Fire Mountain Lodge; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 24467 [2011-10508]

Download as PDF Federal Register / Vol. 76, No. 84 / Monday, May 2, 2011 / Notices o. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: April 26, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–10536 Filed 4–29–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 1992–003] mstockstill on DSKH9S0YB1PROD with NOTICES6 Fire Mountain Lodge; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Existing Minor License. b. Project No.: 1992–003. c. Date filed: April 25, 2008. d. Applicant: Mr. Ken Willis. e. Name of Project: Fire Mountain Lodge. f. Location: On Fern Spring in Tehama County, California. The project is located primarily on privately owned land except for 1.07 acres of the dam and reservoir which is located on U.S. Forest Service land. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Ken Willis, Fire Mountain Lodge, 43500 Highway 36, Mill Creek, CA 96060, (530) 258–1952. i. FERC Contact: Matt Buhyoff, (202) 502–6824 or matt.buhyoff@ferc.gov. j. Deadline for filing motions to intervene and protests, comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your VerDate Mar<15>2010 17:48 Apr 29, 2011 Jkt 223001 name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted, and is ready for environmental analysis at this time. l. The existing Fire Mountain Lodge project consists of: (1) A 265-foot-long earth and concrete filled dam; (2) a 0.24acre reservoir; (3) a 38 inch intake tower; (4) a 1540-foot-long penstock; (5) a powerhouse with an installed capacity of 60-kilowatts; a (6) a 4000 foot-long transmission line and; (7) appurtenant facilities. The power generated by the project is utilized for commercial and residential purposes, solely for the owners of Fire Mountain Lodge, a selfprovider of electricity. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. All filings must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’, ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 24467 otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b), and 385.2010. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Dated: April 25, 2011. Kimberly D. Bose, Secretary. [FR Doc. 2011–10508 Filed 4–29–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC11–74–000. Applicants: Macho Springs Power I, LLC, Element Power US, LLC. Description: Application of Macho Springs Power I, LLC, et al. for Authorization of Disposition of Jursidictional Facilities and Requests for Confidential Treatment and Expedited Consideration. Filed Date: 04/25/2011. Accession Number: 20110425–5248. Comment Date: 5 p.m. Eastern Time on Monday, May 16, 2011. Docket Numbers: EC11–75–000. Applicants: Arroyo DP Holding LP, Delta Power Company, LLC, Vineland Energy, LLC, RC Delta Holdings, LLC. Description: Joint Application of Arroyo DP Holding LP, Delta Power Company, LLC Vineland Energy, LLC and RC Delta Holdings LLC for Authorization for Indirect Disposition of Jurisdictional Facilities and Request for Expedited Treatment. Filed Date: 04/25/2011. Accession Number: 20110425–5254. E:\FR\FM\02MYN1.SGM 02MYN1

Agencies

[Federal Register Volume 76, Number 84 (Monday, May 2, 2011)]
[Notices]
[Page 24467]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-10508]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1992-003]


Fire Mountain Lodge; Notice of Application Accepted for Filing, 
Soliciting Motions To Intervene and Protests, Ready for Environmental 
Analysis, and Soliciting Comments, Recommendations, Terms and 
Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Existing Minor License.
    b. Project No.: 1992-003.
    c. Date filed: April 25, 2008.
    d. Applicant: Mr. Ken Willis.
    e. Name of Project: Fire Mountain Lodge.
    f. Location: On Fern Spring in Tehama County, California. The 
project is located primarily on privately owned land except for 1.07 
acres of the dam and reservoir which is located on U.S. Forest Service 
land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Ken Willis, Fire Mountain Lodge, 43500 
Highway 36, Mill Creek, CA 96060, (530) 258-1952.
    i. FERC Contact: Matt Buhyoff, (202) 502-6824 or 
matt.buhyoff@ferc.gov.
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, terms and conditions, and prescriptions: 60 days from 
the issuance date of this notice; reply comments are due 105 days from 
the issuance date of this notice.
    All documents may be filed electronically via the Internet. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and seven copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted, and is ready for 
environmental analysis at this time.
    l. The existing Fire Mountain Lodge project consists of: (1) A 265-
foot-long earth and concrete filled dam; (2) a 0.24-acre reservoir; (3) 
a 38 inch intake tower; (4) a 1540-foot-long penstock; (5) a powerhouse 
with an installed capacity of 60-kilowatts; a (6) a 4000 foot-long 
transmission line and; (7) appurtenant facilities. The power generated 
by the project is utilized for commercial and residential purposes, 
solely for the owners of Fire Mountain Lodge, a self-provider of 
electricity.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must (1) bear in all capital letters the title 
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in accordance with 
18 CFR 4.34(b), and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and 
issuances related to this or other pending projects. For assistance, 
contact FERC Online Support.
    n. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

    Dated: April 25, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-10508 Filed 4-29-11; 8:45 am]
BILLING CODE 6717-01-P