Entergy Nuclear Operations, Inc,. Entergy Nuclear Vermont Yankee, LLC, Vermont Yankee Nuclear Power Station; License No. DPR-28, Receipt of Request for Action, 15001-15002 [2011-6400]
Download as PDF
Federal Register / Vol. 76, No. 53 / Friday, March 18, 2011 / Notices
Emcdonald on DSK2BSOYB1PROD with NOTICES
file an annual report to the NRC
containing a certification that financial
assurance for decommissioning will be
or has been provided in an amount
which may be more, but not less than,
the amount stated in the regulations,
adjusted as appropriate for changes in
labor, energy, and waste burial costs.
The formula for adequate
decommissioning funds includes an
estimated waste disposal volume based
on the plant design. The actual waste
disposal volume may increase due to a
leak or spill at a level that requires
remediation. The licensee is responsible
for payment of any increased waste
disposal costs, whether paid for out of
the allocated funds from the
decommissioning fund or other assets.
The current remediation of the tritium
in soil and groundwater at VY has been
funded as an operating expense and no
money was used from the
decommissioning trust fund. VY
previously submitted a site-specific
decommissioning cost analysis, which
was approved by the NRC by letter
dated February 3, 2009 (ADAMS
Accession No. ML083390193). VY must
address any required changes in their
next annual report. Because no
violations of NRC requirements were
identified, enforcement action is not
warranted for this concern.
B. Additional NRC Actions Pertaining to
Groundwater Contamination
In March of 2010, NRC’s EDO
established a Groundwater Task Force
(GTF) to review the NRCs approach to
ground water contamination conditions,
given the recent incidents of leaking
buried pipes at commercial nuclear
power plants. The charter of the Task
Force was to reevaluate the
recommendations made in the Liquid
Radioactive Release Lessons Learned
Task Force Final Report dated
September 1, 2006 (ADAMS Accession
No. ML062650312); review the actions
taken in Commission Paper SECY–09–
0174 ‘‘Staff Progress in Evaluation of
Buried Piping at Nuclear Reactor
Facilities’’ (ADAMS Accession No.
ML093160004); and review the actions
taken in response to recent releases of
tritium into groundwater by nuclear
facilities.
The GTF completed its work in June
2010 and provided its report to the EDO.
The report characterized a variety of
issues ranging from policy issues to
communications improvement
opportunities. The complete report may
be found under ADAMS Accession No.
ML101740509. The GTF determined
that the NRC is accomplishing its stated
mission of protecting public health,
safety, and protection of the
VerDate Mar<15>2010
18:30 Mar 17, 2011
Jkt 223001
environment through its response to
groundwater leaks/spills. Within the
current regulatory structure, the NRC is
correctly applying requirements and
properly characterizing the relevant
issues. However, the GTF reported that
there are further observations,
conclusions, and recommendations that
the NRC should consider in its oversight
of groundwater contamination
incidents.
The EDO appointed a group of NRC
senior executives to review the report
and consider its findings. The group
reviewed the GTF final report, including
the conclusions, recommendations, and
their bases. They identified conclusions
and recommendations that do not
involve policy issues, and tasked the
NRC staff to address them. They have
also identified policy issues, and a
policy paper has been sent to the
Commission discussing those issues.
A public workshop was held on
October 4, 2010, with external
stakeholders to discuss the findings of
the GTF Report and to receive input on
the potential policy issues. In addition,
a request for public comment was
published in the Federal Register (75
FR 57987). These efforts help to ensure
the NRC is considering the right issues
on which to focus its attention as it
moves forward. The transcript from this
meeting is available on the NRC’s Web
site at: https://www.nrc.gov/reading-rm/
doc-collections/fact-sheets/buriedpipes-tritium.html.
III. Conclusion
As summarized above, the NRC staff
did not identify any violations and the
public health and safety remains
reasonably assured. Thus, no
enforcement action against VY is
warranted. The NRC staff concludes that
the petitioners’ concerns have been
addressed and resolved such that no
further action is needed in response to
the petitions.
As provided in 10 CFR 2.206(c), a
copy of this Director’s Decision will be
filed with the Secretary of the
Commission for the Commission to
review. As provided for by this
regulation, the Decision will constitute
the final action of the Commission 25
days after the date of the Decision
unless the Commission, on its own
motion, institutes a review of the
Decision within that time.
Dated at Rockville, Maryland, this 11th day
of March 2011.
PO 00000
Frm 00108
Fmt 4703
Sfmt 4703
15001
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor
Regulation.
[FR Doc. 2011–6401 Filed 3–17–11; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–271; NRC–2011–0060]
Entergy Nuclear Operations, Inc,.
Entergy Nuclear Vermont Yankee, LLC,
Vermont Yankee Nuclear Power
Station; License No. DPR–28, Receipt
of Request for Action
Notice is hereby given that petitions
dated January 12, 2010, from Mr.
Michael Mulligan, February 8, 2010,
from Mr. Raymond Shadis, and
February 20, 2010, from Mr. Thomas
Saporito, have requested that, under
Title 10 of the Code of Federal
Regulations (10 CFR) 2.206, ‘‘Requests
for Action under this Subpart,’’ the U.S.
Nuclear Regulatory Commission (NRC)
take action with regard to the Vermont
Yankee Nuclear Power Station (VY).
Mr. Mulligan requested in his petition
that (1) the radioactive leak into the
environment of VY be immediately
stopped, VY be immediately shut down,
and all leaking paths be isolated, and (2)
VY disclose its preliminary root cause
analysis and the NRC release its
preliminary investigative report on this
analysis before plant startup.
Mr. Shadis requested in his petition
that the NRC (1) require VY to go into
cold shutdown and depressurize all
systems in order to slow or stop the
leak, (2) act promptly to stop or mitigate
the leak(s) and not wait until all issues
raised by New England Coalition are
resolved, (3) require VY to reestablish
its licensing basis by physically tracing
records and reporting physical details of
all plant systems that would be within
scope as ‘‘buried pipes and tanks’’ in
NUREG–1801, ‘‘Generic Aging Lessons
Learned (GALL) Report,’’ and under the
requirements of 10 CFR 50.54,
‘‘Conditions of Licenses,’’ (4) investigate
and determine why Entergy has been
allowed to operate VY since 2002
without a working knowledge of all
plant systems, and why the NRC’s
Reactor Oversight Process (ROP) and
review process for license renewal
amendment did not detect this
dereliction, (5) take notice of Entergy
Nuclear Vermont Yankee’s many
maintenance and management failures
(from 2000 to 2010) and the ROP’s
failure to detect them early and
undertake a full diagnostic evaluation
team inspection or NRC Inspection
E:\FR\FM\18MRN1.SGM
18MRN1
Emcdonald on DSK2BSOYB1PROD with NOTICES
15002
Federal Register / Vol. 76, No. 53 / Friday, March 18, 2011 / Notices
Procedure 95003, ‘‘Supplemental
Inspection for Repetitive Degraded
Cornerstones, Multiple Degraded
Cornerstones, Multiple Yellow Inputs or
One Red Input,’’ and (6) require Entergy
VY to apply for an amendment to its
license renewal that would address both
aging analysis and aging management of
all buried piping carrying or with the
potential to carry radionuclides and/or
the potential to interact with any safety
or safety-related system.
Mr. Saporito requested in his petition
that the NRC (1) order a cold-shutdown
mode of operation for VY because of
leaking radioactive tritium and (2) issue
a confirmatory order modifying the
NRC-issued license for VY so that the
licensee must bring the nuclear reactor
to a cold-shutdown mode of operation
until the licensee can provide definitive
reasonable assurance to the NRC, under
affirmation, that the reactor will be
operated in full compliance with the
regulations in 10 CFR Part 50, ‘‘Domestic
Licensing of Production and Utilization
Facilities,’’ and General Design Criteria
60, ‘‘Control of Releases of Radioactive
Materials to the Environment,’’ and 64,
‘‘Monitoring Radioactivity Releases,’’ of
Appendix A, ‘‘General Design Criteria
for Nuclear Power Plants,’’ to 10 CFR
Part 50, and with other NRC regulations
and authority.
The requests are being treated under
10 CFR 2.206 of the Commission’s
regulations. The requests have been
referred to the Director of the Office of
Nuclear Reactor Regulation (NRR). As
provided by 10 CFR 2.206, the NRC will
take appropriate action on this
consolidated petition within a
reasonable time.
Each petitioner stated that the tritium
leak is just one example of many
maintenance and management failures
at VY. All three raised a concern about
what they perceive as the NRC’s failure
to examine the deficiencies at VY in an
integrated manner. Although the
individual petition was written to
request enforcement action specifically
because of the tritium leak, during each
of the transcribed phone calls, each
petitioner urged the NRC to take a
broader view and assess operational and
performance failures at VY collectively
instead of individually. This concern
has met the criteria for review in
accordance with Management Directive
8.11, ‘‘Review Process for 10 CFR 2.206
Petitions.’’
Subsequently, the Petition Review
Board recommended that the NRC
accept the consolidated petition for
review for the following specific issues
and concerns identified in the petitions
and supplemented during the
teleconferences:
VerDate Mar<15>2010
18:30 Mar 17, 2011
Jkt 223001
1. Increasing concentrations of
radiocontaminants in the soil and
groundwater at VY, as well as an
increasing area of contamination, are
manifest on a daily basis. VY risks
aggravating the contamination by
continuing to run the reactor at full
power while attempting over a period of
a month to triangulate the location of a
presumed leak by drilling a series of test
wells in the affected area.
2. During the license renewal
application proceeding, the licensee
averred that it was unaware of the
existence of some buried pipes, now
uncovered, and it has yet to discover
their path and purpose.
3. Entergy has, in 8 years of
ownership, failed to learn and
understand VY’s design, layout, and
construction. This failure to
comprehend and understand the layout,
function, and potentially the interaction
of the plant’s own piping systems
constitutes a loss of design basis.
4. The NRC’s ROP has apparently
failed to capture, anticipate, and prevent
ongoing maintenance, engineering,
quality assurance, and operation issues
that have manifested themselves in a
series of high-profile incidents since
Entergy took over VY. The agency has
repeatedly failed to detect root cause
trends until they have, as in this
instance, become grossly self-revealing.
5. The NRC should ensure that
Entergy has adequate decommissioning
funds. The tritium leak will increase
decommissioning costs because of the
need for site radiological examination
and soil remediation.
The NRC sent a copy of the proposed
Director’s Decision to the petitioners
and the licensee for comment on
January 20, 2011. The staff did not
receive any comments on the proposed
Director’s Decision.
The NRR staff determined that the
activities requested by the petitioners
have been completed, with the
exception of immediate cold shutdown
of Vermont Yankee. Therefore, the
Director of NRR concludes that the
petition has been granted in part and
denied in part. The reasons for this
decision are explained in the Director’s
Decision (DD–11–03) pursuant to 10
CFR 2.206.
Copies of the petitions (Agencywide
Documents Access and Management
System (ADAMS) Accession Nos.
ML100190688, ML100470430, and
ML100621374) and the Director’s
Decision (ADAMS Accession No.
ML110540558) are available for
inspection at the Commission’s Public
Document Room (PDR) at One White
Flint North, Room O1–F21, 11555
Rockville Pike (first floor), Rockville,
PO 00000
Frm 00109
Fmt 4703
Sfmt 4703
Maryland 20852, and from the NRC’s
ADAMS Public Electronic Reading
Room on the NRC Web site at https://
www.nrc.gov/reading-rm/adams.html.
NRC Management Directive 8.11,
‘‘Review Process for 10 CFR 2.206
Petitions’’ (ADAMS Accession No.
ML041770328), describes the petition
review process. Persons who do not
have access to ADAMS or who have
problems in accessing the documents in
ADAMS should contact the NRC PDR
reference staff by telephone at 1–800–
397–4209 or 301–415–4737, or by e-mail
to pdr.resource@nrc.gov.
A copy of the Director’s Decision will
be filed with the Secretary of the
Commission for the Commission’s
review in accordance with 10 CFR 2.206
of the Commission’s regulations. As
provided for by this regulation, the
Director’s Decision will constitute the
final action of the Commission 25 days
after the date of the decision, unless the
Commission, on its own motion,
institutes a review of the Director’s
Decision in that time.
Dated at Rockville, Maryland this 11th day
of March, 2011.
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor
Regulation.
[FR Doc. 2011–6400 Filed 3–17–11; 8:45 am]
BILLING CODE 7590–01–P
SECURITIES AND EXCHANGE
COMMISSION
Proposed Collection; Comment
Request
Upon Written Request, Copies Available
From: U.S. Securities and Exchange
Commission, Office of Investor
Education and Advocacy,
Washington, DC 20549–0213.
Extension:
Rule 611; SEC File No. 270–540; OMB
Control No. 3235–0600.
Notice is hereby given that pursuant
to the Paperwork Reduction Act of 1995
(44 U.S.C. 3501 et seq.), the Securities
and Exchange Commission
(‘‘Commission’’) is soliciting comments
on the collection of information
summarized below. The Commission
plans to submit this existing collection
of information to the Office of
Management and Budget for extension
and approval for Rule 611 (17 CFR
242.611)—Order Protection Rule.
On June 9, 2005, effective August 29,
2005 (see 70 FR 37496, June 29, 2005),
the Commission adopted Rule 611 of
Regulation NMS under the Securities
Exchange Act of 1934 (15 U.S.C. 78a et
E:\FR\FM\18MRN1.SGM
18MRN1
Agencies
[Federal Register Volume 76, Number 53 (Friday, March 18, 2011)]
[Notices]
[Pages 15001-15002]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-6400]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-271; NRC-2011-0060]
Entergy Nuclear Operations, Inc,. Entergy Nuclear Vermont Yankee,
LLC, Vermont Yankee Nuclear Power Station; License No. DPR-28, Receipt
of Request for Action
Notice is hereby given that petitions dated January 12, 2010, from
Mr. Michael Mulligan, February 8, 2010, from Mr. Raymond Shadis, and
February 20, 2010, from Mr. Thomas Saporito, have requested that, under
Title 10 of the Code of Federal Regulations (10 CFR) 2.206, ``Requests
for Action under this Subpart,'' the U.S. Nuclear Regulatory Commission
(NRC) take action with regard to the Vermont Yankee Nuclear Power
Station (VY).
Mr. Mulligan requested in his petition that (1) the radioactive
leak into the environment of VY be immediately stopped, VY be
immediately shut down, and all leaking paths be isolated, and (2) VY
disclose its preliminary root cause analysis and the NRC release its
preliminary investigative report on this analysis before plant startup.
Mr. Shadis requested in his petition that the NRC (1) require VY to
go into cold shutdown and depressurize all systems in order to slow or
stop the leak, (2) act promptly to stop or mitigate the leak(s) and not
wait until all issues raised by New England Coalition are resolved, (3)
require VY to reestablish its licensing basis by physically tracing
records and reporting physical details of all plant systems that would
be within scope as ``buried pipes and tanks'' in NUREG-1801, ``Generic
Aging Lessons Learned (GALL) Report,'' and under the requirements of 10
CFR 50.54, ``Conditions of Licenses,'' (4) investigate and determine
why Entergy has been allowed to operate VY since 2002 without a working
knowledge of all plant systems, and why the NRC's Reactor Oversight
Process (ROP) and review process for license renewal amendment did not
detect this dereliction, (5) take notice of Entergy Nuclear Vermont
Yankee's many maintenance and management failures (from 2000 to 2010)
and the ROP's failure to detect them early and undertake a full
diagnostic evaluation team inspection or NRC Inspection
[[Page 15002]]
Procedure 95003, ``Supplemental Inspection for Repetitive Degraded
Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs or
One Red Input,'' and (6) require Entergy VY to apply for an amendment
to its license renewal that would address both aging analysis and aging
management of all buried piping carrying or with the potential to carry
radionuclides and/or the potential to interact with any safety or
safety-related system.
Mr. Saporito requested in his petition that the NRC (1) order a
cold-shutdown mode of operation for VY because of leaking radioactive
tritium and (2) issue a confirmatory order modifying the NRC-issued
license for VY so that the licensee must bring the nuclear reactor to a
cold-shutdown mode of operation until the licensee can provide
definitive reasonable assurance to the NRC, under affirmation, that the
reactor will be operated in full compliance with the regulations in 10
CFR Part 50, ``Domestic Licensing of Production and Utilization
Facilities,'' and General Design Criteria 60, ``Control of Releases of
Radioactive Materials to the Environment,'' and 64, ``Monitoring
Radioactivity Releases,'' of Appendix A, ``General Design Criteria for
Nuclear Power Plants,'' to 10 CFR Part 50, and with other NRC
regulations and authority.
The requests are being treated under 10 CFR 2.206 of the
Commission's regulations. The requests have been referred to the
Director of the Office of Nuclear Reactor Regulation (NRR). As provided
by 10 CFR 2.206, the NRC will take appropriate action on this
consolidated petition within a reasonable time.
Each petitioner stated that the tritium leak is just one example of
many maintenance and management failures at VY. All three raised a
concern about what they perceive as the NRC's failure to examine the
deficiencies at VY in an integrated manner. Although the individual
petition was written to request enforcement action specifically because
of the tritium leak, during each of the transcribed phone calls, each
petitioner urged the NRC to take a broader view and assess operational
and performance failures at VY collectively instead of individually.
This concern has met the criteria for review in accordance with
Management Directive 8.11, ``Review Process for 10 CFR 2.206
Petitions.''
Subsequently, the Petition Review Board recommended that the NRC
accept the consolidated petition for review for the following specific
issues and concerns identified in the petitions and supplemented during
the teleconferences:
1. Increasing concentrations of radiocontaminants in the soil and
groundwater at VY, as well as an increasing area of contamination, are
manifest on a daily basis. VY risks aggravating the contamination by
continuing to run the reactor at full power while attempting over a
period of a month to triangulate the location of a presumed leak by
drilling a series of test wells in the affected area.
2. During the license renewal application proceeding, the licensee
averred that it was unaware of the existence of some buried pipes, now
uncovered, and it has yet to discover their path and purpose.
3. Entergy has, in 8 years of ownership, failed to learn and
understand VY's design, layout, and construction. This failure to
comprehend and understand the layout, function, and potentially the
interaction of the plant's own piping systems constitutes a loss of
design basis.
4. The NRC's ROP has apparently failed to capture, anticipate, and
prevent ongoing maintenance, engineering, quality assurance, and
operation issues that have manifested themselves in a series of high-
profile incidents since Entergy took over VY. The agency has repeatedly
failed to detect root cause trends until they have, as in this
instance, become grossly self-revealing.
5. The NRC should ensure that Entergy has adequate decommissioning
funds. The tritium leak will increase decommissioning costs because of
the need for site radiological examination and soil remediation.
The NRC sent a copy of the proposed Director's Decision to the
petitioners and the licensee for comment on January 20, 2011. The staff
did not receive any comments on the proposed Director's Decision.
The NRR staff determined that the activities requested by the
petitioners have been completed, with the exception of immediate cold
shutdown of Vermont Yankee. Therefore, the Director of NRR concludes
that the petition has been granted in part and denied in part. The
reasons for this decision are explained in the Director's Decision (DD-
11-03) pursuant to 10 CFR 2.206.
Copies of the petitions (Agencywide Documents Access and Management
System (ADAMS) Accession Nos. ML100190688, ML100470430, and
ML100621374) and the Director's Decision (ADAMS Accession No.
ML110540558) are available for inspection at the Commission's Public
Document Room (PDR) at One White Flint North, Room O1-F21, 11555
Rockville Pike (first floor), Rockville, Maryland 20852, and from the
NRC's ADAMS Public Electronic Reading Room on the NRC Web site at
https://www.nrc.gov/reading-rm/adams.html. NRC Management Directive
8.11, ``Review Process for 10 CFR 2.206 Petitions'' (ADAMS Accession
No. ML041770328), describes the petition review process. Persons who do
not have access to ADAMS or who have problems in accessing the
documents in ADAMS should contact the NRC PDR reference staff by
telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to
pdr.resource@nrc.gov.
A copy of the Director's Decision will be filed with the Secretary
of the Commission for the Commission's review in accordance with 10 CFR
2.206 of the Commission's regulations. As provided for by this
regulation, the Director's Decision will constitute the final action of
the Commission 25 days after the date of the decision, unless the
Commission, on its own motion, institutes a review of the Director's
Decision in that time.
Dated at Rockville, Maryland this 11th day of March, 2011.
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor Regulation.
[FR Doc. 2011-6400 Filed 3-17-11; 8:45 am]
BILLING CODE 7590-01-P