Mississippi 8 Hydro LLC; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 50725-50726 [2011-20753]
Download as PDF
emcdonald on DSK2BSOYB1PROD with NOTICES
Federal Register / Vol. 76, No. 158 / Tuesday, August 16, 2011 / Notices
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to reach a final
decision on a request for federal
authorization within 90 days of the date
of issuance of the Commission staff’s
EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
VerDate Mar<15>2010
18:07 Aug 15, 2011
Jkt 223001
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 14 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426. See,
18 CFR 385.2001(a) (1) (iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Comment Date: August 30, 2011.
Dated: August 9, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–20752 Filed 8–15–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project Nos. P–13010–001]
Mississippi 8 Hydro LLC; Notice of
Intent To File License Application,
Filing of Pre-Application Document,
and Approving Use of the Traditional
Licensing Process
a. Type of Filing: Notice of Intent To
File License Application and Request
To Use the Traditional Licensing
Process.
b. Project No.: P–13010–001.
c. Dated Filed: June 10, 2011.
d. Submitted By: Mississippi 8 Hydro
LLC.
e. Name of Project: Mississippi Lock
& Dam No. 8 Project.
f. Location: The project would be
located on the upper Mississippi River
in Houston County, Minnesota at an
existing lock and dam owned and
operated by the U.S. Corps of Engineers
(Corps) at about river mile 679. The
project would occupy federal lands
managed by the Corps and the U.S. Fish
and Wildlife Service.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Mr.
Brent Smith, Chief Operating Officer,
Symbiotics LLC, 371 Upper Terrace,
Suite 2, Bend, Oregon 97702; Phone:
541–330–8779.
PO 00000
Frm 00011
Fmt 4703
Sfmt 4703
50725
i. FERC Contact: Lesley Kordella at
(202) 502–6406; or e-mail at
Lesley.Kordella@ferc.gov.
j. Mississippi 8 Hydro LLC filed its
request to use the Traditional Licensing
Process on June 10, 2011. Mississippi 8
Hydro LLC provided public notice of its
request on June 13, 2011. In a letter
dated August 9, 2011, the Director of
Hydropower Licensing approved
Mississippi 8 Hydro LLC’s request to
use the Traditional Licensing Process.
k. With this notice, we are initiating
informal consultation with: (a) The U.S.
Fish and Wildlife Service and NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50 CFR
part 402; (b) NOAA Fisheries under
section 305(b) of the Magnuson-Stevens
Fishery Conservation and Management
Act and implementing regulations at 50
CFR 600.920; and (c) the Minnesota
State Historic Preservation Officer, as
required by section 106, National
Historic Preservation Act, and the
implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Mississippi 8 Hydro LLC as the
Commission’s non-federal
representative for carrying out informal
consultation, pursuant to section 7 of
the Endangered Species Act, section 305
of the Magnuson-Stevens Fishery
Conservation and Management Act, and
section 106 of the National Historic
Preservation Act.
m. Mississippi 8 Hydro LLC filed a
Pre-Application Document (PAD;
including a proposed process plan and
schedule) with the Commission,
pursuant to 18 CFR 5.6 of the
Commission’s regulations.
n. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in paragraph h.
o. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
E:\FR\FM\16AUN1.SGM
16AUN1
50726
Federal Register / Vol. 76, No. 158 / Tuesday, August 16, 2011 / Notices
Dated: August 9, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–20753 Filed 8–15–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14170–000]
emcdonald on DSK2BSOYB1PROD with NOTICES
Riverbank Hydro No. 14, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On May 2, 2011, Riverbank Hydro No.
14, LLC (Riverbank Hydro), filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Tuttle Creek
Hydroelectric Project (Tuttle Creek
Project or project) to be located at the
U.S. Army Corps of Engineers’ (Corps)
Tuttle Creek Dam, on Big Blue River,
near Manhattan, Riley County, Kansas.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) A 350-foot-long, 16foot-diameter penstock bifurcating from
the existing outlet structure; (2) a 100foot-long, 50-foot-wide concrete
powerhouse containing one turbine
with a generator rating of 7.9 megawatts;
(3) a tailrace structure directing flows
from the powerhouse back into the river
channel downstream of the existing
dam; (4) a 2.8-mile-long, 25-kilovolt
transmission line connecting the project
to an existing transmission line; and (5)
appurtenant facilities. The estimated
annual generation of the Tuttle Creek
Project would be 30.5 gigawatt-hours.
Applicant Contact: Mr. Kuo-Bao
Tong, Riverbank Power Corporation,
Royal Bank Plaza, South Tower, P.O.
Box 166, 200 Bay Street, Suite 3230,
Toronto, Ontario, Canada M5J2J4;
phone: (416) 861–0092, extension 154.
FERC Contact: Sergiu Serban; phone:
(202) 502–6211.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
VerDate Mar<15>2010
18:07 Aug 15, 2011
Jkt 223001
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14170–000)
in the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: August 9, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–20754 Filed 8–15–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Southwestern Power Administration
Integrated System Power Rates:
Correction
Southwestern Power
Administration, DOE.
ACTION: Notice of public review and
comment; Correction.
AGENCY:
Southwestern Power
Administration published a document
in the Federal Register (76 FR 48159) on
August 8, 2011, announcing the public
review and comment period on
proposed rates. Inadvertently, the date
listed for the combined Public
Information and Comment Forum
(Forum) was erroneously listed in the
DATES section as of August 16, 2011.
The correct date and time for the Forum,
if requested, will be August 30, 2011, at
9 a.m.
SUMMARY:
PO 00000
Frm 00012
Fmt 4703
Sfmt 4703
Mr.
James K. McDonald, Assistant
Administrator, Office of Corporate
Operations, Southwestern Power
Administration, U.S. Department of
Energy, One West Third Street, Tulsa,
Oklahoma 74103, (918) 595–6690,
jim.mcdonald@swpa.gov.
FOR FURTHER INFORMATION CONTACT:
Dated: August 10, 2011.
Jon Worthington,
Administrator.
[FR Doc. 2011–20934 Filed 8–12–11; 4:15 pm]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OW–2004–0013; FRL–9452–1]
Agency Information Collection
Activities; Proposed Collection;
Comment Request; EPA Strategic Plan
Information on Source Water
Protection
Environmental Protection
Agency.
ACTION: Notice.
AGENCY:
In compliance with the
Paperwork Reduction Act (PRA) (44
U.S.C. 3501 et seq.), this document
announces that EPA is planning to
submit a request to renew an existing
approved Information Collection
Request (ICR) to the Office of
Management and Budget (OMB). This
ICR is scheduled to expire on December
31, 2011. Before submitting the ICR to
OMB for review and approval, EPA is
soliciting comments on specific aspects
of the proposed information collection
as described in the SUPPLEMENTARY
INFORMATION section.
DATES: Comments must be submitted on
or before October 17, 2011.
ADDRESSES: Submit your comments,
identified by Docket ID No. EPA–HQ–
OW–2004–0013 by one of the following
methods:
• https://www.regulations.gov: Follow
the on-line instructions for submitting
comments.
• E–mail: OW–Docket@epa.gov.
• Mail: Water Docket, Environmental
Protection Agency, EPA Docket Center
(EPA/DC), Mailcode: 4101T, 1200
Pennsylvania Ave., NW., Washington,
DC 20460.
• Hand Delivery: The EPA Docket
Center at the Public Reading Room,
Room B3334, EPA West Building, 1301
Constitution Avenue, NW., Washington,
DC. Such deliveries are only accepted
during the Docket’s normal hours of
operation, and special arrangements
should be made for deliveries of boxed
information.
SUMMARY:
E:\FR\FM\16AUN1.SGM
16AUN1
Agencies
[Federal Register Volume 76, Number 158 (Tuesday, August 16, 2011)]
[Notices]
[Pages 50725-50726]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-20753]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. P-13010-001]
Mississippi 8 Hydro LLC; Notice of Intent To File License
Application, Filing of Pre-Application Document, and Approving Use of
the Traditional Licensing Process
a. Type of Filing: Notice of Intent To File License Application and
Request To Use the Traditional Licensing Process.
b. Project No.: P-13010-001.
c. Dated Filed: June 10, 2011.
d. Submitted By: Mississippi 8 Hydro LLC.
e. Name of Project: Mississippi Lock & Dam No. 8 Project.
f. Location: The project would be located on the upper Mississippi
River in Houston County, Minnesota at an existing lock and dam owned
and operated by the U.S. Corps of Engineers (Corps) at about river mile
679. The project would occupy federal lands managed by the Corps and
the U.S. Fish and Wildlife Service.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Mr. Brent Smith, Chief Operating
Officer, Symbiotics LLC, 371 Upper Terrace, Suite 2, Bend, Oregon
97702; Phone: 541-330-8779.
i. FERC Contact: Lesley Kordella at (202) 502-6406; or e-mail at
Lesley.Kordella@ferc.gov.
j. Mississippi 8 Hydro LLC filed its request to use the Traditional
Licensing Process on June 10, 2011. Mississippi 8 Hydro LLC provided
public notice of its request on June 13, 2011. In a letter dated August
9, 2011, the Director of Hydropower Licensing approved Mississippi 8
Hydro LLC's request to use the Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with:
(a) The U.S. Fish and Wildlife Service and NOAA Fisheries under section
7 of the Endangered Species Act and the joint agency regulations
thereunder at 50 CFR part 402; (b) NOAA Fisheries under section 305(b)
of the Magnuson-Stevens Fishery Conservation and Management Act and
implementing regulations at 50 CFR 600.920; and (c) the Minnesota State
Historic Preservation Officer, as required by section 106, National
Historic Preservation Act, and the implementing regulations of the
Advisory Council on Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating Mississippi 8 Hydro LLC as
the Commission's non-federal representative for carrying out informal
consultation, pursuant to section 7 of the Endangered Species Act,
section 305 of the Magnuson-Stevens Fishery Conservation and Management
Act, and section 106 of the National Historic Preservation Act.
m. Mississippi 8 Hydro LLC filed a Pre-Application Document (PAD;
including a proposed process plan and schedule) with the Commission,
pursuant to 18 CFR 5.6 of the Commission's regulations.
n. A copy of the PAD is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket
number, excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCONlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
(202) 502-8659. A copy is also available for inspection and
reproduction at the address in paragraph h.
o. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
[[Page 50726]]
Dated: August 9, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-20753 Filed 8-15-11; 8:45 am]
BILLING CODE 6717-01-P