The licensee proposes to raise the
spillway crest elevation of the lower
reservoir by 1 ft, from 818.5 ft to 819.5
ft, by adding wooden flashboards. The
licensee also proposes raising the upper
reservoir pool elevation 2 ft, from 1,555
ft to 1,557 ft, by allowing only 4 ft of
freeboard to the dam crest elevation of
1,561 ft. As an additional precaution to
existing monitors and controls, the
licensee is proposing to install an
overflow structure at the upper reservoir
to prevent overtopping the non-overflow
structures (dikes) in the event of high
water levels. The structure would be
installed for emergency backup purpose.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Dated: March 4, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–5489 Filed 3–9–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2479–011]
Pacific Gas and Electric Company;
Notice of Application Tendered for
Filing With the Commission, and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
transmission line only project
application has been filed with the
Commission and is available for public
inspection.
a. Type of Application: Subsequent
License—Transmission Line Only.
b. Project No: P–2479–011.
c. Date Filed: February 22, 2011.
d. Applicant: Pacific Gas and Electric
Company.
e. Name of Project: French Meadows
Transmission Line Project.
f. Location: The French Meadows
Transmission Line Project is located in
Placer County, California, within the
boundaries of the Eldorado and Tahoe
National Forests.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Forrest
Sullivan, Senior Project Manager,
Pacific Gas and Electric Company, 5555
Florin Perkins Road, Sacramento, CA,
95826. Tel: (916) 386–5580.
i. FERC Contact: Mary Greene, (202)
502–8865 or mary.greene@ferc.gov.
Milestone
Target date
j. Status: This application is not ready
Notice of Acceptance/Notice
April 19, 2011. for environmental analysis at this time.
of Ready for Environmental
k. Description of Project: The Project
Analysis.
is connected with The Middle Fork
Filing of recommendations,
June 18,
American River Hydroelectric Project,
preliminary terms and con2011.
FERC Project No. 2079, owned and
ditions, and fishway preoperated by the Placer County Water
scriptions.
Agency (PCWA). The Project consists of
Commission issues Non-Draft October 16,
a 3-phase, 60-kilovolt, wood-pole
EA.
2011.
Comments on EA .................. November 15, transmission line extending 13.27 miles
from PCWA’s French Meadows
2011.
Modified Terms and CondiJanuary 14,
powerhouse switchyard to PCWA’s
tions.
2012.
Middle Fork powerhouse (feature of
Project 2079). The Project includes a
o. Final amendments to the
3-phase, 60-kV transmission line
application must be filed with the
extending approximately 900 feet from
Commission no later than 30 days from
PCWA’s Oxbow powerhouse (feature of
the issuance date of the notice of ready
Project 2079) to the interconnection at
for environmental analysis.
PG&E’s Weimar #1 60 kV transmission
VerDate Mar<15>2010
14:43 Mar 09, 2011
Jkt 223001
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
line. The transmission line right-of-way
is 40 feet in width for its entire length.
The Project also includes a 230-kV tap
at PCWA’s Ralston powerhouse. The tap
is wholly contained within the
switchyard at Ralston powerhouse.
The French Meadows 60-kV
transmission line is entirely within the
boundaries of the Eldorado National
Forest, and the Oxbow 60-kV tap is
entirely within the boundaries of the
Tahoe National Forest. The combined
length of the two 60-kV transmission
lines on National Forest System lands is
6.58 miles: 6.42 miles in the Eldorado
National Forest and 0.16 mile in the
Tahoe National Forest. Approximately
6.69 miles of the French Meadows 60kV transmission line are located on
private lands within the boundary of the
Eldorado National Forest. The Oxbow
tap is located entirely on National
Forest System lands.
PG&E is not proposing to modify the
existing Project and does not plan any
changes to the operation or maintenance
of the transmission line.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or for TTY,
contact (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
m. With this notice, we are initiating
consultation with the California State
Historic Preservation Officer (SHPO), as
required by section 106, National
Historic Preservation Act, and the
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
n. Procedural schedule and final
amendments: This application will be
processed according to the following
Licensing Schedule. Revisions to the
schedule will be made if the
Commission determines it necessary to
do so.
E:\FR\FM\10MRN1.SGM
10MRN1
13175
Federal Register / Vol. 76, No. 47 / Thursday, March 10, 2011 / Notices
Milestone
Tentative date
Notice of Acceptance/Notice of Ready for Environmental Analysis ..................................................................
Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ...............................
Commission issues EA ......................................................................................................................................
Comments on EA ...............................................................................................................................................
Modified Terms and Conditions .........................................................................................................................
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice soliciting final terms
and conditions.
Dated: March 4, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–5482 Filed 3–9–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2661–082]
jdjones on DSK8KYBLC1PROD with NOTICES
Pacific Gas and Electric Company;
Notice of Application for Amendment
of License and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a: Application Type: Request for
temporary variance of the water surface
elevation requirement, pursuant to
Article 403 of the Hat Creek
Hydroelectric Project.
b: Project No.: 2661–082.
c: Date Filed: February 10, 2011.
d: Applicant: Pacific Gas and Electric
Company.
e: Name of Project: Hat Creek
Hydroelectric Project (P–2661).
f: Location: The Hat Creek
Hydroelectric Project is located on Hat
Creek, near the town of Cassel, in Shasta
County, California.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h: Applicant Contact: Mr. Jason F.R.
Vann, Pacific Gas and Electric
Company, 245 Market Street, San
Francisco, California 94105, Tel: (415)
973–3727.
i. FERC Contact: Kelly Houff, (202)
502–6393, Kelly.Houff@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: 15
days from the issuance date of this
notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
VerDate Mar<15>2010
14:43 Mar 09, 2011
Jkt 223001
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Please include the project number (P–
2661–082) on any documents or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: Pacific Gas
and Electric Company (PG&E) is
requesting a temporary variance of its
water surface elevation requirement of
Cassel Pond, pursuant to Article 403 of
the license. PG&E proposes a temporary
reduction of one foot, from 3,188.27 feet
National Geodetic Vertical Datum
(NVGD) ± 0.5 feet to 3,187.27 feet NVGD
± 0.5 feet. The purpose of the water
surface elevation of Cassel Pond is to
mitigate the new water leakage found on
the downstream side of the embankment
of Hat 1 Fore bay Dam. The water
leakage is in the same general vicinity
of drainage mitigation work performed
in 2009. PG&E does not consider the
leakage an immediate dam safety
concern but needs to reduce the water
surface elevation of Cassel Pond to
actively investigate the cause of the
leakage and perform corrective
measures. The water elevation level
variance would be in effect from the
date of the Commission approval until
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
March 31, 2011.
May 30, 2011.
September 27, 2011.
October 27, 2011.
December 26, 2012.
PG&E can assess whether the source of
the new leaks are related to the leaks
observed in 2009, and can implement
corrective measures. The estimated
length of the elevation reduction is 6 to
8 months; however, the duration of the
reduction depends on the time it takes
to locate the root cause of the leakage
and the time necessary to complete the
corrective actions implemented.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, .214. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
Any filings must bear in all capital
letters the title ‘‘COMMENTS,’’
‘‘PROTEST,’’ or ‘‘MOTION TO
INTERVENE,’’ as applicable, and the
Project Number of the particular
application to which the filing refers. A
copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
Federal, State, and local agencies are
invited to file comments on the
E:\FR\FM\10MRN1.SGM
10MRN1
Agencies
[Federal Register Volume 76, Number 47 (Thursday, March 10, 2011)]
[Notices]
[Pages 13174-13175]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-5482]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2479-011]
Pacific Gas and Electric Company; Notice of Application Tendered
for Filing With the Commission, and Establishing Procedural Schedule
for Licensing and Deadline for Submission of Final Amendments
Take notice that the following transmission line only project
application has been filed with the Commission and is available for
public inspection.
a. Type of Application: Subsequent License--Transmission Line Only.
b. Project No: P-2479-011.
c. Date Filed: February 22, 2011.
d. Applicant: Pacific Gas and Electric Company.
e. Name of Project: French Meadows Transmission Line Project.
f. Location: The French Meadows Transmission Line Project is
located in Placer County, California, within the boundaries of the
Eldorado and Tahoe National Forests.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Forrest Sullivan, Senior Project Manager,
Pacific Gas and Electric Company, 5555 Florin Perkins Road, Sacramento,
CA, 95826. Tel: (916) 386-5580.
i. FERC Contact: Mary Greene, (202) 502-8865 or
mary.greene@ferc.gov.
j. Status: This application is not ready for environmental analysis
at this time.
k. Description of Project: The Project is connected with The Middle
Fork American River Hydroelectric Project, FERC Project No. 2079, owned
and operated by the Placer County Water Agency (PCWA). The Project
consists of a 3-phase, 60-kilovolt, wood-pole transmission line
extending 13.27 miles from PCWA's French Meadows powerhouse switchyard
to PCWA's Middle Fork powerhouse (feature of Project 2079). The Project
includes a 3-phase, 60-kV transmission line extending approximately 900
feet from PCWA's Oxbow powerhouse (feature of Project 2079) to the
interconnection at PG&E's Weimar 1 60 kV transmission line.
The transmission line right-of-way is 40 feet in width for its entire
length. The Project also includes a 230-kV tap at PCWA's Ralston
powerhouse. The tap is wholly contained within the switchyard at
Ralston powerhouse.
The French Meadows 60-kV transmission line is entirely within the
boundaries of the Eldorado National Forest, and the Oxbow 60-kV tap is
entirely within the boundaries of the Tahoe National Forest. The
combined length of the two 60-kV transmission lines on National Forest
System lands is 6.58 miles: 6.42 miles in the Eldorado National Forest
and 0.16 mile in the Tahoe National Forest. Approximately 6.69 miles of
the French Meadows 60-kV transmission line are located on private lands
within the boundary of the Eldorado National Forest. The Oxbow tap is
located entirely on National Forest System lands.
PG&E is not proposing to modify the existing Project and does not
plan any changes to the operation or maintenance of the transmission
line.
l. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the three digits in the docket
number field to access the document. For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866)
208-3676, or for TTY, contact (202) 502-8659. A copy is also available
for inspection and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
m. With this notice, we are initiating consultation with the
California State Historic Preservation Officer (SHPO), as required by
section 106, National Historic Preservation Act, and the regulations of
the Advisory Council on Historic Preservation, 36 CFR 800.4.
n. Procedural schedule and final amendments: This application will
be processed according to the following Licensing Schedule. Revisions
to the schedule will be made if the Commission determines it necessary
to do so.
[[Page 13175]]
------------------------------------------------------------------------
Milestone Tentative date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready for March 31, 2011.
Environmental Analysis.
Filing of recommendations, preliminary May 30, 2011.
terms and conditions, and fishway
prescriptions.
Commission issues EA....................... September 27, 2011.
Comments on EA............................. October 27, 2011.
Modified Terms and Conditions.............. December 26, 2012.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
soliciting final terms and conditions.
Dated: March 4, 2011.
Kimberly D. Bose,
Secretary.