Piedmont Natural Gas Company, Inc.; Notice of Application, 35202-35203 [2011-14964]
Download as PDF
35202
Federal Register / Vol. 76, No. 116 / Thursday, June 16, 2011 / Notices
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Procedural Schedule: The
application will be processed according
to the following revised Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Filing of recommendations, preliminary terms and conditions, and preliminary fishway prescriptions ..................................
Commission issues Single EA .................................................................................................................................................
Comments on EA ....................................................................................................................................................................
Modified terms and conditions .................................................................................................................................................
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
q. A license applicant must file no
later than 60 days following the date of
issuance of the notice of acceptance and
ready for environmental analysis
provided for in 5.22: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: June 10, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–14967 Filed 6–15–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–495–000]
srobinson on DSK4SPTVN1PROD with NOTICES
Piedmont Natural Gas Company, Inc.;
Notice of Application
On June 3, 2011, Piedmont Natural
Gas Company, Inc. (Piedmont) filed
with the Federal Energy Regulatory
Commission (Commission) an
application pursuant to section 7(f) of
the Natural Gas Act (NGA), as amended,
and section 157 of the Commission’s
Regulations, for service area
determination for their Charlotte, North
Carolina and Fort Mill, South Carolina
service areas, all as more fully set forth
in the application, which is on file with
the Commission and open to public
inspection. The filing may also be
viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. There is
an ‘‘eSubscription’’ link on the Web site
that enables subscribers to receive
e-mail notification when a document is
added to a subscribed docket(s). For
VerDate Mar<15>2010
17:18 Jun 15, 2011
Jkt 223001
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Questions regarding this application
should be directed to Michelle R.
Mendoza, Piedmont Natural Gas
Company, Inc., Post Office Box 33068,
Charlotte, NC 28233 or by e-mailing
michelle.mendoza@piedmontng.com or
to James H. Jeffries IV, Moore & Van
Allen PLLC, 100 North Tryon Street,
Suite 4700, Charlotte, NC 28202–4003
or by calling 704–331–1079 or by
e-mailing mvaferc@mvalaw.com.
Pursuant to section 157.9 of the
Commission’s rules, within 90 days of
this Notice the Commission staff will
either: complete its environmental
assessment (EA) and place it into the
Commission’s public record (eLibrary)
for this proceeding; or issue a Notice of
Schedule for Environmental Review. If
a Notice of Schedule for Environmental
Review is issued, it will indicate, among
other milestones, the anticipated date
for the Commission staff’s issuance of
the final environmental impact
statement (FEIS) or EA for this proposal.
The filing of the EA in the
Commission’s public record for this
proceeding or the issuance of a Notice
of Schedule for Environmental Review
will serve to notify Federal and state
agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
Federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
August 9, 2011.
December 7, 2011.
January 6, 2011.
March 5, 2012.
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
seven copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
E:\FR\FM\16JNN1.SGM
16JNN1
Federal Register / Vol. 76, No. 116 / Thursday, June 16, 2011 / Notices
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit original
and seven copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comment Date: July 1, 2011.
Dated: June 10, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–14964 Filed 6–15–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–493–000]
srobinson on DSK4SPTVN1PROD with NOTICES
Dominion Transmission, Inc.; Notice
Application
Take notice that on May 27, 2011,
Dominion Transmission, Inc.
(Dominion), filed an application in
Docket No. CP11–493–000 pursuant to
section 7(c) of the Natural Gas Act
(NGA) and Part 157 of the Commission’s
Regulations, for a certificate of public
convenience and necessity to: (1) Revise
the active storage boundary; and (2)
establish a protective boundary for the
Woodhull Storage Pool located in
Steuben County, New York, all as more
fully set forth in the applications which
is on file with the Commission and open
for public inspection.
Any questions regarding this
application should be directed to
Amanda K. Prestage, Regulatory and
Certificates Analyst III, Dominion
Transmission, Inc., 701 East Cary Street,
Richmond, Virginia 23219, or call at
(804) 771–4416.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify Federal and
VerDate Mar<15>2010
17:18 Jun 15, 2011
Jkt 223001
State agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
Federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA
(18 CFR 157.10). A person obtaining
party status will be placed on the
service list maintained by the Secretary
of the Commission and will receive
copies of all documents filed by the
applicant and by all other parties. A
party must submit 7 copies of filings
made with the Commission and must
mail a copy to the applicant and to
every other party in the proceeding.
Only parties to the proceeding can ask
for court review of Commission orders
in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
35203
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 7 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: July 1, 2011.
Dated: June 10, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–14963 Filed 6–15–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER05–644–013.
Applicants: PSEG Energy Resources &
Trade LLC.
Description: Informational Filing with
a list of planned Additional Project
Investments of the PSEG Companies.
Filed Date: 06/03/2011.
Accession Number: 20110603–5417.
Comment Date: 5 p.m. Eastern Time
on Friday, June 24, 2011.
Docket Numbers: ER11–2617–002.
Applicants: ISO New England Inc.,
Vermont Electric Power Company, Inc.
Description: ISO New England Inc.
submits tariff filing per 35: PTO
Compliance Filing—ER11–2617, to be
effective 4/1/2011.
Filed Date: 06/09/2011.
Accession Number: 20110609–5014.
Comment Date: 5 p.m. Eastern Time
on Thursday, June 30, 2011.
Docket Numbers: ER11–2999–003.
E:\FR\FM\16JNN1.SGM
16JNN1
Agencies
[Federal Register Volume 76, Number 116 (Thursday, June 16, 2011)]
[Notices]
[Pages 35202-35203]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-14964]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP11-495-000]
Piedmont Natural Gas Company, Inc.; Notice of Application
On June 3, 2011, Piedmont Natural Gas Company, Inc. (Piedmont)
filed with the Federal Energy Regulatory Commission (Commission) an
application pursuant to section 7(f) of the Natural Gas Act (NGA), as
amended, and section 157 of the Commission's Regulations, for service
area determination for their Charlotte, North Carolina and Fort Mill,
South Carolina service areas, all as more fully set forth in the
application, which is on file with the Commission and open to public
inspection. The filing may also be viewed on the Web at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. There is an ``eSubscription'' link on the Web site that
enables subscribers to receive e-mail notification when a document is
added to a subscribed docket(s). For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TTY,
(202) 502-8659.
Questions regarding this application should be directed to Michelle
R. Mendoza, Piedmont Natural Gas Company, Inc., Post Office Box 33068,
Charlotte, NC 28233 or by e-mailing michelle.mendoza@piedmontng.com or
to James H. Jeffries IV, Moore & Van Allen PLLC, 100 North Tryon
Street, Suite 4700, Charlotte, NC 28202-4003 or by calling 704-331-1079
or by e-mailing mvaferc@mvalaw.com.
Pursuant to section 157.9 of the Commission's rules, within 90 days
of this Notice the Commission staff will either: complete its
environmental assessment (EA) and place it into the Commission's public
record (eLibrary) for this proceeding; or issue a Notice of Schedule
for Environmental Review. If a Notice of Schedule for Environmental
Review is issued, it will indicate, among other milestones, the
anticipated date for the Commission staff's issuance of the final
environmental impact statement (FEIS) or EA for this proposal. The
filing of the EA in the Commission's public record for this proceeding
or the issuance of a Notice of Schedule for Environmental Review will
serve to notify Federal and state agencies of the timing for the
completion of all necessary reviews, and the subsequent need to
complete all Federal authorizations within 90 days of the date of
issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit seven copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
[[Page 35203]]
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit original and seven copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
Comment Date: July 1, 2011.
Dated: June 10, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-14964 Filed 6-15-11; 8:45 am]