DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12690–003]
Public Utility District No. 1 of
Snohomish County, WA; Notice
Concluding Pre-Filing Process and
Approving Process Plan and Schedule
a. Type of Filing: Notice of Intent to
File a License Application for an
Original License for a Hydrokinetic Pilot
Project.
b. Project No.: 12690–003.
c. Date Filed: December 28, 2009.
d. Submitted by: Public Utility
District No. 1 of Snohomish County,
Washington (Snohomish PUD).
e. Name of Project: Admiralty Inlet
Pilot Tidal Project.
f. Location: On the east side of
Admiralty Inlet in Puget Sound,
Washington, about 1 kilometer west of
Whidbey Island, entirely within Island
County, Washington. The project would
not occupy any Federal lands.
g. Filed Pursuant to: 18 CFR 5.3 and
5.5 of the Commission’s regulations.
h. Applicant Contact: Steven J. Klein,
Public Utility District of Snohomish
County, Washington, P.O. Box 1107,
2320, California Street, Everett, WA
98206–1107; (425) 783–8473.
i. FERC Contact: David Turner (202)
502–6091.
j. Snohomish PUD has filed with the
Commission: (1) A notice of intent (NOI)
to file an application for a pilot
hydrokinetic hydropower project and a
draft license application with
monitoring plans; (2) a request for
waivers of certain Integrated Licensing
Process (ILP) regulations necessary for
expedited processing of a license
application for a hydrokinetic pilot
project; (3) a proposed process plan and
schedule; and (4) a request to be
designated as the non-Federal
representative for section 7 of the
Endangered Species Act (ESA)
consultation and for section 106
consultation under the National Historic
Preservation Act.
k. A notice was issued on December
30, 2009 soliciting comments on the
draft license application from agencies
and stakeholders. Comments were filed
by Federal and state agencies, and nongovernmental organizations.
l. Snohomish PUD was designated as
the non-Federal representative for
section 7 of the Endangered Species Act
consultation and for section 106
41237
consultation under the National Historic
Preservation Act on November 7, 2008.
m. The proposed Admiralty Inlet Pilot
Tidal Project would consist of (1) Two
10-meter, 500-kilowatt (kW) OpenCentre Turbines supplied by
OpenHydro Group Ltd., mounted on
completely submerged gravity
foundations; (2) two 250-meter service
cables connected at a subsea junction
box or spliced to a 0.5-kilometer subsea
transmission cable, connecting to a
cable termination vault about 50 meters
from shore; (3) two 81-meter-long buried
conduits containing the two DC
transmission lines from the turbines and
connecting to a power conditioning and
control building; (4) a 140-meter-long
buried cable from the control building
to the grid; and (5) appurtenant facilities
for operation and maintenance. The
estimated annual generation of the
project is 383,000 kilowatt-hours.
n. The pre-filing process has been
concluded and the requisite regulations
have been waived such that the process
and schedule indicated below can be
implemented.
o. Post-filing process schedule. The
post-filing process will be conducted
pursuant to the following schedule.
Revisions to the schedule may be made
as needed.
Milestones
Dates
Final license application expected ...........................................................................................................................................
Issue notice of acceptance and ready for environmental analysis and request for interventions ..........................................
Issue biological assessment ....................................................................................................................................................
Recommendations, Conditions, Comments and Interventions due ........................................................................................
Issue notice of availability of environmental assessment .......................................................................................................
Comments due and 10(j) resolution, if needed .......................................................................................................................
August 31, 2011.
September 15, 2011.
September 15, 2011.
October 17, 2011.
December 16, 2011.
January 16, 2012.
p. Register online at https://ferc.gov/
esubscribenow.htm to be notified via email of new filing and issuances related
to this or other pending projects. For
assistance, contact FERC Online
Support.
DEPARTMENT OF ENERGY
Dated: July 7, 2011.
Kimberly D. Bose,
Secretary.
Metropolitan Water District of Southern
California; Notice of Effectiveness of
Surrender
[FR Doc. 2011–17588 Filed 7–12–11; 8:45 am]
On September 17, 2001, the
Commission issued an Order Granting
Exemption from Licensing (Conduit) 1 to
the Metropolitan Water District of
Southern California (exemptee) for the
OC–88 Small Conduit Hydroelectric
Project No. 12095. The project was
located in the City of Lake Forest in
Orange County, California at the OC–88
Service Connection, which transfers
water from the Allen-McCulloch
Pipeline to the South County Pipeline.
mstockstill on DSK4VPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
[Project No. 12095–000]
1 Metropolitan Water District of Southern
California, 96 FERC ¶ 62,259 (2001).
VerDate Mar<15>2010
17:36 Jul 12, 2011
Jkt 223001
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
On September 20, 2005, staff from the
Commission’s San Francisco Regional
Office conducted an operation
inspection of the project. During the
inspection, the exemptee advised
Commission staff that it intended to
surrender the exemption and
Commission staff observed that the
exemptee had capped off the penstock
and electrically disconnected the
generator.
On November 4, 2005, the exemptee
filed an application with the
Commission to surrender its exemption
stating that, due to modifications at the
pump station, the physical connections
necessary for operation of the turbine
generator no longer existed.
Accordingly, the Commission hereby
gives notice and accepts the
Metropolitan Water District of Southern
California’s surrender of its exemption
from licensing for the OC–88 Small
Conduit Hydroelectric Project issued on
E:\FR\FM\13JYN1.SGM
13JYN1
41238
Federal Register / Vol. 76, No. 134 / Wednesday, July 13, 2011 / Notices
September 17, 2001, effective November
4, 2005.
Dated: July 7, 2011.
Kimberly D. Bose,
Secretary.
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on Tuesday, July 19, 2011.
Dated: July 7, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–17587 Filed 7–12–11; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2011–17586 Filed 7–12–11; 8:45 am]
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Docket No. PR11–115–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Regency Intrastate Gas LP; Notice of
Filing
Take notice that on July 7, 2011,
Regency Intrastate Gas LP, (Regency)
filed to revise its Operating Statement.
Regency states this version supersedes
and replaces the version filed in Docket
No. PR11–114–000 on June 7, 2011, as
more fully described in the filing.
Any person desiring to participate in
this rate filing must file in accordance
with Rules 211 and 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 7 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
VerDate Mar<15>2010
17:36 Jul 12, 2011
Jkt 223001
Federal Energy Regulatory
Commission
[Docket No. ER11–3980–000]
ORNI 14; Supplemental Notice that
Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
This is a supplemental notice in the
above-referenced proceeding of ORNI
14’s application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is July 27,
2011.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: July 7, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–17598 Filed 7–12–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER11–3959–000]
Post Rock Wind Power Project, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Post
Rock Wind Power Project, LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is July 27,
2011.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
E:\FR\FM\13JYN1.SGM
13JYN1
Agencies
[Federal Register Volume 76, Number 134 (Wednesday, July 13, 2011)]
[Notices]
[Pages 41237-41238]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-17587]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12095-000]
Metropolitan Water District of Southern California; Notice of
Effectiveness of Surrender
On September 17, 2001, the Commission issued an Order Granting
Exemption from Licensing (Conduit) \1\ to the Metropolitan Water
District of Southern California (exemptee) for the OC-88 Small Conduit
Hydroelectric Project No. 12095. The project was located in the City of
Lake Forest in Orange County, California at the OC-88 Service
Connection, which transfers water from the Allen-McCulloch Pipeline to
the South County Pipeline.
---------------------------------------------------------------------------
\1\ Metropolitan Water District of Southern California, 96 FERC
] 62,259 (2001).
---------------------------------------------------------------------------
On September 20, 2005, staff from the Commission's San Francisco
Regional Office conducted an operation inspection of the project.
During the inspection, the exemptee advised Commission staff that it
intended to surrender the exemption and Commission staff observed that
the exemptee had capped off the penstock and electrically disconnected
the generator.
On November 4, 2005, the exemptee filed an application with the
Commission to surrender its exemption stating that, due to
modifications at the pump station, the physical connections necessary
for operation of the turbine generator no longer existed.
Accordingly, the Commission hereby gives notice and accepts the
Metropolitan Water District of Southern California's surrender of its
exemption from licensing for the OC-88 Small Conduit Hydroelectric
Project issued on
[[Page 41238]]
September 17, 2001, effective November 4, 2005.
Dated: July 7, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-17587 Filed 7-12-11; 8:45 am]
BILLING CODE 6717-01-P