Approval and Promulgation of Implementation Plans; Oklahoma; Regional Haze State Implementation Plan; Federal Implementation Plan for Interstate Transport of Pollution Affecting Visibility and Best Available Retrofit Technology Determinations, 16168-16197 [2011-5799]
Download as PDF
16168
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
ENVIRONMENTAL PROTECTION
AGENCY
40 CFR Part 52
[EPA–R06–OAR–2010–0190; FRL–9279–7]
Approval and Promulgation of
Implementation Plans; Oklahoma;
Regional Haze State Implementation
Plan; Federal Implementation Plan for
Interstate Transport of Pollution
Affecting Visibility and Best Available
Retrofit Technology Determinations
Environmental Protection
Agency (EPA).
ACTION: Proposed rule.
AGENCY:
EPA is proposing to partially
approve and partially disapprove a
revision to the Oklahoma State
Implementation Plan (SIP) submitted by
the State of Oklahoma through the
Oklahoma Department of Environmental
Quality (ODEQ) on February 19, 2010
that addresses regional haze for the first
implementation period. This revision
was submitted to address the
requirements of the Clean Air Act (CAA
or Act) and our rules that require states
to prevent any future and remedy any
existing man-made impairment of
visibility in mandatory Class I areas
caused by emissions of air pollutants
from numerous sources located over a
wide geographic area (also referred to as
the ‘‘regional haze program’’). States are
required to assure reasonable progress
toward the national goal of achieving
natural visibility conditions in Class I
areas. EPA is proposing to approve a
portion of this SIP revision as meeting
certain requirements of the regional
haze program and to partially approve
and partially disapprove those portions
addressing the requirements for best
available retrofit technology (BART) and
the long-term strategy (LTS). EPA is
proposing a Federal Implementation
Plan (FIP) to implement sulfur dioxide
(SO2) emission limits on six sources to
address these issues. EPA also is
proposing to disapprove the State’s
submitted alternative to BART; EPA is
taking no action on the submitted
reasonable progress goals at this time. In
addition, EPA is proposing to partially
approve and partially disapprove a
portion of a revision to the Oklahoma
SIP submitted by the State of Oklahoma
on May 10, 2007 and supplemented on
December 10, 2007. We are taking action
on that portion of the submittals
addressing the requirements of CAA as
it applies to visibility for the 1997
8-hour ozone and 1997 particulate
matter (PM2.5) National Ambient Air
Quality Standards (NAAQS). This
portion of the submittals addresses the
srobinson on DSKHWCL6B1PROD with PROPOSALS3
SUMMARY:
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
requirement that Oklahoma’s SIP
contain adequate provisions to prohibit
emissions from interfering with
measures required in another state to
protect visibility. In this action, we
propose a FIP to address the
deficiencies in this portion of
Oklahoma’s SIP submittals. The
proposed FIP will prevent emissions
from six Oklahoma sources from
interfering with other states’ measures
to protect visibility and to implement
sulfur dioxide emission limits on these
six sources to prevent such interference.
DATES: Comments: Comments must be
received on or before May 23, 2011.
Public Hearing. An open house and
public hearing for this proposal is
scheduled to be held on Wednesday
April 13, 2011, at the Metro Technology
Centers, Springlake Campus, Business
Conference Center, Meeting Rooms H
and I, 1900 Springlake Drive, Oklahoma
City, OK 73111, (405) 424–8324. The
Metro Technology Centers Springlake
Campus is located at the intersection of
Martin Luther King Ave. and Springlake
Dr. between NE. 36th and NE. 50th just
south of the Oklahoma City Zoo and
Kirkpatrick Center. Parking for the
Business Conference Center is available
at no charge. The open house will begin
at 1 p.m. and end at 3 p.m. local time.
The public hearing will be held from 4
p.m. until 6 p.m., and again from 7 p.m.
until 9 p.m.
The public hearing will provide
interested parties the opportunity to
present information and opinions to
EPA concerning our proposal. Interested
parties may also submit written
comments, as discussed in the proposal.
Written statements and supporting
information submitted during the
comment period will be considered
with the same weight as any oral
comments and supporting information
presented at the public hearing. We will
not respond to comments during the
public hearing. When we publish our
final action, we will provide written
responses to all oral and written
comments received on our proposal. To
provide opportunities for questions and
discussion, we will hold an open house
prior to the public hearing. During the
open house, EPA staff will be available
to informally answer questions on our
proposed action. Any comments made
to EPA staff during the open house must
still be provided formally in writing or
orally during the public hearing in order
to be considered in the record.
At the public hearing, the hearing
officer may limit the time available for
each commenter to address the proposal
to 5 minutes or less if the hearing officer
determines it to be appropriate. We will
PO 00000
Frm 00002
Fmt 4701
Sfmt 4702
not be providing equipment for
commenters to show overhead slides or
make computerized slide presentations.
Any person may provide written or oral
comments and data pertaining to our
proposal at the Public Hearing.
Verbatim transcripts, in English, of the
hearing and written statements will be
included in the rulemaking docket.
Addresses: Submit your comments,
identified by Docket No. EPA–R06–
OAR–2010–0190, by one of the
following methods:
• Federal e-Rulemaking Portal:
https://www.regulations.gov. Follow the
online instructions for submitting
comments.
• E-mail: r6air_okhaze@epa.gov.
• Mail: Mr. Joe Kordzi, Air Planning
Section (6PD–L), Environmental
Protection Agency, 1445 Ross Avenue,
Suite 1200, Dallas, Texas 75202–2733.
• Hand or Courier Delivery: Mr. Joe
Kordzi, Air Planning Section (6PD–L),
Environmental Protection Agency, 1445
Ross Avenue, Suite 700, Dallas, Texas
75202–2733. Such deliveries are
accepted only between the hours of 8
a.m. and 4 p.m. weekdays, and not on
legal holidays. Special arrangements
should be made for deliveries of boxed
information.
• Fax: Mr. Joe Kordzi, Air Planning
Section (6PD–L), at fax number 214–
665–7263.
Instructions: Direct your comments to
Docket No. EPA–R06–OAR–2010–0190.
Our policy is that all comments received
will be included in the public docket
without change and may be made
available online at https://
www.regulations.gov, including any
personal information provided, unless
the comment includes information
claimed to be Confidential Business
Information (CBI) or other information
whose disclosure is restricted by statute.
Do not submit information that you
consider to be CBI or otherwise
protected through www.regulations.gov
or e-mail. The https://
www.regulations.gov Web site is an
‘‘anonymous access’’ system, which
means we will not know your identity
or contact information unless you
provide it in the body of your comment.
If you send an e-mail comment directly
to us without going through
www.regulations.gov your e-mail
address will be automatically captured
and included as part of the comment
that is placed in the public docket and
made available on the Internet. If you
submit an electronic comment, we
recommend that you include your name
and other contact information in the
body of your comment and with any
disk or CD–ROM you submit. If we
cannot read your comment due to
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
technical difficulties and cannot contact
you for clarification, we may not be able
to consider your comment. Electronic
files should avoid the use of special
characters, any form of encryption, and
be free of any defects or viruses.
Docket: All documents in the docket
are listed in the https://
www.regulations.gov index. Although
listed in the index, some information is
not publicly available, e.g., CBI or other
information whose disclosure is
restricted by statute. Certain other
material, such as copyrighted material,
will be publicly available only in hard
copy. Publicly available docket
materials are available either
electronically in www.regulations.gov
or in hard copy at the Air Planning
Section (6PD–L), Environmental
Protection Agency, 1445 Ross Avenue,
Suite 700, Dallas, Texas 75202–2733.
The file will be made available by
appointment for public inspection in
the Region 6 FOIA Review Room
between the hours of 8:30 a.m. and 4:30
p.m. weekdays except for legal holidays.
Contact the person listed in the FOR
FURTHER INFORMATION CONTACT
paragraph below or Mr. Bill Deese at
214–665–7253 to make an appointment.
If possible, please make the
appointment at least two working days
in advance of your visit. There will be
a 15 cent per page fee for making
photocopies of documents. On the day
of the visit, please check in at the our
Region 6 reception area at 1445 Ross
Avenue, Suite 700, Dallas, Texas.
The state submittal is also available
for public inspection during official
business hours, by appointment, at the
Oklahoma Department of Environmental
Quality, 707 N Robinson, Oklahoma
City, OK 73102.
FOR FURTHER INFORMATION CONTACT: Joe
Kordzi, EPA Region 6 Air Planning
Section, telephone 214–665–7186, email address r6air_okhaze@epa.gov.
SUPPLEMENTARY INFORMATION:
Throughout this document wherever
‘‘we,’’ ‘‘us,’’ or ‘‘our’’ is used, we mean the
EPA.
This action is being taken under
section 110 and part C of the CAA.
srobinson on DSKHWCL6B1PROD with PROPOSALS3
Table of Contents
I. Overview of Proposed Actions
A. Regional Haze
B. Interstate Transport of Visibility
II. SIP and FIP Background
III. What is the background for our proposed
actions?
A. Regional Haze
B. Roles of Agencies in Addressing
Regional Haze
C. The 1997 NAAQS for Ozone and PM2.5
and CAA 110(a)(2)(D)(i)
IV. What are the requirements for regional
haze SIPs?
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
A. The CAA and the Regional Haze Rule
B. Determination of Baseline, Natural, and
Current Visibility Conditions
C. Determination of Reasonable Progress
Goals
D. Best Available Retrofit Technology
E. Long-Term Strategy
F. Coordinating Regional Haze and
Reasonably Attributable Visibility
Impairment
G. Monitoring Strategy and Other SIP
Requirements
H. Consultation With States and Federal
Land Managers
V. Our Analysis of Oklahoma’s Regional
Haze SIP
A. Affected Class I Areas
B. Determination of Baseline, Natural and
Current Visibility Conditions
1. Estimating Natural Visibility Conditions
2. Estimating Baseline Visibility
Conditions
3. Natural Visibility Impairment
4. Uniform Rate of Progress
C. Evaluation of Oklahoma’s Reasonable
Progress Goal
1. Establishment of the Reasonable
Progress Goal
2. ODEQ’s Reasonable Progress ‘‘Four
Factor’’ Analysis
3. Reasonable Progress Consultation
D. Evaluation of Oklahoma’s BART
Determinations
1. Identification of BART-Eligible Sources
2. Identification of Sources Subject to
BART
a. Modeling Methodology
b. Contribution Threshold
c. BART Sources Exempted Due to Permit
Modifications
d. Sources Identified by ODEQ as Subject
to BART
3. BART Determinations
a. OG&E Seminole Units 1, 2, and 3 BART
Determinations
b. OG&E Sooner Units 1 and 2 BART
Determinations
c. OG&E Muskogee Units 4 and 5 BART
Determinations
d. AEP/PSO Comanche Units 1 and 2
BART Determinations
e. AEP/PSO Northeastern Unit 2, 3, and 4
BART Determination
f. AEP/PSO Southwestern Unit 3 BART
Determination
g. ODEQ BART Results and Summary
E. Evaluation of ODEQ’s SO2 BART
Determinations for the OG&E and AEP/
PSO Coal Fired Power Plant Units
1. Cost Effectiveness
a. Dry Scrubbing Cost Analyses
b. Wet Scrubbing Cost Analyses
2. Visibility Benefit
3. Our Conclusion on Oklahoma’s SO2
BART Evaluations for the Six OG&E and
AEP/PSO Units
4. Alternative BART Determination
F. Federal Implementation Plan To
Address SO2 BART for the Six Sources
1. Introduction
2. Appropriate Emission Limits
a. Dry Scrubber Emission Limit
b. Wet Scrubber Emission Limit
3. Visibility Benefit From Dry and Wet
Scrubbing
4. EPA’s SO2 BART Determination for the
Six Units
PO 00000
Frm 00003
Fmt 4701
Sfmt 4702
16169
G. Long-Term Strategy
1. Emissions Inventory
a. Oklahoma’s 2002 Emission Inventory
b. Oklahoma’s 2018 Emission Inventory
2. Visibility Projection Modeling
3. Consultation and Emissions Reductions
for Other States’ Class I Areas
4. Mandatory Long Term Strategy Factors
H. Coordination of RAVI and Regional
Haze Requirements
I. Monitoring Strategy and Other SIP
Requirements
J. Federal Land Manager Coordination
K. Periodic SIP Revisions and Five-Year
Progress Reports
VI. Our Analysis of Oklahoma’s Interstate
Visibility Transport SIP Provisions
VII. Proposed Actions
A. Regional Haze
B. Interstate Transport and Visibility
VIII. Statutory and Executive Order Reviews
I. Overview of Proposed Actions
A. Regional Haze
We propose to partially approve and
partially disapprove Oklahoma’s
regional haze (RH) SIP revision
submitted on February 19, 2010.
Specifically, we propose to disapprove
the SO2 BART determinations for Units
4 and 5 of the Oklahoma Gas and
Electric (OG&E) Muskogee plant; Units
1 and 2 of the OG&E Sooner plant; and
Units 3 and 4 of the American Electric
Power/Public Service Company of
Oklahoma (AEP/PSO) Northeastern
plant. We propose to disapprove these
SO2 BART determinations because they
do not comply with our regulations
under 40 CFR 51.308(e).
We are also proposing to disapprove
the long term strategy (LTS) under
section 51.308(d)(3) because Oklahoma
has not shown that the strategy is
adequate to achieve the reasonable
progress goals set by Oklahoma and by
other nearby States. The visibility
modeling used by Oklahoma in support
of its SIP revision submittal assumed
SO2 reductions from the six sources 1 as
identified above that Oklahoma did not
secure when making its BART
determinations for these sources. As we
discuss elsewhere, ODEQ participated
in the Central Regional Air Planning
Association (CENRAP) visibility
modeling development that assumed
certain SO2 reductions from these six
BART sources. ODEQ also performed its
consultations with other states with the
understanding that these reductions
would be secured. We propose a FIP to
cure these defects in BART and the LTS.
1 In this document, when we say ‘‘six BART
sources,’’ or ‘‘six sources,’’ we mean Units 4 and 5
of the Oklahoma Gas and Electric Muskogee plant;
Units 1 and 2 of the Oklahoma Gas and Electric
Sooner plant; and Units 3 and 4 of the American
Electric Power/Public Service Company of
Oklahoma Northeastern plant.
E:\FR\FM\22MRP3.SGM
22MRP3
srobinson on DSKHWCL6B1PROD with PROPOSALS3
16170
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
We are also proposing to approve the
remaining sections of the RH SIP
submission, except as discussed below.
We propose to find that Units 4 and
5 of the OG&E Muskogee plant, Units 1
and 2 of the OG&E Sooner plant, and
Units 3 and 4 of the AEP/PSO
Northeastern plant are subject to BART
under 40 CFR 51.308(e). Further, we
propose a FIP that specifically imposes
SO2 BART emission limits on these
sources. We propose that SO2 BART for
Units 4 and 5 of the OG&E Muskogee
plant, Units 1 and 2 of the OG&E Sooner
plant, and Units 3 and 4 of the AEP/PSO
Northeastern plant is an SO2 emission
limit of 0.06 lbs/MMBtu that applies
singly to each of these units on a 30 day
rolling average. Additionally, we
propose monitoring, recordkeeping, and
reporting requirements to ensure
compliance with these emission
limitations.
We propose that compliance with the
emission limits be within three (3) years
of the effective date of our final rule. We
solicit comments on alternative
timeframes, of from two (2) years up to
five (5) years from the effective date our
final rule.
Should OG&E and/or AEP/PSO elect
to reconfigure the above units to burn
natural gas, as a means of satisfying
their BART obligations under section
51.308(e), that conversion should be
completed within the same time frame.
We invite comments as to, considering
the engineering and/or management
challenges of such a fuel switch,
whether the full 5 years allowed under
section 308(e)(1)(iv) following our final
approval would be appropriate.
We propose to disapprove section
VI.E of the Oklahoma RH SIP entitled,
‘‘Greater Reasonable Progress
Alternative Determination.’’ We also
propose to disapprove the separate
executed agreements between ODEQ
and OG&E, and ODEQ and AEP/PSO
entitled ‘‘OG&E Regional Haze
Agreement, Case No. 10–024, and ‘‘PSO
Regional Haze Agreement, Case No. 10–
025,’’ housed within Appendix 6–5 of
the RH SIP. We propose that these
portions of the submittal are severable
from the BART determinations and the
LTS; therefore, no FIP is required.
We are taking no action on whether
Oklahoma has satisfied the reasonable
progress requirements of EPA’s regional
haze SIP requirements found at section
51.308(d)(1).
B. Interstate Transport of Visibility
We also propose to partially approve
and partially disapprove a portion of a
SIP revision we received from the State
of Oklahoma on May 10, 2007, as
supplemented on December 10, 2007,
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
for the purpose of addressing the ‘‘good
neighbor’’ provisions of the CAA section
110(a)(2)(D)(i) for the 1997 8-hour ozone
NAAQS and the PM2.5 NAAQS. Section
110(a)(2)(D)(i)(II) of the Act requires that
states have a SIP, or submit a SIP
revision, containing provisions
‘‘prohibiting any source or other type of
emission activity within the state from
emitting any air pollutant in amounts
which will * * * interfere with
measures required to be included in the
applicable implementation plan for any
other State under part C [of the CAA] to
protect visibility.’’ Because of the
impacts on visibility from the interstate
transport of pollutants, we interpret the
‘‘good neighbor’’ provisions of section
110 of the Act described above as
requiring states to include in their SIPs
measures to prohibit emissions that
would interfere with the reasonable
progress goals set to protect Class I areas
in other states.
These SIP revisions were submitted to
address the requirement that
Oklahoma’s SIP must have adequate
provisions to prohibit emissions from
adversely affecting another state’s air
quality through interstate transport.
Oklahoma indicates in its May 10, 2007
submittal that it intended that its RH
SIP be used to satisfy the requirements
of section 110(a)(2)(D)(i)(II) that
emissions from Oklahoma sources do
not interfere with measures required in
the SIP of any other state under part C
of the CAA to protect visibility.
Consistent with our proposed actions
with regard to Oklahoma’s RH SIP
revision submittal, we also propose a
partial approval and partial disapproval
of the Oklahoma Interstate Transport
SIP revision submittals that address the
requirement of section 110(a)(2)(D)(i)(II).
Specifically, we propose a partial
approval and partial disapproval of the
Oklahoma Interstate Transport SIP
revision submittals that address the
requirement of section 110(a)(2)(D)(i)(II)
that emissions from Oklahoma sources
do not interfere with measures required
in the SIP of any other state under part
C of the CAA to protect visibility. We
believe that the controls proposed under
the proposed FIP, in combination with
the controls required by the portion of
the Oklahoma RH submittal that we
propose to approve, will serve to
prevent sources in Oklahoma from
emitting pollutants in amounts which
will interfere with efforts to protect
visibility in other states.
II. SIP and FIP Background
The CAA requires each state to
develop a plan that provides for the
implementation, maintenance, and
enforcement of the NAAQS. CAA
PO 00000
Frm 00004
Fmt 4701
Sfmt 4702
section 110(a). We establish NAAQS
under section 109 of the CAA.
Currently, the NAAQS address six
criteria pollutants: Carbon monoxide;
nitrogen dioxide; ozone; lead;
particulate matter; and sulfur dioxide.
The plan developed by a state is referred
to as the SIP. The content of the SIP is
specified in section 110 of the CAA,
other provisions of the CAA, and
applicable regulations. A primary
purpose of the SIP is to provide the air
pollution regulations, control strategies,
and other means or techniques
developed by the state to ensure that the
ambient air within that state meets the
NAAQS. However, another important
aspect of the SIP is to ensure that
emissions from within the state do not
have certain prohibited impacts upon
the ambient air in other states through
the interstate transport of pollutants.
CAA section 110(a)(2)(D). States are
required to update or revise SIPs under
certain circumstances. See CAA section
110(a)(1). One such circumstance is our
promulgation of a new or revised
NAAQS. Id. Each state must submit
these revisions to us for approval and
incorporation into the federally
enforceable SIP.
If a state fails to make a required SIP
submittal or if we find that, the state’s
submittal is incomplete or
unapprovable, then we must promulgate
a FIP to fill this regulatory gap. CAA
section 110(c)(1). As discussed
elsewhere in this notice, we have made
findings related to Oklahoma SIP
revisions needed to address interstate
transport and the requirement that
emissions from Oklahoma sources do
not interfere with measures required in
the SIP of any other state to protect
visibility, pursuant to section
110(a)(2)(D)(i)(II) of the CAA. We
propose a FIP to address the
deficiencies in the Oklahoma Interstate
Transport SIP.
III. What is the background for our
proposed actions?
A. Regional Haze
RH is visibility impairment that is
produced by a multitude of sources and
activities which are located across a
broad geographic area and emit fine
particles (PM2.5) (e.g., sulfates, nitrates,
organic carbon, elemental carbon, and
soil dust) and their precursors (e.g., SO2,
nitrogen oxides (NOX), and in some
cases, ammonia (NH3) and volatile
organic compounds (VOCs)). Fine
particle precursors react in the
atmosphere to form PM2.5 (e.g., sulfates,
nitrates, organic carbon, elemental
carbon, and soil dust), which also
impair visibility by scattering and
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
absorbing light. Visibility impairment
reduces the clarity, color, and visible
distance that one can see. PM2.5 also can
cause serious health effects and
mortality in humans and contributes to
environmental effects such as acid
deposition and eutrophication.
Data from the existing visibility
monitoring network, the ‘‘Interagency
Monitoring of Protected Visual
Environments’’ (IMPROVE) monitoring
network, show that visibility
impairment caused by air pollution
occurs virtually all the time at most
national park and wilderness areas. The
average visual range 2 in many Class I
areas (i.e., national parks and memorial
parks, wilderness areas, and
international parks meeting certain size
criteria) in the western United States is
100–150 kilometers, or about one-half to
two-thirds of the visual range that
would exist without anthropogenic air
pollution. 64 FR 35714, 35715 (July 1,
1999). In most of the eastern Class I
areas of the United States, the average
visual range is less than 30 kilometers,
or about one-fifth of the visual range
that would exist under estimated
natural conditions. Id.
In section 169A of the 1977
Amendments to the CAA, Congress
created a program for protecting
visibility in the nation’s national parks
and wilderness areas. This section of the
CAA establishes as a national goal the
‘‘prevention of any future, and the
remedying of any existing, impairment
of visibility in mandatory Class I
Federal areas 3 which impairment
results from manmade air pollution.’’
CAA § 169A(a)(1). The terms
‘‘impairment of visibility’’ and ‘‘visibility
impairment’’ are defined in the Act to
include a reduction in visual range and
atmospheric discoloration. Id. section
169A(g)(6). In 1980, we promulgated
2 Visual range is the greatest distance, in
kilometers or miles, at which a dark object can be
viewed against the sky.
3 Areas designated as mandatory Class I Federal
areas consist of national parks exceeding 6000
acres, wilderness areas and national memorial parks
exceeding 5000 acres, and all international parks
that were in existence on August 7, 1977. See CAA
section 162(a). In accordance with section 169A of
the CAA, EPA, in consultation with the Department
of Interior, promulgated a list of 156 areas where
visibility is identified as an important value. See 44
FR 69122, November 30, 1979. The extent of a
mandatory Class I area includes subsequent changes
in boundaries, such as park expansions. CAA
section 162(a). Although states and tribes may
designate as Class I additional areas which they
consider to have visibility as an important value,
the requirements of the visibility program set forth
in section 169A of the CAA apply only to
‘‘mandatory Class I Federal areas.’’ Each mandatory
Class I Federal area is the responsibility of a
‘‘Federal Land Manager’’ (FLM). See CAA section
302(i). When we use the term ‘‘Class I area’’ in this
action, we mean a ‘‘mandatory Class I Federal area.’’
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
regulations to address visibility
impairment in Class I areas that is
‘‘reasonably attributable’’ to a single
source or small group of sources, i.e.,
‘‘reasonably attributable visibility
impairment’’ (RAVI). 45 FR 80084
(December 2, 1980). These regulations
represented the first phase in addressing
visibility impairment. We deferred
action on RH that emanates from a
variety of sources until monitoring,
modeling and scientific knowledge
about the relationships between
pollutants and visibility impairment
were improved.
Congress added section 169B to the
CAA in 1990 to address RH issues, and
we promulgated regulations addressing
RH in 1999. 64 FR 35714 (July 1, 1999),
codified at 40 CFR part 51, subpart P.
The Regional Haze Rule (RHR) revised
the existing visibility regulations to
integrate into the regulations provisions
addressing RH impairment and
established a comprehensive visibility
protection program for Class I areas. The
requirements for RH, found at 40 CFR
51.308 and 51.309, are included in our
visibility protection regulations at 40
CFR 51.300–309. Some of the main
elements of the RH requirements are
summarized in section III. The
requirement to submit a RH SIP applies
to all 50 states, the District of Columbia
and the Virgin Islands.4 States were
required to submit the first
implementation plan addressing RH
visibility impairment no later than
December 17, 2007. 40 CFR 51.308(b).
B. Roles of Agencies in Addressing
Regional Haze
Successful implementation of the RH
program will require long-term regional
coordination among states, tribal
governments and various federal
agencies. As noted above, pollution
affecting the air quality in Class I areas
can be transported over long distances,
even hundreds of kilometers. Therefore,
to address effectively the problem of
visibility impairment in Class I areas,
states need to develop strategies in
coordination with one another, taking
into account the effect of emissions from
one jurisdiction on the air quality in
another.
Because the pollutants that lead to RH
can originate from sources located
across broad geographic areas, we have
encouraged the states and tribes across
the United States to address visibility
impairment from a regional perspective.
4 Albuquerque/Bernalillo County in New Mexico
must also submit a regional haze SIP to completely
satisfy the requirements of section 110(a)(2)(D) of
the CAA for the entire State of New Mexico under
the New Mexico Air Quality Control Act (section
74–2–4).
PO 00000
Frm 00005
Fmt 4701
Sfmt 4702
16171
Five regional planning organizations
(RPOs) were developed to address RH
and related issues. The RPOs first
evaluated technical information to
better understand how their states and
tribes impact Class I areas across the
country, and then pursued the
development of regional strategies to
reduce emissions of particulate matter
(PM) and other pollutants leading to RH.
CENRAP is an organization of states,
tribes, federal agencies and other
interested parties that identifies RH and
visibility issues and develops strategies
to address them. CENRAP is one of the
five Regional Planning Organizations
RPOs across the U.S. and includes the
states and tribal areas of Nebraska,
Kansas, Oklahoma, Texas, Minnesota,
Iowa, Missouri, Arkansas, and
Louisiana.
C. The 1997 NAAQS for Ozone and
PM2.5 and CAA 110(a)(2)(D)(i)
On July 18, 1997, we promulgated
new NAAQS for 8-hour ozone and for
PM2.5. 62 FR 38652. Section 110(a)(1) of
the CAA requires states to submit SIPs
to address a new or revised NAAQS
within 3 years after promulgation of
such standards, or within such shorter
period as we may prescribe. Section
110(a)(2) of the CAA lists the elements
that such new SIPs must address, as
applicable, including section
110(a)(2)(D)(i), which pertains to the
interstate transport of certain emissions.
On April 25, 2005, we published a
‘‘Finding of Failure to Submit SIPs for
Interstate Transport for the 8-hour
Ozone and PM2.5 NAAQS.’’ 70 FR
21147. This included a finding that
Oklahoma and other states had failed to
submit SIPs for interstate transport of air
pollution affecting visibility, and started
a 2-year clock for the promulgation of a
FIP by us, unless a state made a
submission to meet the requirements of
section 110(a)(2)(D)(i) and we approved
the submission. Id.
On August 15, 2006, we issued our
‘‘Guidance for State Implementation
Plan (SIP) Submission to Meet Current
Outstanding Obligations Under Section
110(a)(2)(D)(i) for the 8-Hour Ozone and
PM2.5 National Ambient Air Quality
Standards’’ (2006 Guidance). We
developed the 2006 Guidance to make
recommendations to states for making
submissions to meet the requirements of
section 110(a)(2)(D)(i) for the 1997 8hour ozone standards and the 1997
PM2.5 standards.
As identified in the 2006 Guidance,
the ‘‘good neighbor’’ provisions in
section 110(a)(2)(D)(i) of the CAA
require each state to submit a SIP that
prohibits emissions that adversely affect
another state in the ways contemplated
E:\FR\FM\22MRP3.SGM
22MRP3
16172
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
in the statute. Section 110(a)(2)(D)(i)
contains four distinct requirements
related to the impacts of interstate
transport. The SIP must prevent sources
in the state from emitting pollutants in
amounts which will: (1) Contribute
significantly to nonattainment of the
NAAQS in other states; (2) interfere
with maintenance of the NAAQS in
other states; (3) interfere with provisions
to prevent significant deterioration of air
quality in other states; or (4) interfere
with efforts to protect visibility in other
states.
The 2006 Guidance stated that states
may make a simple SIP submission
confirming that it is not possible at that
time to assess whether there is any
interference with measures in the
applicable SIP for another state
designed to ‘‘protect visibility’’ for the 8hour ozone and PM2.5 NAAQS until RH
SIPs are submitted and approved. RH
SIPs were required to be submitted by
December 17, 2007. See 74 FR 2392
(January 15, 2009).
On May 10, 2007, we received a SIP
revision from Oklahoma to address the
interstate transport provisions of CAA
110(a)(2)(D)(i) for the 1997 ozone and
PM2.5 NAAQS. We received a
supplement to this SIP revision on
December 10, 2007. In a prior action we
approved the Oklahoma SIP submittal
for the ‘‘interfere with measures to
prevent significant deterioration’’ prong
of section 110(a)(2)(D)(i) of the CAA. 75
FR 72695, November 26, 2010. On
February 19, 2010, Oklahoma submitted
a RH SIP to address interstate transport
of emissions that could interfere with
efforts to protect visibility in other
states. Because, for the reasons outlined
below, we can only partially approve
this RH SIP, we propose to partially
approve and partially disapprove the
Oklahoma Interstate Transport SIP
revision submittals that address the
requirement that emissions from
Oklahoma sources do not interfere with
measures required in the SIP of any
other state to protect visibility. See CAA
section 110(a)(2)(D)(i)(II). We propose to
promulgate a FIP in order to cure this
defect in the Oklahoma Interstate
Transport SIP revision submittals.
IV. What are the requirements for
regional haze SIPs?
The following is a summary and basic
explanation of the regulations covered
under the RHR. See 40 CFR 51.308 for
a complete listing of the regulations
under which this SIP was evaluated.
A. The CAA and the Regional Haze Rule
RH SIPs must assure reasonable
progress towards the national goal of
achieving natural visibility conditions
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
in Class I areas. Section 169A of the
CAA and our implementing regulations
require states to establish long-term
strategies for making reasonable
progress toward meeting this goal.
Implementation plans must also give
specific attention to certain stationary
sources that were in existence on
August 7, 1977, but were not in
operation before August 7, 1962, and
require these sources, where
appropriate, to install BART controls for
the purpose of eliminating or reducing
visibility impairment. The specific RH
SIP requirements are discussed in
further detail below.
B. Determination of Baseline, Natural,
and Current Visibility Conditions
The RHR establishes the deciview
(dv) as the principal metric for
measuring visibility. See 70 FR 39104.
This visibility metric expresses uniform
changes in the degree of haze in terms
of common increments across the entire
range of visibility conditions, from
pristine to extremely hazy conditions.
Visibility is sometimes expressed in
terms of the visual range, which is the
greatest distance, in kilometers or miles,
at which a dark object can just be
distinguished against the sky. The
deciview is a useful measure for
tracking progress in improving
visibility, because each deciview change
is an equal incremental change in
visibility perceived by the human eye.
Most people can detect a change in
visibility of one deciview.5
The deciview is used in expressing
Reasonable Progress Goals (RPGs)
(which are interim visibility goals
towards meeting the national visibility
goal), defining baseline, current, and
natural conditions, and tracking changes
in visibility. The RH SIPs must contain
measures that ensure ‘‘reasonable
progress’’ toward the national goal of
preventing and remedying visibility
impairment in Class I areas caused by
manmade air pollution by reducing
anthropogenic emissions that cause RH.
The national goal is a return to natural
conditions, i.e., manmade sources of air
pollution would no longer impair
visibility in Class I areas.
To track changes in visibility over
time at each of the 156 Class I areas
covered by the visibility program (40
CFR 81.401–437), and as part of the
process for determining reasonable
progress, states must calculate the
degree of existing visibility impairment
at each Class I area at the time of each
RH SIP submittal and periodically
5 The preamble to the RHR provides additional
details about the deciview. 64 FR 35714, 35725
(July 1, 1999).
PO 00000
Frm 00006
Fmt 4701
Sfmt 4702
review progress every five years midway
through each 10-year implementation
period. To do this, the RHR requires
states to determine the degree of
impairment (in deciviews) for the
average of the 20 percent least impaired
(‘‘best’’) and 20 percent most impaired
(‘‘worst’’) visibility days over a specified
time period at each of their Class I areas.
In addition, states must also develop an
estimate of natural visibility conditions
for the purpose of comparing progress
toward the national goal. Natural
visibility is determined by estimating
the natural concentrations of pollutants
that cause visibility impairment and
then calculating total light extinction
based on those estimates. We have
provided guidance to states regarding
how to calculate baseline, natural and
current visibility conditions.6
For the first RH SIPs that were due by
December 17, 2007, ‘‘baseline visibility
conditions’’ were the starting points for
assessing ‘‘current’’ visibility
impairment. Baseline visibility
conditions represent the degree of
visibility impairment for the 20 percent
least impaired days and 20 percent most
impaired days for each calendar year
from 2000 to 2004. Using monitoring
data for 2000 through 2004, states are
required to calculate the average degree
of visibility impairment for each Class I
area, based on the average of annual
values over the five-year period. The
comparison of initial baseline visibility
conditions to natural visibility
conditions indicates the amount of
improvement necessary to attain natural
visibility, while the future comparison
of baseline conditions to the then
current conditions will indicate the
amount of progress made. In general, the
2000–2004 baseline period is
considered the time from which
improvement in visibility is measured.
C. Determination of Reasonable Progress
Goals
The vehicle for ensuring continuing
progress towards achieving the natural
visibility goal is the submission of a
series of RH SIPs from the states that
establish two RPGs (i.e., two distinct
goals, one for the ‘‘best’’ and one for the
‘‘worst’’ days) for every Class I area for
each (approximately) 10-year
implementation period. See 70 FR 3915;
6 Guidance for Estimating Natural Visibility
Conditions Under the Regional Haze Rule,
September 2003, EPA–454/B–03–005, available at
https://www.epa.gov/ttncaaa1/t1/memoranda/
rh_envcurhr_gd.pdf (hereinafter referred to as ‘‘our
2003 Natural Visibility Guidance’’); and Guidance
for Tracking Progress Under the Regional Haze
Rule, EPA–454/B–03–004, September 2003,
available at https://www.epa.gov/ttncaaa1/t1/
memoranda/rh_tpurhr_gd.pdf (hereinafter referred
to as our ‘‘2003 Tracking Progress Guidance’’).
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
see also 64 FR 35714. The RHR does not
mandate specific milestones or rates of
progress, but instead calls for states to
establish goals that provide for
‘‘reasonable progress’’ toward achieving
natural (i.e., ‘‘background’’) visibility
conditions. In setting RPGs, states must
provide for an improvement in visibility
for the most impaired days over the
(approximately) 10-year period of the
SIP, and ensure no degradation in
visibility for the least impaired days
over the same period. Id.
States have significant discretion in
establishing RPGs, but are required to
consider the following factors
established in section 169A of the CAA
and in our RHR at 40 CFR
51.308(d)(1)(i)(A): (1) The costs of
compliance; (2) the time necessary for
compliance; (3) the energy and non-air
quality environmental impacts of
compliance; and (4) the remaining
useful life of any potentially affected
sources. States must demonstrate in
their SIPs how these factors are
considered when selecting the RPGs for
the best and worst days for each
applicable Class I area. States have
considerable flexibility in how they take
these factors into consideration, as
noted in our Reasonable Progress
Guidance.7 In setting the RPGs, states
must also consider the rate of progress
needed to reach natural visibility
conditions by 2064 (referred to hereafter
as the ‘‘Uniform Rate of Progress (URP)’’)
and the emission reduction measures
needed to achieve that rate of progress
over the 10-year period of the SIP.
Uniform progress towards achievement
of natural conditions by the year 2064
represents a rate of progress, which
states are to use for analytical
comparison to the amount of progress
they expect to achieve. In setting RPGs,
each state with one or more Class I areas
(‘‘Class I State’’) must also consult with
potentially ‘‘contributing states,’’ i.e.,
other nearby states with emission
sources that may be affecting visibility
impairment at the Class I State’s areas.
40 CFR 51.308(d)(1)(iv).
D. Best Available Retrofit Technology
Section 169A of the CAA directs
states to evaluate the use of retrofit
controls at certain larger, often
uncontrolled, older stationary sources
with the potential to emit greater than
250 tons or more of any pollutant in
order to address visibility impacts from
these sources. Specifically, section
7 Guidance for Setting Reasonable Progress Goals
under the Regional Haze Program, June 1, 2007,
memorandum from William L. Wehrum, Acting
Assistant Administrator for Air and Radiation, to
EPA Regional Administrators, EPA Regions 1–10
(pp. 4–2, 5–1).
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
169A(b)(2)(A) of the Act requires states
to revise their SIPs to contain such
measures as may be necessary to make
reasonable progress towards the natural
visibility goal, including a requirement
that certain categories of existing major
stationary sources 8 built between 1962
and 1977 procure, install, and operate
the ‘‘Best Available Retrofit Technology’’
(BART), as determined by the state or us
in the case of a plan promulgated under
section 110(c) of the CAA. Under the
RHR, States are directed to conduct
BART determinations for such ‘‘BARTeligible’’ sources that may be anticipated
to cause or contribute to any visibility
impairment in a Class I area. Rather
than requiring source-specific BART
controls, states also have the flexibility
to adopt an emissions trading program
or other alternative program as long as
the alternative provides greater
reasonable progress towards improving
visibility than BART.
We promulgated regulations
addressing RH in 1999, 64 FR 35714
(July 1, 1999), codified at 40 CFR part
51, subpart P.9 These regulations require
all states to submit implementation
plans that, among other measures,
contain either emission limits
representing BART for certain sources
constructed between 1962 and 1977, or
alternative measures that provide for
greater reasonable progress than BART.
40 CFR 51.308(e).
On July 6, 2005, we published the
Guidelines for BART Determinations
Under the Regional Haze Rule at
Appendix Y to 40 CFR Part 51 (‘‘BART
Guidelines’’) to assist states in
determining which of their sources
should be subject to the BART
requirements and in determining
appropriate emission limits for each
applicable source. 70 FR 39104. In
making a BART determination for a
fossil fuel-fired electric generating plant
with a total generating capacity in
excess of 750 megawatts, a state must
use the approach set forth in the BART
Guidelines. A state is encouraged, but
not required, to follow the BART
Guidelines in making BART
determinations for other types of
sources.
The process of establishing BART
emission limitations can be logically
broken down into three steps: first,
8 The set of ‘‘major stationary sources’’ potentially
subject to BART are listed in CAA section
169A(g)(7).
9 In American Corn Growers Ass’n v. EPA, 291
F.3d 1 (DC Cir. 2002), the U.S Court of Appeals for
the District of Columbia Circuit issued a ruling
vacating and remanding the BART provisions of the
regional haze rule. In 2005, we issued BART
guidelines to address the court’s ruling in that case.
See 70 FR 39104 (July 6, 2005).
PO 00000
Frm 00007
Fmt 4701
Sfmt 4702
16173
states identify those sources which meet
the definition of ‘‘BART-eligible source’’
set forth in 40 CFR 51.301; 10 second,
states determine whether such sources
‘‘emits any air pollutant which may
reasonably be anticipated to cause or
contribute to any impairment of
visibility in any such area’’ (a source
which fits this description is ‘‘subject to
BART’’) and; third, for each source
subject to BART, states then identify the
appropriate type and the level of control
for reducing emissions.
States must address all visibilityimpairing pollutants emitted by a source
in the BART determination process. The
most significant visibility impairing
pollutants are SO2, NOX, and PM. We
have stated that states should use their
best judgment in determining whether
VOC or ammonia compounds impair
visibility in Class I areas.
Under the BART Guidelines, states
may select an exemption threshold
value for their BART modeling, below
which a BART-eligible source would
not be expected to cause or contribute
to visibility impairment in any Class I
area. The state must document this
exemption threshold value in the SIP
and must state the basis for its selection
of that value. Any source with
emissions that model above the
threshold value would be subject to a
BART determination review. The BART
Guidelines acknowledge varying
circumstances affecting different Class I
areas. States should consider the
number of emission sources affecting
the Class I areas at issue and the
magnitude of the individual sources’
impacts. Any exemption threshold set
by the state should not be higher than
0.5 dv.
In their SIPs, states must identify
potential BART sources, described as
‘‘BART-eligible sources’’ in the RHR, and
document their BART control
determination analyses. The term
‘‘BART-eligible source’’ used in the
BART Guidelines means the collection
of individual emission units at a facility
that together comprises the BARTeligible source. In making BART
determinations, section 169A(g)(2) of
the CAA requires that states consider
the following factors: (1) The costs of
compliance; (2) the energy and non-air
quality environmental impacts of
compliance; (3) any existing pollution
control technology in use at the source;
(4) the remaining useful life of the
source; and (5) the degree of
10 BART-eligible sources are those sources that
have the potential to emit 250 tons or more of a
visibility-impairing air pollutant, were put in place
between August 7, 1962 and August 7, 1977, and
whose operations fall within one or more of 26
specifically listed source categories.
E:\FR\FM\22MRP3.SGM
22MRP3
16174
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
improvement in visibility which may
reasonably be anticipated to result from
the use of such technology. States are
free to determine the weight and
significance to be assigned to each
factor. See 40 CFR 51.308(e)(1)(ii).
A RH SIP must include sourcespecific BART emission limits and
compliance schedules for each source
subject to BART. Once a state has made
its BART determination, the BART
controls must be installed and in
operation as expeditiously as
practicable, but no later than five years
after the date of our approval of the RH
SIP. CAA section 169(g)(4) and 40 CFR
51.308(e)(1)(iv). In addition to what is
required by the RHR, general SIP
requirements mandate that the SIP must
also include all regulatory requirements
related to monitoring, recordkeeping,
and reporting for the BART controls on
the source. See CAA section 110(a). As
noted above, the RHR allows states to
implement an alternative program in
lieu of BART so long as the alternative
program can be demonstrated to achieve
greater reasonable progress toward the
national visibility goal than would
BART.
E. Long-Term Strategy (LTS)
Consistent with the requirement in
section 169A(b) of the CAA that states
include in their regional haze SIP a 10
to 15 year strategy for making
reasonable progress, Section
51.308(d)(3) of the RHR requires that
states include a LTS in their RH SIPs.
The LTS is the compilation of all
control measures a state will use during
the implementation period of the
specific SIP submittal to meet any
applicable RPGs. The LTS must include
‘‘enforceable emissions limitations,
compliance schedules, and other
measures as necessary to achieve the
reasonable progress goals’’ for all Class
I areas within, or affected by emissions
from, the state. 40 CFR 51.308(d)(3).
When a state’s emissions are
reasonably anticipated to cause or
contribute to visibility impairment in a
Class I area located in another state, the
RHR requires the impacted state to
coordinate with the contributing states
in order to develop coordinated
emissions management strategies. 40
CFR 51.308(d)(3)(i). In such cases, the
contributing state must demonstrate that
it has included, in its SIP, all measures
necessary to obtain its share of the
emission reductions needed to meet the
RPGs for the Class I area. The RPOs
have provided forums for significant
interstate consultation, but additional
consultations between states may be
required to sufficiently address
interstate visibility issues. This is
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
especially true where two states belong
to different RPOs.
States should consider all types of
anthropogenic sources of visibility
impairment in developing their LTS,
including stationary, minor, mobile, and
area sources. At a minimum, states must
describe how each of the following
seven factors listed below are taken into
account in developing their LTS: (1)
Emission reductions due to ongoing air
pollution control programs, including
measures to address RAVI; (2) measures
to mitigate the impacts of construction
activities; (3) emissions limitations and
schedules for compliance to achieve the
RPG; (4) source retirement and
replacement schedules; (5) smoke
management techniques for agricultural
and forestry management purposes
including plans as currently exist
within the state for these purposes; (6)
enforceability of emissions limitations
and control measures; (7) the
anticipated net effect on visibility due to
projected changes in point, area, and
mobile source emissions over the period
addressed by the LTS. 40 CFR
51.308(d)(3)(v).
F. Coordinating Regional Haze and
Reasonably Attributable Visibility
Impairment
As part of the RHR, we revised 40
CFR 51.306(c) regarding the LTS for
RAVI to require that the RAVI plan must
provide for a periodic review and SIP
revision not less frequently than every
three years until the date of submission
of the state’s first plan addressing RH
visibility impairment, which was due
December 17, 2007, in accordance with
40 CFR 51.308(b) and (c). On or before
this date, the state must revise its plan
to provide for review and revision of a
coordinated LTS for addressing RAVI
and RH, and the state must submit the
first such coordinated LTS with its first
RH SIP. Future coordinated LTS and
periodic progress reports evaluating
progress towards RPGs, must be
submitted consistent with the schedule
for SIP submission and periodic
progress reports set forth in 40 CFR
51.308(f) and 51.308(g), respectively.
The periodic review of a state’s LTS
must report on both RH and RAVI
impairment and must be submitted to us
as a SIP revision.
G. Monitoring Strategy and Other SIP
Requirements
Section 51.308(d)(4) of the RHR
includes the requirement for a
monitoring strategy for measuring,
characterizing, and reporting of RH
visibility impairment that is
representative of all mandatory Class I
Federal areas within the state. The
PO 00000
Frm 00008
Fmt 4701
Sfmt 4702
strategy must be coordinated with the
monitoring strategy required in section
51.305 for RAVI. Compliance with this
requirement may be met through
‘‘participation’’ in the Interagency
Monitoring of Protected Visual
Environments (IMPROVE) network, i.e.,
review and use of monitoring data from
the network. The monitoring strategy is
due with the first RH SIP, and it must
be reviewed every five (5) years. The
monitoring strategy must also provide
for additional monitoring sites if the
IMPROVE network is not sufficient to
determine whether RPGs will be met.
The SIP must also provide for the
following:
• Procedures for using monitoring
data and other information in a state
with mandatory Class I areas to
determine the contribution of emissions
from within the state to RH visibility
impairment at Class I areas both within
and outside the state;
• Procedures for using monitoring
data and other information in a state
with no mandatory Class I areas to
determine the contribution of emissions
from within the state to RH visibility
impairment at Class I areas in other
states;
• Reporting of all visibility
monitoring data to the Administrator at
least annually for each Class I area in
the state, and where possible, in
electronic format;
• Developing a statewide inventory of
emissions of pollutants that are
reasonably anticipated to cause or
contribute to visibility impairment in
any Class I area. The inventory must
include emissions for a baseline year,
emissions for the most recent year for
which data are available, and estimates
of future projected emissions. A state
must also make a commitment to update
the inventory periodically; and
• Other elements, including
reporting, recordkeeping, and other
measures necessary to assess and report
on visibility.
The RHR requires control strategies to
cover an initial implementation period
extending to the year 2018, with a
comprehensive reassessment and
revision of those strategies, as
appropriate, every 10 years thereafter.
Periodic SIP revisions must meet the
core requirements of section 51.308(d)
with the exception of BART. The
requirement to evaluate sources for
BART applies only to the first RH SIP.
Facilities subject to BART must
continue to comply with the BART
provisions of section 51.308(e), as noted
above. Periodic SIP revisions will assure
that the statutory requirement of
reasonable progress will continue to be
met.
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
H. Consultation With States and Federal
Land Managers
The RHR requires that states consult
with Federal Land Managers (FLMs)
before adopting and submitting their
SIPs. 40 CFR 51.308(i). States must
provide FLMs an opportunity for
consultation, in person and at least 60
days prior to holding any public hearing
on the SIP. This consultation must
include the opportunity for the FLMs to
discuss their assessment of impairment
of visibility in any Class I area and to
offer recommendations on the
development of the RPGs and on the
development and implementation of
strategies to address visibility
impairment. Further, a state must
include in its SIP a description of how
it addressed any comments provided by
the FLMs. Finally, a SIP must provide
procedures for continuing consultation
between the state and FLMs regarding
the state’s visibility protection program,
including development and review of
SIP revisions, five-year progress reports,
and the implementation of other
programs having the potential to
contribute to impairment of visibility in
Class I areas.
V. Our Analysis of Oklahoma’s
Regional Haze SIP
On February 19, 2010, we received a
RH SIP revision from the State of
Oklahoma for approval into the
Oklahoma SIP. The following is a
discussion of our evaluation of that
submission. The parts of the submittal
that are interrelated are discussed
together, in order to provide the reader
with a more ready understanding of our
evaluation. See the Technical Support
Document (TSD) for this proposal for a
step-wise evaluation of ODEQ’s
submission in the order in which the
regulations appear in 40 CFR 51.308,
and a more comprehensive technical
analysis.
srobinson on DSKHWCL6B1PROD with PROPOSALS3
A. Affected Class I Areas
In accordance with 40 CFR 51.308(d),
ODEQ has identified one Class I area
within its borders, the Wichita
Mountains National Wildlife Refuge
(Wichita Mountains). ODEQ has also
determined that Oklahoma emissions
have a small potential to impact
visibility at Class I areas outside of
Oklahoma. Based on projections of
visibility in 2018 for the 20% worst
visibility days, ODEQ has projected that
Oklahoma emissions are responsible for
visibility degradation at the Hercules
Glades in Missouri of approximately
3.61%, the Salt Creek in New Mexico of
approximately 2.53%, and the
Guadalupe Mountains in Texas of
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
approximately 2.0%.11 We note that
these projections are based on modeling
done by CENRAP that assumed a certain
level of reductions of SO2 emissions
from six sources that Oklahoma did not
actually require in its submitted RH SIP
revision. We expect that Oklahoma’s
projected impacts on visibility at Class
I areas outside of Oklahoma would be
greater had these controls and the
associated SO2 emission reductions not
been included in CENRAP’s visibility
modeling.
B. Determination of Baseline, Natural
and Current Visibility Conditions
As required by section 51.308(d)(2)(i)
of the RHR and in accordance with
EPA’s 2003 Natural Visibility
Guidance,12 ODEQ calculated baseline/
current and natural visibility conditions
for its Class I area, the Wichita
Mountains, on the most impaired and
least impaired days, as summarized
below (and further described in the
TSD).
1. Estimating Natural Visibility
Conditions
Natural background visibility, as
defined in EPA’s 2003 Natural Visibility
Guidance, is estimated by calculating
the expected light extinction using
default estimates of natural
concentrations of fine particle
components adjusted by site-specific
estimates of humidity. This calculation
uses the IMPROVE equation, which is a
formula for estimating light extinction
from the estimated natural
concentrations of fine particle
components (or from components
measured by the IMPROVE monitors).
As documented in EPA’s 2003 Natural
Visibility Guidance, EPA allows states
to use ‘‘refined’’ or alternative
approaches to 2003 EPA guidance to
estimate the values that characterize the
natural visibility conditions of Class I
areas. One alternative approach is to
develop and justify the use of
alternative estimates of natural
concentrations of fine particle
components. Another alternative is to
use the ‘‘new IMPROVE equation’’ that
was adopted for use by the IMPROVE
Steering Committee in December
2005.13 The purpose of this refinement
11 Unless otherwise noted, when we refer to
visibility impacts, we mean the impacts due solely
to the source or state named, which do not include
natural conditions.
12 Guidance for Estimating Natural Visibility
Conditions Under the Regional Haze Rule, EPA–
454/B–03–005, September 2003.
13 The IMPROVE program is a cooperative
measurement effort governed by a steering
committee composed of representatives from
Federal agencies (including representatives from
EPA and the FLMs) and RPOs. The IMPROVE
PO 00000
Frm 00009
Fmt 4701
Sfmt 4702
16175
to the ‘‘old IMPROVE equation’’ is to
provide more accurate estimates of the
various factors that affect the calculation
of light extinction.
ODEQ opted to use the default
estimates for the natural conditions
combined with the ‘‘new Improve
equation,’’ for Wichita Mountains. This
is an acceptable approach under our
2003 Natural Visibility Guidance. For
the Wichita Mountains, the default
natural visibility value for the 20
percent worst days is 11.07 deciviews
and for the 20 percent best days it is
3.39 dv. For the Wichita Mountains,
ODEQ also used the new IMPROVE
equation to calculate the ‘‘refined’’
natural visibility value for the 20
percent worst days to be 7.53 deciviews
and for the 20 percent best days to be
4.2 deciviews. We have reviewed
ODEQ’s estimate of the natural visibility
conditions and propose to find it
acceptable using the new IMPROVE
equation.
The new IMPROVE equation takes
into account the most recent review of
the science 14 and it accounts for the
effect of particle size distribution on
light extinction efficiency of sulfate,
nitrate, and organic carbon. It also
adjusts the mass multiplier for organic
carbon (particulate organic matter) by
increasing it from 1.4 to 1.8. New terms
are added to the equation to account for
light extinction by sea salt and light
absorption by gaseous nitrogen dioxide.
Site-specific values are used for
Rayleigh scattering (scattering of light
due to atmospheric gases) to account for
the site-specific effects of elevation and
monitoring program was established in 1985 to aid
the creation of Federal and State implementation
plans for the protection of visibility in Class I areas.
One of the objectives of IMPROVE is to identify
chemical species and emission sources responsible
for existing anthropogenic visibility impairment.
The IMPROVE program has also been a key
participant in visibility-related research, including
the advancement of monitoring instrumentation,
analysis techniques, visibility modeling, policy
formulation and source attribution field studies.
14 The science behind the revised IMPROVE
equation is summarized in Appendix B.2 of the
Tennessee Regional Haze submittal and in
numerous published papers. See for example:
Hand, J.L., and Malm, W.C., 2006, Review of the
IMPROVE Equation for Estimating Ambient Light
Extinction Coefficients—Final Report. March 2006.
Prepared for Interagency Monitoring of Protected
Visual Environments (IMPROVE), Colorado State
University, Cooperative Institute for Research in the
Atmosphere, Fort Collins, Colorado, available at
https://vista.cira.colostate.edu/improve/
publications/GrayLit/016_IMPROVEeqReview/
IMPROVEeqReview.htm and Pitchford, Marc., 2006,
Natural Haze Levels II: Application of the New
IMPROVE Algorithm to Natural Species
Concentrations Estimates. Final Report of the
Natural Haze Levels II Committee to the RPO
Monitoring/Data Analysis Workgroup. September
2006, available at https://vista.cira.colostate.edu/
improve/Publications/GrayLit/029_NaturalCondII/
naturalhazelevelsIIreport.ppt.
E:\FR\FM\22MRP3.SGM
22MRP3
16176
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
temperature. Separate relative humidity
enhancement factors are used for small
and large size distributions of
ammonium sulfate and ammonium
nitrate and for sea salt. The terms for the
remaining contributors, elemental
carbon (light-absorbing carbon), fine
soil, and coarse mass terms, do not
change between the original and new
IMPROVE equations.
2. Estimating Baseline Visibility
Conditions
As required by section 51.308(d)(2)(i)
of the RHR and in accordance with
EPA’s 2003 Natural Visibility
Guidance,15 ODEQ calculated baseline
visibility conditions for the Wichita
Mountains. The baseline condition
calculation begins with the calculation
of light extinction, using the IMPROVE
equation. The IMPROVE equation sums
the light extinction 16 resulting from
individual pollutants, such as sulfates
and nitrates. As with the natural
visibility conditions calculation, ODEQ
chose to use the new IMPROVE
equation.
The period for establishing baseline
visibility conditions is 2000–2004, and
baseline conditions must be calculated
using available monitoring data. 40 CFR
51.308(d)(2). Although visibility
monitoring only began at the Wichita
Mountains in March 2001, ODEQ
concluded that no other monitor
provided a reasonable substitute that
met our completeness criteria.17 As a
consequence, the Oklahoma RH SIP
employed the incomplete visibility data
for 2001, complete data for 2002–2004,
and provisional data for 2005 and 2006.
The resulting baseline conditions
represent an average for 2002–2004.
ODEQ calculated the baseline
conditions at the Wichita Mountains as
23.81 deciviews on the 20 percent worst
days, and 9.78 deciviews on the 20
percent best days. We have reviewed
ODEQ’s estimation of baseline visibility
conditions at Wichita Mountains and
propose to find it acceptable.
srobinson on DSKHWCL6B1PROD with PROPOSALS3
3. Natural Visibility Impairment
To address 40 CFR
51.308(d)(2)(iv)(A), ODEQ also
calculated the number of deciviews by
which baseline conditions exceed
natural visibility conditions at the
15 Guidance
for Estimating Natural Visibility
Conditions Under the Regional Haze Rule, EPA–
454/B–03–005, September 2003.
16 The amount of light lost as it travels over one
million meters. The haze index, in units of
deciviews (dv), is calculated directly from the total
light extinction, bext expressed in inverse
megameters (Mm¥1), as follows: HI = 10 ln(bext/10).
17 Guidance for Tracking Progress Under the
Regional Haze Rule, EPA–454/B–03–004,
September 2003, pages 2–8.
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
Wichita Mountains for the 20 percent
worst days to be 16.28 dv (23.81¥7.53).
ODEQ calculated the baseline and
natural visibility conditions on the 20
percent best days to be 9.78 and 4.2 dv,
respectively. This results in a
calculation in which baseline
conditions exceed natural visibility
conditions at the Wichita Mountains for
the 20 percent best days to be 5.6 dv
(9.78¥4.2). We have reviewed ODEQ’s
estimate of the natural visibility
impairment and propose to find it
acceptable.
4. Uniform Rate of Progress
In setting the RPGs, ODEQ analyzed
and determined the Uniform Rate of
Progress (URP) needed to reach natural
visibility conditions by the year 2064. In
so doing, ODEQ compared the baseline
visibility conditions in the Wichita
Mountains to the natural visibility
conditions in the Wichita Mountains (as
described above) and determined the
uniform rate of progress needed in order
to attain natural visibility conditions by
2064. ODEQ constructed the URP
consistent with our 2003 Tracking
Progress Guidance by plotting a straight
graphical line from the baseline level of
visibility impairment for 2000–2004 to
the level of visibility conditions
representing no anthropogenic
impairment in 2064 for the Wichita
Mountains. Using a baseline visibility
value of 23.81 dv and a ‘‘refined’’ natural
visibility value of 7.53 dv for the 20
percent worst days, ODEQ calculated
the URP to be approximately 0.27 dv per
year. This results in a total reduction of
16.28 dv that are necessary to reach the
natural visibility condition of 7.53 dv in
2064. The URP results in a visibility
improvement of 3.80 dv for the period
covered by this SIP revision submittal
(up to and including 2018).
TABLE 1—SUMMARY OF UNIFORM
RATE OF PROGRESS
Baseline Conditions ..............
Natural Visibility .....................
Total Improvement by 2064 ..
Improvement for this SIP by
2018.
Uniform Rate of Progress .....
23.81 dv.
7.53 dv.
16.28 dv.
3.80 dv.
0.27 dv/year.
We propose to find that ODEQ has
appropriately calculated the URP.
C. Evaluation of Oklahoma’s
Reasonable Progress Goal
We are not taking action on
Oklahoma’s submitted RPGs because, as
described more fully below, we must
first evaluate and act upon the RH SIP
revision submitted by the State of Texas.
We provide a short summary of the
PO 00000
Frm 00010
Fmt 4701
Sfmt 4702
Oklahoma submittal for informational
purposes only.
1. Establishment of the Reasonable
Progress Goal
ODEQ calculated the RPG for the
Wichita Mountains for 2018 for the 20%
best days to be 9.23 dv, which is a 0.54
dv improvement over a baseline of 9.78
dv. ODEQ calculated the reasonable
progress goal for 2018 for the 20% worst
days to be 21.47 dv, which is a 2.3
deciview improvement over a baseline
of 23.81 dv. ODEQ’s RPG establishes a
slower rate of progress than the URP.
ODEQ has calculated that under its
reasonable progress goal, it would attain
natural visibility conditions in 2102. As
we discuss elsewhere, ODEQ indicated
that emissions from other states,
especially Texas, impeded Oklahoma’s
ability to meet the URP.
2. ODEQ’s Reasonable Progress ‘‘Four
Factor’’ Analysis
ODEQ analyzed the largest sources of
visibility impairing pollutants within
the state, including sources of sulfur,
nitrates, ammonia, VOCs, and directly
emitted coarse and fine particles. ODEQ
calculated (1) that sulfurous pollutants
contribute approximately 44% and
nitrate bearing pollutants contribute
approximately 21% of the total light
extinction (or visibility impairment) to
the Wichita Mountains, and (2) sources
within Oklahoma contribute only
approximately 13% of the total
pollutants that contribute to light
extinction.
ODEQ initially relied on CENRAP
modeling, based on an Alpine
Geophysics evaluation of possible
additional point-source controls for
CENRAP states for 2018. That study
relied on AirControlNet, an EPA costbenefit tool for emissions of NOX and
SO2. CENRAP used a maximum
estimated cost of $5,000 per ton of
emissions of NOX or SO2 reduced for
sources over 100 tons of SO2 or NOX in
the year 2018. CENRAP further refined
the analysis, considering controls only
for those sources with emissions of NOX
or SO2 greater than or equal to five tons
per year per kilometer of distance to the
Wichita Mountains or the nearest other
Class I area. This analysis resulted in
the conclusion by ODEQ that visibility
at the Wichita Mountains would be
improved by an additional 0.5 dv, over
what ODEQ projects as its reasonable
progress goal of 21.47 deciview for 2018
if controls were implemented at the
sources that met this combination of
baseline emissions, potential for costeffective reductions, and visibility
impact.
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
Following this analysis, ODEQ
examined sources within Oklahoma that
were not already being controlled via
BART or consent decrees or other
regulatory mechanisms. See the TSD for
a listing of the sources considered. In so
doing, ODEQ analyzed the cost of
compliance by weighing the cost of
potential pollution control equipment
versus the visibility benefit. Based on
this analysis, ODEQ concluded that no
additional controls were required.
ODEQ reasoned that most of the largest
sources of SO2 and NOX were already
being controlled through BART, already
had adequate controls in place, or were
too far from the Wichita Mountains (too
little visibility impact) to justify the cost
of additional controls.
3. Reasonable Progress Consultation
ODEQ used CENRAP as its main
vehicle for facilitating collaboration
with FLMs and other states in
developing its RH SIP. ODEQ was able
to use CENRAP generated products,
such as regional photochemical
modeling results and visibility
projections, and source apportionment
modeling to assist in identifying
neighboring states’ contributions to the
visibility impairment at the Wichita
Mountains.
ODEQ invited those states projected
through visibility modeling to
contribute greater than 1 Mm¥1 of light
extinction at the Wichita Mountains in
2018 to consultations. ODEQ conducted
four consultations. ODEQ directed its
first consultation, to the tribal leaders in
Oklahoma and their environmental
managers, on 14 August 2007. ODEQ
held the next three consultations as
conference calls and invited CENRAP
member clean air agencies, EPA, and the
tribes to participate.
ODEQ received responses from the
Arkansas Department of Environmental
Quality, the Iowa Department of Natural
Resources, and the Missouri Department
of Natural Resources. These states
concluded that emissions from within
their borders do not significantly impact
visibility at the Wichita Mountains, and
they did not offer any additional
reductions from their anthropogenic
sources.
ODEQ has indicated and we agree that
sources in Texas significantly affect the
visibility at the Wichita Mountains. We
note ODEQ communicated this to Texas
in the correspondence included in
Appendix 10–1, and Texas agreed with
that assertion. However, ODEQ did not
request any emission reductions from
Texas. As a result of its correspondence
with Texas, Texas agreed to provide
ODEQ the opportunity to comment on
Best Available Control Technology
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
determinations for Prevention of
Significant Deterioration sources that
have significant impact on the Wichita
Mountains. Specifically, ODEQ will be
afforded the opportunity to review
applications for sources if modeling
predicts a five percent or higher impact
on light extinction in a given year and
provide comments to Texas during its
public review and comment period.
Texas also agreed to notify ODEQ
whenever modeling indicates that a
proposed source may significantly
impact the Wichita Mountains. ODEQ
also requested that Class I impact
reviews be required for all proposed
PSD sources within 300 kilometers of a
Class I area. However, this request was
not agreed to by Texas, who cited the
need for EPA to adopt significant impact
levels for Class I reviews so that there
is a consistent approach to requiring
Class I reviews.
In establishing its RPG, ODEQ is
required by 40 CFR 51.308(d)(1)(i)(B) to
consider the emission reduction
measures needed to achieve the URP for
the period covered by this SIP. Our 1999
RHR 18 further illuminates this
requirement:
[T]he State must identify the amount
of progress that would result if this
uniform rate of progress were achieved
during the period of the first regional
haze implementation plan.
[T]he State must identify and analyze
the emissions measures that would be
needed to achieve this amount of
progress during the period covered by
the first long-term strategy, and to
determine whether those measures are
reasonable based on the statutory
factors. These factors are the costs of
compliance with the measures, the time
necessary for compliance with the
measures, the energy and nonair quality
environmental impacts of the
compliance with the measures, and the
remaining useful life of any existing
source subject to the measures. In doing
this analysis, the State must consult
with other States which are anticipated
to contribute to visibility impairment in
the Class I area under consideration.
Because haze is a regional problem,
States are encouraged to work together
to develop acceptable approaches for
addressing visibility problems to which
they jointly contribute. If a contributing
State cannot agree with the State
establishing the reasonable progress
goal, the State setting the goal must
describe the actions taken to resolve the
disagreement.
18 64
PO 00000
FR 35732.
Frm 00011
Fmt 4701
As further explained by the RHR,19
Oklahoma was under an additional
obligation to consider these controls as
part of its reasonable progress analysis
requirement:
If the State determines that the amount of
progress identified through the analysis is
reasonable based upon the statutory factors,
the State should identify this amount of
progress as its reasonable progress goal for
the first long-term strategy, unless it
determines that additional progress beyond
this amount is also reasonable. If the State
determines that additional progress is
reasonable based on the statutory factors, the
State should adopt that amount of progress
as its goal for the first long-term strategy.
We note that as part of its RH SIP
submittal, Texas did consider the
impact its sources have on the visibility
of the Wichita Mountains. Therefore, we
believe that to properly assess whether
Oklahoma has satisfied the reasonable
progress requirements of section
51.308(d)(1), we must review and
evaluate Texas’ submittal. We will do
this in the course of processing the
Texas RH SIP.
D. Evaluation of Oklahoma’s BART
Determinations
Oklahoma’s submitted BART rule,
OAC 252:100–8, Part 11, became
effective on June 15, 2007. Definitions
related to the BART rule were added in
the Air Quality Rules general definitions
section in OAC 252:100–8.1.1, and
became effective as a permanent rule on
June 15, 2006. These submitted rules
also incorporate by reference 40 CFR
part 51, appendix Y (our BART
Guidelines). The rules further provide
that the resulting source-specific
requirements be incorporated into that
source’s air quality permit.
BART is an element of Oklahoma’s
LTS for the first implementation period.
As discussed in more detail in section
IV.D. of this preamble, the BART
evaluation process consists of three
components: (1) An identification of all
the BART-eligible sources, (2) an
assessment of whether those BARTeligible sources are in fact subject to
BART and (3) a determination of any
BART controls. ODEQ addressed these
steps as follows:
1. Identification of BART-Eligible
Sources
The first step of a BART evaluation is
to identify all the BART-eligible sources
within the state’s boundaries. ODEQ
identified the BART-eligible sources in
Oklahoma by utilizing the three
eligibility criteria in the BART
Guidelines (70 FR 39158) and our
19 Id.
Sfmt 4702
16177
E:\FR\FM\22MRP3.SGM
22MRP3
16178
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
regulations (40 CFR 51.301): (1) One or
more emission units at the facility fit
within one of the 26 categories listed in
the BART Guidelines; (2) the emission
unit(s) was constructed on or after
August 6, 1962, and was in existence
prior to August 6, 1977; and (3)
potential emissions of any visibilityimpairing pollutant from subject units
are 250 tons or more per year. ODEQ
initially screened its emissions
inventory and permitting database to
identify major facilities with emission
units in one or more of the 26 BART
categories. Following this, ODEQ used
its databases and records to identify
facilities in these source categories with
potential emissions of 250 tons per year
or more for any visibility-impairing
pollutant from any unit that was in
existence on August 7, 1977 and began
operation after August 7, 1962. ODEQ
contacted the sources, when necessary,
to obtain or confirm this information.
The BART Guidelines direct states to
address SO2, NOX and direct PM
(including both PM10 and PM2.5)
emissions as visibility-impairment
pollutants, and States must exercise
their ‘‘best judgment to determine
whether VOC or ammonia emissions
from a source are likely to have an
impact on visibility in an area.’’ See 70
FR 39162. CENRAP modeling
demonstrated that VOCs from
anthropogenic sources are not
significant visibility-impairing
pollutants at the Wichita Mountains.
Ammonia emissions in Oklahoma are
primarily due to area sources, such as
livestock and fertilizer application.
Because these are not point sources,
they are not subject to BART.20 ODEQ
did consider ammonia from point
sources. The emissions inventory
prepared for the CENRAP modeling
demonstrates that ammonia from point
sources are not significant visibilityimpairing pollutants in Oklahoma.
ODEQ further argued that because of the
limiting role of NOX and SO2 on PM2.5
formation and the uncertainties in
assessing the effect of an individual
source’s ammonia emissions reductions
on visibility, it did not consider
ammonia among visibility-impairing
pollutants. We have reviewed this
information and propose to agree with
this decision.
Table 2 lists Oklahoma’s BARTeligible sources:
TABLE 2: FACILITIES WITH BART-ELIGIBLE UNITS IN OKLAHOMA
Number of
units
BART source category
Facility name
County
Fossil fuel-fired boilers of more than 250 MMBTU/hr
heat input.
Kraft pulp mill .................................................................
Georgia Pacific Consumer Products (formerly Fort
James Operating) Muskogee Mill.
International Paper (formerly Weyerhaeuser) Valliant
Paper Mill.
Koch Nitrogen Enid Plant ..............................................
Terra International Oklahoma Woodward Complex ......
Terra Nitrogen Partnership Verdigris Plant ...................
Sinclair Oil Tulsa Refinery .............................................
Holly Refining and Marketing (formerly Sunoco) Tulsa
Refinery.
Wynnewood Refining ....................................................
Valero Refinery (formerly TPI Petroleum Inc) Ardmore
Refinery.
Lafarge Building Materials Tulsa Rogers City Line ......
OG&E Horseshoe Lake Generating Station .................
Muskogee ....
2
McCurtain ....
4
Garfield ........
Woodward ...
Rogers ........
Tulsa ...........
Tulsa ...........
7
11
12
7
25
Garvin ..........
Carter ..........
14
24
Rogers .........
Oklahoma ....
10
2
Muskogee ...
Seminole .....
Noble ...........
Comanche ...
Rogers .........
Tulsa ...........
Caddo .........
Caddo .........
Woodward ...
2
3
2
2
3
2
1
3
3
Hydrofluoric, sulfuric, and nitric acid plants ...................
Petroleum refineries .......................................................
Portland cement plants ..................................................
Fossil fuel-fired steam electric plants of more than 250
MMBTU/hr heat input.
OG&E Muskogee Generating Station ...........................
OG&E Seminole Generating Station .............................
OG&E Sooner Generating Station ................................
PSO Comanche Power Station .....................................
PSO Northeastern Power Station .................................
PSO Riverside Jenks Power Station ............................
PSO Southwestern Power Station ................................
Western Farmers Electric Coop Anadarko Plant ..........
Western Farmers Electric Coop Mooreland Station .....
srobinson on DSKHWCL6B1PROD with PROPOSALS3
2. Identification of Sources Subject to
BART
The second step of the BART
evaluation is to identify those BARTeligible sources that may reasonably be
anticipated to cause or contribute to
visibility impairment at any Class I area,
i.e. those sources that are subject to
BART. The BART Guidelines allow
states to consider exempting some
20 ODEQ took the position, and we agree, that it
is not practical at this time to control ammonia from
these types of sources, for the purpose of improving
visibility under the reasonable progress
requirements of section 51.308(d)(1).
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
BART-eligible sources from further
BART review because they may not
reasonably be anticipated to cause or
contribute to any visibility impairment
in a Class I area. Consistent with the
BART Guidelines, ODEQ required each
of its BART-eligible sources to develop
and submit dispersion modeling to
assess the extent of their contribution to
21 Note that our reference to CALPUFF
encompasses the entire CALPUFF modeling system,
which includes the CALMET, CALPUFF, and
CALPOST models and other pre and post
processors. The different versions of CALPUFF
have corresponding versions of CALMET,
CALPOST, etc. which may not be compatible with
PO 00000
Frm 00012
Fmt 4701
Sfmt 4702
visibility impairment at surrounding
Class I areas.
a. Modeling Methodology
The BART Guidelines provide that
states may choose to use the
CALPUFF 21 modeling system or
another appropriate model to predict
the visibility impacts from a single
source on a Class I area and to therefore,
previous versions (e.g., the output from a newer
version of CALMET may not be compatible with an
older version of CALPUFF). The different versions
of the CALPUFF modeling system are available
from the model developer at https://www.src.com/
verio/download/download.htm.
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
determine whether an individual source
is anticipated to cause or contribute to
impairment of visibility in Class I areas,
i.e., ‘‘is subject to BART’’. The
Guidelines state that we believe
CALPUFF is the best regulatory
modeling application currently
available for predicting a single source’s
contribution to visibility impairment (70
FR 39162). ODEQ, in coordination with
CENRAP, used the CALPUFF modeling
system to determine whether individual
sources in Oklahoma were subject to or
exempt from BART.
The BART Guidelines also
recommend that states develop a
modeling protocol for making
individual source attributions, and
suggest that states may want to consult
with us and their RPO to address any
issues prior to modeling. The CENRAP
states, including Oklahoma, developed
the ‘‘CENRAP BART Modeling
Guidelines’’. 22 Stakeholders, including
EPA, FLMs, industrial sources, trade
groups, and other interested parties,
actively participated in the development
and review of the CENRAP protocol.
CENRAP provided readily available
modeling data bases for use by states to
conduct their analyses. We note that the
original meteorological databases
generated by CENRAP did not include
observations as EPA guidance indicates,
therefore sources were evaluated using
the 1st High values instead of the 8th
High values. The use of the 1st High was
agreed to by EPA, representatives of the
Federal Land Managers, and CENRAP
stakeholders. Some sources that did not
screen out did later conduct refined
CALPUFF modeling that incorporated
meteorological data with observations
and which allowed to them to compare
8th High modeling values with the 0.5
deciview threshold. We propose to find
the chosen model and the general
modeling methodology acceptable.
However, we note a few additional
deviations from modeling guidance that
are discussed in the TSD and addressed
in our remodeling of visibility impacts
in support of the FIP for these six
sources.
b. Contribution Threshold
For states using modeling to
determine the applicability of BART to
single sources, the BART Guidelines
note that the first step is to set a
contribution threshold to assess whether
the impact of a single source is
sufficient to cause or contribute to
22 CENRAP BART Modeling Guidelines, T. W.
Tesche, D. E. McNally, and G. J. Schewe (Alpine
Geophysics LLC), December 15, 2005, available at
https://www.deq.state.ok.us/aqdnew/
RulesAndPlanning/Regional_Haze/SIP/
Appendices/index.htm.
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
visibility impairment at a Class I area.
The BART Guidelines state that, ‘‘[a]
single source that is responsible for a 1.0
deciview change or more should be
considered to ‘cause’ visibility
impairment.’’ 70 FR 39104, 39161. The
BART Guidelines also state that ‘‘the
appropriate threshold for determining
whether a source contributes to
visibility impairment’ may reasonably
differ across states,’’ but, ‘‘[a]s a general
matter, any threshold that you use for
determining whether a source
‘contributes’ to visibility impairment
should not be higher than 0.5
deciviews.’’ Id. Further, in setting a
contribution threshold, states should
‘‘consider the number of emissions
sources affecting the Class I areas at
issue and the magnitude of the
individual sources’ impacts. The
Guidelines affirm that states are free to
use a lower threshold if they conclude
that the location of a large number of
BART-eligible sources in proximity of a
Class I area justifies this approach.
ODEQ used a contribution threshold of
0.5 dv for determining which sources
are subject to BART. There are a limited
number of BART-eligible sources in
close proximity to the State’s Class I
area and surrounding Class I areas, and
the results of the visibility impacts
modeling demonstrated that the
majority of the individual BART-eligible
sources had visibility impacts well
below 0.5 dv. We agree with the State’s
rationale for choosing this threshold
value.
c. BART Sources Exempted Due to
Permit Modifications
When performing its initial BART
screening modeling, ODEQ identified
three sources with a contribution of
greater than 0.5 deciviews in visibility
impairment that desired to limit their
emissions in order to avoid a BART
determination. These sources were (1)
the Georgia Pacific Consumer Products
LP, Muskogee Mill; (2) the International
Paper, Valliant Paper Mill; and (3) the
Western Farmers Electric Coop,
Anadarko Plant. An updated BART
modeling analysis, assuming those
controls were in place, demonstrated a
contribution of less than 0.5 deciview of
visibility impairment for each of these
facilities. They are individually
discussed below. ODEQ issued a Title V
operating permit to each of the sources
that imposed an emission limitation
requiring the modeled controls. Since
these three sources are voluntarily
taking limits to avoid a full BART
analysis, any future changes or
relaxation of these limits at these
specific BART-eligible units or in their
permits that would allow for increases
PO 00000
Frm 00013
Fmt 4701
Sfmt 4702
16179
in SO2, NOX, or PM emissions would
subject those sources to BART review,
pursuant to the submitted ODEQ rules
that we propose to approve as part of
the Oklahoma RH SIP.
i. Georgia Pacific Consumer Products
LP, Muskogee Mill
The Georgia Pacific, Muskogee Mill
had two BART eligible boilers, Boiler B–
1 and Boiler B–2. Georgia Pacific
requested of ODEQ that an enforceable
emission limit be imposed on Boiler B–
1 to maintain emissions below the
BART contribution threshold of 0.5
deciviews. Where previously Boiler B–
1 was permitted to burn either No. 2
fuel oil or natural gas, Boiler B–1 is now
restricted to burning natural gas, which
will reduce its NOX emissions. ODEQ
has determined that under the Title V
operating permit modification, this
facility will have a visibility impairment
contribution of less than 0.5 deciviews
at any Class I area, which is below the
contribution threshold used by ODEQ in
their BART analyses. This emission
reduction is housed in a modification to
the facility’s Oklahoma Department of
Environmental Quality, Air Quality
Division operating Permit, No. 99–113–
TV (M–5), issued January 5, 2011. This
permit requires that this fuel switch be
operational no more than five years
following our final action on the
Oklahoma RH SIP.
ii. International Paper, Valliant Paper
Mill
The International Paper, Valliant
Paper Mill has three BART eligible
boilers: EUG D1, Bark Boiler; EUG D2,
Power Boiler; and EUG D3, Package
Boiler. It also has a BART eligible Lime
Kiln, EUG E7a. The Valiant Paper Mill
has accepted limits on the sulfur
content of fuel to the Bark and Power
boilers in order to reduce its visibility
impact. ODEQ has determined that
under this Title V operating permit
modification, this facility will have a
visibility impairment contribution of
less than 0.5 deciviews at any Class I
area, which is below the contribution
threshold used by ODEQ in their BART
analyses. This emission reduction is
housed in a modification to the facility’s
Oklahoma Department of Environmental
Quality, Air Quality Division operating
Permit No. 97–057–TV (M–10), issued
March 24, 2010. This permit requires
these controls be operational no more
than five years following our final
action on the Oklahoma RH SIP.
iii. Western Farmers Electric Coop,
Anadarko Plant
The Western Farmers Electric Coop
(WFEC), Anadarko facility had three
E:\FR\FM\22MRP3.SGM
22MRP3
16180
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
BART eligible combine cycle gas
turbines, AN–Unit 4, AN–Unit 5, and
AN–Unit 6. WFEC agreed to NOX, SO2,
and PM–10 emission limits on the
combined cycle gas turbines in order to
reduce their visibility impact. ODEQ has
determined that under this Title V
operating permit modification, this
facility will have a visibility impairment
contribution of less than 0.5 deciviews
at any Class I area, which is below the
contribution threshold used by ODEQ in
their BART analyses. This emission
reduction is housed in a modification to
the facility’s Oklahoma Department of
Environmental Quality, Air Quality
Division operating Permit, No. 2005–
037–TVR (M–1), issued July 9, 2010.
This permit will require these controls
be operational no more than five years
following our final action on the
Oklahoma RH SIP.
d. Sources Identified by ODEQ as
Subject to BART
Following the elimination of those
sources that were found to have
visibility impacts below the 0.5
deciview threshold, or the three
discussed in the previous section that
received Title V permits limiting their
visibility impact below the 0.5 deciview
threshold, ODEQ identified the sources
contained in Table 3 as being subject to
BART.
TABLE 3—SOURCES IN OKLAHOMA SUBJECT TO BART
Facility name
BART emission units
Source category
OG&E Seminole .......................
OG&E Sooner ..........................
Units 1, 2, and 3 .....................
Units 1 and 2 ...........................
fossil fuel-fired steam electric plants .........................................
fossil fuel-fired steam electric plants .........................................
OG&E Muskogee .....................
Units 4 and 5 ...........................
fossil fuel-fired steam electric plants .........................................
AEP/PSO Comanche ...............
AEP/PSO Northeastern ............
AEP/PSO Northeastern ............
Units 1 and 2 ...........................
Unit 2 .......................................
Units 3 and 4 ...........................
fossil fuel-fired steam electric plants .........................................
fossil fuel-fired steam electric plants .........................................
fossil fuel-fired steam electric plants .........................................
AEP/PSO Southwestern ...........
Unit 3 .......................................
fossil fuel-fired steam electric plants .........................................
srobinson on DSKHWCL6B1PROD with PROPOSALS3
3. BART Determinations
The third step of a BART evaluation
is to perform the BART analysis. The
BART Guidelines 23 describe the BART
analysis as consisting of the following
five basic steps:
• Step 1: Identify All Available
Retrofit Control Technologies,
• Step 2: Eliminate Technically
Infeasible Options,
• Step 3: Evaluate Control
Effectiveness of Remaining Control
Technologies,
• Step 4: Evaluate Impacts and
Document the Results, and
• Step 5: Evaluate Visibility Impacts.
All of the sources that are subject to
BART presented in Table 3 are fossil
fuel fired electricity generating units.
ODEQ performed BART determinations
for all of these sources for NOX, SO2,
and PM. For each BART determination,
we find that ODEQ adequately
considered Steps 1 through 5, above,
except for the SO2 BART determinations
for Units 4 and 5 of the OG&E Muskogee
plant, Units 1 and 2 of the OG&E Sooner
plant, and Units 3 and 4 of the AEP/PSO
Northeastern plants. The SO2 BART
determinations for these six units are
the subject of our FIP and are treated
separately in Section V.E. of this
proposal. We agree with ODEQ’s BART
determinations for all remaining cases
23 70
FR 39164.
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
and summarize them below. For more
details, please see the TSD.
a. OG&E Seminole Units 1, 2, and 3
BART Determinations
The OG&E Seminole Units 1, 2 and 3
are BART-eligible sources. These units
are gas fired boilers with gross outputs
of 567 MW each. ODEQ considered all
NOX control technologies, including
combustion controls such as Low NOX
Burners (LNB) and Flue Gas
Recirculation (FGR); and post
combustion controls, such as Selective
Catalytic Reduction (SCR), and Selective
Noncatalytic Reduction (SNCR). ODEQ
concluded that LNB/OFA +SCR, LNB/
OFA +FGR, and LNB/OFA were
technically feasible. ODEQ then
evaluated the economic, environmental,
and energy impacts associated with the
three proposed control options. This
included CALPUFF visibility modeling,
based on a modeling protocol we find
acceptable. ODEQ determined that the
installation of new LNB with OFA and
FGR was cost effective, with a capital
cost of $16,977,200 per unit for units 1
and 2 and $9,468,600 for unit 3 and an
average cost effectiveness of $1,554–
$2,120 per ton of NOx removed for each
unit over a twenty year operational life.
ODEQ determined that NOX BART
emission limits should be 30-day rolling
averages of 0.203 lb/MMBtu for Unit 1,
0.212 lb/MMBtu for Unit 2 and 0.164 lb/
MMBtu for Unit 3. The BART
PO 00000
Frm 00014
Fmt 4701
Sfmt 4702
Pollutants
evaluated
NOX
SO2
NOX
PM10
SO2
NOX
PM10
NOX
NOX
SO2
NOX
PM10
NOX
Guidelines do not specify a presumptive
NOX BART limit for gas fired power
plants. As Units 1, 2, and 3 are gas fired,
ODEQ determined that SO2 and PM
BART for them are no additional
control. We propose to approve ODEQ’s
determination of BART for the OG&E
Seminole Units 1, 2, and 3.
b. OG&E Sooner Units 1 and 2 BART
Determinations
The OG&E Sooner Units 1 and 2 are
BART-eligible sources. Both units are
coal fired with a gross output of 570
MW. We evaluate ODEQ’s SO2 BART
determinations for Units 1 and 2 in
section V.E. Here we discuss our review
of ODEQ’s NOX and PM BART
determination for these units.
ODEQ considered all NOx control
technologies, including combustion
controls such as LNB and FGR; and post
combustion controls, such as SCR, and
SNCR. ODEQ concluded that LNB/OFA
+SCR, and LNB/OFA were technically
feasible. ODEQ noted that FGR control
systems have been used as a retrofit
NOX control strategy on natural gasfired boilers, but have not generally
been considered as a retrofit control
technology on coal-fired units. ODEQ
then evaluated the economic,
environmental, and energy impacts
associated with the two proposed
control options. This included
CALPUFF visibility modeling, based on
a modeling protocol we find acceptable.
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
For Units 1 and 2, ODEQ determined
the installation of new LNB with OFA
was cost effective, with a capital cost of
$14,055,900 per unit for units 1 and 2
and an average cost effectiveness of
$493–785 per ton of NOX removed for
each unit over a twenty-five year
operational life. ODEQ determined that
NOX BART emission limits should be
30-day rolling averages of 0.15 lbs/
MMBtu, which meets the BART
presumptive limit.
For PM, ODEQ noted there are two
generally recognized PM control devices
that are used to control PM emission
from coal fired boilers, which are
Electrostatic Precipators (ESPs) and
fabric filters (or baghouses). Sooner
Units 1 & 2 are currently equipped with
ESP control systems. ODEQ determined
that although fabric filters offer a slight
improvement in PM control (99.7 versus
99.3 percent control), their additional
cost did not justify the modest
improvement in PM control. ODEQ
determined PM BART is the existing
ESPs with an emission rate of 0.1 lbs/
MMBtu on a 3-hour average. ODEQ
specified additional BART emission
limitations in lbs/hour and tons/year.
We propose to approve ODEQ’s PM and
NOX BART determinations for the
OG&E Sooner Units 1 and 2.
c. OG&E Muskogee Units 4 and 5 BART
Determinations
The OG&E Muskogee Units 4 and 5
are BART-eligible sources. Both units
are coal fired with a gross output of 572
MW. We evaluate ODEQ’s SO2 BART
determinations for Units 4 and 5 in
section V.E. Here we discuss our review
of ODEQ’s NOX and PM BART
determination for these units.
ODEQ considered all NOX control
technologies, including combustion
controls such as LNB and FGR; and post
combustion controls, such as SCR, and
SNCR. ODEQ concluded that LNB/OFA
+SCR, and LNB/OFA were technically
feasible. ODEQ noted that FGR control
systems have been used as a retrofit
NOX control strategy on natural gasfired boilers, but have not generally
been considered as a retrofit control
technology on coal-fired units. ODEQ
then evaluated the economic,
environmental, and energy impacts
associated with the two proposed
control options. This included
CALPUFF visibility modeling, based on
a modeling protocol we find acceptable.
For Units 4 and 5, ODEQ determined
the installation of new LNB with OFA
was cost effective, with a capital cost of
$14,113,700 per unit for units 4 and 5
and an average cost effectiveness of
$260–$281 per ton of NOX removed for
each unit over a twenty-five year
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
operational life. ODEQ determined that
NOX BART emission limits should be
30-day rolling averages of 0.15 lbs/
MMBtu, which meets the BART
presumptive limit.
For PM, ODEQ noted there are two
generally recognized PM control devices
that are used to control PM emission
from coal fired boilers, which are
Electrostatic Precipators ESPs and fabric
filters (or baghouses). Muskogee Units 4
& 5 are currently equipped with ESP
control systems. ODEQ determined that
although fabric filters offer a slight
improvement in PM control (99.7 versus
99.3 percent control), their additional
cost did not justify the modest
improvement in PM control. ODEQ
determined PM BART is the existing
ESPs with an emission rate of 0.1 lbs/
MMBtu on a 3-hour average. ODEQ
specified additional BART emission
limitations in lbs/hour and tons/year.
We propose to approve ODEQ’s PM and
NOX BART determinations for the
OG&E Muskogee Units 4 and 5.
d. AEP/PSO Comanche Units 1 and 2
BART Determinations
The AEP/PSO Comanche Units 1 and
2 are BART-eligible sources. These units
are gas fired turbines with duct burners
and heat recovery steam generators with
a gross output of 94 MW each.
For Units 1 and 2, ODEQ considered
dry LNBs and SCR as being possibly
applicable to gas fired turbines. ODEQ
concluded that due to specific design
considerations, only dry LNBs were
technically feasible. ODEQ then
evaluated the economic, environmental,
and energy impacts associated with that
proposed control option. This included
CALPUFF visibility modeling, based on
a modeling protocol we find acceptable.
ODEQ determined that the installation
of dry LNBs was cost effective, with a
capital cost of $34,660,000 an average
cost effectiveness of $2,600 per ton of
NOX removed for each unit over a
twenty year operational life. ODEQ
determined that NOX BART emission
limits should be 30-day rolling averages
of 0.15 lbs/MMBtu. The BART
Guidelines do not specify a presumptive
NOX BART limit for gas fired power
plants. As Units 1 and 2 are gas fired,
ODEQ determined that SO2 and PM
BART for them are no additional
control. We propose to approve ODEQ’s
determination of BART for the AEP/PSO
Comanche Units 1 and 2.
e. AEP/PSO Northeastern Unit 2, 3, and
4 BART Determination
The AEP/PSO Northeastern Units 2, 3,
and 4 are BART-eligible sources. Unit 2
is a gas fired boiler with a gross output
of 495 MW. Units 3 and 4 are coal fired
PO 00000
Frm 00015
Fmt 4701
Sfmt 4702
16181
with gross outputs of 490 MW each. We
evaluate ODEQ’s SO2 BART
determinations for Units 3 and 4 in
section V.E. Here we discuss our review
of ODEQ’s NOX and PM BART
determination for these units.
For Unit 2, ODEQ considered all NOX
control technologies, including
combustion controls such as LNB and
FGR; and post combustion controls,
such as SCR, and SNCR. ODEQ
concluded that LNB/OFA +SCR, LNB/
OFA +FGR, and LNB/OFA were
technically feasible. ODEQ then
evaluated the economic, environmental,
and energy impacts associated with the
three proposed control options. This
included CALPUFF visibility modeling,
based on a modeling protocol we find
acceptable. ODEQ determined that the
installation of new LNB with OFA was
cost effective, with a capital cost of
$3,450,000 and an average cost
effectiveness of $303 per ton of NOX
removed over a twenty year operational
life. ODEQ determined that NOX BART
emission limits should be 30-day rolling
averages of 0.28 lbs/MMBtu. ODEQ
specified additional BART emission
limitations in lbs/hour and tons/year.
The BART Guidelines do not specify a
presumptive NOX BART limit for gas
fired power plants. As Unit 2 is gas
fired, ODEQ determined that SO2 and
PM BART for it are no additional
control. We propose to approve ODEQ’s
determination of BART for the AEP/PSO
Northeastern Unit 2.
For Units 3 and 4, ODEQ considered
all NOX control technologies, including
combustion controls such as LNB and
FGR; and post combustion controls,
such as SCR, and SNCR. ODEQ
concluded that LNB/OFA +SCR, LNB/
OFA, were technically feasible. ODEQ
noted difficulties posed by the
installation of SNCR on Units 3 and 4
but did evaluate SNCR. ODEQ noted
that FGR control systems have been
used as a retrofit NOX control strategy
on natural gas-fired boilers, but have not
generally been considered as a retrofit
control technology on coal-fired units.
ODEQ then evaluated the economic,
environmental, and energy impacts
associated with the two proposed
control options. This included
CALPUFF visibility modeling, based on
a modeling protocol we find acceptable.
For Units 3 and 4, ODEQ determined
the installation of new LNB with OFA
was cost effective, with a capital cost of
$17,000,000 and an average cost
effectiveness of $313 per ton of NOX
removed over a twenty-five year
operational life. ODEQ determined that
NOX BART emission limits should be
30-day rolling averages of 0.15 lbs/
E:\FR\FM\22MRP3.SGM
22MRP3
16182
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
MMBtu, which meets the BART
presumptive limit.
For PM, ODEQ noted there are two
generally recognized PM control devices
that are used to control PM emission
from coal fired boilers, which are ESPs
and fabric filters (or baghouses).
Northeastern Units 3 & 4 are currently
equipped with ESP control systems.
ODEQ determined that although fabric
filters offer a slight improvement in PM
control (99.7 versus 99.3 percent
control), their additional cost did not
justify the modest improvement in PM
control. ODEQ determined PM BART is
the existing ESPs with an emission rate
of 0.1 lbs/MMBtu on a 3-hour average.
ODEQ specified additional BART
emission limitations in lbs/hour and
tons/year. We propose to approve
ODEQ’s determination of BART for the
AEP/PSO Northeastern Units 3 and 4.
f. AEP/PSO Southwestern Unit 3 BART
Determination
The AEP/PSO Southwestern Unit 3 is
a BART-eligible source. This unit is a
gas fired boiler with a gross output of
332 MW. ODEQ considered all NOX
control technologies, including
combustion controls such as LNB and
FGR; and post combustion controls,
such as SCR, and SNCR. ODEQ
concluded that LNB/OFA +SCR, and
LNB/OFA were technically feasible.
ODEQ then evaluated the economic,
environmental, and energy impacts
associated with the three proposed
control options. This included
CALPUFF visibility modeling, based on
a modeling protocol we find acceptable.
ODEQ determined that the installation
of new LNB with OFA was cost
effective, with a capital cost of
$3,000,000 and an average cost
effectiveness of $947 per ton of NOX
removed over a twenty-year operational
life. ODEQ determined that NOX BART
emission limits should be 30-day rolling
averages of 0.45 lbs/MMBtu on a 30-day
average. ODEQ specified additional
BART emission limitations in lbs/hour
and tons/year.
The BART Guidelines do not specify
a presumptive NOX BART limit for gas
fired power plants. However, due to the
relatively high NOX emission rate that
ODEQ determined was BART, and the
fact that it appeared the annual average
emissions rates recorded with the Clean
Air Markets Division indicates that the
boiler can currently comply with the
standard on an annual average basis, we
asked for additional information. ODEQ
responded with data detailing 9 years of
emissions versus load, that indicate that
the boiler operates through a range
where emissions can reach as much as
1.4 lb/MMBtu at full load. This unit has
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
historically operated as a ‘‘peaking unit’’
responding to increased demand for
electricity. While technically feasible,
LNB/OFA may not be as effective under
all boiler operating conditions,
especially during load changes and at
low and high operating loads. After
having examined the data, attached in
our TSD, we accept ODEQ’s
explanation. As Unit 3 is gas fired,
ODEQ determined that SO2 and PM
BART for it are no additional control.
We propose to approve ODEQ’s
determination of BART for the AEP/PSO
Southwestern Unit 3.
g. ODEQ BART Results and Summary
We have reviewed ODEQ’s BART
determinations for the sources listed in
Table 3, above. We note that these
BART determinations result in
significant reductions in the amount of
NOX that will be emitted by these
sources, totaling 27,043 tons per year.
This results in significant visibility
benefits at the Wichita Mountains,
Caney Creek, Upper Buffalo, and
Hercules Glades Class I areas.
Calculated as the 3-year average of the
modeled visibility improvement at the
98th percentile, these NOX BART
reductions result in a visibility
improvement of 5.46 dv at the Wichita
Mountains, 2.65 deciviews at Caney
Creek, 1.79 dv at the Upper Buffalo, and
1.37 dv at Hercules Glades. This results
in an 11.27 dv improvement over all
these Class I areas. See the TSD for more
details.
Oklahoma’s BART rule requires each
source subject to BART to install and
operate BART no later than 5 years after
we approve this RH SIP. OAC 252–100–
8–75(e). Therefore, we believe this
satisfies ODEQ’s obligation under
section 51.308(e)(1)(iv), that ‘‘each
source subject to BART be required to
install and operate BART as
expeditiously as practicable, but in no
event later than 5 years after approval of
the implementation plan revision.’’
For the reasons discussed above, we
propose to find that with the exception
of the SO2 BART determinations for
Units 4 and 5 of the OG&E Muskogee
plant, Units 1 and 2 of the OG&E Sooner
plant, and Units 3 and 4 of the AEP/PSO
Northeastern plants, ODEQ has satisfied
the BART requirement of section
51.308(e).
E. Evaluation of ODEQ’s SO2 BART
Determinations for the OG&E and AEP/
PSO Coal Fired Power Plant Units
The discussion below is limited to the
SO2 BART assessments for Units 4 and
5 of the Oklahoma Gas and Electric
Muskogee plant, Units 1 and 2 of the
Oklahoma Gas and Electric Sooner plant
PO 00000
Frm 00016
Fmt 4701
Sfmt 4702
(the ‘‘OG&E units’’), and Units 3 and 4
of the American Electric Power/Public
Service Company of Oklahoma
Northeastern plant (the ‘‘AEP/PSO
units’’). ODEQ’s other BART
assessments are covered in Section V.D.,
above.
In the Oklahoma RH SIP submittal,
ODEQ concluded that dry flue gas
desulfurization with spray dryer
absorbers (‘‘dry scrubbers’’) and wet flue
gas desulfurization (‘‘wet scrubbers’’)
were not cost effective for these units.
ODEQ came to this decision after
comparing the cost effectiveness in
annualized dollars per ton of SO2
removed ($/ton) to the visibility
improvement at the nearest Class I
areas. ODEQ determined that SO2 BART
for these units was no control and
specified an SO2 limit of 0.65 lbs/
MMBtu on a 30-day rolling average. The
OG&E units currently burn a low sulfur
coal from the Powder River Basin (PRB)
of Wyoming, and already have historical
annual emission rates significantly
below this limit. Therefore, it is possible
the OG&E units would be able to
actually increase their emissions
slightly, and still be in compliance with
ODEQ’s SO2 BART assessment. The
AEP/PSO units have historical annual
emission rates that have been steadily
decreasing to a point where the
imposition of ODEQ’s proposed BART
SO2 emission rate of 0.65 lbs/MMBtu
would result in very little reduction in
emissions. Below we discuss ODEQ’s
BART evaluation and our assessment of
that evaluation.
1. Cost Effectiveness
We propose to find that ODEQ
properly identified these sources as
BART eligible, in compliance with
section 51.308(e)(1)(i). However, we
propose to find that ODEQ did not
properly follow the requirements of
section 51.308(e)(1)(ii)(A) in
determining BART. Specifically, we
propose that ODEQ did not properly
‘‘take into consideration the costs of
compliance’’ when it relied on cost
estimates that greatly overestimated the
costs of dry and wet scrubbing to
conclude these controls were not cost
effective. Given that scrubbers are
typically considered to be highly costeffective controls for power plants such
as those at issue, we retained a
consultant to independently assess the
suitability and costs of installing these
controls. We have thoroughly reviewed
and evaluated the consultant’s report
and agree with its findings regarding the
cost-effectiveness of dry and wet
scrubbing at the BART units. Our
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
a. Dry Scrubbing Cost Analyses
consultant’s detailed report has been
incorporated into the TSD.24
16183
our estimate. Both ODEQ and we used
BART evaluations performed by OG&E
and AEP/PSO as the starting points for
the assessments.26
Table 4, below, summarizes and
contrasts the cost effectiveness of dry
scrubbers estimated by ODEQ 25 versus
TABLE 4—CONTRAST OF DRY SCRUBBER COST EFFECTIVENESS
ODEQ projected cost
($/ton SO2 removed)
Plant
srobinson on DSKHWCL6B1PROD with PROPOSALS3
Sooner 1 ..................................................................................................................................
Sooner 2 ..................................................................................................................................
Muskogee 4 .............................................................................................................................
Muskogee 5 .............................................................................................................................
Northeastern 3 .........................................................................................................................
Northeastern 4 .........................................................................................................................
EPA’s projected cost
($/ton SO2 removed)
$6,348
7,147
7,378
7,493
3,294
3,294
$1,291
1,291
1,317
1,317
1,544
1,544
Although our TSD provides a detailed
comparison between the costing
methodologies, a few general points can
be made that explain why our costs
differ with those from ODEQ. First, in
the case of the OG&E analyses, a coal
with a significantly higher sulfur
content than is currently burned was
assumed by OG&E’s contractor in
determining the design of the scrubber.
This increased the capital cost of the
scrubber over what would minimally be
needed to scrub the coal currently being
burned. However, the increased tonnage
of SO2 that would have been removed
from the emissions resulting from the
burning of that coal, and the high
efficiency of the scrubber was not used
in calculating the cost effectiveness ($/
ton). Our cost analysis, assumed the
same higher sulfur coal, but adjusted the
cost effectiveness to account for the
increased scrubber efficiency and the
increased tonnage of sulfur that would
be removed. Second, the companies did
not follow the Air Pollution Control
Cost Manual 27 when possible, as
specified in the BART guidelines.28 Our
cost analysis does follow the Air
Pollution Control Cost Manual. Third,
some costs were significantly outside of
the range of the actual costs. In our
analysis these costs are adjusted
accordingly. Fourth, the cost estimates
contained double counting. In our
analysis, the double counted costs are
removed. Lastly, the cost estimates
failed to evaluate the most cost effective
options. Our analysis accounts for the
more cost effective options and is
referred to as ‘‘Option 1’’ in our
consultant’s report.
However, even though it appeared
that costing the larger scrubber was
OG&E’s preferred option, we did not
wish to propose our decision solely on
that basis. We also considered whether
it would be cost effective to scrub the
type of coal currently burned at the
units. Therefore, we also analyzed the
cost of a dry scrubber for the OG&E
units, assuming the scrubber would be
sized to scrub the coal being currently
burned. This approach, referred to as
‘‘Option 2’’ in our consultant’s report, is
summarized in Table 5, below. The
estimates in Table 5 are not refined
estimates and did not consider all of the
issues considered in option 1.
evaluate the most cost effective options.
Additional details concerning this
refinement are covered in our TSD.
In contrasting the results displayed in
Tables 4 and 6, we conclude that based
TABLE 5—UNREFINED MINIMALLYSIZED OG&E DRY SCRUBBER COST on a controlled emission limit of 0.06
lbs/MMBtu, a dry scrubber is cost
EFFECTIVENESS
effective at Units 4 and 5 of the OG&E
Muskogee plant, Units 1 and 2 of the
EPA’s Projected
OG&E Sooner plant, and Units 3 and 4
Cost
Plant
(Unrefined)
of the AEP/PSO Northeastern plant. In
($/ton SO2
OG&E’s case, this is true regardless of
removed)
whether the scrubber is sized to control
Sooner 1 .........................
$4,594 the coal presently burned, or a
Sooner 2 .........................
4,594 significantly dirtier coal. Therefore, we
Muskogee 4 ....................
5,102 propose to find that we cannot accept
Muskogee 5 ....................
5,102 the cost estimates for dry scrubbers
provided in the Oklahoma RH
We further refined the cost of the
submission.
smaller scrubber to account for the
issues discussed above that were
b. Wet Scrubbing Cost Analyses
rectified in Option 1: not following the
Table 7, below summarizes and
Air Pollution Control Cost Manual,
contrasts the cost effectiveness of wet
adjusting costs that were outside of the
scrubbers estimated by ODEQ versus
range of the actual costs, eliminating
our estimates:
double counted costs, and failing to
24 Dr. Phyllis Fox, Revised BART CostEffectiveness Analysis for Flue Gas Desulfurization
at Coal-Fired Electric Generating Units in
Oklahoma: Sooner Units 1 & 2 Muskogee Units 4
& 5 Northeastern Units 3 & 4. Report Prepared for
U.S. EPA, RTI Project Number 0209897.004.085.
25 ODEQ BART analyses housed in Appendix 6–
4 of the OK RH SIP.
26 Sargent & Lundy, Sooner Units 1 & 2, Muskogee
Units 4 & 5 Dry FGD BART Analysis Follow-Up
Report, Prepared for Oklahoma Gas & Electric,
December 28, 2009.
Trinity Consultants, Best Available Retrofit
Technology (BART) Determination, American
Electric Power, Northeastern Power Plant, May 30,
2008.
27 U.S. EPA, EPA Air Pollution Control Cost
Manual, EPA/452/B–02–001, 6th Ed., January 2002.
The EPA Air Pollution Control Cost Manual was
formerly known as the OAQPS Control Cost
Manual.
28 As stated in the BART guidelines, ‘‘[i]n order
to maintain and improve consistency, cost estimates
should be based on the OAQPS Control Cost
Manual, where possible.’’ 70 FR 39104, 39166.
VerDate Mar<15>2010
19:08 Mar 21, 2011
Jkt 223001
PO 00000
Frm 00017
Fmt 4701
Sfmt 4702
TABLE 6—REFINED MINIMALLY-SIZED
OG&E
DRY SCRUBBER COST
EFFECTIVENESS
Plant
Sooner 1 .........................
Sooner 2 .........................
Muskogee 4 ....................
Muskogee 5 ....................
E:\FR\FM\22MRP3.SGM
22MRP3
EPA’s Projected
Cost
(Refined)
($/ton SO2
removed)
$2,048
2,048
2,366
2,366
16184
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
TABLE 7—CONTRAST OF WET SCRUBBER COST EFFECTIVENESS
ODEQ projected cost
($/ton SO2 removed)
Plant
srobinson on DSKHWCL6B1PROD with PROPOSALS3
Sooner 1 ..................................................................................................................................
Sooner 2 ..................................................................................................................................
Muskogee 4 .............................................................................................................................
Muskogee 5 .............................................................................................................................
Northeastern 3 .........................................................................................................................
Northeastern 4 .........................................................................................................................
The ODEQ’s BART analyses
eliminated wet scrubbing, in part,
because the dollars per ton cost
effectiveness was calculated to be higher
than for dry scrubbing; the incremental
cost to go from dry to wet scrubbing was
judged unacceptable; and wet scrubbing
was alleged to have certain adverse
impacts that dry scrubbing did not have.
ODEQ determined that wet scrubbing
was not BART for SO2 for any of the
subject units. This determination was
based in part, on several alleged adverse
collateral impacts including: (1)
Increased sulfuric acid mist (SAM) in
the flue gas; (2) excess particulate
emitted due to the location of a scrubber
downstream of the particulate control
device; (3) the need for more reactant,
which would generate more fugitive
dust; (4) the need for significantly more
water; (5) the generation of a wastewater
stream that must be treated; and (6) the
creation of a higher visibility
impairment due to lower exit velocity,
lower stack temperature, and higher
SAM emissions. We have determined
these claims are either wrong or
overstated. Furthermore, we noted
several benefits of wet scrubbing and
some drawbacks to dry scrubbing,
which were not evaluated by ODEQ.
These issues are detailed in our
consultant’s report. Please see the TSD
for further discussion of our evaluation
of ODEQ’s determination that wet
scrubbing was not BART for SO2.
Although OG&E’s contractor did not
evaluate wet scrubbing in its final
updated BART analyses, ODEQ
modified an earlier OG&E wet scrubber
cost estimate as the basis for estimating
the cost of wet scrubbing. The total
capital requirement for wet scrubbers
was carried forward from the previous
cost estimate. ODEQ then modified
other costing parameters to be
consistent with OG&E’s contractor’s
current dry scrubber cost estimate.
These modifications included the
capital recovery factor, the annual
operating costs, and administrative
costs. AEP/PSO’s contractor did provide
a wet scrubber cost analysis as part of
its BART analyses, which was
incorporated into ODEQ’s BART
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
analysis. However, ODEQ’s wet
scrubber BART analyses for the OG&E
and AEP/PSO plants did not include the
kind of detailed, line-by-line cost
breakdown that is needed for a proper
evaluation.
We approached this problem by
comparing the cost of wet to dry
scrubbing for 13 cost effectiveness
analyses (including the earlier OG&E
analyses and the AEP/PSO analyses).
The results of this analysis indicated
that the average calculated cost
effectiveness of a wet scrubber is
typically about 9% higher than for a dry
scrubber, except in those cases where an
existing ESP can substitute for a new
baghouse. Although that specific option
was not evaluated or assumed in our
cost analyses, we note that the OG&E
and AEP/PSO units in question all have
existing ESPs, and we expect they could
be retained to reduce the cost. After
increasing the cost of our calculated dry
scrubbing estimate by 9%, we propose
to find that the cost of wet scrubbing for
the OG&E and AEP units fall within the
range of values found to be cost effective
in other similar wet scrubber cost
determinations. As we stated in the
BART Rule, ‘‘[a] reasonable range would
be a range that is consistent with the
range of cost effectiveness values used
in other similar permit decisions over a
period of time.’’ 70 FR 39104, 39168.
Dry scrubbers are being successfully
applied to many kinds of stationary
sources worldwide, including many
similar applications in the utility
industry.29 As explained in the
preamble to the BART Guidelines in
explaining the decision to establish
presumptive BART limits for SO2 based
on the use of scrubbers, both wet and
dry scrubbers are highly cost effective
for power plants, with costs of $400 to
$2000 per ton of SO2 removed typically.
70 FR at 39132. Thus, dry scrubbing is
clearly cost effective, barring an
unusual, site specific condition.
29 Electric Power Research Institute (EPRI), A
Review of Literature Related to the Use of Spray
Dryer Absorber Material: Production,
Characterization, Utilization Applications, Barriers,
and Recommendations, December 6, 2006, Table 1–
2.
PO 00000
Frm 00018
Fmt 4701
Sfmt 4702
$6,998
7,827
8,724
8,852
3,625
3,625
EPA’s projected cost
($/ton SO2 removed)
$1,555
1,555
1,417
1,417
1,699
1,699
However, neither OG&E nor AEP/PSO
identified any such conditions.
Similarly, wet scrubbing has been
employed in many coal fired power
plants in the United States, and is in fact
more widely used than dry scrubbing.
This includes the Pleasant Prairie Units
1 and 2 in Wisconsin, which are similar
to the OG&E and AEP/PSO units in
question.30 Therefore, because our cost
effectiveness calculations for the BART
units fall within the range for other
similar scrubber installations, we
propose to find that both dry and wet
scrubbing are cost effective in terms of
dollars per tons of SO2 removed.
Consequently, we propose to disapprove
ODEQ’s evaluation of the cost
effectiveness of control.
2. Visibility Benefit
Having considered the cost
effectiveness of wet and dry scrubbers
for OG&E and AEP/PSO, we then
considered the visibility improvement
that would result from the installation
of controls. As was done in assessing
costs, OG&E and AEP assessed visibility
on a facility basis. ODEQ 31 used the
CALPUFF modeling system, which
consists of a meteorological data preprocessor (CALMET), an air dispersion
model (CALPUFF), and post-processor
programs (POSTUTIL, CALSUM,
CALPOST). The CALPUFF modeling
system is the recommended model for
conducting BART visibility analysis.
The modeling analysis generally
followed the BART protocol developed
by CENRAP.32 In ODEQ’s modeling
approach, CALPUFF visibility modeling
for each pollutant was carried out
separately so that only NOX emissions
were modeled in support of the NOX
30 These units are 620 MW pulverized coal fired
boilers that burn similar low sulfur PRB coal (0.5–
0.7 lb/MMBtu) that were placed into service in 1980
and 1985, respectively. They were retrofitted with
wet scrubbers in 2006 and 2007, respectively.
31 Throughout this document, any reference to
‘‘ODEQ modeling’’ refers to modeling performed or
reviewed by ODEQ.
32 CENRAP BART Modeling Guidelines, T. W.
Tesche, D. E. McNally, and G. J. Schewe (Alpine
Geophysics LLC), December 15, 2005, available at
(https://www.deq.state.ok.us/aqdnew/
RulesAndPlanning/Regional_Haze/SIP/
Appendices/index.htm).
E:\FR\FM\22MRP3.SGM
22MRP3
16185
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
BART determination or only SO2/H2SO4
emissions for SO2 BART
determinations. Due to the nonlinear
nature and complexity of atmospheric
chemistry and chemical transformation
among pollutants, CALPUFF modeling
on a pollutant-specific basis is not
recommended.33 Furthermore, this
approach does not allow for predictions
of total visibility impairment for
different control scenarios at Class I area
receptors and the determination of the
98th percentile day for visibility
impairment. In the case of NOX BART
determinations for gas-fired units
performed by ODEQ, modeling results
from this approach are informative
because SO2 and PM emissions are
minimal.
Although we generally regard the
visibility modeling analyses performed
by ODEQ in support of BART
determinations to be of high quality,
some deviations from our guidance and
errors in emission calculations were
noted. We performed our own modeling
analysis of the three facilities,
incorporating changes to meet our
guidance and correct errors in emission
calculations. We note that refined
CALPUFF modeling included in
ODEQ’s SIP used updated
meteorological fields that included
observations in accordance with EPA
guidance (40 CFR Part 51, Appendix W)
and we utilized this data in our own
modeling analysis. In the ODEQ
modeling, sulfuric acid emissions from
the OG&E units were estimated based on
an assumed 1% SO2 to SO3 conversion
rate across the boiler. A control
efficiency of 40% was assumed for the
wet scrubbing control scenario and 90%
for the dry scrubbing scenario.
Emissions from the AEP/PSO units were
calculated based on an assumed 3 ppm
sulfur content conversion in the flue
gas. As detailed in the TSD, we utilized
a different approach based on the best
current information from the Electric
Power Research Institute (EPRI) 34 to
estimate the sulfuric acid released from
combustion in the boiler. ODEQ’s
speciation of PM emissions, estimated
for use in PM only modeling, contained
errors in the parameters used in the
calculation of speciation factors. As
discussed in the above sections, we
concluded that the dry scrubber and the
wet scrubber could achieve emission
limits of 0.06 lb/MMbtu SO2 and 0.04
lb/MMbtu SO2, respectively, and these
limits were used to calculate emissions
for our visibility modeling. Our
emission estimation methodology is
detailed in the TSD.
We remodeled the visibility impacts
of the OG&E and AEP/PSO units to
correct these errors and to provide
consistency with modeling guidance we
have provided to the states. First, the
model was run using the pre-BART
conditions to establish a baseline. For
all modeling runs, all relevant visibilityimpairing pollutants were included. The
model was then run to include the
control technology selected as NOX
BART, LNB with OFA, in order to
evaluate the visibility benefit expected
from this control and separate the
benefit of installation of NOX BART
from that due to SO2 control
technologies. Modeling results of the
visibility impact due to installation of
LNB show significant improvement in
visibility over the baseline. These
results in combination with review of
the cost analysis and other factors
considered in the ODEQ BART
determination support the conclusion
that LNB with OFA is NOX BART for
these units. To evaluate the anticipated
visibility improvement due to wet and
dry scrubbers, these control
technologies were modeled for each
facility. These modeling control
scenarios with scrubbers for SO2 also
included NOX emissions controlled by
LNB with OFA. The modeled visibility
impacts were then compared to the
impact achieved with only LNB with
OFA and no additional controls on SO2
to evaluate the incremental visibility
benefit of each SO2 control technology
(wet or dry scrubber).
The results of our visibility modeling
analyses, for the maximum impacts of
the 98th percentile delta-dv impacts
from 2001–2003 are presented as Table
8. These results employ our revised
emission calculations and methodology,
and the new IMPROVE equation
(Method 8). As can be seen from these
results, despite employing an SO2
emission limit of 0.04 lbs/MMBtu in the
wet scrubber case (versus 0.06 lbs/
MMBtu in the dry scrubber case), the
visibility modeling does not show a
consistent, clear benefit for wet
scrubbing. A possible explanation for
this is that by reducing the SO2
emissions to the rate of 0.06 lb/MMbtu,
the 98th percentile days are primarily
winter days when nitrate particulates
are responsible for the majority of
visibility impairment. Additional
controls of SO2 do not yield a reduction
in sulfate large enough to provide
significant visibility improvement for
the 98th percentile value. In some cases,
the further reduction in sulfate on these
days results in a small increase in
available ammonia for reaction with
NOX and leads to a slight increase in
visibility impairment due to additional
nitrate particulate that can offset the
benefit due to less sulfate particulate.
TABLE 8—EPA MODELED MAXIMUM IMPACTS OF THE 98TH PERCENTILE DELTA-DV IMPACTS FROM 2001–2003
Class I
area
Visibility impact (D dv)
Baseline
LNB
LNB & DFGD
LNB & WFGD
Improvement
over baseline
due to LNB
Improvement
over LNB
due to DFGD
Improvement
over LNB
due to WFGD
Sooner Units 1&2
srobinson on DSKHWCL6B1PROD with PROPOSALS3
Caney Creek ................
Hercules-Glades ..........
Upper Buffalo ...............
Wichita Mountains ........
0.73
0.71
0.77
2.08
0.50
0.43
0.49
1.46
0.13
0.13
0.13
0.41
0.13
0.12
0.12
0.35
0.23
0.28
0.28
0.62
0.37
0.30
0.35
1.05
0.38
0.31
0.37
1.11
Total ......................
4.28
2.88
0.80
0.71
1.41
2.08
2.16
0.51
0.19
0.29
0.14
0.74
0.74
0.69
0.73
Muskogee Units 4&5
Caney Creek ................
Hercules-Glades ..........
1.48
1.07
1.19
0.92
33 Memo from Joseph Paisie (Geographic
Strategies Group, OAQPS) to Kay Prince (Branch
Chief EPA Region 4) on Regional Haze Regulations
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
0.45
0.19
and Guidelines for Best Available Retrofit
Technology (BART) Determinations, July 19, 2006.
PO 00000
Frm 00019
Fmt 4701
Sfmt 4702
34 Electric Power Research Institute, Estimating
Total Sulfuric Acid Emissions from Stationary
Power Plants, 1016384, technical Update, March
2008.
E:\FR\FM\22MRP3.SGM
22MRP3
16186
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
TABLE 8—EPA MODELED MAXIMUM IMPACTS OF THE 98TH PERCENTILE DELTA-DV IMPACTS FROM 2001–2003—
Continued
Class I
area
Visibility impact (D dv)
Baseline
LNB & DFGD
LNB
LNB & WFGD
Improvement
over baseline
due to LNB
Improvement
over LNB
due to DFGD
Improvement
over LNB
due to WFGD
Upper Buffalo ...............
Wichita Mountains ........
1.52
1.31
1.20
1.03
0.37
0.29
0.33
0.34
0.31
0.27
0.84
0.75
0.87
0.70
Total ......................
5.37
4.35
1.29
1.37
1.02
3.06
2.98
Northeastern Units 3&4
Caney Creek ................
Hercules-Glades ..........
Upper Buffalo ...............
Wichita Mountains ........
1.70
0.92
1.52
1.66
0.99
0.88
0.85
1.39
0.29
0.18
0.28
0.30
0.30
0.20
0.28
0.31
0.71
0.04
0.67
0.27
0.70
0.70
0.57
1.09
0.69
0.68
0.57
1.08
Total ......................
5.80
4.11
1.05
1.09
1.69
3.06
3.02
In Table 9, we extract the results of
our visibility modeling from Table 8 for
the dry scrubbing case, and total the
results across the OG&E and AEP/PSO
facilities, and across Class I areas. This
is again based on the maximum impacts
98th Percentile delta-dv impacts from
2001–2003.
TABLE 9—EPA MODELED MAXIMUM IMPACTS DUE TO DRY SCRUBBING OF THE 98TH PERCENTILE DELTA-DV IMPACTS
FROM 2001–2003
Improvement over LNB + OFA due to dry scrubbing
Class I area
Sooner
Muskogee
Northeastern
Total
Sooner
Muskogee
Northeastern
Caney Creek ....................................................................................................
Hercules-Glades ..............................................................................................
Upper Buffalo ...................................................................................................
Wichita Mountains ...........................................................................................
0.37
0.30
0.35
1.05
0.74
0.74
0.84
0.75
0.70
0.70
0.57
1.09
1.81
1.74
1.76
2.89
Total All Class I Areas ..............................................................................
2.07
3.07
3.06
8.20
srobinson on DSKHWCL6B1PROD with PROPOSALS3
The visibility improvements
documented in Table 9 are significant
and will result in marked steps toward
reaching natural background conditions.
3. Our Conclusion on Oklahoma’s SO2
BART Evaluations for the Six OG&E and
AEP/PSO Units
As discussed above, ODEQ concludes
that it is too expensive to control the
SO2 emissions from the OG&E and AEP/
PSO units in question and that the
potential visibility benefits are not
substantial enough to justify additional
control. As we have shown above, we
disagree with ODEQ’s conclusion on
costs for SO2 controls and we find that
cost effective SO2 controls are available
and our modeling demonstrates that
substantial visibility improvement is
achievable based on the installation of
these controls. In particular, our
modeling indicates that dry scrubbing
will result in a 2.89 deciview
improvement in visibility at the Wichita
Mountains. Furthermore, the addition of
SO2 scrubbers (wet or dry) on each of
the three facilities (2 units at each
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
facility) will reduce visibility
impairment at Class I areas (Wichita
Mountains and/or other surrounding
Class I areas) from values that are above
the 1 deciview impact that is a direct
causation of visibility impairment to
levels that are below the 0.5 deciview
threshold that ODEQ used for
determining if a source contributed to
visibility impairment. We consider the
reduction in visibility impairment at
Wichita Mountains, Caney Creek, Upper
Buffalo, and Hercules-Glades to be
significant both for the RH SIP and also
for reduction of visibility impairment on
other states in meeting the requirements
of the 110 (a)(2)(D) SIP. Therefore, we
propose to disapprove Oklahoma’s
submitted SO2 BART determinations for
the six BART sources in question.
Consequently, we propose a FIP to
address this deficiency.
4. Alternative BART Determination
The RH submittal includes an
alternative to BART for the six BART
sources entitled ‘‘Greater Reasonable
Progress Alternative Determination’’
PO 00000
Frm 00020
Fmt 4701
Sfmt 4702
(Alternative Determination). This
Alternative Determination submittal
includes executed agreements between
ODEQ and OG&E, and ODEQ and AEP/
PSO entitled, ‘‘OG&E Regional Haze
Agreement, Case No. 10–024, and ‘‘PSO
Regional Haze Agreement, Case No. 10–
025.’’ The submitted Alternative
Determination provides for alternative
control scenarios that would apply were
we to disapprove ODEQ’s SO2 BART
determinations for the OG&E and AEP/
PSO units. Under the Alternative
Determination, following the exhaustion
of all administrative and judicial
appeals of disapproval by us of the
BART determinations for the six units,
the BART determination would be
superseded by a requirement that the
OG&E and AEP/PSO units comply with
either of the following requirements:
By January 1, 2018, install dry scrubbers
(and fabric filters for PM control at the OG&E
units) or otherwise meet SO2 and PM
emission limits specified by ODEQ.35
35 These emission limits are a 30-day rolling
average SO2 emission limit of 0.10 lbs/MMBtu.
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
By December 31, 2026, meet a combined
annual SO2 emission limit that is equivalent
to: (i) the SO2 emission limits specified by
ODEQ on half of the OG&E units and half of
the AEP/PSO units; and (ii) being at or below
the SO2 emissions that would result from
switching the remaining units to natural gas.
In other words, after having exhausted
any rights to challenge our disapproval
of ODEQ’s BART determinations, OG&E
and AEP/PSO could elect to either (1)
install dry scrubbers at the beginning of
2018; or (2) scrub half of their units
(again at the higher rate) and switch the
other half (not specified as to plant for
OG&E) to natural gas by the end of 2026.
We find that neither of these
alternatives would comport with the
requirements of section 51.308, as
explained below.
Our regulations do provide states with
the flexibility to adopt alternatives to
BART. Such alternatives, for example,
could include fuel switching beyond the
five-year window allowed for the
installation of BART. Such alternatives,
however, must be shown to provide for
greater reasonable progress than BART
does and must be fully implemented
prior to the close of the planning period
for the first regional haze SIP. 40 CFR
51.308(e)(2)(i) and (iii).
Even assuming that a contingent SIP
provision triggered by the conclusion of
all appeals regarding a related provision
could be considered enforceable, we do
not believe that the Alternative
Determination is approvable. We
propose to disapprove the Alternative
Determination because neither of the set
of contingent emission limitations meets
the requirements of our RH regulations
governing ‘‘better than BART’’
alternatives. As described above, ODEQ
concluded that BART requires no
additional controls at these units. The
Alternative Determination would apply
only where we have disagreed with this
conclusion, disapproved the SIP, and
prevailed in any ensuing litigation. It
seems highly probable in such a
situation that both the courts and we
would have concluded that BART
requires the use of scrubbers. Given this,
the first potential requirement, that the
BART units install scrubbers in January
2018, does not provide for greater
reasonable progress than does BART.
Rather, it allows OG&E and AEP/PSO to
delay the installation of scrubbers
beyond the time period allowed by the
CAA.36 In addition to the question of
timing, the emission limits associated
with the first potential requirement are
substantially higher than what we have
36 BART
must be installed and operational as
expeditiously as practicable, but in no event later
than five years after approval of an implementation
plan. CAA 169A(g)(4).
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
proposed as BART using the same
controls, dry scrubbers. We have not
seen any explanation from ODEQ as to
how allowing OG&E and AEP/PSO
additional time in which to meet less
stringent emission limitations provides
for greater reasonable progress.
The second potential requirement
does not require any reduction in
emissions from the BART units until
2026, near the end of the second longterm strategy period for RH. Again, we
have seen no explanation of how such
an extended compliance period would
result in greater reasonable progress.
More significantly, however, such an
approach is not allowed by our
regulations governing alternatives to
BART, which require all necessary
emission reductions to take place during
the period of the first long-term strategy
for RH, i.e. by 2018. 40 CFR
51.308(e)(2)(iii).
For the reasons discussed here, we
propose to disapprove as part of the
Oklahoma RH SIP, this submitted
‘‘Alternative Determination.’’ If
Oklahoma provides us with an
alternative demonstration that complies
with 40 CFR 51.308(e)(2)(i) and (iii), we
will consider it under a future action.
F. Federal Implementation Plan To
Address SO2 BART for the Six Sources
1. Introduction
As discussed above, we propose to
disapprove Oklahoma’s BART
determination for the six sources in
question. In addition, as discussed in
Section VI, we have determined that
additional controls are necessary on
these units to prevent emissions from
Oklahoma from interfering with other
states’ plans to improve visibility, and
we are partially disapproving the
Oklahoma SIP as it pertains to that
requirement. To correct the deficiencies
identified in these proposed
disapprovals, we are also proposing a
FIP.
In proposing a FIP to address BART,
we must consider the same factors as
states. As discussed above, we agree
with ODEQ’s evaluation for pollutants
other than SO2, but disagree for SO2 in
two respects. First, we believe that dry
scrubbing and wet scrubbing are both
cost effective. Second, we have
identified some concerns with ODEQ’s
estimation of visibility impacts and
accordingly have re-evaluated the
visibility impacts of these controls. Our
modeling shows that the use of these
controls will result in greater
improvement in visibility than
estimated by ODEQ.
We propose to find that both dry
scrubbing and wet scrubbing provide
PO 00000
Frm 00021
Fmt 4701
Sfmt 4702
16187
cost effective reductions of SO2. We also
believe that implementation of these
controls will provide substantial
visibility improvement at four Class I
areas.
2. Appropriate Emission Limits
In our BART Guidelines, we
established an SO2 presumptive limit
that applies to Electricity Generating
Units (EGUs) at power plants with a
total generating capacity in excess of
750 MW of either 0.15 lbs/MMBtu, or
95% control. 70 FR 39104, 39131. We
required that states, as a general matter,
must require owners and operators of
greater than 750 MW power plants to
meet these BART emission limits. In
addition, we noted that the presumption
does not limit the states’ ability to
consider whether a different level of
control is appropriate in a particular
case. We stated that ‘‘[i]f, upon
examination of an individual EGU, a
state determines that a different
emission limit is appropriate based
upon its analysis of the five factors, then
the state may apply a more or less
stringent limit.’’ Id. Because we are
making the BART determinations under
our FIP, we are obligated to determine
the appropriate level of control.
a. Dry Scrubber Emission Limit
As is detailed in our TSD, dry
scrubber performance varies with the
sulfur content of the coal. Our analysis
indicates that a dry scrubber on the
OG&E units can remove approximately
90% of the SO2 when burning coal with
an uncontrolled emission rate of
approximately 0.51 lb/MMBtu, 91.5%
when burning coal corresponding to
ODEQ’s proposed BART limit of 0.65 lb/
MMBtu, and 95% when burning the
coal used to size the scrubber, 1.18 lb/
MMBtu. Similarly, our analysis
indicates that a dry scrubber on the
Northeastern units can remove
approximately 93% of the SO2 when
burning coal with an uncontrolled
emission rate of 0.9 lb/MMBtu, and
91.5% when burning coal
corresponding to ODEQ’s proposed
BART limit of 0.65 lb/MMBtu. This
information is summarized in Table 10:
TABLE 10—EXPECTED DRY SCRUBBER
PERFORMANCE VS. UNCONTROLLED
EMISSION RATES
Control
(percent)
90.0
91.5
93.0
95.0
Uncontrolled
emission rate
(lbs/MMBtu)
........
........
........
........
E:\FR\FM\22MRP3.SGM
22MRP3
0.51
0.65
0.90
1.18
Controlled
emission rate
(lbs/MMBtu)
0.051
0.055
0.063
0.059
16188
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
Based on this information, our
analysis indicates that an SO2 emission
limit of 0.06 lbs/MMBtu can be met on
the basis of a 30-day rolling average for
the OG&E and AEP/PSO units, using dry
scrubber technologies. As is noted in
our TSD, there are already facilities
operating below this emission rate,
using dry scrubber technologies, and
that burn similar coals.
b. Wet Scrubber Emission Limit
According to OG&E’s contractor,
‘‘[w]et scrubbing is the predominant
technology for large-scale utility
applications in most parts of the world.’’
In addition, ‘‘SO2 removal guarantees of
up to 99% (without additives) are
available from the system suppliers and
have been demonstrated in commercial
applications, though there is a practical
outlet limitation at 0.04 lb. SO2/MBtu,
which represents a lower percentage
removal for the lowest sulfur coals.’’ 37
However, as we note in our TSD,
Pleasant Prairie Units 1 and 2, similar
boilers that burn a similar low sulfur
PRB coal, were retrofitted with wet
scrubbers in 2006 and 2007. An
examination of our Clean Air Markets
Division SO2 emissions data for Unit 1
for the period 2007 through June 2010
indicates this unit easily meets a 365day rolling average of less than 0.03 lb/
MMBtu. Similarly, the Minnesota Power
Boswell 3 unit was recently retrofit with
a wet scrubber (among other pollution
control upgrades) and, based on our
Clean Air Markets Division SO2
emissions data, it appears to be
achieving a monthly average emission
rate of less than 0.03 lbs/MMBtu. This,
along with other similar examples
discussed in our TSD, indicates that wet
scrubbing at the OG&E and AEP/PSO
units could consistently result in an SO2
removal efficiency of 98%, or meet an
emission limit of 0.04 lbs/MMBtu on a
30-day rolling average.
srobinson on DSKHWCL6B1PROD with PROPOSALS3
3. Visibility Benefit From Dry and Wet
Scrubbing
As discussed in our evaluation of
ODEQ’s BART evaluation, our modeling
indicates substantial visibility benefit
from the implementation of dry
scrubbing. We did not find substantial
additional visibility benefits on the 98th
percentile value from the use of wet
scrubbers even though we believe wet
scrubbers would be expected to achieve
lower emissions. As a result, we
propose that the emission limit in the
37 Sargent & Lundy, Flue Gas Desulfurization
Technology, Dry Lime vs. Wet Limestone FGD,
Prepared for National Lime Association, March
2007.
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
FIP be based on the emission levels that
can be achieved by dry scrubbing.
4. EPA’s SO2 BART Determination for
the Six Units
As described above, for the particular
cases we are considering in this action,
we have concluded there is a lack of a
clear visibility advantage to wet
scrubbing at the SO2 emission rates we
have considered. Other details
concerning the input values we have
assumed in our visibility modeling are
contained in the TSD. We invite
comment on all aspects of our visibility
modeling. Given that wet scrubbing is
approximately 9% higher in cost on a
$/tons of SO2 removed basis, we
propose that SO2 BART for the Units 4
and 5 of the OG&E Muskogee plant,
Units 1 and 2 of the OG&E Sooner plant,
and Units 3 and 4 of the AEP/PSO
Northeastern plant should be based on
dry scrubbing. We note there are
significant advantages to wet scrubbing
that OG&E and/or AEP/PSO may find
attractive as a means of satisfying our
proposed FIP.
As we note above, under section
51.308(e)(1)(iv), ‘‘each source subject to
BART [is] required to install and operate
BART as expeditiously as practicable,
but in no event later than 5 years after
approval of the implementation plan
revision.’’ Based on the retrofit of other
scrubber installations we have
reviewed, we find that three (3) years
from the date our final determination
becomes effective is adequate time for
the installation and operation of these
controls.38 We solicit comments on
alternative timeframes, of from two (2)
years up to five (5) years from the
effective date our final rule.
We do not wish to dissuade
companies from exercising the option of
switching to natural gas as a means of
satisfying their BART obligations under
section 51.308(e). Such an approach, for
example, would be acceptable for
satisfying SO2 BART,39 if it satisfies the
requirement under section
51.308(e)(1)(iv) that, ‘‘each source
subject to BART be required to install
and operate BART as expeditiously as
38 Engineering and Economic Factors Affecting
the Installation of Control Technologies for
Multipollutant Strategies, EPA–600/R–02/073,
October 2002, pdf pagination 5: ‘‘Conservatively
high assumptions were made for the time, labor,
reagents, and steel needed to install FGD systems.
For LSFO installation timing, it is expected that one
system requires about 27 months of total effort for
planning, engineering, installation, and startup,
with connections occurring during normally
scheduled outages),’’ available at https://
www.epa.gov/clearskies/pdfs/multi102902.pdf.
39 We note that, as with the other fossil fuel fired
power plant BART determinations contained within
this proposal, separate NOx and PM BART
determinations must also be made.
PO 00000
Frm 00022
Fmt 4701
Sfmt 4702
practicable, but in no event later than 5
years after approval of the
implementation plan revision.’’
Switching to natural gas would be an
acceptable method of complying with
the limits proposed in this FIP. In
addition, we invite comments as to,
considering the engineering and/or
management challenges of such a fuel
switch, whether the full 5 years allowed
under section 308(e)(1)(iv) following our
final action would be justified.
G. Long-Term Strategy
As described in section IV.E of this
action, the LTS is a compilation of statespecific control measures relied on by
the state for achieving its RPGs.
Oklahoma’s LTS for the first
implementation period addresses the
emissions reductions from federal, state,
and local controls that take effect in the
state from the end of the baseline period
starting in 2004 until 2018. The
Oklahoma LTS was developed by
ODEQ, in coordination with the
CENRAP RPO, through an evaluation of
the following components: (1)
Construction of a CENRAP 2002
baseline emission inventory; (2)
construction of a CENRAP 2018
emission inventory, including
reductions from CENRAP member state
controls required or expected under
federal and state regulations, (including
BART); (3) modeling to determine
visibility improvement and apportion
individual state contributions; (4) state
consultation; and (5) application of the
LTS factors.
1. Emissions Inventory
Section 51.308(d)(3)(iii) requires that
Oklahoma document the technical basis,
including modeling, monitoring and
emissions information, on which it
relied upon to determine its
apportionment of emission reduction
obligations necessary for achieving
reasonable progress in each mandatory
Class I Federal area it affects. Oklahoma
must identify the baseline emissions
inventory on which its strategies are
based. Section 51.308(d)(3)(iv) requires
that Oklahoma identify all
anthropogenic sources of visibility
impairment considered by the state in
developing its long-term strategy. This
includes major and minor stationary
sources, mobile sources, and area
sources. Oklahoma met these
requirements by relying on technical
analyses developed by its RPO,
CENRAP and approved by all state
participants, as described below.
The emissions inventory used in the
RH technical analyses was developed by
CENRAP with assistance from
Oklahoma. The 2018 emissions
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
inventory was developed by projecting
2002 emissions and applying reductions
expected from federal and state
regulations affecting the emissions of
the visibility-impairing pollutants NOX,
PM, SO2,, and VOCs.
a. Oklahoma’s 2002 Emission Inventory
ODEQ and CENRAP developed an
emission inventory for five inventory
16189
source classifications: Point, area, nonroad and on-road mobile sources, and
biogenic sources for the baseline year of
2002. Oklahoma’s 2002 emissions
inventory is summarized in Table 11:
TABLE 11—OKLAHOMA’S 2002 EMISSIONS INVENTORY
SO2
NH3
NOX
VOCs
PM10–
PM2.5
PM2.5
Point .........................................................
Area ..........................................................
Non-road mobile ......................................
On-road mobile ........................................
Biogenic ...................................................
148,761
11,779
4,773
4,708
0
24,102
114,363
280
4,434
0
158,818
115,407
49,396
142,592
35,909
37,794
201,758
47,863
99,924
988,314
8,026
304,560
433
879
0
8,636
109,279
4,580
2,459
0
Total ..................................................
170,021
143,179
502,122
1,375,653
313,898
124,954
See the TSD for details on how the
2002 emissions inventory was
constructed. We propose that
Oklahoma’s 2002 emission inventory is
acceptable.
b. Oklahoma’s 2018 Emission Inventory
In general, ODEQ used a combination
of our Economic Growth Analysis
System (EGAS 5), our mobile emissions
factor model (MOBILE 6), our off-road
emissions factor model (NONROAD),
and the Integrated Planning Model
(IPM) for electric generating units in
constructing its 2018 emission
inventory. ODEQ modified the projected
emissions from the IPM modeling for
OG&E Sooner and Muskogee electric
power plants and the PSO Northeast
electric power plants to reflect the
application of presumptive BART
controls.40 More specifically, CENRAP
developed emissions for five inventory
source classifications: point, area, nonroad and on-road mobile sources, and
biogenic sources. CENRAP used its 2002
emission inventory, described above, to
estimate emissions in 2018. All control
strategies expected to take effect prior to
2018 are included in the projected
emission inventory. Oklahoma’s 2018
emissions inventory is summarized in
Table 12:
TABLE 12—OKLAHOMA’S 2018 EMISSIONS INVENTORY
SO2
NH3
NOX
VOCs
PM10–
PM2.5
PM2.5
Point .........................................................
Area ..........................................................
Non-road mobile ......................................
On-road mobile ........................................
Biogenic ...................................................
106,701
12,374
156
545
0
35,215
141,532
40
5,818
0
140,298
128,257
25,387
39,397
35,909
125,648
400,056
28,489
39,281
988,314
8,935
275,844
2,914
0
0
13,989
127,018
292
953
0
Total ..................................................
119,776
182,605
369,248
1,581,788
287,693
142,252
srobinson on DSKHWCL6B1PROD with PROPOSALS3
See the TSD for details on how the
2018 emissions inventory was
constructed. CENRAP and ODEQ used
this and other state’s 2018 emission
inventories to construct visibility
projection modeling for 2018. We
propose that Oklahoma’s 2018 emission
inventory is acceptable but for its
inclusion of reductions from the OG&E
and AEP/PSO coal fired units that were
not ultimately required by Oklahoma.
As discussed above, we propose a FIP
to address this deficiency.
2. Visibility Projection Modeling
CENRAP performed modeling for the
RH LTS for its member states, including
Oklahoma. The modeling analysis is a
40 Note, our proposed FIP, discussed in section
V.E, would require a stricter level of SO2 for six
units in these facilities.
41 Guidance on the Use of Models and Other
Analyses for Demonstrating Attainment of Air
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
complex technical evaluation that began
with selection of the modeling system.
CENRAP used (1) the Mesoscale
Meteorological Model (MM5)
meteorological model, (2) the Sparse
Matrix Operator Kernel Emissions
(SMOKE) modeling system to generate
hourly gridded speciated emission
inputs, (3) the Community Multiscale
Air Quality (CMAQ) photochemical grid
model and (4) the Comprehensive Air
Quality model with extensions (CAMx),
as a secondary corroborative model.
CAMx was also utilized with its
Particulate Source Apportionment
Technology (PSAT) tool to provide
source apportionment for both the
baseline and future case visibility
modeling.
The photochemical modeling of RH
for the CENRAP states for 2002 and
2018 was conducted on the 36-km
resolution national regional planning
organization domain that covered the
continental United States, portions of
Canada and Mexico, and portions of the
Atlantic and Pacific Oceans along the
east and west coasts. The CENRAP
states’ modeling was developed
consistent with our guidance.41
CENRAP examined the model
performance of the regional modeling
for the areas of interest before
determining whether the CMAQ model
results were suitable for use in the RH
Quality Goals for Ozone, PM2.5, and Regional Haze,
(EPA–454/B–07–002), April 2007, located at
https://www.epa.gov/scram001/guidance/guide/
final-03-pm-rh-guidance.pdf. Emissions Inventory
Guidance for Implementation of Ozone and
Particulate Matter National Ambient Air Quality
Standards (NAAQS) and Regional Haze
Regulations, August 2005, updated November 2005
(‘‘our Modeling Guidance’’), located at https://
www.epa.gov/ttnchie1/eidocs/eiguid/,
EPA–454/R–05–001.
PO 00000
Frm 00023
Fmt 4701
Sfmt 4702
E:\FR\FM\22MRP3.SGM
22MRP3
16190
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
assessment of the LTS and for use in the
modeling assessment. The 2002
modeling efforts were used to evaluate
air quality/visibility modeling for a
historical episode—in this case, for
calendar year 2002—to demonstrate the
suitability of the modeling systems for
subsequent planning, sensitivity, and
emissions control strategy modeling.
Model performance evaluation is
performed by comparing output from
model simulations with ambient air
quality data for the same time period to
determine whether the model’s
performance is sufficiently accurate to
justify using the model for simulating
future conditions. Once CENRAP
determined the model performance to
be acceptable, it used the model to
determine the 2018 RPGs using the
current and future year air quality
modeling predictions, and compared the
RPGs to the URP. Table 13, derived from
Table VIII–9 of the Oklahoma RH SIP
submittal, summarizes the projected
contribution from Oklahoma emissions
on visibility degradation at Class I areas
for the 20 percent worst days in 2018.
Note, this table only includes
contributions of 0.15 deciviews or
greater.
TABLE 13—PROJECTED CONTRIBUTION FROM OKLAHOMA EMISSIONS ON VISIBILITY DEGRADATION FOR THE 20 PERCENT
WORST DAYS IN 2018
Contribution to
light extinction
(Mm-1)
Class I area
State
Wichita Mountains .......................
Hercules-Glades ..........................
Salt Creek ....................................
Caney Creek ................................
Upper Buffalo ...............................
Guadalupe Mountains ..................
Seney ...........................................
White Mountain ............................
Isle Royale ...................................
Oklahoma ....................................
Missouri .......................................
New Mexico .................................
Arkansas ......................................
Arkansas ......................................
Texas ...........................................
Michigan ......................................
New Mexico .................................
Michigan ......................................
srobinson on DSKHWCL6B1PROD with PROPOSALS3
3. Consultation and Emissions
Reductions for Other States’ Class I
Areas
As in the development of Oklahoma’s
reasonable progress goal for the Wichita
Mountains, ODEQ used CENRAP as its
main vehicle for facilitating
collaboration with FLMs and other
states in satisfying its LTS consultation
requirement. This helped ODEQ and
other state environmental agencies
analyze emission apportionments at
Class I areas and develop coordinated
RH SIP strategies.
Section 51.308(d)(3)(i) requires that
Oklahoma consult with other states if its
emissions are reasonably anticipated to
contribute to visibility impairment at
that state’s Class I area(s), and that
Oklahoma consult with other states if
their emissions are reasonably
anticipated to contribute to visibility
impairment at the Wichita Mountains.
ODEQ’s consultations with other states
are described in section V.C.3 above.
After evaluating whether emissions
from Oklahoma sources contribute to
visibility impairment in other states’
Class I areas, ODEQ concluded there
was no contribution sufficient to require
consultation. ODEQ’s evaluation relied,
however, upon SO2 BART reductions
from the six units of the OG&E and
AEP/PSO three coal fired power plants
but these reductions are not required.
Regardless of its conclusions regarding
the impacts of Oklahoma emissions on
other states’ Class I areas, however,
Oklahoma did consult with other states
VerDate Mar<15>2010
19:03 Mar 21, 2011
Jkt 223001
Total light
extinction
(Mm-1)
12.28
3.74
1.46
2.23
1.97
1.11
1.74
0.69
1.08
and tribes, largely through the CENRAP
process. We propose that those
consultations adequately satisfy the
requirement under Section
51.308(d)(3)(i).
Section 51.308(d)(3)(ii) requires that if
Oklahoma emissions cause or contribute
to impairment in another state’s Class I
area, Oklahoma must demonstrate that it
has included in its RH SIP all measures
necessary to obtain its share of the
emission reductions needed to meet the
progress goal for that Class I area.
Section 51.308(d)(3)(ii) also requires
that since Oklahoma participated in a
regional planning process, it must
ensure it has included all measures
needed to achieve its apportionment of
emission reduction obligations agreed
upon through that process. As we state
in the RHR 42, Oklahoma’s commitments
to participate in CENRAP bind it to
secure emission reductions agreed to as
a result of that process, unless it
proposes a separate process and
performs its consultations on the basis
of that process:
While States are not bound by the
results of a regional planning effort, nor
can the content of their SIPs be dictated
by a regional planning body, we expect
that a coordinated regional effort will
likely produce results the States will
find beneficial in developing their
regional haze implementation plans.
Any State choosing not to follow the
recommendations of a regional body
would need to provide a specific
42 64
PO 00000
FR 35735.
Frm 00024
Fmt 4701
Sfmt 4702
Oklahoma
contribution
(percent)
86.56
103.49
57.67
96.84
97.16
55.43
95.27
40.8
73.71
14.19
3.61
2.53
2.30
2.03
2.00
1.83
1.70
1.46
Deciview
contribution
1.53
0.37
0.26
0.23
0.21
0.20
0.18
0.17
0.15
technical basis that its strategy
nonetheless provides for reasonable
progress based on the statutory factors.
At the same time, EPA cannot require
States to participate in regional
planning efforts if the State prefers to
develop a long-term strategy on its own.
We note that any State that acts alone
in this regard must conduct the
necessary technical support to justify
their apportionment, which generally
will require regional inventories and a
regional modeling analysis.
Additionally, any such State must
consult with other States before
submitting its long-term strategy to EPA.
Consequently, because Oklahoma
accepted and incorporated the CENRAPdeveloped visibility modeling into its
RH SIP, which assumed controls for the
six units discussed above that were not
subsequently secured, we propose to
disapprove Oklahoma’s long term
strategy.
However, our proposed FIP does
include controls for the six units that at
least achieve the level of control
assumed in the CENRAP modeling. In
addition, as described above, Oklahoma
has required controls on additional
sources as part of its BART evaluation.
Therefore, we propose to find that with
the addition of our proposed FIP, the
requirements in section 51.308(d)(3)(ii)
have been met.
4. Mandatory Long Term Strategy
Factors
Section 51.308(d)(3)(v) requires that
Oklahoma minimally consider certain
E:\FR\FM\22MRP3.SGM
22MRP3
srobinson on DSKHWCL6B1PROD with PROPOSALS3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
factors in developing its long-term
strategy (the LTS factors). These
include: (1) Emission reductions due to
ongoing air pollution control programs,
including measures to address RAVI; (2)
measures to mitigate the impacts of
construction activities; (3) emissions
limitations and schedules for
compliance to achieve the reasonable
progress goal; (4) source retirement and
replacement schedules; (5) smoke
management techniques for agricultural
and forestry management purposes
including plans as currently exist
within the state for these purposes; (6)
enforceability of emissions limitations
and control measures; and (7) the
anticipated net effect on visibility due to
projected changes in point, area, and
mobile source emissions over the period
addressed by the long-term strategy. For
the reasons outlined below, we propose
to find that Oklahoma has satisfied all
the requirements of Section
51.308(d)(3)(v).
In addition to its BART
determinations and by extension our
proposed FIP, Oklahoma’s LTS
incorporates emission reductions due to
a number of ongoing air pollution
control programs. This includes the
issuance and enforcement of permits
limiting emissions (based on our
National Ambient Air Quality
Standards) from all major sources in
Oklahoma (the SIP also includes
permits for minor sources), state rules
which specifically limit targeted
emissions sources and categories, and
other air pollution control programs that
ODEQ administers. We note that fine
and coarse particulate, of which
construction-related activities are
thought to be a small contributor, are
themselves minor contributors to
visibility impairment at the Wichita
Mountains. ODEQ relies on fugitive dust
control rules to control and minimize
dust from construction activities. ODEQ
has adopted rules to ensure the
enforceability of these emission
limitations. This includes rules that
govern ODEQ’s permitting process for
major and minor sources, Prevention of
Significant Deterioration (PSD)
provisions, Best Available Control
Technology (BACT), and BART
requirements. These rules have
corresponding compliance schedules
and enforcement protocols and are
summarized in the TSD.
ODEQ issues permits to all major and
minor point sources in Oklahoma, and
each permit contains enforceable
limitations on emissions of various
pollutants, including those which cause
or contribute to RH at the Wichita
Mountains. Unless those permits specify
a different schedule for compliance,
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
ODEQ requires permitted sources to
comply with their permits immediately
upon issuance. ODEQ also enforces
compliance schedules of relevant
administrative and judicial orders,
including consent decrees that result in
significant SO2 and NOX reductions.
We approved ODEQ’s SIP to address
reasonably attributable visibility
impairment at the Wichita Mountains
on November 8, 1999. See 64 FR 60683.
As we note in section V.H, the FLMs did
not identify any integral vistas in
Oklahoma. In addition, the Wichita
Mountains is not experiencing RAVI,
nor are any Oklahoma sources affected
by the RAVI provisions. Therefore, the
Oklahoma RH SIP does not incorporate
any measures to specifically address
RAVI.
ODEQ considered source retirement
and replacement schedules in
developing its long-term strategy of
emissions reductions. ODEQ stated it
cannot reliably predict the retirement or
replacement of sources and
consequently does not rely on source
retirement to achieve any reasonable
progress goal.
Fires are responsible for much of the
directly emitted fine particulate matter
in the Oklahoma emissions inventory.
ODEQ considered smoke management
techniques for the purposes of
agricultural and forestry management in
its LTS. As Tables IV–1 and IV–2 in the
Oklahoma RH SIP revision submittal
indicate, all types of fire sources
(wildfire, agricultural burning,
rangeland burning, etc.) are responsible
for approximately 4.2% of the total SO2,
4.1% of the total NH3, 3.9% of the total
NOX, 2.1% of the total VOCs, and 3.6%
of the total PM10 emissions. In contrast,
fire is responsible for about 33.4% of the
total PM2.5 emissions. However, Table
VIII–3 of the Oklahoma RH SIP
indicates that all Oklahoma area sources
combined, of which fire is only a part,
account for less than 1% of the total
visibility impact at the Wichita
Mountains. Nevertheless, ODEQ states
that it and the Oklahoma Department of
Agriculture, Food, and Forestry intend
to create a basic, voluntary smoke
management program based on our
Interim Air Quality Policy on Wildland
and Prescribed Fires. We commend this
effort and offer our assistance in the
development of this plan.
Section 51.308(d)(3)(v)(F) requires
that Oklahoma ensure the enforceability
of emission limitations and control
measures used to meet reasonable
progress goals. ODEQ has issued
enforceable Title V operating permits
requiring BART-eligible sources subject
to BART to install BART and achieve
the associated BART emission limits.
PO 00000
Frm 00025
Fmt 4701
Sfmt 4702
16191
Similarly, any BART requirement in a
FIP must be included by ODEQ in a Part
70 air quality permit. See 70 FR at
39172.
ODEQ has demonstrated it has the
statutory authority to regulate air
emissions from all facilities and sources
subject to operating permit requirements
under Title V of the CAA. ODEQ also
has the authority to administratively
and judicially enforce any provision of
an ODEQ issued air quality permits. See
the TSD for more details on Oklahoma
laws that provide for this authority.
H. Coordination of RAVI and Regional
Haze Requirements
Our visibility regulations direct states
to coordinate their RAVI LTS and
monitoring provisions with those for
RH, as explained in section IV, above.
Under our RAVI regulations, the RAVI
portion of a state SIP must address any
integral vistas identified by the FLMs
pursuant to 40 CFR 51.304. See 40 CFR
51.302. An integral vista is defined in 40
CFR 51.301 as a ‘‘view perceived from
within the mandatory Class I Federal
area of a specific landmark or panorama
located outside the boundary of the
mandatory Class I Federal area.’’
Visibility in any mandatory Class I
Federal area includes any integral vista
associated with that area. The FLMs did
not identify any integral vistas in
Oklahoma. In addition, the Wichita
Mountains is not experiencing RAVI,
nor are any Oklahoma sources affected
by the RAVI provisions. Thus, the
Oklahoma RH SIP submittal does not
explicitly address the two requirements
regarding coordination of RH with the
RAVI LTS and monitoring provisions.
However, Oklahoma previously made a
commitment to address RAVI should
the FLM certify visibility impairment
from an individual source.43 We
propose to find that this RH submittal
appropriately supplements and
augments Oklahoma’s RAVI visibility
provisions to address RH by updating
the monitoring and LTS provisions as
summarized below in this section.
I. Monitoring Strategy and Other SIP
Requirements
Section 51.308(d)(4) requires the SIP
contain a monitoring strategy for
measuring, characterizing, and reporting
of RH visibility impairment that is
representative of all mandatory Class I
Federal areas within the state. This
monitoring strategy must be coordinated
with the monitoring strategy required in
Section 51.305 for reasonably
43 Oklahoma’s Part 1 and Part II visibility SIP
contained RAVI provisions and was previously
approved by EPA (64 FR 60683).
E:\FR\FM\22MRP3.SGM
22MRP3
srobinson on DSKHWCL6B1PROD with PROPOSALS3
16192
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
attributable visibility impairment. As
Section 51.308(d)(4) notes, compliance
with this requirement may be met
through participation in the IMPROVE
network. Since the monitor at the
Wichita Mountains is an IMPROVE
monitor, we propose that ODEQ has
satisfied this requirement. See the TSD
for details concerning the IMPROVE
network.
Section 51.308(d)(4)(i) requires the
establishment of any additional
monitoring sites or equipment needed to
assess whether reasonable progress
goals to address RH for all mandatory
Class I Federal areas within the state are
being achieved. Shortly after the
creation of CENRAP, its monitoring
workgroup noted the lack of a
representative monitor for the Wichita
Mountains. At that time, an IMPROVE
site for Upper Buffalo, Arkansas, in a
wetter climate several hundred miles to
the east-northeast, provided the closest
available visibility monitoring data.
Because this monitoring data was
deemed unrepresentative, a particle
sampler monitor was established at the
Wichita Mountains and began operating
in March, 2001. As described in section
V.B., above, baseline visibility
conditions were calculated using data
representative of 2002–2004 due to lack
of data from previous years. With the
addition of the monitor at the Wichita
Mountains, we propose to find that
ODEQ has satisfied this requirement.
Section 51.308(d)(4)(ii) requires that
ODEQ establish procedures by which
monitoring data and other information
are used in determining the contribution
of emissions from within Oklahoma to
RH visibility impairment at mandatory
Class I Federal areas both within and
outside the state. The monitor at the
Wichita Mountains is operated by
Wichita Mountains personnel. The
IMPROVE monitoring program is
national in scope, and other states have
similar monitoring and data reporting
procedures, ensuring a consistent and
robust monitoring data collection
system. As section 51.308(d)(4)
indicates, participation in the IMPROVE
program constitutes compliance with
this requirement. We therefore propose
that ODEQ has satisfied this
requirement.
Section 51.308(d)(4)(iv) requires that
the SIP must provide for the reporting
of all visibility monitoring data to the
Administrator at least annually for each
mandatory Class I Federal area in the
state. To the extent possible, Oklahoma
should report visibility monitoring data
electronically. Section 51.308(d)(4)(vi)
also requires that ODEQ provide for
other elements, including reporting,
recordkeeping, and other measures,
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
necessary to assess and report on
visibility. We propose that Oklahoma’s
participation in the IMPROVE network
ensures the monitoring data is reported
at least annually, is easily accessible,
and therefore complies with this
requirement.
Section 51.308(d)(4)(iv) requires that
ODEQ maintain a statewide inventory of
emissions of pollutants that are
reasonably anticipated to cause or
contribute to visibility impairment in
any mandatory Class I Federal area. The
inventory must include emissions for a
baseline year, emissions for the most
recent year for which data are available,
and estimates of future projected
emissions. The state must also include
a commitment to update the inventory
periodically. Please refer to section V.G.,
above, where we discuss ODEQ’s
emission inventory. ODEQ has stated
that it intends to update the Oklahoma
statewide emissions inventories
periodically and review periodic
emissions information from other states
and future emissions projections. We
propose that this satisfies the
requirement.
J. Federal Land Manager Coordination
The Wichita Mountains is one of more
than 546 refuges throughout the United
States managed by the Fish and Wildlife
Service, which is the Federal Land
Manager (FLM) for this Class I area.
Although the FLMs are very active in
participating in the RPOs, the RH Rule
grants the FLMs a special role in the
review of the RH SIPs, summarized in
section IV.H., above. We view both the
FLMs and the state environmental
agencies as our partners in the RH
process.
Section 51.308(i)(1) requires that by
November 29, 1999, Oklahoma must
have identified in writing to the FLMs
the title of the official to which the FLM
of the Wichita Mountains can submit
any recommendations on the
implementation of section 51.308. We
acknowledge this section has been
satisfied by all states via communication
prior to this SIP.
Under Section 51.308(i)(2), Oklahoma
was obligated to provide the Fish and
Wildlife Service with an opportunity for
consultation, in person and at least 60
days prior to holding a public hearing
on it RH SIP. In practice, state
environmental agencies have usually
provided all FLMs—the Forest Service,
the Park Service, and the Fish and
Wildlife Service, copies of their RH SIP,
as the FLMs collectively have reviewed
these RH SIPs. ODEQ followed this
practice and sent its draft of this
implementation plan revision to the
federal land manager staff on October 1,
PO 00000
Frm 00026
Fmt 4701
Sfmt 4702
2009 and notified the federal land
manager staff of the public hearing held
on December 16, 2009. In its letter dated
December 4, 2009, transmitting its
comments, the Fish and Wildlife
Service acknowledged having received
Oklahoma’s draft RH SIP on October 5,
2009.
The FLMs have communicated to us
their dissatisfaction with the fact that
the draft RH SIP they were provided by
ODEQ was markedly different than the
version ODEQ submitted to us as their
final RH SIP. Specifically, the FLMs
note that in the version of the SIP they
reviewed, SO2 BART for the six OG&E
and AEP/PSO coal fired units that are
the subject of our FIP was determined
by ODEQ to be dry SO2 scrubbers with
an emission limit of 0.10 lbs/MMBtu for
the OG&E units, and 0.153 lbs/MMBtu
for the AEP–PSO units. When ODEQ
submitted their final RH SIP to us, those
SO2 BART determinations were changed
to replace the SO2 scrubber
requirements with an SO2 limit of 0.65
lbs/MMBtu on a 30 day rolling average
that corresponds to uncontrolled low
sulfur coal. We note the Fish and
Wildlife Service has not requested that
ODEQ re-open their 60 day comment
period. We would like to address any
question as to whether section
51.308(i)(2) has been satisfied. We
believe, however, that our proposed FIP,
as described in section V.F., above, may
alleviate these concerns. We invite the
FLMs to provide comment on this or
other aspects of our proposal.
Section 51.308(i)(3) requires that
ODEQ provide in its RH SIP a
description of how it addressed any
comments provided by the FLMs. ODEQ
has provided that information in
Appendix 10–2 of its RH SIP.
Lastly, Section 51.308(i)(4) specifies
the RH SIP must provide procedures for
continuing consultation between the
state and Federal Land Manager on the
implementation of the visibility
protection program required by section
51.308, including development and
review of implementation plan revisions
and 5-year progress reports, and on the
implementation of other programs
having the potential to contribute to
impairment of visibility in the
mandatory Class I Federal areas. ODEQ
has stipulated in its RH SIP it will
continue to coordinate and consult with
the FLMs as required by section
51.308(i)(4). ODEQ states it intends to
consult the FLMs in the development
and review of implementation plan
revisions; review of progress reports;
and development and implementation
of other programs that may contribute to
impairment of visibility at the Wichita
Mountains and other Class I areas. We
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
propose that ODEQ has satisfied section
51.308(i).
srobinson on DSKHWCL6B1PROD with PROPOSALS3
K. Periodic SIP Revisions and Five-Year
Progress Reports
ODEQ affirmed its commitment to
complete items required in the future
under our RHR. ODEQ acknowledged its
requirement under 40 CFR 51.308(f), to
submit periodic progress reports and RH
SIP revisions, with the first report due
by July 31, 2018 and every ten years
thereafter.
ODEQ also acknowledged its
requirement under 40 CFR 51.308(g), to
submit a progress report in the form of
a SIP revision every five years following
this initial submittal of the Oklahoma
RH SIP. The report will evaluate the
progress made towards the RPGs for
each mandatory Class I area located
within Oklahoma and in each
mandatory Class I area located outside
Oklahoma which may be affected by
emissions from within Oklahoma.
If another state’s RH SIP identifies
that Oklahoma’s SIP needs to be
supplemented or modified, and if, after
appropriate consultation Oklahoma
agrees, today’s action may be revisited,
or the additional information and/or
changes will be addressed in the fiveyear progress report SIP revision.
VI. Our Analysis of Oklahoma’s
Interstate Visibility Transport SIP
Provisions
We received a SIP from Oklahoma to
address the interstate transport
requirements of CAA 110(a)(2)(D)(i) for
the 1997 8-hour ozone and PM2.5
NAAQS on May 10, 2007, as
supplemented on December 10, 2007.
Concerning such CAA requirements
preventing sources in the state from
emitting pollutants in amounts which
will interfere with efforts to protect
visibility in other states, Oklahoma
stated that it was on track for the
submission of its RH SIP by the
December, 17, 2007 deadline.44
Oklahoma states in its May 10, 2007
submittal that it intended that its RH
SIP be used to satisfy the requirements
of section 110(a)(2)(D)(i)(II) that
emissions from Oklahoma sources do
not interfere with measures required in
the SIP of any other state under part C
of the CAA to protect visibility.
However, it did not establish that
emissions from its sources would not
interfere with the visibility programs of
other states, nor did it as part of its
February 19, 2010 RH SIP submittal. In
order to evaluate whether Oklahoma’s
existing SIP adequately prevents
interference with the visibility programs
44 See
40 CFR 51.308(b).
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
of other states, we propose to address
this question using other available
information.
As an initial matter, we note that
section 110(a)(2)(D)(i)(II) does not
explicitly specify how we should
ascertain whether a state’s SIP contains
adequate provisions to prevent
emissions from sources in that state
from interfering with measures required
in another state to protect visibility.
Thus, the statute is ambiguous on its
face, and we must interpret that
provision.
Our 2006 Guidance recommended
that a state could meet the visibility
prong of the transport requirements of
section 110(a)(2)(D)(i)(II) of the CAA by
submission of the RH SIP, due in
December 2007. Our reasoning was that
the development of the RH SIPs was
intended to occur in a collaborative
environment among the states. In fact,
in developing their respective
reasonable progress goals, CENRAP
states consulted with each other through
CENRAP’s work groups. As a result of
this process, the common understanding
was that each state would take action to
achieve the emissions reductions relied
upon by other states in their reasonable
progress demonstrations under the RHR.
CENRAP states consulted in the
development of reasonable progress
goals, using the products of this
technical consultation process to codevelop their reasonable progress goals.
In developing their visibility projections
using photochemical grid modeling,
CENRAP states assumed a certain level
of emissions from sources within
Oklahoma. As we discuss above in
section V.G, this modeling assumed SO2
reductions from the six OG&E and AEP/
PSO coal fired units that are the subject
of our FIP. Although we have not yet
received all RH SIPs, we understand
that the CENRAP states used the
visibility projection modeling to
establish their own respective
reasonable progress goals. Thus, we
believe that an implementation plan
that provides for emissions reductions
consistent with the assumptions used in
those states’ modeling will ensure that
emissions from Oklahoma sources do
not interfere with the measures
designed to protect visibility in other
states.
However, after the visibility
projection modeling and all
consultations were completed,
Oklahoma revised its SO2 BART
determinations for these six units, as
submitted in the RH SIP submittal of
February 19, 2010, removing the
requirement that they be controlled to
ensure these agreed upon emissions
limits would be met. Consistent with
PO 00000
Frm 00027
Fmt 4701
Sfmt 4702
16193
our proposed conclusion that Oklahoma
has not obtained its needed share of
emission reductions, as we discuss
above in section V.G.3, we propose to
find that the Oklahoma SIP revision
submittals do not ensure that emissions
from sources in Oklahoma do not
interfere with other State’s visibility
programs as required by section
110(a)(2)(D)(i)(II) of the CAA.
Our proposed FIP does include
controls for the six units that at least
achieve the level of control assumed in
the CENRAP modeling. In addition, as
described in section V.D., above,
Oklahoma has required controls on
sources as part of its BART evaluation.
Thus, we believe that the controls
proposed under our FIP, plus the
additional controls required by
Oklahoma under its SIP that we propose
to approve, constitute the assemblage of
cost effective controls that are
reasonable at this time, and serve to
prevent sources in Oklahoma from
emitting pollutants in amounts that will
interfere with efforts to protect visibility
in other states. In light of this, we
propose to partially approve and
partially disapprove the Oklahoma SIP
revision submitted to address the
requirements of section
110(a)(2)(D)(i)(II) of the CAA.
VII. Proposed Actions
A. Regional Haze
We propose to partially approve and
partially disapprove Oklahoma’s RH SIP
revision submitted on February 19,
2010. Specifically, we propose to
disapprove the SO2 BART
determinations for Units 4 and 5 of the
Oklahoma Gas and Electric Muskogee
plant; Units 1 and 2 of the Oklahoma
Gas and Electric Sooner plant; and Units
3 and 4 of the American Electric Power/
Public Service Company of Oklahoma
Northeastern plant. We propose to
disapprove these SO2 BART
determinations because they do not
comply with our regulations under 40
CFR 51.308(e). We are also proposing to
disapprove Oklahoma’s long term
strategy under section 51.308(d)(3)
because it does not incorporate these
emission reductions. ODEQ participated
in the CENRAP visibility modeling
development that assumed certain SO2
reductions from these six BART units.
ODEQ also performed its consultations
with other states with the understanding
that these reductions would be secured.
We propose a FIP to cure these defects
in BART and the LTS.
We propose to find that Units 4 and
5 of the OG&E Muskogee plant, Units 1
and 2 of the OG&E Sooner plant, and
Units 3 and 4 of the AEP/PSO
E:\FR\FM\22MRP3.SGM
22MRP3
srobinson on DSKHWCL6B1PROD with PROPOSALS3
16194
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
Northeastern plant are subject to BART
under 40 CFR 51.308(e). Further, we
propose a FIP that specifically imposes
SO2 BART on these six sources. We
propose that SO2 BART for Units 4 and
5 of the OG&E Muskogee plant, Units 1
and 2 of the OG&E Sooner plant, and
Units 3 and 4 of the AEP/PSO
Northeastern plant is an SO2 emission
limit of 0.06 lbs/MMBtu that applies
singly to each of these units on a 30 day
rolling average. Additionally, we
propose monitoring, record-keeping,
and reporting requirements to ensure
compliance with these emission
limitations.
We propose that compliance with the
emission limits be within three (3) years
of the effective date of our final rule. We
solicit comments on alternative
timeframes, of from two (2) years up to
five (5) years from the effective date of
our final rule.
Should OG&E and/or AEP/PSO elect
to reconfigure the above units to burn
natural gas, as a means of satisfying
their BART obligations under section
51.308(e), that conversion should be
completed by the same time frame. We
invite comments as to, considering the
engineering and/or management
challenges of such a fuel switch,
whether the full 5 years allowed under
section 308(e)(1)(iv) following the
effective date of our final rule would be
appropriate.
We propose to disapprove section
VI.E of the Oklahoma RH SIP entitled,
‘‘Greater Reasonable Progress
Alternative Determination.’’ We also
propose to disapprove the separate
executed agreements between ODEQ
and OG&E, and ODEQ and AEP/PSO
entitled ‘‘OG&E Regional Haze
Agreement, Case No. 10–024,’’ and ‘‘PSO
Regional Haze Agreement, Case No. 10–
025,’’ housed within Appendix 6–5 of
the RH SIP. We propose that these
portions of the submittal are severable
from the BART determinations and the
LTS; therefore, no FIP is required.
We are taking no action on whether
Oklahoma has satisfied the reasonable
progress requirements of section
51.308(d)(1).
We propose to approve all other
portions of the Oklahoma RH SIP. We
note that all controls required as part of
Oklahoma’s BART determinations, not
included as part of our proposed FIP,
must be operational within five years
from the effective date of our final rule.
B. Interstate Transport of Visibility
We are also proposing to partially
approve and partially disapprove a
portion of a SIP revision submitted by
the State of Oklahoma for the purpose
of addressing the ‘‘good neighbor’’
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
provisions of the CAA section
110(a)(2)(D)(i) for the 1997 8-hour ozone
NAAQS and the PM2.5 NAAQS.
Specifically, we propose a partial
approval and partial disapproval of the
Oklahoma Interstate Transport SIP
provisions that address the requirement
of section 110(a)(2)(D)(i)(II) that
emissions from Oklahoma sources do
not interfere with measures required in
the SIP of any other state under part C
of the CAA to protect visibility. With
regard to whether emissions from
Oklahoma sources interfere with the
visibility programs of other states, we
are proposing to find that Oklahoma
sources, except for Units 4 and 5 of the
OG&E Muskogee plant, Units 1 and 2 of
the OG&E Sooner plant, and Units 3 and
4 of the AEP/PSO Northeastern plant,
are sufficiently controlled to eliminate
interference with the visibility programs
of other states, and for the six units we
are proposing specific SO2 emission
limits that will eliminate such interstate
interference.
VIII. Statutory and Executive Order
Reviews
A. Executive Order 12866: Regulatory
Planning and Review
This proposed action is not a
‘‘significant regulatory action’’ under the
terms of Executive Order (EO) 12866 (58
FR 51735, October 4, 1993), and is
therefore not subject to review under the
Executive Order. The proposed FIP
applies to only three facilities and is not
a rule of general applicability.
B. Paperwork Reduction Act
This proposed action does not impose
an information collection burden under
the provisions of the Paperwork
Reduction Act, 44 U.S.C. 3501 et seq.
Under the Paperwork Reduction Act, a
‘‘collection of information’’ is defined as
a requirement for ‘‘answers to * * *
identical reporting or recordkeeping
requirements imposed on ten or more
persons * * *.’’ 44 U.S.C. 3502(3)(A).
Because the proposed FIP applies to just
three facilities, the Paperwork
Reduction Act does not apply. See 5
CFR 1320(c).
Burden means the total time, effort, or
financial resources expended by persons
to generate, maintain, retain, or disclose
or provide information to or for a
Federal agency. This includes the time
needed to review instructions; develop,
acquire, install, and utilize technology
and systems for the purposes of
collecting, validating, and verifying
information, processing and
maintaining information, and disclosing
and providing information; adjust the
existing ways to comply with any
PO 00000
Frm 00028
Fmt 4701
Sfmt 4702
previously applicable instructions and
requirements; train personnel to be able
to respond to a collection of
information; search data sources;
complete and review the collection of
information; and transmit or otherwise
disclose the information.
An agency may not conduct or
sponsor, and a person is not required to
respond to a collection of information
unless it displays a currently valid
Office of Management and Budget
(OMB) control number. The OMB
control numbers for our regulations in
40 CFR are listed in 40 CFR part 9.
C. Regulatory Flexibility Act
The Regulatory Flexibility Act (RFA)
generally requires an agency to prepare
a regulatory flexibility analysis of any
rule subject to notice and comment
rulemaking requirements under the
Administrative Procedure Act or any
other statute unless the agency certifies
that the rule will not have a significant
economic impact on a substantial
number of small entities. Small entities
include small businesses, small
organizations, and small governmental
jurisdictions.
For purposes of assessing the impacts
of today’s proposed rule on small
entities, small entity is defined as: (1) A
small business as defined by the Small
Business Administration’s (SBA)
regulations at 13 CFR 121.201; (2) a
small governmental jurisdiction that is a
government of a city, county, town,
school district or special district with a
population of less than 50,000; and (3)
a small organization that is any not-forprofit enterprise which is independently
owned and operated and is not
dominant in its field.
After considering the economic
impacts of this proposed action on small
entities, I certify that this proposed
action will not have a significant
economic impact on a substantial
number of small entities. The FIP for the
three Oklahoma facilities being
proposed today does not impose any
new requirements on small entities. The
proposed partial approval of the SIP, if
finalized, merely approves state law as
meeting Federal requirements and
imposes no additional requirements
beyond those imposed by state law. See
Mid-Tex Electric Cooperative, Inc. v.
FERC, 773 F.2d 327 (D.C. Cir. 1985)
D. Unfunded Mandates Reform Act
(UMRA)
Under sections 202 of the Unfunded
Mandates Reform Act of 1995
(‘‘Unfunded Mandates Act’’), signed into
law on March 22, 1995, EPA must
prepare a budgetary impact statement to
accompany any proposed or final rule
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
that includes a Federal mandate that
may result in estimated costs to State,
local, or tribal governments in the
aggregate; or to the private sector, of
$100 million or more (adjusted to
inflation). Under section 205, EPA must
select the most cost-effective and least
burdensome alternative that achieves
the objectives of the rule and is
consistent with statutory requirements.
Section 203 requires EPA to establish a
plan for informing and advising any
small governments that may be
significantly or uniquely impacted by
the rule.
EPA has determined that the approval
action proposed does not include a
Federal mandate that may result in
estimated costs of $100 million or more
to either State, local, or tribal
governments in the aggregate, or to the
private sector. This Federal action
proposes to approve pre-existing
requirements under State or local law,
and imposes no new requirements.
Accordingly, no additional costs to
State, local, or tribal governments, or to
the private sector, result from this
action.
srobinson on DSKHWCL6B1PROD with PROPOSALS3
E. Executive Order 13132: Federalism
Federalism (64 FR 43255, August 10,
1999) revokes and replaces Executive
Orders 12612 (Federalism) and 12875
(Enhancing the Intergovernmental
Partnership). Executive Order 13132
requires EPA to develop an accountable
process to ensure ‘‘meaningful and
timely input by State and local officials
in the development of regulatory
policies that have federalism
implications.’’ ‘‘Policies that have
federalism implications’’ is defined in
the Executive Order to include
regulations that have ‘‘substantial direct
effects on the States, on the relationship
between the national government and
the States, or on the distribution of
power and responsibilities among the
various levels of government.’’ Under
Executive Order 13132, EPA may not
issue a regulation that has federalism
implications, that imposes substantial
direct compliance costs, and that is not
required by statute, unless the Federal
government provides the funds
necessary to pay the direct compliance
costs incurred by State and local
governments, or EPA consults with
State and local officials early in the
process of developing the proposed
regulation. EPA also may not issue a
regulation that has federalism
implications and that preempts State
law unless the Agency consults with
State and local officials early in the
process of developing the proposed
regulation.
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
This rule will not have substantial
direct effects on the States, on the
relationship between the national
government and the States, or on the
distribution of power and
responsibilities among the various
levels of government, as specified in
Executive Order 13132, because it
merely addresses the State not fully
meeting its obligation to prohibit
emissions from interfering with other
states measures to protect visibility
established in the CAA. Thus, Executive
Order 13132 does not apply to this
action. In the spirit of Executive Order
13132, and consistent with EPA policy
to promote communications between
EPA and State and local governments,
EPA specifically solicits comment on
this proposed rule from State and local
officials.
F. Executive Order 13175: Consultation
and Coordination With Indian Tribal
Governments
Executive Order 13175, entitled
Consultation and Coordination with
Indian Tribal Governments (65 FR
67249, November 9, 2000), requires EPA
to develop an accountable process to
ensure ‘‘meaningful and timely input by
tribal officials in the development of
regulatory policies that have tribal
implications.’’ This proposed rule does
not have tribal implications, as specified
in Executive Order 13175. It will not
have substantial direct effects on tribal
governments. Thus, Executive Order
13175 does not apply to this rule. EPA
specifically solicits additional comment
on this proposed rule from tribal
officials.
G. Executive Order 13045: Protection of
Children From Environmental Health
Risks and Safety Risks
Executive Order 13045: Protection of
Children from Environmental Health
Risks and Safety Risks (62 FR 19885,
April 23, 1997), applies to any rule that:
(1) is determined to be economically
significant as defined under Executive
Order 12866; and (2) concerns an
environmental health or safety risk that
we have reason to believe may have a
disproportionate effect on children. If
the regulatory action meets both criteria,
the Agency must evaluate the
environmental health or safety effects of
the planned rule on children, and
explain why the planned regulation is
preferable to other potentially effective
and reasonably feasible alternatives
considered by the Agency. However, to
the extent this proposed rule will limit
emissions of SO2, the rule will have a
beneficial effect on children’s health by
reducing air pollution.
PO 00000
Frm 00029
Fmt 4701
Sfmt 4702
16195
This rule is not subject to Executive
Order 13045 because it does not involve
decisions intended to mitigate
environmental health or safety risks.
However, to the extent this proposed
rule will limit emissions of SO2, the rule
will have a beneficial effect on
children’s health by reducing air
pollution.
H. Executive Order 13211: Actions
Concerning Regulations That
Significantly Affect Energy Supply,
Distribution, or Use
This action is not subject to Executive
Order 13211 (66 FR 28355 (May 22,
2001)), because it is not a significant
regulatory action under Executive Order
12866.
I. National Technology Transfer and
Advancement Act
Section 12 of the National Technology
Transfer and Advancement Act
(NTTAA) of 1995 requires Federal
agencies to evaluate existing technical
standards when developing a new
regulation. To comply with NTTAA,
EPA must consider and use ‘‘voluntary
consensus standards’’ (VCS) if available
and applicable when developing
programs and policies unless doing so
would be inconsistent with applicable
law or otherwise impractical.
The EPA believes that VCS are
inapplicable to this action. Today’s
action does not require the public to
perform activities conducive to the use
of VCS.
J. Executive Order 12898: Federal
Actions To Address Environmental
Justice in Minority Populations and
Low-Income Populations
Executive Order 12898 (59 FR 7629,
February 16, 1994), establishes federal
executive policy on environmental
justice. Its main provision directs
federal agencies, to the greatest extent
practicable and permitted by law, to
make environmental justice part of their
mission by identifying and addressing,
as appropriate, disproportionately high
and adverse human health or
environmental effects of their programs,
policies, and activities on minority
populations and low-income
populations in the United States.
We have determined that this
proposed rule, if finalized, will not have
disproportionately high and adverse
human health or environmental effects
on minority or low-income populations
because it increases the level of
environmental protection for all affected
populations without having any
disproportionately high and adverse
human health or environmental effects
on any population, including any
E:\FR\FM\22MRP3.SGM
22MRP3
16196
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
minority or low-income population.
This proposed rule limits emissions of
SO2 from three facilities in Oklahoma.
The partial approval of the SIP, if
finalized, merely approves state law as
meeting Federal requirements and
imposes no additional requirements
beyond those imposed by state law.
List of Subjects in 40 CFR Part 52
Environmental protection, Air
pollution control, Intergovernmental
relations, Nitrogen dioxide, Ozone,
Particulate matter, Reporting and
recordkeeping requirements, Sulfur
dioxides, Visibility, Interstate transport
of pollution, Regional haze, Best
available control technology.
Dated: March 4, 2011.
Al Armendariz,
Regional Administrator, Region 6.
Title 40, chapter I, of the Code of
Federal Regulations is proposed to be
amended as follows:
PART 52—[AMENDED]
1. The authority citation for part 52
continues to read as follows:
Authority: 42 U.S.C. 7401 et seq.
2. Part 52 is proposed to be amended
by adding § 52.1923 to read as follows:
srobinson on DSKHWCL6B1PROD with PROPOSALS3
§ 52.1923 Interstate pollutant transport
provisions; What are the FIP requirements
for Units 4 and 5 of the Oklahoma Gas and
Electric Muskogee plant; Units 1 and 2 of
the Oklahoma Gas and Electric Sooner
plant; and Units 3 and 4 of the American
Electric Power/Public Service Company of
Oklahoma Northeastern plant affecting
visibility?
(a) Applicability. The provisions of
this section shall apply to each owner
or operator, or successive owners or
operators, of the coal burning
equipment designated as: Units 4 or 5 of
the Oklahoma Gas and Electric
Muskogee plant; Units 1 or 2 of the
Oklahoma Gas and Electric Sooner
plant; and Units 3 or 4 of the American
Electric Power/Public Service Company
of Oklahoma Northeastern plant.
(b) Compliance Dates. Compliance
with the requirements of this section is
required within 3 years of the effective
date of this rule unless otherwise
indicated by compliance dates
contained in specific provisions.
(c) Definitions. All terms used in this
part but not defined herein shall have
the meaning given them in the Clean Air
Act and in parts 51 and 60 of this title.
For the purposes of this section:
24-hour period means the period of
time between 12:01 a.m. and 12
midnight. Air pollution control
equipment includes selective catalytic
control units, baghouses, particulate or
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
gaseous scrubbers, and any other
apparatus utilized to control emissions
of regulated air contaminants which
would be emitted to the atmosphere.
Daily average means the arithmetic
average of the hourly values measured
in a 24-hour period.
Heat input means heat derived from
combustion of fuel in a unit and does
not include the heat input from
preheated combustion air, recirculated
flue gases, or exhaust gases from other
sources. Heat input shall be calculated
in accordance with 40 CFR part 75.
Owner or Operator means any person
who owns, leases, operates, controls, or
supervises any of the coal burning
equipment designated as:
(i) Unit 4 of the Oklahoma Gas and
Electric Muskogee plant; or
(ii) Unit 5 of the Oklahoma Gas and
Electric Muskogee plant; or
(ii) Unit 1 of the Oklahoma Gas and
Electric Sooner plant; or
(iv) Unit 2 of the Oklahoma Gas and
Electric Sooner plant; or
(v) Unit 3 of the American Electric
Power/Public Service Company of
Oklahoma Northeastern plant; or
(vi) Unit 4 of the American Electric
Power/Public Service Company of
Oklahoma Northeastern plant.
Regional Administrator means the
Regional Administrator of EPA Region 6
or his/her authorized representative.
Unit means one of the coal fired
boilers covered under paragraph (a) of
this section.
(d) Emissions Limitations. SO2
emission limit. The individual sulfur
dioxide emission limit for a unit shall
be 0.06 pounds per million British
thermal units (lb/MMBtu) as averaged
over a rolling 30 calendar day period.
For each unit, SO2 emissions for each
calendar day shall be determined by
summing the hourly emissions
measured in pounds of SO2. For each
unit, heat input for each calendar day
shall be determined by adding together
all hourly heat inputs, in millions of
BTU. Each day the thirty-day rolling
average for a unit shall be determined
by adding together the pounds of SO2
from that day and the preceding 29 days
and dividing the total pounds of SO2 by
the sum of the heat input during the
same 30-day period. The result shall be
the 30-day rolling average in terms of lb/
MMBtu emissions of SO2. If a valid SO2
pounds per hour or heat input is not
available for any hour for a unit, that
heat input and SO2 pounds per hour
shall not be used in the calculation of
the 30-day rolling average for SO2.
(e) Testing and monitoring. (1) No
later than the compliance date of this
regulation, the owner or operator shall
install, calibrate, maintain and operate
PO 00000
Frm 00030
Fmt 4701
Sfmt 4702
Continuous Emissions Monitoring
Systems (CEMS) for SO2 on Units 4 and
5 of the Oklahoma Gas and Electric
Muskogee plant; Units 1 and 2 of the
Oklahoma Gas and Electric Sooner
plant; and Units 3 and 4 of the
American Electric Power/Public Service
Company of Oklahoma Northeastern
plant in accordance with 40 CFR 60.8
and 60.13(e), (f), and (h), and Appendix
B of Part 60. The owner or operator shall
comply with the quality assurance
procedures for CEMS found in 40 CFR
part 75. Compliance with the emission
limits for SO2 shall be determined by
using data from a CEMS.
(2) Continuous emissions monitoring
shall apply during all periods of
operation of the coal burning
equipment, including periods of startup,
shutdown, and malfunction, except for
CEMS breakdowns, repairs, calibration
checks, and zero and span adjustments.
Continuous monitoring systems for
measuring SO2 and diluent gas shall
complete a minimum of one cycle of
operation (sampling, analyzing, and
data recording) for each successive 15minute period. Hourly averages shall be
computed using at least one data point
in each fifteen minute quadrant of an
hour. Notwithstanding this requirement,
an hourly average may be computed
from at least two data points separated
by a minimum of 15 minutes (where the
unit operates for more than one
quadrant in an hour) if data are
unavailable as a result of performance of
calibration, quality assurance,
preventive maintenance activities, or
backups of data from data acquisition
and handling system, and recertification
events. When valid SO2 pounds per
hour, or SO2 pounds per million Btu
emission data are not obtained because
of continuous monitoring system
breakdowns, repairs, calibration checks,
or zero and span adjustments, emission
data must be obtained by using other
monitoring systems approved by the
EPA to provide emission data for a
minimum of 18 hours in each 24 hour
period and at least 22 out of 30
successive boiler operating days.
(f) Reporting and Recordkeeping
Requirements. Unless otherwise stated
all requests, reports, submittals,
notifications, and other communications
to the Regional Administrator required
by this section shall be submitted,
unless instructed otherwise, to the
Director, Multimedia Planning and
Permitting Division, U.S. Environmental
Protection Agency, Region 6, to the
attention of Mail Code: 6PD, at 1445
Ross Avenue, Suite 1200, Dallas, Texas
75202–2733. For each unit subject to the
emissions limitation in this section and
upon completion of the installation of
E:\FR\FM\22MRP3.SGM
22MRP3
Federal Register / Vol. 76, No. 55 / Tuesday, March 22, 2011 / Proposed Rules
srobinson on DSKHWCL6B1PROD with PROPOSALS3
CEMS as required in this section, the
owner or operator shall comply with the
following requirements:
(1) For each emissions limit in this
section, comply with the notification,
reporting, and recordkeeping
requirements for CEMS compliance
monitoring in 40 CFR 60.7(c) and (d).
(2) For each day, provide the total SO2
emitted that day by each emission unit.
For any hours on any unit where data
for hourly pounds or heat input is
missing, identify the unit number and
monitoring device that did not produce
valid data that caused the missing hour.
(g) Equipment Operations. At all
times, including periods of startup,
shutdown, and malfunction, the owner
VerDate Mar<15>2010
18:40 Mar 21, 2011
Jkt 223001
or operator shall, to the extent
practicable, maintain and operate the
unit including associated air pollution
control equipment in a manner
consistent with good air pollution
control practices for minimizing
emissions. Determination of whether
acceptable operating and maintenance
procedures are being used will be based
on information available to the Regional
Administrator which may include, but
is not limited to, monitoring results,
review of operating and maintenance
procedures, and inspection of the unit.
(h) Enforcement. (1) Notwithstanding
any other provision in this
implementation plan, any credible
PO 00000
Frm 00031
Fmt 4701
Sfmt 9990
16197
evidence or information relevant as to
whether the unit would have been in
compliance with applicable
requirements if the appropriate
performance or compliance test had
been performed, can be used to establish
whether or not the owner or operator
has violated or is in violation of any
standard or applicable emission limit in
the plan.
(2) Emissions in excess of the level of
the applicable emission limit or
requirement that occur due to a
malfunction shall constitute a violation
of the applicable emission limit.
[FR Doc. 2011–5799 Filed 3–21–11; 8:45 am]
BILLING CODE 6560–50–P
E:\FR\FM\22MRP3.SGM
22MRP3
Agencies
[Federal Register Volume 76, Number 55 (Tuesday, March 22, 2011)]
[Proposed Rules]
[Pages 16168-16197]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-5799]
[[Page 16167]]
Vol. 76
Tuesday,
No. 55
March 22, 2011
Part III
Environmental Protection Agency
-----------------------------------------------------------------------
40 CFR Part 52
Approval and Promulgation of Implementation Plans; Oklahoma; Regional
Haze State Implementation Plan; Federal Implementation Plan for
Interstate Transport of Pollution Affecting Visibility and Best
Available Retrofit Technology Determinations; Proposed Rule
Federal Register / Vol. 76 , No. 55 / Tuesday, March 22, 2011 /
Proposed Rules
[[Page 16168]]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[EPA-R06-OAR-2010-0190; FRL-9279-7]
Approval and Promulgation of Implementation Plans; Oklahoma;
Regional Haze State Implementation Plan; Federal Implementation Plan
for Interstate Transport of Pollution Affecting Visibility and Best
Available Retrofit Technology Determinations
AGENCY: Environmental Protection Agency (EPA).
ACTION: Proposed rule.
-----------------------------------------------------------------------
SUMMARY: EPA is proposing to partially approve and partially disapprove
a revision to the Oklahoma State Implementation Plan (SIP) submitted by
the State of Oklahoma through the Oklahoma Department of Environmental
Quality (ODEQ) on February 19, 2010 that addresses regional haze for
the first implementation period. This revision was submitted to address
the requirements of the Clean Air Act (CAA or Act) and our rules that
require states to prevent any future and remedy any existing man-made
impairment of visibility in mandatory Class I areas caused by emissions
of air pollutants from numerous sources located over a wide geographic
area (also referred to as the ``regional haze program''). States are
required to assure reasonable progress toward the national goal of
achieving natural visibility conditions in Class I areas. EPA is
proposing to approve a portion of this SIP revision as meeting certain
requirements of the regional haze program and to partially approve and
partially disapprove those portions addressing the requirements for
best available retrofit technology (BART) and the long-term strategy
(LTS). EPA is proposing a Federal Implementation Plan (FIP) to
implement sulfur dioxide (SO2) emission limits on six
sources to address these issues. EPA also is proposing to disapprove
the State's submitted alternative to BART; EPA is taking no action on
the submitted reasonable progress goals at this time. In addition, EPA
is proposing to partially approve and partially disapprove a portion of
a revision to the Oklahoma SIP submitted by the State of Oklahoma on
May 10, 2007 and supplemented on December 10, 2007. We are taking
action on that portion of the submittals addressing the requirements of
CAA as it applies to visibility for the 1997 8-hour ozone and 1997
particulate matter (PM2.5) National Ambient Air Quality
Standards (NAAQS). This portion of the submittals addresses the
requirement that Oklahoma's SIP contain adequate provisions to prohibit
emissions from interfering with measures required in another state to
protect visibility. In this action, we propose a FIP to address the
deficiencies in this portion of Oklahoma's SIP submittals. The proposed
FIP will prevent emissions from six Oklahoma sources from interfering
with other states' measures to protect visibility and to implement
sulfur dioxide emission limits on these six sources to prevent such
interference.
DATES: Comments: Comments must be received on or before May 23, 2011.
Public Hearing. An open house and public hearing for this proposal
is scheduled to be held on Wednesday April 13, 2011, at the Metro
Technology Centers, Springlake Campus, Business Conference Center,
Meeting Rooms H and I, 1900 Springlake Drive, Oklahoma City, OK 73111,
(405) 424-8324. The Metro Technology Centers Springlake Campus is
located at the intersection of Martin Luther King Ave. and Springlake
Dr. between NE. 36th and NE. 50th just south of the Oklahoma City Zoo
and Kirkpatrick Center. Parking for the Business Conference Center is
available at no charge. The open house will begin at 1 p.m. and end at
3 p.m. local time. The public hearing will be held from 4 p.m. until 6
p.m., and again from 7 p.m. until 9 p.m.
The public hearing will provide interested parties the opportunity
to present information and opinions to EPA concerning our proposal.
Interested parties may also submit written comments, as discussed in
the proposal. Written statements and supporting information submitted
during the comment period will be considered with the same weight as
any oral comments and supporting information presented at the public
hearing. We will not respond to comments during the public hearing.
When we publish our final action, we will provide written responses to
all oral and written comments received on our proposal. To provide
opportunities for questions and discussion, we will hold an open house
prior to the public hearing. During the open house, EPA staff will be
available to informally answer questions on our proposed action. Any
comments made to EPA staff during the open house must still be provided
formally in writing or orally during the public hearing in order to be
considered in the record.
At the public hearing, the hearing officer may limit the time
available for each commenter to address the proposal to 5 minutes or
less if the hearing officer determines it to be appropriate. We will
not be providing equipment for commenters to show overhead slides or
make computerized slide presentations. Any person may provide written
or oral comments and data pertaining to our proposal at the Public
Hearing. Verbatim transcripts, in English, of the hearing and written
statements will be included in the rulemaking docket.
Addresses: Submit your comments, identified by Docket No. EPA-R06-
OAR-2010-0190, by one of the following methods:
Federal e-Rulemaking Portal: https://www.regulations.gov.
Follow the online instructions for submitting comments.
E-mail: r6air_okhaze@epa.gov.
Mail: Mr. Joe Kordzi, Air Planning Section (6PD-L),
Environmental Protection Agency, 1445 Ross Avenue, Suite 1200, Dallas,
Texas 75202-2733.
Hand or Courier Delivery: Mr. Joe Kordzi, Air Planning
Section (6PD-L), Environmental Protection Agency, 1445 Ross Avenue,
Suite 700, Dallas, Texas 75202-2733. Such deliveries are accepted only
between the hours of 8 a.m. and 4 p.m. weekdays, and not on legal
holidays. Special arrangements should be made for deliveries of boxed
information.
Fax: Mr. Joe Kordzi, Air Planning Section (6PD-L), at fax
number 214-665-7263.
Instructions: Direct your comments to Docket No. EPA-R06-OAR-2010-
0190. Our policy is that all comments received will be included in the
public docket without change and may be made available online at https://www.regulations.gov, including any personal information provided,
unless the comment includes information claimed to be Confidential
Business Information (CBI) or other information whose disclosure is
restricted by statute. Do not submit information that you consider to
be CBI or otherwise protected through www.regulations.gov or e-mail.
The https://www.regulations.gov Web site is an ``anonymous access''
system, which means we will not know your identity or contact
information unless you provide it in the body of your comment. If you
send an e-mail comment directly to us without going through
www.regulations.gov your e-mail address will be automatically captured
and included as part of the comment that is placed in the public docket
and made available on the Internet. If you submit an electronic
comment, we recommend that you include your name and other contact
information in the body of your comment and with any disk or CD-ROM you
submit. If we cannot read your comment due to
[[Page 16169]]
technical difficulties and cannot contact you for clarification, we may
not be able to consider your comment. Electronic files should avoid the
use of special characters, any form of encryption, and be free of any
defects or viruses.
Docket: All documents in the docket are listed in the https://www.regulations.gov index. Although listed in the index, some
information is not publicly available, e.g., CBI or other information
whose disclosure is restricted by statute. Certain other material, such
as copyrighted material, will be publicly available only in hard copy.
Publicly available docket materials are available either electronically
in www.regulations.gov or in hard copy at the Air Planning Section
(6PD-L), Environmental Protection Agency, 1445 Ross Avenue, Suite 700,
Dallas, Texas 75202-2733. The file will be made available by
appointment for public inspection in the Region 6 FOIA Review Room
between the hours of 8:30 a.m. and 4:30 p.m. weekdays except for legal
holidays. Contact the person listed in the FOR FURTHER INFORMATION
CONTACT paragraph below or Mr. Bill Deese at 214-665-7253 to make an
appointment. If possible, please make the appointment at least two
working days in advance of your visit. There will be a 15 cent per page
fee for making photocopies of documents. On the day of the visit,
please check in at the our Region 6 reception area at 1445 Ross Avenue,
Suite 700, Dallas, Texas.
The state submittal is also available for public inspection during
official business hours, by appointment, at the Oklahoma Department of
Environmental Quality, 707 N Robinson, Oklahoma City, OK 73102.
FOR FURTHER INFORMATION CONTACT: Joe Kordzi, EPA Region 6 Air Planning
Section, telephone 214-665-7186, e-mail address r6air_okhaze@epa.gov.
SUPPLEMENTARY INFORMATION: Throughout this document wherever ``we,''
``us,'' or ``our'' is used, we mean the EPA.
This action is being taken under section 110 and part C of the CAA.
Table of Contents
I. Overview of Proposed Actions
A. Regional Haze
B. Interstate Transport of Visibility
II. SIP and FIP Background
III. What is the background for our proposed actions?
A. Regional Haze
B. Roles of Agencies in Addressing Regional Haze
C. The 1997 NAAQS for Ozone and PM2.5 and CAA
110(a)(2)(D)(i)
IV. What are the requirements for regional haze SIPs?
A. The CAA and the Regional Haze Rule
B. Determination of Baseline, Natural, and Current Visibility
Conditions
C. Determination of Reasonable Progress Goals
D. Best Available Retrofit Technology
E. Long-Term Strategy
F. Coordinating Regional Haze and Reasonably Attributable
Visibility Impairment
G. Monitoring Strategy and Other SIP Requirements
H. Consultation With States and Federal Land Managers
V. Our Analysis of Oklahoma's Regional Haze SIP
A. Affected Class I Areas
B. Determination of Baseline, Natural and Current Visibility
Conditions
1. Estimating Natural Visibility Conditions
2. Estimating Baseline Visibility Conditions
3. Natural Visibility Impairment
4. Uniform Rate of Progress
C. Evaluation of Oklahoma's Reasonable Progress Goal
1. Establishment of the Reasonable Progress Goal
2. ODEQ's Reasonable Progress ``Four Factor'' Analysis
3. Reasonable Progress Consultation
D. Evaluation of Oklahoma's BART Determinations
1. Identification of BART-Eligible Sources
2. Identification of Sources Subject to BART
a. Modeling Methodology
b. Contribution Threshold
c. BART Sources Exempted Due to Permit Modifications
d. Sources Identified by ODEQ as Subject to BART
3. BART Determinations
a. OG&E Seminole Units 1, 2, and 3 BART Determinations
b. OG&E Sooner Units 1 and 2 BART Determinations
c. OG&E Muskogee Units 4 and 5 BART Determinations
d. AEP/PSO Comanche Units 1 and 2 BART Determinations
e. AEP/PSO Northeastern Unit 2, 3, and 4 BART Determination
f. AEP/PSO Southwestern Unit 3 BART Determination
g. ODEQ BART Results and Summary
E. Evaluation of ODEQ's SO2 BART Determinations for
the OG&E and AEP/PSO Coal Fired Power Plant Units
1. Cost Effectiveness
a. Dry Scrubbing Cost Analyses
b. Wet Scrubbing Cost Analyses
2. Visibility Benefit
3. Our Conclusion on Oklahoma's SO2 BART Evaluations
for the Six OG&E and AEP/PSO Units
4. Alternative BART Determination
F. Federal Implementation Plan To Address SO2 BART
for the Six Sources
1. Introduction
2. Appropriate Emission Limits
a. Dry Scrubber Emission Limit
b. Wet Scrubber Emission Limit
3. Visibility Benefit From Dry and Wet Scrubbing
4. EPA's SO2 BART Determination for the Six Units
G. Long-Term Strategy
1. Emissions Inventory
a. Oklahoma's 2002 Emission Inventory
b. Oklahoma's 2018 Emission Inventory
2. Visibility Projection Modeling
3. Consultation and Emissions Reductions for Other States' Class
I Areas
4. Mandatory Long Term Strategy Factors
H. Coordination of RAVI and Regional Haze Requirements
I. Monitoring Strategy and Other SIP Requirements
J. Federal Land Manager Coordination
K. Periodic SIP Revisions and Five-Year Progress Reports
VI. Our Analysis of Oklahoma's Interstate Visibility Transport SIP
Provisions
VII. Proposed Actions
A. Regional Haze
B. Interstate Transport and Visibility
VIII. Statutory and Executive Order Reviews
I. Overview of Proposed Actions
A. Regional Haze
We propose to partially approve and partially disapprove Oklahoma's
regional haze (RH) SIP revision submitted on February 19, 2010.
Specifically, we propose to disapprove the SO2 BART
determinations for Units 4 and 5 of the Oklahoma Gas and Electric
(OG&E) Muskogee plant; Units 1 and 2 of the OG&E Sooner plant; and
Units 3 and 4 of the American Electric Power/Public Service Company of
Oklahoma (AEP/PSO) Northeastern plant. We propose to disapprove these
SO2 BART determinations because they do not comply with our
regulations under 40 CFR 51.308(e).
We are also proposing to disapprove the long term strategy (LTS)
under section 51.308(d)(3) because Oklahoma has not shown that the
strategy is adequate to achieve the reasonable progress goals set by
Oklahoma and by other nearby States. The visibility modeling used by
Oklahoma in support of its SIP revision submittal assumed
SO2 reductions from the six sources \1\ as identified above
that Oklahoma did not secure when making its BART determinations for
these sources. As we discuss elsewhere, ODEQ participated in the
Central Regional Air Planning Association (CENRAP) visibility modeling
development that assumed certain SO2 reductions from these
six BART sources. ODEQ also performed its consultations with other
states with the understanding that these reductions would be secured.
We propose a FIP to cure these defects in BART and the LTS.
---------------------------------------------------------------------------
\1\ In this document, when we say ``six BART sources,'' or ``six
sources,'' we mean Units 4 and 5 of the Oklahoma Gas and Electric
Muskogee plant; Units 1 and 2 of the Oklahoma Gas and Electric
Sooner plant; and Units 3 and 4 of the American Electric Power/
Public Service Company of Oklahoma Northeastern plant.
---------------------------------------------------------------------------
[[Page 16170]]
We are also proposing to approve the remaining sections of the RH
SIP submission, except as discussed below.
We propose to find that Units 4 and 5 of the OG&E Muskogee plant,
Units 1 and 2 of the OG&E Sooner plant, and Units 3 and 4 of the AEP/
PSO Northeastern plant are subject to BART under 40 CFR 51.308(e).
Further, we propose a FIP that specifically imposes SO2 BART
emission limits on these sources. We propose that SO2 BART
for Units 4 and 5 of the OG&E Muskogee plant, Units 1 and 2 of the OG&E
Sooner plant, and Units 3 and 4 of the AEP/PSO Northeastern plant is an
SO2 emission limit of 0.06 lbs/MMBtu that applies singly to
each of these units on a 30 day rolling average. Additionally, we
propose monitoring, recordkeeping, and reporting requirements to ensure
compliance with these emission limitations.
We propose that compliance with the emission limits be within three
(3) years of the effective date of our final rule. We solicit comments
on alternative timeframes, of from two (2) years up to five (5) years
from the effective date our final rule.
Should OG&E and/or AEP/PSO elect to reconfigure the above units to
burn natural gas, as a means of satisfying their BART obligations under
section 51.308(e), that conversion should be completed within the same
time frame. We invite comments as to, considering the engineering and/
or management challenges of such a fuel switch, whether the full 5
years allowed under section 308(e)(1)(iv) following our final approval
would be appropriate.
We propose to disapprove section VI.E of the Oklahoma RH SIP
entitled, ``Greater Reasonable Progress Alternative Determination.'' We
also propose to disapprove the separate executed agreements between
ODEQ and OG&E, and ODEQ and AEP/PSO entitled ``OG&E Regional Haze
Agreement, Case No. 10-024, and ``PSO Regional Haze Agreement, Case No.
10-025,'' housed within Appendix 6-5 of the RH SIP. We propose that
these portions of the submittal are severable from the BART
determinations and the LTS; therefore, no FIP is required.
We are taking no action on whether Oklahoma has satisfied the
reasonable progress requirements of EPA's regional haze SIP
requirements found at section 51.308(d)(1).
B. Interstate Transport of Visibility
We also propose to partially approve and partially disapprove a
portion of a SIP revision we received from the State of Oklahoma on May
10, 2007, as supplemented on December 10, 2007, for the purpose of
addressing the ``good neighbor'' provisions of the CAA section
110(a)(2)(D)(i) for the 1997 8-hour ozone NAAQS and the
PM2.5 NAAQS. Section 110(a)(2)(D)(i)(II) of the Act requires
that states have a SIP, or submit a SIP revision, containing provisions
``prohibiting any source or other type of emission activity within the
state from emitting any air pollutant in amounts which will * * *
interfere with measures required to be included in the applicable
implementation plan for any other State under part C [of the CAA] to
protect visibility.'' Because of the impacts on visibility from the
interstate transport of pollutants, we interpret the ``good neighbor''
provisions of section 110 of the Act described above as requiring
states to include in their SIPs measures to prohibit emissions that
would interfere with the reasonable progress goals set to protect Class
I areas in other states.
These SIP revisions were submitted to address the requirement that
Oklahoma's SIP must have adequate provisions to prohibit emissions from
adversely affecting another state's air quality through interstate
transport. Oklahoma indicates in its May 10, 2007 submittal that it
intended that its RH SIP be used to satisfy the requirements of section
110(a)(2)(D)(i)(II) that emissions from Oklahoma sources do not
interfere with measures required in the SIP of any other state under
part C of the CAA to protect visibility. Consistent with our proposed
actions with regard to Oklahoma's RH SIP revision submittal, we also
propose a partial approval and partial disapproval of the Oklahoma
Interstate Transport SIP revision submittals that address the
requirement of section 110(a)(2)(D)(i)(II).
Specifically, we propose a partial approval and partial disapproval
of the Oklahoma Interstate Transport SIP revision submittals that
address the requirement of section 110(a)(2)(D)(i)(II) that emissions
from Oklahoma sources do not interfere with measures required in the
SIP of any other state under part C of the CAA to protect visibility.
We believe that the controls proposed under the proposed FIP, in
combination with the controls required by the portion of the Oklahoma
RH submittal that we propose to approve, will serve to prevent sources
in Oklahoma from emitting pollutants in amounts which will interfere
with efforts to protect visibility in other states.
II. SIP and FIP Background
The CAA requires each state to develop a plan that provides for the
implementation, maintenance, and enforcement of the NAAQS. CAA section
110(a). We establish NAAQS under section 109 of the CAA. Currently, the
NAAQS address six criteria pollutants: Carbon monoxide; nitrogen
dioxide; ozone; lead; particulate matter; and sulfur dioxide. The plan
developed by a state is referred to as the SIP. The content of the SIP
is specified in section 110 of the CAA, other provisions of the CAA,
and applicable regulations. A primary purpose of the SIP is to provide
the air pollution regulations, control strategies, and other means or
techniques developed by the state to ensure that the ambient air within
that state meets the NAAQS. However, another important aspect of the
SIP is to ensure that emissions from within the state do not have
certain prohibited impacts upon the ambient air in other states through
the interstate transport of pollutants. CAA section 110(a)(2)(D).
States are required to update or revise SIPs under certain
circumstances. See CAA section 110(a)(1). One such circumstance is our
promulgation of a new or revised NAAQS. Id. Each state must submit
these revisions to us for approval and incorporation into the federally
enforceable SIP.
If a state fails to make a required SIP submittal or if we find
that, the state's submittal is incomplete or unapprovable, then we must
promulgate a FIP to fill this regulatory gap. CAA section 110(c)(1). As
discussed elsewhere in this notice, we have made findings related to
Oklahoma SIP revisions needed to address interstate transport and the
requirement that emissions from Oklahoma sources do not interfere with
measures required in the SIP of any other state to protect visibility,
pursuant to section 110(a)(2)(D)(i)(II) of the CAA. We propose a FIP to
address the deficiencies in the Oklahoma Interstate Transport SIP.
III. What is the background for our proposed actions?
A. Regional Haze
RH is visibility impairment that is produced by a multitude of
sources and activities which are located across a broad geographic area
and emit fine particles (PM2.5) (e.g., sulfates, nitrates,
organic carbon, elemental carbon, and soil dust) and their precursors
(e.g., SO2, nitrogen oxides (NOX), and in some
cases, ammonia (NH3) and volatile organic compounds (VOCs)).
Fine particle precursors react in the atmosphere to form
PM2.5 (e.g., sulfates, nitrates, organic carbon, elemental
carbon, and soil dust), which also impair visibility by scattering and
[[Page 16171]]
absorbing light. Visibility impairment reduces the clarity, color, and
visible distance that one can see. PM2.5 also can cause
serious health effects and mortality in humans and contributes to
environmental effects such as acid deposition and eutrophication.
Data from the existing visibility monitoring network, the
``Interagency Monitoring of Protected Visual Environments'' (IMPROVE)
monitoring network, show that visibility impairment caused by air
pollution occurs virtually all the time at most national park and
wilderness areas. The average visual range \2\ in many Class I areas
(i.e., national parks and memorial parks, wilderness areas, and
international parks meeting certain size criteria) in the western
United States is 100-150 kilometers, or about one-half to two-thirds of
the visual range that would exist without anthropogenic air pollution.
64 FR 35714, 35715 (July 1, 1999). In most of the eastern Class I areas
of the United States, the average visual range is less than 30
kilometers, or about one-fifth of the visual range that would exist
under estimated natural conditions. Id.
---------------------------------------------------------------------------
\2\ Visual range is the greatest distance, in kilometers or
miles, at which a dark object can be viewed against the sky.
---------------------------------------------------------------------------
In section 169A of the 1977 Amendments to the CAA, Congress created
a program for protecting visibility in the nation's national parks and
wilderness areas. This section of the CAA establishes as a national
goal the ``prevention of any future, and the remedying of any existing,
impairment of visibility in mandatory Class I Federal areas \3\ which
impairment results from manmade air pollution.'' CAA Sec. 169A(a)(1).
The terms ``impairment of visibility'' and ``visibility impairment''
are defined in the Act to include a reduction in visual range and
atmospheric discoloration. Id. section 169A(g)(6). In 1980, we
promulgated regulations to address visibility impairment in Class I
areas that is ``reasonably attributable'' to a single source or small
group of sources, i.e., ``reasonably attributable visibility
impairment'' (RAVI). 45 FR 80084 (December 2, 1980). These regulations
represented the first phase in addressing visibility impairment. We
deferred action on RH that emanates from a variety of sources until
monitoring, modeling and scientific knowledge about the relationships
between pollutants and visibility impairment were improved.
---------------------------------------------------------------------------
\3\ Areas designated as mandatory Class I Federal areas consist
of national parks exceeding 6000 acres, wilderness areas and
national memorial parks exceeding 5000 acres, and all international
parks that were in existence on August 7, 1977. See CAA section
162(a). In accordance with section 169A of the CAA, EPA, in
consultation with the Department of Interior, promulgated a list of
156 areas where visibility is identified as an important value. See
44 FR 69122, November 30, 1979. The extent of a mandatory Class I
area includes subsequent changes in boundaries, such as park
expansions. CAA section 162(a). Although states and tribes may
designate as Class I additional areas which they consider to have
visibility as an important value, the requirements of the visibility
program set forth in section 169A of the CAA apply only to
``mandatory Class I Federal areas.'' Each mandatory Class I Federal
area is the responsibility of a ``Federal Land Manager'' (FLM). See
CAA section 302(i). When we use the term ``Class I area'' in this
action, we mean a ``mandatory Class I Federal area.''
---------------------------------------------------------------------------
Congress added section 169B to the CAA in 1990 to address RH
issues, and we promulgated regulations addressing RH in 1999. 64 FR
35714 (July 1, 1999), codified at 40 CFR part 51, subpart P. The
Regional Haze Rule (RHR) revised the existing visibility regulations to
integrate into the regulations provisions addressing RH impairment and
established a comprehensive visibility protection program for Class I
areas. The requirements for RH, found at 40 CFR 51.308 and 51.309, are
included in our visibility protection regulations at 40 CFR 51.300-309.
Some of the main elements of the RH requirements are summarized in
section III. The requirement to submit a RH SIP applies to all 50
states, the District of Columbia and the Virgin Islands.\4\ States were
required to submit the first implementation plan addressing RH
visibility impairment no later than December 17, 2007. 40 CFR
51.308(b).
---------------------------------------------------------------------------
\4\ Albuquerque/Bernalillo County in New Mexico must also submit
a regional haze SIP to completely satisfy the requirements of
section 110(a)(2)(D) of the CAA for the entire State of New Mexico
under the New Mexico Air Quality Control Act (section 74-2-4).
---------------------------------------------------------------------------
B. Roles of Agencies in Addressing Regional Haze
Successful implementation of the RH program will require long-term
regional coordination among states, tribal governments and various
federal agencies. As noted above, pollution affecting the air quality
in Class I areas can be transported over long distances, even hundreds
of kilometers. Therefore, to address effectively the problem of
visibility impairment in Class I areas, states need to develop
strategies in coordination with one another, taking into account the
effect of emissions from one jurisdiction on the air quality in
another.
Because the pollutants that lead to RH can originate from sources
located across broad geographic areas, we have encouraged the states
and tribes across the United States to address visibility impairment
from a regional perspective. Five regional planning organizations
(RPOs) were developed to address RH and related issues. The RPOs first
evaluated technical information to better understand how their states
and tribes impact Class I areas across the country, and then pursued
the development of regional strategies to reduce emissions of
particulate matter (PM) and other pollutants leading to RH.
CENRAP is an organization of states, tribes, federal agencies and
other interested parties that identifies RH and visibility issues and
develops strategies to address them. CENRAP is one of the five Regional
Planning Organizations RPOs across the U.S. and includes the states and
tribal areas of Nebraska, Kansas, Oklahoma, Texas, Minnesota, Iowa,
Missouri, Arkansas, and Louisiana.
C. The 1997 NAAQS for Ozone and PM2.5 and CAA
110(a)(2)(D)(i)
On July 18, 1997, we promulgated new NAAQS for 8-hour ozone and for
PM2.5. 62 FR 38652. Section 110(a)(1) of the CAA requires
states to submit SIPs to address a new or revised NAAQS within 3 years
after promulgation of such standards, or within such shorter period as
we may prescribe. Section 110(a)(2) of the CAA lists the elements that
such new SIPs must address, as applicable, including section
110(a)(2)(D)(i), which pertains to the interstate transport of certain
emissions.
On April 25, 2005, we published a ``Finding of Failure to Submit
SIPs for Interstate Transport for the 8-hour Ozone and PM2.5
NAAQS.'' 70 FR 21147. This included a finding that Oklahoma and other
states had failed to submit SIPs for interstate transport of air
pollution affecting visibility, and started a 2-year clock for the
promulgation of a FIP by us, unless a state made a submission to meet
the requirements of section 110(a)(2)(D)(i) and we approved the
submission. Id.
On August 15, 2006, we issued our ``Guidance for State
Implementation Plan (SIP) Submission to Meet Current Outstanding
Obligations Under Section 110(a)(2)(D)(i) for the 8-Hour Ozone and
PM2.5 National Ambient Air Quality Standards'' (2006
Guidance). We developed the 2006 Guidance to make recommendations to
states for making submissions to meet the requirements of section
110(a)(2)(D)(i) for the 1997 8-hour ozone standards and the 1997
PM2.5 standards.
As identified in the 2006 Guidance, the ``good neighbor''
provisions in section 110(a)(2)(D)(i) of the CAA require each state to
submit a SIP that prohibits emissions that adversely affect another
state in the ways contemplated
[[Page 16172]]
in the statute. Section 110(a)(2)(D)(i) contains four distinct
requirements related to the impacts of interstate transport. The SIP
must prevent sources in the state from emitting pollutants in amounts
which will: (1) Contribute significantly to nonattainment of the NAAQS
in other states; (2) interfere with maintenance of the NAAQS in other
states; (3) interfere with provisions to prevent significant
deterioration of air quality in other states; or (4) interfere with
efforts to protect visibility in other states.
The 2006 Guidance stated that states may make a simple SIP
submission confirming that it is not possible at that time to assess
whether there is any interference with measures in the applicable SIP
for another state designed to ``protect visibility'' for the 8-hour
ozone and PM2.5 NAAQS until RH SIPs are submitted and
approved. RH SIPs were required to be submitted by December 17, 2007.
See 74 FR 2392 (January 15, 2009).
On May 10, 2007, we received a SIP revision from Oklahoma to
address the interstate transport provisions of CAA 110(a)(2)(D)(i) for
the 1997 ozone and PM2.5 NAAQS. We received a supplement to
this SIP revision on December 10, 2007. In a prior action we approved
the Oklahoma SIP submittal for the ``interfere with measures to prevent
significant deterioration'' prong of section 110(a)(2)(D)(i) of the
CAA. 75 FR 72695, November 26, 2010. On February 19, 2010, Oklahoma
submitted a RH SIP to address interstate transport of emissions that
could interfere with efforts to protect visibility in other states.
Because, for the reasons outlined below, we can only partially approve
this RH SIP, we propose to partially approve and partially disapprove
the Oklahoma Interstate Transport SIP revision submittals that address
the requirement that emissions from Oklahoma sources do not interfere
with measures required in the SIP of any other state to protect
visibility. See CAA section 110(a)(2)(D)(i)(II). We propose to
promulgate a FIP in order to cure this defect in the Oklahoma
Interstate Transport SIP revision submittals.
IV. What are the requirements for regional haze SIPs?
The following is a summary and basic explanation of the regulations
covered under the RHR. See 40 CFR 51.308 for a complete listing of the
regulations under which this SIP was evaluated.
A. The CAA and the Regional Haze Rule
RH SIPs must assure reasonable progress towards the national goal
of achieving natural visibility conditions in Class I areas. Section
169A of the CAA and our implementing regulations require states to
establish long-term strategies for making reasonable progress toward
meeting this goal. Implementation plans must also give specific
attention to certain stationary sources that were in existence on
August 7, 1977, but were not in operation before August 7, 1962, and
require these sources, where appropriate, to install BART controls for
the purpose of eliminating or reducing visibility impairment. The
specific RH SIP requirements are discussed in further detail below.
B. Determination of Baseline, Natural, and Current Visibility
Conditions
The RHR establishes the deciview (dv) as the principal metric for
measuring visibility. See 70 FR 39104. This visibility metric expresses
uniform changes in the degree of haze in terms of common increments
across the entire range of visibility conditions, from pristine to
extremely hazy conditions. Visibility is sometimes expressed in terms
of the visual range, which is the greatest distance, in kilometers or
miles, at which a dark object can just be distinguished against the
sky. The deciview is a useful measure for tracking progress in
improving visibility, because each deciview change is an equal
incremental change in visibility perceived by the human eye. Most
people can detect a change in visibility of one deciview.\5\
---------------------------------------------------------------------------
\5\ The preamble to the RHR provides additional details about
the deciview. 64 FR 35714, 35725 (July 1, 1999).
---------------------------------------------------------------------------
The deciview is used in expressing Reasonable Progress Goals (RPGs)
(which are interim visibility goals towards meeting the national
visibility goal), defining baseline, current, and natural conditions,
and tracking changes in visibility. The RH SIPs must contain measures
that ensure ``reasonable progress'' toward the national goal of
preventing and remedying visibility impairment in Class I areas caused
by manmade air pollution by reducing anthropogenic emissions that cause
RH. The national goal is a return to natural conditions, i.e., manmade
sources of air pollution would no longer impair visibility in Class I
areas.
To track changes in visibility over time at each of the 156 Class I
areas covered by the visibility program (40 CFR 81.401-437), and as
part of the process for determining reasonable progress, states must
calculate the degree of existing visibility impairment at each Class I
area at the time of each RH SIP submittal and periodically review
progress every five years midway through each 10-year implementation
period. To do this, the RHR requires states to determine the degree of
impairment (in deciviews) for the average of the 20 percent least
impaired (``best'') and 20 percent most impaired (``worst'') visibility
days over a specified time period at each of their Class I areas. In
addition, states must also develop an estimate of natural visibility
conditions for the purpose of comparing progress toward the national
goal. Natural visibility is determined by estimating the natural
concentrations of pollutants that cause visibility impairment and then
calculating total light extinction based on those estimates. We have
provided guidance to states regarding how to calculate baseline,
natural and current visibility conditions.\6\
---------------------------------------------------------------------------
\6\ Guidance for Estimating Natural Visibility Conditions Under
the Regional Haze Rule, September 2003, EPA-454/B-03-005, available
at https://www.epa.gov/ttncaaa1/t1/memoranda/rh_envcurhr_gd.pdf
(hereinafter referred to as ``our 2003 Natural Visibility
Guidance''); and Guidance for Tracking Progress Under the Regional
Haze Rule, EPA-454/B-03-004, September 2003, available at https://www.epa.gov/ttncaaa1/t1/memoranda/rh_tpurhr_gd.pdf (hereinafter
referred to as our ``2003 Tracking Progress Guidance'').
---------------------------------------------------------------------------
For the first RH SIPs that were due by December 17, 2007,
``baseline visibility conditions'' were the starting points for
assessing ``current'' visibility impairment. Baseline visibility
conditions represent the degree of visibility impairment for the 20
percent least impaired days and 20 percent most impaired days for each
calendar year from 2000 to 2004. Using monitoring data for 2000 through
2004, states are required to calculate the average degree of visibility
impairment for each Class I area, based on the average of annual values
over the five-year period. The comparison of initial baseline
visibility conditions to natural visibility conditions indicates the
amount of improvement necessary to attain natural visibility, while the
future comparison of baseline conditions to the then current conditions
will indicate the amount of progress made. In general, the 2000-2004
baseline period is considered the time from which improvement in
visibility is measured.
C. Determination of Reasonable Progress Goals
The vehicle for ensuring continuing progress towards achieving the
natural visibility goal is the submission of a series of RH SIPs from
the states that establish two RPGs (i.e., two distinct goals, one for
the ``best'' and one for the ``worst'' days) for every Class I area for
each (approximately) 10-year implementation period. See 70 FR 3915;
[[Page 16173]]
see also 64 FR 35714. The RHR does not mandate specific milestones or
rates of progress, but instead calls for states to establish goals that
provide for ``reasonable progress'' toward achieving natural (i.e.,
``background'') visibility conditions. In setting RPGs, states must
provide for an improvement in visibility for the most impaired days
over the (approximately) 10-year period of the SIP, and ensure no
degradation in visibility for the least impaired days over the same
period. Id.
States have significant discretion in establishing RPGs, but are
required to consider the following factors established in section 169A
of the CAA and in our RHR at 40 CFR 51.308(d)(1)(i)(A): (1) The costs
of compliance; (2) the time necessary for compliance; (3) the energy
and non-air quality environmental impacts of compliance; and (4) the
remaining useful life of any potentially affected sources. States must
demonstrate in their SIPs how these factors are considered when
selecting the RPGs for the best and worst days for each applicable
Class I area. States have considerable flexibility in how they take
these factors into consideration, as noted in our Reasonable Progress
Guidance.\7\ In setting the RPGs, states must also consider the rate of
progress needed to reach natural visibility conditions by 2064
(referred to hereafter as the ``Uniform Rate of Progress (URP)'') and
the emission reduction measures needed to achieve that rate of progress
over the 10-year period of the SIP. Uniform progress towards
achievement of natural conditions by the year 2064 represents a rate of
progress, which states are to use for analytical comparison to the
amount of progress they expect to achieve. In setting RPGs, each state
with one or more Class I areas (``Class I State'') must also consult
with potentially ``contributing states,'' i.e., other nearby states
with emission sources that may be affecting visibility impairment at
the Class I State's areas. 40 CFR 51.308(d)(1)(iv).
---------------------------------------------------------------------------
\7\ Guidance for Setting Reasonable Progress Goals under the
Regional Haze Program, June 1, 2007, memorandum from William L.
Wehrum, Acting Assistant Administrator for Air and Radiation, to EPA
Regional Administrators, EPA Regions 1-10 (pp. 4-2, 5-1).
---------------------------------------------------------------------------
D. Best Available Retrofit Technology
Section 169A of the CAA directs states to evaluate the use of
retrofit controls at certain larger, often uncontrolled, older
stationary sources with the potential to emit greater than 250 tons or
more of any pollutant in order to address visibility impacts from these
sources. Specifically, section 169A(b)(2)(A) of the Act requires states
to revise their SIPs to contain such measures as may be necessary to
make reasonable progress towards the natural visibility goal, including
a requirement that certain categories of existing major stationary
sources \8\ built between 1962 and 1977 procure, install, and operate
the ``Best Available Retrofit Technology'' (BART), as determined by the
state or us in the case of a plan promulgated under section 110(c) of
the CAA. Under the RHR, States are directed to conduct BART
determinations for such ``BART-eligible'' sources that may be
anticipated to cause or contribute to any visibility impairment in a
Class I area. Rather than requiring source-specific BART controls,
states also have the flexibility to adopt an emissions trading program
or other alternative program as long as the alternative provides
greater reasonable progress towards improving visibility than BART.
---------------------------------------------------------------------------
\8\ The set of ``major stationary sources'' potentially subject
to BART are listed in CAA section 169A(g)(7).
---------------------------------------------------------------------------
We promulgated regulations addressing RH in 1999, 64 FR 35714 (July
1, 1999), codified at 40 CFR part 51, subpart P.\9\ These regulations
require all states to submit implementation plans that, among other
measures, contain either emission limits representing BART for certain
sources constructed between 1962 and 1977, or alternative measures that
provide for greater reasonable progress than BART. 40 CFR 51.308(e).
---------------------------------------------------------------------------
\9\ In American Corn Growers Ass'n v. EPA, 291 F.3d 1 (DC Cir.
2002), the U.S Court of Appeals for the District of Columbia Circuit
issued a ruling vacating and remanding the BART provisions of the
regional haze rule. In 2005, we issued BART guidelines to address
the court's ruling in that case. See 70 FR 39104 (July 6, 2005).
---------------------------------------------------------------------------
On July 6, 2005, we published the Guidelines for BART
Determinations Under the Regional Haze Rule at Appendix Y to 40 CFR
Part 51 (``BART Guidelines'') to assist states in determining which of
their sources should be subject to the BART requirements and in
determining appropriate emission limits for each applicable source. 70
FR 39104. In making a BART determination for a fossil fuel-fired
electric generating plant with a total generating capacity in excess of
750 megawatts, a state must use the approach set forth in the BART
Guidelines. A state is encouraged, but not required, to follow the BART
Guidelines in making BART determinations for other types of sources.
The process of establishing BART emission limitations can be
logically broken down into three steps: first, states identify those
sources which meet the definition of ``BART-eligible source'' set forth
in 40 CFR 51.301; \10\ second, states determine whether such sources
``emits any air pollutant which may reasonably be anticipated to cause
or contribute to any impairment of visibility in any such area'' (a
source which fits this description is ``subject to BART'') and; third,
for each source subject to BART, states then identify the appropriate
type and the level of control for reducing emissions.
---------------------------------------------------------------------------
\10\ BART-eligible sources are those sources that have the
potential to emit 250 tons or more of a visibility-impairing air
pollutant, were put in place between August 7, 1962 and August 7,
1977, and whose operations fall within one or more of 26
specifically listed source categories.
---------------------------------------------------------------------------
States must address all visibility-impairing pollutants emitted by
a source in the BART determination process. The most significant
visibility impairing pollutants are SO2, NOX, and
PM. We have stated that states should use their best judgment in
determining whether VOC or ammonia compounds impair visibility in Class
I areas.
Under the BART Guidelines, states may select an exemption threshold
value for their BART modeling, below which a BART-eligible source would
not be expected to cause or contribute to visibility impairment in any
Class I area. The state must document this exemption threshold value in
the SIP and must state the basis for its selection of that value. Any
source with emissions that model above the threshold value would be
subject to a BART determination review. The BART Guidelines acknowledge
varying circumstances affecting different Class I areas. States should
consider the number of emission sources affecting the Class I areas at
issue and the magnitude of the individual sources' impacts. Any
exemption threshold set by the state should not be higher than 0.5 dv.
In their SIPs, states must identify potential BART sources,
described as ``BART-eligible sources'' in the RHR, and document their
BART control determination analyses. The term ``BART-eligible source''
used in the BART Guidelines means the collection of individual emission
units at a facility that together comprises the BART-eligible source.
In making BART determinations, section 169A(g)(2) of the CAA requires
that states consider the following factors: (1) The costs of
compliance; (2) the energy and non-air quality environmental impacts of
compliance; (3) any existing pollution control technology in use at the
source; (4) the remaining useful life of the source; and (5) the degree
of
[[Page 16174]]
improvement in visibility which may reasonably be anticipated to result
from the use of such technology. States are free to determine the
weight and significance to be assigned to each factor. See 40 CFR
51.308(e)(1)(ii).
A RH SIP must include source-specific BART emission limits and
compliance schedules for each source subject to BART. Once a state has
made its BART determination, the BART controls must be installed and in
operation as expeditiously as practicable, but no later than five years
after the date of our approval of the RH SIP. CAA section 169(g)(4) and
40 CFR 51.308(e)(1)(iv). In addition to what is required by the RHR,
general SIP requirements mandate that the SIP must also include all
regulatory requirements related to monitoring, recordkeeping, and
reporting for the BART controls on the source. See CAA section 110(a).
As noted above, the RHR allows states to implement an alternative
program in lieu of BART so long as the alternative program can be
demonstrated to achieve greater reasonable progress toward the national
visibility goal than would BART.
E. Long-Term Strategy (LTS)
Consistent with the requirement in section 169A(b) of the CAA that
states include in their regional haze SIP a 10 to 15 year strategy for
making reasonable progress, Section 51.308(d)(3) of the RHR requires
that states include a LTS in their RH SIPs. The LTS is the compilation
of all control measures a state will use during the implementation
period of the specific SIP submittal to meet any applicable RPGs. The
LTS must include ``enforceable emissions limitations, compliance
schedules, and other measures as necessary to achieve the reasonable
progress goals'' for all Class I areas within, or affected by emissions
from, the state. 40 CFR 51.308(d)(3).
When a state's emissions are reasonably anticipated to cause or
contribute to visibility impairment in a Class I area located in
another state, the RHR requires the impacted state to coordinate with
the contributing states in order to develop coordinated emissions
management strategies. 40 CFR 51.308(d)(3)(i). In such cases, the
contributing state must demonstrate that it has included, in its SIP,
all measures necessary to obtain its share of the emission reductions
needed to meet the RPGs for the Class I area. The RPOs have provided
forums for significant interstate consultation, but additional
consultations between states may be required to sufficiently address
interstate visibility issues. This is especially true where two states
belong to different RPOs.
States should consider all types of anthropogenic sources of
visibility impairment in developing their LTS, including stationary,
minor, mobile, and area sources. At a minimum, states must describe how
each of the following seven factors listed below are taken into account
in developing their LTS: (1) Emission reductions due to ongoing air
pollution control programs, including measures to address RAVI; (2)
measures to mitigate the impacts of construction activities; (3)
emissions limitations and schedules for compliance to achieve the RPG;
(4) source retirement and replacement schedules; (5) smoke management
techniques for agricultural and forestry management purposes including
plans as currently exist within the state for these purposes; (6)
enforceability of emissions limitations and control measures; (7) the
anticipated net effect on visibility due to projected changes in point,
area, and mobile source emissions over the period addressed by the LTS.
40 CFR 51.308(d)(3)(v).
F. Coordinating Regional Haze and Reasonably Attributable Visibility
Impairment
As part of the RHR, we revised 40 CFR 51.306(c) regarding the LTS
for RAVI to require that the RAVI plan must provide for a periodic
review and SIP revision not less frequently than every three years
until the date of submission of the state's first plan addressing RH
visibility impairment, which was due December 17, 2007, in accordance
with 40 CFR 51.308(b) and (c). On or before this date, the state must
revise its plan to provide for review and revision of a coordinated LTS
for addressing RAVI and RH, and the state must submit the first such
coordinated LTS with its first RH SIP. Future coordinated LTS and
periodic progress reports evaluating progress towards RPGs, must be
submitted consistent with the schedule for SIP submission and periodic
progress reports set forth in 40 CFR 51.308(f) and 51.308(g),
respectively. The periodic review of a state's LTS must report on both
RH and RAVI impairment and must be submitted to us as a SIP revision.
G. Monitoring Strategy and Other SIP Requirements
Section 51.308(d)(4) of the RHR includes the requirement for a
monitoring strategy for measuring, characterizing, and reporting of RH
visibility impairment that is representative of all mandatory Class I
Federal areas within the state. The strategy must be coordinated with
the monitoring strategy required in section 51.305 for RAVI. Compliance
with this requirement may be met through ``participation'' in the
Interagency Monitoring of Protected Visual Environments (IMPROVE)
network, i.e., review and use of monitoring data from the network. The
monitoring strategy is due with the first RH SIP, and it must be
reviewed every five (5) years. The monitoring strategy must also
provide for additional monitoring sites if the IMPROVE network is not
sufficient to determine whether RPGs will be met.
The SIP must also provide for the following:
Procedures for using monitoring data and other information
in a state with mandatory Class I areas to determine the contribution
of emissions from within the state to RH visibility impairment at Class
I areas both within and outside the state;
Procedures for using monitoring data and other information
in a state with no mandatory Class I areas to determine the
contribution of emissions from within the state to RH visibility
impairment at Class I areas in other states;
Reporting of all visibility monitoring data to the
Administrator at least annually for each Class I area in the state, and
where possible, in electronic format;
Developing a statewide inventory of emissions of
pollutants that are reasonably anticipated to cause or contribute to
visibility impairment in any Class I area. The inventory must include
emissions for a baseline year, emissions for the most recent year for
which data are available, and estimates of future projected emissions.
A state must also make a commitment to update the inventory
periodically; and
Other elements, including reporting, recordkeeping, and
other measures necessary to assess and report on visibility.
The RHR requires control strategies to cover an initial
implementation period extending to the year 2018, with a comprehensive
reassessment and revision of those strategies, as appropriate, every 10
years thereafter. Periodic SIP revisions must meet the core
requirements of section 51.308(d) with the exception of BART. The
requirement to evaluate sources for BART applies only to the first RH
SIP. Facilities subject to BART must continue to comply with the BART
provisions of section 51.308(e), as noted above. Periodic SIP revisions
will assure that the statutory requirement of reasonable progress will
continue to be met.
[[Page 16175]]
H. Consultation With States and Federal Land Managers
The RHR requires that states consult with Federal Land Managers
(FLMs) before adopting and submitting their SIPs. 40 CFR 51.308(i).
States must provide FLMs an opportunity for consultation, in person and
at least 60 days prior to holding any public hearing on the SIP. This
consultation must include the opportunity for the FLMs to discuss their
assessment of impairment of visibility in any Class I area and to offer
recommendations on the development of the RPGs and on the development
and implementation of strategies to address visibility impairment.
Further, a state must include in its SIP a description of how it
addressed any comments provided by the FLMs. Finally, a SIP must
provide procedures for continuing consultation between the state and
FLMs regarding the state's visibility protection program, including
development and review of SIP revisions, five-year progress reports,
and the implementation of other programs having the potential to
contribute to impairment of visibility in Class I areas.
V. Our Analysis of Oklahoma's Regional Haze SIP
On February 19, 2010, we received a RH SIP revision from the State
of Oklahoma for approval into the Oklahoma SIP. The following is a
discussion of our evaluation of that submission. The parts of the
submittal that are interrelated are discussed together, in order to
provide the reader with a more ready understanding of our evaluation.
See the Technical Support Document (TSD) for this proposal for a step-
wise evaluation of ODEQ's submission in the order in which the
regulations appear in 40 CFR 51.308, and a more comprehensive technical
analysis.
A. Affected Class I Areas
In accordance with 40 CFR 51.308(d), ODEQ has identified one Class
I area within its borders, the Wichita Mountains National Wildlife
Refuge (Wichita Mountains). ODEQ has also determined that Oklahoma
emissions have a small potential to impact visibility at Class I areas
outside of Oklahoma. Based on projections of visibility in 2018 for the
20% worst visibility days, ODEQ has projected that Oklahoma emissions
are responsible for visibility degradation at the Hercules Glades in
Missouri of approximately 3.61%, the Salt Creek in New Mexico of
approximately 2.53%, and the Guadalupe Mountains in Texas of
approximately 2.0%.\11\ We note that these projections are based on
modeling done by CENRAP that assumed a certain level of reductions of
SO2 emissions from six sources that Oklahoma did not
actually require in its submitted RH SIP revision. We expect that
Oklahoma's projected impacts on visibility at Class I areas outside of
Oklahoma would be greater had these controls and the associated
SO2 emission reductions not been included in CENRAP's
visibility modeling.
---------------------------------------------------------------------------
\11\ Unless otherwise noted, when we refer to visibility
impacts, we mean the impacts due solely to the source or state
named, which do not include natural conditions.
---------------------------------------------------------------------------
B. Determination of Baseline, Natural and Current Visibility Conditions
As required by section 51.308(d)(2)(i) of the RHR and in accordance
with EPA's 2003 Natural Visibility Guidance,\12\ ODEQ calculated
baseline/current and natural visibility conditions for its Class I
area, the Wichita Mountains, on the most impaired and least impaired
days, as summarized below (and further described in the TSD).
---------------------------------------------------------------------------
\12\ Guidance for Estimating Natural Visibility Conditions Under
the Regional Haze Rule, EPA-454/B-03-005, September 2003.
---------------------------------------------------------------------------
1. Estimating Natural Visibility Conditions
Natural background visibility, as defined in EPA's 2003 Natural
Visibility Guidance, is estimated by calculating the expected light
extinction using default estimates of natural concentrations of fine
particle components adjusted by site-specific estimates of humidity.
This calculation uses the IMPROVE equation, which is a formula for
estimating light extinction from the estimated natural concentrations
of fine particle components (or from components measured by the IMPROVE
monitors). As documented in EPA's 2003 Natural Visibility Guidance, EPA
allows states to use ``refined'' or alternative approaches to 2003 EPA
guidance to estimate the values that characterize the natural
visibility conditions of Class I areas. One alternative approach is to
develop and justify the use of alternative estimates of natural
concentrations of fine particle components. Another alternative is to
use the ``new IMPROVE equation'' that was adopted for use by the
IMPROVE Steering Committee in December 2005.\13\ The purpose of this
refinement to the ``old IMPROVE equation'' is to provide more accurate
estimates of the various factors that affect the calculation of light
extinction.
---------------------------------------------------------------------------
\13\ The IMPROVE program is a cooperative measurement effort
governed by a steering committee composed of representatives from
Federal agencies (including representatives from EPA and the FLMs)
and RPOs. The IMPROVE monitoring program was established in 1985 to
aid the creation of Federal and State implementation plans for the
protection of visibility in Class I areas. One of the objectives of
IMPROVE is to identify chemical species and emission sources
responsible for existing anthropogenic visibility impairment. The
IMPROVE program has also been a key participant in visibility-
related research, including the advancement of monitoring
instrumentation, analysis techniques, visibility modeling, policy
formulation and source attribution field studies.
---------------------------------------------------------------------------
ODEQ opted to use the default estimates for the natural conditions
combined with the ``new Improve equation,'' for Wichita Mountains. This
is an acceptable approach under our 2003 Natural Visibility Guidance.
For the Wichita Mountains, the default natural visibility value for the
20 percent worst days is 11.07 deciviews and for the 20 percent best
days it is 3.39 dv. For the Wichita Mountains, ODEQ also used the new
IMPROVE equation to calculate the ``refined'' natural visibility value
for the 20 percent worst days to be 7.53 deciviews and for the 20
percent best days to be 4.2 deciviews. We have reviewed ODEQ's estimate
of the natural visibility conditions and propose to find it acceptable
using the new IMPROVE equation.
The new IMPROVE equation takes into account the most recent review
of the science \14\ and it accounts for the effect of particle size
distribution on light extinction efficiency of sulfate, nitrate, and
organic carbon. It also adjusts the mass multiplier for organic carbon
(particulate organic matter) by increasing it from 1.4 to 1.8. New
terms are added to the equation to account for light extinction by sea
salt and light absorption by gaseous nitrogen dioxide. Site-specific
values are used for Rayleigh scattering (scattering of light due to
atmospheric gases) to account for the site-specific effects of
elevation and
[[Page 16176]]
temperature. Separate relative humidity enhancement factors are used
for small and large size distributions of ammonium sulfate and ammonium
nitrate and for sea salt. The terms for the remaining contributors,
elemental carbon (light-absorbing carbon), fine soil, and coarse mass
terms, do not change between the original and new IMPROVE equations.
---------------------------------------------------------------------------
\14\ The science behind the revised IMPROVE equation is
summarized in Appendix B.2 of the Tennessee Regional Haze submittal
and in numerous published papers. See for example: Hand, J.L., and
Malm, W.C., 2006, Review of the IMPROVE Equation for Estimating
Ambient Light Extinction Coefficients--Final Report. March 2006.
Prepared for Interagency Monitoring of Protected Visual Environments
(IMPROVE), Colorado State University, Cooperative Institute for
Research in the Atmosphere, Fort Collins, Colorado, available at
https://vista.cira.colostate.edu/improve/publications/GrayLit/016_IMPROVEeqReview/IMPROVEeqReview.htm and Pitchford, Marc., 2006,
Natural Haze Levels II: Application of the New IMPROVE Algorithm to
Natural Species Concentrations Estimates.