Ocean Renewable Power Company, LLC; Notice Concluding Pre-Filing Process and Approving Process Plan And Schedule, 42122 [2011-17992]

Download as PDF 42122 Federal Register / Vol. 76, No. 137 / Monday, July 18, 2011 / Notices Therefore, the preparation of an Environmental Impact Statement (EIS) is not required. Site-specific, focused Environmental Assessments (EA’s) will be tiered from the PEA to evaluate sitespecific impacts at individual MARFORRES facilities identified as having the potential for the development of wind energy. DATES: Effective date: These findings are effective as of July 12, 2011. FOR FURTHER INFORMATION CONTACT: Alain D. Flexer, Energy Manager, Marine Forces Reserve, 2000 Opelousas, New Orleans, LA 70146, 504–697–9571; (this is not a toll-free number). Dated: July 12, 2011. L.M. Senay, Lieutenant, Judge Advocate General’s Corps, U.S. Navy, Federal Register Liaison Officer. [FR Doc. 2011–17980 Filed 7–15–11; 8:45 am] BILLING CODE 3810–FF–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12711–003] Ocean Renewable Power Company, LLC; Notice Concluding Pre-Filing Process and Approving Process Plan And Schedule a. Type of Filing: Notice of Intent to File Application for License for a Hydrokinetic Pilot Project. b. Project No.: 12711–003. c. Dated Filed: July 24, 2009. d. Submitted By: Ocean Renewable Power Company, LLC. e. Name of Project: Cobscook Bay Tidal Energy Project. f. Location: In Cobscook Bay, in Washington County, Maine. The project would not occupy federal lands. g. Filed Pursuant to: 18 CFR 5.3 and 5.5 of the Commission’s regulations. h. Applicant Contact: Christopher R. Sauer, Ocean Renewable Power Company, LLC, 120 Exchange Street, Suite 508, Portland, Maine 04101, (207) 772–7707. i. FERC Contact: Timothy Konnert (202) 502–6359. j. Ocean Renewable Power Company, LLC (ORPC) has filed with the Commission: (1) A notice of intent (NOI) to file an application for a pilot hydrokinetic hydropower project and a draft license application with monitoring plans; (2) a request for waivers of certain Integrated Licensing Process (ILP) regulations necessary for expedited processing of a license application for a hydrokinetic pilot project; (3) a proposed process plan and schedule; and (4) a request to be designated as the non-federal representative for section 7 of the Endangered Species Act consultation and for section 106 consultation under the National Historic Preservation Act. k. A notice was issued on August 7, 2009, soliciting comments on the draft license application from agencies and stakeholders. Comments were filed by federal and state agencies, and nongovernmental organizations. No comments were filed opposing the request to waive the ILP regulations or the proposed process plan and schedule. l. ORPC was designated as the nonfederal representative for section 7 of the Endangered Species Act consultation and for section 106 consultation under the National Historic Preservation Act on August 7, 2009. m. ORPC proposes a two-phased development approach for the Cobscook Bay Tidal Energy Project. The project would consist of: (1) A single 5-meterdiameter axial flow Kinetic System turbine generator unit (TGU) mounted on a triframe mount, with a rated capacity of 60 kilowatts (kW), in Phase 1; (2) four 5-meter-diameter axial flow Kinetic System TGUs mounted on triframe mounts, with a rated capacity of 60 kW each, in Phase 2; (3) a direct current power and data cable approximately 3,800 feet long (3,600 feet underwater and 200 feet on shore) extending from the TGUs to the onshore station house; (4) an on-shore building 32 feet wide by 35 feet long, housing the SatCon power inverter and the supervisory control and data acquisition (SCADA) system; and (5) appurtenant facilities for navigation safety and operation. The project would have a total rated capacity of 300 kW, with an estimated annual generation between 1,200,000 and 1,300,000 kilowatt-hours. n. The pre-filing process has been concluded and the requisite regulations have been waived such that the process and schedule indicated below can be implemented. o. Post-filing process schedule. The post-filing process will be conducted pursuant to the following schedule. Revisions to the schedule may be made as needed. Milestones Dates Final license application expected ........................................................................................................................................... Issue notice of acceptance and ready for environmental analysis and request for interventions .......................................... Issue biological assessment .................................................................................................................................................... Recommendations, conditions, comments and interventions due .......................................................................................... Issue notice of availability of environmental assessment ....................................................................................................... Comments due and 10(j) resolution, if needed ....................................................................................................................... August 31, 2011. September 15, 2011. September 15, 2011. October 15, 2011. December 14, 2011. January 13, 2011. srobinson on DSK4SPTVN1PROD with NOTICES p. Register online at https://ferc.gov/ esubscribenow.htm to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. DEPARTMENT OF ENERGY Dated: July 12, 2011. Kimberly D. Bose, Secretary. Records Governing Off-the-Record; Public Notice [FR Doc. 2011–17992 Filed 7–15–11; 8:45 am] BILLING CODE 6717–01–P VerDate Mar<15>2010 16:43 Jul 15, 2011 Jkt 223001 Federal Energy Regulatory Commission [Docket No. RM98–1–000] This constitutes notice, in accordance with 18 CFR 385.2201(b), of the receipt of prohibited and exempt off-the-record communications. Order No. 607 (64 FR 51222, September 22, 1999) requires PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 Commission decisional employees, who make or receive a prohibited or exempt off-the-record communication relevant to the merits of a contested proceeding, to deliver to the Secretary of the Commission, a copy of the communication, if written, or a summary of the substance of any oral communication. Prohibited communications are included in a public, non-decisional file associated with, but not a part of, the decisional record of the proceeding. Unless the Commission determines that the prohibited communication and any E:\FR\FM\18JYN1.SGM 18JYN1

Agencies

[Federal Register Volume 76, Number 137 (Monday, July 18, 2011)]
[Notices]
[Page 42122]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-17992]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12711-003]


Ocean Renewable Power Company, LLC; Notice Concluding Pre-Filing 
Process and Approving Process Plan And Schedule

    a. Type of Filing: Notice of Intent to File Application for License 
for a Hydrokinetic Pilot Project.
    b. Project No.: 12711-003.
    c. Dated Filed: July 24, 2009.
    d. Submitted By: Ocean Renewable Power Company, LLC.
    e. Name of Project: Cobscook Bay Tidal Energy Project.
    f. Location: In Cobscook Bay, in Washington County, Maine. The 
project would not occupy federal lands.
    g. Filed Pursuant to: 18 CFR 5.3 and 5.5 of the Commission's 
regulations.
    h. Applicant Contact: Christopher R. Sauer, Ocean Renewable Power 
Company, LLC, 120 Exchange Street, Suite 508, Portland, Maine 04101, 
(207) 772-7707.
    i. FERC Contact: Timothy Konnert (202) 502-6359.
    j. Ocean Renewable Power Company, LLC (ORPC) has filed with the 
Commission: (1) A notice of intent (NOI) to file an application for a 
pilot hydrokinetic hydropower project and a draft license application 
with monitoring plans; (2) a request for waivers of certain Integrated 
Licensing Process (ILP) regulations necessary for expedited processing 
of a license application for a hydrokinetic pilot project; (3) a 
proposed process plan and schedule; and (4) a request to be designated 
as the non-federal representative for section 7 of the Endangered 
Species Act consultation and for section 106 consultation under the 
National Historic Preservation Act.
    k. A notice was issued on August 7, 2009, soliciting comments on 
the draft license application from agencies and stakeholders. Comments 
were filed by federal and state agencies, and non-governmental 
organizations. No comments were filed opposing the request to waive the 
ILP regulations or the proposed process plan and schedule.
    l. ORPC was designated as the non-federal representative for 
section 7 of the Endangered Species Act consultation and for section 
106 consultation under the National Historic Preservation Act on August 
7, 2009.
    m. ORPC proposes a two-phased development approach for the Cobscook 
Bay Tidal Energy Project. The project would consist of: (1) A single 5-
meter-diameter axial flow Kinetic System turbine generator unit (TGU) 
mounted on a triframe mount, with a rated capacity of 60 kilowatts 
(kW), in Phase 1; (2) four 5-meter-diameter axial flow Kinetic System 
TGUs mounted on triframe mounts, with a rated capacity of 60 kW each, 
in Phase 2; (3) a direct current power and data cable approximately 
3,800 feet long (3,600 feet underwater and 200 feet on shore) extending 
from the TGUs to the onshore station house; (4) an on-shore building 32 
feet wide by 35 feet long, housing the SatCon power inverter and the 
supervisory control and data acquisition (SCADA) system; and (5) 
appurtenant facilities for navigation safety and operation. The project 
would have a total rated capacity of 300 kW, with an estimated annual 
generation between 1,200,000 and 1,300,000 kilowatt-hours.
    n. The pre-filing process has been concluded and the requisite 
regulations have been waived such that the process and schedule 
indicated below can be implemented.
    o. Post-filing process schedule. The post-filing process will be 
conducted pursuant to the following schedule. Revisions to the schedule 
may be made as needed.

------------------------------------------------------------------------
             Milestones                              Dates
------------------------------------------------------------------------
Final license application expected..  August 31, 2011.
Issue notice of acceptance and ready  September 15, 2011.
 for environmental analysis and
 request for interventions.
Issue biological assessment.........  September 15, 2011.
Recommendations, conditions,          October 15, 2011.
 comments and interventions due.
Issue notice of availability of       December 14, 2011.
 environmental assessment.
Comments due and 10(j) resolution,    January 13, 2011.
 if needed.
------------------------------------------------------------------------

    p. Register online at https://ferc.gov/esubscribenow.htm to be 
notified via e-mail of new filing and issuances related to this or 
other pending projects. For assistance, contact FERC Online Support.

    Dated: July 12, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-17992 Filed 7-15-11; 8:45 am]