Columbia Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Vepco-Warren County Project and Request for Comments on Environmental Issues, 46285-46287 [2011-19471]

Download as PDF erowe on DSK5CLS3C1PROD with NOTICES Federal Register / Vol. 76, No. 148 / Tuesday, August 2, 2011 / Notices document on the Applicant. In reference to filings initiating a new proceeding, interventions or protests submitted on or before the comment deadline need not be served on persons other than the Applicant. As it relates to any qualifying facility filings, the notices of self-certification [or self-recertification] listed above, do not institute a proceeding regarding qualifying facility status. A notice of self-certification [or self-recertification] simply provides notification that the entity making the filing has determined the facility named in the notice meets the applicable criteria to be a qualifying facility. Intervention and/or protest do not lie in dockets that are qualifying facility self-certifications or selfrecertifications. Any person seeking to challenge such qualifying facility status may do so by filing a motion pursuant to 18 CFR 292.207(d)(iii). Intervention and protests may be filed in response to notices of qualifying facility dockets other than self-certifications and selfrecertifications. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First St., NE., Washington, DC 20426. The filings in the above proceedings are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: July 26, 2011. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2011–19465 Filed 8–1–11; 8:45 am] BILLING CODE 6717–01–P VerDate Mar<15>2010 15:03 Aug 01, 2011 Jkt 223001 ferc.gov). This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP11–490–000] Columbia Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Vepco—Warren County Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Vepco—Warren County Project involving construction and operation of facilities by Columbia Gas Transmission, LLC (Columbia) in Charleston, West Virginia. This EA will be used by the Commission in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process we will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine which issues need to be evaluated in the EA. Please note that the scoping period will close on August 25, 2011. This notice is being sent to affected landowners; Federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. State and local government representatives are asked to notify their constituents of this planned project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, you may be contacted by a Columbia representative about survey permission and/or the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the project is approved by the Commission, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the natural gas company could initiate condemnation proceedings in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ is available for viewing on the FERC internet Web site (https://www. PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 46285 Summary of the Proposed Project Columbia proposes in response to a request from Virginia Electric and Power Company (VEPCO), to construct approximately 2.47 miles of 24-inchdiameter natural gas transmission pipeline and an associated meter and regulation (M&R) station in Warren County, Virginia. In addition, the project involves the installation of minor station piping and appurtenance modifications at existing compressor stations in northern Virginia and eastern West Virginia, and abandonment and replacement of an existing pipeline interconnect near Rockville, Maryland. The project would increase the capacity to 246,000 Dth/day during the winter and utilize 224,000 Dth/day of reserved capacity during the summer to meet the fuel requirements of VEPCO’s proposed power station. The general location of the project facilities is shown in Appendix 1. If approved, Columbia proposes to commence construction of the proposed facilities in April 2012. Land Requirements for Construction Construction of the pipeline would temporarily impact about 32.4 acres. Permanent land requirements for operation of the proposed pipeline would impact approximately 19.7 acres and 12.7 acres would be reverted to preconstruction use. Approximately 0.6 acres of land would be utilized at the end point for permanent above-ground valve assemblies and pig receivers. Columbia would use a 75-foot-wide temporary right-of-way during construction and a 50-foot-wide permanent right-of-way for maintenance and operation centered over the centerline of the new pipeline. In addition to the pipeline replacement, Columbia is proposing construction of a pig launcher/receiver at existing Ninevah M&R Station in Warren County, Virginia. A new M&R station would be built at milepost 2.47 of the proposed pipeline within the VEPCO—Warren County Power Station lot. At the Rockville Measuring Station, Columbia proposes to construct an interconnect between its existing 26inch-diameter Line MB pipeline and Transcontinental Pipeline Corporations’ system. Construction and operation of the proposed modifications at the existing Ninevah M&R Station, Loudoun and Lost River Compressor Stations, and Rockville Measuring Station would take E:\FR\FM\02AUN1.SGM 02AUN1 46286 Federal Register / Vol. 76, No. 148 / Tuesday, August 2, 2011 / Notices place within the existing property boundaries of those facilities. Columbia is also proposing to utilize four existing private access roads and two new roads to gain access to the construction areas along the pipeline route. Columbia proposes one temporary pipeyard/contractor yard for the Project. erowe on DSK5CLS3C1PROD with NOTICES The EA Process The National Environmental Policy Act (NEPA) requires that the Commission take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 1 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this Notice of Intent, the Commission staff requests public comments on the scope of the issues to address in the EA. All comments received are considered during the preparation of the EA. State and local government representatives are encouraged to notify their constituents of this proposed action and encourage them to comment on their areas of concern. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and Soils; • Land Use; • Water Resources, Fisheries, and Wetlands; • Cultural Resources; • Vegetation and Wildlife; • Air Quality and Noise; • Endangered and Threatened Species; • Public Safety. We will also evaluate possible alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Our independent analysis of the issues will be in the EA. Depending on the comments received during the scoping process, the EA may be published and mailed to Federal, state, and local agencies, public interest groups, interested individuals, affected landowners, newspapers, libraries, and the Commission’s official service list for 1 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the environmental staff of the Office of Energy Projects (OEP). VerDate Mar<15>2010 15:03 Aug 01, 2011 Jkt 223001 this proceeding. A comment period will be allotted for review if the EA is published. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure your comments are considered, please carefully follow the instructions in the public participation section below. With this NOI, we are asking Federal, state, and local agencies with jurisdiction and/or special expertise with respect to environmental issues to formally cooperate with us in the preparation of the EA. These agencies may choose to participate once they have evaluated the proposal relative to their responsibilities. Additional agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this NOI. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with applicable State Historic Preservation Office(s), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.2 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO(s) as the project is further developed. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Public Participation You can make a difference by providing us with your specific comments or concerns about the Vepco—Warren County Project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful 2 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Historic properties are defined in those regulations as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register for Historic Places. PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 they will be. To ensure that your comments are timely and properly recorded, please send in your comments so that they will be received in Washington, DC on or before August 25, 2011. For your convenience, there are three methods in which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP11–490–000) with your submission. The Commission encourages electronic filing of comments and has dedicated eFiling expert staff available to assist you at 202–502–8258 or efiling@ferc.gov. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s Web site at https:// www.ferc.gov under the link to Documents and Filings. An eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s Web site at https:// www.ferc.gov under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making. A comment on a particular project is considered a ‘‘Comment on a Filing;’’ or (3) You may file a paper copy of your comments at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Room 1A, Washington, DC 20426. Label one copy of the comments for the attention of Gas Branch 3, PJ11.3. Environmental Mailing List An effort is being made to send this notice to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. This includes all landowners who are potential right-ofway grantors, whose property may be used temporarily for project purposes, or who own homes within distances defined in the Commission’s regulations of certain aboveground facilities. If you do not want to send comments at this time but still want to remain on our mailing list, please return the Information Request (Appendix 2). If you do not return the Information Request, you will be taken off the mailing list. E:\FR\FM\02AUN1.SGM 02AUN1 Federal Register / Vol. 76, No. 148 / Tuesday, August 2, 2011 / Notices Becoming an Intervenor DEPARTMENT OF ENERGY In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor,’’ which is an official party to the proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in a Commission proceeding by filing a request to intervene. Instructions for becoming an intervenor are included in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Federal Energy Regulatory Commission Additional Information erowe on DSK5CLS3C1PROD with NOTICES Additional information about the project is available from the Commission’s Office of External Affairs, at 1–866–208–FERC or on the FERC Internet Web site (https://www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number excluding the last three digits in the Docket Number field (CP11–490). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, contact (202)502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries and direct links to the documents. Go to https:// www.ferc.gov/esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: July 26, 2011. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2011–19471 Filed 8–1–11; 8:45 am] BILLING CODE 6717–01–P [Project No. 2047–049] Erie Boulevard Hydropower, L.P.; Notice of Availability of Environmental Assessment In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission’s (Commission or FERC) regulations, 18 CFR Part 380, Commission staff has reviewed the application for amendment of license for the Stewarts Bridge Project (FERC No. 2047) and has prepared an environmental assessment (EA). The project is located on the Sacandaga River in Saratoga County, New York. The EA contains the Commission staff’s analysis of the potential environmental effects of the proposed addition of new generating capacity and concludes that authorizing the amendment, with appropriate environmental protective measures would not constitute a major Federal action that would significantly affect the quality of the human environment. A copy of the EA is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY contact (202) 502–8695. Dated: July 26, 2011. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2011–19468 Filed 8–1–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER11–4111–000] Hudson Ranch Power I LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Hudson Ranch Power I LLC’s application for market-based rate authority, with an VerDate Mar<15>2010 15:03 Aug 01, 2011 Jkt 223001 PO 00000 Frm 00021 Fmt 4703 Sfmt 9990 46287 accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is August 15, 2011. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: July 26, 2011. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2011–19470 Filed 8–1–11; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\02AUN1.SGM 02AUN1

Agencies

[Federal Register Volume 76, Number 148 (Tuesday, August 2, 2011)]
[Notices]
[Pages 46285-46287]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-19471]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 [Docket No. CP11-490-000]


Columbia Gas Transmission, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Vepco--Warren County Project 
and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Vepco--Warren County Project 
involving construction and operation of facilities by Columbia Gas 
Transmission, LLC (Columbia) in Charleston, West Virginia. This EA will 
be used by the Commission in its decision-making process to determine 
whether the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process we will 
use to gather input from the public and interested agencies on the 
project. Your input will help the Commission staff determine which 
issues need to be evaluated in the EA. Please note that the scoping 
period will close on August 25, 2011.
    This notice is being sent to affected landowners; Federal, state, 
and local government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. State and local 
government representatives are asked to notify their constituents of 
this planned project and encourage them to comment on their areas of 
concern.
    If you are a landowner receiving this notice, you may be contacted 
by a Columbia representative about survey permission and/or the 
acquisition of an easement to construct, operate, and maintain the 
proposed facilities. The company would seek to negotiate a mutually 
acceptable agreement. However, if the project is approved by the 
Commission, that approval conveys with it the right of eminent domain. 
Therefore, if easement negotiations fail to produce an agreement, the 
natural gas company could initiate condemnation proceedings in 
accordance with state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC internet Web site (https://www.ferc.gov). This fact 
sheet addresses a number of typically asked questions, including the 
use of eminent domain and how to participate in the Commission's 
proceedings.

Summary of the Proposed Project

    Columbia proposes in response to a request from Virginia Electric 
and Power Company (VEPCO), to construct approximately 2.47 miles of 24-
inch-diameter natural gas transmission pipeline and an associated meter 
and regulation (M&R) station in Warren County, Virginia. In addition, 
the project involves the installation of minor station piping and 
appurtenance modifications at existing compressor stations in northern 
Virginia and eastern West Virginia, and abandonment and replacement of 
an existing pipeline interconnect near Rockville, Maryland. The project 
would increase the capacity to 246,000 Dth/day during the winter and 
utilize 224,000 Dth/day of reserved capacity during the summer to meet 
the fuel requirements of VEPCO's proposed power station. The general 
location of the project facilities is shown in Appendix 1.
    If approved, Columbia proposes to commence construction of the 
proposed facilities in April 2012.

Land Requirements for Construction

    Construction of the pipeline would temporarily impact about 32.4 
acres. Permanent land requirements for operation of the proposed 
pipeline would impact approximately 19.7 acres and 12.7 acres would be 
reverted to pre-construction use. Approximately 0.6 acres of land would 
be utilized at the end point for permanent above-ground valve 
assemblies and pig receivers. Columbia would use a 75-foot-wide 
temporary right-of-way during construction and a 50-foot-wide permanent 
right-of-way for maintenance and operation centered over the centerline 
of the new pipeline.
    In addition to the pipeline replacement, Columbia is proposing 
construction of a pig launcher/receiver at existing Ninevah M&R Station 
in Warren County, Virginia. A new M&R station would be built at 
milepost 2.47 of the proposed pipeline within the VEPCO--Warren County 
Power Station lot. At the Rockville Measuring Station, Columbia 
proposes to construct an interconnect between its existing 26-inch-
diameter Line MB pipeline and Transcontinental Pipeline Corporations' 
system. Construction and operation of the proposed modifications at the 
existing Ninevah M&R Station, Loudoun and Lost River Compressor 
Stations, and Rockville Measuring Station would take

[[Page 46286]]

place within the existing property boundaries of those facilities.
    Columbia is also proposing to utilize four existing private access 
roads and two new roads to gain access to the construction areas along 
the pipeline route. Columbia proposes one temporary pipeyard/contractor 
yard for the Project.

The EA Process

    The National Environmental Policy Act (NEPA) requires that the 
Commission take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\1\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this Notice of Intent, the Commission staff 
requests public comments on the scope of the issues to address in the 
EA. All comments received are considered during the preparation of the 
EA. State and local government representatives are encouraged to notify 
their constituents of this proposed action and encourage them to 
comment on their areas of concern.
---------------------------------------------------------------------------

    \1\ ``We'', ``us'', and ``our'' refer to the environmental staff 
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and Soils;
     Land Use;
     Water Resources, Fisheries, and Wetlands;
     Cultural Resources;
     Vegetation and Wildlife;
     Air Quality and Noise;
     Endangered and Threatened Species;
     Public Safety.
    We will also evaluate possible alternatives to the proposed project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Our independent analysis of the issues will be in the EA. Depending 
on the comments received during the scoping process, the EA may be 
published and mailed to Federal, state, and local agencies, public 
interest groups, interested individuals, affected landowners, 
newspapers, libraries, and the Commission's official service list for 
this proceeding. A comment period will be allotted for review if the EA 
is published. We will consider all comments on the EA before we make 
our recommendations to the Commission. To ensure your comments are 
considered, please carefully follow the instructions in the public 
participation section below.
    With this NOI, we are asking Federal, state, and local agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues to formally cooperate with us in the preparation 
of the EA. These agencies may choose to participate once they have 
evaluated the proposal relative to their responsibilities. Additional 
agencies that would like to request cooperating agency status should 
follow the instructions for filing comments provided under the Public 
Participation section of this NOI.

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with applicable State Historic Preservation Office(s), and to solicit 
their views and those of other government agencies, interested Indian 
tribes, and the public on the project's potential effects on historic 
properties.\2\ We will define the project-specific Area of Potential 
Effects (APE) in consultation with the SHPO(s) as the project is 
further developed. On natural gas facility projects, the APE at a 
minimum encompasses all areas subject to ground disturbance (examples 
include construction right-of-way, contractor/pipe storage yards, 
compressor stations, and access roads). Our EA for this project will 
document our findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \2\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Historic 
properties are defined in those regulations as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register for Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the Vepco--Warren County Project. Your 
comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. The more specific your comments, the more useful they will be. 
To ensure that your comments are timely and properly recorded, please 
send in your comments so that they will be received in Washington, DC 
on or before August 25, 2011.
    For your convenience, there are three methods in which you can use 
to submit your comments to the Commission. In all instances please 
reference the project docket number (CP11-490-000) with your 
submission. The Commission encourages electronic filing of comments and 
has dedicated eFiling expert staff available to assist you at 202-502-
8258 or efiling@ferc.gov.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. An eComment is an 
easy method for interested persons to submit brief, text-only comments 
on a project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. With eFiling, you 
can provide comments in a variety of formats by attaching them as a 
file with your submission. New eFiling users must first create an 
account by clicking on ``eRegister.'' You will be asked to select the 
type of filing you are making. A comment on a particular project is 
considered a ``Comment on a Filing;'' or
    (3) You may file a paper copy of your comments at the following 
address:

Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Room 1A, Washington, DC 20426.
    Label one copy of the comments for the attention of Gas Branch 3, 
PJ11.3.

Environmental Mailing List

    An effort is being made to send this notice to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project. This includes all landowners who are 
potential right-of-way grantors, whose property may be used temporarily 
for project purposes, or who own homes within distances defined in the 
Commission's regulations of certain aboveground facilities.
    If you do not want to send comments at this time but still want to 
remain on our mailing list, please return the Information Request 
(Appendix 2). If you do not return the Information Request, you will be 
taken off the mailing list.

[[Page 46287]]

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor,'' which is an official party to the 
proceeding. Intervenors play a more formal role in the process and are 
able to file briefs, appear at hearings, and be heard by the courts if 
they choose to appeal the Commission's final ruling. An intervenor 
formally participates in a Commission proceeding by filing a request to 
intervene. Instructions for becoming an intervenor are included in the 
User's Guide under the ``e-filing'' link on the Commission's Web site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at 1-866-208-FERC or on the 
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link. 
Click on the eLibrary link, click on ``General Search'' and enter the 
docket number excluding the last three digits in the Docket Number 
field (CP11-490). Be sure you have selected an appropriate date range. 
For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, 
contact (202)502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries and direct links to 
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: July 26, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011-19471 Filed 8-1-11; 8:45 am]
BILLING CODE 6717-01-P