Environmental Impacts Statements; Notice of Availability, 51972-51973 [2011-21223]
Download as PDF
51972
Federal Register / Vol. 76, No. 161 / Friday, August 19, 2011 / Notices
jlentini on DSK4TPTVN1PROD with NOTICES
The mandatory information is reported
using standardized forms and annual
reports, and the regulations are codified
at 40 CFR Parts 144 through 148. The
data are used by UIC authorities to
ensure the protection of underground
sources of drinking water.
Burden Statement: The annual public
reporting and recordkeeping burden for
this collection of information is
estimated to average 2.32 hours per
response. Burden means the total time,
effort, or financial resources expended
by persons to generate, maintain, retain,
or disclose or provide information to or
for a Federal agency. This includes the
time needed to review instructions;
develop, acquire, install, and utilize
technology and systems for the purposes
of collecting, validating, and verifying
information, processing and
maintaining information, and disclosing
and providing information; adjust the
existing ways to comply with any
previously applicable instructions and
requirements which have subsequently
changed; train personnel to be able to
respond to a collection of information;
search data sources; complete and
review the collection of information;
and transmit or otherwise disclose the
information.
The ICR provides a detailed
explanation of the Agency’s estimate,
which is only briefly summarized here:
Estimated total number of potential
respondents: 53,772.
Frequency of response: annual, semiannual, and quarterly.
Estimated total average number of
responses for each respondent: 10.39.
Estimated total annual burden hours:
1,296,167 hours.
Estimated total annual costs:
$194,842,061. This includes an
estimated burden cost of $54,384,103
and an estimated cost of $140,457,959
for capital investment or maintenance
and operational costs.
Are there changes in the estimates from
the last approval?
There is an increase of 233,836 hours
in the total estimated respondent
burden compared with that identified in
the ICR currently approved by OMB.
This increase reflects a variety of
adjustments and program changes. Most
of the burden increase is due to
increases in the inventory of injection
wells and the number of permit
applications and mechanical integrity
tests submitted by operators and
reviewed by permitting authorities.
Other changes and adjustments relate to
reduced activities associated with the
Florida Class I Rule and the 1999 Class
V Rule, addition of burden associated
with the 2010 Class VI Rule, granting of
VerDate Mar<15>2010
18:32 Aug 18, 2011
Jkt 223001
primacy to two Tribes, and burden
reduction associated with electronic
reporting via the National UIC database.
What is the next step in the process for
this ICR?
EPA will consider the comments
received and amend the ICR as
appropriate. The final ICR package will
then be submitted to OMB for review
and approval pursuant to 5 CFR
1320.12. At that time, EPA will issue
another Federal Register notice
pursuant to 5 CFR 1320.5(a)(1)(iv) to
announce the submission of the ICR to
OMB and the opportunity to submit
additional comments to OMB. If you
have any questions about this ICR or the
approval process, please contact the
technical person listed under FOR
FURTHER INFORMATION CONTACT.
Dated: August 15, 2011.
Ronald W. Bergman,
Acting Director, Office of Ground Water and
Drinking Water.
[FR Doc. 2011–21228 Filed 8–18–11; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–8999–6]
Environmental Impacts Statements;
Notice of Availability
Responsible Agency: Office of Federal
Activities, General Information (202)
564–1399 or https://www.epa.gov/
compliance/nepa/.
Weekly receipt of Environmental Impact
Statements
Filed 08/08/2011 Through 08/12/2011
Pursuant to 40 CFR 1506.9.
Notice
In accordance with Section 309(a) of
the Clean Air Act, EPA is required to
make its comments on EISs issued by
other Federal agencies public.
Historically, EPA met this mandate by
publishing weekly notices of availability
of EPA comments, which includes a
brief summary of EPA’s comment
letters, in the Federal Register. Since
February 2008, EPA has included its
comment letters on EISs on its Web site
at: https://www.epa.gov/compliance/
nepa/eisdata.html. Including the entire
EIS comment letters on the Web site
satisfies the Section 309(a) requirement
to make EPA’s comments on EISs
available to the public. Accordingly, on
March 31, 2010, EPA discontinued the
publication of the notice of availability
of EPA comments in the Federal
Register.
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
EIS No. 20110259, Draft EIS, FHWA, FL,
Crosstown Parkway Extension Project,
New Bridge Crossing of the North
Fork St. Lucie River Crosstown
Parkway from Manth Lane to U.S. 1,
St. Lucie County, FL, Comment
Period Ends: 10/03/2011, Contact:
Cathy Kendall 850–553–2225.
EIS No. 20110260, Draft EIS, NPS, FL,
Biscayne National Park, General
Management Plan, Implementation,
Miami-Dade County, FL, Comment
Period Ends: 10/17/2011, Contact:
Morgan Elmer 303–969–2317.
EIS No. 20110261, Final EIS, USFS, NV,
Mountain City, Ruby Mountains, and
Jarbidge Ranger Districts, Combined
Travel Management Project,
Implementation, Humboldt-Toiyabe
National Forest, Elko and White Pine
Counties, NV, Review Period Ends:
10/03/2011, Contact: James Winfrey
775–355–5308.
EIS No. 20110262, Draft EIS, NPS, FL,
Canaveral National Seashore Project,
General Management Plan,
Implementation, Brevard and Volusia
Counties, FL, Comment Period Ends:
10/17/2011, Contact: Chris Church
303–969–2276.
EIS No. 20110263, Draft EIS, USACE,
CA, Salton Sea Species Conservation
Habitat Project, To Serve as a Proof of
Concept for the Restoration of
Shallow Water Habitat that Currently
Support Fish and Wildlife Dependent
Upon the Salton Sea, within the
southern portion of the Salton Sea,
Imperial County, CA, Comment
Period Ends: 10/17/2011, Contact:
Lanika Cervants 760–602–4838.
EIS No. 20110264, Final EIS, FHWA,
MT, Russell Street/South 3rd Street
Reconstruction Project, To Address
Current and Projected Safety and
Operational needs, Funding and U.S.
Army COE Section 404 Permit, City of
Missoula, Missoula County, MT,
Review Period Ends: 09/20/2011,
Contact: Brian Hasselbach 406–449–
5302.
EIS No. 20110265, Draft EIS, ARS, ID,
U.S. Sheep Experiment Station
Grazing and Associated Activities
Project 2010, To Develop Integrated
Methods for Increasing Production
Efficiency of Sheep, Dubois, ID,
Comment Period Ends: 10/03/2011,
Contact: Sue Wingate 603–569–3114.
EIS No. 20110266, Final EIS, BR, CA,
Nimbus Hatchery Fish Passage
Project, To Create and Maintain a
Reliable System for Collecting Adult
Fish to Allow Reclamation, Rancho
Cordova, Gold River, CA, Review
Period Ends: 09/19/2011, Contact:
Dave Robinson 916–989–7179.
EIS No. 20110267, Final EIS, USFS, CA,
Keddie Ridge Hazardous Fuels
E:\FR\FM\19AUN1.SGM
19AUN1
Federal Register / Vol. 76, No. 161 / Friday, August 19, 2011 / Notices
Reduction Project, Implementation,
Plumas National Forest, Mt. Hough
District, Plumas County, CA, Review
Period Ends: 09/19/2011, Contact:
Katherine Carpenter 530–283–7619.
EIS No. 20110268, Second Final EIS
(Tiering), NCPC, DC, Tier-2 FINAL—
Smithsonian Institution National
Museum of African American History
and Culture (NMAAHC), Construction
and Operation, Between 14th and
15th Streets NW. and Constitution
Avenue, NW. and Madison Drive,
NW., Washington, DC, Review Period
Ends: 09/19/2011, Contact: Jane
Passman 202–633–6549.
EIS No. 20110269, Draft Supplement,
USN, 00, Surveillance Towed Array
Sensor System Low Frequency Active
(SURTASS LFA) Sonar Systems,
Updated and Additional Information
on Employment of Four SURTASS
LFA Sonar Systems for Routine
Training, Testing, and Military
Operation, Implementation, Comment
Period Ends: 10/17/2011, Contact:
CDR Neil T. Smith 703–465–8404.
EIS No. 20110270, Draft EIS, NOAA, HI,
PROGRAMMATIC—Hawaiian Monk
Seal Recovery Actions, To Prevent the
Extinction of the Species, HI,
Comment Period Ends: 10/17/2011,
Contact: Jeff Walters 808–944–2200.
EIS No. 20110271, Final EIS, FHWA,
CO, North 1–25 Corridor, To Identify
and Evaluate Multi-Modal
Transportation Improvement along 61
miles from the Fort CollinsWellington Area, Funding and U.S.
Army COE Section 404 Permit,
Denver, CO, Review Period Ends: 09/
19/2011, Contact: Monica Pavlik 720–
963–3012.
Amended Notices:
jlentini on DSK4TPTVN1PROD with NOTICES
EIS No. 20110176, Draft EIS, BLM, NV,
Clark, Lincoln, and White Pine
Counties Groundwater Development
Project, Construction and Operation
of Pipeline System and Associated
Infrastructure, Right-Of-Way
Application, Clark, Lincoln, White
Pine, NV, Comment Period Ends: 10/
11/2011, Contact: Penny Woods 775–
861–6466 Revision to FR Notice 06/
10/2011: Extending comment period
from 09/08/2011 to 10/11/2011.
Dated: August 16, 2011.
Cliff Rader,
Acting Director, NEPA Compliance Division,
Office of Federal Activities.
[FR Doc. 2011–21223 Filed 8–18–11; 8:45 am]
BILLING CODE 6560–50–P
VerDate Mar<15>2010
18:32 Aug 18, 2011
Jkt 223001
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9454–4]
Notice of Regional Waiver Pursuant to
Section 1605 (Buy American
Requirement) of the American
Recovery and Reinvestment Act of
2009, to Mason County, WA
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Regional Administrator
of EPA Region 10 is hereby granting a
waiver request from the Buy American
requirements of ARRA Section 1605
under the authority of Section
1605(b)(1). This waiver request is being
granted because EPA believes it is in the
public interest to allow Mason County,
Washington (the County) to utilize and
install six specific turbo aeration blower
units as part of the County’s Belfair
Wastewater and Water Reclamation
Facilities project. This is a project
specific waiver and only applies to the
use of the specified product for the
ARRA project being proposed. Any
other ARRA recipient that wishes to use
the same product must apply for a
separate waiver based on project
specific circumstances. The Membrane
Bioreactor (MBR) system was selected
and procured by the County in 2008
using non-ARRA funding and prior to
enactment of ARRA. However, since the
MBR equipment is being installed by an
ARRA funded contract, the new Buy
American requirements of ARRA apply.
As ARRA was enacted after the County’s
procurement actions, the County could
not be aware of the need to purchase
and install a Buy American compliant
MBR system and could not reasonably
foresee the need for a waiver.
Requiring the installation of
domestically manufactured turbo
aeration blower units will extend the
time frame of the project significantly
(by at least four months), due to the
redesign, procurement, submittal
delivery, submittal review, fabrication,
delivery, and replacement of the
aeration blower installation at the
construction site. Redesign,
reconstruction, and replacement of the
blowers will likely cost at least an
additional $620,000 and could also void
the three year manufacturer warranty for
the MBR that is valid only if system
components identified in the
manufacturer’s proposal are utilized. A
significant delay in the project schedule
could push the project past the
anticipated September 2011 project
completion into the fall rainy season,
and could cause runoff over areas of
SUMMARY:
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
51973
failing septic systems and pose a risk to
environmental and water quality
protection. This additional cost and
delay is inconsistent with the public
interest, and a waiver of the Buy
American provisions in these
circumstances is justified. This action
allows the installation of the six
specified turbo aeration blower units
that have already been delivered to the
construction site as noted in Mason
County’s May 27, 2011, request and
additional follow up documentation.
DATES: Effective Date: August 9, 2011.
FOR FURTHER INFORMATION CONTACT:
Bryan Fiedorczyk, CWSRF ARRA
Program Management Analyst, Grants
and Strategic Planning Unit, Office of
Water & Watersheds (OWW), (206) 553–
0506, U.S. EPA Region 10 (OWW–137),
1200 Sixth Avenue, Suite 900, Seattle,
WA 98101.
SUPPLEMENTARY INFORMATION: In
accordance with ARRA Section 1605(c),
the EPA hereby provides notice that it
is granting a project waiver of the
requirements of Section 1605(a) of
Public Law 111–5, Buy American
requirements, to Mason County,
Washington, for the utilization and
installation of six specific turbo aeration
blower units as part of the County’s
Belfair Wastewater and Water
Reclamation Facilities project. Based on
the information provided by the County
and its consultant project manager, EPA
has determined that it is inconsistent
with the public interest for the County
to further delay the project and incur
significant additional costs to pursue
the purchase and installation of
domestic manufactured turbo aeration
blower units.
Section 1605 of the ARRA requires
that none of the appropriated funds may
be used for the construction, alteration,
maintenance, or repair of a public
building or a public works project
unless all of the iron, steel, and
manufactured goods used in the project
are produced in the United States, or
unless a waiver is provided to the
recipient by the head of the appropriate
agency, in this case, the EPA. A waiver
may be provided under Section 1605(b)
if EPA determines that (1) applying
these requirements would be
inconsistent with the public interest;
(2) iron, steel, and the relevant
manufactured goods are not produced in
the United States in sufficient and
reasonably available quantities and of a
satisfactory quality; or (3) inclusion of
iron, steel, and the relevant
manufactured goods produced in the
United States will increase the cost of
the overall project by more than
25 percent.
E:\FR\FM\19AUN1.SGM
19AUN1
Agencies
[Federal Register Volume 76, Number 161 (Friday, August 19, 2011)]
[Notices]
[Pages 51972-51973]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-21223]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[ER-FRL-8999-6]
Environmental Impacts Statements; Notice of Availability
Responsible Agency: Office of Federal Activities, General
Information (202) 564-1399 or https://www.epa.gov/compliance/nepa/.
Weekly receipt of Environmental Impact Statements
Filed 08/08/2011 Through 08/12/2011
Pursuant to 40 CFR 1506.9.
Notice
In accordance with Section 309(a) of the Clean Air Act, EPA is
required to make its comments on EISs issued by other Federal agencies
public. Historically, EPA met this mandate by publishing weekly notices
of availability of EPA comments, which includes a brief summary of
EPA's comment letters, in the Federal Register. Since February 2008,
EPA has included its comment letters on EISs on its Web site at: https://www.epa.gov/compliance/nepa/eisdata.html. Including the entire EIS
comment letters on the Web site satisfies the Section 309(a)
requirement to make EPA's comments on EISs available to the public.
Accordingly, on March 31, 2010, EPA discontinued the publication of the
notice of availability of EPA comments in the Federal Register.
EIS No. 20110259, Draft EIS, FHWA, FL, Crosstown Parkway Extension
Project, New Bridge Crossing of the North Fork St. Lucie River
Crosstown Parkway from Manth Lane to U.S. 1, St. Lucie County, FL,
Comment Period Ends: 10/03/2011, Contact: Cathy Kendall 850-553-2225.
EIS No. 20110260, Draft EIS, NPS, FL, Biscayne National Park, General
Management Plan, Implementation, Miami-Dade County, FL, Comment Period
Ends: 10/17/2011, Contact: Morgan Elmer 303-969-2317.
EIS No. 20110261, Final EIS, USFS, NV, Mountain City, Ruby Mountains,
and Jarbidge Ranger Districts, Combined Travel Management Project,
Implementation, Humboldt-Toiyabe National Forest, Elko and White Pine
Counties, NV, Review Period Ends: 10/03/2011, Contact: James Winfrey
775-355-5308.
EIS No. 20110262, Draft EIS, NPS, FL, Canaveral National Seashore
Project, General Management Plan, Implementation, Brevard and Volusia
Counties, FL, Comment Period Ends: 10/17/2011, Contact: Chris Church
303-969-2276.
EIS No. 20110263, Draft EIS, USACE, CA, Salton Sea Species Conservation
Habitat Project, To Serve as a Proof of Concept for the Restoration of
Shallow Water Habitat that Currently Support Fish and Wildlife
Dependent Upon the Salton Sea, within the southern portion of the
Salton Sea, Imperial County, CA, Comment Period Ends: 10/17/2011,
Contact: Lanika Cervants 760-602-4838.
EIS No. 20110264, Final EIS, FHWA, MT, Russell Street/South 3rd Street
Reconstruction Project, To Address Current and Projected Safety and
Operational needs, Funding and U.S. Army COE Section 404 Permit, City
of Missoula, Missoula County, MT, Review Period Ends: 09/20/2011,
Contact: Brian Hasselbach 406-449-5302.
EIS No. 20110265, Draft EIS, ARS, ID, U.S. Sheep Experiment Station
Grazing and Associated Activities Project 2010, To Develop Integrated
Methods for Increasing Production Efficiency of Sheep, Dubois, ID,
Comment Period Ends: 10/03/2011, Contact: Sue Wingate 603-569-3114.
EIS No. 20110266, Final EIS, BR, CA, Nimbus Hatchery Fish Passage
Project, To Create and Maintain a Reliable System for Collecting Adult
Fish to Allow Reclamation, Rancho Cordova, Gold River, CA, Review
Period Ends: 09/19/2011, Contact: Dave Robinson 916-989-7179.
EIS No. 20110267, Final EIS, USFS, CA, Keddie Ridge Hazardous Fuels
[[Page 51973]]
Reduction Project, Implementation, Plumas National Forest, Mt. Hough
District, Plumas County, CA, Review Period Ends: 09/19/2011, Contact:
Katherine Carpenter 530-283-7619.
EIS No. 20110268, Second Final EIS (Tiering), NCPC, DC, Tier-2 FINAL--
Smithsonian Institution National Museum of African American History and
Culture (NMAAHC), Construction and Operation, Between 14th and 15th
Streets NW. and Constitution Avenue, NW. and Madison Drive, NW.,
Washington, DC, Review Period Ends: 09/19/2011, Contact: Jane Passman
202-633-6549.
EIS No. 20110269, Draft Supplement, USN, 00, Surveillance Towed Array
Sensor System Low Frequency Active (SURTASS LFA) Sonar Systems, Updated
and Additional Information on Employment of Four SURTASS LFA Sonar
Systems for Routine Training, Testing, and Military Operation,
Implementation, Comment Period Ends: 10/17/2011, Contact: CDR Neil T.
Smith 703-465-8404.
EIS No. 20110270, Draft EIS, NOAA, HI, PROGRAMMATIC--Hawaiian Monk Seal
Recovery Actions, To Prevent the Extinction of the Species, HI, Comment
Period Ends: 10/17/2011, Contact: Jeff Walters 808-944-2200.
EIS No. 20110271, Final EIS, FHWA, CO, North 1-25 Corridor, To Identify
and Evaluate Multi-Modal Transportation Improvement along 61 miles from
the Fort Collins-Wellington Area, Funding and U.S. Army COE Section 404
Permit, Denver, CO, Review Period Ends: 09/19/2011, Contact: Monica
Pavlik 720-963-3012.
Amended Notices:
EIS No. 20110176, Draft EIS, BLM, NV, Clark, Lincoln, and White Pine
Counties Groundwater Development Project, Construction and Operation of
Pipeline System and Associated Infrastructure, Right-Of-Way
Application, Clark, Lincoln, White Pine, NV, Comment Period Ends: 10/
11/2011, Contact: Penny Woods 775-861-6466 Revision to FR Notice 06/10/
2011: Extending comment period from 09/08/2011 to 10/11/2011.
Dated: August 16, 2011.
Cliff Rader,
Acting Director, NEPA Compliance Division, Office of Federal
Activities.
[FR Doc. 2011-21223 Filed 8-18-11; 8:45 am]
BILLING CODE 6560-50-P