Union Electric Company (dba Ameren Missouri); Notice of Scoping Meetings and Environmental Site Review and Soliciting Scoping Comments, 31322-31323 [2011-13316]
Download as PDF
31322
Federal Register / Vol. 76, No. 104 / Tuesday, May 31, 2011 / Notices
Number of
respondents 6
Average
number of
responses per
respondent
Average number
of burden hours
per response 7
Total annual
hours
(1)
Data collection
(2)
(3)
(1) × (2) × (3)
Totals .......................................................
mstockstill on DSK4VPTVN1PROD with NOTICES
The total estimated annual cost
burden to respondents is:
• Category 1, Entities that have
identified Critical Assets = 658,560
(662,400¥3,840) hours @ $96 =
$63,221,760
• Category 2, Entities that have not
identified Critical Assets = 138,240
(138,720¥480) hours @ $96 =
$13,271,040
• Category 3, New U.S. Entities that
have to comply with CIP Standards =
23,040 hours @ $96 = $2,211,840
• Storage Costs for Entities that have
identified Critical Assets 9 = 345 Entities
@ $15.25 = $5,261
• Total Cost for the FERC–725B =
$78,709,901
The hourly rate of $96 is the average
cost of legal services ($230 per hour),
technical employees ($40 per hour) and
administrative support ($18 per hour),
6 The NERC Compliance Registry as of 9/28/2010
indicated that 2079 entities were registered for
NERC’s compliance program. Of these, 2057 were
identified as being U.S. entities. Staff concluded
that of the 2057 U.S. entities, only 1501 were
registered for at least one CIP-related function.
According to an April 7, 2009, memo to industry,
NERC’s VP and Chief Security Officer noted that
only 31% of entities responded to an earlier survey
and reported that they had at least one Critical
Asset, and only 23% reported having a Critical
Cyber Asset. Staff applied the 23% reporting to the
1501 figure to obtain an estimate. The 6 new
entities listed here are assumed to match a similar
set of 6 entities that would drop out in an existing
year. Thus, the net estimate of respondents remains
at 1501 per year.
7 Calculations:
Respondent category 3:
20 employees × (working 50%) × (40 hrs/week)
× (8 weeks) = 3200 hours
20 employees × (working 20%) × (3200 hrs) = 640
hours
Total = 3840
Respondent category 2:
3 employees × (working 50%) × (40 hrs/week) ×
(2 weeks) = 120 hours
Respondent category 1:
50% of 3840 hours = 1920
8 These respondents and those in the subsequent
column of the table (with the corresponding burden
and cost figures) were not included in the 60-day
public notice due to an oversight by Commission
staff.
9 This cost category was not included in the 60day public notice due to an oversight by
Commission staff.
VerDate Mar<15>2010
17:27 May 27, 2011
Jkt 223001
Category 1: ¥2 .............
1
Category 1 (2 respondents): 1,920.
¥3,840
Category 2: ¥4 .............
Entities no longer required to comply with
CIP Standards (Two category 1 respondents and four category 2 respondents).
............................
Category 2 (4 respondents): 120.
¥480
1,501 .............................
............................
..........................................
based on hourly rates from the Bureau
of Labor Statistics (BLS) and the 2009
Billing Rates and Practices Survey
Report.10 The $15.25 rate for storage
costs for each entity is an estimate based
on the average costs to service and store
1 GB of data to demonstrate compliance
with the CIP Standards.11
The reporting burden includes the
total time, effort, or financial resources
expended to generate, maintain, retain,
disclose, or provide the information
including: (1) Reviewing instructions;
(2) developing, acquiring, installing, and
utilizing technology and systems for the
purposes of collecting, validating,
verifying, processing, maintaining,
disclosing and providing information;
(3) adjusting the existing ways to
comply with any previously applicable
instructions and requirements; (4)
training personnel to respond to a
collection of information; (5) searching
data sources; (6) completing and
reviewing the collection of information;
and (7) transmitting, or otherwise
disclosing the information.
Comments are invited on: (1) Whether
the proposed collection of information
is necessary for the proper performance
of the functions of the Commission,
including whether the information will
have practical utility; (2) the accuracy of
the agency’s estimates of the burden of
the proposed collection of information,
including the validity of the
methodology and assumptions used; (3)
ways to enhance the quality, utility and
clarity of the information to be
collected; and (4) ways to minimize the
burden of the collections of information
on those who are to respond, including
the use of appropriate automated,
10 Bureau of Labor Statistics figures were obtained
from https://www.bls.gov/oes/current/naics2_
22.htm, and 2009 Billing Rates figures were
obtained from https://www.marylandlawyerblog.
com/2009/07/average_hourly_rate_for_lawyer.html.
Legal services were based on the national average
billing rate (contracting out) from the above report
and BLS hourly earnings (in-house personnel). It is
assumed that 25% of respondents have in-house
legal personnel.
11 Based on the aggregate cost of an IBM advanced
data protection server.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
819,840
electronic, mechanical, or other
technological collection techniques or
other forms of information technology,
e.g. permitting electronic submission of
responses.
Dated: May 25, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–13475 Filed 5–27–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2277–023]
Union Electric Company (dba Ameren
Missouri); Notice of Scoping Meetings
and Environmental Site Review and
Soliciting Scoping Comments
Take notice that the following
hydroelectric application has been filed
with Commission and is available for
public inspection:
a. Type of Application: New Major
License.
b. Project No.: 2277–023.
c. Date filed: June 24, 2008.
d. Applicant: Union Electric Company
(dba Ameren Missouri).
e. Name of Project: Taum Sauk
Pumped Storage Project.
f. Location: On the East Fork of the
Black River, in Reynolds County,
Missouri. The project occupies no
Federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Michael O.
Lobbig, P.E., Managing Supervisor,
Hydro Licensing, Ameren Missouri,
3700 S. Lindbergh Blvd., St. Louis, MO
63127; telephone 314–957–3427; e-mail
at mlobbig@ameren.com.
i. FERC Contact: Janet Hutzel,
telephone (202) 502–8675, or by e-mail
at janet.hutzel@ferc.gov.
j. Deadline for filing scoping
comments: July 23, 2011.
All documents may be filed
electronically via the Internet. See 18
E:\FR\FM\31MYN1.SGM
31MYN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 76, No. 104 / Tuesday, May 31, 2011 / Notices
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervener
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application is not ready for
environmental analysis at this time.
l. The existing Taum Sauk Pumped
Storage Project consists of: (1) A lower
reservoir impounded by a concrete
gravity dam downstream of the
confluence of the East Fork Black River
and Taum Sauk Creek; (2) an upper
reservoir on the top of Proffit Mountain
impounded by a rebuilt rollercompacted concrete dam; (3) vertical
shaft, rock and concrete-lined tunnel
sections, and a penstock conduit; (4) a
pump-generating plant with two
reversible pump units and two motor
generators with a total installed capacity
of 408 megawatts; (5) an excavated
tailrace and open channel to the lower
reservoir; (6) a 138-kilovolt switchyard/
substation; (7) a gravel and
sedimentation trap (bin wall) on the
East Fork of the Black River; and (8)
associated ancillary equipment.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
VerDate Mar<15>2010
17:27 May 27, 2011
Jkt 223001
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Scoping Process
The Commission intends to prepare
an environmental assessment (EA) on
the project in accordance with the
National Environmental Policy Act. The
EA will consider both site-specific and
cumulative environmental impacts and
reasonable alternatives to the proposed
action.
Scoping Meetings
Commission staff will conduct one
agency scoping meeting and one public
meeting. The agency scoping meeting
will focus on resource agency and nongovernmental organization concerns,
while the public scoping meeting is
primarily for public input. All
interested individuals, organizations,
and agencies are invited to attend one
or both of the meetings, and to assist the
staff in identifying the scope of the
environmental issues that should be
analyzed in the EA. The times and
locations of these meetings are as
follows:
Agency Scoping Meeting
Date and Time: Thursday, June 23,
2011, at 9 a.m. (CDT).
Location: LaCharette Conference Room,
Lewis and Clark State Office
Building, 1101 Riverside Drive,
Jefferson City, MO.
Public Scoping Meeting
Date and Time: Wednesday, June 22,
2011 at 6 p.m. (CDT).
Location: Lesterville R–IV School,
Cafeteria, 33415 Hwy. 21,
Lesterville, MO.
Copies of the Scoping Document
(SD1) outlining the subject areas to be
addressed in the EA were distributed to
the parties on the Commission’s mailing
list. Copies of the SD1 will be available
at the scoping meeting or may be
viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link
(see item m above).
Environmental Site Review
Ameren Missouri and Commission
staff will conduct a project
environmental site review on
Wednesday, June 22, 2011, at 8 a.m.
CDT. All interested individuals,
organizations, and agencies are invited
to attend. All participants will be
required to sign their name and show a
government-issued, photo I.D.
Participants must wear hard-soled
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
31323
shoes; no sandals or open-toed shoes are
allowed. Smoking will not be allowed
on the site review, and firearms, knives,
or weapons of any kind are not
permitted on Ameren Missouri
property. Please arrive 15 minutes early
to allow time for visitor badging at the
main security gate. All participants
must contact Mr. Michael Lobbig of
Ameren Missouri at (314) 957–3427 or
by e-mail at mlobbig@ameren.com, by
June 9, 2011, to attend the
environmental site review.
At the scoping meetings, the staff will:
(1) Summarize the environmental issues
tentatively identified for analysis in the
EA; (2) solicit from the meeting
participants all available information,
especially quantifiable data, on the
resources at issue; (3) encourage
statements from experts and the public
on issues that should be analyzed in the
EA, including viewpoints in opposition
to, or in support of, the staff’s
preliminary views; (4) determine the
resource issues to be addressed in the
EA; and (5) identify those issues that
require a detailed analysis, as well as
those issues that do not require a
detailed analysis.
Procedures
The meetings are recorded by a
stenographer and become part of the
formal record of the Commission
proceeding on the project.
Individuals, organizations, and
agencies with environmental expertise
and concerns are encouraged to attend
the meeting and to assist the staff in
defining and clarifying the issues to be
addressed in the EA.
Dated: May 23, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–13316 Filed 5–27–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–485–000]
Distrigas of Massachusetts LLC;
Notice of Application
Take notice that on May 18, 2011,
Distrigas of Massachusetts LLC
(DOMAC), 20 City Square, Suite 3,
Charlestown, MA 02129, filed in Docket
No. CP11–485–000, an application,
pursuant to section 3 of the Natural Gas
Act (NGA), as amended, and Parts 153
and 380 of the Commission’s
Regulations, for authority to construct,
install and operate a heating value and
E:\FR\FM\31MYN1.SGM
31MYN1
Agencies
[Federal Register Volume 76, Number 104 (Tuesday, May 31, 2011)]
[Notices]
[Pages 31322-31323]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-13316]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2277-023]
Union Electric Company (dba Ameren Missouri); Notice of Scoping
Meetings and Environmental Site Review and Soliciting Scoping Comments
Take notice that the following hydroelectric application has been
filed with Commission and is available for public inspection:
a. Type of Application: New Major License.
b. Project No.: 2277-023.
c. Date filed: June 24, 2008.
d. Applicant: Union Electric Company (dba Ameren Missouri).
e. Name of Project: Taum Sauk Pumped Storage Project.
f. Location: On the East Fork of the Black River, in Reynolds
County, Missouri. The project occupies no Federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Michael O. Lobbig, P.E., Managing Supervisor,
Hydro Licensing, Ameren Missouri, 3700 S. Lindbergh Blvd., St. Louis,
MO 63127; telephone 314-957-3427; e-mail at mlobbig@ameren.com.
i. FERC Contact: Janet Hutzel, telephone (202) 502-8675, or by e-
mail at janet.hutzel@ferc.gov.
j. Deadline for filing scoping comments: July 23, 2011.
All documents may be filed electronically via the Internet. See 18
[[Page 31323]]
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676,
or for TTY, (202) 502-8659. Although the Commission strongly encourages
electronic filing, documents may also be paper-filed. To paper-file,
mail an original and seven copies to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
The Commission's Rules of Practice and Procedure require all
interveners filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application is not ready for environmental analysis at this
time.
l. The existing Taum Sauk Pumped Storage Project consists of: (1) A
lower reservoir impounded by a concrete gravity dam downstream of the
confluence of the East Fork Black River and Taum Sauk Creek; (2) an
upper reservoir on the top of Proffit Mountain impounded by a rebuilt
roller-compacted concrete dam; (3) vertical shaft, rock and concrete-
lined tunnel sections, and a penstock conduit; (4) a pump-generating
plant with two reversible pump units and two motor generators with a
total installed capacity of 408 megawatts; (5) an excavated tailrace
and open channel to the lower reservoir; (6) a 138-kilovolt switchyard/
substation; (7) a gravel and sedimentation trap (bin wall) on the East
Fork of the Black River; and (8) associated ancillary equipment.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Scoping Process
The Commission intends to prepare an environmental assessment (EA)
on the project in accordance with the National Environmental Policy
Act. The EA will consider both site-specific and cumulative
environmental impacts and reasonable alternatives to the proposed
action.
Scoping Meetings
Commission staff will conduct one agency scoping meeting and one
public meeting. The agency scoping meeting will focus on resource
agency and non-governmental organization concerns, while the public
scoping meeting is primarily for public input. All interested
individuals, organizations, and agencies are invited to attend one or
both of the meetings, and to assist the staff in identifying the scope
of the environmental issues that should be analyzed in the EA. The
times and locations of these meetings are as follows:
Agency Scoping Meeting
Date and Time: Thursday, June 23, 2011, at 9 a.m. (CDT).
Location: LaCharette Conference Room, Lewis and Clark State Office
Building, 1101 Riverside Drive, Jefferson City, MO.
Public Scoping Meeting
Date and Time: Wednesday, June 22, 2011 at 6 p.m. (CDT).
Location: Lesterville R-IV School, Cafeteria, 33415 Hwy. 21,
Lesterville, MO.
Copies of the Scoping Document (SD1) outlining the subject areas to
be addressed in the EA were distributed to the parties on the
Commission's mailing list. Copies of the SD1 will be available at the
scoping meeting or may be viewed on the Web at https://www.ferc.gov
using the ``eLibrary'' link (see item m above).
Environmental Site Review
Ameren Missouri and Commission staff will conduct a project
environmental site review on Wednesday, June 22, 2011, at 8 a.m. CDT.
All interested individuals, organizations, and agencies are invited to
attend. All participants will be required to sign their name and show a
government-issued, photo I.D. Participants must wear hard-soled shoes;
no sandals or open-toed shoes are allowed. Smoking will not be allowed
on the site review, and firearms, knives, or weapons of any kind are
not permitted on Ameren Missouri property. Please arrive 15 minutes
early to allow time for visitor badging at the main security gate. All
participants must contact Mr. Michael Lobbig of Ameren Missouri at
(314) 957-3427 or by e-mail at mlobbig@ameren.com, by June 9, 2011, to
attend the environmental site review.
At the scoping meetings, the staff will: (1) Summarize the
environmental issues tentatively identified for analysis in the EA; (2)
solicit from the meeting participants all available information,
especially quantifiable data, on the resources at issue; (3) encourage
statements from experts and the public on issues that should be
analyzed in the EA, including viewpoints in opposition to, or in
support of, the staff's preliminary views; (4) determine the resource
issues to be addressed in the EA; and (5) identify those issues that
require a detailed analysis, as well as those issues that do not
require a detailed analysis.
Procedures
The meetings are recorded by a stenographer and become part of the
formal record of the Commission proceeding on the project.
Individuals, organizations, and agencies with environmental
expertise and concerns are encouraged to attend the meeting and to
assist the staff in defining and clarifying the issues to be addressed
in the EA.
Dated: May 23, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-13316 Filed 5-27-11; 8:45 am]
BILLING CODE 6717-01-P