Notice of Availability of the Draft Environmental Impact Statement for the Gateway West 230/500 kV Transmission Line Project in Idaho, Nevada, and Wyoming and Prospective Draft Land Use Plan Amendments, 45609-45612 [2011-19094]

Download as PDF Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices mstockstill on DSK4VPTVN1PROD with NOTICES proposed Covered Species. However, the list of Covered Species may change as the planning process progresses; species may be added or removed as more is learned about the nature of Covered Activities and their impact on native species within the plan area. More information on Covered Species, including State-listed and unlisted species, is available on the Internet at https://www.drecp.org/covered species. Environmental Impact Statement Before deciding whether to issue the requested Federal incidental take permit, the Service will prepare a draft EIS as part of the joint EIS/EIR, in order to analyze the environmental impacts associated with potential adoption and implementation of the proposed DRECP as a HCP and NCCP. In the EIS component of the joint EIS/EIR, the Service will consider the following alternatives: (1) The proposed action, which includes the issuance of take authorizations consistent with the proposed DRECP under section 10(a)(1)(B) of the ESA; (2) no action (no Federal ESA permit issuance); and (3) a reasonable range of alternatives that address different scenarios of renewable energy development and species conservation on both Federal and nonFederal land. The EIS/EIR will include a detailed analysis of the impacts of the proposed action and alternatives. The range of alternatives to be considered and analyzed will represent varying levels of conservation and impacts, and may include variations in the scope of Covered Activities; variations in the locations, amount, and type of conservation; variations in permit duration; or a combination of these elements. The BLM may address other considerations in the EIS. In compliance with NEPA, the Service and BLM will be responsible for the scope and preparation of the EIS component of the joint EIS/EIR. The EIS/EIR will identify and analyze potentially significant direct, indirect, and cumulative impacts of the Service’s authorization of incidental take (permit issuance) and the implementation of the proposed DRECP on biological resources, land uses (including BLM, U.S. Department of Defense military operations, and Native American traditional land uses), utilities, air quality, water resources (including surface and groundwater supply and water quality), cultural resources, socioeconomics and environmental justice, outdoor recreation, visual resources, induced growth, climate change and greenhouse gases, and other environmental issues that could occur with implementation of the proposed VerDate Mar<15>2010 16:17 Jul 28, 2011 Jkt 223001 action and alternatives. The Service and the BLM will use all practicable means, consistent with NEPA and other essential considerations of national policy, to avoid or minimize significant effects of their actions upon the quality of the human environment. The Service and BLM have invited the National Park Service (NPS), Environmental Protection Agency (EPA), Department of Energy, and the Department of Defense to be cooperating Federal agencies in the preparation of the EIS, because the proposed project may have effects on lands and facilities under the jurisdictions of those agencies. To date, the NPS and EPA have requested and agreed to be cooperating agencies. The CDFG has requested and agreed to be a State cooperating agency. The Service, BLM, NPS, EPA, and CDFG agree that establishing a cooperating agency relationship will create a more streamlined and coordinated approach in developing this EIS. Reasonable Accommodation Persons needing reasonable accommodations to attend and participate in the public meeting should contact Ken Corey at (760) 431–9440 as soon as possible. To allow sufficient time to process requests, please call no later than 1 week before the public meeting. Information regarding this proposed action is available in alternative formats upon request. Public Comments Before including your address, phone number, e-mail address, or other personal identifying information in your comment, you should be aware that your entire comment—including your personal identifying information—may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information from public review, we cannot guarantee that we will be able to do so. Material the Service receives will be available for public inspection, by appointment, during normal business hours (Monday through Friday, 8 a.m. to 4:30 p.m.) at the Service’s Carlsbad address (see ADDRESSES). At the close of the public comment period, all written comments received by the Federal co-lead agencies will be posted on the Internet at https:// www.drecp.org/public scoping comments. Comments received by CEC in response to their notice of preparation under CEQA will also be posted on the Web site. PO 00000 Frm 00106 Fmt 4703 Sfmt 4703 45609 Authority: 40 CFR 1501.7. Tom Pogacnik, Deputy State Director, Natural Resources, California State Office, Bureau of Land Management, Sacramento, California. Dated: July 22, 2011. Alexandra Pitts, Deputy Regional Director, Pacific Southwest Region, U.S. Fish and Wildlife Service, Sacramento, California. [FR Doc. 2011–19175 Filed 7–28–11; 8:45 am] BILLING CODE 4310–55–P DEPARTMENT OF THE INTERIOR Bureau of Land Management DEPARTMENT OF AGRICULTURE Forest Service [LLWY920000/L51010000.ER0000/ LVRWK09K0990/241A; WYW–174598; IDI– 35849; NVN–089270] Notice of Availability of the Draft Environmental Impact Statement for the Gateway West 230/500 kV Transmission Line Project in Idaho, Nevada, and Wyoming and Prospective Draft Land Use Plan Amendments Bureau of Land Management, Interior; and U.S. Forest Service, Agriculture. ACTION: Notice of Availability. AGENCY: The Bureau of Land Management (BLM) and the U.S. Forest Service (USFS) announce the availability of the Gateway West Transmission Line Project DEIS and prospective draft Land Use Plan (LUP) Amendments. The DEIS analyzes the consequences of granting a right-of-way (ROW) to Idaho Power and Rocky Mountain Power for locating a 1,103mile-long electric transmission line from the proposed Windstar Substation near the Dave Johnston Power Plant at Glenrock, Wyoming, to the proposed Hemingway Substation near Melba, Idaho. The project is composed of 10 transmission line segments of 230 and 500 kilovolts (kV); each segment would carry up to 3,000 megawatts (MW). The requested ROW width would generally be 300 feet but could range from 125 to 350 feet, depending on the design variation and structure type. The proposed route generally follows existing transmission lines and Westwide Energy (WWE) corridors designated pursuant to Section 368 of the Energy Policy Act of 2005. Approximately 610 miles (55 percent) of the proposed route is located within or adjacent to designated corridors or existing transmission lines. SUMMARY: E:\FR\FM\29JYN1.SGM 29JYN1 mstockstill on DSK4VPTVN1PROD with NOTICES 45610 Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices Approximately 500 miles (46 percent) of the total proposed length traverses Federally administered land in Idaho and Wyoming. In Idaho, approximately 280 miles of the proposed transmission lines would cross public land administered by seven BLM Field Offices: Bruneau, Burley, Four Rivers, Jarbidge, Owyhee, Pocatello, and Shoshone. In Wyoming, approximately 220 miles of the proposed transmission lines would cross public land administered by four BLM Field Offices: Casper, Kemmerer, Rawlins, and Rock Springs. The proposed route crosses approximately 16 miles in two units of the National Forest System: 7 miles in the Douglas Ranger District of the Medicine Bow-Routt National Forest in Wyoming and 9 miles in the Montpelier Ranger District of the Caribou-Targhee National Forest in Idaho. In addition, the proposed route crosses approximately 5 miles of land administered by the Bureau of Reclamation. Alternative routes are proposed that would cross the Sawtooth National Forest in Idaho, the Fort Hall Indian Reservation, and the acquisition area of the Cokeville Meadows National Wildlife Refuge. One alternative route in Segment #7 extends 9.5 miles into Nevada with approximately 7 miles on public land administered by the Wells Field Office. This project includes prospective amendments of USFS Land and Resource Management Plans (Forest Plans) and BLM land use plans (Management Framework Plans and Resource Management Plans). By this notice, and the Notice of Intent to prepare an EIS filed in May 2008 (see below), BLM is complying with requirements in 43 Code of Federal Regulations (CFR) 1610.2(c) and the USFS is complying with 36 CFR 219.8 to notify the public of potential amendments to land use plans. The BLM and USFS are integrating the land use planning process with the National Environmental Policy Act (NEPA) analysis process for this project. Your input is important and will be considered in the environmental analysis process. All comment submissions must include the commenter’s name and street address. Comments including the names and addresses of the respondent will be available for public inspection at the locations listed below during their business hours (7:45 a.m. to 4:30 p.m.), Monday through Friday, except Federal holidays. Before including your address, phone number, e-mail address, or any other personal identifying information in your comment, be advised that your entire comment, including your VerDate Mar<15>2010 16:17 Jul 28, 2011 Jkt 223001 personal identifying information, may be publicly available at any time. While you may ask us in your comment to withhold from public review your personal identifying information, we cannot guarantee that we will be able to do so. DATES: The DEIS is now available for public review. The BLM and USFS request that comments be structured so that they are meaningful and alert the agencies to a reviewer’s position and contentions. In order to be considered in the Final EIS, written comments on the Draft EIS must be received within 90 days after EPA’s publication in the Federal Register of a Notice of Availability of this Draft EIS. The BLM and USFS will consider timely filed comments and respond to them in the final EIS. All public meetings or other involvement activities for the Gateway West Transmission Line Project will be announced to the public by the BLM at least 15 days in advance through public notices, media news releases, Web site announcements, or mailings. ADDRESSES: Copies of the DEIS have been sent to affected Federal, State, and local Governments, public libraries in the project area, and to interested parties that previously requested a copy. The DEIS and supporting documents will be available electronically on the following Web site: https:// www.wy.blm.gov/nepa/cfodocs/ gateway_west/. Copies of the DEIS are available for public inspection during normal business hours at the following locations: • Bureau of Land Management, Wyoming State Office, Public Room, 5353 Yellowstone Road, Cheyenne, Wyoming 82009; • Bureau of Land Management, Casper Field Office, 2987 Prospector Drive, Casper, Wyoming 82604; • Bureau of Land Management, Rawlins Field Office, 1300 North Third Street, Rawlins, Wyoming 82301; • Bureau of Land Management, Rock Springs Field Office, 280 Highway 191 North, Rock Springs, Wyoming 82901; • Bureau of Land Management, Kemmerer Field Office, 312 Highway 189 North, Kemmerer, Wyoming 83101; • Bureau of Land Management, Nevada State Office, Public Room, 1340 Financial Boulevard, Reno, Nevada 89502; • Bureau of Land Management, Wells Field Office, 3900 East Idaho Street, Elko, Nevada 89801; • Bureau of Land Management, Idaho State Office, Public Room, 1387 South Vinnell Way, Boise, Idaho 83709; • Bureau of Land Management, Pocatello Field Office, 4350 Cliffs Drive, Pocatello, Idaho 83204; PO 00000 Frm 00107 Fmt 4703 Sfmt 4703 • Bureau of Land Management, Idaho Falls District Office, 1405 Hollipark Drive Idaho Falls, Idaho 83401; • Bureau of Land Management, Burley Field Office, 15 East 200 South, Burley, Idaho 83318; • Bureau of Land Management, Twin Falls District Office, 2536 Kimberly Road, Twin Falls, Idaho 83301; • Bureau of Land Management, Shoshone Field Office, 400 West F Street, Shoshone, Idaho 83325; • Bureau of Land Management, Boise District Office, 3948 Development Avenue, Boise, Idaho 83705; • Bureau of Land Management, Owyhee Field Office, 20 First Avenue West, Marsing, Idaho 83639; • U.S. Department of Agriculture, Medicine Bow-Routt National Forest, 2468 Jackson Street, Laramie, WY 82070–6535; • U.S. Department of Agriculture, Medicine Bow-Routt National Forest, Douglas Ranger District, 2250 East Richards Street, Douglas, WY 82633– 8922; • U.S. Department of Agriculture, Caribou-Targhee National Forest, Montpelier Ranger District, 322 North 4th Street, Montpelier, Idaho 83254; and • U.S. Department of Agriculture, Sawtooth National Forest, Minidoka Ranger District, 3650 Overland Avenue, Burley, Idaho 83318. A limited number of copies of the document will be available as supplies last. To request a copy, contact Walt George, Project Manager, Wyoming State Office, P.O. Box 20879, Cheyenne, Wyoming 82003. Written comments may be submitted by the following methods: • Web site: https://www.wy.blm.gov/ nepa/cfodocs/gateway_west. • E-mail: Gateway_West_WYMail@blm.gov. • Mail: Bureau of Land Management, Gateway West Project, P.O. Box 20879, Cheyenne, Wyoming 82003. • Courier or Hand Deliver: Bureau of Land Management, Gateway West Project, 5353 Yellowstone Road, Cheyenne, Wyoming 82009. FOR FURTHER INFORMATION CONTACT: Walt George, Project Manager, c/o Bureau of Land Management, Wyoming State Office, P.O. Box 20879, Cheyenne, Wyoming 82003 or by telephone at (307) 775–6116. Any persons wishing to be added to a mailing list of interested parties may write or call the Project Manager, at this address or phone number. In May 2007, Idaho Power and Rocky Mountain Power (the Proponents) submitted a ROW application to the BLM requesting SUPPLEMENTARY INFORMATION: E:\FR\FM\29JYN1.SGM 29JYN1 mstockstill on DSK4VPTVN1PROD with NOTICES Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices authorization to construct, operate, maintain, and decommission electric transmission lines on public lands. The application was revised in October 2007, August 2008, May 2009, and January 2010 to reflect changes to the proposed action. The Proponents’ objective for the project is to improve the reliability and efficiency of both utilities’ systems and address congestion problems with the western electrical grid. The project is needed to meet projected load growth in the Proponents’ Service Areas. The project would also tap the developing renewable energy market, especially wind energy, in Idaho and Wyoming and will aid in delivering that energy throughout the region. The BLM and USFS’s purpose and need for the EIS is so that the agencies may respond to the Proponents’ application. On May 16, 2008, the BLM published in the Federal Register (FR Vol. 73, No. 96, pages 28425–28426) its Notice of Intent to prepare an EIS pursuant to NEPA, as required by Federal regulations promulgated for the Federal Land Policy and Management Act (FLPMA) found at 43 CFR Part 2800. The BLM is the lead Federal agency for the NEPA analysis process and preparation of the EIS. Cooperating agencies include: the USFS, National Park Service, U.S. Fish and Wildlife Service, Bureau of Indian Affairs, and U.S. Army Corps of Engineers; the States of Idaho and Wyoming; the Idaho Army National Guard; Cassia, Power, and Twin Falls Counties, Idaho; Elko County, Nevada; Lincoln, Sweetwater, and Carbon Counties, Wyoming; the Medicine Bow and SaratogaEncampment-Rawlins Conservation Districts in Wyoming; and the City of Kuna, Idaho. To allow the public an opportunity to review the proposal and project information, the BLM held public meetings in June 2008 in: Twin Falls, Murphy, Pocatello, Boise, and Montpelier, Idaho; and Casper, Rawlins, Rock Springs, and Kemmerer, Wyoming. Issues and potential impacts to specific resources were identified during scoping and the course of the NEPA process. The following project issues were identified in the scoping process: • Siting on private lands versus public lands, • Land use conflicts and consistency with land use plans, • Electric grid reliability and separation distances of transmission lines, • Effects on wildlife habitat, plants, and animals including threatened, VerDate Mar<15>2010 16:17 Jul 28, 2011 Jkt 223001 endangered, and sensitive species (especially sage grouse), • Effects to visual resources and existing view sheds, • Effects to National Historic Trails and their view sheds, • Effects to Native American traditional cultural properties and respected places, • Effects to paleontological resources in southwest Wyoming, • Avoiding sensitive areas such as National Monuments and Wildlife Refuges, military operating areas, National Conservation Areas, Areas of Critical Environmental Concern, and State Parks, • Effects to soils and water from surface disturbing activities, • Effect of the project on local and regional socioeconomic conditions, and • Management of invasive plant species and ensuring effective reclamation. In response to scoping comments, Idaho Power and Rocky Mountain Power made route changes in Segments 1, 2, 4, 5, 7, 8, and 9 of their original proposal. The proposed action analyzed in the DEIS reflects these revisions to the route. In addition to the proposed action, the DEIS considers the No Action alternative, a structure variation, a phased construction alternative, and 41 route segment alternatives in detail. Other system alternatives and route variations were considered but eliminated from detailed study. Department of the Interior regulations (43 CFR 46.425) give agencies flexibility when identifying preferred alternatives in the DEIS, stating that: ‘‘* * * the draft environmental impact statement should identify the bureau’s preferred alternatives or alternatives [and] the final environmental impact statement must identify the bureau’s preferred alternative.’’ Because substantial differences exist, in some project segments, among cooperating agencies on the preferred route alternative, and the full range of public input on route alternatives will not be available to the BLM until after the DEIS public comment period, the BLM is deferring identification of its preferred route alternative until the Final EIS. The DEIS analyzes the potential environmental consequences of granting a ROW to Idaho Power and Rocky Mountain Power to construct an approximately 1,100-mile transmission line from Glenrock, Wyoming, to its terminus at facilities near Melba, Idaho. The Proposed Route consists of 10 segments: Segment 1 consists of three transmission lines designated 1E, 1W(a), and 1W(c)—between the planned PO 00000 Frm 00108 Fmt 4703 Sfmt 4703 45611 Windstar Substation near the Dave Johnston Power Plant at Glenrock, Wyoming, and the planned Aeolus Substation near Hanna, Wyoming. Segment 1E would include construction and operation of a 100 mile-long, singlecircuit 230-kV transmission line across lands without existing major linear ROWs or designated corridors. Three alternative routes in Segment 1E were considered in detail, including one that parallels (but is outside of) an existing utility corridor for most of its length. Segment 1W is composed of two transmission lines: A new single-circuit 230-kV transmission line (1W(a)) that parallels an existing transmission line and reconstruction of the existing 230kV transmission line (1W(c)). These two lines are approximately 75 miles long and are generally within a WWE corridor. One alternative route for Segment 1W is considered in detail. Segment 2 consists of a 97-mile, double-circuit 500-kV transmission line between the Aeolus Substation and the Creston Substation near Wamsutter, Wyoming, which generally is within a WWE corridor. Three alternative route segments were considered in detail, including one that parallels but is outside of an existing utility corridor for approximately 28 miles. Segment 3 consists of a 57-mile, double-circuit 230/500-kV line from the proposed Creston Substation south of Wamsutter, Wyoming, to the proposed Anticline Substation near the Jim Bridger Power Plant, located approximately 30 miles east of Rock Springs, Wyoming. Approximately 17.8 miles are within or parallel to a WWE corridor. No other alternative routes were considered in detail for this segment. Segment 4 consists of a 203-mile, double-circuit 500-kV line between the Anticline Substation, near the Jim Bridger Power Plant, and the Populus Substation near Interstate 15 in southern Bannock County, Idaho. This segment generally is within an existing transmission line corridor. Six alternative route segments were considered in detail. Segment 5 consists of a 55-mile, single-circuit 500-kV line between the planned Populus Substation and the existing Borah Substation in Power County, Idaho. Five alternative route segments were considered in detail. Segment 6 consists of increasing the voltage capacity of an existing line from the Borah Substation to the Midpoint Substation located approximately 9 miles south of Shoshone, Idaho. The voltage would be increased to 500 kV on the existing Midpoint to Kinport 345-kV transmission line. Five new towers E:\FR\FM\29JYN1.SGM 29JYN1 mstockstill on DSK4VPTVN1PROD with NOTICES 45612 Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices would be required. No new route alternatives were considered in detail because this is a rebuild of an existing line. Segment 7 consists of a 118-mile, single-circuit 500-kV transmission line between the Populus Substation and the proposed Cedar Hill Substation near the county line between Cassia and Twin Falls Counties in Idaho. Ten alternative route segments were considered in detail, including two that cross the Sawtooth National Forest, one of which crosses into Nevada for approximately 9 miles. Segment 8 consists of a 131-mile, single-circuit 500-kV transmission line between the Midpoint Substation and the Hemingway Substation, located approximately 30 miles southwest of Boise, Idaho. Five alternative route segments were considered in detail. Segment 9 consists of a 162-mile, single-circuit 500-kV transmission line between the proposed Cedar Hill Substation and the planned Hemingway Substation near Murphy, Idaho. Eight alternative route segments were considered in detail. Segment 10 consists of a 34-mile, single-circuit 500-kV transmission line between the Midpoint Substation, located approximately 9 miles south of Shoshone, and Cedar Hill Substation near the county line between Cassia and Twin Falls Counties in Idaho. No other alternative routes were considered in detail for this segment. The BLM, USFS, Proponents, and Cooperating Agencies worked together to develop routes that would conform to existing Federal land use plans. However, this objective was not reached for many of the routes analyzed in the DEIS. Unlike the regulations at 43 CFR 46.425 that allow the BLM to defer identification of an agency preferred route alternative until the Final EIS, the BLM planning regulations at 43 CFR 1610.4–7 require identification of the BLM’s Preferred Plan Amendment in the DEIS. The BLM has identified draft plan amendments below for each situation of nonconformance that would bring the Proposed or Alternative Route into conformance with the respective land use plan. Each of these plan amendments is the BLM’s preferred plan amendment. The specific land use plan amendments actually needed will be determined by the final agency preferred route selected. Therefore, some of the following prospective plan amendments may not need to be implemented. The BLM will identify those plan amendments it intends to implement (as Proposed Plan Amendments), along with its preferred route, in the Final EIS. VerDate Mar<15>2010 16:17 Jul 28, 2011 Jkt 223001 The following land-use plan amendments may be needed to bring the Gateway West Transmission Line Project into conformance with the applicable Resource Management Plans (RMPs) and Management Framework Plans (MFPs) for BLM-managed lands and Land and Resource Management Plans (Forest Plans) for National Forest System lands crossed by the project, depending on project approval and on the final route selected. All prospective plan amendments will comply with applicable Federal laws and regulations, be analyzed in the Gateway West EIS, and apply only to Federal lands and mineral estate administered by the BLM or USFS. Casper RMP: An amendment may be needed for visual resource management. Rawlins RMP: An amendment may be needed for visual resource management. Green River RMP: Amendments may be needed for visual resource management, sage-grouse, and raptor management. Kemmerer RMP: Amendments may be needed for management of visual resources, historic trails, heritage resources, sage-grouse, the Rock Creek/ Tunp Special Designation Area, and recreation. Malad MFP: Amendments may be needed for management of visual resources and to designate a new utility corridor. Bennett Hills/Timmerman Hills MFP: An amendment may be needed for visual resource management. Cassia RMP: Amendments may be needed for management of visual resources, historic trails, and to designate a new utility corridor. Twin Falls MFP: An amendment may be needed for visual resource management and to allow a linear facility outside of existing corridors. Jarbidge RMP: Amendments may be needed for management of visual resources, paleontological sites, historic trails, to adjust management objectives in an ACEC, and to designate a new utility corridor. Kuna MFP: An amendment may be needed for a historic site and to designate a new utility corridor. Morley Nelson Snake River Birds of Prey National Conservation Area RMP: Amendments may be needed for management of visual resources, nonmotorized area management, to adjust management objectives in a Special Recreation Management Area, sensitive plant habitat, and to designate a new utility corridor. Bruneau MFP: An amendment may be needed for visual resource management. PO 00000 Frm 00109 Fmt 4703 Sfmt 4703 Wells RMP: An amendment may be needed to allow a linear facility outside of identified planning corridors. Medicine Bow Forest Plan: An amendment may be needed for management of visual resources, goshawk and amphibian habitat, recreation, and to change the management prescription for any area crossed by new transmission lines not within the WWE corridor. Caribou Forest Plan: An amendment may be needed to designate a new utility corridor. Sawtooth Forest Plan: An amendment may be needed for management of visual resources and recreation. The DEIS analyzes the environmental consequences of the No Action alternative, the proposed action, segment and design alternatives, and land use plan amendments. For this EIS, the No Action alternative means that the Idaho Power and Rocky Mountain Power ROW application for the Gateway West project would be denied by the BLM. The BLM will utilize and coordinate the NEPA commenting process to satisfy the public involvement process for Section 106 of the National Historic Preservation Act (16 U.S.C. 470f), as provided for in 36 CFR 800.2(d)(3). Ongoing Native American Tribal consultations will continue to be conducted in accordance with policy, and Tribal concerns, including impacts on Indian trust assets, will be given due consideration. Federal, State, and local agencies, along with other stakeholders that may be interested or affected by the BLM’s decision on this project, are invited to participate. Brent L. Larson, Forest Supervisor, Caribou-Targhee National Forest. Donald A. Simpson, Wyoming State Director. [FR Doc. 2011–19094 Filed 7–28–11; 8:45 am] BILLING CODE 4310–22–P DEPARTMENT OF THE INTERIOR Bureau of Land Management [LLWYP00000–L51100000–GA0000– LVEMK09CK380, WYW172684] Notice of Availability of the Buckskin Mine Hay Creek II Coal Lease-byApplication Final Environmental Impact Statement, Wyoming Bureau of Land Management, Interior. ACTION: Notice of Availability. AGENCY: In accordance with the National Environmental Policy Act of SUMMARY: E:\FR\FM\29JYN1.SGM 29JYN1

Agencies

[Federal Register Volume 76, Number 146 (Friday, July 29, 2011)]
[Notices]
[Pages 45609-45612]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-19094]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

DEPARTMENT OF AGRICULTURE

Forest Service

[LLWY920000/L51010000.ER0000/LVRWK09K0990/241A; WYW-174598; IDI-35849; 
NVN-089270]


Notice of Availability of the Draft Environmental Impact 
Statement for the Gateway West 230/500 kV Transmission Line Project in 
Idaho, Nevada, and Wyoming and Prospective Draft Land Use Plan 
Amendments

AGENCY: Bureau of Land Management, Interior; and U.S. Forest Service, 
Agriculture.

ACTION: Notice of Availability.

-----------------------------------------------------------------------

SUMMARY: The Bureau of Land Management (BLM) and the U.S. Forest 
Service (USFS) announce the availability of the Gateway West 
Transmission Line Project DEIS and prospective draft Land Use Plan 
(LUP) Amendments. The DEIS analyzes the consequences of granting a 
right-of-way (ROW) to Idaho Power and Rocky Mountain Power for locating 
a 1,103-mile-long electric transmission line from the proposed Windstar 
Substation near the Dave Johnston Power Plant at Glenrock, Wyoming, to 
the proposed Hemingway Substation near Melba, Idaho. The project is 
composed of 10 transmission line segments of 230 and 500 kilovolts 
(kV); each segment would carry up to 3,000 megawatts (MW).
    The requested ROW width would generally be 300 feet but could range 
from 125 to 350 feet, depending on the design variation and structure 
type. The proposed route generally follows existing transmission lines 
and West-wide Energy (WWE) corridors designated pursuant to Section 368 
of the Energy Policy Act of 2005. Approximately 610 miles (55 percent) 
of the proposed route is located within or adjacent to designated 
corridors or existing transmission lines.

[[Page 45610]]

    Approximately 500 miles (46 percent) of the total proposed length 
traverses Federally administered land in Idaho and Wyoming. In Idaho, 
approximately 280 miles of the proposed transmission lines would cross 
public land administered by seven BLM Field Offices: Bruneau, Burley, 
Four Rivers, Jarbidge, Owyhee, Pocatello, and Shoshone. In Wyoming, 
approximately 220 miles of the proposed transmission lines would cross 
public land administered by four BLM Field Offices: Casper, Kemmerer, 
Rawlins, and Rock Springs. The proposed route crosses approximately 16 
miles in two units of the National Forest System: 7 miles in the 
Douglas Ranger District of the Medicine Bow-Routt National Forest in 
Wyoming and 9 miles in the Montpelier Ranger District of the Caribou-
Targhee National Forest in Idaho. In addition, the proposed route 
crosses approximately 5 miles of land administered by the Bureau of 
Reclamation. Alternative routes are proposed that would cross the 
Sawtooth National Forest in Idaho, the Fort Hall Indian Reservation, 
and the acquisition area of the Cokeville Meadows National Wildlife 
Refuge. One alternative route in Segment 7 extends 9.5 miles 
into Nevada with approximately 7 miles on public land administered by 
the Wells Field Office.
    This project includes prospective amendments of USFS Land and 
Resource Management Plans (Forest Plans) and BLM land use plans 
(Management Framework Plans and Resource Management Plans). By this 
notice, and the Notice of Intent to prepare an EIS filed in May 2008 
(see below), BLM is complying with requirements in 43 Code of Federal 
Regulations (CFR) 1610.2(c) and the USFS is complying with 36 CFR 219.8 
to notify the public of potential amendments to land use plans. The BLM 
and USFS are integrating the land use planning process with the 
National Environmental Policy Act (NEPA) analysis process for this 
project.
    Your input is important and will be considered in the environmental 
analysis process. All comment submissions must include the commenter's 
name and street address. Comments including the names and addresses of 
the respondent will be available for public inspection at the locations 
listed below during their business hours (7:45 a.m. to 4:30 p.m.), 
Monday through Friday, except Federal holidays. Before including your 
address, phone number, e-mail address, or any other personal 
identifying information in your comment, be advised that your entire 
comment, including your personal identifying information, may be 
publicly available at any time. While you may ask us in your comment to 
withhold from public review your personal identifying information, we 
cannot guarantee that we will be able to do so.

DATES: The DEIS is now available for public review. The BLM and USFS 
request that comments be structured so that they are meaningful and 
alert the agencies to a reviewer's position and contentions. In order 
to be considered in the Final EIS, written comments on the Draft EIS 
must be received within 90 days after EPA's publication in the Federal 
Register of a Notice of Availability of this Draft EIS. The BLM and 
USFS will consider timely filed comments and respond to them in the 
final EIS. All public meetings or other involvement activities for the 
Gateway West Transmission Line Project will be announced to the public 
by the BLM at least 15 days in advance through public notices, media 
news releases, Web site announcements, or mailings.

ADDRESSES: Copies of the DEIS have been sent to affected Federal, 
State, and local Governments, public libraries in the project area, and 
to interested parties that previously requested a copy. The DEIS and 
supporting documents will be available electronically on the following 
Web site: https://www.wy.blm.gov/nepa/cfodocs/gateway_west/. Copies of 
the DEIS are available for public inspection during normal business 
hours at the following locations:
     Bureau of Land Management, Wyoming State Office, Public 
Room, 5353 Yellowstone Road, Cheyenne, Wyoming 82009;
     Bureau of Land Management, Casper Field Office, 2987 
Prospector Drive, Casper, Wyoming 82604;
     Bureau of Land Management, Rawlins Field Office, 1300 
North Third Street, Rawlins, Wyoming 82301;
     Bureau of Land Management, Rock Springs Field Office, 280 
Highway 191 North, Rock Springs, Wyoming 82901;
     Bureau of Land Management, Kemmerer Field Office, 312 
Highway 189 North, Kemmerer, Wyoming 83101;
     Bureau of Land Management, Nevada State Office, Public 
Room, 1340 Financial Boulevard, Reno, Nevada 89502;
     Bureau of Land Management, Wells Field Office, 3900 East 
Idaho Street, Elko, Nevada 89801;
     Bureau of Land Management, Idaho State Office, Public 
Room, 1387 South Vinnell Way, Boise, Idaho 83709;
     Bureau of Land Management, Pocatello Field Office, 4350 
Cliffs Drive, Pocatello, Idaho 83204;
     Bureau of Land Management, Idaho Falls District Office, 
1405 Hollipark Drive Idaho Falls, Idaho 83401;
     Bureau of Land Management, Burley Field Office, 15 East 
200 South, Burley, Idaho 83318;
     Bureau of Land Management, Twin Falls District Office, 
2536 Kimberly Road, Twin Falls, Idaho 83301;
     Bureau of Land Management, Shoshone Field Office, 400 West 
F Street, Shoshone, Idaho 83325;
     Bureau of Land Management, Boise District Office, 3948 
Development Avenue, Boise, Idaho 83705;
     Bureau of Land Management, Owyhee Field Office, 20 First 
Avenue West, Marsing, Idaho 83639;
     U.S. Department of Agriculture, Medicine Bow-Routt 
National Forest, 2468 Jackson Street, Laramie, WY 82070-6535;
     U.S. Department of Agriculture, Medicine Bow-Routt 
National Forest, Douglas Ranger District, 2250 East Richards Street, 
Douglas, WY 82633-8922;
     U.S. Department of Agriculture, Caribou-Targhee National 
Forest, Montpelier Ranger District, 322 North 4th Street, Montpelier, 
Idaho 83254; and
     U.S. Department of Agriculture, Sawtooth National Forest, 
Minidoka Ranger District, 3650 Overland Avenue, Burley, Idaho 83318.
    A limited number of copies of the document will be available as 
supplies last. To request a copy, contact Walt George, Project Manager, 
Wyoming State Office, P.O. Box 20879, Cheyenne, Wyoming 82003.
    Written comments may be submitted by the following methods:
     Web site: https://www.wy.blm.gov/nepa/cfodocs/gateway_west.
     E-mail: Gateway_West_WYMail@blm.gov.
     Mail: Bureau of Land Management, Gateway West Project, 
P.O. Box 20879, Cheyenne, Wyoming 82003.
     Courier or Hand Deliver: Bureau of Land Management, 
Gateway West Project, 5353 Yellowstone Road, Cheyenne, Wyoming 82009.

FOR FURTHER INFORMATION CONTACT: Walt George, Project Manager, c/o 
Bureau of Land Management, Wyoming State Office, P.O. Box 20879, 
Cheyenne, Wyoming 82003 or by telephone at (307) 775-6116. Any persons 
wishing to be added to a mailing list of interested parties may write 
or call the Project Manager, at this address or phone number.

SUPPLEMENTARY INFORMATION: In May 2007, Idaho Power and Rocky Mountain 
Power (the Proponents) submitted a ROW application to the BLM 
requesting

[[Page 45611]]

authorization to construct, operate, maintain, and decommission 
electric transmission lines on public lands. The application was 
revised in October 2007, August 2008, May 2009, and January 2010 to 
reflect changes to the proposed action. The Proponents' objective for 
the project is to improve the reliability and efficiency of both 
utilities' systems and address congestion problems with the western 
electrical grid. The project is needed to meet projected load growth in 
the Proponents' Service Areas. The project would also tap the 
developing renewable energy market, especially wind energy, in Idaho 
and Wyoming and will aid in delivering that energy throughout the 
region. The BLM and USFS's purpose and need for the EIS is so that the 
agencies may respond to the Proponents' application.
    On May 16, 2008, the BLM published in the Federal Register (FR Vol. 
73, No. 96, pages 28425-28426) its Notice of Intent to prepare an EIS 
pursuant to NEPA, as required by Federal regulations promulgated for 
the Federal Land Policy and Management Act (FLPMA) found at 43 CFR Part 
2800. The BLM is the lead Federal agency for the NEPA analysis process 
and preparation of the EIS. Cooperating agencies include: the USFS, 
National Park Service, U.S. Fish and Wildlife Service, Bureau of Indian 
Affairs, and U.S. Army Corps of Engineers; the States of Idaho and 
Wyoming; the Idaho Army National Guard; Cassia, Power, and Twin Falls 
Counties, Idaho; Elko County, Nevada; Lincoln, Sweetwater, and Carbon 
Counties, Wyoming; the Medicine Bow and Saratoga-Encampment-Rawlins 
Conservation Districts in Wyoming; and the City of Kuna, Idaho.
    To allow the public an opportunity to review the proposal and 
project information, the BLM held public meetings in June 2008 in: Twin 
Falls, Murphy, Pocatello, Boise, and Montpelier, Idaho; and Casper, 
Rawlins, Rock Springs, and Kemmerer, Wyoming. Issues and potential 
impacts to specific resources were identified during scoping and the 
course of the NEPA process.
    The following project issues were identified in the scoping 
process:
     Siting on private lands versus public lands,
     Land use conflicts and consistency with land use plans,
     Electric grid reliability and separation distances of 
transmission lines,
     Effects on wildlife habitat, plants, and animals including 
threatened, endangered, and sensitive species (especially sage grouse),
     Effects to visual resources and existing view sheds,
     Effects to National Historic Trails and their view sheds,
     Effects to Native American traditional cultural properties 
and respected places,
     Effects to paleontological resources in southwest Wyoming,
     Avoiding sensitive areas such as National Monuments and 
Wildlife Refuges, military operating areas, National Conservation 
Areas, Areas of Critical Environmental Concern, and State Parks,
     Effects to soils and water from surface disturbing 
activities,
     Effect of the project on local and regional socioeconomic 
conditions, and
     Management of invasive plant species and ensuring 
effective reclamation.
    In response to scoping comments, Idaho Power and Rocky Mountain 
Power made route changes in Segments 1, 2, 4, 5, 7, 8, and 9 of their 
original proposal. The proposed action analyzed in the DEIS reflects 
these revisions to the route. In addition to the proposed action, the 
DEIS considers the No Action alternative, a structure variation, a 
phased construction alternative, and 41 route segment alternatives in 
detail. Other system alternatives and route variations were considered 
but eliminated from detailed study. Department of the Interior 
regulations (43 CFR 46.425) give agencies flexibility when identifying 
preferred alternatives in the DEIS, stating that: ``* * * the draft 
environmental impact statement should identify the bureau's preferred 
alternatives or alternatives [and] the final environmental impact 
statement must identify the bureau's preferred alternative.'' Because 
substantial differences exist, in some project segments, among 
cooperating agencies on the preferred route alternative, and the full 
range of public input on route alternatives will not be available to 
the BLM until after the DEIS public comment period, the BLM is 
deferring identification of its preferred route alternative until the 
Final EIS.
    The DEIS analyzes the potential environmental consequences of 
granting a ROW to Idaho Power and Rocky Mountain Power to construct an 
approximately 1,100-mile transmission line from Glenrock, Wyoming, to 
its terminus at facilities near Melba, Idaho. The Proposed Route 
consists of 10 segments:
    Segment 1 consists of three transmission lines designated 1E, 
1W(a), and 1W(c)--between the planned Windstar Substation near the Dave 
Johnston Power Plant at Glenrock, Wyoming, and the planned Aeolus 
Substation near Hanna, Wyoming. Segment 1E would include construction 
and operation of a 100 mile-long, single-circuit 230-kV transmission 
line across lands without existing major linear ROWs or designated 
corridors. Three alternative routes in Segment 1E were considered in 
detail, including one that parallels (but is outside of) an existing 
utility corridor for most of its length. Segment 1W is composed of two 
transmission lines: A new single-circuit 230-kV transmission line 
(1W(a)) that parallels an existing transmission line and reconstruction 
of the existing 230-kV transmission line (1W(c)). These two lines are 
approximately 75 miles long and are generally within a WWE corridor. 
One alternative route for Segment 1W is considered in detail.
    Segment 2 consists of a 97-mile, double-circuit 500-kV transmission 
line between the Aeolus Substation and the Creston Substation near 
Wamsutter, Wyoming, which generally is within a WWE corridor. Three 
alternative route segments were considered in detail, including one 
that parallels but is outside of an existing utility corridor for 
approximately 28 miles.
    Segment 3 consists of a 57-mile, double-circuit 230/500-kV line 
from the proposed Creston Substation south of Wamsutter, Wyoming, to 
the proposed Anticline Substation near the Jim Bridger Power Plant, 
located approximately 30 miles east of Rock Springs, Wyoming. 
Approximately 17.8 miles are within or parallel to a WWE corridor. No 
other alternative routes were considered in detail for this segment.
    Segment 4 consists of a 203-mile, double-circuit 500-kV line 
between the Anticline Substation, near the Jim Bridger Power Plant, and 
the Populus Substation near Interstate 15 in southern Bannock County, 
Idaho. This segment generally is within an existing transmission line 
corridor. Six alternative route segments were considered in detail.
    Segment 5 consists of a 55-mile, single-circuit 500-kV line between 
the planned Populus Substation and the existing Borah Substation in 
Power County, Idaho. Five alternative route segments were considered in 
detail.
    Segment 6 consists of increasing the voltage capacity of an 
existing line from the Borah Substation to the Midpoint Substation 
located approximately 9 miles south of Shoshone, Idaho. The voltage 
would be increased to 500 kV on the existing Midpoint to Kinport 345-kV 
transmission line. Five new towers

[[Page 45612]]

would be required. No new route alternatives were considered in detail 
because this is a rebuild of an existing line.
    Segment 7 consists of a 118-mile, single-circuit 500-kV 
transmission line between the Populus Substation and the proposed Cedar 
Hill Substation near the county line between Cassia and Twin Falls 
Counties in Idaho. Ten alternative route segments were considered in 
detail, including two that cross the Sawtooth National Forest, one of 
which crosses into Nevada for approximately 9 miles.
    Segment 8 consists of a 131-mile, single-circuit 500-kV 
transmission line between the Midpoint Substation and the Hemingway 
Substation, located approximately 30 miles southwest of Boise, Idaho. 
Five alternative route segments were considered in detail.
    Segment 9 consists of a 162-mile, single-circuit 500-kV 
transmission line between the proposed Cedar Hill Substation and the 
planned Hemingway Substation near Murphy, Idaho. Eight alternative 
route segments were considered in detail.
    Segment 10 consists of a 34-mile, single-circuit 500-kV 
transmission line between the Midpoint Substation, located 
approximately 9 miles south of Shoshone, and Cedar Hill Substation near 
the county line between Cassia and Twin Falls Counties in Idaho. No 
other alternative routes were considered in detail for this segment.
    The BLM, USFS, Proponents, and Cooperating Agencies worked together 
to develop routes that would conform to existing Federal land use 
plans. However, this objective was not reached for many of the routes 
analyzed in the DEIS. Unlike the regulations at 43 CFR 46.425 that 
allow the BLM to defer identification of an agency preferred route 
alternative until the Final EIS, the BLM planning regulations at 43 CFR 
1610.4-7 require identification of the BLM's Preferred Plan Amendment 
in the DEIS. The BLM has identified draft plan amendments below for 
each situation of nonconformance that would bring the Proposed or 
Alternative Route into conformance with the respective land use plan. 
Each of these plan amendments is the BLM's preferred plan amendment. 
The specific land use plan amendments actually needed will be 
determined by the final agency preferred route selected. Therefore, 
some of the following prospective plan amendments may not need to be 
implemented. The BLM will identify those plan amendments it intends to 
implement (as Proposed Plan Amendments), along with its preferred 
route, in the Final EIS.
    The following land-use plan amendments may be needed to bring the 
Gateway West Transmission Line Project into conformance with the 
applicable Resource Management Plans (RMPs) and Management Framework 
Plans (MFPs) for BLM-managed lands and Land and Resource Management 
Plans (Forest Plans) for National Forest System lands crossed by the 
project, depending on project approval and on the final route selected. 
All prospective plan amendments will comply with applicable Federal 
laws and regulations, be analyzed in the Gateway West EIS, and apply 
only to Federal lands and mineral estate administered by the BLM or 
USFS.
    Casper RMP: An amendment may be needed for visual resource 
management.
    Rawlins RMP: An amendment may be needed for visual resource 
management.
    Green River RMP: Amendments may be needed for visual resource 
management, sage-grouse, and raptor management.
    Kemmerer RMP: Amendments may be needed for management of visual 
resources, historic trails, heritage resources, sage-grouse, the Rock 
Creek/Tunp Special Designation Area, and recreation.
    Malad MFP: Amendments may be needed for management of visual 
resources and to designate a new utility corridor.
    Bennett Hills/Timmerman Hills MFP: An amendment may be needed for 
visual resource management.
    Cassia RMP: Amendments may be needed for management of visual 
resources, historic trails, and to designate a new utility corridor.
    Twin Falls MFP: An amendment may be needed for visual resource 
management and to allow a linear facility outside of existing 
corridors.
    Jarbidge RMP: Amendments may be needed for management of visual 
resources, paleontological sites, historic trails, to adjust management 
objectives in an ACEC, and to designate a new utility corridor.
    Kuna MFP: An amendment may be needed for a historic site and to 
designate a new utility corridor.
    Morley Nelson Snake River Birds of Prey National Conservation Area 
RMP: Amendments may be needed for management of visual resources, non-
motorized area management, to adjust management objectives in a Special 
Recreation Management Area, sensitive plant habitat, and to designate a 
new utility corridor.
    Bruneau MFP: An amendment may be needed for visual resource 
management.
    Wells RMP: An amendment may be needed to allow a linear facility 
outside of identified planning corridors.
    Medicine Bow Forest Plan: An amendment may be needed for management 
of visual resources, goshawk and amphibian habitat, recreation, and to 
change the management prescription for any area crossed by new 
transmission lines not within the WWE corridor.
    Caribou Forest Plan: An amendment may be needed to designate a new 
utility corridor.
    Sawtooth Forest Plan: An amendment may be needed for management of 
visual resources and recreation.
    The DEIS analyzes the environmental consequences of the No Action 
alternative, the proposed action, segment and design alternatives, and 
land use plan amendments. For this EIS, the No Action alternative means 
that the Idaho Power and Rocky Mountain Power ROW application for the 
Gateway West project would be denied by the BLM. The BLM will utilize 
and coordinate the NEPA commenting process to satisfy the public 
involvement process for Section 106 of the National Historic 
Preservation Act (16 U.S.C. 470f), as provided for in 36 CFR 
800.2(d)(3). Ongoing Native American Tribal consultations will continue 
to be conducted in accordance with policy, and Tribal concerns, 
including impacts on Indian trust assets, will be given due 
consideration. Federal, State, and local agencies, along with other 
stakeholders that may be interested or affected by the BLM's decision 
on this project, are invited to participate.

Brent L. Larson,
Forest Supervisor, Caribou-Targhee National Forest.
Donald A. Simpson,
Wyoming State Director.
[FR Doc. 2011-19094 Filed 7-28-11; 8:45 am]
BILLING CODE 4310-22-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.