Notice of Availability of the Draft Environmental Impact Statement for the Gateway West 230/500 kV Transmission Line Project in Idaho, Nevada, and Wyoming and Prospective Draft Land Use Plan Amendments, 45609-45612 [2011-19094]
Download as PDF
Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices
mstockstill on DSK4VPTVN1PROD with NOTICES
proposed Covered Species. However,
the list of Covered Species may change
as the planning process progresses;
species may be added or removed as
more is learned about the nature of
Covered Activities and their impact on
native species within the plan area.
More information on Covered Species,
including State-listed and unlisted
species, is available on the Internet at
https://www.drecp.org/covered species.
Environmental Impact Statement
Before deciding whether to issue the
requested Federal incidental take
permit, the Service will prepare a draft
EIS as part of the joint EIS/EIR, in order
to analyze the environmental impacts
associated with potential adoption and
implementation of the proposed DRECP
as a HCP and NCCP. In the EIS
component of the joint EIS/EIR, the
Service will consider the following
alternatives: (1) The proposed action,
which includes the issuance of take
authorizations consistent with the
proposed DRECP under section
10(a)(1)(B) of the ESA; (2) no action (no
Federal ESA permit issuance); and (3) a
reasonable range of alternatives that
address different scenarios of renewable
energy development and species
conservation on both Federal and nonFederal land. The EIS/EIR will include
a detailed analysis of the impacts of the
proposed action and alternatives. The
range of alternatives to be considered
and analyzed will represent varying
levels of conservation and impacts, and
may include variations in the scope of
Covered Activities; variations in the
locations, amount, and type of
conservation; variations in permit
duration; or a combination of these
elements. The BLM may address other
considerations in the EIS. In compliance
with NEPA, the Service and BLM will
be responsible for the scope and
preparation of the EIS component of the
joint EIS/EIR.
The EIS/EIR will identify and analyze
potentially significant direct, indirect,
and cumulative impacts of the Service’s
authorization of incidental take (permit
issuance) and the implementation of the
proposed DRECP on biological
resources, land uses (including BLM,
U.S. Department of Defense military
operations, and Native American
traditional land uses), utilities, air
quality, water resources (including
surface and groundwater supply and
water quality), cultural resources,
socioeconomics and environmental
justice, outdoor recreation, visual
resources, induced growth, climate
change and greenhouse gases, and other
environmental issues that could occur
with implementation of the proposed
VerDate Mar<15>2010
16:17 Jul 28, 2011
Jkt 223001
action and alternatives. The Service and
the BLM will use all practicable means,
consistent with NEPA and other
essential considerations of national
policy, to avoid or minimize significant
effects of their actions upon the quality
of the human environment.
The Service and BLM have invited the
National Park Service (NPS),
Environmental Protection Agency
(EPA), Department of Energy, and the
Department of Defense to be cooperating
Federal agencies in the preparation of
the EIS, because the proposed project
may have effects on lands and facilities
under the jurisdictions of those
agencies. To date, the NPS and EPA
have requested and agreed to be
cooperating agencies. The CDFG has
requested and agreed to be a State
cooperating agency. The Service, BLM,
NPS, EPA, and CDFG agree that
establishing a cooperating agency
relationship will create a more
streamlined and coordinated approach
in developing this EIS.
Reasonable Accommodation
Persons needing reasonable
accommodations to attend and
participate in the public meeting should
contact Ken Corey at (760) 431–9440 as
soon as possible. To allow sufficient
time to process requests, please call no
later than 1 week before the public
meeting. Information regarding this
proposed action is available in
alternative formats upon request.
Public Comments
Before including your address, phone
number, e-mail address, or other
personal identifying information in your
comment, you should be aware that
your entire comment—including your
personal identifying information—may
be made publicly available at any time.
While you can ask us in your comment
to withhold your personal identifying
information from public review, we
cannot guarantee that we will be able to
do so.
Material the Service receives will be
available for public inspection, by
appointment, during normal business
hours (Monday through Friday, 8 a.m. to
4:30 p.m.) at the Service’s Carlsbad
address (see ADDRESSES).
At the close of the public comment
period, all written comments received
by the Federal co-lead agencies will be
posted on the Internet at https://
www.drecp.org/public scoping
comments. Comments received by CEC
in response to their notice of
preparation under CEQA will also be
posted on the Web site.
PO 00000
Frm 00106
Fmt 4703
Sfmt 4703
45609
Authority: 40 CFR 1501.7.
Tom Pogacnik,
Deputy State Director, Natural Resources,
California State Office, Bureau of Land
Management, Sacramento, California.
Dated: July 22, 2011.
Alexandra Pitts,
Deputy Regional Director, Pacific Southwest
Region, U.S. Fish and Wildlife Service,
Sacramento, California.
[FR Doc. 2011–19175 Filed 7–28–11; 8:45 am]
BILLING CODE 4310–55–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
DEPARTMENT OF AGRICULTURE
Forest Service
[LLWY920000/L51010000.ER0000/
LVRWK09K0990/241A; WYW–174598; IDI–
35849; NVN–089270]
Notice of Availability of the Draft
Environmental Impact Statement for
the Gateway West 230/500 kV
Transmission Line Project in Idaho,
Nevada, and Wyoming and Prospective
Draft Land Use Plan Amendments
Bureau of Land Management,
Interior; and U.S. Forest Service,
Agriculture.
ACTION: Notice of Availability.
AGENCY:
The Bureau of Land
Management (BLM) and the U.S. Forest
Service (USFS) announce the
availability of the Gateway West
Transmission Line Project DEIS and
prospective draft Land Use Plan (LUP)
Amendments. The DEIS analyzes the
consequences of granting a right-of-way
(ROW) to Idaho Power and Rocky
Mountain Power for locating a 1,103mile-long electric transmission line
from the proposed Windstar Substation
near the Dave Johnston Power Plant at
Glenrock, Wyoming, to the proposed
Hemingway Substation near Melba,
Idaho. The project is composed of 10
transmission line segments of 230 and
500 kilovolts (kV); each segment would
carry up to 3,000 megawatts (MW).
The requested ROW width would
generally be 300 feet but could range
from 125 to 350 feet, depending on the
design variation and structure type. The
proposed route generally follows
existing transmission lines and Westwide Energy (WWE) corridors
designated pursuant to Section 368 of
the Energy Policy Act of 2005.
Approximately 610 miles (55 percent) of
the proposed route is located within or
adjacent to designated corridors or
existing transmission lines.
SUMMARY:
E:\FR\FM\29JYN1.SGM
29JYN1
mstockstill on DSK4VPTVN1PROD with NOTICES
45610
Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices
Approximately 500 miles (46 percent)
of the total proposed length traverses
Federally administered land in Idaho
and Wyoming. In Idaho, approximately
280 miles of the proposed transmission
lines would cross public land
administered by seven BLM Field
Offices: Bruneau, Burley, Four Rivers,
Jarbidge, Owyhee, Pocatello, and
Shoshone. In Wyoming, approximately
220 miles of the proposed transmission
lines would cross public land
administered by four BLM Field Offices:
Casper, Kemmerer, Rawlins, and Rock
Springs. The proposed route crosses
approximately 16 miles in two units of
the National Forest System: 7 miles in
the Douglas Ranger District of the
Medicine Bow-Routt National Forest in
Wyoming and 9 miles in the Montpelier
Ranger District of the Caribou-Targhee
National Forest in Idaho. In addition,
the proposed route crosses
approximately 5 miles of land
administered by the Bureau of
Reclamation. Alternative routes are
proposed that would cross the Sawtooth
National Forest in Idaho, the Fort Hall
Indian Reservation, and the acquisition
area of the Cokeville Meadows National
Wildlife Refuge. One alternative route in
Segment #7 extends 9.5 miles into
Nevada with approximately 7 miles on
public land administered by the Wells
Field Office.
This project includes prospective
amendments of USFS Land and
Resource Management Plans (Forest
Plans) and BLM land use plans
(Management Framework Plans and
Resource Management Plans). By this
notice, and the Notice of Intent to
prepare an EIS filed in May 2008 (see
below), BLM is complying with
requirements in 43 Code of Federal
Regulations (CFR) 1610.2(c) and the
USFS is complying with 36 CFR 219.8
to notify the public of potential
amendments to land use plans. The
BLM and USFS are integrating the land
use planning process with the National
Environmental Policy Act (NEPA)
analysis process for this project.
Your input is important and will be
considered in the environmental
analysis process. All comment
submissions must include the
commenter’s name and street address.
Comments including the names and
addresses of the respondent will be
available for public inspection at the
locations listed below during their
business hours (7:45 a.m. to 4:30 p.m.),
Monday through Friday, except Federal
holidays. Before including your address,
phone number, e-mail address, or any
other personal identifying information
in your comment, be advised that your
entire comment, including your
VerDate Mar<15>2010
16:17 Jul 28, 2011
Jkt 223001
personal identifying information, may
be publicly available at any time. While
you may ask us in your comment to
withhold from public review your
personal identifying information, we
cannot guarantee that we will be able to
do so.
DATES: The DEIS is now available for
public review. The BLM and USFS
request that comments be structured so
that they are meaningful and alert the
agencies to a reviewer’s position and
contentions. In order to be considered in
the Final EIS, written comments on the
Draft EIS must be received within 90
days after EPA’s publication in the
Federal Register of a Notice of
Availability of this Draft EIS. The BLM
and USFS will consider timely filed
comments and respond to them in the
final EIS. All public meetings or other
involvement activities for the Gateway
West Transmission Line Project will be
announced to the public by the BLM at
least 15 days in advance through public
notices, media news releases, Web site
announcements, or mailings.
ADDRESSES: Copies of the DEIS have
been sent to affected Federal, State, and
local Governments, public libraries in
the project area, and to interested
parties that previously requested a copy.
The DEIS and supporting documents
will be available electronically on the
following Web site: https://
www.wy.blm.gov/nepa/cfodocs/
gateway_west/. Copies of the DEIS are
available for public inspection during
normal business hours at the following
locations:
• Bureau of Land Management,
Wyoming State Office, Public Room,
5353 Yellowstone Road, Cheyenne,
Wyoming 82009;
• Bureau of Land Management,
Casper Field Office, 2987 Prospector
Drive, Casper, Wyoming 82604;
• Bureau of Land Management,
Rawlins Field Office, 1300 North Third
Street, Rawlins, Wyoming 82301;
• Bureau of Land Management, Rock
Springs Field Office, 280 Highway 191
North, Rock Springs, Wyoming 82901;
• Bureau of Land Management,
Kemmerer Field Office, 312 Highway
189 North, Kemmerer, Wyoming 83101;
• Bureau of Land Management,
Nevada State Office, Public Room, 1340
Financial Boulevard, Reno, Nevada
89502;
• Bureau of Land Management, Wells
Field Office, 3900 East Idaho Street,
Elko, Nevada 89801;
• Bureau of Land Management, Idaho
State Office, Public Room, 1387 South
Vinnell Way, Boise, Idaho 83709;
• Bureau of Land Management,
Pocatello Field Office, 4350 Cliffs Drive,
Pocatello, Idaho 83204;
PO 00000
Frm 00107
Fmt 4703
Sfmt 4703
• Bureau of Land Management, Idaho
Falls District Office, 1405 Hollipark
Drive Idaho Falls, Idaho 83401;
• Bureau of Land Management,
Burley Field Office, 15 East 200 South,
Burley, Idaho 83318;
• Bureau of Land Management, Twin
Falls District Office, 2536 Kimberly
Road, Twin Falls, Idaho 83301;
• Bureau of Land Management,
Shoshone Field Office, 400 West F
Street, Shoshone, Idaho 83325;
• Bureau of Land Management, Boise
District Office, 3948 Development
Avenue, Boise, Idaho 83705;
• Bureau of Land Management,
Owyhee Field Office, 20 First Avenue
West, Marsing, Idaho 83639;
• U.S. Department of Agriculture,
Medicine Bow-Routt National Forest,
2468 Jackson Street, Laramie, WY
82070–6535;
• U.S. Department of Agriculture,
Medicine Bow-Routt National Forest,
Douglas Ranger District, 2250 East
Richards Street, Douglas, WY 82633–
8922;
• U.S. Department of Agriculture,
Caribou-Targhee National Forest,
Montpelier Ranger District, 322 North
4th Street, Montpelier, Idaho 83254; and
• U.S. Department of Agriculture,
Sawtooth National Forest, Minidoka
Ranger District, 3650 Overland Avenue,
Burley, Idaho 83318.
A limited number of copies of the
document will be available as supplies
last. To request a copy, contact Walt
George, Project Manager, Wyoming State
Office, P.O. Box 20879, Cheyenne,
Wyoming 82003.
Written comments may be submitted
by the following methods:
• Web site: https://www.wy.blm.gov/
nepa/cfodocs/gateway_west.
• E-mail:
Gateway_West_WYMail@blm.gov.
• Mail: Bureau of Land Management,
Gateway West Project, P.O. Box 20879,
Cheyenne, Wyoming 82003.
• Courier or Hand Deliver: Bureau of
Land Management, Gateway West
Project, 5353 Yellowstone Road,
Cheyenne, Wyoming 82009.
FOR FURTHER INFORMATION CONTACT: Walt
George, Project Manager, c/o Bureau of
Land Management, Wyoming State
Office, P.O. Box 20879, Cheyenne,
Wyoming 82003 or by telephone at (307)
775–6116. Any persons wishing to be
added to a mailing list of interested
parties may write or call the Project
Manager, at this address or phone
number.
In May
2007, Idaho Power and Rocky Mountain
Power (the Proponents) submitted a
ROW application to the BLM requesting
SUPPLEMENTARY INFORMATION:
E:\FR\FM\29JYN1.SGM
29JYN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices
authorization to construct, operate,
maintain, and decommission electric
transmission lines on public lands. The
application was revised in October
2007, August 2008, May 2009, and
January 2010 to reflect changes to the
proposed action. The Proponents’
objective for the project is to improve
the reliability and efficiency of both
utilities’ systems and address
congestion problems with the western
electrical grid. The project is needed to
meet projected load growth in the
Proponents’ Service Areas. The project
would also tap the developing
renewable energy market, especially
wind energy, in Idaho and Wyoming
and will aid in delivering that energy
throughout the region. The BLM and
USFS’s purpose and need for the EIS is
so that the agencies may respond to the
Proponents’ application.
On May 16, 2008, the BLM published
in the Federal Register (FR Vol. 73, No.
96, pages 28425–28426) its Notice of
Intent to prepare an EIS pursuant to
NEPA, as required by Federal
regulations promulgated for the Federal
Land Policy and Management Act
(FLPMA) found at 43 CFR Part 2800.
The BLM is the lead Federal agency for
the NEPA analysis process and
preparation of the EIS. Cooperating
agencies include: the USFS, National
Park Service, U.S. Fish and Wildlife
Service, Bureau of Indian Affairs, and
U.S. Army Corps of Engineers; the
States of Idaho and Wyoming; the Idaho
Army National Guard; Cassia, Power,
and Twin Falls Counties, Idaho; Elko
County, Nevada; Lincoln, Sweetwater,
and Carbon Counties, Wyoming; the
Medicine Bow and SaratogaEncampment-Rawlins Conservation
Districts in Wyoming; and the City of
Kuna, Idaho.
To allow the public an opportunity to
review the proposal and project
information, the BLM held public
meetings in June 2008 in: Twin Falls,
Murphy, Pocatello, Boise, and
Montpelier, Idaho; and Casper, Rawlins,
Rock Springs, and Kemmerer, Wyoming.
Issues and potential impacts to specific
resources were identified during
scoping and the course of the NEPA
process.
The following project issues were
identified in the scoping process:
• Siting on private lands versus
public lands,
• Land use conflicts and consistency
with land use plans,
• Electric grid reliability and
separation distances of transmission
lines,
• Effects on wildlife habitat, plants,
and animals including threatened,
VerDate Mar<15>2010
16:17 Jul 28, 2011
Jkt 223001
endangered, and sensitive species
(especially sage grouse),
• Effects to visual resources and
existing view sheds,
• Effects to National Historic Trails
and their view sheds,
• Effects to Native American
traditional cultural properties and
respected places,
• Effects to paleontological resources
in southwest Wyoming,
• Avoiding sensitive areas such as
National Monuments and Wildlife
Refuges, military operating areas,
National Conservation Areas, Areas of
Critical Environmental Concern, and
State Parks,
• Effects to soils and water from
surface disturbing activities,
• Effect of the project on local and
regional socioeconomic conditions, and
• Management of invasive plant
species and ensuring effective
reclamation.
In response to scoping comments,
Idaho Power and Rocky Mountain
Power made route changes in Segments
1, 2, 4, 5, 7, 8, and 9 of their original
proposal. The proposed action analyzed
in the DEIS reflects these revisions to
the route. In addition to the proposed
action, the DEIS considers the No
Action alternative, a structure variation,
a phased construction alternative, and
41 route segment alternatives in detail.
Other system alternatives and route
variations were considered but
eliminated from detailed study.
Department of the Interior regulations
(43 CFR 46.425) give agencies flexibility
when identifying preferred alternatives
in the DEIS, stating that: ‘‘* * * the
draft environmental impact statement
should identify the bureau’s preferred
alternatives or alternatives [and] the
final environmental impact statement
must identify the bureau’s preferred
alternative.’’ Because substantial
differences exist, in some project
segments, among cooperating agencies
on the preferred route alternative, and
the full range of public input on route
alternatives will not be available to the
BLM until after the DEIS public
comment period, the BLM is deferring
identification of its preferred route
alternative until the Final EIS.
The DEIS analyzes the potential
environmental consequences of granting
a ROW to Idaho Power and Rocky
Mountain Power to construct an
approximately 1,100-mile transmission
line from Glenrock, Wyoming, to its
terminus at facilities near Melba, Idaho.
The Proposed Route consists of 10
segments:
Segment 1 consists of three
transmission lines designated 1E, 1W(a),
and 1W(c)—between the planned
PO 00000
Frm 00108
Fmt 4703
Sfmt 4703
45611
Windstar Substation near the Dave
Johnston Power Plant at Glenrock,
Wyoming, and the planned Aeolus
Substation near Hanna, Wyoming.
Segment 1E would include construction
and operation of a 100 mile-long, singlecircuit 230-kV transmission line across
lands without existing major linear
ROWs or designated corridors. Three
alternative routes in Segment 1E were
considered in detail, including one that
parallels (but is outside of) an existing
utility corridor for most of its length.
Segment 1W is composed of two
transmission lines: A new single-circuit
230-kV transmission line (1W(a)) that
parallels an existing transmission line
and reconstruction of the existing 230kV transmission line (1W(c)). These two
lines are approximately 75 miles long
and are generally within a WWE
corridor. One alternative route for
Segment 1W is considered in detail.
Segment 2 consists of a 97-mile,
double-circuit 500-kV transmission line
between the Aeolus Substation and the
Creston Substation near Wamsutter,
Wyoming, which generally is within a
WWE corridor. Three alternative route
segments were considered in detail,
including one that parallels but is
outside of an existing utility corridor for
approximately 28 miles.
Segment 3 consists of a 57-mile,
double-circuit 230/500-kV line from the
proposed Creston Substation south of
Wamsutter, Wyoming, to the proposed
Anticline Substation near the Jim
Bridger Power Plant, located
approximately 30 miles east of Rock
Springs, Wyoming. Approximately 17.8
miles are within or parallel to a WWE
corridor. No other alternative routes
were considered in detail for this
segment.
Segment 4 consists of a 203-mile,
double-circuit 500-kV line between the
Anticline Substation, near the Jim
Bridger Power Plant, and the Populus
Substation near Interstate 15 in southern
Bannock County, Idaho. This segment
generally is within an existing
transmission line corridor. Six
alternative route segments were
considered in detail.
Segment 5 consists of a 55-mile,
single-circuit 500-kV line between the
planned Populus Substation and the
existing Borah Substation in Power
County, Idaho. Five alternative route
segments were considered in detail.
Segment 6 consists of increasing the
voltage capacity of an existing line from
the Borah Substation to the Midpoint
Substation located approximately 9
miles south of Shoshone, Idaho. The
voltage would be increased to 500 kV on
the existing Midpoint to Kinport 345-kV
transmission line. Five new towers
E:\FR\FM\29JYN1.SGM
29JYN1
mstockstill on DSK4VPTVN1PROD with NOTICES
45612
Federal Register / Vol. 76, No. 146 / Friday, July 29, 2011 / Notices
would be required. No new route
alternatives were considered in detail
because this is a rebuild of an existing
line.
Segment 7 consists of a 118-mile,
single-circuit 500-kV transmission line
between the Populus Substation and the
proposed Cedar Hill Substation near the
county line between Cassia and Twin
Falls Counties in Idaho. Ten alternative
route segments were considered in
detail, including two that cross the
Sawtooth National Forest, one of which
crosses into Nevada for approximately 9
miles.
Segment 8 consists of a 131-mile,
single-circuit 500-kV transmission line
between the Midpoint Substation and
the Hemingway Substation, located
approximately 30 miles southwest of
Boise, Idaho. Five alternative route
segments were considered in detail.
Segment 9 consists of a 162-mile,
single-circuit 500-kV transmission line
between the proposed Cedar Hill
Substation and the planned Hemingway
Substation near Murphy, Idaho. Eight
alternative route segments were
considered in detail.
Segment 10 consists of a 34-mile,
single-circuit 500-kV transmission line
between the Midpoint Substation,
located approximately 9 miles south of
Shoshone, and Cedar Hill Substation
near the county line between Cassia and
Twin Falls Counties in Idaho. No other
alternative routes were considered in
detail for this segment.
The BLM, USFS, Proponents, and
Cooperating Agencies worked together
to develop routes that would conform to
existing Federal land use plans.
However, this objective was not reached
for many of the routes analyzed in the
DEIS. Unlike the regulations at 43 CFR
46.425 that allow the BLM to defer
identification of an agency preferred
route alternative until the Final EIS, the
BLM planning regulations at 43 CFR
1610.4–7 require identification of the
BLM’s Preferred Plan Amendment in
the DEIS. The BLM has identified draft
plan amendments below for each
situation of nonconformance that would
bring the Proposed or Alternative Route
into conformance with the respective
land use plan. Each of these plan
amendments is the BLM’s preferred
plan amendment. The specific land use
plan amendments actually needed will
be determined by the final agency
preferred route selected. Therefore,
some of the following prospective plan
amendments may not need to be
implemented. The BLM will identify
those plan amendments it intends to
implement (as Proposed Plan
Amendments), along with its preferred
route, in the Final EIS.
VerDate Mar<15>2010
16:17 Jul 28, 2011
Jkt 223001
The following land-use plan
amendments may be needed to bring the
Gateway West Transmission Line
Project into conformance with the
applicable Resource Management Plans
(RMPs) and Management Framework
Plans (MFPs) for BLM-managed lands
and Land and Resource Management
Plans (Forest Plans) for National Forest
System lands crossed by the project,
depending on project approval and on
the final route selected. All prospective
plan amendments will comply with
applicable Federal laws and regulations,
be analyzed in the Gateway West EIS,
and apply only to Federal lands and
mineral estate administered by the BLM
or USFS.
Casper RMP: An amendment may be
needed for visual resource management.
Rawlins RMP: An amendment may be
needed for visual resource management.
Green River RMP: Amendments may
be needed for visual resource
management, sage-grouse, and raptor
management.
Kemmerer RMP: Amendments may be
needed for management of visual
resources, historic trails, heritage
resources, sage-grouse, the Rock Creek/
Tunp Special Designation Area, and
recreation.
Malad MFP: Amendments may be
needed for management of visual
resources and to designate a new utility
corridor.
Bennett Hills/Timmerman Hills MFP:
An amendment may be needed for
visual resource management.
Cassia RMP: Amendments may be
needed for management of visual
resources, historic trails, and to
designate a new utility corridor.
Twin Falls MFP: An amendment may
be needed for visual resource
management and to allow a linear
facility outside of existing corridors.
Jarbidge RMP: Amendments may be
needed for management of visual
resources, paleontological sites, historic
trails, to adjust management objectives
in an ACEC, and to designate a new
utility corridor.
Kuna MFP: An amendment may be
needed for a historic site and to
designate a new utility corridor.
Morley Nelson Snake River Birds of
Prey National Conservation Area RMP:
Amendments may be needed for
management of visual resources, nonmotorized area management, to adjust
management objectives in a Special
Recreation Management Area, sensitive
plant habitat, and to designate a new
utility corridor.
Bruneau MFP: An amendment may be
needed for visual resource management.
PO 00000
Frm 00109
Fmt 4703
Sfmt 4703
Wells RMP: An amendment may be
needed to allow a linear facility outside
of identified planning corridors.
Medicine Bow Forest Plan: An
amendment may be needed for
management of visual resources,
goshawk and amphibian habitat,
recreation, and to change the
management prescription for any area
crossed by new transmission lines not
within the WWE corridor.
Caribou Forest Plan: An amendment
may be needed to designate a new
utility corridor.
Sawtooth Forest Plan: An amendment
may be needed for management of
visual resources and recreation.
The DEIS analyzes the environmental
consequences of the No Action
alternative, the proposed action,
segment and design alternatives, and
land use plan amendments. For this EIS,
the No Action alternative means that the
Idaho Power and Rocky Mountain
Power ROW application for the Gateway
West project would be denied by the
BLM. The BLM will utilize and
coordinate the NEPA commenting
process to satisfy the public
involvement process for Section 106 of
the National Historic Preservation Act
(16 U.S.C. 470f), as provided for in 36
CFR 800.2(d)(3). Ongoing Native
American Tribal consultations will
continue to be conducted in accordance
with policy, and Tribal concerns,
including impacts on Indian trust assets,
will be given due consideration.
Federal, State, and local agencies, along
with other stakeholders that may be
interested or affected by the BLM’s
decision on this project, are invited to
participate.
Brent L. Larson,
Forest Supervisor, Caribou-Targhee National
Forest.
Donald A. Simpson,
Wyoming State Director.
[FR Doc. 2011–19094 Filed 7–28–11; 8:45 am]
BILLING CODE 4310–22–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[LLWYP00000–L51100000–GA0000–
LVEMK09CK380, WYW172684]
Notice of Availability of the Buckskin
Mine Hay Creek II Coal Lease-byApplication Final Environmental
Impact Statement, Wyoming
Bureau of Land Management,
Interior.
ACTION: Notice of Availability.
AGENCY:
In accordance with the
National Environmental Policy Act of
SUMMARY:
E:\FR\FM\29JYN1.SGM
29JYN1
Agencies
[Federal Register Volume 76, Number 146 (Friday, July 29, 2011)]
[Notices]
[Pages 45609-45612]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-19094]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
DEPARTMENT OF AGRICULTURE
Forest Service
[LLWY920000/L51010000.ER0000/LVRWK09K0990/241A; WYW-174598; IDI-35849;
NVN-089270]
Notice of Availability of the Draft Environmental Impact
Statement for the Gateway West 230/500 kV Transmission Line Project in
Idaho, Nevada, and Wyoming and Prospective Draft Land Use Plan
Amendments
AGENCY: Bureau of Land Management, Interior; and U.S. Forest Service,
Agriculture.
ACTION: Notice of Availability.
-----------------------------------------------------------------------
SUMMARY: The Bureau of Land Management (BLM) and the U.S. Forest
Service (USFS) announce the availability of the Gateway West
Transmission Line Project DEIS and prospective draft Land Use Plan
(LUP) Amendments. The DEIS analyzes the consequences of granting a
right-of-way (ROW) to Idaho Power and Rocky Mountain Power for locating
a 1,103-mile-long electric transmission line from the proposed Windstar
Substation near the Dave Johnston Power Plant at Glenrock, Wyoming, to
the proposed Hemingway Substation near Melba, Idaho. The project is
composed of 10 transmission line segments of 230 and 500 kilovolts
(kV); each segment would carry up to 3,000 megawatts (MW).
The requested ROW width would generally be 300 feet but could range
from 125 to 350 feet, depending on the design variation and structure
type. The proposed route generally follows existing transmission lines
and West-wide Energy (WWE) corridors designated pursuant to Section 368
of the Energy Policy Act of 2005. Approximately 610 miles (55 percent)
of the proposed route is located within or adjacent to designated
corridors or existing transmission lines.
[[Page 45610]]
Approximately 500 miles (46 percent) of the total proposed length
traverses Federally administered land in Idaho and Wyoming. In Idaho,
approximately 280 miles of the proposed transmission lines would cross
public land administered by seven BLM Field Offices: Bruneau, Burley,
Four Rivers, Jarbidge, Owyhee, Pocatello, and Shoshone. In Wyoming,
approximately 220 miles of the proposed transmission lines would cross
public land administered by four BLM Field Offices: Casper, Kemmerer,
Rawlins, and Rock Springs. The proposed route crosses approximately 16
miles in two units of the National Forest System: 7 miles in the
Douglas Ranger District of the Medicine Bow-Routt National Forest in
Wyoming and 9 miles in the Montpelier Ranger District of the Caribou-
Targhee National Forest in Idaho. In addition, the proposed route
crosses approximately 5 miles of land administered by the Bureau of
Reclamation. Alternative routes are proposed that would cross the
Sawtooth National Forest in Idaho, the Fort Hall Indian Reservation,
and the acquisition area of the Cokeville Meadows National Wildlife
Refuge. One alternative route in Segment 7 extends 9.5 miles
into Nevada with approximately 7 miles on public land administered by
the Wells Field Office.
This project includes prospective amendments of USFS Land and
Resource Management Plans (Forest Plans) and BLM land use plans
(Management Framework Plans and Resource Management Plans). By this
notice, and the Notice of Intent to prepare an EIS filed in May 2008
(see below), BLM is complying with requirements in 43 Code of Federal
Regulations (CFR) 1610.2(c) and the USFS is complying with 36 CFR 219.8
to notify the public of potential amendments to land use plans. The BLM
and USFS are integrating the land use planning process with the
National Environmental Policy Act (NEPA) analysis process for this
project.
Your input is important and will be considered in the environmental
analysis process. All comment submissions must include the commenter's
name and street address. Comments including the names and addresses of
the respondent will be available for public inspection at the locations
listed below during their business hours (7:45 a.m. to 4:30 p.m.),
Monday through Friday, except Federal holidays. Before including your
address, phone number, e-mail address, or any other personal
identifying information in your comment, be advised that your entire
comment, including your personal identifying information, may be
publicly available at any time. While you may ask us in your comment to
withhold from public review your personal identifying information, we
cannot guarantee that we will be able to do so.
DATES: The DEIS is now available for public review. The BLM and USFS
request that comments be structured so that they are meaningful and
alert the agencies to a reviewer's position and contentions. In order
to be considered in the Final EIS, written comments on the Draft EIS
must be received within 90 days after EPA's publication in the Federal
Register of a Notice of Availability of this Draft EIS. The BLM and
USFS will consider timely filed comments and respond to them in the
final EIS. All public meetings or other involvement activities for the
Gateway West Transmission Line Project will be announced to the public
by the BLM at least 15 days in advance through public notices, media
news releases, Web site announcements, or mailings.
ADDRESSES: Copies of the DEIS have been sent to affected Federal,
State, and local Governments, public libraries in the project area, and
to interested parties that previously requested a copy. The DEIS and
supporting documents will be available electronically on the following
Web site: https://www.wy.blm.gov/nepa/cfodocs/gateway_west/. Copies of
the DEIS are available for public inspection during normal business
hours at the following locations:
Bureau of Land Management, Wyoming State Office, Public
Room, 5353 Yellowstone Road, Cheyenne, Wyoming 82009;
Bureau of Land Management, Casper Field Office, 2987
Prospector Drive, Casper, Wyoming 82604;
Bureau of Land Management, Rawlins Field Office, 1300
North Third Street, Rawlins, Wyoming 82301;
Bureau of Land Management, Rock Springs Field Office, 280
Highway 191 North, Rock Springs, Wyoming 82901;
Bureau of Land Management, Kemmerer Field Office, 312
Highway 189 North, Kemmerer, Wyoming 83101;
Bureau of Land Management, Nevada State Office, Public
Room, 1340 Financial Boulevard, Reno, Nevada 89502;
Bureau of Land Management, Wells Field Office, 3900 East
Idaho Street, Elko, Nevada 89801;
Bureau of Land Management, Idaho State Office, Public
Room, 1387 South Vinnell Way, Boise, Idaho 83709;
Bureau of Land Management, Pocatello Field Office, 4350
Cliffs Drive, Pocatello, Idaho 83204;
Bureau of Land Management, Idaho Falls District Office,
1405 Hollipark Drive Idaho Falls, Idaho 83401;
Bureau of Land Management, Burley Field Office, 15 East
200 South, Burley, Idaho 83318;
Bureau of Land Management, Twin Falls District Office,
2536 Kimberly Road, Twin Falls, Idaho 83301;
Bureau of Land Management, Shoshone Field Office, 400 West
F Street, Shoshone, Idaho 83325;
Bureau of Land Management, Boise District Office, 3948
Development Avenue, Boise, Idaho 83705;
Bureau of Land Management, Owyhee Field Office, 20 First
Avenue West, Marsing, Idaho 83639;
U.S. Department of Agriculture, Medicine Bow-Routt
National Forest, 2468 Jackson Street, Laramie, WY 82070-6535;
U.S. Department of Agriculture, Medicine Bow-Routt
National Forest, Douglas Ranger District, 2250 East Richards Street,
Douglas, WY 82633-8922;
U.S. Department of Agriculture, Caribou-Targhee National
Forest, Montpelier Ranger District, 322 North 4th Street, Montpelier,
Idaho 83254; and
U.S. Department of Agriculture, Sawtooth National Forest,
Minidoka Ranger District, 3650 Overland Avenue, Burley, Idaho 83318.
A limited number of copies of the document will be available as
supplies last. To request a copy, contact Walt George, Project Manager,
Wyoming State Office, P.O. Box 20879, Cheyenne, Wyoming 82003.
Written comments may be submitted by the following methods:
Web site: https://www.wy.blm.gov/nepa/cfodocs/gateway_west.
E-mail: Gateway_West_WYMail@blm.gov.
Mail: Bureau of Land Management, Gateway West Project,
P.O. Box 20879, Cheyenne, Wyoming 82003.
Courier or Hand Deliver: Bureau of Land Management,
Gateway West Project, 5353 Yellowstone Road, Cheyenne, Wyoming 82009.
FOR FURTHER INFORMATION CONTACT: Walt George, Project Manager, c/o
Bureau of Land Management, Wyoming State Office, P.O. Box 20879,
Cheyenne, Wyoming 82003 or by telephone at (307) 775-6116. Any persons
wishing to be added to a mailing list of interested parties may write
or call the Project Manager, at this address or phone number.
SUPPLEMENTARY INFORMATION: In May 2007, Idaho Power and Rocky Mountain
Power (the Proponents) submitted a ROW application to the BLM
requesting
[[Page 45611]]
authorization to construct, operate, maintain, and decommission
electric transmission lines on public lands. The application was
revised in October 2007, August 2008, May 2009, and January 2010 to
reflect changes to the proposed action. The Proponents' objective for
the project is to improve the reliability and efficiency of both
utilities' systems and address congestion problems with the western
electrical grid. The project is needed to meet projected load growth in
the Proponents' Service Areas. The project would also tap the
developing renewable energy market, especially wind energy, in Idaho
and Wyoming and will aid in delivering that energy throughout the
region. The BLM and USFS's purpose and need for the EIS is so that the
agencies may respond to the Proponents' application.
On May 16, 2008, the BLM published in the Federal Register (FR Vol.
73, No. 96, pages 28425-28426) its Notice of Intent to prepare an EIS
pursuant to NEPA, as required by Federal regulations promulgated for
the Federal Land Policy and Management Act (FLPMA) found at 43 CFR Part
2800. The BLM is the lead Federal agency for the NEPA analysis process
and preparation of the EIS. Cooperating agencies include: the USFS,
National Park Service, U.S. Fish and Wildlife Service, Bureau of Indian
Affairs, and U.S. Army Corps of Engineers; the States of Idaho and
Wyoming; the Idaho Army National Guard; Cassia, Power, and Twin Falls
Counties, Idaho; Elko County, Nevada; Lincoln, Sweetwater, and Carbon
Counties, Wyoming; the Medicine Bow and Saratoga-Encampment-Rawlins
Conservation Districts in Wyoming; and the City of Kuna, Idaho.
To allow the public an opportunity to review the proposal and
project information, the BLM held public meetings in June 2008 in: Twin
Falls, Murphy, Pocatello, Boise, and Montpelier, Idaho; and Casper,
Rawlins, Rock Springs, and Kemmerer, Wyoming. Issues and potential
impacts to specific resources were identified during scoping and the
course of the NEPA process.
The following project issues were identified in the scoping
process:
Siting on private lands versus public lands,
Land use conflicts and consistency with land use plans,
Electric grid reliability and separation distances of
transmission lines,
Effects on wildlife habitat, plants, and animals including
threatened, endangered, and sensitive species (especially sage grouse),
Effects to visual resources and existing view sheds,
Effects to National Historic Trails and their view sheds,
Effects to Native American traditional cultural properties
and respected places,
Effects to paleontological resources in southwest Wyoming,
Avoiding sensitive areas such as National Monuments and
Wildlife Refuges, military operating areas, National Conservation
Areas, Areas of Critical Environmental Concern, and State Parks,
Effects to soils and water from surface disturbing
activities,
Effect of the project on local and regional socioeconomic
conditions, and
Management of invasive plant species and ensuring
effective reclamation.
In response to scoping comments, Idaho Power and Rocky Mountain
Power made route changes in Segments 1, 2, 4, 5, 7, 8, and 9 of their
original proposal. The proposed action analyzed in the DEIS reflects
these revisions to the route. In addition to the proposed action, the
DEIS considers the No Action alternative, a structure variation, a
phased construction alternative, and 41 route segment alternatives in
detail. Other system alternatives and route variations were considered
but eliminated from detailed study. Department of the Interior
regulations (43 CFR 46.425) give agencies flexibility when identifying
preferred alternatives in the DEIS, stating that: ``* * * the draft
environmental impact statement should identify the bureau's preferred
alternatives or alternatives [and] the final environmental impact
statement must identify the bureau's preferred alternative.'' Because
substantial differences exist, in some project segments, among
cooperating agencies on the preferred route alternative, and the full
range of public input on route alternatives will not be available to
the BLM until after the DEIS public comment period, the BLM is
deferring identification of its preferred route alternative until the
Final EIS.
The DEIS analyzes the potential environmental consequences of
granting a ROW to Idaho Power and Rocky Mountain Power to construct an
approximately 1,100-mile transmission line from Glenrock, Wyoming, to
its terminus at facilities near Melba, Idaho. The Proposed Route
consists of 10 segments:
Segment 1 consists of three transmission lines designated 1E,
1W(a), and 1W(c)--between the planned Windstar Substation near the Dave
Johnston Power Plant at Glenrock, Wyoming, and the planned Aeolus
Substation near Hanna, Wyoming. Segment 1E would include construction
and operation of a 100 mile-long, single-circuit 230-kV transmission
line across lands without existing major linear ROWs or designated
corridors. Three alternative routes in Segment 1E were considered in
detail, including one that parallels (but is outside of) an existing
utility corridor for most of its length. Segment 1W is composed of two
transmission lines: A new single-circuit 230-kV transmission line
(1W(a)) that parallels an existing transmission line and reconstruction
of the existing 230-kV transmission line (1W(c)). These two lines are
approximately 75 miles long and are generally within a WWE corridor.
One alternative route for Segment 1W is considered in detail.
Segment 2 consists of a 97-mile, double-circuit 500-kV transmission
line between the Aeolus Substation and the Creston Substation near
Wamsutter, Wyoming, which generally is within a WWE corridor. Three
alternative route segments were considered in detail, including one
that parallels but is outside of an existing utility corridor for
approximately 28 miles.
Segment 3 consists of a 57-mile, double-circuit 230/500-kV line
from the proposed Creston Substation south of Wamsutter, Wyoming, to
the proposed Anticline Substation near the Jim Bridger Power Plant,
located approximately 30 miles east of Rock Springs, Wyoming.
Approximately 17.8 miles are within or parallel to a WWE corridor. No
other alternative routes were considered in detail for this segment.
Segment 4 consists of a 203-mile, double-circuit 500-kV line
between the Anticline Substation, near the Jim Bridger Power Plant, and
the Populus Substation near Interstate 15 in southern Bannock County,
Idaho. This segment generally is within an existing transmission line
corridor. Six alternative route segments were considered in detail.
Segment 5 consists of a 55-mile, single-circuit 500-kV line between
the planned Populus Substation and the existing Borah Substation in
Power County, Idaho. Five alternative route segments were considered in
detail.
Segment 6 consists of increasing the voltage capacity of an
existing line from the Borah Substation to the Midpoint Substation
located approximately 9 miles south of Shoshone, Idaho. The voltage
would be increased to 500 kV on the existing Midpoint to Kinport 345-kV
transmission line. Five new towers
[[Page 45612]]
would be required. No new route alternatives were considered in detail
because this is a rebuild of an existing line.
Segment 7 consists of a 118-mile, single-circuit 500-kV
transmission line between the Populus Substation and the proposed Cedar
Hill Substation near the county line between Cassia and Twin Falls
Counties in Idaho. Ten alternative route segments were considered in
detail, including two that cross the Sawtooth National Forest, one of
which crosses into Nevada for approximately 9 miles.
Segment 8 consists of a 131-mile, single-circuit 500-kV
transmission line between the Midpoint Substation and the Hemingway
Substation, located approximately 30 miles southwest of Boise, Idaho.
Five alternative route segments were considered in detail.
Segment 9 consists of a 162-mile, single-circuit 500-kV
transmission line between the proposed Cedar Hill Substation and the
planned Hemingway Substation near Murphy, Idaho. Eight alternative
route segments were considered in detail.
Segment 10 consists of a 34-mile, single-circuit 500-kV
transmission line between the Midpoint Substation, located
approximately 9 miles south of Shoshone, and Cedar Hill Substation near
the county line between Cassia and Twin Falls Counties in Idaho. No
other alternative routes were considered in detail for this segment.
The BLM, USFS, Proponents, and Cooperating Agencies worked together
to develop routes that would conform to existing Federal land use
plans. However, this objective was not reached for many of the routes
analyzed in the DEIS. Unlike the regulations at 43 CFR 46.425 that
allow the BLM to defer identification of an agency preferred route
alternative until the Final EIS, the BLM planning regulations at 43 CFR
1610.4-7 require identification of the BLM's Preferred Plan Amendment
in the DEIS. The BLM has identified draft plan amendments below for
each situation of nonconformance that would bring the Proposed or
Alternative Route into conformance with the respective land use plan.
Each of these plan amendments is the BLM's preferred plan amendment.
The specific land use plan amendments actually needed will be
determined by the final agency preferred route selected. Therefore,
some of the following prospective plan amendments may not need to be
implemented. The BLM will identify those plan amendments it intends to
implement (as Proposed Plan Amendments), along with its preferred
route, in the Final EIS.
The following land-use plan amendments may be needed to bring the
Gateway West Transmission Line Project into conformance with the
applicable Resource Management Plans (RMPs) and Management Framework
Plans (MFPs) for BLM-managed lands and Land and Resource Management
Plans (Forest Plans) for National Forest System lands crossed by the
project, depending on project approval and on the final route selected.
All prospective plan amendments will comply with applicable Federal
laws and regulations, be analyzed in the Gateway West EIS, and apply
only to Federal lands and mineral estate administered by the BLM or
USFS.
Casper RMP: An amendment may be needed for visual resource
management.
Rawlins RMP: An amendment may be needed for visual resource
management.
Green River RMP: Amendments may be needed for visual resource
management, sage-grouse, and raptor management.
Kemmerer RMP: Amendments may be needed for management of visual
resources, historic trails, heritage resources, sage-grouse, the Rock
Creek/Tunp Special Designation Area, and recreation.
Malad MFP: Amendments may be needed for management of visual
resources and to designate a new utility corridor.
Bennett Hills/Timmerman Hills MFP: An amendment may be needed for
visual resource management.
Cassia RMP: Amendments may be needed for management of visual
resources, historic trails, and to designate a new utility corridor.
Twin Falls MFP: An amendment may be needed for visual resource
management and to allow a linear facility outside of existing
corridors.
Jarbidge RMP: Amendments may be needed for management of visual
resources, paleontological sites, historic trails, to adjust management
objectives in an ACEC, and to designate a new utility corridor.
Kuna MFP: An amendment may be needed for a historic site and to
designate a new utility corridor.
Morley Nelson Snake River Birds of Prey National Conservation Area
RMP: Amendments may be needed for management of visual resources, non-
motorized area management, to adjust management objectives in a Special
Recreation Management Area, sensitive plant habitat, and to designate a
new utility corridor.
Bruneau MFP: An amendment may be needed for visual resource
management.
Wells RMP: An amendment may be needed to allow a linear facility
outside of identified planning corridors.
Medicine Bow Forest Plan: An amendment may be needed for management
of visual resources, goshawk and amphibian habitat, recreation, and to
change the management prescription for any area crossed by new
transmission lines not within the WWE corridor.
Caribou Forest Plan: An amendment may be needed to designate a new
utility corridor.
Sawtooth Forest Plan: An amendment may be needed for management of
visual resources and recreation.
The DEIS analyzes the environmental consequences of the No Action
alternative, the proposed action, segment and design alternatives, and
land use plan amendments. For this EIS, the No Action alternative means
that the Idaho Power and Rocky Mountain Power ROW application for the
Gateway West project would be denied by the BLM. The BLM will utilize
and coordinate the NEPA commenting process to satisfy the public
involvement process for Section 106 of the National Historic
Preservation Act (16 U.S.C. 470f), as provided for in 36 CFR
800.2(d)(3). Ongoing Native American Tribal consultations will continue
to be conducted in accordance with policy, and Tribal concerns,
including impacts on Indian trust assets, will be given due
consideration. Federal, State, and local agencies, along with other
stakeholders that may be interested or affected by the BLM's decision
on this project, are invited to participate.
Brent L. Larson,
Forest Supervisor, Caribou-Targhee National Forest.
Donald A. Simpson,
Wyoming State Director.
[FR Doc. 2011-19094 Filed 7-28-11; 8:45 am]
BILLING CODE 4310-22-P