With eFiling, you
can provide comments in a variety of formats by attaching them as a
file with your submission. New eFiling users must first create an
account by clicking on ``eRegister.'' You will be asked to select the
type of filing you are making. A comment on a particular project is
considered a ``Comment on a Filing''; or
(3) You may mail a paper copy of your comments to the Commission at
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Indian tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (Appendix 2).
Becoming an Intervenor
Once Freeport files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site. Please note that the Commission will not accept
requests for intervenor status at this time. You must wait until a
formal application for the project is filed with the Commission.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on
the eLibrary link, click on ``General Search'' and enter the docket
number, excluding the last three digits in the Docket Number field
(i.e., PF11-2-000). Be sure you have selected an appropriate date
range. For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: August 18, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-21799 Filed 8-25-11; 8:45 am]
BILLING CODE 6717-01-P