Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 48847 [2011-20152]
Download as PDF
Federal Register / Vol. 76, No. 153 / Tuesday, August 9, 2011 / Notices
Dated: August 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–20154 Filed 8–8–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12933–002]
sroberts on DSK5SPTVN1PROD with NOTICES
FFP Project 49 LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On February 1, 2011, FFP Project 49
LLC filed an application, pursuant to
section 4(f) of the Federal Power Act,
proposing to study the feasibility of
hydropower on the Mississippi River,
near the town of Hickman, in Fulton
County Kentucky and Mississippi
County, Missouri. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed Hickman Bend
hydrokinetic project would consist of
the following: (1) Up to 2,850
SmarTurbine generating units installed
in arrays on the bottom of the river; (2)
the total capacity of the installation
would be up to 114,000 kilowatts; (3)
flexible cables would convey each
arrays power to a metering station; and
(4) a transmission line would
interconnect with the power grid. The
proposed project would have an average
annual generation of 249,660,000
kilowatt-hours (kWh), which would be
sold to a local utility.
Applicant Contact: Ramya
Swaminathan, Free Flow Power
Corporation, 239 Causeway Street,
Boston, MA 02114; phone (978) 283–
2822.
FERC Contact: Michael Spencer, (202)
502–6093.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
VerDate Mar<15>2010
19:06 Aug 08, 2011
Jkt 223001
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–12933–002) in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
Dated: August 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–20153 Filed 8–8–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[FFP Project 47 LLC; Project No.12932–002]
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On February 1, 2011, FFP Project 47
LLC filed an application, pursuant to
section 4(f) of the Federal Power Act,
proposing to study the feasibility of
hydropower on the Mississippi River, in
Mississippi County Arkansas and
Tipton County, Tennessee. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed Williams Point
hydrokinetic project would consist of
PO 00000
Frm 00059
Fmt 4703
Sfmt 9990
48847
the following: (1) Up to 3,550
SmarTurbine generating units installed
in arrays on the bottom of the river; (2)
the total capacity of the installation
would be up to 142,000 kilowatts; (3)
flexible cables would convey each
arrays power to a metering station; and
(4) a transmission line would
interconnect with the power grid. The
proposed project would have an average
annual generation of 310,980,000
kilowatt-hours (kWh), which would be
sold to a local utility.
Applicant Contact: Ramya
Swaminathan, Free Flow Power
Corporation, 239 Causeway Street,
Boston, MA 02114; phone (978) 283–
2822.
FERC Contact: Michael Spencer, (202)
502–6093.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–12932–002) in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
Dated: August 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–20152 Filed 8–8–11; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\09AUN1.SGM
09AUN1
Agencies
[Federal Register Volume 76, Number 153 (Tuesday, August 9, 2011)]
[Notices]
[Page 48847]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-20152]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[FFP Project 47 LLC; Project No.12932-002]
Notice of Preliminary Permit Application Accepted for Filing and
Soliciting Comments, Motions To Intervene, and Competing Applications
On February 1, 2011, FFP Project 47 LLC filed an application,
pursuant to section 4(f) of the Federal Power Act, proposing to study
the feasibility of hydropower on the Mississippi River, in Mississippi
County Arkansas and Tipton County, Tennessee. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed Williams Point hydrokinetic project would consist of
the following: (1) Up to 3,550 SmarTurbine generating units installed
in arrays on the bottom of the river; (2) the total capacity of the
installation would be up to 142,000 kilowatts; (3) flexible cables
would convey each arrays power to a metering station; and (4) a
transmission line would interconnect with the power grid. The proposed
project would have an average annual generation of 310,980,000
kilowatt-hours (kWh), which would be sold to a local utility.
Applicant Contact: Ramya Swaminathan, Free Flow Power Corporation,
239 Causeway Street, Boston, MA 02114; phone (978) 283-2822.
FERC Contact: Michael Spencer, (202) 502-6093.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-
3676; or, for TTY, contact (202) 502-8659. Although the Commission
strongly encourages electronic filing, documents may also be paper-
filed. To paper-file, mail an original and seven copies to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-12932-002) in the docket number field to
access the document. For assistance, contact FERC Online Support.
Dated: August 3, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-20152 Filed 8-8-11; 8:45 am]
BILLING CODE 6717-01-P