Columbia Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Vepco-Warren County Project and Request for Comments on Environmental Issues, 46285-46287 [2011-19471]
Download as PDF
erowe on DSK5CLS3C1PROD with NOTICES
Federal Register / Vol. 76, No. 148 / Tuesday, August 2, 2011 / Notices
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
As it relates to any qualifying facility
filings, the notices of self-certification
[or self-recertification] listed above, do
not institute a proceeding regarding
qualifying facility status. A notice of
self-certification [or self-recertification]
simply provides notification that the
entity making the filing has determined
the facility named in the notice meets
the applicable criteria to be a qualifying
facility. Intervention and/or protest do
not lie in dockets that are qualifying
facility self-certifications or selfrecertifications. Any person seeking to
challenge such qualifying facility status
may do so by filing a motion pursuant
to 18 CFR 292.207(d)(iii). Intervention
and protests may be filed in response to
notices of qualifying facility dockets
other than self-certifications and selfrecertifications.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please email FERCOnlineSupport@ferc.gov or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Dated: July 26, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011–19465 Filed 8–1–11; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
15:03 Aug 01, 2011
Jkt 223001
ferc.gov). This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–490–000]
Columbia Gas Transmission, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Vepco—Warren County
Project and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Vepco—Warren County Project
involving construction and operation of
facilities by Columbia Gas
Transmission, LLC (Columbia) in
Charleston, West Virginia. This EA will
be used by the Commission in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process we will use to
gather input from the public and
interested agencies on the project. Your
input will help the Commission staff
determine which issues need to be
evaluated in the EA. Please note that the
scoping period will close on August 25,
2011.
This notice is being sent to affected
landowners; Federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. State and local
government representatives are asked to
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
Columbia representative about survey
permission and/or the acquisition of an
easement to construct, operate, and
maintain the proposed facilities. The
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
to produce an agreement, the natural gas
company could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC internet Web site (https://www.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
46285
Summary of the Proposed Project
Columbia proposes in response to a
request from Virginia Electric and
Power Company (VEPCO), to construct
approximately 2.47 miles of 24-inchdiameter natural gas transmission
pipeline and an associated meter and
regulation (M&R) station in Warren
County, Virginia. In addition, the
project involves the installation of
minor station piping and appurtenance
modifications at existing compressor
stations in northern Virginia and eastern
West Virginia, and abandonment and
replacement of an existing pipeline
interconnect near Rockville, Maryland.
The project would increase the capacity
to 246,000 Dth/day during the winter
and utilize 224,000 Dth/day of reserved
capacity during the summer to meet the
fuel requirements of VEPCO’s proposed
power station. The general location of
the project facilities is shown in
Appendix 1.
If approved, Columbia proposes to
commence construction of the proposed
facilities in April 2012.
Land Requirements for Construction
Construction of the pipeline would
temporarily impact about 32.4 acres.
Permanent land requirements for
operation of the proposed pipeline
would impact approximately 19.7 acres
and 12.7 acres would be reverted to preconstruction use. Approximately 0.6
acres of land would be utilized at the
end point for permanent above-ground
valve assemblies and pig receivers.
Columbia would use a 75-foot-wide
temporary right-of-way during
construction and a 50-foot-wide
permanent right-of-way for maintenance
and operation centered over the
centerline of the new pipeline.
In addition to the pipeline
replacement, Columbia is proposing
construction of a pig launcher/receiver
at existing Ninevah M&R Station in
Warren County, Virginia. A new M&R
station would be built at milepost 2.47
of the proposed pipeline within the
VEPCO—Warren County Power Station
lot. At the Rockville Measuring Station,
Columbia proposes to construct an
interconnect between its existing 26inch-diameter Line MB pipeline and
Transcontinental Pipeline Corporations’
system. Construction and operation of
the proposed modifications at the
existing Ninevah M&R Station, Loudoun
and Lost River Compressor Stations, and
Rockville Measuring Station would take
E:\FR\FM\02AUN1.SGM
02AUN1
46286
Federal Register / Vol. 76, No. 148 / Tuesday, August 2, 2011 / Notices
place within the existing property
boundaries of those facilities.
Columbia is also proposing to utilize
four existing private access roads and
two new roads to gain access to the
construction areas along the pipeline
route. Columbia proposes one
temporary pipeyard/contractor yard for
the Project.
erowe on DSK5CLS3C1PROD with NOTICES
The EA Process
The National Environmental Policy
Act (NEPA) requires that the
Commission take into account the
environmental impacts that could result
from an action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. NEPA also
requires us 1 to discover and address
concerns the public may have about
proposals. This process is referred to as
‘‘scoping.’’ The main goal of the scoping
process is to focus the analysis in the
EA on the important environmental
issues. By this Notice of Intent, the
Commission staff requests public
comments on the scope of the issues to
address in the EA. All comments
received are considered during the
preparation of the EA. State and local
government representatives are
encouraged to notify their constituents
of this proposed action and encourage
them to comment on their areas of
concern.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and Soils;
• Land Use;
• Water Resources, Fisheries, and
Wetlands;
• Cultural Resources;
• Vegetation and Wildlife;
• Air Quality and Noise;
• Endangered and Threatened
Species;
• Public Safety.
We will also evaluate possible
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to Federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
1 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
VerDate Mar<15>2010
15:03 Aug 01, 2011
Jkt 223001
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission. To ensure your comments
are considered, please carefully follow
the instructions in the public
participation section below.
With this NOI, we are asking Federal,
state, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. These agencies
may choose to participate once they
have evaluated the proposal relative to
their responsibilities. Additional
agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this NOI.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with
applicable State Historic Preservation
Office(s), and to solicit their views and
those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.2 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO(s)
as the project is further developed. On
natural gas facility projects, the APE at
a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA for this project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under section 106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the
Vepco—Warren County Project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. The more
specific your comments, the more useful
2 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
they will be. To ensure that your
comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before August 25,
2011.
For your convenience, there are three
methods in which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number (CP11–490–000) with
your submission. The Commission
encourages electronic filing of
comments and has dedicated eFiling
expert staff available to assist you at
202–502–8258 or efiling@ferc.gov.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. An eComment
is an easy method for interested persons
to submit brief, text-only comments on
a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making. A comment on a particular
project is considered a ‘‘Comment on a
Filing;’’ or
(3) You may file a paper copy of your
comments at the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Room 1A,
Washington, DC 20426.
Label one copy of the comments for
the attention of Gas Branch 3, PJ11.3.
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within distances
defined in the Commission’s regulations
of certain aboveground facilities.
If you do not want to send comments
at this time but still want to remain on
our mailing list, please return the
Information Request (Appendix 2). If
you do not return the Information
Request, you will be taken off the
mailing list.
E:\FR\FM\02AUN1.SGM
02AUN1
Federal Register / Vol. 76, No. 148 / Tuesday, August 2, 2011 / Notices
Becoming an Intervenor
DEPARTMENT OF ENERGY
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor,’’ which is an
official party to the proceeding.
Intervenors play a more formal role in
the process and are able to file briefs,
appear at hearings, and be heard by the
courts if they choose to appeal the
Commission’s final ruling. An
intervenor formally participates in a
Commission proceeding by filing a
request to intervene. Instructions for
becoming an intervenor are included in
the User’s Guide under the ‘‘e-filing’’
link on the Commission’s Web site.
Federal Energy Regulatory
Commission
Additional Information
erowe on DSK5CLS3C1PROD with NOTICES
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field (CP11–490). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
Online Support at
FercOnlineSupport@ferc.gov or toll free
at 1–866–208–3676, or for TTY, contact
(202)502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: July 26, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011–19471 Filed 8–1–11; 8:45 am]
BILLING CODE 6717–01–P
[Project No. 2047–049]
Erie Boulevard Hydropower, L.P.;
Notice of Availability of Environmental
Assessment
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission or FERC)
regulations, 18 CFR Part 380,
Commission staff has reviewed the
application for amendment of license
for the Stewarts Bridge Project (FERC
No. 2047) and has prepared an
environmental assessment (EA). The
project is located on the Sacandaga
River in Saratoga County, New York.
The EA contains the Commission
staff’s analysis of the potential
environmental effects of the proposed
addition of new generating capacity and
concludes that authorizing the
amendment, with appropriate
environmental protective measures
would not constitute a major Federal
action that would significantly affect the
quality of the human environment.
A copy of the EA is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY
contact (202) 502–8695.
Dated: July 26, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011–19468 Filed 8–1–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER11–4111–000]
Hudson Ranch Power I LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Hudson
Ranch Power I LLC’s application for
market-based rate authority, with an
VerDate Mar<15>2010
15:03 Aug 01, 2011
Jkt 223001
PO 00000
Frm 00021
Fmt 4703
Sfmt 9990
46287
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is August 15,
2011.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: July 26, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011–19470 Filed 8–1–11; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\02AUN1.SGM
02AUN1
Agencies
[Federal Register Volume 76, Number 148 (Tuesday, August 2, 2011)]
[Notices]
[Pages 46285-46287]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-19471]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP11-490-000]
Columbia Gas Transmission, LLC; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Vepco--Warren County Project
and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Vepco--Warren County Project
involving construction and operation of facilities by Columbia Gas
Transmission, LLC (Columbia) in Charleston, West Virginia. This EA will
be used by the Commission in its decision-making process to determine
whether the project is in the public convenience and necessity.
This notice announces the opening of the scoping process we will
use to gather input from the public and interested agencies on the
project. Your input will help the Commission staff determine which
issues need to be evaluated in the EA. Please note that the scoping
period will close on August 25, 2011.
This notice is being sent to affected landowners; Federal, state,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. State and local
government representatives are asked to notify their constituents of
this planned project and encourage them to comment on their areas of
concern.
If you are a landowner receiving this notice, you may be contacted
by a Columbia representative about survey permission and/or the
acquisition of an easement to construct, operate, and maintain the
proposed facilities. The company would seek to negotiate a mutually
acceptable agreement. However, if the project is approved by the
Commission, that approval conveys with it the right of eminent domain.
Therefore, if easement negotiations fail to produce an agreement, the
natural gas company could initiate condemnation proceedings in
accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC internet Web site (https://www.ferc.gov). This fact
sheet addresses a number of typically asked questions, including the
use of eminent domain and how to participate in the Commission's
proceedings.
Summary of the Proposed Project
Columbia proposes in response to a request from Virginia Electric
and Power Company (VEPCO), to construct approximately 2.47 miles of 24-
inch-diameter natural gas transmission pipeline and an associated meter
and regulation (M&R) station in Warren County, Virginia. In addition,
the project involves the installation of minor station piping and
appurtenance modifications at existing compressor stations in northern
Virginia and eastern West Virginia, and abandonment and replacement of
an existing pipeline interconnect near Rockville, Maryland. The project
would increase the capacity to 246,000 Dth/day during the winter and
utilize 224,000 Dth/day of reserved capacity during the summer to meet
the fuel requirements of VEPCO's proposed power station. The general
location of the project facilities is shown in Appendix 1.
If approved, Columbia proposes to commence construction of the
proposed facilities in April 2012.
Land Requirements for Construction
Construction of the pipeline would temporarily impact about 32.4
acres. Permanent land requirements for operation of the proposed
pipeline would impact approximately 19.7 acres and 12.7 acres would be
reverted to pre-construction use. Approximately 0.6 acres of land would
be utilized at the end point for permanent above-ground valve
assemblies and pig receivers. Columbia would use a 75-foot-wide
temporary right-of-way during construction and a 50-foot-wide permanent
right-of-way for maintenance and operation centered over the centerline
of the new pipeline.
In addition to the pipeline replacement, Columbia is proposing
construction of a pig launcher/receiver at existing Ninevah M&R Station
in Warren County, Virginia. A new M&R station would be built at
milepost 2.47 of the proposed pipeline within the VEPCO--Warren County
Power Station lot. At the Rockville Measuring Station, Columbia
proposes to construct an interconnect between its existing 26-inch-
diameter Line MB pipeline and Transcontinental Pipeline Corporations'
system. Construction and operation of the proposed modifications at the
existing Ninevah M&R Station, Loudoun and Lost River Compressor
Stations, and Rockville Measuring Station would take
[[Page 46286]]
place within the existing property boundaries of those facilities.
Columbia is also proposing to utilize four existing private access
roads and two new roads to gain access to the construction areas along
the pipeline route. Columbia proposes one temporary pipeyard/contractor
yard for the Project.
The EA Process
The National Environmental Policy Act (NEPA) requires that the
Commission take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\1\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this Notice of Intent, the Commission staff
requests public comments on the scope of the issues to address in the
EA. All comments received are considered during the preparation of the
EA. State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
---------------------------------------------------------------------------
\1\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and Soils;
Land Use;
Water Resources, Fisheries, and Wetlands;
Cultural Resources;
Vegetation and Wildlife;
Air Quality and Noise;
Endangered and Threatened Species;
Public Safety.
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to Federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission. To ensure your comments are
considered, please carefully follow the instructions in the public
participation section below.
With this NOI, we are asking Federal, state, and local agencies
with jurisdiction and/or special expertise with respect to
environmental issues to formally cooperate with us in the preparation
of the EA. These agencies may choose to participate once they have
evaluated the proposal relative to their responsibilities. Additional
agencies that would like to request cooperating agency status should
follow the instructions for filing comments provided under the Public
Participation section of this NOI.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Office(s), and to solicit
their views and those of other government agencies, interested Indian
tribes, and the public on the project's potential effects on historic
properties.\2\ We will define the project-specific Area of Potential
Effects (APE) in consultation with the SHPO(s) as the project is
further developed. On natural gas facility projects, the APE at a
minimum encompasses all areas subject to ground disturbance (examples
include construction right-of-way, contractor/pipe storage yards,
compressor stations, and access roads). Our EA for this project will
document our findings on the impacts on historic properties and
summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\2\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Vepco--Warren County Project. Your
comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. The more specific your comments, the more useful they will be.
To ensure that your comments are timely and properly recorded, please
send in your comments so that they will be received in Washington, DC
on or before August 25, 2011.
For your convenience, there are three methods in which you can use
to submit your comments to the Commission. In all instances please
reference the project docket number (CP11-490-000) with your
submission. The Commission encourages electronic filing of comments and
has dedicated eFiling expert staff available to assist you at 202-502-
8258 or efiling@ferc.gov.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. An eComment is an
easy method for interested persons to submit brief, text-only comments
on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. With eFiling, you
can provide comments in a variety of formats by attaching them as a
file with your submission. New eFiling users must first create an
account by clicking on ``eRegister.'' You will be asked to select the
type of filing you are making. A comment on a particular project is
considered a ``Comment on a Filing;'' or
(3) You may file a paper copy of your comments at the following
address:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas Branch 3,
PJ11.3.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own homes within distances defined in the
Commission's regulations of certain aboveground facilities.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(Appendix 2). If you do not return the Information Request, you will be
taken off the mailing list.
[[Page 46287]]
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor,'' which is an official party to the
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in a Commission proceeding by filing a request to
intervene. Instructions for becoming an intervenor are included in the
User's Guide under the ``e-filing'' link on the Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field (CP11-490). Be sure you have selected an appropriate date range.
For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202)502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: July 26, 2011.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2011-19471 Filed 8-1-11; 8:45 am]
BILLING CODE 6717-01-P