California Independent System Operator Corporation; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 30339 [2011-12890]

Download as PDF Federal Register / Vol. 76, No. 101 / Wednesday, May 25, 2011 / Notices or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 7 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on Wednesday, May 25, 2011. Dated: May 18, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–12866 Filed 5–24–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL11–41–000] WReier-Aviles on DSKGBLS3C1PROD with NOTICES California Independent System Operator Corporation; Notice of Institution of Section 206 Proceeding and Refund Effective Date On May 19, 2011, the Commission issued an order that instituted an investigation in Docket No. EL11–41– 000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e, to evaluate the justness and reasonableness of section 10.3.6.3 of the California Independent System Operator Corporation’s tariff. Cal. Indep. Operator Corp., 135 FERC ¶ 61,159 (2011). The refund effective date in Docket No. EL11–41–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register. Dated: May 19, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–12890 Filed 5–24–11; 8:45 am] BILLING CODE 6717–01–P VerDate Mar<15>2010 17:06 May 24, 2011 Jkt 223001 DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission 30339 Federal Energy Regulatory Commission [Project No. 14120–000] [Docket No. CP11–128–000] National Fuel Gas Supply Corporation; Notice of Public Scoping Meeting for the Proposed Northern Access Project Reliable Storage 1 LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On June 6, 2011, the Office of Energy Projects staff will hold a public scoping meeting to obtain input related to the environmental analysis of National Fuel Gas Supply Corporation’s (National Fuel) Northern Access Project. We scheduled this meeting to provide landowners an opportunity to voice comments on the proposed project, and in response to the requests received during the April 11, 2011 environmental site review of the proposed East Aurora Compressor Station site and subsequent requests filed with the Commission. The environmental site review was noticed in our March 29, 2011, Notice of Intent to Prepare an Environmental Assessment for the Proposed Northern Access Project and Station 230C Project, Request for Comments on Environmental Issues, and Notice of Public Environmental Site Review (NOI). The public scoping meeting is scheduled as follows: On March 25, 2011, Reliable Storage 1 LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of hydropower near the town of Sneedville, on Keaton Creek, in Hancock County, Tennessee. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed pumped storage project would consist of the following: (1) A 160-foot-high, 4,386-foot-long earth embankment dam; (2) an upper reservoir with a surface area of 57.4 acres and an 4,563 acre-foot storage capacity; (3) a 180-foot-high, 323-footlong earth embankment dam creating; (4) a lower reservoir with a surface area of 32.1 acres and an 2,553 acre-foot Northern Access Project Scoping storage capacity; (5) one 24-footMeeting diameter, 3,400-foot-long penstock; (6) a bifurcation to three penstocks each 16June 6, 2011, at 7 p.m., Parkdale Elementary School, 141 Girard Avenue, foot-diameter, and 50-foot-long; (7) a powerhouse/pumping station East Aurora, NY 14052. containing three pump/generating units This notice is being sent to the with a total generating capacity of 309 Commission’s current environmental megawatts; (8) a substation; (9) a 5.62mailing list for this project. The NOI mile-long, 500 kV transmission line to and additional information about the an existing distribution line; and (10) a project is available from the new 3,420-foot-long access road. The Commission’s Office of External Affairs, proposed project would have an average at (866) 208–FERC, or on the FERC Web annual generation of 322,000,000 site at https://www.ferc.gov using the megawatt hours (MWh), which would ‘‘eLibrary’’ link. Click on the eLibrary be sold to a local utility. Applicant Contact: Mr. Daniel R. link, click on ‘‘General Search’’ and enter Irvin, Free Flow Power Corporation, 239 the docket number, excluding the last Causeway Street, Suite 300, Boston MA three digits in the Docket Number field 01244; phone (978) 252–7631. (i.e., CP11–128). Be sure you have FERC Contact: Michael Spencer, (202) selected an appropriate date range. For 502–6093. assistance, please contact FERC Online Deadline for filing comments, motions Support at FercOnlineSupport@ferc.gov to intervene, competing applications or toll free at (866) 208–3676, or for (without notices of intent), or notices of TTY, contact (202) 502–8659. intent to file competing applications: 60 Dated: May 19, 2011. days from the issuance of this notice. Competing applications and notices of Kimberly D. Bose, intent must meet the requirements of 18 Secretary. CFR 4.36. Comments, motions to [FR Doc. 2011–12892 Filed 5–24–11; 8:45 am] intervene, notices of intent, and BILLING CODE 6717–01–P competing applications may be filed PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 E:\FR\FM\25MYN1.SGM 25MYN1

Agencies

[Federal Register Volume 76, Number 101 (Wednesday, May 25, 2011)]
[Notices]
[Page 30339]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-12890]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL11-41-000]


California Independent System Operator Corporation; Notice of 
Institution of Section 206 Proceeding and Refund Effective Date

    On May 19, 2011, the Commission issued an order that instituted an 
investigation in Docket No. EL11-41-000, pursuant to section 206 of the 
Federal Power Act (FPA), 16 U.S.C. 824e, to evaluate the justness and 
reasonableness of section 10.3.6.3 of the California Independent System 
Operator Corporation's tariff. Cal. Indep. Operator Corp., 135 FERC ] 
61,159 (2011).
    The refund effective date in Docket No. EL11-41-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.

    Dated: May 19, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-12890 Filed 5-24-11; 8:45 am]
BILLING CODE 6717-01-P