Pacific Gas and Electric Company; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, and Preliminary Terms and Conditions, 37105-37106 [2011-15790]
Download as PDF
Federal Register / Vol. 76, No. 122 / Friday, June 24, 2011 / Notices
Comment Date: July 11, 2011.
Dated: June 20, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–15858 Filed 6–23–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2784–004]
srobinson on DSK4SPTVN1PROD with NOTICES
Pacific Gas and Electric Company;
Notice of Application Accepted for
Filing, Soliciting Motions To Intervene
and Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, and Preliminary
Terms and Conditions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License—Transmission Line Only.
b. Project No.: P–2784–004.
c. Date filed: April 18, 2011.
d. Applicant: Pacific Gas and Electric
Company.
e. Name of Project: Rollins
Transmission Line Project.
f. Location: The Rollins Transmission
Line Project is located in Placer and
Nevada counties, California.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Forrest
Sullivan, Senior Project Manager,
Pacific Gas and Electric Company, 5555
Florin Perkins Road, Sacramento, CA
95826. Tel: (916) 386–5580.
i. FERC Contact: Mary Greene, (202)
502–8865 or mary.greene@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, preliminary terms
and conditions: 60 days from the
issuance date of this notice; reply
comments are due 105 days from the
issuance date of this notice.
Motions to intervene, protests,
comments, recommendations,
preliminary terms and conditions may
be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
VerDate Mar<15>2010
19:06 Jun 23, 2011
Jkt 223001
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now is ready for
environmental analysis.
l. The Project is connected with the
Yuba-Bear Hydroelectric Project, FERC
project No. 2266, owned and operated
by the Nevada Irrigation District (NID).
Project facilities include a 3,851-ft long,
three-phase, 60-kilovolt (kV), wood-pole
transmission line extending from the
existing Rollins Powerhouse switchyard
to the junction with PG&E’s Drum-Gras
Valley-Weimer 60-kV transmission line.
The current project also includes a
single access road. The transmission
line right-of-way (ROW) is 40-ft in
width.
PG&E is not proposing to modify the
existing project and does not plan any
changes to the operation or maintenance
of the transmission line.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, .214. In determining the
appropriate action to take, the
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
37105
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST,’’ ‘‘MOTION
TO INTERVENE,’’ ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ or
‘‘PRELIMINARY TERMS AND
CONDITIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, or terms
and conditions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application. A copy of
all other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
o. Procedural Schedule:
The application will be processed
according to the following revised
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Filing of recommendations, and preliminary terms and conditions.
Commission issues
EA.
Comments on EA or
EIS.
Modified terms and
conditions.
Target date
August 16, 2011.
December 14, 2011.
January 30, 2012.
March 28, 2012.
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
q. A license applicant must file no
later than 60 days following the date of
issuance of the notice of acceptance and
ready for environmental analysis
provided for in § 5.22: (1) A copy of the
E:\FR\FM\24JNN1.SGM
24JNN1
37106
Federal Register / Vol. 76, No. 122 / Friday, June 24, 2011 / Notices
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: June 17, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–15790 Filed 6–23–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
srobinson on DSK4SPTVN1PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG11–94–000.
Applicants: Hatch Solar Energy
Center I, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Hatch Solar Energy
Center I, LLC.
Filed Date: 06/17/2011.
Accession Number: 20110617–5164.
Comment Date: 5 p.m. Eastern Time
on Friday, July 08, 2011.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER01–1305–018.
Applicants: Westar Generating, Inc.
Description: Westar Generating, Inc.
Informational Filing.
Filed Date: 06/17/2011.
Accession Number: 20110617–5154.
Comment Date: 5 p.m. Eastern Time
on Friday, July 08, 2011.
Docket Numbers: ER08–1501–002;
ER09–86–002.
Applicants: Southwestern Electric
Power Company.
Description: Compliance refund
report of Southwestern Electric Power
Company.
Filed Date: 06/17/2011.
Accession Number: 20110617–5175.
Comment Date: 5 p.m. Eastern Time
on Friday, July 08, 2011.
Docket Numbers: ER10–1786–002.
Applicants: Credit Suisse Energy,
LLC.
Description: Notice of Non-Material
Change in Status of Credit Suisse Energy
LLC.
Filed Date: 06/17/2011.
Accession Number: 20110617–5153.
Comment Date: 5 p.m. Eastern Time
on Friday, July 08, 2011.
Docket Numbers: ER10–2131–001.
Applicants: Grand Ridge Energy LLC.
VerDate Mar<15>2010
19:06 Jun 23, 2011
Jkt 223001
Description: Triennial Report of
Grand Ridge Energy LLC.
Filed Date: 06/20/2011.
Accession Number: 20110620–5093.
Comment Date: 5 p.m. Eastern Time
on Friday, August 19, 2011.
Docket Numbers: ER10–2133–001.
Applicants: Sheldon Energy LLC.
Description: Triennial Report of
Sheldon Energy LLC.
Filed Date: 06/20/2011.
Accession Number: 20110620–5116.
Comment Date: 5 p.m. Eastern Time
on Friday, August 19, 2011.
Docket Numbers: ER10–2137–001.
Applicants: Beech Ridge Energy LLC.
Description: Triennial Report of Beech
Ridge Energy LLC.
Filed Date: 06/20/2011.
Accession Number: 20110620–5094.
Comment Date: 5 p.m. Eastern Time
on Friday, August 19, 2011.
Docket Numbers: ER10–2140–001.
Applicants: Grand Ridge Energy IV
LLC.
Description: Triennial Report of
Grand Ridge Energy IV LLC.
Filed Date: 06/20/2011.
Accession Number: 20110620–5108.
Comment Date: 5 p.m. Eastern Time
on Friday, August 19, 2011.
Docket Numbers: ER10–2141–001.
Applicants: Grand Ridge Energy V
LLC.
Description: Triennial Report of
Grand Ridge Energy V LLC.
Filed Date: 06/20/2011.
Accession Number: 20110620–5106.
Comment Date: 5 p.m. Eastern Time
on Friday, August 19, 2011.
Docket Numbers: ER11–2207–001.
Applicants: Alta Wind IV, LLC.
Description: Alta Wind IV, LLC—
Notice of Non-Material Change in
Status.
Filed Date: 06/17/2011.
Accession Number: 20110617–5177.
Comment Date: 5 p.m. Eastern Time
on Friday, July 08, 2011.
Docket Numbers: ER11–3614–002.
Applicants: Glacial Energy Holdings.
Description: Glacial Energy Holdings
submits tariff filing per 35: Substitute
Market-based Tariff of Glacial Energy
Holdings to be effective 5/23/2011.
Filed Date: 06/20/2011.
Accession Number: 20110620–5000.
Comment Date: 5 p.m. Eastern Time
on Monday, July 11, 2011.
Docket Numbers: ER11–3826–000.
Applicants: Black Hills/Colorado
Electric Utility Company, LP.
Description: Black Hills/Colorado
Electric Utility Company, LP submits
tariff filing per 35.13(a)(1): Black Hills/
Colorado Electric Utility Company, LP,
Updated Rates and Tariff to be effective
8/15/2011.
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
Filed Date: 06/20/2011.
Accession Number: 20110620–5002.
Comment Date: 5 p.m. Eastern Time
on Monday, July 11, 2011.
Docket Numbers: ER11–3827–000.
Applicants: Genon Power Midwest,
LP.
Description: GenOn Power Midwest,
LP submits notice of cancellation of the
Connection and Site Agreement with
American Transmission Systems, Inc et
al.
Filed Date: 06/17/2011.
Accession Number: 20110620–0201.
Comment Date: 5 p.m. Eastern Time
on Friday, July 08, 2011.
Docket Numbers: ER11–3828–000.
Applicants: PJM Interconnection,
LLC.
Description: PJM Interconnection,
LLC submits tariff filing per
35.13(a)(2)(iii: PJM Queue No. W1–076;
Original Service Agreement No. 2945 to
be effective 5/20/2011.
Filed Date: 06/20/2011.
Accession Number: 20110620–5022.
Comment Date: 5 p.m. Eastern Time
on Monday, July 11, 2011.
Docket Numbers: ER11–3829–000.
Applicants: Wisconsin Power and
Light Company.
Description: Wisconsin Power and
Light Company submits tariff filing per
35.13(a)(2)(iii: WPL NSP–LBAAOCA to
be effective 6/20/2011.
Filed Date: 06/20/2011.
Accession Number: 20110620–5024.
Comment Date: 5 p.m. Eastern Time
on Monday, July 11, 2011.
Docket Numbers: ER11–3830–000.
Applicants: Avista Corporation.
Description: Avista Corporation
submits tariff filing per 35.13(a)(2)(iii:
Revised Appendix 6 to Attachment M to
be effective 8/20/2011.
Filed Date: 06/20/2011.
Accession Number: 20110620–5081.
Comment Date: 5 p.m. Eastern Time
on Monday, July 11, 2011.
Docket Numbers: ER11–3831–000.
Applicants: PJM Interconnection,
LLC.
Description: PJM Interconnection,
LLC submits tariff filing per
35.13(a)(2)(iii: Queue Position No. W1–
024 ? Original Service Agreement No.
2943 to be effective 5/20/2011.
Filed Date: 06/20/2011.
Accession Number: 20110620–5083.
Comment Date: 5 p.m. Eastern Time
on Monday, July 11, 2011.
Docket Numbers: ER11–3832–000.
Applicants: Southern California
Edison Company.
Description: Southern California
Edison Company submits tariff filing
per 35.13(a)(2)(iii: Walnut Creek Energy
E:\FR\FM\24JNN1.SGM
24JNN1
Agencies
[Federal Register Volume 76, Number 122 (Friday, June 24, 2011)]
[Notices]
[Pages 37105-37106]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-15790]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2784-004]
Pacific Gas and Electric Company; Notice of Application Accepted
for Filing, Soliciting Motions To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting Comments, Recommendations, and
Preliminary Terms and Conditions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent License--Transmission Line Only.
b. Project No.: P-2784-004.
c. Date filed: April 18, 2011.
d. Applicant: Pacific Gas and Electric Company.
e. Name of Project: Rollins Transmission Line Project.
f. Location: The Rollins Transmission Line Project is located in
Placer and Nevada counties, California.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Forrest Sullivan, Senior Project Manager,
Pacific Gas and Electric Company, 5555 Florin Perkins Road, Sacramento,
CA 95826. Tel: (916) 386-5580.
i. FERC Contact: Mary Greene, (202) 502-8865 or
mary.greene@ferc.gov.
j. Deadline for filing motions to intervene and protests, comments,
recommendations, preliminary terms and conditions: 60 days from the
issuance date of this notice; reply comments are due 105 days from the
issuance date of this notice.
Motions to intervene, protests, comments, recommendations,
preliminary terms and conditions may be filed electronically via the
Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the
Commission's Web site https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1-
866-208-3676, or for TTY, (202) 502-8659. Although the Commission
strongly encourages electronic filing, documents may also be paper-
filed. To paper-file, mail an original and seven copies to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted for filing and is now is
ready for environmental analysis.
l. The Project is connected with the Yuba-Bear Hydroelectric
Project, FERC project No. 2266, owned and operated by the Nevada
Irrigation District (NID). Project facilities include a 3,851-ft long,
three-phase, 60-kilovolt (kV), wood-pole transmission line extending
from the existing Rollins Powerhouse switchyard to the junction with
PG&E's Drum-Gras Valley-Weimer 60-kV transmission line. The current
project also includes a single access road. The transmission line
right-of-way (ROW) is 40-ft in width.
PG&E is not proposing to modify the existing project and does not
plan any changes to the operation or maintenance of the transmission
line.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, .214. In determining the appropriate action to
take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must (1) bear in all capital letters the title
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' or ``PRELIMINARY TERMS AND CONDITIONS;'' (2) set
forth in the heading the name of the applicant and the project number
of the application to which the filing responds; (3) furnish the name,
address, and telephone number of the person protesting or intervening;
and (4) otherwise comply with the requirements of 18 CFR 385.2001
through 385.2005. All comments, recommendations, or terms and
conditions must set forth their evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of
the application directly from the applicant. A copy of any protest or
motion to intervene must be served upon each representative of the
applicant specified in the particular application. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
o. Procedural Schedule:
The application will be processed according to the following
revised Hydro Licensing Schedule. Revisions to the schedule may be made
as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Filing of recommendations, and preliminary August 16, 2011.
terms and conditions.
Commission issues EA...................... December 14, 2011.
Comments on EA or EIS..................... January 30, 2012.
Modified terms and conditions............. March 28, 2012.
------------------------------------------------------------------------
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
q. A license applicant must file no later than 60 days following
the date of issuance of the notice of acceptance and ready for
environmental analysis provided for in Sec. 5.22: (1) A copy of the
[[Page 37106]]
water quality certification; (2) a copy of the request for
certification, including proof of the date on which the certifying
agency received the request; or (3) evidence of waiver of water quality
certification.
Dated: June 17, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-15790 Filed 6-23-11; 8:45 am]
BILLING CODE 6717-01-P