Blue Heron Hydro LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 35873-35874 [2011-15172]
Download as PDF
35873
Federal Register / Vol. 76, No. 118 / Monday, June 20, 2011 / Notices
requirements of FERC–603 ‘‘Critical
Energy Infrastructure Information’’
(OMB No. 1902–0197) is used by the
Commission to implement procedures
for gaining access to critical energy
infrastructure information (CEII) that
would not otherwise be available under
the Freedom of Information Act (5
U.S.C. 552). On February 21, 2003, the
Commission issued Order No. 630 (66
FR 52917) to address the appropriate
treatment of CEII in the aftermath of the
September 11, 2001 terrorist attacks and
to restrict unrestrained general access
due to the ongoing terrorism threat.
These steps enable the Commission to
keep sensitive infrastructure
information out of the public domain,
decreasing the likelihood that such
information could be used to plan or
would negatively affect security,
economic security, public health or
safety, or any combination of those
matters. A person seeking access to CEII
may file a request for that information
by providing information about their
identity and reason as to the need for
the information. Through this process,
the Commission is able to review the
requester’s need for the information
against the sensitivity of the
information. The compliance with these
requirements is mandatory.
Action: The Commission is requesting
a three-year extension of the current
expiration date, with no changes to the
existing collection of data.
Burden Statement: Public reporting
burden for this collection is estimated
as:
execute terrorist attacks. The process
adopted in Order No. 630 is a more
efficient alternative for handling
requests for previously public
documents than FOIA. The Commission
has defined CEII to include information
about ‘‘existing or proposed critical
infrastructure that (i) Relates to the
production, generation, transportation,
transmission, or distribution of energy;
(ii) could be useful to a person planning
an attack on critical infrastructure; (iii)
is exempt from mandatory disclosure
under the Freedom of Information Act,
and (iv) does not simply give the
location of the critical infrastructure.
Critical infrastructure means existing
and proposed systems and assets,
whether physical or virtual, the
incapacity or destruction of which
Number of
respondents
annually 1
(1)
Number of
responses per
respondent (2)
Average burden
hours per
response (3)
Total annual
burden hours
(1)
Data collection
(2)
(3)
(1) × (2) × (3)
200
1
.3
60
FERC–603 .......................................................................................
1 The
sroberts on DSK5SPTVN1PROD with NOTICES
number of respondents corresponds to the number of requests received annually while recognizing that some CEII requests are filed by
multiple parties.
The estimated total cost to
respondents is $4,080. The cost per
respondent = $20.40. (60 hours @ $68
hourly rate). The reporting burden
includes the total time, effort, or
financial resources expended to
generate, maintain, retain, disclose, or
provide the information including: (1)
Reviewing instructions; (2) developing,
acquiring, installing, and utilizing
technology and systems for the purposes
of collecting, validating, verifying,
processing, maintaining, disclosing and
providing information; (3) adjusting the
existing ways to comply with any
previously applicable instructions and
requirements; (4) training personnel to
respond to a collection of information;
(5) searching data sources; (6)
completing and reviewing the collection
of information; and (7) transmitting, or
otherwise disclosing the information.
The estimate of cost for respondents
is based upon salaries for professional
and clerical support, as well as direct
and indirect overhead costs. Direct costs
include all costs directly attributable to
providing this information, such as
administrative costs and the cost for
information technology. Indirect or
overhead costs are costs incurred by an
organization in support of its mission.
These costs apply to activities which
benefit the whole organization rather
than any one particular function or
activity.
VerDate Mar<15>2010
18:24 Jun 17, 2011
Jkt 223001
Comments are invited on: (1) Whether
the proposed collection of information
is necessary for the proper performance
of the functions of the Commission,
including whether the information will
have practical utility; (2) the accuracy of
the agency’s estimates of the burden of
the proposed collection of information,
including the validity of the
methodology and assumptions used; (3)
ways to enhance the quality, utility and
clarity of the information to be
collected; and (4) ways to minimize the
burden of the collections of information
on those who are to respond, including
the use of appropriate automated,
electronic, mechanical, or other
technological collection techniques or
other forms of information technology,
e.g. permitting electronic submission of
responses.
Dated: June 9, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–14900 Filed 6–17–11; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Project No. 13226–003]
Blue Heron Hydro LLC; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: 13226–003.
c. Date filed: November 1, 2010.
d. Applicant: Blue Heron Hydro LLC.
e. Name of Project: Ball Mountain
Dam Hydroelectric Project.
f. Location: At the U.S. Army Corps of
Engineers Ball Mountain Dam on the
West River near the Town of Jamaica,
Windham County, Vermont.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Lori Barg, Blue
Heron Hydro LLC, 113 Bartlett Road,
Plainfield, Vermont 05667. (802) 454–
1874.
i. FERC Contact: Dr. Nicholas Palso,
(202) 502–8854 or
nicholas.palso@ferc.gov.
E:\FR\FM\20JNN1.SGM
20JNN1
sroberts on DSK5SPTVN1PROD with NOTICES
35874
Federal Register / Vol. 76, No. 118 / Monday, June 20, 2011 / Notices
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. Project Description: The Ball
Mountain Dam Hydroelectric Project
would utilize the U.S. Army Corps of
Engineers’ existing Ball Mountain Dam
and reservoir and would consist of: (1)
Two turbine generator modules located
within the existing intake tower, each
containing 6 horizontal mixed flow
turbines directly connected to 6
submersible generator units for a total
installed capacity of 2,200 kilowatts; (2)
a new 12.47-kilovolt, 1,320-foot-long
transmission line; and (3) appurtenant
facilities. The project would have an
estimated average annual generation of
approximately 6,000 megawatt-hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
VerDate Mar<15>2010
16:50 Jun 17, 2011
Jkt 223001
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) Bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
Dated: June 13, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–15172 Filed 6–17–11; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2277–023]
Union Electric Company (dba Ameren
Missouri); Notice of Application
Accepted for Filing and Soliciting
Motions To Intervene and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2277–023.
c. Date filed: June 24, 2008.
d. Applicant: Union Electric Company
(dba Ameren Missouri).
e. Name of Project: Taum Sauk
Pumped Storage Project.
f. Location: On the East Fork of the
Black River, in Reynolds County,
Missouri. The project occupies no
federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Michael O.
Lobbig, P.E., Managing Supervisor,
Hydro Licensing, Ameren Missouri,
3700 S. Lindbergh Blvd, St. Louis, MO
63127; telephone 314–957–3427; e-mail
at mlobbig@ameren.com.
i. FERC Contact: Janet Hutzel,
telephone (202) 502–8675, or by e-mail
at janet.hutzel@ferc.gov.
j. Deadline for filing motions to
intervene and protests: August 15, 2011.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
E:\FR\FM\20JNN1.SGM
20JNN1
Agencies
[Federal Register Volume 76, Number 118 (Monday, June 20, 2011)]
[Notices]
[Pages 35873-35874]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-15172]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Project No. 13226-003]
Blue Heron Hydro LLC; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: 13226-003.
c. Date filed: November 1, 2010.
d. Applicant: Blue Heron Hydro LLC.
e. Name of Project: Ball Mountain Dam Hydroelectric Project.
f. Location: At the U.S. Army Corps of Engineers Ball Mountain Dam
on the West River near the Town of Jamaica, Windham County, Vermont.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Lori Barg, Blue Heron Hydro LLC, 113 Bartlett
Road, Plainfield, Vermont 05667. (802) 454-1874.
i. FERC Contact: Dr. Nicholas Palso, (202) 502-8854 or
nicholas.palso@ferc.gov.
[[Page 35874]]
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. Project Description: The Ball Mountain Dam Hydroelectric Project
would utilize the U.S. Army Corps of Engineers' existing Ball Mountain
Dam and reservoir and would consist of: (1) Two turbine generator
modules located within the existing intake tower, each containing 6
horizontal mixed flow turbines directly connected to 6 submersible
generator units for a total installed capacity of 2,200 kilowatts; (2)
a new 12.47-kilovolt, 1,320-foot-long transmission line; and (3)
appurtenant facilities. The project would have an estimated average
annual generation of approximately 6,000 megawatt-hours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
All filings must (1) Bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
Dated: June 13, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-15172 Filed 6-17-11; 8:45 am]
BILLING CODE 6717-01-P